Created byFuzzy Cloud

Supreme Court of India

STATE BANK OF INDIA & ORS.versusTHE CONSORTIUM OF MR. MURARI LAL JALAN AND MR. FLORIAN FRITSCH & ANR.

Citation
2024 INSC 852
Decided
7 November 2024
Disposal
Appeal(s) allowed

Holding

The Supreme Court held that the PBG cannot be adjusted against the first tranche payment and that the SRA’s failure to implement the approved resolution plan mandates liquidation of the corporate debtor.

Summary

The Supreme Court examined the dispute between State Bank of India and other creditors (petitioners) and the consortium of Murari Lal Jalan and Florian Fritsch (respondent SRA) over the implementation of the approved resolution plan for Jet Airways. The core issue was whether the Performance Bank Guarantee (PBG) of Rs.150 crore could be adjusted against the first tranche payment of Rs.350 crore, contrary to the Supreme Court’s earlier order and the terms of the resolution plan and IBC regulations. The Court held that the PBG could not be set‑off and must remain alive until full implementation, and that the SRA’s failure to infuse the required cash amount constituted a breach of the plan. Consequently, the Court set aside the NCLAT order, directed the encashment of the PBG, forfeiture of the Rs.200 crore already infused, and exercised its plenary powers under Article 142 to order the liquidation of Jet Airways. The appeals were allowed and the corporate debtor was placed in liquidation.

Issues considered

  • Whether the Performance Bank Guarantee (PBG) could be adjusted against the first tranche payment within 180 days from the Effective Date, in contravention of the Supreme Court’s order, the resolution plan and law.
  • Whether the non‑implementation of the resolution plan by the SRA necessarily leads to liquidation under Section 33(3) of the IBC, 2016.
  • Whether timely implementation of the resolution plan is an objective of the IBC, 2016.

Legislation cited

Headnote

Issue for Consideration Whether the Performance Bank Guarantee (PBG) could have been adjusted against the first tranche payment which was to be made under the Resolution Plan, within 180 days from the of the order of this Court dated 18.01.2024, the terms of the Resolution Plan and the provisions of law; In other words, whether the impugned order of the NCLAT allowing the adjustment of the PBG in lieu of payment of the first tranche could be said to be perverse; Whether the

Subjects

Jet Airways liquidationPerformance Bank GuaranteeAdjustment of PBGResolution Plan implementationSection 33(3) IBCTimely liquidationInsolvency and Bankruptcy CodeArticle 142Corporate debtorWorkmen duesAirport duesConditions PrecedentMonitoring Committee

Judgment

                [2024] 11 S.C.R. 2039 : 2024 INSC 852

                  State Bank of India & Ors.
                               v.
           The Consortium of Mr. Murari Lal Jalan and
                   Mr. Florian Fritsch & Anr.
                  (Civil Appeal No(s). 5023-5024 of 2024)
                             07 November 2024
     [Dr. Dhananjaya Y. Chandrachud, CJI, J.B. Pardiwala*
                    and Manoj Misra, JJ.]


                           Issue for Consideration
       Whether the Performance Bank Guarantee (PBG) could have been
       adjusted against the first tranche payment which was to be made
       under the Resolution Plan, within 180 days from the Effective Date,
       in contravention of the order of this Court dated 18.01.2024, the
       terms of the Resolution Plan and the provisions of law; In other
       words, whether the impugned order of the NCLAT allowing the
       adjustment of the PBG in lieu of payment of the first tranche could
       be said to be perverse; Whether the non-implementation of the
       Resolution Plan by the Respondent No.1-Successful Resolution
       Applicant (SRA) necessarily leads to the consequence of liquidation
       as provided under Section 33(3) of the IBC, 2016; Whether the
       timely implementation of the Resolution Plan is also one of the
       objectives of the IBC, 2016.

                                  Headnotes†
       Insolvency and Bankruptcy Code, 2016 – Insolvency and
       Bankruptcy Board of India (Insolvency Resolution Process
       for Corporate Persons) Regulations, 2016 – Constitution of
       India – Article 142 – Inordinate delay in due implementation
       of the Resolution Plan; several dues including the CIRP costs
       of the Corporate Debtor-Jet Airways (India) Limited multiplied;
       appellants incurring huge expenditure and costs every month
       towards maintenance of the Corporate Debtor – Whether the
       Performance Bank Guarantee (PBG) of Rs. 150 Crore could
       be adjusted against the first tranche payment of Rs. 350 Crore
       which was to be made under the Resolution Plan, within 180


* Author
2040                                                         [2024] 11 S.C.R.

                         Supreme Court Reports


    days from the Effective Date – NCLAT allowed the adjustment of
    the PBG in lieu of payment of the first tranche – Sustainability:
    Held: 1.1 NCLAT order is unsustainable in law and perverse
    as it did not consider several material and relevant facts and
    misread the evidence as well – The non-infusion and payment
    of funds in compliance with the applicable laws and the terms
    of the Resolution Plan led to a failure of the Resolution Plan.
    [Paras 186, 90]
    1.2 Impugned order directing the SRA to adjust the PBG of Rs.
    150 Crore against the first tranche payment of Rs. 350 Crore
    was in flagrant disregard of the 18th January order of this Court,
    the terms of the Resolution Plan and established law – In the
    peculiar and alarming circumstances and in view of the fact that
    almost five years have elapsed since the Resolution Plan was
    duly approved however, there being no progress, jurisdiction under
    Article 142 of the Constitution is invoked and it is directed that the
    Corporate Debtor be taken in liquidation – The NCLT, Mumbai
    shall take appropriate steps for appointment of liquidator and all
    other necessary formalities for commencement of liquidation of the
    Corporate Debtor – Rs. 200 Crore already infused by the SRA,
    forfeited – The Lenders/Creditors can encash the Performance Bank
    Guarantee of Rs. 150 Crore furnished by the SRA – Impugned
    order set aside. [Paras 90, 186, 187, 188]
    2. The nature of the Conditions Precedent laid out under the
    Resolution Plan were such that several of them could not be
    fulfilled before the operationalization of the Corporate Debtor –
    The assertion that the Effective Date would kick in only upon
    fulfilment of all the Conditions Precedent and since the Appellants
    had challenged the fulfilment of the Conditions Precedent, such a
    date could not be said to have yet arrived not accepted – It was
    repeatedly declared by different fora that the Effective Date was
    frozen on 20.05.2022 and the obligation of the SRA to implement
    the Resolution Plan was absolute – All steps necessary should
    have been undertaken by the SRA, at least post the impugned
    order of the NCLAT dated 12.03.2024 – To contend that its
    hands were tied since the Conditions Precedent were still being
    challenged before this Court is nothing but a reflection of the mala
    fide intention on the part of the SRA to not fulfil its obligations in
    accordance with the Resolution Plan under the garb of pendency
    of litigation. [Paras 97, 98]
[2024] 11 S.C.R.                                                           2041

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     3. The Effective Date was frozen on 20.05.2022 – As per Clause
     6.3.1(g) on the “Infusion of Funds and Timelines”, and Serial No.11
     under Clause 7.7, the first tranche payment of Rs. 350 Crore had
     to be made by the SRA, upfront, within a period of 180 days from
     the Effective Date – As per the Resolution Plan, this 180-day
     timeline otherwise would have expired on 16.11.2022 – Several
     extensions were granted to the SRA to infuse this amount, at
     different stages of this litigation, by the NCLT, the NCLAT and this
     Court (vide order dtd.18.01.2024, 180 days time for infusion was
     extended up to 31.01.2024) as well. [Para 98]
     4. Further, an adjustment of the PBG against the first tranche
     payment was also in violation of Regulation 36B(4A) of the 2016
     Regulations – The PBG had to be kept alive until the complete
     implementation of the Resolution Plan as per Regulation 36B(4A) –
     This was also provided under Clauses 3.13.2 and 3.13.8 of the
     RFRP (Request for Resolution Plan) respectively wherein the PBG
     was required to be kept alive and was to be returned to the SRA
     only upon 100% completion of the implementation of the Resolution
     Plan – This binding nature of the RFRP was transferred onto the
     Resolution Plan through Clauses 7.3 and 9.4 respectively of the
     Resolution Plan – Even in light of the NCLAT’s own order dated
     26.05.2023, it does not follow that the PBG could have been
     adjusted by the SRA, mid-implementation, against its payment
     obligation. [Paras 104, 105, 107]
     5.1 Once the Adjudicating Authority has approved the plan
     u/s.31(1) of the IBC, 2016, the Resolution Plan is binding on
     all the stakeholders including those stakeholders who are not
     direct participants of the CIRP – Therefore, there is absolutely no
     scope for modification of the terms of a Resolution Plan which
     has received the imprimatur of the Adjudicating Authority, be it by
     the Adjudicating Authority itself, the CoC or the SRA. [Para 116]
     5.2 The NCLT had approved the present Resolution Plan vide
     order dated 22.06.2021, the Resolution Plan was immune to any
     modification or alteration whatsoever – The submission of the
     SRA that the Lender’s Affidavit required an infusion of Rs. 350
     Crore in cash, while the Resolution Plan allowed for the payment
     of Rs. 200 Crore in cash and Rs.150 Crore through adjustment of
     the PBG, rejected – The conditions imposed on the SRA under
     the Lender’s Affidavit and the Resolution Plan were one and the
     same, the only difference being that the Appellants had offered
2042                                                     [2024] 11 S.C.R.

                        Supreme Court Reports


    not to press issues relating to the compliance of the Conditions
    Precedent and grant of extensions/exclusions along with offering
    to withdraw the Company Appeal and the Appeals pending before
    this Court – In view of clear order dated 18.01.2024, the PBG of
    Rs.150 Crore could not have been allowed to be adjusted with
    the first tranche payment of Rs. 350 Crore – Non-compliance of
    the SRA with the order of this Court has led to a dereliction of
    its obligations to implement the Resolution Plan – SRA failed to
    implement the Resolution Plan by not infusing the first tranche
    payment of Rs. 350 Crore in cash, as required by Clause 6.3.1(g)
    and the Implementation Schedule under Clause 7.7 of the
    Resolution Plan. [Paras 117, 121 124, 125]

    Insolvency and Bankruptcy Code, 2016 – ss.33(3), 31(1) –
    Whether there were sufficient grounds before the NCLAT to
    hold that Respondent No.1-SRA had contravened the terms of
    the approved Resolution Plan and that the Corporate Debtor
    must be directed to be liquidated u/s.33(3) – Whether SRA
    failed to implement the Resolution Plan on non-payment of
    the Airport Dues as per the terms of the Resolution Plan –
    Whether SRA could be said to have failed to implement the
    Resolution Plan on account of the non-payment of workmen
    and employees’ dues as per the terms of the Resolution
    Plan and the order of the NCLT dated 21.10.2022 which was
    confirmed by the order dated 31.01.2023 of this Court – Need
    for “timely liquidation” over “endless resolution process”
    emphasised:
    Held: 1.1 The Resolution Plan contemplated that the Airport
    Charges be subsumed within the CIRP Dues and since all of the
    different CIRP dues cannot be satisfied through the bank balance
    which stands to the credit of the Corporate Debtor, a separate
    sum of Rs. 25 Crore was demarcated towards the remaining CIRP
    payments – Hence, NCLAT was right in arriving at the conclusion
    that Airport Dues were indeed a part of the CIRP costs. [Para 129]
    1.2 The impugned order of the NCLAT nowhere caps the Airport
    Dues to a maximum of Rs. 25 Crore – Moreover, such a mention
    of Rs. 25 Crore is plainly absent in its observations regarding
    Airport Dues – The Resolution Plan, too, does not contemplate
    the CIRP costs to be strictly subject to a maximum of Rs. 25
    Crore – To accept such a contention of the Appellants would be
[2024] 11 S.C.R.                                                            2043

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     to misinterpret the observations made in the impugned order.
     [Paras 129, 130]
     1.3 The SRA not having infused the first tranche payment of Rs. 350
     Crore as per Clause 6.3.1(g) and S. No. 11 of the Implementation
     Schedule under Clause 7.7 within a period of 180 days from the
     Effective Date and within the multiple extensions granted therefrom,
     defaulted on its obligation towards the payment of CIRP costs
     (which include airport dues) under Clause 6.4.1 as well. [Para 132]
     2. By not infusing the first tranche payment of Rs. 350 Crore
     as per the Implementation Schedule of the Resolution Plan, the
     SRA breached the terms of the Resolution Plan which required
     a minimum liquidation value of Rs.113 Crore to be paid towards
     the Workmen and Employees’ Dues as well – Moreover, both the
     Provident Fund and Gratuity Dues amounting to Rs. 226 Crore
     should also have been paid by the SRA as per the order dated
     21.10.2022 of the NCLAT in fulfillment of its obligations, which it
     failed to do. [Para 140]
     3.1 The NCLAT declined to accept the submission of the Appellant
     that on account of non-deposit of Rs.150 Crore as directed by
     this Court, the Corporate Debtor should be liquidated – This was
     based on the incorrect assumption that the direction of this Court
     to infuse to Rs.150 Crore in cash was only confined to the terms
     of the Lenders Affidavit dated 16.08.2023 – The Lender’s Affidavit
     could not have provided for conditions incompatible with the terms
     of the Resolution Plan – Such an affidavit would have been in
     direct contravention with s.31(1) of the IBC, 2016 – Therefore, the
     direction of this Court in its order dated 18.01.2024 was w.r.t both
     the Lenders Affidavit and the underlying terms of the Resolution
     Plan – The same was so understood by all the parties involved.
     [Para 142]
     3.2 The Lender’s Affidavit in precise terms stated that “Failing to
     comply with the conditions mentioned in Para 8(a) to (c) above,
     the Corporate Debtor should be directed to go into liquidation” –
     It was in this context that this Court stated that, “the SRA shall
     peremptorily on or before 31 January 2024, deposit an amount of
     Rs. 150 crores into the designated account of SBI, failing which the
     consequences under the Resolution Plan will follow” – Therefore,
     it is incorrect to contend that this Court neither considered nor
     expressed any opinion on the question of liquidation of the Corporate
2044                                                         [2024] 11 S.C.R.

                         Supreme Court Reports


    Debtor – The consequence of non-implementation of the Resolution
    Plan by the SRA must necessarily be liquidation of the Corporate
    Debtor in accordance with s.33(3) of the IBC, 2016. [Para 143]
    3.3 The SRA failed to infuse the first tranche payment of Rs. 350
    Crore as envisaged in the Resolution Plan despite the Effective
    Date being fixed on 20.05.2022 – Consequently, the payment of
    CIRP costs, workmen and employees’ dues etc. which must be
    made in priority over the dues of the other creditors were also not
    made – More than 5 years have passed and the implementation of
    the Resolution Plan still seems to be a dim light at the far end of
    a long tunnel – Over this period of 5 years, several dues such as
    the Airport dues to be paid by the Corporate Debtor have increased
    multi-fold due to the fault of the SRA and this Court must ensure
    that such debts stop running at some point in time. [Para 147]
    3.4 Although one of the key objectives of the IBC, 2016 is to ensure
    the survival of the corporate debtor as a going concern, yet the
    same must not come at the cost of efficiency – In scenarios such
    as the present, “timely liquidation” is indeed preferred over an
    “endless resolution process” – Such a view will prevent the likelihood
    of adversely affecting the interests of all the creditors who have
    been suffering due to no fault of their own and also securing the
    maximization of value of the remaining assets. [Para 148]
    3.5 The consequence of the failure to implement the Resolution
    Plan in terms of Clause 9.4 of the Resolution Plan and Clause
    3.13.7(iii) of the RFRP is that the Appellants are entitled to invoke
    the PBG automatically without any reference to the SRA – The
    PBG may be invoked by the Appellants in accordance with the
    terms of the Resolution Plan. [Para 149]
    Insolvency and Bankruptcy Code, 2016 – Preamble – Timely
    implementation of the Resolution Plan is also one of the
    objectives of the IBC, 2016 – Report of the Bankruptcy Law
    Reforms Committee, 2015, time-bound working of the Code
    emphasised; time and speed are of the essence under the
    Code – NCLT Rules, 2016 – NCLAT Rules, 2016 – r.15 – Power
    of NCLT and NCLAT to extend the time limits not be exercised
    mechanically without any application of mind. [Paras 150, 151,
    152, 154, 157, 158]

    Constitution of India – Article 142 – Insolvency and Bankruptcy
    Code, 2016 – Plenary powers u/Article 142 – When to be
[2024] 11 S.C.R.                                                              2045

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     exercised, discussed – Inordinate delay in due implementation
     of the Resolution Plan, several dues including the CIRP costs
     of the Corporate Debtor multiplied; appellants have to incur
     huge expenditure and costs every month towards maintenance
     of the Corporate Debtor – Corporate Debtor, if to be directed
     to be taken in liquidation exercising power u/Article 142:
     Held: Yes – The fundamental concern of this Court must not only
     be of doing substantial and complete justice but also to ensure
     expeditious resolution of the issues in the interests of the underlying
     objective of the IBC, 2016 and all the stakeholders involved – The
     terms of the Resolution Plan have been contravened and that there
     has been a failure to implement on part of the SRA – Resolution
     Plan is no longer capable of being implemented – In exercise of
     plenary powers u/Article 142, the Corporate Debtor is directed to
     be taken in liquidation – NCLT Rules, 2016 – r.11. [Paras 163-165]

     Insolvency and Bankruptcy Code, 2016 – Deficiencies/
     Shortcomings – Suggestions – Functioning of the NCLTs and
     NCLAT – The Guidelines for Committee of Creditors (CoC)
     issued by the IBBI on 06.08.2024, enumerated – Suggestions
     made to CoC – Role, duty and responsibility of Successful
     Resolution Applicant; lenders and also that of creditors:
     Held: 1. The Guidelines for Committee of Creditors issued by
     the IBBI may go a long way in streamlining the functions of the
     CoC – Adding to the aforesaid guidelines, it is suggested that
     the CoC exercise their commercial wisdom and approve/reject
     the Resolution Plans placed before them exhibiting fairness and
     with good reasons – Such a reasoned decision making on their
     part will only serve to further enable the other key players like the
     Adjudicating Authorities to understand the rationale behind their
     decision and to uphold the correctness of the same – Furthermore,
     it is also suggested that the Central Government or the IBBI explore
     the possibilities of better enforcement of the standards and practices
     enumerated in the guidelines through an independent mechanism
     under the auspices of an oversight committee instead of making
     them self-regulatory. [Para 172]
     2.1 Once a resolution plan is approved under the IBC, 2016, the
     Successful Resolution Applicant undertakes a profound responsibility
     to implement the plan in both letter and spirit – This obligation is
     not merely an empty formality but an enduring commitment to
2046                                                             [2024] 11 S.C.R.

                          Supreme Court Reports


    restore the corporate debtor to viability and ensure a meaningful
    turnaround – The role of a Successful Resolution Applicant is far
    more than a transactional duty towards the creditors or stakeholders;
    it embodies a pivotal responsibility to the distressed entity itself,
    which must be approached with utmost dedication and an earnest
    sense of duty – Regardless of the challenges that may arise, the
    Successful Resolution Applicant cannot treat its obligations as
    optional or conditional, nor can it abdicate its responsibility in the face
    of unforeseen obstacles – Its efforts must reflect a determination to
    implement the plan fully and to rejuvenate the debtor company, as
    this is integral to the success of the IBC framework and the spirit
    of economic revival it seeks to foster – The approach, therefore,
    must not be frugal or narrowly profit-driven, limited to viewing the
    transaction through a purely commercial lens – Instead, it must
    recognize that rescuing a distressed company is a responsibility
    of significant social and economic value, demanding a holistic and
    responsible strategy. [Para 173]
    2.2 In this collaborative effort, the duty to implement the plan does
    not fall on the Successful Resolution Applicant alone; lenders
    and creditors are equally obligated to support the process by
    offering constructive and continuous cooperation – They must
    not impede the implementation process through unnecessary
    demands beyond the pale of the resolution plan or with delays
    in implementation plan but rather should facilitate the Successful
    Resolution Applicant’s efforts to revive the corporate debtor –
    Given their vested interest in the corporate debtor’s successful
    revival, lenders have a fundamental duty to act in good faith and
    with transparency, recognizing that their cooperative stance is
    essential for overcoming the inevitable challenges of the resolution
    process – The lender's role is not merely passive; it requires active
    support that aligns with the ultimate goal of the IBC, 2016- to
    provide a fair and equitable resolution that maximizes asset value
    while enabling the debtor’s recovery – Therefore, the lenders
    must balance their financial interests with the broader objective
    of rehabilitation – They should not take an obstructive approach
    or seek to leverage the resolution process solely for individual
    benefit, as such actions would risk destabilizing the corporate
    debtor’s recovery trajectory – Instead, they must be prepared to
    collaborate fully, sharing the responsibility to make the resolution
    process work in practice. [Paras 174, 175]
[2024] 11 S.C.R.                                                              2047

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     2.3 The IBC, 2016 is silent as regards the phase of implementation
     of the Resolution Plan by the Successful Resolution Applicant – This
     is mostly due to the fact that each Resolution Plan might be unique
     and customized to the specific needs of the Corporate Debtor and
     an excessive amount of statutory control over the implementation
     of the Plan may prove to be counterproductive to the cause of
     the Corporate Debtor – However, this has unfortunately led to
     the consequence of giving excessive leeway to the Successful
     Resolution Applicants to act in flagrant violation of the terms of the
     Resolution Plan in a lackadaisical manner – The SRAs repeatedly
     approach the Adjudicating Authority or the NCLAT for the grant
     of reliefs in relation to relaxation of the strict compliance to the
     terms of the Plan, including the timelines imposed therein – The
     NCLT and NCLAT more often than not, accede to such requests in
     exercise of their inherent powers under Rule 11 or their power to
     extend time under Rule 15 of the NCLT and NCLAT Rules, 2016
     respectively – The NCLT and NCLAT must not entertain such
     repeated attempts at violating the integrity of a CoC approved
     Resolution Plan by accommodating the incessant requests of the
     Successful Resolution Applicants – The exercise of discretion as
     regards altering the binding terms of the Resolution Plan, including
     the timelines imposed, must be kept at a minimum, at best – The
     NCLTs/NCLATs need to be sensitised of not exercising their judicial
     discretion in extending the timelines fixed under IBC, 2016 or the
     Resolution Plan, in such a way that it may make the Code lose its
     effectiveness thereby rendering it obsolete. [Para 176]
     2.4 Section 30(2)(d) of the IBC, 2016 states that the resolution
     professional shall mandatorily examine each resolution plan that
     is received to confirm that it provides for the implementation and
     supervision of the resolution plan – Regulation 38 of the 2016
     Regulations provides for the mandatory contents of a Resolution
     Plan – Regulation 38(2) specifically states that the Resolution Plan
     shall provide for the term of the plan and its implementation schedule,
     along with adequate means for supervising its implementation –
     Further, under Regulation 38(3), a resolution plan must demonstrate
     that it addresses the cause of default, is feasible and viable, has
     provisions for its effective implementation, has provisions for
     approvals required and the timelines for the same and, that the
     resolution applicant has the capability to implement the resolution
     plan – Therefore, in light of these provisions of the IBC, 2016 and
2048                                                       [2024] 11 S.C.R.

                        Supreme Court Reports


    the 2016 Regulations, it can be seen that the resolution plan must
    be impermeable to any shortcuts that prevent its implementation,
    including timely implementation, by the successful resolution
    applicant – A consideration of these provisions reinforces the idea
    that timely implementation and strict adherence to the terms of
    the resolution plan is crucial. [Para 177]
    2.5 Section 74(3) of the IBC, 2016 provides for the punishment
    for contravention of the resolution plan – The Code comes down
    heavily on any knowing and willful contravention of the terms
    of the Resolution Plan, committed by any person, on whom the
    approved Resolution Plan has been made binding under Section
    31 of the IBC, 2016 – A punishment of minimum one year which
    may extend up to five years or minimum fine of one Lakh which
    may be up to one Crore rupees, or both, has been prescribed
    for such a contravention – In light of such strict consequence
    provided for the contravention of the resolution plan envisaged
    under the scheme of the Code itself, there is good reason for us
    to ensure that the successful resolution applicants abide by their
    commitments made under the Resolution Plan – Therefore, it is
    suggested that the authorities including the NCLT and NCLAT must
    not aid the Successful Resolution Applicants in circumventing the
    strict mandates of the law by acceding to their requests to relax
    the terms of the plan itself. [Paras 178, 179]
    2.6 One another suggestion that may aid in a coordinated and
    non-adversarial implementation of the Resolution Plan by all the
    stakeholders is that the Adjudicating Authority while approving a
    Resolution Plan under Section 31 of the IBC, 2016, should record
    the next steps which are to be taken by the respective parties for
    commencement of implementation of the approved Resolution
    Plan – This will ensure that the parties are ad idem about the
    next round of their obligations that each of them is required to
    discharge under the approved Resolution Plan and that they do
    not delay the implementation by initiating any further litigation on
    this aspect. [Para 180]
    2.7 As regards the implementation of the approved Resolution
    Plan, it is suggested that the IBC, 2016 statutorily provide for the
    constitution of a Monitoring Committee, once the plan has been
    approved, for a smooth handover of the Corporate Debtor to the
    Successful Resolution Applicant – Presently, such a provision is
[2024] 11 S.C.R.                                                                2049

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     absent in the Code and it is the Adjudicating Authority that orders
     for the constitution of a Monitoring Committee to ensure smooth
     implementation of the Plan – The CoC must be empowered to
     constitute the Monitoring Committee which may, by default, include
     the Resolution Professional and also include other nominees
     from the CoC and the Resolution Applicant respectively – Such
     a Monitoring Committee would be entrusted with the powers of
     monitoring and supervising the resolution plan till the expiry of the
     term of the Resolution Plan – The Committee shall also be required
     to ensure all statutory compliances during the implementation of
     the plan along with updating the Adjudicating Authorities, Financial
     and other Creditors about the status of implementation of the
     Resolution Plan, on a quarterly basis. [Para 181]
     3.1 As regards certain efficiency issues within the NCLTs and
     NCLAT, it has been noticed over a period of time that there is a
     serious lack of timely admission and disposal of the applications
     filed as regards the initiation of CIRP, approval of the resolution
     plan and liquidation – This only adds to the uncertainty of the
     process and prolongs the dispute thereby jeopardizing the interest
     of all the stakeholders involved – Adjudication in a time-bound
     manner would help prevent any further deterioration of the value
     of the corporate entity – The integrity of the original timelines laid
     down by the Code and the Resolution Plan must not be allowed
     to be violated since it would dilute the objective of the Code in
     its entirety, erode investor confidence and hinder all corporate
     restructuring efforts. [Para 182]
     3.2 The Members often lack the domain knowledge required
     to appreciate the nuanced complexities involved in high-stake
     insolvency matters in order to properly adjudicate such matters –
     One of the salutary objects of the Code, 2016 is to protect the
     assets of the corporate entity in a timely manner and take prompt
     decisions, however, it has become a practice of the NCLT(s) and
     NCLAT to ignore the urgent mentionings and listings of time-sensitive
     matters and show no deference to long-pending matters resulting in
     value erosion of the assets of the Corporate Debtor and rendering
     their insolvency resolution process a foregone conclusion – Over a
     period of time, this Court has noticed the growing tendency amongst
     Members of the NCLT(s) and NCLAT to ignore the orders of this
     Court or act in its defiance – Any act of contravention of this Court’s
     order and the larger rubric of judicial propriety will not be tolerated –
2050                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


    The NCLT(s) and the NCLAT must seriously rethink their approach
    towards admission and disposal of insolvency matters, they should
    not act as a mere rubberstamping authority and must take their
    roles seriously in ensuring time-bound hearings and resolutions –
    Proper and effective hearings, both virtually and in-court, must be
    given to insolvency matters of public importance, and the NCLT(s)
    and NCLAT(s) must earnestly work towards ensuring that the IBC,
    2016 achieves its avowed object. [Para 183]
    3.3 One another serious issue pertaining to the functioning of the
    NCLTs and NCLAT is that there is often a shortage of members
    in the Tribunals and inadequate infrastructure to support their
    functioning – These vacancies heavily impact the insolvency
    reform initiative undertaken by the government since they lead
    to operational inefficiencies – Consequently, the strict timelines
    provided in Section 12 of the IBC, 2016 are not complied
    with – Filling such vacancies with experts having adequate
    domain knowledge in the field must be prioritized along with
    addressing the infrastructure needs of the Tribunals to prevent
    any adverse effect on the resolution process – There must be
    strict mandates regarding the functioning of the Tribunals within
    its normal working hours – The appointment of new members
    must be done in a manner such that it coincides with the date
    of retirement of the sitting members in a seamless manner
    to avoid such operational inefficiencies – Persons with high
    ideals & impeccable integrity should be appointed as Members
    in the NCLT as well as NCLAT – There should be no political
    appointment. [Para 184]
    Insolvency and Bankruptcy Code, 2016 – s.62 – Exercise
    of the jurisdiction under – Code of Civil Procedure, 1908 –
    s.100 – “substantial question of law”, when arises – Discussed.
    [Paras 87-90]

                            Case Law Cited
    IFCI Ltd. v. Sutanu Sinha and Others [2023] 15 SCR 280 : 2023
    SCC OnLine SC 1529; Chandrabhan (Deceased) Through Lrs.
    And Others v. Saraswati and Others [2022] 7 SCR 295 : 2022
    SCC OnLine SC 1273; Maria Colaco and Another v. Alba Flora
    Herminda D’souza and Others (2008) 5 SCC 268; Abdul Raheem v.
[2024] 11 S.C.R.                                                           2051

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     Karnataka Electricity Board and Others [2007] 12 SCR 389 :
     (2007) 14 SCC 138; Ebix Singapore Private Limited v. Committee
     of Creditors of Educomp Solutions Limited and Another [2021]
     14 SCR 321 : (2022) 2 SCC 401; Kridhan Infrastructure Private
     Limited v. Venkatesan Sankaranarayan and Others [2021] 2 SCR
     520 : (2021) 6 SCC 94; Innoventive Industries Limited v. ICICI
     Bank and Another [2017] 8 SCR 33 : (2018) 1 SCC 407; Glas
     Trust Company LLC v. Byju Raveendran and Others, 2024 SCC
     OnLine SC 3032; K Shashidhar v. Indian Overseas Bank and Ors.
     [2019] 3 SCR 845 : (2019) 12 SCC 150 – referred to.

                      Books and Periodicals Cited
     Report of the Bankruptcy Law Reforms Committee, 2015.

                                List of Acts
     Insolvency and Bankruptcy Code, 2016; Insolvency and
     Bankruptcy Board of India (Insolvency Resolution Process for
     Corporate Persons) Regulations, 2016; Constitution of India; NCLT
     Rules, 2016; NCLAT Rules, 2016; Code of Civil Procedure, 1908;
     Employees’ Provident Fund and Miscellaneous Provisions Act,
     1952; Payment of Gratuity Act, 1972.

                             List of Keywords
     Jet Airways liquidation; Aviation sector; Adjustment of Performance
     Bank Guarantee (PBG); In lieu of payment of the First tranche
     payment; Within 180 days from the Effective Date; Successful
     Resolution Applicant (SRA); Non-implementation of the Resolution
     Plan by SRA; Inordinate delay in due implementation of the
     Resolution Plan; CIRP costs; Non-infusion and payment of
     funds; Failure of the Resolution Plan; Failure to implement the
     Resolution Plan; Jurisdiction under Article 142 of the Constitution
     of India; Plenary powers under Article 142 of the Constitution of
     India; Inherent powers; Corporate Debtor to be liquidated; Non-
     fulfilment of Conditions Precedent; Encash the Performance
     Bank Guarantee; Extension of the timeline; Multiple extensions
     granted; Maximum extension; Implementation extension; Lender’s
     Affidavit; Request for Resolution Plan (RFRP); Binding nature of the
     RFRP; Air Operation Certificate (AOC); Slots Allotment Approval;
     Dereliction of obligations to implement the Resolution Plan; Non-
2052                                                   [2024] 11 S.C.R.

                       Supreme Court Reports


    payment of the Airport Dues/Charges; Non-payment of workmen
    and employees’ dues; “timely liquidation”; “endless resolution
    process”; CIRP dues; Implementation Schedule; Survival of the
    corporate debtor as a going concern; Timely implementation of
    the Resolution Plan; Objectives of the IBC; Time-bound working
    of the Insolvency and Bankruptcy Code, 2016; Time and speed
    essence under the Insolvency and Bankruptcy Code, 2016;
    “substantial question of law”; Shortcomings in Insolvency and
    Bankruptcy Code, 2016; Suggestions made to Committee of
    Creditors (CoC); “commercial wisdom” of the CoC; Role, duty
    and responsibility of Successful Resolution Applicant; Lenders
    and creditors; Functioning of the NCLTs and NCLAT.

                         Case Arising From
    CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 5023-5024
    of 2024
    From the Judgment and Order dated 12.03.2024 of the National
    Company Law Apellate Tribunal in Company Appeal (AT)
    (Insolvency) Nos. 129 and 130 of 2023
    With
    Civil Appeal Nos. 12220-12221 of 2024

                      Appearances for Parties
    N. Venkataraman, A.S.G., Mukul Rohatgi, Gopal Sankaranarayanan,
    S. Niranjan Reddy, Amar Dave, Sr. Advs., Vikas Mehta, Mayan
    Prasad, Ms. Anshula Vijay Kumar Grover, Lenpithang Sithlou,
    Ms. Nitika Grover, Nishant Anshul, Sanjay Kapur, Devesh
    Dubey, Ms. Divya Singh Pundir, Arjun Bhatia, Pawanshree
    Agrawal, Debmalya Banerjee, Pooja Mahajan, Kartik Bhatnagar,
    Rohan Sharma, Ashish Vats, Ms. Apurva, Agastya Shelat, Ms.
    Arveena Sharma, Ms. Shruti Pandey, Ms. Trisha Chandran, Ms.
    Tanya Srivastava, Tushar Srivastava, Ms. Aastha Prasad, M/S.
    Karanjawala & Co., Surya Prakash, Ms. Mahima Kapur, Ms.
    Isha Virmani, Mrs. Shubhra Kapur, Dhirajkumar Totala, Nishant
    Upadhyay, Navneet R., Ankit Pal, Ajay Raj, Ms. Vasudha Jain,
    Ms. Palak Arora, Ms. Alankrita Sinha, Ms. Petrushka Dasgupta,
    Mridul Yadav, Raghav Bhatia, Ms. Pallavi Pratap, Pawanshree
    Agrawal, Advs. for appearing parties.
[2024] 11 S.C.R.                                                                                  2053

  State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                     and Mr. Florian Fritsch & Anr.

