Created byFuzzy Cloud

Supreme Court of India

RAMCHANDRA MURARILAL BHATTAD AND ORS.versusSTATE OF MAHARASHTRA AND ORS.

Citation
2006 INSC 951
Decided
5 December 2006
Disposal
Dismissed

Holding

The Authority, not the Executive Committee, may lawfully alter its policy and cancel tenders, and no reason need be assigned for rejection in a contractual tender context.

Summary

The Mumbai Metropolitan Region Development Authority (MMRDA) invited bids for a Convention and Exhibition Centre and the appellant submitted the highest bid, but the Authority later cancelled all bids and re‑tendered, awarding the contract to another bidder. The appellant challenged the cancellation, arguing that the Authority lacked power to alter its policy, that the Executive Committee was the sole body to reject bids, and that reasons for rejection were required. The Supreme Court held that the Executive Committee’s jurisdiction is limited to accepting or rejecting a tender, while the Authority, as a statutory body, may change policy and cancel tenders to re‑examine the project. The Court found that no statutory prohibition existed against the Authority’s policy shift and that reasons need not be given in a purely contractual context. Consequently, the Court concluded that the Authority acted within its legal powers and dismissed the appeals. The decision affirmed that policy decisions of statutory authorities can be altered over time unless they contravene a specific statutory provision or public policy.

Issues considered

  • The extent of the MMRDA Authority’s power to cancel and re‑tender bids under the Mumbai Metropolitan Region Development Authority Act, 1974.
  • Whether the Executive Committee is the sole adjudicator for acceptance or rejection of tenders.
  • The requirement, if any, to assign reasons for rejecting a bid in a contractual tender process.
  • Whether a change in policy regarding disposal of property vitiates the Authority’s earlier decisions.

Legislation cited

Subjects

tender cancellationpolicy changestatutory authorityjudicial reviewexecutive committeecontractual obligationsMMRDApublic procurement

Judgment

A              RAMCHANDRA MURA RI LAL BHATIAD AND ORS.
                                          v.
                      STATE OF MAHARASHTRA AND ORS.

                                 DECEMBER 5, 2006

B                  [S.B. SINHA AND DAL VEER BHANDARI, JJ.]


          Mumbai Metropolitan Region Development Authority Act, I974

          Bids invited by Authority for development of Convention and Exhibition
                                                                                      -
C Centre-A II bids in response thereto, including the highest, rejected by
    Authority, project rendered and granted to highest bidder therein-Correctness
    of -Held-Only because there was change in computation of total price
    under new tender, it could not be said to be invalid in law-It was a case
    where the highest offer was not rejected, but a new policy decision was taken-
D   The Authority in law could alter its policy in regard to disposal of its
    properties-It exercised its power in canceling tenders to have a re-look at
    entire project-Entire policy decision could not be said to be vitiated in law
    merely because Authority at one point of time took a stand in Court that it had
    thought of setting up Convention Centre of their own without any private
    participation-Reasons for rejecting bids were not required to be given as it
E   was a ca,.se of decision involving policy change.

           Section 7-Executive Committee-Power of approval or rejection of
    tenders for projects and schemes of Authority-Scope of-Held-Jurisdiction
    of Committee was lif1Jited-It could not (i) cancel entire tender (ii) change
F   entire scheme or policy (iii) make alterations in methodology of tender (iv) go
     into working of project (v) go into question as to whether project would be
    financially v_iable if method of calculation was changed (vi) exercise any
    special power.

          Power of Authority-Scope of-Held-Authority was a statutory
G   authority, consisting of politicians and other responsible officers-While
    exercising its power under the Act, it must necessarily take policy decisions-
    Though its power was larger and different from that of Executive Committee,
    it could not usurp functions of latter.

          Statutory authority-Power to deal with contractual matter-Scope of-
H                                        IM
                   RAMCHANDRA MURARILAL BHATIAD v. STATE OF MAHARASHTRA               } 07

     ~   Held-It is distinct and different from its power in determining rights and           A
         liabilities of parties-Whereas reasons are required to be assigned in a case
         where civil or evil consequences may ensue, same may not be necessary where
         it is contractual in nature, save and except in some cases.

               Judicial review-Policy decision-Held-It may be changed from time
         to time-Only because a change is effected, decision cannot be termed as              B
         illegal or otherwise vitiated in law-It is more so where ex facie, policy
         decision was not contrary to any statute or against a public policy, or Court
         was not called upon to exercise its equity jurisdiction.

                MMRDA is an authority created under the Mumbai Metropolitan                   C.
         Region Development Authority Act, 1974. Section 7 therefore provided
         for constitution and powers of Executive Committee, inter alia, for approval
..       or rejection of tenders for projects and schemes of the Authority. The
         Authority invited bids for development of a Convention and Exhibition Centre.
         Appellant was one of the several entitles who put in their bids in response.
         Their bid wasfound to be the highest. The Authority, however rejected all the        D
         bids, r~tendered and granted contract to the highest bidder therein. Appellant
         filed a writ petition before High Court questioning the right and power of the
         Authority to reject at any stage all or any of the bids without assigning any
         reason. In response, the Authority conteuded that (i) its decision was in
         pursuance of power conferred by the terms of the contract (ii) in view of            E
         sections 12(1)(b)(d) and (h) and the power to issue directions under S.14 of
         the Act, it could, at any stage, review any decision including the decision of
         the executive committee and direct either rejection of all bids or issuance of
         fresh bids (c) it had decided to set up the convention Centre on its own without
         any private participation. The High Court dismissed the Writ Petition holding
         that (i) under various provisions of the Act, the authority was entitled to          F
         acquire, hold and dispose of the property, so it could not be said that its power
         in such matters did not include the power to reject a bid invited for projects
         and schemes framed by it (ii) the Executive Committee was not sole judge in
         matters of approval or rejection of tenders for projects and schemes of the
         authorities. Aggrieved by this, the appellant filed the present appeal.              G
              Appellant contended that (i) the purported major shift in the policy by
         the Authority was impermissible in law (ii) the Executive Committee alone
         was the sole judge in relation to rejection of bids (iii) in rejecting their bid,
         as sufficient and valid reasons were not assigned, the impugned order was
         vitiated in law (iv) in accepting the bid of the highest bidder in r~tender, their   H
    i08                       SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A offer to pay@ 21120/o per year from the annual turnover from the 21st year
    was not considered.

          Successful bidder in re-tender, subsequently added as respondent,
    contended that (i) the Executive Committee could not have taken a decision
    in regard to the change of policy (ii) in re-tender, appellant did not take
B   part (iii) procedural lapses, if any, cannot be a ground for judicial review.

          The Authority contended that (i) judicial review is not maintainable
    as appellant has not disclosed infringement of any constitutional or
    statutory right (ii) it was entitled to reject the tender on appreciation of
C   professional competence and capacity of appellant to run the centre •
    profitably, as well as the fact that prices offered by them were
    competitively low, and (iii) the policy being in relation to a mega project
    and its judgment being objective, no interference by Court was called for.

          Dismissing the appeals, the Court
D
          HELD I.I. The Executive Committee is a statutory functionary. The
    powers and functions of the authority and the respective committees are
    governed by the provisions of the statute, but, then the jurisdiction of the
    Executive Committee is limited. It is confined to rejection or acceptance of
    the tender. The Authority exercise a larger power. For the said purpose one
E   would assume that the Authority had no incidental or a1_1cillary power, but
    there cannot be any doubt or dispute that the Executive Committee could not
    cancel the entire tender. It could not have caused any change in the entire
    scheme or policy. It could not make alterations in the methodology of tender.
    It could not have gone into the working of the project It also could not have
F   gone into the question as to whether the project would be financially viable if
    the method of calculation is changed. 1123-F, G, HJ

          Marathwada University v. Seshrao Ba/want Rao Chavan, 11989] 3 SCC
    132, referred to.

