Created byFuzzy Cloud

Supreme Court of India

PATEL ENGINEERING LTD.versusNORTH EASTERN ELECTRIC POWER CORPORATION LTD. (NEEPCO)

Citation
2020 INSC 403
Decided
22 May 2020
Disposal
Dismissed

Holding

The Supreme Court held that the High Court correctly applied the law, the arbitral awards are perverse and may be set aside under Section 34(2A), and the review petitions are not maintainable, leading to dismissal of the Special Leave Petitions.

Summary

Patel Engineering Ltd. challenged three arbitral awards dated 29‑03‑2016 concerning payment for extra lead under a contract with North Eastern Electric Power Corporation Ltd. (NEEPCO). NEEPCO filed applications under Section 34 of the Arbitration and Conciliation Act, 1996; the Additional Deputy Commissioner upheld the awards, but the High Court set them aside on appeal under Section 37, holding the awards were patently illegal and perverse. The Supreme Court dismissed the Special Leave Petitions filed by Patel Engineering and, on review of the High Court’s order, affirmed that the High Court correctly applied the post‑2015 amendment (Section 34(2A) – patent illegality) and that the awards were indeed perverse. Consequently, the review petitions were held non‑maintainable and the Special Leave Petitions were dismissed.

Issues considered

  • Whether the High Court was correct in setting aside the arbitral awards on the ground of patent illegality/perversity under Section 34(2A) of the Arbitration and Conciliation Act, 1996.
  • Whether a review petition filed after the dismissal of a Special Leave Petition is maintainable.
  • Whether the amendment Act of 2015 (effective 23‑10‑2015) applies to the awards dated 29‑03‑2016.

Legislation cited

Subjects

ArbitrationSection 34Patent illegalityPerverse awardReview petitionSpecial Leave PetitionAmendment Act 2015Public policyUnjust enrichment

Judgment

156                      [2020]REPORTS
               SUPREME COURT    4 S.C.R. 156               [2020] 4 S.C.R.


A                        PATEL ENGINEERING LTD.
                                        v.
                   NORTH EASTERN ELECTRIC POWER
                     CORPORATION LTD. (NEEPCO)
B             (Special Leave Petition (C) Nos. 3584-3585 of 2020)
                                 MAY 22, 2020
                  [R. BANUMATHI, INDU MALHOTRA
                      AND ANIRUDDHA BOSE, JJ.]
             Arbitration and Conciliation Act, 1996 – ss. 34 and 37 – The
C
      respondent-North Eastern Electric Power Corporation Ltd.
      (NEEPCO) filed three applications u/s. 34 of the Act, 1996
      challenging the three arbitral awards dated 29.03.2016 – The
      Additional Deputy Commissioner (Judicial) vide common judgment
      dated 27.04.2018 rejected the applications and upheld the three
D     arbitral awards – The respondent-NEEPCO filed appeals u/s. 37 of
      the Act, 1996 before the High Court and the same were allowed by
      judgment dated 26.02.2019 and the judgment dated 27.04.2018
      passed by the Additional Deputy Commissioner was set aside –
      Aggrieved, the petitioner preferred Special Leave Petitions, which
      were dismissed – After the dismissal of the SLPs, the petitioner filed
E
      review petitions before the High Court on the ground that the
      judgment of the High Court dated 26.02.2019 suffered from error
      apparent on the face of the record – The said review petitions were
      dismissed by the High Court by order dated 10.10.2019 – On appeal,
      held: In the instant case, the High Court in its judgment dated
F     26.02.2019 has referred to the Supreme Court judgment in Associated
      Builders at length and arrived at the correct conclusion that an
      arbitral award can be set aside u/s. 34, if it is patently illegal or
      perverse – This finding of the High Court was in conformity with
      the Supreme Court judgment in Ssangyong Engineering – The High
      Court held that no reasonable person could have arrived at a
G
      different conclusion while interpreting clauses 2.7 and 3.4 of the
      BoQ and clauses 32(ii) (a) 33(iii) of the conditions of contract –
      The case was decided on the ground that the arbitral award is a
      perverse award and on a holistic reading of all the terms and
      conditions of the Contract, the view taken by the Arbitrator is not
H
                                       156
 PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                      157
         POWER CORPORATION LTD. (NEEPCO)

