STATE OF WEST BENGAL & ORS.versusM/S B.B.M. ENTERPRISES
- Citation
- 2026 INSC 358
- Decided
- 9 April 2026
- Disposal
- Appeal(s) allowed
Holding
Section 42 of the Arbitration and Conciliation Act, 1996 incorporates the Limitation Act, 1963, so a claim for recovery of money arising from work completed in 2000 is time‑barred after three years, and a notice seeking arbitration issued in 2022 cannot validly commence arbitration.
Summary
The work under a contract was completed on 30 July 2000, but no final bill or measurement certificate was issued by the Engineer-in-Charge. The State of West Bengal filed a notice seeking arbitration on 2 June 2022, more than 21 years after completion, and the High Court ordered arbitration, holding that the limitation period was not applicable due to the Engineer's alleged failure. On appeal, the Supreme Court examined whether the Limitation Act, 1963 applies to arbitration proceedings and whether the date of receipt of the notice (under Section 43(2) and Section 21) starts the limitation clock. The Court held that Section 42 of the Arbitration and Conciliation Act incorporates the Limitation Act, making the three‑year limitation under Article 18 applicable, and that the claim was hopelessly time‑barred. Consequently, the High Court’s order initiating arbitration was set aside and the appeal was allowed.
Issues considered
- Whether the Limitation Act, 1963 applies to arbitration proceedings under the Arbitration and Conciliation Act, 1996 for a claim for recovery of money.
- Whether the date of receipt of a notice seeking arbitration is the commencement date for limitation purposes under Section 43(2) and Section 21.
- Whether a notice issued after the statutory limitation period can validly commence arbitration for a dispute arising from work completed decades earlier.
- Whether the failure of the Engineer‑in‑Charge to issue a final measurement certificate can extend the limitation period.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11, s. 21, s. 42, s. 43(2)
- Limitation Act, 1963s. Article 137, s. Article 18
Headnote
Issue for Consideration Whether a notice seeking commencement of arbitration, issued on 02.06.2022, could set in motion the process of resolution of a dispute regarding a work completed as early as on 30.07.2000. Headnotes† Arbitration and Conciliation Act, 1996 – ss.42, 43 – 18 – Work completed in the year 2000 – Notice seeking commencement of arbitration issued after 21 years in 2022 – By way of the impugned judgment, Arbitrator appointed by High Court – Sustainability: Held: Unsustainable – Arbitration though is an alternate dispute
Subjects
Judgment
[2026] 5 S.C.R. 154 : 2026 INSC 358
State of West Bengal & Ors.
v.
M/s B.B.M. Enterprises
(Civil Appeal No. 4320 of 2026)
09 April 2026
[Sanjay Kumar and K. Vinod Chandran, JJ.]
Issue for Consideration
Whether a notice seeking commencement of arbitration, issued
on 02.06.2022, could set in motion the process of resolution of a
dispute regarding a work completed as early as on 30.07.2000.
Headnotes†
Arbitration and Conciliation Act, 1996 – ss.42, 43 – Limitation
Act, 1963 – Article 18 – Work completed in the year 2000 –
Notice seeking commencement of arbitration issued after 21
years in 2022 – By way of the impugned judgment, Arbitrator
appointed by High Court – Sustainability:
Held: Unsustainable – Arbitration though is an alternate dispute
resolution system, which has to be encouraged, it cannot deviate
from the fundamental principle that law favours the diligent and
not the indolent – For recovery of amounts, as in this case, the
limitation is three years as provided in Article 18 of the Limitation
Act, 1963 – The commencement of arbitration proceedings as per
sub-section (2) of s.43 being the date referred in s.21, which is
the date on which a request for initiation of arbitration is received
by the respondent, the claim itself was hopelessly time barred,
the notice having been issued after 21 years – Despite the work
having concluded on 30.07.2000, the petitioner did not attempt to
raise a bill or initiate the arbitration proceedings till 2022, when
a notice requiring commencement of arbitration proceedings was
first issued – Appellant slept over its claim for 21 years before the
notice seeking arbitration was issued in 2022; an ex-facie dead
claim – High Court erred insofar as finding failure on the part of
the Engineer-in-Charge to determine the final amount payable,
having extended the limitation – If there was such a failure on the
part of the Engineer-in-Charge, it was for the contractor to have
initiated arbitration then and there – Neither was notice issued
[2026] 5 S.C.R. 155
State of West Bengal & Ors. v. M/s B.B.M. Enterprises
for arbitration nor was a final bill raised or a request made to
determine the total amount payable – Order initiating arbitration
set aside. [Paras 5, 6]
Case Law Cited
Vishram Varu and Company v. Union of India (2023) 12 SCC 588;
Arif Azim Company Limited v. Aptech Limited [2024] 3 SCR 73 :
(2024) 5 SCC 313; Aslam Ismail Khan Deshmukh v. ASAP Fluids
Private Limited and Another [2024] 12 SCR 108 : (2025) 1 SCC
502; Vidya Drolia and Ors. v. Durga Trading Corporation [2020] 11
SCR 1001 : (2021) 2 SCC 1; Bharat Sanchar Nigan Limited and
Anr. v. Nortel Networks India Private Limited [2021] 2 SCR 644 :
(2021) 5 SCC 738; Interplay between Arbitration Agreements under
Arbitration and Conciliation Act, 1996 and Stamp Act, 1899, In Re.