G          1.2. Further assumption has to be made that the power of the
    Executive Committee and the Authority under the Act are diffrent and
    the latter for all intent and purport could not usurp the functions of the former.
    But in this case, it has not been so done. 1124-BJ

          t.3. Executive Committee does not exercise any special power.1125-GI
H
                   RAMCHANDRA MURAR!LAL BHATTAD v. ST ATE OF MAHARASHTRA             109

              Bhavnagar University v. Palitana Sugar Mill Pvt. ltd. & Ors., (2003) 2         A
        SCC 111, State of Uttar Pradesh v. Singhara Singh & Ors., 11964) 4 SCR
        485, held inapplicable.

               Taylor v. Taylor, (1875) 1 Ch. D. 426, 431, referred to.

              1.4. The action on the part of the Authority was neither illigal nor without   B
        jurisdiction. (124-CI

             JK. Cotton Spinning & Weaving Mills Co., Ltd. v. State of Uttar Pradesh
        & Ors., (1961) 3 SCR 185, distinguished.

              1.5. The Authority has not exercised any power forbidden by law.               C
        The Authority has also not exercised its power in the manner which is not
        in accordance with law. (126-D)

              2.1. The Authority is a statutory authority. It consists of not only
        politicians but also various other responsible officers. It, while exercising
        its power under the Act, must necessarily take policy decisions. (127-G)             D
              2.2. Where as under the 2002 tender the bidder had to quote the rate
        of premium in terms of rupees per square meter of FSI and the total
        premium separately for C&EC and the Real Estate component subject to
        the condition that the rate quoted for the Real Estate component should              E
        be greater than that quoted for the C&EC, upon having come to know
        that the value of the land would be much more, the Authority in the 2005
        tender decided that the bidders should be required to quote a fixed rate
        of 20,000 per sq.m. of built-up area for total built-up area 65,000 sq.m.
        for Convention & Exhibition Centre. Economic viability of the entire
        project component, taking into consideration two different compoenents for           F
        C&EC and the Commearcial Complex, could have been taken differently. The
        premium amount was to be quoted higher than Rs. 350 crores for the
        Commercial Complex. (127-G, H; 128-A, B)

              2.3. It cannot be said that only because a change has been effected
        in computation of total price under the new tender, the same was invalid             G
        in law. (131-F)

              3.1. The highest offer has not been rejected. A new policy decision
        has been taken. Question is not as to whether the offer of the appellants should
        have been rejected but is as to whether the Authority in law could
                                                                                             H
'
I   '
    110                      SUPREME COURT REPORTS (2006] SUPP. 10 S.C.R.

A have altered its policy in regard to disposal of its properties. (129-EJ
          Bangalore Medical Trust v. B.S. Muddappa & Ors., (199114 SCC 54,
    referred to.

          3.2. The Executive Committee in rejecting the tender has not
B exercised its power to reject bid. The power has been exercised by the
    Authority in cancelling the tenders so as to enable it to have a re-look of
    the entire project. (130-FI

         Star Enterprises & Ors. v. City and Industrial Development Corporation
    of Maharashtra & Ors., (1990] 3 SCC 280, distinguished.
c
         Rajesh Kumar & Ors. v. D.C./. T. & Ors., (20061 11 SCALE 409,
    CommissiQner of Police, Bombay v. Gordhardas Bhanji, (19521 1 SCR 135
    and Union of India & Ors. v. Dinesh Enginering Corporation & Anr. etc.,
    1200118sec491, referred to.

D         3.3. It may be true that the Authorities at one point of time, as was
    disclosed in the Counter Affidavit, had thoght of setting up a Convention
    Centre of their own and without any private participation, but only
    because.there has been a deviation from the said stand would not render
    the entire policy decision vitiated in law. (131-A, Bl
E         4. t. A power to deal with a contractual matter and a power of a
    statutory authority to exercise its statutory power in determining the rights
    and liabilities of the perties are distinct and different. Whereas reasons
    are required to be assigned in a case where civil or evil consequenses may
    ensue, the same may not be necessary where it is contractual in nature,
F   save and except in some cases. (130-B, CJ

          4.2. Some reasons may be required to be assigned for rejecting the
    bid, but in the instant case, no reason was required to be assigned as there
    has been a change in the policy decision. (130-GI

G        5.1. While exercising its jurisdiction of judicial review, the Court is
    required to decide the cases before it, keeping the well known principles
    therefor in mind and having regard to the fact situation obtaining therein.
    No hard and fast rule can be laid down therefor. 1128-BI

          Noble Resources Ltd v. State of Orissa and Anr., (200619 SCALE 181,
H   relied on.
           RAMCHANDRA MURARILAL BHATIAD v. STATE OF MAHARASHTRA            111

      Star Enterprises & Ors. v. City and Industrial Development Corporation       A
 of Maharashtra & Ors., (1990) 3 SCC 280, held inapplicable.

        5.2. It is not a case where the Court is called upon to exercise its
 equity jurisdiction. It is also not a case where ex facie the policy decision
 can be held to be contrary to any statute or against a public policy. A policy
 decision may be subjected to change from time to time. Only because a             B
 change is effected, the same by itself does not render a policy decision to
 be illegal or otherwise vitiated in law. (131-DJ

       Harminder Singh Arora v. Union of India & Ors., (1986) 3 SCC 247,
 distinguised.
                                                                                   c
       New Horizons Ltd & Anr. v. Union ofIndia & Ors., {1995J 1SCC478,
 and Ram and Shyam Company v. State of Haryana and Ors.,(1985) 3 SCC
 267, referred to.

       6.1. Appellant stated before the Court that he is ready and willing
 to take a part of the contract, viz., construction of the C&EC and pay the same   D
 amount as has been done by Reliance Industries Ltd. and in addition it would
 pay 2.5% of its annual turnover from the Convention Centre from the 21st
 year, as was initially offered. [132-C)

        6.2. Appellant did not participate in the second bid. The tender           E
  process is complete. Before the Court only a higher bid has been given.
  Appellants could have submitted its bids pursuant to the new tender and
  new conditions, even without prejudice to its rights and contentions in this
  appeal. The stipulations made in 2002 tender could have been repeated
  by it so as to demonstrate before the experts comprising members of the
· Executive Committee that its bid was the highest. If, in view of the change      F
  in the policy decision, the Authority does not intend to become a partner
  in the profit making and opt for having the entire bid amount at one go
  instead of waiting for 20 years, it cannot be faulted. (132-D, E, F)

       6.3. It, however would not mean that the Authority or the Executive
 Committee would not be entitled to take note of the offer of Appellant. It        G
 may do so. It would not further mean that if the terms of new tender are
 violative of the provisions of the master plan, the same would not be-
 suitably dealt with. (134-B)

       CIVIL APPELLATE JURISDICTION : Civil Appeal No. 5610 of2006.
                                                                                   H
    112                      SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A         From the final Judgment and Order dated 20.1.2004 of the High Court
    of Judicature at Bombay in W.P. No. 2942/2003.

        R.F. Nariman, Dr. AM. Singhvi, P.N. Gupta, H. Devarajan and N.V.
    Vimadalal for the Appellants.

