Created byFuzzy Cloud

Supreme Court of India

SYED ISRAR MASOOD, FOREST CONTRACTOR. RET GHAT, BHOPALversusSTATE OF MADHYA PRADESH

Citation
1981 INSC 177
Decided
1 October 1981
Disposal
Appeal(s) allowed

Holding

A substantial variance between the advertised and actual forest produce allows the contractor to repudiate the contract and recover the first instalment, despite the sale notice condition limiting claims for incorrect quantities.

Summary

Syed Israr Masood, a forest contractor, won an auction for two forest coupes in August 1960, paying an earnest money and the first instalment. Upon inspecting the coupes he discovered that the quantity and quality of timber were far less than advertised, and a substantial portion of the marked trees had been later declared "reserved", prohibiting their felling. Masood refused to sign the boundary certificate and sought a refund of the first instalment and an injunction against further demands. The trial court granted the refund; the High Court set it aside, holding that Masood had not proved the shortfall. The Supreme Court held that, despite Condition No. 3 in the sale notice, a substantial variance between the advertised and actual timber defeats the contract’s foundation, allowing repudiation and a refund of the instalment. The appeal was allowed, restoring the trial court decree with the refund amount corrected to Rs 17,250.

Issues considered

  • Whether a contractor can repudiate a forest auction contract and claim a refund of the earnest money when the actual timber available is substantially less than represented at the auction, notwithstanding a contractual condition limiting claims for incorrect quantities.
  • Whether the State is liable for damages or only for refund of the first instalment under the contract.
  • Whether the reservation of part of the forest area after the auction constitutes a breach that justifies termination of the contract.
  • Whether the suppression of the forest department's inspection reports affects the contractor's right to repudiation.

Legislation cited

Subjects

contract repudiationforest auctionmisrepresentationcondition precedentrefund of earnest moneyreservation of forest areasuppression of evidencepublic auctioncivil procedurecontract breach

Judgment

A     s94
             SYED ISRAR MASOOD, FOREST CONTRACTOR.
                         RET GHAT, BHOPAL
                                              v.
B                    STATE OF MADHYA PRADESH

                                     October 1, 1981

                    [A;D. KOSHAL, V. BALAKRISHNA ERADI AND
                              R,B. MISRA, JJ.J                                              •
c
           Rlghl to repudiate a contract and for refund of earnest nwney in deposit
     arise when variation in quantify nnd quality is found on actual count betweeii what
     was held out at the auction as being availab!e-Nonwproduction of the verificatiolJ
     ofrtport is hlt by th~ doctrine of 'suppressio veri'-Condition number 3 of the
     Sale Notice, value· of.
D
           Pursuant to the notice dated July 22, 1960, notifying that forest contracts
     will be settled by public auction, the appel!ant~plaintiff attended the said auction
     on August 17, 1960 after having deposi1ed the requisite earnest money of
     Rs. 1,000 and furnished the solvency certificate for the sum of Rs. 1.5 lakh. At
    the tirrie of auction, the details of the forest produce available in each coupe was
    announced. In the said announcement the total number of trees of each species
    available in each coupe as also their girth etc, were furnished and the bids were
    invited on the basis of the said information given to the intended bidders. The
    appellant was the highest bidder in respect of two coupes, namely, Searmau
    Coupe Cf2 "A" and "B" with a bid of Rs. 69,000 for these two coupes. Pursuant
                                                                                                -r
    thereto, the appellant deposited on August 22, 1960, Rs. 16,250 being the balance
    of the first instalment of Rs. 17,250, after adjustment of the earnest money in
    deposit. On executing the requisite security bonds, the appellant was directed,
F   on October 27, 1960, to proceed to the site and sign the "coupe boundary cer1ifi-
    cate'0, before the Range Officer for getting possession of the two coupes.

