Created byFuzzy Cloud

Supreme Court of India

THE EXECUTIVE ENGINEER, KNNLversusSUBHASHCHANDRA & ORS.

Citation
2024 INSC 208
Decided
12 March 2024
Disposal
Disposed off

Holding

The Supreme Court set aside the High Court’s enhanced compensation orders and remanded the cases for fresh, notification‑wise adjudication to achieve uniformity, without expressing any opinion on the merits.

Summary

The Karnataka Neeravari Nigam Limited (Corporation) sought compensation for about 13,000 acres of land acquired under the Land Acquisition Act, 1894 for several water and irrigation projects. The Karnataka High Court had enhanced compensation amounts in a series of judgments, but the Supreme Court found that the High Court failed to analyse each case independently, notification‑wise or village‑wise, and relied on its own earlier decisions that this Court had previously set aside. The respondents argued that some of the High Court’s enhanced awards had become final and could not be revisited, while the Corporation contended that uniformity across all projects was essential. The Supreme Court held that the High Court’s orders must be set aside and the matters remanded for fresh consideration, ensuring a holistic, project‑wise approach without reducing compensation already paid. The Court directed the High Court to hear the cases expeditiously and kept all other contentions open for determination.

Issues considered

  • Whether the High Court correctly enhanced compensation without independent, notification‑wise analysis as required by law.
  • Whether judgments of the High Court that have attained finality can be reopened in the present batch of appeals.
  • Whether the Supreme Court should set aside the High Court’s enhanced compensation orders and remand the matters for fresh consideration to ensure uniformity.
  • Whether the Corporation can be made a party to the proceedings before the High Court.

Legislation cited

Subjects

Land AcquisitionDrinking water and irrigation projects/schemesAward of compensationCompensation enhanced

Judgment

                  [2024] 3 S.C.R. 661 : 2024 INSC 208

                    The Executive Engineer, KNNL
                                  v.
                       Subhashchandra & Ors.
                       (Civil Appeal No. 4053 of 2024)
                                 12 March 2024
              [Surya Kant* and K.V. Viswanathan, JJ.]

                            Issue for Consideration
       Huge chunk of land measuring 13000 acres was acquired by
       the State of Karnataka for the appellant-Corporation for different
       projects. High Court while passing the impugned orders enhancing
       the compensation for the acquired land, relied upon its own
       decisions which judgments did not find favour with this Court
       in earlier litigation as regards the same chunk of land and were
       remanded to High Court for reconsideration.

                                   Headnotes
       Land Acquisition Act, 1894 – Award of compensation – Big
       chunk of land acquired for different projects at different points
       in time – Enhancement in compensation granted by the High
       Court varied from project to project – Supreme Court found
       that the High Court did not analyze each case independently,
       matters remanded to High Court – High Court while passing
       the impugned orders enhancing the compensation for the
       acquired land, relied upon said decisions which were set
       aside and were remanded to High Court for reconsideration
       – Plea of the appellant-Corporation that after the remand, the
       matter was heard in part by the High Court – Respondents-
       land owners contended that there were numerous cases in
       which similarly placed land owners have already been paid
       compensation at enhanced rate granted by the High Court
       and those judgments of the High Court attained finality and
       are not subject matter of these appeals:
       Held: It is not in dispute that a batch of cases was remanded by
       this Court for reconsideration by the High Court – It is also an
       admitted fact that those matters pertained to the same broader
       acquisition, though they possibly pertain to different projects – In a
       peculiar situation where some of the judgments of the High Court
       attained finality as the compensation amount, as enhanced, stands
       paid whereas the others are still subject matter of adjudication,
* Author
662                                                              [2024] 3 S.C.R.

                        Digital Supreme Court Reports


       these cases also remanded to the High Court so that a holistic
       view pertaining to the subject acquisition, at least project wise, can
       be taken by the High Court – High Court to make an endeavour
       to infuse uniformity in the matter of award of compensation, to the
       extent possible, in accordance with law. [Para 14]

                                   List of Acts
       Land Acquisition Act, 1894.

