TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD. (TANGEDCO) REP. BY ITS CHAIRMAN MANAGING DIRECTOR AND ANR. ETC.versusCSEPDI - TRISHE CONSORTIUM, REP. BY ITS MANAGING DIRECTOR & ANR.
- Citation
- 2016 INSC 968
- Decided
- 18 October 2016
- Disposal
- Appeal(s) allowed
- Bench
- DIPAK MISRA
Holding
The Supreme Court held that the consultant’s financial evaluation is not amenable to judicial review and that the Division Bench erred in extending judicial review to the merits of the evaluation.
Summary
The Tamil Nadu Generation and Distribution Corporation (TANGEDCO) floated a tender for two 660 MW super‑critical power units. After qualifying, two bidders – CSEPDI‑TRISHE and BHEL – submitted supplementary price bids which were evaluated by an independent financial consultant. The consultant’s report awarded the contract to BHEL, citing a lower evaluated EPC cost. CSEPDI‑TRISHE challenged the evaluation, alleging that the consultant incorrectly included commitment fees and interest on management and guarantee fees, inflating its bid. The High Court’s Single Judge dismissed the challenge; the Division Bench set aside the award and directed a fresh evaluation, holding that the tendering authority had not complied with the Tamil Nadu Transparency in Tenders Act, 1998. On appeal, the Supreme Court held that complex fiscal evaluations are within the expertise of the consultant and that courts must apply the doctrine of restraint, limiting judicial review to procedural legality, not the merits of the financial computation. Consequently, the Division Bench’s extension of judicial review was erroneous, the order was set aside, and the appeal was allowed.
Issues considered
- The consultant’s price evaluation report is prima facie erroneous and warrants judicial interference.
- Whether inclusion of commitment fee and interest on management and guarantee fees in the bid evaluation is permissible under the TTIT Act and tender terms.
- Whether the tendering authority complied with the procedural requirements of the Tamil Nadu Transparency in Tenders Act, 1998 (e.g., Section 10(6), Section 25(3)).
- The scope and limits of judicial review in public procurement and tender evaluation.
Legislation cited
- Tamil Nadu Transparency in Tenders Act, 1998s. 10(6), s. 10(7), s. 25(3), s. 6(1)
Subjects
Judgment
[2016] 7 S.C.R. 495
TAMIL NADU GENERATION AND DISTRIBUTION A
CORPORATION LTD. (TANGEDCO) REP. BY ITS CHAIRMAN
& MANAGING DIRECTOR AND ANR. ETC.
v.
CSEPDI - TRISHE CONSORTIUM, REP. BY ITS MANAGING
'-c DIRECTOR & ANR. B
(Civil Appeal Nos. I 0182-10183 of2016)
OCTOBER 18, 2016
(DIPAK MISRA AND SIDVA KIRTI SINGH, JJ.]
Tender - Finalization of the bid - Evaluation report by the
Consultant - Judicial review - Held: Jn a complex fiscal evaluation, c
the court has to apply the doctrine of restraint - Financial
computation involved, the capacity ana efficiency of the bidder and
the perception of feasibility of completion of the project have to be
left to the wisdom of the financial experts and consultants who have
knowledge and skills in the field - Courts cannot really enter into D
the said realm in exercise ofpower ofjudicial review - If the courts
would exercise power ofjudicial review in such a manner it is most
likely to cause confusion and also bring jeopardy in public interest
- Further, an aggrieved party can approach the Court at the
appropriate stage, not when the bids are being considered~ Once
the price bid was opened, a bidder could not have submitted E
representations on his own and sought mandamus from the Court to
take certain aspects into consideration - On facts, Consultant
analysed and determined the offers regard being had to the tender
conditions - Documents were called for by the owner from both the
qualifying bidders in a transparent manner and the same were F
considered at the time of evaluation by the Consultant - It was
carried out before receipt of any additional document from either
side - Thus, the Division Bench erred in adopting the approach of
an appellate forum or authority and extended the principle of
iudicial review to certain areas - Order of Division Bench set aside
- Tamil Nadu Transparency in Tenders Act, 1998. G
Allowing the appeals, the Court
HELD: 1.1 It is manifest that the Corporation in its meeting
held on 30.1.2014 had decided to open the price bids on both the
bidders and thereafter the supplementary price bids were
obtained from both the parties for the additional implications items H
495
496 SUPREME COURT REPORTS [2016] 7 S.C.R.
A in respect of technical deviation quoted by both parties and
thereafter the price bids were opened on 05.2.2014. As the factual
matrix would reveal, the price bids were evaluated by the
Consultant. The Single Judge has adverted to price evaluation
report submitted by the Consultant. (Para 15) (503-D-F)
B 1.2 As per the Price Evaluation Report by the Consultant,
the EPC price of the respondent No.1 was Rs.9207.264 crores
and respondent No.2 to whom the contract was awarded was
Rs.7762.977 crores. Thus, the difference between the two EPC
price is Rs.1444.287 crores. The 1st respondent disputed the
Price Evaluation Report by the Consultant on the ground that it
c wrongly loaded the sum towards the commitment fee, interest
on management fee during me period; and interest ofguarantee
fee during JDC period in its bid amount which had led to the
evaluation of quoted financial charges with interest to Rs.801.18
crores. (Para 16) (505-C-F) ·
D 1.3 The issue pertaining to correctness of Consultant's
report has to be adjudged and scrutinized within the scope of
limited power of judicial review in the obtaining factual score.
The Division Bench in the impugned judgment has taken
exception to the process adopted in the identification of Ll. It
has referred to its order dated 19.8.2014 wherein the 1st
E respondent was granted the time to submit additional documents.
The impugned order takes note of the fact that at that point of
time, the Corporation had never averred that tender had been
finalized. It has referred to the earlier order of the Division Bench
that representations were to be considered and till then the bid
F should not be finalized. It has referred to the letter of the
Chairman-cum-Managing Director of the Corporation dated
20.7.2014 and opined that it appears to be a misstatement of fact.
(Para 21) (509-B-D)
1.4 On interest on management and guarantee fee, the stand
of the Corporation is that the respondent no. 1 quoted Rs.
