Created byFuzzy Cloud

Supreme Court of India

STATE OF KERALAversusM/S ZOOM DEVELOPERS PVT. LTD. & ORS.

Citation
2009 INSC 137
Decided
10 February 2009
Disposal
Dismissed

Holding

The modified consortium agreement did not change the consortium’s membership and the term “joint and several responsibility” does not constitute an objective criterion of non‑admissibility; therefore the bid is admissible.

Summary

The Supreme Court examined the rejection of Zoom Developers’ consortium bid for the Vizhinjam seaport PPP project. The issues were whether the modified consortium agreement dated 11‑March‑2008 altered the membership of the consortium after the 31‑Jan‑2008 cut‑off, and whether the use of the term “joint and several responsibility” instead of “joint and several liability” made the bid non‑responsive under the RFP. The Court held that the consortium’s membership remained unchanged; PMS was the constituent member from the outset and the modification merely cured a curable defect. It also held that the distinction between “responsibility” and “liability” was not an objective criterion in the RFP and could be interpreted subjectively, so the bid could not be rejected on that ground. Consequently, the High Court’s judgment was affirmed and the technical and financial proposals were ordered to be considered. The appeals were dismissed.

Issues considered

  • Whether the modified consortium agreement dated 11‑March‑2008 resulted in a change in the membership of the consortium after the cut‑off date.
  • Whether the use of the expression “joint and several responsibility” instead of “joint and several liability” justified treating the bid as non‑responsive.

Legislation cited

Subjects

consortium agreementjoint and several liabilityjoint and several responsibilitybid evaluation committeepublic‑private partnershipRFPmodification of consortiumadmissibility of bidchange in consortium membershipCompanies Act 212

Judgment

                         [2009) 1 S.C.R. 1150


A                        STATE OF KERALA
                                   V.
          M/S ZOOM DEVELOPERS PVT. LTD. & ORS.
              (Civil Appeal Nos. 841-842 of 2009)
                        FEBRUARY 10, 2009
B
        [DR. ARIJIT PASAYAT AND S.H. KAPADIA, JJ.]

        COMPANIES ACT, 1956:

c      S.212 - Consortium Agreement - Modification of -
  Whether results in change in the constituents membership -
  Bid Evaluation Committee rejecting the Bid proposal made
  by the consortium and excluding the consortium from zone
  of consideration - High Court holding the decision unjustified,
D arbitrary and bad in law - On appeal, Held: The modified
  consortium agreement is in line with the proposal submitted
  - There was no change in the membership of the consortium
  - High Court rightly held that the licence agreement has still
  to be executed and at that stage the change of joint and
E several liability shall be incorporated in the licence
  agreement- No infirmity in the judgment of High Court - The
  Technical and Financial proposals submitted by the
  consortium (Respondent No. 1) to be considered within 15
  days.

F       WORDS & PHRASES:

        'Liability', 'responsibility' - Meaning of.

      The High Court held that the decision of the Bid
  Evaluation Committee dated 6.5.2008 rejecting the Bid
G Proposal made by the Consortium led by the Mis Zoom
  Developers Pvt. Ltd. (ZDL) as non-admissible in terms of
  Request for Proposal (RFP) and thus excluding the said
  consortium from the zone of consideration was
  unjustified, arbitrary and bad in law. Hence the appeals.
H                             1150
STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1151
                    & ORS.

     On the basis of the contentions advanced, the          A
following points emerged for consideration by the Court:

    1. Whether the modified Consortium Agreement
dated 11.3.2008 resulted in a change in the constituents
membership of the Consortium led by M/s ZDL.
                                                            B
    2. Whether use of the expression "joint and several
responsibility" in place of "joint and several liability"
would justify rejection of the Bid proposal made by the
Consortium led by M/s ZDL as non-responsive/non-
admissible in terms of the RFP.                             c
    Dismissing the appeals, the Court

      HELD:1.1. On reading the Proposal, it becomes clear
 that on the date, namely, 31.1.2008, being the cut-off date
(when the bids were opened), M/s PMS was the member- 0
constituent of the consortium led by M/s ZDL. At this
stage, one must keep in mind that Section 212 of the
Companies Act, 1956 which makes it obligatory on behalf
of the holding company to annex to its Balance Sheet the
Balance Sheet and P&L account and other financial E
particulars of its subsidiary. Section 212 requires the legal
relationship of holding company and subsidiary
company to be disclosed to all its members. In the world
of globalization, we have consortium agreements/ joint
venture agreements. It appears from the particulars given F
by the consortium led by Mis ZDL that M/s PMS is a part
of an international group of companies headed by M/s
PPL, UK. The prescribed Form warranted Disclosure
giving particulars of the consortium members. The
particulars furnished indicate that the Lead Member was G
M/s ZDL. It is an Indian company. One of the consortium
member was M/s PMS, which is incorporated in UK. It is
the 100% subsidiary of M/s PPL, UK. This information
also became necessary because the format required the
Bidder to disclose "Ownership" of the member-company. H
    1152      SUPREME COURT REPORTS           [2009] 1 S.C.R.


A Therefore, if one reads the Proposal of the Lead Member,      >-
  M/s ZDL, in the form prescribed, which Proposal was of
  31.1.2008, one finds that Mis PMS alone on its own was
  indicated as a member of the consortium and M/s PPL
  was not shown as the member of the consortium.
8 However, the original consortium/joint venture agreement
  dated 4.10.2007 signed by the member-constituent of the
  consortium led by Mis ZDL stood signed by Mis PMS on
  behalf of M/s PPL, UK. Therefore, on 3.3.2008, IDC (Project
  Advisor) wrote to M/s ZDL pointing out the defect in the
C consortium agreement dated 4.10.2007. Thus, the Project
  Advisor treated the above irregularity in the execution of
  the consortium agreement dated 4.10.2007 as a curable
  defect for which time was given tQ M/s ZDL up to 4.4.2008.
  Further, the Project Advisor clearly understood the
  Proposal to have had been given by M/s ZDL as the Lead
D Member of the Consortium, whose constituent inter alia
  included M/s PMS and not M/s PPL. By the said letter, the
  Project Advisor also called for Annual Reports of three
  financial year of Mis ZDL and Annual Reports of last 3
  years of M/s PMS (its own). This query indicates that the
E Project Advisor not only treated the above irregularity in
  the execution of the consortium agreement dated
  4.10.2007 as the curable defect but it further shows that
  even, according to the Project Advisor, M/s PMS alone
  was the constituent member of the consortium led by M/
F s ZDL and it is for this reason that the Project Advisor
  called for the annual reports of Mis PMS (its own). This
  defect was cured by M/s PMS within the extended period.
  [Para 14] [1066-F-H; 1067-A-H; 1068-A-B]
       1.2. The question of "authorization" by M/s PPL,UK,
G was not raised by the Project Advisor in its letter dated
  3.3.2008. That aspect was raised only by the Law
  Secretary who came to be Invited as a special invitee by
  the Chief Secretary in the meetings of the EC held on
  8.4.2008 and 6.5.2008 (which is after the extended date.
H
STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1153
                    & ORS.

