Created byFuzzy Cloud

Supreme Court of India

PADMAversusHIRALAL MOTILAL DESARDA & ORS.

Citation
2002 INSC 371
Decided
9 September 2002
Disposal
Disposed off

Holding

The Supreme Court held that the High Court was correct in treating the petition as a public‑interest litigation, that CIDCO’s bulk sale and the resultant allotments were illegal and void, and upheld the High Court’s orders with modifications regarding payment of reserve price for constructed plots.

Summary

The Supreme Court examined a public‑interest writ filed by Padma challenging CIDCO's bulk sale of developable land in Aurangabad. The High Court had held that the allotments to several private entities were made without Board approval, at prices below the reserve price, and in violation of Section 115 of the Maharashtra Regional and Town Planning Act, rendering them void. The appellants argued that the High Court exceeded its jurisdiction, that they were denied a chance to defend themselves, and that bulk sale was permissible under CIDCO's policy. The Court rejected these contentions, affirming that the petition could be treated as a PIL and that CIDCO’s actions were contrary to its "no‑profit‑no‑loss" mandate and statutory requirements. While upholding the High Court’s finding of illegality, the Court modified the relief: it ordered the sale to respondent No.9 to be regularised by payment of the reserve price, directed inspection and demarcation of land allotted to respondent No.15, and confirmed the annulment of sales to respondents No.5 and No.6. The judgment reiterated that public‑interest litigation may expand issues beyond the original pleadings to protect public welfare.

Issues considered

  • The High Court's jurisdiction to treat the writ as a public‑interest litigation and to expand issues beyond the petitioner's pleadings.
  • Whether CIDCO’s bulk sale of land was authorized under the Maharashtra Regional and Town Planning Act and its own "no‑profit‑no‑loss" policy.
  • Whether allotments made without Board approval, at prices below the reserve price and without a public tender are void.
  • Whether the appellants were denied a fair opportunity to defend themselves in the High Court proceedings.
  • The appropriate relief given the construction already undertaken on some of the allotted plots.

Legislation cited

Subjects

public interest litigationbulk sale of landCIDCOMaharashtra Regional and Town Planning Actno profit no lossirregularitiesallotment voidreserve pricedevelopment plan

Judgment

                                   PADMA                                           A
                                       V.

                 HIRALAL MOTILAL DESARDA & ORS.

                           SEPTEMBER 9, 2002.

               [G.B. PATTANAIK AND R.C. LAHOTI, JJ.]                               B


      Urban Development-Housing-Allotment of land by bulk sale by
CIDCO-Petition challenging allotment-Treated as Public Interest
Litigation-Irregularities in allotment found and allotment held to be null and     C
void by High Court-In appeal plea of want of necessary pleadings and
denial of opportunity of defending by non-petitioners raised-Plea rejected
and finding of High Court upheld-However, relief modified.

      Constitution of India, 1950, Articles 32, 226-Public Interest litigation--
Technicalities do not deter the Court in wielding its power to do justice,         D
enforcing the law and balancing the equities.

       Government of Maharashtra acquired land for City and Industrial
Development Corporation (CIDCO), a Government Company, the main
objective of which was to develop land for residential, commercial and
allied industrial activities on "no profit no loss" basis. CIDCO got approval      E
of development plan by the Government. A patch of land had been shown
in the approved plan meant for future expansion. After development of
the approved land, CIDCO decided to dispose of the developable land by
butk·sale and consequently the land was allotted to respondent Nos. 5,6,9
and 15.
                                                                                   F
       Respondent No. I filed writ petition before High Court chailenging
the bulk sale by CIDCO. High Court treated the petition as public interest
litigation and called for the records of CIDCO and framed issues, beyond
the pleadings in the writ petition. High Court found that respondent No.12
was Director of CIDCO at the relevant time and respondent Nos. 5, 6 and            G
15 were alteregos of respondent No.12, and they were created during same
period; that allotments were made without approval of Board of Directors
of CIDCO and without assigning any reason for allotment; that allotment
made to respondent No.5 was without affording other rivals an opportunity
of participating in the bid and when the revised development plan was
                                      179
                                                                                   H
    180                      SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A   pending with the Government for approval; that the lands were allotted
    for less than reserve price for no reason and without specific approval by
    the Board or competent authority; that the letters of allotment did not
    set out the nature of land user. Court held that the action of CIDCO in
    the matter of disposal of land by bulk sale was against public interest and
B   allotment of land was null and void, as the draft development plan had
    not been approved by the State G~vernment as required under Section
    I IS of Maharashtra Regional and Town Planning Act; that the
    proclamations issued for disposal of land were illegal; that individual
    allotments made in favour of respondent Nos. 5,8,9,10 and 15 were also
    illegal and the administration was directed to take immediate possession
C   of the respective lots including the structure and buildings standing
    thereon. Respondent No. 6 , allotment in whose favour was subsequently
    cancelled by CIDCO, filed writ petition which was dismissed by High
    Court.

          In appeal to this Court appellant contended that High Court
D committed error in entertaining individual grievance of respondent No.I,
    who himself happened to be a builder on purchase of land, as a Public
    Interest Litigation; that the legality of allotment of land could not have
    been examined by High court in the absence of any pleadings in that
    respect; and that in respect of several plots of land constructions having
E   already been made and the appropriate authority of the Government
    having approved the development as well as proposal of bulk disposal of
    plots it is fully inequitable to cancel the allotments.

          Respondent No. I contended that finding of High Court tantamount
    to finding of fraud committed by CIDCO in the matter of allotment of
F   land and therefore fraud vitiates every action of the authority, and hence
    it wasjust and proper for the High court to set aside the allotment made.

          Dismissing the appeals, the Court

          HELD: I.I. The appellants cannot raise any grievance on the ground
G of want of necessary pleadings and denial of necessary opportunity of
  defending themselves at the hearing in High Court. I192-F; 193-BJ

          1.2. The High Court had, by having framed the issues, put all the
    parties before it on notice that it proposed to enter into issues wider than
    what may have been raised in the writ petition filed before it. The non-
H   petitioners in the High Court, including the appellants, were put on notice
                 PADMA v. HIRALAL MOTJLAL DESARDA                        181

of the issues on which the High Court proposed to dwell upon and they           A
were allowed full opportunities of defending themselves by bringing in such
pleadings and documents as they proposed to do in their defence. The High
Court called for the record of CIDCO and subjected the same to scrutiny
under its magnifying glass of judicial review. The non-petitioners in the
High Court were well aware of CIDCO record of proceedings and the
findings of the High Court are based on the facts discernible from the          B
records and the factual inferences necessarily and inevitably flowing
therefrom. 1192-F-H; 193-AI

       1.3. Litigation before High Court assumed the character of public
interest litigation of wider scope, not necessarily confined to grievance       C
raised by the writ petitioner and the High Court was intervening to bring
under its scrutiny, under the well settled parameters of public interest,
the proceedings of CIDCO relating to attempted disposal of developable
liind. While hearing a public interest litigation the Constitutional Court
acts as the sentinel on the qui vive discharging its obligation as custodian
of the constitutional morals, ethics and code of conduct. Ttie Court is         D
obliged to see while scrutinizing the conduct and activities of a public body
constituted with the avowed object of serving the society to see that its
activities bear no colour except being transparent, are guided with the
object of public good and are within the four corners of law governing
the same. The holder of every public office hold a trust for public good        E
and, therefore, his actions should all be above board. 1191-G, H; 192-A, Bl

     1.4. In public interest litigation jurisdiction the Constitutional Court
is mobilized and acts for redressal of public injury, enforcement of public
duty, protection of social rights and upholding constitutional and
democratic values. Technicalities do not deter the Court in wielding its        F
power to do justice, enforcing the law and balancing the equities.
                                                                   1193-A, BJ

      1.5. It cannot be said that High Court should not have entertained
the writ petition filed by respondent No. I who was a business competitor
of respondent Nos.5,6,9 and 15. Firstly, because respondent No. I has not       G
figured anywhere in or around the impugned transactions of sale. Merely
because at sometime in the past respondent No. I had himself secured some
allotment of land from CIDCO that would not mean that he was a business
competitor so far as the impugned transactions are concerned. Secondly,
because High Court has found respondent Nos.5,6 and 15 having been born
just around the year 1998-99 and, therefore, the question of their being        H
     182                      SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

·A in existence at that point of time ancl hence in rivalry when respondent
     No.I had secured some allotment of land in the past does not arise. The
     proceedings in the High Court show only the ball of judicial scrutiny
     having set rolling by respondent No. I. Soon the High Court found the case
     fit for exercising its own public interest jurisdiction, and therefore, the
 B   High Court framed its own issues which were not necessarily confined to
     the pleas raised in the writ petition filed by respondent No. I. Therefore,
     it cannot be held that the interest served by the proceedings in the High
     Court has been anything other than pro bona publico. 1204-D-H I

