STATE OF ANDHRA PRADESHversusN. RADHAKISHAN
- Citation
- 1998 INSC 175
- Decided
- 7 April 1998
- Disposal
- Dismissed
- Bench
- SUJATA V MANOHAR
Holding
Unexplained delay in disciplinary proceedings prejudices the employee, and in this case the Tribunal was correctly justified in quashing the 31‑July‑1995 charge memo and ordering promotion.
Summary
The respondent, an Assistant Town Planner, was charged under the 1963 Andhra Pradesh Civil Services (CCA) Rules for alleged involvement in unauthorized constructions, based on a 1987 anti‑corruption report. No substantive inquiry was conducted despite the appointment of several inquiry officers, and the charge memo remained pending for years. After the 1991 Rules came into force, a fresh charge memo was issued in July 1995 without cancelling the earlier one, and the respondent was recommended for promotion by the Departmental Promotion Committee. Subsequent charge memos were served in October 1995 and June 1996, and the promotion was withheld. The Andhra Pradesh Administrative Tribunal quashed the July 1995 memo and ordered promotion, ignoring the later memos. The State appealed, arguing that the Tribunal erred. The Supreme Court held that there is no universal rule for delay in disciplinary proceedings; each case must be examined on its facts, and unexplained delay prejudices the employee. Applying this principle, the Court upheld the Tribunal’s decision to quash the 1995 memo and direct promotion, finding the delay unjustified and the later memos irrelevant to the promotion.
Issues considered
- The delay in concluding the disciplinary proceedings vitiates the charge memo and the disciplinary process.
- Whether the Tribunal was justified in quashing the charge memo dated 31‑July‑1995 and directing promotion despite subsequent charge memos.
Subjects
Judgment
STATE OF ANDHRA PRADESH A
v.
N. RADHAKISHAN
APRIL 7, 1998
[SUJATA V. MANOHAR AND D.P. WADHWA, JJ.] B
Service Law :
Andhra Pradesh Civil Services (CCA) Rules, 1963: Rule 19.
Departmental Enquiry-Delay in conclusion of-Not explained-
c
.Proceedings-Vitiating of-Promotion-Effect of-Employee recommended
for promotion by DPC during pendency of charge memo-Subsequently, two
charge memos served on employee-Held: No pre-determined principles
applicable to all cases and all situations can be laid down-Each case has
to be examined taking into consideration all relevant factors-Court has to D
balance between clean and honest administration and the prejudice that
delay causes to the employee-Further unexplained delay in concluding the
proceeding itself causes prejudice to the employee-In the circumstances of
the case, employee directed to be promoted on the basis of recommendations
of DPC-Two subsequent charge memos also directed to be ignored for the E
purpose of promotion-Andhra Pradesh Civil Services (CCA) Rules, 1991,
Rr. 20, 21 and 45.
Departmental 'Enquiry-Charges-General in nature-Framing a/-
Against several employee of Municipal Corporation for unauthorised
construction with their collusion-On basis of report of Anti Corruption F
Bureau-All charges in verbatim without particularising role of each
employee-Held: Such generalisation of charges, deprecated.
Department Enquiry - Charge memo-Issue of fresh charge memos-
Charge memo issued in 1987 under old rules-Enquiry Officer appointed one G
after the other but no progress made-Subsequently, two charge memos
issued in 1995 under new Rules without cancelling the earlier one-New
Rules provided for continua'1CI! of proceedings initiated under old Rules-
He/d: Issue of new charge memos did not causes any prejudice to the delinquent
employee because previous enquiry did not make any progress-Hence,
initiation of fresh proceedings without cancelling the previous one, only an H
693
694 SUPREME COURT REPORTS [1998] 2 S.C.R.
A irregularity and not an illegality.
The respondent was working as Assistant Town Planner in a Municipal
Corporation. The Director General, Anti Corruption Bureau sent a report
dated 7-11-1987 to the State Government about the irregularities and
unauthorised constructions in multi-storied complexes in collusion with
B Municipal authorities.
On the basis of the aforesaid report a charge memo dated 12-12-1987
was served on the respondent and ten others, all in verbatim without
particularising the role of each employee, under Rule 19 of the Andhra
C Pradesh Civil Services (CCA) Rules, 1963. Although several enquiry officers
were appointed one after the other no progress was made in the enquiry.
There was no valid explanation for the delay. However, without cancelling the
earlier charge memo a fresh charge memo dated 31-7-1995 was served on
the respondent on the ground that in the meantime the Andhra Pradesh Civil
Services (CCA) Rules, 1991 had come into force. Out of four charges in this
D new charge memo the respondent was not involved in three charges. During
the pendency of the new charge memo the respondent was recommended for ~
promotion by the Departmental Promotion Committee (DPC). Subsequently,
two more charge memo~ dated 27-10-1995 and 1-6-1996 were served on the
respondent and in spite of the recommendations of the DPC the respondent
wa:i not promoted.