4.4.2008). It is not in dispute that Mis PPL, UK is the A
holding company of Mis PMS. Mis PMS is a subsidiary
company. It is the separate legal entity. This Court is
satisfied that at the stage of Submission of Proposal itself
and right from the inception, it was Mis PMS, who alone
was the constituent member of the consortium. The B
question of authorization raised by the Law Secretary is
clearly an afterthought. In fact, there is a contradiction in
his opinion. If Mis PPL was the member of the consortium,
as construed by the Law Secretary, there was no need
for Mis PPL to authorize Mis PMS to execute the c
consortium agreement. On the other hand, if Mis PMS
being the separate legal entity was a member of the
consortium it had to sign the consortium agreement in its
own capacity. The modified consortium agreement dated
11.3.2008 is supported by a Resolution. The said 0
consortium agreement is in line with the Proposal
submitted on 31.1.2008. [Para 14) [1168-B-F]
      2. Mis Universal Legal (legal advisor to the Sponsor)
 cleared the proposal on 4.4.2008 stating that all requisite
 defects stood cured. It is only after 4.4.2008 that the Law    E
Secretary came into picture and gave an opinion to the
 contrary. Moreover, as found by the High Court in the
impugned judgment, when the Law Secretary was asked
to file his affidavit he came out with the statement that his
advice was "off the record" advice. It was not given            F
through Official Channel. No material has been placed
before the High Court as to the reference made by the
Chief Secretary to the Law Secretary. The very purpose
of routing the query through Official Channel is that the
querist formulates the query on which opinion is given.         G
In this case, there is no formulation of such a query. In
the circumstances, the High Court was right in not giving
weightage to the "off the record" advice of the Law
Secretary. This is one of the circumstances which vitiates
the process of decision making by the EC. The bid was           H
    1154      SUPREME COURT REPORTS           [2009) 1 S.C.R.


A declared as non-admissible in the IVth meeting of the EC      .,..
  held on 6.5.2008. The Minutes indicate that, before the EC,
  there were two Opinions. First opinion was that of Mis
  Universal Legal and the second opinion was that of the
  Law Secretary. There is nothing to indicate in the Minutes
B as to why the opinion of the legal advisor, Mis Universal
  Legal, stood rejected. There is no reason given as to why
  the opinion of the Law Secretary came to be accepted.
  The modified consortium agreement was between
  members of the consortium led by Mis ZDL in which the
C member was Mis PMS and not Mis PPL, UK, right from                   1-
  the inception. Therefore, the entire exercise was to cure
  the defect. Time was given to Mis ZDL to cure the defect
  which in fact was cured before 4.4.2008. For the
  aforestated reasons, it is held that there was no change
  in the membership of the consortium led by Mis ZDL after
D 31.1.2008. In fact, even prior to the IVth meeting the EC
  did not call upon Mis ZDL/PMS to obtain Letter of
  Authority from Mis PPL, UK. [Para 15] [1168-G-H; 1169-
  A-H]
E      3.1. Under the agreement, duties and responsibilities
  of each of the members stood carved out. Vide clause 7,
  members of the consortium were made "jointly and
  severally responsible" for every stage of implementation
  of the Project. The only objection raised by the GoK is
F that the word "liable" ought to have been used instead
  of the word "responsible" in clause 7 and since that
  word has not been used, the Bid Proposal of Mis ZDL
  needs to be dismissed. As stated above, in the meetings
  held prior to 8.4.2008, no such objection was ever raised.
  In fact, no opportunity was given to Mis ZDL to cure this
G defect though it was given to the consortium led by Mis
  Apollo. The important point is that the EC treated the
  above objection as a curable defect. It is only after the
  Law Secretary came on the scene that the above
  objection was raised even after the clearance by M/s
H Universal Legal. Therefore, it is clearly an afterthought.
STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1155
                    & ORS.

 Further under the consortium agreement dated 11.3.2008, A
 it was stated that M/s ZDL, PMS and Peter Fraenkel &
 Partners shall be fully responsible for their individual
portions of work. Under the said Agreement, it was further
stated that, in case the Project stood awarded to the
 Consortium, the Consortium commits to hold a minimum B
stake of 51% in the SPC. This shows that in the matter
of liability, the Consortium Agreement was only a step-
in-aide to the formation of SPC. Further, as rightly held
by the High Court in the impugned judgment, the
apprehension of GoK that in the event of disputes c
between members of the consortium or in the event of
non-implementation of the Project, GoK would not be in
a position to enforce its claim was ill-founded because
the licence agreement between the successful bidder and
the licensor (GoK) was yet to be entered into in which a
                                                           0
provision as to "joint and several liability" had to be
made, as mentioned in the RFP. The consortium
agreement was only an assurance or a commitment to
abide by the licence agreement. Lastly, it may be stated
that the word "responsibility" is no doubt different from
the word "liability". [Para 19] [1171-B-H; 1172-A-B]       E
     3.2. In the absence of a prescribed formEtt and in the
absence of the definition of the word "respohsibility" vis-
·-vis the word "liability" in the RFP, it cannot be said that
the said expression "joint and several liability" was an F
objective criteria. It is true that in terms of RFP, the bidder
was required to stipulate the words "joint and several
liability" in the consortium agreement. But it is equally
true that in certain cases objective words can be
interpreted subjectively. In the instant case, various bids G
were considered by the Project Advisor/Sponsor. They
have themselves used the words "liability" and
"responsibility" interchangeably. They have treated this
defect as a curable defect. They have not rejected the Bid
Proposal on 25.2.2008 in the first meeting on the above H
    1156       SUPREME COURT REPORTS             (2009] 1 S.C.R.