           2. !. The very sale of bulk land by an institution like CIDCO is an
C    anathema to its objective and purpose of its establishment. By no stretch
     of imagination it can be contemplated that it was or could have· been
     intended either at the time of acquisition or at the time of sanction of
     development plans by the State Government that at some point of time in
     future the developable land would be available to be disposed of by bulk
     sale and that too in favour of professional builders. That is why a condition
D    was imposed that the developable land shall be available for being utilized
     in accordance with the plan to be sanctioned by the State Government at
     a later point of time. 1201-B; 201-E-FI

           2.2. It is not disputed that CIDCO is supposec! to carry out its
     activities on 'no profit no loss' basis and that is the basis on which CIDCO
E    has been acting until it decided to part with the chunk of developable land
     by bulk sale which proposal was obviously in departure from the policy
     of serving on 'no profit no loss' basis such people as were craving for a
     roof over their heads. In the present case, if only the proposal would have
     been placed before the Board of CIDCO in all probability it would have
 F   been discarded. Good number of officials, through whose hands the
     proposal passed while traveling up, were not agreeable to and had their
     own reservations on I.he proposal of such bulk sale. What prevailed with
     one or two of those placed at the higher rung of bureaucratic ladder in
     permitting such bulk sale in hot haste defies explanation for the simple
     reason that no reasons have been assigned in favour of endorsing the
 G   proposal for bulk land sale. It cannot be accepted that there was no
     demand of land. Even if the development plan for the developable land
     was not approved by the State Government there is nothing which had
     prevented CIDCO from carving out small middle level and larger plots
     which those who can afford. This finds support from the overwhelming
 H   demand of land which CIDCO had found out of proportion as compared
                  PADMA v. HIRALAL MOTILAL DESARDA                        I 83
to the availability of land with it.1The decision for bulk land sale cannot      A·.
be said to have been taken in public interest. 1202-D-H; 203-A, Bl

      2.3. The land acquired and entrusted to CIDCO cannot just be
permitted to be parted with, guided by the sole consideration of money-
making. CIDCO is not a commercial concern whose performance is to be
assessed by the amount it earns. Its performance would be better assessed        B
by finding out the number of needy persons who have been able to secure
shelter through CIDCO and by the beauty of township and quality of life
for people achieved by CIDCO through its planned development schemes.
So long as such objectives are fulfilled CIDCO's operation on 'No-Profit-
No Loss' basis cannot be found fault with. There should have been no             C
hurry on the part ofCIDCO in disposing of the balance land and that too
guided by the sole consideration of earning more money. Even that object
the CIDCO has not been able to achieve for at the end it has parted with
land at a price less than the reserved price. Even if a sale of left-over land
was a felt-necessity it should have satisfied at least two conditions: (i) a
well-considered decision at the highest level; and (ii) a sale by public         D
auction or by tenders after giving a more wide publicity than what was
done so as to attract a iarger number of bidders. 1203-D-Gl

     2.4. On principle and in substance, the order of the High Court is
maintained. The impugned sales of land in favour of respondent Nos. 5,6
9 and 15 are vitiated and hence not binding on CIDCO. 1206-El                    E
                                   I ). <11.1: ' f I '
      2.5. High Court has pierced the veil of respondent Nos. 5, 6 :rnd 15.
There is every reason to draw lildeduction·.that these legal entities of
different colour and shade were brought into lieing around the crucial
period of time and almost just following1the1point of time When the idea
of disposal of the developabldand through blilk'sale'had dawned upon
                                                                                 F
the CIDCO wherein respondent No. 12 was aDirector. :fhese 'three entities,
though each appearing in a legal cloak outwardly, were in fact family
affair of respondent No.12. 1197-A; 194-B, q

       2.6. Record filed by respondent No. 9 does not show that it had           G
anyone inside CIDCO exerting his or her influence from within to oblige
it as it has been in the case of PWI2 and his cloaked duplicates. Therefore,
in spite of holding of sale in favour of respondent No.9 vitiated, in view of
subsequent events, the situation having become irreversible on account of
construction of vast magnitude having come up and third party interests
having been created, respondent No.9 shall remain liable to pay the price        H
    184                      SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A of the land allotted to it, the reserve price, within a time to be appointed
    by CIDCO. (205-C, D; 206-F(

           2.7. From the pleadings and documents filed by respondent No. 15,
    no idea can be formulated about the nature and extent of construction, if
    11ny, done and the time by which it was done. From the judgment of the
B   High Court only a passing reference is found wherefrom it can be gathered
    that 'some' building has come into existence over the land allotted to it.
    There is not a slightest indication of its having created any third party
    interests. The land sold to it shall be inspected, surveyed and demarcated
    under the supervision ofa highly placed and responsible official ofCIDCO
C   to be nominated by its Board. Such of the land on which substantial
    construction has come up rendering the situation irreversible shall be
    separated alongwith some more area of contiguous land so as to make it
    user practical. The total area of such land shall be calculated and in that
    regard the buyer shall pay to CIDCO the reserve price subject to
    adjustment for the amount already paid. Such other land on which no
D   construction has come up or no substantial construction has been made
    shall be demarcated and revert back to CIDCO. (205-H; 207-A, BJ

          2.8 The pleadings and documents placed on record by respondent
    No. 5, do not project that it has made any construction, much less created
    any third party interest, so as to make the situation irreversible. It is,
E   therefore, proper to sustain the order of the High Court directing
    resumption of land by CIDCO. (206-CI

             (The Court directed that CIDCO and all other law enforcing
             agencies should see that the land user complies with the
             requirements of development plan and local laws and no departure
F            therefrom should be permitted, and that the land which reverts
             to CIDCO in future be utilized strictly in accordance with the
             development plan sanctioned by State Government and after
             meeting with the approval of the Board of CIDCO.) (207-C, DJ

G           CIVIL APPELLATE JURISDICTION : Civil Appeal No. 5698 of
    2002.

         From the Judgment and Order dated I 0.11.2000 of the Bombay
    High Court in W.P. No. 238 of 1999.

                                      WITH
H
           PADMA v. HIRALAL MOTILAL DESARDA [PATTANAIK, J.]                  185

        C.C. Nos. 5699, 5700, 5701, 5702, 5704 of 2002 and SLPL (C)                 A
        Altaf Ahmad, Additional Soliciter General, V.A. Mohta, Yashank P.
  Adharu, P.N. Mishra, Rakesh Dwivedi, R.R. Mantri, Ashok K. Gupta,
  Farrukh Rasheed, S.M. Jadhav, Serva Mitter, A.S. Bahasme, S.K. Visen,
  M.K. Mishra, T. Raja, Uday U. Lalit,, S.V. Kharde, Naresh Kumar, Colin
  Gonsalvis, Ms. Aparna Bhat, Ms. Tashi, S.V. Deshpande and E.P. Sawant             B
  for the appearing parties.

        The Judgment of the Court was delivered by

       PATTANAIK, J. Leave granted in SLP(C) Nos. 19687, 20512, 20666,
  20753 of 2000 and 4606 and 21825 of 2001.                                         C
        In these appeals by grant of special leave the judgment of High Court
  of Bombay, Aurangabad Bench in Writ Petition No. 2338 of 1999 is under
  challenge. A Public Interest Litigation was filed in the High Court challenging
  the procedure adopted by the City and Industrial Development Corporation          D
  (hereinafter referred to as CJDCO) for disposal of the land by bulk sale.
' CIDCO is a company registered under the Companies Act and is a government
  company under section 617 of the Companies Act. The Government of
  Maharashtra incorporated the aforesaid company with several objectives and
  the main objectives being :
                                                                                    E
          (a) To develop land for residential, commercial and allied industrial
          activities and to provide the required physical infrastructure, such as
          roads, drainage, water supply, sewerage, street lights and landscaping
          etc.

          (b) To build as many houses and community centers, shopping centers,      F
          parks, play grounds, bus stations, etc. to meet the day to day needs
          of the population, as well as for a fast take up of new growth areas
          and.also to make available and develop the plots at affordable prices,
          so as to construct residential dwellings for self occupation.

          (c) To promote growth of commercial, wholesale market activities,         G
          warehousing, transport, office and other activities in order to evolve
          expeditiously a sound economic base for self sustained growth and
          achieve, at the same time, a process of relieving congestion in the
          cities like Bombay as well as the fast developing cities in other parts
          of Maharashtra and (d) While doing so, to maintain ecological balance
          and ensure that environmental degradation is not allowed.                 H
    186                       SUPREME COURT REPORTS [2002) SUPP. 2 S.C.R ..

A          The CIDCO was declared as special planning authority for Aurangabad
    notified area under Sub-section 3(A) of Section 113 of the Maharashtra
    Regional and Town Planning Act, 1966 (hereinafter referred to as the Act)
    for residential, commercial and industrial purposes. The state of Mahrashtra
    acquired huge land for CIDCO in villages Mukundwadi, Garkheda, 1-larsul,
B   1-latesingpura, Jaswantsingpura, Bayajipura, Jadhavwadi, Murtizapur,
    Mastanpur etc. which ar.e all located in the outskirts of Aurangabad Municipal
    limits.

