Created byFuzzy Cloud

Supreme Court of India

RELIANCE CELLULOSE PRODUCTS LTD.versusOIL AND NATURAL GAS CORPORATION LTD.

Citation
2018 INSC 623
Decided
20 July 2018
Disposal
Disposed off

Holding

An arbitrator under the Arbitration Act, 1940 may award pre‑reference, pendente‑lite and future interest unless the contract contains a clear and express bar, and clause 16 does not constitute such a bar; therefore the award of 18% interest is upheld.

Summary

Reliance Cellulose Products Ltd. and ONGC entered into a contract for supply of CMC. A dispute arose over the price, which was referred to arbitration. The arbitrator fixed a higher price and awarded pre‑reference, pendente‑lite and future interest at 18% per annum. The Civil Judge reduced the interest to 10% and the Gujarat High Court upheld that reduction. On appeal, the Supreme Court held that under the Arbitration Act, 1940 an arbitrator may award interest for all three periods unless the contract contains an express bar. Clause 16 of the General Conditions of Contract only barred interest for delay in payment and did not expressly prohibit the arbitrator’s award, nor was there any actual delay. Consequently, the Court restored the arbitrator’s award of 18% interest and ordered ONGC to pay the differential amount, allowing Reliance’s appeal and dismissing ONGC’s appeal.

Issues considered

  • The scope of an arbitrator’s power under the Arbitration Act, 1940 to award pre‑reference, pendente‑lite and future interest.
  • Whether clause 16 of the General Conditions of Contract bars the arbitrator from granting such interest.
  • The propriety of the Civil Judge’s reduction of the interest rate from 18% to 10%.
  • The effect of the parties being a public‑sector undertaking on the award of interest.

Legislation cited

Subjects

ArbitrationPre‑reference interestPendente‑lite interestFuture interestContractual bar to interestArbitrator’s discretionArbitration Act 1940Interest Act 1978Public sector undertaking

Judgment

618                      [2018]REPORTS
               SUPREME COURT   6 S.C.R. 618                 [2018] 6 S.C.R.


A                RELIANCE CELLULOSE PRODUCTS LTD.
                                        v.
              OIL AND NATURAL GAS CORPORATION LTD.
                         (Civil Appeal No. 1110 of 2010)
B                                JULY 20, 2018
             [R. F. NARIMAN AND INDU MALHOTRA, JJ.]
              Arbitration Act, 1940 - Pre-reference, pendente lite interest
      and future interest – Power of arbitrator to award – On facts,
      disputes between parties referred to arbitration with regard to price
C
      for supply of goods – Fixation of price by arbitrator and award of
      pre-reference, pendente lite and future interest all at the rate of 18%
      per annum – Reduction of the interest to 10% per annum by the
      Civil Judge – High Court upheld the same – On appeal, held: Under
      the Arbitration Act, an arbitrator has power to grant pre-reference
D     interest under the Interest Act, as well as pendente lite and future
      interest – However, he is constricted only by the fact that an
      agreement between the parties may contain an express bar to the
      award of pre-reference and/or pendente lite interest – In the instant
      case, clause 16 of the General Conditions of Contract clearly bars
      payment of interest for any delay – There is nothing in this clause
E
      which refers even obliquely to the Arbitrator’s power to grant
      interest – There was no delay on account of the higher price as it
      became payable only on and from the date of the award – Even if
      clause 16 were to have application, both pre-reference and pendente
      lite interest are not barred – Only reason given for reducing interest
F     from 18% to 10% being that ONGC is a Public Sector Undertaking,
      would not suffice to set aside what was within the Arbitrator’s
      discretion – Further, there is no finding that arbitrator exercised
      the discretion perversely – Thus, the grant of interest at the rate of
      18% as pre-reference, pendente lite and future interest upheld –
      Interest Act, 1978.
G
           Allowing Reliance’s appeal and dismissing ONGC’s appeal,
      the Court
           HELD: 1.1 Under the Arbitration Act, 1940, an arbitrator
      has power to grant pre-reference interest under the Interest Act,
H
                                     618
    RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                        619
          NATURAL GAS CORPORATION LTD.

1978 as well as pendente lite and future interest. However, he is      A
constricted only by the fact that an agreement between the parties
may contain an express bar to the award of pre-reference and/or
pendente lite interest. Since interest is compensatory in nature
and is parasitic upon a principal sum not having been paid in time,
this Court has frowned upon clauses that bar the payment of
                                                                       B
interest. It has therefore evolved the test of strict construction
of such clauses, and has gone on to state that unless there is a
clear and express bar to the payment of interest that can be
awarded by an arbitrator, clauses which do not refer to claims
before the Arbitrators or disputes between parties and clearly
bar payment of interest, cannot stand in the way of an arbitrator      C
awarding pre-reference or pendente lite interest. Thus, when one
contrasts a clause such as the clause in the *Second Ambica
Construction Case with the clause in **Tehri Hydro
Development Corporation Ltd., it becomes clear that unless a
contractor agrees that no claim for interest will either be
                                                                       D
entertained or payable by the other party owing to dispute,
difference, or misunderstandings between the parties or in
respect of delay on the part of the engineer or in any other respect
whatsoever, leading the Court to find an express bar against
payment of interest, a clause which merely states that no interest
will be payable upon amounts payable to the contractor under           E
the contract would not be sufficient to bar an arbitrator from
awarding pendente lite interest under the 1940 Act. As has been
held in the ***First Ambica Construction Case the grant of
pendente lite interest depends upon the phraseology used in the
agreement, clauses conferring power relating to arbitration, the
                                                                       F
nature of claim and dispute referred to the Arbitrator, and on
what items the power to award interest has been taken away and
for which period. The position as explained in some of the
judgments under Section 31(7) of the 1996 Act, is wholly different,
inasmuch as Section 31(7) of the 1996 Act sanctifies agreements
between the parties and states that the moment the agreement           G
says otherwise, no interest becomes payable right from the date
of the cause of action until the award is delivered. [Para 22]
[645-D-H; 646-A-C]
      1.2 In the instant case, clause 16 of the General Conditions
of Contract only speaks of any delay in payment not making ONGC        H
620            SUPREME COURT REPORTS                      [2018] 6 S.C.R.


A     liable for interest. There is nothing in this clause which refers
      even obliquely to the Arbitrator’s power to grant interest. This
      Court finds that the said clause is narrower than the clause
      considered by the three-Judge Bench in the *Second Ambica
      Construction Case which states that no interest will be payable
      on amounts payable to the contractor under the contract. Clause
B
      16 in the present case confines itself only to delay in payment
      and not to any other amounts payable to the contractor under the
      contract. Also, unlike the clause in **Tehri Hydro Development
      Corporation Ltd., clause 16 does not contain language which is
      so wide in nature that it would interdict an arbitrator from granting
C     pendente lite interest. It will be remembered that the clause in
      **Tehri Hydro Development Corporation Ltd. spoke of no claim
      for interest being entertained or payable in respect of any money
      which may be lying with the Government owing to disputes,
      difference or misunderstanding between the parties and not
      merely in respect of delay or omission; Further, the clause in
D
      **Tehri Hydro Development Corporation Ltd. goes much further
      and makes it clear that no claim for interest is payable “in any
      other respect whatsoever.” It is, thus, clear that clause 16 cannot
      possibly interdict the payment of pendente lite interest on the
      facts of the present case. [Para 23] [646-D-G]
E           1.3 The submission that, in any case, on the facts of the
      present case, clause 16 is not at all attracted inasmuch as factually
      there was no delay in payment as a sum of Rs.14,999/- per MT
      had, in fact, been paid for both 1200 MT and 600 MT, but that
      the balance only became payable on and from the date of the
F     award, is right, as it is nobody’s case that there was delay in
      payment on the facts of this case. It is only after Reliance went in
      a Writ Petition before the High Court that it became clear that a
      higher price would be payable, which was left to the Arbitrator to
      determine vide the High Court’s judgment referring the issue of
      price to an arbitrator, which was accepted by ONGC. In this view
G     of the matter, it is clear that no delay on account of the higher
      price ever took place as it became payable only on and from the
      date of the award, Rs.14,999/- per MT having been paid on time
      earlier. This being the case, it is clear that even if clause 16 were
      to have application, both pre-reference and pendente lite interest
H     are not barred. [Para 24] [646-H; 647-A-C]
    RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                         621
          NATURAL GAS CORPORATION LTD.