A ground because the EC thought that the said defect was
  a curable defect. [Para 19] [1172-D-H; 1173-A]

       3.3. The consortium agreement dated 11.3.2008 spelt
  out the work allocation and the responsibility of each
  member of the consortium. It made the consortium
B
  responsible jointly and severally for implementation of the
  Project. The clause dealing with "relationship of the
  parties" merely stated that till the formation of the SPC,       •
  each member shall be related to each other on principal-
  to-principal basis. This is because the consortium is
c formed to make a bid for this Project only. But once that
  consortium becomes a successful bidder and commits
  to hold the minimum equity stake of 51% in the SPC,
  then the question of joint and several liability would
  certainly arise. Therefore, the High Court rightly held that
D the licence agreement between GoK and the successful
  bidder (consortium) has still to be executed and it is at
  that stage that, in any event, the clause of joint and
  several liability shall stand incorporated in the licence
  agreement. [Para 20] [1173-D-G]
E
      H. W Wade and Forsyth: 'Administrative Law', 9th edn.
  pp. 432-435, referred to.

        4. The Chart submitted on behalf of Mis Lanco
  Kondapalli Power Pvt. Ltd. refers to the Financial Years
F October, 2003 to September, 2004, October 2004 to
  September, 2005, October, 2005 to September, 2006 as far
  as M/s-ZDL is concerned. However, it may be noted that
  initially the last date for-submitting the bid was 31.10.2007,
  which was extended to 31.1.2008. The Balance Sheet and
G P&L account of M/s ZDL for the year ending 30.9.2007
  stood adopted after audit only on 20.3.2008. If the figures
  for that year are taken into account then the financial          t

  qualification criteria stands satisfied. [Para 21] [1173-H;
  1174-A-B]
H
 STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1157
                     & ORS .
            ..
    5. The Technical and Financial Proposals submitted               A
by the Consortium (respondent no. 1) are liable to be
considered within 15 days from the date of this judgment.
[Para 22] [117 4-E]

    CIVIL APPELLATE JURISDICTION: Civil Appeal No. 841-              B
842 of 2009.

     From the Judgment & Order dated 4.1.2008 in R.P. No.
1329/2008 & WA No. 1460/2008 of the High Court of Kerala
at Ernakulam.
                                                                     c
     A.Sharan, ASG, K. Prasaran, K.K. Venugopal, T.B. Hood,
Pradeep Ranjan Tiwary, R. Satish, P.V. Dinesh, Sindhu T.R.,
Kamkal Bhundhiraj, Nishant Menon, Manu Seshadri, Sidharth
Bawa, Gopal Shankarnarayanan (for M/s. Dua Associates) for
the Appellants.                                                      o
    Arun Jaitely, U.U. Lalit, Maninder Singh, Pratibha, M. Singh,
Santosh Mathrew, Gaurav Sharma, Surbhi Mehta, Sumeet
Bhatia, Ankit Gupta, Meenakshi Grover, Ramesh Singh, K.S.
Rama Rao, Bela Maheshwari and Joydeep Nath for the
Respondents.                                                         E

     The Judgment of the Court was delivered by

     S.H. KAPADIA, J.1. Leave granted.

       2. A short question which arises for determination in these   F
 civil appeals is - whether the decision of the Bid Evaluation
 Committee ("EC" for short) dated 6.5.2008 rejecting the Bid
 Proposal made by the Consortium led by M/s Zoom Developers
Pvt. Ltd. as non-admissible in terms of RFP and thus excluding
the said Consortium from the zone of consideration was               G
unjustified, arbitrary and bad in law, as held by the impugned
judgment of the Kerala High Court dated 4.12.2008 in Writ
Appeal No. 1460/2008.

                                                                     H
    1158           SUPREME COURT REPORTS             [2009] 1 S.C.R.


A Facts:

       3. Government of Kerala (GoK) vide G.O. No. 9/07/F&PD
  dated 9.3.2007 decided to invite bids for the Development of
  International Deepwater Seaport and Container Transshipment
  Terminal at Vizhinjam under Public-Private Partnership. Vide
8
  G.O. dated 15.6.2007 GoK decided on the key provisions in
  the Request For Proposal ("RFP" for short) documents for the
  bidding of the above Project. A competitive bid process was
  thus initiated by M/s Vizhinjam International Seaport Ltd. ("VSL"
  for short). VSL was the Sponsor. IL & FS Infrastructure
C Development Corporation ("IDC" for short) was the Project
  Advisor. Accordingly, on 8.8.2007, Press Notification was
  issued by M/s VSL inviting RFP for the development of the
  Project. On 23.1.2008 a Bid Opening Committee was
  constituted vide G.O. of the same date. Thirty-three firms
D obtained the RFP documents. Vide G.O. dated 19.2.2008, Bid
  Evaluation Committee headed by the Chief Secretary was also
  constituted to Evaluate the Bid Proposals. Ultimately, bids were
  received from the following five Consortia by 31.1.2008 (which
  was the last date stipulated for receiving the Bids), they were:
E
        (i)    Apollo Enterprises led consortium

           (ii)    Nagarjuna Construction Co. led consortium

           (iii)   Videocon Industries Ltd. led consortium
F
           (iv)    Lanco Kondapalli Power Pvt. Ltd., Hyderabad, led
                   consortium

           (v)     Zoom Developers Pvt. Ltd., Mumbai led
                   consortium.
G
       4. The bidders were required to submit their proposals in
  four covers, namely, the Outer Cover (containing details of the
  bidder, power of attorney in favour of the lead member,
  consortium agreement entered amongst the members of the
H consortium, legal opinion, security of Rs. 50 million in the form
STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1159
           & ORS. [S.H. KAPADIA, J.)

