SUNDARAM FINANCE LTD.versusNEPC INDIA LTD.
- Citation
- 1999 INSC 10
- Decided
- 13 January 1999
- Disposal
- Disposed off
Holding
A court may entertain an application under Section 9 of the Arbitration and Conciliation Act, 1996 and grant interim relief even before arbitral proceedings commence, provided a valid arbitration agreement exists and the applicant demonstrates a manifest intention to refer the dispute to arbitration.
Summary
Sundaram Finance Ltd entered into a hire‑purchase agreement for two wind‑turbine generators with NEPC India Ltd, which contained an arbitration clause. After the respondent defaulted on payments, the appellant sought interim custody of the equipment under Section 9 of the Arbitration and Conciliation Act, 1996, and the trial court granted the order. The High Court set aside the order, holding that Section 9 could not be invoked before arbitral proceedings were pending. The Supreme Court held that Section 9 expressly allows a court to grant interim measures before or during arbitral proceedings, provided a valid arbitration agreement exists and the applicant shows a manifest intention to arbitrate, and that a notice under Section 21 is not a prerequisite. The Court also emphasized the need for High Courts to frame procedural rules under Section 82. Consequently, the High Court judgment was set aside and the trial court's interim order restored.
Issues considered
- Whether Section 9 of the Arbitration and Conciliation Act, 1996 authorises a court to grant interim relief before the commencement of arbitral proceedings.
- Whether a notice invoking the arbitration clause under Section 21 is a condition precedent to filing an application under Section 9.
- Whether the existence of a valid arbitration agreement and a manifest intention to arbitrate suffice for jurisdiction under Section 9.
- Whether High Courts should make rules under Section 82 to regulate applications under Section 9.
Legislation cited
- Arbitration Act, 1940s. 41(b), s. 4l(b)
- Arbitration and Conciliation Act, 1996s. 17, s. 21, s. 2(d), s. 82, s. 84, s. 9
- UNCITRAL Model Law on International Commercial Arbitrations. Article 9
Subjects
Judgment
t-
SUNDARAM FINANCE LTD. A
~
v.
NEPC INDIA LTD.
JANUARY 13, 1999
(SUJATA V. MANOHAR AND B.N. KIRPAL, JJ.) B
\
Arbitratio11 a11d Conciliatio11 Act, 1996: Sectio11s 9 and 21.
Interim orde1~Seeking of-Before co111111e11ceme11t of arbitra-
tion-Held, Court ca11 pass interim order eve11 before comme11ceme11t of c
wbitral proceedings-It is not necessary to issue a 11otice invoking arbitration
clause to the opposite party before filing application u11der S. 9 for interim
relief-However, before passi11g the interim order court must be satisfied that
there exists a valid arbitration agree111e11t a11d that the applicant inte11ds to
take the dispute to arbitration-Court may pass a co11ditio11al order with a
view to seei11g that effective steps are take11 by the applicant for comme11ci11g D
the arbitral proceedi11gs-Arbitratio11 Act, 1940, Ss.41(c), 20 a11d Sch.
Il--{f11ited Nations Commissio11 on Intemational Trade Law-Model Law
011 I11tematio11al Commercial Arbitration adopted in 1985, .Art.9.
Sections 9 and 22-Rules u11der-Maki11g of-By High Courts-Held, E
High Cuurts should make rules u11der S.82 consistent with the Act providing
for the manner of fili11g the application, the documents which should accom-
pany the same and the manner of dealing with the same under S.9.
Provisio11s-/11terpretation of-Held, Should be construed i11de-
pe11dently without refere11ce to the principles underlying the repealed-Arbitra- F
tion Act, 1940-Should be co11strued with reference to the UNCITRAL Model
Law.
Interpretation of Statutes:
G
Basic Rules--fl.ule of Literal Construction-adopting of.