                       Judgment / Order of the Supreme Court

                                              Judgment

       J.B. Pardiwala, J.

       For convenience of exposition, this judgment is divided into the
       following parts: -
                                                       INDEX*

         A. FACTUAL MATRIX .........................................................                 3
         B. SUBMISSIONS ON BEHALF OF THE APPELLANTS.....                                            41
               i.      Issue No.1: Adjustment of PBG of Rs. 150 Crore
                       towards the first tranche payment .......................                    43
               ii.     Issue No. 2: Non-payment of Airport dues ...........                         53
               iii.    Issue No. 3: Non-payment of Workmen and
                       Employees’ dues ..................................................           55
               iv.     Issue No. 4: Achievement of Effective Date .......                           57
               v.      Issue No. 5: Non-fulfilment of Conditions
                       Precedent ...............................................................    59
         C. SUBMISSIONS ON BEHALF OF THE RESPONDENTS ...                                            63
         D. ISSUES FOR DETERMINATION ...................................                            76
         E. ANALYSIS .......................................................................        77
               i.      Whether the Performance Bank Guarantee
                       (PBG) could have been adjusted against the first
                       tranche payment which was to be made under
                       the Resolution Plan, within 180 days from the
                       Effective Date, in contravention of the order of
                       this Court dated 18.01.2024, the terms of the
                       Resolution Plan and the provisions of law? .....                             85




* Ed. Note: Pagination as per the original Judgment.
2054                                                                   [2024] 11 S.C.R.

                          Supreme Court Reports



              a. Whether the Conditions Precedent were fulfilled
                 by Respondent No.1/SRA and the Effective Date
                 was fixed at 20.05.2022? .................................               85

              b. Whether the NCLAT could have directed the
                 Performance Bank Guarantee (PBG) to be
                 adjusted against the first tranche payment which
                 was to be made within 180 days of the Effective
                 Date? ...............................................................    93

                   I.     The adjustment of the PBG was
                          impermissible under the terms of the
                          Resolution Plan read with Regulation
                          36B(4A) of the 2016 Regulations. ...........                    94

                   II.    The Lender’s Affidavit dated 16.08.2023
                          did not impose conditions which were
                          different from the terms of the Resolution
                          Plan. .......................................................... 106

        ii.   Whether the non-implementation of the
              Resolution Plan by the SRA necessarily leads to
              the consequence of liquidation as under Section
              33(3) of the IBC, 2016? .......................................... 117

              a. Whether Respondent No.1/SRA had failed to
                 implement the Resolution Plan on non-payment
                 of the Airport Dues as per the terms of the
                 Resolution Plan? ................................................ 118

              b. Whether Respondent No.1/SRA could be said
                 to have failed to implement the Resolution
                 Plan on account of the non-payment of
                 workmen and employees’ dues as per the
                 terms of the Resolution Plan and the order
                 of the NCLT dated 21.10.2022 which was
                 confirmed by the order dated 31.01.2023 of
                 this Court? ..................................................... 124
[2024] 11 S.C.R.                                                                              2055

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.


                  c.    Whether there were sufficient grounds before
                        the NCLAT to hold that Respondent No.1/SRA
                        had contravened the terms of the approved
                        Resolution Plan and that the Corporate Debtor
                        must be directed to be liquidated under Section
                        33(3) of the IBC, 2016? .................................... 131

           iii.   Whether the timely implementation of the
                  Resolution Plan is also one of the objectives of
                  the IBC, 2016? ........................................................ 139

      F.   SHORTCOMINGS AND SUGGESTIONS TO THE IBC,
           2016. ................................................................................ 150

      G. CONCLUSION ................................................................. 167




1.   These appeals arise from the judgment and order dated 12.03.2024
     passed by the National Company Law Appellate Tribunal (hereinafter,
     the “NCLAT”) in Company Appeal (AT) (INS) 129-130 of 2023 filed
     by the Appellant herein by which the NCLAT dismissed the appeal
     and upheld the order dated 13.01.2023 passed by the National
     Company Law Tribunal (hereinafter, the “NCLT”). The order of the
     NCLT held that Respondent No.1 had fulfilled all the Conditions
     Precedent as stipulated in the Resolution Plan. The NCLAT further
     issued several directions including a direction that the Performance
     Bank Guarantee of Rs. 150 Crore (hereinafter, the “PBG”) could be
     adjusted towards the first tranche payment of Rs. 350 Crore which
     was to be made by Respondent No.1.

     A.    FACTUAL MATRIX
2.   The NCLT vide its order dated 20.06.2019 in C.P. 2205 (IB)/ (MB)/
     2019 admitted the application for initiation of Corporate Insolvency
     Resolution Process (hereinafter, the “CIRP”) filed by State Bank of
     India (hereinafter, “SBI”) in respect of Jet Airways (India) Limited
     (hereinafter, the “Corporate Debtor”) in accordance with Section 7
     of the Insolvency and Bankruptcy Code, 2016 (hereinafter, the “IBC,
2056                                                     [2024] 11 S.C.R.

                        Supreme Court Reports


     2016”). The total admitted claim of the Financial Creditors was Rs.
     7800 Crore (approx.). Pursuant to the aforesaid Order, Mr. Ashish
     Chhawchharia, was appointed as the Interim Resolution Professional
     and was appointed as the Resolution Professional (hereinafter, the
     “RP”) as well.
3.   On 02.06.2020, the RP issued the 4th Round of the Request for
     Resolution Plan (hereinafter, the “RFRP”) as approved by the
     Committee of Creditors (hereinafter, “CoC”) which invited submissions
     of Resolution Plans for the Corporate Debtor from potential Resolution
     Applicants. The relevant clauses of the RFRP are reproduced
     hereinbelow:
          “3.13 Performance Security
          3.13.1 The Successful Resolution Applicant shall
          furnish or cause to be furnished, an unconditional and
          irrevocable performance bank guarantee or a demand
          draft, issued by any scheduled commercial bank in India
          or a foreign bank which is regulated by the central bank
          of a jurisdiction outside India which is compliant with the
          Financial Action Task force Standards and is a signatory to
          the International Organisation of Securities Commissions
          Multilateral Memorandum of Understanding, provided that
          it is acceptable to the Resolution Professional (acting for
          the CoC) (“PBG Bank”), of an amount of INR 150 Crores
          (Indian Rupees Hundred and Fifty Crores only) or 10%
          of upfront amount (payable as per the resolution plan
          by the Successful Resolution Applicant), whichever is
          higher in favour of “State bank of India, (that is, SBI) (in
          its capacity as an agent of the CoC (and acting on behalf
          of the Company), within 7 (seven) days of declaration of
          the Successful Resolution Applicant, or by way of a direct
          deposit by way of the real time gross settlement system
          into a bank account held by the SBI Bank, the details
          of which shall be shared separately with the Successful
          Resolution Applicant (“Performance Security”)
          3.13.2 If the Performance Security is being provided as
          a performance bank guarantee, it shall be in accordance
[2024] 11 S.C.R.                                                             2057

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          with Format VIII-A of this RFRP (“PBG”). The PBG shall
          be valid, till the later of (i) a period of 180 days from the
          date of the PBG; and (ii) the date of completion of the
          implementation of the Resolution Plan (as determined by
          the RP and the (CoC) and shall be subject to re-issuance
          or extension by the Successful Resolution Applicant as may
          be required by the CoC (as assisted by the Resolution
          Professional) (“PBG Validity”).

                       xxx                xxx                 xxx

          3.13.7 SBI, in its capacity as an agent of the CoC (and
          acting on behalf of the Company), shall have the right to
          invoke the Performance Security on behalf of the CoC (and
          upon receiving approval from the CoC), (by issuance of
          a written demand to the Bank to invoke the Performance
          Security, if provided as a PBG). The Performance Security
          can be invoked and appropriated at any time, upon
          occurrence of any of the following conditions, without any
          reference to the Resolution Applicant.
                i.       any of the condition under the Letter of Intent or
                         the Successful Resolution Plan are breached;
                ii.      if the Resolution Applicant fails to re-issue or
                         extend the Performance Security (if provided
                         as a PBG), in accordance with the terms of
                         this RFRP; or
                iii.     failure of the Successful Resolution Applicant
                         to implement the Approved Resolution Plan to
                         the satisfaction of the CoC, and in accordance
                         with the terms of the Approved Resolution Plan.
          3.13.8 The Performance Security shall be returned to the
          Successful Resolution Applicant within a period 7 (seven)
          Business Days (based on the request received from the
          Successful Resolution Applicant) upon 100% (one hundred
          percent) of the completion of the implementation of the
          Approved Resolution Plan by the Successful Resolution
          Applicant.
2058                                                      [2024] 11 S.C.R.

                        Supreme Court Reports



          3.13.9 The Performance Security shall not be set-off against
          or used as part of the consideration that the Successful
          Resolution Applicant proposes to offer in relation to
          the Company, even if expressly indicated as such by
          the Successful Resolution Applicant in the Successful
          Resolution Plan.”
                                                 (emphasis supplied)

4.   On 21.09.2020, the Consortium of Murari Lal Jalan and Florian Fritsch
     (hereinafter, the “Respondent No.1 / SRA”) submitted its Resolution
     Plan. It was amended by the version dated 30.09.2020 and further
     supplemented and amended by the addendum dated 02.10.2020. At
     the 17th meeting of the CoC held on 03.10.2020, the Resolution Plan
     was placed before the CoC by the RP and was voted upon by the CoC
     from 05.10.2020 to 17.10.2020 in accordance with Regulation 39 of
     the Insolvency and Bankruptcy Board of India (Insolvency Resolution
     Process for Corporate Persons) Regulations, 2016 (hereinafter, the
     “2016 Regulations”). The CoC, in its commercial wisdom, approved
     the Resolution Plan proposed by Respondent No. 1 with a majority
     of 99.22% votes. The relevant clauses of the Resolution Plan are
     reproduced hereinbelow:
          “2. INTRODUCTION OF THE RESOLUTION APPLICANT
          2.1.4. The resolution applicant (“Resolution Applicant”)
          is defined to mean a Consortium of:
          a)   Mr. Murari Lal Jalan who is the Lead Partner of the
               Consortium;
          b)   Mr. Florian Fritsch is the Other Partner of the
               Consortium; and
          2.1.5. Mr. Murari Lal Jalan will hold shares in the Corporate
          Debtor in his personal capacity.
                  xxx                 xxx                 xxx

          6.3.1(c) Summary of Financial Proposal
          THE RESOLUTION PLAN SUBMITTED BY THE
          RESOLUTION APPLICANT IS UNCONDITIONAL AND
          NOT SUBJECT TO SALE OF THE ASSETS OF THE
          CORPORATE DEBTOR.
[2024] 11 S.C.R.                                                                    2059

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.


              HEADS      PACKAGE OF        AMOUNT        PAYMENT TERMS
                          ~RS. 4,783        (In Rs.)
                           CRORES
                        COMPRISING OF

                        ● ~RS.
                          1,090.1 CR
                          COMMITTED
                          CASH
                        ● ~Rs. 3,668
                          Crores –
                          estimated
                          value of 10%
                          Equity Stake                    Within         After
                          in Jet 2.0 at                 180 days       180 from
                          Year 5                        from the       Effective
                        ● 7.5% Equity                   Effective        Date
                          stake in JPPL                   Date
                          for Assenting
                          FCs.
                        ● Airport
                          Savings
                        ● Additional
                          Upside on
                          Aircraft + ATR
                          + Spares +
                          BKC
                        ● ~ Rs. 25
                          Crores for
                          acquisition
                          of additional
                          50.1% stake
                          in JPPL from
                          Etihad
            CIRP Cost   CIRP COST           25 Cr        100%
            ASSENTING   ● Rs. 195 Cr       380 Cr         185 Cr        195 Cr
                          + up to Rs.                  (Incl. 10 Cr     in Yr. 2
               FCS
                          185 Cr +                       for BKC)
                          Guaranteed
                          NPV of                                      Guaranteed
                          Rs. 391 Cr                     9.5%         NPV of 391
                          (using the                   Equity in        Cr (using
                          discount rate                 Jet 2.0       the discount
                          specified in                                    rate
                          the Evaluation                                specified
                                                          7.5%           in the
                          Matrix)
                                                        equity in      Evaluation
                                                         JPPL           Matrix) in
                                                                       Yr. 3, 4, 5
2060                                                          [2024] 11 S.C.R.

                     Supreme Court Reports



                    ● Rs. 40 Cr of                Additional      Upside
                      Positive Cash               Upside on      on BKC
                      Balance                      Aircrafts    Savings on
                                                    Sales +       Airport
                    ● 9.5% equity
                                                  ATR Sales
                      in Jet 2.0 (5th
                                                   + Spares
                      Yr Value ~Rs.
                      3,485 Crore)
                    ● 7.5% equity in               Savings
                      JPPL                         on CIRP
                                                    Costs
                    ● Upside on
                      Aircrafts +
                      ATR Inventory                Positive
                      + Spares +                    Cash
                      BKC Property                 Balance
                      (if given)
                    ● Savings on
                      CIRP Costs
                    ● Savings
                      on airport
                      and parking
                      charges
                    ● Savings on
                      Contingency
                      Fund
                    ● All payments
                      are secured
                      against
                      tangible
                      security
                    ● Dissenting
                      FCs will be
                      paid in priority
                      as per IBC
        Workmen &
                    Rs. 52 Crores        52 Cr      100%
        Employees
          OCs       ● Rs. 15,000 to
                      each of the
                      Operational
                      Creditors,         10 Cr      100%            -
                      irrespective of
                      their claim


        OC (Dutch
         Admin)                          10,000     100%            -
[2024] 11 S.C.R.                                                              2061

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

               Other
             Creditors
            (other than                        10,000     100%           -
              FCs and
                OCs)
            Shareholders
             (promoters,
                                               10,000     100%           -
            Etihad and
               PNB)
           Contingency                                     100%
                                                 8 Cr
               Fund                                     Established
               JPPL         Offer from RA to
                            acquire 50.01%
                             shareholding
                             in JPPL from
                                 Etihad.


                                               25 Cr         -          100%
                            The said sum of
                             Rs. 25 Crores
                             will be infused
                              by the RA in
                             addition to the
                            abovementioned
                                amounts.
                                               475 Cr
                           TOTAL                 +
                                               25 Cr

          *THIS IS A SUMMARY OF THE FINANCIAL PROPOSAL.
          PLEASE REFER TO THE DETAILED PROVISION
          UNDER THE RESPECTIVE HEAD.

                     xxx                   xxx                    xxx

          (d) PROPOSAL FOR RESOLUTION OF OUTSTANDING
          AIRPORT AND PARKING DUES (RS. 240 CRORES AS
          OF AUGUST 31, 2020)
          […]
          BKC Property not part of resolution - If CoC decides
          to retain the BKC Property as a non-core asset and not
          offer it as part of this resolution process as proposed
          above, then the Resolution Applicant will not pay the
          upfront sum of Rs. 10 Crores to the Assenting Financial
2062                                                   [2024] 11 S.C.R.

                      Supreme Court Reports


        Creditors as envisaged in the above Clause for BKC
        Property. Further, then the airport dues and parking
        charges after the ICD (approx. Rs. 240 Crores as of
        August 31, 2020) will be paid by the Resolution Applicant
        upfront in priority over any other payments to the creditors
        of the Corporate Debtor, subject to a maximum of Rs.
        475 Crores. As per the general aviation practice in
        respect to parking and airport space, as and when the
        Corporate Debtor will intend to use/ move the aircrafts
        or use the airport space, such claimants will seek their
        past dues. Therefore, their payments need to be resolved
        upfront by pro rata reduction of amounts payable to other
        creditors, to enable the Corporate Debtor to re-commence
        its operation, which is why the Resolution Applicant
        has suggested that their payments be made upfront
        against the BKC Property. SUCH PAYMENTS WILL
        BE SETTLED UPFRONT IN FULL IN FIRST 180 DAYS
        FROM THE EFFECTIVE DATE AND WITHOUT ANY
        CONDITIONS (INCLUDING NOT BEING STAGGERED
        PAYMENTS SPREAD ACROSS A PERIOD OF TIME) SO
        THAT FLYING CAN START IMMEDIATELY WITHOUT
        ANY FUTURE DISPUTES AND CONCERNS WITH
        SUCH CLAIMANTS FOR PAST DUES. Alternatively,
        the Resolution Professional can provide the Resolution
        Applicant with a no-dues certificate from such contingent
        creditors, in which case, these creditors will be treated
        in compliance with the provisions of the IBC.
        The Resolution Applicant states and confirms that this
        “Proposal for Resolution of outstanding airport and
        parking dues (approx. Rs. 240 Crores as of August 31,
        2020)” which deals with the appropriation of the BKC
        Property is merely a proposal and not a condition to
        the implementation of this Resolution Plan and the CoC
        has the discretion to accept/ reject such proposal. If the
        above-mentioned proposal is acceptable to the CoC, then
        it is acceptable to the Resolution Applicant in the manner
        stated hereinabove.
[2024] 11 S.C.R.                                                                   2063

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          (g) Infusion of funds and timelines
              Infusion              Amount (In Rs.)           Purpose/Utilization
           Timelines (In       As Equity        As ECB
               Days)
           Upfront (within   350,00,00,000         -          CIRP Cost;
           180 days)                                          Contingency
                                                              Fund; Payment to
                                                              FCs, OCs, Other
                                                              Creditors, and
                                                              other stakeholders;
                                                              working capital for
                                                              business; Misc.
                                                              Admin Expenses
           181-365 days      250,00,00,000         -          Working capital
                                                              for business;
                                                              Portion of funds
                                                              can be used for
                                                              acquiring Etihad’s
                                                              stake in JPPL;
                                                              making payments
                                                              to creditors if
                                                              RA is inclined in
                                                              advancing any
                                                              payment timelines
           Year 2                  -         175, 00,00,000   Remaining payment
                                                              to FCs.; Misc.
                                                              expenses for
                                                              general corporate
                                                              and day-to-day
                                                              operations, in
                                                              compliance with
                                                              the extant ECB
                                                              Regulations.
           After Year 2            -         600,00,00,000    Working capital for
                                                              business
           Sub-Total         600,00,00,000   775,00,00,000


           TOTAL                                              1,375,00,00,000



                     xxx                     xxx                    xxx

          6.4. Treatment of Stakeholders
          6.4.1. Treatment of outstanding CIRP Costs
          (a) In terms of Section 30(2)(a) of the IBC, the CIRP
          Costs are to be paid in priority to any other creditor of
          the Corporate Debtor.
2064                                                   [2024] 11 S.C.R.

                       Supreme Court Reports


        (b) As per the information disclosed by the Resolution
        Professional on August 14, 2020, the CIRP Costs includes:
              i.    Operating and Process Costs (Rs. 27.16 Crores,
                    as of August 31, 2020) which includes fees,
                    charges, salaries of Asset Protection Team
                    (APT) of the Corporate Debtor and other costs
                    incurred by the Resolution Professional in
                    running the operations of the Corporate Debtor
                    as a going concern;
              ii.   Interim Finance Cost (Rs. 54.4 Crores, as of
                    August 31, 2020).
        […]
        (d) The Resolution Professional has also disclosed to
        the Resolution Applicant that the Corporate Debtor has
        a positive bank balance of approx. Rs. 92 Crores and
        estimates to collect a further sum of Rs. 40 Crores in the
        next 2-3 months.
        […]
        (f) The Resolution Professional has estimated an approx.
        sum of Rs. 240 Crores (as of August 31, 2020) towards
        parking charges for aircrafts and airport space lease
        charges. Such amounts are good faith estimates of the
        Resolution Professional based on previous invoices as
        it has not received any invoice/ demand from any of
        the lessors/ owners for such amounts. The Resolution
        Applicant shall endeavour to negotiate the parking fee
        and rental fee for the Corporate Debtor with the various
        airports and will endeavour that the cost for such heads
        is kept to the minimum.
        […]
        (h) Based on the information provided, the Resolution
        Applicant have assumed that the amounts standing to
        the credit of the bank account of the Corporate Debtor
        (including amounts estimated to be received subsequently)
        are sufficient to cover for the CIRP Costs of the Corporate
        Debtor (excluding parking charges, rental charges,
        employee dues, taxes etc). Accordingly, the Resolution
[2024] 11 S.C.R.                                                           2065

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          Applicant has set aside a sum of Rs. 25 Crores as CIRP
          Costs towards payment of any such costs until the Approval
          Date. Any expenses incurred by the Corporate Debtor from
          the Approval Date until the Effective Date will be incurred
          out of the positive bank balance of the Corporate Debtor.
          (i) As stated in Clause 6.3.1(d) above, if the CoC agrees
          to offer a clear and marketable title in the BKC Property
          (one floor) to the Resolution Applicant, then the Resolution
          Applicant shall settle the airport and parking charges
          (estimated at approx. Rs. 240 Crores, as of August 31,
          2020). Savings from such charges will be distributed to the
          Assenting Financial Creditors. If the airport and parking
          charges over are over Rs. 245 Crores, then amounts over
          and above Rs. 245 Crores will be first paid out of Rs. 25
          Crores reserved as CIRP Costs (if there are no outstanding
          CIRP Costs) and then out of the positive cash flows of
          the Corporate Debtor. Any amounts over and above such
          amounts will be shared between the Resolution Applicant
          and the Assenting Financial Creditors in equal proportion.
          (j) The Resolution Applicant states that if the CIRP Cost is
          less than the estimated amounts and the airport dues are
          less than Rs. 245 Crores, then the differential amounts will be
          paid by the Resolution Applicant to the Assenting Financial
          Creditors, which amounts are over and above the amounts
          reserved for them this Resolution Plan. However, if the CIRP
          Cost exceeds the current estimates, then the CIRP Costs
          will be paid by the Resolution Applicant as per actuals in
          compliance with the provisions of the IBC and commercial
          proposal for other creditors of the Corporate Debtor will be
          adjusted accordingly, subject however to a maximum of Rs.
          475 Crores. It is clarified that on account of such payments
          from the amounts infused by the Resolution Applicant in the
          Corporate Debtor, the pay-outs towards other claimants as
          currently stated will be reduced proportionately to account
          for such additional CIRP Costs, subject to a minimum
          payment of liquidation value to the Operational Creditors
          and Dissenting Financial Creditors of the Corporate Debtor
          and subject to a maximum of Rs. 475 Crores.
          (k) The outstanding CIRP Costs shall be paid by
          the Resolution Applicant out of funds infused by the
2066                                                   [2024] 11 S.C.R.

                      Supreme Court Reports


        Resolution Applicant in the Corporate Debtor and as per
        the Implementation Schedule set out in Clause 7.7 below.
        […]
        (m) Priority of Payment CIRP Cost shall be fully paid and
        discharged after the Effective Date before payment is
        made to any of the Creditors as per the Resolution Plan.
        The Resolution Applicant will be entitled and will use funds
        available with the Corporate Debtor on the Effective Date
        for making any portion of CIRP payments.
        (n) The Resolution Applicant has sufficient funds and do
        not envisage any challenge in terms of source for making
        such payments. The net worth and financial capabilities
        of the Resolution Applicant are evident from its financial
        statements submitted at the time of submitting its EOI.
        Regarding the Source of Funds, the CIRP Costs shall be
        met out of funds infused by the Resolution Applicant in
        the Corporate Debtor.
                xxx                 xxx                 xxx
        6.4.2. Treatment of Employees/Workmen dues,
        including dues of Authorized Representatives of
        Employees/ Workmen
        (a) The Resolution Applicant proposes to pay a fixed sum
        of Rs. 52 Crores to the Workmen/ Employees towards
        settlement of all the claims made by the Employees
        and Workmen of the Corporate Debtor, including to the
        Authorized Representatives of Employees and Workmen
        as set out in the List of Creditors (“Admitted Workmen
        and Employees Dues”).
        (b) The payments towards Admitted Workmen and
        Employees Dues shall be made out of funds infused by
        the Resolution Applicant in the Corporate Debtor and as
        per the Implementation Schedule set out in Clause 7.7
        below. The said payment is also being made in priority to
        the payment to the financial creditors.
        (c) In any case, if the Liquidation Value due to Operational
        Creditors (Employees/ Workmen dues, including dues of
        the Authorized Representatives of Employees/ Workmen)
[2024] 11 S.C.R.                                                         2067

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          is not “NIL”, then the Resolution Applicant undertakes that
          the Liquidation Value due to such Operational Creditors
          (Employees/ Workmen dues including dues of Authorized
          Representatives of Employees/ Workmen) shall be paid
          and shall be given priority in payment over Financial
          Creditors as is already reflected in the Implementation
          Schedule in Clause 7.7 below. The entire payment to the
          Employees/ Workmen dues including dues of Authorized
          Representatives of Employees/ Workmen is being made
          in priority within 175 (one hundred seventy five) days from
          the Effective Date.
          […]
          (g) Other than Admitted Workmen and Employees Dues
          which the Resolution Applicant proposed to pay, all other
          potential obligations and workmen dues including any
          dues towards Provident Fund (Contribution of Employees /
          Company), Gratuity, Employees State Insurance Scheme,
          Professional Tax or any other taxes in nature of employment
          owed or payable to, (including any demand for any penalty,
          penal interest already accrued/ accruing or in connection
          with any claims) and all rights and entitlements of present
          or past, direct or indirect, permanent or temporary,
          employees and/or workmen of the Corporate Debtor,
          whether admitted or not, due or contingent, asserted
          or unasserted, crystalized or uncrystallized, known or
          unknown, secured or unsecured, disputed or undisputed,
          present or future, whether or not set out in the balance
          sheet of the Corporate Debtor or the profit and loss account
          statements of the Corporate Debtor or the List of Creditors,
          claim submitted or not submitted, claim admitted or not
          admitted, in relation to any period prior to the ICD will be
          written off in full and shall be deemed to be permanently
          extinguished and waived off subject to Clause 9.9 of this
          Resolution Plan by virtue of the order of Adjudicating
          Authority approving the Resolution Plan and neither the
          Corporate Debtor nor the Resolution Applicant shall, at no
          point of time be, directly or indirectly, held responsible or
          liable in relation thereto.
          […]
2068                                                                [2024] 11 S.C.R.

                        Supreme Court Reports


        (i)(xi) For the avoidance of doubt it is hereby clarified that
        notwithstanding the acceptance or rejection of the terms of
        the proposed demerger by the employees and/or workmen,
        the Resolution Applicant shall ensure the payment of (i)
        minimum value due and payable to such employees and
        workmen (under Section 30(2) of the IBC); and (ii) the CIRP
        costs admitted by the Resolution Professional, subject to
        a maximum of Rs. 475 Crores.
                  xxx                   xxx                      xxx
        6.4.4. Treatment of Financial Creditors
        […]
        Summary of payments and security package
          Head     Amount       Security      Value of Date of   Date of
                   Payable      Offered       Security Creation Release of
                                                          of     Security
                                                       Security
         Cash    Up to Rs. PBG of Rs.         Rs. 393.5 Effective        PBG
        Payment 185 Crores 47.5 Crores         Cr (with   Date         adjusted
                                                BKC)
                              BKC Property                                To be
                              (if given)                              released on
                                                                      sale of BKC
                                                 Or
                              Mortgage over                            Year 5 or
                              Dubai                                   on complete
                                                                       payment,
                              Property No. Rs. 147.5
                                                                       whichever
                              1 valued at      Cr                       is earlier
                              more than Rs. (without
                              100 Crores     BKC)
         Cash       Rs. 195   BKC Property    Rs. 445    Effective     To be
        Payment     Crores    (if given)        Cr         Date    released on
                                                                   sale of BKC
                                                (with
                              Mortgage over     BKC)     Effective  Year 5 or
                              Dubai                        Date    on complete
                                                                    payment,
                              Property No.
                                                                    whichever
                              1 valued at        Or
                                                                     is earlier
                              more than Rs.
                              100 Crores
                              Mortgage over   Rs. 200    Effective
                              Dubai             Cr         Date
                              Property No.    (without
                              2 valued at      BKC)
                              more than Rs.
                              100 Crores
[2024] 11 S.C.R.                                                                         2069

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.


            Cash         NPV of     Mortgage over    Rs. 600   Effective  Year 5 or
           Payment      Rs. 391     Dubai            Crores      Date    on complete
                         Crores                                           payment,
                                    Property No.
                       (using the                                         whichever
                                    1 valued at
                        discount                                           is earlier
                                    more than Rs.
                           rate     100 Crores
                        specified
                          in the    Mortgage over              Effective
                       Evaluation   Dubai                        Date
                         Matrix)    Property No.
                                    2 valued at
                                    more than Rs.
                                    100 Crores
                                    Mortgage over              Effective
                                    Dubai                        Date
                                    Property No.
                                    3 valued at
                                    more than Rs.
                                    50 Crores.
                                    Floating                   Effective
                                    charge                       Date
                                    by way of
                                    hypothecation
                                    on India POS
                                    Credit Card
                                    Receivables of
                                    Year 3, Year
                                    4, Year 5 of
                                    the Corporate
                                    Debtor of Rs.
                                    350 Crores
                                    or the total
                                    outstanding
                                    dues of the
                                    Assenting
                                    FCs,
                                    whichever is
                                    lower.
           Upside         Rs. 60   Three 737s;       BV of Rs. Effective    On sale of
              on        Crores + Five 777s &          1,900      Date        relevant
           Aircrafts    upside as                                           aircraft(s)
                        per terms Three A330                                as it could
                       of Series B                                          be sold in
                           ZCB                                             Lots and in
                                                                            phases or
                                                                           on relevant
                                                                           redemption
                                                                               date,
                                                                            whichever
                                                                            is earlier.
2070                                                                   [2024] 11 S.C.R.

                          Supreme Court Reports



         Upside        Rs. 15   Entire ATR        BV of Rs. Effective    On sale of
         on ATR      Crores + Inventory            134 Cr     Date         ATR
        Inventory    upside as
                                                                          Inventory
                     per terms
                                                                         on relevant
                    of Series C
                                                                         redemption
                        ZCB
                                                                             date,
                                                                          whichever
                                                                          is earlier.
         Upside        Rs. 50   Aircraft Spares BV of Rs. Effective       On sale of
           on        Crores +                    600 Cr     Date          Spares on
         Spares      upside as                                             relevant
                     per terms                                           redemption
                    of Series D                                              date,
                        ZCB                                               whichever
                                                                          is earlier.


        (a) COMMITTED CASH PAYMENTS
        (i) The Resolution Applicant will pay the Assenting
        Financial Creditors a total sum of Rs. 185 Crores on
        180th day from the Effective Date. If the BKC Property
        is not provided to the Resolution Applicant as per the
        proposal stated in Clause 6.3.1(d), then the Resolution
        Applicant will pay the Assenting Financial Creditors, a
        total sum of Rs. 175
        Crores on 180th day from the Effective Date. The said
        amounts shall be paid on the following principal terms:

        Amount Payable           Up to Rs. 185 Crores/ up to Rs. 175 Crores

        Payable By               Jet Airways (India) Limited

        Payable To               Financial Creditors against conversion of
                                 admitted claims of equivalent amount.

        Date of Payment          180th day from the Effective Date.

        Security                 ● Performance bank guarantee of Rs. 47.5
                                   Crores
                                 ● Mortgage over BKC Property (if given to the
                                   RA).
                                 ● Mortgage over Dubai Property No. 1 valued
                                   at more than Rs. 100 Crores.

        Date of creation of      Effective Date
        security
[2024] 11 S.C.R.                                                                  2071

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.


           Date of release of   ● BKC Property - On sale of BKC Property (if
           Security               given to the RA) or on the date of payment,
                                  whichever is earlier.

                                ● Charge over Dubai Property No. 1 with
                                  respect to this payment will be released on
                                  the date of payment.

           Security Related     RBI approval required for creating charge
           Terms                over Dubai Property No. 1 will be applied after
                                the CoC approves this Resolution Plan. If the
                                RBI approval for creating such charge is not
                                received by the Effective Date, then alternate
                                security will be provided in India of equivalent
                                value on the Effective Date.

           Event of Default     Corporate Debtor’s failure to make such
                                committed payment

           Consequences of      Enforcement of security for recover the
           Event of Default     outstanding amounts.

           Governing Law and    Indian Law and courts of Mumbai will have
           Jurisdiction         exclusive jurisdiction.

                     xxx                 xxx                       xxx
          6.4.12. Request for the consideration of the CoC - As
          required under the RFRP, the Resolution Applicant shall
          provide the performance security bank guarantee (“PBG”)
          for a total sum of Rs. 150 Crores. The PBG will be provided
          in two parts, with the first PBG of Rs. 47.5 Crores provided
          within 7 (seven) days from the date of receipt of LOI; and
          PBG for the remaining sum of Rs. 102.5 Crores provided
          on the Effective Date.
          7.3. Compliance with respect of Regulation 36B (4A)
          The Resolution Applicant undertakes to provide the
          performance security bank guarantee as per the terms
          of the RFRP in favour of “State Bank of India” (in its
          capacity as an agent of the CoC (and acting on behalf of
          the Corporate Debtor)), within 7 (seven) days of it being
          declared the “Successful Resolution Applicant”, or by way
          of a direct deposit by way of the real time gross settlement
          system into a bank account held by the SBI Bank, as per
          the terms of the RFRP.
                     xxx                 xxx                       xxx
2072                                                   [2024] 11 S.C.R.

