REGENTA HOTELS PRIVATE LIMITEDversusM/S HOTEL GRAND CENTRE POINT AND OTHERS
- Citation
- 2026 INSC 32
- Decided
- 7 January 2026
- Bench
- DIPANKAR DATTA
Holding
Arbitral proceedings are deemed to have commenced on the date the respondent receives the notice invoking arbitration under Section 21, and therefore the appellant complied with the 90‑day requirement, making the High Court’s vacation of the injunction unsustainable.
Summary
Regenta Hotels Private Limited entered into a franchise agreement with M/s Hotel Grand Centre Point and, after disputes arose, obtained an ad‑interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996 on 17 February 2024. The appellant served a notice invoking arbitration on 11 April 2024, to which Respondent No.2 replied on 23 April 2024, thereby triggering the commencement of arbitral proceedings under Section 21. The High Court held that arbitral proceedings had not commenced within the 90‑day period prescribed by Section 9(2) because it treated the filing of a Section 11 petition on 28 June 2024 as the commencement date, and consequently vacated the injunction. The Supreme Court examined the statutory scheme, emphasizing that commencement is fixed by the receipt of the arbitration notice under Section 21 and that Rule 9(4) must be read in harmony with this definition. It held that the arbitration notice was received well within the statutory period, rendering the High Court’s finding untenable. The Court set aside the High Court judgment, restored the original interim injunction, and allowed the appeal, while disposing of the related contempt petition.
Issues considered
- The correct date for commencement of arbitral proceedings under Section 21 of the Arbitration and Conciliation Act, 1996 for the purpose of Section 9(2) and Rule 9(4) of the Arbitration (Proceedings Before the Courts) Rules, 2001.
- Whether the High Court erred in treating the filing of a Section 11 petition as the commencement of arbitration, thereby causing automatic vacation of the ad‑interim injunction.
- The applicability of Rule 9(4) of the 2001 Rules when the arbitration notice has been received within the 90‑day period.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 21, s. 43(2), s. 85(2)(a), s. 9(2)
- Arbitration (Proceedings Before the Courts) Rules, 2001s. Rule 9(4)
- Code of Civil Procedure, 1908
Headnote
Issue for Consideration Whether the High Court was correct in holding that the Appellant has initiated arbitral proceedings after the expiry of 90 days period as prescribed u/s.9(2) of the Arbitration and Conciliation Act, 1996, thereby resulting in automatic vacation in terms of r.9(4) of the Arbitration (Proceedings Before the Courts) Rules, 2001. Headnotes† Arbitration and Conciliation Act, 1996 – ss.21, 9(2) – Arbitration (Proceedings Before the Courts) Rules, 2001 – r.9 – “Commencement of arbitral proceedings”
Subjects
Judgment
[2026] 1 S.C.R. 206 : 2026 INSC 32
Regenta Hotels Private Limited
v.
M/s Hotel Grand Centre Point and Others
(Civil Appeal No. 90 of 2026)
07 January 2026
[Dipankar Datta and Augustine George Masih,* JJ.]
Issue for Consideration
Whether the High Court was correct in holding that the Appellant
has initiated arbitral proceedings after the expiry of 90 days period
as prescribed u/s.9(2) of the Arbitration and Conciliation Act, 1996,
thereby resulting in automatic vacation of ad-interim injunction in
terms of r.9(4) of the Arbitration (Proceedings Before the Courts)
Rules, 2001.
Headnotes†
Arbitration and Conciliation Act, 1996 – ss.21, 9(2) –
Arbitration (Proceedings Before the Courts) Rules, 2001 –
r.9 – “Commencement of arbitral proceedings” under the
Act – Parties entered into a Franchise Agreement in 2019 –
Disputes arose, Appellant filed application u/s.9 and certain
IAs before the Trial Court seeking injunctive reliefs against
the Respondent No.2 – Trial Court vide Order dtd.17.02.2024
granted ad-interim injunction against Respondent No.2 –
On 11.04.2024, appellant issued notice to the Respondents
invoking arbitration – Respondent No.2 sent a reply on
23.04.2024 refusing to concur with the nomination of the
Arbitrator – Appellant filed petition u/s.11(6) before the High
Court on 28.06.2024 seeking appointment of sole Arbitrator
and for referring the parties to arbitration – IAs filed by the
Appellant dismissed by Trial Court – Appeal filed by the
Appellant, dismissed by High Court – Whether the High Court
was correct in holding that the Appellant has initiated arbitral
proceedings after the expiry of 90 days period as prescribed
u/s.9(2), resulting in automatic vacation of ad-interim injunction
in terms of r.9(4), 2001 Rules:
Held: No – Arbitral proceedings, as commenced by the Appellant,
are well within the statutory time frame provided u/s.9(2) and the
* Author
[2026] 1 S.C.R. 207
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
rigor of r.9(4), 2001 Rules is not applicable to the Appellant –
The date on which the respondent receives a notice or request
invoking arbitration is the moment at which the arbitral proceedings
commence u/s.21 – A valid invocation requires the notice to
articulate the dispute sought to be referred but once such notice
is received, commencement is complete and effective for all legal
purposes including limitation, maintainability of the s.11 Petition
and the legal efficacy of any pre-arbitral measures – Trial Court
passed the Order dtd.17.02.2024 granting ad-interim injunction to
the Appellant – Period of ninety days as provided u/s.9(2) would
end on 17.05.2024 – Appellant served a notice invoking arbitration
on 11.04.2024 – Reply of Respondent No.2 dtd.23.04.2024 refusing