-« ,_
Words and Phrases:
"Before''-Mea11i11g of-/n the co11text of S.9 of the Arbitration a11d
Conciliation Act, 1996. H
89
90 SUPREME COURT REPORTS [1999] 1 S.C.R.
A The respondent had entered into a hire-purchase agreement with the ~
appellant in respect of two wind turbine generators along with all acces-
sories. The terms of agreement contemplated payments being made in
instalments by the respondent. However, the respondent paid the first
fifteen instalments and thereafter committed default and payment was not
made in spite of several demands being made by the appellant.
B
The purchase agreement contained an arbitration clause and, there-
fore, the appellant filed an application under Section 9 of the Arbitration
and Con~iliation Act, 1996 before the Trial Court for interim custody of
the hire-purchase equipment. The Trial Court passed an interim order to
c that effect.
The respondent filed a petition before the High Court challenging
the aforesaid order of the Trial Court. The High Court allowed the petition
on the ground that as no arbitration proceedings were pending and even
D the arbitrator had not been appointed, an application under Section 9 of
the 1996 Act for getting interim relief alone was not maintainable and, "
therefore, the Trial Court had no jurisdiction to entertain such an applica-
tion. Hence this appeal.
Disposing of the appeal, this Court
E
HELD: 1.1. Under the Arbitration and Conciliation Act, 1996 the
Court can pass interim orders under Section 9. Arbitral proceedings
commence only when the request to refer the dispute is received by the
respondent as per Section 21 of the Act. The material words occurring in
F Section 9 are "before or during the arbitral proceedings". This clearly con-
templates two stages when the Court can pass interim orders, i.e:, during
the arbitral proceedings or before the arbitral proceedings, There is no
reason as to why Section 9 of the 1996 Act should not be literally construed.
Meaning has to be given to the word "before" occurring in the said section.
G The only interpretation that can be given is that the Court can pass interim
orders before the commencement of arbitral proceedings. The Court has
~ ~-
jurisdiction to entertain an application under Section 9 either before
arbitral proceedings or during arbitral proceedings or after the making of
the arbitral award but before it is enforced in accordance with Section 36
H of the Act. [98-G-H; 99"A·D]
r
SUNDARAM FINANCE LTD. v. NEPC INDIA LTD. 91
1.2. However, when a party applies under Section 9 of the 1996 Act A
it is implicit that it accepts that there is a final and binding arbitration
agreement in ·existence. It is also implicit that a dispute must have arisen
which is referable to the arbitral tribunal. Section 9 further contemplates
arbitration proceedings taking place between the parties. When an applica-
tion under Section 9 is filed before the commeucement of the arbitral
proceedings there has to be manifest intention on the part of the applicant
B
to take recourse to the arbitral proceedings if, at the time when the
application under Section 9 is filed, the proceedings have not commenced
under Section 21 of the 1996 Act. In order to give full effect to the words
"before or dwing arbitral proceedings', occurring in Section 9 it would not
be necessary that a notice invoking the arbitration clause must be issued C
to the opposite party before an application under Section 9 can be filed.
The issuance of a notice may, in a given case, be sufficient to establish the
manifest intention to have the dispute referred to arbitral tribunal; but a
situation may so demand that a party may choose to apply under Section
9 for an interim measure even before issuing a notice contemplated by D
Section _21 of the said Act. If an application is so made the Court will first
have to be satisfied that there exists a valid arbitration agreement and the
applicant intends to take the dispute to arbitration. Once it is so satisfied
the Court will have the jurisdiction to pass orders under Section 9 giving
such interim protection as the facts and circumstances warrant. While
passing such an order and in order to ensure that effective steps are taken E
to commence the arbitral proceedings, the Court while exercising jurisdic-
tion under Section 9 can pass conditional order to put the applicant to
such terms as it may deem fit with a view to see that effective steps are
taken by the applicant for commencing the arbitral proceedings. What is
apparent, however, is that the Court is not debarred from dealing with an
F
application under Section 9 merely because no notice has been issued
under Section 21 of the 1996 Act. [102-C-H]
Channel Tunnel Group Ltd. v. Balfour Betty Co11strnctio11 Ltd. [1992)
2 LLR, referred to.
G
Russel 011 Arbitration 21st Edn. P .386, referred to.