        The Government of Maharashtra approved the development plan
  submitted by CIDCO by its notification dated 3.7.1973. Under the approved
C plan about 900 Hectares of land was to be utilized for residential purposes,
  commercial, education community facilities, medical services etc. and a patch
  of land had been shown in the approved plan meant for future expansion, but
  the purposes for such use had not been indicated.

          Between 1975-76 and 1999-2000, CIDCO constructed tenements within
D notified area popularly known as New Aurangabad and 120 Housing Societies
    also came into existence. Within these societies 39 societies were allotted
    land OI) which the societies themselves have constructed residential tenements.
    It transpires that 37.74% of land has been used for residential purposes,
    4.90% for commercial purposes, 3.27% for educational purposes and 4.60%
E   for industrial purposes. That apart land has also been utilized for providing
    social services and for utilities as well as for road and pathways and Airport
    and part of the land has been kept as open and vacant land.

          CIDCO used to allot plots to citizens and society for construction of
    residential dwelling units and it was also building multi storey building
F   consisting of several apartments and used to sell them. CIDCO used to develop
    commercial and shopping centres. In 1998-99 CIDCO started negotiating
    with the Municipal Corporation of Aurangabad for taking over land in New
    Aurangabad area. Proclamations were issued in the newspapers inviting tenders
    for disposal of bulk land from different Survey Numbers, more particularly
    from Survey Nos. 23 and 24 of Garkheda Village in Sector "B". The total
G   land in these two Survey Numbers admeasured 19.53 Hectares. The land
    owners were given 2.59 Hectares by negotiations and balance 16.94 Hectares
    became the property of CIDCO, which was sought to be disposed of by bulk
    sale. It is this proposal of bulk sale by CIDCO, which was assailed by filing
    a writ petition purported to be one in public interest, essentially challenging
H   the procedure adopted for disposal of the land. After filing of the writ petition
                 PAD MA v. HIRALAL MOTi LAL DESARDA (PA TT ANAIK. J.]     187
in May, 1999, the High Court passed an interim order in July, 1999, directing A
the Cl DCO. not to proceed further with a·cceptance of the tenders in respect
of the bulk sale. After the initial application that was filed, several other
applications were filed, challenging the alleged disposal of land made by
CIDCO and ultimately the High Cout1 by the impugned Judgment, came to
the conclusion that the action of CIDCO in the matter of disposal of land by B
bulk plots is against the public interest and the so-called allotment of land in ·
Sectors N-2 and N-4, consisting of Survey Numbers 23, 24 and 70 is null and
void, as the draft development plan has not been approved by the State
Government, as required under Section 115 of the Maharashtra Regional and
Town Planning Act. Accordingly, those allotments were cancelled. The High
Court also held that the proclamations issued for disposal of land are illegal C
and would stand cancelled. Individual allotments made in favour of respondent
Nos. 5, 8, 9, 10 and 15 also were annulled and the Administrator was directed
to; take immediate possession of the respective lots, including the structure
and buildings standing thereon:It·was further ordered that as and when the
Governmeni of Maharashtra approves the Draft Development Plan, then the
land earmatked for residential purposes could be disposed 'of by CIDCO by D
°inviting• public tenders and by· drawing. lots. There were also certain other
directior.s· in 'the impugned 'judgment.·
,A    1   . ,\    /'l.'   '   H

      ,,Before the High Court, it was stated by the CIDCO and other allottees
     ti

t~at the w~it petitjon filed by one Hiralal Motilal Desarda, purported to be E
o~e in,public _interest, rt<ally does not espouse any public interest as the lands
-ha~~.been allotted to different Housing Societies, many of whom have already
,constructed several flats for the members of the society and any order annulling
those allotment~ .would be against the public interest. It was also averred
 before ,the High Court that the said writ petitioner himself has taken several
 plots ,for, bus.iness purposes and the present writ petition has been filed as a F
 business ,rival and not in public interest. The High Court however was not
persuaded to accept this part of the stand taken by different allottees, though
 factually it cannot be disputed that the writ petitioner before the High Court
and his family members had several plots of land on which building activities
had been carried on.
                                                                                G
      Mr. V.A. Mohta, learned senior counsel appearing for the petitioner in
S.L.P. No. 19687 of 2000, learned Additional Solicitor General appearing in
some of these SLPs and a host of other counsel submitted, that the High
Court committed error in entertaining an individual grievance who himself
happen to be a builder on purchase of land as a Public Interest Litigation and H
    188                        SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A an nu lied the allotments inade for the purpose of construction of houses which
    does not subserve any public interest at all. It was further urged th~t neither
    Section 115 of the MRTP Act nor any regulations framed thereunder restricts
    the right or puts any embargo on the right of the CIDCO to dispose of land
    in accordance with the Regulation framed by it. and that being the position
    the High Court committed error in setting aside the allotment made by
B   CIDCO.lt was also contended that the Court exceeded its jurisdiction_ under
    Article 226 in embarking upon an enquiry on several questions of facts by
    scrutinizing several governmental files and in coming to the conclusion that
    there have been gross irregularities in the matter of allotment of land.
    According to the counsel for the Petitioners the disposal of bulk plots of land
C   by Special Planning Authority, like CIDCO after development of the land in
    question is for providing opportunity to the citizens to have their houses built
    on the land and the action of ClDCO is required to be examined from that
    stand point. It is urged that no personal interest of any authority of the
    C!DCO having been found to have been augmented on account of the allotment
    of bulk land the Court was not justified in exercising its discretionary
D   jurisdiction and interfering with the allotment made. It is urged that C!DCO
    being a Special Planning Authority constituted under Section 40 of the
    Maharashtra Regional Town Planning Act is not required to be covered by
    the provisions of the Act relating to preparation of Draft Development Plan
    and the conclusion of the High Court on that score is thus vitiated. It is also
E   contended that the Regulations in question having been framed by CIDCO in
    exercise of power conferred under Section 159(l)(a) of the Maharashtra
    Regional Town Planning Act, which is known as the New Town Disposal
    Regulation, 1992, and the disposal of lands impugned in the Writ Petition
    having been made in accordance with the said prescribed procedure under
    the Regulation, the High Court should not have interfered with the same,
F   particularly when there has been no allegation of corruption and nepotism in
    the matter of allotment of land, much less any proof of the same. It is
    vehemently urged that the question of distribution or sale of land for
    establishment of a New Township in the context of an abnormal growth of
    the city of Aurangabad, is essentially a matter of policy and whether the sale
G   of bulk plots is more profitable or beneficial subserving public interest or not
     is a matter of policy and such policy decisions would not have been interfered
    with by the High Court in exercise of its power of judicial review under
    Article 226 of the Constitution, when it has not been established how the
    aforesaid policy was erroneous or it caused any injustice to the public interest.
    According to the learned counsel the so-called approval required under Section
H    115 of the MRTP Act having been granted by the Government of Maharashtra,
         PAD MA v. HIRALAL MOTILAL DESARDA (PA TT ANAIK, J.]             189
the Court ought not to have interfered with the allotment of land made. A
According to the counsel for the petitioner the legality of allotment of land
from survey Nos. 23 and 24 could not have been examined by the High
Court in the absence of any pleadings in that respect and, therefore the
impugned judgment cannot be sustained. It is further urged that the change
of user or development of land is permissible with the permission of the B
Planning Authority and once the Planning proposal is published in the gazette
there is no restriction on transfer of ownership. The learned counsel further
contended that under Section 31 of the Act the State Government is required
to approve the plan within one year and if this is not done within the said
period then the restrictions under Section 43 will not be attracted. The learned
counsel lastly urged that in respect of several plots of land constructions C
having already been made and the Appropriate Authority of the government
having approved the development as well as proposal of bulk disposal of
plots it is fully inequitable to cancel the allotments made and also the direction
of the High Court works out gross injustice.

       The learned counsel appearing for respondent no. I, however, D
vehemently urged that the findings of the High Court tantamount to a finding
of fraud committed by CIDCO in the matter of allotment of land and therefore
fraud vitiates every action of the authority. It is urged that the Director of
CIDCO as well as the Chief Administrator have allotted plots to themselves
and their family members which on the face of it is illegal and such an E
allotment could not have sustained the scrutiny of any Court of law. According
to the learned counsel the price fixed for allotment was even lower than the
base price of Rs. 1,500 per sq. metre and this could not have been done
without the board's agreement which was required under the CIDCO
publication title "New Aurangabad Guidelines". The counsel urged that there
has been allotment of land at a price of Rs. 1,300 per sq. metre which was F
done without re-advertising or tendering. So far as procedural irregularities
are concerned, the counsel urged that the applications were entertained without
any formal application and even without any payment of earnest money and
allotments were made to the parties even who never had made any application
for the same. It was also vehemently urged that the very method of sale of G
bulk plot caused serious financial loss to the CIDCO and no court should
permit such sale at the cost of public exchequer. lt was also urged that the
proposal of CIDCO to the State Government for sale of bulk plots to the
builders was never notified and as such there has been an infraction of Section
115(2) and (3) of the Regional Town Planning Act. The counsel urged that
when the Cou11 on consideration has found serious financial and procedural H
    190                        SUPREME COURT REPORTS [2002) SUPP. 2 S.C.R.

