SALUJA CONSTRUCTION COMPANYversusNORTHERN COALFIELDS LIMITED
- Citation
- 2021 INSC 788
- Decided
- 25 November 2021
- Disposal
- Case Partly allowed
Holding
The arbitrator exceeded his jurisdiction in passing award for contracts other than the Bina Project, but the award for the Bina Project is within jurisdiction and is confirmed.
Summary
Saluja Construction Company entered into a contract with Northern Coalfields Limited for the Bina Project and invoked arbitration under Clause 9, filing an application under Sections 8 and 20 of the Arbitration and Conciliation Act, 1996 limited to that project. The arbitrator, however, issued an award that also covered three other contracts (including Amlohri and Jhingurda projects) and sister concerns, which were not part of the arbitration agreement. The High Court quashed the entire award, holding the arbitrator had exceeded his jurisdiction. On appeal, the Supreme Court agreed that the arbitrator was ultra vires concerning the other contracts but held that the award relating to the Bina Project was within jurisdiction and therefore confirmed it. Consequently, the Supreme Court modified the High Court order, setting aside only the portions of the award beyond the Bina Project and confirming the Rs 5,99,158 award for the Bina Project.
Issues considered
- Whether the arbitrator exceeded his jurisdiction by deciding disputes beyond the contract submitted for arbitration (the Bina Project).
- Whether the High Court should have confirmed the award portion relating to the Bina Project despite quashing the rest of the award.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 20, s. 2(a), s. 37, s. 8
Subjects
Judgment
[2021] 7 S.C.R. 1111 1111
SALUJA CONSTRUCTION COMPANY A
v.
NORTHERN COALFIELDS LIMITED
(Civil Appeal No. 7041 of 2021)
NOVEMBER 25, 2021 B
[M. R. SHAH AND SANJIV KHANNA, JJ.]
Arbitration – High Court in appeal set aside award passed
by the Arbitrator – Propriety – Held: On facts, the Arbitrator was
required to adjudicate and decide dispute between the parties with
C
respect to one Project (Bina Project) only – However, the Arbitrator
passed an award not only with respect to the dispute relating to
Bina Project but also with respect to other projects – Therefore, the
High Court rightly held that the arbitrator while decreeing the award
exceeded his jurisdiction in passing award in respect of four
contracts – However, at the same time, the High Court at least ought D
to have confirmed the claim/amount awarded by the Arbitrator with
respect to Bina Project – Order of High Court accordingly modified
to that extent – Arbitration and Conciliation Act, 1996 – ss. 2(a), 8,
20 and 37.
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7041 E
of 2021.
From the Judgment and Order dated 02.01.2018 of the High Court
of Madhya Pradesh at Jabalpur in A.A. No. 30 of 2012.
Pijush K. Roy, Mrs. Kakali Roy, Rajan K. Chourasia, Advs. for
the Appellant. F
Vikas Singh, Sr. Adv., Ashwani Kumar Dubey, Pankaj Sharma,
Kshitij Mudgal, Ms. Deepika Kalia, Satvik Mishra, Kapish Seth, Ashwini
Kr. Upadhyay, Advs. for the Respondent.
The following Order of the Court was passed : G
ORDER
Leave granted
1. Feeling aggrieved and dissatisfied with the impugned judgment
and order dated 02.01.2018 passed by the High Court of Madhya Pradesh
H
1111
1112 SUPREME COURT REPORTS [2021] 7 S.C.R.
A at Jabalpur in A.A. No. 30 of 2012, by which the High Court has allowed
the said appeal filed under Section 37 of the Arbitration and Conciliation
Act, 1996 (Arbitration Act) and has quashed and set aside the award
passed by the learned Arbitrator, the original claimant has preferred the
present appeal.
B 2. That the appellant herein was awarded the contract for
construction of 100 Nos. B-Type Quarters at Bina (hereinafter referred
to as the Bina project). An agreement was entered into between the
parties on 11.01.1986. A dispute arose between the parties with respect
to the Bina project. The contractor issued a notice under Clause 9 of the
agreement to appoint an arbitrator in respect of Bina Project only. The
C respondent rejected the claim of the contractor. The appellant raised a
Bill of Rs.2,23,215/- and then filed an application under Section 8/20 of
the Arbitration Act for filing of agreement and appointment of arbitrator.
