Created byFuzzy Cloud

Supreme Court of India

SAYEED AHMED & CO.versusSTATE OF UP & ORS.

Citation
2009 INSC 896
Decided
9 July 2009
Disposal
Case Partly allowed

Holding

The contractual bar bars interest for the pre‑reference and pendente‑lite periods, but the arbitrator may award interest from the date of the award at the rate specified in the award, and the High Court’s reduction of that rate to 6% is untenable.

Summary

The appellant, a contractor, completed a construction project for the State of Uttar Pradesh in 1996, after which disputes over payment led to arbitration in 1997. The arbitrator awarded the respondents to pay the contractor Rs.24,18,586 with interest at 18% per annum from April 1996, and also specified interest rates for amounts due on finalisation and security deposit. The contract contained clause G‑1.09, which expressly barred any claim for interest or damages, prompting the respondents to challenge the award under Section 34 of the Arbitration and Conciliation Act, 1996. The High Court set aside the award of interest up to the date of the award and reduced the post‑award interest rate to 6% per annum, a decision the contractor appealed. The Supreme Court held that the contractual bar precludes interest for the pre‑reference and pendente‑lite periods, but does not affect interest payable from the date of the award, which must follow the rate specified by the arbitrator under Section 31(7)(b). Consequently, the Court affirmed the High Court’s setting aside of pre‑award interest but restored the arbitrator’s post‑award interest rates, partially allowing the appeal.

Issues considered

  • Whether an arbitrator can award interest for the pre‑reference and pendente‑lite periods when the contract contains an express prohibition on interest.
  • Whether the contractual prohibition extends to interest payable from the date of the award and what rate of interest is permissible under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996.

Legislation cited

Subjects

ArbitrationInterest awardArbitration and Conciliation Act 1996Section 31Contractual bar to interestPre‑reference periodPendente liteSection 34Interest Act 1978

Judgment

.....                              [2009] 10 S.C.R. 841


                                    SAYEED AHMED & CO.                           A
                                                V.
                                    STATE OF UP & ORS.
                                (Civil Appeal No. 4197 of 2009)
                                          JULY 9, 2009
                                                                                 B
                      [R. V. RAVEENDRAN AND P. SATHASIVAM, JJ.)
              ~


                       Arbitration and Conciliation Act, 1996: s.31(7)(a) and (b)
                  - Power of arbitrator to award interest - Pre-reference period,
                  pendente lite and future interest - Held : If arbitration c
                  agreement bars payment of interest, then such bar would
                  operate for pre-reference period and pendente lite only i.e.
                  only till date of award and not thereafter - Award of interest
                  by arbitrator from date of award till date of payment@ 18%
                  p.a. upheld.                                                    D

                       The construction work entrusted to appellant under
                   an agreement was completed on 31.3.1996. The
                  respondent rejected some of the claims of appellant
                  which gave rise to dispute. The matter was referred to
                                                                              E
                  arbitrator on 13.3.1997. The arbitrator made an award
                  dated 31.7.2001 directing the respondents to pay to the
                  appellant Rs.24, 18,5861- with interest at 18% p.a. from
                  1.4.1996 till date of payment; the amount if any, due to
                  appellant on finalizing the final bill with interest at 14%
                  p.a. from 1.5.1996 till date of payment; and the security F
                  deposit amount due with interest at 12% p.a. from
                  1.10.1996 till date of payment. The application was filed
                  under Section 34 of Arbitration and Conciliation Act, 1996
                  for setting aside the award, which was dismissed.
                                                                                G
        ..,           The High Court held that having regard to the bar
                  contained in clause G 1.09 of the contract, the arbitrator
                  had no power to award interest and consequently, it set
                  aside that part of the award granting interest till date of
                                            841                               H
    842      SUPREME COURT REPORTS             [2009] 10 S.C.R.
                                                                     -
A   award. It however granted interest at 6% p.a. from the
    date of award till the date of payment. Hence the appeal.

