SAWARAN LATA ETC.versusSTATE OF HARYANA & ORS.
- Citation
- 2010 INSC 190
- Decided
- 1 April 2010
- Disposal
- Dismissed
- Bench
- M PANCHAL
Holding
A notification under Section 4 of the Land Acquisition Act, 1894 must be challenged within a reasonable period; petitions filed after an inordinate delay are liable to be dismissed.
Summary
The State of Haryana issued a notification under Section 4 of the Land Acquisition Act, 1894 on 2 May 2001, followed by a declaration under Section 6 on 30 April 2002, and made an award under Section 11 on 27 April 2004, taking possession of the petitioners' land. The petitioners filed writ petitions in the High Court on 28 May 2009 seeking to quash the notification and declaration, alleging they were unaware of the proceedings because the newspaper notices had limited circulation. The High Court dismissed the petitions on the ground of delay, and the subsequent review petitions were also dismissed as time‑barred. Special Leave Petitions were filed before the Supreme Court 172 days after the High Court order, and the Court dismissed them, holding that a Section 4 notification must be challenged within a reasonable period and that belated challenges are barred by laches. The Court relied on a series of precedents emphasizing that acquisition proceedings should be contested before they become final, and found no merit in the petitioners' claim of ignorance. Consequently, the petitions were dismissed for inordinate delay.
Issues considered
- Whether a notification under Section 4 of the Land Acquisition Act, 1894 can be challenged at a belated stage after the acquisition proceedings have become final.
- Whether the doctrine of laches and limitation bars the petitioners' writ petitions.
Legislation cited
- Land Acquisition Act, 1894s. 11, s. 4, s. 6
Subjects
Judgment
[2010] 4 S.C.R. 40
A SAWARAN LATA ETC.
v.
STATE OF HARYANA & ORS.
(Special Leave Petition (Civil) Nos. 11023-11026/2010)
APRIL 01, 2010
B
[J.M. PANCHAL AND DR. B.S. CHAUHAN, JJ.]
Land Acquisition Act, 1894 - ss. 4 and 6 - Land
acquisition proceedings - Challenge to, at belated stage -
C Land acquisition proceedings in respect of huge chunk of land
- Notification u/s. 4 and declaration u!s. 6 - Publication in
newspapers - Award by Land Acquisition Collector -
Possession taken by State - Writ petition seeking quashing
of land acquisition proceedings - Dismissed on the ground
D of delay - Review petition also dismissed on the ground of
delay - On appeal, held: Notification u/s. 4 should be
challenged within a reasonable period - Petition challenging
the same is liable to be dismissed if it is challenged at a
belated stage - On facts, not the case of the land owners that
E they were not aware of acquisition proceedings - Very huge
chunk of land belonging to large number of tenure holders
had been notified for acquisition - Order of courts below not
called for interference - SLPs having been filed with an
inordinate delay of 172 days, dismissed - Limitation - Delay/
F /aches.
Hari Singh & Ors. vs. State of U.P. AIR 1984 SC 1020;
Aflatoon & Ors. vs. Lt. Governor, Delhi & Ors. AIR 1974 SC
2077; State of.Mysore vs. V.K. Kangan AIR 1975 SC 2190;
PT. Girdharan Prasad Missir vs. State of Bihar (1980) 2 SCC
G 83; Bhoop Singh vs. Union of India AIR 1992 SC 1414; State
of Orissa vs. Dhobei Sethi & Anr. (1995) 5 SCC 583; State
of Maharashtra vs. Digambar AIR 1995 SC 1991; State of
Tamil Nadu vs. L. Krishnan AIR 1996 SC 497; C. Padma &
Ors. vs. Dy. Secretary to Govt. of Tamil Nadu & Ors. (1997) 2
H 40
SAWARAN LATA ETC. v. STATE OF HARYANA & 41
ORS.
SCC 627; Municipal Corporation of Greater Bombay vs. A
Industrial Development Investment Co. Pvt. Ltd. & Ors. AIR
1997 SC 482; State of Rajasthan & Ors. vs. O.R Laxmi &
Ors. (1996) 6 SCC 445; Northern Indian Glass Industries vs.
Jaswant Singh & Ors. AIR 2003 SC 234; Haryana State
Handloom & Handicrafts Corporation Ltd. vs. Jain School B
Society AIR 2004 SC 850, relied on.