to join in the appointment of an arbitrator entails that notice had
indeed been received and understood as an invocation of the
arbitral process by the Respondent No.2 – Even if 23.04.2024, the
date on which the reply sent by the Respondent No.2, is taken to
calculate the period of ninety days, as stipulated u/s.9(2) and the
consequences thereof provided u/r.9(4), 2001 Rules, the arbitral
proceedings have commenced well within the time and way before
expiry of such periods – High Court treated the date of filing of
the s.11 petition i.e. 28.06.2024 as the date of commencement of
the arbitral proceedings resulting into the finding that ad-interim
stay stood vacated and proceedings commenced after the expiry
of ninety days period provided u/s.9(2) – This finding is not
sustainable as it is contrary to the objective and purpose of the Act –
Impugned Judgment of the High Court unsustainable, set aside –
Order of the Trial Court dtd.01.10.2024 vacating the ad-interim
injunction also set aside, restoring the earlier Order dtd.17.02.2024
[Paras 22, 28, 31 ]
Arbitration and Conciliation Act, 1996 – s.21:
Held: The commencement of arbitral proceedings is a statutory
event defined exclusively u/s.21, wherein the respondent’s receipt
of a request to refer the dispute to arbitration sets the arbitral
proceedings in motion and no judicial application i.e. whether
u/s.9 or s.11 petition, constitutes commencement – Therefore,
the statutory consequences tied to commencement, including the
mandate u/s.9(2), must be assessed solely with reference to the
date of receipt of request invoking arbitration u/s.21. [Para 23]
Arbitration and Conciliation Act, 1996 – s.21 – Purpose of,
explained. [Para 29]
208 [2026] 1 S.C.R.
Supreme Court Reports
Arbitration and Conciliation Act, 1996 – s.21 – Conscious
delinking of the commencement of arbitral proceedings from
any judicial proceedings based on the UNCITRAL framework:
Held: The very frame of s.21 provides that the Legislature has
consciously delinked the commencement of arbitral proceedings
from any judicial proceedings – This is a deliberate legislative choice
modelled on the UNCITRAL framework, meant to ensure that the
commencement of arbitral proceedings is clear and independent of
procedural contingencies – The objective of this statutory scheme
would be defeated if a court is permitted to substitute the date of
commencement u/s.21 with the date of filing a s.11 petition – Resort
to the proceedings u/s.11 would be necessitated only in case
there is refusal or no response to the notice u/s.21 – High Court
proceeded on the premise that since the petition u/s.11 was filed on
28.06.2024, beyond three months from the date of ad-interim Order
dtd.17.02.2024, the arbitral proceedings had not commenced within
time – This view rests on a misconception regarding the statutory
scheme – Article 21 of the Model Law of UNCITRAL. [Para 28]
Arbitration and Conciliation Act, 1996 – ss.9(2), 21 – Rationale
underlying s.9(2), discussed – If the commencement is to be
construed from the date of filing of the petition u/s.11, the
statutory scheme insisting on expedition in commencing
arbitration after the grant of interim protection u/s.9 would
be rendered incoherent – The applicant could serve notice
u/s.21 but still be held non-compliant until a s.11 petition is
filed, an interpretation which would be directly in contrast
with the object and purpose of the Act – Permitting such an
interpretation would mean that the parties would paradoxically
be required to file the s.11 petition to prevent the lapse of
interim measures granted u/s.9 even when the respondent
is cooperating, the contractual appointment procedure is
underway, or even when the s.21 notice has only recently been
served – This is antithetical to the flexibility and autonomy
provided in the Act. [Para 30]
Arbitration and Conciliation Act, 1996 – ss.21, 9(2) – In absence
of any other provision providing for the date of commencement
of the arbitral proceedings, s.21 is to apply to all the provisions
of the Act unless specifically provided otherwise – Plea of the
Respondent No.2 that the commencement u/s.21 is only for
the purpose of calculating limitation u/s.43(2):
[2026] 1 S.C.R. 209
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
Held: Not accepted – s.21 explicitly provides that arbitral proceedings
commence on the date on which a request for dispute to be referred
to arbitration is received by the respondent – In absence of any other
provision providing for the date of commencement of the arbitral
proceedings, s.21 is to be construed to apply to all the provisions
of the Act unless specifically provided as not applicable – The
only exception that is carved out in s.21 pertains to the arbitral
agreement itself, providing that unless otherwise agreed by the
parties, the date of commencement of arbitral proceedings must
be from the date when notice or request invoking arbitration is
received by the respondent – Therefore, as per the mandate of
s.9(2), the arbitration proceedings shall commence within a period
of ninety days from the date of such interim order or within such
further time as the court may determine, and such commencement
will be the date on which notice invoking arbitration is received by
the respondent in consonance of s.21. [Para 23]
Case Law Cited
Sundaram Finance Ltd. v. NEPC India Ltd. [1999] 1 SCR 89 :
(1999) 2 SCC 479; Arif Azim Company Limited v. Aptech Limited
[2024] 3 SCR 73 : (2024) 5 SCC 313; Milkfood Ltd. v. GMC Ice
Cream (P) Ltd. [2004] 3 SCR 854 : (2004) 7 SCC 288; Geo Miller
and Company Private Limited v. Chairman, Rajasthan Vidyut
Utpadan Nigam Limited [2019] 11 SCR 1108 : (2020) 14 SCC
643 – relied on.