A irregularities and the findings arrived at would lead to an irresistible conclusion
    that fraud has been perpetrated in the matter of allotment, it was just and
    proper for the High Court to set aside the allotment made, and therefore, this
    Court should not interfere with the same in exercise of its power under
    Article 136 of the Constitution.

B         The troubled part of story, with which we are concerned, has its genesis
  in certain events seated around the year 1998-99. Two significant events
  occurred in that period of time. Out of several acres of land acquired by
  CJDCO for developing the township of New Aurangabad, 120 housing
  societies had come into existence over 136 plots and some 39 societies were
C relocated in accordance with the developed scheme of CJDCO. What had
  remained was 3.3% of land earmarked as 'developable land'-to be developed
  in accordance with development scheme to be sanctioned by the State
  Government which would obviously depend inter alia on the relevant factors
  to be assigned weight in the light of the development which had taken place
  till then and keeping in view the needs of the population already accommodated
D in vicinity and/or the township already emerged and yet aspiring for still
  better quality of life and better fulfillment of its needs in future consistently
  with the needs of modem living standards. CIDCO, which was till then
  engaged in allotting plots to citizens or societies for construction ofresidential
  dwellings and building up multi-storey buildings catering to small and medium
E sized apartment requirements of families and selling them was yet to pass on
  and enter into the three facet of its developmental activities, i.e. developing
  commercial and shopping centres so as to cater to the needs of the individuals
  and families settled in the township. Left with 3.3% of developable land only
   it dawned upon CIDCO that insofar as the notified area is concerned its
  developmental activities were nearing their end and CIDCO would be better
F advised to hand over the township to Aurangabad Municipal Corporation to
   be looked after in accordance with the municipal law governing it. Suddenly
   CIDCO dropped the idea of developing the township further in accordance
   with the development plan which was yet to be sanctioned by the State
   Government and thought that it would be profitable to hold bulk sales of
G remaining land and earn a lot of money therefrom and thereby enrich itself.
   We can understand an individual being overpowered by greed; however, here
   what the High Court notices is greed of an institution-an institution, the·
   primary object whereof is not solely to earn money but to serve the people
   through activities in tune with the avowed objects with which it has been
   found and as set out in the earlier part of this judgment. However, as the
H several findings arrived at by the High Court and noticed shortly hereinafter
         PAD MA v. HIRALAL MOTILAL DESARDA [PA TT ANAIK, J.)                 191

would show the greed was implanted into the in.stitution by builders who had A
an eye over the left-over developable land so as to grab the same by prevailing
over CIDCO and manipulate allotment to their own commercial advantage.
Lest we should digress and drift away, we revert back to notice yet another
event. In the year 1998, Section 80-IB of the Indian Income Tax Act, 1961
was amended by Parliament whereby payment of income tax was exempted
on income derived from the housing projects commenced and completed B
between I. I 0.1998 and 31.3 .200 I. The object of amendment was to give a
boost to house building activity in big cities. Another requirement of the
exemption was that the project claiming benefit of the exemption ought to be
on a piece of land with a minimum area of one acre and the residential units
shall not exceed 1500 sq. ft. A sense of hurry is writ large on the movements C
ofCIDCO displaying an anxiety to dispose of the land by bulk sale and earn
money before the proposal for handing over the township to Municipal
Corporation could materialize. Advertisements were inserted in the newspapers
inviting tenders for disposal of bulk land out of survey Nos. 23 and 24 of
Garkheda village in 'B' sector, i.e. the land situated on the south of Jalna
Road, wherein was included 19.53 hectares ofland forming part of the survey D
Nos. 23 and 24. Out of this area, 2.59 hectares area of land was parted with
in favo:ir of some land owners through negotiations. 16.94 hectares area of
land was still available.

        At this point of time, the public interest litigation came to be filed on   E
 19.5.1999 knocking the doors of the High Court when it was closed for
summer vacation. The High Court felt that the issue raised in the petition
calls for its attention. Notices were issued to CIDCO and other respondents.
By an interim order proceedings for acceptance of the tenders and thereafter
were directed to remain stayed. The High Court soon realised that the issue
of public interest raised in the writ petition required the conduct of the case     F
not to be left in the hands of the writ petitioner alone, and therefore, by its
order dated 7.12.1999 appointed an amicus curiae to assist the Court. However,
a little later it was brought to the notice of the High Court that the original
writ petitioner was not carrying on well with the amicus curiae and to avoid
the conflict the High Court chose to proceed with the hearing of the petition       G
dispensing with the assistance of the amicus curiae. The fact remains that the
litigation had assumed the character of a public interest litigation of wider
scope, not necessarily confined to grievance raised by the writ petitioner and
the High Court was intervening to bring under its scrutiny, on the well settled
parameters of public interest, the proceedings of CIDCO relating to attempted
disposal of developable land. While hearing a public interest litigation the        H
    192                        SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A constitutional court acts as the sentinel on the qui vive discharging its obligation
  as custodian of the constitutional morals, ethics and code of conduct - well
  defined by series of judicial pronouncements. The Court is obliged to see
  while scrutinising the conduct and activities of a public body constituted with
  the avowed object of serving the society to see that its activities bear no
B colour except being transparent, are guided with the object of public good
  and are within the four corners of law governing the same. The holder of
  every public office hold a trust for public good and therefore his actions
  should all be above board. Whatever may have been the grievance raised in
  the writ petition filed by the original writ petitioner, vide its order dated
  28.4.2000 the High Court framed the following four questions laying down
C the scope of hearing before it:-
           •(a)   Whether CIDCO should be allowed to resort to bulk land sale as
                  a normal course of its activities?
            (b)   Whether such an action by C!DCO is permissible in the public
                  interest vis-a-vis its objectives?
D
            (c)   Whether the bulk land sale transactions made in the recent past
                  and more particularly after the petitioner has· approached this
                  court have been dubious in nature and they have been made by
                  giving a go-bye to the Rules and Regulations as well as objectives
                  of CIDCO?
E
            (d) Whether the plots have been allotted at a price much lower than
                the base price and this has resulted in a substantial loss to C!DCO?

     We have set out the above said part of the High Court proceedings to meet
     plea raised by the appellants before us which complains of want of pleadings
F    and denial of necessary oppo1tunity of defending themselves at the hearing
     in the writ petition. The High Comt had, by having framed the abovesaid
     questions, put all the parties before it on notice that it proposed to enter into
     issues wider than what may have been raised in the writ petition filed before
     ii. The non-petitioners in the High Court, including the appellants before us,
G    were put on notice of the issues on which the High Court proposed to dwell
     upon and they were allowed full opportunities of defending themselves by
     bringing in such pleadings and documents as they proposed to do in their
     defence. The High Court called for the record of CIDCO and subjected the
     same to scrutiny under its magnifying glass of judicial review. The non-
     petitioners in the High Comt were well aware ofCIDCO record of proceedings
H    and the findings of the High Court are based on the facts discernible from the
         PADMA v. HIRALALMOTILALDESARDA[PATTANAIK,J.]                       193

records and the factual inferences necessarily and inevitably flowing therefrom.   A
In public interest litigation jurisdiction the Constitutional Court is mobilized
and acts for redressal of public injury, enforcement of public duty, prntection
of social rights and upholding constitutional and democratic values.
Technicalities do not deter the Court in wielding its power to do justice,
enforcing the law and balancing the equities. We are unhesitatingly of the         B
opinion that the appellants before us cannot raise any grievance on the ground
of want of necessary pleadings.

      The private respondents joined before the High ·Court can be grouped
into three:

       (a)   Sethes Cooperative Housing Society, respondent No.7 and Judges        C
             Cooperative Housing Society, respondent No.8 - The allotments
             to these two do not appear to have materialized and therefore as
             to these respondents the High Court has not roade any direction.
             In any case the controversy as regards these two is not the subject
             matter of proceedings before us.                                      D
       (b) Mrs. Padma representing Tapadia Construction Pvt. Ltd.,
           respondent No.9, (hereafter referred to simply as 'Tapadia', for
           short).
       (c) Aurangabad Ajanta Bahu Udeshiya Seva Sanstha, CIDCO,
           Aurangabad, respondent No.5, Suchita Housing Society,                   E
           Aurangabad, respondent No.6 and Aurangabad Holiday Resort
           Pvt. Ltd., respondent No. I 5.

