Created byFuzzy Cloud

Supreme Court of India

OIL & NATURAL GAS CORPORATION. LTD.versusWESTERN GECO INTERNATIONAL LTD.

Citation
2014 INSC 596
Decided
4 September 2014
Disposal
Appeal(s) allowed

Holding

The Supreme Court modified the arbitral award because the tribunal had erroneously attributed the entire 4‑month‑22‑day delay to ONGC, failing to draw proper inferences and causing a miscarriage of justice, while upholding the tribunal’s other findings.

Summary

The Oil & Natural Gas Corporation (ONGC) awarded a contract to Western Geco for modernising a seismic vessel, which was to be returned by 9 July 2001. The vessel was delayed until 6 May 2002 due to licensing issues for US‑origin hydrophones and subsequent substitution with Canadian ones, leading ONGC to deduct amounts for excess engagement charges and alleged tax liabilities. An arbitral tribunal held that most of the delay was attributable to ONGC, allowing deductions, but awarded the respondent a sum for a four‑month period it deemed ONGC‑responsible. ONGC challenged the award under Section 34 of the Arbitration and Conciliation Act, alleging a miscarriage of justice and violation of public policy. The Supreme Court held that the tribunal erred by attributing the entire 4‑month‑22‑day period to ONGC without proper inference, constituting a miscarriage of justice, and therefore modified the award by reducing the attributable period by 56 days while upholding other findings, including the tax‑deduction rulings. The appeal was allowed and the award was partially modified.

Issues considered

  • Whether the delay in returning the vessel was attributable to ONGC or Western Geco.
  • Whether the arbitral tribunal erred in attributing the entire 4 months 22 days delay to ONGC.
  • Whether deductions for excess engagement charges and tax adjustments were permissible.
  • Whether the arbitral award violated the public policy of India under Section 34(2)(b)(ii).
  • Whether the arbitral tribunal failed to draw proper inferences, resulting in miscarriage of justice.
  • Whether the award should be set aside or modified under Section 34 of the Arbitration and Conciliation Act, 1996.

Legislation cited

Subjects

ArbitrationSection 34Public policyAward modificationDelayLiquidated damagesExcess engagement chargesTax deductionNatural justiceMiscarriage of justice

Judgment

                                                          '




                      [2014] 12 S.C.R. 1


       OIL & NATURAL GAS CORPORATION. LTD.                           A
                               v.
         WESTERN GECO INTERNATIONAL LTD.
            (Civil Appeal No. 3415 of 2007
                   SEPTEMBER 04, 2014
                                                                     B
               [T.S. THAKUR, C. NAGAPPAN,
                ADARSH KUMAR GOEL, JJ.]

      Arbitration and Conciliation Act, 1996 - s. 34 - Application
for setting aside of arbitral award-Award of contract in favour      C
of respondent by appellant-Corporation whereby vessa/
handed over to respondent for carrying modernization and
upgradation work - Vessa/ could not be returned to the
appellant on the stipulated date - Payment made by
appellant - Deduction of certain amount towards excess               D
engagement charges, change in tax law, correction for price
charges inclusive of income tax - Disputes between parties,
referred to arbitral tribunal - Tribunal holding that delay post
21.10.2001 could not be attributed to the respondent, that the
deduction towards excess engagement charges from                     E
01.11.2001to22.03.2002 by the appellant not justified as a/so
deduction on account of taxes - Petition u/s.34 by the
appellant that the award in conflict with the 'public policy of
India u/s. 34(2)(b)(ii) - Dismissed by the Single Judge of the
High Court however, partly allowed by the Division Bench by          F
deleting pendente lite and future interest from the award made
- On appeal, held: If the arbitrators on facts proved before
them fail to draw an inference which ought to have been drawn
or if they have drawn an inference which is untenable resulting
in miscarriage of justice, the award would be open to
challenge - On facts, arbitrato~ erred in holding the appellant-     G
Corporation responsible for the delay post 21.10.2001,
resulting in miscarriage of justice - They also failed to
appreciate and draw inferences that logically flow from such

                                1                                    H
    2        SUPREME COURT REPORTS              [2014] 12 S.C.R.


A   proved facts - Out of the period of 4 months and 22 days
    which the arbitrators have attributed to the appellant, period
    of 56 days reduced - Deductions made by the appellant for
    the said period upheld - Award made by the arbitrators
    modified to that extent.
B
        Allowing the appeal, the Court

         HELD: 1.1. There was delay of 9 months and 28 days
    from 9th July 2001 to 6th May 2002 in the return of the
    vessel to the Corporation after upgradation. As regards
C   the period between 01.11.2001 to 22.03.2002 which comes
    to 4 months and 22 days the Arbitrators have found the
    delay to be attributable to the appellant-Corporation. The
    arbitrators held that delay in taking a decision whether
    or not any formal application should be made to U.S.
D   Authorities for the issue of license and a formal rejection
    obtained by the respondent was attributable only to the
    appellant-Corporation. Deduction made by the appellant
    for the first interval that comprises period between 1st
    November, 2001 and 25th November, 2001, both days
E   inclusive, cannot, therefore, be sustained and the arbitral
    award to that extent cannot be faulted. The second
    interval comprising period between 26th November, 2001-
    the date when the appellant-Corporation issued
    instructions for making of a formal applicati~n for the
F   grant of a license and 8th January, 2002-when such an
    application was actually made by the respondent-
    company, must be attributed to the respondent-claimant.
    The tribunal failed to appreciate this aspect , thus, fell in
    a palpable error leading to miscarriage of justice. The
G   period between 8th January, 2002 and 8th March, 2002
    comprising the third interval during which the U.S.
    authorities decided the. application for the grant of a
    license has been rightly counted against the appellant-
    Corporation as it was at the instance of the Corporation
H   that a formal application was made. The arbitral tribunal,
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN           3
            GECO INTERNATIONAL LTD.