[2023] 15 SCR 1081 : (2024) 6 SCC 1 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996; Limitation Act, 1963.
List of Keywords
Claim ex-facie time barred; Claim hopelessly time barred; Section 42
of the Arbitration and Conciliation Act, 1996; Limitation for recovery
of amounts; Article 18 of the Limitation Act, 1963; Law favours the
diligent; Ex-facie dead claim; Notice seeking commencement of
arbitration issued after 21 years.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4320 of 2026
From the Judgment and Order dated 27.06.2024 of the High Court
at Calcutta in AP No. 535 of 2022.
Appearances for Parties
Advs. for the Appellant(s):
Kunal Chatterji, Ms. Maitrayee Banerjee, Rohit Bansal, Varij Nayan
Mishra.
Advs. for the Respondent(s):
Sudhanshu Choudhari, Sakya Sen, Sr. Advs., Sarad Kumar
Singhania, Yash Singhania, Ms. Nilanjana Adhya.
156 [2026] 5 S.C.R.
Supreme Court Reports
Judgment / Order of the Supreme Court
Order
1. The neat question arising in the above case is as to whether a notice
seeking commencement of arbitration, issued on 02.06.2022, could
set in motion the process of resolution of a dispute regarding a
work completed as early as on 30.07.2000. The High Court dealing
with the application under Section 11 found from the agreement
that there is an ambiguity in Clause 7 which requires the final bill
to be submitted by the contractor within one month from the date
fixed for completion of work dehors which the Engineer-in-Charge is
competent to issue a certificate of measurement and the total amount
payable for the work, which shall be final and binding on all parties.
Since no such certificate was issued by the Engineer concerned
and the communication of 04.01.2001 produced as Annexure P9,
speaks only of a part payment, the dispute would not be beyond the
scope of Section 11 of the Arbitration and Conciliation Act, 19961.
The objection as to limitation was found to be effaced insofar as the
final measurement with the total amounts payable having not been
determined by the Engineer-in-Charge.
2. Sri Kunal Chatterji, learned counsel appearing for the State, the
appellant, would rely on Vishram Varu and Company v. Union of
India2. While Sri Sudhanshu Choudhari, learned Senior Counsel
appearing for the respondent relied on Arif Azim Company Limited
v. Aptech Limited3 and Aslam Ismail Khan Deshmukh v. ASAP
Fluids Private Limited and Another4.
3. Vishram Varu and Company 2 was a case in which the work
undertaken was completed in the year 1985-86 when the claim for
money accrued. Correspondences were initiated from the year 2012
under the RTI Act and eventually a legal notice seeking arbitration
was issued on 22.10.2018. It was held that since the claim arose
in the year 1985-86, the mere issuance of a notice in 2018 cannot
1 For brevity, ‘1996 Act’
2 (2023) 12 SCC 588
3 (2024) 5 SCC 313
4 (2025) 1 SCC 502
[2026] 5 S.C.R. 157
State of West Bengal & Ors. v. M/s B.B.M. Enterprises
enable the party to contend that the cause of action arose in the
year 2018, after expiry of 32 years.
4. Arif Azim Company Limited3 considered both the question of
limitation with respect to the claim for recovery of money and the
limitation provided for filing an application under Section 11(6). It
was categorically found after referring to a host of precedents of
this Court that the Limitation Act, 1963 is applicable to arbitration
proceedings in general and Article 137 of that Act applies to a petition
under Section 11(6) of the 1996 Act in particular. Insofar as the
substantive claim in that case was concerned, it was found that the
right to bring a claim arose on 28.03.2018, the claim being one of
recovery of money. The period of limitation of three years ended on
27.03.2021; within the period in which limitation was suspended by
this Court by reason only of the Covid-19 pandemic. The limitation
having commenced from 01.03.2022 again as per the orders of this
Court, the balance period available from the date of suspension,
extended the expiry of limitation to 13.03.2023. The notice seeking
arbitration under Section 21 was issued on 24.11.2022, bringing the
initiation of the proceeding within the limitation of three years. Insofar
as the limitation for making an application under Section 11(6), this
Court found applicable Article 137, which also provides for a period
of three years, the commencement of which was on expiry of 30
days from the date of receipt of the notice for initiation of arbitration.