E
Being aggrieved, the respondent filed an application before the State
Administrative Tribunal which quashed the memo dated 31-7-1995 and
directed that the respondent be promoted on the basis of the recommendations
of the DPC without taking into consideration the subsequent two charge
F memos. Hence this appeal.
Dismissing the appeal, this Court.
HELD : 1.1. It is not possible to lay down any pre-determined principles
applicable to all cases and in all situations where there is delay in concluding
G the disciplinary proceedings. Whether on that ground the disciplinary
proceedings are to be terminated, each case has to be examined on the facts
and circumstances in that case. The essence of the matter is that the court
has to take into consideration all relevant factors and to balance and weigh
them to determine if it is in the interest of clean and honest administration
that the disciplinary proceedings should be allowed to terminate after delay
H particularly when delay is abnormal and there is no explanation for the delay.
STATE v. N. RADHAKISHAN 695
The delinquent employee has a right that disciplinary proceedings against A
him are concluded expeditiously and he is not made to undergo mental agony
and also monetary loss when these are unnecessarily prolonged without any
fault on his pa11 in delaying the proceedings. In considering whether delay
has vitiated the disciplinary proceedings the Court has to consider the
nature of charge, its complexity and on what account the delay has occurred. B
If the delay is unexplained, Jlrejudice to the delinquent employee is writ large
on the face of it. It could also be seen as to how much disciplinary authority
is serious in pursuing the charges against its employee. It is the basic
principle of adminh1rative justice that an officer entnu.1ed with a pa11icular
job has to 11e1form his duties honestly, etlicicntly and in accordance with the
rules. If he deviates from this path he is to suffer a penalty prescribed. C
Normally, disciplinary proceedings should be allowed to take its course as
per relevant rules but then delay defeats justice. Delay causes prejudice to
the charged officer unless it can be shown that he is to blame for the delay
in conducting the disciplinary proceedings. Ultimately, the court is to balance
these two diverse considerations. [707-B-F)
D
1.2. In the )!resent case it is found that without any reference to
records merely on the re)lort of the Director General, Anti Corru)ltion
Bureau, charges, which are general in nature, were framed against the
respondent and ten others all in verbatim and without particularising the
role played by each of the officers charged. There were four charges against E
the respondent. With three of them the res)londent was not concerned. The
respondent offered explanation regarding the fourth charge but the disciplinary
authmity did not examine the same nor did it choose to appoint any inquiry
officer even assuming that action was validly being initiated under the
Andhra Pradesh Civil Services (CCA) Rules, 1991. There is no explanation
whatsoever for delay in concluding the inquiry proceedings all these years. F
The case depended on records of the Depa11ment only and Director General,
Anti Cmruption Bureau had pointed out that no witnesses had been examined
before he gave his repm1. The Inquiry Officers, who had been appointed one
after the other, had just to examine the records to sec if the alleged deviations
and constructions were illegal and unauthorised and then- as to who was G
responsible for condoning or approving the same against the bye-laws. It is
nobody's case that respondent at any stage ti;ied to obstruct or delay the
inquiry proceedings. The Tribunal rightly did not accept the explanations of
the State as to why delay occurred. In fact there was hardly any explanations
worth consideration. In the circumstances the Tribunal was justified in
quashing the charge memo dated 31-7-1995 amt directing the State to promote H
~-
696 SUPREME COURT REPORTS (1998] 2 S.C.R
A the resJlondent as Jler recommendations of the DPC ignoring the charge
memos dated 27-10-1995 and 1-6-1996. [707-G-H; 708-A-C]
- State of Punjab v. Chaman Lal Goyal, (1995] 2 SCC 570 and A.R.
Antulay v. R.S. Nayak, (1992) 1 SCC 225, referred to.
'r
-
B 2. Jt is an undis)luted fact that without cancelling the charge memo
dated 22-12-1987 another charge memo dated 31-7-1995 was served on the
res)londent under the 1991 Rules. The enquiry Jlroceedings initiated under
the Andhra Pradesh Civil Sen•ices (CCA) Rules coul!I be continued even
after coming into force of the 1991 Rules. Therefore, in the Jlresent case
inuse of a fresh charge memo dated 31-7-1995 could be only an in-egularity
c and not an illegality because there has been no )lrogress in the Jlrevious
enquiry Jlroceedings. [705-E-H)
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3503 of
1997.
D From the Judgment and Order dated 12.12.96 of the Andhra Pradesh ~
Administrative Tribunal in O.A. No. 2239 of 1996.
Ms. K. Amareshwari, VR. Anumolu and T. Anil Kumar for the Appellant.
H.S. Gururaja Rao and T.V Ratnam for the Respondent.
