OM PRAKASH GUPTA ETC.versusDIG VIJENDRAPAL GUPTA ETC.
- Citation
- 1982 INSC 36
- Decided
- 5 March 1982
- Disposal
- Dismissed
- Bench
- A D KOSHAL
Holding
The Act does not apply to the shop because the date of completion is deemed to be the date of the first assessment (1 April 1968), so the ten‑year exemption period had not elapsed and the suit was not pending at the Act’s commencement, precluding the benefit of Section 39.
Summary
The appellant, a tenant, occupied a shop on 16 June 1967. The landlord sought eviction, arguing that the U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972 did not apply because the building was within the ten‑year exemption period. The lower courts held that the date of completion of the building, for purposes of the Act, was the date of the first assessment (1 April 1968) as per Explanation I to Section 2(2), and therefore the exemption period had not expired. The appellant contended that the construction should be deemed completed on the date of occupation and that the Act should apply prospectively only to buildings erected after its commencement, seeking protection under Section 39. The Supreme Court rejected these arguments, stating that the language of Section 2(2) and its explanation is clear, unambiguous, and does not require external aids for interpretation. It held that the building’s completion date is the first assessment date, the ten‑year period had not elapsed, and the suit was not pending at the Act’s commencement, so Section 39 could not be invoked. Consequently, the eviction decree was upheld.
Issues considered
- The meaning of 'date on which construction is completed' under Section 2(2) of the U.P. Urban Buildings Act, 1972 and Explanation I
- Whether the exemption period of ten years applies to buildings constructed before the Act’s commencement
- Whether the tenant is entitled to protection under Section 39 of the Act
Legislation cited
- Code of Civil Procedure, 1908s. 115
- Provincial Small Causes Courts Acts. 25
- U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972s. 2(2), s. 39, s. Explanation I
Subjects
Judgment
491 A
OM PRAKASH GUPTA ETC.
v.
DIG VIJENDRAPAL GUPTA ETC. B
• ii~
March 5, 1982
[A.D. KosHAL, V. BA.LAKRISHNA BRAD! AND
R.B. MISRA, JJ.J
U.P. Urban Building• (&gu/ation of Letting, &nt and Eviction) Act 1972. c
S.2 (1) and Expln.1 ands. 39.
Applicability of th• Act-Act not to apply to building for a period of t411
~ ytars from 'date of completion of construction'.
Date of completion of construction--What is-' Date of first assessmen1•
if asussed-'Date of occupation' when no record of completion of construction or of D
asstssnunt. ·
Interpretation of Statutes-Intention of legislature-To ht ascertain«/
primarily Jrom words 11std by legislative-Question of interpretation .arises whtlt
language ambiguous.
Tho U.P. Urban Buildings (Regulation of Lotting, Rent and (Eviction)
Act, 1972 provided by sub~section (2) of section 2 that except as provided in the
Act, the Act was not to apply to a building during a period of 10 years from the
date on which its construction was completed. Explanation I to the sub-section
provided that the building shaU be deemed t<;> have been completed on the date
on which completion thereof is reported or otherwise recorded by the local
authorities having jurisdiction, and in case of a building subject to assessment. F
the date on which the first. assessment thereof comes into effect, and where the
said dates are different,_ the earliest of the said date, and in the absence of any
such report, record or assessment, the date on which it is actually occupied for
the first time.
The appellant-tenant was in occupation of a shop from the 16th June,
1967 and prior to his occupation the shop was in occupation of another tenant G
for about a month and a half. The first a8'essment of tho shop took place on
!st of April, 1968. The respondent-landlord filed a suit for the eviction of the
tenant on the ground that the Act did not apply to the shop ·and the tenant was
liable to eviction.
The Trial Judge finding that the construction of the shop was completed H
in the year 1967 and that 10 years having not elapsed since then, held that tho
provisions of tho Act did not apply and decreed tho suit. The appellant's
492 SUPRBMB COURT REPORTS [1982] 3 s.c.R.
A petition under section 25 of the Provincial Small Causes Courts Act was dis..
missed. In bis revision petition to the-High Court under section llS of the Civil
Procedure Code the appellant contended that the date of occupation should be
taken to be the date of completion of the construction of the shop and not the
date of first assessment. The High Court overruled the contention and held that
the constru:tion of the shop would be deemed to have been completed on 1st of
April, 1968 the date of the first assessment and ten years not having elapsed,
8 the Act would not be applicable to the building and dismissed the revision
petition.
In the appeal to this Court it was contended on behalf of the appellant:
(1) that by Virtue of sub-s~ction (2) of s'!ction 2, the Act would be applicable to
the shop in question and that the e.:ttemption created by the sub-section did not
c embrace bui1diogs constructed prior to the commencement of the Act and (2)
that the building should be deemed to have been constructed on the date of
occupation on 16th June, 1967 and not on the date or the first assessment. and
that the appellant wa~ entitled to the benefit of section 39 of the Act.