State of Goa v. Praveen Enterprises [2011] 10 SCR 1026 : (2012)
12 SCC 581 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996; Code of Civil Procedure,
1908; Arbitration (Proceedings Before the Courts) Rules, 2001.
List of Keywords
Section 9 (2), Arbitration and Conciliation Act, 1996; Section 21,
Arbitration and Conciliation Act, 1996; Commencement of arbitral
proceedings” ; Rule 9(4), Arbitration (Proceedings Before the
Courts) Rules, 2001; Date on which the respondent receives a
notice or request invoking arbitration is the moment at which the
arbitral proceedings commence; Arbitral proceedings initiated
after the expiry of 90 days period prescribed under Section 9 (2),
210 [2026] 1 S.C.R.
Supreme Court Reports
Arbitration and Conciliation Act, 1996; Franchise Agreement; Arbitral
proceedings as commenced is well within the statutory time frame;
Notice under Section 21, Arbitration and Conciliation Act, 1996;
UNCITRAL Model Law’s formulation; Model Law of UNCITRAL;
Interim measures.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 90 of 2026
With
Contempt Petition (Civil) No. 189 of 2025
From the Judgment and Order dated 14.11.2024 of the High Court
of Karnataka at Bengaluru in MFA No. 7168 of 2024
Appearances for Parties
Advs. for the Appellant(s):
Pranjal Kishore.
Advs. for the Respondent(s):
M/S. Ahmadi Law Offices, Vivek Jain, Ms. Suchitra Kumbhat, Sadiq
Noor, Ms. Benila B M, Rohit H Nair, Ms. Baani Khanna, Robin
Singh, Kapil Balwani, Shrikant Thokchom, Atul Shankar Vinod.
Judgment / Order of the Supreme Court
Judgment
Augustine George Masih, J.
Leave granted.
2. The instant Civil Appeal assails the Judgment dated 14.11.2024
(“Impugned Judgment”) passed by the High Court of Karnataka at
Bengaluru (“High Court”), whereby it dismissed the Miscellaneous
First Appeal No. 7168 of 2024 (AA) filed by the Appellant herein
against the Order dated 01.10.2024 of the IXth Additional City Civil
and Sessions Judge, Bengaluru (“Trial Court”) in I.A. Nos. 5 to 7 in
AA No. 4 of 2024 which has been filed under Order XXXIX Rules 1
and 2 read with Section 151 of the Code of Civil Procedure, 1908
(“CPC 1908”) and Section 9 of the Arbitration and Conciliation Act,
1996 (“Act”) read with Rule 9 of the Arbitration (Proceedings Before
[2026] 1 S.C.R. 211
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
the Courts) Rules, 2001 (“2001 Rules”). The Trial Court vide Order
dated 01.10.2024 dismissed the application seeking temporary
injunction restraining Respondent No.2.
3. The Appellant herein is Regenta Hotels Private Limited, a company
registered under the Companies Act, 1956, engaged in carrying
business, inter alia, of operating hotels and providing hospitality
services in India and abroad. The Respondent No. 1 is M/s Hotel
Grand Centre Point, a partnership firm registered under the
Partnership Act, 1932. Respondents No.2 to 5 are brothers and
partners of Respondent No.1 vide partnership agreement entered on
01.04.2012, with each brother having 25% share in the partnership.
Respondent No.1 is owner of a hotel premises located near Hatrick
Restaurant, Raj Bagh, Srinagar, Jammu and Kashmir (“Hotel”).
4. The abovementioned parties i.e., the Appellant and Respondent
No.1 entered into a Franchise Agreement dated 23.03.2019. The
terms of the agreement were such that the Appellant would aid and
facilitate the business of Respondent No.1 by contributing through
its brand reputation, technical know-how, training and expertise in
running premium quality hotel businesses. In furtherance thereto,
the management and operations of Respondent No.1 were being
carried out as per the said agreement.
5. Interregnum, the Respondents No. 2 to 5 were involved in a family
dispute over rights on properties resulting into a settlement deed dated
20.04.2022 providing that Respondent No. 5 will be responsible for
operations of the Hotel for a period of two years and after the expiry
of said period, the Hotel operation shall be conducted by such party
who shall be nominated by the parties by voting. Profits of the Hotel
were decided to be shared by Respondent No. 2 in the ratio of 25%
and Respondent No. 5 in the ratio of 33.50% as also to include every
month consideration for his responsibility to operate the Hotel. The
remaining share was to be divided among Respondent No. 3 and 4
in the ratio of 21.50% and 20% respectively.
6. As transpires from the material on record, it is alleged that Respondent
No.2 started to interfere in the functioning of the Hotel by shouting
at staff and threatening to cancel bookings and taking away the
records if not paid exorbitant sums separately over and above the
agreed amount under the Franchise Agreement dated 23.03.2019.
As a consequence to the alleged conduct of Respondent No. 2,
212 [2026] 1 S.C.R.
Supreme Court Reports
the Appellant on 16.02.2024 approached the Trial Court by way of
an application under Section 9 of the Act being AA No.4 of 2024
seeking various injunctive reliefs to restrain the Respondent No.2
from interfering with the smooth functioning of the Hotel claiming that
Clause 5.1 of the Franchise Agreement stipulates that Respondent
No.1 will maintain a high moral and ethical standard and atmosphere
at the Hotel premises. The Appellant also filed three applications
being IA No.5 to 7 seeking interim reliefs to restrain Respondent
No.2 from obstructing or impeding in smooth functioning, operations
and management of the Hotel pending disposal of AA No.4 of 2024.