E
The Judgment of the Court was delivered by
WAD HWA, J. Against the judgment dated December 12, 1996 of the
Andhra Pradesh Administrative Tribunal, Hyderabad, in O.A. No. 2239/96
filed by the respondent, the State of Andhra pradesh has come up in appeal.
F By the impugned judgment the Tribunal allowed the petition of the respondent >-
and directed that the respondent be promoted to the category of Director of .,.._
Town and Country Planning, in the existing vacancy, ignoring the charge
memos- (1) Memo No. 2732/FL/87/27/MA, dated July 31, 1995; (2) memo No.
145/82/93-19/MA, dated October 27, 1995; and (3) Memo No. 898/B.2/94/M.A
dated June I, 1996, if the respondent is otherwise eligible. The Tribunal found
G that the Departmental Promotion Committee met on August 16, 1995 and
prepared the panel for the panel year 1994-95, which was approved by the ,._
State Government in October, 1995. One of the persons included in the panel
was promoted to the category of Director of Town and Country Planning by
G.O.M. dated November 14, 1995. The Tribunal observed that the panel itself
H having been prepared on August 16, 1995 should lapse only on December 31,
STATE v. N. RADHAKISHAN [WADHWA, J.] 697
1996 and not on December 31, 1995 as was contended by the State. The name A
of the respondent was included in the panel. The Tribunal, therefore, held that
since the panel would lapse only on December 31, 1996 the respondent was
entitled for promotion before that date. The Tribunal also noticed that the
objection of the State that the panel lapsed on December 31, 1995 was never
raised either before it or in the Supreme Court in a Special Leave Petition filed B
by the State against an interim order earlier made by the Tribunal.
Tribunal was concerned with the question if promotion of the respondent
could be denied to him after his name had been included in the panel prepared
by the DPC on the ground that the disciplinary inquiry initiated against him
had not yet been terminated. The respondent had submitted before the Tribunal C
that the charge memo dated July 31, 1995 was served upon him just before
the meeting of the DPC only to deprive him his claim of promotion and further
that the charge memos dated October 27, 1995 and June 1, 1996 being
subsequent to the date of meeting of DPC could not be taken into consideration
for promoting him to the post of Director, Town and Country Planning. D
Tribunal noticed that the memo dated July 31, 1995 related to the incidents
that happened in the years 1978, 1979 and 1984, which were also the subject-
matter of the memo No. 1412 dated December 22, 1987. While the memo No.
1412 had been issued under Rule 19 of the Andhra Pradesh Civil Services
(CCA) Rules, 1963 (for short" 1963 Rules") that dated July 31, 1995 was issued
under Rule 20 of the Andhra Pradesh Civil Services (CCA) Rules, 1991 (for E
short "1991 Rules"). Earlier memo No. 1412 was neither cancelled nor annulled
before issuance of memo dated July 31, 1995 and the Tribunal was of the view
that because of this circumstance memo dated July 31, 1995 could not have
been issued and inquiry should have proceeded under the old Rules after the
Inquiry Officer had been appointed. F
State has contended before us that the Tribunal wrongly assumed that
the charges communicated to the respondent on July 31, 199 5 were belated
and not only that it quashed that charge memo but also other charge memos
when there was no challenge to that. Merely on the ground of delay the
Tribunal should not have conferred unwanted benefits on the respondent. It G
was submitted that the whole approach of the Tribunal in giving relief to the
""l" °"' respondent has been the delay in not concluding the inquiry in furtherance
to the charge memo. It may, however, be noticed that the respondent did seek
setting aside of the memo dated July 31, 1995 and that dated October 27, 1995.
The Tribunal only quashed memo dated July 31, 1995 and as regards memos H
698 SUPREME COURT REPORTS (1998] 2 S.C.R
A dated October 27, 1995 and June I, 1996, it said that the State might proceed.
against the respondent for taking action as per law but the only rider which
the Tribunal put was that these two memos could not be taken into
consideration in implementing the recommendation of the DPC.
B Whether the delay did vitiate the disciplinary proceedings and if the
Tribunal was justified in giving the directions aforesaid we may refer to the
sequence of the events.
The respondent was appointed as Asstt. Director of Town Planning in
the year 1976. He worked in the Municipal Corporation of Hyderabad
C (hereinafter referred to as ·Corporation') in 1979. He was posted as City
Planner, Municipal Corporation of Visakhapatnam in 1981. A report dated
November 7, 1987 was sent by the Director General, Anti-Corruption Bureau,
Andhra Pradesh, Hyderabad, to the Secretary to the Government, Housing,
Municipal Administration & Urban Development Department, Andl1ra Pradesh,
D Hyderabad, about the irregularities in deviations and unauthorised
constructions in multi-storied complexes in twin cities of Hyderabad and
Secunderabad in collusion with Municipal authorities.