Dismissing the appeal,
D HELD: l(i) The suit was rightly decreed by the Courts below. The
Act had no application and the appellant could not be given the benefit of section
39. [498 G-H]
(ii) Primarily, the language employed is the determining factor of the
intention of the legislature. The first and primary rule of construction is'that the
intenti~n of the legislature must be _found in the words used by the legislature
E itself. The question of interpretation arises only when the language is ambigUoua
and, therefore capable of two interpretations. [497 F)
(iii) The language of sub-section (2) of section Z of the Act is explict
and unambiguous and is not capable of two interpretations. [497 Gl
-
In 'the absence of ally ambiguity there is no question of taking any
F external aid for the interpretation of the sub-section. The sub-section contem- '
plates that the Act shall not apply to a building during a period of 10 yesrs from
the date on which its construction is completed. It no where says that the build-
ing should have been constructed after the enforcement of the Act and to inter· .J,'
pret it in such a way would be to add words to the sub-section. which is not ..
permissible. [497 D-F)
'-.,.-
G 2 (i) Explanation I makes it abundantly clear that the date of occupation
wollld be taken to be the date of completion of the construction only when there
is no report or record of the completion of the construction or no assessment
thereof. If there is an assessment, as in the instant case it will be the date of the
first assessment which will be deemed to be the date of completion of the cons-
truction. The building had not therefore become more than ten years' old on the
H date when the revision came to be decided by the High Court and consequently
there was no question of giving the benefit of section 39 of the Act to the
appellant. [498 D-F]
OM PRAKASH v. DIGVUENDRAPAL (Mi8ra, J.) 493
(ii) In order to attract section 39 the suit must be pending on the date A
of the commencement of the Act which was 15th of July, 1972. (498 F]
In the instant case the suit was filed ou 23rd of March 1974 long after the
commencement of the Act. (498 F]
(iii) In view of sub-section (2) of section 2, the Act is not applicable to a
• building which has not a standing of ten years. If the Act itself was riot appli- .B
cable, it would be &bsurd to say that section 39 thereof would be applicable.
[498 O] .
Rattan Lal Shlnghal v. Smt. Murti Devi (1980) 4 S.C.C. 258 andRam
Saroop Rai v. Lilavati (1980) 3 S.C.C. 452, over-ruled.
c
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1314 of
1978.
Appeal by special leave from the judgment and order dated
the 23rd March, 1978 of the Allahabad High Court in Civil Revision D
No. 1906 for 1976.
WITH
CIVIL APPEAL No. 2436 OF 1981 E
Appeal by special leave from the judgment and order dated
the 20th August, 1981 of the Allahabad High Court in Civil Writ
Petition No. 6909 of 1979.
-.. AND
CIVIL APPEAL. No. 1710 OF 1981
F
From the judgment and Decree dated the 13th March, 1981
of the Allahabad High Court in Writ Petition No. 6167 of G
1979.
AND
H
SPECIAL LEAVE PETITION (CIVIL) NO. 3573 OF 1979
494 SUPREME COURT REPORTS [1982] 3 S.C.Jl.
From the judgment and order dated the 3rd January, 1979
of the Allahabad High Court in Civil Revision No. 3714 of
1978.
G.L. Sangh!, Mrs. A. Verma and D.N. Mishra for the Appellant
in CA. No. 1314 of 1978.
B ,
J.P. Goyal, S. Markandeya and C.K. Ratnaparkhi for the Res-
pondent in CA. 1314 of 1978. -<.-
A.K. Srivastava for the Appellant in CA. 1710/80.
c R.B. Mehrotra for Respondent in CA. 1710/80.
Pramod Swarup and Mrs. S. Markandeya for the appellant in
CA. 2436 of 198J.
S.N. Kacktr and K.K. Gupta for the Respondent in CA. 2436
·D of 1980.
P.R. Mridul, Praveen Jain and K.B. Rohatgl for the Petitioner
in SLP (Civil) No. 3573 of 1979
R.H. Dhebar for the Respondent.
