Created byFuzzy Cloud

Supreme Court of India

SATYAWATIversusRAJINDER SINGH AND ANR.

Citation
2013 INSC 290
Decided
29 April 2013
Disposal
Appeal(s) allowed

Holding

A decree once passed is executable and the executing court must not consider extraneous reports not forming part of the judgment; therefore the decree must be executed based on the original local commissioner’s report.

Summary

The plaintiff, Satyawati, obtained a decree for possession of an 80‑sq‑yard plot of land on 19 January 1996. An execution petition filed in 1996 was rejected by the executing court on the ground that the decree was not executable due to contradictory reports, even though the original judgment relied on a local commissioner’s report dated 17 September 1989 and a sketch of the land. The High Court affirmed the rejection, relying on a later demarcation report of 26 July 2010. The Supreme Court held that the executing court could not consider reports that were not part of the decree or the judgment and therefore must execute the decree based on the original commissioner’s report. The Court set aside the orders of the executing court and the High Court, directing the executing court to carry out the decree without further delay. The appeal was allowed, with no order as to costs.

Issues considered

  • Whether a decree holder’s execution petition can be rejected on the basis of reports not considered in the original judgment and decree.
  • Whether the executing court may disregard the original commissioner’s report and sketch when deciding executability.
  • Whether the delay in execution amounts to laches or unreasonable delay justifying dismissal.

Subjects

execution of decreedecree holdercontradictory reportsdelaylachescivil procedurepossessionland

Judgment

                    [2013] 3 S.C.R. 471


                         SATYAWATI                               A
                              v.
               RAJINDER SINGH AND ANR.
              (Civil Appeal No. 4176 of 2013)

                      APRIL 29, 2013
                                                                 B
     [G.S. SINGHVI, ANIL R. DAVE AND RANJANA
                PRAKASH DESAI, JJ.]

    Execution of decree:
                                                                 c
     Petition for execution of decree entitling the plaintiff to
possession of a plot - Rejected on the ground that decree was
not executable because of contradictory reports - Revision of
plaintiff rejected by High Court - Held: Judgment in favour of
plaintiff was delivered by considering a report dated 17. 9. 1989 0
and a sketch of land in question, which were made by local
commissioner and both are part of record - High Court was
not right while confirming the order passed by executing court,
for latter had taken into account certain other reports for
purpose of rejecting execution proceedings - Once decree E
was made in favour of plaintiff, in pursuance of judgment
delivered by District Judge, executing court should n,0t have
looked into other reports which had been submitted to it
afterwards - Local Commissioner's report dated 17. 9. 1989
along with sketch clearly describes land in question -
Executing court ought to have considered it - Orders of F
executing court and High Court set aside - Executing court
directed to do the needful for execution of decree taking into
account local commissioner's report dated 17. 9. 1989 -
Decree.
                                                                  G
     Delay/Laches:

    Delay in execution of decree - Execution petition filed in
1996 - However, decree not executed till date - Held: There
                             471                                 H
    4 72       SUPREME COURT REPORTS                   [2013] 3 S.C.R.


A should not be unreasonable delay in execution of a decree -
    - Executing court will do the needful at an early date so as to
    see that the long drawn litigation which was decided in favour
    of appellant is finally concluded and he gets effective justice.

         Babu Lal vs. Mis. Hazari Lal Kishori Lal & Ors. 1982 (3)
8
               =
    SCR 94 (1982) 1 SCC 525; Marshall Sons & Co. (I) Ltd.
    vs. Sahi Oretrans (P) Ltd. & Anr. 1999 (1) SCR 311 (1999)=
    2 SCC 325; Shub Karan Bubna alias Shub Karan Prasad
    Bubna vs. Sita Saran Bubna and Ors. 2009 (14) SCR 40              =
c   (2009) 9 sec 689 - referred to.

        The General Manager of the Raj Durbhnga under the
    Court of Wards vs. Maharajah Coomar Ramaput Sing; Kuer
    Jang Bahadur vs. Bank of Upper India Ltd., Lucknow AIR
    1925 Oudh 448- referred to.
D
                           Case Law Reference:

           AIR 1925 Oudh 448        referred to             para 13

           1982 (3) SCR 94          referred to             para 14
E          1999 (1) SCR 311         referred to             para 15

           2009 (14) SCR 40         referred to             para 16

        CIVIL APPELLATE JURISDICTION : Civil Appeal No.
    4176 of 2013.
F
        From the Judgment & Order dated 25.05.2011 of the High
    Court of Punjab & Haryana at Chandigarh in Civil Revision No.
    2047 of 2010 (0 & M)
           B.S. Mor, R.C. Kaushik for the Appellant.
G
           Lalit Trakru, Sandeep Bhalla for the Respondents.

