STATE OF MADHYA PRADESH AND ORS.versusORIENT PAPER MILLS LTD.
- Citation
- 1989 INSC 379
- Decided
- 7 December 1989
- Disposal
- Dismissed
- Bench
- S RANGANATHAN
Holding
The High Court’s decision granting the exemption on the basis of promissory estoppel stands, and the appeal is dismissed.
Summary
The State of Madhya Pradesh, in its 1961 industrial policy, promised a five‑year exemption from electricity duty to industrialists who generated power themselves using new generating sets installed during the Third Plan. Orient Paper Mills Ltd. indicated in 1955 that it would need 5,000 kW and planned to set up its own power plant, but due to price escalations delayed the project until after the policy was announced. After installing the plant and commencing production on 16 February 1965, the company sought the exemption, was denied, and obtained a writ from the High Court invoking promissory estoppel, which quashed demand notices and granted the exemption without ordering the State to issue a notification. The State appealed by special leave, arguing that the company had not acted to its prejudice and that the High Court erred in applying promissory estoppel. The Supreme Court held that the High Court’s factual findings were not unexceptional and therefore not open to interference, and that granting relief without directing a notification did not violate the Madhya Pradesh Electricity Duty Act, 1949. Consequently, the appeal was dismissed, leaving the High Court’s order in force.
Issues considered
- Whether the doctrine of promissory estoppel can be invoked to enforce the State's assurance of electricity‑duty exemption.
- Whether the Supreme Court may interfere with the High Court's factual findings in this case.
- Whether granting relief without directing the State to issue a notification under the Madhya Pradesh Electricity Duty Act, 1949 amounts to a statutory transgression.
Legislation cited
- Constitution of Indias. 136, s. 226, s. 227
- Madhya Pradesh Electricity Duty Act, 1949s. 3-A(vii), s. 3-B
Subjects
Judgment
A STATE OF MADHYA PRADESH AND ORS.
v.
ORIENT PAPER MILLS LTD.
DECEMBER 7, 1989
B [M.M. PUNCHHI AND S. RANGANATHAN, JJ.]
Administrative Law: Promissory estoppel-Industrialists generat-
ing power through their own new generating sets-Assurance given by
Government-Electricity duty exemption-Effect of
Constitution of India, 1950: Article 136-lnterference .with
C factual findings-Only in exceptional cases. ·
Madhya Pradesh Electricity Duty Act, 1949: Section 3-B-
Electricity duty-Exemption-Notification-High Court granting relief
without ordering issuance of notification-Whether amounts to trans-
D gression.
In its· industrial policy, the State Government declared on
1.8.1961 that . where power has to be generated by industrialists
themseb<es, exemption from electricity duty would be granted for a
perit>CI of five years from the date of plant goes into production, and
E that the concession would be applicable only to new generating sets
installed during the Third Plan_ period.
The Respondent indicated to the Government on 3.5.1955 that
about 5000 K. W. of electriclty Would be required by it to run its paper
plant and that it would by itself make arrangements for obtaining the
F necessary generating equipment. It also applied for import licence for
the import of a production plant as also a power plant to run it. The
import licence was granted and the Respondent started negotiation with
the foreign supplier. Since the price had gone up it was rather impossi-
ble for the Respondent to import both the production plant and the
power plant, and if the power plant was not purcha8ed along with the
G production plant, it would make the project unsound. Hence the
Respondent was in two minds whether to have the power plant or not.
Meanwhile, the above said industrial policy was announced and the
Respondent on installation of the power plant was able to start its
production w.e.f. 16.2.1965.
H Thereafter to formalise the matter, the Respondent corresponded
436
STATE OF M.P. v. ORIENT PAPER MILLS 437
with the appellant for the grant of the requisite exemption, which was
A
rejected, and the Respondent approached the High Court by way of a
petition under Articles 226 and 227 of the Constitution of India. The
High Court held that the Petitioner was entitled to invoke the doctrine
of promissory estoppel in order to claim exemption from payment of
electricity duty for a periof of five years from 16.2.1965 in terms of the
assurance of the State Government dated 1.8.1961. B
Against this order of the High Court the State has come in appeal
by Special Leave.
On behalf of the appellant-State it was urged that there was no
occasion to invoke the doctrine of promissory estoppel, since the Respon·
dent had not in any manner acted on the assurance of the Government c
to its own prejudice but on its own it was taking steps to set up a
generating plant much before the industrial policy was announced.
Dismissing the appeal, this Court,
D
HELD: 1. Whether the respondent was ofone mind right from the
beginning to set up a power plant, with or without the assurance of the
State Government dated J.8.1961, as asserted by the State, is neither
borne out nor is the view of the High Court arrived at from the record.