2.1. The 1996 Act does not contain a provision similar to Section 20
of the Arbitration Act, 1940. Nor is Section 9 or Section 17 similar to
Section 41 (b) and the Second Schedule to the 1940 Act. Section 8 of the H
92 SUPREME COURT REPORTS [1999] 1 S.C.R.
A new Act is not in pari materia with Section 20 of the 1940 Act. It is only if
in an action, which is pending before the Court that a party applies that 'ff
the matter is the subject of an arbitration agreement does. the Court get
jurisdiction to refer the parties to arbitration. The said provision does not
contemplate, unlike Section 20 of the 1?40 Act, a party applying to a Court
B •for appointing an arbitrator when no matter is pending before the Court.
Under the 1996 Act appointment of arbitrator/s is made as per the
provision of Section 11 which does not require the Court to pass a judicial !
order appointing arbitrator/s. [98-D-F]
Sant Ram & Co. v. State of Rajasthan, [1997) 1 SCC 147, held
· C inapplicable.
2.2. Further, Section 82 of the 1996 Act gives the High Court power
_to make rules consistent with the Act. All the High Courts have not so far
made rules. Whereas Section 84 gives the Central Government power to
make rules to carry out the provisions of the Act, the High Courts should
D also, wherever necessary, make rules. It would be helpful if such rules deal
with the procedure to be followed by the Courts while exercising jurisdic- ><
tion under Section 9 of the Act. The rules may provide for the manner in
which the application should be filed, the documents which should accom-
pany the same and the manner in which such applications will be dealt
E with by the Courts. The High Courts are, therefore, requested to frame
appropriate rules as expeditiously as possible so as to facilitate quick and
satisfactory disposal of arbitration cases. [103-A-C]
3. The 1996 Act is very different from the Arbitration Act, 1940. The
provisions of the Act have, therefore, to be interpreted and construed
F independently and in fact reference to 1940 Act may actually lead to
misconstruction. In other words the provisions of 1996 Act have to be
interpreted being uninfluenced by the principles underlying the 1940 Act.
In order to get help in construing these provisions it is more relevant to
refer to the UNCITRAL (United Nations Commission on International
G Trade Law) Model Law rather than the 1940 Act. [96-C-D]
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 141-143
of 1999. -r !"
From the Judgment and Order dated 22.6.98 of the Madras High
H Court itJ. C.R.P. No. 1421-23 and C.t.f.P. Nos. 6698-6701of1998.
SUNDARAM FINANCE LTD. v. NEPCINDIALTD. [KIRPAL, J.) 93
Harish Salve and K. Swami for the Appellant. A
Gopal Subramaniam, Gopal Jain, Arvind Kumar, A Choudhary,
(R.Karanjawala) for Mrs. M. Karanjawala for the Respondent.
The Judgment of the Court was delivered by
B
KIRPAL, J. Leave granted.
An important question which arises for consideration in these cases
is whether under Section 9 of The Arbitration and Conciliation Act, 1996
(hereinafter referred to as 'the 1996 Act') the. Court has jurisdiction to pass
interim orders even before arbitral proceedings commence and before an c
arbitrator is appointed.
. The relevant facts which are necessary for the consideration of the
p_oint in issue are that the respondent had entered 1into a hire-purchase
agreement with the appellant herein in respect of supply of two wind D
turbine generators along with all accessories. The terms of the agreement
contemplated payments being made in instalments by the respondent, the
first instalment was payable on 29th September, 1995 and the last was due
by 25th August, 1998. In all the payment was to be made by 36 instalments.
According to the appellant the respondent paid the first fifteen E
instalments and thereafter committed default and payment was not made
i;i spite of several demands being made by the appellant. The hire-purchase
agreement contained an arbitration clause which reads as follqws :
"All disputes, differences and/or claims, arising o.ut of this hire F
purchase agreement whether during its subsistence or thereafter
shall be settled by arbitration in accordance with the provision of
Indian Arbitration Act, 1940 or any statutory amendments thereof
and shall be referred to the sole arbitration of an arbitrator
nominated by the Managing Director of the owner. The award G
given by such an arbitrator shall be final and binding on all the
parties to this agreement.