                                List of Keywords
       Land Acquisition; Drinking water and irrigation projects/schemes;
       Award of compensation; Compensation enhanced.

                               Case Arising From
       CIVIL APPELLATE JURISDICTION : Civil Appeal No.4053 of 2024
       From the Judgment and Order dated 22.03.2018 of the High Court
       of Karnataka at Kalaburagi in MSA No.200214 of 2017
       With
       Civil Appeal Nos.4076, 4070, 4064, 4056, 4068, 4054, 4055, 4057,
       4058, 4059, 4060, 4061, 4062, 4063, 4065, 4066, 4067, 4069, 4071,
       4072, 4073, 4074, 4075, 4077, 4078, 4079, 4080, 4081, 4082, 4083,
       4084, 4085, 4086, 4087, 4088 And 4089-4090 Of 2024
                           Appearances for Parties
       Naveen R. Nath, Sr. Adv., Ms. Hetu Arora Sethi, Abhimanyu Verma,
       Ms. Lalit Mohini Bhat, Ms. Disha Gupta, Advs. for the Appellant.
       Anand Sanjay M Nuli, Mrs. Kiran Suri, Sr. Advs., Suraj Kaushik,
       Agam Sharma, Nanda Kumar, Dharm Singh, M/s. Nuli & Nuli,
       Sharanagouda Patil, Harshvardhan Malipatil, Jyotish Pandey, Ms.
       Supreeta Sharanagouda, S. J. Amith, Mrs. S. Anuradha Bhat, Harisha
       S.R., Advs. for the Respondents.
                  Judgment / Order of the Supreme Court

                                   Judgment
       Surya Kant, J.
1.     Permission to file special leave petition is granted in Diary
       No.12213/2023.
[2024] 3 S.C.R.                                                        663

       The Executive Engineer, KNNL v. Subhashchandra & Ors.


2.   Delay condoned.
3.   Leave granted.
4.   These civil appeals impugn the judgements dated 28.02.2017,
     28.11.2017, 15.02.2018, 20.02.2018, 21.02.2018, 02.03.2018,
     22.03.2018, 06.04.2018, 13.04.2018, 26.04.2018, 07.12.2018,
     12.12.2018, 14.01.2020, 24.01.2020 and 03.03.2021, passed by the
     High Court of Karnataka at Kalaburagi Bench, whereby compensation
     for the acquired land was enhanced. The appellant-Karnataka
     Neeravari Nigam Limited (in short, “Corporation”) claims to be the
     beneficiary of the subject-acquisition.
5.   The Corporation has been entrusted with the assignment to plan,
     execute and operate drinking water and irrigation projects and
     schemes in the State of Karnataka. About 13000 acres of land was
     acquired by the State of Karnataka for the appellant-Corporation for
     various projects like (1) Bennethora Project (2) Gandori Nala Project
     (3) Lower Mullamari Project and (4) Amarja Project. Certain civil
     appeals also refer to a fifth project, namely, the Upper Tunga Project.
     This huge chunk of land measuring 13000 acres also included the
     parcels of lands owned by the respondent-land owners of different
     villages. The acquisition was carried under the Land Acquisition
     Act, 1894 (in short, “Act”). The present civil appeals pertain to the
     Bennethora Project, Lower Mullamari Project and Amarja Project
     situated in Kalaburagi, Karnataka.
6.   The acquisition proceedings in these appeals, as per the project-wise
     classification, progressed as follows-
     (i)   Bennethora Project
           a)   Civil Appeal Nos.4053, 4054, 4055, 4956, 4061, 4064,
                4065, 4066, 4067, 4068, 4069, 4070, 4071, 4072, 4073,
                4074, 4075, 4076, 4077, 4078, 4079, 4080, 4081, 4082,
                4083, 4085, 4086, 4087 of 2024 pertain to this project. In
                this batch of civil appeals coming under the Bennethora
                Project, land measuring a consolidated total of 131 acres
                and 451 guntas (Approx. 142 acres) was acquired
                through different notifications issued under Section 4 of
                the Act followed by declarations under Section 6 of the Act.
                The Section 4 notifications and the Section 6 declarations
                were issued on the following dates-
664                                                  [2024] 3 S.C.R.

