Created byFuzzy Cloud

Supreme Court of India

STATE OF HARYANA & ORS.versusM/S JAI DURGAA FINVEST P. LTD.

Citation
2026 INSC 678
Decided
13 July 2026
Disposal
Appeal(s) allowed

Holding

Clause 19 is a valid and binding term; the security deposit does not earn interest during the three‑month period after termination, but interest at 9% per annum accrues thereafter.

Summary

The State of Haryana awarded a mining contract for Yamuna sand to M/s Jai Durgaa Finvest P. Ltd., which required the contractor to deposit a security amount. The contractor defaulted on instalments and the contract was terminated on 09.03.2000, with the security forfeited. The contractor later claimed interest on the security, arguing that Clause 19 of the Form‑L contract, which states the deposit shall not carry interest, was unsustainable. The Supreme Court examined the contractual language, held that Clause 19 is a valid, binding term, and that interest is payable only after the three‑month refund period post‑termination. Consequently, the security deposit earned no interest up to 09.06.2000, but the contractor is entitled to simple interest at 9% per annum thereafter until refund or adjustment. The Court set aside the High Court’s declaration that Clause 19 was void and allowed the appeals in part.

Issues considered

  • Whether Clause 19 of the Form‑L contract, which provides that the security deposit shall not carry interest, is a valid and enforceable term.
  • Whether the security deposit is liable to accrue interest despite the contractual stipulation to the contrary.
  • Whether the termination of the mining contract by the State was lawful and without illegality.

Legislation cited

Headnote

88 : 2026 INSC 678 State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd. (Civil Appeal No(s). 3145-3146 of 2012) 13 July 2026 [Surya Kant, CJI and V. Mohana,* J.] Issue for Consideration Whether the amount of security deposit given by the Respondent- contractor will carry interest Rules, 1964 – An auction notice was given for the extraction of Yamuna sand from Bega Murthal Sand Zone – Respondent firm was the highest bidder – The bid was accepted by the Appellant – On 30.11.1998, a contract was executed between the parties in terms of the Form-L

Subjects

AgreementValid agreementContractTermination of contractSecurity depositInterest on security depositRefundInterest freePerpetuity

Judgment

                      [2026] 8 S.C.R. 88 : 2026 INSC 678

                            State of Haryana & Ors.
                                       v.
                         M/s Jai Durgaa Finvest P. Ltd.
                      (Civil Appeal No(s). 3145-3146 of 2012)
                                       13 July 2026
                    [Surya Kant, CJI and V. Mohana,* J.]


                                Issue for Consideration
           Whether the amount of security deposit given by the Respondent-
           contractor will carry interest despite there being a contract to the
           contrary between the Appellant and the Respondent.

                                        Headnotes†
           Mines & Minerals (Regulation and Development) Act, 1957 –
           The Punjab Minor Minerals Concession Rules, 1964 – An
           auction notice was given for the extraction of Yamuna sand
           from Bega Murthal Sand Zone – Respondent firm was the
           highest bidder – The bid was accepted by the Appellant –
           On 30.11.1998, a contract was executed between the parties
           in terms of the Form-L – As per the said contract the
           Respondent was to deposit the contract money in advance
           to the Government on a monthly basis – Respondent
           defaulted in their installment – The contract was terminated –
           The Respondent took up the matter in appeal before the
           Appellate Authority – The Appellate Authority ordered that
           the department shall raise the demand of contract money
           and up to date interest and the contractor shall deposit the
           demanded security – Then there were various rounds of
           litigation before the High Court and the Supreme Court –
           Now, finally the only issue that arises in these appeals is
           whether the security money deposited by the contractor will
           carry interest once the contract is determined:
           Held: Clause 19 is a valid binding term of the agreement – The
           two limbs of the Clause 19 have to be read together, and they are
           interdependent – While the first portion states that “it shall not carry
           any interest” and second portion of the same clause reads that
           “shall be refunded to the contractor within three months from the
           date of expiry or sooner determination of the contract” – The correct
* Author
[2026] 8 S.C.R.                                                               89

        State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.