rightly held that deduction for this period was not           A
justified. There is no valid reason why the fourth interval
comprising the period between 8th March 2002 and 22nd
March 2002 when the rejection of the application was
conveyed to the appellant-Corporation should not be
counted against the respondent, who could and indeed          B
should have conveyed the rejection to the appellant
forthwith, instead of taking nearly two weeks to do so .
.[Para 18, 20, 21, 23] [15-C-D, 17-B-H; 18-B-D, F]

     1.2. The expression 'Fundamental policy of Indian
Law' include all such fundamental principles as providing     C
a basis for administration of justice and enforcement of-
law in this country. The three distinct and fundamental
juristic principles are that in every determination whether
by a Court or other authority that affects the rights of a
citizen or leads to any civil consequences, the Court or      D
authority concerned is bound to adopt a 'judicial
approach' in the matter. They cannot act in an arbitrary,
capricious or whimsical manner. Judicial approach
ensures that the authority acts bonafide and deals with
the subject in a fair, reasonable and objective manner and    E
that its decision is not actuated by any extraneous
consideration. The second principle is that a Court and
so also a quasi-judicial authority must, while determining
the rights and obligations of parties before it, do so in
accordance with the principles of natural justice. The        F
Court/authority deciding the matter must apply its mind
to the attendant facts and circumstances while taking a
view one way or the other, which is best done by
recording reasons in support of the decision which the
Court or authority is taking. The third principle is that a   G
decision which is perverse or so irrational that no
reasonable person would have arrived at the same will
not be sustained in a Court of law. Perversity or
irrationality of decisions is tested on the touchstone of
                                                              H
    4       SUPREME COURT REPORTS            (2014] 12 S.C.R.


A   Wednesbury's principle of reasonableness. [Para 26, 28,
    29) [21-H; 22-A-C, E; 23-F-G; 24-8-C]

       1.3. If on facts proved before them the arbitrators fail
  to draw an inference which ought to have been drawn or
  if they have drawn an inference which is on the face of
8
  it, untenable resulting in miscarriage of justice, the
  adjudication even when made by an arbitral tribunal that
  enjoys considerable latitude and play at the joints in
  making awards will be open to challenge and may be cast
  away or modified depending upon whether the offending
C part is or is not severable from the rest.[Para 30] [24-E-F]

       1.4. The arbitrators clubbed the entire period between
  16th October, 2001 and 21st March, 2002 for purposes of
  holding the appellant-Corporation responsible for the
D delay·, they committed an error resulting in miscarriage of
  justice apart from the fact that they failed to appreciate
  and draw inferences that logically flow from such proved
  facts. The arbitrators rightly held that no taxes were
  payable under the Income Tax Act. The challenge to the
E award to that extent is rejected. Out of the period of 4
  months and 22 days which the arbitrators have attributed
  to the appellant, a period of 56 days comprising 42 days
  of the first interval and 14 days of the second interval
  would be reduced. Deductions made by the appellant-
F Corporation for the said period of 56 days is affirmed and
  the award made by the arbitrators is modified to that
  extent with a proportionate reduction in the amount
  payable to the respondent.[Para 23, 31,32,33) [18-F-G; 24·
  F-G; 25-8-H]
G       ONGC Ltd. v. Saw Pipes Ltd. 2003 (3) SCR 691 :(2003)
    5 SCC 705; AC. Companies Ltd vs. P.N. Sharma and Anr.
    1965 SCR 366:AIR 1965 SC 1595 - referred to.

        Ridge v. Baldwin 1963 2 All ER 66 - referred to.
H
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                  5
            GECO INTERNATIONAL LTD.

                      Case Law Reference:                            A
    2003 (3) SCR 69            Referred to            Para 25
    1963 2 All ER 66           Referred to            Para 26
    1965 SCR 3.66              Referred to            Para 27
                                                                     B
    CIVIL APPELLATE JURISDICTION : Civil Appeal No.
3415 of 2007.

    From the Judgment and Order dated 10.02.2006 in Appeal
No. 24 of 2006 in Arbitration Petition No. 203 of 2005 of the        c
High Court of Judicature at Bombay]

    Paras Kuhad, Jitin Chaturvedi, Pranita Shekhar, Abhik
Chimni, Swati, Somiran Sharma, Vishnu Sharma, K.R.
Sasiprabhu for the appellant.
                                                                     D
    N. Ganpathy, Manpreet Lamba for the respondent.

    The Judgment of the Court was delivered by

    T.S. THAKUR, J. 1. This appeal arises out of an order
dated 10th February, 2006 passed by a Division Bench of the          E
High Court of Judicature at Bombay whereby OSA No.24 of
2006 filed by the appellant-Corporation has been partly allowed
and the order passed by a single bench of the High Court in
Arbitration Petition No.203 of 2005 affirmed with the
modification that award of pendente lite and future interest by      F
the Arbitral Tribunal shall stand deleted.

      2. The appellant-Corporation is engaged in the business
of drilling and exploration of oil and natural gases. In November,
1999, the appellant invited offers for technical upgradation of      G
Seismic Survey Vessel, M.V. Sagar Sandhani (hereinafter
referred to as the "Vessef') with a view to modernising the
same. According to the tender conditions, one of the main items
of equipment required for upgradation of the Vessel was
"Streamers" fitted with hydrophones. The specifications,             H
    6        SUPREME COURT REPORTS               [2014] 12 S.C.R.


A   however, did not stipulate the national origin of such
    hydrophones.

