Created byFuzzy Cloud

Supreme Court of India

TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD. (TANGEDCO) REP. BY ITS CHAIRMAN MANAGING DIRECTOR AND ANR. ETC.versusCSEPDI - TRISHE CONSORTIUM, REP. BY ITS MANAGING DIRECTOR & ANR.

Citation
2016 INSC 968
Decided
18 October 2016
Disposal
Appeal(s) allowed

Holding

The Supreme Court held that the consultant’s financial evaluation is not amenable to judicial review and that the Division Bench erred in extending judicial review to the merits of the evaluation.

Summary

The Tamil Nadu Generation and Distribution Corporation (TANGEDCO) floated a tender for two 660 MW super‑critical power units. After qualifying, two bidders – CSEPDI‑TRISHE and BHEL – submitted supplementary price bids which were evaluated by an independent financial consultant. The consultant’s report awarded the contract to BHEL, citing a lower evaluated EPC cost. CSEPDI‑TRISHE challenged the evaluation, alleging that the consultant incorrectly included commitment fees and interest on management and guarantee fees, inflating its bid. The High Court’s Single Judge dismissed the challenge; the Division Bench set aside the award and directed a fresh evaluation, holding that the tendering authority had not complied with the Tamil Nadu Transparency in Tenders Act, 1998. On appeal, the Supreme Court held that complex fiscal evaluations are within the expertise of the consultant and that courts must apply the doctrine of restraint, limiting judicial review to procedural legality, not the merits of the financial computation. Consequently, the Division Bench’s extension of judicial review was erroneous, the order was set aside, and the appeal was allowed.

Issues considered

  • The consultant’s price evaluation report is prima facie erroneous and warrants judicial interference.
  • Whether inclusion of commitment fee and interest on management and guarantee fees in the bid evaluation is permissible under the TTIT Act and tender terms.
  • Whether the tendering authority complied with the procedural requirements of the Tamil Nadu Transparency in Tenders Act, 1998 (e.g., Section 10(6), Section 25(3)).
  • The scope and limits of judicial review in public procurement and tender evaluation.

Legislation cited

Subjects

Tender evaluationJudicial reviewDoctrine of restraintFinancial consultantTamil Nadu Transparency in Tenders ActPublic procurementCommitment feeInterest on feesContract award

Judgment

                        [2016] 7 S.C.R. 495


    TAMIL NADU GENERATION AND DISTRIBUTION                              A
CORPORATION LTD. (TANGEDCO) REP. BY ITS CHAIRMAN
        & MANAGING DIRECTOR AND ANR. ETC.
                               v.
 CSEPDI - TRISHE CONSORTIUM, REP. BY ITS MANAGING
            '-c     DIRECTOR & ANR.                                     B
           (Civil Appeal Nos. I 0182-10183 of2016)
                       OCTOBER 18, 2016
       (DIPAK MISRA AND SIDVA KIRTI SINGH, JJ.]
       Tender - Finalization of the bid - Evaluation report by the
Consultant - Judicial review - Held: Jn a complex fiscal evaluation,    c
the court has to apply the doctrine of restraint - Financial
computation involved, the capacity ana efficiency of the bidder and
the perception of feasibility of completion of the project have to be
left to the wisdom of the financial experts and consultants who have
knowledge and skills in the field - Courts cannot really enter into     D
the said realm in exercise ofpower ofjudicial review - If the courts
would exercise power ofjudicial review in such a manner it is most
likely to cause confusion and also bring jeopardy in public interest
- Further, an aggrieved party can approach the Court at the
appropriate stage, not when the bids are being considered~ Once
the price bid was opened, a bidder could not have submitted             E
representations on his own and sought mandamus from the Court to
take certain aspects into consideration - On facts, Consultant
analysed and determined the offers regard being had to the tender
conditions - Documents were called for by the owner from both the
qualifying bidders in a transparent manner and the same were            F
considered at the time of evaluation by the Consultant - It was
carried out before receipt of any additional document from either
side - Thus, the Division Bench erred in adopting the approach of
an appellate forum or authority and extended the principle of
iudicial review to certain areas - Order of Division Bench set aside
- Tamil Nadu Transparency in Tenders Act, 1998.                         G
        Allowing the appeals, the Court
        HELD: 1.1 It is manifest that the Corporation in its meeting
 held on 30.1.2014 had decided to open the price bids on both the
 bidders and thereafter the supplementary price bids were
obtained from both the parties for the additional implications items    H
                             495
496                SUPREME COURT REPORTS                      [2016] 7 S.C.R.



A         in respect of technical deviation quoted by both parties and
          thereafter the price bids were opened on 05.2.2014. As the factual
          matrix would reveal, the price bids were evaluated by the
          Consultant. The Single Judge has adverted to price evaluation
          report submitted by the Consultant. (Para 15) (503-D-F)
B                1.2 As per the Price Evaluation Report by the Consultant,
          the EPC price of the respondent No.1 was Rs.9207.264 crores
          and respondent No.2 to whom the contract was awarded was
          Rs.7762.977 crores. Thus, the difference between the two EPC
          price is Rs.1444.287 crores. The 1st respondent disputed the
          Price Evaluation Report by the Consultant on the ground that it
c         wrongly loaded the sum towards the commitment fee, interest
          on management fee during me period; and interest ofguarantee
          fee during JDC period in its bid amount which had led to the
          evaluation of quoted financial charges with interest to Rs.801.18
          crores. (Para 16) (505-C-F)                                         ·
D                1.3 The issue pertaining to correctness of Consultant's
          report has to be adjudged and scrutinized within the scope of
          limited power of judicial review in the obtaining factual score.
          The Division Bench in the impugned judgment has taken
          exception to the process adopted in the identification of Ll. It
          has referred to its order dated 19.8.2014 wherein the 1st
E         respondent was granted the time to submit additional documents.
          The impugned order takes note of the fact that at that point of
          time, the Corporation had never averred that tender had been
          finalized. It has referred to the earlier order of the Division Bench
          that representations were to be considered and till then the bid
F         should not be finalized. It has referred to the letter of the
          Chairman-cum-Managing Director of the Corporation dated
          20.7.2014 and opined that it appears to be a misstatement of fact.
          (Para 21) (509-B-D)
                 1.4 On interest on management and guarantee fee, the stand
          of the Corporation is that the respondent no. 1 quoted Rs.
G
          123.9746 crores as Management fees and Rs. 392.0163 crores
          as Guarantee fee in their Price bid. There is no dispute on the
          quantum of fees. The Consultant during the evaluation have
          worked out interest@ 7.2 per annum on the above fees as per
          the term sheet of the Industrial and Commercial Bank of China
H         Limited from the date on which they fall due since the above fees



