Created byFuzzy Cloud

Supreme Court of India

SHIPPING CORPORATION OF INDIA LTD.versusMARE SHIPPING INC.

Citation
2011 INSC 490
Decided
13 July 2011
Disposal
Dismissed

Holding

The vessel was an arrived ship upon reaching the customary anchorage at Vadinar, and the charterers bore responsibility for the failure to moor, making demurrage payable to the owners.

Summary

The case involved a charter party for the carriage of crude oil from Ras Sukheir to a safe Indian port, where the charterers nominated Vadinar Single Berth Mooring (SBM) for discharge. The vessel arrived at Vadinar, tendered a Notice of Readiness (NOR) but could not moor at the SBM due to inadequate equipment. An addendum was later signed, diverting the vessel to Mumbai and making the charterers bear all extra costs, including demurrage. The arbitral tribunal awarded demurrage to the vessel owners, a decision upheld by the Bombay High Court. The Supreme Court examined whether the vessel was an “arrived ship” upon reaching the customary anchorage at Vadinar and, if so, whether the owners were entitled to demurrage. It held that the vessel was an arrived ship under Clause 6 of the charter party, that the charterers were responsible for the failure to moor, and that demurrage was payable to the owners. Consequently, the Special Leave Petition was dismissed.

Issues considered

  • Whether the vessel qualified as an ‘arrived ship’ capable of issuing a Notice of Readiness upon arrival at the customary anchorage at Vadinar despite not being moored at the SBM.
  • Assuming the vessel was an arrived ship, whether the owners were entitled to demurrage (or damages) from the charterers.

Legislation cited

Subjects

demurragenotice of readinessarrived shipcharter partymaritime lawarbitration awardsafe berthliabilityspecial leave petition

Judgment

                         [2011] 9 S.C.R. 70


A           SHIPPING CORPORATION OF INDIA LTD.
                                  v.
                      MARE SHIPPING INC.
          (Special Leave Petition (C) No. 19461 of 2006)
                           JULY 13, 2011
B
           [ALTAMAS KABIR AND A.K. PATNAIK, JJ.]

        Shipping: Demurrage charges on account of delay in
   discharge of cargo - Claim for - Charter Party providing for
C carriage of crude oil from Ras Sukheir to a safe port on the
   Indian coastline - No specific port in the Indian coastline
   mentioned in the Charter Party - Charterers given choice of
   nominating port for discharge of the cargo - After vessel left
   Ras Sukheir, intimation given by Charterers for discharge of
o the cargo at the SBM at Port Vadinar - Vessel reached Port
   Vadinar on 15. 12. 1999 and Master of vessel tendered Notice
  of Readiness (NOR) - However, vessel was not so equipped
  and could not be moored at the SBM - The Addendum to
  Charter Party drawn up between Charterer and owner of vessel
E containing conditions that vessel would be diverted from
   Vadinar to Mumbai for discharge and all extra cost/
  demurrage charges would be borne by Charterer - Thereafter
  vessel diverted to Mumbai and completed discharge - Claim
  for demurrage charges made by owner of vessel - Dispute
  arose and arbitration clause contained in Charter party
F invoked - Arbitral Tribunal allowed the claim of owner of
  vessel - High Court upheld the order of the Arbitral Tribunal
  - On appeal, held: In giving Notice of Readiness upon arrival
  at the customary anchorage at Vadinar, the Master of the
  Vessel duly complied with the conditions of the Charter Party
G - The responsibility for the failure of the ship to moor at the
  SBM in Vadinar lay squarely on the Charterers and the
  receiver as they had nominated the SBM for the safe mooring
  of the vessel -It cannot also be said that the owners of the

H                               70
    SHIPPING CORPORATION OF INDIA LTD. v. MARE                71
                  SHIPPING INC.
    vessel contributed in any way to such failure since the A
    equipment on board the vessel were made known to the
    Charterers when the Charter Party was signed - The terms
    of the Charter Party were agreed upon by the parties with their
    eyes wide open - Even after the vessel was denied mooring
    at the SBM for safety reasons, no steps were taken by the B
    Charterers to either arrange for an alternate safe berthing in
    Vadinar or to give instructions as to where the cargo was to
    be discharged - Even the subsequent deviation of the vessel
    from Vadinar to Mumbai was not on account of any /aches
    on the part of the owners of the vessel - Read with the Charter c
    Party, the Addendum made it abundantly clear that the
    Charterers had accepted the responsibility for the failure of
    the vessel to discharge her cargo at Vadinar and had agreed
    to bear.cal/ the expenses for the delay in diversion of the vessel
    from Vadinar to Mumbai, including the time spent at Vadinar 0
    port and the expenses incurred towards pilotage, tugs and
    other port expenses - Apart from that the Charter Party
    specifically provided that extra expenses incurred on account
    of any change in loading or discharging ports, has to be paid
    by the Charterers, and any time thereby lost to the vessel
     shall count as used lay time - There was no reason to interfere E
    with the award of the Arbitral Tribunal - Arbitration.
         On 9.11.1999, the petitioner-Charterers and the
    respondent-owner entered into a Charter Party in respect
    of the respondent's vessel for carriage of 8150 ·metric         F
    tones of crude oil from the Egyptian Red Sea port of Ras
    Sukheir to one/two safe anchorage/lighterage points/
    SBMs/one/two safe port(s) one/two safe berth(s)
    anywhere in India. The vessel was described in the
    Charter party as being fitted with "AK Tongue Type Bow          G
i   Chain Stopper of min SWL 2000 Mts." The Charter Party
    contained arbitration clause ..
        On 19.11.1999, the vessel arrived at Ras Sukheir at
    4.00 a.m. and tendered Notice of Readiness (NOR). The
    loading commenced at 10 p.m., on 20.11.1999 and was             H
    72       SUPREME COURT REPORTS             [2011J 9 S.C.R.

A completed by 3.15 p.m. on 21.11.1999. The total lay time
  provided for loading and discharge of cargo was 72
  running hours. Out of the said lay time hours, the lay
  time used at Ras Sukheir was 37 hours and 30 minutes.
  On account of a mishap involving the vessel's anchor
B and the submarine pipe-lines, the vessel was delayed at
  Ras Sukheir for fourteen days and could leave the port
  only on 4.12.1999. On 6.12.1999 while the vessel was
  sailing, the respondents-owners nominated Vadinar
  Single Berth Mooring (SBM) for discharge of the cargo.
C The port of discharge was not nominated earlier. The
  vessel arrived at Vadinar and the Master tendered NOR
  at 8 p.m. on 15.12.1999. Since the vessel had only one
  chain stopper/Bow Panama Chock as specified in the
  Charter Party, the vessel could not be safely moored at
  the SBM and the Master was asked by the Receiver,
0
  Indian Oil Corporation on 21.12.1999 to take away the
  vessel from the Vadinar SBM.