        3. In response to the tender notice respondent-Mis
   Weste!rn Geco International Ltd., submitted a bid offering to
   supply Nessie 4 streamers equipped with "Geopoint•
8
   Hydrophones of U.S. origin. The appellant's case is that the
   term relating to supply of such Geopoint Hydrophones formed
   a material part of the offer made by the respondent-company
   in whose favour the appellant-Corporation eventually awarded
  a contract in terms of its letter dated 1Oth October, 2000 duly
C accepted by the respondent on 25th October, 2000. The Vessel
  was resultantly handed over to the respondent on 1Oth April,
  2001 for carrying on the proposed modernisation and
  upgradation work. A formal contract was in due course
  executed between the parties on 18th June, 2001.
D
        4. It is common ground that "Geopoint" Hydrophones of
  U.S. origin were in terms of the contract fitted in the vessel and
  test trials of the same conducted. Even so the vessel could not
  be delivered back to the appellant on 9th July, 2001, the due
E date for that purpose, because of some problem which the
  respondent encountered in obtaining licence from the U.S.
  authorities for sale of such hydrophones. The appellant-
  Corporation asserts that the respondent had for the first time
  made an application to the U.S. authorities for issuance of a
F licence as late as on 1st August, 2001 i.e. nearly a month after
  the due date for delivery of the vessel back to the Corporation.
  No formal rejection of the request for a license was according
  to the Corporation communicated to it as the matter appeared
  to be under some kind of negotiations between the respondent
  and the authorities in U.S.
G
        5. The respondent's case per contra is that it continued
  its efforts to obtain a licence only to be informed by its sources
  in the US that the latter was likely to impose certain onerous
  conditions one of which could be that US made hydrophones
H can _be used only on loan basis that too for a short duration of
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                    7
     GECO INTERNATIONAL LTD. [T.S. THAKUR, J.)
24 months only. Respondent's further case is that its source in        A
US had informed it that the US authorities were not likely to
grant a licence to sell hydrophones to India. Be that as it may
while the matter was pending with the Defence Department, a
massive terrorist attack on 11th September, 2001 shook
America. The respondent's hope of getting a licence for sale           B
of US made hydrophones receded further with this unexpected
development. The respondent accordingly informed the
appellant-Corporation about the new development and
pleading force majeure the respondent informed the appellant-
Corporation of the farmer's inability to equip the vessel with         C
U.S. made hydrophones. The appellant-Corporation refuted the
invocation of force Majeure by its letter dated 20th September,
2001 and informed the respondent that since the field season
was starting shortly any further delay in the delivery of the vessel
would adversely affect its operation. The respondent on its part       D
started looking for and offering alternatives to the U.S. made
hydrophones and argued with the appellant-Corporation that
since origin of the hydrophones was not indicated in the bid
documents it was testing replacement by M-2 US Geo
Spectrum Hydrophones made in Canada at its Norway facilities
to check their suitability which exercise the respondent hoped         E
to complete by 27th September, 2001. The respondent
informed the appellant-Corporation that if the Corporation
accepted the replacement, those hydrophones could be
substituted for the US hydrophones within a short time.
                                                                       F
     6. The appellant-Corporation was, however, in no mood to
accept a substitute for the contracted hydrophones. It was on
the contrary keen to have US made hydrophones fitted on the
vessel. The Corporation, therefore, required the respondent to
continue its efforts to secure a licence from the US Government        G
in which direction the appellant-Corporation on its own moved
the concerned Ministry in Government of India to secure a
licence-. Further information and details in respect of the
proposed Canadian hydrophones was all the same called for
by the Corporation from the respondent. Since, however, the            H
    8       SUPREME COURT REPORTS               [2014] 12 S.C.R.


A efforts to secure a licence from US Government were making
  no progress, the respondent sought approval of the appellant-
  Corporation to remove the US hydrophones from the vessel and
  transfer them to their repair facility in Singapore to facilitate
  replacement by the Canadian made hydrophones. The
B respondent also wrote a detailed letter dated 10th October,
  2001 to the appellant-Corporation informing the latter that the
  US government was not likely to grant a licence and that it had
  withdrawn the application made for that purpose to prevent a
  denial. What is important is that by letter dated 16th October,
C 2001 the respondent clearly stated that it was not in a position
  to deliver the vessel with streamers containing the Geopoint
  Hydmphones of US make. This letter was followed by letter
  dated 21st October, 2001 addressed to the appellant-
  Corporation with a request to permit removal of US
  hydrophones and replacement of Canadian hydrophones which
0
  had been extensively tested 1999 in connection with supply of
  Seismic Survey Vessel delivered to NOIC for the Iran project.
  Further information required by the appellant-Corporation was
  also supplied by the respondent by its letter dated 24th October,
  2001 with a request to the Corporation to approve the proposed
E replacement. The respondent also agreed to give additional
  warranty of one year for the replaced hydrophones. By another
  letter dated 13th November, 2001 the respondent assured the
  appellant-Corporation that if the latter agreed to the
  replacement proposal there would be no financial implications
F and the additional cost involved in fixing the Canadian
  hydrophones would also be borne by the respondent.

      7. It was only on 23rd March, 2002 that the respondent
  conditionally agreed to the proposed replacement of the US
G made hydrophones by those made in Canada. One of the
  conditions imposed for the replacement by the appellant-
  Corporation was the right to recover liquidated damages as per
  Clause 16 and for excess engagement of vessel as per Clause
  14 of the subject contract. The replacement accordingly took
H place and the Vessel eventually delivered back to the
 OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                    9
      GECO INTERNATIONAL LTD. [T.S. THAKUR, J.]

 Corporation with Canadian hydrophones on 6th May, 2002. On             A
 24th May, 2002, a formal amendment to the contract was also
 effected to record the substitution of the US hydrophones by
 those made in Canada.

