Created byFuzzy Cloud

Supreme Court of India

NORTH DELHI MUNICIPAL CORPORATIONversusM/S S.A. BUILDERS LTD.

Citation
2024 INSC 988
Decided
17 December 2024
Disposal
Dismissed

Holding

A clarification issued by the arbitrator after the award is valid if the court permits the party to seek it beyond the statutory 30‑day period, and the arbitrator was not functus officio.

Summary

The North Delhi Municipal Corporation (appellant) contracted with M/s S.A. Builders Ltd. (respondent) for construction work, which was not completed and led to a dispute. An arbitrator awarded Rs. 1,70,70,720.80 with simple interest and later issued a clarification on 15 March 2005 regarding post‑award interest, after the award had been passed in 1997. The appellant argued that the arbitrator had become functus officio and thus lacked jurisdiction to issue the clarification, contending that the clarification altered the award beyond the 30‑day period allowed under Section 33(1) of the Arbitration and Conciliation Act, 1996. The Supreme Court examined the scope of Section 33(1) and the jurisprudence on interest under Section 31(7), concluding that the clarification was permissible because the parties had been allowed by the High Court to seek it beyond the statutory period. Consequently, the Court rejected the appellant's claim of lack of jurisdiction and dismissed the appeal.

Issues considered

  • Whether the arbitrator became functus officio after passing the award dated 16‑12‑1997 and therefore lacked jurisdiction to issue a clarification on 15‑03‑2005.
  • Whether a clarification issued beyond the 30‑day period prescribed in Section 33(1) of the Arbitration and Conciliation Act, 1996 is valid when the court permits the party to seek it.
  • Interpretation of Section 31(7)(a) and (b) of the Arbitration and Conciliation Act, 1996 with respect to pre‑award and post‑award interest.

Legislation cited

Headnote

Issue for Consideration Whether the Arbitrator had become functus officio after passing of the award dated 16.12.1997 and had no jurisdiction to issue the clarification dated 15.03.2005. Headnotes† Arbitration and Conciliation Act, 1996 – s.31 and s.33(1) (a) – Appellant functus officio and therefore lacked jurisdiction to issue the clarification: Held: The interpretation given to Section 33(1) of the 1996 Act and on a cumulative assessment of the attendant facts and circumstances of the case, this Court is of the view that the clarification sought for and

Subjects

Section 33 of the Arbitration and Conciliation Act, 1996Correction of awardInterpretation of awardArbitral awardClerical errorTypographical errorArbitral TribunalFunctus OfficioClarificationClarificatory proceedingsLack of jurisdictionInterest portionInterest awardedDate of awardDate of payment

Judgment

                [2024] 12 S.C.R. 1581 : 2024 INSC 988

                  North Delhi Municipal Corporation
                                  v.
                        M/s S.A. Builders Ltd.
                       (Civil Appeal No. 1878 of 2024)
                              17 December 2024
                [Abhay S. Oka and Ujjal Bhuyan,* JJ.]


                            Issue for Consideration
       Whether the Arbitrator had become functus officio after passing of
       the award dated 16.12.1997 and had no jurisdiction to issue the
       clarification dated 15.03.2005.

                                   Headnotes†
       Arbitration and Conciliation Act, 1996 – s.31 and s.33(1)
       (a) – Appellant contended that the Arbitrator had become
       functus officio and therefore lacked jurisdiction to issue the
       clarification:
       Held: The interpretation given to Section 33(1) of the 1996 Act
       and on a cumulative assessment of the attendant facts and
       circumstances of the case, this Court is of the view that the
       clarification sought for and issued by the Arbitrator would be
       covered by the expression unless another period of time has been
       agreed upon by the parties appearing in Section 33 (1) of the 1996
       Act – This is a case where court had permitted the respondent to
       seek clarification from the Arbitrator beyond the initial period of 30
       days whereafter the appellant fully participated in the clarificatory
       proceeding – Therefore, the present case would be covered
       by the above expression – In the circumstances, contention of
       the appellant that the Arbitrator had become functus officio and
       therefore lacked jurisdiction to issue the clarification cannot be
       accepted and is thus rejected – That apart, it is not the case of
       the appellant that the interest portion is covered by the contract
       agreement between the parties – In the absence thereof, Section
       31(7)(a) as well as Section 31(7)(b) of the 1996 Act would have
       their full effect – The sum awarded would mean the principal
       amount plus the interest awarded from the date of cause of action
       upto the date of the award – Thereafter, as per Section 31(7)(b) of
       the 1996 Act, the sum (principal plus interest) would carry interest

* Author
1582                                                         [2024] 11 S.C.R.

