STATE OF ORISSA & ORS.versusM/S MESCO STEELS LTD. & ANR.
- Citation
- 2013 INSC 138
- Decided
- 6 March 2013
- Disposal
- Appeal(s) allowed
- Bench
- T S THAKUR
Holding
The writ petition was premature as no final decision had been taken, the show‑cause notice could not be ignored and was within jurisdiction, and therefore the High Court’s order was set aside.
Summary
The State of Orissa granted a mining lease to MESCO Steels Ltd. for iron ore, but later a Director of Mines issued an intra‑departmental communication recommending reduction of the lease area due to overlapping claims and forest land. The State then issued a show‑cause notice to MESCO, which the company challenged in a writ petition. The High Court, ignoring the notice, quashed the communication and ordered the lease to be executed, prompting the State to appeal. The Supreme Court held that the communication was only a provisional step and no final decision had been taken, making the writ petition premature, and that the show‑cause notice could not be ignored merely because it was issued after an interim status‑quo order. The Court further observed that the notice was within jurisdiction and should be dealt with by allowing the company to respond. Consequently, the appeal was allowed, the High Court’s order set aside, and the company was directed to file its reply to the show‑cause notice.
Issues considered
- Whether the writ petition filed by the respondent‑company was premature, being against an inter‑departmental communication that did not finally determine any right or obligation of the parties.
- Whether the show‑cause notice could be ignored by the High Court simply because it was issued in violation of the interim status‑quo order.
- Whether the show‑cause notice was without jurisdiction and could therefore be quashed.
Legislation cited
- Forest (Conservation) Act, 1980s. 2
- Mineral Concession Rules, 1960s. Rule 26(1), s. Rule 27(3), s. Rule 59
- Mines and Minerals (Regulation and Development) Act, 1957s. 30
Subjects
Judgment
[2013] 2 S.C.R. 245
STATE OF ORISSA & ORS. A
v.
M/S MESCO STEELS LTD. & ANR.
(Civil Appeal No. 2206 of 2013)
MARCH 6, 2013
B
[T.S. THAKUR AND GYAN SUDHA MISRA, JJ.]
Constitution of India, 1950:
Art. 226 - Writ petition - Challenging intra-departmental c
communication proposing to consider re-a/location of lease
area for mining iron ore - Held: High Court was in error in
proceeding on an assumption that a final decision had been
taken and in quashing what was no more than an inter-
departmental communication constituting at best a step in the 0
process of taking a final decision by the Government - The
writ petition in that view was pre-mature and ought to have
been disposed of as such - Mines and minerals - Iron ore.
Art. 226 - Writ petition - Order by High Court to maintain
status quo - Issuance of show cause notice by government E
- Held: Issue of show cause notice did not interfere with status
) quo - Once the show cause notice was issued, High Court
could have directed the respondent-company to respond to
the same and disposed of the writ petition reserving liberty to
it to take recourse to appropriate remedy - Since the show F
cause notice is not without jurisdiction, Government to
consider the reply that may be submitted by respondent and
pass a reasoned order on the subject.
In response to the advertisement inviting G
• applications for grant of prospecting licenses and mining
leases for iron ore in the notified area, the respondent-
company and others submitted applications. It was
required that the lessee would set up two steel plants and
245 H
246. SUPREME COURT REPORTS (2013] 2 S.C.R
A would utilize the entire iron ore extracted from the lease
area for meeting the captive requirement of such steel
plants and no commercial tracking of the mining material
would be carried out by it. Ultimately, by letter dated
17.3.2000, the State Government sanctioned the grant of
B lease in favour of the respondent-company. However,
when it was pointed out that some area in the proposed
lease in favour of the respondent-company was
overlapping with the area recommended for allotment to
the Orissa Mining Corporation Ltd. and some area came
c under forest land attracting the Provisions of Forest
Conservation Act, 1980, the Director of Mining, by letter
dated 19.9.2006 recommended re-allocation of resources
based on the requirement of iron ore for the existing steel
plant set up by the respondent-company. It was further
recommended that the respondent-company should not
0
be permitted to carry on any trading activity in iron ore
removed from the area to be allocated in its favour. This
intra departmental communication was challenged by the
respondent-company in a writ petition before the High
E Court, which, by order dated 1.2.2007, directed
maintenance of status quo. However, the State
Government issued a notice dated 6.2.2007 to the
respondent-co·mpany to show cause as to why the
overlapping area of 469.25 hectares of State PSU and
921.258 hectares granted in excess of the captive
F requirement of the respondent-company be not deducted
from total mining lease area of 1519.980 hectares. The
High Court ignored the show cause notice, quashed the
letter dated 19.9.2006, and directed the State Government
to execute a formal mining lease in favour of the
G respondent-company.