           When the appellant visited the two coupes and conducted a detailed ins-
    pection of the trees available for extraction, he found that the coupes did not con-
     tain the forest produce as announced at the tin1e of the auction. Inasmuch as
    the number of trees available for cuttiog in the two coupes were found to be
    very much short of the quantity and quality of the forest produce given out at the
G   time of auction as being available in the two coupes, the appellant refused to
    sign the boundary certificate. The forest authorities, on January 19, 1961 served
    a notice calling upon the appetlant to deposit the second and third instalments of
    the bid amount and threatening that in the event of default, the amount would
    be recovered as arrears of land revenue. Subsequently a distraint notice was also
    issuen under section 146 of the Madhya Pradesh Land Revenue Code by the
H   Tehsildar. On April 17, 1961, the forest authorities issued a notice calling upon
    the appellant to show cause why the contract be not terminated and the two
                                        S,i; cMASOOh v. M.P. STATE                           895

              coupes re-auctioned at his risk. Thereupon the appellant, after serving on the          A
              respondent a due notice under section 80 Civil Procedure Code, filed a suit for
              recovery of the amount deposited by way of first instalment plus damages
              arising out of the breach of contract. The appellant also prayed for a permanent
              injunction restraining the State for taking coercive step to recover further instal·
              ments. The Trial Court decreed the suit as prayed for. In appeal by the rcspon·
              dent. State the High Court set aside the decree on the ground that the appellant
              did not prove that the number of trees which were actually available for extrac-        8
              tion in the two coupes, according to proper marking was less than the number
              of trees which was covered by 'the assurance given to the contractor at the time
              of the auction.

          •         Allowing the appeal by certificate under Article 133 (I) (aj of the Constitu-
              tion, the Court,

                    HELD: I. While condition number 3 in the Sale Notice (Ex. D/D) will
                                                                                                      c
              operate to prevent the Contractor from claiming any damages or compensation
              from the State Government on the ground that the details of the quantity of the
              forest produce were ·subsequently found to be-incorrect, it will not predude him
              from repudiating [be contract on its being found that there was substantial vari-
              ance between the particulars furnished at the time of the auction regarding the
              quantity and quality of timber that will be available for extraction·in the concer-     D
              ned coupes and the quantity etc. of tree growth actually found to be available on
              the site. [902 D-F]

                     2 : 1. It has been clCarly established by the evidence in this case that a
               very substantial quantity of timber standing on the bank of NaUa had been
               marked for extraction and numbered and the auction sale had beeil held on the
               basis that the highest bidder would be entitled to fell and remove all those- trees.   E
               But by the time the coupes were allowed to be inspected by the auction
               purchaser, that area was declared to be "reserved", with the result that
               there was a complete prohibition against the feUing of any timber therefrom.
               This has substantially altered the very foundation of the contract an'd hence it
               was perfectly open to the Plaintiff to repudiate the contract and claim a refund
               of the amount deposited by him as a part payment of the purchase price. [902 F-H]

                    2: 2. The subject-matter of the auction sale was the totality of the trees
                                                                                                          F
               which were marked for cutting in the two coupes. Since a substantial number of
               the 1narked trees was contained in the area which was subsequently declared as
               "reserved", it is inevitable that there was a corresponding diminution in the total
               quantity of timber which was announced as available for cutting at· the tini.e of
               the auction sale. [903 A-CJ


                      2 : 3. The appellant has fully proved his claim for the refund of the
                                                                                                      G
                amount paid by him by way of tbe first instalment of the sale price by examin-
                ing himself as P.W. 2 and also through P.Ws. 3 to 6, all of whom had inspected
                the coupes subsequent to the auction sale. The oral testimony given by them is
                further corroborated by the statements contained in Ex. P-1, P-3, P-5, P~6 and
.,,   .         P-8. Further the sworn evidence of respondent's own witnesses (D.W. 2 and
                D.W. 3) and the suppression of their two inspection reports from the court con-
                                                                                                      H
                firmed the right to repudiate the contract and ask for a refund. [899 H, 900 A-E]
         896                       SUPREME COURT REPORTS                  [1982) i s.c.il.

    A           2: 4. That the criticism made by the High Court that the argument by the
         appe11a~t-Plaintiff waS the result of an after-thought is wholly unjustified and
         erroJ,leOus is clear from a mere reference to Ex. P-1. The correct factual position
         is that the plaintiff had categorically complained to the department that a sub-
         stantial 'area containing the forest produce. which had all b~en originally marked
         for ~al.e, ·had been subsequently "reserved" with the result that the quantity of
         timber available for extraction had become substantiallyreduced.(9010 E,H,902A]

                 CIVIL APPELLATE JuRISDICTION : Civil Appeal No. 2060 of
         1970.

             ' From the judgment and order dated the 26th August, 1969 of                      •
         the Madhya Pradesh High Court in First Appeal No. 100 of 1965
c                Harbans Singh. for the Appellant.