                 Digital Supreme Court Reports



                Date of Section 4            Date of Section 6
                  Notification                 Notification
                   18.02.1982                   10.05.1984
                   17.03.1983                   23.02.1984
                   05.04.1990                   22.11.1990
                   05.07.1990                   09.05.1991
                   23.08.1990                   04.04.1991
                   07.02.1991                   28.11.1991
                   16.05.1991                   26.03.1992
                   13.06.1991                   20.12.1991
                   19.06.1991                   17.12.1992
                   11.07.1991                   27.08.1997
                   06.08.1992                   13.01.1994
       b)   The Special Land Acquisition Officer (in short, “SLAO”)
            passed the awards for the acquired lands on different
            dates, whereby compensations were granted at the
            following rates-

             Date of SLAO award       Compensation granted by
                                        SLAO (Rupees/acre)
                  23.01.1985                     3,167
                  28.02.1985                     3,500
                  08.01.1991                     5,400
                  20.05.1991              6,000 for wet lands
                  15.06.1992                     9,800
                                        28,000 for dry lands &
                  30.01.1993             42,000 for wet lands
                  03.02.1993                    15,000
                  22.11.1993                    15,000
                  27.11.1993                    15,000
                  24.12.1993                    15,000
                  31.05.1994                     9,000
       c)   The rates of compensation awarded by the SLAO were
            enhanced by the Reference Court, keeping in view the year
            when the acquisition process commenced. The enhanced
            compensation amounts granted by the Reference Court
            was further enhanced, upon appeal, by the District Court.
[2024] 3 S.C.R.                                                        665

       The Executive Engineer, KNNL v. Subhashchandra & Ors.


            d)   The dissatisfied landowners further approached the High
                 Court for a higher compensation, which was subsequently
                 granted vide the impugned judgements. The original rates
                 of compensation awarded by the SLAO, the enhanced
                 compensation amounts granted by the Reference Court,
                 the compensation amounts as further enhanced by the
                 District Court and impugned compensation amounts
                 granted by the High Court, vide the impugned judgements,
                 can be understood as follows-

                     Amount       Amount         Amount         Amount
                     granted    granted by       granted        granted
                    by SLAO     Reference      by District       by the
                    (Rupees/       Court          Court       High Court
                      acre)      (Rupees/       (Rupees/       (Rupees/
                                    acre)         acre)          acre)
                       3,167       11,000        19,000        1,09,034
                       3,500       11,000        26,100         83,500
                       5,400      25,500         50,500        1,52,059
                      15,000      28,500         74,000        1,64,223
                      15,000      32,000         74,000        1,64,223
                       9,000      32,000         67,000        1,76,388
                      15,000      32,000         81,400        1,76,388
                       6,000      36,000       Rs.90,200     2,28,088 for
                                                               wet lands
                    28,000 for    42,000       55,888 for       1,52,059
                    dry lands & for limited    dry lands     for dry lands
                    42,000 for   extent of     83,832 for    2,28,088 for
                     wet lands land instead    wet lands       wet lands
                                 of 28,000
                       9,800      42,000         75,750      1,64,223 for
                                                              dry lands
                                                             2,46,334 for
                                                              wet lands
     (ii)   Amarja Project
            a)   Civil Appeal Nos.4057, 4058, 4059, 4060 & 4062, 4084 of
                 2024 pertain to this Project. In the batch of civil appeals
                 coming under the Amarja Project, land measuring a
666                                                    [2024] 3 S.C.R.