G
123.9746 crores as Management fees and Rs. 392.0163 crores
as Guarantee fee in their Price bid. There is no dispute on the
quantum of fees. The Consultant during the evaluation have
worked out interest@ 7.2 per annum on the above fees as per
the term sheet of the Industrial and Commercial Bank of China
H Limited from the date on which they fall due since the above fees
'
TAMIL NADU GENERATION AND DISTRIBUTION 497
CORPORATION LTD. v. CSEPDI - TRISHE CONSORTIUM
form part of the debt to be repaid by the appellant; that it is clear A
from the Tender Conditions as well as the Term Sheet provided
by Industrial and Commercial Bank of China Limited and the
clarification dated 21.10.2013 (issued by Industrial and
Commercial Bank of China Limited) that appellant would be bound
to pay the interest on the whole loan amount which would include
B
the financial charges. [Para 34) [520-C-E}
1.5 It is vivid that the Consultant analysed the offers regard
being had to the tender conditions. Be it ingeminated that the
analysis and determination made by the financial consultant was
carried out before receipt of any additional document from either
side. The documents were called for by the owner from both the c
qualifying bidders in a transparent manner and the same were
considered at the _time of evaluation by the Consultant. The
respondent submitted that the evaluation is ex f acie defective
inasmuch as the ConsuUant loaded certain charges as a
consequence of which the price went gone up. The counsel for D
BHEL and counsel appearing for the Corporation submitted that
the evaluation is founded on definities leaving nothing to any kind
-of contingency. They referred to the Term Sheet and what was
put up by Industrial and Commercial Bank of China Limited. In a
complex fiscal evaluation the Court has to apply the doctrine of
restraint. Several aspects, clauses, contingencies, etc. have to E
be factored. These calculations are best left to experts and those
who have knowledge and skills in the field.· The financial
computation involved, the capacity and efficiency of the bidder
and the perception of feasibility of completion of the project have
to be left to the wisdom of the financial experts and consultants. F
The courts cannot really enter into the said realm in exercise of
power of judicial review. Suffice it to say, it is neither ex /acie
erroneous nor can be perceived as flawed for being perverse or
absurd. (Para 36} (521-F-H; 522-A-C}
1.6 The respondent, before finalization of the financial bid
submitted series of representations and seeing. the silence of G
the owner it knocked at the doors of the writ court which directed
for consideration of the representations. The High Court at that
stage should have exercised caution. If the courts would exercise
power of judicial review in such a manner it is most likely to
cause confusion and also bring jeopardy in public interest. An H
498 SUPREME COURT REPORTS [2016] 7 S.C.R.
A aggrieved party can approach the Court at the appropriate stage,
not when the bids are being considered. It is appreciable the
owner in certain kind of tenders call the bidders for negotiations
to show fairness transparently. But the instant case is not a one
· of such nature. Once the price bid was opened, a bidder could
not have submitted representations on his own and seek a
B
mandamus from the Court to take certain aspects into
consideration. This aspect is only to highlight the role of the Court
keeping in mind the established principle of restraint. [Para 37]
[522-D-F]
1.7 The Division Bench through the delineation has adopted
c the approach of an appellate forum or authority and extended the
principle of judicial review to certain areas to which it could not
have and, therefore, the judgment and order of the Division Bench
followed the path of error in continuum. [Para 38] [522-G]
Jagdish Manda/ v. State of Orissa 2006 (10) Suppl.
D SCR 606: (2007) 14 SCC 517; Star Enterprises v. City
and Industrial Development Corporation of
Maharashtra Ltd. 1990 (2) SCR 826 : (1990) 3 SCC
280 - referred to.
Case Law Reference
2006 (10) Suppl. SCR 606 referred to Para 11
E
1990 (2) SCR 826 referred to Para 11
CIVILAPPELLATE JURISDICTION: Civil Appeal Nos. 10182-
10183 of2016
.From the Judgment and Order dated 07.09.2015 of the High Court
F of Madras in WA No. 712 and 713 of2015
WITH
Civil Appeal No. 10184-10185 of2016.
Mukul Rohatgi, A.G., Parag P. Tripathi, L. Nageshwar Rao,
Subramonium Prasad, Sr. Advs., Atul Shankar Mathur, Ms. Nimita Kaul,
G Ms. Sweta Singh, (for Mis. Khaitan & Co.), Mayank Pandey, Ms. Meha
Aggarwal, B. Balaji, Advs. for the Appellants.
Kapil Sibal, Sriram Panchu, Sr. Advs. Gautam Narayan, N.L.
Rajah,ArunAnbumani, Santanam Swaminathan, Gautam Narayan, N.L.
Rajah, Arun Anbumani, Advs. for the Respondents.
H The Judgment of the Court was delivered by
TAMIL NADU GENERATION AND DISTRIBUTION 499
CORPORATION LTD. v. CSEPDJ - TRI SHE CONSORTIUM
DIPAK MISRA, J. I. Leave granted. A
2. The appellant, Tamil Nadu Generation and Distribution
Corporation Ltd (for short 'the Corporation') vide notification dated
06.05.2013 floated a tender for setting up of two units of 660 MW Ennore
SEZ Supercricitcal Thermal Power Project at Ash Dyke of NCTPS,
Chennai wherein four bidders including the respondents herein · lJ
participated. However, two bidders out of four were disqualified as they
failed to meet the Bid Qualification Requirements (BQR) as a result of
which bids of Consortium ofTrishe Energy Infrastructure Services Private
Limited (CSEPDJ) and Bharat Heavy Electrical Ltd (BHEL) were taken
up for consideration. Prior to the opening of the price bid, CSEPDJ and
BHEL submitted supplementary price bids on 05.02.2014. Price bids C
were opened on 05.02.2014 by the appellant in the presence of the
representatives of the respondents, the qualified bidders.
3. The uncurtaining of facts would depict that the !."respondent
sent series ofrepresentations dated 16.06.20 I4, I 7.06.2014, 01.07.20 I4
and 08.07.2014 to the appellant highlighting various aspects of the bid D
and the relevance of para (viii) of Clause 29.0 of the "Instructions to
Bidders" (ITB) which also deals with the rejection of bids of the tenderer
whose past performance/vendor rating is not satisfactory. Since the
appellant paid no heed to the request made by the respondent No. I, it
filed W.P. No. 1924 7 of 2014 seeking issue of a writ of mandamus to.
direct the appellant to consider the representations and comply with Tamil E
Nadu Transparency In Tenders Act, 1998 (for short, "the TTIT Act").
An undertaking was given before the learned Single Judge by the learned
Advocate General that post-bid representations submitted by the
respondent No. I will be duly considered while finalizing the tenders and
appropriate orders will be ·passed in accordance with the tender F
specifications and the TTIT Act and rules framed thereunder and in
terms of the said undertaking, learned Single Judge vide order dated
31.07.2014 directed the appellant to consider and pass orders on the
representations of the respondent no. I herein after affording them an
opportunity of personal hearing and directed that till such orders are
passed, the tender should not be finalised. G
4. Being aggrieved by the said order, the appellant filed writ appeal
W.A. No. 1065 of 2014 before the Division Bench which, by judgment
and order dated 19.08.2014, disposed of the writ appeal by modifying
the order of the learned Single Judge only to the extent that affording of
opportunity of personal hearing to the person was impermissible having H
500 SUPREME COURT REPORTS [2016] 7 S.C.R.
A not contemplated under the Rules (for short, "the rules") and further
permitted the respondent No. I to submit additional documents raising
all its objections and the appellant was directed to pass an order and
communicate the same to the respondents, CSEPDf and BHEL.
However, the Division Bench did not modify the direction of the learned
Single Judge which was to the effect that till a decision was taken on
B
representations of the I" respondent, the bid shall not be finalised.
5. After the disposal of the writ appeal, the respondent No. l sent
its representation on 25.08.2014 along with necessary documents which
was rejected by the appellant v.ide its communication dated 27.09.2014.
The legal propriety of the said rejection was cal led in question by way of
c writ petition W.P. No. 26762 of 2014 seeking quashment of the same
and further restraining the owner from taking steps to finalise the tender.
During the hearing of the writ petition, a copy ofletter dated 27.09.2014
awarding the contract to BHEL, respondent No. 2 herein, was brought
on record. It was mentioned therein with regard to price negotiation
D meetings with the respondent No. 2. The respondent No. I sent a letter
dated I. I 0.2014 to the appellant, highlighting the arbitrariness, anomalies
and inconsistencies in its reasoning and the mala-fide intent in the matter
of evaluation of the bid submitted by it. However, the appellant by letter
dated 10.10.2014, informed the I" respondent that the subject tender
had been finalised and awarded to BHEL.