It is a term of this agreement that in the event of such an arbitrator
to whom the matter has been originally referred doing or being
unable to act for any reason, the Managing Director of the owner, H
94 SUPREME COURT REPORTS [1999) 1 S.C.R.
A at the time of such death of the arbitrator or his inability to act as
arbitrator shall appoint another person to sit as arbitrator. Such a
person shall be entitled to proceed with the reference from the
stage at which it was left by his predecessor".
When the appellant came to know that other litigation was pending against
B the respondent it filed an application under Section 9 of the 1996 Act
before the City Trial Court, Chennai, praying for the appointment of an '
Advocate Commissioner to take custody of the hire-purchase
machinery/equipment and restore .the same to the interim custody of the
appellant herein. This application was taken up for hearing on 7th April,
c 1998 and the Trial Court passed an interim order appointing a Commis-
sioner to take possession of the turbines with the help of the police.
The aforesaid order of the Trial Court was challenged with the
respondent filing a petition under Article 227 of the Constitution before
the High <;:ourt at Madras. One of the main contentions urged on behalf
D of the respondent was that as no arbitration proceedings were pending and .,<.
even the arbitrator had not been appointed, an application under Section
9 of the 1996 Act for getting interim relief alone was not maintainable. On
merits it was contended that the ex parte order which was passed by the
trial court was uncalled for. While. supporting the order of the Trial Court
the appellant herein had submitted before the High Court that interim
E
order could be passed even before the commencement of the arbitral
proceedings.
By it's judgment dated 22nd June 1998, the High Court allowed the·
respondent's petition. In it's judgment, after referring to the provisions of
F Section 41 of the Arbitration Act, 1940 and the relevant provisions of the ·•
1996 Act, the High Court observed as follows :
"Second Schedule to the 1940 Act is the powers of the Court and
item No. 4 is "interim injunction or the appointment of a receiver".
Therefore, there is no virtual difference between Section 41 read
G with Schedule 2 and present Section 9 of the Arbitration Act.
Moreover, if an interpretation such as the one contended by the -f' I
Learned Counsel for the appellant is to be given to Section 9 the
very object of the Act would be defeated. Any party, who has an
agreement for arbitration with another can rush to Civil Court and
H straight away get an order under Section 9 and thereafter keep
I
SUNDARAM FINANCE LTD. v. NEPCINDIALTD. [KIRPAL,J.] 95
quiet without referring the matter to Arbitration. That will have a A
very serious consequence on the provisions of the Act. It could not
have been the intention of the legislature in enacting the present
Arbitration Act. Further, the very fact that Section 9 comes after
Section 8 which deals with the reference of disputes to Arbitration,
the only interpretation that could be given to Section 9 is that it
B
could be availed of when an arbitration proceedings is pending
~
before the Arbitral Tribunal or is at the reference stage before the
Court or after the Arbitral award has been made."
While coming to the conclusion that the application under Section 9 of the
1996 Act before the trial court was misconceived, as no effort had at the c
time of filing of such an application, being made by the appellant to have
an arbitrator appointed, the High Court chose not to consider the merits
of the trial court's order as in its opinion the trial court had no jurisdiction
to entertain such an application. Hence these appeals by special leave.
Under the provisions of the Arbitration Act, 1940, the powers of the D
Court to pass interim orders were derived from Section 4l(b) read with
2nd Schedule to the Arbitration Act, 1940. Mr. Gopal Subramaniam,
learned senior counsel appearing for the respondent, placed reliance on
Sant Ram & Co. v. State of Rajasthan and Others, [1997) 1SCC147 wherein
at page 150 it was observed that "The initiation of pendency of any proceed-
E
ings in the Coult in relation to the arbitration proceedings would, therefore,
be a precondition for the exercise of the power by the civil co ult under the
Second Schedule of the Act." Even if this be the position under the 1940
Act we still have to examine whether there has been any change in the law
with the promulgation of The Arbitration and Conciliation Act, 1996.