B        Shekhar Naphade, Harish N. Salve, Milind Sathe, A.S. Bhasme, Ravindra
    Keshavrao Adsure, Atul S. Dayal, K.R. Sasiprabhu,_ Ashwin Dave, Meenakshi
    Grover and Chandarchud for the Respondents.

          The Judgment of the Court was delivered by

C         S.B. SINHA, J. Leave granted.

           The Mumbai Metropolitan Region Development Authority (for short,
    'the Authority') was created under the Mumbai Metropolitan Region
    Development Authority Act, 1974 ('the Act'). It conceptualized the idea of
    establishing a Convention and Exhibition Centre_ ('C&EC'). Pursuant thereto
D   and in furtherance thereof it called for "Expression of Interest for development
    of C&EC" in Sandra Kurla Complex. An advertisement was issued inviting
    'Expression of Interest for development of C&EC. Appellant No. I, pursuant
    whereto and in furtherance whereof, entered into a Memorandum of
    Understanding (MoU) with Mis. Larsen & Toubro Ltd. (L&T) for setting up
E   such a complex. It also conducted conference of investors therefor. It
    submitted its tender on 7.4.2003, highlighting :

           (a)   Entire ground of75,000 sq.m. would be required for international
                 standard C&EC.
           (b) They have formed a consortium for bidding for the said project
F              and giving the names of the members of the consortium as
               including L&T and IMAG (Germany).
           (c)   Letters of acceptance from L&T was also annexed to show its
                 participation.
           (d) The Authority was offered equity participation to the extent of
G              5% of the total equity base.

          Several other companies also submitted their tenders.

         The tenders were to be considered at three stages and thus, three different
    covers were to be submitted along with tenders. The first cover contained
H
   RAMCHANDRA MURARILAL BHAITAD v. STATE OF MAHARASHTRA [S.B. SINHA,J.] 113

compliance with minimum eligibility criteria, the second cover contained            A
financial bid and the third one contained technical and business proposals.
The technical bid was opened on 7.5.2003. The financial bid was thereafter
opened which was contained in second cover, on 8.5.2003. Appellant was
the highest bidder having offered 91.514 crores. Mis. Reliance Capitals Ltd.
was said to be the lowest bidder therein. The offer of the bidders thereof are
as under :                                                                          B

              I.   Mis. Shapurji Pallonji & Co. Ltd.      Rs.50.005 Crores.
              2.   Mis. Reliance Capitals Ltd.            Rs.13.032 Crores.

              3.   Mis: R.M. Bhuther & Co. Ltd. and
                   its Associate companies in consor-                               c
                   tium with L&T Ltd.                 Rs. 91.514 Crores.
      3rd Cover thereof was opened thereafter and the Authority, on 26.6.2003
informed Appellants that it had decided to arrange a presentation on the
business proposal by them on 3.7.2003. Pursuant thereto they made a
presentation on 4.7.2003.                                                           D
      Appellants, by a letter dated 29.8.2003, informed the Authority that :

        (a)   reputed concerns like L&T and IMAG were associated in the
              project.

        (b) A presentation was made on 4th July, 2003, a copy whereof was
                                                                                    E
            enclosed.
        (c)   Thereafter it did not receive any query from the Authority.

       (d) List of business partners shown with details of Convention projects
           of L&T and business of IMAG.                                             F
       (e)    Role of IMAG was also set out.

     The Authority, however, took a decisio.n to reject all the bids on 1.9.2003,
which was said to have been communicated to Appellants by a fax message
on 22. 10.2003.
                                                                                    G
      Allegedly, the news item appeared in the 'Economic Times' on
2.10.2003, wherein, inter alia, it was reported that :

       (a)    The Authority is close to finalizing the much talked about
              Convention centre in Bandra Kurla Complex.
                                                                                    H
     114                      SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.              ~·


A           (b)   An official of the Authority had stated that they were trying to
                  get private participation and three bidders had been finalized and
                  in a few days the plans for the Centre would be finalized in an
                  area of 5.5 hectares.

           Appellant issued a letter to the Chairman of the Authority, in terms
B whereof he was, inter alia, informed that the project would start getting yield
     only after 12 years from the date of commencement thereof. It was furthermore
 _,,/informed that its consortium members included L&T and IMAG.
(/
           It was contended :

c           (i) The company has offered highest bid price for the land at BKC for
            a reserved plot for C&EC since the company is interested in bringing
            up an international standard Exhibition Centre, a long over-due
            infrastructure asset for a city like Mumbai inspite of reserved plot
            (restricted utility) area with high gestation period and longest break
            even which is almost about 7 years. In all, the project starts getting
D           yield only after 12 year5 from date of commencement of construction.

            (ii) It has also been the contention of the company to relocate the
            asset base of the company on account of core competency of the
            company in the field for more than 50 years and intending to continue
            to command on industry.
E
            (iii) As per the press release for a commercial block bidding invited
            by the Authority, it was awarded at Rs. 25,000/- per square metre in
            spite of having a total flexibility to exploit the commercial aspect vis-
            a-vis an offer given by the company for the reserved plot for
            convention centre at the rate of Rs.14,642/- per square metre.
F
            (iv) Company also expressed that the projects of such type are always
            being given land at very concessional rate. Statistics indicates that
            world over such exhibition centres are either funded by way of
            concessional land price or absolute government contribution by way
            of land to make the project to early break even.
G
           The expertise of L&T and IMAG in setting up Exhibition Centres was
     again highlighted by a letter dated 20.10.2002, therein it was alleged:

            (a) The Authority had informed in the presence of other bidders that

H
..      RAMCHANDRA MURARilAL BHAITADv. STATE OF MAHARASHTRA [S.B. SINHA, J.J 115

             the consortium led by the appellants were the successful bidders.        A
             (b) Sorrie committee members informed that the matter had not been
             decided on 1.9.2003 and the matter was deferred till the next meeting
             to be held on 27.10.2003.

             (c) The detailed history was set out including the fact that Reliance    B
             Capital had quoted Rs.13.032 crores against Rs.91.514 crores quoted
             by Appellants.

            (d) L&T and IMAG were the consortium members and the decision
            would have an international impact.

           A writ petition was filed before the Bombay High Court by Appellants,      C
     inter a/ia, questioning :

            (a) the validity of clause 2.4 of the Request for Proposal in which the
            Authority reserved the right to reject at any stage all or any of the
            bids without assigning any reason.
                                                                                      D
            (b) the power of the Authority to cancel or reject the bids.

            (c) the cancellation of the bid by the decision purported to have been
            made on 1.9.2003.

          The contentions of Respondents before the High Court were :                 E
            (a) the decision to reject all bids is in pursuance of the power was
            conferred by the terms of the contract.

            (b) the authorities acted reasonably and fairly and have now reached
            a decision to set up the convention centre on their own without any       F
            private participation.

            (c) By virtue of section 12(l)(b)(d) and (h) and the power to issue
            directions under S.14 of the Act, it could, at any stage, review any
            decision including the decision of the executive committee and direct
            either rejection of all bids or issuance of fresh bids.                   G
          The writ petition filed by Appellants was dismissed by the High Court
     holding:

            A. The Executive Committee is not the sole judge in matters of
            approval or rejection of tenders for projects and schemes of the          H
                                                                                        .
    116                       SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A           authorities.

            B. In view of sections 12, 13, 14 and other provisions of the Chapter,
            the power of the Authority cannot be whittled down or restricted.