\, E 6. The letter dated 27.9.2014 awarding the contract to respondent
No. 2 and letter dated I 0.10.20 I 4 were assailed by the respondent No. I
by filing W.P. No. 27529of2014 for annulments of the letters and further
for issue of directions to the Corporation to determine the award of the
tender strictly in terms of the Tender/Bid document and taking into
F account the bid of respondent No. I and that of BHEL, the respondent
No. 2 herein.
7. The learned Single Judge dismissed the writ petition primarily
based on the perusal of notes in the files containing the Consultant Report
dated 30.05.2014 and on that basis opined that the conduct of process of
evaluation of the tenders did not appear to be arbitrary, capricious or
G unfair; and that price bids of the bidders had been evaluated as per the
parameters indicated in the tender notification by an independent
consultant who was selected as per the Board Resolution that was within
the knowledge of both the bidders. The reasoning of the learned Single
Judge basically hinged on the Consultant's Report that had determined
H that the respondent No.2 herein was LI and, therefore, the decision of
TAMILNADU GENERATION AND DISTRJBlITION CORPORATION 50 l
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
the Corporation in treating BHEL as LI and awarding the contract was A
neither arbitrary nor malafide.
8. Aggrieved by the order of the learned Single Judge, the
respondent No. I preferred writ appeals before the Division Bench. The
Division Bench took note of the various pleas raised by the respondent
No. I including violation ofthe statutory provisions, arbitrariness, adoption B
of unfair and non-transparent procedure, erroneous delineation of the
consultant's report by the learned Single Judge and non-consideration of
public interest.
9. The Corporation, in its turn, contended before the Division
Bench that there was no violation of procedure and the award of the
contract was not amenable to judicial review in the obtaining factual c
matrix and any interference would only delay the execution of the work.
It was also urged that Tender Accepting Authority (TAA) had accepted
the lowest tender and negotiations were held only with lowest bidder;
that Clause 25 .4 ofthe Instruction to Bidders did not permit the bidder to
change the substance of the bids after the bids were opened; that though D
the respondent No. I had offered lower rate on interest, the original interest
rate offered was not in accordance with tender terms, for as per clause
14.0(d)(5) the rate of interest quoted should be fixed, whereas the
CSEPDI had not specified the fixed rate of interest; that there was no
perversity or arbitrariness in the decision taken as per the terms of the
tender, prevalent banking practice and the Term Sheet given by the lender; E
that the Consultant was appointed pursuant to the Board Resolution dated
28.01.2012 who participated in all pre-bid and post-bid meetings and the
minutes had been signed by all the parties and the consultant and,
therefore, CSEPDl was very much aware of appointment of the
consultant and the role played by consultant could neither be criticised F
nor ignored.
I 0. The 2"d Respondent herein contended that respondent No. I
lacked credibility to make any allegation against it; that design was the
core area of leader of the consortium and they have no experience in
India insofar as supercritical Thermal Power Projects are concerned;
and that the work was under progress and they had expended substantial G
amount.
I I. After hearing the rival. contentions, the Division Bench placed
reliance on Jagdisb Manda/ v. State of Orissa1 and observed that the
approach of the owner was unfair in the tendering process. It further
1 (2001) 14 sec s11 H
502 SUPREME COURT REPORTS [2016] 7 S.C.R.
A analysed the scheme of Section I 0 of the TTIT Act and held that the
Tender Accepting Authority (TAA) has a role to cause objective
evaluation of the tenders. Referring to Section I 0( 6) of the TTIT Act, it
held that the Corporation had not complied with the said provision and it
was a case of procedural impropriety, unfair approach and arbitrariness.
The appellate Bench referred to the authority in Star Enterprises v.
B
City and Industrial Development Corporation of Maharashtra Ltd."
and declined to accept the stand of the Corporation by opining that
reasons for rejection of I" respondent'sJepresentations could not be
treated as reasons for rejection of its bid and hence, the decision making
process was flawed and in breach of Section l 0(7) of the Act. It further
c held that in the "Tender Bulletin", absence ofreasons for acceptance of
tender, no statement of evaluation of tenders and no comparative
statement of tenders.received and, decision thereon was in clear violation
of the requirements of Section 6(1) read with Section IO of the TTIT
Act and Rule 30(3) of the TTIT Rules. On the interest component and
commitment fee, the Division Bench held that the approach was wholly
D
arbitrary and the intention was to oust the respondent No. I, for the
evaluation process adopted was meant to suit one and reject the other. It
further held that the process adopted 1\11d the decision taken by the owner
was arbitrary, unfair, irrational, biased and mala fide and did not serve
the larger public interest. In view of the said analysis, the Division Bench
E allowed the appeals and directed the Corporation to evaluate the price
bid of the respondents in the light of its findings and taking into
consideration all relevant parameters including the representations/
documents submitted by respondent No. I and to record detailed reasons
for the decision and communicate the same to the respondent No. I so
as to comply with the requirement of the provisions of the TTIT Act and
F
TTIT Rules and various decisions of this Court.
12. Being aggrieved by the aforesaid judgment, the corporation
and the successful bidder, by way of special leave, have preferred separate
appeals.
G
13. We have heard Mr. Mukul Rohatgi, learned Attorney General
and Mr. Parag P. Tripathi, learned senior counsel for the appellant-SHEL
and Mr. Subramonium Prasad, learned senior counsel for the appellant-
Corporation, and Mr. Kapil Sibal, learned senior counsel for respondent
No. I and Mr. Sriram Panchu, learned senior counsel for the respondent
No.2.
H '(1990) 3 sec 2so
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 503
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
14. It is apposite to note that in course of hearing it has been A
opined that the singular issue that is required to be addressed is "whether
the Evaluation Report dated 301h May, 2014 by the Consultant, is prima
facie erroneous, requiring interference within the parameters ofjudicial
. review". Such a singular point was required to be focused as Mr. Mukul
Rohatgi, learned Attorney General appearing for BHEL and Mr.
B
Subramonium Prasad learned senior counsel appearing for the Corporation
had submitted as the subsequent offers either by BHEL or by the I"
respondent need not be considered. At that juncture, Mr. Kapil Sibal
learned senior counsel appearing for the I" respondent, the contesting
party, had submitted that the Consultant's Report would graphically
exposit that the respondent No. I was entitled to be declared as L-1 c
even ifit is scrutinized within the limited parameters ofthe judicial review.
The Court had directed for handing over the Consultant's Report to the
learned counsel appearing forthe l" respondent. In view of the aforesaid
submission, the opinion expressed on other issues by the learned Single
Judge or by the Division Bench need not be adverted to.
D
15. On a"perusal of the facts brought on record, it is manifest that
the Corporation in its meeting held on 30.1.2014 had decided to open the
price bids on both the bidders and thereafter the supplementary price
bids were obtained from both the parties for the additional implications
items in respect of technical deviation quoted by both parties and
thereafter the price bids were opened on 05.2.2014. As the factual E
matrix would reveal, the price bids were evaluated by the Consultant.
The learned Single Judge has adverted to price evaluation report submitted
by the Consultant. Certain paragraphs from the report of the Consultant
that were reproduced by him are as follows:-
"4.0 Evaluation F
4.1 BHEL
BHEL has arranged finance from Mis .. Power Finance
Corporation oflndia.
They are arranged to finance 75% of the total cost as debt G
at an interest rate of 12.25% p.a.