      '
    TAMIL NADU GENERATION AND DISTRIBUTION                               497
  CORPORATION LTD. v. CSEPDI - TRISHE CONSORTIUM

 form part of the debt to be repaid by the appellant; that it is clear   A
 from the Tender Conditions as well as the Term Sheet provided
 by Industrial and Commercial Bank of China Limited and the
 clarification dated 21.10.2013 (issued by Industrial and
 Commercial Bank of China Limited) that appellant would be bound
 to pay the interest on the whole loan amount which would include
                                                                          B
 the financial charges. [Para 34) [520-C-E}
       1.5 It is vivid that the Consultant analysed the offers regard
 being had to the tender conditions. Be it ingeminated that the
 analysis and determination made by the financial consultant was
 carried out before receipt of any additional document from either
 side. The documents were called for by the owner from both the           c
 qualifying bidders in a transparent manner and the same were
 considered at the _time of evaluation by the Consultant. The
 respondent submitted that the evaluation is ex f acie defective
 inasmuch as the ConsuUant loaded certain charges as a
 consequence of which the price went gone up. The counsel for             D
 BHEL and counsel appearing for the Corporation submitted that
 the evaluation is founded on definities leaving nothing to any kind
-of contingency. They referred to the Term Sheet and what was
 put up by Industrial and Commercial Bank of China Limited. In a
 complex fiscal evaluation the Court has to apply the doctrine of
 restraint. Several aspects, clauses, contingencies, etc. have to         E
 be factored. These calculations are best left to experts and those
 who have knowledge and skills in the field.· The financial
 computation involved, the capacity and efficiency of the bidder
 and the perception of feasibility of completion of the project have
 to be left to the wisdom of the financial experts and consultants.       F
 The courts cannot really enter into the said realm in exercise of
 power of judicial review. Suffice it to say, it is neither ex /acie
 erroneous nor can be perceived as flawed for being perverse or
 absurd. (Para 36} (521-F-H; 522-A-C}
        1.6 The respondent, before finalization of the financial bid
 submitted series of representations and seeing. the silence of           G
 the owner it knocked at the doors of the writ court which directed
 for consideration of the representations. The High Court at that
 stage should have exercised caution. If the courts would exercise
 power of judicial review in such a manner it is most likely to
 cause confusion and also bring jeopardy in public interest. An           H
498          SUPREME COURT REPORTS                      [2016] 7 S.C.R.


A   aggrieved party can approach the Court at the appropriate stage,
    not when the bids are being considered. It is appreciable the
    owner in certain kind of tenders call the bidders for negotiations
    to show fairness transparently. But the instant case is not a one
  · of such nature. Once the price bid was opened, a bidder could
    not have submitted representations on his own and seek a
B
    mandamus from the Court to take certain aspects into
    consideration. This aspect is only to highlight the role of the Court
    keeping in mind the established principle of restraint. [Para 37]
    [522-D-F]
           1.7 The Division Bench through the delineation has adopted
c the approach of an appellate forum or authority and extended the
    principle of judicial review to certain areas to which it could not
    have and, therefore, the judgment and order of the Division Bench
    followed the path of error in continuum. [Para 38] [522-G]
           Jagdish Manda/ v. State of Orissa 2006 (10) Suppl.
D          SCR 606: (2007) 14 SCC 517; Star Enterprises v. City
           and Industrial Development Corporation of
           Maharashtra Ltd. 1990 (2) SCR 826 : (1990) 3 SCC
           280 - referred to.
                            Case Law Reference
    2006 (10) Suppl. SCR 606                 referred to    Para 11
E
    1990 (2) SCR 826                         referred to     Para 11
           CIVILAPPELLATE JURISDICTION: Civil Appeal Nos. 10182-
     10183 of2016
          .From the Judgment and Order dated 07.09.2015 of the High Court
F   of Madras   in WA No. 712 and 713 of2015
                                     WITH
           Civil Appeal No. 10184-10185 of2016.
           Mukul Rohatgi, A.G., Parag P. Tripathi, L. Nageshwar Rao,
     Subramonium Prasad, Sr. Advs., Atul Shankar Mathur, Ms. Nimita Kaul,
G Ms. Sweta Singh, (for Mis. Khaitan & Co.), Mayank Pandey, Ms. Meha
     Aggarwal, B. Balaji, Advs. for the Appellants.
           Kapil Sibal, Sriram Panchu, Sr. Advs. Gautam Narayan, N.L.
     Rajah,ArunAnbumani, Santanam Swaminathan, Gautam Narayan, N.L.
     Rajah, Arun Anbumani, Advs. for the Respondents.
 H         The Judgment of the Court was delivered by
    TAMIL NADU GENERATION AND DISTRIBUTION                                 499
  CORPORATION LTD. v. CSEPDJ - TRI SHE CONSORTIUM

       DIPAK MISRA, J. I. Leave granted.                                      A
       2. The appellant, Tamil Nadu Generation and Distribution
Corporation Ltd (for short 'the Corporation') vide notification dated
06.05.2013 floated a tender for setting up of two units of 660 MW Ennore
SEZ Supercricitcal Thermal Power Project at Ash Dyke of NCTPS,
Chennai wherein four bidders including the respondents herein · lJ
participated. However, two bidders out of four were disqualified as they
failed to meet the Bid Qualification Requirements (BQR) as a result of
which bids of Consortium ofTrishe Energy Infrastructure Services Private
Limited (CSEPDJ) and Bharat Heavy Electrical Ltd (BHEL) were taken
up for consideration. Prior to the opening of the price bid, CSEPDJ and
BHEL submitted supplementary price bids on 05.02.2014. Price bids C
were opened on 05.02.2014 by the appellant in the presence of the
representatives of the respondents, the qualified bidders.
       3. The uncurtaining of facts would depict that the !."respondent
sent series ofrepresentations dated 16.06.20 I4, I 7.06.2014, 01.07.20 I4
and 08.07.2014 to the appellant highlighting various aspects of the bid D
and the relevance of para (viii) of Clause 29.0 of the "Instructions to
Bidders" (ITB) which also deals with the rejection of bids of the tenderer
whose past performance/vendor rating is not satisfactory. Since the
appellant paid no heed to the request made by the respondent No. I, it
filed W.P. No. 1924 7 of 2014 seeking issue of a writ of mandamus to.
direct the appellant to consider the representations and comply with Tamil E
Nadu Transparency In Tenders Act, 1998 (for short, "the TTIT Act").
An undertaking was given before the learned Single Judge by the learned
Advocate General that post-bid representations submitted by the
respondent No. I will be duly considered while finalizing the tenders and
appropriate orders will be ·passed in accordance with the tender F
specifications and the TTIT Act and rules framed thereunder and in
terms of the said undertaking, learned Single Judge vide order dated
31.07.2014 directed the appellant to consider and pass orders on the
representations of the respondent no. I herein after affording them an
opportunity of personal hearing and directed that till such orders are
passed, the tender should not be finalised.                                   G
        4. Being aggrieved by the said order, the appellant filed writ appeal
W.A. No. 1065 of 2014 before the Division Bench which, by judgment
 and order dated 19.08.2014, disposed of the writ appeal by modifying
the order of the learned Single Judge only to the extent that affording of
 opportunity of personal hearing to the person was impermissible having H
     500             SUPREME COURT REPORTS                           [2016] 7 S.C.R.


     A     not contemplated under the Rules (for short, "the rules") and further
           permitted the respondent No. I to submit additional documents raising
           all its objections and the appellant was directed to pass an order and
           communicate the same to the respondents, CSEPDf and BHEL.
           However, the Division Bench did not modify the direction of the learned
           Single Judge which was to the effect that till a decision was taken on
     B
           representations of the I" respondent, the bid shall not be finalised.
                   5. After the disposal of the writ appeal, the respondent No. l sent
           its representation on 25.08.2014 along with necessary documents which
           was rejected by the appellant v.ide its communication dated 27.09.2014.
           The legal propriety of the said rejection was cal led in question by way of
     c     writ petition W.P. No. 26762 of 2014 seeking quashment of the same
           and further restraining the owner from taking steps to finalise the tender.
           During the hearing of the writ petition, a copy ofletter dated 27.09.2014
           awarding the contract to BHEL, respondent No. 2 herein, was brought
           on record. It was mentioned therein with regard to price negotiation
     D     meetings with the respondent No. 2. The respondent No. I sent a letter
           dated I. I 0.2014 to the appellant, highlighting the arbitrariness, anomalies
           and inconsistencies in its reasoning and the mala-fide intent in the matter
           of evaluation of the bid submitted by it. However, the appellant by letter
           dated 10.10.2014, informed the I" respondent that the subject tender
           had been finalised and awarded to BHEL.
\,   E             6. The letter dated 27.9.2014 awarding the contract to respondent
           No. 2 and letter dated I 0.10.20 I 4 were assailed by the respondent No. I
           by filing W.P. No. 27529of2014 for annulments of the letters and further
           for issue of directions to the Corporation to determine the award of the
           tender strictly in terms of the Tender/Bid document and taking into
      F    account the bid of respondent No. I and that of BHEL, the respondent
           No. 2 herein.
                   7. The learned Single Judge dismissed the writ petition primarily
           based on the perusal of notes in the files containing the Consultant Report
           dated 30.05.2014 and on that basis opined that the conduct of process of
           evaluation of the tenders did not appear to be arbitrary, capricious or
     G     unfair; and that price bids of the bidders had been evaluated as per the
           parameters indicated in the tender notification by an independent
           consultant who was selected as per the Board Resolution that was within
           the knowledge of both the bidders. The reasoning of the learned Single
           Judge basically hinged on the Consultant's Report that had determined
     H     that the respondent No.2 herein was LI and, therefore, the decision of
TAMILNADU GENERATION AND DISTRJBlITION CORPORATION                               50 l
  LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

