Created byFuzzy Cloud

Supreme Court of India

STEEL AUTHORITY OF INDIA LTD.versusGUPTA BROTHER STEEL TUBES LTD.

Citation
2009 INSC 1121
Decided
9 September 2009
Disposal
Dismissed

Holding

The arbitrator’s construction of Clause 7.2 was a permissible view and no ground under Section 30 existed to set aside the award, so the appeal was dismissed.

Summary

The Steel Authority of India Ltd. (SAIL) appealed a 1993 arbitration award that granted damages to Gupta Brother Steel Tubes Ltd. for alleged breaches of a supply scheme. SAIL contended that the arbitrator exceeded his jurisdiction by applying Clause 7.2, which provides for liquidated damages, to a refusal to supply, and by ignoring Section 74 of the Indian Contract Act. The Supreme Court examined whether Clause 7.2 covered refusal to supply, whether the arbitrator’s interpretation was a permissible view, and whether the award could be set aside under Section 30 of the Arbitration Act, 1940. It held that the clause was intended only for delayed or failed supply, not for outright refusal, and that the arbitrator’s construction was a possible, non‑perverse view. Consequently, no ground existed for setting aside the award, and the appeal was dismissed.

Issues considered

  • Whether Clause 7.2 of the contract covers refusal to supply and thus the arbitrator exceeded his jurisdiction.
  • Whether the arbitrator erred by ignoring Section 74 of the Indian Contract Act in awarding damages.
  • Whether the arbitrator exceeded jurisdiction by entertaining a claim quantified after the arbitration had commenced.
  • Whether the award can be set aside under Section 30 of the Arbitration Act, 1940.
  • Whether new pleas not raised before the High Court can be raised in a Supreme Court appeal under Article 136.

Legislation cited

Subjects

ArbitrationSection 30 Arbitration ActLiquidated damagesClause 7.2Indian Contract Act Section 74Award setting asideJurisdiction of arbitratorArticle 136

Judgment

....J:.,
                                    [2009) 14 (ADDL.) S.C.R. 253


         ,'"''r                 STEEL AUTHORITY OF INDIA LTD.                            A
....,                                            v.
                               GUPTA BROTHER STEEL TUBES LTD.
                                  (Civil Appeal No. 5241 of 2002)

                                        SEPTEMBER 9, 2009                                B
                         [TARUN CHAlTERJEE AND R. M. LODHA, JJ.]
             A,
     I
                         Arbitration Act, 1940:

    {                    s. 30 - Application for setting aside of award passed by        c
         •           arbitrator - On ground of error of jurisdiction and legal
                     misconduct by arbitrator - Legal position discussed - HELD:
                     Where a provision of liquidated damages for specific
             ~
                     breaches only is made, such clause cannot be read as
                     covering all types of breaches - In the instant case, Clause D
                     7.2 of agreement specifying the compensation for failure to
                     supply or delayed supply of material cannot be said to cover
                     refusal to supply the material - Thus, the claim of damages
                     made by claimant for breaches committed by SAIL was
                     entirely different from breaches contemplated by Clause 7.2 E.
                     - The view of the arbitrator that s. 74 of Contract Act had no

  -          ,.-.A   application to the case and that the breach due to refusal on
                     part of SAIL to supply materials in respect of the quarter July-
                     September, 1988 did not fall within ambit of the terms
                     contained in compensation Clause .7.2 is a possible view and F
                     having not been found to be perverse or unreasonable by the
                     three courts below, no case for setting the award within the four
                     comers of s.30 is made out warranting interference in exercise
                     of powers under Article 136 of the Constitution - Constitution
                     of India, 1950 - Articles 136 - Contract Act, 1872 - s. 74.       G
               -~
                         Constitution of India, 1950:

                         Article 136 - Scope of:.... Application for setting aside the

                                                   253                                   H
    254   SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.

                                                                       ~-
A award passed by arbitrator - Plea not raised before High
  Court - HELD: There has to be some sanctity and finality to
  the decision of arbitrator and new plea, which was not raised
  before High Court cannotbe allowed to be raised in appeal
  under Article 136 - Even otherwise, in considering the claims
B as quantified by application dated 12.9.1991, arbitrator has
  not exceeded the jurisdiction - Arbitration Act, 1940 - s.30. ·
                                                                      ~
         The appellant-SAIL formulated a Scheme entitled
    "Full Requirement Supply Scheme" for meeting the full
    requirements of HR CoilslSkolps to the customers. Those
c who     wanted to avail the said material as per the Scheme
    were required to register their requirements with SAIL.
    The Scheme was in operation in respect of two quarters,
    namely, (i) July to September, 1988 and (ii) October to
                                                                    ~
    December, 1988. The respondents indented 1500 metric
D
    tonnes of imported material for the first quarter (July to
    September, 1988). On September 15, 1988 SAIL informed
    the respondents, of their inability to arrange for the
    import. The respondents thereafter indented for supply
    of 1500 metric tonnes of imported material for the second
E quarter (October to December, 1988). The respondents
                                                                    .... ...
    were delivered the goods and payments were made.
    Thereafter dispute 2.rose between the parties and the
  . respondents made a claim of Rs.1,75,41,359 before the
                                                                               --
    Arbitrator who passed an award on September 7, 1993.
F As regards .Clause 7.2 of the agreement specifying the                       I


    compensation to the contractor and providing for
    maximum cap for liquidated damages for failure to supply
    and delayed supply of the material, the arbitrator held that
    Clause 7.2 was not applicable as it was not a case of
G delayed supply but refusal to supply. The objections filed
                                                                    ¥-
   by SAIL to the award were overruled by the Sub-Judge
    and the award was made rule of the court. The appeal
                                                                               ..;
    filed by the SAIL was dismissed by the District Judge.
    The revision petition filed by the appellant-SAIL was
H
                                                                        .   ,.-..
~
                        STEEL AUTHORITY OF INDIA LTD. v. GUPTA                 255
                             BROTHER STEEL TUBES LTD.
    1..-c,
                    dismissed by the High Court.                                       A
    .
    (                   In the instant appeal by SAIL, the plea relating to time
                    barred claim raised before the High Court was not
                    pressed and the only question for consideration before
                    the Court was: whether the breaches alleged by the                 B
                    respondents were covered by the stipulations contained
                    in Clause 7.2 of the contract?
    '       -"'
                         Dismissing the appeal, the Court

                          HELD: 1. The legal position that emerges from the            c
;
                    decisions of this Court can be summarised thus: (i) In a
                    case where an arbitrator travels beyond the contract, the
                    award would be without jurisdiction and would amount
                    to legal misconduct and because of which the award
                    would become amenable for being set aside by a court;              D
                    (ii) An error relatable to interpretation of the contract by
                    an arbitrator is an error within his jurisdiction and such
                    error is not amenable to correction by courts as such
                    error is not an error on the face of the award; (iii) If a
                    specific question of law is submitted to the arbitrator and        E
                    ha answers it, the fact that the answer involves an
    ' it'     ...
                    erroneous decision in point of law does not make the
                    award bad on its face; (iv) An award contrary to
                    substantive provision of law or against the terms of
                    contract would be patently illegal; (v) Where the parties          F
                    have deliberately specified the amount of compensation
                    in express terms, the party who has suffered by such
                    breach can only claim the sum specified in the contract
                    and not in excess thereof; (vi) If the conclusion of the
                    arbitrator is based on a possible view of the matter, the          G
            -Ir     court should not interfere with the award; (vii) It is not
                    permissible to a court to examine the correctness of the
                    findings of the arbitrator, as if it were sitting in appeal over
                    his findings. [Para 26] [280-C-G; 281-A-D]
                                                                                       H
    256   SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A        Tarapore & Co. vs. State of M.P. (1994) 3 SCC 521;
    Associated Engineering Co. vs. Govt. of A.P. (1991)4 SCC
    93; Mis Sudarsan Trading Co. vs. Gov~mment of Kera/a and
    Anr. (1989) 2 SCC 38; Managing Director, J&K Handicrafts,
    Jammu vs. Good Luck Carpets (1990) 4 SCC 740 - referred
B to.