      interpretation of this Clause would mean the Respondent’s deposit
      will earn no interest and it will be returned to the Respondent
      within three months of the contract coming to an end or within
      three months of the termination of the contract – On a proper
      reading of the Clause 19 it is clear that the Appellant cannot
      retain the money which is interest free, in perpetuity – Once the
      contract is determined then it is the obligation upon the State to
      refund the security deposit within the period prescribed in the
      agreement – If the State retains the security deposit beyond three
      months the Respondent-contractor is entitled for interest which
      is very clear from a proper reading of Clause 19 – Therefore,
      since the contract has been determined on 09.03.2000 and the
      period of three months expired on 09.06.2000, the Respondent is
      entitled to interest for the period commencing from the expiry of
      three months from the determination of the contract that is from
      09.06.2000 till the date on which the security was so adjusted
      or appropriated towards the dues payable by the Respondent to
      the Appellant. [Paras 27, 28, 29]

      Mines & Minerals (Regulation and Development) Act, 1957 –
      The Punjab Minor Minerals Concession Rules, 1964 – An
      auction notice was given for the extraction of Yamuna sand
      from Bega Murthal Sand Zone – Respondent firm was the
      highest bidder – The bid was accepted by the Appellant –
      On 30.11.1998, a contract was executed between the parties
      in terms of the Form-L – As per the said contract the
      Respondent was to deposit the contract money in advance to
      the Government on a monthly basis – Respondent defaulted
      in their installment – On 09.03.2000, after affording due
      opportunity to the Respondent and after perusing the reply,
      the contract was terminated by the Director of Mines and
      Geology – Whether the order of termination of the contract
      suffer from any illegality:
      Held: The Respondent was fully aware of the statutory Rules
      and Form as per the terms of which there are certain conditions
      to be fulfilled and failure thereof will entail certain consequences –
      Likewise, the Respondent was also aware that the security
      deposited will not carry any interest and it will be refunded within
      three months from the date of the expiry of the contract or sooner
      determination of the contract – When the Respondent signed the
      contract/agreement on 30.11.1998 as prescribed under Form-L,
90                                                             [2026] 8 S.C.R.

                          Supreme Court Reports


      it was conscious of all the clauses, especially Clause 19 which
      prescribed that the security deposited will not carry any interest –
      The order of termination of the contract was effected due to the
      failure of the Respondent in abiding by the conditions as stipulated
      in the agreement – Though the Appellant had served a notice
      on the Respondent calling upon them to make the payment of
      monthly installment failing which contract would be cancelled,
      Respondent did not abide by the same and took excuses for not
      carrying out the obligation – It has been found by the courts below
      that the order of termination of the contract does not suffer from
      any illegality particularly when the Respondent failed to respond
      even to the notice of termination – This aspect has attained
      finality, especially in view of order dated 08.05.2009 passed by
      a coordinate bench of this Court in SLP(C) Nos.9761-9762 of
      2009. [Paras 25, 26]

                              Case Law Cited
      Venkataraman Krishnamurthy and Another v. Lodha Crown
      Buildmart Private Limited (2024) 4 SCC 230 – relied on.
      National Highways Authority of India v. Ganga Enterprises and
      Another [2003] Supp. 3 SCR 114 : (2003) 7 SCC 410; Shri
      Hanuman Cotton Mills and Others v. Tata Aircraft Limited [1970]
      3 SCR 127 : (1969) 3 SCC 522 – referred to.

                                 List of Acts
      Punjab Minor Minerals Concession Rules, 1964; Mines & Minerals
      (Regulation and Development) Act, 1957.

                              List of Keywords
      Agreement; Valid agreement; Contract; Termination of contract;
      Security deposit; Interest on security deposit; Refund; Interest
      free; Perpetuity.

                             Case Arising From
      CIVIL APPELLATE JURISDICTION: Civil Appeal No(s).
      3145-3146 of 2012
      From the Judgment and Order dated 21.03.2009 of the High
      Court of Punjab and Haryana at Chandigarh in RA No. 5 of 2010
      and LPA No. 215 of 2006
[2026] 8 S.C.R.                                                        91

        State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.


                        Appearances for Parties
      Advs. for the Appellant(s):
      Akshay Amritanshu, Sarthak Srivastava.
      Advs. for the Respondent(s):
      Lalita Kaushik, Manoj Joshi, Ms. Shikha John.