       8. With the upgradation and modernisation work                   B
 completed as per the amended contract, the respondent raised
 invoices for payment due to it but realised that the appellant-
 Corporation had deducted from its dues a sum of US $
 5, 114,300.98 towards excess .engagement charges in terms
 of Clause 14 of the contract. By another letter dated 20th
 August, 2002, the appellant-Corporation further deducted a             C
 sum of US$ 410,641.20 based on a change in tax law
 applicable at 4.8% followed by a deduction of a sum of US $
 80,530.10 based on correction for price charges inclusive of
 income tax at 4.8%. These deductions gave rise to disputes
 which were referred for adjudication to an arbitral tribunal           D
 comprising three former Chief Justices of India before whom
 the respondent claimed a sum of US$ 7,327,610.68 towards
 principal dues plus US $1,205,564.13 by way of interest for the
 period from 20th August, 2003 to 15th November, 2003
 totalling US$ 8,533,174,81 with interest pendent lite at 12%           E
  p.a. from the date of the filing of the claim till the award at the
 same rate.

        9. The appellant-Corporation stoutly contested the claim
  made against it and alleged that hydrophones being an                 F
  important component, the respondent had not only offered to
  fit US made hydrophones in the streamer section of the Vessel
  but actually fitted the same. The appellant's case was that the
  claimant having contracted to supply US made hydrophones
  was legally obliged to handover the Vessel duly filled with such      G
  hydrophones within the stipulated period of 90 days which
  expired on 9th July, 2001. The appellant's further case was that
  the requirement of a licence was first mentioned by the
· respondent when letter dated July 9, 2001 was delivered to the
  appellant's representative on board the vessel at Singapore in        H
    10       SUPREME COURT REPORTS                [2014] 12 S.C.R.


A an atteimpt to explain the respondent's failure to hand over the
  vessel on the due date. The appellant-Corporation asserted that
  the respondent had not even applied for a licence till then and
  had simply asked for an extension of time. It was only when the
  appellant-Corporation asked the respondent to specify on a
B realistic basis, the period for wh.ich extension was being
  demanded that the respondent had by letter dated 26th July,
  2001 stated that according to their understanding the licence
  will bi~ issued towards the first week of September, 2001.
  Since time was the essence of the contract between the parties,
c the respondent's failure to return the vessel duly upgraded within
  9 months from the date of Letter of Acceptance or 90 days from
  the deilivery of the vessel i.e. on or before 9th July, 2001 was a
  clear breach of its contractual obligation rendering the
  respondent liable to payment of liquidated damages and for
  excess engagement of the vessel, argued the appellant-
0
  Corporation.

          10. The Corporation also disputed the invocation of force
    majeure clause in the fact situation of the case especially when
    securing of a licence for the equipment was not a part of the
E   contract between the parties, it being the sole responsibility of
    the respondent to determine the type and make of
    hydrophones. The terrorist attack on the twin towers was,
    according to the appellant-Corporation a post-contractual
    period issue as the date of the delivery of the vessel under the
F   contract had since long expired by the time the attack took
    place. It was also contended that the delay in the completion
    of thE! contract was entirely attributable to the respondent who
    when called upon by the appellant-Corporation to submit the
    performance report of the M-2 hydrophones used in Seismic
G   Survey Vessel PEJWAK suggested that the appellant-
    Corporation should obtain the same directly from NIOC forcing
    the appellant-Corporation to send a representative to Oslo to
    verify the parameters of the M-2 hydrophones at their own
    expense. It was asserted that once the respondent informed the
H   appellant-Corporation that the US department of Commerce
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                 11
     GECO INTERNATIONAL LTD. [T.S. THAKUR, J.)
had finally rejected the licence, the appellant-Corporation was      A
left with no alternative except to agree to the replacement of
the .US made hydrophones by Canadian M-2 hydrophones
resulting in the delivery of the vessel back to the Corporation
on 6th May, 2002 after considerable delay.
                                                                     B
    11. On the pleadings of the parties the Arbitral Tribunal
framed the following issues for determination:

      (1)   Was the national origin of hydrophones used in
            the Nessie-4 streamers, a material term of the
            contact betWeen the parties?                             C
      (2)   Was the respondent justified' in refusing to allow
            substitution of the Canadian M-2 hydrophones for
            the US Geopoint hydrophones?

      (3)    Was the claimant's declaration of force majeure         D
            justified under the terms of the contract?

      (4)   Whether there was any delay in the performance
            of the contact?
                                                                     E
      (5)   If the answer to point No.4 is in the affirmative, who
            is responsible for such delay?

      (6)   If the answer to point No.4 is in the affirmative,
            whether the Claimant is entitled to damages?
                                                                     F
      (7)   Whether the respondent was entitled to adjust the
            sum of US $ 491,000 out of the sum payable, in
            whole or in part, as alleged in para 30 of the
            statement?
                                                                     G
      (8)   Is respondent entitled to both Liquidated
            Damages and Excess Engagement charges for
            the same periods of time under the provisions of
            the Contract?

                                                                     H
    12      SUPREME COURT REPORTS                (2014] 12 S.C.R..


A      12. In the award which the Tribunal made and published
  Issue No. 1 was answered in the negative holding that since
  the choice of the hydrophones was left to the bidders subject
  to the equipment meeting the specifications prescribed for the
  purpose and since the stipulations did not indicate the make
B or the country of origin of the hydrophones, the national origin
  of such hydrophones was not a material term of the contract
  betwe!en the parties.

        13. Issue No. 2 was, however, answered by the Tribunal
C in the affirmative, who took the view that once the respondent
  had made the choice and contracted to supply hydrophones
  madei in the U.S. the appellant-Corporation was entitled to insist
  on the supply of the contracted equipment. The arbitrators
  further held that once the respondent had informed the
  appellant that the option of U.S. made hydrophones was closed,
D the later was not justified in insisting that the request for a
  license with the U.S. authorities should be pursued further. The
  arbitral tribunal decided Issue No.3 against the respondent
  holding that none of the events mentioned in the contract had
  taken place and since the parties to the contract did not belong
E to U.S., the force majeure clause could not have been validly
  invoked by the respondent.