In the instant appeal filed by the State Government,
the questions for consideration before the High Court
were: (1) Whether the writ petition filed by the.
H respondent-company was premature, the same having
STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 247
&ANR.
. been filed against an inter-departmental communication A
that did not finally determine any right or obligation of the
parties?; (2) Whether the show cause notice could be
ignored by the High Court simply because it had been
issued in violation of the interim order passed by it
requiring the parties to maintain status quo?; and B
(3)Whether the show cause notice was without
jurisdiction and could, therefore, be quashed?·
Allowing the appeal, the Court
HELD: c
Question No.1
1. It is obvious from a conjoint reading of letter dated
12.1.2006 and communication dated 19.9.2006 sent by the
Director of Mines in response thereto that a final decision D
on the subject had yet to be taken by the Government. It
is only after the Government provisionally decided to
. resume the area in part or full that a show cause notice
could have been issued. To put the matter beyond any
pale of controversy, an unequivocal statement has been E
made at the bar on behalf of the State Government that
,) no final decision regarding resumption of any part of the
lease area has been taken by the State Government so
far and all that had transpired till date must necessarily
be taken as provisional. Such being the case, the High F
Court was in error in proceeding on an assumption that
a final decision had been taken and in quashing what
was no more than an inter-departmental communication
constituting at best a step in the process of taking a final
decision by the Government. The writ petition in that view G
was pre-mature and ought to have been disposed of as
such. [para 15) [258-8, E-H, 259-A]
Question No.2
2. It is true that the High Court had by an interlocutory H
248 SUPREME COURT REPORTS [2013) 2 S.C.R.
A order directed the parties to maintain status quo, but the
issue of show cause notice did not interfere with the
status quo. It simply enabled the respondent-company to
respond to the proposed action. However, once the show
cause notice was issued, the High Court could have
B directed the respondent-company to respond to the
same and disposed of the writ petition reserving liberty
to it to take recourse to such remedy as may have been
considered suitable by it depending upon the final order
that the Government passed on the said notice. The
c respondent-company had not assailed the validity of the
show cause notice on the ground of jurisdiction or
otherwise. The High Court could not simply ignore the
notice even if it was issued in breach of the order passed
by it. The High Court could have taken the show cause
notice as a reason to relegate the parties to a procedure
0
which was just and fair and in which the respondent
1 could urge all its contentions whether on facts or in law.
[para 16] [259-8-E, F-H]
Question No.3
E
3. So long as the show cause notice is not without
jurisdiction as indeed it does not appear to be so, the
question whether the grounds taken in the same provide
a good basis for proposed action can be left open for the
F Government to decide. The Government would carefully
consider the reply which the respondent may submit to
the said show cause notice and pass a reasoned order
on the subject. [para 18] [260-D-E, G]
T.N. Godavarman Thirumulkpad v. Union of India &
=
G Ors. 1996 (9) Suppl. SCR 982 (1997) 2 SCC 267 - cited.
Case Law Reference:
1996 (9) Suppl. SCR 982 cited para 12
H
STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 249
& ANR.
CIVIL APPELLATE JURISDICTION : Civil Appeal No. A
2206 of 2013.
From the Judgment & Order dated 16.05.2~08 of the High
Court of Orissa at Cuttack in W.P. (C) No. 14044 of 2006.
U.U. Lalit, Kirti Renu Misra, Shibashish Misra for the B
Appellants.
Rakesh Dwivedi, Sanjit Mohanty, Naveen Kumar, Nikhil
Sharma, Preetika Dwivedi, R.K. Rathore, Shailender Saini, A.
Dev Kumar, D.S. Mahra for the Respondents. c
The Judgment of the Court was delivered by
T.S. THAKUR, J. 1. Leave granted.
