Created byFuzzy Cloud

Supreme Court of India

PUNJAB STATE & ORS.versusDINA NATH

Citation
2007 INSC 570
Decided
14 May 2007
Disposal
Dismissed

Holding

Clause 4 of the Work Order is an arbitration agreement and the Section 20 application was filed within the limitation period.

Summary

The Punjab State issued a work order containing a clause that any dispute between the department and the contractor would be referred to the Superintending Engineer, whose decision would be final and binding. After the contractor completed the work, a dispute arose over final bills and measurements, and the contractor filed an application under Section 20 of the Arbitration Act, 1940 for appointment of an arbitrator. The trial court held that the clause constituted an arbitration agreement and that the application was filed within the three‑year limitation period prescribed by Article 137 of the Limitation Act, 1963. The appellate court reversed this view, holding that the clause was not an arbitration agreement and that the application was time‑barred; the High Court restored the trial court’s decision. The Supreme Court examined the definition of an arbitration agreement under Section 2(a) of the 1940 Act and held that the clause satisfied all the required ingredients, and that the limitation period began when the demand notice was served, making the application timely. Consequently, the Court dismissed the appeals, confirming the validity of the arbitration agreement and the appointment of an arbitrator.

Issues considered

  • Whether Clause 4 of the Work Order constitutes an arbitration agreement within the meaning of Section 2(a) of the Arbitration Act, 1940.
  • Whether the application for appointment of an arbitrator under Section 20 of the Arbitration Act, 1940 was barred by the limitation period under Article 137 of the Limitation Act, 1963.

Legislation cited

Subjects

arbitration agreementArbitration Act 1940Limitation Act 1963work order clauseSection 20 applicationfinal and binding decisionSuperintending Engineerdispute resolution

Judgment

A                              PUNJAB STA TE & ORS.
                                           v.
                                     DINA NATH

                                    MAY 14, 2007

B               [TARlJN CHATTERJEE AND ALTAMAS KABIR, JJ.]


           Arbitration Act. 1940-Sections 2(a) & 20-Limitation Act, 1963-
    Article 137-Contractor filing an application before trial court for                )-
    appointment of an arbitrator under a relevant clause of the Work Order to
c   settle dispute-State opposing the application contending that the relevant
    clause of the Work Order is not an arbitration agreement and that the
    application is barred by /imitation-Trial Court allowing the application of
    the contractor but reversed by the appellate court in State appeal-High
    Court upholding the judgment ofl'he trial court-Correctness of-Held, there
D   is no particular form of arbitration agreement-On facts, the relevant clause
    of the Work Order is an arbitration agreement and the application to appoint
    an arbitrator is not barred by /imitation-Hence, appointment of arbitrator
                                                                                       'T"
    is valid in law.

          Appellant-State issued a Work Order to respondent for a construction
                                                                                        •
E work. After completion of the work, the respondent issued a notice to prepare
   final bills and take final measurements for the purpose of payment under the
   Work Order. Due to a dispute regarding preparation of the final bills by the
   appellants, the respondent issued a notice to the appellants to refer the dispute
   is arbitration as per the relevant clause or the Work Order. Since the
F 'appellants failed to respond to the notice, the respondent filed an application
   under section 20 of the Arbitration Act, 1940 before trial Court seeking
   appointment of an arbitrator. The trial Court allowed the application               .,,..,.
   construing the relevant clause of the Work Order to be an 'arbitration
   agreement' under section 2(a) of the Act and holding that the application is
   not barred by limitation. The appellate Court allowed the State appeal A Civil
    !


G Revision Petition filed by the respondent was allowed by High Court.
           In appeal to this Court, the appellant contended that the relevant clause
     under the Work Order cannot be construed as an arbitration agreement; that
    lthe application is barred by limitation; and that there was no existence of any        ...
H                                         536
                                  PUNJAB STATE v. DINA NATH                              537
         dispute for reference to arbitration under the Work Order since it had got             A
         the work executed at its own cost when the respondent failed to execute the
         work under the Work Order.