AttachedAnnexures I to 5 indicate the methodology adopted
in calculating the various components required for evaluation
like !DC-Debt, !DC-Equity, IDC-UF Fess; Debt Repayment
Schedule etc.
H
504 SUPREME COURT REPORTS [2016] 7 S.C.R.
A 4.2 CSEPDI - TRISHE
CSEPDI-TRISHE has arranged finance from Mis. ICBC,
China.
They have arranged a finance 85% of the total cost as debt
at an interest rate of7.2% p.a.
Attached Annexures 6 to 12 indicate the methodology
B
adopted in calculating the various components required for
evaluation like JDC-Debt, JDC-Equity, IDC-UF Fess, Debt
Repayment Schedule etc.
5.0 Evaluated Lower Cost
BHEL CSEPDI-
c TRISHE
All figures in All figures in
Rs. (Crores) Rs. (Crores)
Capacity 1320MW 1320 MW
A Total EPC cost 7762.977 9207.264
excluding VAT
D
B EPC Debt 75% 5822.233 7826.174
c EPC Equity 25% 1940.744 1381.090
D !DC Debt 12.25% 1295.079 1228.378
E EPC Debt Including 7117.311 9054.552
!DC (B + D)
E F Upfront Fees 8.925 801.180
Including Interest
G Total Debt (E + F) 7126.237 9855.732
H Interest on Equity 14% 509.597 . 456.606
I Total Equity (C+H) 2450.341 1837.695
F J Total Project Cost 9576.578 11693.427
(G +I)
K Total Cost per MW 7.255 8.859
L PV - Debt 7553.364 8464.318
M PV - Equity 2809.403 2106.984
N Total PV 10362.767 10271.302
G
0 PV Cost per MW 7.851 7.781
p Loading for 10.287 173.229
Deficiency
Q Total (N+P) 10373.054 10444.531
R Evaluated Bid 7.858 7.913
Price per MW
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 505
LTD. v. CSEPDI - TRlSHE CONSORTIUM [DlPAK MISRA, J.]
Paragraphs 4.0 and 5.0 of the "Price Evaluation Report" submitted by A
the Consultant, which I have extracted above, show that the Consultant
took into account only the interest rate of 12.25% per annum for the
debt component arranged by BHEL from the Power Finance Corporation
of India. The Consultant did not take note of the reduced rate namely
12.15, subsequently offered by BHEL, for arriving at the conclusion that
B
the "Evaluated Bid Price" ofBHEL was the lowest."
16. There is no dispute that as per the Price Evaluation Report by
the Consultant, the EPC price of the respondent No. 1 was Rs.9207 .264
crores and respondent No.2 to whom the contract was awarded was
Rs.7762.977 crores. Thus, the difference between the two EPC price c
is Rs.1444.287 crores. The 1" respondent disputed the Price Evaluation
Report by the Consultant on the ground that it wrongly loaded the sum
towards (a) the commitment fee, (b) interest on management fee during
JDC period; and (c) interest of guarantee fee during IDC period in its
bid amount which had led to the evaluation of quoted financial charges
with interest to Rs.80 l .18 crores. D
17. As regards the commitment fee, learned counsel for the
appellant submits that the contention of the respondent No. I that since
commitment fee was the fee to be charged on the unutilised amount of
the loan meaning thereby ifthe appellant failed to draw the loan amount
as undertaken, then only the commitment fee would be charged and, E
therefore, the detennination after addition of the same was without any
rationale as the respondent No. I had quoted in the 'Calculation Sheet
for Financial Cost' in the supplementary bid commitment fee to the tune
of Rs.164.72 crores which was to be charged @ l o/o p.a. on accrued
drawals and if no commitment fee was required to be paid, the respondent F
No.I should have mentioned the same to be nil or z.ero. To show that
the commitment fee is a part of the financial charges, learned senior
counsel has drawn our attention to clause 14(d) 6 of the Instruction to
Bidders under the tender, which reads as follows:-
"6. Financing Charges : All financing charges of any G
nomenclature relating to financing of the project including
but not limited to Finders Fees, Commitment Fees,
Arrangement Fees, Management Fees, Up Front Fees,
Syndication Fees, Service Charges, Guarantee Charges,
Other Fees and Taxes, if any should be clearly outlined in
H
506 SUPREME COURT REPORTS [2016) 7 S.C.R.
A the Financing Term Sheet. No variation in Financing
Charges is permitted during the tenor of loan.
3.37 "Financing Cost" means all financing charges of any
nomenclature relating to financing of the project including
but not limited to Finders Fees, Arranger's Fees,
B Commitment Fees, Management Fees, Up Front Fees,
Syndication Fees, Service Charges, Guarantee Charges,
Other Fees and Taxes, if any."
18: At this juncture we may also refer to clause 3.37 of Section 2
that deals with the General Terms and Conditions of the Contract. It
c defines the "Financing Cost" as follows:-
"Financing Cost" means all financing charges of any
nomenclature relating to financing of the project including
but not limited to Finders Fees, Arranger's Fees,
Commitment Fees, Management Fees, Up Front Fees,
D Syndication Fees, Service Charges, Guarantee Charges,
Other Fees and Taxes, if any".
19. Clause 14 that deals with the conditions for a Binding Debt
Financing Term Sheet, which needs to be reproduced in entirety. It
reads as follows:-
E
"14.0 Conditions for a Binding Debt Financing Term
Sheet
Bidder shall enter into a Memorandum of Understanding
(MoU) with the Lender for the Debt Financing agreeing to
F provide Financing for the Project and making payments
directly to the Bidder based on bills certified by
TANGEDCO as per the terms of payment Clause.
The MoU shall be submitted by the Bidder along with their
offer for signing of the loan agreement.
G The Bidder shall be responsible for arranging the required
financing and achieving Financial Closure of the project
within 4 (Four months) from the date of Letter of Intent·
(Loi).
a. The Bidder and Lender shall furnish a joint undertaking
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 507
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
to fulfill the commitment made in the offer for Debt A
Financing arrangement from the Lender subject to due
diligence.
TANGEDCO will furnish the following documents to the
lender for processing of Debt Financing to the successful
bidder. B
I. Profile ofTANGEDCO
2. Audited Balance Sheet ofTANGEDCO for the last three
financial years
3. MOU entered between TANGEDCO & MMTC for long c
term supply of coal of this project.
4. Tariff order for sale of power.
5. Copy of DPR
b. It shall be understood that the Financing Term Sheet shall D
be based on preliminary appraisal of the project jointly by
the Bidder and the Lender satisfying themselves on the
project financial viability.
c. It shall be understood that the Award of Contract to the
Bidder is contingent upon successful financial Closure based E
on the Terms and Conditions provided in the Financing Term
Sheet and in the event onhe Financial Closure does not
materialize due to reasons attributable to the Bidder or the
Lender or in the event of withdrawal by the Lender from
the Project, the Bidder will forfeitthe security deposit. F
d. The Term Sheet should be full and complete with all
material terms of financing including but not limited to:
I. Loan Amount : At least 75% of the Total EPC Cost +
100% of Interest during construction and Financing Cost.
G
2. Currency of Loan: INR/USD/Euro or a combination
thereof.
3. Tenor of the Loan: From the date of first drawal of the
Loan upto 6 months from COD of the I" or 2nd unit
H
508 SUPREME COURT REPORTS [2016] 7 S.C.R.
A whichever is later and 15 years thereafter.