the Corporation in treating BHEL as LI and awarding the contract was              A
neither arbitrary nor malafide.
       8. Aggrieved by the order of the learned Single Judge, the
respondent No. I preferred writ appeals before the Division Bench. The
Division Bench took note of the various pleas raised by the respondent
No. I including violation ofthe statutory provisions, arbitrariness, adoption     B
of unfair and non-transparent procedure, erroneous delineation of the
consultant's report by the learned Single Judge and non-consideration of
public interest.
       9. The Corporation, in its turn, contended before the Division
Bench that there was no violation of procedure and the award of the
contract was not amenable to judicial review in the obtaining factual             c
matrix and any interference would only delay the execution of the work.
It was also urged that Tender Accepting Authority (TAA) had accepted
the lowest tender and negotiations were held only with lowest bidder;
that Clause 25 .4 ofthe Instruction to Bidders did not permit the bidder to
change the substance of the bids after the bids were opened; that though          D
the respondent No. I had offered lower rate on interest, the original interest
rate offered was not in accordance with tender terms, for as per clause
 14.0(d)(5) the rate of interest quoted should be fixed, whereas the
CSEPDI had not specified the fixed rate of interest; that there was no
perversity or arbitrariness in the decision taken as per the terms of the
tender, prevalent banking practice and the Term Sheet given by the lender;        E
that the Consultant was appointed pursuant to the Board Resolution dated
28.01.2012 who participated in all pre-bid and post-bid meetings and the
minutes had been signed by all the parties and the consultant and,
therefore, CSEPDl was very much aware of appointment of the
consultant and the role played by consultant could neither be criticised          F
nor ignored.
        I 0. The 2"d Respondent herein contended that respondent No. I
lacked credibility to make any allegation against it; that design was the
core area of leader of the consortium and they have no experience in
India insofar as supercritical Thermal Power Projects are concerned;
and that the work was under progress and they had expended substantial            G
 amount.
        I I. After hearing the rival. contentions, the Division Bench placed
 reliance on Jagdisb Manda/ v. State of Orissa1 and observed that the
 approach of the owner was unfair in the tendering process. It further
 1 (2001) 14   sec s11                                                            H
502               SUPREME COURT REPORTS                         [2016] 7 S.C.R.


A     analysed the scheme of Section I 0 of the TTIT Act and held that the
      Tender Accepting Authority (TAA) has a role to cause objective
      evaluation of the tenders. Referring to Section I 0( 6) of the TTIT Act, it
      held that the Corporation had not complied with the said provision and it
      was a case of procedural impropriety, unfair approach and arbitrariness.
      The appellate Bench referred to the authority in Star Enterprises v.
B
      City and Industrial Development Corporation of Maharashtra Ltd."
      and declined to accept the stand of the Corporation by opining that
      reasons for rejection of I" respondent'sJepresentations could not be
      treated as reasons for rejection of its bid and hence, the decision making
      process was flawed and in breach of Section l 0(7) of the Act. It further
c     held that in the "Tender Bulletin", absence ofreasons for acceptance of
      tender, no statement of evaluation of tenders and no comparative
      statement of tenders.received and, decision thereon was in clear violation
      of the requirements of Section 6(1) read with Section IO of the TTIT
      Act and Rule 30(3) of the TTIT Rules. On the interest component and
      commitment fee, the Division Bench held that the approach was wholly
D
      arbitrary and the intention was to oust the respondent No. I, for the
      evaluation process adopted was meant to suit one and reject the other. It
      further held that the process adopted 1\11d the decision taken by the owner
      was arbitrary, unfair, irrational, biased and mala fide and did not serve
      the larger public interest. In view of the said analysis, the Division Bench
E     allowed the appeals and directed the Corporation to evaluate the price
      bid of the respondents in the light of its findings and taking into
      consideration all relevant parameters including the representations/
      documents submitted by respondent No. I and to record detailed reasons
      for the decision and communicate the same to the respondent No. I so
      as to comply with the requirement of the provisions of the TTIT Act and
F
      TTIT Rules and various decisions of this Court.
             12. Being aggrieved by the aforesaid judgment, the corporation
      and the successful bidder, by way of special leave, have preferred separate
      appeals.
G
             13. We have heard Mr. Mukul Rohatgi, learned Attorney General
      and Mr. Parag P. Tripathi, learned senior counsel for the appellant-SHEL
      and Mr. Subramonium Prasad, learned senior counsel for the appellant-
      Corporation, and Mr. Kapil Sibal, learned senior counsel for respondent
      No. I and Mr. Sriram Panchu, learned senior counsel for the respondent
      No.2.
H     '(1990) 3   sec 2so
 TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                               503
   LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

         14. It is apposite to note that in course of hearing it has been         A
  opined that the singular issue that is required to be addressed is "whether
  the Evaluation Report dated 301h May, 2014 by the Consultant, is prima
  facie erroneous, requiring interference within the parameters ofjudicial
. review". Such a singular point was required to be focused as Mr. Mukul
  Rohatgi, learned Attorney General appearing for BHEL and Mr.
                                                                                  B
  Subramonium Prasad learned senior counsel appearing for the Corporation
  had submitted as the subsequent offers either by BHEL or by the I"
  respondent need not be considered. At that juncture, Mr. Kapil Sibal
  learned senior counsel appearing for the I" respondent, the contesting
  party, had submitted that the Consultant's Report would graphically
  exposit that the respondent No. I was entitled to be declared as L-1            c
  even ifit is scrutinized within the limited parameters ofthe judicial review.
  The Court had directed for handing over the Consultant's Report to the
  learned counsel appearing forthe l" respondent. In view of the aforesaid
  submission, the opinion expressed on other issues by the learned Single
  Judge or by the Division Bench need not be adverted to.
                                                                                  D
        15. On a"perusal of the facts brought on record, it is manifest that
 the Corporation in its meeting held on 30.1.2014 had decided to open the
 price bids on both the bidders and thereafter the supplementary price
 bids were obtained from both the parties for the additional implications
 items in respect of technical deviation quoted by both parties and
 thereafter the price bids were opened on 05.2.2014. As the factual                E
 matrix would reveal, the price bids were evaluated by the Consultant.
 The learned Single Judge has adverted to price evaluation report submitted
 by the Consultant. Certain paragraphs from the report of the Consultant
 that were reproduced by him are as follows:-
        "4.0 Evaluation                                                            F
        4.1 BHEL
        BHEL has arranged finance from Mis .. Power Finance
        Corporation oflndia.
        They are arranged to finance 75% of the total cost as debt                 G
        at an interest rate of 12.25% p.a.
        AttachedAnnexures I to 5 indicate the methodology adopted
        in calculating the various components required for evaluation
        like !DC-Debt, !DC-Equity, IDC-UF Fess; Debt Repayment
        Schedule etc.
                                                                                   H
504         SUPREME COURT REPORTS                          [2016] 7 S.C.R.