even a possible view – The view of the High Court was correct –        A
Thus, the High Court rightly dismissed the review petitions by the
impugned order dated 10.10.2019 – Resultantly, all the Special Leave
Petitions are dismissed.
      Ssangyong Engineering and Construction Company
      Limited v. National Highways Authority of India (NHAI)           B
      (2019) 15 SCC 131 : [2019] 7 SCR 522; Associate
      Builders v. Delhi Development Authority (2015) 3 SCC
      49; [2014] 13 SCR 895 – relied on.
      Bussa Overseas and Properties Private Limited and
      Another v. Union of India and Another (2016) 4 SCC               C
      696 : [2016] 1 SCR 266; Durga Shankar Mehta v.
      Thakur Raghuraj Singh and Others [1955] 1 SCR 267;
      Shanker Motiram Nale v. Shiolalsing Gannusing Rajput
      (1994) 2 SCC 753; Thungabhadra Industries Ltd. v.
      Government of Andhra Pradesh Represented by the
      Deputy Commissioner of Commercial Taxes, Anantapur               D
      [1964] 5 SCR 174; Oil & Natural Gas Corporation
      Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 : [2003] 3
      SCR 691; Oil & Natural Gas Corporation Ltd. v. Western
      Geco International Limited (2014) 9 SCC 263 : [2014]
      12 SCR 1; HRD Corporation (Marcus Oil and                        E
      Chemical Division) v. GAIL (India) Limted (2018) 12
      SCC 471: [2017] 11 SCR 857; Board of Control for
      Cricket in India v. Kochi Cricket Private Limited and
      Others (2018) 6 SCC 287 : [2018] 2 SCR 829 –
      referred to.
                                                                       F
                      Case Law Reference
[2016] 1 SCR 266               referred to            Para 8
[1955] 1 SCR 267               referred to            Para 8
(1994) 2 SCC 753               referred to            Para 8
                                                                       G
[1964] 5 SCR 174               referred to            Para 10
[2003] 3 SCR 691               referred to            Para 13
[2014] 12 SCR 1                referred to            Para 13
[2017] 11 SCR 857              referred to            Para 13          H
158            SUPREME COURT REPORTS                          [2020] 4 S.C.R.


A     [2019] 7 SCR 522                 relied on                 Para 13
      [2018] 2 SCR 829                 referred to               Para 15
      [2014] 13 SCR 895                relied on                 Para 17
             CIVIL APPELLATE JURISDICTION: Special Leave Petition
B     (Civil) Nos. 3584-3585 of 2020.
            From the Judgment and Order dated 10.10.2019 of the High Court
      of Meghalaya at Shillong in Review Petition No. 16 of 2019 and MC
      (Review Petition) No. 14 of 2019 respectively.
            With
C
            Special Leave Petition (Civil) Nos. 3438-3439, 3434-3435 of 2020.
            Tushar Mehta, SG, Harish Salve, Neeraj Kishan Kaul, Huzeffa
      Ahmadi, Sr. Advs., Syed Jafar Alam, Ketan Gaur, Ashish Bhan, Rajendra
      Dangwal, Mohit Rohatgi, Aayush Mitruka, Deepak Joshi, Ms. Liz Mathew,
      Advs. for the appearing parties.
D
            The following Order of the Court was passed:
                                    ORDER
             1. These special leave petitions arise out of the impugned order
      dated 10.10.2019 passed by the High Court of Meghalaya at Shillong in
E     and by which the High Court declined to entertain the review petitions
      filed by the petitioner seeking review of the judgment and order dated
      26.02.2019 in Arbitration Appeal Nos.3, 4 and 5 of 2018 on the ground
      that no ground for review is made out and that there is a delay in filing
      the application for review.
F            2. We have heard Mr. Harish Salve and Mr. Neeraj Kishan Kaul,
      learned Senior counsel appearing on behalf of the petitioner. On behalf
      of the respondent, we have heard Mr. Tushar Mehta, learned Solicitor
      General and Mr. Huzeffa Ahmadi, learned Senior counsel at some length,
      even at the time of the admission.
G           3. The learned sole arbitrator has passed the arbitral award dated
      29.03.2016 in respect of Package-I holding as follows:-
                  “Based on my findings above, I have no hesitation in
            coming to the considered finding that the contract itself
            provides rate(s) for payment of extra lead in item Nos.2.7
H           and 3.4 of the BOO for surface and underground structures
 PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                             159
         POWER CORPORATION LTD. (NEEPCO)

      respectively. Admittedly material had been transported from             A
      a lead much longer than that envisaged at the time of award
      of work in favour of the claimant. It is also an admitted case
      of the parties that the claimant is entitled to extra payment
      for the extra lead. The only point at issue is whether Clause
      33(ii)(a) or Clause 33(iii) would be applicable for working
                                                                              B
      out the rate payable for transportation. In view of my findings,
      I have no hesitation in holding that the payment of extra lead
      is to be determined in accordance with Clause 33(ii)(a) for
      the item which has deviated being already available in the
      contract.
             I, therefore, answer the reference as follows:                   C

             The rate for extra lead for transportation of sand and
      boulders from Government approved quarries to the work
      site for package-I works under KaHEP shall be decided in
      terms of Clause 33(ii)(a) of Part-III, Volume-I, Conditions of
      Contract of Book-II of Contract Agreement No.NEEPCO/ED/                 D
      QP/C&P/R/C/KaHEP/560 of 2004-05 dated 17.12.2004.”
        Similar Declaratory Arbitral Awards dated 29.03.2016 were
passed by the learned sole arbitrator in respect of the other two Arbitral
References in respect of contracts pertaining to Package-II and Package-
III of the project.                                                           E