F
Prior to the promulgation of the 1996 Act the law on arbitration in
India was substantially contained in three enactments, namely, The Ar-
bitration Act, 1940, the Arbitration (Protocol and Convention) Act, 1937
and the Foreign Awards (Recognition and Enforcement) Act, 1961. In the
Statement of Objects and Reasons appended to the Bill it was stated that
the 1940 Act, which contained the general law of arbitration, had become G
outdated. The said objects and reasons noticed that the United Nations
~
Commission on international Trade Law (UNCITRAL) adopted in 1985
the Model Law on International Commercial Arbitration. The General
Assembly had recommended that all countries give due consideration to
the said Model Law which, along with the rules, was stated to have H
96 SUPREME COURT REPORTS [1999) 1 S.C.R.
A harmonised concepts on arbitration and conciliation of different legal
systems of the world and thus contained provisions which were designed
for universal application. The above said Statement of Objects and Reasons
in para 3 states that "Though the said UNCITRAL Model Law and rnles are
intended to deal with international commercial arbitration and conciliation,
B they could, with appropriate modifications, serve as a model for legislation
on domestic arbitration and conciliation. The present Bill seeks to consolidate
and amend the law relating to domestic arbitration, international commercial
arbitration, enforcement of foreign arbitral awards and to define the law
relating to conciliation, taking into account the said UNCITRAL Model Law
and Rules."
c
The 1996 Act is very different from the Arbitration Act, 1940. The
provisions of this Act have, therefore, to be interpreted and construed
independently and in fact reference to 1940 Act may actually lead to
misconstruction. In other· words the provisions of 1996 Act have to be
interpreted being uninfluenced by the principles underlying the 1940 Act.
D In order to get help in construing these provisions it is more relevant to "
refer to the UNCITRAL Model Law rather than the 1940 Act.
Some of the provisions of the 1996 Act which are relevant in the
present case are Sections 2( d), 9, 17 and Section 21. Section 2( d) defines
E an Arbitral Tribunal to mean a sole arbitrator or a panel of arbitrators.
Section 9 of the_ 1996 Act, which gives power to the Court to pass interim
orders, and with the interpretation of which we are concerned in the
present case, reads thus :
"9. Interim measures by court - A party may, before or during
F arbitral proceedings or at any time after the making of the arbitral
award but before it is enforced in accordance with section 36,
apply to a court :
(i) for the appointment of a guardian for a minor or a person of
unsound mind for the purposes of arbitral proceedings; or
G
(ii) for an interim measure of protection in respect of any of the
following matters, namely :
(a) the preservation, interim custody or sale of any goods which·
H are the subject-matter of the arbitration agreement;
SUNDARAMFINANCELTD. v. NEPCINDIALTD. [KIRPAL,J.] 97
(b) securing the amount in dispute in the arbitration; A
(c) the detention, preservation or inspection of any property or
thing which is the subject-matter of the dispute in arbitration, or
as to which any question may arise therein and authorising for any
of the aforesaid purposes any person to enter upon any land or
B
building in the possession of any party, or authorising any samples
to be taken or any observation ~o be made, or experiment to be
tried, which may be necessary or expedient for the purpose of
obtaining full information or evidence;
(d) interim injunction or the appointment of a receiver; c
(e) such other interim measure of protection as may appear to the
court to be just and convenient,
;.
and the Court shall have the same power for making order as it D
has for the purpose of, and in relation to, any proceedings before
it."
As this section refers to ''Arbitral Tribunaf' the same has to be read along
with Section 21 which relates to the commencement of the arbitral
proceedings and reads as follows : E
"21. Commencement of arbitral proceedings - Unless otherwise
agreed by the parties, the arbitral proceedings in respect of a
. particular dispute commence on the date on which a request for
that dispute to be referred to arbitration is received by the respon- F
dent."