               Dismissing the appeal, the Court

               HELD: I.I. A bare perusal of the definition of'arbitration agreement'            B
         under section 2(a) of the Arbitration Act, 1940 would clearly show that an
         arbitration agreement is not required to be in any particular form. What is
         required to be ascertained is whether the parties have agreed that if any
  --<'
         dispute arises between them in respect of the subject matter of the contract,
         such dispute shall be referred to arbitration. In that case such agreement             C
         would certainly spell out of an arbitration agreement. However, from the
         definition of the arbitration agreement, it is also clear that the agreement
         must be in writing and to interpret the agreement as an 'arbitration
         agreement' one has to ascertain the intention of the parties and also treatment
         of the decision as final. If the parties had desired and intended that a dispute
         must be referred to arbitration for decision and they would undertake to abide         D
         by that decision, there cannot be any difficulty to hold that the intention of the
         parties to have an arbitration agreement; that is to say, an arbitration
 >       agreement immediately comes into existences. [Para 8] (542-C, D, E)

               Rupmani Bai Gupta v. Collector of Jabalpur, AIR (1981) SC 479,
         referred to.                                                                           E
                1.2. The Work Order between the parties can be interpreted to be an
         arbitration agreement. The omission to mention the words "arbitration" and
                                    I
         "arbitrator" cannot be a ground to hold that the said clause was not an
         arbitration agreement within the meaning of Section 2(a) of the Act. The
         essential requirements are that the parties have intended to make a reference          F
---,.-   to. arbitration and treat the decision of the arbitrator as final. As the condition,
         to constitute an 'arbitration agreement' have been satisfied, the relevant clause
         of the Work Order must be construed to be an arbitration agreement and
         dispute raised by the parties must be referred to the arbitrator.
                                                   [Paras 9 and IOI (542-F; 543-A, B, CJ        G
              Bihar State Mineral Development Corporation v. Encon Building,
         [2003) 7 SCC 418; K.K. Modi v. K.N Modi, [1998) 3 SCC 573 and State of
         UP. v. Tippar Chand, (1980[ 3 SCC 241, referred to.

               1.3. The Work Order categorically states that the decision of the                H
    538                    SUPREME COURT REPORTS                    (2007] 6 S.C.R.

A Superintending Engineer shall be binding on the parties. The jurisdiction of
    the Superintending Engineer to decide the rights of the parties has also been
    derived from the consent of the parties to the Work Order. The agreement
    contemplates that the Superintending Engineer shall determine substantive
    rights of parties as the clause encompasses all varieties of disputes that may
B   arise between the parties amd does not restrict the jurisdiction of the
    Superintending Engineer to specific issues only. That the agreement of the
    parties to refer their disputes to the decision of the Superintending Engineer
    is intended to the enforceabl1e in law as it is binding in nature. The relevant
    Clause of the Work Order is an Arbitration Agreement. All the ingredients
    to hold a particular agreement as an arbitration agreement have been satisfied
C   in the present case. The relevant clause in the Work Order is wide in its
    ambit as it deals with any dispute between the contractor and the department.
    As the Superintending Engineer will decide the matter on reference, he has
    to act judicially and decide the dispute after hearing both the parties and
    permitting them to state their claim by adducing materials in support.
                                  [Paras 12, 13 and 191 [543-G; 544-C, F; 547-BI
D
         1.4. The use of the words 'any dispute' in the relevant Clause of the
                                                                                      T
  Work Order is wide enough to include all disputes relating to the said Word
  Order. Therefore, when a party raises a dispute for non-payment of money
  after completion of the work, which is denied by the other party, such a dispute
E would come within the meaning of 'arbitration agreement' between the parties.
  The relevant Clause of the Work Order also clearly provided that any dispute
  between the department and the contractor shall be referred to the
  Superintending Engineer for orders. The word 'orders' would indicate some
  expression of opinion, which is to be carried out or enforced and which is a
  conclusion of a body. Then again the conclusion and decision of the
F Superintending Engineer will be final and binding on both the parties. This
  being the position and since the relevant Clause of the Work Order is not
  under challenge, the decision that would be arrived at by Superintending
  Engineer must also be binding on the parties as a result whereof the relevant
  Clause must be held to be a binding arbitration agreement.
                                                 (Para 141 [544-G-H; 545-A, Bl
G
          State of Orissa v. Damodar Das, (199612 SCC 216, distinguished.