2. This appeal arises out of a judgment and order dated D.
16th May, 2008 passed by the High Court of Orissa at Cuttack
whereby Writ Petition No.14044 of 2006 filed by the
- respondent-company has been allowed, an inter-departmental
communication in the form of a letter dated 19th September,
2006 addressed by the Director of Mines to Joint Secretary to E
Government of Orissa quashed and by writ of mandamus the
State Government directed to execute a mining lease for an
area measuring 1519.980 hectares in favour of the respondent-
company.
.F
3. By Notification No.647/91 dated 23rd August, 1991, the
Government of Orissa de-reserved and threw open Iron/
Manganese Ore areas spreading over 282.46 square miles in
five blocks located in Keonjhar and Sundergarh districts in the
State. Applications were then invited from interested private
parties in terms of Rule 59 of the Mineral Concession Rules, G
1960 for grant of prospecting licenses and mining leases in
\ respect of the said blocks. The exercise was, it appears,
intended to boost the economy of the State by ensuring
optimum utilisation of its mineral reserves and in the process ..
generating employment opportunities for the predominantly H
250 SUPREME COURT REPORTS [2013] 2 S.C.R. ·
A tribal population inhabiting the two districts of the State. The
invitation to apply for leases and to set up steel plants was open
to all leading steel manufacturers.
4. In response to the advertisement notice applications
were received from different parties including one filed by
8
respondent-Mesco Steels Ltd. These applications appear to
have been evaluated, culminating in a conditional
recommendation made by the State Government in favour of
the respondent-company. One of the conditions which the State
Government imposed in exercise of its power under Rule 27
C (3) of the Mineral Concession Rules, 1960 required that the
lessee shall set up two full-fledged Steel Plants within a
reasonable time to be intimated by the lessee at the time of
issue of the terms and conditions for the grant of the proposed
mining lease. The other condition required that the lessee would
D utilise the entire iron ore extracted from the lease area for
meeting the captive requirement of the Steel Plants to be set
up at Duburi and Jakhapura and that no commercial trading of
the mining material shall be carried out by it.
E 5. By an order dated 7th January, 1999 the Government
of India, Ministry of Steel and Mines, Department of Mines,
conveyed the approval of the Central Government for grant of
the mining lease for extraction of iron ore from an area
measuring 1011.480 hectares in villages Kadakala and
F Luhakala besides an area measuring 508.500 hectares in
villages Sundara and Pidapokhari in district Keonjhar for a
period of 30 years. The approval was subject to the State
Government ensuring compliance of the amended provisions
·-
of the Mines and Minerals (Regulation and Development) Act,
1957 and the Rules made thereunder besides the provisions
G of the Forest (Conservation) Act, 1980 and Notification dated
27th January, 1994 issued in terms thereof.
6. On receipt of the approval from the Central Government
the State Government conveyed to the respondent-company the
H terms and conditions subject to which it proposed to grant a ·
· STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 251
& ANR. [T.S. THAKUR, J.]
mining lease for mining of iron ore from the area mentioned A
above which included 377.690 hectares of forest land in
villages Sundara and Pidapokhari of Keonjhar district. A letter
dated 8th February, 1999 issued by the State Government to
the respondent-company stipulated the terms and conditions
that would govern the proposed mining lease and required the B
respondent-company to convey its acceptance to the same. In
response, the respondent-company by its letter dated 15th
February, 1999 conveyed its unconditional acceptance of the
terms and conditions stipulated in the letter mentioned earlier.
The acceptance letter was followed by another letter dated 13th c
March, 1999 by which the respondent-company informed the
State Government that it had already taken steps for
preparation of a mining plan and initiated action for preparation
and approval of de-reservation proposal for the mining lease
in village Sundara and Pidapokhari over an area measuring D
· 508.500 hectares said to be forest land. What is significant is
that the respondent-company also pointed out that it was on the
verge of completion of its Steel Plant at Kalinga Nagar,
Industrial Complex, Sukinda, P.O. Danagadi, District Jajpur,
Orissa which was expected to be commissioned by April/May, E
1999. The State Government eventually sanctioned the grant
of a lease in favour of the respondent-company to the extent
indicated earlier in terms of its order dated 17th March, 1999.