          Partly allowing the appeal, the Court

       HELD : 1.1. The legislature while enacting the
B Arbitration and Conciliation Act, 1996, incorporated a
  specific provision in regard to award of interest by
  Arbitrators. Sub-section (7) of section 31 of the Act deals
  with the arbitrator's power to award interest. Clause (a)
  relates to the period between the date on which the cause
C of action arose. and the date on which the award is made.
  Clause (b) relates to the period from the date of award to
  date of paymen~. [Para 10] [849-E-F]

       Secretary, Irrigation Department, Govt. of Orissa vs. G. C.
D Roy 1992 (1) SCC 508; Executive Engineer, Dhenkanal
  Minor Irrigation Division vs. N. C. Budharaj 2001 (2) SCC 721;
  Bhagawati Oxygen Ltd. vs. Hindustan Copper Ltd. 2005 (6)
  SCC 462; Superintending Engineer v. Subba Reddy 199 9
  (4) SCC 423 and State of Rajasthan v. Ferro Concr.ete
E Construction Pvt. Ltd. 2009(8) SCALE 753, referred to.

       1.2. Clause G-1.09 of the Contract makes it clear that
  no interest or damages will be paid by Government, in
  regard to : (i) any money or balance which may be lying
  with the Government; (ii) any money which may become
F due owing to any dispute, difference or misunder-
  standing between the Engineer-in-charge on the one
  hand and the contractor on the other hand; (iii) any delay
  on the part of the Engineer-in-Charge in making
  periodical or final payment; or (iv) any other respect
G whatsoever. The clause is comprehensive and bars
  interest under any head in clear and categorical terms.
  In view of clause (a) of sub-section (7) of section 31 of
  the Act, it is clear that the Arbitrator could not have
  awarded interest upto the date of the award, as the
H
~              SAYEED AHMED & CO. v. STATE OF U P & ORS.              843

         ~
             agreement between the parties barred payment of A
             interest. The bar against award of interest would operate
             not only during the pre-reference period that is up to
             13.3.1997 but also during the pendente lite period that is
             from 14.3.1997 to 31.7.2001. Whether the provision in the
             contract bars the employer from entertaining any claim B
             for interest or bars the contractor from making any claim
             for interest, it amounts to a clear prohibition regarding
             interest. The provision need not contain another bar
             prohibiting arbitrator from awarding interest. [Paras 11
             and 14] (850-H; 855-D-E]                                   c
                  State of U.P. v. Harish Chandra & Co. 1999 (1) sec 63;
             State of Orissa vs. 8.N. Agarwal/a 1997 (2) Sec 469, held
             inapplicable.
        )_
                 Board of Trustees for Port of Calcutta vs. Engineers-De-   D
             Space-Age 1996(1) SCC 516, referred to.

                   1.3. The arbitrator awarded interest at the rate of 18%
              p.a. on Rs.24.18 lacs, 14% p.a. on amount found due on
             finalisation the final bill and 12% p.a. on the security
                                                                             E
             deposit amount if any that has to be refunded. Clause (b)
             of sub-section (7) of section 31 of the Act provides that if
             the award does not otherwise direct, the amount awarded
    ~
             shall carry interest at 18% p.a. Any provision in the
             contract barring interest, will therefore operate only till the
                                                                             F
             date of award and not thereafter. The arbitrator has
             awarded interest at three different rates on three different
             amounts which are all less than 18% p.a. The said award
             of interest by the arbitrator is not contrary to section
             31(7)(b) of the Act. Unless the award of interest is found
             to be unwarranted for reasons to be recorded, the court G
             should not alter the rate of interest awarded by the
             Arbitrator. The High Court did not assign any reasons for
             reducing the rate of interest to 6% p.a. Therefore, such
             reduction cannot be sustained. The rate of interest on the
                                                                             H
    844       SUPREME COURT REPORTS                [2009] 10 S.C.R.