          Dewan Chand v. Stale of Jammu & Kashmir, AIR (1961) J&K 58,
    referred to.
H         1.5. The application under section 20 of the Arbitration Act, 1940 for
                      PUNJAB STATE 1>. DINA NATH [TARUN CHATTERJEE, J.)                 539
    ._      appointment of an arbitrator was filed with 3 years from the date of demand
            notice was made by the respondent under Article 137 of the Limitation Act,
                                                                                               A
            1963. The right to apply accrued for the difference arising between the parties
 I          only when services of demand notice was effective, which should be the date
            for holding that the difference had already arisen between the parties. Hence,
            the application under section 20 of the Arbitration Act was clearly filed within
            the period of limitation. (Paras 22 and 261 (547-G; 548-G-H; 549-AI
                                                                                               B

                 S. Rajan v. State of Kera/a, (1992) 3 SCC 608 and Hari Shankar
            Singhania & Ors. v. Gaur Hari Singhania & Ors., (20061 4 SCC 658, referred
 '· -{      to.

                  CIVIL APPELLATE JURISDICTION: Civil Appeal No. 5197 of2000.
                                                                                               c
                 From the Final Judgment and Order dated 05.08.1999 of the High Court
            of Punjab and Haryana at Chandigarh in Civil Revision No. 3547of1997.

                                                   WITH                                        D
                  C.A. No. 5198 of2000.
       ~
                 R.K. Rathore, AAG., Pb., M.K. Verma, Aron K. Sinha, Harinder Mohan
       )>
            Singh and Kaushal Yadav for the Appellants.

                  Manoj Swarup for the Respondent.
                                                                                               E

                  Rr-Ex-parte

                  The Judgment of the Court was delivered by

                  T ARUN CHATTERJEE, J. l. The crucial question that needs to be               F
            decided in these appeals is whether Clause 4 of Work Order No.114 dated 16th
y           of May, 1985 (in short 'Work Order') which says that: "Any dispute arising
            between the department and the contractor/society shall be referred to the
            Superintending Engineer, Anandpur Sahib, Hyde! Circle No. I Chandigarh for
            orders and his decision will be final and acceptablelbinding on both the           G
            parties" constituted an arbitration agreement.

                   2. Before proceeding further, we may bring it on record that though the
            facts in both the appeals are identical, but for purposes of disposal of these
.,._
            appeals, the facts in CA No. 5197 are being considered which are as follows:
                                                                                               H
        540                SUPREME COURT REPORTS                    [2007] 6 S.C.R.

A        3. The parties entered into a contract for the work of dowel drain and
  wire crate at RD No. 9400 to l 0400 kms. in the State of Punjab. The appellants
  made running payments to the respondent during the period of execution of
  the works in terms of the Work Order. However, after completion of the work,
  the final measurements were no1t made, nor the final bills were prepared. The
  dispute remained pending with the department for which the respondent
B called upon the appellants to finalise the dispute and prepare the final bill as
  per the rates quoted by the respondent and accepted by the appellants. A
  final notice was issued on 16th April, 1990, calling upon the appellants to refer
  the dispute to an arbitrator as per Clause 4 of the Work Order. Since the
  appellants had failed to appoint an Arbitrator, the respondent filed an
C application before the Additional Senior Subordinate Judge, Ropar, Punjab
                                                                                      ~   -
  under Section 20 of the Arbitration Act, 1940 (in short 'the Act') seeking
  appointment of an Arbitrator.