7. The Trial Court vide Order dated 17.02.2024 granted ad-interim
injunction against the Respondent No.2 as prayed for in IA No.5 to
7 till next date of the hearing and issued notice to the Respondents.
8. Thereafter, the Appellant on 11.04.2024 issued an Arbitration notice
to the Respondents invoking arbitration in terms of Clause 19.1 of the
Franchise Agreement for the adjudication of the disputes that have
arisen between the parties. The Respondent No. 2, in response to the
said notice dated 11.04.2024, sent a reply on 23.04.2024 refusing to
concur with the nomination of the Arbitrator claiming that he has not
signed any Franchise Agreement with the Appellant. The Appellant,
on 28.06.2024 filed CMP No.314 of 2024 under Section 11(6) of Act
before the High Court seeking appointment of sole Arbitrator and for
referring the parties to arbitration under the Franchise Agreement
dated 23.03.2019.
9. The Respondent No.2 has filed written statement before Trial Court in
AA No. 4 of 2024 denying allegations and contended that the suit itself
is not maintainable claiming that Respondent No.2 is not a signatory
to the Franchise Agreement. He contested that Respondent No.5
is not allowing Respondent No.2 to inspect the books of accounts,
ledgers or bills etc.
10. The Trial Court vide Order dated 01.10.2024 dismissed IA Nos.5
to 7 filed by the Appellant with the observation that the Appellant
failed to produce any document demonstrating that Respondent No.2
granted consent for the contested Franchise Agreement, thereby
failing to establish a prima facie case or the balance of convenience
in its favour. It was further stated that AA No.4 of 2024 was filed
on 16.02.2024, and more than six and a half months had elapsed
without the Appellant producing any document except for the notice
[2026] 1 S.C.R. 213
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
and reply for initiation of arbitral proceedings as mandated after filing
an application under Section 9 of the Act nor was any substantive
material produced to satisfy the requirements under Section 21 of the
said Act, as Respondent No.2 had not agreed to refer the dispute to
arbitration. The Trial Court also observed that all partners held equal
rights under the partnership deed and must obtain mutual written
consent for any substantive decision or agreement.
11. This Order dated 01.10.2024 was challenged by the Appellant in
Miscellaneous First Appeal No. 7168 of 2024 (AA) before the High
Court. The High Court vide Impugned Judgment dismissed the
appeal holding that Section 9(2) of the Act read with Rule 9(4) of
the 2001 Rules mandate that arbitral proceedings must commence
within 90 days or three months from the date of an interim order
or presentation of the Section 9 application, failing which any
interim relief granted stands vacated automatically. The High Court
reiterated that arbitral proceedings commence only when a request
for reference to arbitration is received by the respondent, and mere
issuance of notice does not constitute such commencement. The
petition under Section 11 of Act was filed on 28.06.2024 which was
beyond the permissible period, as arbitral proceedings ought to have
been initiated by 17.05.2024. The High Court, however, rejected
the contention of the Respondent No. 2 that he is not a signatory
to Franchise Agreement and noted that the Trial Court erred in
relying upon clauses of the partnership deed to conclude absence
of a prima facie case or existence of Franchise Agreement dated
23.03.2019 as the same evidenced consent among partners and
was acted upon as the Hotel kept running as per agreement and the
partners kept quiet from 2019 to 2023. The High Court nevertheless
upheld the dismissal of the Appellant’s application, holding that
failure to initiate arbitration within 90 days rendered the interim order
unsustainable, and issuance of notice alone could not be construed
as commencement of arbitration.
12. It would not be out of way to mention here that the above finding of
High Court with respect to the existence of the Franchise Agreement
dated 23.03.2019 has not been challenged by the Respondent
No.2. It is only the Appellant being aggrieved by the dismissal of the
Appeal by the High Court on the ground of arbitration proceedings
having not commenced within 90 days from the date of ad-interim
injunction, is before this Court.
214 [2026] 1 S.C.R.
Supreme Court Reports
13. This Court, on 17.12.2024, while issuing notice to the Respondents
had granted interim injunction in terms of Order dated 17.02.2024
of the Trial Court and continued it till the disposal of the Appeal.
14. The learned counsel for the Appellant submits that the arbitration
proceedings commence on the date of receipt of notice given under
Section 21 of the Act unless parties agree otherwise. The phrase
commencement is defined under Section 21 of the Act, and it is
also used in Section 9, 43(2) and 85(2) of the Act. In all these
contexts, this Court has held that it is the date of receipt of notice
under Section 21 that is determinative of the commencement of
arbitration proceedings. Reliance is placed on Sundaram Finance
Ltd. v. NEPC India Ltd.1, Arif Azim Company Limited v. Aptech
Limited2, Milkfood Ltd. v. GMC Ice Cream (P) Ltd.3, Geo Miller
and Company Private Limited v. Chairman, Rajasthan Vidyut
Utpadan Nigam Limited4. He submits that the dispute between
the brothers, who are partners of the Respondent No.1, have no
bearing on the Franchise Agreement and in any case, it has been
decided in favour of the Appellant by the High Court by the Impugned
Judgment which has not been challenged by the Respondents either
by filing an appeal or by cross-objections. The learned counsel further
submits that the Respondent No.2 and other partners suppressed an
agreement dated 09.10.2025 entered into between them by which
they have decided to close the hotel in violation of this Court’s interim
order dated 17.12.2024.