                Judgment / Order of the Supreme Court

                               Judgment

      V. Mohana, J.

1.    These appeals arise out of the judgement and order dated 21.03.2009
      in LPA No. 215 of 2006 and subsequent order dated 19.03.2010
      in Review Application No. 5 of 2010 passed by the Division Bench
      of the High Court of Punjab and Haryana at Chandigarh. The only
      issue that arises for consideration in these appeals is whether the
      amount of security deposit given by the Respondent-contractor will
      carry interest despite there being a contract to the contrary between
      the Appellant and the Respondent.

      BRIEF FACTS:-
2.    The Punjab Minor Minerals Concession Rules, 1964 (for short “the
      Rules”) were notified on 25.04.1964 under the Mines & Minerals
      (Regulation and Development) Act, 1957. Rule 33 of the Rules
      provides for execution of a contract. When a bid is confirmed
      or a tender is accepted, the bidder or tenderer shall execute an
      agreement in Form-L within one month. As per Clause 1 of Form-L
      the contractors shall, during the subsistence of the contract, pay
      in advance to the Government the contract money in respect of
      the land given to them on a monthly basis. As per Clause 2 of the
      Form-L, if the contractor fails to pay instalment of contract money
      or any part thereof, under the terms and conditions of the contract,
      on the due date without written permission of the Director in that
      behalf, he will be liable to pay interest thereon at the rate of 24
      percent per annum till such amount is paid. Clause 17 stipulates that
      the contract may be terminated by the Government if considered
      by it to be in public interest by giving one-month notice. Clause 16
      stipulates that in case of default in the due observance of the terms
92                                                        [2026] 8 S.C.R.

                        Supreme Court Reports


      and conditions of the contract or in payment of the contract money
      on the due date, the contract may be terminated by the Government
      or by any officer authorised by the Government in this behalf, by
      giving one-month notice, with forfeiture of security deposit as also
      the instalment, paid in advance, if any. The contractor shall deliver
      the possession of the quarry / mine to the mining officer concerned
      within seven days of the receipt of order of termination of contract.
3.    In the very same Form, there is a Clause 19 which stipulates that the
      security deposited by the contractor(s) shall not carry any interest.
      It shall be refunded to the contractor within three months from the
      date of the expiry or sooner determination of the contract.
4.    In the instant case, an auction notice was given for the extraction
      of Yamuna sand from Bega Murthal Sand Zone on 26.03.1998.
      The auction was held on 06.04.1998 for grant of contract for the
      extraction of sand and the Respondent firm was the highest bidder
      for Rs.1.48 crores per annum for a mining contract which was for
      a period of 3 years i.e., up to 31.03.2001. The bid was accepted
      by the Appellant. On 30.11.1998, a contract was executed between
      the parties in terms of the aforementioned Form-L. As per the said
      contract the Respondent was to deposit the contract money in
      advance to the Government on a monthly basis and the amount was
      also stipulated in the contract. There were also stipulations about
      interest on delayed payment and penalty for default.
5.    After the agreement the Respondent had also given an affidavit to
      the Appellant that they will take the lands from the owners at their
      own level. Subsequently, the records show that the Respondent
      has been defaulting in their instalment due to the Appellant from the
      month of September, 1999 and a notice was issued on 19.01.2000
      for termination of the contract as prescribed in Clause 16 of the
      contract and the Respondent was called upon to give possession
      of the land.
6.    On 09.03.2000, after affording due opportunity to the Respondent
      and after perusing the reply, the contract was terminated by the
      Director of Mines and Geology and the security amount was also
      forfeited for non-observance of the terms of the agreement. By this
      order, the Respondent was also directed to immediately handover
      the possession of the Bega Murthal Sand Zone to the Mining Officer,
      Sonepat as per the terms of the contract.
[2026] 8 S.C.R.                                                          93

        State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.


