RAM CHAND AND ORS.versusUNION OF INDIA AND ORS.
- Citation
- 1993 INSC 315
- Decided
- 30 September 1993
- Disposal
- Disposed off
- Bench
- S VERMA
Holding
The delay in making awards was unreasonable, the amendment provisions do not validate it, and the petitioners are entitled to additional compensation at 12% per annum from 23 August 1974 until the award date.
Summary
The petitioners challenged land acquisition proceedings initiated between 1959 and 1965, alleging that the government delayed making awards and paying compensation for more than fourteen years after declarations under Section 6 of the Land Acquisition Act, 1894. The Court examined whether such delay violated the statutory requirement to complete acquisition promptly and the constitutional mandate to pay market value compensation under Article 31A. It held that the proviso to Section 11A of the 1984 amendment does not validate the pre‑amendment delay and that the delay was unreasonable. Consequently, the Court ordered additional compensation at 12% per annum from 23 August 1974 (the date of the Aflatoon judgment) until the award date, calculated on the market value as of the original notification. The writ petitions and the civil appeal were allowed in part, granting modified relief instead of quashing the acquisition, and no costs were awarded.
Issues considered
- The reasonableness of the delay in making awards and paying compensation under the Land Acquisition Act, 1894.
- Whether Section 11A (and its proviso) of the Land Acquisition (Amendment) Act, 1984 validates delays that occurred before its commencement.
- Whether the acquisition proceedings should be quashed on the ground of unreasonable delay.
- Whether additional compensation is payable for the period of delay and at what rate.
- Whether the courts may grant modified relief under Articles 32 and 226 instead of quashing the acquisition.
Legislation cited
- Constitution of Indias. Article 226, s. Article 31A, s. Article 32
- Land Acquisition Act, 1894s. 11, s. 11(1), s. 11A, s. 16, s. 18, s. 23(1), s. 28, s. 34, s. 4, s. 4(1), s. 48, s. 48A, s. 6
- Land Acquisition (Amendment) Act, 1984s. Section 11A, s. Section 48A
- Land Acquisition (Amendment and Validation) Act, 1967s. Section 4(3)
Subjects
Judgment
A RAM CHAND AND ORS.
v.
UNION OF INDIA AND ORS.
AND
B SHRI VED PRAKASH AND ORS.
v.
UNION OF INDTA AND ORS.
SEPTEMBER 30, 1993
c (J.S. VERMA, N.P. SINGH AND S.P. BHARUCHA, JJ.]
Land Acquisition Act, 1894:
Sections 4, 4(1), 6, 11, 11(1), llA, 16, 23(1)--Delay in making Awards
D and Payment of compensation-Award made several years later on the basis
of Market value of land at the time of notice under Section 4(1}-Held: Not
proper compliance of mandate regarding payment of market value of land.
Constitution of India, 1950 :
E Articles 32 & 226-Exercise of jurisdiction-Inaction of the authorities-
Injury caused to public-Power of Court to grant modified relief and to direct
payment of additional compensation.
Proceedings had been initiated between the years 1959 and 1965 by
issuance of notifications under section 4 of the Land Acquisition Act for
F acquisition of lands owned by the petitioners/appellants. Though declara-
tions under section 6 of the Act had been made in the years 1966 and 1969,
awards were made only in the years 1980, 1981 and 1983.
Writ Petition and a civil appeal were filed before the Court quashing
G the land acquisition proceedings.
The petitioners/appellants, contended that the respondents had is-
sued the declarations in respect of several thousand bighas of lands, but
no further steps, for making of the award or payment of the compensation,
were taken for more that 14 years from the date of the declarations under
H section 6 of the Act, and the awards were only in the years 1980, 1981 and
558
RAM CHAND v. U.0.1. 559
1983. This procedure was adopted only to peg the market value of the lands A
between the years 1959 and 1965.
The respondents contended that even if it be assumed that there had
been an unreasonable delay in completion.-Of..the-land acquisition proceed·
ings, that delay had been condoned and validated by Section llA which
was introduced by the Land Acquisition (Amendment) Act, 1984, and that B
in view of the proviso to section llA of the Act, where a declaration under
section 6 had been published before the commencement of the Amendment
Act of 1984, like the instant cases, the awards could be made within a
period of two years from the commencement of the Amendment Act, i.e.
up to 23rd September, 1986. C
Allowing the writ petitions and the appeal, this court
HELD: 1. The different sections of the Land Acquisition Act, 1894
indicate that the framers of the Act enjoined, that after publication of
notification under sub-section(l) of section 4 of the Act, further proceed- D
ings should be taken as early as possible. A special feature of the Act is
that it requires award to be made and compensation to be paid before the
land, which is the subject matter of acquisition, vests in the Government.