        14. Dealing with the question of delay in the performance
  of the contract and its consequences covered by Issue Nos. 4
F to 8, the Arbitrators held that the respondent-claimant had
  completed the performance of the contractual obligations within
  the stipulated time frame and would have but for the U.S.
   licence requirement delivered the vessel to the appellant on July
  9, 2001 in which event there would have been no necessity to
G ·invoke the force majeure clause or to seek extension of time
  or to offer the Canadian hydrophones. Even so the fact
   remained that the respondent had not delivered the vessel back
  to the appellant-Corporation on time. The Tribunal then
  examined whether the respondent was responsible for the
H entire delay between July 9, 2001 and 6th May 2002 when the
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                   13
     GECO INTERNATIONAL LTD. [T.S. THAKUR, J.]

vessel was actually returned. The Tribunal rejected the                A
contention on behalf of the respondent that extension of time
for completing the contracted works had the effect of waiving
the rights vested in the appellant under clause 14 and 16 of the
contract. The Tribunal held that waiver ought to be express or
the fact situation must be necessary implication manifest an           s
intention to waive. Mere extension of time did not signify waiver
of the rights flowing from clause 15 and 16 of the contract,
observed the Arbitral Tribunal. Having said so the Tribunal held
that since the respondent had informally intimated to the
appellant Corporation as early as on October 24, 2001 that it          c
did not desire to pursue the request for a licence with ~he U.S.
authorities any further and since by a letter dated 25th October
2001 the final particulars in regard to the Canadian
hydrophones were duly supplied, allowing some time to the
 respondent to take a decision, the delay post October 21, 2001
                                                                       0
could not be attributed to the respondent. That finding,
observed the Tribunal, did not impact the amount deducted by
 the respondent towards liquidated damages as the capping
provision limited to 10% was less than the sum payable for the
delay upto October 31, 2001. As regards excess engagement              E
charges the Arbitrators held that except for the period
commencing November 1, !2001 to March 22, 2002 the
appellant Corporation was justified in making deductions for the
 rest of the period from the claim of the respondent. The
 Arbitrators held that the deductions in relation to the period from
 November 1, 2001 to March 22, 2002 amounting to US$                   F
2,445,246.54 were wrongly made by the appellant-Corporation
which amount the respondent was entitled to get from the
 appellant together with interest at the rate indicated in the
award.
                                                                       G
     15. As regards deductions based on change of tax law or
non payment of taxes under the Indian Law, the Tribunal held
that the same were not permissible in the facts and
circumstances of the case especially when the contracted work
was to be executed and completed at the ship repair unit of            H
    14        SUPREME COURT REPORTS                 [2014] 12 S.C.R.


A the respondent claimant in Singapore and so was the handing
  over of the completed vessel to the appellant-Corporation. No
  part of the work having been undertaken outside Singapore no
  deduction could be made on account of non-payment of any
  tax. The Arbitrators held that since no taxes were attracted
B under the Indian Income Tax Act the price could not include the
  said tax component. The Arbitrators accordingly held that
  deductions made on two counts, being of US $ 410,641.20 and
  US $ 80,530.10 were also unjustified and unwarranted by law
  or contract.
c         16. Aggrieved by the award made by the Arbitral Tribunal,
    the appellant Corporation preferred a petition under Section 34
    of the Arbitration and Conciliation Act, 1996 which failed and
    was dismissed by a Single Judge of the High Court but was
    allowed in part in O.S.A No. 241 of 2006 by the Division Bench
D   of the High Court to the extent of deleting pendente lite in future
    interest from the award made by the Tribunal. Before the
    Division Bench, a three-fold submission was urged on behalf
    of t'he appellant-Corporation. Firstly, it was contended that the
    Tribunal had fallen in error in holding that the delay between 14th
E   September 2001 and 21st March 2002 was not attributable to
    the respondent company. Secondly, it was contended that the
    Arbitral Tribunal was not right in holding that the deductions
    made by the appellant towards taxes was not legally
    permissible. Thirdly it was contended that the award by the
F   Arbitral Tribunal for the pendente lite and future interest was
    not justified. While the Division Bench rejected the first two
    contentions the respondent appears to have made a statement
    before the. High Court waiving pendente lite interest and
    agreeing to the modification of the award to that extent. The
G   High Court held that the Arbitral Tribunal's findings to the effect
    that the delay between 16th October and 21st March 2002 is
    not attributable to the respondent, was based on the
    consideration of the material placed before the Arbitral Tribunal
    which called for no interference. So also deductions towards
H
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN             15
     GECO INTERNATIONAL LTD. [T.S. THAKUR, J.]
payment of taxes were, according to the High Court, rightly     A
disallowed by the Arbitrators.

    17. The present appeal assails the correctness of the
Award of the Arbitral Tribunal and the orders passed by the
High Court as noticed in the beginning of this order.
                                                                B
     18. We have heard learned counsel for the parties at length
who have taken us through the award made by the Arbitral
Tribunal, provisions of the contract executed between the
parties and the correspondence exchanged between them.
There is no denying the fact that there was delay in the return C
of the vessel to the Corporation after upgradation. In terms of
the contractual time schedule the vessel ought to have returned
to the Corporation by 9th July 2001 which was instead returned
to the Corporation only on 6th May 2002 i.e. after a delay of 9
months and 28 days. Who is responsible for this delay is the D
essence of the dispute between the. parties. According to the
appellant-Corporation the delay is entirely attributable to the
respondent while according to the respondent the delay is
attributable to the appellant. The Arbitrators have after
examining the material placed before them recorded a finding E
to the effect that the delay between 10th July 2001 and 31st
 March 2001 was entirely attributable to the respondent. That
finding was not challenged by the respondent before the High
Court nor is it under challenge before us. The Arbitrators have
on the basis of the finding recorded by them allowed to the F
appellant-Corporation excess engagement charges under
clause 14 besides liquidated damages under clause 16 of the
Contract executed between the parties. But for the period
between 1st November, 2001 and 22nd March, 2002 which
comes to 4 months and 22 days the Arbitrators have found the
delay to be attributable to the appellant-Corporation. Deduction G
made by the Corporation in regard to this period has been
faulted by the arbitrators and the amount directed to be
 released in favour of the respondent-Company. The award

                                                                H
    16      SUPREME COURT REPORTS                [2014) 12 S.C.R.