           The Order of the Court was delivered by

H
            SATYAWATI v. RAJINDER SINGH                         473


                            ORDER                                       A

     ANIL R. DAVE, J. 1. Leave granted.

    2. In relation to the difficulties faced by a decree holder in
execution of the decree, in 1872, the Privy Council had
observed that " ....... the difficulties of a litigant in India begin   B
when he has obtained a Decree ...... ".

     3. Even today, in 2013, the position has not been
improved and still the decree holder faces the same problem
which was being faced in the past. We are concerned with the            c
case of the appellant-plaintiff who had succeeded in Civil
Appeal No. 89 of 1993 in the Court of District Judge, Faridabad
on 19th January, 1996. Decree was drawn in pursuance of the
aforestated judgment but till today, the appellant-plaintiff is not
in a position to get fruits of his success.                             D

     4. It is not in dispute that the judgment delivered in Civil
Appeal No. 89 of 1993 in favour of the appellant has become
final as it was not challenged before the High Court. In
pursuance of the decree drawn, the appellant made several
efforts to get the decree executed. His last effort, with which         E
we are concerned, had been initiated in 1996, when he had
approached the court of Additional Senior Division, Palwal with
an Execution Petition for execution of the decree.

      5. As the decree had already been made in favour of the           F
appellant, we need not go into the facts of the case, however it
will be worth noting that by virtue of the decree, the appellant-
plaintiff is entitled to possession of land admeasuring 80 sq.
yard forming part of land of Khasra No.95/24/2 situated within
municipal limits of Palwal town, District Faridabad. When the           G
Execution Petition was filed, the Executing Court rejected the
Execution Petition by observing that the decree was not
executable because of certain contradictory reports. It is
pertinent to note that the judgment in favour of the appellant-
plaintiff was delivered by considering a report dated 17th              H
    474      SUPREME COURT REPORTS                 [2013] 3 S.C.R.

A September, 1989 and a sketch of land in question, which were
  made by the local commissioner and both are forming part of
  the record. It appears that some other reports were considered
  by the Executing Court and after considering all the reports, the
  Executing Court, by its order dated 16th March, 2009 came to
B the conclusion that the decree was not executable.

        6. Being aggrieved by the aforestated order dated 16th
  March, 2009, the appellant approached the High Court by filing
  Civil Revision No. 2047 of 2010. The said Revision application
  was rejected by an order dated 25th May, 2011 and therefore,
C the appellant-plaintiff has approached this court by way of this
  Appeal.

       7. While confirming the order of the Executing Court dated
  16th March, 2009, the High Court took into consideration the
D subsequent demarcation report dated 26th July, 2010 and after
  discussing both the reports came to the conclusion which had
  been arrived at by the Executing Court.

          ~· We have heard the learned counsel appearing for the
E appellant-plaintiff as well as for the respondents.

       9. Looking to the facts of the case, in our opinion, the High
  Court was not right while confirming the order passed by the
  Executing Court for the reason that the Executing Court had
  taken into account certain other reports for the purpose of
F rejecting the execution proceedings and for coming to the
  conclusion that the decree was not executable.
       10. Looking to the facts of the case and upon hearing the
  learned counsel, we are of the view that the order passed by
G the Executing Court dated 16th March, 2009, which has been
  confirmed by the High Court is not correct for the reason that
  the Executing Court ought not to have considered other factors
  and facts which were not forming part of the judgment and the
  decree passed in favour of the appellant-plaintiff. Once the
  decree was made in favour of the appellant-plaintiff, in
H
 SATYAWATI v. RAJINDER SINGH [ANIL R. DAVE, J.] 475


pursuance of the judgment dated 19th January, 1996 delivered            A
by the District Judge Faridabad, in our opinion, the Executing
Court should not have looked into other reports which had been
submitted to it afterwards.

     11. Upon perusal of the reports, we find that the local
                                                                        8
commissioner's report clearly describes the land which
admeasures 80 sq. yard and which is forming part of Khasra
No. 95/24/2 and the report given by the local commissioner also
gives details of the land in question by way of a sketch. In our
opinion, the Executing Court ought to have looked at the sketch         C
which was prepared by the local commissioner and which was
accepted as a correct sketch by the Appellate Court while
delivering the judgment dated 19th January, 1996, which has
become final.