The Arbitral Tribunal has also been given jurisdiction to pass interim
orders by Section 17 of the said Act which reads as follows:
"17. Interim measures ordered by arbitral tribunal : G
'· ' (1) Unless otherwise agreed by the parties, the arbitral tribunal
may at the request of a party, order a party to take any interim
measure of protection as the arbitral tribunal may consider neces-
sary in respect of the subject-matter of the dispute. H
98 SUPREME COURT REPORTS (1999] 1 S.C.R.
A (2) The arbitral tribunal may require a party to provide ap-
propriate security in connection with a measure ordered under
sub-section (1)."
The reading of Section 21 clearly shows that the arbitral proceedings
commence on the date on which a request for a dispute to be referred to
B
arbitration is received by the respondent. It is in this context that we have
to examine and interpret the expression "before or during arbitral proceed-
ings" occurring in Section 9 of the 1996 Act. We may here observe that
though Section 17 gives the arbitral tribunal the power to pass orders the
same cannot be enforced as orders of a Court. It is for this reason that
C Section 9 admittedly gives the Court power to pass interim orders during
the arbitration proceedings.
The position under the Arbitration Act, 1940 was that a party could
~
commence proceedings in Court by moving an application under Section
20 for appointment of an arbitrator and simultaneously it could move an
D ~
application for interim relief under the Section Schedule read with Section
""'
41(b) of the 1940 Act. The 1996 Act does not contain a provision similar
to Section 20 of the 1940 Act. Nor is Section 9 or Section 17 similar to
Section 41(b) and the Second Schedule to the 1940 Act. Section 8 of the
new Act is not in pari materia with Section 20 of the 1940 Act. It is only if
E in an action which is pending before the Court that a party applies that the
matter is the subject of an arbitration agreement does the Court get
jurisdiction to refer the parties to arb~tration. The said provision does not
contemplate, unlike Section 20 of the 1940 Act, a party applying to a Court
for appointing an arbitrator when no matter is pending before the Court.
F Under th_e 1996 Act appointment of arbitrator/s is made as per the .,-
provision of Section 11 which does not require the Court to pass a judicial
order appointing arbitrator/s. The High Court was, therefore, wrong in ·-'
referring to these provisions of the 1940 Act while interpreting Section 9
of the new Act.
G Under the 1996 Act the Court can pass interim orders under section-
9. Arbitral proceedings, as we have seen, commence only when the request i /
to refer the dispute is received by the respondent as per Section 21 of the
Act. The material words occurring in Section 9 are "before or during the_
arbitral proceedings". This clearly contemplates two stages when the Court
H can pass interim orders, i.e., during the arbitral proceedings or before the
SUNDARAM FINANCE LTD. v. NEPCINDIALTD. [KIRPAL,J.] 99
·~ arbitral proceedings. There is no reason as to why Section 9 of the 1996 A
Act should not be literally construed. Meaning has to be given to the word
"before" occurring in the said section. The only interpretation that can be
given is that the Court can pass interim orders before the commencement
of arbitral proceedings. Any other interpretation, like the one given by the
High Court, will have .the effect of rendering the word "before" in Section
9 as redundant. This is clearly not permissible. Not only does the language
B
warrants such an interpretation but it was necessary to have such a
provision in the interest of justice. But for such a provision no party would
have a right to apply for interim .measure before notice under Section 21
is received by the r.espondent. It is not unknown when it becomes difficult
to serve the respondents. It was, therefore, necessary that provision was c
made in the Act which could enable a party to get interim relief urgently
in order to protect it's interest. Reading the section as a whole it appears
to us that the Court has jurisdiction to entertain an application under
Section 9 either before arbitral proceedings or during arbitral proceedings
or after the making of the arbitral award but before it is enforced in
_,, ... D
accordance with Section 36 of the Act.
Section 9 of the said Act corresponds to Article 9 of the UNCITRAL
Model Law which is as follows :
"It is not incompatible with an arbitration agreement for a party E
to request, befpre or during arbitral proceedings, from a court an
interim measure of protection and for a court to grant such
measure."