        ·On 21.12.1999, a message was sent to the petitioner's
    agents by the Manager of the respondents drawing
E   attention to the fact that the vessel could not be berthed
    at the SBM and requesting that immediate steps be taken
    to berth the vessel. But no steps were taken by the
    petitioners in that regard. Finally a decision was arrived
    at on 28.12.1999 and Addendum to the Charter Party was
F   drawn up and signed by the Owner and the Charterers
    containing the conditions that the vessel would be
    diverted by the Charterers from Vadinar to L.P.O. Mumbai
    for discharge into a daughter vessel and all the extra cost/


                                                                   -
    expenses of daughter vessel/demurrage charges would
G   be born by the Charterers. Pursuant to this arrangement,
    the vessel sailed from Vadinar at 1 a.m. on 29.12.1999 and
    arrived at Mumbai Lighterage point on 30.12.1999 at 2
    p.m. The vessel tendered Notice of Readiness at 2 p.m.
    on 30.12.1999 and completed discharge at 3.30 p.m. on
H   1.1.2000. The respondents/owner submitted the
 SHIPPING CORPORATION OF INDIA LTD. v. MARE                73
               SHIPPING INC.
demurrage claims along with supporting documents to              A
the Charterer. As the said claim was disputed, arbitration
clause was invoked by the parties under the provisions
of the Arbitration & Conciliation Act, 1996. The Arbitral
Tribunal passed an award allowing the respondents'
demurrage claim in full. Certain other amounts payable           B
under the Addendum were also· awarded in favour of the
respondents. The petitioner-charterers challenged the
award. The Single Judge of the High Court upheld the
award. The Division Bench of the High Court affirmed the
same.                                                            c
    The question which arose for consideration in the
instant special leave petition was whether on arriving at
anchorage point at Port Vadinar, despite the destination
point being the SBM mooring, it could be said that it was
an arrived ship which was competent under the Charter            0
Party dated 9.11.1999, to issue Notice of Readiness of
discharge of its cargo; if the finding of the Arbitral
Tribunal that the vessel was an arrived ship at Port
Vadinar, as upheld by the Single Judge and the Division
Bench of the High Court is accepted, would the                   E
respondent/owners of the vessel be entitled to damages
or demurrage.

    Dismissing the special leave petition, the Court
                                                                 F
     HELD: 1. The Charter Party dated 9.11.1999 was in
respect of a transaction which provided for carriage of
crude oil from Ras Sukheir to a safe port on the Indian
coastline. The Charterers were given the choice of
nominating such port for discharge of the said cargo of
crude oil. In the absence of any named port of destination       G
in the Charter Party itself, it was only after the vessel left
Ras Sukheir that an intimation was given by the
Charterers for discharge of the cargo at the SBM at Port
Vadinar in Gujarat. That the said nomination was a
conscious decision on the part of the Charterers, despite        H
    74       SUPREME COURT REPORTS             [2011] 9 S.C.R.


A having knowledge of the equipment available on board
  the vessel for mooring at a SBM, and in keeping with
  such decision the vessel set its course from Ras Sukheir
  to Vadinar. The fiasco at Vadinar was occasioned by the
  fact that no prior checking had been done to see whether
B with the mooring equipment on board, the vessel would
  be able to safely berth at the SBM for discharge of its
  cargo. (Para 43] (95-A-E]

         2. The concept of an arrived ship in shipping
    terminology requires that a vessel should reach a
C   destination in a port where she could be safely berthed
    and thereupon be ready to either discharge or load cargo
    from and on to the vessel. That is a general concept, but
    the Charterers and the Owners of the vessel could in the
    Charter Party agree to a specific destination point within
D   the port area for discharging or loading of cargo. Once
    the vessel arrived at the said spot and was ready to
    discharge its cargo, it could be described as an "arrived
    ship" with the authority to issue and tender Notice of
    Readiness. In the instant case, the nominated port for the
E   arrival of the vessel was Vadinar Port, but the destination
    point was the SBM where the vessel was to be moored
    and was to discharge its cargo of crude oil. In fact, in the
    Charter Party dated 9.11.1999, Clause 6 specifically
    provided for arrival of the vessel at the port of loading or
F   discharge and cast an obligation upon the Master or his
    Agent to give the Charterer or his Agent Notice of
    Readiness in relation to discharge of the cargo. It is a
    possibility that since no specific port in the Indian
    coastline had been mentioned in the Charter Party, the
G   Master of the vessel or his Agent was required to give
    Notice of Readiness upon the vessel arriving at
    customary anchorage. It is only after the vessel sailed
    from Ras Sukheir that the receiver, IOC, nominated
    Vadinar to be the port of discharge with the specific
H   destination point being the SBM within the port. In giving
 SHIPPING CORPORATION OF INDIA LTD. v. MARE           75
               SHIPPING INC.
such Notice of Readiness upon arrival at the customary A
anchorage at Vadinar, the Master of the Vessel duly
complied with the conditions of Clause 6 of the Charter
Party and in terms of the said clause irrespective of
whether a berth was available or not, lay time
commenced upon the expiry of six hours after receipt of B
such notice. That the vessel could not be moored at the
SBM is a different facet of the story. The Charterers had
full knowledge of the equipment on board vessel through
the questionnaire provided by the respondents/Owners
to the petitioners/Charterers. It cannot be denied that c
despite having such knowledge the IOC nominated the
SBM as the destination point for discharge of the cargo.
Obviously, the parties to the Charter Party had not made
any attempt to verify as to whether the equipment on
board the vessel was sufficient for her to be safely 0
moored at the SBM and to discharge her cargo safely. As
it turned out later on, the vessel was not so equipped and
could not, therefore, be moored at the SBM and had to
be requested to move away therefrom.                   The
responsibility for the failure of the ship to moor at the E
SBM in Vadinar must lie squarely with the Charterers and
the receiver as it was they who had nominated the SBM
for the safe mooring of the vessel. The lay time must,
therefore, be held to have recommenced after the expiry
of six hours from the tendering of the Notice of
Readiness upon the vessel's arrival at the customary F
anchorage at Vadinar on 15.12.1999 in keeping with the
provisions of Clause 6 of the Charter Party. It was not the
case of the Charterers that the failure of the vessel to
discharge its cargo at the SBM at Vadinar was for
reasons beyond their control. It cannot also be said that G
the owners of the vessel contributed in any way to such
failure since the equipment on board the vessel had been
made known to the Charterers when the Charter Party
was signed.[Paras 44 and 45) [95-G-H; 96-A-C-G-H; 97-A-
H; 98-A-B]                                                  H
    76      SUPREME COURT REPORTS            [2011] 9 S.C.R.


A      3. In the face of the specific conditions indicated in
  Clause 6 of the Charter Party, the theoretical and/or
  academic exercise of what constitutes an "arrived ship"
  loses much of its relevance. The terms of the Charter
  Party were agreed upon by the parties with their eyes
B wide open. Even after the vessel was denied mooring at
  the SBM for safety reasons on 21.12.1999, no steps were       ~
  taken on behalf of the petitioners to either arrange for an
  alternate safe berthing in Vadinar or to give instructions
  as to where the cargo was to be discharged. In fact, on
c behalf of the respondent/Owners a legal notice was
  addressed to the petitioners on 24.12.1999 pointing out
  that the vessel continued to await discharge incurring
  demurrage. It was only thereafter that Addendum to the
  Charter Party was drawn up and signed on 28.12.1999 by
0 the Owners and the Charterers, whereby the vessel was
  diverted by the Charterers from Vadinar to a Lighterage
  point at Mumbai port for discharge and it was specifically
  agreed that the Charterers would bear all the costs of
  discharge, including freight charges and the expenses of
E the daughter vessel. It was also agreed that demurrage
  would be settled as per the terms of the Charter Party.
  [Para 46] [98-C-G]

       4. Once it is held that the vessel was an arrived ship
  on reaching the customary anchorage at Vadinar port
F and it was the Charterers who having the choice of a safe
  port, had selected the SBM at Vadinar as the discharge
  point, the suggestion made on behalf of the Charterers
  that it was the responsibility of the Owners of the vessel
  to check whether the ship could be safely moored at the
G SBM, is untenable. The responsibility of the Owners of
  the vessel ended with the declaration of the equipment
  available on board for mooring and berthing for the
  purpose of discharge of its cargo. Consequently, all the
  other ancillary issues which arose had to be answered
H in favour of the respondents. The fiasco at Vadinar was
              SHIPPING CORPORATION OF INDIA LTD. v. MARE   77
                            SHIPPING INC.