     12. In our opinion, the view expressed by the Executing            D
Court and confirmed by the High Court is not correct and
therefore, we allow this appeal and quash and set aside the
impugned order of the High Court passed in C.R. No. 2047 of
2010 dated 25th May, 2011, confirming the order passed by
the Executing Court dated 16th March, 2009. We direct the               E
Executing Court to do the needful for execution of the decree
by taking into account the local commissioner's report and
sketch prepared by him dated 17th September, 1989.

       13. It is really agonizing to learn that the appellant- decree   F
holder is unable to enjoy the fruits of her success even today
i.e. in 2013 though the appellant- plaintiff had finally succeeded
in January, 1996. As stated hereinabove, the Privy Council in
the case of The General Manager of the Raj Durbhnga under
the Court of Wards vs. Maharajah Coomar Ramaput Sing had
observed that the difficulties of a litigant in India begin when        G
he has obtained a Decree. Even in 1925, while quoting the
aforestated judgment of the Privy Council in the case of Kuer
Jang Bahadur vs. Bank of Upper India Ltd., Lucknow [AIR
1925 Oudh 448), the Court was constrained to observe that
                                                                        H
    476      SUPREME COURT REPORTS                     [2013] 3 S.C.R.


A   "Courts in India have to be careful to see that process of the
    Court and law of procedure are not abused by the judgment-
    debtors in such a way as to make Courts of law instrumental
    in defrauding creditors, who have obtained decrees in
    accordance with their rights."
8
        14. In spite of the aforestated observation made in 1925,
  this Court was again constrained to observe in Babu Lal vs.
  Mis. Hazari Lal Kishori Lal & Ors. [(1982) 1 SCC 525] in para
  29 that "Procedure is meant to advance the cause of justice
C and not to retard it. The difficulty of the decree holder starts in
  getting possession in pursuance of the decree obtained by him.
  The judgment debtor tries to thwart the execution by all possible
  objections ...... "

             15. This Court, again in the case of Marshall Sons & Co.
D   (/) Ltd. vs. Sahi Oretrans (P) Ltd. & Anr. [ (1999) 2 SCC 325]
    was constrained to observe in para 4 of the said judgment that
    " .... .it appears to us, prima facie, that a decree in favour of the
    appellant is not being executed for some reason or the other,
    we do not think it proper at this stage to direct the respondent
E   to deliver the possession to the appellant since the suit filed
    by the respondent is still pending. It is true that proceedings are
    dragged for a long time on one count or the other and on
    occasion, become highly technical accompanied by unending
    prolixity at every stage providing a legal trap to the unwary.
F   Because of the delay, unscrupulous parties to the proceedings
    take undue advantage and person who is in wrongful
    possession draws delight in delay in disposal of the cases by
    taking undue advantage of procedural complications. It is also
    a known fact that after obtaining a decree for possession of
G   immovable property, its execution takes long time ..... "

        16. Once again in the case of Shub Karan Bubna alias
    Shub Karan Prasad Bubna vs. Sita Saran Bubna and Ors.
    (2009) 9 sec 689] at para 27 this Court observed as under :

H         "In the present system, when preliminary decree for
SATYAWATI v. RAJINDER SINGH [ANIL R. DAVE, J.] 477


        partition is passed, there is no guarantee that the plaintiff       A
        will see the fruits of the decree. The proverbial observation
        by the Privy Council is that the difficulties of a litigant begin
        when he obtains a decree. It is necessary to remember
        that success in a suit means nothing to a party unless he
        gets the relief. Therefore, to be really meaningful and             B
        efficient, the scheme of the Code should enable a party
       .not only to get a decree quickly, but also to get the relief
        quickly. This requires a conceptual change regarding civil
        litigation, so that the emphasis is not only on disposal of
        suits, but also on securing relief to the litigant."                c
      17. As stated by us hereinabove, the position has not been
improved till today. We strongly feel that there should not be
unreasonable delay in execution of a decree because if the
decree holder is unable to enjoy the fruits of his success by
getting the decree executed, the entire effort of successful                D
litigant would be in. vain.

     18. We are sure that the Executing Court will do the needful
at an early date so as to see that the long drawn litigation which
was decided in favour of the appellant is finally concluded and             E
the appellant-plaintiff gets effective justice.

       19. The appeal is allowed with no order as to costs.


R.P.                                                 Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "execution of decree"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.