A         4.2 CSEPDI - TRISHE
          CSEPDI-TRISHE has arranged finance from Mis. ICBC,
          China.
          They have arranged a finance 85% of the total cost as debt
          at an interest rate of7.2% p.a.
          Attached Annexures 6 to 12 indicate the methodology
B
          adopted in calculating the various components required for
          evaluation like JDC-Debt, JDC-Equity, IDC-UF Fess, Debt
          Repayment Schedule etc.
          5.0 Evaluated Lower Cost
                                          BHEL              CSEPDI-
c                                                           TRISHE
                                          All figures in    All figures in
                                          Rs. (Crores)      Rs. (Crores)
            Capacity                      1320MW            1320 MW
      A     Total EPC cost                7762.977          9207.264
            excluding VAT
D
      B     EPC Debt             75%      5822.233          7826.174
      c     EPC Equity           25%      1940.744          1381.090
      D     !DC Debt             12.25%   1295.079          1228.378
      E     EPC Debt Including            7117.311          9054.552
            !DC (B + D)
E     F     Upfront Fees                  8.925             801.180
            Including Interest
      G     Total Debt (E + F)            7126.237          9855.732
      H     Interest on Equity   14%      509.597          . 456.606
      I     Total Equity (C+H)            2450.341          1837.695
 F    J     Total Project Cost            9576.578          11693.427
            (G +I)
      K     Total Cost per MW             7.255             8.859
      L     PV - Debt                     7553.364          8464.318
      M     PV - Equity                   2809.403          2106.984
      N     Total PV                      10362.767         10271.302
G
      0     PV Cost per MW                7.851             7.781
      p     Loading for                   10.287            173.229
            Deficiency
      Q     Total (N+P)                   10373.054         10444.531
      R     Evaluated Bid                 7.858             7.913
            Price per MW
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                          505
  LTD. v. CSEPDI - TRlSHE CONSORTIUM [DlPAK MISRA, J.]

Paragraphs 4.0 and 5.0 of the "Price Evaluation Report" submitted by        A
the Consultant, which I have extracted above, show that the Consultant
took into account only the interest rate of 12.25% per annum for the
debt component arranged by BHEL from the Power Finance Corporation
of India. The Consultant did not take note of the reduced rate namely
12.15, subsequently offered by BHEL, for arriving at the conclusion that
                                                                            B
the "Evaluated Bid Price" ofBHEL was the lowest."
       16. There is no dispute that as per the Price Evaluation Report by
the Consultant, the EPC price of the respondent No. 1 was Rs.9207 .264
crores and respondent No.2 to whom the contract was awarded was
Rs.7762.977 crores. Thus, the difference between the two EPC price           c
is Rs.1444.287 crores. The 1" respondent disputed the Price Evaluation
Report by the Consultant on the ground that it wrongly loaded the sum
towards (a) the commitment fee, (b) interest on management fee during
JDC period; and (c) interest of guarantee fee during IDC period in its
bid amount which had led to the evaluation of quoted financial charges
with interest to Rs.80 l .18 crores.                                        D

       17. As regards the commitment fee, learned counsel for the
appellant submits that the contention of the respondent No. I that since
commitment fee was the fee to be charged on the unutilised amount of
the loan meaning thereby ifthe appellant failed to draw the loan amount
as undertaken, then only the commitment fee would be charged and,            E
therefore, the detennination after addition of the same was without any
rationale as the respondent No. I had quoted in the 'Calculation Sheet
for Financial Cost' in the supplementary bid commitment fee to the tune
of Rs.164.72 crores which was to be charged @ l o/o p.a. on accrued
drawals and if no commitment fee was required to be paid, the respondent     F
No.I should have mentioned the same to be nil or z.ero. To show that
the commitment fee is a part of the financial charges, learned senior
counsel has drawn our attention to clause 14(d) 6 of the Instruction to
Bidders under the tender, which reads as follows:-
      "6. Financing Charges : All financing charges of any                   G
      nomenclature relating to financing of the project including
      but not limited to Finders Fees, Commitment Fees,
      Arrangement Fees, Management Fees, Up Front Fees,
      Syndication Fees, Service Charges, Guarantee Charges,
      Other Fees and Taxes, if any should be clearly outlined in
                                                                             H
506            SUPREME COURT REPORTS                         [2016) 7 S.C.R.


A           the Financing Term Sheet. No variation in Financing
            Charges is permitted during the tenor of loan.
            3.37 "Financing Cost" means all financing charges of any
            nomenclature relating to financing of the project including
            but not limited to Finders Fees, Arranger's Fees,
B           Commitment Fees, Management Fees, Up Front Fees,
            Syndication Fees, Service Charges, Guarantee Charges,
            Other Fees and Taxes, if any."

             18: At this juncture we may also refer to clause 3.37 of Section 2
      that deals with the General Terms and Conditions of the Contract. It
c     defines the "Financing Cost" as follows:-

            "Financing Cost" means all financing charges of any
            nomenclature relating to financing of the project including
            but not limited to Finders Fees, Arranger's Fees,
            Commitment Fees, Management Fees, Up Front Fees,
D           Syndication Fees, Service Charges, Guarantee Charges,
            Other Fees and Taxes, if any".

             19. Clause 14 that deals with the conditions for a Binding Debt
      Financing Term Sheet, which needs to be reproduced in entirety. It
      reads as follows:-
E
            "14.0 Conditions for a Binding Debt Financing Term
            Sheet
            Bidder shall enter into a Memorandum of Understanding
            (MoU) with the Lender for the Debt Financing agreeing to
F           provide Financing for the Project and making payments
            directly to the Bidder based on bills certified by
            TANGEDCO as per the terms of payment Clause.
            The MoU shall be submitted by the Bidder along with their
            offer for signing of the loan agreement.
G           The Bidder shall be responsible for arranging the required
            financing and achieving Financial Closure of the project
            within 4 (Four months) from the date of Letter of Intent·
            (Loi).
            a. The Bidder and Lender shall furnish a joint undertaking
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                  507
  LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

    to fulfill the commitment made in the offer for Debt            A
    Financing arrangement from the Lender subject to due
    diligence.
    TANGEDCO will furnish the following documents to the
    lender for processing of Debt Financing to the successful
    bidder.                                                         B
    I. Profile ofTANGEDCO
    2. Audited Balance Sheet ofTANGEDCO for the last three
    financial years
    3. MOU entered between TANGEDCO & MMTC for long                 c
    term supply of coal of this project.
    4. Tariff order for sale of power.
    5. Copy of DPR
    b. It shall be understood that the Financing Term Sheet shall   D
    be based on preliminary appraisal of the project jointly by
    the Bidder and the Lender satisfying themselves on the
    project financial viability.
    c. It shall be understood that the Award of Contract to the
    Bidder is contingent upon successful financial Closure based     E
    on the Terms and Conditions provided in the Financing Term
    Sheet and in the event onhe Financial Closure does not
    materialize due to reasons attributable to the Bidder or the
    Lender or in the event of withdrawal by the Lender from
    the Project, the Bidder will forfeitthe security deposit.        F
    d. The Term Sheet should be full and complete with all
    material terms of financing including but not limited to:
    I. Loan Amount : At least 75% of the Total EPC Cost +
    100% of Interest during construction and Financing Cost.
                                                                    G
    2. Currency of Loan: INR/USD/Euro or a combination
    thereof.
    3. Tenor of the Loan: From the date of first drawal of the
    Loan upto 6 months from COD of the I" or 2nd unit
                                                                    H
508      SUPREME COURT REPORTS                        [2016] 7 S.C.R.