          4. By an order dated 20th October, 1993 the learned Additional Senior
   Subordinate Judge, Ropar, Punjab after hearing both the parties, allowed the
D application filed by the respondent and referred the dispute for decision to
   the Superintending Engineer, Anandpur Sahib, Hyde! Circle No. I Chandigarh.
   The Additional Senior Subordinat1~ Judge, Ropar, while allowing the application,
                                                                                      T
   held that Clause 4 of the Work Order must be construed to be an arbitration
   agreement within the meaning of Section 2(a) of the Act and that the application
E filed under Section 20 of the Act was filed within the period of limitation.
   According to the learned Additional Senior Subordinate Judge, Ropar, the
   cause of action arose from the date the final notice of demand was sent, i.e.,
   16th April 1990, which was well within the period of 3 years from the date of
   filing the application as contemplated under Article 137 of the Limitation Act
   1963. Feeling aggrieved by the aforesaid order, the appellants preferred an
F appeal in the Court of the District Judge, Roopnagar, Punjab, which by an
   order dated 24th April, 1997 was allowed, inter a!ia, on a finding that Clause
   4 of the Work Order could not be held to be an 'arbitration agreement' nor
   the dispute was covered within the ambit of the Act. On the question of
 , limitation in filing the application under Section 20 of the Act, the appellate
G court held that the application under Section 20 of the Act was barred by
    1




   limitation. Feeling aggrieved by the order of the learned Additional District
   Judge, Roopnagar, Punjab, reversing the order of the Additional Senior
   Subordinate Judge, Ropar, the respondent filed a Civil Revision Case before
   the High Court of Punjab and Haryana at Chandigarh, which by the impugned
   order was allowed and the order of the Additional Subordinate Judge, Ropar
H was restored. Dissatisfied with this order of the High Court, a special leave
          PUNJAB STATE v. DINA NATH [T ARUN CHATTERJEE, J.]                  541
petition was filed by the appellants, which on grant of leave was heard in the A
presence of the learned counsel for the parties.

       5. Having heard the learned counsel for the parties and after going
through the impugned order of the High Court as well as the orders of the
appellate court and the trial court and the materials on record and considering
the clauses in the Work Order, we are of the view that the High Court was           B
fully justified in setting aside the order of the appellate court and restoring
the order of the Additional Subordinate Judge by which the dispute was
referred to arbitration for decision. Before proceeding further, we may, however,
take note of some of the relevant clauses in the Work Order which read as
under: -                                                                            c
        "Clause 13 of the Work Order: - "If the contractor does not carry out
        the work as per the registered specifications, the department will have
        the option to employ its own labour or any other agency to being the
        work to the departmental specification and recover the cost therefrom."

        Clause 4: "Any dispute arising between the department and the D
        contractor/society sh.all be referred to the. Superintending Engineer,
        Anandpur Sahib, Hyde! Construct Circle No. I, Chandigarh for orders
        and his decision will be final and acceptable/binding on both parties."

      6. As pointed out herein earlier, the trial court on consideration of E
Clause 4 of the Work Order held that Clause 4 of the Work Order must be
held to be an arbitration agreement and accordingly an arbitrator was appointed
in compliance with Clause 4 of the Work Order At this stage we feel it
appropriate to examine in detail whether clause 4 of the Work Order can be
held to be an arbitration agreement within the meaning of Section 2(a) of the
A~                                                                                  F
      7. Section 2[a] of the Act defines 'arbitration agreement' which means
a written agreement to submit present or future differences to arbitration
whether arbitrator is named therein or not. Mr. Tathore learned Additional
Solicitor General appearing on behalf of the appellants contended that although
the Work Order was allotted to the respondent on 16th May, 1985, the G
respondent had failed to execute the work allotted to him and the appellants
had got the work executed at its own cost in terms of clause 13 of the Work
Order which, as noted herein earlier, provides that in case the contractor does
not execute the allotted work, the department could get the same executed by
other agencies or by itself. He further contended that owing to such failure H
        542                     SUPREME COURT REPORTS                     [2007] 6 S.C.R.

A on the part of the respondent, final bills were not prepared nor were the final           -'.:
  measurements taken for the purpose of payment to the respondent. Accordingly,
  Mr. Tathore contended that there was no existence of any dispute and
  accordingly the question of referring such disputes in terms of Clause 4 of
  the Work Order could not arise at all. This submission of Mr. Tathore was
B contested by the learned counsel for the respondent. Therefore, a dispute
  arose as to whether the respondent had completed the work allotted to him
  under the Work Order. This is an issue, according to the High Court as well
  as the Subordinate Court, which should be referred for decision to an arbitrator.