       2.1. Insofar as booking of July-September, 1988                      r
                                                                       >-   '
  quarter by the respondent is concerned, it is an admitted
  position that the appellant-SAIL-declined the supply of
C materials on the ground of 'reasons beyond control'. The
  arbitrator in the award observed that SAIL has admitted
  that the demand was validly registered by the claimant; ..
  that material was available in abundance specially from
  domestic source and that supplies were made to others
  ignoring the claim of the respondent. The arbitrator held
0
  that the intimation of the SAIL to the claimant-respondent
  that the material will not be supplied to it cannot fall within
  the ambit of Clause 7.2. [Para 29] [282-D-F]

       2.2. It is well known that intention of the parties to an
E instrument has to be gathered from the terms thereof and
  that the contract must be construed having regard to the
  terms and conditions as well as nature thereof. Clause
  7.2 that provides for 1...ompensation to the respondent for
  failure to supply or delayed supply of the materials by
F SAIL was never intended to cover refusal to deliver the
  materials of the supplies on the part of the SAIL. Refusal
  to· supply i:naterials by SAIL resulting in breach is neither
  contemplated nor covered in Clause 7.2. There is no
  impediment I obstacle for the parties t~ a contract to
G make provision of liquidated damages for specific
                                                                    . '1-
  breaches only leaving other types of breaches to be dealt
  with as unliquidated damages. It can not be said that once
  the provision of liquidated damages has been made in
  the contract, in the event of breach by one of the parties,
H
                        STEEL AUTHORITY OF INDIA LTD. v. GUPTA            257
                             BROTHER STEEL TUBES LTD.
    ~-~            such clause has to be read covering all types of breaches     A
I

''                 although parties may not have intended and provided for
                   compensation in express terms for all types of breaches.
                   It is not a question of giving restrictive or wider meaning
                   to clause 7.2 but the question is what is intended by the
                   parties by making a provision such as this and does           B
                   such clause cover all situations of breaches by SAIL. A
           ~
                   careful consideration of clause 7.2 would show that it
                   does not prescribe compensation for every type of
                   breach. [Para 30 and 31) [283-A-F]
                                                                                 c
    ..,                 2.3. In substance and in form, the claim of damages
                    by the respondent for the breaches of contract by SAIL
                    is essentially distinct from the breaches contemplated by
                    Clause 7.2. In this back-drop, if the High Court observed
     '    --,,     that Clause 7.2 is not panacea of all ills, it cannot be said
                                                                                 D
                   that High Court fell into an error. Again, the view of the
                   arbitrator that breach due to refusal on the part of SAIL
                   to supply materials in July-September, 1988 quarter does
                   not fall within the ambit of relevant terms contained in the
                   compensation Clause (7.2), by no stretch of imagination
                                                                                 E
                   can be said to be an absurd view. The arbitrator's view
         ,,- ..l   about non-applicability of Clause 7.2 for refusal to supply
                   materials in July-Sep~ember, 1988 quarter and delayed
                   supply of materials for October-December, 1988 quarter
                   is founded on diverse grounds elaborately discussed in
                   the award. The view of the arbitrator being possible view
                                                                                 F
                   on construction of Clause 7.2, and having not been found
                   absurd or perverse or unreasonable by any of the three
                   courts, namely, Sub-Judge, District Judge and the High
                   Court, no case for interference is made out in exercise
                   of jurisdiction of this Court under Article 136 of the G
           --~
                   Constitution. Once the arbitrator has construed clause 7.2
                   in a particular manner, and such construction is not
                   absurd, but appears to be plausible, it is not open to the
                   courts to interfere with the award of the arbitrator. [Para
                   31 and 32] (283-G-H; 284-A-F]                                 H
    258   SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A      3.1. Legal position is no more res integra that the           l-'
  arbitrator having been made the final arbiter of resolution
  of disputes between the parties, the award is not open
  to challenge on the ground that arbitrator has reached at
  a wrong conclusion. The courts do not interfere with the
s co.nclusion of the arbitrator even with regard to
  construction of a contract, if it is a possible view of the
  matter. The words "no award shall be set aside" in s. 30
  mandate the courts not to set aside the award on the
  ground other than those specified in s. 30. In a case such
c as this, where the arbitrator has given elaborate reasons
  that compensation c.lause 7.2 is not attracted for the
  breaches for which the compensation has been claimed
  by the respondent and such view of the arbitrator is a
  possible view, in the circumstances award is not
                                                                   ~.
D amenable   to correction by the court. [Para 2:1 [284-F-H;
  285-A]

       3.2. The arbitrator having taken the view in respect
  of Clause 7.2 that claim of damages by the respondent
  of the breaches committed by the SAIL for refusal to
E supply materials in July-September, 1988 quarter and
  delayed supply of the materials for October-December,            j._   .,.

  1988 quarter did not fall within the a111bit of that clause,
  his further view that s. 74 of the Contract Act has no
  application as the contract does not determine damages ,
F for the breaches in question cannot be said to be legally
  flawed. It is true that s. 74 declares the law as to liability
  upon breach of contract where compensation is by
  agreement of the parties pre-determined. However, in the
  absence of any agreement specifying damages for the
G breaches alleged by the respondent, s. 74, in the facts and
                                                                   'f-
  circumstances, is not at all attracted. [Para 33] [285-B-D]

        Sir Chunilal V. Mehta & Sons Ltd. vs. Century Spinning
    and Manufacturing Co., Ltd. AIR 1962 SC 1314; Fateh Chand
H
        STEEL AUTHORITY OF INDIA LTD. v. GUPTA              259
             BROTHER STEEL TUBES LTD.
    vs. Balkishan Dass AIR 1963 SC 1405, held in applicable.       A

        Oil & Natural Gas Corporation Ltd. vs. Saw Pipes Ltd.
    (2003) 5 sec 705, referred to.

          4. The plea raised by the appellant before this Court
     that the arbitrator had no jurisdiction to enter the claim B
     preferred on 12.9.1991 by way of an application
     indicating quantification of claims, was not raised before
    the High Court. There has to be some sanctity and finality
    attached to the decision of the arbitrator and new plea
    cannot be allowed to be raised in an appeal under Article C
     136 which was not raised before the High Court. Even
    otherwise, it has been stated by the respondent in para
     18 that in view of non-availability of certain details which
    were in possession of the appellant and otherwise, the ·
     claimant reserved its right to add, amend and/or modify D
    the statement of claims. Consequently, the respondent
    quantified the claims, namely, 'A', 'AA' and 'AAA' by
    application dated 12.9.1991. Therefore, it cannot be said
    that by consideration of the claims as quantified by
    application dated 12.9.1991 the arbitrator exceeded his E
    jurisdiction. [Para 34 and 36] [285-E-H; 286-A-G]

        Rajasthan State Mines & Minerals Ltd. Vs. Eastern
    Engineering Enterprises & Anr. (1999) 9 SCC 283; Food
    Corporation of India vs. Chandu Construction & Anr. (2007)     F
    4 SCC 697; Steel Authority of India Ltd. vs. J.C. Budharaja,
    Government & Mining Contractor (1999) 8 SCC 122 and
    State of Jammu & Kashmir and_ Anr. vs. Dev Dutt Pandit
    (1999) 7 sec 339, relied on.

~        5. The courts below have concurrently held that the       G
    arbitrator has gone into the issues of facts thoroughly,
    applied his mind to the pleadings, evidence before him
    and the terms of the contract and then passed duly

                                                                   H
    260 SUPREME COURT REPORTS [2009) 14 (ADDL.) S.C.R.

                                                                     1---
A considered award and no ground for setting aside the
  award within the four corners of s.30 has been made out.
  [Para 38] [287-F-G]

                        Case Law Reference:
B       AIR 1962 SC 1314         held in applicable para 20
        AIR· 1963 SC 1405        held in applicable para 20
        (2003) s sec 705         referred to         para 20

c       (1994) 3 sec 521         referred to         para 20
        (1991) 4 sec 93          referred to ·       para 24
        (1989) 2 sec 38          referred to         para 24
                                                                    y--
        (1990) 4 sec 140         referred to         para 24
0
        (1999) 9 sec 283         relied on           para 37
        (2001) 4 sec 697         relied on           para 37
        (1999) 8 sec 122         relied on           para 37
E       (1999) 1 sec 339         relied on           para 37
                                                                    ~      ~
        CIVIL APPELLATE JURISDICTION : Civil Appeal No.
    5241 of 2002.

F       From the Judgment & Order dated 15.5.2001 of the High ·
    Court of Punjab & Haryana at Chandigarh in Civil Revision No.
    6132 of 1999.

        Jagdeep Dhankar, Sunil Kumar Jain, Ajay Kr. Bhatia,
    K.P.S. Chani for the Appellant.
G                                                                   't--
        Dr. A.M. Singhvi, Varun Goswa~i. R.C. Kaushik for the
    Respondent.