A     whichever is later and 15 years thereafter.
      4. Rate of Interest.
      5. Fixed Rate oflnterest till the entire tenor of the loan
      after taking into account the hedged cost.
B     6. Financing Charges : All financing charges of any
      nomenclature relating to financing of the project including
      but not limited to Finders Fees, Commitment Fees,
      Arrangement Fees, Management Fees, Up Front Fees,
      Syndication Fees, Service Charges, Guarantee Charges,
      Other Fees and Taxes, if any should be clearly outlined in
c     the Financing Term Sheet. No variation in Financing Charges
      is permitted during the tenor ofloan.
      7. Terms and conditions for draw down schedule.
      8. Moratorium for Repayment of Installment, Interest and
D     Financing Charges: All cash outflow obligation of
      TANGEDCO towards repayment of Installment, Interest
      and Financing Charges should be in INR (fully hedged) for
      the entire tenure of the loan and the repayment will
      commence only after 6months from the date of COD of
      later unit.
E
      9. Repayment Period: 15 years post IDC and moratorium
      in 60 equated quarterly installments
      I 0. Project Cash Flows and Installment Repayments
      statement should be submitted and will form part of the
F     Financing proposal. The Bidder shall indicate Draw Down
      Schedule of finance to match the supply and erection
      schedule of project activities.
      11. Equity requirements and related covenants.
      12. Security: Against Security the following can be made
G     available by TANGEDCO
      a. Hypothecation of all I 00% Project Assets
      b. Government Guarantee for the repayment of loan
      13. Validity period of the Term Sheet will be co-terminus
      with the validity of the bid."
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                              509
  LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

       20. The stand of the respondent as regards the interpretation of         A
Clause 14(d) 6 is that it only outlines all fees, but it does not mean that
every such fee is to be loaded for evaluating the bid to determine L l and
no commitment fee can be loaded for such evaluation. It is also put
forth that there can be no question of loading interest on commitment
~-                                                        -
                                                                                B
        21. As has been stated earlier, the issue pertaining to correctness
of Consultant's report has to be adjudged and scrutinized within the scope
of limited power of judicial review in the obtaining factual score. The
Division Bench in the impugned judgment has taken exception to the
process adopted in the identification of Ll. It has referred to its order
dated 19.8.2014 wherein the l" respondent was granted the time to                c
submit additional documents. The impugned order takes note of the fact
that at that point of time, the Corporation had never averred that tender
had been finalized. It has referred to the earlier order of the Division
Bench that representations were to be considered and till then the bid
should not be finalized. It has referred to the letter of the Chairman-         D
cum-Managing Director of the Corporation dated 20. 7.2014 and opined
that it appears to be a misstatement of fact.
       22, Be it stated that the Division Bench has posed two questions:-
       "(i) Whether interest offered by appellant is vague; and
                                                                                E
       (ii) Whether the reduction of interest from 7.2% to 6.2%
       should be accepted."
       23. While dealing with the said issue, the Division Bench has
referred to the publication in the tender bulletin stating about the decision
on tender:-
                                                                                 F
       " l. Name of the Tender: Chief Engineer/Civil/Projects &
       Environment, Inviting Officer, J•d Floor, NPKRR Maal igai,
       144, Anna Salai, Chennai - 600 002.
       2. a) Name of the Project/Detail of Purchase & Works:
       Establishment of coal based 2 x 660 MW Ennore SEZ                         G
       Supercritical Thermal Power Project in the ash dyke of
       existing NCTPS under Single EPC cum Debt Finance basis.
       Vayalurvillage, Thiruvallur District, Tamil Nadu.

                 '··                                                            H
510              SUPREME COURT REPORTS                            [2016) 7 S.C.R.


A
        SI.     Details             Tender Value      Decision on Tender
        No

                Mis.      Bharat 7840.087        Out of four bids received
                Heavy            Crores        & for this work and among
                Electricals      Lender: Powe1 the -qualified two bidders,
B
                Limited, BHEL    Finance         negotiation was called for
                House, Sirifort, Corporation     & held with the lowest
                New Delhi -      Limited         bidder viz M/s.BHEL.
                110 049          Rate of         After negotiation, tender
                                 Interest:       value of Rs. 7788 Crores, ·
c                                12.25%          Rate oflnterest at 12.15%
                                                 was accepted by the
                                                 Chief Engineer/Projects
                Consortium o; 9716.5974
                                                 and order for acceptance
                Central Southern Crores &
                                                 of the tender issued vide
                China Electric Lender:           this      office      issue
D       2       Power Design - Industrial &      Lr.No.CE/P/SE/M/EE-
                Ms. Trishe, 668, Commerce        1O/E/File.       2x660MW
                Minz      Road, Bank of China Ennore                    SEZ
                Ughan, China - Rate of           STPP/D.No.60/dt.27.09.2
                430 071          Interest; 7.2% 014
                                 (USD@Rs.
E                                59.26 at SBI
                                 Bill selling
                                 rate)

      Finally, M/s. BHEL/New Delhi offered bid for Rs. 7788 Crores was
      accepted by thtl Chief Engineer/Projects/Chennai and order for
F     acceptance of the tender was issued vide this officer Lr.No.CE/P/SE/
      M/EE-10/ E/File.2x660MW Ennore SEZ STPP/D.No.60/dt. 27.09.2014."
              24. Thereafter, the Division Bench has recorded as follows:-
              "31.3 While it is the plea of the appellant that fixed rate of
              7 .2-7 .5% per annum or LIBOR floating rate has been
G
              quoted by them, it is the case of the learned Advocate
              General that Clause 12.1 of the Instructions to Bidders
              stated that interest is to be quoted at fixed rate and it is not
              subject to change, and since the interest quoted is variable,
              it is not possible to evaluate the bid.
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                     511
  LTD. v, CSEPDI - TRISHE CONSORTIUM [DIPAK MISRA, J.]

    31.4 It is seen from the records, that subsequently, based         A
    on a query from the first respondent, the appellant had
    confirmed that it would be fixed rate of interest at 7.2%.
    the same was also confirmed in the Repayment Schedule
    and the same rate of interest was taken into consideration
    by the Consultant in his report dated 30.5.2014. He did not
                                                                        B
    find fault with the rate of interest. It is to be noted that the
    Term Sheet was submitted during July, 2013 and tender
    was evalu11ted in" the year 2014. The contention of
    vagueness in rate of interest does not appeal to us. When
    the Consultant's report dated 30.5.2014 is accepted by
    TANGEDCO for the purpose of evaluation, it has to be                c
    accepted for all purposes, though we have reservation on
    the Consultant's report dated 30.5.2014. There is; therefore,
    no vagueness in the rate of interest quoted at 7.2%.
    31.5 The second issue relates to the reduction of rate of
    interest. It is not in dispute that various meetings were held      D
    between the appellant and the TANGEDCO. The learned
    Advocate General states that the Consultant was appointed
    based on the 21" Board Meeting on 28.1.2012 and the
    Consultant participated in all pre-bid and post-bid meetings
    and minutes were signed by all parties, including BHEL
    and the appellant. He stated that the appellant was aware           E
    of the Consultant's appointment and his role. This only
    fortifies the fact that there have been series of consultation
    between both the bidders. The finding of the learned Single
    Judge that the appellant acted on inside information is
    demolished by the stand of the learned Advocate General             F
    as above. The insinuation has no basis.
    31.6 Coming to the issue of reduction of rate of interest,
    taking into consideration the prevailing market rate, the
    appellant offered to reduce the-rate of interest from 7.2%
    to 6.2% on 5.6.2014, even prior to any form of litigation.          G.
    When such an offer was given by the appellant the tender
    was not accepted in terms of Section 10(6) of the Act. To
    recapitulate, what has happened earlier is that the writ
    petition in W.P. No. 19247 of2014 was filed on 17. 7.2014,
    subsequent to the offer made on 5.6.2014. The first interim
                                                                        H
512            SUPREME COURT REPORTS                         [2016] 7 S.C.R.