In this report four multi-storied buildings were mentioned, viz.,
Chandralok Complex, Chenoy Market Commercial Complex, Shajahan
E Apartments and Progressive Towers. It was stated that in September, 1987
these premises were inspected and irregularities in deviations and unauthorised
construction were noticed and the relevant files of the Corporation were also
perused. Town Planning Staff of the Corporation in collusion with the builders
permitted them to flout building bye-laws and the staff abused their official
F position for obtaining pecuniary advantage for themselves and the builders
causing loss of revenue to the Corporation in the shape of house-taxes.
Eleven officers were named including the respondent, who were said to be
responsible for the abnormal deviations and unauthorised constructions.
-
On the basis of the report the State issued two memos both dated
G December 12, 1987 (!) in respect of three officials, viz., Radha Krishna, the
then Asstt. City Planner, the respondent, (2) P. V Janaki Raman, the then City
Planner and (3) A. Ram Reddy, the then Asstt. City Planner. In the second
memo seven other officers of the rank of Section Officers and one Assistant
City Planner were named. The memo respecting the respondent and two
H others said that under Rule 19(2) of 1963 Rules one Sri N. Venugopal Reddy,
STATE v. N. RADHAKJSHAN [WADHWA, J.] 699
Director of Town and Country Planning, Andhra Pradesh, Hyderabad, was A
appointed as Inquiry Officer to conduct a detailed inquiry against them, who
were allegedly involved and found responsible for the irregularities. The
Inquiry Officer was directed to complete his inquiry within a period of two
months and to submit his report to the Government with specific findings. As
we see this memo is entirely based on the report of the Director General, Anti- B
Corruption Bureau. In one of the letters 'dated January 7,1988 of the Director
,.__ General Anti-Corruption Bureau, it is mentioned that during the course of the
checking of the buildings witnesses were neither examined nor their statements
were recorded and as such there was no part-B file. It was suggested that
action be taken on the basis of the report already sent to the Government.
Rule 19(2) of the 1963 Rules requires that when it is proposed to impose on C
. a member of a service any of the penalties specified therein the authority
competent to impose the penalty shall appoint an inquiry officer or itself hold
an inquiry. In every such case the ground on which it is proposed to take
action shall be reduced to the form of definite charges, which shall be
communicated to the person charged together with a statement of the D
allegations on which each charge is based and any of other circumstances
which it is proposed to take into consideration in passing orders in the case.
The charged employee shall be required within a reasonable time to file a
written statement of his defence and to state whether he desires an oral
inquiry or to be heard in person or both. It is not necessary to refer to further E
steps in the inquiry proceedings as in the present case we find that till July
31, 1995 article of charges had not been served on the respondent by which
time 1991 Rules had come into force in supersession of the t:arlier 1963 Rules.
Rule 45 of 1991 Rules provided that repeal shall not affect the previous
operation of 1963 Rules, or any notification or order made, or anything done, p
or any action taken thereunder, in any proceeding under those Rules pending
at the commencement of 1991 Rules and shall be continued and disposed of
as far as may be in accordance with the provisions of 1991 Rules. In 1991
Rules procedure for imposing penalties had been changed by Rules 20 and
21. Now, the Inquiry Officer is to be appointed after written statement of the G
defence of the charged employee has been received. When it is proposed to
hold inquiry against a Government servant, the disciplinary authority is required
to draw up the substance of the imputations of misconduct or misbehaviour
into definite and distinci article of charge; a statement of the imputations of
misconduct or misbehaviour in support of each article of charge containing
(a) a statement of all relevant facts (b) list of documents and (c) list of H
700 SUPREME COURT REPORTS [1998] 2 S. C.R.
A witnesses. These shall be served upon the Government Servant. who shall be
required to s11bmit written statement in defence and to state whether he
desires to be heard in person. If on receipt of the written statement of the
defence the disciplinary authority finds that it is necessary to inquire into the
charges, it shall appoint an Inquiry Officer of the purpose. Of course. the
B disciplinary authority can itself inquire into the article of charges, if it so
chooses or thinks to do so. Again, we are not concerned as to how the
inquiry officer is to proceed further in the matter as per 1991 Rules as after
the article of charge was served upon the respondent and his statement of
defence was received there was no progress and he moved the Tribunal.