4. Rate of Interest.
5. Fixed Rate oflnterest till the entire tenor of the loan
after taking into account the hedged cost.
B 6. Financing Charges : All financing charges of any
nomenclature relating to financing of the project including
but not limited to Finders Fees, Commitment Fees,
Arrangement Fees, Management Fees, Up Front Fees,
Syndication Fees, Service Charges, Guarantee Charges,
Other Fees and Taxes, if any should be clearly outlined in
c the Financing Term Sheet. No variation in Financing Charges
is permitted during the tenor ofloan.
7. Terms and conditions for draw down schedule.
8. Moratorium for Repayment of Installment, Interest and
D Financing Charges: All cash outflow obligation of
TANGEDCO towards repayment of Installment, Interest
and Financing Charges should be in INR (fully hedged) for
the entire tenure of the loan and the repayment will
commence only after 6months from the date of COD of
later unit.
E
9. Repayment Period: 15 years post IDC and moratorium
in 60 equated quarterly installments
I 0. Project Cash Flows and Installment Repayments
statement should be submitted and will form part of the
F Financing proposal. The Bidder shall indicate Draw Down
Schedule of finance to match the supply and erection
schedule of project activities.
11. Equity requirements and related covenants.
12. Security: Against Security the following can be made
G available by TANGEDCO
a. Hypothecation of all I 00% Project Assets
b. Government Guarantee for the repayment of loan
13. Validity period of the Term Sheet will be co-terminus
with the validity of the bid."
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 509
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
20. The stand of the respondent as regards the interpretation of A
Clause 14(d) 6 is that it only outlines all fees, but it does not mean that
every such fee is to be loaded for evaluating the bid to determine L l and
no commitment fee can be loaded for such evaluation. It is also put
forth that there can be no question of loading interest on commitment
~- -
B
21. As has been stated earlier, the issue pertaining to correctness
of Consultant's report has to be adjudged and scrutinized within the scope
of limited power of judicial review in the obtaining factual score. The
Division Bench in the impugned judgment has taken exception to the
process adopted in the identification of Ll. It has referred to its order
dated 19.8.2014 wherein the l" respondent was granted the time to c
submit additional documents. The impugned order takes note of the fact
that at that point of time, the Corporation had never averred that tender
had been finalized. It has referred to the earlier order of the Division
Bench that representations were to be considered and till then the bid
should not be finalized. It has referred to the letter of the Chairman- D
cum-Managing Director of the Corporation dated 20. 7.2014 and opined
that it appears to be a misstatement of fact.
22, Be it stated that the Division Bench has posed two questions:-
"(i) Whether interest offered by appellant is vague; and
E
(ii) Whether the reduction of interest from 7.2% to 6.2%
should be accepted."
23. While dealing with the said issue, the Division Bench has
referred to the publication in the tender bulletin stating about the decision
on tender:-
F
" l. Name of the Tender: Chief Engineer/Civil/Projects &
Environment, Inviting Officer, J•d Floor, NPKRR Maal igai,
144, Anna Salai, Chennai - 600 002.
2. a) Name of the Project/Detail of Purchase & Works:
Establishment of coal based 2 x 660 MW Ennore SEZ G
Supercritical Thermal Power Project in the ash dyke of
existing NCTPS under Single EPC cum Debt Finance basis.
Vayalurvillage, Thiruvallur District, Tamil Nadu.
'·· H
510 SUPREME COURT REPORTS [2016) 7 S.C.R.
A
SI. Details Tender Value Decision on Tender
No
Mis. Bharat 7840.087 Out of four bids received
Heavy Crores & for this work and among
Electricals Lender: Powe1 the -qualified two bidders,
B
Limited, BHEL Finance negotiation was called for
House, Sirifort, Corporation & held with the lowest
New Delhi - Limited bidder viz M/s.BHEL.
110 049 Rate of After negotiation, tender
Interest: value of Rs. 7788 Crores, ·
c 12.25% Rate oflnterest at 12.15%
was accepted by the
Chief Engineer/Projects
Consortium o; 9716.5974
and order for acceptance
Central Southern Crores &
of the tender issued vide
China Electric Lender: this office issue
D 2 Power Design - Industrial & Lr.No.CE/P/SE/M/EE-
Ms. Trishe, 668, Commerce 1O/E/File. 2x660MW
Minz Road, Bank of China Ennore SEZ
Ughan, China - Rate of STPP/D.No.60/dt.27.09.2
430 071 Interest; 7.2% 014
(USD@Rs.
E 59.26 at SBI
Bill selling
rate)
Finally, M/s. BHEL/New Delhi offered bid for Rs. 7788 Crores was
accepted by thtl Chief Engineer/Projects/Chennai and order for
F acceptance of the tender was issued vide this officer Lr.No.CE/P/SE/
M/EE-10/ E/File.2x660MW Ennore SEZ STPP/D.No.60/dt. 27.09.2014."
24. Thereafter, the Division Bench has recorded as follows:-
"31.3 While it is the plea of the appellant that fixed rate of
7 .2-7 .5% per annum or LIBOR floating rate has been
G
quoted by them, it is the case of the learned Advocate
General that Clause 12.1 of the Instructions to Bidders
stated that interest is to be quoted at fixed rate and it is not
subject to change, and since the interest quoted is variable,
it is not possible to evaluate the bid.
H
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 511
LTD. v, CSEPDI - TRISHE CONSORTIUM [DIPAK MISRA, J.]
31.4 It is seen from the records, that subsequently, based A
on a query from the first respondent, the appellant had
confirmed that it would be fixed rate of interest at 7.2%.
the same was also confirmed in the Repayment Schedule
and the same rate of interest was taken into consideration
by the Consultant in his report dated 30.5.2014. He did not
B
find fault with the rate of interest. It is to be noted that the
Term Sheet was submitted during July, 2013 and tender
was evalu11ted in" the year 2014. The contention of
vagueness in rate of interest does not appeal to us. When
the Consultant's report dated 30.5.2014 is accepted by
TANGEDCO for the purpose of evaluation, it has to be c
accepted for all purposes, though we have reservation on
the Consultant's report dated 30.5.2014. There is; therefore,
no vagueness in the rate of interest quoted at 7.2%.
31.5 The second issue relates to the reduction of rate of
interest. It is not in dispute that various meetings were held D
between the appellant and the TANGEDCO. The learned
Advocate General states that the Consultant was appointed
based on the 21" Board Meeting on 28.1.2012 and the
Consultant participated in all pre-bid and post-bid meetings
and minutes were signed by all parties, including BHEL
and the appellant. He stated that the appellant was aware E
of the Consultant's appointment and his role. This only
fortifies the fact that there have been series of consultation
between both the bidders. The finding of the learned Single
Judge that the appellant acted on inside information is
demolished by the stand of the learned Advocate General F
as above. The insinuation has no basis.
31.6 Coming to the issue of reduction of rate of interest,
taking into consideration the prevailing market rate, the
appellant offered to reduce the-rate of interest from 7.2%
to 6.2% on 5.6.2014, even prior to any form of litigation. G.