        The Judgment of the Court was delivered by
H
              STEEL AUTHORITY OF INDIA LTD. v. GUPTA                261
                   BROTHER STEEL TUBES LTD .
.,__ \        R.M. LODHA, J. 1. Steel Authority of India Ltd. (SAIL) has - A
         preferred this appeal by special- leave aggrieved by the
         judgment of High Court of Punjab and Haryana passed on May
         15, 2001 whereby the learned Single Judge dismissed Revision
         Petition preferred by the present appellant against the judgment
         dated September 1, 1999 passed by District Judge, B
         Chandigarh affirming· the judgment and order dated May 9,
         1994 passed by the Court of Sub-Judge, 1st Class, Chandigarh
  4      dismissing the objections preferred by the present appellant
         under Sections 30/33 of the Indian Arbitration Act, 1940 and
         the award dated September 7, 1993 given by the sole arbitrator    c
         was made rule of the Court.

            2. Brief narration of facts is necessary before we embark
       upon the contentions raised on behalf of the appellant. On April
--..,- 18, 1988, SAIL formulated a scheme entitled "Full Requirement       D
       Supply Scheme" (for short, 'the Scheme'). The said scheme is
       said to have been designed for meeting the full requirements
       of HR Coils/Skolps to the customers. Those who wanted to
       avail the said material as per the scheme were required to
       register the requirements with SAIL. The scheme further
       stipulated that those who wanted material over and above what       E
       was likely to be available from indigenous sources and were
~ ~, willing to accept imported HR Coils were required to register
       the requirements separately. The scheme was in operation in
       respect of two quarters, namely, (i) July to September, 1988
       and (ii) October to December, 1988.                                 F

          3. The case of the respondent is that pursuant to the terms
     of said scheme, they submitted an application for 1500 metric
     tones of imported material for the first quarter(July to
     September, 1988). It is also their case that they furnished the       G
 --r financial cover in terms of the said scheme.

              4. On September 15, 1988, SAIL informed their inability
         to arrange for the import against the indent for reasons beyond
         its control.
                                                                           H
    262    SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A         5. The respondent, thereafter, indented for supply of 1500
                                                                             ~   -
    metric tonnes . of imported. material for the second quarter
                                                               '·

    (October to December, 1988). The indent was accepted by .
    SAi~. The respondent furnished securities in terms of bank
    guarantee in lieu of irrevocable letter of credit and took physical
B   delivery of the goods on March 7, 1989 and made payment for
    the same on February 15, 1989.

          6. It appears that dispute/differences arose between the
    parties and.the respondent lodged its claim to the appointing
    authority on March 11, 1989. Initially, one Shri K. Janardhana
c   was appointed as Arbitrator but he resigned later on and in his
    place Shri K.P. Bhaumik was appointed arbitrator.

         7. It may be noticed here that an application was made
    by the respondent before the arbitrator on September 12, 1991
                                                                           y-
D for quantification of claims under the heads 'A', 'AA' and 'AAA'
  and thereby they made a total claim of Rs. 1, 75,41,359/-
  alongwith interest @ 21 per cent against SAIL before the
  arbitrator.

E         8. The claimant - respondent in support of its claim
    produced oral as well as documentary evidence. In opposition,
    SAIL also produced oral as well as documentary evidence                ;__
    before the arbitrator.

     . 9. The arbitrator seems to have .had fifty sittings and after
F hearing the parties and taking into consideration the
    documentary as well as oral evidence passed an award on
    September 7, 1993. The award runs into almost 290 foolscap
    pages.

G         10. The objections to the award were filed by SAIL before
    Sub-Judge, 1st Class, Chandigarh raising diverse grounds, inter
                                                                           't-
    alia; that the arbitrator was biased in favour of the claimant; that
    he committed a jurisdictional error in adjudication of claims for
    the period from July to September, 1988 and granting claim in
H
                 STEEL AUTHORITY OF INDIA LTD. v. GUPTA                   263
               BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
 ;,._ 4      this regard when there was no pre-existing dispute; that the         A
-i           arbitrator entertained claim in respect of future disputes i.e.
 ~           disputes not existing at the time of reference; that he went into
             constitutional questions such as discrimination, etc. which he
             had no jurisdiction to decide; that he ignored the terms of
             contract and returned the findings contrary to the express terms     B
             thereof; that the arbitrator failed to call for material documents
             and gave the award which is perverse and based on no
       ""'   evidence and that he committed jurisdictional error by ignoring
             the express term of the contract, particularly Clause 7 .2 and the
             provisions of the Contract Act.                                      c
-...               11. The Sub-Judge, 1st Class, Chandigarh, after hearing
             the parties overruled the objections raised by SAIL and made
             the award rule of the Court on May 9, 1994. The Sub-Judge,
 . --"T      1st Class, Chandigarh directed that claimant shall be entitled
             to interest @ 12% per annum from the date of the judgment            D
             until realization.
                   12. SAIL challenged the judgment and order dated May
             9, 1994 passed by the Sub-Judge, 1st Class, Chandigarh by
             filing an appeal before the District Judge, Chandigarh who by        E
             its decision dated September 1, 1999 dismissed the appeal.
 '   ,, -·     13. SAIL preferred revision petition before the High Court
          of Punjab & Haryana against the aforesaid decisions. It is
          pertinent to notice here that before the High Court on behalf of
                                                                             F
          SAIL, two contentions were raised, namely, (i) that the arbitrator
          had committed error of jurisdiction when he entered a time
          barred claim and (ii) that the Arbitrator had awarded damages
          to the claimant under category 'A', 'AA' and 'C' by exercising
          his power beyond Clause 7.2 of the agreement. It was thus
                                                                             G
          submitted that the arbitrator committed misconduct by going
       -f
          beyond the terms of the contract (7.2) and violating the
          provisions of the Contract Act.

                  14. The High Court was not persuaded by the two
                                                                                  H
    264 SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A   submissions made on behalf of the SAIL and dismissed Civil               ~
    Revision Petition on May 15, 2001 ..

          15. It is appropriate at this stage to reproduce the
    arbitration clause in the agreement and Clause 7.2. which is
    material for deciding this appeal.
B
                        "ARBITRATION CLAUSE:

         (i) In the event of any question, dispute or difference arising
        under the conditions referred to above or any special
c        conditions or Contract or in connection with this Contract
         (except as to any matters, the decision of which is
        specifically provided for in the conditions referred to above
        or the special conditions) the same shall be referred to the
        Sole Arbitration of the Chief Executive (by whatever name          ,,,_
0       he may be designated at the relevant time) of the Central
        Marketing Organisation, Steel Authority of India Ltd. (CMO/
        SAIL) for short) or his nominee. It will be no objection that
        the Arbitrator is a company's (CMO/SAIL) employee and/
        or that he had to deal with the matters to which the
        Contract relates or that in the course of his duties as a
E
        company's employees, he has expressed views on all or
        any of the matters in dispute or difference. The award of          ;_
        the Arbitrator shall be find and binding on the parties to
        this contract.
F       (ii)· in the event of the Arbitrator dying, neglecting or
        refusing to act or resigning or being unable to act for any
        reason or his award being set aside by the court for any
        reason, it shall be lawful for the Chief Executive of the
        Central Marketing Organisation, Steel. Authority of India
G       Ltd. to adopt/nominate another arbitrator in place of the
        outgoing arbitrator in the manner aforesaid.

       (iii) It is further a term of his contract that no person other
       than the Chief Executive of the Central Marketing
H
          STEEL AUTHORITY OF INDIA LTD. v. GUPTA                  265
        BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]

- ~      Organisation, Steel Authority of India Ltd. or his nominee       A
         as aforesaid, shall act as Arbitrator and that, if for any
         reason that is not possible, the Chief Executive of the
         Central Marketing Organisation, Steel Authority of India
         Ltd. shall have the right to nominate/appoint another person
         as second Arbitrator and if the second Arbitrator also fails     B
         to arbitrate for any reason, what so ever the matter is not
         to be referred to Arbitration to all.
 ~
         (iv) The arbitrator may from time to time, with the consent
         of all the parties to the contract enlarge the time for making   c
         the award.

         (v) Upon every and any such reference, the assessment
         of costs incidental to the reference and award respectively
_..,,    shall be in the discretion of the Arbitrator.
                                                                          D
         (vi) Subject as aforesaid, the Arbitration Act, 1940 and the
         Rules thereunder and any statutory modifications thereof,
         for the time being proceedings under this clause.