E The Judgment of the Court was delivered by
MISRA J. The first two appeals by special leave and the third
)(
by certificate and the special leave petition raise a common question
of law and, therefore, we propose to dispose of them by a common
F judgment. '
~
The pattern of facts in all these cases is similar. We, therefore '
set out the facts of Civil Appeal No. 1314 of 1978 to bring out the ,,.J,
point for consideration in these matters. •
\-
The appellant Om Prakash Gupta is a tenant of a shop on a
G
monthly rent of Rs. 150/-. The respondent-landlord filed a suit for
the eviction of the tenant on the ground that the U.P. Urban Buildings
(Regulation of Letting, Rent and Eviction) Act, 1972 (Act 13 of I 972
and hereinafter referred to as 'the Act') did not apply to the shop
H and the tenant was liable to eviction. The Judge, Small Causes
Court, Mainpuri decreed the suit on the finding inter a/ia that the
construction of the shop in suit was completed in the year I 967 and
"-
OM PRAl:ASH. V. DIGVJJENDRAPAL (Mista, J.) 495
that ten years having not elapsed since then, the provisions ·of the
· Act did not apply to the case. The defendant went op in revision
under section 25 of the Provincial. Small Causes Courts Act against
the judgment and decre' of the trial Court but the same was
substantially dismissed.. The defendant thereupon filed a revision
ander section 115 of the Civil Procedure Code in the High Court 8
which came up for hearing before a learned Single Jupge who remit-
ted the following issue to the trial court :
"On what date was the construction of the building
in dispute completed within the meaning of section 2 (2)
c
~·· of the U.P. Urban Buildings (Regulation of Letting, Rent
and Eviction) Act, 1972, and deemed to have been comple-
ted as contemplated by Explanation I (a) thereto."
The Judge Small Causes Court by his order dated 26th of November
1977 returned the following finding :
D
"The construction of the disputed shop will be deemed
to have been completed op the date of the first assessment
i.e., 1.4.68 within the meanini: or section 2 (2) of the U.P.
Urban Buildings Act, 1972."
E
The finding returned by the trial court was sought to be challenged
on behalf or the tenant on the ground that the date of occupation
should be taken to be the date of completion of the cqnstru~ion of
the shop and not the date of the first assessment. In Tilak Raj v.
Sardar Derendra Singh,(') a learned Single Judge of the same High
.. •
(
Court had the occasion to consider section 2 (2) of the Act. He
held : -·
"It is apparent from tJ;iis provision that for purposes
F
of this Act, a building is to be deemed to be constructed,
if it is subject to assessment, on the date with effect from
which the first assessment is made. It is immaterial whether G
the building was constructed actually prior to that date or
it had come into occupation prior to that date. The law
recognised for the purposes of this Act, the date of assess-
ment as the date of the completion of the building. There
is thus no error in the judgment of the court below." H
(1) 1976 (2) ALR 721...
496 SUPREME COURT REPORTS [1982] 3 S.C.R.
A The learned Single Judge before whom the revision in the instant
case came up for hearing doubted the correctness of the above
decision. He, therefore, referred the case to a Division Bench.
The~ is no dispute that the first assessment of the shop took
· place on 1st of April, 1968. It is also not in dispute that the shop
8 in question was occupied by the defendent on 16th of June, 1967,
and prior to his occupation the shop was in occupation of another
tenant for about a month and a half. The appellant sought the
benefit of section 39 of the Act on the ground that if the date of
occupation was taken to be the date of the completion of the cons-
c truction of the shop, then ten years having elapsed during the
pendency of the revision before the High Court, the Act would be --~
applicable. The Division Bench, however, over-ruled the contention
of the appellant and held that the _construction of the shop in
question would be deemed to have been completed on !st of April
1968 and, therefore, the Act would not be applicable to the building
till the date of the decision of the revision on March 23, 1968. The
D
defendant undaunted by the failure came to this Court to challenge
the judgment of the High Court.
Mr. G.L. Sanghi, senior counsel; appearing for the appellant
strongly contended that on a correct interpretation of sub-section (2)
E of section 2, the Act would be applicable to the shop in question.
It wonld be appropriate at .this stage to extract sub- section (2) of
section 2 of the Act insofar ·as it is material for the purposes of the
case :
"Except as provided in sub-section (5) of section 12,
.'
sub-section (1-A) of section 21, sub-section (2) of section
24, sections 24A, 24B, 24C or sub-section (3) of section 29, I
nothing in this Act shall apply to a building during a > ,),
period of ten years from th~ date on which its construction
is completed :
G Explanation I. For the purposes of this sub-section:
(a) the construction of a building shall be deemed to
have been completed on the date on which the
completion thereof is reported to or otherwise
H recorded by the local authority having jurisdiction
and in the ca~e of a building subject to_ assessment
the date on which the first assessment thereof
OM PRAKASH v. DIGVIJENDRAPAL (Misra, J.) 497
comes into effect, and where the said dates are A
different, the earliest of the said dates, and in the
absence of any such report, record or assessment,
the date on which it is actually occupied (not
including occupation merely for the purposes of
supervising the construction or guarding the build-
• ing under construction) for the first time : . " B
The precise contention on behalf of the appellant is that the exemp·
tion created by this sub-section does not embrace buildings construc-
ted prior to the enforcement of the Act. In support of his conten-
tion, Mr. Sanghi, relied upon Rattan Lal Shinghal v. Smt. Murti c
Devi.( 1) The same contention was raised by him in that case also
and a Division Bench of this Court accepted the contention and
held that Act 13 of 1972 was prospective and applied only to build·
ings brought into being de nova after the Act came into force. In
that case there is no discussion except this bald observation. This
Court in a subsequent case Ram Saroop Rai v. Li/avati( 2 ) held to the D
contrary. It is on this account that the present appeals were referred
to a larger Bench. There ~ no ambiguity in the language of sub·
section (2) of section 2 and in the absence of any ambiguity there is
no question of taking any external aid for the interpretation of the
sub-section. In plain words the sub.section contemplates that the . E
Act shall not apply to a building during a period of ten years from
the date on which its construction is completed. It nowhere says
. .