                         Supreme Court Reports


    @ 18% from the date of the award to the date of payment – This
    would be consistent with the law laid down by this Court in M/s.
    Hyder Consulting (UK) Ltd. [Paras 59, 60]

    Arbitration and Conciliation Act, 1996 – s.33(1) – Correction
    and interpretation of award; additional award:
    Held: As per sub-Section (1), within 30 days from the date of
    receipt of the arbitral award, a party with notice to the other party,
    may request the arbitral tribunal to correct any computation errors,
    any clerical or typographical errors or any other errors of a similar
    nature occurring in the award – Further, if the parties agree, a party
    with notice to the other party, may request the arbitral tribunal to
    give an interpretation of a specific point or part of the award –
    The period of 30 days contemplated under sub-Section (1) may
    stand extended to another period of time if agreed upon by the
    parties – Therefore, ordinarily the time limit for correction of errors
    or for interpretation of a specific point or part of the award is 30
    days from the date of receipt of the arbitral award – However, the
    limitation of 30 days can be waived for another period of time, if
    agreed upon by the parties – Question for consideration is what
    would be the contours of the expression unless another period of
    time has been agreed upon by the parties, as appearing in sub-
    Section (1) of Section 33. [Para 45.1]

                              Case Law Cited
    M/s. Hyder Consulting (UK) Ltd. v. Governor, State of Orissa [2014]
    14 SCR 1029 : (2015) 2 SCC 189 – relied on.
    State of Haryana v. S.L. Arora [2010] 2 SCR 297 : (2010) 3 SCC
    690; Gyan Prakash Arya v. Titan Industries Ltd. [2021] 11 SCR
    1 : (2023) 1 SCC 153; Harshad Chiman Lal Modi v. DLF Universal
    Ltd. [2005] Supp. 3 SCR 495 : (2005) 7 SCC 791; Mohanlal
    Goenka v. Benoy Kishna Mukherjee [1953] 1 SCR 377 : (1952)
    2 SCC 648; Gas Authority of India Limited v. Keti Construction (I)
    Limited [2007] 6 SCR 439 : (2007) 5 SCC 38; Delhi Airport Metro
    Express Private Limited v. Delhi Metro Rail Corporation [2022]
    3 SCR 716 : (2022) 9 SCC 286; UHL Power Company Limited
    v. State of Himachal Pradesh [2022] 1 SCR 1 : (2022) 4 SCC
    116; Delhi Airport Metro Express Private Limited v. Delhi Metro
    Rail Corporation [2022] 3 SCR 716 : (2022) 9 SCC 286; Morgan
    Securities & Credits (P) Ltd. v. Videocon Industries Ltd. [2022] 9
    SCR 819 : (2023) 1 SCC 602 – referred to.
[2024] 11 S.C.R.                                                              1583

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     Ircon International Ltd. v. Budhiraja Mining & Construction Ltd.,
     2007(4) Arb. LR 159 (Delhi) – referred to.

                                 List of Acts
     Arbitration and Conciliation Act, 1996; Arbitration Act, 1940; Interest
     Act, 1978.

                              List of Keywords
     Section 33 of the Arbitration and Conciliation Act, 1996; Correction
     of award; Interpretation of award; Arbitral award; Clerical error;
     Typographical error; Arbitral Tribunal; Functus Officio; Clarification;
     Clarificatory proceedings; Lack of jurisdiction; Interest portion;
     Interest awarded; Date of award; Date of payment.

                             Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1878 of 2024
     From the Judgment and Order dated 01.07.2019 of the High Court
     of Delhi at New Delhi in EFAOS No. 17 of 2017

                          Appearances for Parties
     Ms. Madhavi Divan, Sr. Adv., Amol Chitale, Nirnimesh Dube,
     Sunil Goel, Ankur S. Kulkarni, Susheel Joseph Cyriac, Ms. Uditha
     Chakravarthy, Ms. Aiashani Narayan, Ms. Priya S. Bhalerao, Varun
     Kanwal, M/s. Lex Regis Law Offices, Advs. for the Appellant.
     C Aryama Sundaram, Sr. Adv., Tarun Gupta, Abhishek Gupta,
     Ms. Rohini Musa, Zafar Wayat, Raj Sudhakar Yadav, Atul Kumar,
     Yatinder Chaudhary, Davinder Singh Khurana, Manish Bansal,
     Advs. for the Respondent.