                      Supreme Court Reports


        7.1. Term of the Resolution Plan
        7.1.2. The effectiveness and implementation of the
        Resolution Plan by the Resolution Applicant shall be subject
        to the approval of the NCLT. Notwithstanding anything
        set out in this Resolution Plan, the implementation of this
        Resolution Plan by the Resolution Applicant shall not be
        conditional upon satisfaction of any conditions, other than
        approval of the NCLT.
        7.6. Conditions to the Implementation of the Resolution
        Plan
        7.6.1. Conditions Precedent - The obligation of the
        Resolution Applicant to re-commence operations as
        an aviation company, being the business proposed to
        be acquired is subject to the fulfilment of the following
        conditions after the Approval Date (“Conditions Precedent”):
        (a)   Validation of AOP of the Corporate Debtor by DGCA
              & MoCA - The AOP of the Corporate Debtor shall
              have been validated by the DGCA, the MoCA and
              any other relevant Government Authority and grant
              of all other mandatory approvals to the Corporate
              Debtor to enable it to re-commence flying operations
              (including commercial/ cargo operations) and related
              on-ground services.
        (b)   Submission and approval of the Business Plan
              to DGCA & MoCA - The Business Plan of the
              Resolution Applicant shall have been submitted
              after the Approval Date to the DGCA and MoCA for
              their review, and approval. The Resolution Applicant
              agrees to modify its business plan to incorporate all
              reasonable changes required by the DGCA/ MoCA,
              which otherwise does not make the business unviable
              for the Resolution Applicant.
        (c)   Slots Allotment Approval - The DGCA and MoCA
              shall have approved the reinstatement of all the
              suspended slots (including the bilateral rights and
              traffic rights) back to Jet Airways/ Corporate Debtor.
              The slots (along with related bilateral rights and
[2024] 11 S.C.R.                                                         2073

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

                traffic rights) can be allotted to the Corporate Debtor
                gradually as per its Business Plan with immediate
                slots allotment approval (along with related bilateral
                rights and traffic rights) for sectors on which Jet
                2.0 proposes to recommence operations after the
                Effective Date.
          (d)   International Traffic Rights Clearance - The Corporate
                Debtor shall have received the International Traffic
                Rights Clearance in compliance with Applicable Laws.
          (e)   Demerger - The Scheme filed as part of this
                Resolution Plan shall have been approved under
                Applicable Laws and the Demerged Employees
                shall have demerged from the Corporate Debtor to
                AGSL along with all their past dues, liabilities and
                outstanding’s with effect from the Approval Date,
                without the requirement of any further consent or
                approval of any other stakeholder of AGSL (since we
                understand that AGSL currently does not have any
                creditor) or any stakeholder of the Corporate Debtor
                (including existing or past employee or workmen or
                employees’ unions of the Corporate Debtor).
          7.6.2. Fulfilment of Conditions Precedent - The date
          of fulfilment of all the Conditions Precedent as stated
          in Clause 7.6.1 above shall be the effective date for the
          purposes of this Resolution Plan (“Effective Date”).
          7.6.4. Automatic Withdrawal - The Resolution Applicant
          is confident of completing all the Conditions Precedent
          (as set out in Clause 7.6.1 above) within 90 (ninety) days
          from the Approval Date. In the unlikely event that all the
          Conditions Precedent cannot be fulfilled within 90 (ninety)
          days, the Resolution Applicant takes the responsibility of
          completing the outstanding Conditions Precedent at the
          earliest and seeks to extend the Conditions Precedent
          fulfilment period by another term of maximum 180 (one
          hundred and eighty) days. If all the Conditions Precedent
          are not fulfilled within such period (i.e. 270 (two hundred
          and seventy) days from the Approval Date), then this
          Resolution Plan shall automatically stand withdrawn without
2074                                                                   [2024] 11 S.C.R.

                         Supreme Court Reports


        any further acts, deeds, or things. On such withdrawal,
        the members of the Resolution Applicant in the Monitoring
        Committee shall resign, and the remaining members of
        the Monitoring Committee shall assume absolute control
        of the Corporate Debtor.
        7.7. Implementation Schedule -
        7.7.1. The Resolution Applicant shall take the following
        steps in the order of sequence (except otherwise mentioned
        in any step for any part of the step) as an integral part
        of the Resolution Plan. It is provided that the procedure,
        timelines and the sequence of steps listed below are only
        indicative and that they may be re-arranged/ changed as
        may be required or directed based on discussions with
        the necessary Governmental Authorities/ stock exchange
        (on account of past non-compliances of the Corporate
        Debtor or otherwise) or for the purposes of advancing
        any payments to the stakeholders, and at all times in
        compliance with Applicable Laws:
        Step                         Activity                              Days
          1.   Receipt of approval from the Competition                    Before
               Commission of India under the provisions of the           approval of
               Competition Act, 2002 read with the provisions            Resolution
               of the IBC.                                              Plan by CoC
          2.   Declaration of the Successful Resolution Applicant            X
               and Receipt of LoI from the CoC
          3.   Unconditional acceptance of the LoI                         X+3
          4.   Issuance of Performance Security Bank Guarantee             X+7
          5.   Finalization of the members of the Monitoring             Between X
               Committee                                                and Approval
                                                                            Date
          6.   Approval Date                                                 Y
          7.   Monitoring Committee to take control as per                   Y
               Clause 7.8.2.
          8.   Fulfilment of Conditions Precedent as per                  After Y
               Clause 7.6.1
          9.   Filings of the certified copy of the Order of Approval     Y + 10
               received from Adjudicating Authority sanctioning
               the Resolution Plan with the relevant Government
               Authorities/ Stock Exchange/ Departments.
         10.   Effective Date                                                Z
[2024] 11 S.C.R.                                                                    2075

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.


            11.   Infusion of Rs. 350 Crores in the Corporate           Z + 150
                  Debtor
            12.   Setting up the Contingency Fund                       Z + 170
            13.   Cancellation of Shares (excluding Public Shares)      Z + 170
                  as per Clause 7.4.1(c).
            14.   Reconstitution of Share Capital as per Clause         Z + 170
                  7.4.2 above.
            15.   Steps towards issuance of equity shares as per        Z + 170
                  Clause 7.4.3
                  above.
            16.   Payment of CIRP Costs as per Clause 6.4.1.            Z + 170
            17.   Payment to the Operational Creditors (Workmen and     Z + 175
                  Employees, including Authorized Representatives
                  of Workmen and Employees) as per Clause 6.4.2.
            18.   Payment to all the Operational Creditor (other        Z + 175
                  than Workmen and Employees) as per Clause
                  6.4.3 above.
            19.   Payment to Other Creditors and Stakeholders as        Z + 175
                  per Clause 6.4.5, Clause 6.4.6, 6.4.7, and 6.4.8
            20.   Payment to Dissenting Financing Creditors as per      Z + 176
                  Clause 6.4.4(m)(i).
            21.   1st Tranche payment to Financial Creditors as per     Z + 180
                  Clause 6.4.4.
            22.   Monitoring Committee to be released and               Z + 180
                  Reconstituted Board of Directors to take over the
                  management of the Corporate Debtor.
            23.   Closing Date.                                        Z + 180
            24.   Redemption of Series B, Series C; and Series         Z + 365
                  D ZCBs
            25.   Necessary statutory approvals                        Y + 365
                                                                          (in
                                                                      accordance
                                                                       with Sec
                                                                      31(4) of the
                                                                         IBC)
            26.   Redemption of Series A ZCB                           Z + 730
            27.   Release of charge (if any) over assets of the        Z + 730
                  Corporate Debtor (which have not been previously
                  released).
            28.   Redemption of NCDs and release of any charge        Z + 5 Years
                  (if any)

                     xxx                    xxx                       xxx
2076                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


          9.4. Implementation - The performance guarantee
          provided by the Resolution Applicant can be invoked in
          accordance with the terms of the RFRP.”
5.   The RP preferred an application under Section 30(6) read with
     Section 31 of the IBC, 2016 before the NCLT seeking approval of
     the Resolution Plan submitted by Respondent No.1 and vide order
     dated 22.06.2021, the NCLT approved the Resolution Plan. In
     view of the uncertainty regarding the achievement of the “Effective
     Date” under Clauses 7.6.2 and 7.6.4 of the Resolution Plan, it was
     clarified that the same would be fixed on the 90th day from the Plan
     Approval Order dated 22.06.2021. Respondent No.1 was also given
     liberty to approach the NCLT for appropriate orders with respect to
     an extension of the timeline, subject to a maximum of another 180
     days, in case they fail to fulfill all the Conditions Precedent within
     90 days. The relevant observations are reproduced hereinbelow:
          “33. During the hearing, the uncertainty of the time frame
          for implementation of the Resolution Plan was discussed.
          It is stated by the SRA in clause no. 7.6.2 (pdf 276) of
          the Resolution Plan that the effective date would mean
          the date of the fulfilment of all the conditions precedent
          as stated in clause 7.6.1 thereof. The SRA, at clause no.
          7.6.4, has gone on to add that the consortium would make
          all endeavor to ensure all the compliances are done for the
          fulfillment of the conditions precedent within a period of 90
          days. In the unlikely event that the conditions precedent
          are not complied within this period, SRA would require a
          maximum of 180 days more to fulfil the conditions. Failing
          which the Resolution Plan would stand automatically
          withdrawn without any further act, deed or thing. In view of
          such uncertainty in the ‘effective date’ the Bench suggested
          that let the effective date be the 90th day from the Approval
          Date (clause 3.1 at pdf page 201). The SRA as well as
          the Applicant (RP of the Corporate Debtor) had agreed
          to the suggestion. This in our opinion is not in the nature
          of a substitution or addition to the decision, commercial
          or otherwise, of the CoC. The suggestion is made only to
          give finality and certainty to the effective date, which the
          SRA has otherwise committed in the Resolution Plan to
          endeavor to do. It could accordingly be ordered so. Failing
[2024] 11 S.C.R.                                                       2077

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          which the SRA / Corporate Debtor would be at liberty to
          approach this Authority for appropriate orders with regard
          to extension of the timeline, as would be deemed proper.
          That would help prevent the SRA from the frustration of
          ‘automatic withdrawal’ referred to in clause 7.6.4 of the
          Resolution Plan.”
                                                  (emphasis supplied)

6.   Since the initial period of 90 days for fulfilment of the Conditions
     Precedent expired on 22.09.2021, an extension of another 90 days
     was granted by the NCLT vide order dated 29.09.2021 (1st extension).
     The 1st extension of 90 days expired on 22.12.2021. The NCLT vide
     order dated 20.01.2022, again, granted an extension of another
     90 days (2nd extension). The 2nd extension of 90 days expired on
     22.03.2022. The maximum extension that could have been provided
     under Clause 7.6.4 of the Resolution Plan i.e., an additional 180 days,
     had now come to an end. However, vide order dated 11.04.2022, the
     NCLT granted exclusion of a period of 65 days from 17.01.2022 to
     22.03.2022, which was spent in moving the application for grant of
     time. This finally extended the time for achieving the Effective Date
     from 22.03.2022 to 25.05.2022 (3rd extension).
7.   On 20.05.2022, Respondent No.1 obtained the Air Operation
     Certificate (hereinafter, the “AOC”) and asserted that all the Conditions
     Precedent required under Clause 7.6.1 of the Resolution Plan had
     been met and that the Effective Date in accordance with Clause 7.6.2
     had been achieved. As a consequence, Respondent No.1 had 180
     days from 20.05.2022 i.e., until 16.11.2022 to infuse an amount of
     Rs. 350 Crore in the Corporate Debtor as per Clause 6.3.1(g) and the
     Implementation Schedule under Clause 7.7.1 of the Resolution Plan.
8.   The workmen and employees of the Corporate Debtor and several
     Operational Creditors challenged the order of the NCLT dated
     22.06.2021 by which the Resolution Plan was approved before the
     NCLAT. Vide order dated 21.10.2022, the NCLAT upheld the order
     of the NCLT dated 22.06.2021. However, it was observed that the
     workmen and employees are entitled to the payment of their full
     provident fund and gratuity which was unpaid as on the insolvency
     commencement date and that the balance of the above dues should
     be paid by the Successful Resolution Applicant i.e., Respondent No.1,
     in order to satisfy its statutory obligations. It was further stated that
2078                                                      [2024] 11 S.C.R.

                         Supreme Court Reports


     “Non-payment of full PF and Gratuity shall lead to violation of Section
     30(2)(e) and hence, to save the plan, the above payments have to
     be made”. On 20.12.2022, Respondent No.1 preferred Civil Appeal
     Nos. 465-469 of 2023 against the aforesaid order dated 21.10.2022
     passed by the NCLAT, before this Court.
9.   It is the case of Respondent No.1 that between May 2022 and
     October 2022, the Appellants disputed the fulfilment of the Conditions
     Precedent by Respondent No.1 on one ground or another. Therefore,
     on 18.10.2022, Respondent No.1 filed two Interim Applications – First,
     IA No. 3398 of 2022 (hereinafter, “Implementation Application”)
     before the NCLT seeking necessary directions for the implementation
     of the Resolution Plan and a declaration that all the Conditions
     Precedent have been fulfilled; Second, IA No. 3508 of 2022
     requesting that the period from 20.05.2022 till the date on which
     the Implementation Application would be decided by the NCLT be
     excluded for the purpose of calculating 180 days from the Effective
     Date, for the purpose of making the first tranche payment of Rs.
     350 Crore.
10. The NCLT allowed both the aforesaid IAs and vide its common order
    dated 13.01.2023 held that all the Conditions Precedent have been
    duly complied with and therefore, 20.05.2022 would be the Effective
    Date. Further, it excluded the period from 20.05.2022 to 16.11.2022
    (180 days) from the period of 180 days within which the first tranche
    payment had to be made, in the interests of justice and to achieve
    the primary objective of maximization of assets and resolution of
    the Corporate Debtor. As a consequence, the deadline to meet with
    the first tranche payment obligation of Rs. 350 Crore was extended
    till 15.05.2023 (hereinafter, “1st implementation extension”). The
    appellants challenged this common order dated 13.01.2023 passed
    by the NCLT before the NCLAT by way of Company Appeal (AT)
    (INS) Nos. 129-130 of 2023 (hereinafter, “Company Appeal”) and
    also sought a stay on the same.
11. On 30.01.2023, this Court dismissed Civil Appeal Nos. 465-469 of
    2023 filed by Respondent No.1 and upheld the order dated 21.10.2022
    passed by the NCLAT. In such circumstances, Respondent No.1 was
    obliged to pay the full provident fund and gratuity that the workmen
    and employees were entitled to within 180 days from the Effective
    Date.
[2024] 11 S.C.R.                                                     2079

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

12. The NCLAT vide its order dated 03.03.2023, declined to stay the
    order dated 13.01.2023 passed by the NCLT while observing that the
    steps regarding the implementation of the Resolution Plan have to
    be taken by the SRA which needs to be overseen by the Monitoring
    Committee. On 17.04.2023, the Appellants filed Civil Appeal Nos.
    3736-3737 of 2023 before this Court against the order of the NCLAT
    declining the grant of stay.
13. Since 15.05.2023 was fixed as the deadline to make the first tranche
    payment of Rs. 350 crore, Respondent No.1, on 11.05.2023, filed
    IA Nos. 2028-2029 of 2023 respectively before the NCLAT in the
    Company Appeal for the purpose of seeking exclusion of the period
    from 16.11.2022 till the time the Company Appeal is decided from
    the calculation of 180 days stipulated for the infusion of first tranche
    of funds under the Resolution Plan. Immediately thereafter, on
    17.05.2023, IA Nos. 2059-2060 of 2023 in the Company Appeal were
    also filed by Respondent No.1 seeking to restrain the Appellants
    from encashing or appropriating the Performance Bank Guarantee
    and Earnest Money deposited by Respondent No.1 in favor of the
    Appellants under the Resolution Plan.
14. The NCLAT vide its common order dated 26.05.2023, stated that the
    period between 16.11.2022 and 03.03.2023 (107 days) be excluded
    from the calculation of 180 days for the infusion of first tranche of
    funds under the Resolution Plan and also held that the Appellants
    could invoke the PBG only with the leave of the NCLT. This, effectively,
    extended the period to infuse Rs. 350 Crore under the first tranche
    till 31.08.2023 (2nd implementation extension). Soon thereafter, on
    13.06.2023, the Appellants filed Civil Appeal Nos. 4131-4134 of 2023
    against the common order dated 26.05.2023 passed by the NCLAT.
15. On 16.06.2023, Respondent No. 1 filed two other IA Nos. 3789-3790
    of 2023 (hereinafter, “Gratuity Application”) in the Company Appeal
    requesting that they be allowed to discharge the gratuity claims of the
    employees and workmen of the Corporate Debtor in three tranches and
    also allow them to approach the EPFO authorities in order to reduce
    or waive off the claim towards damages amounting to Rs. 24.4 Cr
    imposed on the Corporate Debtor or grant permission to challenge the
    imposition of damages in an appeal before the appropriate authority.
16. In the meantime, vide letter dated 27.07.2023, the Office of the
    Director General of Civil Aviation, Government of India (hereinafter,
2080                                                          [2024] 11 S.C.R.

                           Supreme Court Reports


     “DGCA”) extended the validity of the AOC issued to the Corporate
     Debtor until 03.09.2023 subject to certain conditions. The relevant
     extracts from the letter are reproduced hereinbelow:
          “Sir,
          Reference is invited to Jet Airways Letter dated 16.05.2023
          followed by email dated 12.06.2023 and discussions with
          Sh Ankit Jalan, representative of Jalan-Kalrock Consortium
          (SRA) on 14.07.2023 and 27.07.2023 regarding extension
          of validity of AOC.
          2. In view of the fact that Jet Airways is still undergoing CIRP
          under IBC, 2016, NCLT and NCLAT having the jurisdiction
          in respect of the insolvency of the Company have granted
          extension(s)/exclusion(s) of time for implementation of the
          approved Resolution Plan upto 03.09.2023, the AOC No. 6A
          in respect of Jet Airways (India) Ltd. shall be considered as
          valid until 03.09.2023, subject to the following conditions:-
          i.      This extension shall be applicable only for the limited
                  purpose of completing the ongoing CIRP.
          ii.     Jet Airways shall be required to undergo re-certification
                  in accordance with the procedure contained in
                  CAP 3100, as applicable for issuance of AOC
                  and demonstrate compliance of all the applicable
                  regulatory requirements afresh before commencement
                  of flight operations.
          iii.    Fee as applicable for issuance of AOC, shall be
                  payable for such re-certification.
          iv.     Jet Airways shall submit a firm action plan for revival
                  of operations after the company is taken over by
                  the SRA in accordance with the NCLT approved
                  resolution plan.
          This issues with the approval of the Director General.”.
17. While the Company Appeal was pending before the NCLAT, the
    Appellants filed an Affidavit dated 16.08.2023 (hereinafter, “Lender’s
    Affidavit”) before the NCLAT. The Lender’s Affidavit provided that,
    if Respondent No.1, firstly, infuses Rs. 350 Crore by 31.08.2023;
    secondly, complies with the payment obligations to the workmen and
[2024] 11 S.C.R.                                                          2081

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     employees, and; thirdly, scrupulously follows the other terms and
     conditions of the Resolution Plan - the Appellants would not contest
     the issues relating to the grant of exclusion/extension of time as well
     as the issue relating to the compliance of all Conditions Precedent by
     the Respondent and would withdraw the Company Appeal pending
     before the NCLAT along with the Civil Appeals filed before this Court.
     The Lender’s Affidavit also provided that, upon failure to comply with
     the aforesaid conditions, the Corporate Debtor should be directed to
     go into liquidation. This opportunity was given to Respondent No.1/
     SRA as a one-time measure. Para 8 of the Lender’s Affidavit which
     stipulates these conditions is reproduced hereinbelow:
          “8. In the present appeal, the lenders are agreeable that
          in case;
          a)    SRA infuses Rs. 350 Crores by 31.08.2023, the date
                by which said payment is to be made as per the
                Resolution Plan, read with Order dated 26.05.2023
                passed by this Hon’ble Tribunal; and
          b)    SRA Undertakes to scrupulously follow the other terms
                and conditions of the resolution plan and
          c)    SRA complies with the liabilities relating to payment
                to the employees as per order of NCLAT dated
                21.10.2022 which has been upheld by the Hon’ble
                Supreme Court in its order dated 30.01.2023,
                the Lenders would not contest the issues relating to
                granting of exclusion/extension of time (in terms of the
                orders dt. 13.01.2023 passed by NCLT and order dt.
                26.05.2023 passed by this Hon’ble Tribunal) as well
                as on the issue relating to compliance of condition
                precedent by the SRA and accordingly undertakes
                to withdraw the present Company Appeal (AT) Ins
                129-130 of 2023 which is pending adjudication before
                this Hon’ble Tribunal along with Civil Appeal Nos.
                4131-34 of 2023 & 3736-37 of 2023 filed before the
                Hon’ble Supreme Court, on the said two issues. In
                other words, lenders would not contest the granting
                of exclusions as well as on the issue regarding the
                compliance of Conditions Precedent, in case the
                aforesaid steps are taken by SRA without any further
2082                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


                delay. Failing to comply with the conditions mentioned
                in Para 8(a) to (c) above, the Corporate Debtor should
                be directed to go into liquidation.”
18. In response to the aforesaid Lender’s Affidavit, Respondent No.1
    on 18.08.2023 filed IA Nos. 3801 and 3802 of 2023 (hereinafter,
    “Adjustment application”) in the Company Appeal seeking inter
    alia – First, a direction to the Appellants to adjust the PBG of Rs. 150
    Crore towards part payment of the first tranche under the Resolution
    Plan; second, to allow Respondent No.1 to infuse Rs. 100 Crore as
    share application money on or by 31.08.2023 and; thirdly, to allow
    Respondent No.1 to infuse the remaining Rs. 100 Crore as share
    application money on or before 30.09.2023. Through these applications,
    Respondent No.1 further urged that, in the event the Gratuity Application
    was not allowed, the Resolution Plan would not be implemented and
    in such eventuality, the Appellants and the Corporate Debtor may be
    directed to refund all the amounts infused or deposited by Respondent
    No.1. including the share application money and the PBG.
19. The NCLAT, vide its order dated 28.08.2023, partly allowed the
    Adjustment Application so far as the payment of the first tranche
    of Rs. 350 Crore was concerned and stated that as regards the
    prayer with respect to the Gratuity Application, the submissions
    required further consideration. The PBG of Rs. 150 was allowed
    to be adjusted against the first tranche payment and the remaining
    Rs. 200 Crore was allowed to be infused on or by 31.08.2023
    and 30.09.2023 respectively. Therefore, the deadline to infuse the
    aforesaid amount and implement the Resolution Plan was further
    extended to 30.09.2023 (3rd implementation extension). Immediately
    thereafter, the Appellants filed Civil Appeal Nos. 6427-6428 of 2023
    before this Court against the aforesaid order dated 28.08.2023
    passed by the NCLAT.
20. Meanwhile, on 03.09.2023, the conditional AOC issued by the DGCA
    came to an end. Before the expiry of the 3rd implementation extension
    i.e., 30.09.2023, Respondent No. 1 had deposited an amount of Rs.
    200 Crore. However, it is the case of the Appellants that the manner
    of infusion of the same was in contravention of the Resolution Plan,
    specifically Clause 2.1.5, since Respondent No.1 infused a portion
    of the funds through a third party, thereby inducting them into the
    Resolution Plan as a shareholder.
[2024] 11 S.C.R.                                                         2083

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

21. Before this Court, the following three Interim Orders passed by the
    NCLAT came to be challenged by the Appellants over a period of time:
     i)     Civil Appeal Nos. 3736-3737 of 2023 challenging the Interim
            Order dated 03.03.2023 passed by the NCLAT by which it
            declined to stay the NCLT Order dated 13.01.2023 which held
            that all the Conditions Precedent had been fulfilled;
     ii)    Civil Appeal Nos. 4131-4134 of 2023 challenging the Interim
            Order dated 26.05.2023 passed by the NCLAT through which
            the NCLAT restrained the Appellants from invoking the PBG
            and extended the time for infusion of first tranche payment of
            Rs. 350 Crore up to 31.08.2023; and
     iii)   Civil Appeal Nos. 6427-6428 of 2023 challenging the Interim
            Order dated 28.08.2023 passed by the NCLAT allowing the
            PBG of Rs. 150 Crore to be adjusted against the first tranche
            payment and allowing the remaining amount of Rs. 200 Crore
            to be infused by 30.09.2023.
22. All the aforementioned appeals were heard together and vide common
    judgment and order dated 18.01.2024, this Court held that the PBG
    cannot be permitted to be adjusted against the first tranche payment
    and therefore, directed that the amount of Rs. 150 Crore be infused
    in cash on or before 31.01.2024 (4th implementation extension).
    In the event of failure by Respondent No.1 to infuse the said amount
    within the said date, this Court held that the consequences under
    the Resolution Plan would follow. It disposed of the appeals as thus:
            “25. The lenders have argued in the appeals that there
            has been a failure on the part of the successful resolution
            applicant to comply with the conditions precedent. If the
            successful resolution applicant were to comply with the
            terms as envisaged in SBI's affidavit dated August 16,
            2023, evidently issues pertaining to compliance with the
            conditions precedent were not to be pressed thereafter.
            In order to furnish this successful resolution applicant a
            final opportunity to comply and consistent with the above
            position, we issue the following directions:
            (i) The successful resolution applicant shall peremptorily
            on or before January 31, 2024, deposit an amount of Rs.
            150 crores into the designated account of SBI, failing
2084                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


          which the consequences under the resolution plan
          shall follow;
          (ii) The performance bank guarantee of Rs. 150 crores shall
          continue to remain in operation and effect, pending the final
          disposal of the appeal before the National Company Law
          Appellate Tribunal, and shall abide by the final outcome of
          the appeal and the directions that may be issued by the
          National Company Law Appellate Tribunal; and
          (iii) Whether or not the successful resolution applicant has
          been compliant with all the conditions of the resolution
          plan as well as of the conditions set out in paragraph 8
          of the affidavit dated August 16, 2023 shall be decided
          by the National Company Law Appellate Tribunal in the
          pending appeal.”
                                                 (emphasis supplied)

23. Respondent No.1 failed to deposit Rs. 150 Crore in cash by
    31.01.2024 as directed by this Court. Therefore, on 27.01.2024,
    Respondent No.1 filed Misc. Application Nos. 216-217 of 2024 in the
    Civil Appeal Nos. 6427-6428 of 2023 seeking an extension of time
    for making the deposit of Rs. 150 Crore. The same was dismissed
    by us vide order dated 02.02.2024 as being misconceived in view
    of our previous order dated 18.01.2024. This order is reproduced
    hereunder:
                                      “ORDER
          1. The Miscellaneous Application is misconceived in view
          of the final order passed by this Court on 18 January 2024.
          2. The Miscellaneous Application is accordingly dismissed.
          3 Pending applications, if any, stand disposed of.”
24. Later, the NCLAT, vide its impugned order dated 12.03.2024,
    dismissed the Company Appeal filed by the Appellants against
    the order of the NCLT dated 13.01.2023 while holding that
    Respondent No.1 had fulfilled all the Conditions Precedent and
    had also complied with all the other terms of the Resolution Plan.
    The following were the concluding observations in the impugned
    order of the NCLAT:
[2024] 11 S.C.R.                                                        2085

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          “129. In view of our foregoing discussions and conclusions,
          we dispose of these Appeals in the following manner:
                1.   The impugned order passed by the Adjudicating
                     Authority dated 13.01.2023 is upheld.
                2.   The Monitoring Committee and MC Lenders
                     as well as SRA are directed to take steps for
                     creation of charge over the Dubai Property No. 1,
                     Dubai Property No. 2, and Dubai Property No.3
                     within a period of 30 days from today. The SRA
                     to bear all necessary expenses for creation of
                     necessary charge.
                3.   The Performance Bank Guarantee of INR
                     150 Crores, which is lying with the Monitoring
                     Committee/MC Lenders, shall be adjusted
                     towards the first tranche payment of INR 350
                     crores as INR 200 crores have already been
                     paid by the SRA. By adjustment of PBG as per
                     the Resolution Plan, the first tranche of payment
                     of INR 350 crores shall be completed.
                4.   Steps shall be taken for re-constitution of the
                     shares as per the Resolution Plan forthwith.
                5.   Out of the first tranche payment of INR 350
                     crores, payments shall be made to the workmen
                     and employees and the creditors as per the
                     Resolution Plan, including the payment of CIRP
                     cost as per the Resolution Plan, which payment
                     shall be completed within 60 days from the date
                     of this judgment.
                6.   The SRA shall submit an Application for
                     re-issue of Air Operation Certificate which may
                     be obtained within 90 days from the date of
                     this judgment.
                7.   The closing date shall be 90th day from the
                     date of this judgment, on which date, handing
                     over of the Corporate Debtor to the SRA by
                     the Monitoring Committee shall be completed.
2086                                                     [2024] 11 S.C.R.

                         Supreme Court Reports


                8.   Towards the payment of provident fund dues, as
                     per the order dated 21.10.2022 passed by this
                     Tribunal in Company Appeal (AT) (Insolvency)
                     Nos. 643 of 2021, SRA has undertaken to make
                     payment of provident fund upfront along with
                     payment of dues of workmen and employees
                     as per the Resolution Plan, which payment of
                     INR 12 Crores as undertaken, shall be made
                     in addition to the payments as directed above.”
                                                (emphasis supplied)

25. The aforesaid judgment and order of the NCLAT once again
    extended the time limit for implementation of the Resolution Plan
    and satisfaction of the first tranche payment obligation of Rs. 350
    Crore to 11.04.2024 i.e., the date within which the creation of
    charge over the various Dubai properties was to be completed (5th
    implementation extension). The same charge has, admittedly, not
    been created as on date.
26. In light of the above, the Appellants have challenged the aforesaid
    impugned order of the NCLAT dated 12.03.2024 by way of the present
    Civil Appeals filed under Section 62 of the IBC, 2016.

     B.    SUBMISSIONS ON BEHALF OF THE APPELLANTS
27. Mr. N. Venkataraman, learned ASG appearing for the Appellants
    broadly classified his submissions into the following issues:
     i.    That the direction of the NCLAT in the impugned order dated
           12.03.2024 allowing Respondent No.1 to adjust the PBG of
           Rs. 150 Crore towards the first tranche payment of Rs. 350
           Crore, runs counter to the judgement of this Court dated
           18.01.2024. The Resolution plan mandates a cash infusion
           and the question of PBG adjustment would arise only when the
           three Dubai properties valued at Rs.250 crores are mortgaged
           by Respondent No.1.
     ii.   That the NCLAT, through its impugned order dated 12.03.2024
           erroneously limited the Airport Dues to Rs. 25 Crore and further
           categorising it as a part of the CIRP costs especially when
           the Resolution Plan obligates an upfront payment of Rs. 475
           Crore towards Airport Dues. Such an error is glaring since the
[2024] 11 S.C.R.                                                        2087

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

            Resolution Plan clearly excludes the Airport Dues from the
            ambit of CIRP costs.
     iii.   That the NCLAT while approving the Resolution Plan vide its
            Order dated 21.10.2022 increased the workmen’s dues from Rs.
            52 Crore to Rs. 289.2 Crore (which according to the appeals
            filed by the workmen would be reduced to Rs. 226 Crore post
            the demerger of the ground handling business). An appeal
            against the order stood dismissed by this Court on 30.01.2023.
            Therefore, it is a matter of concern that the impugned order of
            the NCLAT limited the workmen’s compensation to a mere Rs.
            12 Crore which is contrary to its earlier order dated 21.10.2022
            as upheld by this Court on 30.01.2023.
     iv.    Clause 7.6.1 of the Resolution Plan deals with the five Conditions
            Precedent and imposes an obligation on the SRA to fulfil the
            same in order to recommence the operations of the Corporate
            Debtor as an aviation company. The SRA could be said to
            have breached three of these conditions i.e. Condition (a) on
            obtaining the AOC; Condition (c) on obtaining the Slots Allotment
            Approval, and; Condition (d) on obtaining the International Traffic
            Rights Clearance. The NCLT, vide its order dated 13.01.2023
            had held that the Conditions (a) and (c) stood fulfilled and
            amended Condition (d) which effectively transformed it from a
            condition precedent to a condition subsequent. Such erroneous
            findings came to be wrongly affirmed by the NCLAT through its
            impugned order dated 12.03.2024.

     i.     Issue No.1: Adjustment of PBG of Rs. 150 Crore towards
            the first tranche payment
28. As far as the first tranche payment of Rs. 350 Crore is concerned,
    it was submitted that a payment of only Rs. 200 Crore in cash has
    been made and the SRA has failed to infuse the remaining Rs. 150
    Crore in cash.
29. The learned ASG submitted that Clause 6.3.1(g) relating to the
    “Infusion of Funds and Timelines” provides that the timeline for the
    infusion of the upfront first tranche payment of Rs. 350 Crore was
    within 180 days from the Effective Date. The clause also indicates the
    manner in which the first tranche would be utilized and obligates a
    distribution pattern towards the CIRP costs, contingent fund, payments
2088                                                     [2024] 11 S.C.R.