              Gopal Subramaniam, D.P. Mohanty and R.A. Shroff for the
         Respondent.

                 The Judgment of the Court was delivered by
D
                BALAKRISHNA ERADI, J. This appeal hy certificate granted
         by the High Court of Madhya Pradesh under Article 133 (I) (a)
         arises out of a suit-Regular Civil Suit No. 7-A of 1963-on the file
        of the First Additional District Judge, Bhopal instituted by the
        appellant herein against the State of Madhya Pradesh, for recovery
E       of a sum of Rs. 29,500 from the defendant by way of refund of the
        first instalment of the sale price deposited by the plaintiff with the
        Forest Department of the defendant-State pursuant to an auction of
        two forest coupes held on August 17, 1960, together with damages
        alleged to have been sustained by the plaintiff on account of alleged
F
        breach of contract by the defendant. The plaint contained a further                                  ..
        prayer that the defendant should he restrained by a permanent
        injunction from taking any steps to recover from the plaintiff the
        second and third instalments of the sale price for which the two
        coupes had been knocked down in favour of the plaintiff at the                                 j'
        auction sale.
G             The tJ ial court held that the plaintiff is entitled to recover from
        the defendant Rs. 17, 500 by way of refund of the first instalment of
        the sale price of the two coupes, but rejected the plaintiff's claim for
        recovery of damages. Accordingly, a decree was passed in the
        plaintiff's favour for recovery of Rs. 17,500 with proportionate costs.
H       The plaintiff's prayer for the relief of permanent injunction was also
                                                                                                   ~   ...
        granted by the trial court.
                  S.I. MASOOD v. M.P. STATE (Balakrishna Eradi, J.)         891

             The State (defendant) carried the matter in appeal before the         A
       High Court of Madhya Pradesh. The High Court took the view
       that the plaintiff's claim for refund of the first instalment of the sale
       price was unsustainable inasmuch as he had not proved that the
      number of trees which were actually available for extraction in the
      two coupes, according to the proper markings, was less than the
       number of trees which was covered by the assurance given to the             B
       contractor at the time of the auction. As regards the relief of
       permanent injunction, the High Court.held that from the notice (Exh.
       P-7) issued by the concerned Divisional Forest Officer to the plaintiff
       on April 17, 1961, it was seen that the Government had indicated to
      the plaintiff its intention to terminate the contract before the second
       instalment had become due and hence the only right which the                c
      Government thereafter had was to realise from the plaintiff the
      deficiency, if any, occasioned by a resale of the two coupes. In this
      view, the High Court held that the Government had no longer the
      right to claim from the plaintiff the balance of the sale consideration
      represented by the second and third instalments and that the decree
      for permanent injunction granted by the trial court did not, there-          D
      fore, call for any interference. Accordingly, the appeal filed by the
      defendant was allowed in part by the High Court and the decree
      granted to the plaintiff by the trial court for recovery of Rs. 17,500
      was set aside. Hence, this appeal by the plaintiff.

                                                                                   E
             The facts of the case on which there is no dispute are as
       follows. On July 22, 1960, the Forest Department of the State
       Government of Madhya Pradesh publist ed in the State Gazette a
       notice notifying for general information that forest contracts of East
       Bhopal, Forest Division will be settled by public auction to be held
       by the Divisional Forest Officer at Sader Manjil, Bhopal on August          F
       17, 1960. The plaintiff attended the said auction after having
       deposited the requisite earnest money. At the time o the auction,
      the respective Range Officers announced the details of the quantities
      of the forest produce available in each coupe. In the said announce-
      ment, the total number of trees of each species available in each
      coupe as also their girth etc., were announced by the concerned
                                                                                   G
      Range Officers and the bids were invited on the basis of the said
      information given out to the intended bidders. The plaintiff was the
      highest bidder in respect of two coupes, namely, Searmau Coupe C/2
      "A" and "B". The plaintiff's bid of Rs. 69,000 for those two

"'.   coupes was accepted by the Auctioning Officer and pursuant thereto
      the plaintiff deposited on August 22, 1960 Rs. 16, 250 being th~
                                                                                   H
      balance of the first instalment of Rs. 17,250 after adjustment of the
     898                 SUPREME COURT REPORTS                 {l 982] l s.c.R.