.,.. This article recognises, just like Section 9 of the 1996 Act, a request being F
made before a Court for an interim measure of protection before arbitral
proceedings. It is possible that in some countries if a party went to the
Court seeking interim measure of protection that might be construed under
the local law as meaning that the said party had waived its right to take
recourse to arbitration. Article 9 of the UNCITRAL Model Law seeks to
clarify that merely because a party to an arbitration agreement requests the G
Court for an interim measure "before or during arbitral proceedings" such
recourse would not be regarded as being incompatible with an arbitration
agreement. To put it differently the arbitration proceedings can i::ommence
and continue notwithstanding a party to the arbitration agreement having
approached the Court for an order for interim protection. The language H
100 SUPREME COURT REPORTS (1999] 1 S.C.R.
A of Section 9 of the 1996 Act is not identical to Article 9 of the UNCITRAL
Model Law but the expression "before or during arbitral proceedings" used
in Section 9 of the 1996 Act seems to have been inserted with a view to
give it the same meaning as those words have in Article 9 of the UN-
CITRAL Model Law. It is clear, therefore, that a party to an arbitration
agreement can approach the Court for interim relief not only during the
B arbitral proceedings but even before the arbitral proceedings. To that
extent Section 9 of the 1996 Act is similar to Article 9 of the UNCITRAL
Model Law.
It will also be useful to refer to a somewhat similar provision in the
C Arbitration Act, 1996 of England. Section 44 of this Act gives the Court
powers which are exercisable in support of the arbitral proceedings. Sub-
section (3) of Section 44 permits, in the case of urgency, the Court to make
an order contemplated by sub-section (2) even on an application by a
''proposed party to the amitral proceedings". The expression used in this sub-
D section ''party or proposed party to the arbitral proceedings" shows that where
arbitral proceedings have commenced then the application will obviously
be of a party to the said proceedings but where the arbitral proceedings
have not commenced a ''proposed party" has been given the right to ap-
proach the Court. A proposed party to the arbitral proceedings would,
therefore, be one who is party to an arbitration agreement and where
E disputes have arisen but the arbitral proceedings have not commenced.
While referring to Section 44 of the English Act in ddi'ling with the
question of grant of interim injunctions in support of arbitral proceedings
Russell on Arbitration (21st Edition) at page 386 has stated as under :
F "The Court may exercise its power to grant an interim injunction
before there has been any request for arbitration or the appoint-
ment of arbitrators, provided that the applicant intends to refer
the dispute to arbitration in due course.
G The power to grant an interim injunction under Section 44 of the
Act extends to the granting of a Mareva injunction in appropriate
cases. It may also include granting an interim mandatory injunc-
tion, although the court will be slow to grant an injunction which
provides a remedy of essentially the Sjlme kind as is ultimately
H being sought from the arbitral tribunal.
SUNDARAMFINANCELTD. v. NEPCINDIALTD. [KIRPAL,J.] 101
., In our opinion this view correctly represents the position in law, A
namely, that even before the commencement of arbitral proceedings the
Court can grant interim relief. The said provision contains the same
principle which underlies Section 9 of the 1996 Act.
Our attention was also drawn to the case of (171e Channel Tunnel
~ Group Ltd. and France Manche SA. v. Balfour Betty Constrnction Ltd. and B
Others, [1992) 2 Lloyd's Law Reports) dealing with question of the juris-
diction of the England' Court to grant an interim injunction in a case where
the parties have agreed that the disputes shall be settled by arbitration. The
Court of Appeal referred to Section 12 (6) of the Arbitration Act, 1950
which provided as follows : c
"The High Court shall have, for the purpose of and in relation to
a reference, the same power of making orders in respect of - (h)
interim injunctions or the appointment of a receiver; as it has for
the purpose of and in relation to an action or matter in the High
Court... .. D
Construing this Staughton L.J observed as under :
"In my view this power cai:t be exercised before there has been any
request for arbitration or the appointment of arbitrators, provided
E
that the applicant intends to take the dispute to arbitration in due
course. Whatever the meaning of "reference" to s.12(6)(h) (and it
is not always_ easy to determine the precise meaning of the word
in arbitration_ statutes) I would hold that the power of the Court
in such a case would be exercised for the purpose of and in relation
to a reference." F
We are in respect agreement with the aforesaid observations which are in
conformity with the view which we have taken in construing Section 9 of
the 1996 Act.