                        Supreme Court Reports


     to FCs, OCs, other creditors and other stakeholders, working capital
     for business and miscellaneous administrative expenses.
30. The learned ASG then elaborated on the scope of Clause 7.7 of
    the Resolution Plan which provides the “Implementation Schedule”
    and requires that the Resolution Plan be completed within 5 years
    from the Effective Date. According to this clause, the performance of
    different obligations was to be completed within the said corresponding
    timelines. S.No. 11 under this table specifically requires the infusion
    of Rs.350 Crore in the Corporate Debtor by the SRA within “Z+150
    days” where “Z” represents the Effective Date. The expression
    “infusion” has been interpreted by this Court vide its judgement dated
    18.01.2024 to mean “payment in cash”.
31. Reference was made by the learned ASG to the RFRP, more
    particularly to Clauses 3.13.1, 3.13.2, 3.13.7(iii) and 3.13.9 which
    mandate the execution of a PBG for an amount of Rs. 150 Crore
    and also provide that the PBG cannot be set-off against or used
    as a part of the consideration which the SRA proposes to offer in
    relation to the company even if expressly indicated as such in the
    successful Resolution Plan. It also provides for an automatic right to
    invoke the PBG without any reference to the SRA, should the SRA
    fail to implement the approved Resolution Plan in accordance with
    the terms of the Resolution Plan and to the satisfaction of the CoC.
    It was also submitted that vide Clauses 7.3 and 9.4 of the Resolution
    Plan respectively the spirit and intention of the RFRP stood translated
    into the Resolution Plan. Under Clause 7.3 of the Resolution Plan,
    the SRA undertook to provide the PBG as per the RFRP and in
    compliance with Regulation 36B(4A) of the 2016 Regulations. Clause
    9.4 of the Resolution Plan authorizes the invocation of the PBG in
    terms of the RFRP.
32. The learned ASG submitted that Clause 6.4.4 of the Resolution Plan
    on “Treatment of Financial Creditors - Summary of payments and
    Security package” under its tabular column evidently conveys the
    mandate that the SRA is under an obligation to execute a mortgage
    over the three Dubai properties i.e., Property No. 1 valued at Rs.
    100 Crore, Property No.2 valued at Rs. 100 Crore and Property No.3
    valued at Rs. 50 Crore. The table provides that the date of creation
    of such security would be the Effective Date. This security had to be
    created at the cost of the SRA. Therefore, the SRA was obliged to
[2024] 11 S.C.R.                                                     2089

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     not only infuse an amount of Rs. 350 Crore within 180 days of the
     Effective Date, but also execute the mortgage of the three Dubai
     properties on the Effective Date. In other words, the Resolution
     Plan obligated the SRA to satisfy the following twin conditions for
     the PBG to be discharged – (a) infusing Rs. 350 Crore as the first
     tranche payment and (b) executing a mortgage on the three Dubai
     properties worth Rs. 250 Crore on the Effective Date. The learned
     ASG submitted that, it is not in dispute that the NCLT vide its order
     dated 11.04.2022 extended the time for achieving the Effective Date
     to 25.05.2022 and Respondent No.1 claimed to have achieved the
     same on 20.05.2022. Consequently, all the three Dubai properties
     ought to have been mortgaged on or before 20.05.2022.
33. It was submitted that the Respondent SRA failed to make the first
    tranche payment of Rs. 350 Crore despite the fact that it ought to
    have been infused within 6 months from 20.05.2022. Instead, the
    Respondent SRA continuously contended that the order of the NCLT
    dated 13.01.2023 (holding that the Conditions Precedent have been
    fulfilled) was challenged by the Appellants before the NCLAT and that
    they could not therefore bring in Rs. 350 Crore since the Effective
    Date had not yet materialized.
34. It was submitted that the Appellants filed the Lender’s Affidavit dated
    16.08.2023 before the NCLAT and vide Para 8 of the Lender’s
    Affidavit, the Appellants agreed not to contest the issues relating
    to the grant of exclusion of time (granted by the Order of the NCLT
    dated 13.01.2023 and the NCLAT dated 26.05.2023) and the issue
    relating to the compliance with the Conditions Precedent. In the
    said affidavit, the Appellants also agreed to withdraw the Company
    Appeal pending before the NCLAT along with the Civil Appeal Nos.
    4131-4134 of 2023 and Civil Appeal Nos. 3736-3737/2023 filed before
    this Court. However, this would be subject to the fulfilment of the
    three conditions imposed vide Para 8 by the SRA. The conditions
    were that – firstly, the SRA infuses an amount of Rs. 350 Crore by
    31.08.2023 i.e., the date by which the said payment is to be made
    as per the Resolution Plan read with order dated 26.05.2023 passed
    by the NCLAT; secondly, the SRA undertakes to scrupulously follow
    the other terms and conditions of the Resolution Plan and; thirdly,
    the SRA complies with the liabilities in relation to the payment to be
    made to the employees as per the order of NCLAT dated 21.10.2022,
    which has been upheld by this Court vide order dated 30.01.2023
2090                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


35. It was submitted that in terms of Serial No. 11 under Clause 7.7.1
    read with Clause 6.1.3(g), the SRA had to infuse cash amounting to
    Rs 350 Crore and it was for this reason alone that Para 8(a) of the
    Lender’s Affidavit refers specifically to the infusion of Rs. 350 crore in
    cash by 31.08.2023. It was reiterated that the first tranche payment
    had to necessarily be made in cash since such a requirement flows
    from the Resolution Plan. It was not open to the SRA to contend
    that the Resolution Plan had a different mode of payment namely,
    the payment of Rs. 200 Crore in cash and Rs. 150 Crore by way
    of adjusting the PBG. The learned ASG contended that none of
    the clauses in the Resolution Plan stipulates such condition. To the
    contrary, under Clause 6.4.4, the PBG could be released or adjusted
    only upon the satisfaction of the twin requirements abovementioned.
    Therefore, the assumption by the Respondent that the infusion of
    Rs. 350 Crore emanates only out of the Lender’s Affidavit dated
    16.08.2023, is totally incorrect. The Lender’s Affidavit has not and
    cannot impose any condition over and above those which are
    provided under the Resolution Plan. The Lender’s Affidavit was filed
    to only set out a deadline for infusing Rs. 350 Crore by 31.08.2023,
    which was subsequently extended by the order dated 28.08.2023
    of the NCLAT to 30.09.2023. The Lender’s Affidavit only insisted on
    compliance with payment obligations within specified timelines and
    neither did it alter the Resolution Plan nor lay out new conditions.
36. The NCLAT in its order dated 28.08.2023 fell in error in allowing the
    adjustment of PBG of Rs. 150 Crore as a part of the first tranche
    payment. This is evident from the order of this Court dated 18.01.2024,
    specifically under Para 21, wherein it was held that an infusion of Rs.
    350 Crore would only mean an infusion by cash and the same could
    not be substituted for the adjustment of PBG. This Court, further,
    under Para 25 directed that a failure to make this payment on or
    before 31.01.2024 would necessitate the consequences under the
    Resolution Plan to follow. This Court further issued a direction that the
    NCLAT shall decide whether the SRA had been compliant with all the
    conditions contained in the Resolution Plan as well as the conditions
    in Clause 8 of the Affidavit dated 16.08.2023. This Court made it
    clear that the non-infusion of Rs. 150 Crore in cash would lead to
    consequences both in terms of the Affidavit and also the Resolution
    Plan since the condition insofar as infusion was concerned, remained
    the same both in the Affidavit and in the Resolution Plan. Therefore,
[2024] 11 S.C.R.                                                    2091

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     the observation of the NCLAT in the impugned order holding that
     the consequences of non-deposit of Rs. 350 Crore was that “the
     SRA was not entitled to take any benefit of the offer” is contrary to
     the Resolution Plan and the order of this Court dated 18.01.2024.
37. This Court had directed a cash payment of Rs. 150 Crore on or before
    31.01.2024 and the SRA had admittedly failed to remit the same.
    Realizing that this would lead to the initiation of the consequences
    under the Resolution Plan, Respondent No.1 had applied for an
    extension before this Court which was declined outright as being
    misconceived vide order dated 02.02.2024. Therefore, the SRA
    having failed to make the payment and having breached this Court’s
    order dated 18.01.2024, the NCLAT ought to have concluded that
    the Resolution Plan had failed.
38. In the alternative, the ASG argued that, assuming without admitting
    that the non-compliance of this Court’s Judgement dated 18.01.2024
    would only have the consequence of bringing a closure to the offer
    made in the Lender’s Affidavit dated 16.08.2023 and not have any
    effect on the Appeal that was pending before the NCLAT, the NCLAT
    while passing it’s final order dated 12.03.2024 ought to have insisted
    on the payment of Rs. 150 Crore in cash. That would have been in
    tune with the specific direction that was issued by this Court & the
    intent with which the direction was issued, and the SRA having not
    paid the same, had committed a breach of the Resolution Plan. The
    NCLAT went to the extent of swapping the conditions laid out in the
    Resolution Plan by directing the adjustment of the PBG first and the
    execution of the mortgage on the three Dubai properties later i.e.,
    within 30 days from its order dated 12.03.2024. It was submitted that
    even the extension that was allowed for the execution of mortgage
    expired on 11.04.2024 and the SRA continues to be a defaulter in
    this regard as well.
39. The ASG vehemently contended that, there has been a triple breach
    on the part of SRA – Firstly, breach of the Resolution Plan; secondly,
    violation of the directions issued by this Court dated 18.01.2024
    and; thirdly, the failure to execute the mortgage of the three Dubai
    properties before 11.04.2024.
40. The ASG submitted that the impugned order of the NCLAT dated
    12.03.2024 at Para 129, granted 30 days’ time to the SRA for the
    creation of charge over the Dubai properties and directed the SRA
2092                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


    to bear all the necessary expenses. It was submitted that there was
    complete inaction on the part of the SRA for 29 days from the date
    of the impugned order and on 10.04.2024 at 16:38 hours, the SRA
    sent an email stating that they are willing to proceed with the security
    creation of the Dubai properties and also informed that since its value
    had reduced by Rs. 14 Crore, they would bridge the gap with an
    additional property or a cash security. On the same date, another
    email was sent by the SRA at 17:18 hours stating that an account
    balance of Rs. 76.07 Lakh is available with the Appellants and the
    same may be used to execute the mortgage. The ASG submitted
    that the Appellants replied to the said communication on the same
    day at 19:18 hours stating that:
    (a)   The assenting financial creditors on 13.10.2023 have appointed
          Mashreq Bank to act as the agent for creation of the mortgage in
          terms of the prevailing law in Dubai and the necessary amount
          required to be paid to them had not yet been received.
    (b)   After the impugned order of the NCLAT came to be passed
          on 12.03.2024, the Appellants sent an email on 22.03.2024
          regarding the cost for the creation of a mortgage over the
          properties located in Dubai, which had not been paid till date.
    (c)   That, instead of remitting the amount for creation of security
          as already advised, the SRA was sending an email that it had
          “no objection with the MC lenders immediately proceeding with
          the security creation of the Dubai properties”.
    (d)   It was also brought to the notice of the SRA that 11.04.2024
          would be the last date for complying with the impugned order
          of the NCLAT and that the SRA was well aware of the fact
          that the cost of creation of securities is Rs. 2,36,00,767 and
          not Rs. 76.07 lakh. This shows the SRA’s clear disinclination
          to execute the mortgage. It was further brought to the SRA’s
          notice that they had failed to comply with the Resolution Plan
          and the impugned order of the NCLAT dated 12.03.2024.
    Further, on the same day, at 21:05 hours, the SRA sent an email
    referring to 12 acres of contiguous land situated in Aligarh, Uttar
    Pradesh which had been valued in excess of Rs. 250 Crore, owned
    by a reputed individual entrepreneur resident in India and that the
    SRA was ready to offer this property as an alternative security in
[2024] 11 S.C.R.                                                    2093

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     India. The Appellants replied to the said email on 16.04.2024 and
     stated that the period of 30 days had already expired on 11.04.2024,
     the expenses for creation of charge had not been paid and that
     accepting the property in India which belongs to a third party would
     tantamount to modification of the Resolution Plan.
41. The ASG therefore submitted that the above exchanges patently
    bring out the SRA’s non-cooperation, defiance to judicial orders and
    desperate attempts to suggest the creation of security of unknown
    third-party properties, all of which were done after the expiry of the
    time period of 30 days provided by the NCLAT for compliance with
    their order dated 12.03.2024. Consequently, even in terms of the
    impugned Order of the NCLAT, there has been a total breach on the
    part of the SRA which only indicates that they have no inclination
    worth the name to implement the Resolution Plan. Consequently,
    in terms of Clause 9.4 of the Resolution Plan and Clause 3.13.7(iii)
    of the RFRP respectively, the Appellants are entitled to invoke the
    PBG automatically without any reference to the SRA.

     ii.   Issue No. 2: Non-payment of Airport dues
42. It was submitted that in terms of Clause 6.3.1(d), the airport dues
    and parking charges are to be paid by the SRA upfront in priority
    over any other payment to the creditors of the Corporate Debtor.
    Clause 6.4.1(f) provides that on 31.08.2020, an approximate figure
    of Rs 240 Crore towards parking charges for aircrafts and airport
    space lease charges was arrived at through the estimate given
    by the RP and this was subject to a maximum of Rs. 475 Crore.
    Specific attention was drawn to the expression in Clause 6.3.1(d)
    which states that “such payments will be settled upfront in full in
    first 180 days from the effective date and without any conditions
    (including not being staggered payments spread across a period of
    time) so that flying can start immediately without any future disputes
    and concerns with such claimants for past dues”. The respondents,
    however, have not remitted any amount towards the airport dues
    nor have they allowed the Resolution Plan to be implemented. As a
    result of the several extensions/exclusions given by the NCLT and
    NCLAT to the SRA, the airport dues as on date stand at a staggering
    figure of Rs. 1100 Crore approx., which amount, again, is to be paid
    by the respondents alone.
2094                                                    [2024] 11 S.C.R.

                        Supreme Court Reports


43. The ASG submitted that, when the aforesaid is the position in the
    Resolution Plan, the NCLAT in its impugned order dated 12.03.2024
    vide Paras 53-55 respectively has chosen to restrict the Airport
    dues to a mere Rs. 25 Crore and has erroneously construed it to
    be a part of the CIRP cost. The counsel drew specific attention to
    Para 53 of the impugned order wherein the NCLAT had referred to
    Clause 6.4.1(h) and stated that “…CIRP cost of the Corporate Debtor
    (excluding parking charges, rental charges, employees dues, taxes
    etc.) Accordingly, the Resolution Applicant has set aside a sum of
    Rs 25 crores as CIRP cost towards payment of any such cost until
    the approval date…”. Thus, despite the fact that Clause 6.4.1(h)
    on treatment of Outstanding CIRP Costs excludes the parking
    charges, rental charges, employees’ dues, taxes etc., the NCLAT
    has surprisingly read the same to mean as “inclusive of/included in”
    the CIRP costs while directing the payment of a mere Rs. 25 Crore.
    Therefore, this is an error apparent on the face of it which requires
    interference by this Court.
44. It was submitted that, in case the argument of the SRA that a maximum
    of only Rs. 475 Crore is to be paid by the SRA under the Resolution
    Plan, is accepted, then the entire amount of Rs. 475 Crore shall
    go towards the airport dues and as a consequence, nothing would
    become payable to the financial creditors, operational creditors,
    workmen etc. The amount of Rs. 240 Crore was a mere estimate of
    the dues payable in the year 2020. Due to non-payment and non-
    commencement of flying operations, the same amount in the year
    2024 has increased multi-fold. To contend that such an increased
    amount does not fall under the Resolution Plan and therefore, is
    not payable, will cast a further burden on the CoC of the Corporate
    Debtor. Further, it would be unfair to accept that, for the reason of
    the Respondent’s default in payment, the CoC would have to bear
    the Airport dues of Rs. 1100 Crore and none of the creditors or
    workmen would get anything out of this plan. This misconceived
    contention which intentionally makes the plan unworkable needs to
    be outrightly rejected.

     iii.   Issue No. 3: Non-payment of Workmen and Employees’ dues
45. The ASG submitted that the Resolution Plan originally provides
    for a sum of Rs. 52 Crore towards the payment of workmen’s
    and employees’ dues. However, the NCLAT vide its order dated
[2024] 11 S.C.R.                                                    2095

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     21.10.2022, in Para 78, had increased the same to Rs. 289.2 Crore
     which now stands modified to about Rs. 226 Crore. The NCLAT
     in the order dated 21.10.2022 under Para 80 had observed in
     unambiguous terms that “the workmen are entitled to full payment of
     provident fund and gratuity, hence the balance of above dues ought
     to be paid by the SRA to satisfy statutory obligations. Non-payment
     of full provident fund and gratuity shall lead to violation of Section
     30(2)(e) and hence, to save the Plan the above payments have to
     be made”. This view of the NCLAT had also been upheld by this
     Court vide its order dated 30.01.2023. The Resolution Plan under
     Clause 6.3.1(c) obligates the payment of such dues within 180 days
     from the Effective Date.
46. It was submitted that, the NCLAT, vide Paras 111-114 had erroneously
    directed the payment of an amount of Rs. 12 Crore towards the
    Provident Fund and has completely ignored the payment of dues
    pertaining to gratuity of the workmen and employees. The Appellants
    contend that this finding is not only an error apparent but completely
    inconsistent with the NCLAT’s own earlier order dated 21.10.2022,
    which stood upheld by this Court on 31.01.2023.

     iv.   Issue No. 4: Achievement of Effective Date
47. It was submitted that Clause 7.6.2 of the Resolution Plan provided
    that the date of fulfilment of all the Conditions Precedent as stated
    in Clause 7.6.1, shall be the Effective Date for the purposes of
    the Resolution Plan. A failure to fulfill the Conditions Precedent
    within 270 days of the Approval Date would lead to an automatic
    withdrawal of the Resolution Plan as per Clause 7.6.4. However,
    the NCLT, vide its order dated 22.06.2021, expressed its opinion
    that there was uncertainty with respect to the achievement of the
    Effective Date under the Resolution Plan and therefore, modified
    Clause 7.6.4. As a consequence, it fixed the Effective Date to be
    the 90th day from the Approval Date of 22.06.2021 and stated that
    this could be extended for a maximum period of another 180 days.
    The Effective Date, therefore, became 22.09.2021 i.e., 90 days
    from 22.06.2021. Subsequently, three extensions were given to the
    SRA with respect to the achievement of the Effective Date – First,
    vide order dated 29.09.2021, the NCLT extended it to 22.12.2021;
    Secondly, vide order dated 20.01.2022, the NCLT extended to
    22.03.2022 through which the maximum extension of 270 days that
2096                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


     could be provided under the Resolution Plan had been reached and;
     Thirdly, vide order dated 11.04.2022, the NCLT further extended it
     to 25.05.2022 by excluding a period of 65 days spent in moving
     the application for grant of time. Therefore, the Effective Date was
     finally frozen on 25.05.2022.
48. The learned ASG submitted that the SRA, however, contended
    that the Effective Date had been achieved on 20.05.2022 and the
    same was accepted by the NCLT in its order dated 13.01.2023.
    Therefore, the calculation of 180 days for the infusion of the First
    Tranche Payment begins from 20.05.2022. The initial 180 days had
    expired on 16.11.2022. However, several extensions were given to
    the SRA for infusion of the first tranche payment – Firstly, vide order
    dated 13.01.2023, the NCLT extended the timeline for infusion of
    First Tranche Payment till 15.05.2023; Secondly, vide order dated
    26.05.2023, the NCLAT further extended the timeline of 180 days
    till 31.08.2023; Thirdly, vide order dated 28.08.2023, the NCLAT
    extended the timeline of 180 days till 30.09.2023 and; Fourthly, vide
    Order dated 18.01.2024, this Court extended the time of 180 days
    for infusion till 31.01.2024.
49. The learned ASG highlighted that Respondent No.1 had failed to
    make the first tranche payment of Rs. 350 Crore, airport dues of Rs.
    475 Crore and the workmen’s and employees’ dues of Rs. 226 Crore
    within the initial 180 days from the Effective Date as well as within the
    multiple extensions granted by the NCLT, NCLAT and this Court. The
    ASG submitted that multiple extensions and accommodations have
    already been granted to the SRA for implementation of the Resolution
    Plan. Therefore, it is too late in the day to claim that the non-infusion
    of Rs. 150 Crore to complete the first tranche payment of Rs. 350
    Crore is only a breach of the Lender’s Affidavit dated 16.08.2023 and
    not the Resolution Plan. The same needs to be rejected outrightly.

     v.   Issue No. 5: Non-fulfilment of Conditions Precedent
50. The ASG submitted that the respondents have failed to comply with
    3 Conditions Precedent, specifically under Clauses 7.6.1(a), (c)
    and (d) of the Resolution Plan respectively.
51. It was submitted that Clause 7.6.1 (a) requires the SRA to obtain
    an AOC which has to be validated by the DGCA and the Ministry
[2024] 11 S.C.R.                                                     2097

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     of Civil Aviation (hereinafter, “MoCA”). The Respondent possessed
     an AOC on 20.05.2022 i.e., the Effective Date as contended by the
     SRA. The validity of the AOC was further extended by the DGCA
     on 27.07.2023 up to 03.09.2023 subject to certain conditions. It
     was clearly stated that the extension is only for the limited purpose
     of completing the ongoing CIRP process and the Corporate Debtor
     would be required to undergo fresh re-certification in accordance
     with the prescribed procedure for issuance of an AOC and also
     submit a firm action plan for the revival of its operations. The AOC
     expired on 03.09.2023 and the same was never extended by the
     SRA.
52. It was submitted that the NCLT in its order dated 13.01.2023 had
    recorded a finding that the Condition Precedent with respect to the
    AOC was fulfilled but it must be noted that this was an observation
    made during a time when the SRA had a valid subsisting AOC, which
    subsequently expired.
53. It was further submitted that vide letter dated 26.12.2023, the Director
    General of Civil Aviation confirmed that no further extension of the
    AOC was granted to the Corporate Debtor beyond 03.09.2023. The
    NCLAT in its impugned order dated 12.03.2024 required the SRA
    to submit an application for re-issuance of the AOC within 90 days
    from the date of its order and the deadline for the same had expired
    on 12.06.2024. It was submitted that, even today, the Respondents
    do not have a valid AOC and the fact that the Respondents are
    contending that they had not renewed the AOC solely because of
    the matter being under litigation, only exposes their disinterest and
    disinclination in taking their obligations forward.
54. It was then submitted that Clause 7.6.1(c) requires the SRA to obtain
    Slot Allotment Approval. The NCLT in its order dated 13.01.2023 vide
    para 124 had clearly rendered a finding that “there is no dispute that
    slots for which SRA applied were granted to them by the concerned
    competent authority including the slots in Delhi and Mumbai on settling
    the old dues and as such, it cannot be considered as non-allotment
    of slots, as SRA has received the slots it requested for in compliance
    with the plan approval order.” The ASG also referred to the email
    dated 27.06.2022 issued by MAIL and the same reads as under: “We
    are happy to consider your request for slots on parking bay during
    the ongoing summer schedule. The same is subject to the closure
2098                                                      [2024] 11 S.C.R.

                         Supreme Court Reports


     of ongoing discussions pertaining to settlement of outstanding dues
     of jet airways towards MAIL.”
55. While the NCLT had correctly recorded a finding that the slot allotment
    is subject to the payment of airport dues (which the Respondents
    had not paid even today), the NCLAT vide para 50 and Para 55
    erroneously concluded that “the adjudicating authority has rightly
    observed that settling of old dues cannot be considered as non-
    allotment of slots” and therefore condition 7.6.1(c) stands fulfilled.
    This finding is contrary to the finding recorded by NCLT and the
    Resolution Plan and as a consequence, the Respondents could be
    said to have breached this condition precedent as well.
56. The ASG submitted that Clause 7.6.1(d) requires the SRA to obtain
    the International Traffic Rights Clearance. The NCLT, vide Para
    125, had righty held that “the international traffic rights clearance is
    required to be obtained in compliance with the applicable laws which
    stipulates that minimum 20 aircrafts are required to be deployed before
    applying for such clearance”. However, after holding so, the NCLT
    proceeded to conclude that this condition cannot be satisfied upfront
    and can be fulfilled only when the operations have recommenced
    successfully and that, therefore, this condition precedent stood
    fulfilled. In simple terms, the NCLT could be said to have modified
    a condition precedent to a condition subsequent and this view of
    the NCLT has been upheld by the NCLAT in Paras 56 to 58. These
    findings are in clear contradiction to the express stipulation in the
    Resolution Plan and therefore, this condition too stands breached
    by the respondents.
57. One more aspect that the learned ASG highlighted through his
    submissions was that, the Circular F.No.AV.14027/17/2018-AT-1
    issued by the Office of Director General of Civil Aviation provides
    certain requirements for undertaking aerial work. Para 6 of the said
    Circular deals with Security Clearance and the same requires the
    Applicant or Company and its Board of Directors to obtain Security
    Clearance from the Ministry of Home Affairs (MHA) if they are foreign
    nationals. It was submitted that according to the communications
    dated 09.07.2024 issued by the Ministry of Civil Aviation, it had
    been confirmed that Security Clearance had not been conveyed in
    respect of Mr. Florian Fritsch. Hence, the threshold requirement of
    security clearance has not yet been obtained by one of the Resolution
[2024] 11 S.C.R.                                                   2099

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     Applicants, who according to Clause 2.1.4 of the Resolution Plan, is
     the other partner to the Consortium along with Mr. Murari Lal Jalan.
     The ASG also placed reliance on news items which suggested
     that Mr. Florian Fritsch is facing money laundering proceedings in
     three different jurisdictions. The same had been dealt with by the
     NCLAT summarily in its impugned order in Para 125. However, it
     was wrongly concluded that this was yet another attempt by the
     Appellants to create roadblocks in the process of implementation
     of the Resolution Plan.
58. The counsel finally submitted that, since the Airport Dues and the
    CIRP costs have substantially increased solely on account of the
    delay, the Court should invoke its powers under Article 142 of the
    Constitution of India and direct that the Corporate Debtor be sent
    to liquidation.

     C.   SUBMISSIONS ON BEHALF OF THE RESPONDENTS
59. On the other hand, Mr. Mukul Rohatgi, learned senior counsel
    appearing on behalf of Respondent No.1 submitted that Section 62
    of the IBC, 2016 requires an appeal to the Supreme Court from an
    order of the NCLAT to be on a “question of law”. He submitted that
    the present appeal only seeks to challenge the concurrent findings of
    fact recorded by the NCLT and the NCLAT, with regard to compliance
    of the Conditions Precedent by the SRA and does not bring out
    any question of law. To fortify this submission, the counsel placed
    reliance on the decision of this Court in IFCI Ltd. v. Sutanu Sinha
    and Others reported in 2023 SCC OnLine SC 1529.
60. The counsel submitted that the directions issued by this Court vide
    order dated 18.01.2024 were interim and not final. The appeals which
    were decided by this Court arose out of an interlocutory application
    which was filed by the SRA seeking directions from the NCLAT on
    the mode of satisfying the conditions in the Lender’s Affidavit dated
    16.08.2023. It was submitted that the same is evident from a reading
    of Para 19 which reads that “.. Observations in the present judgment
    are confined to the arrangement which must operate during the
    pendency of the appeal without the court expressing a final view
    on merits of the appeal, which will fall for consideration before the
    NCLAT”. Further, Para 21 of the same order stated that, “…The
    impugned order of the NCLAT, on the other hand, allowed the plea
2100                                                     [2024] 11 S.C.R.

                        Supreme Court Reports


     of the SRA for adjustment and consequential release of the PBG at
     the interlocutory stage. This prima facie would not be in accordance
     with the tenor of paragraph 8 of the affidavit…”. Therefore, it was
     submitted that the directions issued by this Court only related to
     a scenario were the SRA sought benefit of the offer made in the
     Lender’s Affidavit.
61. The counsel submitted that the NCLAT in its impugned order dealt
    with this Court’s order dated 18.01.2024 at length and concluded
    that the direction issued by this Court to deposit the amount of Rs.
    150 Crore peremptorily on or before 31.01.2024 was in reference to
    the Lender’s Affidavit dated 16.08.2023. Meaning thereby, the order
    of the NCLAT dated 28.08.2023 to adjust the PBG of Rs. 150 Crore
    was substituted by the direction of the Supreme Court. Therefore,
    the SRA would render itself disentitled to take benefit of the offer of
    the Appellant that they would withdraw the Company Appeal and the
    appeals before the Supreme Court. As such, the pending Company
    Appeal was to be heard on merits and decided in accordance with
    law by the NCLAT. In short, the entire issue before this Court was
    confined to an interpretation as to how the condition of Rs. 150
    Crore in the affidavit was to be interpreted and if the condition was
    complied with, the Appeals would stand withdrawn, if not, they would
    be decided on their own merits.
62. It was further submitted that the NCLAT rightly observed that, the
    submission of the Appellant that the Corporate Debtor should be
    directed to be liquidated on account of non-deposit of Rs. 150 Crore,
    cannot be accepted since the Supreme Court neither considered nor
    expressed any opinion on the question of liquidation. Liquidation was
    never recorded as a consequence and this is evident from liquidation
    not being mentioned in; (a) the arguments of the Appellants recorded
    by the NCLAT in its order dated 28.08.2023, (b) the judgment of
    the NCLAT dated 28.08.2023, (c) the arguments of the Appellants
    recorded by this Court in its order dated 18.01.2024 and, the findings
    or the directions of this Court in its order dated 18.01.2024.
63. The counsel also submitted that the adjustment of the PBG against
    the first tranche payment was possible under the Resolution Plan,
    specifically under Clause 6.4.4 which sets out the “Summary of
    payments and security package”. It is evident through Clause 6.4.4
    that a revolving package was agreed against each tranche of the
[2024] 11 S.C.R.                                                     2101

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     payment under the Resolution Plan. For the first tranche of payment,
     the security package comprises of the PBG and one of the Dubai
     Properties and it is stated that the PBG will be adjusted against the
     first tranche payment. For subsequent tranches of payment, the
     security package does not include the PBG and instead includes
     other types of security. It was submitted that the Lenders are relying
     on the RFRP to claim that no adjustment of the PBG was possible.
     However, the RFRP is only a wish list of the CoC which was informed
     to the applicants at the time of inviting plans. Therefore, it cannot
     override a negotiated and approved provision of the Resolution Plan.
     This is precisely why the approved Resolution Plans often deviate
     from the RFRP.
64. The counsel submitted that according to Clause 6.4.4 of the Resolution
    Plan, the Balance Security is in the form of immovable properties
    located in Dubai and since they are located outside India, the
    approval of the RBI was necessary for the creation of security. The
    security on the Dubai properties of the SRA was to be created on
    the Effective Date, i.e., 20.05.2022. On 21.05.2022, a day after the
    Effective Date, the SBI had applied for the approval and the same
    was received on 22.07.2022.
65. It was submitted that, on 03.02.2023 the SRA had shared drafts of the
    transaction documents required for the creation of security. However,
    no comments were received from the Appellants. It is the case of
    the SRA that the Appellants did not reply to the reminder emails
    sent between the months of May and October 2023 and this issue
    was also discussed during the 37th MC Meeting dated 09.10.2023.
    However, after more than a year of sharing the transaction documents,
    the Appellants sent their comments on the same on 08.04.2024 i.e.,
    three days before the expiry of the 30-day timeline given under the
    impugned order of the NCLAT.
66. It was further submitted that, only in the 42nd MC Meeting that took
    place on 02.04.2024 the SRA was informed for the first time that,
    as per the recent valuation, the valuation of the Balance Security
    worked out at Rs. 236 Crore and that there was a shortfall of Rs.
    14 Crores. In the same meeting, the SRA suggested that a property
    in India valued at Rs. 250 Crore could be provided as an alternate
    security. Vide email dated 10.04.2024, the SRA provided details of the
    alternate security equivalent to Rs. 250 Crore in India. However, the
2102                                                     [2024] 11 S.C.R.

                        Supreme Court Reports


     Appellants responded to the above vide their email dated 16.04.2024
     stating that providing an alternate security would tantamount to
     modification of the Resolution Plan.
67. The counsel submitted that the SRA, vide email dated 16.04.2024
    conveyed that they had not received any invoice from Mashreq
    Bank towards payment of their costs for acting as an agent for
    security creation and that the payment of security related costs to
    the extent of Rs. 76 Lakh could be done from the existing deposit
    with the Appellants. For the balance amounts, they requested that
    the invoices be shared with the SRA and that the same would be
    processed immediately. On 20.04.2024 and 01.05.2024 respectively,
    the SRA reminded the Appellants to share the invoices for the purpose
    of security creation.
68. On the issue of security creation, the counsel summed up submitting
    that the SRA had done everything within its control to enable the
    Appellants to create security including agreeing to bear all costs and
    expenses for creation and preservation of security, providing contracts
    for such security creation, and providing title documents of all the
    immovable properties to the Appellants. Therefore, the contention
    that the SRA failed to create Balance Security is factually incorrect.
69. With respect to the payment of the Airport Dues, it was submitted that,
    the Resolution Plan provides for the adjustment of CIRP dues from
    the positive cash balance of the Corporate Debtor and then from the
    share of the Lenders. The Appellants’ own case is that the Airport
    Dues amount to Rs. 1000 Crore approximately. Therefore, as per the
    Resolution Plan, Rs. 400 Crore approx. is payable towards the airport
    dues, first, from the positive cash balance of the Corporate Debtor
    and if that is insufficient, then from the Lenders’ share being CIRP
    Dues. Finally, the remaining Rs. 600 Crore would be borne by the SRA
70. As regards the payment of Provident Fund and Gratuity to the
    workmen and employees, it was submitted that the NCLAT did
    not waive off the liability of the SRA towards the payment of PF
    and Gratuity. On the contrary, for the implementation of the same,
    the NCLAT had provided timelines for making such payments in
    compliance with the applicable laws. It was further submitted that
    in the 42nd MC meeting held on 02.04.2024, the SRA undertook to
    make the payment towards the dues of PF and gratuity and the
    Appellants are aware of the same.
[2024] 11 S.C.R.                                                      2103

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

71. The counsel submitted that there are concurrent findings on the
    fulfillment of Conditions Precedent vide the order of the NCLT dated
    13.01.2023 and the impugned order of the NCLAT dated 12.03.2024.
    Clause 7.6.1 of the Resolution Plan sets out five Conditions
    Precedent. It was submitted that two of the five Conditions Precedent
    were “admittedly complied” with. On the remaining three, both the
    Tribunals have rendered concurrent findings, which ought not to
    be interfered with in an appeal under Section 62 of the IBC, 2016,
    which is effectively a Second Appeal.
72. The counsel submitted that the SRA cannot suo moto infuse funds
    into the Corporate Debtor since such infusion necessarily requires
    steps/actions to be taken by the Appellants and the Corporate Debtor
    acting through the MC. These steps include the appointment of
    directors on the board of the Corporate Debtor and seeking in-principal
    approval from the relevant stock exchanges under the SEBI LODR
    Regulations by the Corporate Debtor. However, despite constantly
    following up with the Appellants, the same has not been received
    yet and therefore, they have not allowed the SRA to undertake such
    a funding.
73. The Counsel submitted that the first Condition Precedent is the
    Validation of AOC by DGCA and MoCA as provided under Clause
    7.6.1(a). The SRA had a valid AOC until 03.09.2023 and the lapse of
    the AOC during the pendency of the appeals cannot mean that the
    Condition Precedent was not met. It was submitted that the condition
    was met on the date of the implementation application being filed
    before the NCLT and that the AOC has not been renewed only due
    to the fault of the Appellants.
74. It was submitted that the third Condition Precedent was the requirement
    of Slot Allotment Approval as provided under Clause 7.6.1(c). The
    counsel rejected the contention of the Appellants that the slots were
    not provided because the airport charges were not paid and stated
    that the airport charges are a part of the CIRP costs which could be
    met as and when the Resolution Plan was operationalized. It was
    further submitted that the SRA had obtained 48 slots on the Effective
    Date when it was supposed to secure only 46 slots. The NCLT in its
    order dated 21.06.2022 had also held that it was not possible for the
    SRA to obtain the slots that were historically available to the Corporate
    Debtor. Therefore, this Condition Precedent has also been met.
2104                                                      [2024] 11 S.C.R.