This is apparent from section 16, which says that when the Collector has
made an award under> section 11, "he may take possession of the land,
which shall thereupon vest absolutely in the Government, free from all E
encumbrances." Normally, in statutes relating to acquisition of interest of
the holder, question of assessment and payment of compensation arise
after the vesting of the right, title interest of the holder. But the Act
conceives that there may be delay in taking possession, due to some
unavoidable reasons and, as such making of the award or payment of the F
compensation should not be dependent on taking of the possession of such
land and vesting thereof in the Government. (564-B-D]
State of Gujarat v. Pastel Raghav Natha, AIR (1969) SC 1297 = (1970)
SLR 335; Mansaram v. S.P. Pathak, (1984] 1 SCC 125; State of Madhya
Pradesh v. Vishnu Prashad Shanna, (1966] 3 SCR 551,Ambalal Purshottam G
v. Ahmedabad Municipal Corporation, (1968] 3 SCR 207; Khadim Hussain
v. State of U.P., (1976] 3 SCR 1 = AIR (1976) SC 417; The Tiverton and
North Devon Railway Company v. Robert Francis Loosemore, 9 Appeal
Cases 480 at 489; Grice v. Duley Corporation, (1958) 1 Chancery Division
329 andBinningham City Corpn. v. West Midland Baptist (Trnst) Association H
560 SUPREME COURT REPORTS (1993) SUPP. 2 S.C.R.
A (Incorporated), [1969] 3 All England Reports 172, referred to.
Craies on Statute Law, Seventh Edition, Pl.282, referred to
2. It cannot be said that the pr~viso to section llA of the Act in any
manner validates or justified the inaction on the part of the authorities in
B delaying and keeping land acquisition proceedings pending for a decade
and half, after declarations had been made under section 6 of the Act.
[569-E-F]
Aflatoon v. Lt. Governor of Delhi, [1975] 4 SCC 285 and Ramjas
Foundation v. Union of India, [1991] Suppl. 2 SCC 20, referred to.
c 3. In a case where after declaration under section 6, but prior to
making of the award acquisition is withdrawn under section 48, the land
having enhanced market value remains with the holder thereof. Different
States in India by State Amendments introduced section 48A, in order to
safeguard the interest of the persons in respect of whose lands declaration ·
D have been issued under section 6, but no awards have been made within a
reasonable time. In view of section 48A aforesaid, the declaration under
section 6 may not become invalid because of the delay in the completion
of the proceeding for acquisition, but after a period of two years from the
date of the publication of such declaration, unless the owner of the land
E had been responsible for the delay, the owner shall be entitled to receive
compensation for the damage suffered by him in consequence of such
delay. Such damage is to be determined under part III of the Act, as
compensation payable under section 48A. In view of this section, while
computing the quantum of compensation, what damage the owner of the
land has suffered due to delay in completion of the acquisition proceeding,
F has also to be calculated. Unfortunately, no such amendment was intro-
duced in the principle Act and even when several amendments were intro-
duced by the Land Acquisition (Amendment) Act, 1984, this aspect of the
matter appears to have been overlooked. [571-B-F]
Special Land Acquisition Officer Bombay v. Godrej and Boyce, [1988)
G
1 SCR 590, distinguished.
4. The petitioners/appellants are under great predicament because
of the delay and inaction on the part of the respondents. Any amount
determined as market value of their lands acquired, with reference to the
H dates of issunace of notifications under sub-section(l) of section 4 of the
RAM CHAND v. U.0.1. 561
Act i.e. at the rate prevalent 15 to 21 years prior to the dates of the making A
of the award, cannot be said to be the compliance of the mandate regarding
payment of market value of the land so acquired, under the Constitution
and the Land Acquisition Act. [573-E-F]
Ujjain Vikas Pradhikaran v. Raj Kumar Johari, [1992] 1 SCC 328,
Akhara Brahm Buta Amritsar v. State of Punjab, JT (1992) 5, 136, Bihar State B
Housing Board, State of Bihar v. Ban Bihari Mahato, AIR (1988) SC 2134
I and Union Carbide corporation v. Union of India, [1992] SC 248= [1991] 4
sec 548 ' refered to.
5. The exercise of power in the facts and circumstances of the cases, c
by the respondents is against the spirit of the provisions of the Act, tending
arbitrariness. In such a situation this Court in exercise of power under
Article 32 and the High Court under Article 226, could have quashed the
proceedings. But, taking into consideration that in most of the cases, the
Delhi Administration and Delhi Development Authority have taken pos- D
session of the lands and even developments have been made, it shall not
be a proper exercise of discretion on the part of this Court to quash the
proceedings because, in that event, it shall affect the public interest.