              8. A bare perusal of the definition of arbitration agreement would clearly
C show that an arbitration agreement is not required to be in any particular form.
        What is required to be ascertained is whether the parties have agreed that
                                                                                                   -
        if any dispute arises between them in respect of the subject matter of the
        contract, such dispute shall be referred to arbitration. In that case such
        agreement would certainly spell out an arbitration agreement. [See Rupmani
        Bai Gupta v. Collector of Jabalpur, AIR (1981) SC 479] However, from the
D       definition of the arbitration agreement, it is also clear that the agreement must
        be in writing and to interpret the agreement as an 'arbitration agreement' one
        has to ascertain the intention of the parties and also treatment of the decision
        as final. If the parties had desired and intended that a dispute must be referred
        to arbitration for decision and they would undertake to abide by that decision,
E       there cannot be any difficulty to hold that the intention of the parties to have
        an arbitration agreement; that is to say, an arbitration agreement immediately
        comes into existence.

        9. In the case of Bihar State Mineral Development Corporation v.
  Encon Building, (2003] 7 SCC 418, this Court held that "there is no dispute
p with regard to the proposition that for the purpose of construing an arbitration
  agreement, the term "arbitration" is not required to be specifically mentioned
  therein." Looking to the opinion of the Hon 'ble Judges in the said case and
  also considering clause 4 of the Work Order in depth, we are of the opinion
  that Clause 4 of the Work Order between the parties can be interpreted to be
  an arbitration agreement even though the term "arbitration" is not expressly
G mentioned in the agreement. In this decision of this Court the test of 'dispute'
    1




  and 'reference' was again reiterated. In Para 17, it was stated that there cannot
  be any doubt whatsoever that an arbitration agreement must contain broad
  consensus between the parties that the disputes and differences should be
  referred to a domestic tribunal.
H
            PUNJAB STATE v. DINA NA TH [TARUN CHATTERJEE, J.]                 543
        10. We have already noted Clause 4 of the Work Order as discussed            A
hereinabove. It is true that in the aforesaid Clause 4 of the Work Order the
 words "arbitration" and "arbitrator" are not indicated; but in our view, omission
to mention the words "arbitration" and "arbitrator" as noted herein earlier
cannot be a ground to hold that the said clause was not an arbitration
agreement within the meaning of Section 2[a] of the Act. The essential
requirements as pointed out herein earlier are that the parties have intended        B
to make a reference to an arbitration and treat the decision of the arbitrator
as final. As the conditions to constitute an 'arbitration agreement' have been
satisfied. we hold that clause 4 of the Work Order must be construed to be
an arbitration agreement and dispute raised by the parties must be referred
to the arbitrator. In the case of K.K. Modi v. K.N. Modi [I998] 3 SCC 573, this      C
Court had laid down the test as to when a clause can be construed to be an
arbitration agreement when it appears from the same that there was an
agreement between the parties that any dispute shall be referred to the
arbitrator. This would be clear when we read Para 17 of the said judgment and
points 5 and 6 of the same which read as under:
                                                                                     D
            "5. That the agreement of the parties to refer their disputes to the
        decision of the tribunal must be intended to be enforceable in law;
        and

            6. Agreement must contemplate that the tribunal will make a
        decision upon a dispute, which is already formulated at the time when        E
        reference is made to tribunal."

      11. That apart, in Para 23 of the decision in the case of K. K. Modi
(supra), this Court also noticed its earlier decision in the case of State of U.P.
v. Tippar Chand, [1980] 3 SCC 241. In that case, the test as indicated above
was also recorded in which it was stated that "this court said that there was F
no mention in this clause in any dispute much less any reference thereof."

      12. Keeping the ingredients as indicated by this Court in the case of K.
K. Modi (supra) in mind for holding a particular agreement as an arbitration
agreement, we now proceed to examine the aforesaid ingredients in the context        G
of the present case.

     (a) Clause 4 of the Work Order categorically states that the decision of
the Superintending Engineer shall be binding on the parties.

     (b) The jurisdiction of the Superintending Engineer to decide the rights        H
     544                     SUPREME COURT REPORTS                    [2007) 6 S.C.R.