7.    The Respondent took up the matter in appeal before the Appellate
      Authority which is the Director of Mines and Geology, Government
      of Haryana. By an order dated 10.07.2000, the Appellate Authority
      disposed of the appeal by holding that ends of justice would be
      met if, like in the similar cases, forfeited security money is adjusted
      against the outstanding contract money and the interest. Accordingly,
      the Appellate Authority ordered that the department shall raise the
      demand of contract money and up to date interest within a period
      of seven days of the order and the contractor shall deposit the
      demanded security within a period of one month in two fortnightly
      instalments. The Appellate Authority held that in case they deposit
      this amount within the stipulated period then the security amount
      shall be adjusted against the balance amount, but in case they fail to
      adhere to the schedule of the payment then the appeal shall stand
      rejected without any further notice to the Contractor.
8.    The Appellant served a notice upon the Respondent for depositing
      a sum of Rs.68,35,298/- out of which the Respondent seems to
      have deposited a sum of Rs.26 lakhs and requested for extension
      of time which was granted. However, the Respondent instead of
      depositing the contract money for the period up to 31.03.2000
      deposited only for the period up to 09.03.2000 on which date the
      contract was terminated.
9.    The Respondent then filed a Writ Petition being CWP No.12114
      of 2000 before the Punjab and Haryana High Court at Chandigarh
      for quashing the notice to the extent it demanded contract money
      and interest thereon at the rate of 24 percent per annum and
      also challenging the validity of Clause 19 of the agreement which
      stipulated that there is no interest payable on the amount of security
      deposited by the Respondent and further it prayed for a direction
      to be issued to the State to pay interest at the rate of 24 percent
      per annum on the amount of security till final adjustment of the
      outstanding contract money.
10.   The learned Single Judge by its judgement dated 07.10.2002 partly
      allowed the writ petition. The learned Single Judge held that the
      demand of a contract money after 09.03.2000 does not arise since
      the contract had been terminated on 09.03.2000. However, on the
      issue of entitlement of interest of security deposit as per Clause
      19 of the agreement the learned Single Judge held that the firm
94                                                           [2026] 8 S.C.R.

                          Supreme Court Reports


      has voluntarily entered into a contract with an obligation to deposit
      some amount as security with full knowledge that the same would
      not carry any interest. The learned Single Judge also noted that
      this plea had been taken when the major period of contract had
      already expired and the contractor has taken it for the first time in
      the writ petition and he cannot be permitted to assail the contract
      as unconscionable and oppressive.
11.   The Respondent-contractor thereafter filed a Special Leave Petition
      being SLP (C) No. 9491 of 2003 before this Court which was
      disposed of and this Court by its order dated 05.01.2004, after
      referring to various provisions of the agreement dated 30.11.1998,
      held that the matter needs to be re-examined by the High Court
      and remanded the same.
12.   After remand by this Court the learned Single Judge of the High
      Court re-examined the entire issue. There were predominantly two
      issues before the learned Single Judge. The first issue being whether
      the State complied with their statutory obligations when the request
      was made by the contractor, and if not, what would be the effect
      of non-compliance of the statutory obligation of the State insofar
      as they did not comply with the contractor’s request which had a
      direct bearing on the rights of the contractor. The second issue was
      whether the security deposited by the Respondent-contractor would
      carry any interest after the contract was terminated. The learned
      Single Judge, on a detailed examination of the facts and documents,
      and after analysing the contentions, came to the conclusion that the
      contractor has failed to prove that State has failed to comply with
      their statutory obligations. The learned Single Judge also found that
      there was nothing to show that the contractor was not permitted
      to carry out the mining or that the termination was as the result of
      non-compliance of statutory obligations by the authorities. Finally,
      the learned Single Judge held that the contractor had failed to abide
      by the terms and conditions of the agreement dated 30.11.1998 and
      had failed to pay monthly instalments, as stipulated, therefore the
      order of termination of the contract does not suffer from any illegality.
      It held that the contractor himself was responsible for not extracting
      sand from the licensed land and for his failure to comply with the
      provisions of Clause 27 of the agreement. However, the learned
      Single Judge held that the demand for the period from 10.03.2000
      to 07.04.2000 is not justified as the Respondent herein was denied
[2026] 8 S.C.R.                                                         95

        State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.