       4. Respondent-North Eastern Electric Power Corporation Ltd.
(NEEPCO) filed three applications under Section 34 of the Arbitration
and Conciliation Act, 1996 before the Additional Deputy Commissioner
(Judicial), Shillong challenging the three arbitral awards dated 29.03.2016
in respect of Packages-I, II and III. The Additional Deputy Commissioner      F
(Judicial) vide common judgment dated 27.04.2018 rejected the
applications under Section 34 of the Act and upheld all the three arbitral
awards. The respondent-NEEPCO filed three appeals under Section 37
of the Act before the High Court in Arbitration Appeal No(s).3, 4 and 5
of 2018. By the common judgment dated 26.02.2019, the High Court              G
allowed the respondent’s appeals and set aside the common judgment
dated 27.04.2018 passed by the Additional Deputy Commissioner
(Judicial).
       5. Aggrieved by the common judgment dated 26.02.2019, the
petitioner preferred special leave petitions before the Supreme Court in
                                                                              H
160             SUPREME COURT REPORTS                               [2020] 4 S.C.R.


A     SLP (C) Nos.13629-13631 of 2019. After hearing both the parties, the
      Supreme Court vide order dated 19.07.2019 dismissed all the three SLPs
      filed by the petitioner holding that the Court is not inclined to interfere in
      the matters.
              6. After dismissal of the SLPs, the petitioner filed review petitions
B     before the High Court on the ground that the judgment of the High Court
      dated 26.02.2019 suffers from error apparent on the face of the record
      as it had not taken into consideration the amendments made to Arbitration
      and Conciliation Act, 1996 by Amendment Act of 2015. The said review
      petitions came to be dismissed by the High Court vide the impugned
      orders.
C
             7. We heard the matter at some length at the time of admission
      and carefully considered the submissions of the learned counsel appearing
      for the parties and the judgments relied upon by both the sides and the
      judgment of the High Court dated 26.02.2019 and other materials on
      record.
D
              8. Contention of the learned Senior counsel for the petitioner is
      that dismissal of the earlier SLP vide order dated 19.07.2019 is a non-
      speaking order and not on merits and hence no objection could be taken
      for filing of the review petition. Placing reliance upon Bussa Overseas1
      and Constitution Bench decisions in Durga Shankar Mehta2, it was
E     submitted that Article 136 of the Constitution confers on the Supreme
      Court special or residuary powers which are exercisable outside the
      purview of the ordinary laws in cases where the needs of justice demand
      interference by the Supreme Court. It was submitted that in paragraph
      (30) of Bussa Overseas3, the Supreme Court held that though the decision
F     in Shanker Motiram Nale4 referred to Order 47 Rule 7 of the Code of
      Civil Procedure bars an appeal against the order of the court rejecting
      the review, it is not to be understood that the court has curtailed the
      plenary jurisdiction under Article 136 of the Constitution by taking recourse
      to the provisions in the Code of Civil Procedure.

G
      1
        Bussa Overseas and Properties Private Limited and Another v. Union of India and
      Another (2016) 4 SCC 696
      2
        Durga Shankar Mehta v. Thakur Raghuraj Singh and Others (1955) 1 SCR 267
      3
        Bussa Overseas and Properties Private Limited and Another v. Union of India and
      Another (2016) 4 SCC 696
      4
H       Shanker Motiram Nale v. Shiolalsing Gannusing Rajput (1994) 2 SCC 753
    PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                                161
            POWER CORPORATION LTD. (NEEPCO)

      9. Mr. Tushar Mehta, learned Solicitor General also relied upon               A
Bussa Overseas5and contended that the appeal is not maintainable
against the order rejecting the application for review of judgment and
such appeal is not against the main judgment. In support of his contention,
learned Solicitor General has placed reliance upon paragraph (22), which
reads as under:-
                                                                                    B
       “22. Recently in Sandhya Educational Society vs. Union of
       India (2014) 7 SCC 701, the Court referred to the decision in
       Vinod Kapoor vs. State of Goa (2012) 12 SCC 378 and opined
       thus: (SCC p. 706, para 16)
           “16. This Court in Vinod Kapoor v. State of Goa (2012) 12                C
           SCC 378, has categorically observed that once the special leave
           petition is dismissed as withdrawn without obtaining appropriate
           permission to file a special leave petition once over again after
           exhausting the remedy of review petition before the High Court,
           the same is not maintainable.”
                                                                                    D
       10. After considering the Constitution Bench decision in Durga
Shankar Mehta6 and number of other judgments, in Bussa Overseas7,
the Court held that consistency is the cornerstone of the administration
of justice and courts have evolved and formulated a principle that if the
basic judgment is not assailed and the challenge is only to the order
passed in review, the Supreme Court is obliged not to entertain such                E
special leave petitions. In paragraphs (30) and (31) of Bussa Overseas8,
the Supreme Court held as under:-
       “30. The decisions pertaining to maintainability of special leave
       petition or for that matter appeal have to be seemly understood.
       Though in the decision in Shanker Motiram Nale Shiolalsing                   F
       Gannusing Rajput (1994) 2 SCC 753, the two-Judge Bench
       referred to Order 47 Rule 7 of the Code of Civil Procedure that
       bars an appeal against the order of the court rejecting the review,
       it is not to be understood that the Court has curtailed the plenary
       jurisdiction under Article 136 of the Constitution by taking recourse        G

5
  Bussa Overseas and Properties Private Limited and Another v. Union of India and
Another (2016) 4 SCC 696
6
  Durga Shankar Mehta v. Thakur Raghuraj Singh and Others (1955) 1 SCR 267
7
  Bussa Overseas and Properties Private Limited and Another v. Union of India and
Another (2016) 4 SCC 696
                                                                                    H
162             SUPREME COURT REPORTS                               [2020] 4 S.C.R.