       1.4 The only reason given for reducing interest from 18%         A
to 10% being that ONGC is a Public Sector Undertaking, would
not suffice to set aside what was within the Arbitrator’s discretion.
There is no finding that this discretion has been exercised
perversely, given the interest rates at the time of the award. The
grant of interest at the rate of 18% as pre-reference and pendente
                                                                        B
lite interest is upheld. Considering the fact that ONGC has
deposited the difference in the principal sums payable, and pre-
reference, pendent lite and future interest, all at the rate of 10%
being a sum of Rs.1,09,34,323/- till 21.01.1999, and a sum of
Rs.46,86,138/- on 30.04.2003, it is made clear that recovery of
interest till the two aforementioned dates will be at the rate of       C
18%. Thus, for pre-reference, pendent lite and future interest,
ONGC is to pay the differential amount of interest of 8% till
21.01.1999 and 30.04.2003 within a period of eight weeks from
today. In the interest of justice, it is clarified that on and from
21.01.1999, till payment, future interest is to be paid at 6% per
                                                                        D
annum on the balance differential sum of interest, being the
difference between 10% and 18%, and similarly, on the balance
differential sum of interest between 10% and 18% on and from
30.04.2003 till payment. [Para 25] [647-D-G]
      Irrigation Department, State of Orissa v. G.C. Roy (1992)
      1 SCC 508 : [1991] 3 Suppl. SCR 417 ; Executive                   E
      Engineer (Irrigation), Balimela v. Abhaduta Jena
      (1988) 1 SCC 418 : [1988] 1 SCR 253 ; Executive
      Engineer, Dhenkanal Minor Irrigation Division, Orissa
      and Ors. v. N.C. Budharaj (2001) 2 SCC 721 :
      [2001] 1 SCR 264 ; Board of Trustees for the Port of              F
      Calcutta v. Engineers-De-Space-Age, (1996) 1 SCC
      516 : [1995] 6 Suppl. SCR 327 ; Bhagwati Oxygen
      Ltd. v. Hindustan Copper Ltd., (2005) 6 SCC 462 :
      [2005] 3 SCR 232 ; M.B. Patel and Co. v. ONGC (2008)
      8 SCC 251 : [2008] 8 SCR 35 ; State of Rajasthan and
      Anr. v. M/s. Ferro Concrete Construction (P) Ltd. (2009)          G
      12 SCC 1: [2009] 10 SCR 31 ; Union of India v.
      Saraswat Trading Agency (2009) 16 SCC 504 : [2009]
      10 SCR 1063; Madnani Construction Corporation (P)
      Ltd. v. Union of India and Ors. (2010) 1 SCC 549 :
                                                                        H
622          SUPREME COURT REPORTS                     [2018] 6 S.C.R.


A          [2009] 16 SCR 216 ; State of U.P. v. Harish Chandra
           and Co. (1999) 1 SCC 63 : [1998] 2 Suppl. SCR 660 ;
           Sree Kamatchi Amman Constructions v. The Divisional
           Railway Manager (Works), Palghat and Ors., (2010) 8
           SCC 767 : [2010] 10 SCR 487; Union of India v.
           Krafters Engineering and Leasing (P) Ltd. (2011) 7 SCC
B
           279 : [2011] 8 SCR 196 ; **Tehri Hydro Development
           Corporation Ltd. v. Jai Prakash Associates Ltd. (2012)
           12 SCC 10 : [2012] 8 SCR 813 ; Union of India v.
           Bright Power Projects (India) (P) Ltd. (2015) 9 SCC
           695 : [2015] 6 SCR 488 ; ***Union of India v. Ambica
C          Construction (“First Ambica Construction Case”),
           (2016) 6 SCC 36 : [2016] 2 SCR 810; *Ambica
           Construction v. Union of India (“Second Ambica
           Construction Case”) (2017) 14 SCC 323 ;
           M/s Raveechee v. Union of India 2018 (8) SCALE 415
           – referred to.
D
                           Case Law Reference
      [1991] 3 Suppl. SCR 417      referred to            Para 7
      [1988] 1 SCR 253             referred to            Para 7
      [2001] 1 SCR 264             referred to            Para 7
E     [1995] 6 Suppl. SCR 327      referred to            Para 8
      [2005] 3 SCR 232             referred to            Para 9
      [2008] 8 SCR 35              referred to            Para 10
      [2009] 10 SCR 31             referred to            Para 11
      [2009] 10 SCR 1063           referred to            Para 12
F
      [2009] 16 SCR 216            referred to            Para 13
      [1998] 2 Suppl. SCR 660      referred to            Para 13
      [2010] 10 SCR 487            referred to            Para 14
      [2011] 8 SCR 196             referred to            Para 15
G     [2012] 8 SCR 813             referred to            Para 17
      [2015] 6 SCR 488             referred to            Para 18
      [2016] 2 SCR 810             referred to            Para 19
      (2017) 14 SCC 323            referred to            Para 20
      2018 (8 ) SCALE 415          referred to            Para 21
H
    RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                 623
          NATURAL GAS CORPORATION LTD.

      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1110                      A
of 2010.
      From the Judgment and Order dated 23.08.2006 of the High Court
of Gujarat at Ahmedabad in First Appeal No. 5767 of 1998
                                   WITH                                         B
      Civil Appeal No. 1111 of 2010.
       Sandeep Sethi, ASG, K. V. Viswanathan, Sr. Adv., Shabyashachi
Patra, Sanjeev Kumar (for M/s Khaitan & Co.), P. B. Suresh, Vipin
Nair, Abhay Pratap Singh, Advs.for the appearing parties.
                                                                                C
      The Judgment of the Court was delivered by
       R. F. NARIMAN, J. 1. The present appeals relate to questions
which arise qua the pre-reference and pendente lite interest under the
Arbitration Act, 1940. The ONGC floated a notice inviting tender for the
supply of 1200 Metric Tons (hereinafter referred to as “MT”) of Sodium          D
Carboxyl Methyl Cellulose (hereinafter referred to as “CMC”). Reliance
Cellulose Products Ltd. (hereinafter referred to as “Reliance”) submitted
its tender quoting a price of Rs.14,999/- per MT for quantities above 900
MT. It is not disputed that the offer of Reliance was accepted for the
supply of 1200 MT of CMC, and accordingly, a supply order dated                 E
01.12.1988 was placed on Reliance. Since Reliance agreed to supply
1200 MT only if the price is higher than Rs.14,999/- per MT, the parties
ultimately went to arbitration in order to decide what should be the contract
price for supply of 1200 MT of CMC. A separate order, referred to as
the repeat order, was also placed for supply of 600 MT of CMC. It is
undisputed that the supply was made on time and payments were received          F
for both contracts at the rate of Rs.14,999/- per MT.
       2. In October 1990, the petitioner filed a Special Civil Application
before the Gujarat High Court in the course of which, by an order dated
11.10.1990, the disputes between the parties were referred to arbitration,
                                                                                G
which were with regard to the price for the supply of 1200 MT and 600
MT of CMC respectively. The original Arbitral Tribunal consisted of
Justice V.S. Deshpande and Mr. S. Tibrewal. Shri Deshpande having
died, Justice B.J. Divan was appointed in his place.

                                                                                H
624            SUPREME COURT REPORTS                           [2018] 6 S.C.R.


A           3. By an award dated 29.12.1993, the Arbitrators fixed the price
      of 1200 MT at Rs.18,500/- per MT, and Rs.20,500/- per MT insofar as
      600 MT of CMC was concerned. The Arbitrators awarded pre-reference,
      pendente lite and future interest all at the rate of 18% per annum.
      Objections were filed to the award by the ONGC. The learned Civil
      Judge, by his judgment dated 30.07.1998, rejected these objections, but
B
      ultimately reduced the interest for all three periods to 10% per annum.
      Needless to state, this interest was payable on the difference between
      Rs.14,999/- and Rs.18,500/- and Rs.20,500/- respectively. The appeals
      that were filed to the High Court yielded the same result vide the
      impugned judgment dated 23.08.2006. Both parties are in appeal before
C     us.
             4. Shri K.V. Viswanathan, who argued Civil Appeal No.1110/2010,
      has argued before us that no good reason is given for reducing interest
      from 18% to 10%. Indeed, the only reason that is forthcoming from the
      impugned judgment is that interest has been reduced because ONGC is
D     a Public Sector Undertaking. According to him, therefore, pre-reference,
      pendente lite and future interest at 18% all become payable from the
      date of the cause of action till 21.01.1999, when the ONGC had deposited
      an amount of Rs.1,09,34,323/-, and an amount of Rs.46,86,138/- on
      30.04.2003, on account of principal and interest at the rate of 10% per
      annum, and differential interest till date.
E
             5. In the ONGC appeal, the learned Additional Solicitor General,
      Shri Sandeep Sethi, has argued that though the plea that no pre-reference
      or pendente lite interest was payable, there is an express bar to the grant
      of such interest between the parties, which was noted by both the learned
      Civil Judge and the High Court, but no finding has been given thereon.
F     According to the learned ASG, clause 16 of the General Conditions of
      Contract clearly bars payment of interest for any delay and is set out
      hereinbelow:
            “16. Our standard terms of payment are within 30 days of receipt
            of stores and inspection at site. But any delay in payment will not
G           make the Commission liable for any interest.”
             6. He has cited a number of judgments to buttress his submission
      that clause 16 would amount to a contractual bar to the payment of any
      interest on the facts of this case. On the other hand, Shri Viswanathan
      has also referred to various judgments. His argument is that clause 16
H
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                 625
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