  of bank guarantee etc.}, Cover-1 (Statement of Qualification},    A
  Cover-2 (Technical Proposal) and Cover-3 (Financial
  Proposal). In this case, evaluation was done in three stages.
  In the first stage, there was evaluation of Outer Cover and
  Cover-1 to check the admissibility of bids and evaluation of
  qualifications as stipulated in the RFP. It may be noted that     B
  evaluation of the Technical Proposal had to be done only of
 those bidders who met the "Qualification Criteria" (vide second
 stage). The third stage contemplated evaluation of the Technical
  Proposal. As stated above, only five bids were received. These
 bids (Outer Cover and Cover-1) were opened on 31.1.2008 by         c
 the Bid Opening Committee. The said firms were found to have
 satisfied prima facie the requisite requirements. The bids were
 accepted by the Bid Opening Committee for further scrutiny.
 The bids submitted were considered at the meeting of the EC
 on 25.2.2008. In the said meeting it was observed that, with
                                                                    0
 regard to the bid submitted by the consortium led by M/s Zoom
 Developers Pvt. Ltd. ("ZDL" for short), the Power of Attorney
 and the Consortium Agreement were unstamped and they
 needed to be stamped. It was further pointed out by the EC that
 the lead member in terms of the RFP, namely, M/s ZDL was
 required to hold a minimum equity of 26% in the Special            E
 Purpose Company ("SPC" for short), which has not been
expressly mentioned in the Consortium Agreement. The EC
further pointed out to M/s ZDL that one of the consortium
member, namely, M/s Portia Management Services Ltd. ("PMS"
for short) had signed the consortium agreement on behalf of         F
Peel Ports Ltd. ("PPL" for short) but M/s PPL is not a member
of the consortium. Additional information regarding the
financials of M/s PMS (on its own) and of M/s ZDL were also
called for. On 25.2.2008, accordingly the EC granted ten days
time to remove the above defects. M/s ZDL sought extension          G
of time. Ultimately, time was extended up to 4.4.2008. In short,
meetings of the EC took place on 25.2.2008, 13.3.2008,
8.4.2008 and 6.5.2008. By 2.4.2008, M/s ZDL submitted all the
relevant documents duly updated. It may be noted that M/s
Universal Legal, Bangalore, were appointed as Legal Advisor         H
   1160        SUPREME COURT REPORTS              [2009] 1 S.C.R.


A of the Project by the EC.

        5. As stated above, on 2.4.2008 M/s ZDL submitted their
  modified documents. On 4.4.2008 the said M/s Universal Legal
  furnished their opinion that the Consortium Agreement
B submitted by the Consortium led by M/s ZDL had complied with
  the requirements of the RFP and that they had removed all
  defects pointed out to them by the EC and accordingly the EC
  may consider their Bid Proposals. However, in the third meeting
  held on 8.4.2008, the EC after having considered the
  documents submitted by the Consortium led by M/s ZDL came
C to the conclusion that in the modified consortium agreement
  dated 11.3.2008, Mis PMS has signed the consortium
  agreement on its own whereas in its original consortium
  agreement dated 4.10.2007, M/s PMS has signed the
  consortium agreement on behalf of Mis PPL. Accordingly, the
D opinion of the Law Secretary (Invitee to the Meeting) was
  sought. The Law Secretary opined that the modified consortium
  agreement dated 11.3.2008 cannot be treated as a part of the
  Original Proposal as the modified consortium agreement stood
  entered into by a new member, namely, M/s PMS, without the
E authorization of M/s PPL. According to the Law SP.cretary, there
  was one more defect. There was no provision in the modified
  consortium agreement to the effect that the consortium
  members shall be jointly and severally liable for the execution
  of the Project and that the only expression used was joint and
F several "responsibility", which, according to the Law Secretary,
  was a concept different from joint and several "liability". This
  opinion of the Law Secretary was placed before the EC in its
  meeting held on 6.5.2008 in which meeting the EC concluded
  that the Bid submitted by the consortium led by Mis ZDL was
G "non-responsive"/"non-admissible" in terms of the RFP.
  Accordingly on 24.5.2008, GoK issued Government Order
  approving the proposal given by Lanco Kondapalli Power Pvt.
  Ltd., Hyderabad (hereinafter referred to as "Lanco led             •
  Consortium"). Thus, the Bid Proposal of the consortium led by
H M/s ZDL came to be rejected.
        STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1161
                   & ORS. [S.H. KAPADIA, J.]

               6. Aggrieved by the said decision, M/s ZDL preferred Writ      A
  "'·    Petition (C) No. 15570/2008 in the Kerala High Court which
         came to be dismissed by the learned single Judge on
         3.7.2008. It was held by the learned Single Judge that the
         concept of "liability" was different from "responsibility". It was
        further held that since the consortium members led by M/s ZDL         B
         had not undertaken "joint and several liability", the EC was right
         in treating the bid proposal as non-responsive. It was further
  ...   held by the learned single Judge that the original consortium
        agreement dated 4.10.2007 was signed by M/s PMS on behalf
        of Mis PPL though no such authorization was found in that             c
        regard. According to the learned single Judge, in the modified
        consortium agreement dated 11.3.2008, M/s PPL, which was
        the party to the original consortium agreement, stood deleted
        and M/s PMS had emerged as a member of consortium for the
        first time only under the modified consortium agreement dated
                                                                              D
        11.3.2008 without explaining under whose authority such
        change was made and consequently, the EC was right in
        treating the Bid Proposal made by M/s ZDL as non-responsive.
        Accordingly, the writ petition stood dismissed. Aggrieved by
        the said decision, Mis ZDL preferred Writ Appeal No. 1460/
        2008, which stood allowed by the Division Bench of the Kera la        E
        High Court, hence, these civil appeals are filed by the State of
        Kerala (licensor), M/s Lanco Kondapalli Power Pvt Ltd. and
        M/s Vizhinjam International Sea Port Ltd. (Sponsors).

        Contention:                                                           F
              7. On behalf of State of Kerala, Shri K. Parasaran, learned
        senior counsel submitted that after 31.1.2008 (the cut-off date)
        there was a change in M/s ZDL led Consortium which was
        impermissible in terms of the RFP and, therefore, the Bid
                                                                          G
        Evaluation Committee was right in treating the Bid submitted
        by M/s ZDL led Consortium as non-responsive/non-admissible
...     in terms of the RFP. In support of his contention, learned senior
        counsel submitted that as per clause 3.4 of RFP, only the Lead
        Member could be changed and that too with the written consent
                                                                          H
    1162       SUPREME COURT REPORTS               [2009] 1 S.C.R.