A of the parties has also been derived from the consent of the parties to the
     Work Order.

           (c) The agreement contemplates that the Superintending Engineer shall
    determine substantive rights of parties as the clause encompasses all varieties
    of disputes that may arise between the parties and does not restrict the
B   jurisdiction of the Superintending Engineer to specific issues only.

           (d) That the agreement of the parties to refer their disputes to the
    decision of the Superintending Engineer is intended to be enforceable in law
    as it is binding in nature.

C         13. In view of the aforesaid conditions being satisfied, which were
    based on the principles laid down by this Court in K.K. Modi's case (supra),
  there cannot be any doubt in our mind that the arbitration agreement does
  exist. Clause 4 of the Work Order is an Arbitration Agreement. The learned
  Counsel appearing on behalf of the appellants contended that the ingredients
D laid down in the case of K.K. Modi are not satisfied in the present case and
  therefore following the principles laid down in that case, this Court must hold
  that clause 4 of the Work order cannot be construed as an arbitration agreement.
  We are unable to accept this contention of the learned counsel of the
  appellants for two reasons. First, in view of our discussions herein earlier, to
  the effect that all the ingredients to hold a particular agreement as an arbitration
E agreement have been satisfied in the preset case. Secondly, the factual
  situations in the case of K.K. Modi (supra) and in the case before us are very
  1different. That case dealt with the !~valuation and distribution of assets, which
  required expert decision rather than arbitration. The clause in the K.K. Modi
  case (supra) had a very restricted operation as it dealt with only disputes
F regarding implementation of contract whereas, in the case before us, Clause
  4 is much wider in its ambit as it deals with any dispute between the contractor
  l!lld the depa1tment.

          14. The words "any dispute'' appears in Clause 4 of the Work Order.
    Therefore only on the basis of the materials produced by the parties in
G   support of their respective claims a decision can be arrived at in resolving the
    ~ispute between the parties. The use of the words 'any dispute' in Clause
    4of the Work Order is wide enough to include all disputes relating to the said
    Work Order. Therefore, when a party raises a dispute for non-payment of
    money after completion of the work, which is denied by the other party, such
    a dispute would come within the meaning of 'arbitration agreement' between
H   fie parties. Clause 4 of the Work Order also clearly provides that any dispute
                PUNJAB STATE v. DINANATH[TARUNCHATTERJEE,J.]                    545
    - between the department and the contractor shall be referred to the A
       Superintending Engineer, Hyde! Circle No. I, Chandigarh for orders. The word
       'orders' would indicate some expression of opinion, which is to be carried out,
      or enforced and which is a conclusion of a body (in this case Superintending
      Engineer, Hyde! Circle No. I, Chandigarh). Then again the conclusion and
      decision of the Superintending Engineer will be final and binding on both the B
      parties. This being the position in the present case and in view of the fact
      that Clause 4 of the Work Order is not under challenge before us, the decision
      that would be arrived at by Superintending Engineer, Hyde! Circle No. I,
      Chandigarh must also be binding on the parties as a result whereof Clause
      4 must be held to be a binding arbitration agreement.

              15. In the decision of this Court in the case of State of UP v. Tippar
                                                                                        c
       Chand (supra), this Court however held that the clause in dispute in that
       decision between the parties did not amount to an arbitration agreement. In
       that decision, this Court further held that clause under consideration before
      them which provided that except where otherwise specified in the contract the
       decision of the Superintending Engineer for the time being shall be final,       D
      conclusive and binding on all the parties to the contract upon all questions
~      relating to the meaning of the specifications etc and the decision of the
       Superintending Engineer as to the quality, workmanship etc. shall be final,
       conclusive and binding between the parties does not constitute an arbitration
       agreement but while arriving at such a conclusion this Court referred to a       E
      decision of the Jammu and Kashmir High Court in the case of Dewan Chand
      v. State of Jammu and Kashmir, AIR (1961) J & K 58. Jn the Dewan Chand
      case (supra) the relevant clause runs as follows:- "For any dispute between
      the contractor and the Department the decision of the Chief Engineer PWD
      Jammu and Kashmir, will be final and binding upon the contractor. This Court
      in that decision had put strong reliance on the expression "any dispute           F
      between the contractor and the department" and approved the conclusions
      arrived at by the J & K High Court. It came to the conclusion by interpretation
      of that clause that there did not exist any arbitration agreement as the
      decision of the Superintending Engineer in connection with the work done by
      the contractor was meant for supervision and execution of the work and
      administrative control over it from time to time. However, in Clause 4 of the     G
      Work Order in the present case, which specifically states that in case of any
      dispute between the appellants and the contracting parties, the matter shall
      be referred to the Superintending Engineer. Therefore, the use of the words
      "any dispute" would clearly mean that it would lead to conclude that the said
      agreement was in fact an arbitration agreement and thus these words do not        H
    546                    SUPREME COURT REPORTS                    [2007] 6 S.C.R.