A deals with this period and the amount deducted for the same
  in the following words:

         "In the result we are of the opinion that except for the
         period from November 1, 2001 to March 23, 2002 for
         which deduction has been made from the Claimant's
B
         invoices, no exception can be taken for the rest of the
         deduction made from the claim of the Claimant. The
         deduction in relation to the period from November 1,
         :2001 to March 22, 2002 (4 months + 22 days) works out
         to a sum of US$ 2,445,246.53 which the Claimant would
c        be entitled to from the Respondent together with interest
         at the rate of indicated hereafter".

        19. The above period of 4 months and 22 days between
  1st November, 2001 and 22nd March, 2002, in our opinion,
D comprises four separate intervals. The first of these four intervals
  is the period between 1st November, 2001 and 26th November,
  2001 which period was taken by the appellant-Corporation to
  take a final decision whether or not an application should be
  made to the U.S authorities for the issue of a licence. The
E second interval comprises time taken by the respondent-
  claimant to make an application between 27th November, 2001
  and 7th January, 2002, both days inclusive. The application for
  grant of a license was filed by the respondent only on 8th
  January, 2002. The third interval comprises time taken by the
F U.S Authorities between 8th January, 2002 and 7th March, ·
  2002 to formally decline the issue of a license for sale of US
  made hydrophones to India. The fourth interval comprises time
  taken by the respondent-claimant to convey the decision of the
  U.S Authorities between 8th March, 2002 and 21st March,
G 2002. It is common ground that while the U.S Authorities had
  rejected the request for grant of a license on 8th March, 2002,
  the said rejection was conveyed to the appellant-corporation
  only on 22nd March, 2002.

       20. From the findings of the fact recorded by the arbitrators
H with which we see no reason to interfere or disagree, it is
 OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                  17
      GECO INTERNATIONAL LTD. [T.S. THAKUR, J.]
 evident, that the appellant-corporation was solely responsible        A
 for the de!ay in taking a decision in the matter between 24th
 October, 2001 and 26th November, 2001. The arbitrators have
 found and, in our opinion, rightly so that the respondent-claimant
 had by its letter dated 24th October, 2001 clearly informed the
 appellant Iha~ there was no use pursuing the matter with the          B
 U.S. Authorities any further. Even particulars regarding
 Canadian hydrophones were supplied to the appellant in terms
 of a letter dated 25th October, 2001. The arbitrators have held
 that delay in taking a decision whether or not any formal
 application should be made and a formal rejection obtained by         c
 the respondent was attributable only to the appellant-
. Corporation. There is, in our opinion, no legal flaw, infirmity or
  perversity in that finding which we hereby affirm. Deduction
 made by the appellant-Corporation for the First interval that
 comprises period between 1st November, 2001 and 25th                  0
  November, 2001, both days inclusive, cannot, therefore, be
 sustained and the arbitral award to that extent cannot be
 faulted.

     21. That brings us to the second interval comprising period
between 26th November, 2001-the date when the appellant-               E
Corporation issued instructions for making of a formal
application for the grant of a license and 8th January, 2002-
when such an application was actually made by the respondent-
company. This period reckoned from 27th November, 2001 to
7th January, 2002 works out to 42 (Forty two) days which must          F
be attributed to the respondent-claimant, who could and indeed
ought to have acted diligently and with reasonable despatch in
the matter instead of taking the same easy, and if we may say
so somewhat reluctantly. We cannot help saying with utmost
respect at our command for the eminence and erudition of the           G
distinguished jurists comprising the Arbitral Tribunal that the
tribunal failed to appreciate this aspect hence fell in a palpable
error leading to miscarriage of justice. The test adopted by the
Tribunal for holding the appellant-Corporation responsible for
delay ought to have been applied to the respondent as well for         H
    18       SUPREME COURT REPORTS                 [2014) 12 S.C.R.


A   its failure to take action in the right earnest instead of sitting
    over the matter leading to detention of the vessel for a period
    more than what was absolutely necessary.

        22. The period between 8th January, 2002 and 8th March,
B 2002 comprising the third interval during which the U.S.
  authorities decided the application for the grant of a license has
  been rightly counted against the appellant-Corporation as it
  was at the instance of the Corporation that a formal application
  was made. The time spent by the U.S. authorities for disposal
c of the request could not in the facts and circumstances be
  attributed to or counted against the respondent-claimant who
  had advised the appellant against any such move. The arbitral
  Tribunal, therefore rightly held that deduction for this period was
  not justified.
D      23. That leaves us with the fourth and the last interval
  comprising the period between 8th March, 2002 and 22nd
  March, 2002 when the rejection of the application was conveyed
  to the appellant-Corporation. There is, in our opinion, no valid
  reason why this period.should not be counted against the
E respondent, who could and indeed should have conveyed the
  rejection to the appellant-Corporation forthwith, instead of
  taking nearly two weeks to do so. To sum up; the period of 4
  months and 22 days which the arbitrators have attributed to the
  appellant-Corporation shall have to be reduced by 42 days
F comprising the first interval and 14 days comprising the fourth
  making a total of 56 days. Resultantly, deduction made by the
  appellant-Corporation for 56 days referred to above deserve
  to be affirmed, and the award made by the arbitrators modified
  to that extent. It follows that the amount awarded to the
G respondent-Company shall on a proportionate basis, stand
  reduced.