            C. It being the authority entitled to acquire, hold and dispose of the
            property it cannot be said that its power in such mattes will not
B
            include the power to reject a tender or bid which is invited for projects
            and schemes framed by it.

            D. In exercise of the powers under Article 226 it could not act as an
            Appellate Authority to review of supervise the functions of authorities
C           like the Mumbai Metropolitan Region Development Authority.

            E. Considering the material on record it cannot be held that the
            Authority acted unreasonably unfairly or in an unjust manner.

            F. The Authority consisting of people possessing expertise and skill
            in the field its decision to develop the property as a C&EC by itself
D           cannot be faulted with.

            G. It is not a case where Article 14 can be said to have been infringed.

            H. Jt cannot be said the facts which are pleaded are not based on
            evidence or materials which are not annexed to the counter affidavit.
E
            I. Reasons in such matters can. be gathered from files/records
            maintained by the authorities.

          A review petition filed thereagainst was dismissed.

F         Appellants filed the special leave petition on 29.10.2004 against the
    order dated 20.1.2004 as also against the order dated 11.10.2004 dismissing
    the review petition.

          In its counter affidavit filed before this Court the Authority, inter a/ia,
    disclosed that the rate of premium for the commercial properties was increased
G   from Rs.25,000/- per square metre to Rs.42,500/- per square metre. It was
    further disclosed that the Authority called for fresh tenders for development
    of 5.5 hectares as C&EC and 2.0 hectares for a commercial complex, in
    terms whereof the bidders were required to quote separately for C&EC and
    Real Estate Components. Whereas the rate for C&EC was fixed at 130
    crores (Rs.20,000/- per square metre); for the Real Estate Component the
H
   RAMCHANDRAMURARILALBHATIADv. STATEOFMAHARASHTRA[S.B. SINHA,J.] l l 7

bidder was required to quote higher than 350 crores (i.e. higher than Rs. 70,000/   A
- per square metre). It was further stipulated that the successful bidder was
required to pay 50% of the compensation amount within one month of
acceptance thereof and the rest 50% within three months thereof. The other
terms and conditions and procedure for evaluating bids, however, remained
the same. A supplementary affidavit was filed by Respondents on 20th
February, 2006, wherein it was brought to this Court's notice that in response
                                                                                    B
to the tender floated in 2005, Reliance Industries Ltd. had bid
Rs.974,00,00, 111/- for the commercial portion and the fixed price of Rs.130
crores for the C&EC. Reliance Industries Limited thereafter was directed to
be impleaded as a party by an order dated 24.4.2006, wherein this Court
recorded :                                                                          ~


            "These matters pertain to the construction of a Convention-cum-
        Exhibition Centre and commercial complex at Bandra Kurla, Mumbai.
        The petitioner before us is the unsuccessful bidder who has challenged
        the action of the Mumbai Metropolitan Region Development Authority
        (MMRDA) cancelling all the bids at an earlier stage. Despite the            D
        application made by the petitioner, we declined to grant injunction in
        the matter. As a result, MMRDA re-tendered and we are informed
        that the highest bid was by Reliance Industries Limited, which is said
        to have been granted the contract and paid a sum of Rs.552 crores.

           The petitioner desires to demonstrate to this Court (a) that the bid     E
       was cancelled by the MMRDA, which had no jurisdiction to do so
       under the Act; and (b) that there was ma/a fides in cancelling all the
       bids as it was intended to engineer the re-tendering process to favour
       the party who has now succeeded. To demonstrate his bonafides, the
       petitioner's counsel states that the petitioner would not only match
                                                                                    F
       the bid of the presently successful party only for the Convention
       Centre, but that he would also pay the amount at one go instead of
       paying it over a period of time.

           We are informed that there is another party who is involved. Mr.
       R.F. Nariman, the learned senior counsel, states that the petitioner
                                                                                    G
       would move an application to implead that other party (Reliance
       Industries Limited)."

      The Reliance Industries Limited was impleaded as a party to this appeal
thereafter.
                                                                                    H
    118                     SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A        Mr. R.F. Nariman, learned Senior Counsel appearing on behalf of
    Appellant- in support of this appeal would contend that-

           (i) the purported major shift in the policy by the Authority was
           impermissible in law;

B           (ii) rejection of the bid offered by the Authority was wholly illegal
            as the Executive Committee alone was the sole judge in relation
          . thereto;

           (iii) in accepting the bid of Reliance Industries Ltd., the offer of the
           appellants that they would pay @2 112% per year from the annual
C          turnover from the 21st year had not been considered;

           (iv) in rejecting the tender of the appellant, the Executive Committee/
           Mumbai Metropolitan Region Development Authority was required
           to assign sufficient and valid reason; and the same having not been
           done, the order impugned in the writ petition was vitiated in law.
D
          Mr. Harish N. Salve, learned Senior Counsel appearing on behalf of the
    Reliance Industries Ltd., on the other hand, would submit that-

           (i) th~ Executive Committee could not have taken a decision in regard
           to the change of policy;
E          (ii) when the second tender was floated, Appellant did not take part
           therein;

           (iii) procedural lapses, if any, cannot be a ground for judicial review.

         Contentions of Mr. Shekhar Naphade, learned Senior Counsel'appearing
F   on behalf of the Authority were-

           (i) judicial review is not maintainable as Appellant has not disclosed
           infringement of any constitutional or statutory right;

           (ii) the Authority was entitled to reject the tender on appreciation of
G          professional competence and capacity of Appellant to run the centre
           profitably, as well as the fact that prices offered by them were
           competitively low; and

           (iii) the policy being in relation to a mega project and the judgment
           of the authority being objective criterion, no interference is called for
H
  RAMCHANDRA MURARILAL BHATT AD v. STATE OF MAHARASHTRA [S.B. SINHA,J.) 119

        by this Court.                                                            A
      The Act was enacted for forming Brihan Mumbai and certain areas
round about into a Mumbai Metropolitan Region. Section 4 thereof deals
with the composition of the Authority. Section 4A provides for powers and
functions, inter alia, of its Chairman and Metropolitan Commissioner. Section
7 provides for constitution and powers of Executive Committee. Clause (iii)       B
of Sub-Section (3) of Section 7 reads as under :

           "7. (3)(iii) Approval or rejection of tenders for projects and
       schemes of the Authority;"

      Section 12 of the Act provides for powers and functions of the Authority.   C
Clause (b) of Sub-Section (I) of Section 12 deals with the power ofreviewing
any project or scheme for development which may be proposed or may be
in the course of execution or may be completed in the Metropolitan Region.
Clause (d) thereofrefers to execution of projects and schemes and Clause (h)
provides for co-ordination in execution of the project or schemes for the         D
development of the Metropolitan Region. Pursuant to or in furtherance of its
regulation making power contained in Section 50 of the Act, regulations
were framed by the Authority, known as the Mumbai Metropolitan Region
Development Authority (Disposal of Land) Regulations, 1977 (Regulations).
Regulations 7 and 9 of the Regulations are as under :
                                                                                  E
          "7. Disposal of land by offers to Government, Local Authority or
       Public Sector Undertaking

             Where the Authority determines to dispose of land by making
       .offers to the Government, Local Authority or Public Sector
        Undertaking, the offers shall be made by the Metropolitan                 F
        Commissioner in such form as he may decide, incorporating the terms
        and conditions of offers determined by the Authority which shall
        include the condition that the offer shall remain open and valid for
        acceptance for a period of 30 days and shall lapse if it remains
        unaccepted by the expiry of this period; provided that it shall be
        lawful for the Metropolitan Commissioner to renew any lapsed offer        G
        on an additional condition that the Government, Local Authority or
        Public Sector Undertaking, as the case may be, shall pay interest at
        the rate of 18% per annum over the premium specified in the lapsed
        offer with effect from the date on which the lapsed offer was made;
        provided further that nothing contained herein shall authorize the        H
    120                       SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.
                                                                                        ..
A           Metropolitan Commissioner to renew any lapsed offer after three
            months of its lapse."