      the right to extract sand after termination of the contract vide order
      dated 09.03.2000, therefore, the claim made by the State for this
      period was set aside.
13.   The learned Single Judge held that Clause 19 is “unsustainable in
      law” and directed the Appellant herein to refund the security amount
      of Rs. 37 lakhs with interest at the rate of 9 percent per annum from
      the date of its deposit.
14.   The Appellants herein filed LPA No.215 of 2006 and the Respondent
      herein also filed LPA No.85 of 2007 before the High Court of Punjab
      and Haryana at Chandigarh. The Division Bench of the High Court
      dismissed both the appeals filed by the parties and upheld the
      judgement of the learned Single Judge.
15.   The Respondent subsequently filed SLP(C) Nos.9761-9762 of 2009
      which were dismissed by this Court by its order dated 08.05.2009.
      Subsequent Review Petition and Curative Petition have also
      been dismissed by this Court by its orders dated 22.07.2009 and
      08.12.2009, respectively.
16.   A subsequent SLP was filed by the Appellant herein which was
      disposed of by this Court by an order dated 14.12.2009 granting
      liberty to the Appellant to file a Review Petition before the High
      Court. It appears that the Appellant had filed a Review Petition in
      the High Court which was also dismissed by the second impugned
      order. The Appellant is before us challenging both the orders.
17.   Initially this Court had issued notice on 07.03.2011 and stayed the
      operation of the impugned orders. Subsequently, by an order dated
      16.03.2012 this Court granted leave and made the interim order
      absolute till the disposal of the appeal.
18.   The only issue that arises in these appeals is whether the security
      money deposited by the contractor will carry interest once the
      contract is determined.
19.   Heard Mr. Akshay Amritanshu, ably assisted by Mr. Sarthak
      Srivastava, learned counsel for the Appellants, and Mr. Manoj Joshi
      ably assisted by Ms. Shikha John and Mrs. Lalita Kaushik, learned
      counsel for the Respondent, and perused the documents on record.
20.   The Appellant submitted that the High Court could not have rewritten
      the contract between the parties nor it could have substituted its
96                                                           [2026] 8 S.C.R.

                          Supreme Court Reports


      own terms in the agreement that the parties have arrived at. It
      was further submitted that Clause 19 was an express term which
      was unambiguous and it was standard statutory form accepted by
      the Respondent in an open commercial tender which was never
      challenged by the Respondent during the currency of the agreement
      or even when the Respondent filed statutory appeal before the
      authorities and the challenge was raised for the first time in the
      writ petition. It was further submitted that the security deposit paid
      by the contractor is always kept in a non-interest bearing Treasury
      Head (8443-Civil Deposit and Advances) and that the department is
      not doing any banking business and it does not earn anything from
      out of the security deposit. The purpose of the security works as a
      deterrent for securing performance and finally it was submitted that
      the reasoning of the High Court that the interest should be paid on
      the security because the State charges interest on instalments is not
      correct as the interest charged under Clause 2 of the agreement is
      only as a compensation for the default of the contractor.
21.   Learned Counsel for the Respondent supported the impugned
      judgment and he submitted that contract was unconscionable, one
      sided and in favor of the State, and that while on the one hand the
      State is charging interest on the contractor for delay in payments
      and for non-performance, it is denying the contractor interest on his
      own security. He submitted that the judgment of the High Court is
      founded on equity, justice and good conscience and ought not to
      be disturbed on technical reasons and that the contract had been
      frustrated by failure of the State in procuring the land under Clause 27.

      ANALYSIS AND CONCLUSION:-
22.   Form-L, prescribed under Rules 28A and 33 of the Rules, prescribes
      the form in which a contract will be executed when a bid is confirmed
      or a tender is accepted. The relevant clauses in Form-L, which is
      prescribed under the Rules, are mentioned below:-
            “1. Amount and mode of payment of contract money:
            The contractor/contractors shall during the subsistance
            of the contract pay in advance to the Government the
            following contract money in respect of the said land
            given to him on contract for the period from _____ to
            _____ on the dates mentioned below:-
[2026] 8 S.C.R.                                                                        97

        State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.



                    Number of Instalments                 Amount of       The date
                                                         instalments      on which
                                                                       instalments is
                                                                         to be paid
                                1                            2                3
             (a) In case of contract where the          Rs. ______     1.4.19____
             annual contract money does not             (annual
             exceed Rs. 1000/- in annual instalment     contract       1.4.19____
             after adjusting Rs. ______ as contract     money)         1.4.19____
             money for the period from ____ to
             31.03.19 _____ remaining amount of                        1.4.19____
             Rs. _____ out Rs. _____ (deposited
                                                                       And so on
             at the time of auction) is adjustable
             against the annual instalment falling
             due from 1.4.19__
             (b) In case of contract where the annual   Rs. ______     1.4.19____
             contract money exceed Rs. 1000/- and       (quarterly
             does not exceed Rs. 5 lacs in quarterly    instalment     1.7.19____
             instalments after adjusting Rs. _____      of contract    1.10.19____
             as contract money for the period from      money)
             _____ to ____ remaining amount of                         1.1.19_____
             Rs. _____ out of Rs. ____ (Advance
                                                                       And so on
             quarterly instalment deposited at the
             time of auction) is adjustable against
             the quarterly instalment falling due
             from 1st of ______
             (c) In case of contract where the          Rs. ______     1.1.19____
             annual contract money exceeds              (monthly
             Rs. 5 lacs in monthly instalments          instalment     1.2.19____
             after adjusting Rs. ____ as contract       of contract    1.3.19____
             money for the period from _____ to         money)
             _____ remaining amount of Rs. _____                       1.4.19____
             out of Rs. _____ (advance monthly
                                                                       1.5.19____
             instalment) is adjustable against the
             monthly instalment falling due from                       1.6.19____
             ____ 19 _____.
                                                                       1.7.19____
                                                                       1.8.19____
                                                                       1.9.19____
                                                                       1.10.19____
                                                                       1.11.19____
                                                                       1.12.19____
                                                                       And so on