C Coming back to the stage when Shri N. Venugopal Reddy was appointed
as Inquiry Officer we find from the official file produced before us that he sent
various communications to the Secretary to the Government. Housing,
Municipal Administration & Urban Development Department, to send him the
relevant files. This he went on writing but without any response from the
State Government till Shri N. Venugopal Reddy retired on attaining the age
D of superannuation on September 30, 1991. As to why there was no response
to various letters of the Inquiry Officer from the State Government the file
does not ·reveal anything. Meanwhile respondent was promoted as Joint
Director of Town and Country Planning on September IO, 1991. Thereafter, the
State Government appointed Sri P.B. Chowdhary, O.S.D. (legal cases), Municipal
E Corporation of Hyderabad, as Inquiry Officer by order dated September 7,
I 992. Shri Chowdhary did not submit the inquiry report and his term of office
as O.S.D. (legal cases) expired on November 20, 1992. Again, orders were
issued on March 6, 1993 appointing Shri A. Vidyasagar, I.A.S., Additional
Commissioner of the Corporation as Inquiry Officer. He was transferred from
his post on May 25, 1993. Yet again orders mere issued on June 17, 1993
F appointing Shri Adityanath Dass, IAS, Additional Commissioner (Genl.) of
the Corporation, as Inquiry Officer. On August 16, I 994 Shri Dass informed
the authorities concerned that connected files and records have been received
from the appropriate authority .. recently" and promised that he would submit
his report as early as possible. No report was submitted and Shri Dass was
G transferred from the post. Thereafter, orders were issued on March 20, 1995
appointing Shri M.Veerahhadraiah, !AS, O.S.D. oft11e Corporation, as Inquiry
Officer. At this stage it was observed that procedure as contained in 1991
Rules had not been followed. Therefore, the order dated March 20, 1995
appointing Shri M. Veerahhadraiah as Inquiry Officer was cancelled by order
dated June 16, 1995. It was at this stage that articles of charges dated July
H 31, 1995 were issued to the respondent.
STATE v. N. RADHAKISHAN [WADHWA, J.) 701
The Tribunal did not go into the culpability of the respondent with A
respect to the charges as contained in memo dated July 31. 1995 and did not
record any finding of guilt or otherwise on those charges. The Tribunal.
however, said that the memo dated July 3 L 1995 related to the incidents that
happened ten years or more prior to the date of the memo and that there was
absolutely no explanation by the Government for this inordinate delay in
framing the charges and conducting the inquiry against the respondent. The B
explanation given by the State that for some reason or the other the Inquiry
Officer was being changed from time to time and on that account inquiry
could not be conducted, did not find favour by the Tribunal. It said that there
was no justification on the part of the State now conducting the inquiry
againsr the respondent in respect of the incidents at this late stage. The C
Tribunal noticed that in the meanwhile respondent had been promoted as
Senior Joint Director of Town and Country Planning notwithstanding the
appointment of Inquiry Officer one after the other after memo No. l·H2 dated
December 22, 1987 and plea of the State that when respondent was promoted
as Senior Joint Director of Town and Country Planning his file relating to
inquiry against him was not brought to the notice of the administrative D
section in the year 1991 at the time of convening the DPC and which resulted
in promoting the respondent, also did not find favour with the Tribunal. The
Tribunal said that both the sections were within the Municipal Administration
and this explanation, now offered, was without any any merit. The Tribunal
while quashing memo dated July 31, 1995 did not quash the memos dated E
October 27, 1995 and June I, 1996 and said that the State, if so advised, might
proceed against the respondent according to law for taking action against
him. What the Tribunal said about the later two memos was that they should
not be taken into consideration while promoting the respondent in pursuance
to the recommendations of DPC which was held on August 16, 1995.
F
A letter dated March 27, 1995 from the Vigilance Commissioner to the
Principal Secretary to Government, Municipal Administration and Urban
Development Department has been brought to our notice. In this letter the
Vigilance Commissioner \\Tit es that after consideration of the facts it is observed
that there was abnormal and avoidable delay in taking disciplinary action G
against various categories of officers, who are alleged to have committed
several irregularities in the matter of permission given for construction of
multi-storied complexes in the Twin Cities of Hyderabad and Secunderabad.
The letter says that the Inquiry Officer has now been appointed without
following the procedure under Rule 20 of 1991 Rules. The Department was
asked to verify if the earlier Inquiry Officers had served charge memos on the H
702 SUPREME COURT REPORTS [1998] 2 S. C.R
A charged officers and if not to take immediate action to frame the charges, first
as provided under Rule 20 of 1991 Rules. The Vigilance Commissioner advised
y ...
that the draft charges may be shown to him before issuance. A reminder was
sent by the Vigilance Commissioner on April 26, 1995. It was thereafter that
charges dated July 31, 1995 were framed and served upon the respondent and
others.
B
Four articles of charges have been set out against the respondent, now
working as Joint Director, Office of the Director of Town and Country Planning,
which are as under:-
C "ARTICLES OF CHARGES
(1) That Sri N. Radha Krishna, formerly Assistant Town Planner,
Municipal Corporation of Hyderabad, Secunderabad, and presently
working as Joint Director, Directorate of Town Planning, Hyderabad,.
while working as Assistant Town Planner during the year 1978
D committed misconduct in as much as he has put up misleading note
with certain omissions and commissions to the City Planner
recommending permission for construction of 4th floor, 5th floors and
part of 6th floor subject to certain conditions at Chandralok Complex,
Secunderabad in favour of Mis. Swastik Builders in File No. 234/241/
7/1/B4/78 in violation of Building Bye-laws and Zoning Regulations.