                Judgment / Order of the Supreme Court

                                  Judgment

     Ujjal Bhuyan, J.

     Heard learned counsel for the parties.
2.   This civil appeal by special leave is directed against the impugned
     order dated 01.07.2019 passed by a Division Bench of the High Court
1584                                                      [2024] 11 S.C.R.

                         Supreme Court Reports



      of Delhi at New Delhi (‘High Court’) disposing of EFA(OS) No. 17/2017
      and C.M. No. 20662/2017 (North Delhi Municipal Corporation Vs.
      M/s. S A Builders Ltd).
3.    By the impugned order dated 01.07.2019, the Division Bench held
      that this Court vide the order dated 12.03.2015 had directed the
      High Court to decide the issue of interest component payable to
      the respondent in accordance with the law laid down in M/s. Hyder
      Consulting (UK) Ltd. Vs. Governor, State of Orissa 1 and not in
      accordance with the law laid down in State of Haryana Vs. S.L.
      Arora,2 declaring that the matter relating to amount payable to the
      respondent had attained finality and could not be interfered with.
      The Division Bench set aside that part of the order of the learned
      Single Judge dated 19.04.2017 passed in E.A. (OS) No. 34/2016
      pertaining only to the calculations and permitted both the parties
      (appellant and respondent) to make submissions before the learned
      Single Judge restricted to the quantum of the amount payable to
      the respondent. The appeal and the miscellaneous application were
      disposed of with the observation that learned Single Judge would
      decide the amount payable by the appellant to the respondent after
      hearing both the sides.
4.    At the outset, it would be appropriate to advert to the relevant facts
      having a material bearing on the lis.

      Facts
5.    Respondent was awarded a contract work relating to construction
      of approaches to flyover at the level crossing on New Rohtak Road
      with clover-leaf slip road and service road etc. by the appellant. A
      contract agreement was entered into between the parties in this
      regard on 11.11.1983. The work however could not be completed
      even beyond the stipulated date of completion till March, 1990 and,
      therefore, the work had to be closed in an incomplete form. The main
      reason for closing the work was non-availability of site.
      5.1. The last payment to the tune of Rs. 4,71,48,122.00 was made
           to the respondent on 09.02.1988. Thereafter, no payments were



1    (2015) 2 SCC 189
2    (2010) 3 SCC 690
[2024] 11 S.C.R.                                                      1585

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.



          made to the respondent for the work done upto March, 1990
          when the contract was closed. Respondent submitted its final
          bill which the appellant failed to pay. As a result, dispute arose
          between the parties.
6.   Thereafter, respondent filed an application under Section 20 of the
     Arbitration Act, 1940 before the High Court seeking appointment of
     an arbitrator to arbitrate the dispute between the parties. High Court
     appointed Sh. S.P. Rai, Ex-Member(Personnel), Postal Services
     Board and Additional Secretary to the Government of India, Ministry
     of Communications, as the sole Arbitrator. It may be mentioned that
     on the consent of both the parties, the arbitration proceedings were
     carried out in terms of the Arbitration and Conciliation Act, 1996
     whereafter award was passed by the sole Arbitrator on 16.12.1997.
     Learned Arbitrator awarded various sums under different heads
     out of the 26 claims, while rejecting a few of the claims of the
     respondent. Counter claim of the appellant was also allowed to a
     limited extent under three heads. After adjusting the two, an amount
     of Rs. 1,70,70,720.80 was awarded to the respondent with simple
     interest @ 18% per annum on the award amount w.e.f. 01.04.1990
     upto the date of actual payment except on claim No. 23(b) which
     related to expenses incurred by the respondent on account of bank
     guarantee commission, margin money etc. for keeping the bank
     guarantee alive.
     6.1. Thereafter, the sole Arbitrator issued a corrigendum dated
          18.12.1997 pointing out certain typographical errors in the
          award, whereafter it was mentioned that the net amount payable
          to the respondent would be Rs. 1,70,40,720.80 instead of Rs.
          1,70,70,720.80, further clarifying that the above correction would
          form part of the award dated 16.12.1997.
7.   Respondent filed an execution petition being Ex.P. No. 99/1998 under
     Section 36 of the Arbitration and Conciliation Act, 1996 (briefly ‘the
     1996 Act’ hereinafter) before the Single Bench of the High Court
     for execution of the arbitral award. Learned Single Judge vide the
     order dated 26.08.2004 framed the following issue for consideration:
          Whether post award interest under Section 31(7) of the
          Arbitration and Conciliation Act, 1996 would be calculated
          on the principal sum adjudged or would it be calculated on
1586                                                        [2024] 11 S.C.R.