Thus it appears that the dispute at the relevant time was only with respect
to the work relating to the Bina Project. However, before the learned
D Arbitrator, the claim was raised with respect to the other projects and in
relation to the sister concerns regarding ‘Amlohri Project’ and ‘Jhingurda
Project’. The learned Arbitrator passed an award with respect to the
dispute relating to other agreements/contracts even in relation to sister
concerns over and above the dispute with respect to the Bina Project.
The appeal under Section 34 of the Arbitration Act against the judgment
E and award passed by the learned Arbitrator came to be dismissed against
which the respondent preferred an appeal under Section 37 before the
High Court. It was submitted that the learned Arbitrator appointed only
for the contract relating to Bina Project and the agreement relating to
the Bina Project was filed before the learned Arbitrator. It was submitted
F that as per Section 2(a), 8 and 20 of the Arbitration Act, the mandatory
requirement was to decide the dispute in relation to a written agreement
which was filed before the arbitrator. Therefore, it was submitted that
the learned Arbitrator has travelled beyond in passing the award in respect
of four contracts. The High Court in the impugned judgment and order
has accepted the submissions on behalf of the respondent and has quashed
G and set aside the award passed by the learned Arbitrator.
3. Feeling aggrieved and dissatisfied with the impugned judgment
and order passed by the High Court, the contractor has preferred the
present appeal.
H
SALUJA CONSTRUCTION COMPANY v. 1113
NORTHERN COALFIELDS LIMITED
4. We have heard Shri Pijush K. Roy, learned counsel appearing A
on behalf of the appellant and Shri Vikas Singh, learned senior counsel
appearing on behalf of the respondent.
5. We have gone through the judgment and order passed by the
High Court. It is to be noted that the application under Section 8/20 of
the Arbitration Act was filed by the appellant – Saluja Construction B
Company – a partnership firm, with respect to the contract for
construction of 100 Nos. B-Type Quarters at Bina Project only. The
agreement between the appellant and respondent with respect to the
Bina Project was produced in application under 8/20 of the Arbitration
act. Therefore, the learned Arbitrator was required to adjudicate and
decide the dispute between the parties with respect to the Bina Project C
only. However, learned Arbitrator passed an award not only with respect
to the dispute relating to Bina Project but also with respect to the other
projects that too not only with the appellant but with the sister concerns.
Therefore, the High Court has rightly observed and held that the arbitrator
while decreeing the award exceeded in his jurisdiction in passing the D
award in respect of 4 contracts/contracts. Therefore, as such the High
Court is right in quashing and setting aside the award passed by the
learned Arbitrator with respect to the dues/claims with respect to the
contracts other than the Bina Project and the contracts with other
projects/contractors may be by sister concerns.
E
6. However, at the same time, learned counsel appearing on behalf
of the appellant is right in making the submissions that the High Court at
least ought to have confirmed the claim/amount awarded by the learned
Arbitrator with respect to the Bina Project. It is submitted that the High
Court has set aside the entire award passed by the learned Arbitrator
including the award with respect to the Bina Project. Therefore, to that F
extent the present appeal is required to be allowed in part and the judgment
and order passed by the High Court is required to be modified to the
extent setting aside the award passed by the learned Arbitrator with
respect to the claims with respect to other projects/other contracts other
than Bina Project. G
7. In view of the above, the present appeal is allowed in part. The
impugned judgment and order passed by the High Court is modified to
the extent quashing and setting aside the entire judgment and award
passed by the learned Arbitrator. The judgment and award passed by
the learned Arbitrator except the claims with respect to the Bina Project H
1114 SUPREME COURT REPORTS [2021] 7 S.C.R.
A was required to be quashed and set aside and is accordingly quashed
and set aside. Meaning thereby, award passed by the learned Arbitrator
with respect to the Bina Project i.e. Rs.5,99,158/- is hereby confirmed.
The impugned judgment and order passed by the High Court quashing
and setting aside the award passed by the learned Arbitrator with respect
to the projects other than Bina Project is rightly set aside by the High
B
Court. We confirm the same. It is reported that pursuant to the earlier
order passed by the High Court, the respondent has deposited 50% of
the amount awarded by the learned Arbitrator. Therefore, whatever the
amount deposited in excess of Rs.5,99,158/- with interest @ 8% per
annum from the date of the award passed by the learned Arbitrator till
C the amount was deposited pursuant to the interim order passed by the
High Court, shall be returned by the appellant to the respondent, if any
excess amount is deposited and withdrawn by the appellant. The present
appeal is allowed to the aforesaid extent. In the facts and circumstances
of the case there shall be no order as to costs.
D
Bibhuti Bhushan Bose Appeal partly allowed.
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.