                 Digital Supreme Court Reports


            consolidated total of 15 acres 83 guntas (Approx. 17
            acres) was acquired through a notification issued under
            Section 4 of the Act followed by a declaration under Section
            6 of the Act. The Section 4 notification and the Section 6
            declaration were issued on the following dates-

                 Date of Section 4             Date of Section 6
                   Notification                  Notification
                    07.04.1988                    06.07.1989
       b)   Thereafter, the SLAO passed the award for the acquired
            lands whereby compensations was granted at the following
            rate-

             Date of SLAO award         Compensation granted by
                                          SLAO (Rupees/acre)
                  06.03.1990                    7,000
       c)   The rate of compensation awarded by the SLAO was
            enhanced by the Reference Court, keeping in view
            the year when the acquisition process commenced.
            The enhanced compensation amount granted by the
            Reference Court was further enhanced, upon appeal,
            by the District Court.
       d)   The dissatisfied landowners further approached the High
            Court for a higher compensation, which was subsequently
            granted vide the impugned judgements. The original rate
            of compensation awarded by the SLAO, the enhanced
            compensation amount granted by the Reference Court, the
            compensation amount as further enhanced by the District
            Court and impugned compensation amount granted by
            the High Court, vide the impugned judgements, can be
            understood as follows-

              Amount         Amount         Amount         Amount
              granted      granted by       granted        granted
             by SLAO       Reference      by District       by the
             (Rupees/         Court          Court       High Court
               acre)        (Rupees/       (Rupees/       (Rupees/
                              acre)          acre)          acre)
                7,000        30,000         79,200        1,78,429
[2024] 3 S.C.R.                                                         667

       The Executive Engineer, KNNL v. Subhashchandra & Ors.


     (iii) Lower Mullamari Project
           a)   Civil Appeal Nos. 4063, 4088, 4089 of 2024 pertain to this
                Project. In the batch of civil appeals coming under the Lower
                Mullamari Project, land measuring a consolidated total of
                19 acres 59 guntas (Approx. 20 acres) was acquired
                through notifications under Section 4 of the Act followed
                by declarations under Section 6 of the Act, which were
                issued on different dates. The Section 4 notifications and
                the Section 6 declarations were issued on the following
                dates-

                       Date of Section 4           Date of Section 6
                         Notification                Notification
                          30.05.1991            11.05.1992 / 03.09.1992
                          14.01.1993                   07.04.1994
                          04.03.1993                   07.04.1994
           b)   Thereafter, the SLAO passed the awards for the acquired
                lands on different dates, whereby compensations were
                granted at the following rates-

                    Date of SLAO award      Compensation granted by
                                              SLAO (Rupees/acre)
                                           8,000 for dry lands & 10,000
                        04.05.1983                 for wet lands
                        18.11.1995         10,000 for dry lands & 15,000
                                                   for wet lands
                        01.01.1996                      8,000
           c)   The rates of compensation awarded by the SLAO were
                enhanced by the Reference Court, keeping in view the year
                when the acquisition process commenced. The enhanced
                compensation amounts granted by the Reference Court
                was further enhanced, upon appeal, by the District Court.
           d)   The dissatisfied landowners further approached the High
                Court for a higher compensation, which was subsequently
                granted vide the impugned judgements. The original rates
                of compensation awarded by the SLAO, the enhanced
                compensation amounts granted by the Reference Court,
668                                                          [2024] 3 S.C.R.

                       Digital Supreme Court Reports


                 the compensation amounts as further enhanced by the
                 District Court and impugned compensation amounts
                 granted by the High Court, vide the impugned judgements,
                 can be understood as follows-