                         Supreme Court Reports


75. The counsel submitted that the fourth Condition Precedent related
    to obtaining the International Traffic Right Clearance as stated under
    Clause 7.6.1(d) of the Resolution Plan. This Condition Precedent
    had to be satisfied in accordance with the “applicable laws”. Upon
    applying for the Clearance, the MoCA had informed the SRA that,
    Clause 8(b) of the National Civil Aviation Policy, 2016 requires a
    minimum of 20 aircrafts to be deployed for domestic operations
    before applying for international clearance and that therefore, the
    same can be granted when 20 aircrafts of the Corporate Debtor
    are in operation. The Business Plan only envisages 6 aircrafts and
    the SRA can operationalize 20 aircrafts once the operations of the
    Corporate Debtor begin. This is evident from Clause 8.2.6(f) that
    states that the restart of international operations can be envisaged
    only after the completion of 12 months of operating the airline. Since
    this condition requires operations to re-commence before it can be
    satisfied, this Condition Precedent has also been complied with.
76. Mr. Gopal Sankaranarayanan, learned senior counsel also appearing
    for the Respondents, concurred with all the aforesaid submissions
    made on behalf of the SRA. In addition to bringing our attention to
    Clause 6.4.4 on the issue of adjustment of the PBG, he also referred
    to Clause 6.4.12 of the Resolution Plan which stated that the PBG
    will bring financial flexibility for the SRA and help the SRA to advance
    the committed payments and achieve its goal of re-commencing the
    operations of the Corporate Debtor at the earliest.
77. It was submitted that the NCLAT order dated 28.08.2023 rightly
    recognized that Regulation 36B(4A) of the 2016 Regulations only
    provides for the PBG requirement for the purposes of the RFRP and
    the same has been complied with by the SRA. Further, the counsel
    pointed out that Clause 6.4.4 (a)(i) elaborates on the “Committed
    Cash Payments” to be made to the Financial Creditors. In the table,
    under the heading “Date of release of Security”, the PBG of Rs.
    150 Crore was not mentioned while the other two forms of security
    find a mention. Thus, the intention was that, the PBG be adjusted
    in making the first tranche payment.
78. The counsel further submitted that there is no specific consequence
    provided under the Resolution Plan for a default in the creation of
    security. It was reiterated that the SRA had undertaken all possible
    steps to further the execution of the mortgage of the Dubai properties
[2024] 11 S.C.R.                                                    2105

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     as per the Resolution Plan and it is the Appellants who have not
     cooperated in this regard.
79. The counsel submitted that the Appellants have taken contradictory
    stances at different stages of the dispute before different forums.
    Before the NCLAT in its pending Company Appeal, it was contended
    by the Appellants that the NCLT had erroneously allowed the
    Resolution Plan to be implemented without the complete compliance
    of the Conditions Precedent by the SRA. However, before this Court,
    they have argued that the SRA has claimed that the Conditions
    Precedent were fulfilled on 20.05.2022 and has asserted that it would
    be the Effective Date. As a consequence, the SRA should have met
    with their first tranche payment obligations within 180 days from the
    Effective Date.
80. The counsel submitted that the consequences of non-compliance with
    the Conditions Precedent were that the SRA would not be able to
    re-commence operations as an aviation company as stated in Clause
    7.6.1 of the Resolution Plan. He also submitted that the Effective
    Date for the purposes of the Resolution Plan would only kick in upon
    the fulfillment of all the Conditions Precedents. The consequence
    of non-compliance with the Conditions Precedent would be that the
    Resolution Plan shall automatically stand withdrawn and upon, such
    withdrawal, the members of the SRA in the MC shall resign and the
    remaining members of the MC shall assume absolute control of the
    Corporate Debtor.
81. Adding to the submissions as regards the Airport Dues, it was
    submitted that as per the estimates made by the RP, the airport dues
    i.e., the parking charges and airport space lease charges were Rs.
    240 Crore and this was reflected in Clause 6.4.1(f) of the Resolution
    Plan. It was submitted that the dues accrued during the period of
    CIRP i.e., till the date of approval of the Resolution Plan, is a part
    of the CIRP costs and such payments have to be made within 170
    days from the Effective Date as per Clause 6.4.1 of the Resolution
    Plan. As per Clause 6.4.1(h), a sum of Rs. 25 Crore was set aside for
    CIRP costs. However, it must be noted that Clause 6.4.1(m) allows
    the SRA to utilize the funds available with the Corporate Debtor for
    making payments of any portion of the CIRP costs. It was submitted
    that the Lenders rely on Clause 6.3.1(d) to state that the airport
    dues have to be settled upfront and not in staggered payments.
2106                                                         [2024] 11 S.C.R.

                          Supreme Court Reports


     However, Clause 6.3.1(d) is just a proposal and not a condition of
     the Resolution Plan.
82. On workmen and employees’ dues, it was submitted that, as per
    Clause 6.4.2 on the “Summary of Financial Proposal” the amount
    demarcated for all the claims related to employees or workmen was
    Rs. 52 Crore and as per the Implementation Schedule, these claims
    were to be paid within 175 days from the Effective Date. However,
    the NCLAT vide its order dated 21.10.2022 increased it to Rs. 113
    Crore since it was the minimum liquidation value that they were
    entitled to as per the estimates of the RP. The final directions issued
    by the NCLAT in the aforesaid order conveyed that the workmen and
    employees are entitled to the payment of unpaid PF and gratuity
    till the Insolvency Commencement Date and the RP was directed
    to compute such payment within 30 days. The RP had calculated
    such amounts to be Rs. 14 Crore towards PF and Rs. 188.7 Crore
    towards gratuity. It was submitted that neither the NCLAT order dated
    21.10.2022 nor the order of this Court dated 30.01.2023 had provided
    any specific timelines for fulfillment of these additional liabilities which
    were cast upon the SRA. This is precisely why the SRA proposed
    to pay Rs. 14 Crore towards PF upfront in compliance with Section
    11 of the PF Act and pay the Gratuity dues of Rs. 188.2 Crore in a
    staggered manner.
83. The counsel finally referred to the letter dated 16.08.2024 sent by
    MoCA which provided Security Clearance in respect of a proposed
    Director of the Corporate Debtor, Mr. Swapnil Jain. The validity period
    of this Security Clearance was stated to be co-terminus with the
    validity period of the AOC which was issued by the DGCA.

     D.    ISSUES FOR DETERMINATION
84. Having heard the learned counsel appearing for the parties and
    having gone through the materials on record, the following questions
    of law fall for our consideration: -
     i.    Whether the Performance Bank Guarantee (PBG) could have
           been adjusted against the first tranche payment which was to
           be made under the Resolution Plan, within 180 days from the
           Effective Date, in contravention of the order of this Court dated
           18.01.2024, the terms of the Resolution Plan and the provisions
           of law? To put it in other words, whether the impugned order of
[2024] 11 S.C.R.                                                            2107

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

            the NCLAT allowing the adjustment of the Performance Bank
            Guarantee (PBG) in lieu of payment of the first tranche could
            be said to be perverse?
     ii.    Whether the non-implementation of the Resolution Plan by the
            SRA necessarily leads to the consequence of liquidation as
            provided under Section 33(3) of the IBC, 2016?
     iii.   Whether the timely implementation of the Resolution Plan is
            also one of the objectives of the IBC, 2016?

     E.     ANALYSIS
85. Before we proceed to advert to the rival submissions canvassed
    on either side and the issues outlined above, we must look into
    the preliminary objection raised on behalf of the SRA i.e., that the
    scope of an appeal under Section 62 of the IBC must be restricted
    to a “question of law”. In this regard, reliance was placed on the
    decision of this Court in IFCI Ltd. v. Sutanu Sinha and Others
    reported in 2023 SCC OnLine SC 1529 which dealt with the
    issue as to whether compulsorily convertible debentures could be
    treated as a “debt” instead of an equity instrument, to submit that
    the jurisdiction under Section 62 is restricted to a question of law
    akin to a second appeal. The relevant observations are reproduced
    hereinbelow:
            “29. Last but not the least, we must also note that our
            jurisdiction comes from section 62 of the Code. The said
            section reads as under:
                 “62. (1) Any person aggrieved by an order of the
                 National Company Law Appellate Tribunal may file
                 an appeal to the Supreme Court on a question of
                 law arising out of such order under this Code within
                 forty-five days from the date of receipt of such order”.
            30. The jurisdiction is restricted to a question of law akin
            to a second appeal. The law does not envisage unlimited
            tiers of scrutiny and every tier of scrutiny has its own
            parameters. Thus, the lis inter se the parties has to be
            analysed within the four corners of the ambit of the statutory
            jurisdiction conferred on this court.
2108                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


          31. We are thus of the view that the appeal does not raise
          any such question of law and that the findings of the courts
          below are in accordance with settled principles.”
                                                 (emphasis supplied)

86. Section 100 of the Code of Civil Procedure, 1908 is the provision
    related to a second appeal and it reads as thus:
          “100. Second appeal – (1) Save as otherwise expressly
          provided in the body of this Code or by any other law for
          the time being in force, an appeal shall lie to the High
          Court from every decree passed in appeal by any Court
          subordinate to the High Court, if the High Court is satisfied
          that the case involves a substantial question of law.
          (2) An appeal may lie under this section from an appellate
          decree passed ex parte. (3) In an appeal under this
          section, the memorandum of appeal shall precisely state
          the substantial question of law involved in the appeal.
          (4)Where the High Court is satisfied that a substantial
          question of law is involved in any case, it shall formulate
          that question.
          (5)The appeal shall be heard on the question so formulated
          and the respondent shall, at the hearing of the appeal,
          be allowed to argue that the case does not involve such
          question:
          Provided that nothing in this sub-section shall be deemed
          to take away or abridge the power of the Court to hear, for
          reasons to be recorded, the appeal on any other substantial
          question of law, not formulated by it, if it is satisfied that
          the case involves such question.”
                                                 (emphasis supplied)

87. This Court in Chandrabhan (Deceased) Through Lrs. And Others
    v. Saraswati and Others reported in 2022 SCC OnLine SC 1273
    explained as to what constitutes a “substantial question of law” under
    Section 100 of the Code of Civil Procedure, 1908. The relevant
    observations made are reproduced hereinbelow:
[2024] 11 S.C.R.                                                            2109

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          “33. The principles relating to Section 100 of the CPC
          relevant for this case may be summarised thus:
          (i) An inference of fact from the recitals or contents of a
          document is a question of fact. But the legal effect of the
          terms of a document is a question of law. Construction
          of a document involving the application of any principle
          of law, is also a question of law. Therefore, when there is
          misconstruction of a document or wrong application of a
          principle of law in construing a document, it gives rise to
          a question of law.
          (ii) The High Court should be satisfied that the case involves
          a substantial question of law, and not a mere question of law.
          A question of law having a material bearing on the decision
          of the case (that is, a question, answer to which affects the
          rights of parties to the suit) will be a substantial question
          of law, if it is not covered by any specific provisions of law
          or settled legal principle emerging from binding precedents
          and involves a debatable legal issue. A substantial question
          of law will also arise in a contrary situation, where the legal
          position is clear, either on account of express provisions of
          law or binding precedents, but the court below has decided
          the matter, either ignoring or acting contrary to such legal
          principle. In the second type of cases, the substantial
          question of law arises not because the law is still debatable,
          but because the decision rendered on a material question,
          violates the settled position of law.
          (iii) The general rule is that the High Court will not interfere
          with findings of facts arrived at by the courts below. But
          it is not an absolute rule. Some of the well-recognised
          exceptions are where (i) the courts below have ignored
          material evidence or acted on no evidence; (ii) the courts
          have drawn wrong inferences from proved facts by applying
          the law erroneously; or (iii) the courts have wrongly cast
          the burden of proof. When we refer to “decision based
          on no evidence”, it not only refers to cases where there
          is a total dearth of evidence, but also refers to any case,
          where the evidence, taken as a whole, is not reasonably
          capable of supporting the finding.”
                                                   (emphasis supplied)
2110                                                         [2024] 11 S.C.R.

                          Supreme Court Reports


     This Court recapitulated that a substantial question of law would
     also arise in a situation where the legal position is clear, either on
     account of express provisions of law or binding precedents, but the
     Court below has ignored or acted contrary to such legal principles
     while deciding the matter. In such circumstance, the decision
     rendered by the Court below would violate a settled position of law
     and therefore, constitute a substantial question law. Furthermore, it
     was observed therein that it is not an absolute rule that the Court
     in a second appeal will not interfere with findings of fact. One of the
     well-recognized exceptions is where the Courts below have drawn
     wrong inferences from proved facts, by applying the law erroneously.
88. In Maria Colaco and Another v. Alba Flora Herminda D’souza
    and Others reported in (2008) 5 SCC 268, it was held that in the
    second appeal under Section 100 CPC, the High Court should not
    interfere on the questions of fact. However, if on a scrutiny of the
    evidence, it is found that the finding recorded by the first appellate
    court is totally perverse then an interference is certainly possible in the
    matter as it constitutes a question of law. The relevant observations
    are reproduced hereinbelow:
           “7. The learned Single Judge after considering the matter
           found that these averments did not constitute the basis
           on the part of the plaintiff that he was not in possession
           of the suit property. On the contrary, the learned Single
           Judge found in reply to Para 13 of the plaint that the
           defendants in their written statement admitted that the
           work was stopped by Defendant 1 for some time but they
           restarted the work again. This, according to the learned
           Single Judge was a proof of the fact that Defendants 1 and
           2 and Defendant 3 were not sure about the possession
           and right of Defendants 1 and 2 over the property. In fact,
           what transpires from all these facts is that the trial court
           reached the same conclusion as the learned Single Judge
           in second appeal in the High Court. It is true normally that
           in the second appeal the High Court should not interfere on
           the questions of fact. But if on the scrutiny of the evidence
           it is found that the finding recorded by the first appellate
           court is totally perverse then certainly the High Court can
           interfere in the matter as it constitutes the question of law.”
                                                   (emphasis supplied)
[2024] 11 S.C.R.                                                           2111

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

89. In Abdul Raheem v. Karnataka Electricity Board and Others
    reported in (2007) 14 SCC 138, the Court acknowledged that the
    High Court’s jurisdiction in terms of Section 100 is limited. Having
    said so, it was also observed that a consideration of irrelevant
    facts, non-consideration of relevant facts and a finding of fact
    arrived at by overlooking vital documents would also give rise to a
    substantial question of law. The relevant observations are reproduced
    hereinbelow:
          “10. A substantial question of law ordinarily would not arise
          from the finding of facts arrived at by the trial court and
          the first appellate court. The High Court’s jurisdiction in
          terms of Section 100 of the Code is undoubtedly limited.
          11. The question as to whether the plaintiff was ready and
          willing to perform its part of contract by itself may not give
          rise to a substantial question of law. Substantial question
          of law should admittedly be formulated relying on or on
          the basis of findings of fact arrived at by the trial court
          and the first appellate court.
          12. However, there cannot be any doubt whatsoever that
          consideration of irrelevant fact and non-consideration of
          relevant fact would give rise to a substantial question of law.
          Reversal of a finding of fact arrived at by the first appellate
          court ignoring vital documents may also lead to a substantial
          question of law. In Vidhyadhar v. Manikrao [(1999) 3 SCC
          573] this Court held : (SCC p. 586, para 23)
                “23. The findings of fact concurrently recorded by
                the trial court as also by the lower appellate court
                could not have been legally upset by the High Court
                in a second appeal under Section 100 CPC unless
                it was shown that the findings were perverse, being
                based on no evidence or that on the evidence on
                record, no reasonable person could have come to
                that conclusion.”
          (See also Iswar Bhai C. Patel v. Harihar Behera [(1999)
          3 SCC 457] .)
          14. We may, however, notice a few decisions in regard
          to the jurisdiction of the High Court under Section 100
2112                                                      [2024] 11 S.C.R.

                      Supreme Court Reports


        of the Code. In Commr. of Customs (Preventive) v. Vijay
        Dasharath Patel [(2007) 4 SCC 118] this Court held : (SCC
        p. 128, paras 22-26)
             “22. We are not oblivious of the fact that the High
             Court’s jurisdiction in this behalf is limited. What would
             be substantial question of law, however, would vary
             from case to case.
             23. Moreover, although, a finding of fact can be
             interfered with when it is perverse, but, it is also trite
             that where the courts below have ignored the weight
             of preponderating circumstances and allowed the
             judgment to be influenced by inconsequential matters,
             the High Court would be justified in considering
             the matter and in coming to its own independent
             conclusion. (See Madan Lal v. Gopi [(1980) 4 SCC
             255] .)
             24. The High Court shall also be entitled to opine
             that a substantial question of law arises for its
             consideration when material and relevant facts have
             been ignored and legal principles have not been
             applied in appreciating the evidence. Arriving at a
             decision, upon taking into consideration irrelevant
             factors, would also give rise to a substantial question
             of law. It may, however, be different that only on the
             same set of facts the higher court takes a different
             view. (See Collector of Customs v. Swastic Woollens
             (P) Ltd. [1988 Supp SCC 796 : 1989 SCC (Tax) 67]
             and Metroark Ltd. v. CCE [(2004) 12 SCC 505] .)
             25. Even in a case where evidence is misread,
             the High Court would have power to interfere.
             (See W.B. Electricity Regulatory Commission v. CESC
             Ltd. [(2002) 8 SCC 715] and also Commr. of
             Customs v. Bureau Veritas [(2005) 3 SCC 265] .)
             26. In Dutta Cycle Stores v. Gita Devi Sultania [(1990)
             1 SCC 586] this Court held : (SCC p. 587, para 4)
                  ‘4. Whether or not rent for the two months in
                  question had been duly paid by the defendants
[2024] 11 S.C.R.                                                          2113

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

                      is a question of fact, and with a finding of such
                      fact, this Court does not ordinarily interfere in
                      proceedings under Article 136 of the Constitution,
                      particularly when all the courts below reached
                      the same conclusion. But where the finding of
                      fact is based on no evidence or opposed to the
                      totality of evidence and contrary to the rational
                      conclusion to which the state of evidence must
                      reasonably lead, then this Court will in the
                      exercise of its discretion intervene to prevent
                      miscarriage of justice.’
           (See also P. Chandrasekharan v. S. Kanakarajan [(2007)
           5 SCC 669] .)”.
                                                   (emphasis supplied)

     Therefore, what would constitute a substantial question of law would
     differ in each case. When material and relevant facts have been
     ignored and legal principles have not been applied while appreciating
     the evidence, a substantial question of law can be said to have
     arisen. Additionally, even in a case where evidence is misread, the
     power to interfere under Section 100 would exist.
90. In our considered view the impugned order of the NCLAT directing
    the SRA to adjust the PBG of Rs. 150 Crore against the first tranche
    payment of Rs. 350 Crore was in flagrant disregard of the order of
    this Court dated 18.01.2023, the terms of the Resolution Plan and
    established law. Such an order was perverse for having not properly
    considered several material and relevant facts and misreading
    evidence as well. Furthermore, the non-infusion and payment of
    funds in compliance with the applicable laws and the terms of the
    Resolution Plan had led to circumstances causing a failure of the
    Resolution Plan. We have no doubt in our mind that the NCLAT
    acted contrary to the settled legal principles and went to the extent
    of drawing wrong inferences from proved facts while deciding the
    matter. This itself justifies the examination of various issues in exercise
    of the jurisdiction afforded to us under Section 62 of the IBC, 2016.
     i.    Whether the Performance Bank Guarantee (PBG) could
           have been adjusted against the first tranche payment which
           was to be made under the Resolution Plan, within 180 days
2114                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


          from the Effective Date, in contravention of the order of
          this Court dated 18.01.2024, the terms of the Resolution
          Plan and the provisions of law?

     a.   Whether the Conditions Precedent were fulfilled by
          Respondent No.1/SRA and the Effective Date was fixed at
          20.05.2022?
91. Clause 7.6.1 of the Resolution Plan details five Conditions Precedent
    that have to be fulfilled by the SRA. They are: - (a) Validation of
    AOC, (b) Approval of Business Plan, (c) Slot Allotment Approval, (d)
    International Traffic Rights Clearance, and (e) Demerger of AGSL.
    Of the five Conditions Precedent that find mention under Clause
    7.6.1 of the Resolution Plan, the Appellants have only disputed
    the fulfilment of three Conditions Precedent i.e., Validation of AOC,
    Slots Allotment Approval and International Traffic Rights Clearance.
    According to Clause 7.6.2 of the Resolution Plan, the date of fulfillment
    of all the Conditions Precedent as stated in Clause 7.6.1 would be
    the Effective Date for the purposes of the Resolution Plan. A failure
    to fulfil the Conditions Precedent within a maximum of 270 days
    from the date of approval of the Resolution Plan would lead to an
    automatic withdrawal of the Resolution Plan as per Clause 7.6.4.
92. On 22.06.2021, the NCLT had given its imprimatur to the Resolution
    Plan that was submitted by the SRA and this was the Approval Date
    i.e., “Y” as per the Implementation Schedule set out under Clause
    7.7 of the Resolution Plan. The SRA had to fulfil the five Conditions
    Precedent within a period of 90 days, that was extendable to an
    additional 180 days i.e., 270 days in total. This period expired on
    22.03.2022. However, the same was extended vide order dated
    11.04.2022 by the NCLT until 25.05.2022, by allowing an exclusion
    of 65 days.
93. Upon receiving the AOC from the relevant authorities on 20.05.2022
    i.e., within the extended time period as allowed by the NCLT, the
    SRA asserted that the Effective Date had been achieved. The SRA
    had approached the NCLT seeking a declaration from the Tribunal
    that all the Conditions Precedent have been met and that the SRA
    be allowed to begin the implementation of the Resolution Plan.
    Vide order dated 13.01.2023, the NCLT held that all the Conditions
    Precedent had indeed been met and that 20.05.2022 would be
[2024] 11 S.C.R.                                                         2115

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     considered as the Effective Date for the purposes of implementation
     of the Resolution Plan. The findings of the NCLT in the aforesaid
     order are reproduced hereinbelow:
          “Findings:
          122. […] However, having considered the rival submissions
          and on perusal of record with regards to satisfactory
          compliance of conditions precedent (CPs) it is noted that
          there is no dispute so far as satisfactory compliance of
          CPs at serial no. (i) and (v) as per approved plan i.e.:- (i)
          Validation of Air Operator Certificate by Directorate General
          of Civil Aviation (DGCA) and Ministry of Civil Aviation
          (MoCA) and (v) Approval of demerger of ground handling
          business into all capital AGSL.
          In this background we have thus considered if the remaining
          three CPs are duly complied with by the applicant or
          otherwise.
          123. As regards to CP No. 2 i.e. Submission and approval
          of business plan to DGCA and MoCA: The business plan
          was submitted to above Authorities to fulfil compliance of
          DGCA’s Show Cause Notice (SCN) to CD of April 2019.
          SCN states that Air Operator Certificate will be issued after
          MoCA approves the business plan. Thus, with issuance
          of Air Operator Certificate, it is implied that the business
          plan has been approved. Even otherwise, guidelines for
          issuance of Air Operator Certificate being CAP 3100 clearly
          states that the DGCA will review the detailed business
          plan of the Applicant before issuance of Air Operator
          Certificate and with issuance of Air Operator Certificate
          there is implied approval of MoCA. In the background of
          above we find that this CP is satisfactorily complied with
          the issuance of AOC.
          124. As regards to CP No. 3 i.e. Slots Allotment Approval:
          It is noted that plan approval order of this Tribunal dated
          22nd June, 2021 stipulates that no historic slots will be
          granted to Corporate Debtor or SRA. Admittedly, there is
          no challenge to this order thereby accepting the fact that
          old slot cannot be reinstated. Accordingly, this CP needs to
2116                                                    [2024] 11 S.C.R.

                      Supreme Court Reports


        be read with plan approval order, where Corporate Debtor
        shall be provided with such slots for which it applies. There
        is no dispute that slots for which SRA applied were granted
        to them by the concerned Competent Authority including the
        slots in Delhi and Mumbai, on settling the old dues and as
        such it cannot be considered as non-allotment of slots, as
        SRA has received the slots it requested for in compliance
        with plan approval order. The SRA cannot get all previous
        slots as this condition needs to be read with plan approval
        order of this Tribunal. In that view of the matter, above CPs
        is also found to be Satisfactorily complied with.
        125. As regards to CP no. 4: International Traffic Right
        Clearance: On perusal of the plan approval order dated
        22nd June, 2021, it is found that no blanket approval can
        be granted upfront to the SRA as it has to approach the
        concerned authorities for grant of such approval as per
        applicable laws. As already stated above, the plan approval
        order has reached its finality, thus, accepting the fact
        that all the approval issued upfront cannot be reinstated.
        Accordingly, this condition precedent needs to be read with
        plan approval order. Even otherwise there is no dispute that
        under the approved plan, SRA has to re-commence with
        operation of six aircrafts. The International Traffic Rights
        clearance is required to be obtained in compliance with
        the applicable laws which stipulates that minimum twenty
        aircrafts are required to be deployed before applying for
        such clearance. In view of this, we find that this condition
        cannot be satisfied upfront and needs to be satisfied in
        compliance with applicable laws i.e., after the SRA has
        twenty aircrafts in operation which can only be achieved
        once the operation is re-commenced successfully.
        Accordingly, this condition can only be fulfilled after the
        SRA/Applicants re-commences its business and not prior
        to its commencement.
        It goes without saying that plan approved by this Tribunal
        has to be implemented without any modification much less
        than on satisfaction of any other undertaking and thus, the
        effective date and completion date of condition precedent
        under the plan shall have to be read as 20th May, 2022.
[2024] 11 S.C.R.                                                        2117

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          126. In the background of above facts and for the reasons
          stated above we hold that in addition to CPs (I) & (V) which
          are admittedly complied, remaining CPs (II), (III), (IV) are
          also duly complied.”
94. During the period when the aforesaid order of the NCLT was
    passed, the SRA possessed a valid AOC and therefore, there was
    no dispute pertaining to this Condition Precedent. With respect
    to the Slot Allotment Approval, the NCLT observed that although
    the historic slots which were available to the Corporate Debtor
    could not be obtained by the SRA, yet the slots for which the SRA
    had applied were granted to it by the concerned authorities upon
    settling the old dues and as such, this could not be considered as
    non-allotment of slots. Therefore, this Condition Precedent was
    found to be satisfactorily complied with. As regards the Condition
    Precedent on obtaining International Traffic Rights Clearance, the
    applicable law required a minimum of 20 aircrafts to be deployed
    before applying for such a clearance. However, under the approved
    Plan, the SRA had to re-commence with the operations with only six
    aircrafts. It was, therefore, held that this Condition Precedent could
    not have been satisfied upfront and could only be satisfied once the
    operations of the Corporate Debtor had commenced successfully.
    With such observation, this Condition Precedent was also found to
    be duly complied with. The NCLT noted that the plan which was
    approved vide the Plan approval order dated 22.06.2021 had to be
    implemented without any modification and thus the Effective Date
    i.e., the date of completion of the Conditions Precedent under the
    Resolution Plan should be read as 20.05.2022.
95. The Appellants filed a statutory appeal against the order of the NCLT
    dated 13.01.2023 before the NCLAT and also sought a stay on the
    same. However, the grant of stay was declined by the NCLAT on
    03.03.2023. This should have closed the debate on the understanding
    between the parties that the Effective Date was set in stone.
96. The NCLAT also vide its impugned order held that the SRA had
    fulfilled all the required Conditions Precedent. On Slot Allotment
    Approval, it was held that 48 slots have been obtained by the
    SRA for the recommencement of operations. The contention of the
    Appellants that airport charges are required to be paid upfront for
    obtaining such slots was rejected since the NCLAT was of the opinion
2118                                                    [2024] 11 S.C.R.

                        Supreme Court Reports


     that the payment towards airport charges, which are a part of CIRP
     costs, must be made as per the terms of the Resolution Plan when
     its implementation had begun. Therefore, it was declared that the
     Condition Precedent on Slot Allotment Approval was fulfilled despite
     the non-payment of Airport Dues by the SRA. On International Traffic
     Rights Clearance, the NCLAT echoed the opinion of the NCLT that
     it could not have obtained this clearance without commencing and
     amplifying the operations of the Corporate Debtor. It was observed
     that this Condition Precedent should not come in the way of the
     implementation of the Resolution Plan. As regards the AOC, it
     was contended by the Appellants that the same had lapsed after
     03.09.2023 and no extension was granted by the DGCA thereafter.
     However, the NCLAT was of the view that the AOC was valid on
     the date when the SRA had approached the NCLT for a declaration
     that the Conditions Precedent were fulfilled and also when the order
     dated 13.01.2023 of the NCLT was passed. The expiry of the validity
     period of the AOC during the pendency of the Company Appeal
     was not considered sufficient grounds to hold that the Condition
     Precedent was not fulfilled. The NCLAT while reaffirming that all
     the Conditions Precedent were satisfactorily fulfilled observed that
     there was no infirmity in the order of the NCLT dated 13.01.2023.
     The NCLAT further directed the SRA to make an application for the
     re-issuance of the AOC within 90 days from the date of its order
     i.e., by 12.06.2024.
97. The nature of the Conditions Precedent laid out under the Resolution
    Plan were such that several of them could not be fulfilled before
    the operationalization of the Corporate Debtor. The assertion that
    the Effective Date would kick in only upon fulfilment of all the
    Conditions Precedent and since the Appellants had challenged
    the fulfilment of the Conditions Precedent, such a date could not
    be said to have yet arrived, cannot be accepted. The order of
    the NCLT dated 22.06.2021 approving the Resolution Plan had
    fixed the Effective Date as the 90th day from the Approval date,
    which was subject to a maximum extension of another 180 days.
    It consciously removed the ambiguity that plagued Clauses 7.6.2
    and 7.6.4 respectively for the precise reason & with the idea that
    the Effective Date should not be endlessly postponed. Agreeing
    to such an erroneous proposition would mean that the Effective
    Date would never be achieved as long as the parties are litigating
[2024] 11 S.C.R.                                                      2119

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     before the Courts and the SRA would be absolved of taking the
     implementation under the Resolution Plan further. The NCLAT
     had declined to stay the order of the NCLT dated 13.01.2023
     which held that all the Conditions Precedent were fulfilled. Further,
     on a perusal of the impugned order, it is evident that the NCLT
     and NCLAT rendered concurrent findings of fact that the SRA
     had fulfilled all the Conditions Precedent. In other words, it was
     repeatedly declared by different fora that the Effective Date was
     frozen on 20.05.2022 and the obligation of the SRA to implement
     the Resolution Plan was absolute. All steps necessary should have
     been undertaken by the SRA, at least post the impugned order of
     the NCLAT dated 12.03.2024. To contend that its hands were tied
     since the Conditions Precedent were still being challenged before
     this Court is nothing but a reflection of the mala fide intention on
     the part of the SRA to not fulfil its obligations in accordance with the
     Resolution Plan under the garb of pendency of litigation. Such an
     undue delay cannot be permitted, especially in light of the intention
     of the IBC, 2016 to ensure a successful and time-bound revival of
     the Corporate Debtor. This places a higher obligation on the SRA
     to act in an expeditious manner.

     b.   Whether the NCLAT could have directed the Performance
          Bank Guarantee (PBG) to be adjusted against the first
          tranche payment which was to be made within 180 days
          of the Effective Date?
98. There is no dispute to the fact that the Effective Date was frozen on
    20.05.2022. Therefore, as per Clause 6.3.1(g) on the “Infusion of
    Funds and Timelines”, and Serial No.11 under Clause 7.7, the first
    tranche payment of Rs. 350 Crore had to be made by the SRA, upfront,
    within a period of 180 days from the Effective Date i.e., 20.05.2022.
    As per the Resolution Plan, this 180-day timeline otherwise would
    have expired on 16.11.2022. Several extensions were granted to
    the SRA to infuse this amount, at different stages of this litigation,
    by the NCLT, the NCLAT and this Court as well - First, by the NCLT
    vide order dated 13.01.2023, by which the timeline for infusion of
    first tranche payment was extended till 15.05.2023; Secondly, by the
    NCLAT vide order dated 26.05.2023, where the timeline of 180 days
    was further extended up to 31.08.2023; Thirdly, again by the NCLAT
    vide order dated 28.08.2023, where the timeline of 180 days was
2120                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


     extended up to 30.09.2023; and Fourthly, by this Court vide order
     dated 18.01.2024, whereby the time of 180 days for infusion was
     extended up to 31.01.2024.

