TEHRI HYDRO DEVELOPMENT CORPORATIONversusALSTOM HYDRO FRANCE & ANR.
- Citation
- 2010 INSC 175
- Decided
- 26 March 2010
- Disposal
- Disposed off
- Bench
- V S SIRPURKAR
Holding
The Supreme Court ordered fresh bids to be invited, a panel of experts to give a final report on the objections, and left the ultimate award decision to THDC, disposing of the appeals.
Summary
The Tehri Hydro Development Corporation (THDC) invited bids for the Tehri Pump Storage Plant, Phase‑II. Two consortia, Alstom Hydro France (respondent No.1) and Voith Siemens (respondent No.2), submitted bids. Alstom challenged the High Court’s order directing fresh bids on the grounds that the other consortium was not technically qualified and had submitted two price bids contrary to the tender terms. The High Court upheld the qualification of the second consortium and ordered fresh bidding, a decision appealed to the Supreme Court. The Supreme Court held that, in the national interest, fresh bids should be invited and the objections raised should be examined by a panel of experts, giving the parties a final hearing, after which THDC alone will decide the award. The Court emphasized that it will not award the contract and that the earlier controversies become extinguished once fresh bids are received. Consequently, both appeals and the transfer case were disposed of.
Issues considered
- The qualification of respondent No.2 under the tender specifications
- Whether a bidder may submit two price bids (as assignee and partner) under the tender
- The propriety of directing fresh bids after the High Court’s order
- The role of the Supreme Court versus the corporation in awarding the contract
- The need for a panel of experts to examine technical objections and ensure transparency
Subjects
Judgment
[2010) 3 S.C.R. 863
TEHRI HYDRO DEVELOPMENT CORPORATION A
v.
ALSTOM HYDRO FRANCE & ANR.
(Civil Appeal No. 2761 of 2010)
MARCH 26, 2010
B
[V.S. SIRPURKAR AND DR. MUKUNDAKAM
SHARMA, JJ.]
Tenders:
c
Tehri Hydro Development Corporation - Inviting tenders
- Acceptance of bid challenged in writ petition before High
Court - Direction by High Court for inviting fresh bids -
, Challenged before Supreme Court - Corporation directed to
invite fresh bids and process the matter accordingly - D
Objections filed - Panel of Experts appointed to examine
objections - Objections raised to report submitted by Panel
of Experts - HELD: A very important project like the instant
one is being held up in a legal battle between two multinational
companies - Contractual rights of these companies are not E
more important than national interest - In the interest of the
project, the Panel of Experts shall give a .JrftBh report after
giving one more final opportunity of hearing to the parties -
The Corporation would then, without loss cj/ime take the
decision regarding the award of contract, cYinsidering the
report of the Panel of Experts - Once the fresh bids were F
allowed to be given, the old controversies before the High
Court would naturally become extinct and nothing survives in
the appeals arising out of its decision - The exercise of
bidding before the Supreme Court was ordered with the sole
objective of saving time and to give the transparency to the G
whole exercise - It is not for this Court to award the contracts
by accepting or rejecting the tender bids - It is exclusively for
the Corporation to do that - Hydro-Electric Projects.
863 H
864 SUPREME COURT REPORTS [2010] 3 S.C.R.
A CIVIL APPELLATE JURISDICTION : Civil Appeal No.
2761 of 2010.
From the Judgment & Order dated 29.6.2009 of the High
Court of Uttarakhand at Nainital in W.P. No. 167 of 2009.
B WITH
SLP(C) No.19890 of 2009
T.C. (C) No. 33 of 2009.
c G.E. Vahanvati, AG, F.S. Nariman, A. Sharan, Harish
Salve, Dr. A.M. Singhvi, Pratap, Venugopal, Surekha Raman,
Dileep Poolakkot, Purushottam Kumar Jha (for K.J. John &
Co.) Jai Munim, Gursharan, Anuradha Bindra, J.N. Patel, Amit
Anand Tiwari, Abhinav Mukerji, Shiv Prakash Pandey for the
D appearing parties.
The Order of the Court was delivered by
ORDER
E V.S. SIRPURKAR, J. 1. Leave granted in SLP (C)
Nos.15779 and 19890 of 2009.