does not apply at all on the facts of this case as there was no delay in       A
payment, but only the difference between the sum of Rs.14,999/- per
MT and the higher figures mentioned above were payable on account of
the disputes between the parties being resolved through arbitration. In
any case, he submitted that a holistic reading of the various decisions
cited by both the learned ASG as well as by him would show that so far
                                                                               B
as the 1940 Act is concerned, interest would be payable only if there is
no express bar in the agreement, and agreements between the parties
have to be construed strictly as interest is the grant of compensation for
value of money lost, as has been held in some of the judgments. This
being so, though there may be a bar inter-se the parties, yet the Arbitrator
is not barred from awarding either pre-reference or pendente lite interest.    C
It may be added that there is no dispute that future interest is to be
granted, except as to the rate of interest awarded.
       7. Two important five-Judge Bench judgments have laid down
that, under the 1940 Act, in the absence of an express bar under the
agreement, the Arbitrator has jurisdiction to award interest for all three     D
periods, i.e., pre-reference, pendente lite as well as future interest. The
judgment of this Court in Irrigation Department, State of Orissa v.
G.C. Roy, (1992) 1 SCC 508, overruled Jena’s case [Executive
Engineer (Irrigation), Balimela v. Abhaduta Jena, (1988) 1 SCC 418]
and held that arbitrators under the 1940 Act would be clothed with the
jurisdiction to award pendente lite interest. Insofar as pre-reference         E
interest is concerned, another five-Judge Bench in Executive Engineer,
Dhenkanal Minor Irrigation Division, Orissa and Ors. v. N.C.
Budharaj, (2001) 2 SCC 721, held that arbitrators under the 1940 Act
were clothed with the power to award pre-reference interest even before
the 1978 Interest Act came into force. We are concerned in the present         F
case only with the 1940 Act. The 1996 Act has made a major departure
from the position under the 1940 Act qua pre-reference and pendente
lite interest which will emerge from the conspectus of case law laid
down by this Court.
       8. In Board of Trustees for the Port of Calcutta v. Engineers-          G
De-Space-Age, (1996) 1 SCC 516, a two-Judge Bench of this Court
had to consider whether clause 13(g) of the contract barred the award
of interest pendente lite. Clause 13(g) of the contract in that case is set
out hereunder:-

                                                                               H
626               SUPREME COURT REPORTS                            [2018] 6 S.C.R.


A              “No claim for interest will be entertained by the Commissioners
               with respect to any money or balance which may be in their hands
               owing to any dispute between themselves and the Contractor or
               with respect to any delay on the part of the Commissioners in
               making interim or final payment or otherwise.”
B                                                                  [at paragraph 2]
               After setting out the judgment in G.C. Roy (supra), this Court
      held:-
               “4. We are not dealing with a case in regard to award of interest
               for the period prior to the reference. We are dealing with a case
C              in regard to award of interest by the arbitrator post reference.
               The short question, therefore, is whether in view of sub-clause
               (g) of clause 13 of the contract extracted earlier the arbitrator
               was prohibited from granting interest under the contract. Now
               the term in sub-clause (g) merely prohibits the Commissioner from
D              entertaining any claim for interest and does not prohibit the
               arbitrator from awarding interest. The opening words “no claim
               for interest will be entertained by the Commissioner” clearly
               establishes that the intention was to prohibit the Commissioner
               from granting interest on account of delayed payment to the
               contractor. Clause has to be strictly construed for the simple reason
E              that as pointed out by the Constitution Bench, ordinarily, a person
               who has a legitimate claim is entitled to payment within a reasonable
               time and if the payment has been delayed beyond reasonable time
               he can legitimately claim to be compensated for that delay
               whatever nomenclature one may give to his claim in that behalf.
F              If that be so, we would be justified in placing a strict construction
               on the term of the contract on which reliance has been placed.
               Strictly construed the term of the contract merely prohibits the
               Commissioner from paying interest to the contractor for delayed
               payment but once the matter goes to arbitration the discretion of
               the arbitrator is not, in any manner, stifled by this term of the
G              contract and the arbitrator would be entitled to consider the question
               of grant of interest pendente lite and award interest if he finds the
               claim to be justified. We are, therefore, of the opinion that under
               the clause of the contract the arbitrator was in no manner prohibited
               from awarding interest pendente lite.”
H
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                   627
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

       9. In Bhagwati Oxygen Ltd. v. Hindustan Copper Ltd., (2005)               A
6 SCC 462, a judgment of two learned judges arising out of the 1940
Act, this Court was concerned with all the three periods relating to interest,
and held that it was open for the Arbitrator acting under the 1940 Act to
award interest for each of these periods provided there is no contractual
bar.
                                                                                 B
      10. In M.B. Patel and Co. v. ONGC, (2008) 8 SCC 251, the
clause which was said to interdict interest was clause 18 of the
Agreement which provided as follows:
       “18. Interest on amounts.—No interest will be payable on the
       security deposit or any other amount payable to the contractor            C
       under the contract.”
                                                            [at paragraph 4]
       The Court held that interest had been awarded in violation of
clause 14 of the Agreement as the Arbitrator did not take into account
this clause at all. On this and other grounds, the Award as a whole was          D
set aside, and remanded to the Arbitrator to consider the matter afresh.
       11. In State of Rajasthan and Anr. v. M/s. Ferro Concrete
Construction (P) Ltd., (2009) 12 SCC 1, a two-Judge Bench decision
of this Court was concerned with pre-reference interest given by an
award under the 1940 Act. This Court restated the position qua pre-              E
reference interest by referring to the five-Judge Bench referred to
hereinabove and Bhagwati Oxygen (supra). What was highlighted was
the importance of the Interest Act, 1978, under Section 3 of which it is
clear that pre-reference interest can be allowed by an arbitrator unless
there is a bar by virtue of an express provision between the parties (see        F
paragraphs 63 and 64).
      12. In Union of India v. Saraswat Trading Agency, (2009) 16
SCC 504, the question of pendente lite interest arose under the Arbitration
and Conciliation Act, 1996. The clause which was said to bar interest in
the aforesaid case was clause 31 of the Agreement which provided as
                                                                                 G
follows:
       “31. No interest or damage for delay in payment.—No interest
       or damage shall be paid to the contractor for delay in payment
       of the bill or any other amount due to the contractor for any
                                                                                 H
628            SUPREME COURT REPORTS                          [2018] 6 S.C.R.