A restrict the scope of the contract.
           16. Before parting with this aspect of the matter we may note the
    decision of State of Orissa v. Damodar Das, [1996] 2 SCC 216 on which strong
    reliance was placed before us by the! learned counsel for the appellants. This
    decision of this court may not be helpful to the appellants as we find the
B   agreement in question in that case was different from Clause 4 of the Work
    Order. For proper appreciation, we may reproduce the agreement in the case
    of Damodar Das which reads as under:-

                 "25. Decision of Public Health Engineer to be final - Except where   ,..
            otherwise specified in this contract, the decision of the Public Health
c           Engineer for the time being shall be final, conclusive and binding on
            all parties to the contract upon all questions relating to the meaning
            of the specifications; drawings and instructions hereinbefore mentioned
            and as to the quality of workmanship or materials used on the work,
            or as to any other question, claim, right, matter or thing, whatsoever
D           in any way arising our of, or relating to, the contract, drawings
            specifications estimates, instructions, orders or these conditions, or
            otherwise concerning the works or the execution or failure to execute
            the same, whether arising during the progress of the work or after the
            completion or the sooner determination thereof of the contract."

E        17. A plain reading of this c:Jause in the case of Damodar Das, it is
  ¢vident that the powers of the Public Health Engineer were essentially to
  ~upervise and inspect. His powers were limited to the questions relating to
  ~he meaning of the specifications; drawings and instructions, quality of
  '!Vorkmanship or materials used on the work, or any other question, claim,
F tight, matter, drawings specifications estimates_, instructions, orders or these
  ¢onditions, or otherwise concerning the works or the execution or failure to
  execute the same. However, in the case before us, the Superintending Engineer
  was given full power to resolve any dispute arising between the parties which
  power in our view is wide enough to cover any nature of dispute raised by
  the parties. The Clause in the instant case categorically mentions the word
G "dispute" which would be referred to him and states "his decision would be
  final and acceptable/binding on both the parties."

           18. That being the position, we are of the view that the clause in the
    case ofDamodar Das and Clause 4 of the Work Order of the present case are
    totally different. We accordingly do not find any reason to hold otherwise.
H
                     PUNJAB STATE v. DINANATH[TARUNCHATTERJEE,J.]                     547
--">-'
                 19. At the risk of repetition we may also say before parting with this A
          judgment that Clause 4 of the Work Order speaks for a dispute between the
          parties. It also speaks of a dispute and all such disputes between the parties
          to the Work Order shall be decided by the Superintending Engineer, Anandpur
          Sahib Hydel Circle No. I. Obviously, such decision can be reached by the
          Superintending Engineer, Anandpur Sahib Hydel Circle No. I only when it is
          referred to him by either party for decision. The reference is also implied. As B
          the Superintending Engineer will decide the matter on reference, there cannot
)         be any doubt that he has to act judicially and decide the dispute after hearing
     -{   both the parties and permitting them to state their claim by adducing materials
          in support. In Clause 4 of the Work Order it is also provided as noted herein
          earlier that the decision of the Superintending Engineer shall be final and such   c
          agreement was binding between the parties and decision shall also bind both
          the parties. Therefore, the result would be that the decision of the
          Superintending Engineer would be finally binding on the parties. Accordingly,
          in our view, as discussed herein above that although the expression "award"
          or "arbitration" does not appear in Clause 4 of the Work Order even then such
          expression as it stands in Clause 4 of the Work Order embodies an arbitration D
    ,.    clause which can be enforced.