2. These appeals emanate out of the order passed by the
learned Single Judge of Uttaranchal High Court. On 31st
F August, 2007, the appellant herein invited bids for turn-key
execution of the Tehri Pump Storage Plant, Phase-II. After the
pre-bid conference and amendments four pre-qualification bids
were submitted on 29th December, 2007 by respondent no.1
- Alstom Hydro France, Patel Engineering, Sumitomo
Corporation, Japan and Voith Seimens as leaders of their
G respective consortia. Initially respondents 1 and 2 along with
Sumitomo Corporation, Japan were qualified, however,
subsequently the bid of Sumitomo Corporation was declined
as non-responsive. Thus there were two parties in the fray, they
being respondents 1 and 2 herein. These two gave two price
H options. However, respondent no.1 filed a Writ Petition being
TEHRI HYDRO DEVELOPMENT CORPORATION v. 865
ALSTOM HYDRO FRANCE [V.S. SIRPURKAR, J.]
W.P. No.167 of 2009 in the Uttarakhand High Court on two A
grounds, namely, (a) that respondent no.2 was not technically
qualified; (b) that respondent no.2 had submitted two price bids
which was in contravention of the terms and conditions of the
ITB. The High Court by its final judgment came to the conclusion
that the respondent no.2 was qualified. It was further held that B
there was no violation of terms and conditions of ITB. However,
the learned Single Judge passed the following order by way of
final directions:
"Consequently this Court holds as follows:
c
The qualifications of respondent no.2 for having done the
work of 'erection' at Ghangzhou II seems to be in order as
this court holds 'st:1pervision of erection' as equivalent to
that of 'erection' and rejects the arguments of petitioner on
the eligibility of respondent no.2. Further, under the facts D
of this case, if two price bids had been invited by the
employer - one as an assignee and the other as a partner,
then again there is nothing wrong in such an approach and
if consequent to it two price bids have been given by
respondent no.2- one as an assignee and the other as a E
partner, it is in order and will not be called as a non-
responsive bid. However, since the process of calling two
bids is flawed for lack of clarity, the benefit has to be given
to the petitioner, for the reasons already stated above.
Hence, it is directed that respondent no.1 must ask for F
fresh bids from the petitioner as well as respondent no.2."
Being aggrieved the appellant herein filed the present
appeals.
3. As it appears from lhe appeal filed by Tehri Hydro G
Development Corporation, the appellant assails the direction
of the learned Single Judge to issue fresh bids as it was bound
to further delay the project which was already delayed for six
months only because of the pending proceedings. A contention
was also raised that the fresh bidding was directed without H
866 SUPREME COURT REPORTS [2010] 3 S.C.R.
A offering any protection to the appellant herein against
cartelization. It was, therefore, apprehended that the two
multinational corporations, they being respondents 1 and 2 in
the appeal filed by Tehri Hydro, as leaders of the Consortia
could possibly get together and submit revised reduced bids
B which would not be in the public interest. The criticism by the
learned Single Judge in the impugned judgment to the effect
that there was no clarity on the issue whether two price bids
could be submitted was also assailed on various grounds. It
was pointed out that the price options of the respondent no.1
c were at Rs.2520.60 crores while after discount it was at
Rs.2483.80 crores. The price options of the respondent no.2
was at Rs.2327.50 crores as assignee and under Clause
9.4.4(v)(e) as a partner it was Rs.2261.60 crores and thus the
respondent no.2 was the lowest bidder. According to the
0 appellant this fact was completely lost sight of by the High Court.
4. Notice was ordered to be issued on 11.9.2009. At that
stage itself all the interested parties were being represented
through counsel. It was, however, expressed by the learned
Attorney General for India that in the national interest of
E completing the project early, the appellant was not averse to
inviting the fresh bids in light of the judgment of the High Court.
Accepting that plea, the following order came to be passed:
"Issue Notice.
F The affidavits shall be exchanged within three weeks from
today. Tehri Hydro Development Corporation shall invite
fresh bids in the light of the judgment of the High Court.
Both Alstom Hydro France and Voith Siemens Hydro
Germany shall be entitled to put in their bids. These bids
G shall be examined by the Tehri Hydro Development
Corporation and report shall be submitted to this Court in
a sealed cover. Needless to mention, all this shall be done
without prejudice to their rights and contentions. All
contentions shall be open. We are passing this order
H deliberately as we are told that a very important project is
TEHRI HYDRO DEVELOPMENT CORPORATION v. 867
ALSTOM HYDRO FRANCE [V.S. SIRPURKAR, J.]
held up. A
Put up after six weeks."