E He thereby exhibited his conduct which is unbecoming on the part of
a Government servant and failed to maintain absolute integrity and
devotion to duty. Thereby the said Sri N. Radha Krishna, contravened
rule 3 of the Andhra Pradesh Civil Services (Conduct) Rules, 1964.
(2) Sri N. Radha Krishna while working as such has also committed
~
F misconduct in allowing the Cellar of Chenoy Market Co!11mercial
complex, Secunderabad for using as godowns by various concerns
such as ELCOM ENGINEERING COMPANY, HYDERABAD
PUMPS LIMITED, ET & T. LIMITED by converting the Cellar
portion as Garages when the Cellar was actually meant for parking and
he has also allowed the North-East Corner of Cellar to convert as
G Strong Room for Lockers occupied by Suman Safe Deposit Lockers
Private Limited. He has further committed misconduct in allowing to
raise the height of the building to 130' - 8" instead of the permitted
average height of the building 92' wide whereas permit No. 92/84 dated
11. 7 .1985 and the sanctioned plan pennitted the average height of the
H building is only 92' i.e., Ground+ 7 floors. He thereby exhibited his
STATE v. N. RADHAKISHAN [WADHWA, J ] 703
conduct which is unbecoming on the part of a Government servant A
and failed to maintain absolute integrity and devotion to duty. Thereby
the said Sri N. Radha Krishna contravened mle 3 of the Andhra
Pradesh Civil Services (Conduct) Rules, 1964.
(3) Sri N Radha Krishna has also committed mis-conduct in allowing
the Cellar of Shahjahan Apartments bearing premises No. 6-2-974, B
Khairatabad for being used as shops and office godowns when it was
supposed to be used as Car Parking as per Permit No. 24/15 of 1979
dt. 30 .3 .1979. He thereby exhibited his conduct which is unbecoming
on the part of a Government Servant and failed to maintain absolute
integrity and devotion to duty. Thereby the said Sri N. Radha Krishna, C
contravened rule 3 of the Andhra Pradesh Civil Services (Conduct)
Rules, 1964.
(4) Sri N. Radha Krishna has also committed misconduct in not insisting
to erect railings on the eastern side of Progressive Towers abutting
the Rajbhavan Road even though the condition was stipulated that D
no opening should be provided towards Rajbhavan Road as per
permit No. 145/42, dt. 19.3.1981 read with G.O. MS. No. 1065, M.A.
dated 16.9.1981, thus he failed to maintain absolute integrity and
devotion to duty and thereby contravened Rule 3(1) of Andhra Pradesh
Civil Services (Conduct) Rules, 1964."
E
It is interesting to note that same Articles of Charges in verbatim have been
served upon Sri A. Sree Rami Reddy also, now working as Joint Director,
Office of Director Town and Country Planning and also 8 other named in the
report dated November 7, 1987 of the Director General, Anti Corruption Bureau.
By letter dated August 3, 1995 respondent informed the disciplinary F
authority, who issued the Articles of charges, that he worked as Assistant
City Planner in she Corporation from December 6, 1977 to February 16, 1979
in different circles and that from that it could be seen that only charge No.
1 related to his period when he was working as Assistant City Planner in that
circle. The respondent wanted copies of the relevant records in respect of G
charges contained in the memo to facilitate him to submit detailed written
statement.
In his written statement dated September 25, 1995 the respondent
explained as to how charges 2, 3 and 4 could not relate to him and subsequently
also in his letter to the Chief Secretary to the government of Andhra Pradesh H
704 SUPREME COURT REFORTS [1998] 2 S.C.R.
A he said that charges 2 and 4 related to the period when he was working in
Andhra Pradesh State Scheduled Castes and Tribes Co-operative Housing
,,..._ .r
Society Federation from Febrnary 9, 1979 to September 30, 1981. During the
period charge No. 3 related to, the respondent said that he was on deputation
at Oxford Polytechnic in United Kingdom from October 11, 1984 to September
26, 1985 for his post-graduation course. On the first charge his statement of
B defence was as under :-
;...