On the contrary, the view taken is that the respondent's indecision in
that regard ended and it became decisive on the announcement of the E
assurance dated 1.8.1961. Such view of the High Court was a possible
view to be taken on the material placed before it and the inference
drawn therefr(!m could be that the respondent had acted on the basis of
the assurance. [441E-F]
2. This Court ordinarily d~s not interfere with factual findings F
arrived at by the High Court and this case has not been shown to be an
exception. The view taken by the High Court was unexceptional
warranting it to be tell uninterferred with. I44 lF]
3. Without commanding the State Government to issue such a
Notification, the High Courf has granted relief to the respondent to G
which there was no bar. Accordingly no provision of Madhya Pradesh
Electricity Duty Act, 1949 or any other law can be said to have .been
transgressed. [442A] ·
CIVIL APPELLATE JURSIDICTION: Civil Appeal No 498 of
~. H
438 SUPREME COURT REPORTS [ 1989] Supp. 2 S.C.R.
A From the Judgment and Order dated 31.7.1974 of the Madhya
Pradesh High Court in Misc. Petition No. 316 of 1973.
Prithvi Raj, Satish K. Agnihotri and Ashok Singh for the
Appellants.
B Shankar Ghosh, Vivek Gambhir and Parveen Kumar for the
Respondent.
The Judgment of the Court was delivered by
PUNCHHI, J. This is an appeal by special leave against the judg-
ment and order of the High Court of Madhya Pradesh at J abalpur
C whereby the petition under Articles 226 and 227 of the Constitution of
India preferred by Orient Paper Mills Ltd., the sole respondent
herein, was allowed and sequally the order dated 15.3.1973 of the
State Government declining to grant the respondent exemption from
payment of electricity duty for the period from 16.2.1965 to 15.2.1970
D and pursuant demand notices dated 20.3.1973 and 3.4.1973 were
quashed. The aggreived State of Madhya Pradesh and its concerned
Officers are the appellants challenging the same
The respondent had neea to go to the High Court to have an
assurance dated 1.8.1961 regarding exemption from payment of elect-
£ ricity duty given by the State of Madhya Pradesh in its declared indust-
rial policy observed, which may well be reproduced here at the outset:
"Where power has to be generated by industrialists
themselves, exemption from electricity duty shall be
granted for a period of five years from the date of plant
f goes into production. The concession shall be applicable
only to new generating sets installed during the Third Plan
period."
Factually it was not disputed before the High Court, that the case
of the respondent squarely fall within the scope o( the assurance repro-
G duced above since tbe industrial plant of the respondent had gone into
production w.e.f. lli.2.1965, the generating set put up was new, and
had been installed during the Third Plan period. To formalise the
matter, the respondent had corresponded with the Government for the
grant of the requisite exemption. Since the same was rejected and
demands for payment of electricity duty created, the High Court was
H requested to issue suitable writs, directions and orders cancelling the
STATE OF M.P. v. ORIENT PAPER MILLS [PUNCHHI, J.] 439
aforesaid orders and demand notices and granting exemption from
payment of electricity duty in respect of electricity self-generated by A
the respondent during the said period of five years, and also command-
ing the State to carry out the assurance and promises made in the said
industrial policy dated 1.8.1961 extracted above and then, requiring
the State to issue a Notification under Section 3-B of the Madhya
Pradesh Electricity Duty Act, 1949 granting exemption or exception to B
the respondent from payment of electricity duty and other allied
consequential reliefs.
Before the High Court voluminous documentary evidence was
given by the parties in support of their respective pleadings. The High
Court, on consideration of the entire material placed before it, spelled
out a promissory estoppel in favour of the respondent and conclnded c
as follows:
"To conclude, we are of opinion that the petitioner is
entitled to invoke the doctrine of promissory estoppel in
order to claim exemption from payment of electricity duty D
for a period of five years from 16.2.1965 to 15.2.1970 in
terms of the assurance of the State Government, dated
1.8.1961. Of course, as indicated earlier it is not for us to
issue any writ directing the State Government to grant the
petitioner exemption in terms of S. 3-A (vii) or Section 3-B
of the M.P. Electricity Duty (Amendment) Act, 1949. But F
in view of the unambiguous and unequivocal assurance
given by the State Governmet on 1.8.1961 we can certainly
quash the order of the State Government, dated 15.3.1973
as also the demand notices, dated 20.3.1973 (Petitioner's
Annexure-48) and dated 3.4.1973 (Petitioner's Annexure
50) and leave the matter at that. It would be for the F
Government to work out its own course of action on that
basis."