Accordingly fresh bids were invited and the respondents
1 and 2 submitted the same. As ordered in the earlier order
two bids were submitted to the Registry of this Court in the B
sealed covers. Learned Attorney General also offered that the
sealed covers could be opened in the office of the Registrar.
Accordingly, the bids were directed to be opened on
26.10.2009 at 4.30 p.m. in the office of Registrar (Judicial-I)
and copies thereof were directed to be given to the C
representatives of the respective parties. A Report was
submitted thereafter in the sealed covers and vide order dated
4.12;2009, the appellant was directed to process the matter
further on the basis of the fresh bids. The appellant, at this
stage, also offered to give hearing, if any, to the parties in D
respect of their objections to the fresh bids.
5. Before that since it was found that respondent no.2 had
impugned the order of the learned Single Judge dated
29.12.2009 by way of an appeal before the Division Bench of E
the Uttaranchal High Court being Special Appeal No.131 of
2009. That appeal got transferred to this Court.
6. On 3.12.2009 the respondent no.1 submitted a
representation against the exercise of scrutiny by the appellant.
It was suggested that the respondent no.1 had no opportunity F
to review the contents of the Report. Some other objections
were also raised insisting that ultimately the Tender should be
awarded in favour of the respondent no.1 alone. It seems that
all these objections raised by the respondent no. 1 were referred
to a Panel of Experts on 29.1.2010. A letter to that effect was G
written to both the respondents by the appellant. It was stated
in this letter that the examination report on fresh bids was
opened in the Court on 4.12.2009 and since the court had
directed the appellant herein to give hearing to the objections
· raised by the parties, if any, before the final decision and since H
868 SUPREME COURT REPORTS [2010] 3 S.C.R.
A the copies of the examination report were already supplied and
the appellant had received a representation raising objections,
in order to maintain the transparency the appellant had
constituted a Panel of three experts of national repute and
impeccable integrity to examine the objections raised by the
B Consortium of respondents. This panel of experts comprises
of following experts:
(i) Shri Ramesh Chandra (Ex-Chairman, CWC)
(ii) Shri D.V. Khera (Ex-Chairman, CEA)
c
(iii) Shri A.K. Shangle (Ex-Member, CWC)
The objections raised by the first respondent were inquired
into by the Panel of Experts. The Panel of Experts framed the
following question:
D
"Whether the examination report of THDC declaring the bid
of the Consortium of Mis.Alstom as non-responsive is OK
or the objections raised by the Consortium of Mis.Alstom
are justified with reference to the Terms & Conditions of
E the Tender, Techno-commercial bid submitted in October
2008 and fresh price bid submitted in October, 2009 and
their bid can be considered as responsive."
The Panel of experts have drawn a conclusion in their
report to the following effect:
F
"Based upon the views outlined above, POE is of the
opinion that fresh price bid of consortium of Mis.Alstom is
non-responsive. Their quoted price on partnership basis
even though non-responsive is however lower by Rs.84.5
crores (Mls.Voith Rs.21,551,245,304.00 - Mis.Alstom
G
Rs.20,705,840,090.00). Similarly, the quoted price on·
assignee basis though non-responsive is lower by
Rs.108.7 cores (Mls.Voith Rs.22,343, 174,985.00 - Ml
s.Alstom Rs.21,256,007,413.00). The unconditional offer
of consortium of Mis.Alstom to take care of THDC
H
TEHRI HYDRO DEVELOPMENT CORPORATION v. 869
ALSTOM HYDRO FRANCE [V.S. SIRPURKAR, J.)
observation without any extra cost so that bid becomes A
responsive and in accordance with employers' requirement
is not acceptable as this is not permissible under Bidding
Document of this Tender."
7. Ultimately when the matter was heard on 15.2.2010, a
8
copy of the report of the Panel of Experts was handed over to
the parties.