The allotments to group 'b' and group 'c' above though made during the
same period oftime and suffering from vitiating factors of more or less equal
magnitude yet have some essential difference which· will have a bearing on         F
constructing the ultimate relief to be given and therefore we have carved out
these groups. The High Court has also, during the course of its judgment, set
out the facts referable to these two groups with some margin of differentiation.

      So far as the facts, and the findings flowing from the documents, are
concerned, for the purpose of this judgment, it would suffice if we extract G
and reproduce the gist thereof from the detailed and well cast judgment of the
High Court inasmuch as after affording full-dressed hearing to the learned
counsel for the parties we are satisfied that so far as the findings of fact are
concerned no fault can be found with the ones arrived at and recorded by the
High Court in its judgment. We proceed accordingly.                              H
    194                    SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A          Shri Sambhaji Pawar, respondent No.12, has been a Director of CIDCO
    between 1995 and 1999. Aurangabad Ajanta Bahu Uddeshiya Seva Sanstha
    ('Sewa Sanstha', for short), Suchita Housing Society and Aurangabad Holiday
    Resorts Pvt. Ltd. ('Holiday Resorts', for short), as the facts found by the
    High Court go to show, are nothing but alter-ego of Shri Sambhaji Pawar,
    respondent No.12. There is every reason to draw a deduction that these legal
B   entities of different colour and shade were brought into being around the
    crucial period of time and almost just following the point of time when the
    idea of disposal of the developable land through bulk sale had dawned upon
    the CJDCO wherein Shri Sambhaji Pawar was a Director. These three entities,
    though each appearing in a legal cloak outwardly, were in fact family affair
C   of Shri Sambhaji Pawar, respondent No.12. While these legal entities were
    entering the portals of CIDCO from the front door demanding its developable
    land, the respondent No.12 was already inside the portals to welcome theni
    and exercise his influence--and if not influence at least his contacts within-
    to enable the land being parted with in favour of his own alter-egos.

D        First, we shall see how the proposal for allotment of land by bulk sale
    was mooted and pushed through and how its pricing was done.

         On 15.1.1999 was published the CIDCO proclamation inviting tenders
  for bulk sale of four plots designated as plot nos. A, B, C and D. Only three
  tenders were received. The tenderers included Shri Gaud and Pandey and M/
E s. Tapadia Construction Ltd. As against the minimum acceptable price of Rs.
  120 l per sq. meter set out in the proclamation the tenderers offered Rs. 95 I
  for plot C and Rs.1224 for plots Nos. A, B, C and D. One Shri B.G. Ajmera,
  styling himself as 'Director of proposed private limited company' made an
  offer of Rs. 1201 per sq. meter. All the tenders being below the minimum
p price were rejected and the earnest money deposited by the tenderers was
  directed to be refunded. All the tenders were defective, not liable to be
  accepted, in view of their suffering from one or other shortcomings taken
  note of by the Administrator of CIDCO in his note dated I 8.2. I 999 and put
  up on 25.2.1999 recommending cancellation of all the tenders. Of their own,
  the ten~erers started negotiations and revision of their offers. On 20.4.1999,
G Shri Ajmera made a representation revising his offer of Rs. 1300 per sq. meter
   for plot A. This revised offer was endorsed by the Administrator on 28.4. I 999
   recommending allotment of plots A and D, having an area of 4182 sq. meters
   each to Shri Ajmera. The Joint Managing Director, having held a discussion
   with the Administrator and the Chief Economist of CIDCO, opined in favour
H of counter offers of the base rate for these plots which was Rs. I 500 per sq.
          PAD MA v. HIRALAL MOTILAL DESARDA [PATT ANAJK, J.]              195

 meter being mooted to the tenderers. On 29.4.1999, the counter offers were A
 sent to all the three tenderers calling for their response within three days. On
 13.5.1999, Tapadia responded by revising its offer to Rs. 1300 per sq. meter
 for two or four plots whereas Ajmera revised his offer to Rs. 130 I per sq.
 meter for four plots, viz. A, B, C and D.

       On 13.5.1999, CIDCO issued tender notices for sale of bulk plots from    B
 survey no. 70 of Mukundwadi and survey No.23 and 24 of Garkheda (south).
 Plots Nos. A, B, C and D were excluded from the tender notice. At this point
 of time the writ petition came to be filed.

         On 26.5.1999, the Administrator, CIDCO put up a fresh note to the
  Chief Administrator (NT) wherein it was stated that the Chief Economist had C
  fixed the base rate at Rs. 1300 per sq. meter. Chief Administrator (NT) had
  fixed the base rate at Rs. 1400 to Rs.1500 per sq. meter and that was being
  given a wide publicity through brochures published and released by CJDCO.
· Attention of the Chief Administrator was invited to the fact that the Court
  had by an oral order directed the sale proceedings of bulk plots to be stayed D
  till 11.6.1999, the next date of hearing. The note mentioned Ajmera's offer
  to take all the six plots. On 28.5.1999, the Chief Administrator submitted a
  note for approval of the Joint Managing Director for giving the six plots to
  Ajmera @ Rs. 1300 per sq. meter. The Chief Economist, in his note dated
  31.5.1999, expressed his mild dissention by pointing out that the counter
  offers under consideration were equal to the base rate but below the rate E
  printed in the brochures issued by CIDCO. The Chief Economist advised the
  counter offer rate of R,s.. 1300 per sq. meter being accepted in view of the
  poor response of offers. But at the same time he suggested the plots being
  advertised afresh at a fixed rate of Rs. 1300 per sq. meter for allotment on
  'first come first serve' basis. In either case, the Chief Economist advised the F
  proposal being approved by the Board before being accepted. The General
  Manager (Admn.) of CIDCO, in his note dated 1.6.1999, advised for the
  result of the writ petition pending in the High Court being awaited before
  taking any decision. The Joint Managing Director, in his note dated 2.6.1999,
  sounded a note of caution in the interest of CIDCO. He said that if the plots
  in question which were frontline plots abutting on the roads were disposed G
  of at the rate of Rs.1301 per sq. meter the price of the plots situated away ·
  from the roads would be lesser than Rs.1300 per sq. meter, and therefore, in
  his opinion, the counter offers deserved to be rejected. On 16.6.1999, the
  Chief Administrator(NT) put up a note which in the opinion of the High
  Court is 'surprising' apparently for its somersault and vagueness. It states H
    196                     SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A ·that the case was discussed with the Joint Managing Director on 9.6.1999 at
    his residence \vhen the Administrator was also present and CIOCO could
    proceed furtlier ·as per the instructions given by the Joint Managing Director·
    during the course of discussion on 9.6.1999 without placing on recol"d what
    those instructions were. On the next day the same authority directed plots
    Nos. A and B to be allotted to Ajmera and plots Nos. C and D to be allotted
B   to Tapadia. This was approved by the Joint Managing Director on 24.6.1999.
    Ajmera's offer in respect of plots No. E and F was rejected. Another striking
    feature of the allotment is that allotment letters to Holiday Resorts in respect
    of plots No. A and B and to Tapadia in respect of plots No. C and D were
    issued by the Administrator, CIDCO on 21.6.1999 although the approval of
C   Joint Managing Director is dated 24.6.1999 and the approval of the Board of
    Directors, which was insisted on by the Chief Economist in his note dated
    31.5.1999, was never obtained. While plots No. A, B, C and D were so
    allotted, the tender notice in respect of plots other than these issue'd on
     13.5.1999 was cancelled in view of the pendency of the writ petition in the
    High Court in view of the note put up by the Administrator, CIDCO (on
D    16.9.1999).

         Tapadia and Holiday Resorts were required to pay the first instalment
  of the leased premium on or before 21.7.1999 and the second instalment on
  or before 21.8.1999. The possession over the plots was to be handed over
E only after the entire lease amount was paid and documentation legally done.
  It is pertinent to note that the letters of allotment mention the use of land only
  as bulk land and do not specify as to whether the plots could be used for
  residential or commercial or what purpose. The Court having been apprised
  of the issuance of allotment letters, vide its order dated 19.7.1999 directed
  CIDCO not to proceed further in the matter. Now CIDCO was advised by
F their counsel not to execute the agreement and hand over the possession of
  the plots to allottees and so the CIDCO called upon the allottees to receive
  the amount deposited by them. But the allottees in their tum insisted on
  documentation and delivery of possession making it plain that it was for
  CIDCO to have the order of the High Court vacated or modified. On 18.1.2000,
G by an interim order, the Court directed execution of agreements of lease
  whereafter lease deeds also came to be registered in May, 2000. Copy of the
  order dated 21.5.2000 passed by the Division Bench of the High Court, brief
  obviously as it is, shows the applicant allottees had appealed to the High
  Court into passing of the order by highlighting that unless that was done the
  allottees would be deprived of the benefit of income-tax exemption which
H loss would be irreversible. Each of the applicants undertook to pay any
         PADMA v. HIRALAL MOTILAL DESARDA [PATTANAIK,J.]                  J97

difference in premium which the Cou1i may find ultimately to be payable         A
additionally by them.