that the buildieg should have been constructed after the enforce·
ment of the Act and to interpret it in the way the learned counsel
for the appellant seeks to interpret it, we would be adding words to
the sub-section, which is not permissible. Primarily the language
employed is the determining factor of the intention of the legislature. F
The first and primary rule of construction is that the intention of
the legislature must be found in the words used by the legislature
itself. The question of interpretation arises only when the language
is ambiguous and, therefore, capable of two interpretations. In the
present case the language of sub-section (2) of section 2 of the
G
Act is explicit and unambiguous and it is not capable of two inter-
pretations.
(I) [1980] 4 s.c.c. 258. H
(2) [1980] 3 s.c.c. 452.
•
498 SUPREME COURT REPORTS [1982] 3 S.C.R.
A As a second limb to the first argument, it is contended that
the building will be deemed to have been constructed on the date
of occupation on 16th of June, 1967 and not on the date of the first
assessment, and that if this he so, the appellant would be entitled to
the benefit of section 39 of the Act on the date when the revision
came to be decided by the High Court on 23rd of March, 1978. In
B order to appreciate this argument it will be expedient to refer to
Explanation I to sub-section (2) of section 2 which has already been
extracted. Explanation I provides that the building shall be deemed
to have been completed on the date on which completion thereof is
reported to or otherwise recorded by the local authorities I:taving
c jurisdiction, and in case of a buildlng subject to assessment the
date on which the first assessment thereof comes into effect and
where the said dates are-different, the earliest of the said dates, and
in the absence of anv such report, record or assessment, the date on
which it is actually occupied .for the first time. A perusal of
Explanation I makes it abundantly clear that the date of occupation
D wonld be taken to be the date of completion of the construction
only when there is no report or record of the completion of the
construction or no assessment, thereof. If there is an assessment,
as in tbe present case it is, it will be the date of tbe first assessment
which will be deemed to be the date of completion of tbe construction
and in that view of the matter the building had not become more
E than ten years' old on the date when the revision came to be decided
by the High Court, and therefore there was no question of giving the
benefit of section 39 of tl1e Act to the appellant.
Further, in order to attract section 39 the suit must be pending
on the date of commencement of the Act which is 15th of July,
F 1972 but the suit giving rise to the present appeal was filed on 23rd
of March, 1974 long after the commencement of the Act. There is
yet another reason why section 39 wilt have no application to the
present case. In view of sub-section (2) of section 2 of the Act the
Act is not applicable to a building which bas not a standing of ten
years and if the Act itself was not applicable, it would be absurd to
G
say that section 39 thereof would be applicable. Considered from
any angle the Act bas no application to the present case and the
appellant could not be given the benefit of section 39. The suit bas,
therefore, been rightly decreed by the courts below.
H.
We find no force in either of the contentions raised by Mr.
Sanghi. The counsel for the appellants in the other appeals and
OM PRAKASH v. DIOVIJENDRAPAL (Misra, J.) 499
the petitioner in the special leave petition, adopted the arguments of A
Mr. Sanghi.
For the foregoing discussion the appeals and the special leave
petition are dismissed. There shall, however, be no order as to
costs. '
• B
We, however, direct that the order of eviction in each case
shall not be executed before 30th of June, 1982 on condition that
each of the appellants in the appeals and the petitioner in the special
leave petition files an undertaking in this Court within four weeks
from today to the following effect :
I. that he will hand over vacant and peaceful posses- c
- 2.
sion of the suit premises to the landlord-respon-
dent on or before 30th of June, J982;
that he will pay to the respondent arrears of rent,
if any, within a month from today;
D
3. that he will pay to the respondent future compen-
sation for use and occupation of the suit premises
for each calendar month by the l 0th of the suc-
ceeding month; and
4. that he will not induct any other person in the
suit premises as a sub-tenant or licensee or in any
other capacity whatsoever.
We further direct that in default of compliance with any one or
..
more of the conditions of the undertaking or if the undertaking is
not filed within the stipulated time, the decree of eviction shall
F.
become executable forthwith .
N.V.K. Appeal dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.