          Regulation 9 provides for the mode and manner of payment of premium.

          Sub-Regulation (ii) of Regulation 9 reads as under :
B
                "9(ii) Notwithstanding anything contained in the foregoing Clause
            to contrary, if there shall a scheme fonnulated and sanctioned by the
            Authority to erect or to finance erection of a building or buildings on
            land agreed to be leased to the Government, a Local Authority or a
            Public Sector Undertaking to subserve the development of the
c           Metropolitan Region or any part thereof and to grant in lease such
            building or buildings to th.e concerned government, Local Authority
            or Public Sector Undertaking it shall be lawful to agree with the
            concerned Government local authority or Public Sector Undertaking
            to recover the premium agreed to be paid in consideration of the
            lease of such building or buildings in yearly installments, not exceeding
D           ten in number."

          We may also notice some of the provisions of "Request for Proposal
    for Grant of Lease of Land for developing and operating a Convention and
    Exhibition Centre". Clause 3.15 defines "successful bidder" to mean the
E   bidder selected according to the evaluation criteria as detailed in Section 7
    for grant of lease of land. The concept of Convention and Exhibition Centre
    is contained in Clause 4.3 thereof. Clause 5 provides for specification of
    C&EC. Clause 5.1 reads as under :

            "5.1. The C&EC facility for Phase I is estimated to require
F           approximately 35,750 sq.m. of built up area which will be reckoned
            as 44,525 sq.m. for computation of FSI after allowing for height in
            excess of 4.20 m. for exhibitions areas. In Phase II there is a provision
            of a further I 0,650 sq.m. of built up area (which will be reckoned as
            15,975 sq.m. for computation of FSI for Exhibition areas having
            height in excess of 4.20 m) that is to be used for further expansion
G           of exhibition areas having at least 2 additional exhibition halls having
            an area of 5000 sq.m. each."

          The total built-up area comes to about 60,500 sq,m.

          Provision of Convention Auditorium was made in Clause 5.3. Clause
H   7 provides for submission and evaluation of bids stating that interested parties
-     RAMCHANDRA MURARILAL BHA ITAD v. STA TE OF MAHARASHTRA [S.B. SINHA, J.] J 2 J

    shall submit their bids in three separate sealed covers : (1) Cover 1 should       A
    contain compliance in regard to minimum eligibility criteria. Evaluation of
    minimum eligibility criteria is contained in clause 7.15 in the following terms:

            "7.15 The objective of the minimum eligibility criteria is to short list
            Bidders who have :
                                                                                       B
            e   The financial strengths necessary to contribute and/or arrange
                the funds required to execute the Project in the desired time
                frame.
            e   The technical skills necessary to design, construct, operate and
                maintain the Facility as per the Principles of Good Industry           C
                Practice.
            e   The commercial skills necessary to market the Facility and
                successfully develop business.

          Clause 7.17 provides for the eligibility criteria being :
                                                                                       D
            e   "Tangible Net worth not less than Rs. 750 Million as per the
                latest audited financial statement.
            •   Annual turnover not less than Rs.500 Million as per the latest
                audited financial statement.

            •   Net Profit not less than Rs. 50 Million as per the latest audited      E
                financial statement or Average annual net profit of the last three
                financial years not less than Rs.50 Million."

         Category "I", related to field of activity defined as Convention &
    Exhibition Centres, Hotels, Restaurants and Banquet Halls.
                                                                                       F
          Clause 7.22 provides for Category "II" to include an indirectly related
    field of activity defined as shopping centers, commercial complexes, housing
    or office complexes, retail stores, entertainment centres and amusement parks.
    Clause 7.23 provides for the eligibility criteria to show that the bidding
    company must have developed during last five years at least one Project
    having Capital Cost not less than Rs.1,000 Million. Clauses 7.24 and 7.25          G
    thereof read as under :

           "7.24 The turnover of the Bidding Company or the combined turnover
                of the Financially Significant Members of the Bidding Consortium
                from the directly related field of activities shall not be less than   H
    122                                    SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A                    Rs.500 million.
             725 Format for Cover I compliance to minimum eligibility criteria
                     Bidders are required to organize "Cover I          Companies with
                     Minimum Eligibility Criteria'' according to the following checklist:
B   Cover I            Compliance to Minimum Eligibility Criteria

     :::iect1on 1       ················
     :::iect1on L.     taJ ............

c                      (b) .............

                       (c) Letters of Acceptance, as per the format specified in Exhibi1
                       4, from each of the Consortium Members in case of a Bidding
                       Consortium.

D    Section 3         (a) ................

                       (b) Letters of Commitment as per the format specified in Exhibi1
                       3, from each of the entities which are Financially Significan1
                       Consortium Member, the strengths of which is to be considered
                       for the purpose of evaluation.
E
            Clause 7.26 reads as under :

             "7 .26 ·MMRDA on demand will return unopened Financial Bids and
                   Technical Bids (Covers 2 and 3) of the Bidders who do not
                   comply with the minimum eligibility criteria."
F
         Step 2 (Cover 2) provides for financial bid. Clause 7.30 provh.!es for
    methodology for evaluation of bids.

            Clause 7.30 deals with the manner in which the bids would be dealt
    with.
G
           Clause 7.34 provides for technical and business proposal evaluation
    criteria. Clauses 7.38 and 7.39 are as under :

             "7.38 In evaluating the Business Proposal, MMRDA reserves the right
                  to seek clarificati~ns from the Bidders. The Bidders shall be
H                 required to furnish such clarifications.
  RAMCHANDRA MURARILALBHATIAD v. STATE OF MAHARASHTRA [S.B. SINHA, J.] 123

       139 The Technical and Business Proposal of only the Rank I bidder      A
            will be opened. He may also be requested to make a presentation
            at his own cost, for clarifications and additional information on
            bidder's capability, concept plan and the business proposal in
            this regard to the evaluation committee appointed by the
            Metropolitan Commissioner, MMRDA. The Committee may seek
            further clarifications and make suggestions in respect of the B
            proposal, within the permitted built-up area, which will not include
            any change in the premium or the manner in which it is to be
            paid. These suggestions will have to be incorporated by the
            bidder."

     The Bidding Companies/Bidding Consortium of Appellants included :
                                                                              c
       I.   Mis. R.M. Bhuther & Co. Ltd.
       2.   Mis. Larsen & Toubro Ltd.
       3.   Mis. R.M. Bhuther & Co.
                                                                              D
       4.   Mis. M.B. Development Corporation
       5.   Mis. M.B. Constructions
       6.   Mis. Bhattad Bros.
       7.   Mis. Alusett System (India) Pvt. Ltd.

     The principal question which arises for consideration is as to whether
the Authority had any jurisdiction to cancel the bid.