A of Mis VSL (Sponsor). According to the learned counsel, RFP
  did not permit change of consortium member after the cut-off
  date. It may be noted that the Proposals of the Bidders were
  to be submitted on or before 31.1.2008. Learned counsel
  pointed out that along with the Proposal, Mis ZDL submitted
B the Consortium Agreement dated 4.10.2007 in which Mis PMS
  signed the consortium agreement on behalf of Mis PPL, UK.
  Therefore, according to the learned counsel, Mis PMS singed
  the Consortium Agreement dated 4.10.2007 as an agent of Ml           ...
  s PPL, UK. According to the learned counsel, in the Consortium
c Agreement dated 4.10.2007, Mis ZDL did not stipulate that as
  a Lead Member it would hold a minimum equity of 26% in the
  SPC. The Consortium Agreement dated 4.10.2007 was not
  notarized and stamped. That apart, the said consortium did not
  submit documents from Mis PPL, UK authorizing Mis PMS to
  sign the Consortium Agreement on behalf of Mis PPL, UK.
0
  According to the learned counsel, all the above circumstances
  came to be considered by the EC in its meeting held on
  25.2.2008. The EC, according to the learned counsel, recorded
  in its Minutes that since Mis PPL was the member of the
  Consortium in terms of Consortium Agreement dated
E 4.10.2007, but, since Mis PPL was not shown in the Outer
  Cover, therefore, a query was raised by the EC in its letter dated
  3.3.2008 to the effect that although Mis PMS has signed the
  Consortium Agreement on behalf of Mis PPL, the latter was not
  a member of the Consortium. According to the learned counsel,
F in the said letter dated 3.3.2008, there was no direction from
  the EC to Mis ZDL to delete the words "on behalf of Mis PPL"
  and consequently, after the cut-off date, it was not open to Mis
  ZDL led Consortium to submit a fresh Consortium Agreement
  dated 11.3.2008 deleting the words "on behalf of Mis PPL".
G According to the learned counsel, therefore, there was a change
  in the membership of the Consortium led by Mis ZDL and that
  too after 31.1.2008. Therefore, according to the learned
  counsel, it was not a case of curing of defect. According to the
  learned counsel, change of consortium membership after the
H cut-off date made the Proposal of Mis ZDL led Consortium
            STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1163
                       & ORS. [S.H. KAPADIA, J.)

           non-admissible in terms of the RFP.                                   A

                   8. Shri K. Parasaran, learned senior counsel, next
             contended that vide clause 3.5 of the RFP, all members of the
             Consortium were "jointly and severally liable" for execution of
             the Project in terms of the Licence Agreement and a statement
                                                                                  B
             to that effect was required to be stated in the consortium
             agreement, which statement was not incorporated in
       T
             consortium agreement dated 4.10.2007 nor in the consortium
             agreement dated 11.3.2008. According to the learned senior
             counsel, the two words, namely, "liabilities" and "responsibilities"
             are not interchangeable. They are distinct and different
                                                                                 c
            concepts. According to the learned counsel, RFP required a
             statement regarding "joint and several liability" to be
             incorporated in the consortium agreement because the word
            "liability" represented an objective criteria, which criteria has not
            been satisfied despite opportunity being given to M/s ZDL led D
            Consortium to incorporate such a statementin the consortium
            agreement. Learned counsel submitted that despite opportunity
            being given to Mis ZDL led Consortium, even in the fresh
            Agreement dated 11.3.2008, M/s ZDL led Consortium had
            insisted on using the words "joint and several liabilities" in E
            support of the words "joint and several responsibilities".
           Therefore, for non-compliance of the said criteria, the EC was
            right in treating the Bid Proposal of M/s ZDL led Consortium
       ,    as non-admissible/non-responsive in terms of RFP.
                                                                                  F
---+
                 9. In short, on two of the aforestated grounds, namely,
           change of consortium membership and non incorporation of
           joint and several liability Clause in the consortium agreement,
           learned counsel for the State of Kerala submitted that the EC
           was right in treating the Bid Proposal of M/s ZDL as non-
                                                                                  G
           responsive.

               9A. Shri A. Sharan, learned Additional Solicitor General
           appearing on behalf of Mis VSL substantially adopts the
           contentions advanced by Shri K. Parasaran, learned senior
           counsel for the State of Kerala.                                     H
    1164        SUPREME COURT REPORTS                 [2009] 1 S.C.R.


A       10. Shri K.K. Venugopal, learned senior counsel appearing
  on behalf of Mis Lanco led Consortium submitted in addition
  to the above contentions that, in any event, the figures submitted
  by M/s ZDL led Consortium indicated that, on its own M/s PMS
  did not fulfill the financial parameters of net worth, total turnover
B and cash accruals and that Mis PMS was solely dependent
  upon the financials of M/s PPL, UK, consequently, the Bid
  Proposal of M/s ZDL led Consortium was not admissible in
  terms of RFP. Learned senior counsel further submitted that in
  the Consortium Agreement dated 4.10.2007, there was a
c clause under the caption "Relationship of Parties". Reading of
  that clause, according to the learned counsel, indicated that the
  consortium members were to act on principal-to-principal basis
  and despite opportunity, even in the fresh Consortium
  Agreement dated 11.3.2008, the said clause stood retained.
  Therefore, according to the learned counsel, the criteria of joint
0
  and several liability was not satisfied by M/s ZDL led
  Consortium.

         11. On the other hand, it was submitted on behalf of M/s
  ZDL led Consortium that the interpretation given by the
E Sponsor/Advisor on various terms and conditions of the RFP
  should be read as a standard to evaluate the admissibility of
  the bids. According to Shri Harish N. Salve, learned senior
  counsel appearing on behalf of M/s ZDL, the Minutes of the EC
  held on 25.2.2008 indicated that the words "responsibility" and
F "liability" were used interchangeably. That, it is only after the Law
  Secretary gave his opinion that the question of the connotation             -
  of the two words "liability" and "responsibility" were made an
  issue, which was clearly an afterthought. According to the
  learned counsel, the said hair-splitting exercise was undertaken
G as an afterthought only after the Law Secretary gave his
  opinion, which opinion was "off the record" advice (which
  expression is used by the Law Secretary in his affidavit).              "
  According to the learned counsel, there was no change in the
  membership of the Consortium led by Mis ZDL because right
H from the inception, at the time of submitting the Proposals, it
                STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1165
                           & ORS. [S.H. KAPADIA, J.]

                was made clear that M/s PMS would be the member of M/s A
                ZDL led Consortium. It was submitted that M/s PMS was the
                subsidiary of Mis PPL, UK, and the words "on behalf of were
                used in the Consortium Agreement dated 4.10.2007 only to
                indicate the relationship between M/s PMS and M/s PPL, UK.
                This position, according to the learned counsel, is indicated by B
                the Bid documents submitted on 31.1.2008, Power of Attorney
                dated 18.10.2007, Notary Certificate, Covering letter dated
                31.1.2008 and annexures to the Bid documents submitted by
                M/s ZDL.