A            to the provisions in the Code of Civil Procedure. It has to be
             understood that the Court has evolved and formulated a principle
             that if the basic judgment is not assailed and the challenge is only
             to the order passed in review, this Court is obliged not to entertain
             such special leave petition. The said principle has gained the
             authoritative status and has been treated as a precedential principle
B
             for more than two decades and we are disposed to think that
             there is hardly any necessity not to be guided by the said precedent.
             31. In this context, we may profitably reproduce a passage from
             State of A.P. v. A.P. Jaiswal (2001) 1 SCC 748, wherein a three-
             Judge Bench has observed thus: (SCC p. 761, para 24)
C
                 “24. Consistency is the cornerstone of the administration of
                 justice. It is consistency which creates confidence in the system
                 and this consistency can never be achieved without respect to
                 the rule of finality. It is with a view to achieve consistency in
                 judicial pronouncements, the courts have evolved the rule of
D                precedents, principle of stare decisis, etc. These rules and
                 principle are based on public policy….” (emphasis supplied)
           The Supreme Court held that the decision rendered in
      Thungabhadra Industries Ltd.9 is not correct.

E            11. It was submitted by the learned Solicitor General and
      learned Senior counsel appearing on behalf of the respondent that the
      earlier SLP was heard at length and thereafter, the SLP came to be
      dismissed as there was no ground to interfere in the matters. After
      dismissal of the SLP and without seeking for liberty, the petitioner
      thereafter filed the review petition.
F
             12. In our considered view, it is not necessary to go into the question
      of maintainability of these SLPs preferred against the order rejecting
      the review, after the challenge to the main judgment had been rejected
      in the earlier SLPs. As noted earlier, in this case, the judgment of the
      High Court under Section 37 of the Act was challenged before the
G     Supreme Court and the SLPs were dismissed by the Supreme Court
      after hearing the Senior Counsel for the parties vide order dated

      8
        Bussa Overseas and Properties Private Limited and Another v. Union of India and
      Another (2016) 4 SCC 696
      9
        Thungabhadra Industries Ltd. v. Government of Andhra Pradesh Represented by the
H     Deputy Commissioner of Commercial Taxes, Anantapur (1964) 5 SCR 174
     PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                                  163
             POWER CORPORATION LTD. (NEEPCO)

19.07.2019. Be it noted when the earlier SLPs were dismissed, no liberty               A
was taken to file the review before the High Court. Be that as it may,
we are not inclined to go into this aspect any further.
       13. On behalf of the petitioner, Mr. Harish Salve and Mr. Neeraj
Kishan Kaul, learned Senior counsel mainly contended that in the
judgment of the High Court dated 26.02.2019, the High Court erroneously                B
applied the provisions as applicable prior to the Amendment Act, 2015
and the judgment of the High Court suffers from error apparent on the
face of the record since the High Court relied upon the decision in Saw
Pipes Ltd.10and Western Geco International Limited11, which are no
longer good law after the Amendment Act, 2015 brought into effect
from 23.10.2015. It is submitted that the judgment of the High Court                   C
dated 26.02.2019 suffers from error apparent on the face of the record
and therefore, the petitioner is justified in seeking the review of the
judgment dated 26.02.2019 and the High Court was not right in rejecting
the review petition. In support of the contention of the petitioners, reliance
was placed upon HRD Corporation12and Ssangyong Engineering and                         D
Construction Company Limited13.
       14. Mr. Tushar Mehta, learned Solicitor General and Mr. Huzeffa
Ahmadi, learned Senior counsel have submitted that at the time when
the earlier SLP(C) Nos.13629-13631 of 2019 were heard, they were
heard at length and all the arguments including the effect of the                      E
amendment to Section 34 was also raised and only thereafter, the earlier
SLPs came to be dismissed. It was submitted that though the dismissal
of order dated 19.07.2019 is a non-speaking order, the petitioner had
raised all contentious points, now urged, and faced an order of dismissal,
and the petitioner cannot be allowed to reagitate the matter by filing a
review petition.                                                                       F

      15. In Board of Control for Cricket in India14, the Supreme
Court held that the Amendment Act, 2015 would apply to Section 34
10
   Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705
11
   Oil & Natural Gas Corporation Ltd. v. Western Geco International Limited (2014) 9   G
SCC 263
12
   HRD Corporation (Marcus Oil and Chemical Division) v. GAIL (India) Limted
(2018) 12 SCC 471
13
   Ssangyong Engineering and Construction Company Limited v. National Highways
Authority of India (NHAI) (2019) 15 SCC 131, Para No.19
14
   Board of Control for Cricket in India v. Kochi Cricket Private Limited and Others
(2018) 6 SCC 287                                                                       H
164              SUPREME COURT REPORTS                                 [2020] 4 S.C.R.