A           reason whatsoever. The Railway Administration will, however,
            make every endeavour for payment of the bills or other amount
            due to the contractor within a reasonable time.”
                                                          [emphasis supplied]
             The judgment in Engineers-De-Space-Age (supra) was
B     distinguished by stating that clause 31 of the Agreement was materially
      different as no interest or damage was payable for any reason
      whatsoever, as a result of which it was held:
            “33. In the case in hand Clause 31 of the agreement is materially
            different. It bars payment of any interest or damage to the
C           contractor for any reason whatsoever. We are, therefore, clearly
            of the view that no pre-reference or pendente lite interest was
            payable to the respondent on the amount under Item 3 and the
            arbitrator’s award allowing pre-reference and pendente lite interest
            on that amount was plainly in breach of the express terms of the
D           agreement. The order of the High Court insofar as pre-reference
            and pendente lite interest on the amount under Item 3 is concerned
            is, therefore, unsustainable.”
              This case has later been distinguished as having arisen under the
      1996 Act, under which the position qua both pre-reference and pendente
E     lite interest is materially different.
             13. In Madnani Construction Corporation (P) Ltd. v. Union
      of India and Ors., (2010) 1 SCC 549, two judges of this Court had to
      deal with the grant of pre-reference interest under the Interest Act in an
      award passed under the 1940 Act. Paragraphs 22 and 23 of the judgment
F     set out the clauses which interdict payment of interest as follows:
            “22. … Clause 16(2) of GCC is set out below:
                “16. (2) No interest will be payable upon the earnest money or
                the security deposit or amounts payable to the contractor under
                the contract but government securities deposited in terms of
G               such Clause (1) of this Clause will be repayable with interest
                accrued thereto.”
            23. … The relevant portion of Clause 30 relating to interest is set
            out below:

H
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                629
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

          “… That the contractor will have no claim for interest and          A
          damage whatsoever on any account in respect of such
          withholding or retention under the lien referred to supra and
          duly notified as such to the contractor.”
      After referring to the Interest Act and Section 29 of the Arbitration
Act, 1940, the Court referred to a three-Judge Bench decision in State        B
of U.P. v. Harish Chandra and Co., (1999) 1 SCC 63, as follows:
      “34. In a subsequent decision of a three-Judge Bench in State of
      U.P. v. Harish Chandra and Co. [(1999) 1 SCC 63] there was
      stipulation in the arbitration agreement against grant of interest.
      The relevant clause, namely, Clause 1.9 to the aforesaid effect is      C
      set out below: (SCC p. 67, para 9)
          “9. … ‘1.9. No claim for delayed payment due to dispute,
          etc.—No claim for interest or damages will be entertained by
          the Government with respect to any moneys or balances which
          may be lying with the Government owing to any dispute,              D
          difference; or misunderstanding between the Engineer-in-
          Charge in marking periodical or final payments or in any other
          respect whatsoever.’ “
      Considering the said clause, the Court held that the prohibition in
      the said clause does not prevent the contractor from raising the        E
      claim of interest by way of damages before the arbitrator on the
      relevant items placed for adjudication. (See SCC p. 67, para 10.)
      In saying so, the learned Judges relied on the ratio in B.N.
      Agarwalla [(1997) 2 SCC 469] and G.C. Roy [(1992) 1 SCC
      508].”
                                                                              F
      It then referred to Engineers-De-Space-Age (supra) in
paragraph 35 and Saraswat Trading Agency (supra) in paragraphs 37
and 38. Finally, however, the two-Judge Bench held:-
      “39. In the instant case also the relevant clauses, which have
      been quoted above, namely, Clause 16(2) of GCC and Clause 30
                                                                              G
      of SCC do not contain any prohibition on the arbitrator to grant
      interest. Therefore, the High Court was not right in interfering
      with the arbitrator’s award on the matter of interest on the basis
      of the aforesaid clauses. We therefore, on a strict construction of

                                                                              H
630            SUPREME COURT REPORTS                            [2018] 6 S.C.R.


A           those clauses and relying on the ratio in Engineers [(1996) 1 SCC
            516] find that the said clauses do not impose any bar on the arbitrator
            in granting interest.”
             14. In Sree Kamatchi Amman Constructions v. The
      Divisional Railway Manager (Works), Palghat and Ors., (2010) 8
B     SCC 767, a two-Judge Bench of this Court, after referring to some of
      the earlier judgments of this Court, held: -
            “18. At the outset it should be noticed that Engineers-De-Space-
            Age [(1996) 1 SCC 516] and Madnani [(2010) 1 SCC 549] arose
            under the old Arbitration Act, 1940 which did not contain a provision
C           similar to Section 31(7) of the new Act. This Court, in Sayeed
            Ahmed [(2009) 12 SCC 26] held that the decisions rendered under
            the old Act may not be of assistance to decide the validity of grant
            of interest under the new Act. The logic in Engineers-De-Space-
            Age [(1996) 1 SCC 516] was that while the contract governed
            the interest from the date of cause of action to date of reference,
D           the arbitrator had the discretion to decide the rate of interest from
            the date of reference to date of award and he was not bound by
            any prohibition regarding interest contained in the contract, insofar
            as pendente lite period is concerned. This Court in Sayeed Ahmed
            [(2009) 12 SCC 26] held that the decision in Engineers-De-Space-
E           Age [(1996) 1 SCC 516] would not apply to cases arising under
            the new Act. We extract below, the relevant portion from Sayeed
            Ahmed [(2009) 12 SCC 26] : (SCC p. 36, paras 23-24)
               “23. The observation in Engineers-De-Space-Age [(1996) 1
               SCC 516] that the term of the contract merely prohibits the
F              department/ employer from paying interest to the contractor
               for delayed payment but once the matter goes to the arbitrator,
               the discretion of the arbitrator is not in any manner stifled by
               the terms of the contract and the arbitrator will be entitled to
               consider and grant the interest pendente lite, cannot be used to
               support an outlandish argument that bar on the Government or
G              department paying interest is not a bar on the arbitrator
               awarding interest. Whether the provision in the contract bars
               the employer from entertaining any claim for interest or bars
               the contractor from making any claim for interest, it amounts
               to a clear prohibition regarding interest. The provision need
H
 RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                              631
NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

     not contain another bar prohibiting the arbitrator from awarding     A
     interest. The observations made in the context of interest
     pendente lite cannot be used out of contract.
     24. The learned counsel for the appellant next contended on
     the basis of the above observations in Engineers-De-Space-
     Age [(1996) 1 SCC 516], that even if Clause G 1.09 is held to        B
     bar interest in the pre-reference period, it should be held not to
     apply to the pendente lite period, that is, from 14-3-1997 to 31-
     7-2001. He contended that the award of interest during the
     pendency of the reference was within the discretion of the
     arbitrator and therefore, the award of interest for that period
     could not have been interfered with by the High Court. In view       C
     of the Constitution Bench decisions in G.C. Roy [(1992) 1 SCC
     508] and N.C. Budharaj [(2001) 2 SCC 721] rendered before
     and after the decision in Engineers-De-Space-Age [(1996) 1
     SCC 16], it is doubtful whether the observation in Engineers-
     De-Space-Age [(1996) 1 SCC 516] in a case arising under              D
     the Arbitration Act, 1940 that the arbitrator could award interest
     pendente lite, ignoring the express bar in the contract, is good
     law. But that need not be considered further as this is a case
     under the new Act where there is a specific provision regarding
     award of interest by the arbitrator.”
                                                                          E
     The same reasoning applies to the decision in Madnani [(2010)
     1 SCC 549] also as that also relates to a case under the old
     Act and did not independently consider the issue but merely
     relied upon the decision in Engineers-De-Space-Age [(1996)
     1 SCC 516].
                                                                          F
  19. Section 37(1) [Sic Section 31(7)] of the new Act by using the
  words “unless otherwise agreed by the parties” categorically
  clarifies that the arbitrator is bound by the terms of the contract
  insofar as the award of interest from the date of cause of action
  to the date of award. Therefore, where the parties had agreed
  that no interest shall be payable, the Arbitral Tribunal cannot award   G
  interest between the date when the cause of action arose to the
  date of award.”
                                                [emphasis supplied]

                                                                          H
632            SUPREME COURT REPORTS                          [2018] 6 S.C.R.


A           15. In Union of India v. Krafters Engineering and Leasing
      (P) Ltd. (2011) 7 SCC 279, a two-Judge Bench considered as to whether
      clause 1.15 of the contract in that case would bar pendente lite interest.
      Clause 1.15 reads as follows:
            “1.15. Interest on amounts.—No interest will be payable upon
B           the earnest money or the security deposit or amounts payable to
            the contractor under the contract but government securities
            deposited in terms of Clause 1.14.4 will be repayable with interest
            accrued thereon.”
            This Court, after referring to Engineers-De-Space-Age (supra)
C     and Sayeed Ahmed [Sayeed Ahmed and Co. v. State of U.P., (2009)
      12 SCC 26], then held that they were of the view that Sayeed Ahmed
      (supra) having held to the contrary, Engineers-De-Space-Age (supra)
      could not possibly be followed. Same was the position with Madnani
      Construction (supra) which was dismissed by saying that it did not
      independently consider the issue but merely relied upon the decision in
D     Engineers-De-Space-Age (supra). The Court then went on to state:-
            “20. In the light of the above discussion, the following conclusion
            emerges: reliance based on the ratio in Engineers-De-Space-
            Age [(1996) 1 SCC 516] is unacceptable since the said view has
            been overruled in Sayeed Ahmed and Co. [(2009) 12 SCC 26 :
E           (2009) 4 SCC (Civ) 629] and insofar as the ratio in Madnani
            Construction Corpn. (P) Ltd. [(2010) 1 SCC 549 : (2010) 1 SCC
            (Civ) 168] which is also unacceptable for the reasons mentioned
            in the earlier paras, we reject the stand taken by the counsel for
            the respondent. On the other hand, we fully accept the stand of
F           the Union of India as rightly projected by Mr. A.S. Chandhiok,
            learned ASG. We reiterate that where the parties had agreed that
            no interest shall be payable, the arbitrator cannot award interest
            for the amounts payable to the contractor under the contract.
            Where the agreement between the parties does not prohibit grant
            of interest and where a party claims interest and the said dispute
G           is referred to the arbitrator, he shall have the power to award
            interest pendente lite. As observed by the Constitution Bench in
            G.C. Roy case [(1992) 1 SCC 508], in such a case, it must be
            presumed that interest was an implied term of the agreement
            between the parties. However, this does not mean that in every
H           case, the arbitrator should necessarily award interest pendente
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                 633
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