7. By a letter dated 19th June, 2000 addressed to the
respondent-company the State Government pointed out that the F
company had failed to submit the required mining plan and
obtain the approval of Ministry of Environment and Forest,
Government of India, in regard to forest land involved in the
proposed mining lease despite extension of time allowed to the
respondent-company by the Government in terms of its letter G
dated 11th October, 1999. The State Government further
pointed out that on account of the company's inaction in the
matter of setting up the proposed two steel plants, IDCO had
initiated action for cancellation of allotment of 3100 acres of
land allotted in favour of MESCO Kalinga Steel Plant, the sister H
"·
252 SUPREME COURT REPORTS (2013] 2 S.C.R.
A concern of the respondent-company, for the proposed steel
plant, captive power plant and township. The letter in that
backdrop invited the respondent-company for a personal
hearing in terms of Rule 26(1) of the Mineral Concessions
Rules, 1960 to discuss whether the iron ore required by the
B respondent-company for the steel plant which was already in
existence could be assessed to enable the company to retain
the iron ore deposits required for the said plant and restore back
the remainder to the Government.
8. The respondent-company acknowledged receipt of the
C letter above mentioned and, inter alia, pointed out that the
mining plan for the entire area had been prepared and
submitted separately on 31st January, 2000. It was also pointed
out that out of the total extent covered by the proposed lease
only 508.500 hectares was forest land for which extent alone
D was a diversion proposal required to be submitted. It also
referred to certain other steps taken by the company like survey
and demarcation of the area which was underway. More
importantly, the company stated that it had already invested
Rs.57.12 crores in the project but had to put the same on hold
E on account of the steel market passing through a lean phase
because of which all steel majors were facing problems due
to a glut in the market. The respondent-company claimed to
have undertaken substantial work for developing the mine
including financial participation by a Canadian company and
F assured the Government that the proposed project would
create enormous job opportunities for the people of Orissa.
9. For nearly four years thereafter the matter appears to
have remained pending for a final decision at different
G administrative levels in the Government. What is significant is
that by letter dated 26th May, 2004 the Director of Mines,
Orissa, wrote to the Joint Secretary, Department of Steel and
Mines, Government of Orissa, inter alia, pointing out that an
area measuring 469.25 hectares included in the proposed
lease in favour of the respondent-company was overlapping
H
STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 253
& ANR. [T.S. THAKUR, J.]
'·with the area recommended for allotment to the Orissa Mining A
Corporation Ltd. and that even though the Government had
moved for elimination of the said overlapping area in terms of
Director's letter dated 1st June, 2000, no formal Government
order in the matter had been received. The Director further
pointed out that D.F.O., Keonjhar had reported in terms of its B
letters dated 15th January, 2004 and 7th February, 2004 that
major portion of the surveyed and demarcated area came under
Khandadhar D.P.F. and was reported to be forest land as per
column 7 of the D.L.C. report to which effect an affidavit had
also been filed before this Court by the State Government. It c
was also mentioned that the Mining Officer had reported that
an area measuring 692.6953 hectares out of the surveyed and
demarcated area of 802.6678 hectares came under forest land
which attracted the provisions of Forest Conservation Act, 1980.