     I.   The adjustment of the PBG was impermissible under the
          terms of the Resolution Plan read with Regulation 36B(4A)
          of the 2016 Regulations.
99. It is the case of the SRA that as per Clause 6.4.4 on the “Treatment
    of Financial Creditors” and the table adduced under the heading
    “Summary of payment and security package”, the PBG of Rs. 150
    Crore could have been adjusted against the payment of the first
    tranche. It was submitted that in the last column of the table, the
    “Date of Release of Security” is provided. In the very first head in the
    column on date of release of security, the expression “PBG adjusted”
    has been mentioned against the first tranche of cash payment to be
    made to the Financial Creditors. Further, in the explanation given to
    the said table under Clause 6.4.4(a)(i), against the heading “Date
    of Release of Security”, there is no mention of the PBG while the
    other two types of security find a mention. It was submitted that
    the only good reason for this exclusion was the understanding that
    the PBG was adjustable against the obligation of the SRA towards
    payment of the first tranche. Further, it is the case of the SRA that
    since a revolving security package was agreed to under Clause
    6.4.4, other types of security were envisioned for the subsequent
    tranches of payment and therefore, no issue could have been raised
    in adjusting the PBG towards the first tranche. However, we find it
    extremely difficult to agree with the stance of the SRA for multiple
    reasons which are detailed below.
100. The RFRP under Clause 3.13 deals with the Performance Security
     to be given by the SRA. Clause 3.13.1 provides that the SRA shall
     furnish or cause to be furnished, an unconditional and irrevocable
     PBG, of an amount of Rs. 150 Crore in favor of the SBI within 7 days
     of being declared as the SRA. Clause 3.13.2 provides that the PBG
     shall be valid, till the later of (a) a period of 180 days from the date
     of the PBG; and (b) the date of completion of the implementation of
     the Resolution Plan, as determined by the RP and the CoC. Clause
     3.13.7 provides that the PBG can be invoked or appropriated at
     any time by the SBI, without any reference to the SRA, upon the
     occurrence of any of the following conditions;
[2024] 11 S.C.R.                                                          2121

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     i.     If any of the conditions under the Letter of Intent or the Resolution
            Plan are breached;
     ii.    If the SRA fails to re-issue or extend the PBG in accordance
            with the terms of the RFRP; or
     iii.   Failure of the SRA to implement the Resolution Plan to the
            satisfaction of the CoC, and in accordance with the terms of
            the Resolution Plan.
     Clause 3.13.8 provides that the PBG shall be returned to the SRA
     within a period of 7 days, upon 100% completion of the implementation
     of the Resolution Plan by the SRA. Finally, Clause 3.13.9 states in
     categorical terms that, the PBG shall not be set-off against or used
     as part of the consideration that the SRA proposes to offer in relation
     to the Corporate Debtor, even if expressly indicated as such by the
     SRA in the Resolution Plan.
101. It is of vital importance that the aforementioned clauses of the RFRP
     are read conjointly with Clauses 7.3 and 9.4 of the Resolution Plan.
     Clause 7.3 of the Resolution Plan deals with the “Compliance with
     respect to Regulation 36B(4A)” and states that the SRA undertakes
     to provide the PBG as per the terms of the RFRP in favor of the
     SBI within 7 days of it being declared as the SRA. Clause 9.4 of
     the Resolution Plan is titled “Implementation” and states that “the
     performance guarantee provided by the Resolution Applicant can
     be invoked in accordance with the terms of the RFRP”. Therefore,
     it is as clear as a noonday that the terms of the RFRP, particularly
     in relation to the performance security i.e., PBG, stood incorporated
     in the Resolution Plan by way of Clauses 7.3 and 9.4 respectively
     of the Resolution Plan.
102. Furthermore, in the Covering Letter adduced with the Resolution
     Plan, the SRA stated as thus:
            “4. We hereby undertake that we, and our Representatives,
            shall at all times, be in compliance with the provisions of
            the RFRP, the Non-Disclosure Agreement, the IB Code
            and the CIRP Regulations.
                   xxx                   xxx                  xxx
            c. Acceptance
            We hereby unconditionally and irrevocably agree and
            accept the terms of the RFRP and that the decision made
2122                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


          by the Resolution Professional, CoC and/or the Adjudicating
          Authority in respect of any matter with respect to, or arising
          out of, the RFRP and the Resolution Plan Submission
          Process shall be binding on us…

                  xxx                  xxx                 xxx
          10. We confirm that we have not taken any deviations so as
          to be deemed non-responsive with respect to the provisions
          of the RFRP, the IB Code and the CIRP Regulations.”
                                                 (emphasis supplied)

     A bare reading of the above also strengthens the conclusion that
     the SRA has to remain compliant with the terms of the RFRP, at all
     times, in addition to being obedient to the terms of the Resolution
     Plan. Therefore, to say that the RFRP was merely a wish list of the
     CoC which was informed to the applicants at the time of inviting plans
     is incorrect, to say the least. The provisions of the RFRP, especially
     those provisions related to the Performance Security or PBG, were
     binding on the SRA.
103. The learned counsel for the SRA tried to place reliance on one
     another Clause of the Resolution Plan i.e., Clause 6.4.12 which
     stated that the PBG would bring financial flexibility and help the
     SRA to advance certain committed payments. This according to
     the SRA is an affirmation of the fact that the PBG could have been
     adjusted against the first tranche payment. However, it must be
     pointed out that Clause 6.4.12 was amended vide an Addendum to
     the Resolution Plan dated 02.10.2020. The erstwhile Clause 6.4.12
     of the Resolution Plan reads thus:
          “6.4.12. Request for the consideration of the CoC - The
          Resolution Applicant shall provide a performance security
          bank guarantee for a total sum of Rs. 47.5 Crores, which
          will bring financial flexibility for the Resolution Applicant
          and help the Resolution Applicant advance the committed
          payments and achieve its goal of re-commencing the
          operations of Jet Airways at the earliest.”
     However, the aforesaid Clause 6.4.12 of the Resolution Plan was
     deleted in its entirety and replaced with the following:
[2024] 11 S.C.R.                                                        2123

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

           “6.4.12. Request for the consideration of the CoC - As
          required under the RFRP, the Resolution Applicant shall
          provide the performance security bank guarantee (“PBG”)
          for a total sum of Rs. 150 Crores. The PBG will be provided
          in two parts, with the first PBG of Rs. 47.5 Crores provided
          within 7 (seven) days from the date of receipt of LOI; and
          PBG for the remaining sum of Rs. 102.5 Crores provided
          on the Effective Date.”
     A reading of the amended Clause 6.4.12 of the Resolution Plan
     indicates that the parties had mutually agreed to do away with
     the phrase “which will bring financial flexibility for the Resolution
     Applicant and help the Resolution Applicant advance the committed
     payments and achieve its goal of re-commencing the operations of
     Jet Airways at the earliest”. What can be plainly deduced from such
     a deletion is that the PBG cannot be used by the SRA to advance
     any payments that are required to be paid under the scheme of the
     Resolution Plan. This, additionally, cements the idea that the PBG
     could not be adjusted towards any consideration or payment which
     had to be made by the SRA. Such an amendment in Clause 6.4.12
     only brought the Resolution Plan further in line with the terms of
     the RFRP.
104. An adjustment of the PBG against the first tranche payment would
     also be in violation of Regulation 36B(4A) of the 2016 Regulations
     which was inserted by Notification No. IBBI/2019-20/GN/REG040
     dated 24.01.2019. The same is reproduced hereinbelow:
          “(4A) The request for resolution plans shall require
          the resolution applicant, in case its resolution plan is
          approved under sub-section (4) of section 30, to provide
          a performance security within the time specified therein
          and such performance security shall stand forfeited if the
          resolution applicant of such plan, after its approval by the
          Adjudicating Authority, fails to implement or contributes to
          the failure of implementation of that plan in accordance
          with the terms of the plan and its implementation schedule.
          Explanation I. – For the purposes of this sub-regulation,
          “performance security” shall mean security of such nature,
          value, duration and source, as may be specified in the
          request for resolution plans with the approval of the
2124                                                        [2024] 11 S.C.R.

                          Supreme Court Reports


           committee, having regard to the nature of resolution plan
           and business of the corporate debtor.
           Explanation II. – A performance security may be specified
           in absolute terms such as guarantee from a bank for
           Rs. X for Y years or in relation to one or more variables
           such as the term of the resolution plan, amount payable
           to creditors under the resolution plan, etc.”
                                                   (emphasis supplied)

105. Regulation 36B(4A) states that the performance security shall stand
     forfeited if the resolution applicant fails to implement or contributes to
     the failure of implementation of the plan, in accordance with the terms
     of the Resolution Plan and its implementation Schedule. Therefore,
     the PBG had to be kept alive until the complete implementation of
     the Resolution Plan as per Regulation 36B(4A) as well. This is also
     what is provided under Clauses 3.13.2 and 3.13.8 of the RFRP
     respectively wherein the PBG was required to be kept alive and
     was to be returned to the SRA only upon 100% completion of the
     implementation of the Resolution Plan. This binding nature of the
     RFRP was transferred onto the Resolution Plan through Clauses
     7.3 and 9.4 respectively of the Resolution Plan.
106. The NCLAT in one of its orders i.e., the order dated 26.05.2023, had
     restrained the Appellants from invoking the PBG without the leave of
     the NCLT. While saying so, the following observations were made;
           “19. When the Resolution Plan of the Corporate Debtor
           has received approval up to Hon’ble Supreme Court and
           the Monitoring Committee is constituted under the Plan
           to oversee implementation, the Monitoring Committee
           has to act as a facilitator for implementation of the
           Resolution Plan instead of finding fault and taking steps,
           which does not facilitate the implementation, rather delay
           the implementation. There is no doubt that Performance
           Bank Guarantee can be invoked by the MC Lenders, but
           the said invocation can only take place when SRA has
           failed to implement the Plan. Present is a case where
           directions have been issued to both MC Lenders and
           SRA to implement the Plan and the event of failure of the
           Plan has not yet arrived. When the Adjudicating Authority
[2024] 11 S.C.R.                                                         2125

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          has directed on 13.01.2023 to take steps towards the
          implementation of the Plan and which order was not been
          stayed by this Tribunal on 03.03.2023, the steps ought
          to have been taken by the MC Lenders in furtherance
          of the implementation. The time has not arrived for
          invoking the Performance Bank Guarantee. When the
          SRA is ready to undertake to perform its obligations
          under the Plan, we are of the view that Performance
          Bank Guarantee given by the SRA cannot be permitted
          to the invoked by the MC Lenders. MC Lenders instead
          of threatening to invoke Performance Bank Guarantee,
          should take steps, which may help implementation of the
          Plan and to achieve the objective of Resolution Plan. The
          Resolution Plan has been approved with the intent and
          purpose to revive the Corporate Debtor, which revival
          is in accordance with objective and purpose of the IBC.
          We again reiterate that efforts by MC Lenders and SRA
          should be coordinated for revival of the Corporate Debtor,
          so as to start its operations at an early date, which is in
          the interest of all stake holders as well as in the interest
          of Corporate Debtor.
          20. In view of the aforesaid, we direct that MC Lenders shall
          not invoke the Performance Bank Guarantee in the facts
          of the present case as on date, and for invocation, if any,
          MC Lenders may take leave of the Adjudicating Authority.
          The IA Nos.2159-2160 is disposed of accordingly.”
                                                 (emphasis supplied)

107. A careful reading of the aforesaid order of the NCLAT reflects that
     the NCLAT had itself conceded to the position that the Appellants
     have a right to invoke the PBG in a situation where the SRA had
     failed to implement the Resolution Plan. This is again in line with
     the intention under Regulation 36B(4A). Therefore, even in light of
     the NCLAT’s own order dated 26.05.2023, it does not follow that the
     PBG could have been adjusted by the SRA, mid-implementation,
     against its payment obligation.
108. The NCLAT in its order dated 28.08.2023 dealt with the issue of
     adjustment of PBG against the first tranche payment in light of the
2126                                                     [2024] 11 S.C.R.

                       Supreme Court Reports


    offer made in the Lender’s Affidavit dated 16.08.2023 and made
    certain observations regarding Regulation 36B(4A) of the 2016
    Regulations. The same are as follows:
        “26. When we look to the Regulation 36B (4A) it is clear that
        the provision provides that RFRP shall require Resolution
        Applicant to provide Performance Bank Guarantee within the
        time specified. Sub-Section 4A provides that if Resolution
        Applicant after approval fails to implement Performance
        Security it shall stand forfeited. Present is a case, where
        Performance Security has already been provided in
        compliance of sub- Regulation 4A and present is not a case
        that any power to forfeit the Performance Bank Guarantee
        to be exercised under sub-Regulation (4A). On Explanation
        I, attention of the Court was drawn by Learned Counsel for
        SRA, which indicates that the performance security which
        is contemplated, can be of such nature, value, duration and
        source as may be specified. Thus, Performance Security
        can be of a particular duration and when the Resolution
        Plan provides release of security at the time of first tranche
        of payment of Rs. 350 Crores, no exception can be taken
        to adjustment of the Performance Bank Guarantee. The
        request of SRA to adjust Performance Bank Guarantee
        of Rs. 150 Crores is thus according to Clause 6.4.4 of the
        Resolution Plan on which no exception can be taken.
        27. Submission was made by Learned Sr. Counsel for the
        Appellant that performance Bank Guarantee has to be
        maintained till the completion of the plan. The summary of
        payment and security package as contained in the table
        indicate that there are large numbers of other securities
        which are to be continued. The securities in the last column
        which are mortgaged over three Dubai Properties are to be
        released on year 5 or on complete payment whichever is
        earlier. The plan thus provides for adequate securities to
        ensure the payment hence the adjustment of Performance
        Bank Guarantee in the first tranche of payment cannot be
        said to be against the Resolution Plan. We thus are of the
        view that prayer made by the Applicant in the Application
        in Prayer (a) is to be allowed.”
                                               (emphasis supplied)
[2024] 11 S.C.R.                                                     2127

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

109. A bare perusal of the above observations would indicate that the
     NCLAT proceeded on an incorrect understanding of Regulation
     36B(4A) and its First Explanation. Regulation 36B(4A) does not state
     that if the Resolution Applicant, after approval, fails to implement
     the PBG, then it shall stand forfeited. Instead, what the Regulation
     actually states is that the performance security shall stand forfeited,
     if the resolution applicant of such a plan, after its approval by the
     Adjudicating Authority, “fails to implement or contributes to the
     failure of implementation of that plan in accordance with the terms
     of the plan and its implementation schedule”. It is not the failure to
     implement the performance security i.e., the PBG, that is dealt with
     in this Regulation but the consequence of the failure to implement
     “the Plan” by the SRA.
110. Further the order dated 28.08.2023 proceeds to interpret Explanation I
     to Regulation 36B(4A) and states that since according to Explanation
     I, the performance security can be of a particular duration, the
     Resolution Plan can provide for the release of security at the time of
     the first tranche payment of Rs. 350 Crore and no exception can be
     taken to the adjustment of the PBG. However, what the NCLAT failed
     to take notice of is that under Explanation I to Regulation 36B(4A),
     the performance security shall mean security of such nature, value,
     duration and source, as may be specified “in the request for resolution
     plans”. The duration of the performance security that has been
     specified in the RFRP is given under Clauses 3.13.2 and 3.13.8 of
     the RFRP which categorically states that the PBG shall be kept alive
     until the Resolution Plan has been completely implemented. This is the
     duration which is referred to in Explanation I to Regulation 36B(4A).
111. Now, if the intention under the RFRP, the Resolution Plan (under
     Clauses 7.3 and 9.4) and Regulation 36B(4A) was that the PBG
     had to be kept alive till the completion of implementation of the
     Resolution Plan by the SRA and that it cannot be set-off against
     any payment obligation, then how do we reconcile such an intention
     with the expression “PBG adjusted” mentioned under Clause 6.4.4
     of the Resolution Plan? As mentioned above, Clauses 7.3 and 9.4
     respectively of the Resolution Plan incorporated the terms of the
     RFRP into the Resolution Plan. Clause 3.13.9 of the RFRP states that
     the PBG shall not be set off against any payment or consideration
     which is to be made by the SRA, even if expressly provided so
     under the Resolution Plan. Clause 6.4.4 is quite ambiguous in
2128                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


     its construction regarding the question whether the PBG can be
     specifically adjusted against the first tranche payment. Although in
     the Summary of Payments and Security Package, under the column
     titled “Date of release of security”, the expression “PBG adjusted”
     exists, yet Clause 6.4.4(a)(i) which furnishes some additional clarity
     on the Summary of Payments and Security Package provides no
     mention of the PBG under the heading “Date of release of Security”,
     while the other two forms of security i.e., the BKC property and Dubai
     property No.1 are mentioned. The argument of the counsel for the
     Respondent is that this omission indicates that the PBG would be
     adjusted under the first tranche payment. However, in our considered
     opinion irrespective of whether Clause 6.4.4 expressly or impliedly
     provided for the PBG to be adjusted, such a provision would create
     a dissonance with Clause 3.13.9 of the RFRP which has also been
     made binding on the SRA through Clauses 7.3 and 9.4 respectively
     of the Resolution Plan. Therefore, such an adjustment should not
     be allowed in the facts of the present case.

     II.   The Lender’s Affidavit dated 16.08.2023 did not impose
           conditions which were different from the terms of the
           Resolution Plan.
112. It is the case of the Appellants that Serial No.11 under Clause 7.7.1
     read with Clause 6.1.3(g) evidences that the SRA had to infuse Rs.
     350 Crore “in cash” and it was for this reason alone that Para 8(a) of
     the Lender’s Affidavit required the infusion of Rs. 350 Crore to be done
     in cash by 31.08.2023. It was submitted that such a requirement for
     cash payment flowed directly from the Resolution Plan under which
     an adjustment of the PBG was impermissible and not just out of the
     Lender’s Affidavit dated 16.08.2023. This is because the Lender’s
     Affidavit has not and cannot impose any condition over and above
     the one laid under the Resolution Plan.
113. On the other hand, the Respondents vehemently submitted that it
     was only the Lender’s Affidavit dated 16.08.2023 which stipulated
     the condition that Rs. 350 Crore had to be infused in cash by
     31.08.2023, while the Resolution Plan, under Clause 6.4.4 allowed
     for the payment of Rs. 200 Crore in cash and Rs. 150 Crore through
     adjusting the PBG. In other words, they argued that the conditions
     envisaged in the Lender’s Affidavit were different from those stipulated
     in the Resolution Plan.
[2024] 11 S.C.R.                                                         2129

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

114. However, the intent of the legislature is very clear on the aspect that
     once a Resolution Plan is approved by the Adjudicating Authority
     i.e., the NCLT, it becomes binding on all the stakeholders involved in
     the Resolution Plan. Section 31(1) of the IBC, 2016 reads as thus:
          “31. (1) If the Adjudicating Authority is satisfied that
          the resolution plan as approved by the committee of
          creditors under sub-section (4) of section 30 meets the
          requirements as referred to in sub-section (2) of section
          30, it shall by order approve the resolution plan which shall
          be binding on the corporate debtor and its employees,
          members, creditors,[including the Central Government,
          any State Government or any local authority to whom
          a debt in respect of the payment of dues arising under
          any law for the time being in force, such as authorities
          to whom statutory dues are owed,] guarantors and other
          stakeholders involved in the resolution plan.”
                                                 (emphasis supplied)

115. This Court in Ebix Singapore Private Limited v. Committee Of
     Creditors of Educomp Solutions Limited and Another reported
     in (2022) 2 SCC 401 was faced with the issue whether withdrawals
     or modifications by successful resolution applicants were permissible
     under the IBC, 2016 i.e., whether a resolution applicant is entitled to
     withdraw or modify its Resolution Plan, once it has been submitted
     by the Resolution Professional to the Adjudicating Authority and
     before it is approved by such authority under Section 31(1) of the
     IBC, 2016. It was unequivocally held that, based on the plain terms
     of the IBC, 2016, the Adjudicating Authority lacks the power to allow
     the withdrawal or modification of the Resolution Plan by a successful
     resolution applicant or to give effect to any such clauses in the
     Resolution Plan. The relevant observations made are reproduced
     hereinbelow:
          “164. The approval of the adjudicating authority under
          Section 31(1) IBC has the effect of making the resolution
          plan binding on all stakeholders. These stakeholders
          include the employees of the corporate debtor whose terms
          of employment would be governed by the resolution plan,
          the Central and State Governments who would receive
2130                                                      [2024] 11 S.C.R.

                       Supreme Court Reports


        their tax dues on the basis of the terms of the resolution
        plan and local authorities to whom dues are owed. These
        stakeholders are not direct participants in the CIRP but
        are bound by its consequence by virtue of the approval
        of the resolution plan, under Section 31(1) IBC. Section
        31(1) ensures that the resolution plan becomes binding
        on all stakeholders after it is approved by the adjudicating
        authority. The language of Section 31(1) cannot be
        construed to mean that a resolution plan is indeterminate
        or open to withdrawal or modification until it is approved
        by the adjudicating authority or that it is not binding
        between the CoC and the successful resolution applicant.
        Regulation 39(4) of the CIRP Regulations mandates that
        the RP should endeavor to submit the plan at least fifteen
        days before the statutory period of the CIRP under Section
        12 is due to expire along with a receipt of a PBG and a
        compliance certificate as Form H. It is pertinent to note
        that sub-section (3) to Section 12 mandates that the CIRP
        process, including legal proceedings, must be concluded
        within 330 days. This three-hundred-and-thirty-day period
        can be extended only in exceptional circumstances, if the
        process is at near conclusion and serves the object of IBC,
        as held by a three-Judge Bench of this Court in Essar
        Steel [Essar Steel (India) Ltd. (CoC) v. Satish Kumar Gupta,
        (2020) 8 SCC 531 : (2021) 2 SCC (Civ) 443]. Therefore,
        after accounting for all statutorily envisaged delays which
        the RP has to explain in its Form H and otherwise through
        Regulation 40-B, the procedure envisages a fifteen-day
        window between submission of resolution plan and its
        approval or rejection by the adjudicating authority. This
        clearly indicates that the statute envisages a certain level of
        finality before the resolution plan is submitted for approval
        to the adjudicating authority. Even the CoC is not permitted
        to approve multiple resolution plans or solicit EoIs after
        submission of a resolution plan to the adjudicating authority,
        which would possibly be in contemplation if the resolution
        applicant was permitted to withdraw from, or modify, the
        plan after acceptance by the CoC. Regulation 36-B(4-A)
        requires the furnishing of a performance security which
[2024] 11 S.C.R.                                                          2131

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          will be forfeited if a resolution applicant fails to implement
          the plan. This is collected before the adjudicating authority
          approves the plan. Notably, the Regulations also direct
          forfeiture of the performance security in case the resolution
          applicant “contributes to the failure of implementation”,
          which could potentially include any attempts at withdrawal
          of the plan.
                     xxx               xxx                 xxx
          172. Based on the plain terms of the statute, the adjudicating
          authority lacks the authority to allow the withdrawal
          or modification of the resolution plan by a successful
          resolution applicant or to give effect to any such clauses in
          the resolution plan. Unlike Section 18(3)(b) of the erstwhile
          SICA which vested the Board for Industrial and Financial
          Reconstruction with the power to make modifications to a
          draft scheme for sick industrial companies, the adjudicating
          authority under Section 31(2) IBC can only examine the
          validity of the plan on the anvil of the grounds stipulated
          in Section 30(2) and either approve or reject the plan. The
          adjudicating authority cannot compel a CoC to negotiate
          further with a successful resolution applicant. A rejection
          by the adjudicating authority is followed by a direction of
          mandatory liquidation under Section 33. Section 30(2) does
          not envisage setting aside of the resolution plan because
          the resolution applicant is unwilling to execute it, based
          on terms of its own resolution plan.
                     xxx               xxx                 xxx
          222. If the legislature in its wisdom, were to recognise the
          concept of withdrawals or modifications to a resolution plan
          after it has been submitted to the adjudicating authority, it
          must specifically provide for a tether under IBC and/or the
          Regulations. This tether must be coupled with directions
          on narrowly defined grounds on which such actions are
          permissible and procedural directions, which may include
          the timelines in which they can be proposed, voting
          requirements and threshold for approval by the CoC (as
          the case may be). They must also contemplate at which
          stage the corporate debtor may be sent into liquidation
2132                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


          by the adjudicating authority or otherwise, in the event
          of a failed negotiation for modification and/or withdrawal.
          These are matters for legislative policy.
          223. In the present framework, even if an impermissible
          understanding of equity is imported through the route
          of residual powers or the terms of the resolution plan
          are interpreted in a manner that enables the appellants›
          desired course of action, it is wholly unclear on whether
          a withdrawal of a CoC-approved resolution plan at a
          later stage of the process would result in the adjudicating
          authority directing mandatory liquidation of the corporate
          debtor. Pertinently, this direction has been otherwise
          provided in Section 33(1)(b) IBC when an adjudicating
          authority rejects a resolution plan under Section 31. In this
          context, we hold that the existing insolvency framework in
          India provides no scope for effecting further modifications
          or withdrawals of CoC-approved resolution plans, at the
          behest of the successful resolution applicant, once the
          plan has been submitted to the adjudicating authority. A
          resolution applicant, after obtaining the financial information
          of the corporate debtor through the informational utilities
          and perusing the IM, is assumed to have analysed the
          risks in the business of the corporate debtor and submitted
          a considered proposal. A submitted resolution plan is
          binding and irrevocable as between the CoC and the
          successful resolution applicant in terms of the provisions
          of IBC and the CIRP Regulations. In the case of Kundan
          Care, since both, the resolution applicant and the CoC,
          have requested for modification of the resolution plan
          because of the uncertainty over the PPA, cleared by the
          ruling of this Court in Gujarat Urja [Gujarat Urja Vikas
          Nigam Ltd. v. Amit Gupta, (2021) 7 SCC 209 : (2021) 4
          SCC (Civ) 1] , a one-time relief under Article 142 of the
          Constitution is provided with the conditions prescribed in
          Section K.2.”
                                                  (emphasis supplied)

116. In light of the aforesaid, it is clear that the existing insolvency
     framework does not provide any scope for effecting further
[2024] 11 S.C.R.                                                     2133

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     modifications or withdrawals of the Resolution Plan approved by the
     CoC, at the behest of the successful resolution applicant, once the
     plan has been submitted to the adjudicating authority. The submitted
     Resolution Plan is binding and irrevocable as between the CoC and
     the successful resolution applicant in terms of the provisions of the
     IBC, 2016 and the 2016 Regulations as well. In other words, once
     a CoC-approved resolution plan is submitted to the Adjudicating
     Authority i.e., NCLT, it immediately becomes binding on the CoC
     and the SRA, even if the Adjudicating Authority has not yet given
     its stamp of approval on the same. While deciding so, this Court
     re-emphasized the object under Section 31(1) of the IBC, 2016 and
     observed that once the Adjudicating Authority has approved the
     plan under Section 31(1) of the IBC, 2016, the Resolution Plan is
     binding on all the stakeholders including those stakeholders who are
     not direct participants of the CIRP. Therefore, there is absolutely no
     scope for modification of the terms of a Resolution Plan which has
     received the imprimatur of the Adjudicating Authority, be it by the
     Adjudicating Authority itself, the CoC or the SRA.
117. When the aforesaid is the position of law, and the NCLT had
     approved the present Resolution Plan vide order dated 22.06.2021,
     the Resolution Plan was immune to any modification or alteration
     whatsoever. Therefore, the Appellants could have only proposed an
     offer under the Lender’s Affidavit dated 16.08.2023 which stood true
     to the terms of the Resolution Plan approved by the NCLT. They could
     not have created any deviations, alterations or modifications of the
     terms of the Resolution Plan. It is in this context that the submission
     of the SRA that, the Lender’s Affidavit required an infusion of Rs. 350
     Crore in cash, while the Resolution Plan allowed for the payment
     of Rs. 200 Crore in cash and Rs. 150 Crore through adjustment
     of the PBG, must be rejected. Both the Resolution Plan and the
     Lender’s Affidavit dated 16.08.2023 reflected the same terms i.e.,
     infusion “in cash” of the first tranche payment of Rs. 350 Crore. In
     fact, even the date within which the Lender’s Affidavit required Rs.
     350 Crore to be infused in cash i.e., 31.08.2023 was in compliance
     with the order dated 26.05.2023 passed by the NCLAT granting the
     2nd Implementation Extension. Therefore, no new terms were cast
     on the SRA.
118. The fact that the Lender’s Affidavit did not impose any condition
     which was different from that contemplated under the Resolution
2134                                                      [2024] 11 S.C.R.

                         Supreme Court Reports


    Plan, was also understood by all the parties involved, including
    the SRA. This is evident from the arguments put forth by the SRA,
    before the NCLAT and before this Court respectively, which dealt
    with the issue of whether the adjustment of the PBG was possible
    under the terms of the Lender’s Affidavit. The following were the
    submissions made by the SRA in the order dated 28.08.2023 as
    recorded by the NCLAT:
         “20. Learned Sr. Counsel for the SRA has submitted
         that approved Resolution Plan provides adjustment of
         Performance Bank Guarantee towards first tranche of
         payment whereas Learned Counsel for the Appellants has
         referred to certain clauses of RFRP and also provisions
         of Regulation 36B (4A) to support his submission that
         performance bank guarantee cannot be permitted to be
         invoked towards payment of first tranche.”
                                                 (emphasis supplied)

119. The submissions made by the SRA as recorded in the order of this
     Court dated 18.01.2024 are as follows:
         “18. The submission which has been urged on behalf of
         the lenders has been opposed on behalf of the SRA by
         Mr. Krishnendu Datta, senior counsel, on behalf of the
         SRA, it has been submitted that:
         (i)    The Resolution Plan specifically contemplates the
                adjustment of the PBG (originally of Rs. 47.5 crores,
                subsequently enhanced to Rs. 150 crores). In support
                of this submission, reliance has been placed on the
                summary of payments and security package forming
                a part of clause 6.4.4 of the Resolution Plan;
         (ii)   The SRA was in the first tranche required to pay an
                amount of up to Rs. 185 crores against the creation
                of securities, namely, (i) PBG of Rs. 47.5 crores;
                (ii) BKC Property (if given); and (iii) Mortgage over
                Dubai Property No 1 valued at over Rs. 100 crores.
                In the last column of the table, it has been stipulated
                that the securities would be released, as indicated;
         (iii) The PBG was liable to be adjusted against the cash
               payment of the first tranche of Rs. 185 crores;
[2024] 11 S.C.R.                                                        2135

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          (iv) No specific date for the release of the security in
               relation to the PBG has been mentioned;
          (v)   Moreover, in respect of the second tranche comprising
                of Rs. 195 crores, there was no requirement to furnish
                any security in the form of a PBG;
          (vi) The securities, in other words, were of a revolving
               nature, but significantly on the release of the PBG
               against a cash payment of Rs. 185 crores, the PBG
               is not required to be renewed as a fresh security for
               the following tranches; and …”
                                                (emphasis supplied)

120. A perusal of the abovementioned would indicate that both the
     parties as well as the NCLAT were ad idem on the fact that the
     terms imposed by the Lender’s Affidavit dated 16.08.2023 were
     in pursuance of and similar to the terms of the Resolution Plan.
     This is because, in order to take benefit of the offer made in the
     Lender’s Affidavit, the SRA had repeatedly asserted that the PBG
     should be allowed to be adjusted under the terms of the Resolution
     Plan and as a consequence, such an adjustment must be allowed
     under the Lender’s Affidavit as well. Even the NCLAT in its order
     dated 28.08.2023 had held that the SRA could adjust the PBG of
     Rs. 150 Crore to take benefit of the offer of the Lender’s Affidavit
     by relying on Clause 6.4.4 of the Resolution Plan which provided
     for the summary of payments and security package.
121. Therefore, in our view the conditions imposed on the SRA under the
     Lender’s Affidavit and the Resolution Plan were one and the same,
     the only difference being that the Appellants had offered not to press
     issues relating to the compliance of the Conditions Precedent and
     grant of extensions/exclusions along with offering to withdraw the
     Company Appeal and the Appeals pending before this Court.
122. The order of this Court dated 18.01.2024 must be seen & understood
     in the aforesaid background. While the appeal before us had resulted
     from several interim orders of the NCLAT, the question before us
     was whether the adjustment of the PBG of Rs. 150 Crore was
     permissible under the Lender’s Affidavit as well as the terms of the
     Resolution Plan, being one and the same. We interpreted the term
2136                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


     “infuse” as mentioned in the affidavit and under the Resolution Plan,
     and arrived at the conclusion that it demonstrably meant “payment
     in cash”. Therefore, the directions that were issued by this Court,
     especially the direction that - “the SRA shall peremptorily on or
     before 31 January 2024, deposit an amount of Rs. 150 crores into
     the designated account of SBI, failing which the consequences under
     the Resolution Plan shall follow”, must have been necessarily seen
     in the context of the Resolution Plan as well. The phrase “failing
     which the consequences under the Resolution Plan shall follow” was
     a mandatory direction that should have been taken into account by
     the NCLAT in its impugned order dated 12.03.2024. There was no
     escape for the NCLAT in this regard. There was no option which
     was given to the SRA to deviate from this direction which purely
     stemmed from the Resolution Plan. The fact that this direction was
     binding was clearly understood by the SRA since it attempted to file
     another Miscellaneous Application before this Court requesting for
     an extension to comply with our order dated 18.01.2024 which was
     dismissed as misconceived.
123. There were two other directions which were issued by us in our
     order dated 18.01.2024 i.e., (ii) that the PBG of Rs. 150 Crore shall
     continue to remain in operation and effect pending the final disposal
     of the appeal before the NCLAT, and shall abide by the final outcome
     of the appeal and the directions that may be issued by the NCLAT;
     and (iii) whether or not the SRA has been compliant with all the
     conditions of the Resolution Plan as well as of the conditions set out
     in paragraph 8 of the affidavit dated 16 August 2023 shall be decided
     by the NCLAT in the pending appeal. These two directions must
     not be seen as giving any leeway to the NCLAT to act in complete
     ignorance or defiance of the first direction that was issued by us. Such
     a selective compliance with our order dated 18.01.2024 deserves
     to be nipped in the bud more particularly when it was mandated
     that our directions be considered and complied with in its entirety.
     Therefore, the NCLAT, while finally deciding the pending Company
     Appeal on merits which led to the impugned order dated 12.03.2024
     has, either by design or unknowingly, ignored the directions issued
     by this Court vide order dated 18.01.2024 that the remaining amount
     of Rs. 150 Crore had to be necessarily deposited in cash only. This
     has resulted in a perverse decision which stands contrary to law
     and to the terms of the Resolution Plan itself.
[2024] 11 S.C.R.                                                        2137

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

124. In view of our crystal clear order dated 18.01.2024, we are of the
     opinion that the PBG of Rs. 150 Crore could not have been allowed
     to be adjusted with the first tranche payment of Rs. 350 Crore.
     Non-compliance of the SRA with the order of this Court has led to
     a dereliction of its obligations to implement the Resolution Plan.

     ii.   Whether the non-implementation of the Resolution Plan by
           the SRA necessarily leads to the consequence of liquidation
           as under Section 33(3) of the IBC, 2016?
125. In the foregoing paragraphs, we have reached the conclusion that
     the SRA failed to implement the Resolution Plan by not infusing
     the first tranche payment of Rs. 350 Crore in cash, as required by
     Clause 6.3.1(g) and the Implementation Schedule under Clause
     7.7 of the Resolution Plan. It is now to be seen if this has resulted
     in the contravention of other terms of the Resolution Plan as well.

     a.    Whether Respondent No.1/SRA had failed to implement
           the Resolution Plan on non-payment of the Airport Dues
           as per the terms of the Resolution Plan?
126. With respect to the Airport dues, the impugned order of the NCLAT
     had taken into consideration Clauses 6.4.1(e), 6.4.1(h) and 6.4.1(m)
     respectively. Specifically dealing with Clause 6.4.1(h), it said that this
     provision dealt with the treatment of outstanding CIRP costs which
     included parking charge i.e., Airport Charges. While considering so,
     the following observations were made:
           “54. The provisions of Resolution Plan as noted above
           clearly indicates that CIRP costs includes Airport Charges.
           SRA is also entitled to use funds available with the
           Corporate Debtor as on effective date to meet any portion
           of CIRP costs. The submission of the Appellants that the
           entire Airport Charges have to be borne by the SRA upfront
           cannot be accepted nor non-payment of Airport Charges by
           SRA as on date makes the allotment of slot unavailable to
           the SRA. Allotment of slot having been achieved by the SRA
           as noted above, non-payment of airport charges upfront
           by SRA cannot be said to be a reason to not accept the
           fulfillment of condition of slot allotment. The payment of
           Airport Charges has to be made as per the Resolution Plan
2138                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


          when the implementation of the plans commences as per
          the Resolution Plan. We thus do not find any substance in
          the submission of Learned Counsel for the Appellant that
          allotment of slot is not completed since airport charges
          have not been paid by the SRA.
          55. With regard to submission of the Appellant that old
          dues of Airport Charges having not been settled, the
          Adjudicating Authority has rightly observed that settling
          old dues cannot be conceded as non-allotment of slots.
          We thus fully concur with the finding of the Adjudicating
          Authority that conditions precedent under Clause 7.6.1(c)
          were fulfilled.”
                                                 (emphasis supplied).