      lite. In the subsequent decision of the Constitution Bench i.e. N.C.     A
      Budharaj case [(2001) 2 SCC 721], it has been reiterated that in
      the absence of any specific stipulation or prohibition in the contract
      to claim or grant any such interest, the arbitrator is free to award
      interest.
      21. In the light of the above principle and in view of the specific      B
      prohibition of contract contained in Clause 1.15, the arbitrator
      ceases to have the power to grant interest. We also clarify that
      the Arbitration Act, 1940 does not contain any specific provision
      relating to the power of arbitrator to award interest. However, in
      the Arbitration and Conciliation Act, 1996, there is a specific
      provision with regard to award of interest by the arbitrator. The        C
      bar under Clause 1.15 is absolute and interest cannot be awarded
      without rewriting the contract.”
      16. Clearly, the conclusion of the Court that Engineers-De-
Space-Age (supra) had been overruled by Sayeed Ahmed (supra) is
incorrect for two reasons: first, a Bench of two learned Judges cannot         D
overrule a coordinate Bench of two learned Judges; and second, the
Court in Sayeed Ahmed (supra) was not deciding a case arising under
the 1940 Act, but was deciding a case arising under the 1996 Act.
      17. In Tehri Hydro Development Corporation Ltd. v. Jai
Prakash Associates Ltd., (2012) 12 SCC 10, a three-Judge Bench of              E
this Court dealt with an award passed under the 1940 Act. The relevant
clauses barring interest under the agreement in that case are set out
herein below:-
      “14. … Clauses 1.2.14 and 1.2.15 on which much arguments
      have been advanced by the learned counsel for both sides may             F
      now be extracted below:
                                      “PART II
                             CONDITIONS OF CONTRACT

         1.2.14. No claim for delayed payment due to dispute, etc.—            G
         The contractor agrees that no claim for interest of damages
         will be entertained or payable by the Government in respect of
         any money or balances which may be lying with the
         Government owing to any disputes, differences or
         misunderstandings between the parties or in respect of any
                                                                               H
634           SUPREME COURT REPORTS                           [2018] 6 S.C.R.


A             delay or omission on the part of the engineer-in-charge in
              making immediate or final payments or in any other respect
              whatsoever.
              1.2.15. Interest on money due to the contractor.—No
              omission on the part of the engineer-in-charge to pay the amount
B             due upon measurement or otherwise shall vitiate or make void
              the contract, nor shall the contractor be entitled to interest upon
              any guarantee or payments in arrears nor upon any balance
              which may on the final settlement of his accounts be due to
              him.”
C            After referring to Krafters Engineering (supra) and some of
      the earlier judgments, it was held:
           “16. In Krafters Engg. case [(2011) 7 SCC 279 : (2011) 3 SCC
           (Civ) 533] the somewhat discordant note struck by the decisions
           of this Court in Port of Calcutta v. Engineers-De-Space-Age
D          [(1996) 1 SCC 516] and Madnani Construction Corpn. (P) Ltd.
           v. Union of India [(2010) 1 SCC 549 : (2010) 1 SCC (Civ) 168]
           were also taken note of. Thereafter, it was also noticed that the
           decision in Engineers-De-Space-Age case [(1996) 1 SCC 516]
           was considered in Sayeed Ahmed & Co. v. State of U.P. [(2009)
           12 SCC 26 : (2009) 4 SCC (Civ) 629] and the decision in Madnani
E          Construction case [(2010) 1 SCC 549 : (2010) 1 SCC (Civ) 168]
           was considered in Sree Kamatchi Amman Constructions v.
           Railways [(2010) 8 SCC 767 : (2010) 3 SCC (Civ) 575] . In Sayeed
           Ahmed case [(2009) 12 SCC 26 : (2009) 4 SCC (Civ) 629] (SCC
           para 24) it was held that in the light of the decisions of the
F          Constitution Bench in G.C. Roy case[(1992) 1 SCC 508] and
           N.C. Budharaj case [(2001) 2 SCC 721] it is doubtful whether
           the observations in Engineers-De-Space-Age case [(1996) 1
           SCC 516] to the effect that the arbitrator could award interest
           pendente lite, ignoring the express bar in the contract, is good law.
           In Sree Kamatchi Amman Constructions case [(2010) 8 SCC
G          767 : (2010) 3 SCC (Civ) 575] while considering Madnani case
           [(2010) 1 SCC 549 : (2010) 1 SCC (Civ) 168] this Court noted
           that the decision in Madnani case [(2010) 1 SCC 549 : (2010) 1
           SCC (Civ) 168] follows the decision in Engineers-De-Space-
           Age case[(1996) 1 SCC 516].”
H
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                635
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

      In this view of the matter, the Court held:                             A
      “19. Clauses 1.2.14 and 1.2.15, already extracted and analysed,
      imposed a clear bar on either entertainment or payment of interest
      in any situation of non-payment or delayed payment of either the
      amounts due for work done or lying in security deposit. On the
      basis of the discussions that have preceded we, therefore, take         B
      the view that the grant of pendente lite interest on the claim of Rs
      10,17,461 lakhs is not justified. The award as well as the orders of
      the courts below are accordingly modified to the aforesaid extent.
      20. However, the grant of interest for the post-award period would
      stand on a somewhat different footing. This very issue has been         C
      elaborately considered by this Court in B.N. Agarwalla [(1997) 2
      SCC 469] in the light of the provisions of Section 29 of the
      Arbitration Act, 1940. Eventually this Court took the view that in
      a situation where the award passed by the arbitrator granting
      interest from the date of the award till the date of payment is not
      modified by the Court “… the effect would be as if the Court            D
      itself had granted interest from the date of the decree till the date
      of payment…”. In view of the above, the grant of interest on the
      amount of Rs 10,17,461 lakhs from the date of the award till the
      date of the decree or date of payment, whichever is earlier, is
      upheld. In the facts of the case we are of the view that the rate of    E
      interest should be 12% per annum as determined in the arbitration
      proceeding between the parties.”
       18. In Union of India v. Bright Power Projects (India) (P)
Ltd., (2015) 9 SCC 695, a three-Judge Bench of this Court had to deal
with interest awarded by an arbitral award under the 1996 Act. This           F
judgment, like Sree Kamatchi Amman Constructions (supra), sets
out how Section 31(7)(a) is a complete departure from the position under
the 1940 Act. This Court held:-
      “12. Section 31(7) of the Arbitration and Conciliation Act, 1996
      (hereinafter referred to as “the Act”) is clear to the effect that      G
      unless otherwise agreed by the parties, the Arbitral Tribunal can
      award interest at reasonable rate for a period commencing from
      that date when the cause of action arises till the date of the award.
      Section 31(7) of the Act, reads as under:

                                                                              H
636      SUPREME COURT REPORTS                         [2018] 6 S.C.R.