Moreover, third party interests created in the meantime are also likely to
be affected and such third parties are not impleaded. The relief of quash-
ing the acquisition proceeding having become in appropriate due to the E
subsequent events, the grant of a modified relief, considered appropriate
in the circumstances, would be the proper course to adopt., [574-C-F]
6. After the judgment of this Court in Aflatoon's case rendered on
23rd August, 1974, the reasonable time for making the awards was about I
two years from that date. Beyond two years, the time taken for making of
the awards will be deemed to be unreasonable. As. 'such, after expiry of the
period of two years, some additional compensation has to be awarded to
the cultivators. Taking into consideration the interest of the cultivators
and the public, instead of quashing the proceedings for acquisition, it is
directed that the petitioners/appellants shall be paid an additional amount
of compensation to be calculated at the rate of twelve percent per annum,
after expiry of two years from 23.8.1974, till the date of the making of the
awards by the Collector, to be calculated with reference to the market value
of the lands in question, on the date of the notifications under sub-sec-
tion(!) of section 4. [575-B-D]
562 SUPREME COURT REPORTS [1993) SUPP. 2 S.C.R.
A Aflatoon v. Lt. Govemor of Delhi, [1975] 4 SCC 285, refered to.
CIVIL ORIGINAL APPELLATE JURISDICTION: Writ petitions
Nos. 1609 to 1622 of 1981.
(Under Article 32 of the Constitution of India.)
B
AND
Civil Apeal No. 2630 of 1980.
From the Judgment and Order dated 21.10.80 of the Delhi High
Court in Civil Writ Petition No. 963 of 1980.
c
G.L. Sanghi, A.K. Sen, S.K. Mehta, Dhruv Mehta and B.S. Chauhan
for the petitioners/appellants.
N.N. Goswamy, T.C. Sharma, S.N.Sikka, Arun Kumar Sharma and
B.K. Prasad for the respondents.
D
The Judgment of the Court was delivered by
N.P. SINGH, J. Writ petitions and a civil appeal have been filed for
quashing the land acquisition proceedings, which had been initiated be-
tween the years 1859 and 1965 by issuance of notifications under section 4
E of the Land Acquisition Act (hereinafter referred to as "the Act") but in
which no awards were made up to the years 1979-80, although the decla-
rations under section 6 of the Act had been made in the years 1966 and
1969. The first such notification under section 4 of the Act was issued on
13.1.1959 in respect of 24,000 acres of land. Another notification under
section 4 was issued on 24.10.1961 in respect of 16,000 acres of land. One
F such notification under section 4 was issued on 23.1.1965. Declarations
under section 6 of the Act were issued on 16.5.1966 and 13.1.1969. The
declaration dated 16.5.1966 related to 2,153 Bighas of land, whereas the
declaration dated 13.1.1969 was in respect of 88 Bighas. a declaration
under section 6 had been made on 6.12.1966 in respect of 5,898 bighas of
G land which is subject matter of controversy in other writ petitions.
According to the petitioners, having issued the declarations in
respect of several thousand Bighas of land, no further steps, for making of
the award or payment of the compensation, were taken for more than 14
years from the date of the declarations under section 6 of the Act. The
H awards were made only in the years 1980, 1981 and 1983. This procedure
RAM CHAND v. U.O.I. [N.P. SINGH, J.] 563
was adopted only to peg the market value of the lands between the years A
1959 and 1965. This has inflicted great injury to the petitioners, inasmuch
as the compensation has been worked out with reference to the dates of
notifications under section 4 of the Act.
The power to acquire private property for public use is an attribute
of sovereignty and is essential to the existence of the Government. The B
power of eminent domain was recognised on the principle that the
sovereign State can always acquire the property of a citizen for public good,
without the owner's consent. Later, either in the Constitution or in the Act
enacted for that purpose, not only this power was recognised, but limita-
tions on exercise of such power were prescribed, for striking a balance c
between the interest of the public and the individual.
The right to acquire an interest in land compulsorily has assumed
increasing importance as a result of requirement of such land more and
more everyday, for different public purpose and to implement the promises D
made by the framers of the Constitution to the people of India. But, the
Constitution ensures under the second proviso to Article 31A, that wh>;~e
any law makes provision for the acquisition by the State of land held by a
person, under his personal cultivation, within the ceiling limit, it shall not
be lawful for the State to acquire any portion of such land land "unless the
law relating to the acquisition of such land, building or structure, provides E
for payment of compensation at a rate which shall not be less than the
market value thereof." By Constitution (Forty-fourth Amendment) Act,
1978, clause (t) of Article 19 and Article 31 have beep. deleted and, as such,
to hold property is no more a fundamental right. But, still the mandate
under second proviso to Article 31A continues regarding payment of F
market value in respect of the land, the subject-matter of acquisition. The
Act provides for payment of compensation in respect of the acquisition
made, at the market value of the land, as such it is consistent with second
proviso to Article 31A. But in view of sub section (1) of section 11 and
sub-section (1) of section 23, the market value of such land is to be fixed
with reference to " the date of the publication of the notification under G
section 4, sub-section (1)", irrespective of the dates on with declaration
under section 6 or award under section 11 are made or possession is taken
under section 16 of the Act. Prior to coming in force of the Land Acquisi-
tion (Amendment) Act, 1984, no time limit was prescribed for making an
award under section 11 of the Act with reference to the date of declaration H
564 SUPREME COURT REPORTS (1993) SUPP. 2 S.C.R.
A under section 6.