It was submitted by Mr. Subramaniam that even if the Court can G
exercise jurisdiction under Section 9 before the arbitral proceedings have
' commenced the party seeking to invoke Section 9 must express a manifest
intention to arbitrate. The learned counsel submitted that this intention can
take the following forms : (a) In an application under Section 9, the party
would have to state that it unequivocably relies on the arbitration agree- H
102 SUPREME COURT REPORTS (1999] 1 S.C.R.
~
A ment and makes an averment that it would invoke the arbitration clause;
(b) At the time when the Court passes an interim order under Section 9,
an express undertaking is given by the party before the Court that it would
invoke the arbitration clause forthwith and within a fixed period; and ( c)
a notice invoking arbitration clause should have been issued k the opposite
party. It was contended that mere filing of an application Ul).der Section 9
B was not sufficient to establish manifest intention to this extent. ,,
When a party applies under Section 9 of the 1996 Act it is implicit
that it accepts that there is a final and binding arbitration agreement in
existence. It is also implicit that a dispute must have arisen which is
c referable to the arbitral tribunal. Section 9 further contemplates arbitration
proceedings taking place between the parties. Mr. Subramaniam is, there-
fore, right in submitting that when an application under Section 9 is filed
before the commencement of the arbitral proceedings there has to be
manifest intention on the part of the applicant to take recourse to the
D arbitral proceedings if, at the time when the application under Section 9 is
filed, the proceedings have not commenced under Section 21 of the 1996
Act. In order to give full effect to the words "be/ore or during arbitral
proceedings" occurring in Section 9 it would not be necessary that a notice
invoking the arbitration clause must be issued to the opposite party before
an application under Section 9 can be filed. The issuance of a notice may,
E iri a given case, be sufficient to establish the manifest intention to have the
dispute referred to arbitral tribunal, but a situation may so demand that a
party may choose to apply under Section 9 for an interim measure even
before issuing a notice contemplated by Section 21 of the said Act. If an
application is so made the Court will first have to be satisfied that there
F exists a valid arbitration. agreement and the applicant intends to take the T
dispute to arbitration. Once it is so satisfied the Court will have the
jurisdiction to pass orders under Section 9 giving such interim protection
as the facts and circumstances warrant. While passing such an order and
in order to ensure that effective steps are taken to commence the arbitral
proceedings, the Court while exercising jurisdiction under Section 9 can
G pass conditional order to put the applicant to such terms as it may deem
fit with a view to see that effective steps are taken by the applicant for
commencing the arbitral proceedings. What is apparent, however, is that
1
~
the Court is not debarred from dealing with an application under Section
9 merely because no notice has been issued under Section 21 of the 1996
H Act.
SUNDARAMFINANCELTD. v. NEPCINDIALTD.[KIRPAL,J.] 103
There is another aspect which calls for our attention. Section 82 of A
the 1996 Act gives the High Court power to make rules consistent with the
Act. We were informed that all the High Courts have not so far made rules.
Whereas the Section 84 gives the Central Government power to make rules
to carry out the provisions of the Act, the High Court should also, wherever
necessary, make rules. It would be helpful if such rules deal with the
procedure to be followed by the Courts while exercising jurisdiction under
B
Section 9 of the Act. The rules may provide for the manner in which the
application should be filed, the documents which should accompany the
same and the manner in which such applications will be dealt with by the
Courts. The High Courts are, therefore, requested to frame appropriate
rules as expeditiously as possible so as to facilitate quick and satisfactory c
disposal of arbitration cases.
In view of the aforesaid discussions it follows that the High Court
erred in coming to the conclusion that the trial court had no jurisdiction
in entertaining the application under Section 9 because arbitration
proceedings had not been initiated by the appellant. D
We accordingly set aside the judgment of the High Court but as the
High Court has not considered the merits of the case, it is directed that
the petition filed by the respondent, challenging the order of the Trial
court, be decided on merits. The appeals are disposed of accordingly.
There will be no order as to costs. E
v.s.s. Appeals disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.