"!. With reference to the Charge No. 1, I submit that I have perused
the file bearing No 234/24 l/7/l/B4/78 belonging to Mis. Swastik
Constructions in the Chambers of Deputy Secretary to Government,
M.A. & U.D. Department on 20.9.1995. As seen from the file that
c Mis. Swastik Constructions have applied for the construction of 4th
5th and 6th floors over the existing ground, 1st, 2nd, and 3rd floors
vide their application dt. 18.9.1978. The proposals have been examined
in detail in pages 6 and 7 of note file at paras 1 to 27 giving clear
statement of the F. S.I permissible and also other Rules and Regulations
D for the proposed construction in the light of the material available in
the file. At para 23rd the proposals were submitted for consideration
to the Higher Authorities as per corrected plan subject to certain
conditions. As it can be seen from the endorsement of the then City
Planner Sri P.V Janakiraman on the right hand side margin "This may
be restricted to 4th and 5th floors only, let us delete part of 6th floor.
E The then City Planner has approved the proposed construction of 4th
and 5th floors and part of 6th floor regularising the deviation imposing
the compound fee of Rs. 1000 on 1.1. 79 and marked the. file to the
Deputy Commissioner. The Deputy Commissioner in tum approved
the proposal on 10 .1.1979. It is clear from the above note that I did
F not put up any misleading note and did not recommend the proposals
irregularly against any rule and regulation as alleged in the charge.
The Higher Officers have also not pointed out any lapses in the
submitted note before approval of the said proposals and also
regularised the offence by levy of compounding fee.
,._
-
G Hence, I submit that since I have not recommended the proposals
irregularly, the charge may kindly be dropped."
...... '\"'
As a matter of fact the disciplinary authority got verified the facts that what
the respondent had said about the article of charges 2, 3 and 4 was correct
and that he could not be concerned with any deviations or unauthorised
H constructions in respect of the buildings mentioned in those charges. This
-t·
STATE v_ N. RADHAKISHAN [WADHWA, J_] 705
is by letter dated October 10, 1995 from the Director of Town and Country A
Planning to the Principal Secretary to the Govermnent, Municipal Administration
and Urban Development Department, and was in answer to a query raised by
the disciplinary authority from the Director of Town and Country Planning_
On March 15, 1996 Vigilance Commissioner advised the disciplinary authority
"to process the explanations of the Accused Officers with reference to the B
connected files returned by the A C.B. vide its report dated 7 .11.1987 and then
refer the file to Vigilance Commissioner for further advice". Nothing happened
Everything was at standstill.
It is in April, 1996 that respondent moved the Andhra Pradesh
Administrative Tribunal for relief.
c
It would, therefore, appear that charges have been farmed against the
respondent merely on the basis of the report dated November 7, 1987 from
the Director General, Anti-Corruption Bureau, which is of general in nature
raising accusing fingers on the various officers of the corporation, but without
any reference to the relevant files and pin pointing if respondent or any other D
official charged was at all concerned with the alleged deviations and
unauthorised construction in multi-storied complexes.
It would not be necessary for us to refer to the charges issued by the
memos dated October 27, 199 5 and June 1, 1996 as that was not the subject-
matter for quashing either in the Tribunal or before us. E
One of the grounds on which the Tribunal quashed memo dated July
31, 1995, issued under 1991 Rules, was that without cancelling the earlier
memo No. 1412 dated December 22, 1987, issued under 1963 Rules, the latter
memo could not be issued. We have seen that under Rule 45 of 1991 Rules
the inquiry proceedings initiated under 1963 Rules could be continued even F
after coming into force of 1991 Rules. It is correct that inquiry proceedings
did progress after issuance of memo No. 1412 dated December 22, 1987 to the
extent that an inquiry officer was appointed and should have been concluded
under 1963 Rules. If memo of charge had been served for the first time before
1991 there would have been no difficulty. However, in the present case it G
could be only an irregularity and not an illegality vitiating the inquiry
proceedings inasmuch as after the Inquiry Officer was appointed under memo
No. 1412 dated December 22, 1987, there had not been any progress. If a fresh
memo is issued on the same charges against the delinquent officer it cannot
be said that any prejudice has been caused to him. He can always challenge
the second memo and rather even the first one on the ground of delay which H
706 SUPREME COURT REPORTS [1998] 2 S.C.R
A he did.
In State of Punjab and others v. Chm nan Lal Goyal, [1995] 2 SCC 570,
State of Put\jab was aggricyed by the order of the High Court of Punjab and
Haryana quashing memo of charges against Goyal and also the order appointing
Inquiry Officer to inquire into those charges. In this case the incident, which
B was the subject-matter of charge, happened in December, 1986 and in early
January, 1987, when Goyal was working as Supdt. ofNabha High Security Jail.
It was only on July 9, 1992 that memo of charges was issued to Goyal. He
submitted his explanation of January 4, 1993 denying the charges. Inquiry
Officer was appointed on July 20, 1993 and soon thereafter Goyal filed writ
C petition in the High Court on August 24, 1993. The High Court quashed the
memo of charges on the principal ground of delay of five and a half years
in serving the memo of charges, for which there was no acceptable explanation.