         ·I




     •




·•

                                                                H
    78       SUPREME COURT REPORTS               [2011) 9 S.C.R.


A                        Case Law Reference:
         (1908) 1 K.B. 499        referred to       Para 14, 18

         (1917) 2 K.B. 204        referred to       Para 14
         (1917) 2 K.B. 593        referred to       Para 14
B
         (1973) 11 LLR 285        referred to       Para 17,18

         2003 (3) SCR 691         referred to       Para 25

         CIVIL APPELLATE JURISDICTION : SLP (Civil) No.
c 19461 of 2004.
        From the Judgment & Order dated 20.01.2006 of the
    High Court of Judicature at Bombay in Appeal No. 1158 of
    2005 in Arbitration Petition No. 531 of 2003.
D
         Bhaskar Gupta, Manoj Khanna, R.K. Khanna for the
    Petitioner.

        Prashant Pratap, Siddhartha ['ave, Jemtiben AO, Vibha
    Datta Makhija for the Respondent.
E
         The Judgment of the Court was delivered by

         ALTAMAS KABIR, J. 1. The Special Leave Petition
    arises out of the Judgment and Order dated 24.10.2005
    passed by the learned Single Judge of the Bombay High Court
F   in A.P.No.531 of 2003 affirming the Award of the Arbitral
    Tribunal dated 8.9.2005, and the judgment and order dated
    20.1.2006 passed by the Division Bench dismissing
    A.N.No.1158 of 2005 filed by the Petitioners herein.

G        2. On 9.11.1999 the Petitioners and the Respondent(s)
    entered into a Charter Party in respect of the Respondents'
    vessel, "m.t. Prestige", for carriage of minimum 8150 metric
    tonnes of crude oil from the Egyptian Red Sea port of Ras
                                                                     ,
    Sukheir to one/two safe anchorage(s)/lighterage points/SBM(s)/
H   one/two safe port(s)one/two safe berth(s) anywhere in India.
              SHIPPING CORPORATION OF INDIA LTD. v. MARE 79
         r          SHIPPING INC. [ALTAMAS KABIR, J.]   \
             The vessel was described in Clause 41 of the Charter Party A
             as being fitted with "AK Tongue Type Bow Chain Stopper of
             min SWL 2000 Mts."

                  3. Clause 9 of the Charter Party provided for settlement
    -\       of all disputes arising out of the Charter Party by arbitration B
             under the Arbitration & Conciliation Act, 1996, and the Maritime
             Arbitration Rules of the Indian Council of Arbitration (ICA).

                  4. The vessel arrived at Ras Sukheir at 4.00 a.m. on
             19.11.1999 and tendered Notice of Readiness (NOR). The
             loading commenced at 10 p.m. on 20.11.1999 and was                C
             completed by 3.15 p.m. on 21.11.1999. The total lay time
             provided for loading and discharge of cargo was 72 running
             hours. Out of the said lay time hours, the lay time used at Ras
             Sukheir was 37 hours and 30 minutes. On account of a mishap
             involving the vessel's anchor and the submarine_pipe-lines, the   D
             vessel was delayed at Ras Sukheir for fourteen days and could
             leave the port only on 4.12.1999. On 6.12.1999 while the
             vessel was sailing, the Respondents nominated Vadinar Single
             Berth Mooring (SBM) for discharge of the cargo. Port of
             discharge had not been nominated earlier. The vessel arrived      E
             at Vadinar and the Master tendered NOR at 8 p.m. on
             15.12.1999. Since the vessel had only one chain stopper/Bow
             Panama Chock, which had been specified in the Charter Party,
             the vessel could not be safely moored at the SBM and the
             Master was asked by the Receiver, Indian Oil Corporation on       F
             21.12.1999 to take away the vessel from the Vadinar SBM.
                  5. On 21.12.1999 a message was sent to the Petitioners'
             Agents, Mis. J.M. Baxi & Co. by the Manager of the
             Respondents drawing attention to the fact that the vessel could G
             not be berthed at the SBM and requesting that immediate steps
             be taken to berth the vessel. In the absence of any positive
'            response to the said letter, the Respondents' lawyer, Mr.
             Prashant Pratap, sent a legal notice to the Petitioners on
             24.12.1999 indicating that the vessel continued to await
             discharge incurring demurrage for which the Petitioners were H
    80        SUPREME COURT REPORTS                  [2011] 9 S.C.R.
                                                                           1

A   held responsible. The Petitioners were also informed that on
    account of the detention of the vessel at Vadinar, there was a
    serious possibility of the vessel missing its next engagement.

        6. Finally a decision was arrived at on 28.12.1999 and
    Addendum No.1 to the Charter Party dated 9.11.1999 was
8
    drawn up and signed by the Owners and the Charterers
    containing the following further conditions agreed upon, namely,

         (a) m.t. Prestige will be diverted by the Charterers from
         Vadinar to L.P.O. Mumbai for discharge.
c
         (b) Charterers will pay freight basis Ras Sukheir/LPO
         Mumbai where cargo will be discharged into a daughter
         vessel and Charterers will pay all the expenses of the
         daughter vessel, M.T. Maharaja Agrasen.
0        (c) Charterers will bear the cost of deviation of m.t. Prestige
         basis Ras Sukheir/LPO Mumbai v/s Ras SukheirNadinar/
         LOP Mumbai which included time at the demurrage rate.
         (d) The extra cost of bunkers incurred as a result of the
E        deviation will be on Charterers' account, subject to the
         Owners submitting documentary evidence.

         (e) All direct expenses incurred by the Owners at Vadinar
         towards pilotage, tugs and other port expenses and
         Agency fees, will be settled by the Charterers.
F
         (f) Oemurrage to be settled as per Charter Party terms.

       7. Pursuant to the above arrangement, m.t. Prestige sailed
  from Vadinar at 1 a.m. on 29.12.1999 and arrived at Mumbai
G Lighterage point on 30.12.1999 at 2 p.m. The vessel tendered
  Notice of Readiness at 2 p.m. on 30.12.1999 and completed
  discharge at 3.30 p.m. on 1.1.2000. The Respondents/Owners
                                                                               I
  submitted their demurrage claims along with supporting
  documents to the Charterers on 3.2.2000. As the said claim
H was disputed, arbitration was invoked by the parties under the
                   SHIPPING CORPORATION OF INDIA LTD. v. MARE               81
         r               SHIPPING INC. [ALTAMAS KABIR, J.]
                provisions of the Arbitration & Conciliation Act, 1996, A
              · hereinafter referred to as "the 1996 Act". Both the parties
                appointed their Arbitrators and the two Arbitrators appointed
                a third as the Presiding Arbitrator. The Arbitrators made and
                published their Award dated 26.8.2003 by which they allowed
    ·\
                the Respondents' demurrage claim in full. Certain other B
                amounts payable under the Addendum dated 28.12.1999 were
                also awarded in favour of the Claimants/Respondents.

                    8. The said Award was challenged by the Petitioners/
               Charterers in the Bombay High Court on the ground that the
               Respondents had not proved that the Notice of Readiness had C
               been tendered at Vadinar and consequently the Respondents
               were not entitled to demurrage for the period that m.t. Prestige
               was detained at Vadinar. The learned Single Judge of the High
               Court accepted the submission made on the Petitioners' behalf
               and by his order dated 25.4.2005 remitted the matter to the D
               Arbitration for a proper finding in this regard, with leave to the
               Respondents/owners to lead evidence to prove tender of the
               Notice of Readiness to the Petitioners/Charterers.
                      9. After remand, the Arbitrators passed another Award on     E
                8.9.2005 after admitting fresh evidence, including documentary
                evidence, holding that the service of the Notice of Readiness
                by the Master of the vessel on the Agents of the Petitioners at
                Jamnagar had been duly proved in view of the evidence of the
                 Petitioners' witness, Mr. Sunil D'Souza that he had asked         F
                Captain Jude D'Souza for a copy of the Notice of Readiness
                sent by the Master to the Petitioners' Agents at Jamnagar. The
                 said fact was also confirmed by Mr. S.J. Joshi during his
                evidence before the Tribunal. The Arbitrators also noted that
         .j      no attempt had been made by the Charterers to rebut Mr. Sunil     G
               ) D'Souza's evidence by producing Captain Jude D'Souza.