15. The learned counsel for the Respondent No.2 submits that the
Appellant’s right in the management of the Hotel is limited to getting
royalty payment of 5% each month along with taxes, while the
Respondent No.1 retains and exercises direct management and
control over the day-to-day operations of the Hotel, which was the duty
Respondent No.5 has undertaken and despite completion of two years
has not stepped down. The Respondent No.5 has not taken written
consent of all the partners while signing the Franchise Agreement
on behalf of the Respondent No.1. He submits that Section 21 of
1 (1999) 2 SCC 479
2 (2024) 5 SCC 313
3 (2004) 7 SCC 288
4 (2020) 14 SCC 643
[2026] 1 S.C.R. 215
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
the Act is a deeming provision whereby the date of commencement
of arbitral proceedings relates back to the date on which the notice
invoking arbitration was received. Section 43(2) of the Act provides
that an arbitration is deemed to have commenced from the date
referred in Section 21 of the Act. Reliance is placed on State of
Goa v. Praveen Enterprises5, contending that the primary object
of Section 21 of the Act is to determine the date of commencement
of the arbitral proceedings to decide if claims were ex-facie time
barred. The learned counsel further submits that “commencement”
in Section 21 is not for the purpose of Section 9(2) of the Act but
for Section 43, which explicitly mentions Section 21.
16. Having heard the learned counsels for the parties and upon perusal
of material on record, it emerges that the finding as returned by the
High Court with regard to the existence of Franchise Agreement
dated 23.03.2019 is not challenged by the Respondent No.2 by
way of cross-objection in this appeal nor is there any material on
record to show that any other petition is filed in this regard. The
said finding has thus attained finality to the effect that the consent
of Respondent No.2 was there to the Franchise Agreement.
16(A). The only issue which concerns the present Appeal is whether
the High Court was correct in holding that the Appellant has
initiated arbitral proceedings after the expiry of 90 days period
as prescribed under Section 9(2) of the Act, thereby resulting in
automatic vacation of ad-interim injunction in terms of Rule 9(4)
of the 2001 Rules.
17. Before delving into the jurisprudential foundation governing the
commencement of the arbitral proceedings under the Act, let us
reproduce the relevant provisions of the Act for convenience.
18. Sections 9, 21 and 43(2) of Act read as follows:
“9. Interim measures, etc., by Court.––(1) A party may,
before or during arbitral proceedings or at any time after
the making of the arbitral award but before it is enforced
in accordance with section 36, apply to a court—
5 (2012) 12 SCC 581
216 [2026] 1 S.C.R.
Supreme Court Reports
(i) for the appointment of a guardian for a minor or a
person of unsound mind for the purposes of arbitral
proceedings; or
(ii) for an interim measure of protection in respect of any
of the following matters, namely:—
(a) the preservation, interim custody or sale of
any goods which are the subject-matter of the
arbitration agreement;
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any
property or thing which is the subject-matter of
the dispute in arbitration, or as to which any
question may arise therein and authorising for
any of the aforesaid purposes any person to
enter upon any land or building in the possession
of any party, or authorising any samples to
be taken or any observation to be made, or
experiment to be tried, which may be necessary
or expedient for the purpose of obtaining full
information or evidence;
(d) interim injunction or the appointment of a
receiver;
(e) such other interim measure of protection as may
appear to the Court to be just and convenient,
and the Court shall have the same power for making
orders as it has for the purpose of, and in relation to, any
proceedings before it.
(2) Where, before the commencement of the arbitral
proceedings, a Court passes an order for any interim
measure of protection under sub-section (1), the arbitral
proceedings shall be commenced within a period of ninety
days from the date of such order or within such further
time as the Court may determine.
(3) Once the arbitral tribunal has been constituted, the Court
shall not entertain an application under sub-section (1),
unless the Court finds that circumstances exist which
[2026] 1 S.C.R. 217
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
may not render the remedy provided under section 17
efficacious.
21. Commencement of arbitral proceedings.––Unless
otherwise agreed by the parties, the arbitral proceedings in
respect of a particular dispute commence on the date on
which a request for that dispute to be referred to arbitration
is received by the respondent.
43. Limitations.––(1) . . .
(2) For the purposes of this section and the Limitation Act,
1963 (36 of 1963), an arbitration shall be deemed to have
commenced on the date referred in section 21.”
19. The jurisprudential foundation governing the commencement of
arbitral proceedings under the Act stands on a principled and
consistent line of authority emanating from this Court. In Sundaram
Finance Ltd. (supra), this Court, while dealing with the issue as to
whether a court has jurisdiction to pass interim orders under Section
9 of the Act even before the arbitral proceedings commence, has
observed that reading of Section 21 of the Act clearly shows that the
arbitral proceedings commence on the date on which a request for
a dispute to be referred to arbitration is received by the respondent.
20. The contours of this principle were later given sharper precision in
Milkfood Ltd. (supra), wherein a three-Judge Bench of this Court
held that the Legislature has deliberately adopted the UNCITRAL
Model Law’s formulation, whereby the arbitral proceedings commence
upon respondent’s receipt of a request or notice that the dispute be
referred to arbitration. The provisions under Section 21 of the Act
are consistent with Article 21 of the Model Law of UNCITRAL. The
Court further observed that the issuance of notice under Section
21 is required to be interpreted broadly and not for the purpose of
limitation only but for other purposes also.
21. In Geo Miller (supra), this Court reaffirmed the principles of Milkfood
Ltd. (supra), holding that for the purpose of determining which law
applies or for computing limitation, the date of commencement is
invariably the date on which the notice invoking arbitration is received
by the respondent. The Court clarified that the procedural route
adopted thereafter i.e., whether the parties agree on an arbitrator
or whether a Section 11 petition becomes necessary, is irrelevant
218 [2026] 1 S.C.R.