         ·(vii) If the value of the claim in a reference exceeds Rs.1
                                                                          E
          lakh, the Arbitrator shall give reasoned award.

         (viii) The value of Arbitration shall be the place where the
         contract was concluded or at Calcutta, being the
         headquarters of the Central Marketing Organization, as it
         may be fixed by the Arbitrator at his discretion and the         F
         place so fixed by the Arbitrator shall be final and binding
         upon the parties to the contract.

         (ix) In this clause, the expression, the Chief Executive of
         the Central Marketing Organisation, Steel Authority of India     G
         Ltd. means the Chief Executive of the Central Marketing
         Organization (by whatever name he may be designated at
         the relevant time) for the time being and includes, if there
         be no Chief Executive, or the Chief Executive is on leave
         or he i~ absent from duty or is not available for any reason     H
    266     SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A         whatsoever, the officer looking after the duties of the Chief
          Executive of the Central Marketing Organisation whether
                                                                          .     -"'--


          in addition to his other "functions or otherwise".

          Clause 7.2
B         "SAIL shall supply materials as described in the offer/work
          order(s)/Delivery order(s) issued by SAIL from time to time.
          SAIL, however, shall have a· period of one month after          ,._
          expiry of the indicated quarter/quarters as grace period for
          the purpose of supply or supplies. In the event of SAIL's
c         failure(s) to deliver the indicated quantities even after the
          expiry of the grace period, SAIL shall pay to the                        (-
          customer(s) compensation @0.25% (quarter per cent) per
          month or part thereof on the value of the materials of the
          supplies delayed -beyond the quarter/quarters plus the          '(-
D         grace period(s) subject to a maximum of 3% (three per                   'l

          cent ) of the value of the delayed supplies. The value for
          this purpose shall be worked out on the same basis as
          mentioned in note (iii) to para 3.1 regarding caiculation of
          Initial Financial Cover. The aforesaid compensation shall
E         be paid within th:-c2 1,-jonths from the date of completion
          of order. In case an order is not executed within 12 months
          from the expiry date of the grace period, the order would       ~       ...
          be treated as closed after payment of applicable
          compensation, if and as due. Delay(s) caused in effecting
F         supplies on account of or all of the force majuere
          conditions and/or on account of the failure/non-observance                '
          of the required formalities by the customer(s) shall be
          accepted the SAIL shall not bear any liability for such
          period(s)."
G
        16. With regard to the question relating to Clause 7.2 of
    General Terms and Conditions of the Contract, the arbitrator
    considered the matter thus:

          "19.14 I .have given my .careful consideration to the
H
                  STEEL AUTHORITY OF INDIA LTD. v. GUPTA                 267
                BROTHER STEEL TUf?ES LTD. [R. M. LODHA, J.]
                  arguments of the counsels for the parties. I find that the     A
--- ~             compensation was to be paid by the Respondent within a
                  period of three months from the date of completion of the
                  transaction. In case the order is not executed within 12
                  months from the expiry of the grace period, the same was
                  treated as closed after payment of compensation as due.        B
                  It is proved on record that no supply was made for July-
                  September 1988 quarter against the duly registered indent
                  demand placed by the claimant and within 15 days of the
     '~
                  beginning of the quarter itself i.e. 15. 7.1988; the
                  Respondent intimated that the material will not be supplied    c
                  to the claimant. The case, therefore, cannot fall within the
                  ambit of the relevant terms contained in the compensation
                  Clause reproduced above whereby, in case the order is
                  not executed within 12 months .after the expiry of the grace
 _..,.            period the same was to be treated as closed and that too
                                                                                 D
                  after payment of applicable compensation. Neither, it is a
                  case of delayed supply (for July September 1988
                  quarter's booked).

                  19.15 In the instant case e-ven otherwise, in this Clause is
                  to be brought into play the cut off date would be 30th         E
                  October, 1989 (i.e. July-September 1988 + one month
                  grace period (October 1988) + 12 months i.e. upto 30th
 -        .i.
                  October, 1989 i.e. to say that after 30th October, 1989 in
                  the event of non-supply, the order was to be treated as
                  closed, but that too after the payment of applicable           F
                  compensation i.e. 3%, as limited under Clause 7.2. In the
                  instant case what has happened that on 15th July, 1988
                  itself the Respondent regretted inability to supply the
                  material (vide C-5, C-7 and C-9) despite confirmed and
                  duly registered demand (C-3) by the claimant. No               G
                  reference of any compensation Clause (7.2) was made
                  nor any cheque for the amount of compensation at the
                  given rate was sent nor the account of claimant was
                 .credited with the amount as per Clause 7.2. ObviouslyJhe
                                                                                 H
    268     SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A         case is a case of deliberate act of non-supply as 'reasons'
          beyond control as intimated in C-5, C-7 and C-9 have not
          been proved by the Respondent, inspite of rigorous cross-
          examination by the claimant's advocate and more than the~
          ample time and opportunity, at the disposal of the
B         Respondent. What has been contemplated in the
          compensation Clause is where the force majuere Clause
          is not invoked, there is complete lull or silence on the part
          of the parties and a period of 12 months expires after the
          expiry of grace period. In the instant case even the said
c         date would have been 30. 10.1989 and even then the
          Respondent should/must have paid the compensation as
          stipulated if they wanted to bring the case within the ambit
          of Clause 7 .2, only thereafter the liability of Respondent
          would have extinguished.
D         19.16. There is thus, substance in the contention of the
          claimant that the compensation Clause as discussed
          hereinabove cannot be made applicable in the fact and
          circumstances duly proved on record. The alternate
          argument of the Claimant regarding unconscionability of
E         the contract/partlcillar term thereof vis-a-vis the present
          Clause 7.2 and relying on AIR 1986 SC 1571 need not
          be gone into. Under issue No.15, I have attempted to set
          out various clauses of document C-2, including the present
          Clause and giving a finding that the Scheme C-2 is in
F         favour of the Respondent,- but since the findings under the
          present issues are that the Clause, even otherwise, is not
          applicable in the case of non-supply of material for July-
          September, 1988 quarter I leave the matter to rest without
          going into the question of unconscionability."
G
         17. The Sub-Judge, 1st Class, Chandigarh while dealing
    with the objections of the appellant with regard to Clause 7 .2 ·
    considered the matter thus:

          "Sf If the above observations of the arbitrator are read
H
               STEEL AUTHORITY OF INDIA LTD. v. GUPTA                 269
             BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
"'- ~          carefully it would become clear that he never out stepped A
               the confines of the contract, he has remained inside the
               parameters of the contract and has construed the clause
               7.2 thereof. If he has committed any error in the
               construction of the contract, that is an error within his            i




              jurisdiction. Therefore, the authority of law in Associated B
               Engineering Co. vs. Government of Andhra Pradesh
      :J.      (ibid) is of no help to the objector. In that case the error
               had arisen not by mis-reading or mis-construing or by mis-
               understanding the contract but by acting contrary of what
               was agreed. In that case the arbitrator had traveled outside · c
               the permissible territory not by construction of the contract
               but by merely looking at the same. It was held by Hon'ble
               Supreme Court that if the arbitrator remained inside the

·-     ')-
               parameters of the contract and has construed the
               provisions of the contract, his award be interfered with : D
               unless he has given reasons for the award disclosing an
              error apparent on the fact of it. In the present case the
              arbitrator has reached the conclusion by interacting the
              contract. The conclusion cannot be termed as conscious
              disregard of the law or the provisions of the contract. The E
..            findings of the arbitrator that clause 7.2 of the scheme is
                                                                                I




       ~
              not applicable on the facts and circumstances of the case
              is not perverse but based on reasoning. Similarly there is
              no error apparent on the face of record which would vitiate
              the award. In Sudarsan Trading Co. vs. Government of F
              Kera/a And Anr., AIR 1989 SC 890 (ibid) it was held that          1




              if on a view taken of a contract, the decision of the
              arbitrator on certain amounts awarded is a possible view
              though perhaps not the only correct view, the award cannot
              be examined by the court and that the court has no G
 .   ""(
              jurisdiction to substitute its own evaluation of the          I




              conclusions of law or fact to come to the conclusion that
              the arbitrator had acted contrary to the bargain between
              the parties. It was further held that by purporting to construe
              the contract the court cannot take upon itself the burden
                                                                              H
    270     SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.