     earnest money already deposited. The plaintiff also produced a
    solvency certificate and executed the requisite Security Bonds. On
    October 27, 1960, the plaintiff was informed by the concerned
    Divisional Forest Officer that the security bonds furnished by the
    plaintiff were accepted and that the contract in respect of the two
    coupes was sanctioned in his favour by the Chief Conservative
B
    Officer of Forests. By the said communication, the plaintiff was
    directed to proceed to the site and sign the 'coupe boundary certi-
    ficate' before the Range Officer for getting possession of the two
    coupes.
                                                                                  •
c           The plaintiff's case is that when, in pursuance of the aforesaid
     intimation, he visited the two coupes and conducted a detailed
     inspection of the trees available for extraction, he found that the
     coupes did not contain the forest produce as announced at time of
     auction, that a very large number of big trees which had been marked
     for felling an.d given serial numbers did not bear hammer marks
D    either at the breast height or at the bottom, with the result that the
     contractor was debarred under the rules from felling those trees, that
     similarly a large number of trees which were hammer marked had
     not, however, been given serial numbers and that a large number of
     trees situated along the bank of a Nala in Coupe No. 2 "B" which
     had been marked for felling and had been serially numbered were
E   found to have been subsequently "reserved" with the result that it was
    no longer open to the contractor to cut any of those trees. The
    plaintiff states that the aforesaid vital discrepancies and irregularities
    were pointed out by him to the Range Officer and inasmuch as the
    number of trees available for cutting in the two coupes was found
    to be very much short of the quantity and quality of the forest
F   produce given out at the time of auction as being available in the
    two coupes, he. refused to sign the boundary certificate. Thereafter,
    correspondence concerning the matter passed between the plaintiff
    and the Department, but notwithstanding joint inspections of the site
    and <leliberations the parties could not reach any agreement. The
    plaintiff took the stand that unless the Department was ready and
G   willing to put him in possession of the forest produce conforming to
    the quantity and quality of timber announced at the time of the
    auction, he was entitled to repudiate the contract and claim a refund
    of the amount remitted by him by way of first instalment of the sale
    price. The Forest Department issued a notice to the. plaintiff on
H   April 17, 1961, calling upon him to show cause why the contract
    should not be terminated and the two coupes reauctioned at the
               S.I. MASOOD v. M.P. STATE (Balakrishna Eradi, J.)        899

     plaintiff's risk. In the meantime, on January, 19, 1961, the plaintiff     A
     had been served with a notice requiring him to deposit the second
     instalment of Rs. 17,250 and threatening that in the event of failure
     to comply with the said demand, the amount will be recovered as
     arrears of land revenue. Subsequently, the Forest authorities of the
     State initiated action for recovering from the plaintiff the sum of
     Rs. 34,500 purporting to be the second and third instalments of the        B
     sale price, and a notice of demand under Section 146 of the Madhya
     Pradesh Land Revenue Code was issued to the plaintiff by the
     Tehsildar, Bhopal. Thereupon, the plaintiff instituted the present
     suit praying for the relief aforementioned, after serving on the
      defendant a due notice under Section 80, Code of Civil Procedure.
                                                                                G
           Admittedly, the auction sale was of the right to cut the trees
     which had been marked and numbered in the entire area covered by
     the two coupes in question. Details regarding the quantity and
     quality of timber available for cutting in the respective coupes were
     announced by the concerned Range Officers at the time of auction
     and it was on the basis of the said information that the participants      D
     in the auction were invited to bid. The tnal Court as well as the
     High Court have concurrently found that an assurance bad been
     given by the Department at the time of the auction that the two
     coupes contained the specified quantity of timber of different varieties
     and girth and that the details then given were as set out in the tabular
     statement appended to paragraph 3 of the written statement of the
     defendant. The plaintiff (examined as P.W. 2) and P.Ws. 3 to 6 all
     of whom had inspected the coupes subsequent to the auction sale
     have sworn that the quantity of the timber that was actually available
     for cutting in the two coupes was considerably less than the quantity
     announced at the time of the auction. The oral testimony given by
     them is corroborated by the statements contained in Exhibits P· l,         F
     P-3. P-5, P-6 and P-8, which are copies of the various representations
     made by the plaintiff to the Offices of the Forest Department after
      he found out on inspection of the coupes that there was vast diver-
     gence between what was announced at the time of the auction as the
     quantity of the timber available for cutting from the two coupes in
      question and the quantity that was actually found to be available.        G
     Even though the then Sub-Divisional Forest Officer, who was
     examined as D.W. 2, has stated in the evidence that after receipt of
     the plaintiff's complaint, he inspected the coupes and submitted a
     detailed inspection report to the Divisional Forest Officer the
••    defendant did not pr\l\IU~ tll~ s;iid report in Court, lt ha~' iilso      H
     90()               SUPREME COURT REPORTS                [J 982] I S.C.R.