            Money for the subsequent years of the contract shall be
            paid by the contractor/contractors in advance in equal
            monthly/quarterly/yearly instalments.]
98                                                          [2026] 8 S.C.R.

                         Supreme Court Reports


            2. Interest for delayed payment:- If the contractor (s)
            fails to pay instalment of contract money or any part
            thereof due to the Government under the terms of the
            conditions of the contract on the due date without written
            permission of the Director in that behalf, he/they will be
            liable to pay interest thereon at the rate of *[twenty four
            percent] per annum till such amount is paid: Provided
            that no interest shall be payable if the amount is paid
            within three days in case the annual contract money
            does not exceed five lacs and within 7 days in case the
            annual contract money exceed Rs. 5 lacs.
            16. Penalty for default:- In case of default in the due
            observance of the terms and conditions of the contract
            or in payment of the contract money on the due date,
            the contract may be terminated by the Government or
            by any officer authorised by Government in this behalf,
            by giving one month’s notice, with forfeiture of security
            deposit as also the instalment, paid in advance, if any.
            18. Recovery of contract money as arrears of land
            revenue:- Any sum due from the Contractor/Contractors
            on account of contract money in respect of the contract,
            shall be recovered from him/them as arrears of land
            revenue.
            19. Security deposit shall carry no interest:- The
            security deposited by the Contractor/Contractors shall not
            carry any interest. It shall be refunded to the Contractor
            within three months from the date of expiry or sooner
            determination of the contract.”
23.   It is well settled that in matters of contract between the parties the
      function of a Court is to interpret and enforce the terms as has
      been agreed between parties. The Court will not re-write the terms
      howsoever reasonable the substituted term may appear to be. In
      matters of commercial contracts where the parties stand on equal
      footing and have committed to certain unambiguous terms, the
      language of the contract is to be clearly looked into and parties are
      bound by the same. Once the parties with their eyes open without
      any protest whatsoever and with free will accept certain terms of a
      contract they cannot afterwards be permitted to go back on the same
[2026] 8 S.C.R.                                                               99

           State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.


        merely because at a later point of time the stipulation proves to be
        onerous. The agreed forfeiture/security stipulation is to be enforced
        according to the terms of the contract as held in National Highways
        Authority of India v. Ganga Enterprises And Another1, and Shri
        Hanuman Cotton Mills and Others Vs. Tata Aircraft Limited2.
24.     In Venkataraman Krishnamurthy And Another v. Lodha Crown
        Buildmart Private Limited 3 this Court held as under:-
                “21. In this regard, we may refer to the Constitution
                Bench decision in General Assurance Society Ltd. v.
                Chandumull Jain , wherein it was observed that, in
                interpreting documents relating to a contract of insurance,
                the duty of the court is to interpret the words in which the
                contract is expressed by the parties because it is not for
                the court to make a new contract, however reasonable,
                if the parties have not made it themselves. Thereafter,
                in Rajasthan State Industrial Development & Investment
                Corpn. v. Diamond & Gem Development Corporation Ltd,
                this Court reiterated that a contract, being a creature
                of an agreement between two or more parties, is to
                be interpreted giving the actual meaning to the words
                contained in the contract and it is not permissible for the
                court to make a new contract, however reasonable, if
                the parties have not made it themselves.
                22. More recently, in Shree Ambica Medical Stores v.
                Surat People’s Coop. Bank Ltd., it was observed that,
                through its interpretative process, the court cannot rewrite
                or create a new contract between the parties and has to
                simply apply the terms and conditions of the agreement
                as agreed between the parties. Again, in GMR Warora
                Energy Ltd. v. CERC, it was observed that courts cannot
                substitute their own view of the presumed understanding
                of commercial terms by the parties, if the terms are
                explicitly expressed. It was held that the explicit terms
                of a contract are always the final word with regard to
                the intention of the parties.”