When such an offer was given by the appellant the tender
was not accepted in terms of Section 10(6) of the Act. To
recapitulate, what has happened earlier is that the writ
petition in W.P. No. 19247 of2014 was filed on 17. 7.2014,
subsequent to the offer made on 5.6.2014. The first interim
H
512 SUPREME COURT REPORTS [2016] 7 S.C.R.
A order was passed on I 8. 7.20 I 4. The second interim order
was passed on 31.7.2014. The Division Bench passed an
order on I 9.8.2014. At that point of time, there was never
a statement by the TANGEDCO that LI was identified
and discussion was going on. We have also clearly stated
that the statement of the Chairman-cum-Managing Director
8
of TANGEDCO that the representations of the appellant
will be duly considered by the Board of Directors while
finalizing the tender and appropriate orders will be passed
strictly in accordance with the tender specifications and by
following the provisions ofTTIT Act and TTIT Rules.
c 31. 7 Therefore, the issue relating to reduction of rate of
interest should have been considered. This reasoning of
ours is also based on the fact that we have clearly held that
the third respondent could not be ascertained as LI on
2.6.2014 as per the statement of TANGEDCO or on
D 30.5.2014 as per the finding of the learned Single Judge.
Once there is no identification of Lt, TANGEDCO is bound
to consider the reduction in rate of interest of both the
appellant in their offer dated 5.6.2014 aiid that of the third
respondent dated 27.6.2014, reducing the rate of interest
from I 2.25% to 12. I 5%.
3 I .8 Even otherwise, by virtue of the power under Clause
25 .3 of the Instructions to bidders, which states that "The
Purchaser reserves the right to relax or waive any of the
conditions of this Specification in the best interests ofthe
TANGEDCO", the TANGEDCO could have considered
F such reduced rate of interest offered by the appellant and
the third respondent."
25. With regard to commitment fee, the analysis of the Division
Bench is worth referring to:-
G "It clearly states that Commitment Fee is only on the
cancelled portion of the loan. That apart, even as per the
Drawdown Schedule, the fee is to be paid only if the loan
amount is not drawn by the I 81h, 30th and 42"d month.
Moreover, the appellant in the letters dated
13.6.2014, 16.6.20 I 4 and 17.6.2014, clarified that
H
TAMJL NADU GENERATION AND DISTRIBUTION CORPORATION 513
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
Commitment Fee is only on the unused credit line and that A
there shall be no Commitment Fee if the loan amount is
fully utilized as per the Drawdown Schedule. All these
representations sent by the appellant were not considered
by TANGEDCO, despite there being a specific direction
by the Division Bench of this Court to consider the same.
B
It is a clear case of arbitrariness in approach and intended
to oust the appellant. This act of the TANGEDCO is nothing
but a case of malafide in evaluation process to suit one and
reject the other."
26. While dealing with the consultant's report, the Division Bench
has proceeded to state thus:- c
"33.3 Even as per the Consultant's Report the difference
between the bid of the appellant and the third respondent is
around Rs. 71 Crores. That being the case, if either the
Commitment Fee of Rs.156.184 Crores or the interest on
Management Fee and Guarantee Fee for the 36 month D
construction period is not loaded on the appellant, it will
have a bearing on deciding which one of the two is the
lowest bid. Assuming the Consultant's report is of any value,
such report without considering the relevant material is of
no use. The approach to add these figures without taking E
note of the representations and additional particulars/
documents is, therefore, arbitrary and tainted in bias. This
is in violation ofthe Division Bench judgment as well as the
orders of the learned Single Judge in the first round of
litigation."
F
27. And again:-
"The financial implication in respect of two tenderers has
been specified by the Consultant. .The issue is what factors
mean and how it impacts the bid. We find that the
Repayment Schedule submitted by the appellant with regard G
to interest on management fee ang guarantee fee during
JDC period is an accepted document by the Consultant. If
nothing more is to be paid beyond that and that is clarified
in the course of representation fo clear terms, we fail to
understand as to how this amount could be included in the
H
514 SUPREME COURT REPORTS [2016] 7 S.C.R.
A cost when there is no implication. The Consultant, as we
have held, did not have the benefit of considering the
representation and other documents on the financial
implications in this issue. His opinion is therefore not based
on relevant document/representation. This we have held is
not in conformity with the orderofthe learned Single Judge
B
in the first round oflitigation, which was confirmed by the
Division Bench. Withholding such a factor and to obtain an
evaluation from the Consultant loading the bid of the
appellant is clearly a case of bias. It is an unreasonable
approach and an unfair gesture which crumbles the spirit
c of transparent tender."
"33.6 We, therefore, have no hesitation to hold that the first
respondent had erroneously added interest on Management
Fee and Guarantee Fee when there is none and there is no
ambiguity or vagueness. Once the appellant has indicated
D _,in the representation, in clear terms, as to how it should be
treated, in the light of the order ofthe Division Bench, which
TANGEDCO accepted to consider the bid of the appellant,
the first respondent ought not to have loaded this amount
on the basts of the Consultant's Report. In all fairness, the
Tender Accepting Authority of the first respondent should
E have excluded this amount, if both the bidders are to be
treated on the touchstone of fairness and on the doctrine of
level-playing field. This becomes necessary because the
entire tender is tested on the larger public interest, that is to
say, the implementation of the project in a time bound manner
F where cost is another important factor to be considered in
the_ decision making. In a Welfare State, public authority
cannot decide arbitrarily to throw away such an offer which
they agreed to consider in the course ofjudicial proceedings,
which we have referred to above. These factors, namely,
adding interest on Management Fee and Guarantee Fee,
G have to be eschewed for the purpose of considering the bid
of the appellant, otherwise, it will suffer from the vice of
_ mu:~ason~bl~ness and irrationality."
28. Eventually, it was directed as follows:-
H "The TANGEDCO is directed to evaluate the appellant's
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 5I5
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
price bid along with the bid of the third respondent, in the A
light of our findings as .above and also taking into
consideration in all required parameters and the clarifications
submitted by the appellant in its various representations, as
directed by the Single Judge in the order dated 31.7.2014
and that of the Division Bench in its order dated 19.8.2014,
B
afresh, at the earliest."
29. Before this Court, the consultant's report is criticized by the
I" respondent stating thus:-
"2.3 The Consultant has made the following errors in the
calculation of the said 'Upfront Fees Including Interest' in c
respect of CSEPDI's bid:
Error 1 : Included Commitment Fees
Error 2: Calculated and loaded interest on (a.) Guarantee
Fee, (b.) Management Fee and (c.) Commitment Fee during
the constructiori period of 36 months, i.e., IDC (Interest D
During Construction) ---
2.4 In 5.0 Item F - 'Upfront Fees Including Interest', the
Consultant has loaded BHEL with Rs.8.925 Crores and
CSEPDI with Rs. 801.l80 Crores. The break-up of this
Rs. 801.180 Crores in the Consultant's Report is as follows: E
a. Guarantee Fee ·· Rs. 371.743 Crores
b. Management Fee· Rs. 117.393 Crores
c. Commitment Fee Rs. 156.184 Crores
d. Interest for 36 months F
!
... ·1
on a,b,c (Rs. 127.613 Crores)
e. Interest from J7•h to 42nd month: Rs. I 5 5 . 8 6 0
Crores on a,b, & c (Rs. 28.247 Crores)
Total Rs. 801.180 Crores G
-2.4.1 There is no issue on entries a. and b. above
2.4.2 The issue is with regard to entries c. and d. above.
2.4.3. As regards c., no Commitment Fee can be loaded,
for the reasons explained below. H
516 SUPREME COURT REPORTS (2016] 7 S.C.R.
A 2.4.4 As regards d., no interest can be loaded for the
construction period of 36 months on Guarantee Fee and
Management Fee, for the reasons explained below. The
question of interest on Commitment Fee does not arise at
all because no Commitment Fee can be loaded in the first
place for evaluation of CSEPDI's bid.