A          order was passed on I 8. 7.20 I 4. The second interim order
           was passed on 31.7.2014. The Division Bench passed an
           order on I 9.8.2014. At that point of time, there was never
           a statement by the TANGEDCO that LI was identified
           and discussion was going on. We have also clearly stated
           that the statement of the Chairman-cum-Managing Director
8
           of TANGEDCO that the representations of the appellant
           will be duly considered by the Board of Directors while
           finalizing the tender and appropriate orders will be passed
           strictly in accordance with the tender specifications and by
           following the provisions ofTTIT Act and TTIT Rules.
c          31. 7 Therefore, the issue relating to reduction of rate of
           interest should have been considered. This reasoning of
           ours is also based on the fact that we have clearly held that
           the third respondent could not be ascertained as LI on
           2.6.2014 as per the statement of TANGEDCO or on
D          30.5.2014 as per the finding of the learned Single Judge.
           Once there is no identification of Lt, TANGEDCO is bound
           to consider the reduction in rate of interest of both the
           appellant in their offer dated 5.6.2014 aiid that of the third
           respondent dated 27.6.2014, reducing the rate of interest
           from I 2.25% to 12. I 5%.
            3 I .8 Even otherwise, by virtue of the power under Clause
            25 .3 of the Instructions to bidders, which states that "The
            Purchaser reserves the right to relax or waive any of the
            conditions of this Specification in the best interests ofthe
            TANGEDCO", the TANGEDCO could have considered
F           such reduced rate of interest offered by the appellant and
            the third respondent."
           25. With regard to commitment fee, the analysis of the Division
      Bench is worth referring to:-

G           "It clearly states that Commitment Fee is only on the
            cancelled portion of the loan. That apart, even as per the
            Drawdown Schedule, the fee is to be paid only if the loan
            amount is not drawn by the I 81h, 30th and 42"d month.
            Moreover, the appellant in the letters dated
            13.6.2014, 16.6.20 I 4 and 17.6.2014, clarified that
H
TAMJL NADU GENERATION AND DISTRIBUTION CORPORATION                         513
  LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

      Commitment Fee is only on the unused credit line and that            A
      there shall be no Commitment Fee if the loan amount is
      fully utilized as per the Drawdown Schedule. All these
      representations sent by the appellant were not considered
      by TANGEDCO, despite there being a specific direction
      by the Division Bench of this Court to consider the same.
                                                                            B
      It is a clear case of arbitrariness in approach and intended
      to oust the appellant. This act of the TANGEDCO is nothing
      but a case of malafide in evaluation process to suit one and
      reject the other."
      26. While dealing with the consultant's report, the Division Bench
has proceeded to state thus:-                                               c
      "33.3 Even as per the Consultant's Report the difference
      between the bid of the appellant and the third respondent is
      around Rs. 71 Crores. That being the case, if either the
      Commitment Fee of Rs.156.184 Crores or the interest on
      Management Fee and Guarantee Fee for the 36 month                     D
      construction period is not loaded on the appellant, it will
      have a bearing on deciding which one of the two is the
      lowest bid. Assuming the Consultant's report is of any value,
      such report without considering the relevant material is of
      no use. The approach to add these figures without taking              E
      note of the representations and additional particulars/
      documents is, therefore, arbitrary and tainted in bias. This
      is in violation ofthe Division Bench judgment as well as the
      orders of the learned Single Judge in the first round of
      litigation."
                                                                            F
      27. And again:-
      "The financial implication in respect of two tenderers has
      been specified by the Consultant. .The issue is what factors
      mean and how it impacts the bid. We find that the
      Repayment Schedule submitted by the appellant with regard             G
      to interest on management fee ang guarantee fee during
      JDC period is an accepted document by the Consultant. If
      nothing more is to be paid beyond that and that is clarified
      in the course of representation fo clear terms, we fail to
      understand as to how this amount could be included in the
                                                                            H
514       SUPREME COURT REPORTS                              [2016] 7 S.C.R.


A      cost when there is no implication. The Consultant, as we
       have held, did not have the benefit of considering the
       representation and other documents on the financial
       implications in this issue. His opinion is therefore not based
       on relevant document/representation. This we have held is
       not in conformity with the orderofthe learned Single Judge
B
       in the first round oflitigation, which was confirmed by the
       Division Bench. Withholding such a factor and to obtain an
       evaluation from the Consultant loading the bid of the
       appellant is clearly a case of bias. It is an unreasonable
       approach and an unfair gesture which crumbles the spirit
c      of transparent tender."
        "33.6 We, therefore, have no hesitation to hold that the first
        respondent had erroneously added interest on Management
        Fee and Guarantee Fee when there is none and there is no
        ambiguity or vagueness. Once the appellant has indicated
D     _,in the representation, in clear terms, as to how it should be
        treated, in the light of the order ofthe Division Bench, which
        TANGEDCO accepted to consider the bid of the appellant,
        the first respondent ought not to have loaded this amount
        on the basts of the Consultant's Report. In all fairness, the
        Tender Accepting Authority of the first respondent should
E       have excluded this amount, if both the bidders are to be
        treated on the touchstone of fairness and on the doctrine of
        level-playing field. This becomes necessary because the
        entire tender is tested on the larger public interest, that is to
        say, the implementation of the project in a time bound manner
F       where cost is another important factor to be considered in
        the_ decision making. In a Welfare State, public authority
        cannot decide arbitrarily to throw away such an offer which
        they agreed to consider in the course ofjudicial proceedings,
        which we have referred to above. These factors, namely,
        adding interest on Management Fee and Guarantee Fee,
G       have to be eschewed for the purpose of considering the bid
        of the appellant, otherwise, it will suffer from the vice of
      _ mu:~ason~bl~ness and irrationality."
       28. Eventually, it was directed as follows:-

H      "The TANGEDCO is directed to evaluate the appellant's
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                           5I5
  LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

      price bid along with the bid of the third respondent, in the           A
      light of our findings as .above and also taking into
      consideration in all required parameters and the clarifications
      submitted by the appellant in its various representations, as
      directed by the Single Judge in the order dated 31.7.2014
      and that of the Division Bench in its order dated 19.8.2014,
                                                                             B
      afresh, at the earliest."
       29. Before this Court, the consultant's report is criticized by the
I" respondent stating thus:-
      "2.3 The Consultant has made the following errors in the
      calculation of the said 'Upfront Fees Including Interest' in           c
      respect of CSEPDI's bid:
      Error 1 : Included Commitment Fees
      Error 2: Calculated and loaded interest on (a.) Guarantee
      Fee, (b.) Management Fee and (c.) Commitment Fee during
      the constructiori period of 36 months, i.e., IDC (Interest             D
      During Construction)                                   ---
      2.4 In 5.0 Item F - 'Upfront Fees Including Interest', the
      Consultant has loaded BHEL with Rs.8.925 Crores and
      CSEPDI with Rs. 801.l80 Crores. The break-up of this
      Rs. 801.180 Crores in the Consultant's Report is as follows:            E
      a. Guarantee Fee            ··       Rs. 371.743 Crores
      b. Management Fee·                   Rs. 117.393 Crores
      c. Commitment Fee                    Rs. 156.184 Crores
      d. Interest for 36 months                                               F
                                                                                      !
                                                                                   ... ·1
         on a,b,c (Rs. 127.613 Crores)
      e. Interest from J7•h to 42nd month:          Rs. I 5 5 . 8 6 0
      Crores on a,b, & c (Rs. 28.247 Crores)
                         Total                 Rs. 801.180 Crores             G
     -2.4.1 There is no issue on entries a. and b. above
      2.4.2 The issue is with regard to entries c. and d. above.
      2.4.3. As regards c., no Commitment Fee can be loaded,
      for the reasons explained below.                                       H
516            SUPREME COURT REPORTS                         (2016] 7 S.C.R.