-              '
                        10. The Tribunal accordingly held that the Respondents/
                   Owners were entitled to receive demurrage in the amount of
                   U.S. $220376.48, together with interest and costs, as awarded
                   in the earlier Award of 26.8.. 2003.                            H
      82         SUPREME COURT REPORTS                [2011] 9 S.C.R.


A       11. On receiving a copy of the Award of the Tribunal dated
  8.9.2005, the Petitioners applied for amendment of the Petition
  under Section 34 of the 1996 Act. However, by order dated
  24.10.2005 the learned Single Judge dismissed the Arbitration
  Petition No.531 of 2003. An appeal, being No.1158 of 2005,
B was filed by the Petitioners before the Division Bench of the          ..
  Bombay High Court which dismissed the same on 20.1.2006.

       12. The present Special Leave Petition has been filed
  against the said Award of the Arbitration dated 8.9.2005, as
  well as the judgments and orders dated 24.10.2005 and
C 20.1.2006 passed by the learned Single Judge and the Division
  Bench of the Bombay High Court confirming the Award.

        13. Mr. Bhaskar Gupta, learned Senior Advocate, who
   appeared for the Petitioners, focused his submissions on the
D sustainability of the Respondents' claim for demurrage. Urging
  that a claim for demurrage can only arise after the expiry of the
  "lay days", namely, the time specified for loading or discharging
  the cargo from the vessel, Mr. Gupta submitted that the all-
  important question in respect of such a claim is when do the
E lay days commence and when are they used up. Mr. Gupta
  submitted that the commencement of lay days depends on three
  factors :-

           (a)   Firstly, the ship must be an "arrived ship" in order
                 to give Notice of Readiness.
F
           (b)   Secondly, she must have given the prescribed
                 notice to load or discharge, as the case may be.
           (c)   Thirdly, she must be ready to load or discharge, as
G                the case may be.
          14. Mr. Gupta submitted that whether the ship is an "arrived
    ship" or not depends on the point designated as the destination
    in the mutual understanding of the parties in the Charter Party           •
    itself or the terms thereof - the degree of precision being a
H
     SHIPPING CORPORATION OF INDIA LTD. v. MARE                    83
r          SHIPPING INC. [ALTAMAS KABIR, J.]
    matter of agreement between the parties. Mr. Gupta urged that        A
    in practice, the destination is usually a part or a specified area
    within the port such as a basin, a dock, or a buoy at a certain
    distance from the shore or a river. A still more precise point
    would be where the loading or discharge is to take place, e.g.,
    a particular quay, pier, wharf or mooring. Mr. Gupta submitted       s
    that a ship is said to be an "arrived ship" only when she has
    reached the particular point and has moored there. Mr. Gupta
    urged that the said propositions are well-established and have
    been laid down in (1) Leonis Steamship Company Ltd. Vs.
    Rank Limited (1908) 1 K.B. 499; (2) Armament Adolf Deppe             c
     Vs. John Robinson & Company Ltd. [1917) 2 K.B. 204; and
    (3) Owners of S.S. Plata Vs. Ford & Co. (1917) 2 K.B. 593.
    We shall have recourse to refer to the aforesaid decisions later
    in this judgment.

         15. Mr. Gupta submitted that Clause 'D' of the Charter          D
    Party dated 9.11.1999, specifies "discharging port" as one/two
    safe anchorage(s)/lighterage point(s)/SBM(s), 1/2 safe Ports,
    1/2 safe Berth(s) and full India. Mr. Gupta also submitted that
    the Charter Party provides that on arrival of the vessel for
    discharge__at Vadinar, the vessel was to maintain 70% of her         E
    deadweight on board for safe mooring at a SBM.

          16. Mr. Gupta urged that by a communication dated
    6.12.1999, the Petitioners/Charterers designated Vadinar SBM
    as the destination and not a 'Port'. The destination was, F
    therefore, a specific point and not a large area like a Port.
    Vadinar SBM, therefore, became the destination as if
    incorporated in the Charter Party itself. Mr. Gupta submitted
    that inspite of the best efforts of the Terminal Authorities, IOC,
    who were also the receivers of the cargo, m.t. Prestige was G
    unable to moor at the Vadinar Single Berth Mooring (SBM) on
    account of the fact that it had only one bow chain. It may be of
    interest to note that Vadinar is the only SBM in the whole of
    India. Mr. Gupta urged that inspite of the various attempts of
    the Port Authorities, the vessel could not be berthed at the
                                                                       H
    84          SUPREME COURT REPORTS                  [2011] 9 S.C.R.


A Vadinar SBM and was asked to move away. Mr. Gupta
  contended that since the vessel could not be moored at
  Vadinar, it was not an "arrived vessel' and "lay time" could not
  be said to have commenced running on 15.12.1999. The
  Notice of Readiness given by the Petitioners could not,
B therefore, be treated as valid and the period spent at Vadinar
  could not be taken into consideration while computing the
  number of lay days utilized.

       17. In support of his aforesaid contention, Mr. Gupta
  referred to and relied on the decision of the House of Lords in
C the case of Johanna Oldendorff, (1973) 11 LLR 285, in which
  Viscount Dilhorne laid down ten tests for determining when a
  ship is an arrived ship. Mr. Gupta referred to the first and fifth
  tests as being relevant in the context of this case and the same
  are extracted hereinbelow :
D
         (i)     That under a port Charter Party to be an "arrived
                 ship", that is to say a ship c1t a place where a valid
                 Notice of Readiness to load or discharge can be
                 given, she must have ended her voyage at the port
E                named; and

         (ii)    A vessel has not reached her port of destination until
                 it has ended its voyage within the port, either in its
                 legal, or if it differs, in its commercial sense. If it is
                 refused permission and ordered to wait outside the
F                port by the Port Authority, it is not an "arrived ship".
       18. Mr. Gupta submitted that the mere fact that the vessel
  had arrived near the SBM and had anchored there would not
  make the vessel an "arrived ship", because the destination was
G the SBM and not the port and the vessel could end her voyage
  only when she was moored at the SBM, which the vessel was
  unable to do. Mr. Gupta submitted that the decision in Johanna
  Oldendorff's case was an affirmation of the Kings Bench
  decision in the case of Leonis Steamship Company Ltd. Vs.
H Rank Limited (1908) 1 K.B. 499. Mr. Gupta urged that not
      SHIPPING CORPORATION OF INDIA LTD. v. MARE                   85
            SHIPPING INC. [ALTAMAS KABIR, J.]
     having been allowed to berth at the SBM, the vessel could not       A
     be categorized as an "arrived ship" for the purpose of issuing
     Notice of Readiness, which Mr. Gupta submitted had not been
     served on the Petitioners in the first place.