                         Supreme Court Reports


           the principal sum plus interest on the principal sum which
           has accrued from the date of cause of action to date of
           passing of award, as under the new 1996 Act, award is
           enforced as a decree of the court.
8.   Simultaneously, appellant also filed before the Single Bench a
     petition under Section 34 of the 1996 Act challenging the award
     dated 16.12.1997. By order dated 08.01.2002, the petition of the
     appellant under Section 34 of the 1996 Act was dismissed.
9.   Appellant then preferred an appeal under Section 37 of the 1996 Act
     before the Division Bench assailing the order dated 08.01.2002 being
     FAO(OS) No. 89/2002. The said appeal was, however, dismissed
     by the Division Bench of the High Court by the judgment and order
     dated 14.03.2002.
10. Being aggrieved by the order dated 14.03.2002, appellant filed a
    special leave petition before this Court being SLP(C) No. 7474/2002.
    Though this Court had initially issued notice and granted limited stay
    qua execution of the award vis-à-vis claim Nos. 22, 25 and 26, the
    said special leave petition was subsequently dismissed by this Court
    on 03.02.2010.
11. Reverting back to the execution petition filed by the respondent,
    learned Single Judge vide the order dated 26.08.2004 after framing
    the issue as above expressed the view that post-award interest under
    Section 31(7) of the 1996 Act affects a large volume of litigation
    before the court. Therefore, in order to avoid proliferation of litigation
    and unnecessary appeals, learned Single Judge referred the matter
    to the Division Bench to clarify the position in this regard.
12. When the matter was placed before the Division Bench, respondent
    sought leave to approach the learned Arbitrator for seeking the
    clarification as to whether the interest awarded in the award was
    under Section 31(7)(a) of the 1996 Act or not? Division Bench vide the
    order dated 03.01.2005 granted such permission to the respondent
    with the clarification that the permission so granted should not be
    understood to contain any expression of opinion of the Division
    Bench about payment of interest under Section 31(7)(a) or Section
    31(7)(b) of the 1996 Act.
13. Pursuant thereto, an application was filed by the respondent before
    the learned Arbitrator seeking clarification in terms of the order dated
[2024] 11 S.C.R.                                                     1587

       North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     03.01.2005. It was contended on behalf of the respondent that though
     under sub-Section (7) of Section 31 of the 1996 Act interest can be
     awarded, Arbitral Tribunal, however, had not clarified as to whether
     the said interest was awarded under clause (a) of sub-Section (7) of
     Section 31 of the 1996 Act or not. Appellant filed objection to such
     application primarily contending on merit that no such clarification
     was warranted in the facts and circumstances of the case.
14. Learned Arbitrator after hearing the parties issued a clarification on
    15.03.2005 vis-à-vis payment of interest. After analysing the provisions
    of both Section 31(7)(a) and Section 31(7)(b) of the 1996 Act, learned
    Arbitrator clarified that post-award interest shall be payable on the
    awarded sum i.e. on the amount of claim awarded plus the interest
    for the pre-reference period as well as interest pendente lite from
    the date of the award till it is paid @ 18% per annum.
15. It may be mentioned that against the order of the Division Bench
    of the High Court dated 03.01.2005 whereby the Division Bench
    had granted permission to the respondent to approach the Arbitral
    Tribunal for clarification, appellant had filed special leave petition
    before this Court being SLP(C) CC No. 5011/2007 and by order
    dated 09.07.2007, the said special leave petition was dismissed.
16. Against the clarification of the learned Arbitrator dated 15.03.2005,
    an application was filed by the appellant before the Single Bench
    being EA(OS) No. 270/2005 in the pending Ex.P. No. 99/1998 for
    setting aside the said clarification. By the order dated 19.02.2008,
    learned Single Judge, after referring to Section 32 of the 1996 Act
    and a decision of the Delhi High Court in Ircon International Ltd. Vs.
    Budhiraja Mining & Construction Ltd.,3 held that learned Arbitrator had
    become functus officio and, therefore, had no authority to entertain
    the application for clarification. After 30 days of the award, learned
    Arbitrator had no authority to make any change in the award. The
    earlier order of the learned Arbitrator awarding simple interest @
    18% per annum on the awarded amount from 01.04.1990 till the date
    of actual payment takes care of the interest part. Learned Single
    Judge, therefore, set aside the clarification issued by the learned