                    Amount        Amount         Amount          Amount
                    granted     granted by       granted         granted
                   by SLAO      Reference      by District        by the
                   (Rupees/        Court          Court        High Court
                     acre)       (Rupees/       (Rupees/        (Rupees/
                                   acre)          acre)           acre)
                   8,000 for
                  dry lands &
                                  70,000            -           1,15,086
                  10,000 for
                   wet lands
                  10,000 for     50,000 for                    1,24,992 for
                  dry lands &    dry lands                      dry lands
                                                    -
                  15,000 for     75,000 for                    1,86,440 for
                   wet lands     wet lands                      wet lands
                     8,000        33,000      74,750/75,543     1,33,500
7.     It may thus be seen that the enhancement in the compensation
       granted by the High Court varies from project to project and while
       the minimum amount is Rs.83,500/- per acre, the maximum amount
       is seen to have gone up to Rs.1,78,429/- per acre for dry lands and
       Rs. 2,46,334/- for wet lands.
8.     Having regard to the big chunk of land acquired for different projects
       referred to above, at different points in time, the enhancement
       made by the High Court in a few cases, where the compensation of
       Rs.1,20,814/- per acre for dry lands and Rs.1,81,221/- per acre for
       wet lands was awarded, came to be challenged before this Court
       in a batch of appeals, including C.A. No.2591/2022 (The Executive
       Engineer, KNNL Vs. Annarao @ Anveerappa & Anr.), in which this
       Court, vide Judgment dated 10.05.2022, having found that the
       High Court has not analyzed each case independently, much less
       notification wise, concerning particular village or area and that the
       parameters delineated in various decisions of this Court were not
       adverted to, held as follows:
[2024] 3 S.C.R.                                                              669

       The Executive Engineer, KNNL v. Subhashchandra & Ors.


           “In the impugned judgment(s) and order (s), the High court
           has made no effort to analyze the concerned case(s) either
           notification-wise or for that matter, village-wise, including
           the other parameters required to be observed for arriving
           at a just compensation amount.
           Further, in most of the appeals, the appellant (Karnataka
           Neeravari Nigam Limited} was not made party in the appeal
           proceeding before the High Court.
           It is also the grievance of the appellant that most of
           the cases, entertained at the instance of land owners,
           were grossly delayed and yet they have been granted
           enhancement, and in some cases along with interest.
           The fact remains that the High Court in the impugned
           judgment(s) and order(s) has not analyzed each case
           independently much less notification-wise concerning
           particular village or area and keeping in mind the
           parameters delineated in the reported decision, adverted
           to earlier.
           In our opinion, it is appropriate that the parties are relegated
           before the High Court for reconsideration of the entire
           matter afresh and in accordance with law.
           Learned counsel appearing for the land owners were at
           pains to point out that some matters pertaining to some
           of the notifications, referred to in the present appeal
           proceedings, have reached upto this Court and decided
           in favour of the land owners, including in some cases
           the appellants have acted upon the decision by paying
           compensation amount. Even the effect of such orders
           passed by this Court can be examined by the High Court
           on its own merits and in accordance with law.
           Accordingly, we keep all contentions available to both
           sides open, to be considered by the High Court on its
           own merits and in accordance with law.
           The impugned judgment(s) and order(s) are set aside and
           the concerned appeals/petitions are remanded to the High
           Court for reconsideration in the above terms.
670                                                         [2024] 3 S.C.R.