A           2.4.4 As regards d., no interest can be loaded for the
            construction period of 36 months on Guarantee Fee and
            Management Fee, for the reasons explained below. The
            question of interest on Commitment Fee does not arise at
            all because no Commitment Fee can be loaded in the first
            place for evaluation of CSEPDI's bid.
B
            2.4.5 e. above will stand reduced as it depends on c. and d.
            2.5 If the Consultant had correctly evaluated CSEPDI's
            price bid by not including Commitment Fee and Interest on
            Guarantee Fee. Management Fee and Commitment Fee
c           for the construction period of 36 months, then CSEPDI
            would be LI by Rs. 171.600 Crores. NeitherTANGEDCO
            nor BHEL have disputed this fact.
                      x       x        x       x        x       x
            2. 7 The Consultant has confused Commitment Fee with an
D           Upfront Fee. Commitment Fee, as stated above, is a
            contingency fee payable ifthe scheduled drawal does not
            take place. An Upfront Fee is levied by the lender as a
            definite fee without any contingency. This is made clear
            by PFC (BHEL's lender) letter dated 30-04-2015 showing
E           Commitment Fee and Upfront Fee as distinct alternatives.
            The Consultant has loaded BHEL with Upfront Fee. The
            Consultant has erroneously treated Commitment Fee as an
            Upfront Fee for CSEPDI and has in fact applied the label
            Upfront Fee in Item F".

F           30. With regard to the commitment fee, various financial nuances
      have been stated. We think it apt to reproduce some ofthem:-
            "2.8.3 When the earmarked funds are drawn, the interest
            agreed is payable. When the earmarked funds are not
            drawn, the interest is not payable but instead the
            Commitment Fee has to be paid on the amount not drawn.
G
          · 2.8.4 CSEPDI's Term Sheet clearly mentions that the
            Commitment Fee is payable on the cancelled portion of the
            loan,
            2.8.5 The term 'Accrued Drawal' refers to the amount
'H          accured and available for drawal, but not drawn.
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                   517
  LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

     2.8.6 Commitment Fee is therefore only a contingent fee         A
   · leviable ifthe funds are not drawn as per the Drawdown
     Schedule. It is more in the nature of a penalty in the event
     of a default by the borrower TANGEDCO and is payable
     by TANGEDCO. This cannot be added to the project cost
     for evaluation of the price bid.
                                                                     B
              x        x        x       x        x        x
    2.8.8 The Repayment Schedule sets out the entire amount
    to be paid by TANGEDCO in the form of 48 Equated
    Quarterly Installments (EQI) starting from the 43'd months
    of the date of financial closure for 12 years. If there is one   c
    document to be termed as most important to evaluate the
    Price Bid, it is this Repayment Schedule. The Repayment
    Schedule is part of the Price Bid and is absolutely crucial
    as it caps the amount TANGEDCO has to pay. Not a
    single rupee needs to be paid over and above the amounts
    mentioned in the Repayment Schedule.                             D

    2.8.9 The EQI in the Repayment Schedule is based on the
    figure of Rs. 15,038.2914 Crores, which. comprises of
    interest Rs. 5,025.3628 Crores on the Net Loan amount of
    Rs. I 0,012.9286 Crores. The components of this Net Loan
    amount are:                                                       E
    a. Loan amount
    (85% of Total EPC
    Cost of9709.3822 Crores)                  Rs. 8252.9748/-
    b. Interest at 7.2% p.a. on the
    above loan amount during                                          F
    the Construction Period of36               Rs. 896.2032/-
    months
    c. Guarantee Fee                           Rs. 392.0163/-
    d. Management Fee                          Rs. 123.7946/-
    Moratorium Period interest
    for 37'h to 42°d month                                           G
    (interest at 7.2% p.a. for
    6 months on the total of
    a,b,c and d. above)                        Rs. 347.9396/-
    Total                                      Rs.10,012.9286/-*
                                                                     H
518            SUPREME COURT REPORTS                           [2016) 7 S.C.R.


A           *The Price Bid submitted by CSEPDI was Rs. 9709.3822
            Crores and the above calculations were on that basis.
            However the admitted position is that of this sum, Rs.
            509.339 Crores was disallowed by TANGEDCO and the
            Price Bid was arrived at Rs.9207.264 Crores. The
            Consultant has also evaluated CSEPDl's bid at Rs. 9207.264
B
            Crores".
            31. With regard to no interest on guarantee fee and management
      fee during the construction period of 36 months and no interest on
      Commitment fee, the stand of the l" respondent has been put forth in
      various compartments. We think it apt to reproduce the relevant grounds:-
c
            "2.9.1 The Consultant ought not to have loaded interest on·
            Guarantee Fee and Management Fee during the construction
            period of36 months, for the evaluation ofCSEPDI's Price
            Bid.
D           2.9.2 The very same Repayment Schedule calculalion set
            out above shows that no interest is being charged on
            Guarantee Fee and Management Fee during the construction
            period of36 months and does not form part of the amount
            which TANGEDCO has to repay. Not a single rupee needs
            to be paid over and above the amounts mentioned in the
.E
            Repayment Schedule.
            2.9 .3 The only interest payable during the construction period
            of36 months is interest calculated at 7.2% p.a. on the basic
            loan amount (85% of the EPC cost) and not on any other
            amount like Guarantee Fee and Management Fee. This is
 F          made clear in the specific calculation sheet for Interest
            During Construction submitted by CSEPDI in its Price Bid.
            2.9.4 The Term Sheet submitted by CSEPDI outlines the
            fees required to be paid by TANGEDCO and the
            circumstances in which they are payable. In the very nature
G           of this contract, the items chargeable have to be mentioned,
            not the items not chargeable. The contract requires to be
            evaluated based on what the bidder is charging
            TANGEDCO.
            2.9.5 In CSEPDI's Term Sheet, mention is made of
H           Management Fee and SINOSURE Re-insurance
  TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION                         519
    LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]

        (Guara11tee Fee). No mention is made of interest on                   A
        Management Fee and Guarantee Fee for the construction
        period of36months.                              ·
        2.9.6 As far as interest on Commitment Fee is concerned,
        the same does not arise as Commitment Fee itself cannot
        be loaded for evaluating CSEPDl's bid."         -                     B
            J2. The 1" respondent has also put forth that the Consultant was
   not right in loading on CS.EPDI bid the values for Commitment Fee and.
   Interest thereon and Interest on Guarantee Fee and Management Fee
   during the construction period of36 month~, because that Clause 14.d.6
   only states that details ofthe Financing Charges should be clearly outlined C
   in the Financing Term Sheet and does.not state that it should be include.d
   in the pdce evaluation; that the reference to Commitment Fee in the
   Term Sheet clearly indicates that it is only on the cancelled portion of the
   loan; that the fee is to be paid only if the loan amount is not drawn by the
    I 8'h, 30'h and 42"d months in accordance with the Drawdown Schedule;
   that Clause I 2. i and Clause 32. I.I makes no mention of hiterest on · D
   Financing Charges (i.e., on Management Fee and Guarantee Fee) during
   the IDC period; that the words 'Interest and Financing Charges' cannot
   mean interest on financing charges; that there is absolutely no variance
   between the Term Sheet and Repayment Schedule submitted by·
•. CSEPDl; that the Term Sheet and the entire Financial Prop<?sill/Price E
   Bid, incl.uding the Repayment Schedule, are to be read together;·thatthe''
   CSEPDI's Term Sheet only mentions that a Management Fee Is to .be
   paid but'does not mention any interest .on Management Fee'for the 36
   month construction period (lDC period) and that the Consultan~ ought.
   notto have loaded the disputed amounts for evaluating the price bid of
   CSEPDI. It is also the stand that on a perusal ofthe Comparison Sheet F
   filed would indicate that CSEPDI is LI by Rs.17L600 crores if the ·
   evalul!-tion is done correctly. That apait, the I" respondent has raised
   other grounds which we need not refer to in detai I.·
        33. The Corporati~n in supe.~rt ofthe Gons~ltant's Report has
 stated that the stand of the l" respondent thatNet.LoanAmQunt in the G
 repayment schedule provided by respond~nt No. I gives no break up of
 how the said figure has been reached; that one cannot find out from a
 bare perusal of the said Repayment Schedule as to whether the
 respondent No. I has factored the component ofCommfrmentFee in the
 Net Loan A1~ount; that the resppndent having not been declar~d as Ll . H
520             SUPREME COURT REPORTS                           [2016] 7 S.C.R. ·