      The Executive Committee is a statutory functionary. The powers and
functions of the authority and the respective committees concededly are F
governed by the provisions of the statute, but, then the jurisdiction of the
Executive Committee is limited. It was confined to rejection or acceptance
of the tender. The Authority exercises a larger power. For the sai!i purpose
we would assume that the Authority had no incidental or ancillary power, but
there cannot be any doubt Cir dispute that the Executive Committee could not
cancel the entire tender. It could not have caused any change in the entire G
scheme or policy. It could not make alterations in the methodology of
tender. It could not have gone into the working of the project. It also could
not have gone into the question as to whether the project would be financially
viable if the method of calculation is changed.
                                                                              H
    124                       SUPREME COURT REPORTS (2006] SUPP. IO S.C.R.

A         Strong reliance has been placed by Mr. Nariman on Marathwada
    University v. Seshrao Ba/want Rao Chavan, [1989) 3 SCC 132: AIR (1989)
    SC 1582 to contend that as therein the power of the Vice Chancellor and the
    Executive Council was different, the former's power could not have been
    exercised by the latter.

B         We do not dispute the proposition of law laid down therein.

         We would assume that the power of the Executive Committee and the
    Authority under the Act are different and the latter for all intent and purport
    could not usurp the functions of the fonner. But in this case, it has not been
    so done.
c
          Jurisdiction of the Authority being larger, and the power to cancel the
    tender being not vested in the Executive Committee, the action on the part
    of the fonner was neither illegal nor without jurisdiction.

          This Court rejected the contention that the power of the Vice Chancellor
D   to regulate work also included the power to initiate disciplinary action, stating:

                "This takes us to the second contention urged for the appellants.
            The contention relates to the legal effect of ratification done by the
            Executive Council in its meeting held on December 26/27, 1985. The
            decision taken by the Executive Council is in the fonn of a resolution
E           and it reads as follows :

                "Considering the issues, the Executive Council resolved as follows:

                 l. The Executive Council at its meeting held on 22-3-1979, had
            by a resolution given full authority to the Vice-Chancellor for taking
F           further proceedings and decision in both the cases of the defaulting
            officers.

                2. In exercise of above authority, the Vice-Chancellor appointed
            an Inquiry-Officer and as suggested by the Inquiry Officer issued
            show-cause notices, obtained replies from the officers and lastly issued
G           orders for terminating their services;

                *                    *                   *
                It was further resolved that-

                (i) There has been no inadequacy in the proceedings against both
H
   RAMCHANDRA MURARILAL BHA ITAD v. STATE OF MAHARASHTRA [S.B. SINHA, J.] 125

        the officers;                                                              A
            (ii) The punishment ordered against both the officers is
        commensurate with the defaults and allegations proved against both
        the officers; and

            (iii) The Executive Council, therefore, wholly, endorses the actions   B
        taken by the then Vice-Chancellor against both the officers."

             By this resolution, we are told that the Executive Council has
        ratified the action taken by the Vice-Chancellor. Ratification is
        generally an act of principal with regard to a contract or an act done
        by his agent. In Friedman's Law of Agency (5th edn.) Chapter 5 at p.       C
        73, the principle of ratification has been explained:

            "What the 'agent' does on behalf of the 'principal' is done at a
            time when the relation of principal and agent does not exist:
            (hence the use in this sentence, but not in subsequent ones, of
            inverted commas). The agent, in fact, has no authority to do           D
            what he does at the time he does it. Subsequently, however, the
            principal, on whose behalf, th~ugh without whose authority, the
            agent has acted, accepts the agent's act, and adopts it, just as if
            there had been a prior authorisation by the principal to do exactly
            what the agent has done."
                                                                                   E
      As noticed hereinbefore, we have proceeded on the basis that the powers
of the Executive Committee and the Authority are separate and distinct and
we have pointed out that the powers vested in the Executive Committee
being limited, the decision taken by the Authority cannot be said to be illegal.

      It was furthermore contended that the Executive Committee had a special      F
power which would prevail over general power vested in the Authority. In
J.K. Cotton Spinning & fVeaving Mills Co., Ltd v. The State of Uttar Pradesh
& Ors., [1961) 3 SCR 185, this Court applied the rule of construction that
general provisions yield to special provisions, but, the said rule has no
application in the facts and circumstances of the present case. Executive          G
Committee does not exercise any special power. The jurisdictions of both
the authorities are separate and distinct.

     Dr. A.M. Singhvi, learned Senior Counsel appearing for Appellants in
the connected appeal relied upon Bhavnagar University v. Palitana Sugar
Mill Pvt. Ltd & Ors., [2003) 2 SCC 111, wherein it was held :                      H
    126                      SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A              "It is the basic principle of construction of statute that the same
           should be read as a whole then chapter by chapter, section by section
           and words by words. Recourse to construction or interpretation of
           statute is necessary when there is ambiguity, obscurity, or inconsistency
           therein and not otherwise. An effort must be made to give effect to
           all parts of statute and unless absolutely necessary, no part thereof
B          shall be rendered surplusage or redundant."

          We fail to understand as to how the principle laid down therein can be
    said to have been violated.

          Reliance has also been placed on State of Uttar Pradesh v. Singhara
C Singh and Ors., AIR (1964) SC 358: [1964] 4 SCR 485, wherein this Court
    quoted with approval the decision in Taylor v. Taylor, [1875] I Ch. D. 426,
    431] for the proposition that where a power is given to do a certain thing in
    a certain way, the thing must be done in that way or not at all and that other
    methods of performance are necessarily forbidden. There is again no quarrel
D   over the aforementioned proposition of Jaw. Here the Authority has not
    exercised any power forbidden by law. The Authority has also not exercised
    its power in the manner which is not in accordance with law.

         On merit of the matter, Mr. Nariman has pointed out, the distinction
    between 2002 and 2005 tenders to show that such a policy decision as laid
E   down in the 2005 tender was not in pari materia with 2002 tender. The
    comparison of methodology for evaluation of bids is as under :

     2005TENDER                               2002 TENDER METHODOLOGY
                                              FOR EVALUATION OF BIDS
     METHODOLOGY        FOR
F    EVALUATION OF BIDS

     7.30 The bidder will have to             7.30 The bidder will have to quote
     quote separately for the                 separately for the C&EC and the
     Convention & Exhibition Centre           Real Estate component. The built-
     and the Commercial Complex.              up area (considered for FSI
G    The built-up area (considered for        computation) of C&EC shall be
     FSI computa-tion) of the                 considered as 60,500 sq.m. (Phase
     Convention & Exhibi- tion Centre         I and II) irrespective of the
     shall be considered as 65,000            reduction that may be possible on
     sq.m. irrespective of the reductio~      finalization of detailed architectural
     that may be possible on                  designs. Similarly the floor space
H
   RAMCHANDRA MURARILAL BHATIAD v. STATE OF MAHARASHTRA [S.B. SINHA, J.] 127

  finalization       of    detailed       considered in FSI computation for        A
 architectural designs. Similarly         the Real Estate component shall be
 the floor space considered for FSI       15,000 sq.m. The bidder has the
 computation for the commercial           option of bidding only for the
  Complex will be 50,000 sq.m.            C&EC without the Real Estate
  The bidder will have to quote a         component. The bidder has to
 fixed rate of Rs.20,000 per sq.m.        quote a rate of premium in terms         B
 of built up area for total built-up      of Rs. per sq.m. of FSI and the
 area 65,000 sq.m. for Convention         total premium, separately for the
 & Exhibition Centre. The amount          C&EC and the Real Estate
 will be Rs.130 crores. The bidder        component subject to the condition
 will also have to quote a rate of        that the rate quoted for the Real        c
 premium higher than Rs.70,000            Estate component shall be greater
 per sq.m. of built-up area for           than that quoted for the C&EC.
 50,000 sq.m. of total built-up area
 for Commercial Complex. The
 premium amount will be higher
 than Rs.350 crores. The total                                                     D
 minimum amount of lease
 premium to be quoted by the
 bidder will be higher than Rs.480
 crores of the total amount of lease
 premium that will be payable to                                                   E
 MMRDA 50% will have to be
 paid within one month and the
 balance will have to be paid within
 two months i.e. within three
 months from the time the bid is
 accepted. The lease period is of                                                  F
 80 years as is indicated in the
 MMRDA (Disposal of Land)
 Regulation 1977.