But the different sections of the Act indicate that the framers of the
Act enjoined, that after publication of notification under sub-section (1) of
section 4 of the Act, proceedings should be taken as early as possible. A
special feature of the Act is that it requires award to be made and
B compensation to be paid before the land, which is the subject-matter of
acquisition, vests in the Government. This is apparent from section 16,
which says that when the Collector has made an award under section 11,
"he may take possession of the land, which shall thereupon vest absolutely
in the Government, free from all encumbrances." Normally, in statutes
c relating to acquisition of interest of the holder of any right, questions of
assessment and payment of compensation arise after the vesting of the
right, title interest of the holder. But the Act conceives that there may be
delay in taking possession, due to some unavoidable reasons and, as such,
making of the award or payment of the compensation should not be
dependent on taking of the possession of such land and vesting thereof in
D the Government. Still, the experience of the courts have been that proceed-
ings for land acquisition have been moving at snail's pace for reasons not
always easy to ascertain.
In the case of State of Gujarat v. Raghav Natha, AIR (1969) SC 1297
E [1970) 1 SCR 335, it was considered whether in a statute, if for exercise of
the power, no time limit has been fixed, the authority, who has to exercise
such power, can exercise the same at any time. It was said :-
"The question arises whether the Commissioner can revise an order
made under Section 65 at any time. It is true that there is no period
F of limitation prescribed under Section 211, but it seems to us plain
that this power must be exercised in reasonable time and the length
of the reasonable time must be determined by the facts of the case
and the nature of the order which is being revised."
G Same view was reiterated in the case of Mansaram v. S.P. Pathak, (1984) 1
sec 125. It was said :-
"But as stated earlier, where power is conferred to effectuate a
purpose, it has to be. exercised in a reasonable manner and the
reasonable exercise of power inheres its exercise within a
H reasonable time."
RAM CHAND v. U.O.l. [N.P. SINGH, J.] 565
In connection with land acquisition proceeding itself, in the case A
State of Madhya Pradesh v. Vishnu Prasad Shanna, [1966] 3 SCR 557,
where a grievance had been made in respect of delay in issuance of the
declaration under section 6 of the Act, after issuance of notification under
section 4( 1) of the Act, it was pointed out :
B
"It is clear from this intimate connection between ss. 4, 5-A and 6
that as soon as the government has made up its mind what par-
ticular land out of the locality it requires, it has to issue a decla-
ration under s.6 to that effect."
This must be followed· by expeditious conclusion of the acquisition C
proceedings culminating in the Awards and payment of compensation. This
Court in the case ofAmbalal Purshottam v.Ahmedabad Municipal Corpora-
tion, (1968] 3 SCR 207, said :
"We are not hereby to be understood as suggesting that after issue D
of the notifications under ss. 4 & 6 the appropriate Government
would be justified in allowing the matters to drift and to take in
hand the proceeding for assessment of compensation whenever
they think it proper to do. It is intended by the scheme of the Act
that the notification under s.6 of the Land Acquisition Act must
be followed by a proceeding for determination of compensation E
without any unreasonable delay.
In the case of Khadim Hussain v. State of U.P., [1976] 3 SCR 1
AIR (1976) SC 417, this Court again said:-
F
"As indicated by the Division Bench of the Allahabad High Court,
the amendment of 1967, was the result of a decision of this court
in the State of Madhya Pradesh ·v. Vishnu Prasad Shanna, AIR
(1966) SC 1593, holding successive notifications, under Section 6,
with excessive intervening delay between a notification under Sec-
tion 4(2) and a declaration under Section 6, keeping the owner or G
other person entitled to compensation in suspense all the time, to
be illegal. It may be that, if an umeasonable delay between a
declaration and its notification in shown to exist, it may raise a
suspicion about the existence of the declaration itself or about the
bona fides of acquisition proceedings." H
566 SUPREME COURT REPORTS (1993) SUPP. 2 S.C.R.
A Craies on Statute Law, Seventh Edition, p. 282, has also emphasised
that the proceeding for compulsory acquisition must be concluded without
unreasonable delay :-
"Powers conferred by Act of Parliament must, as a general rule,
be exercised within reasonable time after notice has been given to
B the persons whose property will be affected by their exercise,
otherwise the notice will be liable to be treated as being no longer
effective."