A    come out in the evidence of D. W. 3, who was the Forest Guard in
     the area concerned at the relevant time, that he had submi1:ted to the
     Range Officer a report containing details of tbe timber available for
     cut1ing in the two coupes. The aforementioned two reports would
     have been of valuable assistance in determining the extent of
     shortfall, if any, in the quantity of timber actually available for
B    cutting in the coupes when compared with the particulars given
     out al the auction. The non-production of the two reports by the
     defendant, who alone was in possession of the documentary evidence
     capable of throwing light on the subject-matter of this crucial issue,



                                                                                -
     assumes significance in view of :he admission made by D.W. 3 that
     during his inspection of the coupes pursuant to the complaint
c    received from the plaintiff he had found that there were some trees
     which had been numbered for cutting but had not been hammer
     marked, that there were some other trees which contained hammer
     marks only at one place instead of at the base as well as at breast
     height, as required under the rules, and that there were still some
    other trees which had been marked by hammer but had not been
D   assigned any number. The inspection report prepared by this
    witness which has beeu suppressed is a very material docu·.11ent since
    the witness has sworn that he had actually counted and noted the
    precise number of trees in respect of which such irregularities were
    found to have been committed. Another important admis:;ion made
    by this witness is that there was some truth in the complaint of the
E   plaintiff with respect to the 'reservation' of the Nala.

           The evidence clearly shows that there was a large number of
     trees of different varieties situated on the bank of a Nalta in Coupe
     No. 2 "B" and they had been hammer marked and serially numbered
F    for cutting and removal. At the time of the auction sale, the Depart-
     ment had treated these trees as being available for extraction by the
     contractor and it was on that basis that the particulars regarding the
    total quantity of timber belonging to different species available for
    cutting in the two conpes were announced to the bidders. However,
    subsequently, the area comprising the bank of the said :llalla was
G   declared as "reserved", with the result that there was a pmhibition
    against cutting of the trees from the said 'reserved' area. The
    plaintiff in his evidence, as P. W.2, has stated that there were about
    300 teak trees in the area forming the bank of the Nalla and that
    the value of those trees would amount to between Rs. J0,000 and
H   Rs. 12,000. Though three Officers of the Forest Departrr,ent were
    examined on the side of the defendant, the aforesaid testimony given
    by the plaintiff bas not been controverted by them.
         s.I. MASOOD v. M.P. iiTAtE (Baiakrishna Eradi, J.)      901

      Notwithstanding the aforesaid facts brought out in the              A
evidence, the High Court summarily rejected the plaintiff's conten-
tion based on the factum of reservation of the trees standing on the
bank of Nalla by stating as follows:

           "But there is nothing in the plaintiff's complaints to
     the Department at any stage alleging that this reservation
                                                                          B
     had been made after the auction had taken place. The
     idea appears to be an after-thought. The mere oral
     statement of the plaintiff and his witnesses that this marking
     for reservation had taken place rafter the auction, on the
     basis that they did not see these markings about reservation
     of the trees near the Nalla when they had gone to that
                                                                          c
     forest on earlier occasions, are wholly insufficient to come
      to the conclusion that the Nalla area had been reserved
     after the auction."

The aforesaid reasoning is based entirely on the assumption that
                                                                          D
in one of the complaints preferred by the plaintiff before the
Department Officers, it had been alleged by him, that the reservation
 of the trees on the bank of Nalla had been made after the auction
had taken place. A mere reference to Exh. P-1 is sufficient to show
that the aforesaid assumption made by the High Court is wholly
erroneous. Exh. P-1 is a copy of the representation dated December        E
 28, 1960 submitted by the plaintiff to the Divisional Forest Officer
 (East), Bhopal. In paragraph 4 thereof, the plaintiff had stated as
follows:

           "That the applicant inspected the coupe in or about
      the first week of November 1960 to give the coupe boundary
                                                                          F
      certificate as is required under Clause 2 of the draft agree-
      ment deed. During this inspection the applicant was
      surprised to know that there were numerous irregularities
      committed in the marking of trees and huge area containing
      the Forest Produce marked for sale in the said coupe was
      subsequently reserved."
                                                                          G
                                             (underlining supplied)