A     petitions that are made after 23.10.2015 (the day on which the
      Amendment Act came into force). In the present case, admittedly, after
      the arbitral awards are dated 29.03.2016, the applications under Section
      34 of the Act were filed before the Judicial Commissioner, Shillong as
      per the decision in Board of Control for Cricket in India15, the provisions
      of the Amendment Act would apply.
B
             16. Patent illegality as a ground for setting aside a domestic award
      was first expounded in the judgment of Saw Pipes Ltd.16 where this
      Court was dealing with a domestic award. This Court gave a wider
      interpretation to the ‘public policy of India’ in Section 34(2)(b)(ii) in Part
      I of the 1996 Act. The Court held that an award would be “patently
C     illegal”, if it is contrary to the substantive provisions of law; or, provisions
      of the 1996 Act; or, terms of the contract.
             17. In the subsequent judgment of Associate Builders17, this Court
      discussed the ground of patent illegality as a ground under public policy
      for setting aside a domestic award. The relevant extract of the judgment
D     in Associate Builders case (supra) reads as follows:-
             “40. Patent Illegality
             We now come to the fourth head of public policy namely, patent
             illegality. It must be remembered that under the explanation to
E            Section 34(2)(b), an award is said to be in conflict with the public
             policy of India if the making of the award was induced or affected
             by fraud or corruption. This ground is perhaps the earliest ground
             on which courts in England set aside awards under English law.
             Added to this ground (in 1802) is the ground that an arbitral award
             would be set aside if there were an error of law by the
F            arbitrator….”
             “42. In the 1996 Act, this principle is substituted by the ‘patent
             illegality’ principle which, in turn, contains three sub heads-
             42.1 (a) a contravention of the substantive law of India would
             result in the death knell of an arbitral award. This must be
G
             understood in the sense that such illegality must go to the root of

      15
         Board of Control for Cricket in India v. Kochi Cricket Private Limited and Others
      (2018) 6 SCC 287
      16
         Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705
      17
H        Associate Builders v. Delhi Development Authority (2015) 3 SCC 49, paras 40 to 45.
     PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                              165
             POWER CORPORATION LTD. (NEEPCO)

          the matter and cannot be of a trivial nature. This again is a really     A
          a contravention of Section 28(1)(a) of the Act, which reads as
          under:
              28. Rules applicable to substance of dispute.—(1) Where the
              place of arbitration is situated in India,-
                  (a) in an arbitration other than an international commercial     B
                  arbitration, the arbitral tribunal shall decide the dispute
                  submitted to arbitration in accordance with the substantive
                  law for the time being in force in India;
          42.2 (b) a contravention of the Arbitration Act itself would be
          regarded as a patent illegality-for example if an arbitrator gives       C
          no reasons for an award in contravention of Section 31(3) of the
          Act, such award will be liable to be set aside.
          42.3 (c) Equally, the third sub-head of patent illegality is really a
          contravention of Section 28(3) of the Arbitration Act, which reads
          as under:                                                                D
              28. Rules applicable to substance of dispute.-
              (3) In all cases, the arbitral tribunal shall decide in accordance
              with the terms of the contract and shall take into account the
              usages of the trade applicable to the transaction.
                                                                                   E
          This last contravention must be understood with a caveat. An
          arbitral tribunal must decide in accordance with the terms of the
          contract, but if an arbitrator construes a term of the contract in a
          reasonable manner, it will not mean that the award can be set
          aside on this ground. Construction of the terms of a contract is
                                                                                   F
          primarily for an arbitrator to decide unless the arbitrator construes
          the contract in such a way that it could be said to be something
          that no fair minded or reasonable person could do.” (emphasis
          supplied)
       18. The Law Commission in its 246th Report18 recommended the
insertion of the ground of ‘patent illegality’ for setting aside a domestic        G
award by the insertion of clause (2A) in Section 34 of the Act. The
relevant extract from the Report of the Law Commission is extracted
herein below:-

18
     Available at : http://lawcommissionofindia.nic.in/reports/Report246.pdf       H
166      SUPREME COURT REPORTS                           [2020] 4 S.C.R.