                       12. On the question of financials, Shri Arun Jaitley, learned c
                 senior counsel for M/s ZDL, submitted that the Chart submitted
                 before this Court by the learned counsel for M/s Lance led
                 Consortium was defective because the Financials for FY 2006-
                 2007 has not been projected. In this connection, it was pointed
                 out that M/s ZDL had submitted the details for FY October, 2003 D
                 to September, 2004, October, 2004 to September, 2005 and
              . October, 2005 to September, 2006 as on 31.1.2008. It was
                 pointed out that, M/s ZDL was following the Accounting Year
                from October to September. It was submitted that the last date
                for submission of Bids was 31.10.2007 initially, which stood E
,,...           extended later on till 31.1.2008. Acccrding to the learned
~
                counsel, the Balance Sheet for FY 2006-2007 was in the
                process of being prepared when the Bid documents were


.               submitted on 31.1.2008 and consequently, the Balance Sheet
        _,,
                for FY 2006-2007 could not be submitted. According to the F
                learned counsel, if the Financials for the year including FY
                2006-2007 are taken into account; then M/s ZDL lead
                Consortium satisfies all the financial parameters of net worth,
                turnover and cash accruals.
                                                                                   G
                    13. Points for Consideration:

                     (A)   Whether the modified Consortium Agreement
                           dated 11.3.2008 resulted in a change in the
                           constituents membership of the Consortium led by
                           M/s ZDL.                                         H
    1166         SUPREME COURT REPORTS                  [2009] 1 S.C.R.

                                                                                  ..--'----
A          (B)   Whether use of the expression "joint and several              --...,......
                 responsibility" in place of "joint and several liability"
                 would justify rejection of the Bid Proposal made by
                 the Consortium led by M/s ZDL as non-responsive/

B
                 non-admissible in terms of the RFP.

    Findings on Point No. (A):
                                                                                        -
        14. As per the scheme of RFP, at the stage of Submission             ...
  of Proposals, the bidders were required to furnish the names
  of the Lead Member and other members of the consortium. In
c this case, one of the members of the consortium was Mis PMS.                          '
                                                                                         ?
  While furnishing "Details of Bidders", the name of the
  consortium member was shown as PMS. Similarly, against the
  column "Brief Description of the Company", the name of M/s
  PMS was mentioned as the international arm of M/s PPL.
D Therefore, at the stage of Submission of Proposals, M/s ZDL
  had stated that M/s PMS was the member of its Consortium.
  There was one more column which was required to be filled-in
  by the bidders, namely, "Ownership of the Organisation". In this
  column, M/s ZDL indicated that M/s PMS was a consortium
E member which was the wholly subsidiary company of M/s PPL,
  UK. It may be noted that, under the Scheme of RFP, the bidders                     ,- ..,
  had to offer a firm commitment to form SPC to implement and                            ~·

  operate the above Project in i<erala, should the Sponsor (M/s
  VSL) select one of the five bidders as Licensee. Therefore, the
                                                                             ~



F Proposal had to be made in a prescribed format. On reading
  the said Proposal, therefore, it becomes clear that on the date,
  namely, 31.1.2008, being the cut-off date (when the bids were                         '
  opened), M/s PMS was the member-constituent of the
  consortium led by Mis ZDL. At this stage, one must keep in
  mind that Section 212 of the Companies Act, 1956 which
G
  makes it obligatory on behalf of the holding company to annex
  to its Balance Sheet the Balance Sheet and P&L account and                  ;
  other financial particulars of its subsidiary. Section 212 requires
  the legal relationship of holding company and subsidiary                                  .;,::
  company to be disclosed to all its members. In the world of
H
       STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1167
                  & ORS. [S.H. KAPADIA, J.]

       globalization, we have consortium agreements/ joint venture         A
       agreements. It appears from the particulars given by the
       consortium led by M/s ZDL that M/s PMS is a part of an
       international group of companies headed by Mis PPL, UK.
       The prescribed Form warranted Disclosure giving particulars
       of the consortium members. The particulars furnished indicate       B
       that the Lead Member was Mis ZDL. It is an Indian company.
...    One of the consortium member was M/s PMS, which is
       incorporated in UK. It is the 100% subsidiary of M/s PPL, UK.
       This information also became necessary because the format
       required the Bidder to disclose "Ownership" of the member-          c
       company. Therefore, if one reads the Proposal of the Lead
       Member, M/s ZDL, in the form prescribed, which Proposal was
       of 31.1.2008, one finds that M/s PMS alone on its own was
       indicated as a member of the consortium and M/s PPL was
       not shown as the member of the consortium. However, the
                                                                           D
       original consortium/joint venture agreement dated 4.10.2007
       signed by the member-constituent of the consortium led by Ml
       s ZDL stood signed by Mis PMS on behalf of M/s PPL, UK.
       Therefore, on 3.3.2008, IDC (Project Advisor) wrote to Mis
       ZDL inter alia pointing out the defect in the consortium
       agreement dated 4.10.2007 in the following words:                   E

            "M/s PMS has signed consortium agreement dated
            4.10.2007 on behalf of M/s PPL but Mis PPL is not a
  }·        member of the consortium."
                                                                           F
             Thus, the Project Advisor treated the above irregularity in
       the execution of the consortium agreement dated 4.10.2007
       as a curable defect for which time was given to M/s ZDL up
       to 4.4.2008. Further, the Project Advisor clearly understood the
       Proposal to have had been given by M/s ZDL as the Lead
                                                                           G
       Member of the Consortium, whose constituent inter a/ia
       included Mis PMS and not Mis PPL. By the said letter, the
       Project Advisor also called for Annual Reports of three
       financial year of M/s ZDL and Annual Reports of last 3 years
       of Mis PMS (its own). This query indicates that the Project
                                                                           H
    1168         SUPREME COURT REPORTS                [2009] 1 S.C.R.


A Advisor not only treated the above irregularity in the execution
  of the consortium agreement dated 4.10.2007 as the curable
  defect but it further shows that even, according to the Project
  Advisor, Mis PMS alone was the constituent member of the
  consortium led by Mis ZDL and it is for this reason that the
B Project Advisor called for the annual reports of Mis PMS (its
  own). This defect was cured by Mis PMS within the extended
  period. It is interesting to note that the question of "authorization"
  by Mis PPL,UK, was not raised by the Project Advisor in its
  letter dated 3.3.2008. That aspect was raised only by the Law
c Secretary who came to be Invited as a special invitee by the
  Chief Secretary in the meetings of the EC held on 8.4.2008
  and\6.5.2008 (which is after the extended date 4.4.2008). ltis
  not in dispute that Mis PPL, UK is the holding company of Ml
  s PMS. Mis PMS is a subsidiary company. It is the separate
  legal entity. We are satisfied that at the stage of Submission
0
  of Proposal itself and right from the inception, it was Mis PMS,
  who alone was the constituent member of the consortium. The
  question of authorization raised by the Law Secretary, in his
  opinion, is clearly an afterthought. In fact, there is a contradiction
  in his opinion. If Mis PPL was the member of the consortium,
E as construed by the Law Secretary, there was no need for Ml
  s PPL to authorize Mis PMS to execute the consortium
  agreement. On the other hand, if Mis PMS being the separate
  legal entity was a member of the consortium it had to sign the
  consortium agreement in its own capacity. The modified.
F consortium agreement dated 11.3.2008 is supported by a
  Resolution. The said consortium agreement is in line with the
  Proposal submitted on 31.1.2008.