3   2007(4) Arb. LR 159 (Delhi)
1588                                                      [2024] 11 S.C.R.

                         Supreme Court Reports


     Arbitrator, declaring that the award dated 16.12.1997 passed earlier
     and the interest granted thereunder would hold the field and would
     be payable by the judgment debtor (appellant) to the judgment
     holder (respondent).
17. According to the appellant, it paid the interest component and
    submitted before the executing court that the decree stood satisfied.
    Learned Single Judge vide the order dated 08.10.2010 disposed
    of the execution petition being Ex.P. No. 99/1998 holding that the
    decree stood satisfied.
18. Against the order dated 19.02.2008, respondent preferred an appeal
    before the Division Bench being EFA(OS) No. 16/2008. Division
    Bench vide the order dated 23.02.2012 referred to the decision
    of this Court in S.L. Arora (supra) and held that the settled legal
    position that prevailed was that compound interest under the 1996
    Act could not be granted in view of the decision in S.L. Arora (supra).
    Resultantly, the amount covered by the compound interest was not
    payable. It was observed that in view of the settled legal position that
    respondent was not entitled to compound interest as per the decision
    in S.L. Arora (supra), the appeal had become an academic exercise.
    Division Bench therefore declined to examine the reasoning of the
    learned Single Judge while passing the order dated 19.02.2008. The
    appeal of the appellant was dismissed in the aforesaid manner and
    not on the basis of the reasons given by the learned Single Judge.
19. Assailing the order dated 23.02.2012 of the Division Bench,
    respondent preferred SLP(C) No. 18614/2012. This Court passed
    an order on 13.07.2012 to tag the aforesaid SLP with Civil Appeal
    No. 3148 of 2012 (M/s. Hyder Consulting (UK) Ltd. Vs. Governor,
    State of Orissa Thr. Chief Engineer).
20. On leave being granted, SLP(C) No. 18614/2012 came to be
    registered as Civil Appeal No. 2841 of 2015. Civil Appeal No. 3148
    of 2012 (M/s. Hyder Consulting (UK) Ltd. Vs. Governor, State of
    Orissa) came to be disposed of alongwith Civil Appeal No. 2841
    of 2015 (M/s. S.A. Builders Vs. North Delhi Municipal Corporation)
    and other connected appeals vide the order dated 12.03.2015. This
    Court referred to its earlier decision in M/s. Hyder Consulting (UK)
    Ltd. (supra) and held that the decision in S.L. Arora (supra) does
    not lay down the correct law. Computation of the amount has to be
    done by the executing court on the basis of the principles stated in
[2024] 11 S.C.R.                                                        1589