      The Authority is a statutory authority. It consists ofnot only politicians   G
but also various other responsible officers. It, while exercising its power
under the Act, must necessarily take policy decisions. Whereas under the
2002 tender the bidder had to quote the rate of premium in terms of rupees
per square meter of FSl and the total premium separately for C&EC and the
Real Estate component subject to the condition that the rate quoted for the
Real Estate component should be greater than th.at quoted for the C&EC,            H
    128                      SUPREME COURT REPORTS [2006) SUPP. 10 S.C.R.

A   upon having come to know that the value of the land would be much more,
    the Authority in the 2005 tender decided that the bidders should be required
    to quote a fixed rate of 20,000 per sq.m. of built-up area for total built-up
    area 65,000 sq.m. for Convention & Exhibition Centre. Economic viability
    of the entire project component, taking into consideration two different
B   components for C&EC and the Commercial Complex, could have been taken
    differently. The premium amount was to be quoted higher than Rs. 350
    crores for the Commercial Complex. While exercising its jurisdiction of
    judicial review, the Court is required to decide the cases before it, keeping
    the well known principles therefor in mind and having regard to the fact
    situation obtaining therein. No hard and fast rule can be laid down therefor.
C   Recently, in Noble Resources Ltd v. State of Orissa and Anr., (2006) 9
    SCALE 181 this Court has noticed the power of judicial review vis-a-vis
    contractual disputes, opining .:

                "Although terms of the invitation to tender may not be open to
           judicial scrutiny, but the courts can scrutinize the award of contract
D          by the Government or its agencies in exercise of their power of
           judicial review to prevent arbitrariness or favouritism. [See Directorate
           of Education and Ors. v. Educomp Datamatics Ltd. and Ors., [2004]
           4 SCC 19]. However, the court may refuse to exercise its jurisdiction,
           if it does not involve any public interest.

E              Although the scope of judicial review or the development of law
           in this field has been noticed hereinbefore particularly in the light of
           the decision of this Court in ABL International Ltd (supra), each
           case, however, must be decided on its own facts. Public interest as
           noticed hereinbefore, may be one of the factors to exercise power of
           judicial review. In a case where a public law element is involved,
F
           judicial review may be permissible."

           Noticing some of the areas where judicial review would be permissible,
    this Court opined that ordinarily, this Court would not enforce specific
    performance of contract where damages would be adequate remedy. It was
G   also held that conduct pf the parties would also play an important role. The
    expansive role of Courts in exercising its power of judicial review is not in
    dispute. But as indicated hereinbefore, each case must be decided on its own
    facts.

          Dr. Singhvi placed reliance upon Star Enterprises & Ors. v. City and
H Industrial Development Corporation of Maharashtra & Ors., [1990] 3 SCC
   RAMCHANDRAMURARILALBHATIADv.STATEOFMAHARASHTRA[S.B.SINHA,J.] 129

 280, wherein Ranganath Misra, J., as His Lordship then was, opined :               A
             "In recent times, judicial review of administrative action has
         become expansive and is becoming wider day by day. The traditional
         limitations have been vanishing and the sphere of judicial scrutiny is
         being expanded. State activity too is becoming fast pervasive. As the
        State has descended into the commercial field and giant public sector       B
        undertakings have grown up, the stake of the public exchequer is also
        large justifying larger social audit, judicial control and review by
        opening of the public gaze; these necessitate recording of reasons for
        executive actions including cases of rejection of highest offers. That
        very often involves long stakes and availability of reasons for action      C
        on the record assures credibility to the action; disciplines public
        conduct and improves the culture of accountability. Looking for
        reasons in support of such action provides an opportunity for an
        objective review in appropriate cases both by the administrative
        superior and by the judicial process. The submission of Mr. Dwivedi,
        therefore, commends itself to our acceptance, namely, that when             D
        highest offers of the type in question are rejected reasons sufficient
        to indicate the stand of the appropriate authority should be made
        available and ordinarily the same should be communicated to the
        concerned parties unless there be any specific justification not to do
        so."
                                                                                    E
       In this case, highest offer has not been rejected. A new policy decision
 has been taken. Question as noticed herein is not as to whether the offer of
 the Appellants should have been rejected but is as to whether the Authority
 in law could have altered its policy in regard to disposal of its properties.
 'Public Trust· Doctrine' was also sought to be invoked by Mr. Nariman against      F
 the Authority and in this behalf reliance has been placed on Bangalore Medical
 Trust v. B.S. Muddappa & Ors., [1991] 4 SCC 54. This Court therein was
dealing with a master plan in the light of justifiability of exercise of
discretionary jurisdiction under the Town Planning Act. Having regard to
the provisions contained in Sub-Section (4) of Section 19 of the Bangalore
Development Authority Act, 1976 as also the fact that the discretionary             G
jurisdiction had been arbitrarily exercised, this Court invoked the 'public
trust doctrine' saying that although the State is required to keep a vigil on the
local body, but, thereby the power thereunder cannot be stretched so as to
entitle the Government to alter any scheme and convert any site or power
specifically reserved in the statute in the Authority.
                                                                                    H
    130                       SUPREME COURT REPORTS [2006] SUPP. IO S.C.R.

A        By floating a tender in furtherance of a public project, the Authority
    was not truly concerned with the enforcement of its master plan. No such
    argument was advanced. before the High Court. Such an argument has been
    advanced for the first time before us. We would consider the efficacy of said
    contention a little later.

B         The next question which arises for consideration is as to whether any
    reason was required to be assigned. A power to deal with a contractual
    matter and a power of a statutory authority to exercise its statutory power in
    determining the rights and liabilities of the parties are distinct and different.
    Whereas reasons are required to be assigned in a case where civil or evil
C   consequences may ensue, the same may not be necessary where it is contractual
    in nature, save and except in some cases, e.g., Star Enterprises (supra).

           Whether assignment of reasons forms third pillar of principle of natural
    justice, is not free from doubt. There is a diversity of opinion as has been
    noticed by this Court in Rajesh Kumar & .Ors. v. D.C./. T. & Ors., (2006) 11
D   SCALE 409.

          Reliance has also been placed by Mr. Nariman on Commissioner of
    Police, Bombay v. Gordhardas Bhanji, [1952] I SCR 135 and Union of India
    & Ors. v. Dinesh Enginering Corporation & Anr. etc., [2001] 8 SCC 491. In
    Commissioner of Police (supra) the Court was concerned with a situation
E   where a statutory authority had acted on dictation of an Appellate Authority,
    which was found to be illegal. In Dinesh Enginering (supra), this Court
    opined that the Railways have no arbitrary power to reject the bid offered by
    a party merely because it has that power, particularly, when the same can be
    exercised only on the existence of certain conditions which in the opinion of
F   the Railways are not in the interest of the Railways to accept the offer.