 Thus, the correct factual position is that the plaintiff had categori-
 cally complained to the Department that a substantial area con-
 taining the forest produce, which had all been originally marked for
                                                                          H
 sale, had been subsequently 'reserved', with the result that the quan-
     902                    SIJPllllMll colJllt lll!l>ORtS     [1982] I s.c.tl

A   tity of timber available for extraction bad become substantially
    reduced, The criticism made by the High Court that the argument
    advanced by the plaintiff was the result of an after-thought, was
    therefore not justified.

          We may at this stage refer to Condition No. 3 in the sale-
B   notice (Exn. D/I) on which strong reliance was placed on behalf of
    the respondent, That condition reads:

                 "The details of quantities of forest produce announced
           at the time of auction are correct to the best of the know-
c           ledge of the Divisional Forest Officer but are not guaran-
           teed to any extent. The intending bidders are, therefore,
           advised to inspect on the spot the contract area and the
           produce they intend to bid for with a view to satisfy
           themselves about its correctness. No claim shall lie against
           the State Government for compensation or any other                        -~·

D          relief, if the details of the quantities are subsequently found
           to be incorrect".
                                                                                 •
    In our opinion, the trial court was perfectly right in its view that,
     while the said condition will operate to prevent the Contractor from
    claiming any damages or compensation from the State Government
E   on the ground that the details of the quantity of the forest produce
    were subsequently found to be incorrect, it will not preclude him
    from repudiating the contract on its being found that there was
    substantial variance between the particulars furnished at the time of
    the auction regarding the quantity and quality of timber that will
    be available for extraction in the concerned coupes and the quantity
F
    etc. of tree growth actually found to be available on the site. It has
    been clearly established by the evidence in this case that a very
    substantial quantity of timber standing on the bank of Nalla bad
    been marked for extraction and numbered and the auction sale had
    been held on the basis that the highest bidder would be entitled to
    fell and remove all those trees. But by the time the coupes were
G
    allowed to be inspected by the auction-purchaser, that area was
    declared to be "reserved", with the result that there was a com-
    plete prohibition against the felling of any timber therefrom. This
    has substantially altered the very foundation of the contract and
    hence it was perfectly open to the plaintiff to repudiate the contract
e   and claim a refund of the amount deposited by him as a part pay-
    ment of the purchase price.
                 S.I. MASOob V. M.P. STATE (/Jalakrishna Eradi, J.)    903

           We are unable to agree with the view expressed by the High           A
~-
     Court that "the plaintiff cannot succeed unless he proved that, even
     after excluding the trees standing on the reserved area, the rest of
     the forest did not have sufficient number of trees which would
     satisfy the assurance given at the time of the auction". The subject-
     matter of the auction sale was the totality of the trees which were
     marked for cutting in the two coupes. Since a substantial number           B
     of the marked trees was contained in the area which was subse-
     quently declared as "reserved", it is inevitable that there was a
     corresponding diminution in the total quantity of timber which was
     announced as available for cutting at the time oft he auction sale.

           We do not, therefore, find it possible to agree with the reasons     c
     stated by the High Court for refusing the plaintiff's prayer for refund
     of the amount paid by him by way of the first instalment of the sale
     price. The conclusion recorded by the trial court on this issue was
     perfectly correct and the High Court was in error in interfering with
     the said finding.
                                                                                D
            We notice, however, that a slight mistake has crept into the
     judgment and decree of the trial court, inasmuch as the amount of
     the first instalment refund has been wrongly mentioned therein as
     Rs. 17,500, whereas the amount actually paid by the plaintiff by way
     of the first instalment was only Rs. I 7,250. A modification to this
     extent is, therefore, called for in the decree passed by the trial
     court.

            This appeal is accordingly allowed, the judgment and decree
      passed by the High Court are set aside and those of the trial court
      are restored subject to the modification that the amount recoverable
      by the plaintiff from the defendant shall be only Rs. 17,250 and not      F
      Rs. 17 ,5CO as stated in the trial court decree. In all other respects,
      the decree passed by the trial court will remain in tact. The
      respondent (defendant) will pay the costs of the piaintiff in this
      Court as well as in the High Court.

      S.R.                                                                      G
                                                             Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "contract repudiation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.