.,          19. By way of an alternative argument, Mr. Gupta submitted   B
     that under Clause 6 Part II of the Charter Party, the delay at
     Vadinar could not be counted as lay time, because it was the
     receivers (1.0.C.) and not the Charterers who declared that safe
     berthing of the vessel at Vadinar was not possible because of
     infra-structural deficiencies and not because of any fault on
     behalf of the Petitioners since the Petitioners had no control      C
     over the situation. Accordingly, the entire time from the tender
     of the Notice of Readiness on 15.12.1999, if at all tendered,
     till the vessel started discharge in Bombay, had to be excluded
     in calculating lay time.                                    ·
                                                                         D
          20. Mr. Gupta submitted that service of the Notice of
     Readiness had not been proved even after remand, as the only
     evidence tendered was that of Sunil D'Souza which, in any
     event, did not prove anything beyond the fact that he had been
     asked to get a copy of the Notice of Readiness from the Agent.      E
     Furthermore, the entire evidence of Sunil D'Souza was hearsay.

          21. On the question of Safe Port Warranty, Mr. Gupta
     contended that only after all attempts had been made to berth
     the vessel at the SBM that it was asked to move away from
     the mooring. Consequently, even if the finding of the Arbitrators   F
     that the Petitioners had failed to designate a safe port was
     accepted, at best the ship owners could be entitled to damages
     and not demurrage and would be subject to the ordinary rules
     as to remoteness, mitigation etc., as available under Section
     73 of the Contract Act. Mr. Gupta submitted that the                G
     Respondents had claimed damages before the learned
     Arbitr~tors who, however, allowed demurrage in their Award on
     the ground that demurrage is a genuine pre-estimate of
     damages. Mr. Gupta submitted that even if there was a breach
     of warranty on the Petitioners' part, the same would give rise      H
    86       SUPREME COURT REPORTS                [2011] 9 S.C.R.


A to a claim for damages and not demurrage within the scope of
  Sections 73 and 74 of the Contract Act.

       22. Mr. Gupta submitted that in the Addendum dated
   28.12.1999 to the Charter Party dated 9.11.1999 since the
  Charterers had agreed to bear the cost of deviation basis Ras
B Sukheir/LPO Mumbai vs Ras SukheirNadinar/LPO Mumbai,
  which included time at the demurrage rate, there could not be
  a separate claim for demurrage as that would amount to double
  jeopardy. Mr. Gupta submitted that it is the said provision
  contained in Clause (f) of the aforesaid Addendum which has
C given rise to this arbitration. Mr. Gupta submitted that although
  the Award has relied on Clause 4(1) of Part II of the Charter
  Party, which provides that extra expenses incurred in
  connection with any change in loading or discharging ports, has
  to be paid by the Charterers, and any time thereby lost to the
D vessel shall count as used lay time, the said clause would have
  to be read in the context of Clauses 4(a) and 4(b) where certain
  ports, other than any Indian Port, have been named.
        23. On the question of mitigation of damages, Mr. Gupta
E urged that the Petitioners/Owners had done everything in its
  power to safely berth the vessel at the SBM Vadinar, which was
  perhaps the only SBM in operation in India at the relevant point
  of time and would otherwise have been ideal for discharge of
  the cargo of crude oil. Mr. Gupta contended that it was IOC,
F the receiver, who had taken almost two weeks to decide to
  redirect the vessel from Vadinar to Mumbai. Mr. Gupta
  submitted that it was, in effect, the Respondents who did not
  take any steps to mitigate the damages.
       24. On the quantum of demurrage or damages, Mr. Gupta
G submitted that since the demurrage rate was fixed at US
  $16000 per day and the same has really a genuine pre-
  estimate of damages, the Tribunal should have awarded
  damages at a reasonable rate, instead of making its Award
  on the consideration of damage as fixed in the Charter Party.
H Mr. Gupta urged that the Tribunal had gone completely wrong
          SHIPPING CORPORATION OF INDIA LTD. v. MARE                   87
                SHIPPING INC. [ALTAMAS KABIR, J.)
;
         in giving a go-bye to the provisions of Sections 73 and 74 of A
         the Contract Act in awarding compensation in keeping with the
         provisions for fixed demurrage in the Charter Party, particularly
         when all the lay days had not been used up.

              25. Mr. Gupta submitted that the scope of a petition under
    ..   Section 34 of the 1996 Act had been considered by this Court
                                                                          8
         in detail in Oil & Natural Gas Corporation Ltd. Vs. Saw Pipes
         Ltd. [(2003) 5 sec 705), and it was indicated therein that if
         the Award passed by the Arbitral Tribunal was contrary to any
         of the provisions of the Act or the substantive law governing C
         the parties or was against the terms of the contract, the same
         could be set aside. Mr. Gupta urged that even in the instant
         case, the law had been misapplied by the Arbitrators who had
         missed considering the all-important issue that no valid Notice
         of Readiness could have been tendered by a ship which was
         not an "arrived ship". In such circumstances, the petition under D
         Section 34 of the 1996 Act was clearly not maintainable.
              26. In conclusion, Mr. Gupta drew our attention to the
         wording of Clause 6 of the Charter Party which deals with
         Notice of Readiness and in particular, to the last sentence         E
         thereof where delay in getting a berth for a vessel after giving
         Notice of Readiness, for any reason over which the Charterer
         has no control, shall not count as used lay time. Mr. Gupta
         submitted that the facts of the case would clearly indicate that
         the Arbitral Tribunal failed to take into consideration the facts   F
         in their true sequence and ended up in a "cart before the horse"
         situation, since no demurrage, which is the consequence of
         using up all the lay time, could have been awarded without a
         correct computation of the used "lay time".
              27. Going to the heart of the matter, Mr. Prashant Pratap, G
         learned Advocate, submitted that the case of the Petitioners/
         Charterers of the vessel depended primarily on the terms and
         conditions of the Charter Party on the basis whereof the Arbitral
         Tribunal had awarded demurrage to the Respondents/Owners
         of the vessel. As was also done by Mr. Gupta, special H
    88        SUPREME COURT REPORTS                 [2011) 9 S.C.R.


A emphasis was laid by Mr. Prashant Pratap on Clause 6 of the             '
  Charter Party relating to Notice of Readiness. Learned
  counsel emphasized the fact that in terms of the said clause,
  the Master of the vessel or his Agent would give the Charterer
  or his Agent notice by letter, telegraph, wireless or telephone
B that the vessel is ready to load or discharge cargo, berth or no
  berth, and lay time would commence upon the expiration of six
  hours from receipt of such notice or upon the vessel's arrival
  in berth, which would mean finished mooring when at a sea
  loading or discharging terminal and all fast when loading or
c discharging alongside a wharf whichever first occurs. Then
  follows the rider that, however, where the delay is caused to
  the vessel getting into berth after giving Notice of Readiness
  for any reason over which the Charterer has no control, the delay
  caused could not be counted as used lay time.
D        28. Mr. Prashant Pratap referred to Clauses 8 and 9 of
    the Charter Party dealing with Demurrage and Safe Berthing
    Shifting. Clause 8 provides that the Charterer shall pay
    demurrage per running hour and pro rata for a part thereof at
    the rate specified in Part I for all the time taken for loading and
E   discharging when the time taken for discharging the cargo
    exceeds the allowed lay time specified. If, however, delay in
    discharge of the cargo is caused at the port of loading and/or
    discharge by reason of fire or other unavoidable circumstances,
    the rate of demurrage would be reduced to one-half of the
F   amount stated in Part I per running hour or pro rata for part of
    an hour for demurrage so incurred. It was also stipulated that
    the Charterer would not be liable for demurrage for delay
    caused by strike, lockout, stoppage or restraint of labour for
    master, officers and crew of the vessel or tugboat or pilots. Mr.
G   Prashant Pratap also pointed out that Clause 9 of the Charter
    Party which provides for Safe Berthing Shifting indicates that
    the vessel shall load and discharge at any safe place or wharf,
    or alongside vessels or lighterage point reachable on her
    arrival, which shall be designated and procured by the
H   Charterer, provided the vessel could proceed thereto, lie at and
  SHIPPING CORPORATION OF INDIA LTD. v. MARE                   89
        SHIPPING INC. [ALTAMAS KABIR, J.]