B
2.4.5 e. above will stand reduced as it depends on c. and d.
2.5 If the Consultant had correctly evaluated CSEPDI's
price bid by not including Commitment Fee and Interest on
Guarantee Fee. Management Fee and Commitment Fee
c for the construction period of 36 months, then CSEPDI
would be LI by Rs. 171.600 Crores. NeitherTANGEDCO
nor BHEL have disputed this fact.
x x x x x x
2. 7 The Consultant has confused Commitment Fee with an
D Upfront Fee. Commitment Fee, as stated above, is a
contingency fee payable ifthe scheduled drawal does not
take place. An Upfront Fee is levied by the lender as a
definite fee without any contingency. This is made clear
by PFC (BHEL's lender) letter dated 30-04-2015 showing
E Commitment Fee and Upfront Fee as distinct alternatives.
The Consultant has loaded BHEL with Upfront Fee. The
Consultant has erroneously treated Commitment Fee as an
Upfront Fee for CSEPDI and has in fact applied the label
Upfront Fee in Item F".
F 30. With regard to the commitment fee, various financial nuances
have been stated. We think it apt to reproduce some ofthem:-
"2.8.3 When the earmarked funds are drawn, the interest
agreed is payable. When the earmarked funds are not
drawn, the interest is not payable but instead the
Commitment Fee has to be paid on the amount not drawn.
G
· 2.8.4 CSEPDI's Term Sheet clearly mentions that the
Commitment Fee is payable on the cancelled portion of the
loan,
2.8.5 The term 'Accrued Drawal' refers to the amount
'H accured and available for drawal, but not drawn.
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 517
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
2.8.6 Commitment Fee is therefore only a contingent fee A
· leviable ifthe funds are not drawn as per the Drawdown
Schedule. It is more in the nature of a penalty in the event
of a default by the borrower TANGEDCO and is payable
by TANGEDCO. This cannot be added to the project cost
for evaluation of the price bid.
B
x x x x x x
2.8.8 The Repayment Schedule sets out the entire amount
to be paid by TANGEDCO in the form of 48 Equated
Quarterly Installments (EQI) starting from the 43'd months
of the date of financial closure for 12 years. If there is one c
document to be termed as most important to evaluate the
Price Bid, it is this Repayment Schedule. The Repayment
Schedule is part of the Price Bid and is absolutely crucial
as it caps the amount TANGEDCO has to pay. Not a
single rupee needs to be paid over and above the amounts
mentioned in the Repayment Schedule. D
2.8.9 The EQI in the Repayment Schedule is based on the
figure of Rs. 15,038.2914 Crores, which. comprises of
interest Rs. 5,025.3628 Crores on the Net Loan amount of
Rs. I 0,012.9286 Crores. The components of this Net Loan
amount are: E
a. Loan amount
(85% of Total EPC
Cost of9709.3822 Crores) Rs. 8252.9748/-
b. Interest at 7.2% p.a. on the
above loan amount during F
the Construction Period of36 Rs. 896.2032/-
months
c. Guarantee Fee Rs. 392.0163/-
d. Management Fee Rs. 123.7946/-
Moratorium Period interest
for 37'h to 42°d month G
(interest at 7.2% p.a. for
6 months on the total of
a,b,c and d. above) Rs. 347.9396/-
Total Rs.10,012.9286/-*
H
518 SUPREME COURT REPORTS [2016) 7 S.C.R.
A *The Price Bid submitted by CSEPDI was Rs. 9709.3822
Crores and the above calculations were on that basis.
However the admitted position is that of this sum, Rs.
509.339 Crores was disallowed by TANGEDCO and the
Price Bid was arrived at Rs.9207.264 Crores. The
Consultant has also evaluated CSEPDl's bid at Rs. 9207.264
B
Crores".
31. With regard to no interest on guarantee fee and management
fee during the construction period of 36 months and no interest on
Commitment fee, the stand of the l" respondent has been put forth in
various compartments. We think it apt to reproduce the relevant grounds:-
c
"2.9.1 The Consultant ought not to have loaded interest on·
Guarantee Fee and Management Fee during the construction
period of36 months, for the evaluation ofCSEPDI's Price
Bid.
D 2.9.2 The very same Repayment Schedule calculalion set
out above shows that no interest is being charged on
Guarantee Fee and Management Fee during the construction
period of36 months and does not form part of the amount
which TANGEDCO has to repay. Not a single rupee needs
to be paid over and above the amounts mentioned in the
.E
Repayment Schedule.
2.9 .3 The only interest payable during the construction period
of36 months is interest calculated at 7.2% p.a. on the basic
loan amount (85% of the EPC cost) and not on any other
amount like Guarantee Fee and Management Fee. This is
F made clear in the specific calculation sheet for Interest
During Construction submitted by CSEPDI in its Price Bid.
2.9.4 The Term Sheet submitted by CSEPDI outlines the
fees required to be paid by TANGEDCO and the
circumstances in which they are payable. In the very nature
G of this contract, the items chargeable have to be mentioned,
not the items not chargeable. The contract requires to be
evaluated based on what the bidder is charging
TANGEDCO.
2.9.5 In CSEPDI's Term Sheet, mention is made of
H Management Fee and SINOSURE Re-insurance
TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION 519
LTD. v. CSEPDI- TRISHE CONSORTIUM [DIPAK MISRA, J.]
(Guara11tee Fee). No mention is made of interest on A
Management Fee and Guarantee Fee for the construction
period of36months. ·
2.9.6 As far as interest on Commitment Fee is concerned,
the same does not arise as Commitment Fee itself cannot
be loaded for evaluating CSEPDl's bid." - B
J2. The 1" respondent has also put forth that the Consultant was
not right in loading on CS.EPDI bid the values for Commitment Fee and.
Interest thereon and Interest on Guarantee Fee and Management Fee
during the construction period of36 month~, because that Clause 14.d.6
only states that details ofthe Financing Charges should be clearly outlined C
in the Financing Term Sheet and does.not state that it should be include.d
in the pdce evaluation; that the reference to Commitment Fee in the
Term Sheet clearly indicates that it is only on the cancelled portion of the
loan; that the fee is to be paid only if the loan amount is not drawn by the
I 8'h, 30'h and 42"d months in accordance with the Drawdown Schedule;
that Clause I 2. i and Clause 32. I.I makes no mention of hiterest on · D
Financing Charges (i.e., on Management Fee and Guarantee Fee) during
the IDC period; that the words 'Interest and Financing Charges' cannot
mean interest on financing charges; that there is absolutely no variance
between the Term Sheet and Repayment Schedule submitted by·
•. CSEPDl; that the Term Sheet and the entire Financial Prop<?sill/Price E
Bid, incl.uding the Repayment Schedule, are to be read together;·thatthe''
CSEPDI's Term Sheet only mentions that a Management Fee Is to .be
paid but'does not mention any interest .on Management Fee'for the 36
month construction period (lDC period) and that the Consultan~ ought.