A   amounts due and payable under the award, from the date
    of award till date of payment shall be in terms of the award
    of the arbitrator. [Paras 18 and 19] [856-B-E; 856-G]

                         Case Law Reference:

B         1992 (1) sec 508           referred to          Para 9

          2001 (2) sec 121           referred to          Para 9

          2005 (6) sec 462           referred to          Para 9

          1999 (4) sec 423           referred to          Para 9
c
          2009(8) SCALE 753          referred to           Para 9

          1999 (1) sec 63            held inapplicable Para 12

          1997 (2) sec 469           held inapplicable Para 13
D
          1996 (1) sec 516           referred to           Para 14

        CIVIL APPELLATE JURISDICTION : Civil Appeal No.
    4197 of 2009.

E       From the Judgment & Order dated 27.2.2008 of the High
    Court of Uttarakhand at Nainital in A.O. No. 457 of 2006.

          Vinay Kumar Garg for the Appellant.

         Pramod Swarup, T.N. Singh, Chandra Prakash Pandey for
F   the Respondents.

          The Judgment of the Court was delivered by

        R.V. RAVEENDRAN J. 1. Leave granted. The issue in
G this appeal is whether the Arbitrator can award interest for pre-
  reference period and pendente lite, when the contract prohibits
  the employer from entertaining any claim for interest.

        2. The respondents entrusted a construction work to
    appellant under an agreement dated 30.3.1990. The work was
H
        SAYEED AHMED & CO. v. STATE OF U P & ORS. 845
                  [R. V. RAVEENDRAN, J.]

      completed by the appellant on 31.3.1996. Disputes arose                 A
      between the parties by reason by rejection of claims of
      appellant and they were referred to Arbitration on 13.3.1997.
      Before the Arbitrator, the appellant made 11 claims
      aggregating to Rs.133.43 lakhs. The Arbitrator made an award
      dated 31.7.2001 directing the respondents to pay to the                 B
      appellant the following:-

           (i) Rs.24,18,586/- with interest at 18% PA from 1.4.1996
           till date of payment.

           (ii) The amount if any, due to appellant on finalizing the final   c
           bill with interest at 14% PA from 1.5.1996 till date of
           payment; and

           (iii) The security deposit amount due with interest at 12%
           PA from 1.10.1996 till date of payment.                    D
            3. The civil court by its judgment dated 7.12.2005
       dismissed the application to set aside the award, filed by the
       respondents under section 34 of the Arbitration and
       Conciliation Act, 1996 ('Act' for short). The appeal filed by the
       respondents was allowed in part by the High Court by impugned          E
      judgment dated 27.2.2008. The High Court held that having
      regard to the bar contained in clause G 1.09 of the contract,
      the arbitrator had no power to award interest and consequently,
      set aside that part of the award granting interest till date of
      award. The High Court however granted interest at 6% PA from            F
      the date of award till the date of payment. Aggrieved by the
      deletion of interest upto the date of award and reduction of
      interest from the date of award to 6% per annum, the appellant
      has filed this appeal.
                                                                              G
-•,       4. At the outset, it is necessary to refer to an erroneous
      assumption made by the High Court in para 31 of the impugned
      judgment. It has proceeded on the basis that the sum of
      Rs.24, 18,586/- awarded by the Arbitrator includes the amount
      due in regard to the final bill as also the amount of security
                                                                              H
    846          SUPREME COURT REPORTS               [2009] 10 S.C.R.