English Courts have been consistenly impressing that the land ac-
C quisition proceeding should be completed within a reasonable time, failing
which the whole proceeding is vitiated. It was said in the case of The
Tiverton and North Devon Railway Company v. Robert Francis Loosemore,
9 Appeal Cases 480 at 489 : -
"If nothing more was done and the company have slept upon their
D rights, and certainly if the delay cannot be explained, they should
be held to be disabled from going on with any compulsory pur-
.chase, ...... "
Same view was reiterated in the case of Grice v. Dudley Corporation, (1958)
1 Chancery Division 329.
E
House of Lords in the case of Binningham City Corporation v. West
Midland Baptist (Trust) Association (Incorporated), [1969] 3 "All England
Reports 172, pointed out that the land acquisition proceedings should be
conducted in such a manner that the person affected from the land
acquisition, gets substantially the value of his land, which he would got on
F
the date of his dispossession. It was said :-
"The principle and the rule cannot be reconciled except on the
basis that the total value to the owner at the date of the notice to
treat is always substantially the same as the value at the date of
G the expulsion."
The Land Acquisition (Amendment) Act, 1984 has now introduced
a time limit before which a declaration under section 6 has to be made.
The relevant part of amended section 6 says :-
H " Provided that no declaration in respect of any particular land
RAM CHAND v. U.O.I. [N.P. SINGH, J.] 567
covered by a notification under Section 4, sub- section (1),- A
(i) published after the commencement of the Land Acquisi-
tion (Amendment and Validation) Ordinance, 1967(of1967),
but before the commencement of the Land Acquisition
(Amendment) Act, 1984, shall be made after the expiry of
three years from the date of the publication of the notifica- B
tion; or
(ii) published after the commencement of the Land Acquisi-
tion (Amendment) Act, 1984, shall be made after the date of
the publication of the notification :"
c
By the same Act, section 11-A has been introduced, which fixes a time limit
for the making of the award under section 11 of the Act, failing which the
proceeding for the acquisition of the land is to lapse. Section 11-A is as
follows:-
D
"11-A. Period within which an award shall be made.- The Collector
shall make an award under Section 11 within a period of two years
from the date of the publication of the declaration and if no award
is made within that period, the entire proceedings for the acquisi-
tion of the land shall lapse :
E
Provided that in a case where the said declaration has been
published before the commencement of the Land Acquisition
(Amendment) Act, 1984, the award shall be made within a period
of two years from such commencement.
Explanation.- In computing the period of two years referred to in F
this section, the period during which any action or proceeding to
be taken in pursuance of the said declaration is stayed by an order
of a Court shall be excluded."
The Parliament has recognised and taken note of the inaction and
non-exercise of the statutory power on the part of the authorities, enjoined G
by the provisions of the Act to complete acquisition proceedings within a
reasonable time and because of that now a time limit has been fixed for
making of the award, failing which the entire proceeding for acquisition
shall lapse. But, can it be said that before the introduction of amendment
aforesaid in. the Act, the authorities were at liberty to proceed with the H
568 SUPREME COURT REPORTS [1993) SUPP. 2 S.C.R.
A acquisition proceedings, irrespective of any schedule or time-frame and to
complete the same as and when they desired? It is settled that in a statute
where for exercise of power no time limit is fixed, it has to be exercised
within a time which can be held to be reasonable. This aspect of the matter
can be examined in the light of second proviso to Article 31A of the
Constitution, which in clear and unambiguous terms prohibits making of
B any Jaw which does not contain a provision for payment of compensation
at a rate, which shall not be Jess than the market value thereof. The Act is
consistent with the second proviso to Article 31A, because it provides for
payment of compensation at the market value of the land acquired. But,
whether the constitutional and statutory requirement of the payment of the
c market value to the persons, whose lands have been compulsorily acquired,
is not being circumvented and violated by keeping the land acquisition
proceedings pending for more than a decade and half, without making the
awards and paying the compensation, which has been pegged to the dates,
of notifications under sub-section (1) of section 4 of the Act, which in the
D present cases had been issued 14 to 21 years before the making of the
awards. If a person is paid compensational in the year 1980/1981 at the
market rate, prevailing twenty year before, will that be the compliance of
the constitution and statutory mandate? Ignoring the escalation of the
market value of the lands, especially near the urban agglomeration or
metropolitan cities, will amount to ignoring an earthquake and courts can
E certainly take judicial notice of the said fact. The interest and the solatium,
which have to be paid under the pro~isions of the Act, are linked with the
market value of the land with reference to the date of the notification under
sub-section (1) of section 4 of the Act. If a decision had been taken as early
as in the year 1966, by issuance of declarations under section 6, that the
F lands belonging to the different cultivators, who held those lands within the
ceiling limit for cultivation, were needed for public purpose, respondents
should have taken steps for completion of the acquisition proceedings and
payment of compensation at an early date. In the present cases, unless a
justification is furnished on behalf of the respondents, can it be said that
the statutory power of making an award under section 11 has been exer-
G cised, within a reasonable time from the date of the declaration under
section 6? Due to escalation in prices of land, more so in this area, during
the preceding two decades, in reality, the market rate, on the date of the
notification under section 4(1) is a mere fraction, of the rate prevailing at
the time of its determination in the Award.