        15. One more aspect needs to be pointed out. The RFP
G prescribes the form in which a bidder has to make his proposal.
  However, bidder was free to submit the consortium agreement
  in its own format. M/s Universal Legal (legal advisor to the
  Sponsor) cleared the proposal on 4.4.2008 stating that all
  requisite defects stood cured. It is only after 4.4.2008 that the
H Law Secretary came into picture and gave an opinion to the
     STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1169
                & ORS. [S.H. KAPADIA, J.]

      contrary. Moreover, as found by the High Court in the impugned A
      judgment, when the Law Secretary was asked to file his
      affidavit he came out with the statement that his advice was "off .
      the record" advice. It was not given through Official Channel.
      At this stage, we may also point out that no material has been
      placed before the High Court as to the reference made by the B
      Chief Secretary to the Law Secretary. Whenever opinion is
      sought, the persons seeking opinion has to formulate the query
•     for which opinion is sought. We do not know the query raised
      by the Chief Secretary before the Law Secretary. No material
      has been placed before us in this regard. In fact, the very c
      purpose of routing the query through Official Channel is that the
     querist formulates the query on which opinion is given. In tl:lis
     case, there is no formulation of such a query. In the
     circumstances, we find that the High Court was right in not
     giving weightage to the "off the record" advice of the Law
                                                                          0
     Secretary. This is one of the circumstances which vitiates the
     process of decision making by the EC. The bid was declared
     as non-admissible in the IVth meeting of the EC held on
     6.5.2008. The Minutes indicate that, before the EC, there were
     two Opinions. First opinion was that of Mis Universal Legal and
     the second opinion was that of the Law Secretary. There is E
     nothing to indicate in the Minutes as to why the opinion of the
     legal advisor, Mis Universal Legal, stood rejected. There is no
     reason given as to why the opinion of the Law Secretary came
    to be accepted. Be that as it may, we are of the view that the
    modified consortium agreement was between members of the F
    consortium led by Mis ZDL in which the member was Mis PMS
    and not Mis PPL, UK, right from the inception. Therefore, the
    entire exercise was to cure the defect. Time was given to Mis
    ZDL to cure the defect which in fact was cured before 4.4.2008.
    For the aforestated reasons, we hold that there was no change G
    in the membership of the consortium led by Mis ZDL after
    31.1.2008. In fact, even prior to the IVth meeting the EC did
    not call upon Mis ZDL/PMS to obtain Letter of Authority from
    Mis PPL, UK.
                                                                        H
    1170        SUPREME COURT REPORTS                [2009] 1 S.C.R.


A       16. For the above reasons we hold that there was no
    change in the membership of the Consortium led by M/s ZDL.

    Findings on Point No. (8):

        17. As stated above, the second ground for treating the
B Bid Proposal of the consortium led by M/z ZDL as non-
  responsive was that, in the consortium agreement, Mis ZDL has
  failed to incorporate the expression "joint and several liability".
  That, Mis ZDL has incorporated the clause under the
  expression "joint and several responsibility" in place of "joint and
C several liability" and consequently, the Bid Proposal became
  non-admissible/non-responsive in terms of the RFP. This was
  the basic argument advanced on behalf of GoK.

       18. At the outset, it may be stated that in letter dated
0 3.3.2008 no such point was ever raised by the Project Advisor.
  As stated above, by the said letter dated 3.3.2008 curable
  defeds were pointed out regarding M/s PMS having signed the
  consortium agreement dated 4.10.2007 on behalf of M/s PPL,
  UK, but no query was ever raised on the above point. On the
E contrary, as can be seen from the Minutes of the meetings held
  prior to 8.4.2008, the Project Advisor/Sponsor has used the
  word "responsibility" interchangeably with the word "liability". It
  is only in the opinion of the Law Secretary that, for the first time,
  the above objection is taken.

F      19. Be that as it may, the question is whether in the
  modified consortium agreement dated 11.3.2008
  responsibilities and allocation of works stood clearly
  demarcated between the members of the consortium? We
  have examined the consortium agreement dated 11.3.2008. It
G clearly indicates that Mis ZDL is an Indian company. It is a lead
  member of the consortium. The agreement further indicates that
  there were two members in the consortium apart from M/s ZDL,
  namely, M/s PMS and M/s Peter Fraenkel & Partners. The
  agreement indicates that M/s ZDL shall be responsible for
H implementation of the Project along with M/s PMS and Mis
STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1171
           & ORS. [S.H. KAPADIA, J.]

  Peter Fraenkel & Partners. Mis ZDL had to submit technical          A
  and financial bids. M/s ZDL had to act as project developers
 and principal coordinators. M/s ZDL had to arrange finances.
  On the other hand, Mis Peter Fraenkel & Partners had to do
 the work of designing and budget preparations whereas M/s
 PMS had to provide operational support during the                    B
 implementation of the Project. Therefore, under the said
 Agreement, duties and responsibilities of each of the members
 stood carved out. Vide clause 7, members of the consortium
 were made "jointly and severally responsible" for every stage
 of implementation of the Project. The only objection raised by       c
 the GoK is that the word "liable" ought to have been used
 instead of the word "responsible" in clause 7 and since that
 word has not been used, the Bid Proposal of M/s ZDL needs
 to be dismissed. As stated above, in the meetings held prior
 to 8.4.2008, no such objection was ever raised. In fact, no
                                                                      0
 opportunity was given to M/s ZD~ to cure this defect though it
 was given to the consortium led by M/s Apollo (see page 81
 of the SLP paper book in SLP (C) Nos. 30204-30205/2008
 entitled State of Kerala v. M/s Zoom Developers Pvt. Ltd. &
 Ors.). The important point is that the EC treated the above
 objection as a curable defect. It is only after the Law Secretary    E
 came on the scene that the above objection was raised even
 after the clearance by M/s Universal Legal. Therefore, it is
 clearly an afterthought. Further under the consortium agreement
dated 11.3.2008, it was stated that M/s ZDL, PMS and Peter
Fraenkel & Partners shall be fully responsible for their individual   F
portions of work. Under the said Agreement, it was further
stated that, in case the Project stood awarded to the
Consortium, the Consortium commits to hold a minimum stake
of 51% in the SPC. This shows that in the matter of liability, the
Consortium Agreement was only a step-in-aide to the formation         G
of SPC. Further, as rightly held by the High Court in the
impugned judgment, the apprehension of GoK that in the event
of disputes between members of the consortium or in the event
of non-implementation of the Project, GoK would not be in a
position to enforce its claim was ill-founded because the licence     H
    1172         SUPREME COURT REPORTS                  [2009) 1 S.C.R.