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     M/s. Hyder Consulting (UK) Ltd. (supra). In M/s. Hyder Consulting
     (UK) Ltd. (supra), it has been held that the sum directed to be paid
     by the award would mean a sum inclusive of the principal amount
     adjudged and the interest thereon. Therefore, the post-award interest
     that may be awarded would be on the principal amount as well as on
     the interest on the principal amount which together would constitute
     the sum awarded.
21. Civil Appeal No. 2841 of 2015 i.e. the civil appeal of the respondent
    was allowed by directing that the interest component payable to the
    respondent shall be computed in accordance with the law laid down
    in M/s. Hyder Consulting (UK) Ltd. (supra) and not in accordance
    with S.L. Arora (supra) since S.L. Arora (supra) has been overruled
    in M/s. Hyder Consulting (UK) Ltd. (supra). Resultantly, the decisions
    of the Single Bench as affirmed by the Division Bench were set
    aside; respondent was given liberty to seek execution of the award
    in terms of M/s. Hyder Consulting (UK) Ltd. (supra).
22. It is stated by the appellant that in the course of an audit, it transpired
    that it had made excess payment to the respondent due to an error
    in calculation of interest. Therefore, appellant filed an application
    being EA(OS) No. 364/2013 in the disposed of execution petition
    being Ex. P. No. 99/1998 praying for a direction for refund of the
    excess payment which was quantified at Rs. 1,54,19,281.00 alongwith
    interest @ 18% from 09.09.2010 till the date of payment. Thereafter,
    appellant filed another application being EA(OS) No. 25/2015 for
    amending the earlier application being EA(OS) No. 364/2013. It
    was stated that the refund claim amount was Rs. 5,45,41,756.00
    as on 09.09.2010. In the proceedings held on 10.03.2017, learned
    Single Judge prima facie held that respondent would be entitled to
    interest on the pre-award interest. Appellant was directed to verify
    the calculation of interest and to deposit the said amount before
    the High Court which would be without prejudice to the rights and
    contentions of the appellant.
23. Respondent filed a fresh application before the Single Bench being
    EA(OS) No. 34/2016 claiming a sum of Rs. 9,10,43,399.53 as on
    31.12.2015 from the appellant in view of the order of this Court dated
    12.03.2015 passed in C.A. No. 2841 of 2015.
24. Appellant also filed an application being EA(OS) No. 166/2017
    before the executing court for recall of the direction for deposit of
1590                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


     the additional interest. Learned Single Judge vide the judgment and
     order dated 19.04.2017 held that the arbitral award dated 16.12.1997
     has to be considered in the light of the decision of this Court in
     M/s. Hyder Consulting (UK) Ltd. (supra). On the contention of the
     appellant that the learned Arbitrator had no jurisdiction to issue such
     clarification as the Arbitral Tribunal had become functus officio, the
     same was rejected by the learned Single Judge on the ground that
     such clarification was obtained in terms of the leave granted by
     the Division Bench; the special leave petition filed by the appellant
     against the order of the Division Bench was dismissed by this Court;
     further, the decision of the Single Bench dated 19.02.2008 setting
     aside the clarification issued by the learned Arbitrator as upheld by
     the Division Bench was expressly set aside by this Court. Therefore,
     learned Single Judge held that respondent would be entitled to
     post-award interest not only on the claims as awarded [except claim
     No. 23(b)] but also on the pre-award interest. The quantum of pre-
     award interest would be included in the amount awarded and that
     the post-award interest would run on the said composite amount.
     Thus, the amount payable by the appellant to the respondent would
     have to be computed on the said basis. Accordingly, the appellant
     was directed to verify the calculations and to pay the amount to the
     respondent within four weeks.
25. The aforesaid judgment and order of the learned Single Judge
    dated 19.04.2017 was assailed by the appellant in appeal before the
    Division Bench being EFA(OS) No.17/2017. Division Bench vide the
    order dated 26.07.2017 noted that an amount of Rs. 5,14,44,393.00
    was outstanding, due to be paid by the appellant to the respondent.
    Accordingly, without prejudice to the respective rights and contentions
    of the parties, a direction was issued to the appellant to deposit
    a sum of Rs. 5,14,44,393.00 before the High Court on or before
    06.09.2017 to be released in favour of the respondent, subject to
    offering of solvent security.
26. In terms of the aforesaid direction, appellant deposited on 04.09.2017
    a sum of Rs. 5,14,44,393.00 before the High Court by way of a
    demand draft dated 30.08.2017.
27. Thereafter, an application was filed before this Court by the appellant
    for seeking clarification of the order dated 12.03.2015 passed in C.A.
    No. 2541 of 2015. It was contended therein that the civil appeal of
[2024] 11 S.C.R.                                                          1591

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     the respondent was decided on the principles of law laid down in
     M/s. Hyder Consulting (UK) Ltd. (supra) but the main issue that
     learned Arbitrator lacked jurisdiction to entertain the application for
     clarification and then to pass a clarificatory order was not gone into.
28. However, the aforesaid application being M.A. No. 927 of 2018 was
    withdrawn by the appellant and was disposed of as such vide the
    order dated 13.04.2018.
29. Division Bench thereafter passed the impugned order dated
    01.07.2019 rejecting the contention of the appellant that the learned
    Arbitrator had no jurisdiction because by the order dated 12.03.2015,
    this Court had directed that the High Court would decide the issue of
    interest component payable to the respondent in accordance with the
    law laid down in M/s. Hyder Consulting (UK) Ltd. (supra) and not in
    accordance with S.L. Arora (supra). That apart, such a contention was
    not available to the appellant at the stage of execution proceeding.
    The matter had attained finality upto the level of this Court and, thus,
    cannot be interfered with on merit. Therefore, with the consent of
    the parties, Division Bench set aside the operative part of the order
    dated 19.04.2017 pertaining only to the calculations and permitted
    both the parties to make submissions restricted to the quantum of
    the amount payable to the respondent. Learned Single Judge was
    requested to decide the amount payable to the respondent after
    hearing both the sides.