Clearance from the Ministry of Environment and Forests, D
Government of India, was, therefore, absolutely necessary for
execution of any mining lease in respect of the said area and
till such time this essential pre-condition was not fulfilled, the
execution of the lease deed was not legally permissible. By
another letter dated 19th Siaptember, 2006, the Director of E
Mines recommended re-allocation of resources based on the
requirement of iron ore for the existing steel plant set up by the
respondent-company. It was further recommended that the
respondent-company should not be permitted to carry on any
trading activity in iron ore removed from the area to be allocated
in its favour based on its actual requirement for the existing unit. F
10. Aggrieved by the said inter-departmental
communication the respondent-company filed Writ Petition
No.14044 of 2006 before the High Court of Orissa at Cuttack
in which the company prayed for quashing of the G
recommendations made by the Director of Mines proposing to
reduce the lease area granted to the respondent-company and
prayed for a mandamus directing the State Government to
execute the mining lease in respect of the entire 1519.980
hectares of land in the villages mentioned earlier. By an order H
254 SUPREME COURT REPORTS [2013] 2 S.C.R.
A dated 1st February, 2007 the High Court directed maintenance
of status quo. Despite the said order, however, the Government
of Orissa issued a notice dated 6th February, 2007 by which it
called upon the respondent-company to show cause as to why
the overlapping area of 469.25 hectares of the State PSU and
B 921.258 hectares granted in excess of the captive requirement
of the unit set up by the respondent-company may not be
deducted from the total mining lease area of 1519.980 granted
to the company. The High Court ignored the show cause notice
primarily on the ground that the same had been issued in the
c teeth of the interim order by which the parties had been directed
to maintain status quo, and eventually came to the conclusion
that the proposed reduction of the mining lease area whether
on account of the alleged overlapping of the areas with the area
approved for Orissa Mining Corporation or on account of the.
failure of the respondent-company and its sister concern to set
0
up the second steel plant was not justified. The High Court held
that although the State Government had not issued any final
order so far regarding the deduction of the area yet since a final
decision appeared to have been taken by it, thereby implying
that the issue of a show cause notice after taking of such a
E decision was a mere formality. In coming to that conclusion, the
High Court placed reliance upon paragraph 8 of the counter
affidavit filed by the State Government before the High Court.
The High Court also held that in the absence of a mining lease
in favour of the respondent-company, it could not take the risk
F of setting up of a steel plant. The High Court accordingly
quashed letter dated 19th September, 2006 and by mandamus •
directed the State Government to execute a formal mining
lease in favour of the respondent-company. The present appeal
assails the correctness of the said judgment of the High Court
G as already noticed earlier.
11. Appearing for the appellant, Mr. U.U. Lalit, learned
senior counsel, made a three-fold submission before us.
Firstly, he contended that the writ petition filed by the
H respondent-company was manifestly premature as the
STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 255
& ANR. [f.S. THAKUR, J.]
Government had not taken any final decision that could have A
been challenged by the respondent-company nor was the writ
petition, according to the learned counsel, maintainable against
a mere inter-departmental letter dated 19th September, 2006,
which did not by itself finally decide any right or obligation of
the parties so as to furnish a cause of action to the respondent B
to challenge the same in the extra ordinary writ jurisdiction of
the High Court. Secondly, it was contended that even if the
letter could be described as a final decision taken by the State
Government in regard to the reduction of the lease area, the
respondent-company ought to have taken recourse to c
proceedings under Section 30 of the Act before the Central
Government instead of rushing to the High Court in a writ
petition. Thirdly, it was contended that the very issue of a show
cause notice to the respondent-company suggesting reduction
of the lease area after assessment of the actual requirement
0
by reference to the plant already set up, meant that the
Government had not taken any final decision in the matter and
that the respondent-company could say whatever it intended to
say in opposition to the action proposed in the show cause
· notice where upon the Government could notify a final order on
E
the same, which order could then be challenged by the
respondent-company either before the Central Government or
before the High Court in a writ petition if otherwise permissible.
Inasmuch as the High Court ignored the show cause notice and
proceeded on the assumption that the same was an exercise
in futility, it fell in a serious error, argued Mr. Lalit. The proper F
course, according to the learned counsel, was to allow the State
Government to take a final view on tha§how cause notice after
considering the response which the respondent-company may
have to make.