                 20. For the reasons aforesaid, we are of the view that Clause 4 of the
          Work Order can safely be interpreted to be an arbitration agreement even
          though the term 'arbitration' is not expressly mentioned in the agreement. In
                                                                                         E
          view of our discussions made herein earlier, we therefore conclude that Clause
          4 of the Work Order constitutes an arbitration agreement and if any dispute
          arises, such dispute shall be referred to Superintendent Engineer for decision
          which shall be binding on the parties.

                 21. Before parting with this judgment, we may consider a short F
'r        submission advanced at the Bar on the question of limitation in filing the
          application under· Section 20 of the Act. At the risk of repetition, we may keep
          it on record that the Additional Senior Subordinate Judge, Ropar, held that
          the application was filed in time whereas the appellate court held that the
          application was barred by limitation. However, the High Court in revision
          restored the order of the Additional Senior Subordinate Judge, Ropar, by G
          holding that application was filed within the period of limitation.

•·              22. For the purpos.: of deciding the question of limitation, it may be
          stated that the application under Section 20 of the Act was filed within 3 years
          from the date the demand notice was made by the respondent as contemplated
                                                                                             H
    548                     SUPREME COURT REPORTS                     [2007) 6 S.C.R.

A under Article 13 7 of the Limitation Act.
          23. In order to determine wh1:n the cause of action arose, it is essential
    for us to refer to a case decided by this court. In the case of S. Rajan v. State
    of Kera/a, [1992] 3 SCC 608 it was held by this Court that the right to apply
    for arbitration proceeding under Section 20 of the Arbitration Act, 1940 runs
B   from the date when the dispute arises. It observed:

                 "Reading Article 13 7 and Sub-section (I) of Section 20 together,
            it must be said that the right to apply accrues when the difference         ,..
            arises or differences arise, as the case may be, between the parties.
            It is thus a question of fact to be determined in each case having
c           regard to the facts of that case."

        24. Accepting the principles laid down in the case of S. Rajan (supra),
  this Court in the case of Hari Shankar Singhania and Ors. v. Gaur Hari
  Singhania and Ors., (2006] 4 SCC 658 again reiterated the principle that an
  application under section 20 of the Act for filing the arbitration agreement in
D ~ourt and for reference of the dispute to arbitration in accordance therewith
  i~ required to be filed within a period of three years when the right to apply         T


  accrues and that the said right accrues when difference or dispute arises
  between the parties to the arbitration agreement. Keeping the principles in
  mind, let us now examine as to when difference or dispute arises between the
E parties to the arbitration agreement, when the right to apply accrues. As
  r)oted herein earlier, demand notice was served on the appellants by the
  respondent on 16th April 1990 and the application under section 20 of the Act
  was filed on 13th November 1990 which is admittedly within the period of
  limitation as contemplated under Article 137 of the Limitation Act.

F         25. The Additional District judge, Roopnagar, Punjab, held on the
    question oflimitation in filing the application under section 20 of the Act that          -<
    the cause of action did not arise when notice of demand was served but arose
    when the respondent first acquired either the right of action or the right to
    require that arbitration takes place upon the dispute concerned.
G        26. Keeping the decisions of this court in the cases of S. Rajan (supra)
  and Hari Shankar Singhania (supra) in mind, in our opinion, the view of the
  Additional District Judge was totally erroneous. In the aforesaid two decisions,
  it was held that the right to apply accrued for the difference arising between               ..
  the parties only when service of demand notice was effective, which should
H be  the date for holding that the difference had already arisen between the
                   PUNJAB STATE v. DINANATH[TARUNCHATTERJEE.J.)                    549
         parties. Such being the settled law, we are of the view that the application     A
         under section 20 of the Act was clearly filed within the period of limitation.

              27. Forthe reasons aforesaid we do not find any merit in these appeals.
         Accordingly, the appeals are disposed of with no orders as to cost.

         B.S.                                                  Appeals dismissed of.      B




-   Jr


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "arbitration agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.