      The High Court has pierced the veil of respondents Nos. 5, 6 and 15.
At the very outset let it be noted that Aurangabad Ajanta Bahu Uddeshiya
Seva Sanstha, CIDCO, Aurangabad, respondent No.5, Suchita Housing Society,
respondent No.6 and Aurangabad Holiday Resorts Pvt. Ltd., respondent No.15 B
have all but one address, i.e. 'Raj Heights', Town Centre, Behind Fire Brigade,
CIDCO, Aurangabad. The same is the address of Shri Sambhaji Pawar,
respondent No. 12. The allotment of land secured by him, through his
projections has been about 7 acres of such valuable land. Sewa Sanstha, the
respondent No.5 claims to have been registered as a society under the Societies C
Registration Act, 1860 on 29.9.1998. It also claims to have applied on
17.8.1999 for allotment of bulk land for developing a sports club and
maintenance of play field. This vague expression employed by Sewa Sanstha
outwardly sound to be very benevolent as if the sports club and a play field
are meant for serving the inhabitants of New Aurangabad. However, the
Sewa Sanstha came to be registered as a public trust on 6.2.1999 under the D
Bombay Public Trust Act, 1950. The list of trustees too is revealing. Shri
Sambhaji Pawar, respondent No.12, who was already holding the office of
Director in CIDCO, is one of the trustees in the above said trust and the other
trustees are his. wife, his son, his daughters, his aunt, his niece and so on. The
High Court has found it as 'abundantly clear' that it was a trust managed by E
Shri Sambhaji Pawar, his family members and close relations.

       Suchita Housing Society, respondent No.6, has as its members most of
whom are either the family members of Shri Sambhaji Pawar, the respondent
No.12 or his close relations/friends and some senior government officers.
Beyond this we need not dwell further in view of the High Court having p
noticed that the allotment of land by CIDCO to this society was at a later
stage cancelled by CIDCO itself and that cancellation is sub-judice in some
other writ petition filed by the respondent No.6. We are taking note of this
fact here for the limited purpose that there were at least three entities bearing
legal cloaks projected by Shri Sambhaji Pawar, the respondent No.12 soliciting
allotment of land from CIDCO.                                                     G
      The Holiday Resorts. respondent No.15, does not have a different story
to be told about. The High Court has found that Shri Sambhaji Pawar was
directly connected with this company and Mrs. Aruna Patil, another Director,
is a family member of Shri Sambhaji Pawar, respondent No.12. The list of
Directors of this company is not on record and was also not revealed either H
    198                     SUPREME COURT REPORTS (2002] SUPP. 2 S,C.R.

A to the CIDCO or to the High Court. The fact is, as we will notice shortlv
    hereinafter, that although the decision of Joint Managing Director of CIDCO
    was to allot plots to Ajmera yet ultimate allotment was made to Holiday
    Resorts. CIDCO never bothered to find out how Ajmera was acting for Holiday
    Resorts or had any interest therein whether as a Director, as a major share
B   holder or as any official of the limited company.

          Having said so much to reveal the real identity behind respondent
    No.5, 6 and 15 as found by the High Court we revert back to the facts found
    by the High Court touching the allotment of land and termed at one place by
    High Court as 'surprising and shocking'.
c          By letter dated 27. 1.1999, CIDCO allotted 18015 sq. meters plot to
    Sewa Sanstha. On I 1.5.J 999, lease agreement was entered into between
    CIDCO and Sewa Sanstha. Possession slip was also issued to Sewa Sanstha
    which slip does not bear any date. Out of the total area of land it is stated
    that an area admeasuring 4114 sq. meter would be used for 'construction of
D   sports building' and 1390 I sq. meter would be used 'as per wishes of the
    trust/lessees'. Such proposed users are disclosed by the documents as drafted.
    However, once the lease deed was ready and before it was presented for
    registration there is an insertion made in hand which goes on to say that an
    area admeasuring 4118.04 sq. meter would be used for commercial purpose
    (sports club) and balance of area admeasuring 13901 sq. meter would be used
E   as play field without any FSI but the ownership of play field will be with the
    lessee. All this is in the background that such user, vague and uncertain as
    it is, was so kept by employing choicest expression and is not supported by
    any resolution or decision of CIDCO. The allotment as per recitals of the
    lease deed purports to have been made pursuant to the resolution dated
F   22.12.1998.

          The allotment of land made to Sewa Sanstha, the respondent No.5
    suffers from several serious infirmities. An area of about 4 acres has been
    parted in favour of respondent No.5 without affording other competitors or
    rivals an opportunity of participating in the bid at the price at which it has.
G   been parted with. The revised development plan of CIDCO as regards this
    allotment was pending with the Goverrment of Maharashtra for approval as
    required by Section 115 of the Act and was not cleared by the State
    Government. The parting with has been without any transparency and almost
    in secrecy.                                                                     ..
H          A marginal percentage of a huge chunk of land was kept reserved in
         PAD MA v. HIRALAL MOTILAL DESARDA [PA TT ANAIK. J.)               199
the development plan for development in accordance with requirements of            A
future expansion obviously which should be guided by the paramount
consideration of catering to the needs of those who have already become a
part and parcel of development and expansion till then. That is why the law
 insists on a development plan being sanctioned at the level of the State
Government where the decision is taken in consultation with experts in the
field of planning. The High Court which is closer to realities prevailing in       B
Maharashtra has made a pertinent observation during the course of its
judgment. The High Court has noted-"There is nothing on record as to what
is meant by sports club, specially when it has been stated in the agreement
that it is for commercial use. The term 'sports club' has acquired a dubious
meaning in the recent past and more particularly in and around Aurangabad          C
city. It is common knowledge that some Five Star Hotels have been named
as sports club. In the absence of specific purpose for the utility of such plots
it was totally unwarranted and unlawful for CIDCO to allot the land to
respondent No.5."

       Now, we take a quick note of some out of the several infirmities and D
vitiating factors found by the High Court touching the allotment of land to
Holiday Resorts. The tender submitted by Ajmera in February 1999 which
was for plot No.A only seeking allotment to a proposed private limited
company which was yet to come in existence and yet to be named even, was
cancelled by CIDCO. The process of allotment had originated by inviting E
tenders. On 20.4. I 999, Ajmera submitted a letter showing his interest in
allotment of plots No. A and D @ Rs. I 300 per sq. meter. This proposal by
Ajmera was in a tender and certainly not accompanied by any earnest money
deposit. The EMO submitted alongwith his tender in February 1999 was for
one plot and that too had been directed to be refunded. It had no relevance
nor adequacy to act as EMO for the offer dated 20.4.1999. CIDCO's response F
to Ajmera's proposal was in the negative grounded on the minimum rate
acceptable by CIDCO being of Rs. 1500 per sq. meter. Now on 1.5.1999,
Mrs. Aruna Patil stepped in joining Ajmera and informing that they were
interested in all the four plots i.e. plot Nos. A, B, C and D. Needless to say
this proposal is neither a tender nor accompanied by any EMD. We have G
already noticed the Managing Director's decision dated 24.6.1999 in favour
of allotment of plots No. A and B to Ajmera but the decision preceded by
allotment letter dated 21.6.1999 by Administrator, CIDCO in favour of Holiday
Resorts for plots No. A and B. On the same day, Holiday Resorts submitted
its Certificate of Incorporation and Memorandum of Association to CIDCO
projecting as if this was the private limited company in the mind of Ajmera H
    200                     SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A   when he had submitted his tender in February 1999. Even in the affidavit
    filed in the High Court, as late as on 30.8.2000, Ajmera, irnpleaded as
    respondent No.IO in the writ petition. does not indicate how and in what
    manner he was connected or associated with Holiday Resorts, a private limited
    company. The High Court has noted it as a 'mystery' the failure on the part
    of the record of CIDCO to reveal as to how and under what circumstances
B   on 21.6.1999 the Administrator, CIDCO issued letter of allotment in favour
    of Aurangabad Holiday Resorts Pvt. Ltd. touching plots No. A and B though
    Ajmera had not at all till then revealed the name and particulars of M/s.
    Ajmera Holiday Resorts Pvt. Ltd. In the opinion of the High Cou1i the issuance
    of letter of allotment in the name of such company was most uncalled for. ·
C   There was some ghost-play indeed inasmuch as the learned Judges of the
    High Court meticulously compared the signatures of Ajmera appearing at
    various places in the numerous letters addressed to CIDCO purportedly by
    him and found such variations in the signatures that they were doubtful if the
    letter dated 15.6.1999 was at all signed by Ajmera.