A        “31. (7)(a) Unless otherwise agreed by the parties, where
         and insofar as an arbitral award is for the payment of money,
         the Arbitral Tribunal may include in the sum for which the
         award is made interest, at such rate as it deems reasonable, on
         the whole or any part of the money, for the whole or any part
         of the period between the date on which the cause of action
B
         arose and the date on which the award is made.”
      13. Section 31(7) of the Act, by using the words “unless otherwise
      agreed by the parties”, categorically specifies that the arbitrator
      is bound by the terms of the contract so far as award of interest
      from the date of cause of action to date of the award is
C     concerned. Therefore, where the parties had agreed that no
      interest shall be payable, the Arbitral Tribunal cannot award
      interest.
      14. We may also refer to the decision of this Court in Union of
      India v. Saraswat Trading Agency [(2009) 16 SCC 504: (2011)
D     3 SCC (Civ) 499]. This Court has observed in the said case that if
      there is a bar against payment of interest in the contract, the
      arbitrator cannot award any interest for such period. In view of
      the specific bar under Clause 13(3) of the contract entered into
      between the parties, we are of the view that the Arbitral Tribunal
E     was not justified in awarding interest from the date of entering
      upon the reference to the Arbitral Tribunal till the date of the
      award.
      xxxxxx
      16. Relying upon the aforestated judgment delivered by this Court,
F     the Arbitral Tribunal thought it proper to award interest on the
      amount payable to the contractor for the period commencing from
      the date on which the reference was entered upon till the date of
      the award. The Tribunal, however, failed to consider the provisions
      of Section 31(7) of the Act and Clause 13(3) of the contract before
G     awarding interest in the present case.
      17. It is also pertinent to note that G.C. Roy case [(1992) 1 SCC
      508] had been decided on 12-12-1991 on the basis of the provisions
      of the Arbitration Act, 1940, which was not operative at the time
      when the dispute on hand was decided by the Arbitral Tribunal.
H
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                             637
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

      18. Section 31(7)(a) of the Act ought to have been read and          A
      interpreted by the Arbitral Tribunal before taking any decision
      with regard to awarding interest. The said section, which has been
      reproduced hereinabove, gives more respect to the agreement
      entered into between the parties. If the parties to the agreement
      agree not to pay interest to each other, the Arbitral Tribunal has
                                                                           B
      no right to award interest pendente lite.”
                                                   [emphasis supplied]
       19. Given the labyrinth of case law referred to hereinabove, and
the perception that some of the judgments were pulling in different
directions, a reference was made to a three-Judge Bench. In Union of       C
India v. Ambica Construction (“First Ambica Construction Case”),
(2016) 6 SCC 36, paragraph 1 reflects how the matter had been referred
to a larger Bench for decision. After referring to the labyrinth of case
law that has been referred to in this case, this Court held:
      “21. This Court in Sayeed Ahmed [Sayeed Ahmed & Co. v.               D
      State of U.P., (2009) 12 SCC 26 : (2009) 4 SCC (Civ) 629] has
      also distinguished the decision in Harish Chandra [State of U.P.
      v. Harish Chandra & Co., (1999) 1 SCC 63] in which Clause
      1.09 came up for consideration thus: (Sayeed Ahmed case
      [Sayeed Ahmed & Co. v. State of U.P., (2009) 12 SCC 26 :
      (2009) 4 SCC (Civ) 629], SCC pp. 33-34, paras 17-19)                 E

         “17. … This Court held that the said clause did not bar award
         of interest on any claim for damages or for claim for payment
         for work done. We extract below the reasoning for such
         decision: (SCC p. 67, para 10)
                                                                           F
           ‘10. A mere look at the clause shows that the claim for
           interest by way of damages was not to be entertained against
           the Government with respect to only a specified type of
           amount, namely, any monies or balances which may be lying
           with the Government owing to any dispute, difference between
           the Engineer-in-Charge and the contractor; or                   G
           misunderstanding between the Engineer-in-Charge and the
           contractor in making periodical or final payments or in any
           other respect whatsoever. The words “or in any other respect
           whatsoever” also referred to the dispute pertaining to the
                                                                           H
638   SUPREME COURT REPORTS                             [2018] 6 S.C.R.


A      monies or balances which may be lying with the Government
       pursuant to the agreement meaning thereby security deposit
       or retention money or any other amount which might have
       been with the Government and refund of which might have
       been withheld by the Government. The claim for damages
       or claim for payment for the work done and which was
B
       not paid for would not obviously cover any money which
       may be said to be lying with the Government. Consequently,
       on the express language of this clause, there is no prohibition
       which could be culled out against the respondent contractor
       that he could not raise the claim for interest by way of damages
C      before the arbitrator on the relevant items placed for
       adjudication.’
      18. In Harish Chandra [State of U.P. v. Harish Chandra &
      Co., (1999) 1 SCC 63] a different version of Clause 1.09 was
      considered. Having regard to the restrictive wording of that
D     clause, this Court held that it did not bar award of interest on a
      claim for damages or a claim for payments for work done and
      which was not paid. This Court held that the said clause barred
      award of interest only on amounts which may be lying with the
      Government by way of security deposit/retention money or
      any other amount, refund of which was withheld by the
E     Government.
      19. But in the present case, clause G1.09 is significantly
      different. It specifically provides that no interest shall be payable
      in respect of any money that may become due owing to any
      dispute, difference or misunderstanding between the Engineer-
F     in-Charge and contractor or with respect to any delay on the
      part of the Engineer-in-Charge in making periodical or final
      payment or in respect of any other respect whatsoever. The
      bar under Clause G1.09 in this case being absolute, the decision
      in Harish Chandra [State of U.P. v. Harish Chandra &
G     Co., (1999) 1 SCC 63] will not assist the appellant in any
      manner.”
                                                  (emphasis in original)



H
 RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                               639
NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

     In Harish Chandra [State of U.P. v. Harish Chandra &                  A
     Co., (1999) 1 SCC 63], this Court has laid down that Clause
     1.09 did not bar award of interest for claim of damages for
     payment for work done and which was not paid for would not
     obviously cover any money which may be said to be lying with
     the Government.
                                                                           B
     22. In our opinion, it would depend upon the nature of the
     ouster clause in each case. In case there is express stipulation
     which debars pendente lite interest, obviously, it cannot be
     granted by the arbitrator. The award of pendente lite interest
     inter alia must depend upon the overall intention of the
     agreement and what is expressly excluded.”                            C

  After referring to the earlier judgments, this Court held:-
  “28. It is apparent from various decisions referred to above that
  in G.C. Roy [Irrigation Deptt., State of Orissa v. G.C. Roy,
  (1992) 1 SCC 508] the Constitution Bench of this Court has laid          D
  down that where the agreement expressly provides that no interest
  pendente lite shall be payable on amount due, the arbitrator has
  no power to award interest. In N.C. Budharaj [Dhenkanal
  Minor Irrigation Division v. N.C. Budharaj, (2001) 2 SCC 721]
  a Constitution Bench has observed that in case there is nothing in
  the arbitration agreement to exclude jurisdiction of the arbitrator      E
  to entertaining claim for interest, the jurisdiction of the arbitrator
  to consider and award interest in respect to all periods is subject
  to Section 29 of the Act. In Hindustan Construction Co. Ltd.
  [Hindustan Construction Co. Ltd. v. State of J&K, (1992) 4
  SCC 217] this Court has followed the decision in G.C. Roy                F
  [Irrigation Deptt., State of Orissa v. G.C. Roy, (1992) 1 SCC
  508] and laid down that on the basis of principles of Section 34
  the arbitrator would have the power to award pendente lite interest
  also. In B.N. Agarwalla [State of Orissa v. B.N. Agarwalla,
  (1997) 2 SCC 469], this Court has again followed G.C. Roy
  [Irrigation Deptt., State of Orissa v. G.C. Roy, (1992) 1 SCC            G
  508] and Hindustan Construction Co. Ltd. [Hindustan
  Construction Co. Ltd. v. State of J&K, (1992) 4 SCC 217] with
  respect to the power of the arbitrator to award pendente lite interest

                                                                           H
640      SUPREME COURT REPORTS                            [2018] 6 S.C.R.