127. The case of the Appellants is that upon consideration of Clause
     6.4.1(h), the NCLAT erroneously concluded that the Airport Charges
     would be a part of the CIRP costs. Clause 6.4.1(h) of the Resolution
     Plan is reproduced hereinbelow:
          “(h) Based on the information provided, the Resolution
          Applicant have assumed that the amounts standing to
          the credit of the bank account of the Corporate Debtor
          (including amounts estimated to be received subsequently)
          are sufficient to cover for the CIRP Costs of the Corporate
          Debtor (excluding parking charges, rental charges,
          employee dues, taxes etc). Accordingly, the Resolution
          Applicant has set aside a sum of Rs. 25 Crores as CIRP
          Costs towards payment of any such costs until the Approval
          Date. Any expenses incurred by the Corporate Debtor from
          the Approval Date until the Effective Date will be incurred
          out of the positive bank balance of the Corporate Debtor.”
                                                 (emphasis supplied)

128. A plain reading of Clause 6.4.1(h) reveals that the amount standing
     to the credit of the bank account of the Corporate Debtor would be
     sufficient to cover the CIRP costs of the Corporate Debtor but that this
     would exclude the parking charges, rental charges, employee dues,
     taxes etc. Therefore, the clause does not expressly exclude Airport
     Charges from the ambit of CIRP costs entirely but only states that
[2024] 11 S.C.R.                                                       2139

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     the amount available in the bank account of the Corporate Debtor
     would be insufficient to cover the parking charges, rental charges etc
     which also form a part of the CIRP costs. Since such a bank balance
     would not cover the parking charge, rental charges, employee dues,
     taxes etc, the Resolution Plan had set apart a separate sum of Rs.
     25 Crore for the payment of any such CIRP costs which might have
     accrued till the Approval Date. Further, the other expenses including
     parking charges, rental charges etc. which have been incurred post
     the Approval Date but within the Effective Date i.e., the period during
     which the Conditions Precedent would be fulfilled, would also be
     incurred out of the positive bank balance of the Corporate Debtor.
     This is what Clause 6.4.1(h) provides for. To hold that Clause 6.4.1(h)
     excludes airport dues from the scope of CIRP costs altogether would
     also question the placement of clauses such as Clauses 6.4.1(f)
     (which provides for an estimate of Rs. 240 Crore towards parking
     charges) under the larger umbrella of Clause 6.4.1 which deals with
     the “Treatment of Outstanding CIRP Costs” in totality.
129. Therefore, what the Resolution Plan contemplates is that the Airport
     Charges be subsumed within the CIRP Dues and since all of the
     different CIRP dues cannot be satisfied through the bank balance
     which stands to the credit of the Corporate Debtor, a separate
     sum of Rs. 25 Crore was demarcated towards the remaining CIRP
     payments. Hence, the NCLAT was right in arriving at the conclusion
     that Airport Dues were indeed a part of the CIRP costs.
130. It must further be noted that, the impugned order of the NCLAT
     nowhere caps the Airport Dues to a maximum of Rs. 25 Crore.
     Moreover, such a mention of Rs. 25 Crore is plainly absent in its
     observations regarding Airport Dues. All that is mentioned is that “The
     payment of Airport Charges has to be made as per the Resolution
     Plan when the implementation of the plan commences as per the
     Resolution Plan”. It is in this regard that Clause 6.4.1(j) provides that
     if the CIRP costs exceed the current estimates, then they will be paid
     as per “actuals” in compliance with the provisions of the IBC and as
     a consequence, the pay-outs towards the other creditors would be
     reduced proportionately to account for such additional CIRP costs.
     This would be subject to a minimum payment of liquidation value
     to the Operational Creditors and Dissenting Financial Creditors of
     the Corporate Debtor and subject to a maximum of Rs. 475 Crore.
     Therefore, the Resolution Plan, too, does not contemplate the CIRP
2140                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


     costs to be strictly subject to a maximum of Rs. 25 Crore. To accept
     such a contention of the Appellants would be to misinterpret the
     observations made in the impugned order.
131. The Appellants rely on Clause 6.3.1(d), specifically under the heading
     “BKC Property not part of Resolution” to assert that the Airport Dues
     have to be settled upfront and in full in the first 180 days from the
     Effective Date and that it cannot be in staggered payments spread
     across a period of time. However, Clause 6.3.1(d) which is titled
     “Proposal for Resolution of Outstanding Airport and Parking Dues
     (Rs. 240 Crores as of August 31, 2020” is attached with the following
     qualification:
          “The Resolution Applicant states and confirms that this
          “Proposal for Resolution of outstanding airport and parking
          dues (approx. Rs. 240 Crores as of August 31,2020)” which
          deals with the appropriation of the BKC Property is merely
          a proposal and not a condition to the implementation of this
          Resolution Plan and the CoC has the discretion to accept/
          reject such a proposal. If the above-mentioned proposal
          is acceptable to the CoC, then it is acceptable to the
          Resolution Applicant in the manner stated hereinabove”.
                                                 (emphasis supplied)

     The contention of the SRA is that the aforesaid qualification applies
     equally to the part of Clause 6.3.1(d) under the heading “BKC Property
     not part of resolution” and that the entire Clause 6.3.1(d) would remain
     a proposal and not a binding condition on the SRA. Irrespective of a
     determination on the same, even as per Clause 6.4.1, the payment
     towards CIRP costs including Airport Charges had to be made in full,
     in priority, within 180 days from the Effective Date. This is evident
     from – (a) Clause 6.4.1(a) which states that the CIRP Costs are to
     be paid in priority to any other creditor of the Corporate Debtor in
     terms of Section 30(2)(a) of the IBC, 2016; (b) Clause 6.4.1(k) which
     states that the outstanding CIRP costs shall be paid by the Resolution
     Applicant out of the funds infused by the Resolution Applicant in
     the Corporate Debtor and as per the Implementation Schedule set
     out in Clause 7.7 below; (c) Clause 6.4.1(m) which states that the
     CIRP cost shall be “fully paid and discharged after the Effective
     Date” before payment is made to any of the creditors as per the
[2024] 11 S.C.R.                                                     2141

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     Resolution Plan; (d) Clause 6.4.1(n) which states that the Resolution
     Applicant has sufficient funds and that the CIRP costs shall be met
     out of funds infused by the Resolution Applicant; and (e) S.No. 16
     of the Implementation Schedule under Clause 7.7 which states that
     the CIRP costs must be paid as per Clause 6.4.1 within Z+170 days.
132. Therefore, the SRA not having infused the first tranche payment of Rs.
     350 Crore as per Clause 6.3.1(g) and S. No. 11 of the Implementation
     Schedule under Clause 7.7 within a period of 180 days from the
     Effective Date and within the multiple extensions granted therefrom,
     has defaulted on its obligation towards the payment of CIRP costs
     (which include airport dues) under Clause 6.4.1 as well.

     b.   Whether Respondent No.1/SRA could be said to have
          failed to implement the Resolution Plan on account of the
          non-payment of workmen and employees’ dues as per the
          terms of the Resolution Plan and the order of the NCLT
          dated 21.10.2022 which was confirmed by the order dated
          31.01.2023 of this Court?
133. The Resolution Plan, under Clause 6.4.2 deals with the “Treatment
     of Employees/Workmen dues, including dues of the Authorized
     Representatives of Employees/Workmen”. Clause 6.4.2(a) provides
     for a fixed sum of Rs. 52 Crore to be paid to the workmen and
     employees towards settlement of all their claims. Clause 6.4.2(b)
     states that this payment shall be made out of the funds infused by
     the SRA in the Corporate Debtor, in priority to the payment to the
     financial creditors and as per the Implementation Schedule set out
     in Clause 7.7 i.e., within 175 days from the Effective Date. Clause
     6.4.2(c) provides that if the Liquidation Value due to the workmen and
     employees is not “nil”, then the SRA would pay such a Liquidation
     Value. If this Liquidation Value is over and above the amount proposed
     to be paid under the Resolution Plan, then such additional amounts
     shall be first paid out of the positive bank balance of the Corporate
     Debtor as on the Effective Date and the remaining amounts shall be
     paid out of the amounts reserved for other creditors on a pro rata
     basis, subject to a maximum of Rs. 475 Crore.
134. The order dated 21.10.2022 of the NCLAT dealt with the entitlements
     of the workmen and employees to several payments and made the
     following observations:
2142                                                      [2024] 11 S.C.R.

                       Supreme Court Reports


        “71. In view of the aforesaid discussion, we arrive at
        following conclusions:
        (i) The workmen and employees are entitled for payment
        of full amount of provident fund and gratuity till the date of
        commencement of the insolvency which amount is to be
        paid by the Successful Resolution Applicant consequent
        to approval of the Resolution Plan in addition to the 24
        months workmen dues as the workmen is entitled to
        under Section 53(1)(b) of the Code. It is made clear that
        in addition to part amount of provident fund and gratuity
        as proposed in Resolution Plan to workmen, Successful
        Resolution Applicant is obliged to make payment of balance
        unpaid amount of provident fund and gratuity to workmen
        and employees.
        72. Our answer to Question II and III is as follows:
        (i) The workmen and employees are entitled to receive the
        amount of provident fund and gratuity in full since they are
        not part of the liquidation estate under Section 36(4)(b)(iii).
        (ii) The workmen are entitled to receive their dues from the
        Corporate Debtor for period of 24 months as per provision
        of Section 53(1)(b) at least to minimum liquidation value
        envisaged under Section 32(2)(b) read with Section 53(1).
        80. As observed above, in admitted claim of workmen
        provident fund, gratuity and leave encashment was
        included, and payment proposed in plan partly satisfy
        above dues also. The workmen are entitled to full payment
        of provident fund and gratuity, hence, the balance of
        above dues are to be paid by the Successful Resolution
        Applicant, to satisfy statutory obligations. Non-payment
        of full provident fund and gratuity shall lead to violation
        of Section 30(2)(e), hence, to save the plan the above
        payments have to be made.

        xxx                          xxx                           xxx
        128. In the forgoing discussions, we have noted that the
        liquidation value of the workmen as has been referred to in
        Form-H preferred by the Resolution Professional is Rs.113
[2024] 11 S.C.R.                                                          2143

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          crores and workmen were entitled to receive at least Rs.113
          crores as per Section 30(2)(b) read with Section 53(1)(b)
          of the Code. Shri Krishnendu Datta, learned Counsel for
          Successful Resolution Applicant during his submission,
          submitted that Successful Resolution Applicant shall be
          paying an amount of Rs.113 crores to the workmen as
          per the Resolution Plan, since it was contemplated that, if
          liquidation value is more than Rs.52 crores, the liquidation
          value shall be payable to the workmen. To clear any doubt,
          we deem it fit and proper to issue direction to Successful
          Resolution Applicant to make payment to the workmen of
          Rs.113 crores as per the Resolution Plan.

           xxx                         xxx                          xxx
          134. In result, the Appeal(s) are decided in following
          manner:
          (I) The Appeal(s) of workmen and employees being
          Company Appeal (AT) (Insolvency) Nos. 643 of 2021, 752
          of 2021, 801 of 2021, 915 of 2021, 771 of 2022 are partly
          allowed with following directions:
          (a) Successful Resolution Applicant is directed to make
          payment of unpaid provident fund to the workmen till date
          of insolvency commencement, after deducting the amount
          already paid towards provident fund in the Resolution Plan
          to the workmen.
          (b) The workmen are also entitled for payment of their
          gratuity dues as on insolvency commencement date,
          after adjusting any amount towards gratuity paid under
          the Resolution Plan.
          It is made clear that entitlement of those employees and
          workmen, who were demerged into AGSL shall not be
          there, since demerger has not been treated as termination
          of their services.
          (c) The employees are also entitled for the payment of
          their full provident fund, unpaid up to the date of insolvency
          commencement date. It is made clear that full payment of
          provident fund would be of that unpaid part of provident
2144                                                     [2024] 11 S.C.R.

                        Supreme Court Reports


          fund, which has not been deposited by the Corporate
          Debtor in the EPFO.
          (d) Employees shall also be entitled for the gratuity, which
          fell due up to insolvency commencement date.
          (e) The rest of the prayers of the workmen and employees
          are denied.
          (f) The Chairman of the Monitoring Committee, erstwhile
          Resolution Professional is directed to compute the
          payments to be made to workmen and employees within
          one month from today and communicate the same to the
          Successful Resolution Applicant to take steps for payment.”
                                                (emphasis supplied)

135. Thus, it was held in clear terms that the workmen and employees
     are entitled to full payment of Provident Fund and Gratuity. The non-
     payment of these amounts shall lead to a violation of Section 30(2)
     (e) of the IBC, 2016 which requires that the Resolution Plan must
     not contravene any of the provisions of the law for the time being
     in force. Further, it was held that the workmen and employees are
     entitled to a liquidation value of Rs. 113 Crore instead of Rs. 52
     Crore as contemplated in the Resolution Plan. The NCLAT directed
     the Chairman of the Monitoring Committee (the erstwhile Resolution
     Professional) to compute the payments to be made to the workmen
     and employees within one month and to communicate the same to
     the SRA. The RP had arrived at a figure of Rs. 226.6 Crore which
     comprised of Rs. 14 Crore towards Provident Fund dues, Rs. 188.2
     Crore towards Gratuity dues and Rs. 24.4 Crore towards damages
     for non-payment of Provident Fund.
136. The SRA sought a clarification of the aforesaid order before the
     NCLAT and vide order dated 02.12.2022, it was made clear that
     the cost of paying the unpaid amount towards the Provident Fund
     and Gratuity to the workmen and employees has to be borne by
     the SRA. The same cannot be paid out of the amounts reserved
     for the other creditors of the Corporate Debtor on a pro-rata basis
     subject to a maximum of Rs. 475 Crore as stated in Clause 6.4.2(e)
     of the Resolution Plan since that was a contemplation pertaining to
     the liquidation value only and not for the dues relating to Provident
[2024] 11 S.C.R.                                                    2145

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     Fund and Gratuity. An appeal against the order dated 21.10.2022
     was dismissed by this Court vide order dated 30.01.2023. Therefore,
     there was no scope left for the SRA to avoid payment of the Provident
     Fund and Gratuity dues to the workmen and employees. Such an
     obligation was in addition to the payment of minimum liquidation
     value that the workmen/employees were entitled to under the terms
     of the Resolution Plan.
137. The SRA had filed IA Nos. 3789-3790 of 2023 in the Company Appeal
     on 16.06.2023 praying that the Gratuity Claims be allowed to be
     paid in three tranches i.e., within 3, 4 and 5 years from the Closing
     Date. The SRA also sought leave from the NCLAT to approach
     the EPFO Authorities under Section 14B to seek a reduction or
     waiver of the damages of Rs. 24.4 crore imposed on the Corporate
     Debtor and to also pursue an appeal against the order of the EPFO
     Authorities directing the SRA to pay the damages. Subsequently,
     on 18.08.2023, the SRA filed two other IAs 3801-3802 of 2023 in
     the Company Appeal, praying that, in case the previous IA relating
     to the Gratuity and Provident Fund Claims is not allowed, then the
     Resolution Plan cannot be implemented under Section 30(2)(e) and
     as a consequence, the Lenders be directed to refund all amounts
     invested or infused into the Corporate Debtor by the SRA.
138. The NCLAT in its impugned order has taken note of its own order
     dated 21.10.2022 but has, however, only allowed the upfront payment
     of the Provident Fund dues of Rs. 12 Crore to the workmen and
     employees along with the payments that they are entitled to under
     the Resolution Plan. There is no specific direction as regard the
     payment obligations related to Gratuity nor any decision rendered
     on the two aforesaid IAs filed by the SRA in the Company Appeal.
     The NCLAT committed a serious error in failing to consider these
     IAs filed by the SRA and has given the impression that the SRA is
     liable to pay only the Provident Fund dues upfront.
139. According to the SRA, the dues relating to the Provident Fund would
     be paid upfront in compliance with Section 11 of the Employees’
     Provident Fund and Miscellaneous Provisions Act, 1952. However,
     the Gratuity Dues could be paid in tranches since neither the order
     dated 21.10.2022 of the NCLAT nor the order dated 30.01.2023
     of this Court had imposed any timelines for the payment of the
     Gratuity Dues. Furthermore, it was submitted that the provisions of
2146                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


     the Payment of Gratuity Act, 1972 were not so stringent. However,
     such a proposal cannot be allowed especially in light of the fact
     that the order dated 21.10.2022 of the NCLAT is unambiguous in
     its declaration that both Provident Fund and Gratuity dues have to
     be paid by the SRA in order to save the Resolution Plan from being
     hit by Section 30(2)(e) of the IBC, 2016.
140. Therefore, by not infusing the first tranche payment of Rs. 350 Crore
     as per the Implementation Schedule of the Resolution Plan, the SRA
     has breached the terms of the Resolution Plan which required a
     minimum liquidation value of Rs. 113 Crore to be paid towards the
     Workmen and Employees’ Dues as well. Moreover, both the Provident
     Fund and Gratuity Dues amounting to Rs. 226 Crore should also
     have been paid by the SRA as per the order dated 21.10.2022 of
     the NCLAT in fulfillment of its obligations, which it failed to do.

     c.   Whether there were sufficient grounds before the NCLAT to
          hold that Respondent No.1/SRA had contravened the terms
          of the approved Resolution Plan and that the Corporate
          Debtor must be directed to be liquidated under Section
          33(3) of the IBC, 2016?
141. The NCLAT in its impugned order held that the non-deposit of Rs.
     150 Crore in cash towards the first tranche payment of Rs. 350 Crore
     cannot lead to the conclusion that the Resolution Plan had failed.
     The relevant observations are reproduced hereinbelow:
          “79. The submission of the Appellant that on account of
          non-deposit INR 150 crores as directed by the Hon’ble
          Supreme Court, should lead to liquidation of the Corporate
          Debtor, cannot be accepted. The Hon’ble Supreme Court
          in its judgment dated 18.01.2024 has clearly held that its
          order modifying the direction of the Tribunal is confined only
          to the permission granted to the SRA to adjust INR 150
          crores PBG. Thus, modification of the order by the Hon’ble
          Supreme Court also has to confine to the adjustment of
          the PBG. It was held by the Hon’ble Supreme Court that
          Appellant have asked for infusion of INR 350 crores and
          infusion does not include adjustment of PBG. The Hon’ble
          Supreme Court neither considered nor expressed any
          opinion on the question of liquidation of the Corporate Debtor,
[2024] 11 S.C.R.                                                          2147

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          nor the order dated 18.01.2024 can be read to mean that
          non-compliance of the direction to deposit INR 150 crores
          by the SRA by 31.01.2024 should lead to liquidation of the
          Corporate Debtor. The submission of the Appellant that non-
          deposit of INR 150 crores leads to failure of Resolution Plan,
          cannot be accepted. As observed above, consequence of
          non-deposit of INR 150 crores is that these Appeals have
          to be heard on merits and the question, which has arisen
          in the Appeal has to be decided regarding compliance of
          conditions precedent by the SRA by 20.05.2022.
          Further submission of the Appellant that this Tribunal may
          exercise jurisdiction under Section 33, sub-section (3) in
          directing liquidation of the Corporate Debtor due to non-
          compliance of deposit on INR 150 crores also cannot be
          accepted. For passing an order under Section 33, sub-
          section (3), there has to be adjudication that Resolution
          Plan approved by the Adjudicating Authority has been
          contravened by the Successful Resolution Applicant. We
          do not accept the submission of the Appellant that by
          non-deposit of INR 150 crores by 31.01.2024, the SRA
          has contravened the Resolution Plan and order be passed
          under Section 33, sub-section (3).
          In view of our above observations and conclusions, we
          answer Question Nos. v, vi, and vii in following manner:

           Question No. v:     Direction of Hon’ble Supreme Court
                               permitting the Successful Resolution
                               Applicant to infuse INR 150 crores by
                               31.01.2024 was in reference to offer
                               made by Appellant in affidavit dated
                               16.08.2023

           Question No. iv:    The Successful Resolution Applicant
                               having not been able to infuse funds
                               by 31.01.2024 as directed by Hon’ble
                               Supreme Court vide its judgment dated
                               18.01.2024, it cannot be held that
                               Resolution Plan has failed and cannot
                               be implemented by the SRA.
2148                                                        [2024] 11 S.C.R.

                         Supreme Court Reports



           Question No. vii:    No grounds have been made out to
                                direct the liquidation of the Corporate
                                Debtor under Section 33, sub-section
                                (3) in these Appeals.”

                                                  (emphasis supplied)

142. The NCLAT declined to accept the submission of the Appellant that
     on account of non-deposit of Rs. 150 Crore as directed by this Court,
     the Corporate Debtor should be liquidated. However, this was based
     on the incorrect assumption that the direction of this Court to infuse to
     Rs. 150 Crore in cash was only confined to the terms of the Lenders
     Affidavit dated 16.08.2023. Previous segments of the judgment
     have elaborated in sufficient detail that the Lender’s Affidavit could
     not have provided for conditions which were incompatible with the
     terms of the Resolution Plan. Such an affidavit would have been in
     direct contravention with Section 31(1) of the IBC, 2016 which does
     not permit any modifications to be made in the Resolution Plan duly
     approved by the Adjudicating Authority. Therefore, the direction of
     this Court in its order dated 18.01.2024 was with respect to both the
     Lenders Affidavit and the underlying terms of the Resolution Plan.
     The same was so understood by all the parties involved.
143. The Lender’s Affidavit in precise terms stated that “Failing to comply
     with the conditions mentioned in Para 8(a) to (c) above, the Corporate
     Debtor should be directed to go into liquidation”. It was in this context
     that this Court stated that, “the SRA shall peremptorily on or before
     31 January 2024, deposit an amount of Rs. 150 crores into the
     designated account of SBI, failing which the consequences under
     the Resolution Plan will follow”. Therefore, it is incorrect to contend
     that this Court neither considered nor expressed any opinion on the
     question of liquidation of the Corporate Debtor. The consequence
     of non-implementation of the Resolution Plan by the SRA must
     necessarily be liquidation of the Corporate Debtor in accordance
     with Section 33(3) of the IBC, 2016. Section 33(3) of the IBC, 2016
     reads as thus:
           “(3) Where the resolution plan approved by the Adjudicating
           Authority is contravened by the concerned corporate
           debtor, any person other than the corporate debtor, whose
           interests are prejudicially affected by such contravention,
[2024] 11 S.C.R.                                                            2149

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

           may make an application to the Adjudicating Authority for
           a liquidation order as referred to in sub-clauses (i), (ii) and
           (iii) of clause (b) of sub-section (1).”
                                                   (emphasis supplied)

144. The non-deposit of Rs. 150 Crore had in fact lead to a failure of
     the Resolution Plan on several counts as elaborated herein. In
     addition to the breach of Clauses 6.3.1(g), 6.4.4 and S. No. 11 of
     the Implementation Schedule under Clause 7.7, the non-infusion
     of the first tranche payment in accordance with the terms of the
     Resolution Plan has also led to an infraction as regards Clause 6.4.1
     on the payment of CIRP costs and Clause 6.4.2 on the payment of
     workmen/employees’ dues. Further, the payment of the Provident
     Fund and Gratuity dues of the workmen/Employees as mandated
     by the order dated 21.10.2022 of the NCLAT which was confirmed
     by this Court on 31.01.2023, has also not been made by the SRA.
145. The SRA was given multiple extensions, post the Effective Date
     i.e., 20.05.2022 in order to implement the Resolution Plan and
     infuse the first tranche payment of Rs. 350 Crore into the Corporate
     Debtor. This includes the extensions granted by (a) the NCLT vide
     order dated 13.01.2023, by which the timeline for infusion of the
     first tranche payment was extended till 15.05.2023; (b) the NCLAT
     vide order dated 26.05.2023, where the timeline of 180 days was
     further extended up to 31.08.2023; (c) the NCLAT vide order dated
     28.08.2023, where the timeline of 180 days was extended up to
     30.09.2023; and (d) this Court vide order dated 18.01.2024, whereby
     the time of 180 days for infusion was extended up to 31.01.2024.
     However, indisputably, there has been a failure on the part of the
     SRA to abide by all these extended timelines as well. No further
     extensions or accommodations can be given to the SRA in light
     of the multiple opportunities already granted as aforesaid. Further,
     if such a request for further extension is entertained, it would only
     serve to bring us to the position that the parties were at when the
     order of this Court dated 18.01.2024 was passed.
146. In Kridhan Infrastructure Private Limited v. Venkatesan
     Sankaranarayan and Others reported in (2021) 6 SCC 94 the
     appellant had failed to fulfil its obligations under the Resolution Plan,
     including that of equity infusion, despite numerous opportunities
2150                                                       [2024] 11 S.C.R.

                        Supreme Court Reports


    granted over a period of 6 months. Therefore, the CoC voted by
    a majority to liquidate the corporate debtor as a result of failure
    to implement the resolution plan. The NCLT had allowed the
    liquidation to proceed and the NCLAT had upheld the same. On an
    appeal before this Court, a statement was made by the successful
    resolution applicant therein that an amount of Rs. 50 Crore would be
    deposited on or before 10.01.2021. Bearing in mind that liquidation
    under the IBC is a matter of last resort, such an opportunity was
    granted. The time for making the said deposit was further extended
    until 25.02.2021. However, no payment was made. By underscoring
    that time is a crucial facet of the scheme under the IBC, this Court
    held that there was a failure on part of the resolution applicant to
    implement the resolution plan and it was ordered that the liquidation
    proceedings against the corporate debtor be revived. The relevant
    observations are reproduced hereinbelow:
         “11. The appellant has been unable to raise the funds. The
         fact of the matter, as it emerges from Mr Viswanathan’s
         submissions, is that the appellant will be unable to raise
         funds from the term lenders who are insisting that the
         status of the Company should change from a company
         under liquidation to an active status. The order of liquidation
         has not been set aside. Ultimately, what the request of the
         appellant reduces itself to, is that it would raise funds on
         a mortgage of the assets of the Company and unless the
         Company is brought out of liquidation, it would not be in
         a position to raise the funds. This is unacceptable. At this
         stage, the order of liquidation has only been stayed, but a
         final view was, thus, to be taken by this Court. Sufficient
         opportunities were granted to the appellant earlier during
         the pendency of the proceedings both before the NCLT
         and NCLAT. The orders of the NCLT and Nclat make it
         abundantly clear that despite the grant of sufficient time,
         the appellant has not been able to comply with the terms of
         the resolution plan. Since 9-10-2020, despite the passage
         of almost five months, the appellant has not been able
         to deposit an amount of Rs 50 crores. Time is a crucial
         facet of the scheme under IBC [Innoventive Industries
         Ltd. v. ICICI Bank, (2018) 1 SCC 407, paras 12-16 :
         (2018) 1 SCC (Civ) 356] . To allow such proceedings to
[2024] 11 S.C.R.                                                          2151

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

           lapse into an indefinite delay will plainly defeat the object
           of the statute. A good faith effort to resolve a corporate
           insolvency is a preferred course. However, a resolution
           applicant must be fair in its dealings as well. The appellant
           has failed to abide by its obligations. In that view of the
           matter, we see no reason or justification to entertain the
           civil appeal any further. The consequence envisaged
           under the order of this Court shall accordingly ensue in
           terms of the forfeiture of the amount of Rs 20 crores. As
           a consequence of this order, the management shall revert
           to the liquidator for taking steps in accordance with law.
           The civil appeal is accordingly dismissed.”
                                                   (emphasis supplied).

147. The SRA herein has failed to infuse the first tranche payment of Rs.
     350 Crore as envisaged in the Resolution Plan despite the Effective
     Date being fixed on 20.05.2022. As a consequence, the payment
     of CIRP costs, workmen and employees’ dues etc. which must be
     made in priority over the dues of the other creditors have also not
     been made. More than 5 years have passed and the implementation
     of the Resolution Plan still seems to be a dim light at the far end
     of a long tunnel. Over this period of 5 years, several dues such as
     the Airport dues to be paid by the Corporate Debtor have increased
     multi-fold due to the fault of the SRA and this Court must ensure
     that such debts stop running at some point in time.
148. Although one of the key objectives of the IBC, 2016 is to ensure the
     survival of the corporate debtor as a going concern, yet the same
     must not come at the cost of efficiency. In scenarios such as the
     present, “timely liquidation” is indeed preferred over an “endless
     resolution process”. Such a view will prevent the likelihood of adversely
     affecting the interests of all the creditors who have been suffering
     due to no fault of their own and also securing the maximization of
     value of the remaining assets.
149. At this stage of the implementation of the Resolution Plan, it is no longer
     viable for the SRA to submit that the Resolution Plan shall automatically
     stand withdrawn according to Clause 7.6.4 of the Resolution Plan
     and upon, such withdrawal, the members of the SRA in the MC shall
     resign, the remaining members of the MC shall assume absolute
2152                                                       [2024] 11 S.C.R.

                          Supreme Court Reports


     control of the Corporate Debtor and all the amounts infused by the
     SRA would be refunded. This is especially so, since the Conditions
     Precedent were declared to be fulfilled and the Effective Date was
     achieved on 20.05.2022. The consequence of the failure to implement
     the Resolution Plan in terms of Clause 9.4 of the Resolution Plan
     and Clause 3.13.7(iii) of the RFRP is that the Appellants are entitled
     to invoke the PBG automatically without any reference to the SRA.
     Therefore, it is directed that the PBG may be invoked by the Appellants
     in accordance with the terms of the Resolution Plan.

     iii.   Whether the timely implementation of the Resolution Plan
            is also one of the objectives of the IBC, 2016?
150. The Preamble to the Insolvency and Bankruptcy Code, 2016 reads
     as thus:
            “An Act to consolidate and amend the laws relating to
            reorganisation and insolvency resolution of corporate
            persons, partnership firms and individuals in a time
            bound manner for maximisation of value of assets of
            such persons, to promote entrepreneurship, availability
            of credit and balance the interests of all the stakeholders
            including alteration in the order of priority of payment of
            Government dues and to establish an Insolvency and
            Bankruptcy Board of India, and for matters connected
            therewith or incidental thereto.”
                                                 (emphasis supplied)

151. The Report of the Bankruptcy Law Reforms Committee, 2015
     (hereinafter, the “2015 Report”) also serves to provide valuable
     insight into the several purposes for which the Code was enacted.
     Upon highlighting the various benefits of a consolidated insolvency
     regime, the Report also emphasizes on the time-bound working of
     the Code. The relevant observations are reproduced hereinbelow:
            “Speed is of essence
            Speed is of essence for the working of the bankruptcy
            code, for two reasons. First, while the “calm period” can
            help keep an organisation afloat, without the full clarity
            of ownership and control, significant decisions cannot
[2024] 11 S.C.R.                                                          2153

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          be made. Without effective leadership, the firm will tend
          to atrophy and fail. The longer the delay, the more likely
          it is that liquidation will be the only answer. Second, the
          liquidation value tends to go down with time as many
          assets suffer from a high economic rate of depreciation.
          From the viewpoint of creditors, a good realisation can
          generally be obtained if the firm is sold as a going concern.
          Hence, when delays induce liquidation, there is value
          destruction. Further, even in liquidation, the realisation is
          lower when there are delays. Hence, delays cause value
          destruction. Thus, achieving a high recovery rate is primarily
          about identifying and combating the sources of delay.”
                                                 (emphasis supplied)

     The Report acknowledged that time and speed are of the essence
     for the working of the Code. It conceded that significant decisions
     cannot be made for the company without full clarity as to ownership
     and control. Therefore, the longer it takes for installing effective
     leadership, the quicker will be the rate of atrophy of the company.
     Over a period of time, this delay in taking control of the company
     will lead to liquidation being the only viable answer. In this context,
     if there is additional delay during the process of liquidation, the
     liquidation value might also reduce significantly since the company’s
     assets might suffer a high economic rate of depreciation.
152. We hasten to add that any delay in arriving at the conclusion that
     the company is to be liquidated is also detrimental to a Company,
     especially when the Company has long awaited timely and positive
     action from the successful resolution applicant as regards the
     implementation of the approved resolution plan. Therefore, although
     liquidation should be the last resort, yet one should also ensure that
     further delay in arriving at this decision does not have the effect of
     hampering the realizations that can be made through liquidation.
153. The decision in Innoventive Industries Limited v. ICICI Bank and
     Another reported in (2018) 1 SCC 407 held that the Maharashtra
     Relief Undertakings (Special Provisions) Act, 1959 was repugnant
     to the IBC, 2016 and elaborated on the scheme of the IBC, 2016 by
     placing reliance on the 2015 Report as aforementioned. The relevant
     observations are reproduced hereinbelow:
2154                                                     [2024] 11 S.C.R.