H
RAM CHAND v. U.0.1. [N.P. SINGH, J.] 569
"Mr. J aitley, appearing for Delhi Development Authority, took a stand A
that even if it be assumed that there has been an unreasonable delay in
completion of the land acquisition proceedings, that delay has been con-
doned and validated by section llA aforesaid, which was introduced by
the Land Acquisition (Amendment) Act, 1984. He pointed out that in view
of the proviso to section llA of the Act, where a declaratfon under section
B
6 had been published before the commencement of the Amendment Act
. of 1984, like present cases, the award can be made within a period of two
years from the commencement of such Act i.e. up to 23rd September, 1986.
As a first impression this argument is attractive. But, from reading of
section llA it is apparent that the said section neither purports to validate
any pending acquisition nor it condones any delay which had already c
occurred. The main part of section llA introduces a statutory mandate to
made an award within a period of two years, from the date of the publica-
tion of the declaration under section 6 and provides that if no award is
made within that period, the entire proceeding for acquisition of the land
is to lapse. In the proviso, yet another mandate has been introduced by the D
Parliament, saying that in cases where declaration under section 6 had been
published ·before the commencement of the Land Acquisition (Amend-
ment) Act, 1984, the award shall be made within a period of two years from
such commencement. The role of a proviso, hardly needs elucidation, in
view of well-settled position by series of judgments of this Court and the
rules of interpretation of statutes. The proviso, only carves out an excep- E
tion, which could have been covered otherwise by the substantive part of
the section. According to us, it cannot be held that the proviso to section
llA, in any manner, validates or justifies the inaction on the part of the
authorities in delaying and keeping land acquisition proceedings, pending
for a decade and a half, after declaration had been made under section 6
F
of the Act. Apart from that, it is not in dispute that section llA, will not
be applicable to land acquisition proceedings, where awards had been
made, as in the present cases, prior to 24th September, 1984 when the
Amending Act of 1984 came in force. As such, pnJviso tQ section llA is
not at all applicable to the proceedings with which we are concerned.
G
On behalf of the respondents, it was pointed out that the petitioners
have approached this Court only after making of the awards, or when
awards were to be made, having waited for more than fourteen years,
without invoking the jurisdiction of the High Court under Article 226 or of
this Court under Article 32. It is true that this Court has taken note of H
570 SUPREME COURT REPORTS [1993] SUPP. 2 S.CR.
A delay on the part of the petitioners concerned, in invoking the jurisdiction
of the High Court or of this Court for quashing the land acquisition
proceedings on the ground that the proceedings for acquisition of the lands
in question, have remained pending for more than a decade, in the cases
of Aflatoon v. Lt. Governor of Delh4 [1975] 4 SCC 285, and Ramjas
B Foundation v. Union of India, (1993] Suppl. 2 SCC 20 = AIR (1993) SC
852. According to us, the question of delay in invoking the writ jurisdiction
of the High Court under Article 226 or of this Court under Article 32, has
to be considered along with the inaction on the part of the authorities, who
had to perform their statutory duties. Can the statutory authority take a
plea that. although it had not performed its duty within a reasonable time,
C but it is of no consequence because the person, who has been wronged or
deprived of his right, has also not invoked the jurisdiction of the High
Court or this Court, for a suitable writ or direction to grant the relief
considered appropriate in the circumstances? The authorities are enjoined
by the statute concerned, to perform their duties within a reasonable time,
D and as such they are answerable to the Court. why such duties have not
been performed by them, which has caused injury to the claimants. By not
questioning, the validity of the acquisition proceedings for a long time since
the declarations were made under section 6, the relief of quashing the
acquisition proceedings has become inappropriate, because, in the mean-
time, the lands notified have been developed and put to public use. The
E lands are being utilised to provide shelter to thousands and to implement
the scheme of a planned city, which is a must in the present set up. The
outweighing public interest has to be given due weight. That is why this
Court has been resisting attempts on the part of the land holders, seeking
quashing of the acquisition proceedings, on ground of delay in completion
p of such proceedings. But, can the respondents be not directed to compen-
sate the petitioners, who were small cultivators, holding lands within the
ceiling limit, in and around Delhi, for the injury caused to them, not by the
provisions of the Act, because of the non-exercise of the power by the
authorities under the Act within a reasonable time?
G Mr. Goswami, on behalf of the respondents, referred to the judgment
of this Court in the case of Special Land Acquisition Officer Bombay v.
Godrej and Boyce, [1988] 1 SCR 590. There an order under section 48 of
the Act, withdrawing the acquisition of the land in question, was being
challenged on the ground that such order had been issued, long time after
H the declaration under section 6. In that context, it was said by this Court
RAM CHAND v. U.O.I. [N.P. SINGH, J.] 571
that the petitioners, who were the holders of the lands and were in A
possession thereof, had not been prejudiced by the delay. On basis of that
judgment, it was urged that even in present cases, the petitioners have
remained in possession of their lands and, such, there is no question of
their suffering any injury due to delay in the completion of land acquisition
proceedings. That decision is inapplicable in the present situation because
B
section 48 is not applicable after making of the awards, In a case where
after declaration under section 6, but prior to making of the award acquisi-
tion is withdrawn, under section 48, the land having enhanced market value
remains with the holder thereof.