depart therefrom always safely afloat. Clause 9 also enables          A
the Charterer to shift the vessel at ports of loading and/or
discharge from one safe berth to another on payment of towage
and pilotage for shifting to the next berth and other expenses
and the time consumed on account of such shifting would count
as used lay time, except as otherwise provided in Clause 15.          B

       29. Mr. Prashant Pratap then contended that the question
 as to whether M/s. m.t. Prestige was an "arrived ship" or not at
 port Vadinar, had never been raised either before the learned
 Single Judge or the Division Bench of the High Court, nor was        C
 it taken as a ground in the Special Leave Petition. Learned
 counsel submitted that even the ground taken with regard to the
 Notice of Readiness being invalid, as the vessel was allegedly
 not ready in all respects to discharge its cargo, was neither
·argued before the learned Single Judge or the Division Bench
 nor was the ground taken in the Special Leave Petition before        D
 this Court.

      30. Coming to the question as to what constitutes an
"arrived ship", Mr. Prashant Pratap submitted that the said
question was extensively considered by the House of Lords in          E
the case of Johanna Oldendorff (supra), which was also relied
upon by Mr. Gupta, where the House of Lords was of the view
that the vessel should have reached a position in the port where
she is at the immediate and effective disposition of the
Charterers and for practical purposes it is so much easier to         F
establish that if the ship is at the usual waiting place within the
port where waiting vessels would normally lie before
proceeding to the berth nominated by the Charterers for
discharge of cargo. If the vessel is at such a place, then the
vessel is considered to be an "arrived ship". It is only thereafter   G
that the vessel can tender Notice of Readiness. Furthermore,
if the Charter Party provides for the location where the vessel
should arrive and tender Notice of Readiness, then if the vessel
has reached that location, the vessel is considered to be an
"arrived ship". Mr. Prashant Pratap submitted that in the present     H
   90        SUPREME COURT REPORTS               [2011] 9 S.C.R.

A Charter Party, the parties have expressly agreed in Clause 6
  for the vessel to arrive at customary anchorage (emphasis
  supplied) at the port of loading or discharge and tender Notice
  of Readiness. Accordingly, once the vessel arrived at
  anchorage at Vadinar, it became an arrived ship in terms of
8 Clause  6 of the Charter Party and was entitled to tender Notice
  of Readiness.

       31. Mr. Prashant Pratap submitted that it was not disputed
  that Mis. m.t. Presitge was at customary anchorage at Vadinar
  Port when Notice of Readiness was tendered. Mr. Prashant
C Pratap also placed emphasis on the expression "berth or no
  berth", included in Clause 6 of the Charter Party which meant
  that even if a berth was not available or the vessel had not
  reached the berth, the vessel is entitled to tender Notice of
  Readiness. Mr. Prashant Pratap submitted that the term had
D been explained in the case of the NOTOs where dealing with
  a clause identical to Clause 6 of the Charter Party, it was held
  that the meaning of the said words indicated that the Notice
  of Readiness could be given upon arrival at the customary
  anchorage and could take effect whether or not a berth was
E then available or not for the vessel.

       32. Mr. Prashant Pratap then argued that the submission
  made on behalf of the Petitioners/Charterers that since the
  destination in the Charter Party had been shown as "SBM" and
F the vessel had failed to be moored at the SBM, no demurrage
  could be claimed, was wholly erroneous on account of the fact
  that such notice could be tendered on the arrival of the vessel
  at the customary anchorage. The vessel is not, therefore,
  required to be at the destination within the port for the purpose
G of becoming an "arrived ship" and for tendering of Notice of
  Readiness.
       33. Referring to Mr. Gupta's submissions that for the
  purpose of tendering Notice of Readiness, the vessel must be
  an arrived ship, Mr. Prashant Pratap submitted that the vessel,
H therefore, must be at the effective disposal of the Charterers
       SHIPPING CORPORATION OF INOIA LTD. v. MARE                       91
             SHIPPING INC. [ALTAMA$:1(A8lR, J.).
     who would have unrestricted access to the vessel's cargo                  A
     tanks and the vessel pumps must b~ inworking order to pump
     out the cargo upon the hoses being,connected, provided that
     the Charterers were ready to receive the cargo. In this regard,
     Mr. Prashant Pratap referred to the decision in the Leonis
     Steamship Co. Ltd. (supra), where it was observed by Lord                 B
     Justice Kennedy that "the ship's obligations, therefore, under
     such a Charter Party the performance of which much precede
     the commencement of the lay days (as the fixed loading period
     is commonly termed) are three : Firstly, the ship must have
     arrived at her destination and so be within the designation of            C
     an arrived ship. Till then she is not entitled to give a Notice of
     Readiness to load. Secondly, she must have given the
     prescribed Notice of Readiness to load. Thirdly, she must, in
     fact, be so far as she· is concerned, ready to load. The ship
     owner cannot claim against the Charterer that the lay days
                                                                               0
     begin to count until the ship is an arrived ship; .............. ." Mr.
     Prashant Pratap submitted that the .aforesaid passage made
     it clear that the vessel has to be ready to load or discharge,
     as the case may be. The Tribunal's,flndings are that the vessel
     was ready, but the terminal was not. The Tribunal held that the
     vessel was at the immediate and effective disposition of the              E
     Charterers when Notice of Readiness was given.

            34. Mr. Prashant Pratap then urged that from the Charter
.,     Party it is quite clear that the responsibility of providing a berth
       where the vessel could moor safely was that of the Charterers           F
       and the same would be clear from the use of the word "safe"
       in Clause D of Part I of the Charter Party which precedes the
       words "Ahchorage/Lighterage Points/SBM". Even in terms of
       Clause 9 of the Charter Party, the place of discharge must be
       safe and has to be designated and procured by the Charterers.           G
       Mr. Prashant Pratap referred to various other judgments such
       as the Sea Queen [(1988) Vol.1 KKR 500) and Fjordaas
       [(1988) Vol.1 LLR 336). In the later case, it has been indicated
     . that "reachable" or "arrival" are well-known expressions and
       mean precisely what they say. It was further observed that if           H
    92       SUPREME COURT REPORTS                [2011] 9 S.C.R.


A the berth cannot be reached on arrival, the warranty is broken,
  unless there is some relevant protecting exception. Such berth,
  in its term, is required to have two characteristics: it has to be
  safe and it also has to be reachable on arrival. By nominating
  SBM at Vadinar as the destination of the vessel and also the
B place for discharge of the cargo, it was the responsibility of the
  Charterers to ascertain as to whether the vessel could be
  moored there safely and be in a position to discharge the cargo
  safely.

        35. Apart from the aforesaid questions regarding the vessel
C being an arrived ship, Mr. Prashant Pratap urged that service
  of the Notice of Readiness by the Master on the Agents of the
  Charterers have been duly proved and is a finding based on
  appreciation of evidence by the Arbitrators, which has been
  upheld by the learned Single Judge and the Division Bench,
D whose orders were under challenge in the Special Leave
  Petition.