1     (2003) 7 SCC 410
2     (1969) 3 SCC 522
3    (2024) 4 SCC 230
100                                                          [2026] 8 S.C.R.

                          Supreme Court Reports


25.    The Respondent was fully aware of the statutory Rules and Form
       as per the terms of which there are certain conditions to be fulfilled
       and failure thereof will entail certain consequences. Likewise, the
       Respondent was also aware that the security deposited will not
       carry any interest and it will be refunded within three months from
       the date of the expiry of the contract or sooner determination of
       the contract. The Respondent had at least two opportunities of
       perusing the terms and conditions. Despite knowing the existence
       of the clause, the Respondent applied for the bid and became
       a successful bidder. Secondly when the Respondent signed the
       contract/agreement on 30.11.1998 as prescribed under Form-L,
       it was conscious of all the clauses, especially Clause 19 which
       prescribed that the security deposited will not carry any interest.
       It is not the case of the Respondent that it had been coerced into
       signing the contract nor is it the case that when the contract was
       signed it was under some mistake or undue influence. Respondent
       has voluntarily entered into the contract by which they were obliged to
       deposit the amount as prescribed therein and the failure would result
       in termination. It has been consistently held by the learned Single
       Judge and the Division Bench of the High Court that the termination
       of the contract was purely by the conduct of the Respondent and it
       was the Respondent who is to be blamed for non-performance and
       for not depositing the monthly payments on time. The courts below
       have clearly examined the conditions and the exchange of letters and
       notices between the parties and have finally concluded that there
       was no failure on the part of the Appellant for non-performance of
       the contract by the Respondent.
26.    It has been consistently found that the order of termination of
       the contract was effected due to the failure of the Respondent in
       abiding by the conditions as stipulated in the agreement. It has been
       noticed that after one year of the execution of the agreement the
       Respondent-company sent a letter to the Appellant stating that they
       have been obstructed by the land owners and, therefore, they are
       unable to carry out the mining. However, it has been found that the
       Respondent did not carry out the mining on their own and they have
       had made up a false plea with regard to the issuance of a notice in
       order to secure benefits from the Department. The Respondent was
       also required to submit a monthly return about sand extracted and if
       it was not extracting any sand due to problems created by the land
       owners then it would certainly submit a monthly report to that effect
[2026] 8 S.C.R.                                                          101

        State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.


      mentioning therein that extraction of the sand is Nil. It was clearly
      found by the High Court that the Respondent was negligent in not
      reporting the matter though they were working in other villages and
      carrying out mining. Though the Appellant had served a notice on
      the Respondent calling upon them to make the payment of monthly
      instalment failing which contract would be cancelled, Respondent
      did not abide by the same and took excuses for not carrying out
      the obligation. Therefore, it has been found by the courts below that
      the order of termination of the contract does not suffer from any
      illegality particularly when the Respondent failed to respond even
      to the notice of termination. This aspect has also attained finality,
      especially in view of order dated 08.05.2009 passed by a coordinate
      bench of this Court in SLP(C) Nos.9761-9762 of 2009.
27.   The High Court fell into error in declaring Clause 19 as unsustainable
      in law and against public policy. The public policy cannot be pressed
      into service to set at naught the commercial contract which expressly
      denies interest on security deposit. Such a stipulation is neither
      immoral nor unlawful nor can it be classified as unsustainable in the
      legal sense. The Respondent as a commercial entity had participated
      in open auction and emerged as the highest bidder and executed
      the standard statutory Form-L with full knowledge and furnished an
      undertaking to abide by the same. Once parties have voluntarily
      accepted a contract they cannot turn around and assail the same as
      oppressive after major part of the contract period has gotten over.
      The reasoning of the High Court that when State charges interest on
      belated instalment they should pay interest on the security does not
      stand scrutiny. The stipulations in Clause 2 and in Clause 19 operate
      in different fields and they serve different purposes. While Clause 2
      provides for liquidated damages or compensation which is payable
      or referable to the contractor’s default on the timely payment which
      is a consequence of the contractor’s own breach, the security deposit
      in Clause 19 is a performance guarantee held by the State and the
      parties have clearly agreed that it would carry no interest. There is
      no reciprocal obligation upon the State to pay interest on the security.
      In fact, both the Clauses are seen in the same contract which has
      been agreed between both the parties with their eyes open. To reason
      otherwise and without interpreting the contract as agreed but to add
      new terms which were not admittedly written therein amounts to re-
      writing the contract which a Writ Court is not entitled to do.
102                                                          [2026] 8 S.C.R.