Mr. Prithvi Raj, learned counsel for the appellant urged that on
the facts and circumstances of the case there was no occasion to invoke
the doctrine of promissory estoppel. It was asserted that though the G
industria.I policy was published by the State Government on 1.8.1961
containing the assurance extracted above, the respondent had not in
any manner acted thereon to its own prejudice, but nad rather on its
own been taking steps to set up a generating plant much before the
industrial policy was announced and had factually set up the generat-
ing plant as per its earlier resolve. The facts highlighted were that the H
440 SUPREME COURT REPORTS [ 1989] Supp. 2 S.C.R.
A respondent Paper Mill, had been set up at Amlai in Vindhya Pradesh,
when a Part-C State under the administration of the Central Govern-
ment. It had in its application dated 3.5.1955 to the Government indi-
cated that about 5000 K.W. electricity would be required by it to run
its paper plant and. it would by itself make arrangements for obtaining
B the necessary generating equipment. It appears that the State Govern-
ment had at that time its own project in view for installing a power
plant. On that basis some correspondence ensued between the respon-
dent and the State Gdvernment with regard-to its annual requirement
of electricity. That exercise was abandoned for some reasons which are
not relevant here. Thereafter the respondent applied for· import
licence for the import of a production plant as also a power plant to run
C it. The respondent was granted an import licence on the strength of
which it started negotiation with an American supplier. While negotia-
tions were in process the American supplier increased the price. It
became impossible for the respondent to import the production plant
and the power plant within the funds allotted to it by the World Bank
D and in these circumstances, the American suppliers advised the appel-
lant to drop procurement of the power plant. At the same time the
American supplier warned the respondent that if the power plant was
not purchased along with the production plant, it would make the
project unsound and it would not be able to fulfil its guarantees as
desired by the respondent. The respondent in these circumstances
became of two minds, whether to have the power plant or not. When it
E was in that state of mind, the industrial policy was announced by the
Government on 1.8.1961. Thereafter, on 21.8.1961, the respondent
applied to the Government of India for sanction of permission to
import 3.5 million dollar worth goods more. than the sanctioned
amount. Finally, the respondent with the consent of the Government
of India and with the aid of the World Bank was able to import the
F production plant and the power plant and after its installation was able
to go on production w .e.f. 16.2.1965.
The course of the events set out earlier were not disputed as such
by the appellants before the High Court but it was maintained as now
before us, that the respondent would have on its own gone on to instal
,¢J the power Ijlant even without the announcement of the industrial
policy dated\ 1.8.1961. Additionally, it was maintained, in the like
manner, that the respondent had not acted to its prejudice on the basis
of the aforesaid assurance dated 1.8.1961 and so that doctrine of
promissory estoppel was not invokable. The defence of the State thus
H raised was rejected by the High Court in the following words:
STATE OF M.P. v. ORIENT PAPER MILLS IPUNCHHI, J.] 441
"We have already dealt with that aspect earlier and we A
have already held that the petitioner's action in setting up a
power plant was postponed on account of certain circum-
. stances and ultimately on the advise of the manufacturers
who refused to continue the guarantee, the petitioner
decided to set up its own power plant. In the meantime, the
assurance of the State Government, dated 1.8.1961 had B
already been given and the petitioner's action in making a
final decision to set up its own power plant can be directly
connected with the State Government's assurance dated
1.8.1961. No sooner the petitioner took the final decision
in that behalf, it applied to the State Government for grant
of an exemption, although that application was premature,
because the petitioner's paper mill had not started func-
c
tioning. As such, the petitioner would certainly be entitled
to claim exemption in terms of the assurance of the State
Government dated 1.8.1961 with effect from tile date the
paper mill started functioning, namely, 16.2.1965 and the
exemption would last for a period of five years upto D
15.2.1970."
'
Whether the respondent was of one mind right from the begin-
ning to set up a power plant, with or without the assurance of the State
Government dated 1.8.1961, as asserted by the State, is neither borne
out nor is the view of the High Court arrived at from the record. E
Rather, on the contrary, the view taken is that the respondent's indeci-
sion in that regard ended and it became decisive on the announcement
of the assurance dated 1.8 .1961. Such view of the High Court was a
possible view to be taken on the material placed before it and the
inference drawn therefrom could be that the respondent had acted on
the basis of the assurance. The effort here to re-do the exercise in this F
regard must inevitably fail, for this Court ordinarily does not interfere
with factual findings arrived at by the High Court and this case has not
been shown to us to be an exception. In this situation, the view taken
by the High Court was unexceptional warranting it to be left unin-
terferred with.
G
Some attempt was made by learned counsel for the appellant to
contend that the doctrine of promissory estoppel could not be pressed
into service to command the State Government under Section 3cA (vii)
(before its amendment) and Section 3-B of the Madhya Pradesh
Electricity Duty Act, 1949 (as amended) to issue a Notification
exempting the respondent from payment ·of electricity duty. The H
442 SUPREME COURT REPORTS [ 1989] Supp. 2 S.C.R.
A answer to this argument is available in the conclusion arrived at by the
High Court extracted above. Without commanding the State Govern-
ment to issue such a Notification, it has granted relief to the respon-
dent to which there was no bar. Accordingly, no provision of Madhya
Pradesh Electricity Duty Act, 1949 or any other law can be said to
have been transgressed. We thus reject this argument too.
B
Thus for the foregoing reasons this appeal fails and is hereby
dismissed. No costs.
G.N. Appeal dismissed
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.