A     and it was held that the arbitrator has the power to award interest.
      In Harish Chandra [State of U.P. v. Harish Chandra & Co.,
      (1999) 1 SCC 63] this Court interpreted Clause 1.9 which provided
      that no claim for interest or damages will be entertained by the
      Government in respect to any monies or balances which may be
      lying with the Government. It was held that there was no provision
B
      which could be culled out against the contractor not to claim interest
      by way of damages before the arbitrator on the relevant items
      placed for adjudication. In Ferro Concrete Construction (P) Ltd.
      [State of Rajasthan v. Ferro Concrete Construction (P) Ltd.,
      (2009) 12 SCC 1 : (2009) 4 SCC (Civ) 604] this Court considered
C     Clause 4 containing a stipulation that no interest was payable on
      amount withheld under the agreement. It was held that Clause 4,
      which dealt with rates, material and workmanship, did not bar
      award of interest by the arbitrator on claims of the contractor
      made in the said case. In Sayeed Ahmed [Sayeed Ahmed & Co.
      v. State of U.P., (2009) 12 SCC 26 : (2009) 4 SCC (Civ) 629] this
D
      Court has emphasised that award of interest would depend upon
      nature of the clause in the agreement. In Bright Power Projects
      (India) (P) Ltd. [Union of India v. Bright Power Projects
      (India) (P) Ltd., (2015) 9 SCC 695 : (2015) 4 SCC (Civ) 702] this
      Court has considered the expression “unless otherwise agreed by
E     parties” employed in Section 31(7)(a) of the 1996 Act and laid
      down that in case contract bars claim of interest the contractor
      could not have claimed interest. The provision of Section 31(7)(a)
      of the 1996 Act is binding upon the arbitrator. In Sree Kamatchi
      Amman Constructions [Sree Kamatchi Amman Constructions
      v. Railways, (2010) 8 SCC 767: (2010) 3 SCC (Civ) 575] similar
F
      view has been taken.
      29. Now we come to the question of correctness of decision of
      this Court rendered by a Bench of two Judges in Engineers-De-
      Space-Age [Port of Calcutta v. Engineers-De-Space-Age,
      (1996) 1 SCC 516] which has been referred for our consideration
G     in which this Court after consideration of G.C. Roy case [Irrigation
      Deptt., State of Orissa v. G.C. Roy, (1992) 1 SCC 508] has
      observed thus: (Engineers-De-Space-Age case [Port of
      Calcutta v. Engineers-De-Space-Age, (1996) 1 SCC 516] , SCC
      pp. 519-20, paras 3-4)
H
 RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                 641
NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

     “3. … It will appear from what the Constitution Bench stated            A
     to be the legal position, that ordinarily a person who is deprived
     of his money to which he is legitimately entitled as of right is
     entitled to be compensated in deprivation thereof, call it by
     whatever name. This would be in terms of the principle laid
     down in Section 34 of the Code of Civil Procedure. Their
                                                                             B
     Lordships pointed out that there was no reason or principle to
     hold otherwise in the case of an arbitrator. Pointing out that
     arbitrator is an alternative forum for resolution of disputes arising
     between the parties, it said that he must have the power to
     decide all disputes and differences arising between the parties
     and if he were to be denied the power to award interest                 C
     pendente lite, the party entitled thereto would be required to go
     to a court which would result in multiplicity of proceedings, a
     situation which the court should endeavour to avoid. Reliance
     was, however, placed on the observation in sub-para (iii)
     wherein it is pointed out that an arbitrator is a creature of an
                                                                             D
     agreement and if the agreement between the parties prohibits
     the payment of interest pendente lite the arbitrator must act in
     accordance therewith. In other words, according to Their
     Lordships the arbitrator is expected to act and make his award
     in accordance with the general law of the land but subject to
     an agreement, provided, the agreement is valid and legal. Lastly,       E
     it was pointed out that interest pendente lite is not a matter of
     substantive law, like interest for the period anterior to reference.
     Their Lordships concluded that where the agreement between
     the parties does not prohibit grant of interest and where a party
     claims interest and that dispute is referred to the arbitrator, he
                                                                             F
     shall have the power to award interest pendente lite for the
     simple reason that in such a case it is presumed that interest
     was an implied term of the agreement between the parties; it
     is then a matter of exercise of discretion by the arbitrator. The
     position in law has, therefore, been clearly stated in the aforesaid
     decision of the Constitution Bench.                                     G
     4. We are not dealing with a case in regard to award of interest
     for the period prior to the reference. We are dealing with a
     case in regard to award of interest by the arbitrator post
     reference. The short question, therefore, is whether in view of
                                                                             H
642      SUPREME COURT REPORTS                          [2018] 6 S.C.R.


A        sub-clause (g) of Clause 13 of the contract extracted earlier
         the arbitrator was prohibited from granting interest under the
         contract. Now the term in sub-clause (g) merely prohibits the
         Commissioner from entertaining any claim for interest and does
         not prohibit the arbitrator from awarding interest. The opening
         words “no claim for interest will be entertained by the
B
         Commissioner” clearly establishes that the intention was to
         prohibit the Commissioner from granting interest on account
         of delayed payment to the contractor. Clause 13 has to be
         strictly construed for the simple reason that as pointed out by
         the Constitution Bench, ordinarily, a person who has a legitimate
C        claim is entitled to payment within a reasonable time and if the
         payment has been delayed beyond reasonable time he can
         legitimately claim to be compensated for that delay whatever
         nomenclature one may give to his claim in that behalf.”
      30. In Sayeed Ahmed [Sayeed Ahmed & Co. v. State of U.P.,
D     (2009) 12 SCC 26 : (2009) 4 SCC (Civ) 629] the decision in
      Engineers-De-Space-Age[Port of Calcutta v. Engineers-De-
      Space-Age, (1996) 1 SCC 516] has been considered and it was
      observed that it cannot be used to support an outlandish argument
      that bar on the Government or department paying interest is not a
      bar on the arbitrator awarding interest. This Court expressed doubt
E     as to the correctness of certain observations made in Engineers-
      De-Space-Age [Port of Calcutta v. Engineers-De-Space-Age,
      (1996) 1 SCC 516] to the extent that the arbitrator could award
      interest pendente lite ignoring the express bar in the contract. But
      this Court did not consider the question further as the case in
F     Sayeed Ahmed [Sayeed Ahmed & Co. v. State of U.P., (2009)
      12 SCC 26 : (2009) 4 SCC (Civ) 629] arose under the Arbitration
      and Conciliation Act, 1996, and there was a specific provision
      under the new Act regarding the award of interest by the arbitrator.
      From the discussion made in Sayeed Ahmed [Sayeed Ahmed &
      Co. v. State of U.P., (2009) 12 SCC 26 : (2009) 4 SCC (Civ) 629]
G     it is apparent that this Court has emphasised that it would depend
      upon the nature of clause and claim, etc. and it is required to be
      found on consideration of stipulation whether interest is barred, if
      yes, on what amounts interest is barred under the contract.”

H
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                               643
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

      The Court then referred to the three-Judge Bench judgment in           A
Tehri Hydro Development Corporation Ltd. (supra) and finally
answered the reference as follows:-
      “32. In para 4 in Engineers-De-Space-Age [Port of Calcutta v.
      Engineers-De-Space-Age, (1996) 1 SCC 516] this Court has
      observed that bar under the contract will not be applicable to the     B
      arbitrator cannot be said to be observation of general application.
      In our opinion, it would depend upon the stipulation in the contract
      in each case whether the power of the arbitrator to grant pendente
      lite interest is expressly taken away. If answer is “yes” then the
      arbitrator would have no power to award pendente lite interest.
                                                                             C
      33. The decision in Madnani Construction Corpn. [Madnani
      Construction Corpn. (P) Ltd. v. Union of India, (2010) 1 SCC
      549 : (2010) 1 SCC (Civ) 168] has followed the decision in
      Engineers-De-Space-Age [Port of Calcutta v. Engineers-De-
      Space-Age, (1996) 1 SCC 516]. The same is also required to be
      diluted to the extent that express stipulation under contract may      D
      debar the arbitrator from awarding interest pendente lite. Grant
      of pendente lite interest may depend upon several factors such as
      phraseology used in the agreement, clauses conferring power
      relating to arbitration, nature of claim and dispute referred to
      arbitrator and on what items power to award interest has been          E
      taken away and for which period.
      34. Thus, our answer to the reference is that if the contract
      expressly bars the award of interest pendente lite, the same cannot
      be awarded by the arbitrator. We also make it clear that the bar to
      award interest on delayed payment by itself will not be readily        F
      inferred as express bar to award interest pendente lite by the
      Arbitral Tribunal, as ouster of power of the arbitrator has to be
      considered on various relevant aspects referred to in the decisions
      of this Court, it would be for the Division Bench to consider the
      case on merits.”
                                                                             G
       20. The aforesaid judgment was applied by another three-Judge
Bench soon thereafter in Ambica Construction v. Union of India
(“Second Ambica Construction Case”), (2017) 14 SCC 323. In this
case, the concerned clause, which is clause 2 of the Agreement, reads
as follows:-
                                                                             H
644            SUPREME COURT REPORTS                           [2018] 6 S.C.R.