Case Law Reference:
AIR 1984 SC 1020 Relied on. Para 6
AIR 1974 SC 2077 Relied on. Para 7
c
AIR 1975 SC 2190 Relied on. Para 8
(1980) 2 sec 83 Relied on. Para 8
AIR 1992 SC 1414 Relied on. Para ·8 D
(1995) 5 sec 583 Relied on. Para 8
AIR 1995 SC 1991 Relied on. Para 8
AIR 1996 SC 497 Relied on. Para 8 E
(1997) 2 sec 627 Relied on. Para 8
AIR 1997 SC 482 Relied on. Para 9
(1996) 6 sec 445 Relied on. Para 10
F
AIR 2003 SC 234 Relied on. Para 11
AIR 2004 SC 850 Relied on. Para 11
CIVIL APPELLATE JURISDICTION : SLP (Civil) No.
11023-11026 of 2009. G
From the Judgment & Orders dated 30.5.2009, 25.9.2009
of the High Court of Punjab & Haryana at Chandigarh in Civil
Writ Petition No. 8794, RP 337 in CWP 8794 of 2009, Civil
Writ Petition No. 8761 of 2009, RP No. 338 in CWP 8761 of
2009. H
42 SUPREME COURT REPORTS [2010] 4 S.C.R.
A Dinesh Verma, Rajat Sharma, R.V. Kameshwaran for the
Petitioners.
The Order of the Court was delivered by
ORDER
B
DR. B.S. CHAUHAN, J. 1. These special leave petitions
reveal a very sorry state of affair and make it evident that litigants
are eager to abuse the process of the Court, having no idea
for the law of limitation/delay and laches.
C 2. These special leave petitions have been filed against
the judgment and order of the Punjab and Haryana High Court
dated 30.5.2009 by which the Civil Writ Petition Nos.8794 of
2009 and 8761 of 2009 have been dismissed only on the
ground of delay. The Review Petitions were filed which were
D also time barred by 48· days. The same stood dismissed vide
order dated 25.9.2009. These special leave petitions have
been filed with an inordinate delay of 172 days. Petitioners
sought relief of quashing the land acquisition proceedings in
respect of which the award had been made under Section 11
E of the Land Acquisition Act, 1894 (hereinafter called as "Act
1894") on 27.4.2004.
3. The facts and circumstances giving rise to these
petitions are that the respondent - State of Haryana issued a
notification under Section 4 of Act 1894 in respect of a huge
F chunk of land including some land of the petitioners on 2nd May,
2001. Substance of the said notification was published in two
newspapers on 5.5.2001. The respondents issued a declaration
under Section 6 of Act 1894 on 30.4.2002 and the substance
thereof was also published in local newspapers immediately
G thereafter. The Land Acquisition Collector made an award on
27.4.2004 and in pursuance thereof, the respondents took
possession of the land and removed the trees from the land of
the petitioners.
4. Petitioners approached the High Court by filing Writ
H
SAWARAN LATA ETC. v. STATE OF HARYANA & 43
ORS. [DR. B.S. CHAUHAN, J.]
Petition Nos. 8794/200Q and 8761/2009 on 28.5.2009 praying A
for quashing the notification dated 2.5.2001 under Section 4
and declaration dated 30.4.2002 under Section 6 of Act 1894.
The High Court dismissed both the petitions on the ground of
delay observing that the award under Section 11 of Act 1894
had already been made on 27.4.2004. Beirig aggrieved, B
petitioners filed Review Petitions with 48 days' delay which
have also been dismissed vide order dated 25.9.2009. These
petitions have been filed with 172 days' delay. There is further
delay of 37 days' in re-filing of the same.
5. The issue involved in these petitions is as to whether C
the acquisition proceedings can be challenged at a belated
stage. The issue is no more res integra as the issue has been
considered by this Court time and again.
6. When a person challenges Section 4 Notification on any
0
ground, it should be challenged within a reasonable period, and
if the acquisition is challenged at a belated stage, the petition
deserves to be dismissed only on this count. (Vide Hari Singh
& Ors. Vs. State of U.P., AIR 1984 SC 1020).