                                                                           •
A   deposit and that interest has been awarded from different
    dates, on different parts of the said sum of Rs.24, 18,586/-. But          .,,.
    the award of Rs.24, 18,586/- did not include the amount due in
    regard to the final bill or security deposit. In fact the arbitrator
    did not quantify the amount due in regard to the final bill or the
B   security deposit, but directed the respondents to calculate and
    pay the same with interest as indicated in the award. We give
    below the break up of Rs.24, 18,586/- awarded by the arbitrator,
    to show that the said amount did not include the final bill dues
    or security deposit :
c     SI. Claim No. Description of claim             Amount
      No.                                            awarded

      (i)         (1)    For non-availability of site Rs.6,30, 130/-

D     (ii)        (2)    For non-payment for         Rs.3,90,000/-
                         20,000 cubic meters of
                         earth work

     (iii)        (3)    For non-availability of     Rs. 20,000/-
                         drawings & design
E
     (iv)         (4)    For variations in quantity Rs.1,03,500/-
                         of different items of work

     (v)          (5)    For extra items             Rs. 72,956/-

F    (vi)         (8)    For stoppage of work        Rs. 31,500/-

     (vii)        (9)    For non-availability of     Rs. 84,000/-
                         cement

     (viii)       (10)   For delay in completion     Rs. 1,55,000/-
G
                         of work

    Re : Interest from the date of cause of action to date of
    award

H            6. The issue regarding interest as noticed above revolves
               SAYEED AHMED & CO. v. STATE OF U P & ORS. 847
                         [R. V. RAVEENDRAN, J.]
.....   '     around clause G1 .09 of Technical Provisions forming part of the A
              contract extracted below :
----              "G 1.09 No claim for interest or damages will be
                  entertained by the Government with respect to any money
                  or balance which may be lying with the Government or any
                                                                               B
                  become due owing to any dispute, difference or
                  misunderstanding between the Engineer-in-Charge on the
                  one hand and the contractor on the other hand or with
                  respect to any delay on the part of the Engineer-in-charge
                  in making periodical or final payment or any other respect
                  whatsoever."
                                                                               c

'                  7. Sub-section (i) of Section 3 of the Interest Act 1978
             provides that a court (as also an arbitrator) can in any
             proceedings for recovery of any debt or damages, allow interest
             to t.he person entitled to the debt or damages at a rate not D
             exceeding the current rate of interest, for the whole or part of
             the following period that is to say : (a) if the proceedings related
             to a debt payable by virtue of a written instrument at a certain
             time, then, from the date when the debt is payable to the date
             of institution of proceedings; (b) if the proceedings did not E
             relate to any such debt, then, from the date mentioned in this
             regard in a written notice given by the person entitled or the
             person making the claim to the person liable, that interest will
        l'
             be claimed to the date of institl1tion of the proceedings. Sub-
             section (3) of section 3 provides that nothing in section 3 shall F
             apply to any debt or damages upon which interest is payable
             as of right by virtue of any agreement; or to any debt or
             damages upon which payment of interest is barred by virtue
             of an express agreement.

                  8. The Arbitration Act, 1940 did not contain any specific G
        '"   provision relating to power of Arbitrator to award interest. That
             led to considerable confusion about the power of Arbitrators
             in regard of award of interest from the date of e;ause of action
             to date of award, that is pre-reference period (from the date of
             cause of action upto the date of reference) and pendente lite H
    848         SUPREME COURT REPORTS               [2009] 10 S.C.R.


A   (from the date of reference to date of award). Ultimately, this
    Court made it clear that the Arbitrator had the jurisdiction and
    authority to award interest for the three periods namely pre-
    reference period, pendente lite and future period (from the date
    of award) if there was no express bar in the contract regarding
B   award of interest - vide Secretary, Irrigation Department, Govt.
    of Orissa vs. G. C. Roy - 1992 (1) SCC 508, Executive
    Engineer, Dhenkanal Minor Irrigation Division vs. N. C.
                                                                           t
    Budharaj - 2001 (2) SCC 721 as also the decision in
    Bhagawati Oxygen Ltd. vs. Hindustan Copper Ltd. - 2005 (6)
c sec 462.
           9. Two more decisions dealing with cases arising under
    Arbitration Act, 1940 requires to be noticed. In Superintending
    Engineer v. Subba Reddy [1999 (4) SCC 423] this Court held
    that interest for pre-reference period can be awarded only if
D   there was an agreement to that effect or if it was allowable
    under the Interest Act, 1978. Therefore, claim for interest for pre-
    reference period, which is barred as per the agreement or
    under the Interest Act, 1978 could not be allowed. This Court
    however held that Arbitrator can award interest pendente lite
E   and future interest. The principles relating to interest were
    summarized by this court in State of Rajasthan v. Ferro
    C'::>ilcrete Construction Pvt. Ltd. (CA No.2764 of 2009 decided
    on 22.4.2009) thus:

F         (a)    where a provision for interest is made on any debt
                 or damages, in any agreement, interest shall be
                 paid in accordance with the such agreement.

          (b)    Where payment of interest on any debt or damages
                 is barred by express provision in the contract, no
G                interest shall be awarded.

          (c)    Where there is no express bar in the contract and
                 where there is also no provision for payment of
                 interest then the principles of section 3 of Interest
H                Act will apply and consequently interest will be
           SAYEED AHMED & CO. v. STATE OF U P & ORS. 849
                     [R. V. RAVEENDRAN, J.]
                     payable:                                                A

                     (i) where the proceedings 1elate to a debt
                     (ascertained sum) payable by virtue of a written
                     instrument at a certain time, then from the date when
                     the debt is payable to the date of institution of the
                                                                             8
                     proceedings;

                     (ii) where the proceedings is for recovery of
     t
                     damages or for recovery of a debt which is not
                     payable at a certain time, then from the date
                     mentioned in a written notice given by the person C
-(                   making a claim to the person liable for the claim that
                     interest will be claimed.

               (d)   Payment of interest pendente lite and future interest
                     shall not be governed by provisions of Interest Act, 0
                     1978, but by provisions of section 34 of Code of
                     Civil Procedure 1908 or the provisions of ~a_w
                     governing Arbitration as the case may be.

             10. The Legislature while enacting the Arbitration and
         Conciliation Act, 1996, incorporated a specific provision in E
         regard to award of interest by Arbitrators. Sub-section(?) of
         section 31 of the Act deals with the Arbitrato~s power to award
         interest. Clause (a) relates to the period between the date on
         which the cause of action arose and the date on which the
         award is made. Clause (b) relates to the period from the date       F
         of award to date of payment. The said sub-section (7) is
         extracted below :

              "?(a) Unless otherwise agreed by the parties, where and
              in so far as an arbitral award is for the payment of money, G
             the arbitral tribunal may include in the sum for which the
            'award is made interest, at such rate as it deems
              reasonable, on the whole or any part of the money, for the
             whole or any part of the period between the date on which
             the cause of action arose and the date on which the award H
    850       SUPREME COURT REPORTS                [2009] 10 S.C.R.
                                                       '

A         is made.

          (b) A sum directed to be paid by an arbitral award shall,
          unless the award otherwise directs, carry interest at the
          rate of eighteen per centum per annum from the date of
                                                                               -
          the award to the date of payment.
B
    Having regard to sub-section (7) of section 31 of the Act, the
    difference between pre-reference period and pendente lite
    period has disappeared in so far as award of interest by
    arbitrator. The said section recognises only two periods and
C   makes the following provisions :

          (a) In regard to the period between the date on which the
          cause of action arose and the date on which the award is
          made (pre-reference period plus pendente lite), the arbitral
D         tribunal may award interest at such rate as it deems
          reasonable, for the whole or any part of the period, unless
          otherwise agreed by the parties.

          (b) For the period from the date of award to the date of ' .
          payment the interest shall be 18% per annum if no specific
E         order is made in regard to interest. The arbitrator may
          however award interest at a different rate for the period
          between the date of award and date of payment.