A     “It is for this reason that the Commission has recommended the
      addition of section 34 (2A) to deal with purely domestic awards,
      which may also be set aside by the Court if the Court finds that
      such award is vitiated by “patent illegality appearing on the face
      of the award.” In order to provide a balance and to avoid excessive
      intervention, it is clarified in the proposed proviso to the proposed
B
      section 34 (2A) that such “an award shall not be set aside merely
      on the ground of an erroneous application of the law or by
      reappreciating evidence.” The Commission believes that this will
      go a long way to assuage the fears of the judiciary as well as the
      other users of arbitration law who expect, and given the
C     circumstances prevalent in our country, legitimately so, greater
      redress against purely domestic awards. This would also do away
      with the unintended consequences of the decision of the Supreme
      Court in ONGC v. Saw Pipes Ltd, (2003) 5 SCC 705, which,
      although in the context of a purely domestic award, had the
      unfortunate effect of being extended to apply equally to both
D
      awards arising out of international commercial arbitrations as well
      as foreign awards, given the statutory language of the Act. …”
      (emphasis supplied)
      To give effect to the said recommendation, it was suggested that:
E     “(iii) After the Explanation in sub-section (2), insert sub-section
      ‘(2A) An arbitral award arising out of arbitrations other than
      international commercial arbitrations, may also be set aside by
      the Court if the Court finds that the award is vitiated by patent
      illegality appearing on the face of the award. Provided that an
      award shall not be set aside merely on the ground of an erroneous
F     application of the law or by re-appreciating evidence.’
      [NOTE: The proposed S.34(2A) provides an additional, albeit
      carefully limited, ground for setting aside an award arising out of
      a domestic arbitration (and not an international commercial
      arbitration). The scope of review is based on the patent illegality
G     standard set out by the Supreme Court in ONGC Ltd. v. Saw
      Pipes Ltd., (2003) 5 SCC 705. The proviso creates exceptions for
      erroneous application of the law and re-appreciation of evidence,
      which cannot be the basis for setting aside awards.]” (emphasis
      supplied)
H
     PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                                  167
             POWER CORPORATION LTD. (NEEPCO)

       19. Pursuant to the recommendations of the Law Commission,                      A
the 1996 Act was amended by Act 3 of 2016, which came into force
w.e.f. 23.10.2015. The ground of “patent illegality” for setting aside a
domestic award has been given statutory force in Section 34(2A) of the
1996 Act. The ground of “patent illegality” cannot be invoked in
international commercial arbitrations seated in India. Even in the case of
                                                                                       B
a foreign award under the New York Convention, the ground of “patent
illegality” cannot be raised as a ground to resist enforcement, since this
ground is absent in Section 48 of the 1996 Act. The newly inserted sub-
section (2A) in Section 34, reads as follows:-
        “(2A) An arbitral award arising out of arbitrations other than
        international commercial arbitrations, may also be set aside by                C
        the Court, if the Court finds that the award is vitiated by patent
        illegality appearing on the face of the award :
        Provided that an award shall not be set aside merely on the ground
        of an erroneous application of the law or by reappreciation of
        evidence.”                                                                     D

       20. In Ssangyong Engineering and Construction Company
Limited19, this Court was considering a challenge to an award passed in
an international commercial arbitration, between the Appellant – company
a foreign entity registered under the laws of Korea, and the Respondent,
a Government of India undertaking. In paragraph (19) of the judgment,                  E
this Court noted that the expansive interpretation given to “public policy
of India” in the Saw Pipes (supra) and Western Geco International
Limited20 cases, which had been done away with, and a new ground of
“patent illegality” was introduced which would apply to applications under
Section 34 made on or after 23.10.2015. In paragraphs (36) and (37) of                 F
the judgment, this Court held that insofar as domestic awards are
concerned, the additional ground of patent illegality was now available
under sub-section (2A) to Section 34. However, re-appreciation of
evidence was not permitted under the ground of “patent illegality”
appearing on the face of the award.
                                                                                       G
      21. In paragraphs (39) and (40) of Ssangyong Engineering
(supra), the Court reiterated paragraphs (42.2) and (42.3) of Associate
19
   Ssangyong Engineering and Construction Company Limited v. National Highways
Authority of India (NHAI) (2019) 15 SCC 131
20
   Oil & Natural Gas Corporation Ltd. v. Western Geco International Limited (2014) 9
SCC 263                                                                                H
168             SUPREME COURT REPORTS                            [2020] 4 S.C.R.


A     Builders (supra) wherein, it was held that the construction of the terms
      of a contract is primarily for an arbitrator to decide, unless the arbitrator
      construes a contract in a manner which no fair minded or reasonable
      person would take i.e. if the view taken by the arbitrator is not even a
      possible view to take. In paragraphs (39) and (40), the Supreme Court
      held as under:-
B
             “39. To elucidate, para 42.1 of Associate Builders v. Delhi
             Development Authority (2015) 3 SCC 49, namely, a mere
             contravention of the substantive law of India, by itself, is no longer
             a ground available to set aside an arbitral award. Para 42.2 of
             Associate Buildersv. Delhi Development Authority (2015) 3 SCC
C            49, however, would remain, for if an arbitrator gives no reasons
             for an award and contravenes Section 31(3) of the 1996 Act, that
             would certainly amount to a patent illegality on the face of the
             award.
             40. The change made in Section 28(3) by the Amendment Act
D            really follows what is stated in paras 42.3 to 45 in Associate
             Builders v. Delhi Development Authority (2015) 3 SCC 49,
             namely, that the construction of the terms of a contract is primarily
             for an arbitrator to decide, unless the arbitrator construes the
             contract in a manner that no fair-minded or reasonable person
E            would; in short, that the arbitrator’s view is not even a possible
             view to take. Also, if the arbitrator wanders outside the contract
             and deals with matters not allotted to him, he commits an error of
             jurisdiction. This ground of challenge will now fall within the new
             ground added under Section 34(2-A).” (emphasis supplied)