It may be pointed out that different States in India including C
Maharashtra, Madhya Pradesh, Tamil Nadu and West Bengal have in the
years 1950 and 1955, by State Amendments introduced section 48A, in the
relevant Land Acquisition Act, in order to safeguard the interest of the
persons in respect of whose lands declaration have been issued unde'.
section 6, but no awards have been made within a reasonable time. In view D
of section 48A aforesaid, the declaration under section 6 may not become
invalid because of the delay in the completion of the proceeding for
acquisition, but after a period of two years from the date of the publication
of such declaration, unless the owner of the land had been responsible for
the delay, the owner shall be entitled to receive compensation for the
damage suffered by him in consequence of such delay. Such damage is to E
be determined under part III of the Act, as compensation payable under
section 48A. In view of this section, while computing the quantum of
compensation, what damage the owner of the land has suffered due to
delay in completion of the acquisition proceeding, has also to be calculated.
Unfortunately, no such amendment was introduced in the principal Act F
and even when several amendments were introduced by the Land Acquisi-
tion (Amendment) Act, 1984, this aspect of the matter appears to have
been overlooked.
The learned counsel, appearing for the respondents, while resisting
the charge of unreasonable delay in completing the acquisition proceeding, G
stated that between the years 1959-65 more than 68 thousand acres of land
had been notified under sub- section (1) of section 4 of the Act. Thereafter,
several thousand objections had been filed; even writ applications had been
filed in Delhi High Court, questioning the validity of notifications under
section 4 and declarations under section 6 of the Act. In such petitions, the H
572 SUPREME COURT REPORTS (1993] SUPP. 2 S.C.R.
A High Court had also passed interim orders.
On behalf of the petitioners, it was pointed out that in most of the
writ applications, which had been filed questioning the notifications under
section 4 and declarations under section 6 of the Act, the interim orders
were only in respect of dispossession of the petitioners of such writ
B applications. As such the respondents were at liberty to proceed with the
land acquisition proceedings and should have prepared the awards within
a reasonable time. In any case, all such writ applications were dismissed
,by judgment of this Court on 23rd August, 1974, in the case of Aflatoon v.
Lt. Governor of Delhi, (Supra). From the counter affidavits filed before
C this Court on behalf of the respondents, there does not appear to be any
reasonable explanation, why after dismissal of the aforesaid writ applica-
tions on 23rd August, 1974, no effective steps were taken till 1980-1981 and
in some cases till 1983 for preparation of the awards.
D It was urged on behalf of the respondents that in view of sub-section
(3) of section 4 of the Land Acquisition (Amendment and Validation) Act,
1967, if the declarations under section 6 have been made after expiry of
three years from the· date of publication of notifications under sub-section
(1) of section 4, then the persons concerned are entitled to be paid simple
interest, calculated at the rate of six per cent annum on the market value
E of such land, as determined under section 23 of the Act, up to the date of
the tender or payment of the compensation awarded by the Collector for
the acquisition of such land. The aforesaid sub-section (3) of section 4 of
the Land Acquisition (Amendment and Validation) Act, 1967, may be
applicable to cases where the declaration under section 6 has been made
p either before or after the commencement of the said Act, but made after
the expiry of three years of the notification under sub-section (1) of section
4 of the Act. But in cases where declaration has been made within three
years from the date of issuance of notification under sub-section (1) of
section 4, obviously the aforesaid Amending Act shall not be applicable.
This provision can hardly be said to compensation the persons, who have
G been deprived of the legitimate compensation for years.
Reference was also made to section 34 of the Act. That provision
will apply where the compensation had neither been paid nor deposited
before taking the possession of the land and, interest at the rate of 6 per
H cent which has been later substituted. to 9 per cent by Act 68 of 1984, has
RAM CHAND v. U.O.I. [N.P. SINGH, J.] 573
to be paid for the time of taking possession until the compensation has A
been paid or deposited. This section has no relevance in the context of the
question involved in the present cases.
Section 28 of the Act is also applicable only in respect of the excess
amount, which is determined by the Court after a reference· under section B
18 of the Act. This Court had held in the case of Union of India v. Zora
Singh, [1992) 1 SCC 673, that sub-section (1-A), which was introduced by
Act 68 of 1984, in section 23 regarding payment of interest at the rate of
12 per cent per annum, over the market value of the land for the period
commencing on the from the date of the publication of the notification
under section 4, sub-section (1), up to the date of the award of the C
Collector or up to the date of the taking of the possession of the land
whichever is earlier, was applicable to case which were pending after the
reference under section 18 of the Act. But in the meantime the correctness
of the judgment has been doubted in the case of KS. Pariapooran v. State
of Kerala, [1992) 1 sec 684, and the matter has been· referred to the D
Constitution Bench.