                                                                            f.
A         of saying that this was contrary to the contract. Therefore,
          there is no substance in the contention of the objector that
          the arbitrator has exceeded his jurisdiction by traveling .
          outside the bounds of the contract and by ignoring clause
          7.2 of the terms and conditions.
8
          52. The next objection of the objector is that the arbitrator
           not only ignored the provisions of Clause 7.2 of the contract    ).
          but he also ignored the provisions of Section 74 of the
          Contract Act wherein it has been specified that if' a sum
           named in the contract is the amount to be paid in case of
c          breach, or if the contract conditions any other stipulation
          by way of penalty, the party complaining of the Qreach is
          only entitled to receive from the party who has broken the
          contract a reasonable compensation not exceeding the             --('~


          amount so named. Learned counsel argued that the
D
          arbitrator knowingly went against this provision of law. He
          further argued that in Sir Chuni Lal V. Mehta & Sons vs.
           Century Spinning and Manufacturing Co. AIR 1962 SC
           1314, ,the Apex Court has held that where the parties have
          deliberately specified the amount of liquidated damages,
E         there can be no presumption that they at the same time
          intends to allow the party who had suffered by the breach
          to say good bye to the sums specified and claim instead
          a sum of money which was not ascertained at the date of
          breach. Learned counsel further argued that the arbitrator
F         proceeded contrary to the settled principle of law that
          damages for breach of contract by seller by failure to
          deliver goods are confined to the difference between the
          contract price of the goods and the market price of the
          goods if the same are available in the market. Learned
G         counsel pointed out that in the present case the claimant          r
          has specifically admitted that the goods were available in
          the market. It was, therefore, the duty of the claimant to
          purchase the said goods from the market and the SAIL
          could have only been made liable for the difference if any
H
                       STEEL AUTHORITY OF INDIA LTD. v. GUPTA                  271
 j
                     BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
~--+                    between the contractual price and market price.                A

                       53. To my mind, in view of my above finding, there is no
                       substance in the contention of the objector that the
                       arbitrator ignored the provisions of Section 74 of the
                       Contract Act. Once the arbitrator held that clause 7 .2 of
                                                                                       ~
                       the Contract was not applicable on the facts and
                       circumstances, there can be no question of any liquidated
                       damages. Resultantly it cannot be said that provisions of
          --           Section 74 of the Contract Act have been ignored. The
                       authority of law in Chuni Lal V. Mehta (ibid) would have
                       been applicable only if it was held that clause 7.2 of the
                                                                                       c
  ,,
                       Contract was applicable. In Hindustan Tea Co. vs. Mis K.
                       Shashikant & Co. AIR 1987 SC 81, it was held that where
                       a reasoned award is challenged on the ground that the
        ,,. 't-
                       arbitrator acted contrary to the provisions of Section 70 of
                                                                                       D
                       the Contract Act, it would be not ground for settling aside
                       the award. On the same analogy, even if the contention of
                       the objector is accepted, the present award cannot be set
                       aside merely on the ground that the arbitrator acted
                       contrary to the provisions of Section 74 of the Contract Act.
                       In the similar way the contention that the provisions of Sale   E

__.._
     ..     _..,       of Goods Act were not followed is also devoid of any merit
                       because the arbitrator gave due weight to the respective
                       contention of the parties and reached the conclusion which
                       cannot be termed as absurd."
                                                                                       F
                         18. When the matter came to the District Judge in appeal,
                   he after taking into consideration the findings recorded by the
                   arbitrator and the Sub-Judge, 1st Class, Chandigarh, recorded
                   his findings:
                                                                                       G
        ..-~1          "18. On careful reading of these observations of the
                       arbitrator, it would be clear that he never outstepped the
                       parameters of the contract. He remained inside the
                       Laxman Rekha of the contract and construed clause 7.2
                       thereof in a reasonable manner. If he has committed any
                                                                                       H
    272    SUPREME COURT REPORTS (2009] 14 (ADDL.) S.C.R.


A       error in the construction of the contract, it was error within
        his jurisdiction. Therefore, the authority reported as AIR
        1992 SC 232 Associated Engineering Co. vs.
        Government of Andhra Pradesh does not help the
        Appellant. In that case, the error had arisen not by mis-
B       reading or misconstruing or misunderstanding the contract,
        but by acting contrary to what was agreed. In that case,
        the arbitrator had traveled outside the permissible territory
        not by construction of the contract but by merely looking
        at the same. So ft was held by Hon'ble Supreme Court that
c       if the arbitrator remained inside the parameters of the
      , contract, and has construed the provisions of the contr.act,
        his award cannot be interfered with, unless he has given
        reasons for the award disclosing an error apparent on the
        face of it. In the present case, the arbitrator does not
                                                                           t
D       appear to have showed any conscious disregard of the law
        or the provisions of the contract. So the findings of the
        arbitrator that the provisions of clause 7 .2 of the scheme
        are not applicable to lhe facts and circumstances of the
        present case, cannot be said to be perverse. These are
E       manifestly based on sound reasoning which cannot be said
        to be perverse. Surely there is no error apparent on the
        face of the record.

          19. In AIR 1989 SC 890 Sudarsan Trading Co vs.
          Government of Kera/a, it inter-alia ruled that if on a view
F         taken of a contract, the decision of the arbitrator on certain
          amounts awarded is a possible view though perhaps not
          the bnly correct view, then the award cannot be examined
          by the Court, and the Court has got no jurisdiction to
          substitute its oWn evaluation of the conclusion of law or fact
G         to come to the conclusion that the arbitrator had acted
          contrary to the bargain between the parties. It was further
          ruled ibid that by purporting to construe the contract, the
          Court cannot take upon itself the burden of saying that this
          was contrary to the contract. So the learned trial Court was
H
                       STEEL AUTHORITY OF INDIA LTD. v. GUPTA                 273
                     BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
.... _.               justified in holding that the arbitrator had not exceeded his   A
                      jurisdiction, nor he had traveled outside the bounds of the
                      contract while interpreting clause 7.2 of the scheme.

                      20. Surely the quantum of damages is closely inter-related
                      with the interpretation of clause 7.2 of the scheme. But as     B
                      demonstrated above, the arbitrator concluded, and not
                      perversely or unreasonably, that clause 7.2 of the scheme
            ~         was not applicable to the facts of the case in hand.
                      Therefore, it proceeded to examine the question of
                      damages in paras 52 and 53 of the impugned judgment.            c
                      21. The contention of the learned counsel for the appellant
                      is that not only has the arbitrator ignored the provisions of
                      clause 7 .2 of the contract, but he had also ignored the
       ,,. 't'        provisions of section 74 of the Contract Act wherein it has
                      been stipulated that if a sum named in the contract is the D
                      amount to be paid in case of breach, or if the contract
                      conditions or any other stipulation by way of penalty, the
                      party complaining of the breach is only entitled to receive
                      from the party who has broken the contract, a reasonable
                      compensation not exceeding the amount so named. It is E
                      submitted by the Id. Counsel for the appellant that the
  ,...,.
                "'    arbitrator intentionally and knowingly went against the
                      provisions of Section 74 of the Contract Act. Ld. Counsel
                      for the appellant has also relied on AIR 1962 SC 1314 Sir
                      Chuni Lal V. Mehta & Sons vs. Century Spinning and F
                      Manufacturing co. where it was inter-alia held that where
                      the parties had deliberately specified the amount of
                      liquidated damages, there can be no presumption that
                      they at the same time intended to allow the party who had
                      suffered by the breach to say good-bye to the .sums G
           ,.,.'i     specified and claim instead a sum of money which was
                      not ascertained at the date of breach. He has further
                      contended that the arbitrator proceeded contrary to the
                      settled principle of law that damages for breach of contract·
                                                                                    H
                          STEEL AUTHORITY OF INDIA LTD. v. GUPTA                     275
                        BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
----I' .,, •
                                  "Thus, a reading of the above clause which has been        A
   ·1·                     relied upon by the learned counsel for the petitioner, makes
                           it abundantly clear that this clause has only covered one
                           exigency regarding the delivery or non-delivery or late
                          delivery of the goods. This clause gives power to the
                          Arbitrator to award compensation starting from 0.25% to            B
                          the upper limit of 2.01 %. This clause never debars the
               '"'        Arbitrator from entertaining the contract and consequential
                          losses which had been suffered by the respondent on
                          account of non-delivery or late delivery of the goods. If on

     ...
                          account of the act of the petitioner, the respondent-firm had      c
                          suffered huge losses to itself for the benefit of its customers,
_,                        certainly it has a right to recover the same. Be that as it
    ...                   may, I am not to.look at the merits of the case but I have
          ,.    ~         to examine whether the Arbitrator had exceeded beyond
                          the realm of arbitration clause or clauses of the contract.        D
                           If he had not, the civil court will not impose its impression/
                          judgment or opinion over the opinion of the arbitrator, but
                          I had already held thatthe Arbitrator is the master of facts
                          as well as of law. Even his erroneous interpretation of the
                          contract so long as he acts within the contract, is not
                                                                                             E
   ,,..-
                          supposed to be interfered by the civil court much less by
                 "'       the High Court, in the exercise of its revisional jurisdiction."