     Pleadings
30. According to the appellant, learned Arbitrator had become functus
    officio after passing of the award dated 16.12.1997. Therefore, he
    had no jurisdiction to issue the clarification dated 15.03.2005.
     30.1. In the garb of the clarification dated 15.03.2005, learned
           Arbitrator had substantially modified the award dated
           16.12.1997. Appellant’s challenge to the same on the ground
           that learned Arbitrator had no jurisdiction to issue the clarification
           since he had become functus officio was upheld by the learned
           Single Judge vide the order dated 19.02.2008. Challenge to the
           aforesaid order by the respondent was rejected by the Division
           Bench vide the order dated 23.02.2012. However, Division
           Bench did not examine the question of jurisdiction but applied
           the ratio of S.L. Arora (supra) while dismissing the appeal of
1592                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


          the respondent though this was the issue before the Division
          Bench. When the aforesaid order of the Division Bench was
          questioned before this Court by the respondent in C.A. No.
          2841 of 2015, the same was allowed vide the order dated
          12.03.2015 relying on the decision of this Court in M/s. Hyder
          Consulting (UK) Ltd. (supra) which had overruled the earlier
          decision in S.L. Arora (supra). This Court also did not examine
          the primary question as to whether the learned Arbitrator had
          become functus officio while issuing the clarification.
    30.2. When the appellant had earlier questioned the award under
          Section 34 of the 1996 Act and thereafter under Section 37
          of the 1996 Act, the clarification dated 15.03.2005 was not
          in existence. Therefore, appellant could challenge the same
          only in the execution proceeding. Though the learned Single
          Judge had upheld the objection of the appellant and had set
          aside the clarification, Division Bench of the High Court while
          upholding the decision of the learned Single Judge and this
          Court while setting aside both the orders of the learned Single
          Judge and the Division Bench, did not examine this aspect
          of the matter.
    30.3. It is also contended that learned Arbitrator had terminated the
          arbitral proceedings vide the award dated 16.12.1997 followed
          by the corrigendum dated 18.12.1997. No application having
          been moved for rectification of any clerical or calculation error
          within 30 days in terms of Section 33 of the 1996 Act and the
          respondent having not challenged the award under Section 34
          of the said Act, learned Arbitrator could not have introduced
          any correction to the award, that too, in the manner in which it
          has been done. In the award, he had granted simple interest
          whereas by way of clarification, the same was changed to
          compound interest.
    30.4. It is settled law that Section 33 is the only provision in the
          1996 Act which allows correction of clerical errors. In the garb
          of clarification or correcting clerical errors, learned Arbitrator
          introduced substantial change in the award. In any view of
          the matter, the power under Section 33 of the 1996 Act could
          not have been exercised by the learned Arbitrator more than
          6 years after passing of the award.
[2024] 11 S.C.R.                                                       1593