F            22. The present case arises out of a domestic award between
      two Indian entities. The ground of patent illegality is a ground available
      under the statute for setting aside a domestic award, if the decision of
      the arbitrator is found to be perverse, or, so irrational that no reasonable
      person would have arrived at the same; or, the construction of the contract
      is such that no fair or reasonable person would take; or, that the view of
G     the arbitrator is not even a possible view.
            23. In the present case, the High Court has referred to the judgment
      in Associated Builders (supra) at length in paragraph (42) of its judgment
      dated 26.02.2019 and arrived at the correct conclusion that an arbitral
      award can be set aside under Section 34 if it is patently illegal or perverse.
H
 PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                             169
         POWER CORPORATION LTD. (NEEPCO)

This finding of the High Court is in conformity with paragraph (40) of        A
the judgment of this Court in Ssangyong Engineering (supra).
       24. In the present case, the High Court in paragraph (51) has held
that no reasonable person could have arrived at a different conclusion
while interpreting Clauses 2.7 and 3.4 of the BoQ and Clauses 32(ii)(a)
and 33(iii) of the Conditions of Contract. Any other interpretation of the    B
above clauses would definitely be irrational and in defiance of all logic.
The relevant extract reads:-
      “51. …Clause 33(iii) specifically provides that “if the rates for
      such items of work cannot be determined in the manner as specified
      in Clause 33(ii), the rates for such items to be executed shall be      C
      determined by the Engineer-in-Charge on the basis of actual and
      analysed cost taking the following into consideration the rates for
      such items of works as are required to be executed due to
      deviations as stated in sub-clause shall be payable in the manner
      as stated hereunder…..”. We are of the firm view that this is the
      only possible interpretation of Clauses 2.7 and 3.4 of the BoQ and      D
      Clauses 32(ii)(a) and 33(iii) of the Conditions of Contract. No
      reasonable person would arrive at a different conclusion while
      interpreting Clauses 2.7 and 3.4 of the BoQ and Clauses 32(ii)(a)
      and 33(iii) of the Conditions of Contract. Any other interpretation
      of the above clauses would definitely be irrational and defiance of     E
      all logic.” (emphasis supplied)
      25. The High Court in paragraph (52) came to the finding that the
findings in the award suffer from the vice of irrationality and perversity,
and held as follows:-
      “52. The Arbitral Awards and the findings of the learned Arbitrator     F
      suffer from the vice of perversity. The learned Arbitrator has
      taken into account various factors irrelevant in coming to the
      decision and has ignored vital clauses of the tender documents
      like Clause 2 and various Sub-clauses i.e. Sub-clauses 2.1 to 2.8.7
      under Clause 2 and Clause 3 and various Sub-Clauses i.e. Sub-           G
      clauses 3.1 to 3.7 under Clause 3 of the BoQ, Clause 2 and various
      Sub-clauses i.e. Sub-clause 2.1 to 2.17.7 under Clause 2 and
      Clause 3 and various Sub-clauses i.e. Sub-clause 3.1 to 3.10.5
      under Clause 3 of “Particular Technical Specifications”, Vol. 2,
      Part II. The learned Arbitrator has taken into consideration an
                                                                              H
170      SUPREME COURT REPORTS                            [2020] 4 S.C.R.


A     irrelevant fact that while making provisional payment, the initial
      lead of 3.0 km has been deducted and that this shows that Clause
      2.7 and 3.4 of the BoQ are applicable. The provisional payment
      was an interim arrangement and was preceded by meetings dated
      07.12.2012 and 08.12.2012 wherein it was specifically agreed
      between the parties that HoP, NEEPCO would take steps for
B
      referring the dispute to arbitration and that till the arbitral award,
      the payment would be made as per the prevailing provisional rate
      without any escalation and that final rate payable for transportation
      of sand and boulder shall be done on implementation of the arbitral
      award. As such the fact that provisional payment was made by
C     deducting initial lead of 3.0 km was an irrelevant fact for deciding
      the issue. The findings of the learned Arbitrator having been arrived
      at by taking into account irrelevant factors and by ignoring vital
      clauses, the same suffers from vice of irrationality and perversity.
      It must be borne in mind that the Arbitral Awards in question are
      Declaratory Arbitral Awards and involved interpretation of Clauses
D
      2.7 and 3.4 of the BoQ and Clauses 32(ii)(a) and 33(iii) of the
      Conditions of Contract and the learned arbitrator was required to
      interpret the same in accordance with the established rules of
      interpretation. The findings of the learned Additional Deputy
      Commissioner (Judicial), Shillong while upholding the arbitral
E     awards of the learned Arbitrator also suffer from the similar vice.
      We are, therefore, of the considered view that that the common
      order dated 27.04.2018 passed by the learned Additional Deputy
      Commissioner (Judicial), Shillong in Arbitration Case No. 5 (T)
      2016, Arbitration Case No. 6 (T) 2016 and Arbitration Case No. 7
      (T) 2016 as well as the 3 (three) Arbitral Awards dated 29.03.2016
F
      passed by the learned Arbitrator warrant interference in these
      appeals under Sec. 37 of the Arbitration and Conciliation Act,
      1996.
      53. There are additional reasons for interfering with order dated
      27.04.2018 passed by the learned Additional Deputy Commissioner
G     (Judicial), Shillong and the Arbitral Awards dated 29.03.2016
      passed by the learned Arbitrator. As the learned counsel for the
      appellant has submitted, the potential effect of the Arbitral Award
      on public exchequer is that the appellant, which is a public sector
      undertaking, will have to pay a sum of about Rs. 3.56 Lakh for
H     every truckload of 10 cubic metre of sand or boulder (travelling
 PATEL ENGINEERING LTD. v. NORTH EASTERN ELECTRIC                             171
         POWER CORPORATION LTD. (NEEPCO)