The petitioners because of the delay and inaction on the part of the
respondents are under great predicament. Any amount determined as
market value of their lands acquired, with reference to the dates of issuance
of notifications under sub-section (1) of section 4 of the Act i.e. at the rate E
prevalent 15-21 years prior to the dates of the making of the award, cannot
be held to be the compliance of the mandate regarding payment of market
value of the land so acquired, under the Constitution and the Act. This
Court faced with such a situation, where proceedings have remained
pending for years, after issuance of declarations under section 6, in order F
to protect the petitioners concerned from irreparable injury i.e. getting
compensation for their lands acquired with reference to the date of
notification under sub- section (1) of section 4, which may be more than a
decade before the date of the making of the award, has a~vanced the date
of notification under sub-section (1) of section 4 of the Act, so that market
value of the land so acquired is paid at a just and reasonable rate. G
Reference in this connection may be made to the cases of Ujjain Vikas
Pradhikaran v. Raj Kumar Johri, [1992) 1 SCC 328, Akhara Brahm Buta
Amritsar.v. State of Punjab, JT (1992) §SC 136 and Bihar State Housing
Board, State of Bihar v. Ban Bihari Mahilto, AIR (1988) SC 2134. This
Court has advanced the date of notification under sub-section (1) of section H
574 SUPREME COURT REPORTS (1993] SUPP. 2 S.C.R.
A 4 of the Act, in the cases referred to above, without assigning any reason,
as to how the date fixed by sections 11 and 23 or the Act, can be altered
for ascertainment of the market value of land. The power of this Court
under Article 142 is very wide and can be exercised in the ends of justice.
The scope of the said Article was recently examined in the case of Union
Carbide Corporation v. Union of India, AIR (1992) SC 248 = (1991) SCC
B
584.
There appears to be some force in the contention of the petitioners
that the object of respondents, was to peg the price of the lands acquired
from the different cultivators to a distant part and not .to proceed further
C because if the awards had been made soon after the declarations under
section 6, respondents had to pay or tender the compensation to the
claimants, which for some compulsion, respondents were not in a position
to pay or tender then. But, nonetheless, the exercise of power in the facts
and circumstances of the cases by the respondents have to be held to be
D against the spirit of the provisions of the Act, tending towards arbitrariness.
In such a situation this Court in exercise of power under Article 32 and
the High Court under Article 226, could have quashed the proceedings.
But, taking into consideration that in most of the cases, the Delhi Ad-
ministration and Delhi Development Authority have taken possession of
the lands and even developments have been made, it shall not .be proper
E execise of discretion on the part of this Court to quash the proceedings
because, in that event, it shall affect the public interest. Moreover, third
party interests created in the meantime are also likely to be affected and
such third parties are not impleaded. The relief of quashing the acquisition
proceeding having become inappropriate due to the subsequent events, the
grant of a modified relief, considered appropriate in the circumstances,
F
would be the proper course to adopt. The High Court or this Court, can
grant a modified relief taking into consideration the injury caused to the
claimants by the inaction on the part of respondents and direct payment
of any additional amount, in exercise of power under Article 226 or Article
32 of the Constitution.
G
We are of the view, that there was no justification on the part of the
respondents, for the delay in completion of the proceedings, after the
judgment of this Court in Aflatoon's case (supra) on 23rd August, 1974.
There is no explanation, except that there were several cases and, as such,
H in normal course, there was bound to be delay in making of the awards,
J
RAM CHAND v. U.O.I. [N.P. SINGH, J.] 575
This may have been acceptable if the delay was only in respect of some of A
the awards. It is an admitted position that till 1980, no award had been
made in respect of any of the acquisitions. As such, the respondents have
failed to satisfy that they have performed their statutory duty within a time
which can be held to be reasonable.
According to us. after the judgment of this Court inAflatoon's case B
(supra) on 23rd August, 1974, the reasonable time for making the awards
was about two years from that date. Beyond two years, the time taken for
making of the awards will be deemed to be unreasonable. As such, after
expiry of the expiry of the period of two years, some additional compensa-
tion has to be awarded to the cultivators. Taking into consideration the C
interest of the cultivators and the public, instead of quashing the proceed-
ings for acquisition, we direct that the petitioners shall be paid an addi-
tional amount of compensation to be calculated at the rate of twelve per
cent per annum, after expiry of two years form 23.1.1974, the date of the
judgment of this Court inAflatoon's case (supra) till the date of the making
of the awards by the Collector, to be calculated with reference to the D
market value of the lands in question, on the date of the notifications under
sub-section (1) of section 4.
Accordingly, the writ petitions and the civil appeal are allowed in
part to the extent indicated above. However, in the circumstances of the E
cases, there shall be no order as to costs.
U.M. Petitions allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.