A agreement between the successful bidder and the licensor
  (GoK) was yet to be entered into in which a provision as to "joint
  and several liability" had to be made, as mentioned in the RFP.
  The consortium agreement was only an assurance or a
  commitment to abide by the licence agreement. Lastly, it may
B be stated that the word "responsibility" is no doubt different from
  the word "liability". What is submitted before us is that the
  expression "joint and several liability" was required to be
  incorporated in the consortium agreement in terms of RFP.
  What was submitted before us was that the said expression
c constituted an objective criteria. What was submitted before us
  was that since the above expression in the RFP was treated
  as an objective criteria, the manner in which the said
  expression stood understood by the EC was irrelevant. We do
  not find merit in this argument. As stated above, though the
  Form of Proposal was prescribed, the bidder was free to
0
  submit the consortium agreement in its own Form. In our view,
  in the absence of a prescribed format and in the absence of
  the definition of the word "responsibility" vis-a-vis the word
  "liability" in the RFP, it cannot be said that the said expression
  "joint and several liability" was an objective criteria. It is true that
E in terms of RFP, the bidder was required to stipulate the words
  "joint and several liability" in the consortium agreement. But it
   is equally true that in certain cases objective words can be
   interpreted subjectively. For example, the word "regulate". It has
   several times been decided that the power to regulate does
F not extend to a power to prohibit. But this very word has been
   held in some other cases to include the power to prohibit. In
   U.K., the Railway Board was entitled to impose a ban on
   smoking in trains under this very power to regulate. Therefore,
   one has to construe each of these words in that context. (see
G Administrative Law by H.W. Wade and Forsyth- 9th ed. at pp.
   432-435). In this very case, various bids were considered by
   the Project Advisor/Sponsor. They have themselves used the
   words "liability" and "responsibility" interchangeably. They have
   treated this defect as a curable defect. They have not rejected
H the Bid Proposal on 25.2.2008 in the first meeting on the above
   STATE OF KERALA v. ZOOM DEVELOPERS PVT. LTD. 1173
              & ORS. [S.H. KAPADIA, J.]

   ground because the EC thought that the said defect was a A
   curable defect. -

         20. It was vehemently urged on behalf of Mis Lanco led
    Consortium that in the consortium agreement dated 4.10.2007
 · as well as in the consortium agreement dated 11.3.2008, there           B
    was a clause under the heading "Relationship of Parties" which
    indicated that each member of the consortium shall deal with
    the other on principal-to-prin~ipal basis till the formation of SPC.
    In the said clause, it was further stated that, nothing contained
    in the agreement shall be deemed to constitute any of the
    parties as agent of the other. Therefore, the members of the           C
    consortium led by Mis ZDL cannot be said to be jointly and
    severally liable at every stage of implementation of the Project.
    We do not find merit in this argument. As stated above, the
    consortium agreement dated 11.3.2008 spelt out the work
    allocation and the responsibility of each member of the                D
   consortium. It made the consortium responsible jointly and
   severally for implementation of the Project. The clause dealing
   with "relationship of the parties" merely stated that till the
   formation of the SPC, each member shall be related to each
   other on principal-to-principal basis. This is because the              E
 · consortium is formed to make a bid for this Project only. Till the
   formation of SPC and till the consortium becomes a successful
, bidder, the parties relate to each other on principal-to-principal
   basis. But once that consortium becomes a successful bidder
   and commits to hold the minimum equity stake of 51% in the              F
   SPC, then the question of joint and several liability would
   certainly arise. Therefore, the High Court rightly held that the
  licence agreement between GoK and the successful bidder
  (consortium) has still to be executed and it is at that stage that,
  in any event, the clause of joint and several liability shall stand      G
  incorporated in the licence agreement.

     21. Before concluding, an attempt was made on behalf of
 Mis Lanco Kondapalli Power Pvt. Ltd. (appellant in the civil
 appeal arising out of SLP (C) No. 30305/2008) to demonstrate
                                                                           H
    1174        SUPREME COURT REPORTS                [2009] 1 S.C.R.


A before us that but for the financials of Mis PPL, the consortium
  led by M/s ZDL would not have rnet the financial qualification
  criteria as on the date of the submission of the Bid Proposal
  (31 .1.2008). Learned counsel appearing on behalf of Mis Lanco
  Kondapalli Power Pvt. Ltd. submitted a Chart in support of his
B above contention. We find no merit in this argument. The said
  Chart refers to the Financial Years October, 2003 to
  September, 2004, October 2004 to September, 2005, October,
  2005 to September, 2006 as far as M/s ZDL is concerned.
  However, it may be noted that initially the last date for submitting
c the bid was 31 .10.2007, which was extended to 31.1 .2008. The
  Balance Sheet and P&L account of Mis ZDL for the year ending
  30.9.2007 stood adopted after audit only on 20.3.2008. If the
  figures for that year are taken into account then the financial
  qualification criteria stands satisfied.
D      22. For the aforestated reasons, we find no infirmity in the
  impugned judgment of the Division Bench of the Kerala High
  Court which has given a declaration to the effect that the Outer
  Cover and Cover-1 submitted by the consortium led by Mis
  ZDL is admissible/responsive in terms of RFP. Consequently,
E we declare that the Technical and Financial Proposals
  submitted by the said Consortium (respondent no. 1) are liable
  to be considered within 15 days from the date of this judgment.

      23. Accordingly, the civil appeals stand dismissed with no
F order as to costs.

    G.N.                                        Appeals dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "consortium agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.