D         The Board of CIDCO had never approved the allotment of lands to
    Ajmera or Holiday Resorts, though the same was insisted on by the Chief
    Economist in. his note. The minimum price notified by CIDCO in its various
    brochures which was Rs 1500 per sq. meter was given a go-by apparently
    for no reason and certainly without a specific approval in this regard by the
E   Board or anyone vested by competence to do so. Here it may be noted that
    pursuant to order dated 28.4.2000 of the High Court, the CIDCO had called
    for tenders for smaller size plots in place of bulk land and the response was
    overwhelming. The tenderers were too willing to pay a price more than the
    lease price of Rs. 1750 and demand was out of proportion tJ what C!DCO
    could meet. The letter of allotment to Holiday Resorts does not set out the
F   nature of land user which the allottee would be competent to do. The tender
    by Ajmera having been cancelled there was no occasion for allotment in
    favour of Ajmera or Mrs. Aruna Patil or two of them or Holiday Resorts
    except by affording others also an opportunity of availing the allotment at the
    rates at which it was done to Holiday Reso11s.

G         Allotment of land to Tapadia need not be dealt with by extensively
    dealing with findings arrived at by the High Court in this regard. Suffice it
    to observe generally that it suffers from infirmities and deficiencies of more
    or less the same magnitude as the High Court has found attaching with the
    allotments in favour of Sewa Sanstha and Holiday Resorts. In view of the
H   ultimate directions which we propose to make in partial modification of those
         PAD MA v. HlRALAL MOTILAL DESARDA [PATT ANAIK.J.J                 20 J

made by the High Court it would suffice for us to note that allotment for any     A
price less than Rs. 1500 per sq. meter except by approval of the Board of
Directors of CIDCO or any other authority competent in this regard and
except by affording others an opportunity of competing with Tapadia in the
matter of allotment of land at the rate at which it was allotted to Tapadia
cannot be sustained.
                                                                                  B
       Very sale of bulk land by an institution like CIDCO is an anathema to
 its objective and purpose of its establishment. Large scale land acquisitions
 were made by the Government of Maharashtra and land handed over to
 CIDCO for planned development of the township of New Aurangabad. The
 development plans were finalized and approved by the State Government            C
whereon CIDCO acted and marginal land was left out of decision by the
State Government at that point of time and it can safely be ·assumed that it
was a conscious decision to plan the development of such left over land at
a later and appropriate point of time by which point of time the other land
stands utilized so as to keep in view the till then development over major part
of the acquired land, its trend and needs and the march of times. The State       D
Government could have approved a development plan for the land left out
from planning earlier and earmarked only as 'developable land' so as to cater
to the needs of the township which had come into existence by that time
guided by the requirements of healthy human living. By no stretch of
imagination it can be contemplated that it was or could have been intended        E
either at the time of acquisition or at the time of sanction of development
plans by the State Government that at some point of time in future the
developable land would be available to be disposed of by bulk sale and that
too in favour of professional builders. That is why a condition was imposed
that the developable land shall be available for being utilized in accordance
with the plan to be sanctioned by the State Government at a later point of        F
time.

       Laws dealing with development planning are indispensable to sanitation
and healthy urbanization. Development planning comprehensively takes care
of statutory, manual, administrative and I.and-use laws hand in hand with
architectural creativity. In the words of a well-known architect, development     G
planning is the DNA of urbanization the genetic code that determines what
will get built. A development plan is essential to aesthetics of urban society.
American Jurisprudence 2d (Volume 82, at page 388) states: "'Planning', as
that term is used in connection with community development, is a generic
term, rather than a word of art, and has no fixed meaning. Broadly speaking,      H
    202                      SUPREME COURT REPORTS [2002) SUPP. 2 S.C.R.

A however, the term connotes the systematic development of a community or
    an area with particular reference to the location, character, and extent of
    streets, squares, and parks, and to kindred mapping and charting. Planning
    has in view the physical development of the community and its environs in
    relation to its social and economic well-being for the fulfillment of the rightful
B   common destiny, according to a "master plan" based on. careful and
    comprehensive surveys and studies of present conditions and the prospects of
    future growth of the municipality, and embodying scientific teachings and
    creative experience."

          The significance of a development planning cannot therefore be denied.
C Planned development is the crucial zone that strikes a balance between the
    needs of large-scale urbanization and individual building. It is the science
    and aesthetics of urbanization as it saves the development from chaos and
    uglification. A departure from planning may result in disfiguration of the
    beauty of an upcoming city and may pose a threat for the ecological balance
    and environmental safeguards.
D
         It is not disputed that CJDCO is supposed to carry out its activities on
  'no profit no loss' basis and that is the basis on which CJDCO, as per its own
  case, has been acting until it decided to part with the chunk of developable
  land by bulk sale which proposal was obviously in departure from the policy
  of serving on 'no profit no loss' basis such people as were craving for a roof
E over their heads. The High Court while dealing with this aspect of the matter
  has assigned several convincing reasons why the very concept of sale of bulk
  land cannot sail with CIDCO, either in law of in propriety. Assuming that an
  extraordinary situation-which there was none-had warranted a policy
  decision for bulk sale the decision should have been of the Board and
p accompanied by reasons. Jn the present case, if only the proposal would have
   been placed before the Board of CIDCO in all probability it would have been
  discarded. It is pertinent to note that good number of officials, through whose
   hands the proposal passed while travelling up, were not agreeable to and had
  their own reservations on the proposal of such bulk sale. What prevailed with
  one or two of those placed at the higher rung of bureaucratic ladder in
G permitting such bulk sale in hot haste defies explanation for the simple reason
   that in the decisions available on the note sheets of the record looked into by
   the High Court no reasons have been assigned in favour of endorsing the
   proposal for bulk land sale. We are not prepared to accept even for a moment
   that there was no demand of land. Even if the development plan for the
H developable land was not approved by the State Government there is nothing
         PADMA v. HIRALALMOTILALDESARDA[PATTANAIK,J.]                      203
which had prevented the CIDCO from carving out small middle level and              A
larger plots which those who can afford would have certainly been prepared
to take and build small, middle level or spacious houses or bungalows for
their own residential requirements. This find support from the overwhelming
demand of land which the High Court has noted and which demand the
CIDCO had found out of proportion as compared to the availability of land
with it. The decision for bulk land sale cannot be said to have been taken in      B
public interest. The High Court has rightly observed in its judgment that
some public institutions who were allotted large pieces of land have developed
parks and gardens but they are not open for free access by people generally.
The local residents and children must have place enough to be used as parks,
gardens and for entertainment which not only act as lungs and ventilators for      C
suffocating growth of population but also add luster and beauty to the township.
The utility of such pieces of land acting as buffer for maintaining ecological
balance and environmental demands needs no emphasis. We entirely agree
with the reasons of the High Court and the observations made by it while
recording its strong disapproval of bulk sale.
                                                                                   D
       There is yet another angle of looking at the propriety of the questioned
bulk sale of land by CIDCO and the manner in which it was done. The land
acquired and entrusted to CIDCO cannot jJst be permitted to be parted with
guided by the sole consideration of money-making. CIDCO is not a
commercial concern whose performance is to be assessed by the amount it E
earns. Its performance would be better assessed by finding out the number of
needy persons who have been able to secure shelter through CIDCO and by
the beauty of township and quality of life for people achieved by CIDCO
through its planned development schemes. So long as such objectives are
fulfilled CIDCO's operation on 'No-profit-No Loss' basis cannot be found
fault with. There should have been no hurry on the part of CIDCO in disposing F
of the balance land and that too guided by the sole consideration of earning
more money. Even that object the CIDCO has not been able to achieve for
at the end it has parted with land at a price less than Rs. 1500 per square
meter-the reserved price. Even if a sale of left-over land was a felt-necessity
it should have satisfied at least two conditions: (i) a well-considered decision G
at the highest level; and (ii) a sale by public auction or by tenders after giving
a more wide publicity than what was done so as to attract a larger number
of bidders.

      It was contended that Shri Sambhaji Pawar, the respondent no.12 was
not a party to any of the decisions whereby the land was allotted to Sewa H
    204                     SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A   Sanstha, Suchita Housing Society or Holiday Resorts (respondent nos. 5, 6
    and 15 respectively) and therefore the allotment is not vulnerable on this
    count. We are not impressed. Shri Sambhaji Pawar was holding a public
    office and that too in CIDCO. If he directly or indirectly proposed to deal in
    property and in the course of such business activity to encounter with CIDCO
B   then he should have not accepted the directorship of CIDCO. Else if he was
    motivated with the idea of serving the society by being a Director of CIDCO
    he should have seen that he cautiously kept away from directly or indirectly
    dealing with CIDCO. The least that was expected of him was to have informed
    CIDCO very specifically that the respondent nos. 5, 6 and 15 consisted of his
    family members and/or relations and CIDCO while dealing with them should
C   be consciously aware of this. Such standards are required to be maintained
    by public office-holders in the interest of probity in public life.