A            “(2) Interest on amounts.— No interest will be payable upon
            the earnest money or the security deposit or amounts payable to
            the contractor under the contract, but government securities
            deposited in terms of sub-clause (1) of this clause will be repayable
            with interest accrued thereon.”
B                                                               [at paragraph 5]
             This Court found that the aforesaid clause was no bar, after
      referring to paragraph 34 of the First Ambica Construction Case
      (supra):
            “6. The only contention advanced at the hands of the learned
C           counsel for the appellant, was based on the judgment of this Court
            in Union of India v. Ambica Construction [Union of India v.
            Ambica Construction, (2016) 6 SCC 36 : (2016) 3 SCC (Civ)
            36], wherein, having examined the legal position declared by this
            Court by a Constitution Bench in Irrigation Deptt., State of Orissa
D           v. G.C. Roy [Irrigation Deptt., State of Orissa v. G.C. Roy,
            (1992) 1 SCC 508], it was held as under: (Ambica Construction
            case [Union of India v. Ambica Construction, (2016) 6 SCC
            36 : (2016) 3 SCC (Civ) 36] , SCC p. 59, para 34)
               “34. Thus, our answer to the reference is that if the contract
E              expressly bars the award of interest pendente lite, the same
               cannot be awarded by the arbitrator. We also make it clear
               that the bar to award interest on delayed payment by itself will
               not be readily inferred as express bar to award interest pendente
               lite by the Arbitral Tribunal, as ouster of power of the arbitrator
               has to be considered on various relevant aspects referred to in
F              the decisions of this Court, it would be for the Division Bench
               to consider the case on merits.”
               A perusal of the conclusions drawn by this Court in the above
               judgment, rendered by a three-Judge Division Bench, leaves
               no room for any doubt, that the bar to award interest on the
G              amounts payable under the contract, would not be sufficient to
               deny payment of pendente lite interest. In the above view of
               the matter, we are satisfied, that the clause relied upon by the
               learned counsel for the Union of India, to substantiate his
               contention, that pendente lite interest could not be awarded to
H
   RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                  645
  NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

          the appellant, was not a valid consideration, for the proposition     A
          being canvassed. We are therefore satisfied, that the arbitrator,
          while passing his award dated 28-6-1999, was fully justified in
          granting interest pendente lite to the appellant.”
        21. To complete the litany of case law, we must now refer to a
recent judgment delivered on 03.07.2018 by yet another Division Bench           B
of this Court in M/s Raveechee v. Union of India (Civil Appeal Nos.
5964-5965 of 2018). Clause 16.3, with which this judgment was
concerned, was identical in terms with the clause which barred interest
in the Second Ambica Construction Case (supra). This judgment
referred to and followed judgments in Engineers-De-Space-Age
(supra), Madnani Construction (supra) and the three-Judge Bench in              C
the Second Ambica Construction Case (supra) to hold that such a
clause would not be considered to be a bar to the payment of pendente
lite interest.
       22. A conspectus of the decisions that have been referred to above
would show that under the 1940 Act, an arbitrator has power to grant            D
pre-reference interest under the Interest Act, 1978 as well as pendente
lite and future interest. However, he is constricted only by the fact that
an agreement between the parties may contain an express bar to the
award of pre-reference and/or pendente lite interest. Since interest is
compensatory in nature and is parasitic upon a principal sum not having         E
been paid in time, this Court has frowned upon clauses that bar the
payment of interest. It has therefore evolved the test of strict construction
of such clauses, and has gone on to state that unless there is a clear and
express bar to the payment of interest that can be awarded by an arbitrator,
clauses which do not refer to claims before the Arbitrators or disputes
between parties and clearly bar payment of interest, cannot stand in the        F
way of an arbitrator awarding pre-reference or pendente lite interest.
Thus, when one contrasts a clause such as the clause in the Second
Ambica Construction Case (supra) with the clause in Tehri Hydro
Development Corporation Ltd. (supra), it becomes clear that unless
a contractor agrees that no claim for interest will either be entertained       G
or payable by the other party owing to dispute, difference, or
misunderstandings between the parties or in respect of delay on the part
of the engineer or in any other respect whatsoever, leading the Court to
find an express bar against payment of interest, a clause which merely

                                                                                H
646             SUPREME COURT REPORTS                           [2018] 6 S.C.R.


A     states that no interest will be payable upon amounts payable to the
      contractor under the contract would not be sufficient to bar an arbitrator
      from awarding pendente lite interest under the 1940 Act. As has been
      held in the First Ambica Construction Case (supra), the grant of
      pendente lite interest depends upon the phraseology used in the agreement,
      clauses conferring power relating to arbitration, the nature of claim and
B
      dispute referred to the Arbitrator, and on what items the power to award
      interest has been taken away and for which period. We hasten to add
      that the position as has been explained in some of the judgments above
      under Section 31(7) of the 1996 Act, is wholly different, inasmuch as
      Section 31(7) of the 1996 Act sanctifies agreements between the parties
C     and states that the moment the agreement says otherwise, no interest
      becomes payable right from the date of the cause of action until the
      award is delivered.
              23. In the present case, clause 16 of the General Conditions of
      Contract only speaks of any delay in payment not making ONGC liable
D     for interest. There is nothing in this clause which refers even obliquely
      to the Arbitrator’s power to grant interest. This Court finds that the
      aforesaid clause is narrower than the clause considered by the three-
      Judge Bench in the Second Ambica Construction Case (supra) which
      states that no interest will be payable on amounts payable to the contractor
      under the contract. Clause 16 in the present case confines itself only to
E     delay in payment and not to any other amounts payable to the contractor
      under the contract. Also, unlike the clause in Tehri Hydro Development
      Corporation Ltd. (supra), clause 16 does not contain language which
      is so wide in nature that it would interdict an arbitrator from granting
      pendente lite interest. It will be remembered that the clause in Tehri
F     Hydro Development Corporation Ltd. (supra) spoke of no claim for
      interest being entertained or payable in respect of any money which
      may be lying with the Government owing to disputes, difference or
      misunderstanding between the parties and not merely in respect of delay
      or omission; Further, the clause in Tehri Hydro Development
      Corporation Ltd. (supra) goes much further and makes it clear that no
G     claim for interest is payable “in any other respect whatsoever.” It is,
      thus, clear that clause 16 cannot possibly interdict the payment of
      pendente lite interest on the facts of the present case.
             24.We now come to Shri Viswanathan’s argument that, in any
      case, on the facts of the present case, clause 16 is not at all attracted
H
    RELIANCE CELLULOSE PRODUCTS LTD. v. OIL AND                                   647
   NATURAL GAS CORPORATION LTD. [R. F. NARIMAN, J.]

inasmuch as factually there was no delay in payment as a sum of                   A
Rs.14,999/- per MT had, in fact, been paid for both 1200 MT and 600
MT, but that the balance only became payable on and from the date of
the award. Shri Viswanathan is right, as it is nobody’s case that there
was delay in payment on the facts of this case. It is only after Reliance
went in a Writ Petition before the High Court that it became clear that a
                                                                                  B
higher price would be payable, which was left to the Arbitrator to
determine vide the High Court’s judgment referring the issue of price to
an arbitrator, which was accepted by ONGC. In this view of the matter,
it is clear that no delay on account of the higher price ever took place as
it became payable only on and from the date of the award, Rs.14,999/-
per MT having been paid on time earlier. This being the case, it is clear         C
that even if clause 16 were to have application, both pre-reference and
pendente lite interest are not barred.
       25.Coming to Shri Viswanathan’s appeal, we think that the only
reason given for reducing interest from 18% to 10% being that ONGC
is a Public Sector Undertaking, would not suffice to set aside what was           D
within the Arbitrator’s discretion. There is no finding that this discretion
has been exercised perversely, given the interest rates at the time of the
award. We thus uphold the grant of interest at the rate of 18% as pre-
reference and pendente lite interest. Considering the fact that ONGC
has deposited the difference in the principal sums payable, and pre-
reference, pendent lite and future interest, all at the rate of 10% being a       E
sum of Rs.1,09,34,323/- till 21.01.1999, and a sum of Rs.46,86,138/- on
30.04.2003, we make it clear that recovery of interest till the two
aforementioned dates will be at the rate of 18%. Thus, for pre-reference,
pendent lite and future interest, ONGC is to pay the differential amount
of interest of 8% till 21.01.1999 and 30.04.2003 within a period of eight         F
weeks from today. In the interest of justice, we clarify that on and from
21.01.1999, till payment, future interest is to be paid at 6% per annum on
the balance differential sum of interest, being the difference between
10% and 18%, and similarly, on the balance differential sum of interest
between 10% and 18% on and from 30.04.2003 till payment. Accordingly,
the appeal of ONGC is dismissed and the appeal of Reliance is allowed             G
in terms of this judgment.


Nidhi Jain                                                 Appeals disposed of.

                                                                                  H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.