Notice issued on 24.11.2022 was delivered on 29.11.2022, thus, the
limitation having commenced from 28.12.2022. The application under
Section 11(6) was filed on 19.04.2023 within the period of three
years from the expiry of 30 days from the receipt of notice. Thus,
both the claim and the application under Section 11(6) were found
to be within the limitation period, which in the present case is not
satisfied insofar as the claim is concerned. We extract paragraph 68
from the aforesaid decision :
“68. Although, limitation is an admissibility issue, yet it is
the duty of the Courts to prima facie examine and reject
non-arbitrable or dead claims, so as to protect the other
party from being drawn into a time-consuming and costly
arbitration process.”
5. Aslam Ismail Khan Deshmukh4, was a case in which the question
arose as to whether the claim was barred by limitation, while the
158 [2026] 5 S.C.R.
Supreme Court Reports
application for appointment of an Arbitrator under Section 11(6)
though moved before a wrong forum, the High Court, was within
the limitation period of 3 years as found in Arif Azim3. Arif Azim3
was found to have been concerned with two issues. First whether
Limitation Act, 1963 is applicable to an application for appointment
of arbitrator under Section 11(6) and whether the Court may decline
reference under Section 11 if the claims are ex-facie and hopelessly
time barred. This Court noticing Vidya Drolia and Ors v. Durga
Trading Corporation5, and Bharat Sanchar Nigan Limited and
Anr. v. Nortel Networks India Private Limited6 held that period
of limitation for filing a petition seeking appointment of an Arbitrator
cannot be confused or conflated with the period of limitation applicable
to substantive claims made in the underlying contract. In BSNL6, the
notice invoking arbitration having been issued five and a half years
after the cause of action arose i.e. rejection of claims of Nortel by
BSNL, the claim itself was held to be ex-facie time barred. However,
noticing the decision in Interplay between Arbitration Agreements
under Arbitration and Conciliation Act, 1996 and Stamp Act,
1899, In Re.7, it was held that in a scenario where the Referral Court
is able to deal with the frivolity of the litigation on the basis of bare
minimum pleadings it would be incorrect to assume or doubt that the
Arbitral Tribunal would not be able to arrive at the same inference.
It was held that the Referral Court cannot indulge in any intricate
evidentiary inquiry into the question whether the claims raised by the
petitioner are time barred which determination has to be left to the
decision of the Arbitrator. In the case of Arif Azim3, the question of
limitation was to be considered on the basis of the facts disclosed,
whether the period commenced from; the date of the letter forming
the basis of the claim, the date of resignation of the petitioner or
the date of subsequent legal notice sent by the respondent to the
petitioner, which was left to be considered by the Arbitrator. However,
in the present case there is no intricate evidentiary inquiry to be
done. After Annexure P9 of 04.01.2001, whether it be the interim
determination of dues or not, the appellant slept over its claim for 21
years before the notice seeking arbitration was issued on 02.06.2022;
an ex-facie dead claim.
5 (2021) 2 SCC 1
6 (2021) 5 SCC 738
7 (2024) 6 SCC 1
[2026] 5 S.C.R. 159
State of West Bengal & Ors. v. M/s B.B.M. Enterprises
6. Arbitration though is an alternate dispute resolution system, which has
to be encouraged, it cannot deviate from the fundamental principle
that law favours the diligent and not the indolent. Section 42 of the
Arbitration and Conciliation Act, 1996 applies the Limitation Act, 1963
to arbitrations as it is applied to proceedings in Court. Hence, for
recovery of amounts, as in this case, the limitation is three years as
provided in Article 18 of the Limitation Act, 1963. The commencement
of arbitration proceedings as per sub-section (2) of Section 43 being
the date referred in Section 21, which is the date on which a request
for initiation of arbitration is received by the respondent, the claim
itself was hopelessly time barred, the notice having been issued
after 21 years.
7. In the present case, despite the work having concluded on 30.07.2000,
the petitioner did not attempt to raise a bill or initiate the arbitration
proceedings till 2022, when a notice requiring commencement of
arbitration proceedings was first issued. The High Court erred insofar
as finding failure on the part of the Engineer-in-Charge to determine
the final amount payable, having extended the limitation. If there was
such a failure on the part of the Engineer-in-Charge, it was for the
contractor to have initiated arbitration then and there. Neither was
notice issued for arbitration nor was a final bill raised or a request
made to determine the total amount payable.
8. We find absolutely no reason to sustain the order initiating arbitration.
We set aside the same and allow the appeal.
9. Pending application(s), if any, shall stand disposed of.
Result of the case: Appeal allowed.
†
Headnotes prepared by: Divya Pandey
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.