                          Supreme Court Reports


28.    Hence, it is held that Clause 19 is a valid binding term of the
       agreement and the finding of the learned Single Judge as affirmed
       by the Division Bench that Clause 19 is unsustainable in law and
       opposed to public policy is set-aside.
29.    Having held as above, it is to be seen that Clause 19 of the agreement
       is in two parts. Clause 19 is extracted hereinbelow:-
             “19. Security deposit shall carry no interest:- The
             security deposited by the Contractor/Contractors shall not
             carry any interest. It shall be refunded to the Contractor
             within three months from the date of expiry or sooner
             determination of the contract.”
       The two limbs of the Clause 19 have to be read together, and they
       are interdependent. While the first portion states that “it shall not
       carry any interest” and second portion of the same clause reads that
       “shall be refunded to the contractor within three months from the
       date of expiry or sooner determination of the contract.” The correct
       interpretation of this Clause would mean the Respondent’s deposit
       will earn no interest and it will be returned to the Respondent within
       three months of the contract coming to an end or within three months
       of the termination of the contract. On a proper reading of the Clause
       19 it is clear that the Appellant cannot retain the money which is
       interest free, in perpetuity. It does not clothe the Appellant with the
       power to read the first portion of the Clause in isolation without
       any limitation on time, therefore, while the first portion states that
       security deposited will carry no interest, the same clause would read
       further that it shall be refunded within three months from the date
       of expiry or sooner determination of the contract. Once the contract
       is determined then it is the obligation upon the State to refund the
       security deposit within the period prescribed in the agreement. If
       the State retains the security deposit beyond three months the
       Respondent-contractor is entitled for interest which is very clear
       from a proper reading of Clause 19. While the Clause 19 states
       that there is no interest from the date of deposit while securing it,
       once it is determined, the amount cannot be withheld by the State
       beyond three months as provided in the clause itself.
30.    Therefore, since the contract has been determined on 09.03.2000 and
       the period of three months expired on 09.06.2000, the Respondent
       is entitled to interest for the period commencing from the expiry of
[2026] 8 S.C.R.                                                           103

           State of Haryana & Ors. v. M/s Jai Durgaa Finvest P. Ltd.


      three months from the determination of the contract that is from
      09.06.2000 till the date on which the security was so adjusted or
      appropriated towards the dues payable by the Respondent to the
      Appellant. The direction of the High Court that the security deposit
      will carry interest from the date of deposit is erroneous and is
      contrary to the agreed terms of the contract and therefore, the said
      direction is set aside.
31.   Having regard to the above, the rate of interest as fixed by the High
      Court at 9 percent per annum is reasonable and we see no reason
      to disturb the same.
32.   In the result the Appeals are partly allowed in the following terms:-
      A.       The judgment of the learned single Judge dated 04.08.2006
               as affirmed by the Division Bench on 21.03.2009 and the
               order dated 19.03.2010 dismissing the review insofar as they
               declare Clause 19 of the Form-L to be unsustainable in law
               and granting interest at 9 percent per annum on the security
               amount from the date of its deposit is set aside;
      B.       Clause 19 is declared to be valid and binding in term of the
               contract and no interest is payable on security deposit of Rs.37
               lakhs for the period up to expiry of three months from the
               date of determination of the contract, i.e., up to 09.06.2000;
      C.       The Respondent shall be entitled to simple interest at the
               rate of 9 percent per annum on the security deposit for the
               period commencing from 09.06.2000 and ending on the date
               on which the said amount was appropriated towards the dues
               or refunded to the Respondent; and
      D.       There shall be no order as to cost.
33.   The Appeals are allowed and disposed of accordingly.

      Result of the case: Appeals allowed.




      †
          Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.