                      Digital Supreme Court Reports


            The parties to appear before the High Court on 11.07.2022,
            when the High Court may assign suitable date for hearing
            of the concerned batch of cases which, as aforesaid, must
            proceed notification-wise pertaining to concerned village
            as a separate group.
            Needless to observe that some of the notifications pertain
            to the year 1983, therefore, it would be appropriate that
            the High Court disposes of the appeal(s) expeditiously.
            The appeals are disposed of in the above terms.”
9.     The High Court judgments, which were set aside and the cases
       remanded back for fresh consideration, also included the judgments
       rendered by the High Court in MSA No.200020/2018 (LAC) titled
       Rajshekhar s/o Sangappa deceased by Lrs. vs. The Special Land
       Acquisition Officer, MSA No.200014/2018 (LAC) titled Kalappa
       S/o Paudapppa v. The Special Land Acquisition Officer and MSA
       No.200147/2017 (LAC) titled Motibee W/o Mashak Patel v. The Spl.
       Land Acquisition Officer & Anr. decided on 19.02.2018, 21.02.2018 and
       09.01.2018 respectively, awarding compensation of Rs.1,64,223/acre,
       Rs.1,64,223/acre and Rs.1,52,059/acre respectively for the dry lands.
       Consequently, Rajshekhar’s case (supra) has also been remanded to
       the High Court for fresh adjudication. The abovementioned judgements
       of the High Court had in turn placed reliance on MSA No. 200055/2016
       (LAC) titled Malkajappa @ Mallikarjun vs. The Special Land Acquisition
       Officer & Anr, decided by the High Court on 13.03.2017, which has
       also been remanded to the High Court vide this Court’s order dated
       10.05.2022 in Annarao @ Anveerappa case (supra).
10. We find that in the present batch of appeals, the brief impugned
    order passed by the High Court in CA No.4053/2024, has solely
    relied upon its own decision in Rajshekhar’s case (supra). In some
    of the other appeals, namely CA Nos. 4954, 4055, 4056, 4064, 4065,
    4066, 4067, 4068, 4079, 4080, 4081, 4082, 4083, 4087 and 4088
    of 2024, the High Court has relied upon its decision in Malkajappa
    @ Mallikarjun (supra), Kalappa (supra) (which placed reliance on
    Malkajappa @ Mallikarjun (supra)) and Motibee (supra)(which placed
    reliance on Malkajappa @ Mallikarjun (supra)). These judgments
    did not find favour with this Court in Annarao @ Anveerappa case
    (supra), whereby the matters have been remanded to the High Court
    for reconsideration.
[2024] 3 S.C.R.                                                       671

       The Executive Engineer, KNNL v. Subhashchandra & Ors.


11. Learned senior counsel for the appellant-Corporation, submits that
    after the remand, the matter has been heard in part by the High Court.
12. On the other hand, learned senior counsel for the respondents-land
    owners submits that there are numerous cases in which similarly
    placed land owners have already been paid compensation at
    enhanced rate granted by the High Court. Those judgments of the
    High Court have attained finality and are not subject matter of these
    appeals.
13. Learned senior counsel for the appellant(s), however, counters this
    submission, as according to him, those matters pertain to different
    villages and the respondents cannot claim parity with those cases.
14. We have considered the rival submissions made by learned senior
    counsel for the parties. It is not in dispute that a batch of cases has
    been remanded by this Court for reconsideration by the High Court,
    as seen above. It is also an admitted fact that those matters pertain
    to the same broader acquisition, though they possibly pertain to
    different projects. In a peculiar situation where some of the judgments
    of the High Court attained finality as the compensation amount, as
    enhanced, stands paid whereas the others are still subject matter
    of adjudication, we deem it appropriate to remand these cases also
    to the High Court so that a holistic view pertaining to the subject
    acquisition, at least project wise, can be taken by the High Court.
    The High Court will make an endeavour to infuse uniformity in the
    matter of award of compensation, to the extent it is possible, in
    accordance with law.
15. It goes without saying that the High Court, while undertaking this
    exercise, will not reduce the compensation to a rate which has
    already been paid to some of the land owners and which has attained
    finality. The rest of the contentions from both sides are kept open to
    be gone into by the High Court.
16. It is clarified that we have not expressed any opinion on the merits
    of the case.
17. The parties are directed to appear before the High Court of Karnataka
    at Kalaburagi Bench on 18.03.2024. We request the High Court to
    take up these matters also, along with the Rajshekhar’s case (supra)
    and other cases, which are already part heard before the High Court.
    Since the acquisition is more than three decades old, we request
672                                                       [2024] 3 S.C.R.

                       Digital Supreme Court Reports


       the High Court to decide the matters expeditiously and preferably
       within three months from the date of this judgement.
18. The instant civil appeals are disposed of in the above terms.


       Headnotes prepared by: Divya Pandey              Result of the case:
                                                       Appeals disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Land Acquisition"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

THE EXECUTIVE ENGINEER, KNNL versus SUBHASHCHANDRA & ORS. — 2024 INSC 208 - Legal Desk AI