8. When the matter came up on 19.3.2010 Shri Harish
Salve, Senior Advocate and Dr.AM. Singhvi, Senior Advocate'
appearing for the respondent no.1 urged that the Panel of C
Experts had not given a· fair opportunity to it and that it had
merely reiterated what was already done by the appellant. The
respondent no.1, however, in order to give quietus to the matter
urged as under:-
0
"it is agreeable if the Government of India sends for the
files and considers all the objections raised by it and Voith
and issues appropriate directions to the appellant. Such
a power is available with the Government in relation to
PSUs in any event. If such an 'administrative review', is
conducted, the petitioner (respondent no.1 in the appeal E
filed by Tehri Hydro) states that it shall not challenge any
decision that may be taken in the matter by the Government
of India and the matter shall, as far as the petitioner
(respondent no.1 in the appeal filed by Tehri Hydro) is
concerned, be given a quietus". F
In short the respondent no.1 whose bid has been found to
be non-responsive by the appellant as well as Panel of Experts
was prepared to have a final decision from the Government of
India. G
9. Learned Attorney General as well as Shri F.S. Nariman,
Senior Advocate appearing on behalf of the respondent no.2,
however, opposed this plea. It was pointed out by the learned
Attorney General that at no point of time the integrity,
competence or capability of the members of the Panel of H
870 SUPREME COURT REPORTS [2010] 3 S.C.R.
A Experts was ever challenged by anybody including the
respondent no.1. The nature of objections raised to the report
is of technical character. Even in its objections the respondent
no.1 has not challenged the bonafides of the Panel of Expert.
though during the arguments the possibility of bias was
B expressed though haltingly. Learned Attorney General pointed
out that in case the respondent no.1 has any grievance of not
being heard by the Panel of Experts, the respondent no.1 could
still address the Panel of Experts which could be requested to
give a hearing to the respondent no.1. The Attorney General
c Pointed out that all the grievances, technical or otherwise could
well be raised before the Panel of Experts and for that purpose
a hearing could be given to all the concerned parties on the
basis of the objections raised by them which would atleast put
an end to the controversy.
D 10. The offer given by the Attorney General is undoubtedly
a fair offer. The respondent no.1 has no problem about the
matter being referred to the Government of India. We do not
think that in absence of any allegations/ charges made and
substantiated against the Panel of Experts, it would be proper
E to change the Panel of Experts and to appoint a new Panel of
Experts through the Government of India or some other panel.
There has to a finality somewhere. We are pained to note that
a very important project like the present one is being held up
in a legal battle between the two multinational companies. Till
F today, even the contract has not been finalized. All this would
invariably cause loss to the nation. After all, contractual rights
of these companies are not more important than the national
interest.
11. Under the circumstances we order that the Panel of
G Experts shall give one more final opportunity to the parties to
be heard and more particularly the respondent no.1 on the
objections that it has raised on the earlier report of Panel of
Experts and give a fresh report in the nature of
recommendations. This exercise should be completed by the
H end of April, 2010. The appellant herein would then, without loss
/
TEHRI HYDRO DEVELOPMENT CORPORATION v. 871
ALSTOM HYDRO FRANCE [V.S. SIRPURKAR, J.]
of time, take the decision, considering the report of the Panel A
of Experts regarding the award of contract.
12. This course would leave nothing to be decided in the
pending appeals. Firstly, when the Attorney General for India
agreed to invite fresh bids as per the directions of the High
8
Court, there remained nothing in that appeal as the invitation
for new bids would straightaway put the clock back and the
parties would be back to square one. Secondly, when all the
parties agreed to give their fresh bids in pursuance of the offer
made by Attorney General for India, there remained nothing in
the original controversies. The challenge to the judgment by C
respondent no.1 in the appeal arising out of SLP 19890 of
2009 would also not survive once both the contesting
respondents accepted the proposal to put bids again.
Therefore, at this juncture, it is futile to go into the earlier
controversies. Even the challenge by respondent no.2 would be D
of no consequence once the respondent no.2 was given a
fresh opportunity for bidding. The exercise of bidding before
this Court was ordered with the sole objective of saving time
and to give the transparency to the whole exercise. Once the
fresh bids were allowed to be given the old controversies before E
the High Court would naturally become extinct. In our opinion it
would be in the interest of the project which has already been
dragged by more than a year that the Panel of Experts should
be allowed to consider the objections and express their
opinion. That opinion shall then be considered by the appellant F
which would take the final decision on that basis. We must
reiterate here that it is not for this Court to award the contiacts
by accepting or rejecting the tender bids. It is exclusively for the
appellant herein to do that. One?. ail this exercise is over,
nothing would remain for :.:s t.J decide in these appeals. G
13. In view of the directions passed above both the
appeals as well as the Transfer Case No.33/2009 are
disposed of.
R.P. Matters disposed of. H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.