                           20. Mr. Jagdeep, Dhankar, learned senior Counsel for tile
                      appellant urged that the stipulation in Clause 7 .2 is in
                      consonance with Section 74 of the Indian Contract Act 1872             F
                      and in that clause compensation is provided in respect of
                      supplies made beyond specified period; that the said clause
                      provides for maximum cap of liquidated damages by way of
                      compensation "to a maximum of three per cent of the value of
                      the delayed supplies" and that Clause 7.2 is a complete answer         G
 -(~
                      to any breach of the contract for whatsoever reason and,
                      therefore, under no situation the quantum of damages can
                      exceed the stipulation in the liquidated damages clause. The
                      learned senior Counsel would, thus, urge that the arbitrator
                      exceeded his jurisdiction m disregarding well settled principle        H
    276     SUPREME COURT REPORTS (2009) 14 (ADDL.) S.C.R.


A that where the contract incorporates liquidated damages                           I.,,.'\

  clause, for breach of contract under no circumstances the
  quantum of damages be awarded in excess of the cap                                         "
  provided therein. He strongly relied upon two Constitution Bench
  decisions of this Court in the case of Sir Chunilal V. Mehta &
                                                                  1
B Sons Ltd. vs. Century Spinning and Manufacturing Co., Ltd.
  and Fateh Chand vs. Balkishan Dass2. He also relied upon
  decisions of this Court in Oil & Natural Gas Corporation Ltd.
  vs. Saw Pipes LtcP. and Tarapore & Co~ vs. State of M.P. 4 •

          21. In Chuni/al V. Mehta & Sons, the Constitution Bench
c considered Section 74 of the Contract Act and held that right
  to claim liquidated damages is enforceable under Section 74                            ....
  of the Contract Act and where such a right is f9und to exist, no
  question of ascertaining damages really arises. It was held that
                                                                                        ' ,,
  where parties have deliberately specified the amount of                         -f .....
D liquidated damages there can be no pre:sumption that they, at
  the same time, intended to allow the party who has suffered by
  the breach to give a go-by to the sum specified and claim
  instead a sum of money which was not ascertained or
  ascertainable at the date of the breach. While construing
E Clause 14 therein, the Court held that by providing for
  compensation in express terms, the right to claim damages
                                                                                  )<.    .....
  under the general law is necessarily excluded.

       22. Section 74 of the Indian Contract Act fell for
F consideration before the Constitution Bench again in the case
  of Fateh Chand. The Constitution Bench held thus:

          "8 ..................................................................

          The Section is clearly an attempt to eliminate the sometime

                                                                                  ~\
G
    1.   AIR 1962 SC 1314.
    2.   AIR 1963 SC 1405.
    3. , (2003) 5 sec 705.
    4.   (1994) 3-SCC 521
H
         STEEL AUTHORITY OF INDIA LTD. v. GUPTA                               277
       BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]

        elaborate refinements made under the English common                            A
        law in distinguishing between stipulations providing for
        payment of liquidated damages and stipulations in the
        nature of penalty. Under the common law a genuine pre-
        estimate of damages by .mutual agreement is regarded as
        a stipulation naming liquidated damages and binding                            B
        between the parties: a stipulation in a contract in terrorem
)..     is a penalty and the Court refuses to enforce it, awarding
        to the aggrieved party only reasonable compensation. The
        Indian Legislature has sought to cut across the web of rules
        and presumptions .under the English common law, by                             c
        enacting a uniform principle applicable to all stipulations
        naming amounts to be paid in case of breach, and
                                                 -
        stipulations by way of penalty.

        9 ..........................................................................
                                                                                       D
         10. Section 74 of the Indian Contract Act deals with the
        measure of damages in two classes of cases (1) where the
        contract names a sum to be paid in case of breach and
        (ii) where the contract contains any other stipulation by way
        of penalty. We are in the present case not concerned to                        E
        decide whether a contract containing a covenant of
        forfeiture of deposit for due performance of a contract falls
        within the first class. The measure of damages in the case
        of breach of a stipulation by way of penalty is by Section
        74 reasonable compensation not exceeding the penalty                           F
        stipulated for. In assessing damages the Court has, subject
        to the limit of the penalty stipulated, jurisdiction to award
        such compensation as it deems reasonable having regard
        to all the circumstances of the case. Jurisdiction of the
        Court to award compensation in case of breach of contract                      G
 ~-{
        is unqualified except as to the maximum stipulated; but
        compensation has. to be reasonable, and that imposes
        upon the Court duty to award compensation according to
        settled principles. The section undoubtedly says that the
                                                                                       H
    278     SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.

                 .
A         aggrieved party is entitled to receive compensation from           •
          the party who has broken the contract, whether or not actual
          damage or loss is proved to have been caused by the
          breach. Thereby it merely dispenses with proof of "actual
          loss or damage"; it does not justify the award of
B         compensation when in consequence of the breach no
          legal injury at all has resulted, because co.mpensation for
          breach of contract can be awarded to make good loss or
          damage which naturally arose in the usual course of things,
          or which the parties knew when they made the contract,
c         to be likely to result from the breach.

        11. Before turning to the question about the compensation
        which may be awarded to the plaintiff, it is necessary to
      ··~onsider whether Section 74 applies to stipulations for
        forfeiture of amounts deposited or paid under the contract.      .of
D
        It was urged that the section deals in terms with the right
        to receive from the party who has broken the contract
        reasonable compensation and not the right to forfeit what
        has already been received by the party aggrieved. There
        is however, no warrant for the assumption made by some
E    · ofthe High Courts in India, that Section 74 applies only to
       cases where the, aggrieved party is seeking to receive
       some amount on breach of contract and not to cases
       where upon breach of contract an amount received under
       the contract is sought to be forfeited. In our judgment the
F      expression "the contract contains any other stipulation by
       way of penalty" comprehensively applies to every covenant
       involving-a penalty whether it is for payment on breach of
       contract of money or delivery of property in future, or for
       forfeiture of right to money or other property already            ,
G      delivered. Duty not to enforce the penalty_clause but only        I
       to award reasonable compensation is statutorily imposed           '>
       upon courts by Section 74. In all cas.es, therefore, where
       there is a stipulation in the nature of penalty for forfeiture
       of an amount deposited. pursuant to the terms of contract
H
          STEEL AUTHORITY OF INDIA LTD. v. GUPTA                  279
        BROTHER STEEL ~USES LTD. [R. M. LODHA, J.]
...       which expressly provides for forfeiture, the court has         A
          jurisdiction to award such sum only as it considers
          reasonable, but not exceeding the amount specified in the
          contract as liable to forfeiture ...... n

            23. In Oil and Natural Gas Corporation Ltd., while dealing   8
      with the aspects of liquidated damages, this Court considered
      the aforesa'd Constitution Bench decisions in Chuni Lal V.
      Mehta & Sons and Fateh Chand and after reference to
      relevant parts of Sections 73 and 74 of the Contract Act held
      thus:
                                                                         c
          "46. From the aforesaid sections, it can be held that when
          a contract has been broken, the party who suffers by such
          breach is entitled to receive compensation for any loss
          which naturally arises in the usual course of things from
          such breach. These sections further contemplate that if D
          parties knew when they made the contract that a particular
          loss is likely to result from such breach, they can agree for
          payment of such compensation. In such a case, there may
          not be any necessity of leading evidence for proving
          damages, unless the court arrives at the conclusion that E
          no loss is likely to occur because of such breach. Further,
          in case where the court arrives at the conclusion that the
          term contemplating damages is by way of penalty, the court
          may grant reasonable compensation not exceeding the
          amount so named in the contract on proof of damages. F
          However, when the terms of the contract are clear and
          unambiguous then its meaning is to be gathered only from
          the words used therein. In a case where agreement is
          executed by experts in the field, it would be difficult to hold
          that .the intention of the parties was different from the G
          language used therein. In such a case, it is for the party.
          who contends that stipulated amount is not reasonable
          compensation, to prove the same."