Supreme Court Reports
to the date of commencement, which remains tethered exclusively
to Section 21 of the Act.
22. In Arif Azim (supra), a three-Judge Bench of this Court has
consolidated and restated what is being held in Milkfood Ltd.
(supra) and Geo Miller (supra). The Court re-emphasized that
the date on which the respondent receives a notice or request
invoking arbitration is the moment at which the arbitral proceedings
commence under Section 21 of the Act. It further clarified that a
valid invocation requires the notice to articulate the dispute sought
to be referred but once such notice is received, commencement is
complete and effective for all legal purposes including limitation,
maintainability of the Section 11 Petition and the legal efficacy of
any pre-arbitral measures. The relevant portion in paras 88 to 91,
are reproduced herein:
“88. Section 21 of the 1996 Act provides that the arbitral
proceedings in relation to a dispute commence when a
notice invoking arbitration is sent by the claimant to the
other party:
‘21. Commencement of arbitral proceedings.—
Unless otherwise agreed by the parties, the arbitral
proceedings in respect of a particular dispute
commence on the date on which a request for that
dispute to be referred to arbitration is received by
the respondent.’
89. In Milkfood Ltd. v. GMC Ice Cream (P) Ltd. [(2004) 7
SCC 288] , it was observed thus : (SCC pp. 301-302 &
307, paras 26-27, 29 & 49)
‘26. The commencement of an arbitration proceeding
for the purpose of applicability of the provisions of
the Indian Limitation Act is of great significance.
Even Section 43(1) of the 1996 Act provides that
the Limitation Act, 1963 shall apply to the arbitration
as it applies to proceedings in court. Sub-section
(2) thereof provides that for the purpose of the said
section and the Limitation Act, 1963, an arbitration
shall be deemed to have commenced on the date
referred to in Section 21.
[2026] 1 S.C.R. 219
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
27. Article 21 of the Model Law which was modelled
on Article 3 of the Uncitral Arbitration Rules had been
adopted for the purpose of drafting Section 21 of the
1996 Act. Section 3 of the 1996 Act provides for as
to when a request can be said to have been received
by the respondent. Thus, whether for the purpose
of applying the provisions of Chapter II of the 1940
Act or for the purpose of Section 21 of the 1996 Act,
what is necessary is to issue/serve a request/notice
to the respondent indicating that the claimant seeks
arbitration of the dispute.
***
29. For the purpose of the Limitation Act an arbitration
is deemed to have commenced when one party to
the arbitration agreement serves on the other a
notice requiring the appointment of an arbitrator.
This indeed is relatable to the other purposes also,
as, for example, see Section 29(2) of the (English)
Arbitration Act, 1950.
***
49. Section 21 of the 1996 Act, as noticed hereinbefore,
provides as to when the arbitral proceedings would
be deemed to have commenced. Section 21 although
may be construed to be laying down a provision for
the purpose of the said Act but the same must be
given its full effect having regard to the fact that the
repeal and saving clause is also contained therein.
Section 21 of the Act must, therefore, be construed
having regard to Section 85(2)(a) of the 1996 Act.
Once it is so construed, indisputably the service of
notice and/or issuance of request for appointment of
an arbitrator in terms of the arbitration agreement must
be held to be determinative of the commencement
of the arbitral proceeding.’
90. Similarly, in BSNL v. Nortel Networks (India) (P) Ltd.
[(2021) 5 SCC 738], it was held by this Court thus: (SCC
p. 766, para 51)
220 [2026] 1 S.C.R.
Supreme Court Reports
‘51. The period of limitation for issuing notice of
arbitration would not get extended by mere exchange
of letters, [S.S. Rathore v. State of M.P., (1989) 4 SCC
582 : 1990 SCC (L&S) 50; Union of India v. Har Dayal,
(2010) 1 SCC 394; CLP (India) (P) Ltd. v. Gujarat
Urja Vikas Nigam Ltd., (2020) 5 SCC 185] or mere
settlement discussions, where a final bill is rejected
by making deductions or otherwise. Sections 5 to 20
of the Limitation Act do not exclude the time taken on
account of settlement discussions. Section 9 of the
Limitation Act makes it clear that: ‘where once the
time has begun to run, no subsequent disability or
inability to institute a suit or make an application stops
it’. There must be a clear notice invoking arbitration
setting out the “particular dispute” [ Section 21 of
the Arbitration and Conciliation Act, 1996.] (including
claims/amounts) which must be received by the other
party within a period of 3 years from the rejection of
a final bill, failing which, the time bar would prevail.’
91. In the present case, the notice invoking arbitration was
received by the respondent on 29-11-2022, which is within
the three-year period from the date on which the cause
of action for the claim had arisen. Thus, it cannot be said
that the claims sought to be raised by the petitioner are
ex facie time-barred or dead claims on the date of the
commencement of arbitration.”
23. Upon perusal of the binding decisions of this Court and provisions
of the Act, there is no doubt left with regard to the correct
conceptualization of “commencement of arbitral proceedings” under
the Act. The settled position as emerged is that the commencement
of arbitral proceedings is a statutory event defined exclusively under
Section 21 of the Act, wherein the respondent’s receipt of a request
to refer the dispute to arbitration sets the arbitral proceedings in
motion and no judicial application i.e. whether under Section 9 or
Section 11 petition, constitutes commencement. Therefore, the
statutory consequences tied to commencement, including the
mandate under Section 9(2) of the Act, must be assessed solely
with reference to the date of receipt of request invoking arbitration
under Section 21 of the Act.