This Court examined the factual position as to how the delay occurred and
if Goyal had been prejudiced in any way on account of delay. This Court
relied on the Principles laid down inA.R. Antulay v. R.S. Nayak (1992] l SCC
D 225, and said, that though that case pertained to criminal prosecution the
principles enunciated therein were broadly applicable to the pleas of delay in
taking the disciplinary proceedings as well. Referring to decision in A.R.
Antulay case this Court s~id:-"
"In paragraph 86 of the judgment, this Court mentioned the
E propositions emerging from the several decisions considered therein
and observed that ''ultimately the court has to balance and weigh the
several relevant factors - balancing test or balancing process - and
determine in each case whether the right to speedy trial has been
denied in a given case." It has also been held that, ordinarily speaking,
where the court comes to the conclusion that right to speedy trial of
F the accused has been infringed, the charges, or the conviction, as the
case may be, will be quashed. At the same time, it has been observed
that is not the only course open to the court and that in a given case,
the nature of the offence and other circumstances may be such that
quashing the proceedings may not be in the interest of justice. In
G such a case, it has been observed, it is open to the court to make such
other appropriate order as it finds just and equitable in the circumstance
of the case."
In that case this Court said that it was more appropriate and in interest of
justice as well as in the interest of administration that inquiry which had
H proceeded to a large extent be allowed to be completed. At the same time the
STATE v. N. RADHAKISHAN [WADHWA, J.] 707
Court directed that Goyal should be considered forthwith for promotion without A
reference to and without taking into consideration the charges or the pendency
~ '"' of the inquiry, if he is found fit for promotion.
It is not possible to lay down any pre-determined principles applicable
to all cases and in all situations where there is delay in concluding the
disciplinary proceedings. Whether on that ground the disciplinary proceedings B
... are to be terminated each case has to be examined on the facts and
circumstances in that case. The essence of the matter is that the court has
to take into consideration all relevant factors and to balance and weight them
to determine if it is in the interest of clean and honest administration that the
disciplinary proceedings should be allowed to terminate after delay particularly c
when delay is abnomial and there is no explanation for the delay. The delinquent
employee has a right that disciplinary proceedings against him are concluded
expeditiously and he is not made to undergo mental agony and also monetary
loss when these are unnecessarily prolonged without any fault on his part
in delaying the proceedings. In considering whether delay has vitiated the
disciplinary proceedings the Court has to consider the nature of charge, its D
complexity and on what account the delay has occurred. If the delay is
unexplained prejudice to the delin0uent employee is writ large on the face of
it. It could also be seen as to how much disciplinary authority is serious in
pursuing the charges against its employee. It is the basic principle of
administrative justice that au officer enterusted with a particular job has to E
perform his duties honestly, efficiently ;µid in accordance with the rules. If he
deviates from this path he is to suffer a penalty prescribed. Normally,
disciplinary proceedings should be allowed to take its course as per relevant
rules but then delay defeats justice. Delay causes prejudice to the charged
officer unless it can be shown that he is to blame for the delay or when there
IL F
... is proper explanation for the delay in conducting the disciplinary proceedings .
Ultimately, the court is to balance these two diverse considerations.
Jn the present case we find that without any reference to records
merely on the report of the Director General, Anti-Corruption Bureau, charges
were framed against the respondent and ten others, an in verbatim and G
without particularizing the role played by each of the officers charged. There
... A
were four charges against the respondent. With three of them he was not
concerned. He offered explanation regarding the fourth charge but the
disciplinary authority did not examine ~he same nor did it choose to appoint
any inquiry officer even assuming that action was validly being initiated
under 1991 Rules. There is no explanation whatsoever for delay in concluding H
708 SUPREME COURT REPORTS [1998] 2 S.C.R
A the inquiry proceedings all these years. The case depended on records of the
Department only and Director General, Anti Corruption Bureau had pointed ,_.... ,.,
out that no witnesses had been examined before he gave his report. The
Inquiry Officers, who had been appointed one after the other, had just to
examine the records to see if the alleged deviations and constructions were
B illegal and unauthorised and then as to who was responsible for condoning
or approving the same against the bye-laws. It is nobody's case that
respondent at any stage tried to obstruct or delay the inquiry proceedings.
The Tribunal rightly did not accept the explanations of the State as to why
delay occurred. In fact there was hardly any explanation worth consideration.
In the circumstances the Tribunal -.vas justified in quashing the charge memo
C dated July 31, 1995 and directing the State to promote the respondent as per
recommendation of the DPC ignoring memos dated October 27, 1995 and June
1, 1996. The Tribunal rightly did not quash these two later memos.
Accordingly we do not find any merit in the appeal. It is dismissed with
costs.
D
v.s.s. Appeal dismissed.
-·
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.