G
12. On behalf of the respondent-company it was contended
by Mr. Rakesh Dwivedi, learned senior counsel, that although
the show cause notice issued by the appellant-State had not
been specifically challenged in the writ proceedings before the
High Court, this Court could look into the notice and examine H
256 SUPREME COURT REPORTS (2013) 2 S.C.R.
A whether the same had been validly issued on grounds and
material that are legally tenable. He urged that although the
State Government may be competent to recall its
recommendations in exceptional situations, any such exercise
of powers of recall can never be exercised arbitrarily or
B whimsically. At any rate, the exercise of power of recall was,
according to the learned counsel, wholly unjustified in the facts
and circumstances of this case as the whole attempt of the
Government appeared to be to somehow deprive the
respondent-company of the benefit of the mining lease already
c sanctioned in its favour. It was also contended that the question
of overlapping of the area had since been examined and
rejected by the State Government as was apparent from the
Minutes of the Meeting held in the office of the Chief Minister
on 29th October, 2001, a copy whereof has been placed on
record as Annexure R-1. It was'also contended that the State
0
Government was making much ado about nothing regarding the
setting up of the second steel plant and that the same was no
more than a pretext to deny to the respondent-company its
rightful due under the sanction order issued by the Central
Government and the grant made by the State. It was contended
E by Mr. Dwivedi that the requirement of an approved mining plan
which was one of the conditions for the grant of lease had
already been complied with while the execution of a lease
deed could be made subject to the clearance of the project and
the grant of a no objection by the Ministry of Environment and
F Forest under Section 2 of the Forest (Conservation) Act, 1980.
The order passed by the High Court could to that extent be
modified, argued Mr. Dwivedi. Inasmuch as the High Court had
not taken note of the requirement of such clearance being
essential not only under the Act aforementioned but also
G because of the directions issued by this Court in T.N.
Godavarman Thirumulkpad v. Union of India & Ors. (1997) 2
sec 267, it had no doubt committed a mistake but that did
not warrant, setting aside of the entire order passed by the High
Court.
H
STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 257
& ANR. [T.S. THAKUR, J.)
13. We have given our anxious consideration to the A
submissions made at the bar. The following questions, in our
opinion, arise for determination:
( 1) Whether the writ petition filed by the respondent-
company was premature, the same having been filed
8
against an inter-departmental communication that did not
finally determine any right or obligation of the parties?
(2) Whether the show cause notice could be ignored by
the High Court simply because it had been issued in
violation of the interim order passed by it requiring the C
parties to maintain status quo?
(3) Whether the show cause notice was without jurisdiction
and could, therefore, be quasheq?
D
14. We propose to deal with the 1questions ad seriatim.
Regarding Question No.1
15. The writ petition, as already noticed above, was
directed against a communication that had emanated from the E
office of Director of Mines and brought forward certain factual
aspects relevant to the question whether a lease deed could
be immediately executed in favour of the respondent-company.
A careful reading of the said communication would show that
it was issued in pursuance of a letter dated 12th January, 2006 F
from the Joint Secretary, Government of Orissa to the Director
of Mines and another letter dated 29th August, 2006. By the
former letter the Joint Secretary to the Government had
instructed the Director of Mines to take action pursuant to
certain directions issued by the Chief Minister of Orissa. This G
included making a real assessment of the requirement of
respondent-company and permitting execution of a lease deed
subject to clearance of the Ministry of Environment and Forest,
Government of India. The instructions issued to the Director
of Mines also required him to resume the excess area for
reallocation of the same to other deserving parties. The
I •
H
258 SUPREME COURT REPORTS (2013] 2 S.C.R.
A Director .of Mines had responded to the said communication
and assessed the mineral deposits in the area by reference to
maps and surveys and made a recommendation back to the
State Government. It is obvious from a conjoint reading of letter
dated 12th January, 2006 and communication dated 19th
B September, 2006 sent by the Director of Mines in response
thereto that a final decision on the subject had yet to be taken
by the Government, no matter the Government may have
provisionally decided to follow the line of action indicated in its
communication dated 12th January, 2006 issued under the
c signature of the Joint Secretary, Department of Steel and
Mines. It is noteworthy that there was no challenge to the
communication dated 12th January, 2006 before the High Court
nor was any material placed before us to suggest that any final
decision was ever taken by the Government on the question of
D deduction of the area granted in favour of the respondent so
as to render the process of issue of show cause notice for
hearing the respondent-company an exercise in futility. On the
contrary, the issue of the show cause notice setting out the
reasons that impelled the Government to claim resumption of
a part of the proposed lease area from the respondent-
E company clearly suggested that the entire process leading up •
to the issue of the show cause notice was tentative and no final
·decision on the subject had been taken at any level. It is only
after the Government provisionally decided to resume the area
in part or full that a show cause notice could have been issued.