           For all the foregoing reasons we find ourselves in agreement with the
    conclusion arrived at by the High Court holding the impugned sales to be
    vitiated.
D
       • It was urged during the course of hearing that the H~gh Court should
    not have entertained the writ petitior, filed by the respondent no. I herein who
    was a business competitor of respondent nos. 5, 6, 9 and 15. This submission
    has been noted only to be rejected for several reasons. Firstl;r, we do not find
    the respondent no. I having figured anywhere in or arou~d the impugned
E   transactions of sale. He was not bidding with any of the 1espondents who
    have been successful in securing allotment of land. Merely because at
    sometime in the past the respondent no.1 had himself secured some allotment
    of land from CIDCO that would not mean that he was a business competitor
    so far as the impugned transactions are concerned though he might be a
p   business competitor otherwise for which we find no material available to
    hold so. Secondly, the High Court has found the respondent nos. 5, 6 and 15
    having been born just around the year 1998-99 and therefore· the question of
    their being in existence at that point of time and hence n rivalry when
    respondent no. I had secured some allotment of land in the past does not
    arise. The proceedings in the High Court show only the ball of judicial
G   scrutiny having set rolling by the respondent no. I. Soon the High Court
     found the case fit for exercising its own public interest j·Jrisdiction, and
    therefore, the High Court framed its own issues which were not necessarily
     confined to the pleas raised in the writ petition filed by respcndent no. I. We   I
     cannot hold that the interest served by the proceedings in the High Court has
H    been anything other than pro bona publicp.
         PADMA v. HIRALAL MOTILAL DESARDA [PATTANAIK,J.]                 205
      However, so far as the relief allowed by the High Court is concerned       A
it needs a re-touching and some minor variation which we propose to do and
set out our reasons hereunder.

      We have already noticed the High Court having restrained of the
proceedings for attempted bulk sale of land by CIDCO by its interim direction
in May 2000 and the same having been brought to the notice of CIDCO, and         B
therefore, the prospective buyers as well. However, the contesting respondents
herein persuaded the High Court in modifying its order by demonstrating a
pressing necessity in that regard. Obviously any change of status quo brought
about during the pendency of the proceedings is at the risk of beneficiaries
thereof.
                                                                                 c
      Record of SLP(C) No.19687/2000 filed by Tapadia does not show that
Tapadia had anyone inside CIDCO exerting his or her influence from within
to oblige Tapadia as it has been in the case of Shri Sambhaji Pawar and his
cloaked duplicates. By 16.10.2000, the date on which Tapadia filed her
affidavit in the High Court, five buildings having 72 tenants had come up as     D
'complete' and rest of the construction was in 'full swing' with an investment
to the tune of over rupees three crores on the project for which she had taken
a loan of about rupees one crore from the bank and rest from other sources.
Vide para 30, the High Court has noted the contention of Tapadia, the
respondent No.9, that it had already constructed multi-storeyed building         E
consisting of residential apartments and those apartments were ready for
allotment; in all 132 tenements had been constructed on plot No. C and D.
Several persons had booked their flats. Thus, third party interests had also
been created. These facts are not controverted in the pleadings and therefore
we do not find any reason to doubt the correctness thereof. Such flat buyers
would obviously be innocent and least wary investors craving for shelter but     F
unmindful of the consequences which awaited their lot. No useful purpose
would be served by divesting Tapadia of the land secured by her for the edge
of the axe would fall on lot of unwary buyers and investors. In such
circumstances it would meet the ends of justice if Tapadia is called upon and
compelled to pay the difference in price between the one paid by her and the
reserve price.                                                                   G

      From the pleadings and documents filed in SLP(C) No.20666/2000
preferred by Holiday Resorts, no idea can be formulated about the nature and
extent of construction, if any, done and the time by which it was done. From
the judgment of the High Court (para 28 of the paper book) we find only a        H
    206                      SUPREME COURT REPORTS (2002] SUPP. 2 S.C.R.

A passing reference wherefrom it can be gathered that 'some' building has
    come into existence over the land allotted to Holiday Reso11s. The High
    Court has in its judgment stated-"We have no alternative but to restrain the
    respondent No.15 from further proceedings of lhe cun.1·1rnctio11 work on the
    said plot and direct the respondent No. I to take possession of the land as well
B   as the building as ii exist today". There is not a slightest indication of Holiday
    Reso11s having created any third party interests. Whatever may have been
    done by Holiday Resorts it has been done only to its own advantage.

        The case of Sewa Sanstha, respondent No.5, is the worst. The pleadings
  and documents placed on the record of SLP(C) No. 20512/2000 preferred by
C Sewa Sanstha do not project (and none brought to our notice) that the Sewa
  Sanstha has made any construction, much less created any third party interest,
  so as to make the situation irreversible. We, therefore, deem it proper to
  sustain the order of the High Court directing resumption of land so far as
  Sewa Sanstha is concerned. So far as Holiday Resort is concerned, some
  further investigation is called for.
D
           Accordingly, the appeals are disposed of in terms of the following
    directions:-

            1.   On principle and in substance, the order of the High Court is
                 maintained. We agree with the High Court that the impugned
E                sales of land in favour of respondent Nos. 5, 6, 9 and 15 are
                 vitiated and hence not binding on CIDCO;
           2.    In spite of holding the sale in favour of respondent No.9 vitiated,
                 in view of subsequent events, the situation having become
                 irreversible on account of construction of vast magnitude having
F                come up and third party interests having been created, we direct
                 that the respondent No. 9 shall remain liable to pay the price of
                 the land allotted to it @ Rs.1500 per sq. meter-the reserve
                 price, within a time to be appointed by CIDCO.
           3.    The sale in favour of Aurangabad Ajanta Bahu Uddeshiya Sewa
G                Sanstha, respondent No.5, shall stand annulled, as held by the
                 High Court and the land shall revert back to CIDCO.
           4.    The land sold to Aurangabad Holiday Resorts, the respondent
                 No.15. shall be inspected, surveyed and demarcated under the
                 supervision of a highly placed and responsible official of CIDCO
                 to be nominated by its Board. Such of the land on which
H
         PADMA v. HIRALAL MOTILAL DESARDA [PATTANAIK, J.]                  207
             substantial construction· has come up rendering the situation         A
             irreversible shall be separated alongwith some more area of
             contiguous land so as to make its user practical. The total area
             of such land shall be calculated and in that regard the buyer shall
             pay to CIDCO the price @ Rs.1500 per sq. meter subject to
             adjustment for the amount already paid. Such other land on which      B
             no construction has come up or no substantial construction has
             been made shall be demarcated and revert back to CIDCO.

       5.    The difference in price, in terms of the above said direction no.
             2 and 4, shall be recovered by CIDCO by securing enforcement
             of undertakings furnished by these respondents in the High Court      C
             and by such other means and methods as may be available.

       6.    The CIDCO and all other law enforcing agencies shall see that
             the land user complies with the requirements of development
             plan and local laws and no departure therefrom shall be permitted.

       7.    Such of the land as shall revert to CIDCO shall in future be          D
             utilized strictly in accordance with the development plan
             sanctioned by State Government and after meeting with the
             approval of the Board of CIDCO.

       8.    Inasmuch as we have upheld the judgment of the High Court
             except for minor variations in the relief granted by the High         E
             Court, it shall be open to CIDCO or to any other party, for the
             matter of that, to seek directions of the High Court so as to
             implement the judgment of the High Court as sustained by this
             Court. The costs of these proceedings throughout shall be borne
             by the respondent Nos. 5, 6, 9 and 15 (in the High Court).            p
SLP (C) No.14121/2000

       We have referred to the allotment made in favour of Suchita Cooperative
Housing Society having been cancelled by CIDCO itself and the society
having filed a civil writ petition laying challenge to the cancellation. Having    G
disposed of the public interest litigation by its judgment dated 10.11.2000,
which has been dealt with hereinabove, the High Court dismissed the writ
petition filed by Suchita Cooperative Housing Society by brief order and
holding that in view of its judgment delivered earlier on the same day the
petition of the society did not survive and was liable to be rejected summarily.
We cannot find fault with the view taken by the High Court. It is interesting      H
    208                    SUPREME COURT REPORTS [2002) SUPP. 2 S.C.R.

A to note that this SLP has been filed by the proposed Suchita Cooperative
    Housing Society through Its member Satyajit Hanumantrao 13hand. The
    proposed society is petitioner No, I and Satyajit Hanumantrao Bhand is
    petitioner No.2. Copy of writ petition filed in the High Court has not been
    produced in this Court. There is no disclosure made of the members of the
    proposed society. In view of what has been stated in the main judgment
B   hereinabove we are not inclined to grant leave to appeal to these petitioners.
    The petition is dismissed,

    K.K.T.                                         Appeals/Petition disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "public interest litigation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.