          24. In Tarapore & Co., a two Judge Bench of this Court         H
    280     SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.
                                                                                         ....
A considered few decisions of this Court including the decisions                { -+ . . .
  in.the.case of Mis Sudarsan Trading Co. vs. Government of
  Kera/a and Anr°., Associated Engineering Co. vs. Govt. of                              -...
  A.P. 6 and Managing Director, J&K Handicrafts, Jammu vs.
  Good Luck Carpets7 and held that where an arbitrator travels
B beyond a contract,- the award would be without jurisdiction and
  the same would amount to misconduct and such award would
  become amenable for being set aside by a Court.
                                                                                ~


         25. In Sudarsan Trading Co., this Court held that an error
    by the arbitrator relatable to interpretation of the contract is not
c   amenable_ to correction by courts.
                                                                                    ~


          26. It is not necessary to multiply the references. Suffice it             ......
    to say that the legal position that emerges from the decisions
    of this Court can be summarised thus:                                      -f   -~

D
          (i) In a case where an arbitrator travels beyond the contract,
          the award would be without jurisdiction and would amount
          to legal misconduct and because of which the award would
          become amenable for being set aside by a Court
E
          (ii) An error relatable to interpretation of the contract by an
          arbitrator is an error within his jurisdiction and such error        ... ,.
          is not amenable to correction by Courts as such error is
          not an error on the face of the award.

F         (iii) If a specific question of law is submitted to the arbitrator
          and he answers it, the fact that the answer involves an
          erroneous decision in point of law does not make the
          award bad on its face.

G         (iv) An award contrary to substantive provision of law or
                                                                               \
                                                                                }__.,_____


    5.   (1989) 2 sec 38.
    a.   (1991) 4 sec 93.
H 7.     (1990) 4 sec 740. -
                         STEEL AUTHORITY OF INDIA LTD. v. GUPTA                    281
                       BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]
~, ...ari.   •
                         against the terms of contract would be patently illegal.          A

                         (v) Where the parties have deliberately ,specified the
                         amount of compensation in express terms, ~he party who
                         has suffered by such breach can only cl~im the sum
                         specified in the contract and not in excess therepf. In other     B
                         words, no award of compensation in case of breach of
                         contract, if named or specified in the contract, could be
                         awarded in excess thereof.

                         (vi) If the conclusion of the arbitrator is based on a possible
                         view of the matter, the court should not interfere with the       c
                         award.

                         (vii) It is not permissible to a court to examine the
                         correctness of the findings of the arbitrator, as if it were
     .I' ."
                         sitting in appeal over his findings.                              D
                          27. Having noticed the legal position, we now tum to Clause
                     7.2 which can be analysed thus:

                         (i) SAIL shall supply materials as described in the offer/
                         work order(s)/delivery order(s) issued from time to time.         E
                 ~       (ii) SAIL shall have a period of one month as grace period
      ~
                         for the purpose of supply or supplies after expiry of the
                         indicated quarter(s).
                                                                                           F
                         (iii) S"'IL shall pay to the customer(s) compensation @
                         0.25 per cent per month or part thereof on the value of the
                         materials of the supplies in the event of its failure(s) to
                         deliver the indicated quantity e\(en after the expiry of the
         __      ,       grace period subject to maximum of three per cent of the
                         value of the delayed supplies.
                                                                                           G

                         (iv) The compensation shall be paid within three months
                         from the date of completion of order.

                         (v) In case the order is not executed within 12 months from       H
    282     SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.

                                                                            ,_ .........
A       . the expiry of grace period, the order would be treated as
          closed after payment of applicable compensation.

          (vi) SAIL shall not bear any liability for such period where
          delay caused in effect of supplies is on account of failure/.
B         non-observance of the required formalities by the
          customer.

            28. The question that needs to be determined by us is
      whether the breaches alleged by the respondent are covered
      by the stipulations contained in Clause 7.2. If the answer is in
c     affirmative, obviously compensation cannot be awarded
      beyond what is provided th~rein. On the other hand, if breaches
      are not covered by clause 7.2, cap provided therein with regard
    . to liquidated damages will not be applicable at all.
                                                                          -f ....__
D       29. Insofar as booking of July-September, 1988 quarter
  by the respondent is concerned, it is an admitted position that
  the appellant (SAIL) declined the supply of materials i.e. 1500MT
  of 2mm thickness HR coils on the .ground of 'reasons beyond
  control'. The arbitrator in the award observed that SAIL has
E admitted that the demand w:ic validly registered by the claimant;
  that material was available in abundance specially from
  domestic source and that supplies were made to others ignoring
                                                                          _, .
  the claim of the present respondent. The arbitrator held that the          '
  intimation of the SAi L to the present respondent that the
F material will not be supplied to the claimant cannot fall within
  the ambit of Clause 7.2.

      30. Although it has been strenuously urged on behalf of the
  appellant that stipulations contained in Clause 7 .~ are
  comprehensive enough to include all types of breaches, on a
G careful consideration thereof, we are unable to accept. the               ,._,,
  submission made on behalf of the appellant. Can it be said that
  SAIL intended to provide for liquidated damages in the contract
  even in a situation where they were unable to make supply of
  materials for the reasons beyond control or they declined to .
H
                       STEEL AUTHORITY OF INDIA LTD. v. GUPTA                      283
                     BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]

"'-."""'   .        supply the materials on one ground or the other. The answer
                    has to be plainly in the negative. It is well known that intention
                                                                                           A

                     of the parties to an instrument has to be gathered from the
                    terms thereof and that-the contract must be construed having
                    regard to the terms and conditions as w~ll as nature thereof.
                    Clause 7.2 that provides for compensation to the respondent            B
                    for failure to supply or delayed supply of the materials by SAIL
                    was never intended to cover refusal to deliver the materials of
                    the supplies on the part of the SAIL. Refusal to supply materials
                  . by SAIL resulting in breach is neither contemplated nor covered
                    in Clause 7.2. There is no impediment nor we know of any               c
                    obstacle for the parties to a contract to make provision of
                    liquidated damages for specific breaches only leaving other
                    types of breaches to be dealt with as unliquidated damages.
                   We are not aware of any principle that .once the ·provision of
      }    "'-      liquidated damages has been made in the contract, in the               D
                   event of breach by one of the parties, such clause has to be
                    read covering all types of breaches although parties may not
                   have intended and provided for compensation in express term~
                   for all types of breaches. It is not a question of giving restrictive
                    or wider meaning to clause 7.2 but the question is what is
                                                                                           E
                    intended by the parties by making a provision such as this and
""I        'i'-    does such clause cover all situations of breaches by SAIL
  ..
                       31. A careful consideration of clause 7.2 would show that
                  it does not prescribe compensation for every type of breach;
                  To name a few, breaches such as: (i) supplies of materials not F
                  in conformity with the contract; (ii) defective materials of
                  supplies; (iii) deficient or short supply; (iv) different materials
                  of the supplies are apparently not covered by Clause 7.2. We
                  have indicated these breaches by way of illustration only to
                  make a point that the provision in the contract for damages vide G
   ._ i
                  clause 7.2 cannot be said to extend to all situations and all
                  types of breaches. In substance and in form, the claim of
                  damages by the respondent for the breaches of contract by
                  SAIL is essentially distinct from the breaches contemplated by ·
                                                                                      H
    284   SUPREME COURT REPORTS [2009) 14 (ADDL.) S.C.R.

                                                                         J
A   Clause 7.2. In this back-drop, if the High Court observed that           Jle,..."'