·A      bidder as a post facto contention, now say that Commitment Fee shall
       not be taken for evaluation in spite of the fact that they themselves have
      . quoted Commitment Fees for Rs.164.702 crores with split up details in
        the price bid and the above post facto contention is against all tenets of
        fairness and justice; that had the respondent No.1 become L1, they would
        have insisted that Commitment Fee being a financial charge forms part
 B
        of the loan and therefore is payable by the borrower i.e., the Corporation
        as per their price bids submitted by respondent No. I; that since the
        respondent No. I had not been evaluated as LI, a contention is advanced
        that Commitment Fee should not be taken for evaluation citing universal
        definition.
 C              34 .. On interest on management and guarantee fee, the stand of_
        the Corporation is that the CSEPDI-TRISHE CONSROTIUM have
        quoted Rs_ J23 .9746 crores asManagemenffees and Rs. 392.0163 crori:s
        as.Guarantee fee in their Price bid. There is no dispute on the quantum
        of fees. The Consultant during the evaluation have worked out interest
 D      @ 7.2 per annum on the above. fees as per the term sheet of the Industrial
        and Commercial Bank of China Limited from the date on which tliey fall
        due. since· the above fees form part of the debt to be repaid by the
        appellant; that it is clear from the Tender Conditions as well as the Term
        Sheet provided by Industrial and Commercial Bank of China l,.imited
        and the clarification dated 21.10.2013 (issued by Industrial and
 E      Commercial Bank of China Limited) that appellant herein would be bound
        to pay the interest on the whole loan amount which will include the
        finanqial charges.                                     ··
           35. The Corporation has quoted the relevant tender conditions
     from the Term Sheet submitted by Industrial and Commercial Bank of
 F . China Limited which are reproduced below:-
              • "Clause 14(d)I of the Instruction to Bidders under the
              Tender defines the "Loan Amount" to include at least 75%
              ofthe totalEPC cost+ 100% ofinterest during construction ·
              and Financing Cost. As per clause 14(d) 6_of the Instruction
 G            to Bidders under the Tender management fee and guarantee
            · ftie is part oft~e financial charges/financial
                                                   '        '
                                                             cost.
                                                             .     '

             • Under thti term relating to "Interest rate" in term sheet
             submitted by Industrial and Commercia! BankofChina it is
             clearly provided that the Borrower will pay interest on the
 H           full loan amount at a fixed rate per annum.
                                                                                ,   .
TAMILNADU GENERATION AND DISTRIBUTION CORPORATION                         52 l
  LTD. v. CSEPDI - TRlSHE CONSORTIUM [DIPAK MISRA, J.]

      • Under the terms defined as "management fee". in the                A
      term sheet submitted .by Industrial and Commercial Bank·
      of ChinaLimited .it is specified that Management fee of
      1.5% tlaton the Loan Amount will be payable to the lender
      within a period of60 days from the date offinancial closure.
      Six months is the time given for financial closure and so 8          B
      months in case of management fee in view of outer limit of
      60 days.
      • · Similarly;· under the terms relating to "Conditions
      Ptecedent'', tlie-condition(d) the term sheet specifies that
      petitioners will •be charged .guarantee Jee (termed as
      Insura11ce··Policyofo4he·term,.sheet) ·at.the rate of·5% on
                                                                           c
      95%oftheJoan amountand.the.samewill be payable from
      the ·end ofthe 6'h month.          ·                .
      • .According to the term sheet the amounts get debited
      to the Petitioners account at the end of the s•1t month and          D·
      61h month respectively.
      • Allfin.ancial .costsform part ofthe debt taken fro1n the
      lndustrial"and Commercial Bank ofChina Limited .. As per
      theclarification dated2l.10.2013 issued by Industrial and
      Commercial BankoofChina Limited which is the Lender                  E
      institutionforRespondent no. I all costs and fee charged by
      ICBGwill fQrrn·partofthe debt financing".
                                                  "
       36; From the aforesaid, it is vivid that the Consultant has analysed
the offers regard being had to the tender conditions, Be it ingeminated .
that the analysis and determination made by the financial consultant has
                                                                            F
been carried out before receipt of any additional document from either
side. The documents were called· for by the owner from both the
qualifying bidders in a transparentmanner and the same, have been
considered at the time of evaluation byth.e Consultant Submission of
Mr, Sibatis thatthe evaluation is exjacie defective foasmuch as the
Consultant has loaded ce1tain charges as a consequence of which the G
price has gone up, Mr; Rohatgi, learned Attorney(foneral appearing for
BHELand Mr;·l>tasad;Jearned senior .counsel appearing for the
Corporation would submit thatthe evaluation·is founded on definities
leaving nothing to any kind of contingency. They have referred to the
Term ~heeNmd what is put up by Industrial and Commercial Bank of H.
                                                                     _,
522               SUPREME COURT REPORTS                       [2016) 7 S.C.R.


A · China Limited. At this juncture we are obliged to say that in a complex
    fiscal evaluation the Court has to apply the doctrine of restraint. Several
    aspects, clauses, contingencies, etc. have to be factored. These
  · calculations are best leftto experts and those who have knowledge and
    skills in the field, The financial computation involved, the capacity and
B efficiency ofthe bidder and the perception of feasibility of completion of
  · the project have to be left to the wisdom of the financial experts and
    consultants. The courts cannot really enter into the said realm in exercise
    of p,ower of judicial review. We cannot sit in appeal over the financial
    consultant's assessment. Suffice it to say, it is neither exfacie erroneous
    nor can we perceive as flawed for being perverse or absurd.
c            37. Before parting with the case we _are constrained to add
     something. We do so with immense pain. The respondent, before '
     finalization of the financial bid submitted series ofrepresentation~ and
     seeing the silence of the owner it knocked at the doors of the writ court
     which directed for consideration of the representations. We are disposed
D    to think that the High Court at that stage should have exercised caution.
    If the courts would exercise power of judicial review in.such a manner
     it is most likely to cause confusion and also bring jeoplirdy i11 public
   · interest. An aggrieved party can approach the Court at the appropriate
     stage, not when the bids are beiiig considered. We do not intend to specify.
     It is appreciable the owner in certain kind of tenders call the bidders for
E negotiations to show fairness transparently. But the present case is not a
     one of such nature. Once the price bid was opened, a bidder could not
     have submitted representations on his own il:nd seek a mandamus from
     the Court to take certain aspects into consideration. We have stressed
  . this aspect only to highlightthe role of the Court keeping in mind the
F · established principle of restraint.
           38. In view of our preced.ing analysis we are of the considered
    opinion that the Division Bench through the delineation hasndopted the
    approach of an appellate forum or authority and extende~ the principle
    ofjudicial review to certain areas to which it could not have and, therefore,
G thej\ldgment and order of the Division Bench followed the path of error
    in continuum. Consequently, the inevitable conclusion is, unsettlement of
  . the impugned order and we so direct. In the ultimate eventual the appeals· ·
   'stand allowed. There shall be no order as to costs.
      NidhiJain                                                 Appeals allowed .
                                                                  .'~




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Tender evaluation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.