        36. Mr. Prashant Pratap uri;ied that if the Notice of
  Readiness was valid, as had been found not only by the Arbitral
E Tribunal but also by the learned Single Judge and the Division
  Bench of the Bombay High Court, then lay time commenced
  six hours after the tender of Notice of Readiness. Accordingly,
  lay time expired on 17.12.1999, and, thereafter, the vessel was
  on demurrage all throughout, till discharge of the cargo was
F completed. Since in the instant case, the Charterers had failed
  to nominate a safe berth at which the vessel could safely lie
  and discharge the cargo and failing to provide a berth which
  was reachable upon arrival of the vessel at Vadinar, the
  consequent delay in berthing and discharge of the cargo, was
G the responsibility of the Charterers for which demurrage was
  payable by them. Mr. Prashant Pratap pointed out that at no
  stage did the Charterers question the validity of the Notice of
  Readiness tendered at Vadinar either on the ground that the
  vessel was not an arrived ship, or on the ground that the vessel
  was not ready to discharge the cargo. On the contrary, the
H
...           SHIPPING CORPORATION OF INDIA LTD. v. MARE
                    SHIPPING INC. [ALTAMAS KABIR, J.]
                                                                          93


            Charterers signed the Addendum dated 28.12.1999 by which            A
            they agreed to bear all the expenses incurred by the vessel at
            Vadinar and also agreed to pay additional freight charges for
            discharge of cargo at Mumbai. Significantly, the Charterers
            also agreed that the time taken for the vessel to proceed from
            Vadinar to Mumbai would count as demurrage time. Mr.                B
            Prashant Pratap urged that the Charterers would not have
            agreed to the terms and conditions of the Addendum if it was
            their contention that the vessel was not an arrived ship or that
            the Notice of Readiness was invalid.

                 37. Mr. Prashant Pratap then submitted that the only
                                                                                c
            requirement as far as the vessel was concerned was that it had
            to maintain 70% of the dead weight on board for safe mooring
            at the SBM at Vadinar and it is nobody's case that the vessel
            did not conform to such condition.                            ·
                                                                                D
                 38. On the question of designation of the SBM as the
            destination point within Vadinar Port by the Charterers, Mr.
            Prashant Pratap contended that the Charterers had been put
            on notice regarding the berthing arrangement both in the
            Charter Party as well as in the questionnaire setting out the       E
            vessel's mooring arrangements provided to the Charterers.
            Learned counsel submitted that it was for the Charterers to
            check the vessel equipment vis-a-vis facilities available at the
      -.,   Port of loading and discharge, before nominating the same.
            Since the Charterers had failed to undertake such an exercise,      F
            there was a resultant problem faced at Vadinar whereby the
            vessel could not discharge its cargo at Vadinar but had to be
            diverted to Mumbai. Mr. Prashant Pratap also pointed out that
            while the entire Indian coastline was available to the Charterers
            to nominate a safe port for discharge of the cargo, it made a       G
            conscious decision to nominate the SBM at Vadinar which
            ultimately turned out to be unsafe for mooring of the vessel,
            given the equipment available on board the ship.

                39. Mr. Prashant Pratap submitted that it had been agreed
            on behalf of the Charterers that demurrage is a genuine pre-        H
    94         SUPREME COURT REPORTS                [2011] 9 S.C.R.


A estimate of damages and even if the Charterers' argument is
                                                                          -
  to be accepted that the owners are entitled to damages and
  not demurrage, the calculation of such damages would have
  to be the demurrage rate in the facts and circumstances of the
  case.
B
       40. Mr. Prashant Pratap, accordingly, submitted that the
  award of the Arbitral Tribunal, as upheld both by the learned
  Single Judge and the Division Bench of the Bombay High
  Court, did not warrant any interference and the Special Leave
C Petition was liable to be dismissed with appropriate costs.
       41. Having gone through the submissions made on behalf
  of the respective parties in the background of the facts as
  disclosed, it is clear that we are required to consider two basic
  questions for the purpose of deciding the present Special
D Leave Petition, namely :-                                 ·

         (a)    Whether on arriving at anchorage point at Port
                Vadinar, despite the destination point being the
                SBM mooring, it could be said that it was an arrived
                ship which was competent under the Charter Party
E
                dated 9.11.1999, to issue Notice of Readiness of
                discharge of its cargo?

         (b)    If the finding of the Arbitral Tribunal that the vessel
                was an arrived ship at Port Vadinar, as upheld by
F               the learned Single Judge and the Division Bench
                of the Bombay High Court is accepted, would the
                Respondents/Owners of the vessel be entitled to
                damages or demurrage?
G        42. Various ancillary questions connected with the
    aforesaid two questions also crop up, which we shall consider
    shortly.
         43. From the undisputed facts, the position that emerges
    is as follows :-
H
            SHIPPING CORPORATION OF INDIA LTD. v. MARE                      95
                  SHIPPING INC. [ALTAMAS KABIR, J.]
..,   ~

      '          (i)     The Charter Party dated 9.11.1999 was in respect         A
                         of a transaction which provided for carriage of
                         crude oil from Ras Sukheir to a safe port on the
                         Indian coastline. The Charterers were given the
                         choice of nominating such port for discharge of the
                         aforesaid cargo of crude oil.                            B
                 (ii)    In the absence of any named port of destination in
                         the Charter Party itself, it was only after the vessel
                         left Ras Sukheir that an intimation was given by the
                         Charterers for discharge of the cargo at the SBM
                         at Port Vadinar in Gujarat.
                                                                                  c
                 (iii)   That the aforesaid nomination was a conscious
                         decision on the part of the Charterers, despite
                         having knowledge of the equipment available on
                         board the vessel for mooring at a SBM, and in            D
                         keeping with such decision m.t. Prestige set its
                         course from Ras Sukheir to Vadinar.
                 (iv)    The fiasco at Vadinar was occasioned by the fact
                         that no prior checking had been done to see
                                                                                  E
                         whether with the mooring equipment on board, the
                         vessel would be able to safely berth at the SBM for
                         discharge of its cargo.

                 (v)     Who was responsible for the detention of the vessel
                         at Vadinar since its arrival at the anchorage point      F
                         and its final departure from the said Port? Whether
                         there was contributory negligence on the part of
                         both the parties in the cause of such delay?

                 44. The concept of an arrived ship in shipping terminology G
            requires that a vessel should reach a destination in a port where
          -sf:le..could_b~...§_afely berthed and thereupon be ready to either
            discharge or load-cargo from and on to the vessel. That is a
            general concept, but the Charterers and the Owners of the
            vessel could in the Charter Party agree to a specific destination
                                                                              H
    96        SUPREME COURT REPORTS                [2011] 9 S.C.R.


A point within the port area for discharging or loading of cargo.
  Once the vessel arrived at the said spot and was ready to
  discharge its cargo, it could be described as an "arrived ship"
  with the authority to issue and tender Notice of Readiness. In
  the instant case, the nominated port for the arrival of the vessel
B was Vadinar Port, but the destination point was the SBM where
  the vessel was to be moored and was to discharge its cargo
  of crude oil. In fact, in the Charter Party dated 9.11.1999,
  Clause 6 specifically provided for arrival of the vessel at the
  port of loading or discharge and cast an obligation upon the
c Master or his Agent to give the Charterer or his Agent Notice
  of Readiness in relation to discharge of the cargo. Since the
  decision in this case will to a large extent depend on the
  interpretation of Clause 6, the same is extracted hereinbelow :

         "Clause 6 Notice of Readiness :
D
         Upon arrival at customary anchorage at each port of
         loading or discharge, the Master or his Agent shall give
         the charterer or his Agent notice by letter, telegraph,
         wireless or telephone that the vessel is ready to load or
E        discharge cargo berth or no berth and lay time as
         hereinafter provided shall commence upon the expiration
         of six (6) hours after receipt of such notice or upon the
         vessel arrival in berth - finished mooring when at a sea
         loading or discharging terminal and all fast when loading
F        or discharging alongside a wharf which ever first occurs.
         However, where delay is caused to vessel getting - berth
         after giving notice of readiness for any reason over which
         charterer has no control, such delay shall not count as used
         lay time."
G      45. As will be evident from the above clause, the Master
  of the vessel was under an obligation to give Notice of
  Readiness on arrival at the customary anchorage at the port
  of discharge. It is a possibility that since no specific port in
  the Indian coastline had been mentioned in the Charter Party,
H the Master of the vessel or his Agent was required to give
 SHIPPING CORPORATION OF INDIA LTD. v. MARE                    97
       SHIPPING INC. [ALTAMAS KABIR, J.]