7. A Constitution Bench of this Court, in Aflatoon & Ors. E
Vs. Lt. Governor, Delhi & Ors. AIR 1974 SC 2077, while
dealing with the issue, observed as unper:-
".... to have sat on the fence and allowed the government
to complete the acquisition on the basis that notification
under Section 4 and the declaration under Section 6 were F
valid and then to attack the notification on the grounds
which were available to them at the time when the
notification was published, would be putting a premium of
dilatory tactics. The writ petitions are liable to be dismissed
on the ground of laches and delay on the part of the G
petitioner."
8. Same view has been reiterated by this Court observing
that acquisition proceedings should be challenged before the
same attain finality, in State of Mysore Vs. V.K. Kangan AIR
H1
44 SUPREME COURT REPORTS [2010] 4 S.C.R.
A 1975 SC 2190; PT. Girdharan Prasad Missir Vs. State of
Bihar (1980) 2 SCC 83; Bhoop Singh Vs. Union of India AIR
1992 SC 1414; State of Orissa Vs. Dhobei Sethi & Anr. (1995)
5 SCC 583; State of Maharashtra Vs. Digambar AIR 1995 SC
1991; State of Tamil Nadu Vs. L. Krishnan AIR 1996 SC 497;
B and C. Padma & Ors. Vs. Dy. Secretary to Govt. of Tamil Nadu
& Ors. (1997) 2 sec 627.
9. In Municipal Corporation of Greater Bombay Vs.
Industrial Development Investment Co. Pvt. Ltd. & Ors. AIR
1997 SC 482, this Court observed as under:-
c
"lf the interested person allows the grass to grow
under his feet by allowing the acquisition proceedings to
go on and reach its terminus in the award and possession
is taken in furtherance thereof and vest in the State free
from all encumbrances, the slumbered interested person
D
would be told off the gates of the Court that his grievance
should not be .entertained when there is inordinate delay
in filing the writ petition and when all steps taken in the
acquisition proceedings have become final, the Court
should be loath to quash the notifications. (Emphasis
E added)
10. Similar view has been reiterated in State of Rajasthan
& Ors. Vs. D.R. Laxmi &Ors., (1996) 6 SCC 445, wherein this
Court has held that even the void proceedings need not be set
F at naught if the party has not approached the Court within
reasonable time, as judicial review is not permissible at a
belated stage. This Court held as under:
"...... Delay in challenging the notification was fatal and writ
petition entails with dismissal on grounds of laches. It is
G thus, well-settled law that when there is inordinate delay in
filing the writ petition and when all steps taken in the
acquisition proceedings have become final, the Court
should be loathe to quash the notifications ........ The order
or action, if ultra vires the power, becomes void and it
H does not confer any right. But the action need not
SAWARAN LATA ETC. v. STATE OF HARYANA & 45
ORS. [DR. B.S. CHAUHAN, J.]
necessarily be set at naught in all events. Though the A
order may be void, if the party does not approach the
Court within reasonable time, which is always a question
of fact and have the order invalidated or acquiesced or
waived, the discretion of the Court has to be exercised
in a reasonable manner. When the discretion has been B
conferred on the Court, the Court may in appropriate case
decline to grant the relief, even if it holds that the order was
void. The net result is that extraordinary jurisdiction of the
Court may not be exercised in such circumstances."
(Emphasis Added) c
11. Similar view has been reiterated by this Court in
Northern Indian Glass Industries Vs. Jaswant Singh & Ors.
AIR 2003 SC 234; and Haryana State Handloom &
Handicrafts Corporation Ltd. Vs. Jain School Society AIR
2004 SC 850. D
12. In the instant case, it is not the case of the petitioners
that they had not been aware of acquisition proceedings as the
only ground taken in the writ petition has been that substance
of the notification under Section 4 and declaration under
Section 6 of Act 1894 had been published in the newspapers E
having no wide circulation. Even if, the submission made by the
petitioners is accepted, it cannot be presumed that they could
not be aware of acquisition proceedings for the reason that very
huge chunk of land belonging to large number of tenure holders
had been notified for acquisition. Therefore, it should have been F
a talk of the town. Thus, it cannot be presumed that petitioners
could not have knowledge of the acquisition proceedings.
13. In such circumstances, we do not find any fault with the
impugned judgment and order. The petitions are dismissed on G
the ground of delay.
N.J. Petitions dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.