[2026] 1 S.C.R. 221
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
24. The contention of the Respondent No.2 that the commencement
under Section 21 of the Act is only for the purpose of calculating
limitation under Section 43(2) of the Act does not find force with us.
Section 21 explicitly provides that arbitral proceedings commence on
the date on which a request for dispute to be referred to arbitration
is received by the respondent. In absence of any other provision
providing for the date of commencement of the arbitral proceedings,
Section 21 is to be construed to apply to all the provisions of the Act
unless specifically provided as not applicable. The only exception
that is carved out in Section 21 pertains to the arbitral agreement
itself, providing that unless otherwise agreed by the parties, the
date of commencement of arbitral proceedings must be from the
date when notice or request invoking arbitration is received by the
respondent. Therefore, as per the mandate of Section 9(2) of the
Act, the arbitration proceedings shall commence within a period
of ninety days from the date of such interim order or within such
further time as the court may determine, and such commencement
will be the date on which notice invoking arbitration is received by
the respondent in consonance of Section 21 of the Act.
25. At this stage, it requires to be mentioned that the consequences
flowing from the non-compliance of mandate under Section 9(2)
of the Act are not provided for in the said Act. To fill in this gap
reference is required to be made at this juncture to Rule 9 of 2001
Rules framed by the High Court as per the powers conferred on it
under Section 82 of the Act, which reads as follows:
“Rule 9. Application for interim measure, etc.––
(1) When an application is made for an interim measure,
under Section 9 of the Act, the Court shall in all cases,
except where it appears that the object of granting the
interim measure would be defeated by the delay, before
passing the interim order, direct notice of the application
to be given to the opposite party:
Provided that, where it is proposed to make an order
by way of interim measure without giving notice of the
application to the opposite party, the Court shall record
the reasons for its opinion that the object of granting the
interim measure would be defeated by delay, and require
applicant.––
222 [2026] 1 S.C.R.
Supreme Court Reports
(a) to deliver to the opposite party, or to sent to him by
registered post, immediately after the order granting
the interim measure has been made, a copy of the
Application for interim order together with:
(i) a copy of affidavit filed in support of the
application;
(ii) copies of documents on which the applicant
relies;
(b) to file, on the day on which such interim order is
granted or on the day immediately following that day,
an affidavit stating that the copies aforesaid have
been so delivered or sent.
(2) Where an interim order has been granted without
giving notice to the opposite party, the Court shall make
endeavours to finally dispose of the Application within
thirty days from the date on which the interim order was
granted and where it is unable so to do, it shall record its
reasons for such inability.
(3) In an application for interim measure filed under Section
9, before the commencement of the arbitral proceedings,
the applicant shall specifically refer to the steps, if any,
already taken to seek arbitration and that he is willing and
prepared to take necessary steps with utmost expedition
to seek reference to arbitration in terms of the Arbitration
Agreement/Clause.
(4) In the case of an application for interim measure
made before initiating arbitral proceedings, if the arbitral
proceedings are not initiated within three months from the
date of the presentation of the Application under Section 9,
any interim order granted shall stand vacated without any
specific order being passed by the Court to that effect.”
26. Upon the reading of Section 9 of the Act, it is evident that the said
section does not provide for the consequences of non-compliance
with its mandate of commencing arbitral proceedings within ninety
days, however, the said vacuum stands statutorily filled through
Rule 9(4) of the 2001 Rules. According to this Rule where an interim
order has been granted on an application made under Section 9 of
[2026] 1 S.C.R. 223
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
the Act but no arbitral proceedings are initiated within three months
from the date of presentation of the application, the interim order
shall stand vacated automatically.
27. It requires to be noted and mentioned here that Rule 9(4) employs
the expression “initiated” whereas Section 9(2) uses the expression
“commenced” in the context of arbitral proceedings. As per Concise
Oxford English Dictionary (Eleventh Edition, Revised), the term
“initiation” connotes the act of causing something to begin or taking
the first step towards beginning a process, whereas “commencement”
denotes the actual beginning of the process itself, which is a step
further than mere initiation. Thus, linguistically, initiation precedes
commencement and as per Rule 9(4) the initiation shall be within three
months from the date of presentation of such application, which would
be before the commencement as per Section 21 of Act and would
ideally be the date on which the notice invoking arbitration is sent by a
party. However, the expression “initiated” occurring in Rule 9(4) cannot
be interpreted in isolation or in a manner divorced from the statutory
context in which it appears. Rule 9 has been framed in aid of, and
to give procedural effect to, Section 9 of the Act, and therefore the
terminology employed therein must be construed harmoniously with
the parent provision. If “initiation” in Rule 9(4) were to be understood
as something short of “commencement” as contemplated under
Section 21 of the Act, the mandate under Section 9(2) prescribing
a strict timeline for commencement of arbitral proceedings would be
rendered otiose and susceptible to circumvention. Consequently, for
the purposes of Rule 9(4), the expression “initiated” has necessarily
to be read as “commenced” within the meaning of Section 21 of the
Act. It follows that upon failure to commence arbitral proceedings
within three months, the period stipulated under Rule 9(4) of 2001
Rules attracts the consequence as provided therein, namely, the
interim order shall stand vacated automatically.