Notice of Readiness upon the vessel arriving at customary            A
anchorage. It is only after the vessel sailed from Ras Sukheir
that the receiver, IOC, nominated Vadinar to be the port of
discharge with the specific destination point being the SBM
within the port. In giving such Notice of Readiness upon arrival
at the customary anchorage at Vadinar, the Master of the             B
Vessel duly complied with the conditions of Clause 6 of the
Charter Party and in terms of the aforesaid clause irrespective
of whether a berth was available or not, lay time commenced
upon the expiry of six hours after receipt of such notice. That
the vessel could not be moored at the SBM is a different facet       c
of the story. The Charterers had full knowledge of the equipment
on board m.t. Prestige through the questionnaire provided by
the Respondents/Owners to the Petitioners/Charterers. It could
not be denied that despite having such knowledge the IOC.
nominated the SBM as the destination point for discharge of          0
the cargo. Obviously, the parties to the Charter Party had not
made any attempt to verify as to whether the equipment on
board the vessel was sufficient for her to be safely moored at
the SBM and to discharge her cargo safely. As it turned out
later on, the vessel was not so equipped and could not,
therefore, be moored at the SBM and had to be requested to           E
move away therefrom. Although, an attempt has been made
on behalf of the Charterers to convince us that it was really the
duty and responsibility of the Owner of the vessel to check
whether the vessel could be safely moored at the SBM in
Vadinar, we are unable to convince ourselves that such a duty        F
was that of the Owners of the vessel and not the Charterers
which had a choice of all the ports in India for discharge of the
cargo, as was subsequently done in Mumbai port. As has been
held by the Arbitral Tribunal and subsequently affirmed both by
the learned Single Judge and the Division Bench of the Bombay        G ,
High Court, the responsibility for the failure of the ship to moor
at the SBM in Vadinar must lie squarely with the Charterers and
the receiver as it was they who had nominated the SBM for the
safe mooring of the vessel. The lay time must, therefore, be
held to have recommenced after the expiry of six hours from          H
    98        SUPREME COURT REPORTS               [2011) 9 S.C.R.


A the tendering of the Notice of Readiness upon the vessel's
  arrival at the customary anchorage at Vadinar on 15.12.1999
  in keeping with the provisions of Clause 6 of the Charter Party.
  It was not the case of the Charterers that the failure of the
  vessel to discharge its cargo at the SBM at Vadinar was for
B reasons beyond their control. It cannot also be said that the
  owners of the vessel contributed in any way to such failure since   ..
  the equipment on board the vessel had been made known to
  the Charterers when the Charter Party was signed.
         46. In the face of the specific conditions indicated in
C Clause 6 of the Charter Party, the theoretical and/or academic
  exercise of what constitutes an "arrived ship" loses much of its
   relevance. The terms of the Charter Party were agreed upon
   by the parties with their eyes wide open. What is also
  significant and cuts at the root of the submissions advanced
D on behalf of the Charterers is that even after the vessel was
  denied mooring at the SBM for safety reasons on 21.12.1999,
   no steps were taken on behalf of the Petitioners to either
  arrange for an alternate safe berthing in Vadinar or to give
  instructions as to where the cargo was to be discharged. In
E fact, on behalf of the Respondents/Owners a legal notice was
  addressed to the Petitioners on 24.12.1999 pointing out that
  the vessel continued to await discharge incurring demurrage.
  It is only thereafter that Addendum No.I to the Charter Party was
  drawn up and signed on 28.12.1999 by the Owners and the
F Charterers, whereby m.t. Prestige was diverted by the
  Charterers from Vadinar to a Lighterage point at Mumbai port
  for discharge and it was specifically agreed that the Charterers
  would bear all the costs of discharge, including freight charges
  and the expenses of the daughter vessel, m.t. Maharaja
G Agrasen. It was also agreed that demurrage would be settled
  as per the terms of the Charter Party. In our view, the various
  decisions cited on behalf of the Petitioners/Charterers do not
  help them in the facts of this case. We do not, therefore, think
  it necessary to consider all the decisions cited on behalf of the
H respective parties and those referred to hereinbefore are
          SHIPPING CORPORATION OF INDIA LTD. v. MARE                  99
                SHIPPING INC. [ALTAMAS KABIR, J.]
    /I
         sufficient for our purpose. The decisions relied upon by the       A
         parties lay down certain propositions of law which are well-
         established and with which there cannot be any disagreement,
         but for the purposes of this case they are basically academic.
              47. Once we have affirmed the finding that m.t. Prestige
                                                                            B
~
         was an arrived ship on reaching the customary anchorage at
         Vadinar port and once we have also held that it was the
         Charterers who having the choice of a safe port, had selected
         the SBM at Vadinar as the discharge point, the suggestion
         made on behalf of the Charterers that it was the responsibility
         of the Owners of the vessel to check whether the ship could be     c
         safely moored at the SBM, is untenable. The responsibility of
         the Owners of the vessel ended with the declaration of the
         equipment available on board for mooring and berthing for the
         purpose of discharge of its cargo. Consequently, all the other
         ancillary issues which arise have to be answered in favour of      D
         the Respondents herein. As indicated hereinbefore, the fiasco
         at Vadinar was occasioned by the fact that no prior checking
         had been done by the Charterers to ascertain as to whether
         with the mooring equipment on board the vessel she would be
         able to moor safely at the SBM for discharge of her cargo.         E
         Even the subsequent deviation of the vessel from Vadinar to
         Mumbai was not on account of any laches on the part of the
         Owners of the vessel who were awaiting instructions once the
         vessel had been asked to move away from the SBM. In fact, it
         took a notice from the Owners of the vessel and a week for the     F
         Charterers to galvanize themselves into action, which ultimately
         resulted in the Addendum No.1 dated 28.12.1999.
             48. Read with Clause 6 of the Charter Party, the Addendum
         dated 28.12.1999 makes it abundantly clear that the Charterers
         had accepted the responsibility for the failure of the vessel to   G
         discharge her cargo at Vadinar and had agreed to bear all the
         expenses for the delay in diversion of the vessel from Vadinar
         to Mumbai, including the time spent at Vadinar port and the
         expenses incurred towards pilotage, tugs and other port
         expenses.                                                          H
    100      SUPREME COURT REPORTS                 [2011] 9 S.C.R.


A      49. Apart from the above, Clause 4(1) of Part II of the
  Charter Party specifically provides that extra expenses incurred
  on account of any change in loading or discharging ports, has
  to be paid by the Charterers, and any time thereby lost to the
  vessel shall count as used lay time. We are not inclined to
B accept Mr. Gupta's submission that the aforesaid clause has
  to be read in the context of Clauses 4(a) and 4(b) which refer
  to ports other than Indian Ports in a different context.

       50. We, therefore, see no reason to interfere with the
  Award of the Arbitral Tribunal and the decisions, both of the
C learned Single Judge and the Division Bench, confirming the
  Award of the Arbitral Tribunal and, accordingly, dismiss the
  Special Leave Petition. In the facts of the case, the parties shall
  bear their own costs as far as these proceedings are
  concerned.
D
    D.G.                        Special Leave Petition dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "demurrage"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.