    The decisions of this Court with reference to the awards under        r
F   the old Arbitration Act making a distinction between the pre-
    reference period and pendente lite period and the observation
    therein that arbitrator has the discretion to award interest during
    pendente lite period inspite of any bar against interest
    contained in the contract between the parties are not applicable
G   to arbitrations governed by the Arbitration and Conciliation Act
    1996.
                                                                          .,
        11. Clause G-1.09 makes it clear that no interest or
    damages will be paid by Government, in regard to : (i) any
    money or balance which may be lying with the Government; (ii)
H   any money which may become due owing to any dispute,
      SAYEED AHMED & CO. v. STATE OF U P & ORS. 851
                [R. V. RAVEENDRAN, J.]
     difference or misunderstanding between the Engineer-in-charge A
     on the one hand and the contractor on the other hand; (iii) any
     delay on the part of the Engineer-in-Charge in making
     periodical or final payment; or (iv) any other respect whatsoever.
     The clause is comprehensive and bars interest under any head
     in clear and categorical terms. In view of clause (a) of sub- B .
     section (7) of section 31 of the Act, it is clear that the Arbitrator
     could not have awarded interest upto the date of the award, as
     the agreement between the parties barred payment of interest.
     The bar against award of interest would operate not only during
     tt1e pre-reference period that is up to 13.3.1997 but also d·uring   c
     the pendente lite period that is from 14.3.1997 to 31.7.2001.

           12. The appellant strongly relied upon the decision of this
     Court in State of U.P. v. Harish Chandra & Co. [1999 (1) SCC
     63], to contend that clause 1.09 of the contract did not bar the
     award of interest. The clause barring interest that fell for D
     consideration in that decision was ~s under :

          "1.9. No claim for delayed payment due to dispute etc.-
          No claim for interest or damages will be entertained by the
          Government with respect to any moneys or balances which         E
          may be lying with the Government owing to any dispute,
          difference; or misunderstanding between the Engineer-in-
          Charge in marking periodical or final payments or in any
          other respect whatsoever."

     This Court held that the said clause did not bar award of interest   F
     on any claim for damages or for claim for payment for work
     done. We extract below the reasoning for such decision :

         "A mere look at the clause shows that the claim for interest
         by way of damages was not to be entertained against the G
         Government with respect to only a specified type of amount,
.~       namely, any moneys or balances which may be lying with
         the Government owing to any dispute, difference between
         the Engineer"in-Charge and the contractor; or
         misunderstanding between the Engineer-in-Charge and H
    852       SUPREME COURT REPORTS               [2009] 10 S.C.R.


A         the contractor in marking periodical or finally payments or
                                                                        ~
          in any other respect whatsoever. The words 'or in any other
          respect whatsoever" also referred to the dispute pertaining        ·~
          to the moneys or balances which may be lying with the
          Government pursuant to the agreement meaning thereby
B         security deposit or retention money or any other amount
          which might have been with the Government and refund of
          which might have been withheld by the Government. The
          claim for damages or claim for payment for the work done
          and which was not paid for would not obviously cover any
c         money which may be said to be lying with the
          Government. Consequently, on the express language of
          this clause, there is no prohibition which could be culled
          out against the respondent-contractor that he could not
          raise the claim for interest by way of damages before the
          arbitrator on the relevant items placed for adjudication."
D
  In Harish Chandra (supra) a different version of clause 1.09
  was considered. Having regard to the restrictive wording of that
  clause, this Court held that it did not bar award of interest on a
  claim for damages or a claim for payments for work done and
E which was not paid. This Court held that the said clause barred
  award of interest only on amounts which may be lying with the
  Government by way of security deposit/retention money or any
  other amount refund of which was withheld by the government.
  But in this case, clause G-1.09 is significantly different. It        ,.
F specifically provides that no interest shall be payable in respect
  of any money that may become due owing to any dispute,
  difference or misunderstanding between the Engineer-in-
  Charge and contractor or with respect to any delay on the pa11
  of the Engineer-in-Charge in making periodical or final payment
G or in respect of any other respect whatsoever. The bar under
  clause G-1.09 in this case being absolute, the decision in
  Harish Chandra will not assist the appellant in any manner.