      for 100 km) and the total potential effect would be about Rs.           A
      1,000 Crore. We are of the considered view that payment of Rs.
      3.56 Lakh per truck (10 Cubic Metre) of sand or boulder (100 km
      distance) is definitely a case of unjust enrichment which is contrary
      to the Fundamental Policy of Indian Law. Unjust enrichment being
      contrary to the Fundamental Policy of Indian Law is a ground for
                                                                              B
      interference with an Arbitral Award under Sec. 34(2) of the Act.
      The Bombay High Court in Angerlehner Structural and Civil
      Engineering co. v. Municipal Corporation of Greater Mumbai has
      recognized unjust enrichment of a party at the cost of public
      exchequer as being against the fundamental policy of Indian law.
      The Bombay High Court has held:                                         C
         “If the argument of the Contractors is accepted, it lead to them
         blatantly enriching themselves over and above what they are
         entitled. Such completely unjust enrichment, that too at the
         cost of public funds, is abhorrent under the fundamental policy
         of Indian Law. The award in AJECT, which permits such blatant        D
         enrichment is therefore is also vitiated on the ground that it is
         against the fundamental policy of Indian Law.”
      We are also of the considered view that the Arbitral Award which
      would potentially result in unjust enrichment of the respondent to
      the extent of about Rs. 1,000 Crores is against the fundamental         E
      policy of Indian law and, therefore, warrant interference on this
      count as well.
      Though this court is not sitting in appeal over the award of the
      arbitral tribunal, the presence of grounds under Section 34[2] of
      the Act and the satisfaction arrived at by this Court in this regard,   F
      warrants interference more so, as the Arbitral Awards in question
      are Declaratory Arbitral Awards and involved interpretation of
      Clauses 2.7 and 3.4 of the BoQ and Clauses 32(ii)(a) and 33(iii)
      of the Conditions of Contract and the learned arbitrator was
      required to interpret the same in accordance with the established
      rules of interpretation and in line with the fundamental policy of      G
      Indian law.”
                                                     (emphasis supplied)
       26. Even though the High Court in paragraph (44) of the judgment
referred to various judgments, including Western Geco (supra) [which
                                                                              H
172                SUPREME COURT REPORTS                          [2020] 4 S.C.R.


A     is now no longer good law], the case has been decided on the ground
      that the arbitral award is a perverse award and on a holistic reading of
      all the terms and conditions of the contract, the view taken by the arbitrator
      is not even a possible view. The High Court has rightly followed the test
      set out in paragraph (42.3) of Associate Builders (supra), which was
      reiterated in paragraph (40) of the Ssangyong Engineering judgment
B
      (supra).
             27. In our view, while dealing with the appeal under Section 37 of
      the Act, the High Court has considered the matter at length, and held
      that while interpreting the terms of the contract, no reasonable person
      could have arrived at a different conclusion and that the awards passed
C     by the arbitrator suffer from the vice of irrationality and perversity.
             28. The learned Solicitor General Mr. Tushar Mehta and
      Mr. H. Ahmadi, Senior Advocate for the respondent, submitted that all
      these contentions were raised in the earlier round when challenge to the
      substantive Judgment dated 26.02.2019 was made. The said challenge
D     was repelled by this Court vide Order dated 19.07.2019 by dismissal of
      the earlier SLPs. It is now not open to re-open the matter by filing a
      review petition on the same grounds, which have been rightly dismissed
      by the High Court. The Petitioner has failed to make out any error on
      the face of the judgment dated 26.02.2019. The High Court by the
E     impugned order dated 10.10.2019 rightly dismissed the review petitions
      and we do not find any ground warranting interference with the impugned
      order.
            29. In the result, all the special leave petitions are dismissed with
      no order as to costs.
F
      Ankit Gyan                                     Special Leave Petitions dismissed.




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.