       24. We may at this stage deal with the contention urged
  on behalf of the respondent that the jurisdiction of the Court to
H set aside an arbitral award being limited to grounds set out in
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                 19
     GECO INTERNATIONAL LTD. [T.S. THAKUR, J.]
Section 34 of the Arbitration and Conciliation Act, 1996, this       A
Court ought not to interfere with the same. It was contended that
none of the grounds on which a Court is authorised to interfere
with an arbitral award are present in the case at hand.
Alternatively, it was contended that even if a contrary view is
possible on the facts proved before the Arbitral Tribunal, the       s
Court cannot, in the absence of any compelling reason, interfere
with the view taken by the Arbitrators as if it was sitting in
appeal over the award made by the Tribunal. Section 34 of the
Arbitration and Conciliation Act, 1996 reads :

     "34. Application for setting aside arbitral award.-(1)          C
     Recourse to a court against an arbitral award may be
     made only by an application for setting aside such award
     in accordance with sub-section (2) and sub-section (3).

     (2) An arbitral award may be set aside by the court only        D
     if.-
     (a) the party making the application furnishes proof that-

     (i) a party was under some incapacity, or
                                                                     E
     (ii) the arbitration agreement is not valid under the law to
     which the parties have subjected it or, failing any
     indication thereon, under the law for the time being in
     force; or
                                                                     F
     (iii) the party making the application was not given proper
     notice of the appointment of an arbitrator or of the arbitral
     proceedings or was otherwise unable to present his case;
     or

     (iv) the arbitral award deals with a dispute not                G
     contemplated by or not falling within the terms of the
     submission to arbitration, or it contains decisions on
     matters beyond the scope of the submission to
     arbitration:
                                                                     H
    20       SUPREME COURT REPORTS                [2014] 12 S.C.R.


A        Provided that, if the decisions on matters submitted to
         arbitration can be separated from those not so submitted,
         only that part of the arbitral award which contains
         decisions on matters not submitted to arbitration may be
         set aside; or
B
         (v) the composition of the Arbitral Tribunal or the arbitral
         procedure was not in accordance with the agreement of
         the parties, unless such agreement was in conflict with a
         provision of this Part from which the parties cannot
         derogate, or, failing such agreement, was not in
c        accordance with this Part; or

         (b) the court finds that-

         (i) the subject-matter of the dispute is not capable of
o        settlement by arbitration under the law for the time being
         in force, or

         (ii) the arbitral award is in conflict with the public policy
         of India.

E        Explanation.-Without prejudice to the generality of sub-
         clause (ii), it is hereby declared, for the avoidance of any
         doubt, that an award is in conflict with the public policy of
         India if the making of the award was induced or affected
         by fraud or corruption or was in violation of Section 75 or
F        Section 81."

       25. It is true that none of the grounds enumerated under
  Section 34(2)(a) were set up before the High Court to assail
  the arbitral award. What was all the same urged before the High
  Court and so also before us was that the award made by the
G arbitrators was in conflict with the "public policy of India" a
  ground recognised under Section 34(2)(b)(ii) (supra). The
  expression "Public Policy of India" fell for interpretation before
  this Court in ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705
  and was, after a comprehensive review of the case law on the
H
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                21
     GECO INTERNATIONAL LTD. [T.S. THAKUR, J.]

subject, explained in para 31 of the decision in the following     A
words:

    "31. Therefore, in our view, the phrase "public policy of
    India" used in Section 34 in context is required to be
    given a wider meaning. It can be stated that the concept
    of public policy connotes some matter which concerns
                                                                    8
    public good and the public interest. What is for public
    good or in public interest or what would be injurious or
    harmful to the public good or public interest has varied
    from time to time. However, the award which is, on the
    face of it, patently in violation of statutory provisions C
    cannot be said to be in public interest. Such award!
    judgment/decision is likely to adversely affect the
     administration of justice. Hence, in our view in addition
     to narrower meaning given to the term "public policy" in
     Renusagar case1il it is required to be held that the award D
     could be set aside if it is patently illegal. The result would
     be - award could be set aside if it is contrary to:

    (a) fundamental policy of Indian law; or
                                                                   E
    (b) the interest of India; or

    (c) justice or morality, or

    (d) in addition, if it is patently illegal.
                                                                   F
    Illegality must go to the root of the matter and if the
    illegality is of trivial nature it cannot be held that award
    is against the public policy. Award could also be set aside
    if it is so unfair and unreasonable that it shocks the
    conscience of the court. Such award is opposed to public
    policy and is required to be adfudged void."                   G
     26. What then would constitute the 'Fundamental policy
of Indian Law' is the question. The decision in Saw Pipes Ltd.
(supra) does not elaborate that aspect. Even so, the expression
must, in our opinion, include all such fundamental principles as   H
    22       SUPREME COURT REPORTS                 (2014] 12 S.C.R.


A   providing a basis for administration of justice and enforcement
    of law in this country. Without meaning to exhaustively
    enumerate the purport of the expression "Fundamental Policy
    of Indian Law", we may refer to three distinct and fundamental
    juristic principles that must necessarily be understood as a part
B   and parcel of the Fundamental Policy of Indian law. The first
    and foremost is the principle that in every determination
    whether by a Court or other authority that affects the rights of a .
    citizen or leads to any civil consequences, the Court or authority
    concerned is bound to adopt what is in legal parlance called a
C    judicial approach' in the matter. The duty to adopt a judicial
    approach arises from the very nature of the power exercised
    by the Court or the authority does not have to be separately or
    additionally enjoined upon the fora concerned. What must be
    remembered is that the importance of Judicial approach in
    judicial and quasi judicial determination lies in the fact so long
0
    as the Court, Tribunal or the authority exercising powers that
    affect the rights or obligations of the parties before them shows
    fidelity to judicial approach, they cannot act in an arbitrary,
    capricious or whimsical manner. Judicial approach ensures that
    the authority acts bonafide and deals with the subject in a fair,
E   reasonable and objective manner and that its decision is not
    actuated by any extraneous consideration. Judicial approach
    in that sense acts as a check against flaws and faults that can
    render the decision of a Court, Tribunal or Authority vulnerable
    to challenge. In Ridge v. Baldwin [1963 2 All ER 66], the
F   House of Lords was considering the question whether a Watch
    Committee in exercising its authority under Section 191 of the
     Municipal Corporations Act, 1882 was required to act judicially.
    The majority decision was that it had to act judicially and since
    the order of dismissal was passed without furnishing to the
G   appellant a specific charge, it was a nullity. Dealing with the
    appellant's contention that the Watch Committee had to act
    judicially, Lord Reid relied upon the following observations
    made by Atkin L.J. in (1924] 1 KB at pp. 206,207:

         "Wherever any body of persons having legal authority to
H
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                   23
     GECO INTERNATIONAL LTD. [T.S. THAKUR, J.]
     determine questions affecting the rights of subjects, and          A
     having the duty to act judicially, act in excess of their legal
     authority, they are subject to the controlling jurisdiction
     of the King's Bench Division exercised in these writs."

    27. The view taken by Lord Reid was relied upon by a
                                                                        B
Constitution Bench of this Court in A.C. Companies Ltd vs.
P.N. Sharma and Anr. (AIR 1965 SC 1595) where
Gajendragadkar, C.J. speaking for the Court observed :

     "In other words, according to Lord Reid's judgment, the
     necessity to follow judicial procedure and observe the C
     principles of natural justice, flows from the nature of the
     decision which the watch committee had been authorised
     to reach under S.191(4). It would thus be seen that the
     area where the principles of natural justice have to be
     followed and judicial approach has to be adopted, has D
     become wider and consequently, the horizon of writ
     jurisdiction has been extended in a corresponding
      measure. In dealing with questions as to whether any
      impugned orders could be revised under A. 226 of our
      Constitution, the test prescribed by Lord Reid in this E
     judgment may afford considerable assistance."

       28. Equally important and indeed fundamental to the policy
  of Indian law is the principle that a Court and so also a quasi-
 judicial authority must, while determining the rights and
  obligations of parties before it, do so in accordance with the        F
  principles of natural justice. Besides the celebrated 'audi
· alteram partem' rule one of the facets of the principles of natural
 justice is that the Court/authority deciding the matter must apply
  its mind to the attendant facts and circumstances while taking
  a view one way or the other. Non-application of mind is a defect      G
 that is fatal to any adjudication. Application of mind is best
  demonstrated by disclosure of the mind and disclosure of mind
  is best done by recording reasons in support of the decision
 which the Court or authority is taking. The requirement that an
  adjudicatory authority must apply its mind is, in that view, so       H
    24       SUPREME COURT REPORTS                [2014] 12 S.C.R.


A   deeply embedded in our jurisprudence that it can be described
    as a fundamental policy of Indian Law.

       29. No less important is the principle now recognised as
  a salutary juristic fundamental in administrative law that a
8 decision which is perverse or so irrational that no reasonable
  person would have arrived at the same will not be sustained in
  a Court of law. Perversity or irrationality of decisions is tested
  on the touchstone of Wednesbury's principle of
  reasonableness. Decisions that fall short of the standards of
C reasonableness are open to challenge in a Court of law often
  in writ jurisdiction of the Superior courts but no less in statutory
  processes where ever the same are available.

       30. It is neither necessary nor proper for us to attempt an
  exhaustive enumeration of what would constitute the
D fundamental policy of Indian law nor is it possible to place the
  expression in the straitjacket of a definition. What is important
  in the context of the case at hand is that if on facts proved
  before them the arbitrators fail to draw an inference which ought
  to have been drawn or if they have drawn an inference which
E is on the face of it, untenable resulting in miscarriage of justice,
  the adjudication even when made by an arbitral tribunal that
  enjoys considerable latitude and play at the joints in making
  awards will be open to challenge and may be cast away or
  modified depending upon whether the offending part is or is
F not severable from the rest.

        31. Inasmuch as the arbitrators clubbed the entire period
  between 16th October, 2001 and 21st March, 2002 for
  purposes of holding the appellant-Corporation responsible for
  the delay, they committed an error resulting in miscarriage of
G justice apart from the fact that they failed to appreciate and
  d.raw inferences that logically flow from such proved facts. We
  have, therefore, no hesitation in rejecting the contention urged
  on behalf of the respondent that the arbitral award should not
  despite the infirmities pointed out by us be disturbed.
H
OIL & NATURAL GAS CORPORATION. LTD. v. WESTERN                  25
     GECO INTERNATIONAL LTD. [TS.THAKUR, J.] ·

     32. That brings us to the last submission that deduction         A
on account of taxes not paid should have been allowed by the
respondent-arbitral tribunal. The Tribunal has, in our opinion,
correctly held that no part of the work was undertaken outside
Singapore which was to be executed on a turnkey basis for a
price that was pre-determined. The arbitrators have, in our           B
opinion, rightly held that no taxes were payable under the Indian
Income tax Act so as to entitle the Corporation to deduct any
amount on that account by reason of non-payment of such
taxes. The challenge to the award to that extent must fail and
is, hereby, rejected.                                                 c
     33. In the result, we allow this appe~I but only to the extent
that out of the period of 4 months and 22 days which the
arbitrators have attributed to the appellant-Corporation a period
of 56 days comprising 42 days of the first interval and 14 days
of the second referred to in the judgment shall be reduced.           0
Resultantly, deductions made bY, the appellant-Corporation for
the said period of 56 days shall stand affirmed and the award
made by the arbitrators modified to that extent with a
proportionate reduction in the amount payable to the
respondent. No costs.                              ··                 H

Nidhi Jain                                          Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.