        13. The appellant next relied upon the judgment of this
    Court in State ofOrissa vs. B.N. Agarwa/la [1997 (2) SCC 46H].
H
             SAYEED AHMED & CO. v. STATE OF UP & ORS. 853
 '                     [R. V. RAVEENDRAN, J.]

           In that case, this Court held that Arbitrator has jurisdiction to         A
           award (i) interest for pre-reference period, (ii) interest for
           pendente lite and (iii) future interest. This Court also held that
-;
           the following part of clause (4) of the contract dealing with
           "Rates, materials and workmanship" did not bar award of
           interest by the arbitrator on the claims of the contractor :              B
                "No interest is payable on amount withheld under the item
                of the agreement".

           Interpreting the said clause (which provided that interest was
           not payable on the amount which was withheld), this Court held            c
           that it referred only to the amount withheld by the employer State
           towards retention money for the defect liability period. This
           Court in fact clarified that the position that if the terms of contract
           expressly stipulated that no interest would be payable, then
           arbitrator would not get the jurisdiction to award interest. As           D
           clause G-1.09 in the present case contains an express bar and
           is different from the clause considered in B.N. Agarwal/a
           (supra), the said decision is also of no assistance.

                 14. The learned counsel for the appellant submitted that
                                                                                     E
           even though the bar in clause G-1.09 may prohibit the employer
           from paying interest, it does not bar the Arbitrator from
           awarding interest. For this purpose, he relied upon the decision
           of this Court in Board of Trustees for Port of Calcutta vs.
      '(
           Engineers-De-Space-Age [1996 (1) SCC 516]. In that case,
                                                                                     F
           this Court considered the validity of award of interest pendente
           lite by the Arbitrator notwithstanding the prohibition contained
           in the contract against payment of interest on delayed
           payments. The following clause fell for consideration of this
           Court in that case : ·
                                                                                     G
               "No claim for interest will be entertained by the
     _..       Commissioners with respect to any money or balance
               which may be in their hands owing to any dispute between
               themselves and the Contractor or with respect to any delay
               on the part of the Commissioners in making interim or final           H
    854       SUPREME COURT REPORTS                  [2009] 10 S.C.R.


A         payment or otherwise."

    After referring to the Constitution Bench decision in G. C. Roy         ·'
    (supra) this Court held :

           "We are not dealing with a case in regard to award of
B          interest for the period prior to the reference. We are
          dealing with a case in regard to award of interest by the
          arbitrator post reference. The short question, therefore, is
          whether in view of sub-clause (g) of clause 13 of the
          contract extracted earlier the arbitrator was prohibited from
c         granting interest under the contract. Now the term in sub-
          clause (g) merely prohibits the Commissioner from
          entertaining any claim for interest and does not prohibit the
          arbitrator from awarding interest. The opening words 'no
          claim for interest will be entertained by the Commissioner"
D         clearly establishes that the intention was to prohibit the
          Commissioner from granting interest on account of
          delayed payment to the contractor. Clause has to be strictly
          construed for the simple reason th.at as pointed out by the
          Constitution Bench, ordinarily, a person who has a
E         legitimate claim is entitled to payment within a reasonable
          time and if the payment has been delayed beyond
          reasonable time he can legitimately claim to be
          compensated for that delay whatever nomenclature one
          may give to his claim in that behalf. If that be so, we would
F         be justified in placing a strict construction on the term of
          the contract on which reliance has been placed. Strictly
          construed the terms of the contract merely prohibits the
          Commissioner from paying interest to the contractor for
          delayed payment but once the matter goes to arbitration
          the discretion of the arbitrator is not, in any manner, stifled
G
          by this term of the contract and the arbitrator would be
          entitled to consider the question of grant of interest
          pendente lite and award interest if he finds the claim to be       ,
          justified. We are, therefore, of the opinion that under the
          clause of the contract the arbitrator was in no manner
H
  SAYEED AHMED & CO. v. STATE OF U P & ORS.                855
            [R. V. RAVEENDRAN, J.]