F To put the matter beyond any pale of controversy, Mr. Lalit made
an unequivocal statement at the bar on behalf of the State
Government that no final decision regarding resumption of any
part of.the lease area has been taken by the State Government
so far and all that had transpired till date must necessarily be
G taken as provisional.. Such being the case the High Court was
in error in proceeding on an assumption that a final decision
had been taken and in quashing what was no more than an
inter-departmental communication constituting at best a step
in the process of taking a final decision by the Government. The
H writ petition in that view was pre-mature and ought to have been
STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 259
& ANR. [T.S. THAKUR, J.] .
disposed of as such. Our answer to question No.1 is A
accordingly in the affirmative.
Regarding Question No.2
16. In the light of what we have said while deciding
question No.1 above, this question should not hold us for long. B
It is true that the High Court had by an interlocutory order
directed the parties to maintain status quo, but whether the said
order had the effect of preventing the State Government from
issuing a show cause notice was arguable. The issue of show
cause notice did not interfere with the status quo. It simply C
enabled the respondent-company to respond to the proposed
action. Be that as it may, once the show cause notice was
issued, the High Court could have directed the respondent-
company to respond to the same and disposed of the writ
petition reserving liberty to it to take recourse to such remedy D
as may have been considered suitable by it depending upon
the final order that the Government passed on the said notice.
What was significant was that the respondent-company had not
assailed the validity of the show cause notice on the ground of
jurisdiction or otherwise. If the validity of the show cause notice E
was itself in question on the ground that the Government had
no jurisdiction to issue the same, nothing prevented the
company from maintaining a writ petition and challenging the
notice on that ground. The High Court would in that event have
had an opportunity to examine the validity of the notice. In the F
absence of any such challenge the High Court could not simply
ignore the notice even if it was issued in breach of the order
passed by the Court. It was one thing to prevent further steps ·
being taken pursuant to the notice issued by the Government
but an entirely different thing to consider the notice to be non G
est in the eye of law. The High Court coul~ have taken the show
caµse notice as a reason to relegate the parties to a procedure
which was just and fair and in which the respondent could urge
all its contentions whether on facts or in law. Our answer to
question No.2 is, therefore, in the negative.
H
260 SUPREME COURT REPORTS [2013] 2 S.C.R.
A Regarding Question No.3
17. Although it is not necessary for us now to examine the
question of validity of the show cause notice as the same was
not questioned before the High Court in the writ petition filed
B by the respondent-company, we may to the credit of Mr.
Dwivedi, learned senior counsel appearing for the respondent-
company, mention that he did not seriously challenge the validity
of the notice on the ground of jurisdiction. Mr. Dwivedi fairly
conceded that the State Government could, in appropriate
situations, exercise the option of recalling or modifying its
C recommendations but contended that the pre!?ent case did not
present a situation that could justify such a recall.
18. We do not propose to make any comment or express
any opinion to the merits of the show cause notice. So long as
D the notice is not without jurisdiction as indeed it does not appear
to be so, the question whether the grounds taken in the same
provide a good basis for proposed action can be left open for
the Government to decide. All that we need say is that learned
counsel for the parties made detailed submissions in regard
E to the grounds given in the notice and the validity thereof from
their respective points of view and in support of their respective
versions. Some of these grounds and submissions were quite
attractive also. But so long as the matter is yet to be examined
by the State Government, we consider it unnecessary to
F prejudice the issues or express any opinion about the merits
of the said contentions on either side. The proper course, in
our opinion, would be to leave the contentions available to the
parties open for being determined by competent authority in the
Government who would, in our opinion, do well to carefully
G consider the reply which the respondent may submit to the said
show cause notice and pass a reasoned order on the subject.
Question No.3 is answered accordingly.
19. In the result we allow this appeal, set aside the
judgment and order passed by the High Court and direct that
H the respondent-company shall submit its reply to the show
STATE OF ORISSA & ORS. v. MESCO STEELS LTD. 261
& ANR. (T.S. THAKUR, J.]
cause notice dated 6th February, 2007 issued by the State A
Government within three months from today. The Government
may then upon consideration of the reply so submitted pass a
reasoned order on the subject within two months thereafter
under intimation to the respondent. If the order so made is, for
any reason found to be unacceptable by the respondent- B
company, it shall have the liberty to take recourse to
appropriate proceedings before an appropriate forum in
accordance with law. ·
20. Parties are left to bear their own costs.
c
R.P. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.