notto have loaded the disputed amounts for evaluating the price bid of
CSEPDI. It is also the stand that on a perusal ofthe Comparison Sheet F
filed would indicate that CSEPDI is LI by Rs.17L600 crores if the ·
evalul!-tion is done correctly. That apait, the I" respondent has raised
other grounds which we need not refer to in detai I.·
33. The Corporati~n in supe.~rt ofthe Gons~ltant's Report has
stated that the stand of the l" respondent thatNet.LoanAmQunt in the G
repayment schedule provided by respond~nt No. I gives no break up of
how the said figure has been reached; that one cannot find out from a
bare perusal of the said Repayment Schedule as to whether the
respondent No. I has factored the component ofCommfrmentFee in the
Net Loan A1~ount; that the resppndent having not been declar~d as Ll . H
520 SUPREME COURT REPORTS [2016] 7 S.C.R. ·
·A bidder as a post facto contention, now say that Commitment Fee shall
not be taken for evaluation in spite of the fact that they themselves have
. quoted Commitment Fees for Rs.164.702 crores with split up details in
the price bid and the above post facto contention is against all tenets of
fairness and justice; that had the respondent No.1 become L1, they would
have insisted that Commitment Fee being a financial charge forms part
B
of the loan and therefore is payable by the borrower i.e., the Corporation
as per their price bids submitted by respondent No. I; that since the
respondent No. I had not been evaluated as LI, a contention is advanced
that Commitment Fee should not be taken for evaluation citing universal
definition.
C 34 .. On interest on management and guarantee fee, the stand of_
the Corporation is that the CSEPDI-TRISHE CONSROTIUM have
quoted Rs_ J23 .9746 crores asManagemenffees and Rs. 392.0163 crori:s
as.Guarantee fee in their Price bid. There is no dispute on the quantum
of fees. The Consultant during the evaluation have worked out interest
D @ 7.2 per annum on the above. fees as per the term sheet of the Industrial
and Commercial Bank of China Limited from the date on which tliey fall
due. since· the above fees form part of the debt to be repaid by the
appellant; that it is clear from the Tender Conditions as well as the Term
Sheet provided by Industrial and Commercial Bank of China l,.imited
and the clarification dated 21.10.2013 (issued by Industrial and
E Commercial Bank of China Limited) that appellant herein would be bound
to pay the interest on the whole loan amount which will include the
finanqial charges. ··
35. The Corporation has quoted the relevant tender conditions
from the Term Sheet submitted by Industrial and Commercial Bank of
F . China Limited which are reproduced below:-
• "Clause 14(d)I of the Instruction to Bidders under the
Tender defines the "Loan Amount" to include at least 75%
ofthe totalEPC cost+ 100% ofinterest during construction ·
and Financing Cost. As per clause 14(d) 6_of the Instruction
G to Bidders under the Tender management fee and guarantee
· ftie is part oft~e financial charges/financial
' '
cost.
. '
• Under thti term relating to "Interest rate" in term sheet
submitted by Industrial and Commercia! BankofChina it is
clearly provided that the Borrower will pay interest on the
H full loan amount at a fixed rate per annum.
, .
TAMILNADU GENERATION AND DISTRIBUTION CORPORATION 52 l
LTD. v. CSEPDI - TRlSHE CONSORTIUM [DIPAK MISRA, J.]
• Under the terms defined as "management fee". in the A
term sheet submitted .by Industrial and Commercial Bank·
of ChinaLimited .it is specified that Management fee of
1.5% tlaton the Loan Amount will be payable to the lender
within a period of60 days from the date offinancial closure.
Six months is the time given for financial closure and so 8 B
months in case of management fee in view of outer limit of
60 days.
• · Similarly;· under the terms relating to "Conditions
Ptecedent'', tlie-condition(d) the term sheet specifies that
petitioners will •be charged .guarantee Jee (termed as
Insura11ce··Policyofo4he·term,.sheet) ·at.the rate of·5% on
c
95%oftheJoan amountand.the.samewill be payable from
the ·end ofthe 6'h month. · .
• .According to the term sheet the amounts get debited
to the Petitioners account at the end of the s•1t month and D·
61h month respectively.
• Allfin.ancial .costsform part ofthe debt taken fro1n the
lndustrial"and Commercial Bank ofChina Limited .. As per
theclarification dated2l.10.2013 issued by Industrial and
Commercial BankoofChina Limited which is the Lender E
institutionforRespondent no. I all costs and fee charged by
ICBGwill fQrrn·partofthe debt financing".
"
36; From the aforesaid, it is vivid that the Consultant has analysed
the offers regard being had to the tender conditions, Be it ingeminated .
that the analysis and determination made by the financial consultant has
F
been carried out before receipt of any additional document from either
side. The documents were called· for by the owner from both the
qualifying bidders in a transparentmanner and the same, have been
considered at the time of evaluation byth.e Consultant Submission of
Mr, Sibatis thatthe evaluation is exjacie defective foasmuch as the
Consultant has loaded ce1tain charges as a consequence of which the G
price has gone up, Mr; Rohatgi, learned Attorney(foneral appearing for
BHELand Mr;·l>tasad;Jearned senior .counsel appearing for the
Corporation would submit thatthe evaluation·is founded on definities
leaving nothing to any kind of contingency. They have referred to the
Term ~heeNmd what is put up by Industrial and Commercial Bank of H.
_,
522 SUPREME COURT REPORTS [2016) 7 S.C.R.
A · China Limited. At this juncture we are obliged to say that in a complex
fiscal evaluation the Court has to apply the doctrine of restraint. Several
aspects, clauses, contingencies, etc. have to be factored. These
· calculations are best leftto experts and those who have knowledge and
skills in the field, The financial computation involved, the capacity and
B efficiency ofthe bidder and the perception of feasibility of completion of
· the project have to be left to the wisdom of the financial experts and
consultants. The courts cannot really enter into the said realm in exercise
of p,ower of judicial review. We cannot sit in appeal over the financial
consultant's assessment. Suffice it to say, it is neither exfacie erroneous
nor can we perceive as flawed for being perverse or absurd.
c 37. Before parting with the case we _are constrained to add
something. We do so with immense pain. The respondent, before '
finalization of the financial bid submitted series ofrepresentation~ and
seeing the silence of the owner it knocked at the doors of the writ court
which directed for consideration of the representations. We are disposed
D to think that the High Court at that stage should have exercised caution.
If the courts would exercise power of judicial review in.such a manner
it is most likely to cause confusion and also bring jeoplirdy i11 public
· interest. An aggrieved party can approach the Court at the appropriate
stage, not when the bids are beiiig considered. We do not intend to specify.
It is appreciable the owner in certain kind of tenders call the bidders for
E negotiations to show fairness transparently. But the present case is not a
one of such nature. Once the price bid was opened, a bidder could not
have submitted representations on his own il:nd seek a mandamus from
the Court to take certain aspects into consideration. We have stressed
. this aspect only to highlightthe role of the Court keeping in mind the
F · established principle of restraint.
38. In view of our preced.ing analysis we are of the considered
opinion that the Division Bench through the delineation hasndopted the
approach of an appellate forum or authority and extende~ the principle
ofjudicial review to certain areas to which it could not have and, therefore,
G thej\ldgment and order of the Division Bench followed the path of error
in continuum. Consequently, the inevitable conclusion is, unsettlement of
. the impugned order and we so direct. In the ultimate eventual the appeals· ·
'stand allowed. There shall be no order as to costs.
NidhiJain Appeals allowed .
.'~
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.