     prohibited from awarding interest pendente lite."            A

This Court held that the bar in the contract operated only for
the pre-reference period and that the Arbitrator had the power
and authority to award interest pendente lite at his discretion,
without reference to the bar in the contract. The observation in B
Engineers-De-Space-Age (supra) that the term of the contract
merely prohibits the department/employer from paying interest
to the contractor for delayed payment but once the matter goes
to arbitrator, the discretion of the arbitrator is not in any manner
stifled by the terms of the contract and the arbitrator will be
entitled to consider and grant the interest pendente lite, 9annot C
be used to support an outlandish argument that bar on the
Government or department paying interest is not a bar on the
arbitrator awarding interest. Whether the provision in the
contract bars the employer from entertaining any claim for
interest or bars the contractor from making any claim for D
interest, it amounts to a clear prohibition regarding interest. The
provision need not contain another bar prohibiting Arbitrator
from awarding interest. The observations made in the context
of interest pendente lite cannot be used out of contract.
                                                                  E
       15. The learned counsel for appellant next contended on
the basis of the above observations in Engineers-Oe-Space-
Age, that even if clause G-1.09 is held to bar interest in the pre-
 reference period, it should be held not to apply to the pendente
 lite period that is from 14.3.1997 to 31.7.2001. He contended F
that the award of interest during the pendency of the reference
was within the discretion of the arbitrator and therefore, the
award of interest for that period could not have been interfered
by the High Court. In view of the Constitution Bench decisions
in G.C. Roy and N.C. Budharaj (supra) rendered before and G
after the decision in Engineers-De-Space-Age, it is doubtful
whether the observation in Engineers-De-Space-Age in a case
arising under Arbitration Act, 1940 that Arbitrator could award
interest pendente lite, ignoring the express bar in the contract,
is good law. But that need not be considered further as this is
                                                                  H
    856        SUPREME COURT REPORTS                 [2009] 10 S.C.R.


A   a case under the new Act where there is a specific provision
    regarding award of interest by Arbitrator.

    Re : interest from the date of award

        18. The arbitrator awarded interest at the rate of 18% per
B annum on Rs.24,18,586/-, 14% per annum on amount found due
  on finalisation the final bill and 12% per annum on the security
  deposit amount if any that has to be refunded. As noticed
  above, clause (b) of sub-section (7) of section 31 of the Act
  provides that if the award does not otherwise direct, the amount
C awarded shall carry interest as directed by the award and in
  the ab~ence of any provision of 18% per annum. Any provision
  in the contract barring interest, will therefore operate only till the
  date of award and not thereafter. The arbitrator has awarded
  interest at three different rates on three different amounts which
D are all less than 18% per annum. The said award of interest
  by the arbitrator is not contrary to section 31 (7)(b) of the Act.
  Unless the award of interest is found to be unwarranted for
  reasons to be recorded, the court should not alter the rate of
  interest awarded by the Arbitrator. The High Court has not
E assigned any reasons for reducing the rate of interest to 6%
  per annum. Therefore, such reduction cannot be sustained.

        19. In view of the above, we allow this appeal in part and
    modify the judgment of the High Court as follows :

F          (a) The Judgment of the High Court setting aside the award
           of interest upto the date of award is affirmed.

           (b) The decision of the High Court reducing the rate of
           interest to 6% per annum from the date of award is set
G          aside. The rate of interest on the amounts due and payable
           under the award, from the date of award till date of
           payment shall be in terms of the award of the Arbitrator.

           (c) Parties to bear their respective costs.

H   D.G.                                      Appeal partly allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.