    Clause 7.2 is not panacea of all ills, it cannot be said that High
    Court fell into an error. Again, the view of the arbitrator that
    breach due to refusal on the part of SAIL to supply materials in
   July-September, 1982 quarter does not fall within the ambit of
B relevant terms contained in the compensation Clause (7.2), by
  '•no stretch of imagination can be said to be an absurd view.
   The arbitrator's view about non-applicability of Clause 7 .2 for
    refusa! to supply materials in July-September, 1988 quarter and
   delayed supply of materials for October-December, 1988
c  quarter is founded on diverse grounds elaborately discussed .
    in the award. Whether this is or is not a totally correct view is
    really immaterial but such view is a possible view that flows
   from reasonable construction of Clause 7.2. The view of the
   arbitrator being possible view on construction of Claus~_ 7.2,        ~   ....
D and having not been found absurd or perverse or unreasonable
   by any of the three Courts, namely , Sub-Judge, District Judge
   and the High ~ourt, we are afraid, no case for interference is
   made out in exercise of our jurisdiction under Article 136 of the
   Constitution.
E      32. Once the arbitrator has construed clause 7.2 in a
  particular manner, and such construction is not absurd and             ~          ;.

  appears to be plausible, it is not open to the courts to interfere             ..
  with the award of the arbitrator. Legal position is no more res
  integra that the arbitrator having been made the final arbiter of
F resolution of disputes between the parties, the award is not
  open to challenge on the ground that arbitrator has reached at
  a wrong conclusion. The courts do not interfere with the
  conclusion of the arbitrator even with regard to construction of
  a contract, if it is a possible view of the matter. The words "no
G award shall be set aside" in Section 30 mandate the courts not         )-    ...
  to set aside the award on the ground other than those specified
  in Section 30. In a case such as this, where the arbitrator has
  given elaborate reasons that compensation clause 7 .2 is not
  attracted for the breaches for which the compensation has been
H
                      STEEL AUTHORITY OF INDIA LTD. v. GUPTA                   285

..   ,...   .       BROTHER STEEL TUBES LTD. [R. M. LODHA, J.]

                  claimed by the respondent and such view of the arbitrator is a
                  possible view, we are afraid in the circumstances award is not
                                                                                      A

                  amenable to correction by the court.

                        33. The arbitrator having taken the view in respect of
                  Clause 7.2 that claim of damages by the respondent of the B
                  breaches committed by the SAIL for refusal to supply materials
                  in July-September, 1988 quarter and delayed supply of the
                  materials for October-December, 1988 quarter did not fall within
                  the ambit of that clause, his further view that Section 74 of the
                  Contract Act has no application as the contract does not
                  determine damages for the breaches in question cannot be
                                                                                      c
                  said to be legally flawed. It is true that Section 74 declares the
                  law as to liability upon breach of contract where compensation
                  is by agreement of the parties pre-determined. However, in the
,,. 'r
                  absence of any agreement specifying damages for the
                                                                                      D.
                  breaches alleged by the respondent, Section 74, in the facts
                  and circumstances, is not at all attracted. Seen thus, the two
                  decisions of the Constitution Bench of this Court in Chunilal
                  V. Mehta & Sons and Fateh Chand have no application to the
                  fact situation of the present case.
                                                                                      E
                        34. The learned senior counsel for the appellant would urge
,~           "'   that the arbitrator had no jurisdiction whatsoever to entertain the
                  claim preferred on September 12, 1991 by way of an
                  application indicating quantification of claims. The learned
                  senior counsel submitted that the claimant preferred the claim F
                  of about Rs. 64 lacs to the designated authority on November
                  3, 1989 in terms of Clause 10 of the Scheme. The designated
                  authority nominated initially one Shri K. Janardhana as an
                  arbitrator but later on appointed Shri K.P. Bhaumik as Shri K.
                  Janardhana submitted his resignation. Learned senior counsel G
     ,._ i        submitted that the claim submitted on November 3, 1989,
                  pertained to the first quarter and for the first time, after the
                  arbitration proceedings had made substantial headway, the
                  claimant preferred an application designated as quantification
                                                                                      H
    286       SUPREME COURT REPORTS [2009] 14 (ADDL) S.C.R.

          ,
                                                                           ~        ....   "-

 A of claims thereby trebling the original claim of Rs. 64 lacs to
    Rs.175 lacs and introducing the claim in respect of first quarter
    (July-September, 1988). He, thus, strenuously urged that                               "
    arbitrator had no jurisdiction to address the fresh claims made
    on September 12, 1991.
 8
         35. We are not. persuaded by the aforenoted submission
    of the learned senior counsel for the appellant for more than
                                                                           :"-
    one reason. For one, the aforesaid argument was not at all
    canvassed before the High Court. A perusal of the judgment
    of the High Court would show that only two contentions were
 c raised there, namely; (i) that arbitrator committed error of
   jurisdiction when he entered a time barred claim and (ii) that
   the arbitrator awarded damages to the claimant under category
   'A'; 'AA' and 'C' by exercising his power beyond Clause 7.2
                                                                         -;.        "':.
   of the agreement. We are afraid the appellant cannot be
 D permitted to raise a contention before this Court in an appeal
   by special leave which was not raised before the High Court.
   This contention is not even indirectly or remotely connected with
   the plea of limitation that was canvassed before the High Court.
   For another, even otherwise, we find no merit in the submission



                                                                                       -
 E of the learned senior counsel that fresh claim was made by the
   respondent on September 12, 1991. In the claim petition filed         ~

   by the respondent, in paragraph 18, it has been stated that in
   view of non availability of certain details which are in
   possession of the respondent and otherwise, the claimant
.F reserves its right to add, amend and/or modify the statement
                                                                                           ,ii--

   of claims. Consequent upon the right already reserved in
   paragraph 18 of the claim petition, the respondent quantified
   the claims, namely, 'A', 'AA', 'AAA' vide application dated
   Septembe~ 12, 1991. We find no merit that by consideration
 G of the claims as quantified vide application dated September                      ...
   12, 1991, the arbitrator exceeded his jurisdiction.
                                                                               ~-
                                                                                                ..
        36. The learned senior counsel for the appellant also urged                 -~
   that claim 'A' pertaining to difference in price has come to be
 H determined by the arbitrator de-hors contract stipulations. In this
                                                                     \

                                                                                           ,.,,
                                  STEEL AUTHORITY OF INDIA LTD. v. GUPTA                287
._,,                            BROTHER STEEL TUBES LTD. [R. M. LODHA! J.]
        .....    I.
                           regard the learned senior counsel referred to paragraph 20.21       A
                           and 20.22 of the award·. We are afraid, this contention too,
                           cannot be permitted to be raised before us since no such
                           contention was raised before the High Court. There has to be
                           some sanctity and finality attached to the decision of the
                           arbitrator and new plea cannot be allowed to be raised in an        B
                           appeal under Article 136 which was not raised before the High
                           Court.
                ~

                                37. The learned senior counsel for the appellant vehemently
                           contended that the present case throws up the prescribed
                           jurisdiction issue wherein the ,arbitrator had chosen to function
                                                                                               c
                           only outside the confines of the contract and with total disregard
                           of express stipulations and, therefore, this Court must interfere
                           in the matter. He relied upon decisions of this Court in the case
            >         "t   of Rajasthan State Mines & Minerals Ltd. Vs. Eastern
                           Engineering Enterprises & Anr8., Food Corporation of India D
   ~,




                           vs. Chandu Construction & Anr8., Steel Authority of India Ltd.
                           vs. J.C. Budharaja, Government & Mining Contractor10 and
 _,-,                      Associated Engineering Co. vs. Govt. of Andhra Pradesh &
    t                      Anr. 6, State of Jammu & Kashmir and Anr. vs. Dev Dutt
   '    \                  Pandit11 •                                                         E

 -  ""'
                      ~
                                38. We are afraid none of the decisions cited by the
                           learned senior Counsel for the appellant has any application
                           to the facts of the present case. The courts below have
                           concurrently held that the arbitrator has gone into the issues of   F
                           facts thoroughly, applied his mind to the pleadings, evidence
                           before him and the terms of the contract and then passed duly
                           considered award and no ground for setting aside the award
                           within the four corners of Section 30 has been made out. We
                                                                                               G
                ---1       8. (1991) 9 sec 283.
                           9. (2001) 4 sec 697.
        •                  10. (1999) 8 sec 122.
            "
                           11. (1999) 1 sec 339.
                                                                                               H
   288    SUPRE~E COURT REPORTS [200.9] 14 (ADDL.) S.C.R.


A have no justifiable reason to take a different view. As. noticed
   above, only two grounds were urged before the High Cot1rt in
  ·assailing the award, one of which relating to time b(lrred claim
  was ultimately notessed before us and the only argument
   survived for consideration before us related to clause 7.2 of the
B contract. In what we have already discussed above, the view
   of the arbitrator in this regard is a possible view.

      39. Consequently, appeal has no merit and must fail. The
   same is dismissed with no order as to costs.

C R.P.                                         Appeal dismissed.




                                                                       ,...__




                                                                       ..'


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.