28. In the case at hand, the High Court proceeded on the premise that
since the petition under Section 11 was filed on 28.06.2024, beyond
three months from the date of ad-interim Order dated 17.02.2024,
the arbitral proceedings had not commenced within time. This view
of the High Court rests on a misconception regarding the statutory
scheme. The very frame of Section 21 provides that the Legislature
has consciously delinked the commencement of arbitral proceedings
from any judicial proceedings. This Court, in Milkfood Ltd. (supra)
224 [2026] 1 S.C.R.
Supreme Court Reports
described this as a deliberate legislative choice modelled on the
UNCITRAL framework, meant to ensure that the commencement
of arbitral proceedings is clear and independent of procedural
contingencies. The objective of this statutory scheme would be
defeated if a court is permitted to substitute the date of commencement
under Section 21 with the date of filing a Section 11 petition. Resort
to the proceedings under Section 11 would be necessitated only in
case there is refusal or no response to the notice under Section 21
of the Act.
29. The High Court in the Impugned Judgment conflates the trigger
for arbitral proceedings with remedial mechanism made available
when the respondent obstructs or declines to participate. The
purpose of Section 21 is to specify the date of commencement of
arbitral proceedings in order to determine whether a claim is barred
by limitation and whether a party has complied with the requisite
statutory or contractual time limit for initiation of arbitration. If the
date of filing of the Section 11 petition is to be treated as the date
of commencement of arbitral proceedings, as has been observed by
the High Court in the Impugned Judgment, that would result into the
displacement of commencement of arbitral proceedings as provided
under Section 21 and would be contrary to the text and purpose of
the Act. Such a position is impermissible as has been consistently
held in the dicta of this Court from the decision in Sundaram Finance
Ltd. (supra) to that in Arif Azim (supra).
30. The rationale underlying Section 9(2) of the Act is that the arbitral
proceedings shall be commenced within ninety days from the grant
of interim protection. This prevents a party from abusing Section 9 to
obtain interim protection without submitting to the arbitral forum and
it also ensures that interim measures remain tied to the arbitration
they are meant to support. If this safeguard is interpreted in a manner
that contradicts the statutory definition of the commencement, to
do so would allow courts to rewrite Section 21 sub silentio. If the
commencement is to be construed from the date of filing of the
petition under Section 11 of the Act, the statutory scheme insisting
on expedition in commencing arbitration after the grant of interim
protection under Section 9 would be rendered incoherent. The
applicant could serve notice under Section 21 but still be held non-
compliant until a Section 11 petition is filed, an interpretation which
would be directly in contrast with the object and purpose of the Act.
[2026] 1 S.C.R. 225
Regenta Hotels Private Limited v.
M/s Hotel Grand Centre Point and Others
Permitting such an interpretation would mean that the parties would
paradoxically be required to file the Section 11 petition to prevent the
lapse of interim measures granted under Section 9 of the Act even
when the respondent is cooperating, the contractual appointment
procedure is underway, or even when the Section 21 notice has
only recently been served. This is antithetical to the flexibility and
autonomy provided in the Act.
31. The legal position as settled when applied to the present factual
matrix yields a clear conclusion. The Trial Court passed the Order
dated 17.02.2024 granting ad-interim injunction to the Appellant. The
period of ninety days as provided under Section 9(2) of the Act would
end on 17.05.2024. The Appellant served a notice invoking arbitration
on 11.04.2024. The reply of Respondent No. 2 dated 23.04.2024
refusing to join in the appointment of an arbitrator entails that notice
had indeed been received and understood as an invocation of the
arbitral process by the Respondent No.2. Under Section 21 of the
Act, the date of receipt of the notice is the date of commencement
of arbitral proceedings. Even if 23.04.2024, the date on which the
reply sent by the Respondent No.2, is taken to calculate the period
of ninety days, as stipulated under Section 9(2) of the Act and the
consequences thereof provided under Rule 9(4) of the 2001 Rules,
the arbitral proceedings have commenced well within the time and
way before expiry of such periods. The High Court, however, in
the Impugned Judgment treated the date of filing of the Section 11
petition i.e. 28.06.2024 as the date of commencement of the arbitral
proceedings resulting into the finding that ad-interim stay stood
vacated and proceedings commenced after the expiry of ninety
days period provided under Section 9(2) of the Act. This finding of
the High Court cannot sustain as it is contrary to the objective and
purpose of the Act. The arbitral proceedings, as commenced by
the Appellant, is well within the statutory time frame provided under
Section 9(2) of the Act and the rigor of Rule 9(4) of the 2001 Rules
cannot be attracted to the Appellant.
32. Therefore, in the light of the above discussion and perusal of material
on record, the Impugned Judgment of the High Court is set aside
for being unsustainable in law. As a consequence thereof, the
Order dated 01.10.2024 of the Trial Court vacating the ad-interim
injunction also stands set aside, restoring the earlier Order dated
17.02.2024.
226 [2026] 1 S.C.R.
Supreme Court Reports
33. Before parting, it is essential that we request the High Court to
expeditiously decide the Section 11 petition filed by the Appellant for
appointment of the arbitrator on its own merits and in accordance
with law, if already not decided. Nothing stated in this judgment will
influence or prejudice the arbitral process in any manner.
34. The appeal is allowed in the above terms.
35. As the appeal stands allowed, we would not like to proceed as of
now with the Contempt Petition (C) No.189 of 2025 as filed by the
appellant and the same is disposed of at this stage.
36. There shall be no order as to costs.
37. Pending application(s), if any, stand disposed of.
Result of the case: Appeal allowed, Contempt Petition disposed of.
†
Headnotes prepared by: Divya Pandey
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.