          We have noticed hereinbefore that power has not been exercised by the
    Executive Committee in rejecting the tender. The power has been exercised
    by the Authority in canceling the tenders so as to enable it to have a re-look
    of the entire project.
G
          Some reasons may be required to be assigned for rejecting the bid, but
    in the instant case, in our opinion, no reason was required to be assigned as
    there has been a change in the policy decision.

          The news item appearing in the Economic Times is not of much
H significance. No affidavit has been affirmed as regards the correctness or
  RAMCHANDRAMURARILALSHATIADv.STATEOFMAHARASITTRA[S.RSINHA,J.J 131


otherwise of the said news item.                                                   A
      It may be true that the Authorities at one point of time, as was disclosed
in the Counter Affidavit, had thought of setting up a Convention Centre of
their own and without any private participation, but only because there has
been a deviation from the said stand would not, in our considered opinion,
render the entire policy decision vitiated in law.                                 B
     It had set up its Evaluation Committee. The decision presumably has
been reached by experts.

     The reasons as regards purported unsatisfactory performance of
Appellants, take a back seat once having a re-look to the entire situation was     C
thought of.

       It is not a case where the Court is called upon to exercise its equity
jurisdiction. It is also not a case where ex facie the policy decision can be
held to be contrary to any statute or against a public policy. A policy            D
decision may be subjected to change from time to time. Only because a
change is effected, the same by itself does not render a policy decision to be
illegal or otherwise vitiated in law.

      In Harminder Singh Arora v. Union of India & Ors., [1986] 3 SCC
247, whereupon Dr. Singhvi relied upon, the tender was arbitrarily rejected.       E
Therein the writ petition was dismissed in limine only on the premise that the
question involved therein related to contractual obligations and the policy
decision could not be tenned as unfair or arbitrary. It was opined that therein
no question of policy decision arose and as such contract was to be given to
the lowest bidder in tenns of the tender notice and the contract should have
been awarded to the appellant therein, especially when he had been doing the       F
job for many years. As to how the said decision is applicable to the facts
of the present case, we fail to understand. For the self-same reasons we are
unable to appreciate the contention that only because a change has been
effected in computation of total price under the new tender, the same was
invalid in law.
                                                                                   G
      In New Horizons ltd. & Anr. v. Union of India & Ors., [1995] I SCC
478, this Court opined that in the matter of grant of tender the State cannot
act as a private person having regard to Article 14 of the Constitution of
India. It was categorically opined that departing from the narrow legalistic
view the Courts have taken note of the realities of the situation which, by no     H
    132                      SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A   stretch of imagination, would mean that the Court would substitute itself in
    the place of a statutory authority. The Court in a case of this nature must
    exercise judicial restraint. It may be one thing to say that having regard to
    the public interest, the Court may itself invite bids so as to verify the
    justification of accepting a palpably lower bid as was done in Ram and
B   Shyam Company v. State of Haryana and Ors., [1985] 3 SCC 267, but it is
    another thing to say the Court would under all circumstances not allow a play
    in joint in favour of the employer.

          However, if the Court in a given situation is not in a position to allow
    a bid to take place before, it may not still venture to strike down an Act in
C   the name of public interest, although, no such public interest exists.

           Appellant stated before us that he is ready and willing to take a part of
    the contract, viz., construction of the C&EC and pay the same amount as has
    been done by ReFance Industries Ltd. and in addition it would pay 2.5% of
    its annual turnover from the Convention Centre from the 21st year, as was
D   initially offered.

           Appellant did not participate in the second bid. The tender process is
    complete. Before us only a higher bid has been given. We do not intend
    to enter into the intricacies of the question. Appellants could have submitted
    its bids pursuant to the new tender and new conditions, even without prejudice
E   to its rights and contentions in this· appeal. The stipulations made in 2002
    tender could have been repeated by it so as to demonstrate before the experts
    comprising members of the Executive Committee that its bid was the highest.
    If, in view of the change in the policy decision, the Authority does not intend
    to become a partner in the profit making and opt for having the entire bid
    amount at one go instead of waiting for 20 years, we do not find any fault
F   therewith.

         Before us comparative bids of the bidders have been placed on the
    second tender, which are as follows :
    SR      Name of the Bidder                Bid Amount              Rate per sq.
    No.                                       Rs.                     m.
G                                         .                          (approx.) Rs .

     1.     Reliance Industries Ltd.          l l ,04,00,00, l l l     96000

    2.      DLF                               1050 crores              91304
H
      RAMCHANDRA MURARILAL BHATTAD v. STATE OF MAHARASHTRA [S.B. SINHA, J.] 133
                                                                                    A
 3.        Reliance Communications &         1011.12 crores          87913
           Infrastructure Ltd.

 4.        Gammon India                      1011 crores            87913

 5.        EMAR                              911.07 crores           79217          B

         The comparative statistics reads as under
  l.       Rate offered by the Petitioners Rs.         Rs. 12,121 per sq. mtrs.
           91.514 crores (divided by)
           75,500 sq.mtrs.                                                          c
 2.        Rate expected by MMRDA                      Rs. 25,000 per sq.mtrs.

 3.        Amount for 75,500 sq. mtrs                  Rs. 188.75 crores
           @ Rs.25,000/- per sq.mtrs. (This should
           have been the minimum bid in 2003)                                       D
 4.        Amount for 1,15,000 sq.mtrs                 Rs.287.50 crores
           @ Rs.25,000/- per sq.mtrs. (This would
           have been the reserve price at old
           rate in 2005)
                                                                                    E
 5.        Reserve Bid of MMRDA in 2005                Rs.480 crores
           (Minimum price revised as below)
 6.        Rate per sq. mtrs in the Reserve            Rs.41, 739/- per sq. mtrs.
           bid Rs.480 crores (divided by)
           1,15,000 sq.mtrs.
                                                                                    F
 7.        Bid by Reliance Industries Ltd.             Rs.1104,00,00, 111/-

 8.        Rate per sq.mtrs of RIL Bid                 Rs.96,000/- per sq. mtrs.
           Rs.11,04,00.00.111/- (divided by)
           1,15,000 sq. mtrs.
                                                                                    G
      Appellant complains that whereas the bid of Sister concern of Reliance
Industries Ltd. was very low; now it has offered a bid of Rs.1104,00,00, 111/
-. From the chart placed before us it would appear that there had been a stiff
computation. The Reliance Industries Ltd. has become the highest bidder. Its
competitors had taken part in the earlier contracts. No ma/a fide in accepting      H
    134                      SUPREME COURT REPORTS [2006] SUPP. 10 S.C.R.

A   the tender has been alleged nor do we find any.

          We, therefore, in the facts and circumstances of this case and having
    regard to the subsequent events, are of the opinion that it is not a case where
    we should interfere with the judgment of the High Court.

B         It, however, would not mean that the Authority or the Executive
    Committee would not be entitled to take note of the offer of Appellant. It.
    may do so. It would not further mean that if the terms of new tender are
    violative of the provisions of the master plan, the same would not be suitably
    dealt with. We merely place on record that we have not gone into the said
C   questions, although raised before us by the learned counsel for the appellant,
    simply on the ground that no such plea had been taken before the High
    Court. In the absence of any plea that the policy decision adopted by the
    Authority. would be violative of the provisions of the Act or any master plan,
    the same cannot be entertained. The question, however, is left open.

D          For the reasons aforementioned, there is no merit in these appeals,
    which are accordingly dismissed. There shall, however, be no order as to
    costs.

    vs                                                        Appeals dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "tender cancellation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.