                       Supreme Court Reports


        “13. One of the important objectives of the Code is to
        bring the insolvency law in India under a single unified
        umbrella with the object of speeding up of the insolvency
        process. As per the data available with the World Bank
        in 2016, insolvency resolution in India took 4.3 years on
        an average, which was much higher when compared with
        the United Kingdom (1 year), USA (1.5 years) and South
        Africa (2 years). The World Bank’s Ease of Doing Business
        Index, 2015, ranked India as country number 135 out of
        190 countries on the ease of resolving insolvency based
        on various indicia.

        xxx                          xxx                          xxx
        16. At this stage, it is important to set out the important
        paragraphs contained in the Report of the Bankruptcy Law
        Reforms Committee of November 2015, as these excerpts
        give us a good insight into why the Code was enacted
        and the purpose for which it was enacted:

        xxx                          xxx                          xxx
        Speed is of essence
        Speed is of essence for the working of the bankruptcy
        code, for two reasons. First, while the “calm period” can
        help keep an organisation afloat, without the full clarity
        of ownership and control, significant decisions cannot
        be made. Without effective leadership, the firm will tend
        to atrophy and fail. The longer the delay, the more likely
        it is that liquidation will be the only answer. Second, the
        liquidation value tends to go down with time as many
        assets suffer from a high economic rate of depreciation.
        From the viewpoint of creditors, a good realisation can
        generally be obtained if the firm is sold as a going concern.
        Hence, when delays induce liquidation, there is value
        destruction. Further, even in liquidation, the realisation is
        lower when there are delays. Hence, delays cause value
        destruction. Thus, achieving a high recovery rate is primarily
        about identifying and combating the sources of delay.

        xxx                          xxx                          xxx
[2024] 11 S.C.R.                                                        2155

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

          Objectives
          The Committee set the following as objectives desired
          from implementing a new Code to resolve insolvency and
          bankruptcy:
          (1) Low time to resolution.
          (2) Low loss in recovery.
          (3) Higher levels of debt financing across a wide variety
          of debt instruments.”
                                                (emphasis supplied)

154. Several decisions of this Court have highlighted the importance of
     a speedy resolution process under the IBC, 2016 in the context of
     either completing the CIRP process in a time-bound manner as per
     Section 12 of the IBC, 2016 or ensuring that the Liquidator does not
     cause unnecessary delay or inefficiency in the Liquidation process.
     A primary and predominant consideration behind minimizing delay is
     to ensure that the assets of the Corporate Debtor do not get frittered
     away or depreciated due to the time lag caused either during the
     CIRP or during the liquidation process overseen by the Liquidator.
     Such a time bound action is also equally important and imperative
     while the Resolution Plan is being implemented by the successful
     resolution applicant. Unnecessary delay caused in implementation
     of the Resolution Plan would also lead to similar consequences of
     the assets of the corporate debtor diminishing in value. Therefore,
     there is no doubt that the timely implementation of the Resolution
     Plan is also one of the underlying objectives of the IBC, 2016.
155. It is in the above context that the Rules regarding the power of the
     NCLT and NCLAT to extend time, have to be discussed. Rule 15 of
     the NCLT Rules, 2016 reads as thus:
          “15. Power to extend time.- The Tribunal may extend the
          time appointed by these rules or fixed by any order, for
          doing any act or taking any proceeding, upon such terms,
          if any, as the justice of the case may require, and any
          enlargement may be ordered, although the application
          therefore is not made until after the expiration of the time
          appointed or allowed.”
2156                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


156. Rule 15 of the NCLAT Rules, 2016 reads as thus:
          “15. Power to extend time.- The Appellate Tribunal may
          extend the time appointed by these rules or fixed by any
          order, for doing any act or taking any proceeding, upon such
          terms, if any, as the justice of the case may require, and
          any enlargement may be ordered, although the application
          therefore is not made until after the expiration of the time
          appointed or allowed.
157. Rule 15 of the NCLT and NCLAT Rules, 2016 grants power to the
     NCLT and NCLAT respectively, to extend the time limits for doing
     any act which have been fixed, either by the rules or by an order,
     as the justice of the case may require. However, such power must
     not be exercised mechanically without any application of mind. An
     extension on the strict timelines fixed under the resolution plan must
     be done by adequately weighing the period of extension sought with
     the consequences of such extension on the continued implementation
     of the Resolution Plan. After all, such a discretion cannot be exercised
     to the detriment of the resolution plan and its implementation itself.
     While one of the reasons supporting the grant of extension would
     be to ensure the successful revival of the corporate debtor, multiple
     extensions may seriously hamper the economic feasibility of the
     Resolution Plan and also lead to an increase in the debts of the
     corporate debtor. Not to mention, during the extended period, there
     are several costs incurred towards maintaining the corporate debtor as
     well. The feasibility and practicability of the resolution plan adjudged
     by the “commercial wisdom” of the CoC might no longer remain in
     cases where incessant extensions are granted by the NCLT and
     NCLAT under their discretionary powers.
158. The discretion in extending the time limits fixed under the Resolution
     Plan must be exercised in a much more circumspect manner,
     especially in cases such as the present, which pertains to the aviation
     sector, wherein timely resolution and revival of the Corporate Debtor
     is all the more crucial since the sector operates in such a way that
     a continuous flow of cash is required to maintain the company in a
     position of status quo.
159. We are now left to finally consider whether in view of the gross facts
     on record, we should, in exercise of our plenary jurisdiction under
     Article 142 of the Constitution, direct that the Corporate Debtor be
     taken in liquidation.
[2024] 11 S.C.R.                                                         2157

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

160. This Court in Ebix (supra) had opined that the exercise of powers,
     even under Article 142, must be broadly compliant with the insolvency
     framework and its underlying objective. It was highlighted therein
     that the Court must remain cautious in granting reliefs that may run
     counter to the timeliness and predictability that is central to the IBC,
     2016. The relevant observations made are reproduced hereinbelow:
          “101. Any claim seeking an exercise of the adjudicating
          authority’s residuary powers under Section 60(5)(c) IBC,
          NCLT’s inherent powers under Rule 11 of the NCLT
          Rules, 2016 or even the powers of this Court under Article
          142 of the Constitution must be closely scrutinised for
          broader compliance with the insolvency framework and
          its underlying objective. The adjudicating mechanisms
          which have been specifically created by the statute,
          have a narrowly defined role in the process and must be
          circumspect in granting reliefs that may run counter to
          the timeliness and predictability that is central to IBC. Any
          judicial creation of a procedural or substantive remedy that
          is not envisaged by the statute would not only violate the
          principle of separation of powers, but also run the risk of
          altering the delicate coordination that is designed by IBC
          framework and have grave implications on the outcome
          of the CIRP, the economy of the country and the lives of
          the workers and other allied parties who are statutorily
          bound by the impact of a resolution or liquidation of a
          corporate debtor.”
                                                 (emphasis supplied)

161. We are conscious of our recent decision Glas Trust Company
     LLC v. Byju Raveendran and Others reported in 2024 SCC OnLine
     SC 3032, taking the view that the Court must be circumspect in
     deviating from the prescribed procedure, especially in the context of
     the IBC, 2016. However, if such a deviation is made, then the Court
     must justify as to why the deviation was necessary to prevent the
     abuse of the process of the Court. The relevant observations are
     reproduced hereinbelow:
          “70. When a procedure has been prescribed for a
          particular purpose exhaustively, no power shall be
2158                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


           exercised otherwise than in the manner prescribed by
           the said provisions. In such cases, the court must be
           circumspect in invoking its ‘inherent powers’ to deviate
           from the prescribed procedure. If such deviation is made,
           the court must justify why this was necessary to “prevent
           the abuse of the process of the Court”.
           71. The need to be circumspect while invoking “inherent
           powers”, when there is an exhaustive legal framework
           is amplified in the context of a legislation like the IBC.
           In Ebix Singapore (P) Ltd. v. Educomp Solutions Ltd.
           (CoC), a two-judge bench of this Court, speaking through
           one of us (DY Chandrachud, J), affirmed this position and
           observed as follows:
           “Any claim seeking an exercise of the adjudicating
           authority’s residuary powers under Section 60(5)(c) IBC,
           NCLT’s inherent powers under Rule 11 of the NCLT Rules
           or even the powers of this Court under Article 142 of
           the Constitution must be closely scrutinized for broader
           compliance with the insolvency framework and its
           underlying objective. The adjudicating mechanisms
           which have been specifically created by the statute,
           have a narrowly defined role in the process and must be
           circumspect in granting reliefs that may run counter to the
           timeliness and predictability that is central to the IBC. Any
           judicial creation of a procedural or substantive remedy that
           is not envisaged by the statute would not only violate the
           principle of separation of powers, but also run the risk of
           altering the delicate coordination that is designed by the
           IBC framework and have grave implications on the outcome
           of the CIRP, the economy of the country and the lives of
           the workers and other allied parties who are statutorily
           bound by the impact of a resolution or liquidation of a
           Corporate Debtor.”
                                                  (emphasis supplied)

162. However, the aforementioned decision should in no manner be read
     so as to restrict the exercise of plenary powers under Article 142 of the
     Constitution even while in deviating from the statutory procedure and
[2024] 11 S.C.R.                                                      2159

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     framework of the IBC, 2016 or the rules and regulations thereunder,
     if such deviation is very much necessary. This Court in Glas Trust
     (supra) only went so far as to say that, where there is a prescribed
     procedure in place for a particular purpose, then that particular thing
     must be done only in the manner prescribed. It no way lays a dictum
     that even where cogent reasons exist warranting such deviation, the
     court would be powerless to exercise such inherent powers. In other
     words, Glas Trust (supra) only went to the extent of saying that in the
     absence of any exceptional circumstances or extraordinary reasons
     necessitating a deviation from the procedure laid down, the court
     should refrain from invoking its inherent jurisdiction to do something
     which otherwise could have been validly done in accordance with
     the procedure.
163. We are of the considered view that where there exists extraordinary
     circumstances warranting the exercise of such powers in order to
     ensure that the very salutary purpose of the Code, 2016 is not
     frustrated, then the Court would be well-within its prerogative to
     exercise them to secure the object of the IBC, 2016. If the proposition
     that there ought to be no exercise of the inherent powers where a
     procedure is laid down were to be blanketly accepted then it may have
     a very chilling effect whereby the very purpose of vesting this Court
     with inherent powers under Article 142 and Tribunals with Rule 11
     of the NCLT Rules would be rendered otiose and meaningless.
164. On account of the inordinate delay in due implementation of the
     Resolution Plan, several dues including the CIRP costs of the
     Corporate Debtor have continuously multiplied. The Appellants
     are incurring huge expenditure and costs each month towards
     maintenance of the Corporate Debtor. The fundamental concern of
     this Court must not only be of doing substantial and complete justice
     but also to ensure expeditious resolution of the issues in the interests
     of the underlying objective of the IBC, 2016 and all the stakeholders
     involved. We must obviate the possibility of the Corporate Debtor
     being stuck, embroiled and its resolution being further delayed,
     especially in light of the delay that has already ensued.
165. Having due regard to the materials on record, a determination that the
     terms of the Resolution Plan have been contravened and that there
     has been a failure to implement on part of the SRA, has already been
     made on a consideration of the issues before us. As such, since the
2160                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


     Resolution Plan is no longer capable of being implemented, we must
     ensure that at least liquidation remains as a “viable” last resort for the
     Corporate Debtor and its creditors. Being mindful of the underlying
     objective that “Time and Speed are of the essence under the Code”
     and to prevent the frustration of this objective, we have thought fit
     and necessary to exercise our plenary powers under Article 142 and
     direct the Corporate Debtor into liquidation in the manner as laid
     down in the IBC, 2016. Granting this relief to the Appellants would
     not run counter to the timelines and predictability that is central to
     IBC. On the contrary, it would be in furtherance of it. Ensuring that
     liquidation commences as soon as possible would also be in the
     best interests of the Corporate Debtor and the creditors including the
     workmen/employees who are yet to receive their rightful dues. To be
     precise, it would not be necessary for the parties to again approach
     the Adjudicating Authority for a determination under Section 33(3)
     of the IBC, 2016 on the ground that the provisions of the approved
     Resolution Plan have been contravened.

     F.   SHORTCOMINGS AND SUGGESTIONS TO THE IBC, 2016.
166. This litigation is an eye opener for one and all and therefore, before
     we close this matter, we deem it absolutely necessary to bring to
     light certain deficiencies in the IBC, 2016 which require immediate
     attention. We would also like to definitely say something as regards
     the functioning of the NCLTs and NCLAT.
167. Given the importance of the IBC, 2016 for the betterment of the
     economy at large, it is imperative that the insolvency ecosystem
     be continuously strengthened through a regular identification of its
     shortcomings and a quick redressal of its practical deficiencies. This
     would significantly improve its implementation and yield better results
     for all the stakeholders involved. While the receptiveness of the
     regime to the incorporation of novel and relevant recommendations
     is important, it is paramount that there also be strict adherence to
     the existing provisions of the Code, both in letter and spirit.
168. Scrupulous following of the provisions of the Code along with
     behavioural and ethical discipline is especially required from the
     key participants of the IBC who are central to its design i.e., the
     Adjudicating Authorities, Corporate Debtor, Resolution Professionals,
     Committee of Creditors, potential and Successful Resolution
     Applicants, Approved Valuers and Liquidators.
[2024] 11 S.C.R.                                                            2161

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

169. A Resolution Plan evolves through these players referred to above.
     However, it is the “commercial wisdom of the CoC” that assumes a
     position of superiority and becomes binding on all the stakeholders.
     The NCLT, which is the adjudicating authority and who has to approve
     the Resolution Plan under Section 31 of the IBC, 2016 also cannot
     trespass into the commercial wisdom exercised by the CoC. This
     decision to restrict the scope of interference on the commercial wisdom
     of the CoC was conscious and possibly taken bearing in mind the
     time delays that may arise out of a subsequent adjudication of the
     resolution plans approved by the CoC. Therefore, the commercial
     wisdom of the CoC has achieved paramount status, immune from
     any judicial intervention, to ensure the completion of the respective
     processes under the IBC, 2016 within the timelines prescribed therein.
170. The position that the “commercial wisdom” of the CoC is non-
     justiciable and only a limited judicial review is available in this regard
     is well-settled through several decisions of this Court. This Court
     in the case of K Shashidhar v. Indian Overseas Bank and Ors.
     reported in (2019) 12 SCC 150, held that:
           “52. As aforesaid, upon receipt of a “rejected” resolution
           plan the adjudicating authority (NCLT) is not expected to do
           anything more; but is obligated to initiate liquidation process
           under Section 33(1) of the I&B Code. The legislature
           has not endowed the adjudicating authority (NCLT) with
           the jurisdiction or authority to analyse or evaluate the
           commercial decision of CoC much less to enquire into
           the justness of the rejection of the resolution plan by the
           dissenting financial creditors. From the legislative history
           and the background in which the I&B Code has been
           enacted, it is noticed that a completely new approach has
           been adopted for speeding up the recovery of the debt due
           from the defaulting companies. In the new approach, there
           is a calm period followed by a swift resolution process to
           be completed within 270 days (outer limit) failing which,
           initiation of liquidation process has been made inevitable
           and mandatory. In the earlier regime, the corporate
           debtor could indefinitely continue to enjoy the protection
           given under Section 22 of the Sick Industrial Companies
           Act, 1985 or under other such enactments which has
           now been forsaken. Besides, the commercial wisdom
2162                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


          of CoC has been given paramount status without any
          judicial intervention, for ensuring completion of the stated
          processes within the timelines prescribed by the I&B Code.
          There is an intrinsic assumption that financial creditors are
          fully informed about the viability of the corporate debtor and
          feasibility of the proposed resolution plan. They act on the
          basis of thorough examination of the proposed resolution
          plan and assessment made by their team of experts. The
          opinion on the subject-matter expressed by them after due
          deliberations in CoC meetings through voting, as per voting
          shares, is a collective business decision. The legislature,
          consciously, has not provided any ground to challenge the
          “commercial wisdom” of the individual financial creditors or
          their collective decision before the adjudicating authority.
          That is made non-justiciable.”
                                                 (emphasis supplied)

171. Thus, there is no doubt that the commercial wisdom of the CoC cannot
     be subjected to judicial review. However, in order to foster a much
     more effective and time-bound decision making by the members of
     the CoC, in the interests of maximization of value of the assets of
     the Corporate Debtor, certain self-regulating guidelines were issued
     by the IBBI on 06.08.2024 with immediate effect. The Guidelines for
     Committee of Creditors are reproduced hereinbelow:
                “6. Guidelines
                A member of the CoC shall: -

                Objectivity and Integrity
          (a)   follow relevant provisions of the Code and regulations,
                in letter and spirit, while performing their roles and
                functions.
          (b)   maintain integrity in discharging their roles and
                functions as envisioned under the Code.
          (c)   maintain objectivity during the decision-making
                process.
          (d)   foster informed decision making and share with the
                CoC/ Insolvency Professional any relevant information
[2024] 11 S.C.R.                                                           2163

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

                relating to transactions, guarantees, recoveries,
                claims, etc. relating to the corporate debtor

                Independence and Impartiality
          (e)   disclose to the CoC/ Insolvency Professional the
                details of any existing or potential conflict of interest
                arising due to pecuniary, personal or professional
                relationship with any stakeholder, immediately on
                becoming aware of it.

                Professional Competence and Participation
          (f)   keep themselves updated with the provisions of
                the Code, rules and regulations and the role and
                responsibilities assigned thereunder.
          (g)   nominate representative with proper authorisation
                and sufficient mandate to effectively participate
                in meetings. The nominated representative may
                endeavour to obtain approval of the competent
                authority, if required, at the earliest.
          (h)   participate actively, constructively and effectively in
                deliberations and decision making of the CoC.

                Co-operation, supervision and timeliness
          (i)   supervise and facilitate the Insolvency Professional
                in discharging his duties under the Code.
          (j)   facilitate expeditious appointment of various
                professionals within the timelines prescribed under
                the Code and regulations.
          (k)   endeavour to resolve any inter-se disputes between
                the members, particularly in relation to claims,
                preferably, through dialogue, or other non-adversarial
                means, with a view to avoid litigation to the extent
                possible.

                Confidentiality
          (l)   ensure at all times complete adherence to the
                undertaking regarding confidentiality of information.
2164                                                       [2024] 11 S.C.R.

                       Supreme Court Reports


              Costs
        (m) take necessary measures to ensure that the
            insolvency resolution process cost is reasonable.
        (n)   expeditiously decide on all the expenses to be
              incurred by the Insolvency Professional including
              the going concern expenses of the corporate debtor
              and his fee.
        (o)   prudently fix the fee payable to the liquidator while
              deciding to liquidate the corporate debtor.

              Meeting of the CoC
        (p)   regularly monitor the activities of the Insolvency
              Professional and seek rationale of decisions/actions
              taken by him.
        (q)   diligently recommend for the inclusion or otherwise
              of the belated claims collated by the Insolvency
              Professional and categorised as acceptable, in the
              list of creditors and its treatment in the resolution
              plan, if any.
        (r)   actively participate in the presentation of valuation
              methodologies made by the Registered Valuers.
        (s)   ensure the conduct of the meeting at regular intervals
              as specified in the regulations.

              Sharing of information
        (t)   proactively share the latest financial statements,
              relevant extract from the audits of the corporate
              debtor, conducted by the creditors such as stock audit,
              transaction audit, forensic audit, etc. and other relevant
              information available, with the Insolvency Professional
              to enable efficient conduct of the process.
        (u)   seek details of all litigation filed against or by the
              corporate debtor from Insolvency Professional
              and recommend necessary actions to Insolvency
              Professional to safeguard the interest of the corporate
              debtor.
[2024] 11 S.C.R.                                                      2165

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

                Feasibility and viability of corporate debtor
          (v)   carefully review and assess the information
                memorandum prepared by Insolvency Professional
                and offer additional insights.
          (w) duly contribute to the preparation of the marketing
              strategy by the Insolvency Professional and may
              also take measures for marketing of the assets of
              the corporate debtor, if necessary.
          (x)   ensure that all resolution plans as received by
                Insolvency Professional are placed before CoC.
          (y)   suitably consider the requirement of a monitoring
                committee for the implementation of the resolution
                plan.”
172. The aforesaid guidelines may go a long way in streamlining the
     functions of the CoC. Adding to the aforesaid guidelines, we suggest
     that the CoC exercise their commercial wisdom and approve/reject
     the Resolution Plans placed before them exhibiting fairness and with
     good reasons. Such a reasoned decision making on their part will
     only serve to further enable the other key players like the Adjudicating
     Authorities to understand the rationale behind their decision and to
     uphold the correctness of the same. Furthermore, it is also suggested
     that the Central Government or the IBBI explore the possibilities of
     better enforcement of the standards and practices enumerated in the
     guidelines through an independent mechanism under the auspices
     of an oversight committee instead of making them self-regulatory.
     This will enable the guidelines to achieve some level of practical
     and operational relevance and also prevent any significant lapse in
     decision making on the part of the CoC.
173. This litigation is an eye-opener also as regards the manner in which
     the implementation of plans are handled by the Successful Resolution
     Applicant and the Lenders involved in the process. Once a resolution
     plan is approved under the IBC, 2016 the Successful Resolution
     Applicant undertakes a profound responsibility to implement the
     plan in both letter and spirit. This obligation is not merely an empty
     formality but an enduring commitment to restore the corporate
     debtor to viability and ensure a meaningful turnaround. The role of a
     Successful Resolution Applicant is thus far more than a transactional
2166                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


     duty towards the creditors or stakeholders; it embodies a pivotal
     responsibility to the distressed entity itself, which must be approached
     with utmost dedication and an earnest sense of duty. Regardless of
     the challenges that may arise, the Successful Resolution Applicant
     cannot treat its obligations as optional or conditional, nor can it
     abdicate its responsibility in the face of unforeseen obstacles. Its
     efforts must reflect a determination to implement the plan fully and to
     rejuvenate the debtor company, as this is integral to the success of
     the IBC framework and the spirit of economic revival it seeks to foster.
     The approach, therefore, must not be frugal or narrowly profit-driven,
     limited to viewing the transaction through a purely commercial lens.
     Instead, it must recognize that rescuing a distressed company is a
     responsibility of significant social and economic value, demanding a
     holistic and responsible strategy. This involves a dedication to long-
     term outcomes, where the Successful Resolution Applicant adopts
     measures that genuinely support the debtor’s rehabilitation, rather
     than making minimal or half-hearted attempts at implementation.
     Courts and tribunals have consistently underscored that the
     Successful Resolution Applicant’s role transcends commercial interest
     and embodies a commitment to the larger purpose of corporate
     revival. Consequently, it must make thoughtful and sustained efforts,
     demonstrating adaptability and resilience even when faced with
     obstacles or operational impediments. Simply put, the Successful
     Resolution Applicant cannot step back or dismiss its obligations by
     attributing delays or setbacks to the conduct of other stakeholders,
     as this would undermine the very purpose of insolvency resolution.
174. In this collaborative effort, the duty to implement the plan does
     not fall on the Successful Resolution Applicant alone; lenders and
     creditors are equally obligated to support the process by offering
     constructive and continuous cooperation. They must not impede the
     implementation process through unnecessary demands beyond the
     pale of the resolution plan or with delays in implementation plan but
     rather should facilitate the Successful Resolution Applicant’s efforts
     to revive the corporate debtor. Given their vested interest in the
     corporate debtor’s successful revival, lenders have a fundamental
     duty to act in good faith and with transparency, recognizing that
     their cooperative stance is essential for overcoming the inevitable
     challenges of the resolution process. The lender’s role is not merely
     passive; it requires active support that aligns with the ultimate goal
[2024] 11 S.C.R.                                                     2167

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     of the IBC, 2016 — to provide a fair and equitable resolution that
     maximizes asset value while enabling the debtor’s recovery.
175. Therefore, the lenders must balance their financial interests with
     the broader objective of rehabilitation. They should not take an
     obstructive approach or seek to leverage the resolution process solely
     for individual benefit, as such actions would risk destabilizing the
     corporate debtor’s recovery trajectory. Instead, they must be prepared
     to collaborate fully, sharing the responsibility to make the resolution
     process work in practice. Through a spirit of cooperation and shared
     purpose, the Successful Resolution Applicant and lenders together
     can ensure that the corporate debtor is given the best chance for
     revival and sustained growth, reflecting the Code’s intent to rescue
     viable companies and protect broader economic interests.
176. The IBC, 2016 is silent as regards the phase of implementation of
     the Resolution Plan by the Successful Resolution Applicant. This is
     mostly due to the fact that each Resolution Plan might be unique
     and customized to the specific needs of the Corporate Debtor and
     an excessive amount of statutory control over the implementation
     of the Plan may prove to be counterproductive to the cause of
     the Corporate Debtor. However, this has unfortunately led to
     the consequence of giving excessive leeway to the Successful
     Resolution Applicants to act in flagrant violation of the terms of the
     Resolution Plan in a lackadaisical manner. The SRAs repeatedly
     approach the Adjudicating Authority or the NCLAT for the grant of
     reliefs in relation to relaxation of the strict compliance to the terms
     of the Plan, including the timelines imposed therein. The NCLT and
     NCLAT more often than not, accede to such requests in exercise of
     their inherent powers under Rule 11 or their power to extend time
     under Rule 15 of the NCLT and NCLAT Rules, 2016 respectively.
     It is reiterated that the NCLT and NCLAT must not entertain such
     repeated attempts at violating the integrity of a CoC approved
     Resolution Plan by accommodating the incessant requests of the
     Successful Resolution Applicants. The exercise of discretion as
     regards altering the binding terms of the Resolution Plan, including
     the timelines imposed, must be kept at a minimum, at best. The
     NCLTs/ NCLATs need to be sensitised of not exercising their judicial
     discretion in extending the timelines fixed under IBC, 2016 or the
     Resolution Plan, in such a way that it may make the Code lose its
     effectiveness thereby rendering it obsolete.
2168                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


177. Section 30(2)(d) of the IBC, 2016 states that the resolution professional
     shall mandatorily examine each resolution plan that is received to
     confirm that it provides for the implementation and supervision of
     the resolution plan. Regulation 38 of the 2016 Regulations provides
     for the mandatory contents of a Resolution Plan. Regulation 38(2)
     specifically states that the Resolution Plan shall provide for the term
     of the plan and its implementation schedule, along with adequate
     means for supervising its implementation. Further, under Regulation
     38(3), a resolution plan must demonstrate that it addresses the
     cause of default, is feasible and viable, has provisions for its
     effective implementation, has provisions for approvals required and
     the timelines for the same and, that the resolution applicant has the
     capability to implement the resolution plan. Therefore, in light of these
     provisions of the IBC, 2016 and the 2016 Regulations, it can be seen
     that the resolution plan must be impermeable to any shortcuts that
     prevent its implementation, including timely implementation, by the
     successful resolution applicant. A consideration of these provisions
     reinforces the idea that timely implementation and strict adherence
     to the terms of the resolution plan is crucial.
178. Furthermore, Section 74(3) of the IBC, 2016 provides for the
     punishment for contravention of the resolution plan and reads as
     follows:
           “(3) Where the corporate debtor, any of its officers or
           creditors or any person on whom the approved resolution
           plan is binding under section 31, knowingly and wilfully
           contravenes any of the terms of such resolution plan or
           abets such contravention, such corporate debtor, officer,
           creditor or person shall be punishable with imprisonment
           of not less than one year, but may extend to five years,
           or with fine which shall not be less than one lakh rupees,
           but may extend to one crore rupees, or with both.”
                                                  (emphasis supplied)

179. The Code comes down heavily on any knowing and willful
     contravention of the terms of the Resolution Plan, committed by
     any person, on whom the approved Resolution Plan has been
     made binding under Section 31 of the IBC, 2016. A punishment of
     minimum one year which may extend up to five years or minimum
[2024] 11 S.C.R.                                                        2169

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     fine of one Lakh which may be up to one Crore rupees, or both,
     has been prescribed for such a contravention. In light of such strict
     consequence provided for the contravention of the resolution plan
     envisaged under the scheme of the Code itself, there is good reason
     for us to ensure that the successful resolution applicants abide by
     their commitments made under the Resolution Plan. Therefore, it is
     suggested that the authorities including the NCLT and NCLAT must
     not aid the Successful Resolution Applicants in circumventing the
     strict mandates of the law by acceding to their requests to relax the
     terms of the plan itself.
180. One another suggestion at our end that may aid in a coordinated
     and non-adversarial implementation of the Resolution Plan by all
     the stakeholders is that the Adjudicating Authority while approving
     a Resolution Plan under Section 31 of the IBC, 2016, should record
     the next steps which are to be taken by the respective parties for
     commencement of implementation of the approved Resolution
     Plan. This will ensure that the parties are ad idem about the next
     round of their obligations that each of them is required to discharge
     under the approved Resolution Plan and that they do not delay the
     implementation by initiating any further litigation on this aspect. If
     such an approach is adopted, the parties would be able to put forth
     any difficulty that they might face in performing those next steps
     before the NCLT itself and seek necessary relief in that regard.
     Recording the next steps that are to be undertaken in the order of
     the Adjudicating Authority, will keep the parties more vigilant since
     a non-performance of the obligation may lead to a violation of the
     terms of the approved Resolution Plan and also violation of the order
     approving the Resolution Plan as well.
181. As regards the implementation of the approved Resolution Plan, it is
     suggested that the IBC, 2016 statutorily provide for the constitution
     of a Monitoring Committee, once the plan has been approved,
     for a smooth handover of the Corporate Debtor to the Successful
     Resolution Applicant. Presently, such a provision is absent in the Code
     and it is the Adjudicating Authority that orders for the constitution of a
     Monitoring Committee to ensure smooth implementation of the Plan.
     The CoC must be empowered to constitute the Monitoring Committee
     which may, by default, include the Resolution Professional and also
     include other nominees from the CoC and the Resolution Applicant
2170                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


     respectively. Such a Monitoring Committee would be entrusted with
     the powers of monitoring and supervising the resolution plan till the
     expiry of the term of the Resolution Plan. The Committee shall also be
     required to ensure all statutory compliances during the implementation
     of the plan along with updating the Adjudicating Authorities, Financial
     and other Creditors about the status of implementation of the
     Resolution Plan, on a quarterly basis.
182. Moving on to certain efficiency issues within the NCLTs and NCLAT, it
     has been noticed over a period of time that there is a serious lack of
     timely admission and disposal of the applications filed as regards the
     initiation of CIRP, approval of the resolution plan and liquidation. This
     only adds to the uncertainty of the process and prolongs the dispute
     thereby jeopardizing the interest of all the stakeholders involved.
     Adjudication in a time-bound manner would help prevent any further
     deterioration of the value of the corporate entity. The integrity of the
     original timelines laid down by the Code and the Resolution Plan
     must not be allowed to be violated since it would dilute the objective
     of the Code in its entirety, erode investor confidence and hinder all
     corporate restructuring efforts.
183. The Members often lack the domain knowledge required to appreciate
     the nuanced complexities involved in high-stake insolvency matters
     in order to properly adjudicate such matters. It has been noticed
     that the benches of NCLT(s) and NCLAT don’t have the practice
     of sitting for the full working hours. They are particularly lacking in
     the capacity to manage the growing number of cases and giving
     undivided attention required in such matters. There are serious issues
     in the manner in which the insolvency matters are listed. There is
     no effective system in place before the NCLTs for urgent listings.
     The staff of the Registry is given wide power to list or not to list a
     particular matter. One of the salutary objects of the Code, 2016 is
     to protect the assets of the corporate entity in a timely manner and
     take prompt decisions, however, it has become a practice of the
     NCLT(s) and NCLAT to ignore the urgent mentionings and listings
     of time-sensitive matters and show no deference to long-pending
     matters resulting in value erosion of the assets of the Corporate
     Debtor and rendering their insolvency resolution process a foregone
     conclusion. Over a period of time, this Court has noticed the growing
[2024] 11 S.C.R.                                                       2171

 State Bank of India & Ors. v. The Consortium of Mr. Murari Lal Jalan
                    and Mr. Florian Fritsch & Anr.

     tendency amongst Members of the NCLT(s) and NCLAT to ignore
     the orders of this Court or act in its defiance. We put the NCLT(s)
     and the NCLAT to notice, that any act of contravention of this Court’s
     order and the larger rubric of judicial propriety will not be tolerated.
     The NCLT(s) and the NCLAT must seriously rethink their approach
     towards admission and disposal of insolvency matters, they should
     not act as a mere rubberstamping authority and must take their
     roles seriously in ensuring time-bound hearings and resolutions.
     Proper and effective hearings, both virtually and in-court, must be
     given to insolvency matters of public importance, and the NCLT(s)
     and NCLAT(s) must earnestly work towards ensuring that the IBC,
     2016 achieves its avowed object.
184. One another serious issue pertaining to the functioning of the NCLTs
     and NCLAT is that there is often a shortage of members in the
     Tribunals and inadequate infrastructure to support their functioning.
     These vacancies heavily impact the insolvency reform initiative
     undertaken by the government since they lead to operational
     inefficiencies. A shortfall of members and the lack of requisite strength
     has led to Tribunals only sitting for a few days of the week or a few
     hours in a day. Even in Tribunals where there is no vacancy, the
     absence of requisite infrastructure has forced the benches to share
     courtrooms or halls on a rotation basis. As a consequence, the strict
     timelines provided in Section 12 of the IBC, 2016 are not complied
     with. Filling such vacancies with experts having adequate domain
     knowledge in the field must be prioritized along with addressing the
     infrastructure needs of the Tribunals to prevent any adverse effect
     on the resolution process. There must be strict mandates regarding
     the functioning of the Tribunals within its normal working hours. The
     appointment of new members must be done in a manner such that
     it coincides with the date of retirement of the sitting members in a
     seamless manner to avoid such operational inefficiencies. Persons
     with high ideals & impeccable integrity should be appointed as
     Members in the NCLT as well as NCLAT. There should not be any
     political appointment.
185. It is now for the Parliament to look into our suggestions in consultation
     with the Insolvency Bankruptcy Board of India and the Ministry of
     Finance.
2172                                                      [2024] 11 S.C.R.

                            Supreme Court Reports


     G.      CONCLUSION
186. For all the foregoing reasons, we have reached the conclusion
     that the impugned order passed by the NCLAT is perverse and
     unsustainable in law. It has led to further complications. As a result,
     the appeals succeed and are allowed. The impugned order passed
     by the NCLAT is set aside.
187. In the peculiar and alarming circumstances as discussed in this
     judgment and also keeping in mind the fact that almost five years
     have elapsed since the Resolution Plan was duly approved by the
     NCLAT and there being no progress worth the name, we are left
     with no other option but to invoke our jurisdiction under Article 142
     of the Constitution and direct that the Corporate Debtor be taken
     in liquidation. The NCLT, Mumbai shall now take appropriate steps
     for appointment of liquidator and all other necessary formalities for
     commencement of liquidation of the Corporate Debtor.
188. The amount of Rs 200 Crore already infused by the SRA stands
     forfeited. The Lenders/ Creditors are further permitted to encash the
     Performance Bank Guarantee of Rs. 150 Crore furnished by the
     SRA. We accordingly order so.
189. These appeals are disposed of in the aforesaid terms.
190. The Registry shall forward one copy each of this judgment to the
     Principal Secretary, Ministry of Finance, Government of India and the
     Chairperson, Insolvency Bankruptcy Board of India with a request
     to look into this judgment more particularly the suggestions made
     by this Court.

     Result of the case: Appeals allowed.



     †
         Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Jet Airways liquidation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.