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


31. Respondent in its counter affidavit has stated that the special
    leave petition out of which the present civil appeal arises is totally
    misconceived and is an abuse of the process of law.
     31.1. Learned Arbitrator vide the award dated 16.12.1997 had
           awarded a sum of Rs. 1,70,70,720.80 (corrected to Rs.
           1,70,40,720.80) alongwith interest @ 18% per annum in favour
           of the respondent. In the course of the execution proceeding,
           the executing court i.e. the learned Single Judge referred the
           matter to the Division Bench on the question as to whether under
           Section 31(7) of the 1996 Act, post-award interest would be on
           the principal sum adjudged or would be on the principal sum plus
           interest on the principal sum which had accrued from the date of
           the cause of action to the date of passing of the award. Division
           Bench permitted the respondent to seek clarification from the
           learned Arbitrator. This order was challenged by the appellant
           before this Court by way of a special leave petition. However, the
           said special leave petition was dismissed. It was, thereafter, that
           the clarification was issued by the learned Arbitrator. Appellant
           never challenged the clarified award under Section 34 of the
           1996 Act; instead approached the executing court. The executing
           court i.e. learned Single Judge had erroneously set aside the
           clarification. Appeal filed by the respondent against such order
           was dismissed by the Division Bench. When the respondent
           had approached this Court by filing special leave petition, a
           three-Judge Bench of this Court had already decided the issue
           in M/s. Hyder Consulting (UK) Ltd. (supra). In the said decision,
           this Court held that an arbitrator has the power to grant post-
           award interest under Section 31(7) of the 1996 Act on the sum
           comprising of the principal plus interest on the principal which
           has accrued from the date of cause of action to the date of
           passing of the award. Leave was granted whereafter the civil
           appeal of the respondent was allowed by this Court. Following
           the law laid down in M/s. Hyder Consulting (UK) Ltd. (supra),
           the orders of Single Bench and Division Bench were set aside.
           Liberty was granted to the respondent to seek execution as per
           the law in M/s. Hyder Consulting (UK) Ltd. (supra).
     31.2. In the above context, it is contended on behalf of the respondent
           that the clarification issued by the learned Arbitrator stood
           affirmed by this Court. Therefore, post the decision of this
1594                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


            Court, it is not open to the appellant to again question the
            clarification on the ground that learned Arbitrator had no
            jurisdiction to issue such clarification.
     31.3. Notwithstanding the same, appellant had filed M.A.
           No. 927/2018 before this Court seeking clarification of the order
           dated 12.03.2015 passed in the disposed of civil appeal which
           was decided in favour of the respondent. Same grounds qua
           lack of jurisdiction on the part of the learned Arbitrator were
           raised in the miscellaneous application as are being raised
           now. The miscellaneous application was extensively argued
           before this Court. It was orally observed by this Court during
           the hearing that the clarification was in consonance with the
           law laid down by the three-Judge Bench of this Court in M/s.
           Hyder Consulting (UK) Ltd. (supra) and was on the verge of
           dismissing the miscellaneous application. It was at that stage
           that learned counsel for the appellant sought leave of this Court
           to withdraw the miscellaneous application and accordingly,
           the same was disposed of as withdrawn. However, no liberty
           was granted to the appellant to reagitate the said issue again
           in any other proceeding. That being the position, appellant is
           estopped from raking up the said issue again before this Court.
     31.4. It is contended that learned Arbitrator was well within his powers
           under Section 33 of the 1996 Act to issue the clarification
           which has now attained finality.
     31.5. In that view of the matter, the civil appeal being devoid of any
           merit should be dismissed.

     Submissions
32. Ms. Madhavi Divan, learned senior counsel for the appellant, at
    the outset, submitted that the clarification of the learned Arbitrator
    dated 15.03.2005 is a nullity in the eyes of law. Referring to the final
    award dated 16.12.1997, learned senior counsel submits that learned
    Arbitrator had awarded simple interest @ 18% per annum from the
    date of the cause of action i.e. 01.04.1990 till the date of actual
    payment which includes the post-award period as well. She submits
    that since the award provided for post-award interest, provisions of
    Section 31(7)(b) of the 1996 Act would not come into play.
[2024] 11 S.C.R.                                                      1595

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     32.1. This position is clear and unambiguous. Notwithstanding the
           same, after a period of about 8 years, respondent, at the stage
           of execution proceeding, made a request before the Division
           Bench of the High Court for clarification from the learned
           Arbitrator as to whether the interest was awarded under
           Section 31(7) of the 1996 Act or not. Without expressing any
           opinion on the said issue, Division Bench vide the order dated
           03.01.2005 permitted the respondent to approach the learned
           Arbitrator for clarification. Though this decision of the Division
           Bench was challenged before this Court by the appellant by
           way of special leave petition, the same was dismissed.
     32.2. Learned senior counsel submits that the clarification sought
           for by the respondent from the learned Arbitrator was that in
           the award it was not specifically mentioned that interest was
           granted under sub-Section(7) of Section 31 of the 1996 Act.
           Highlighting this aspect, learned senior counsel submits that
           learned Arbitrator was requested only to specifically mention
           whether the interest was awarded under Section 31(7) of the
           1996 Act or not.
     32.3. She further submits that in the clarificatory proceedings before
           the learned Arbitrator, it was specifically urged on behalf of
           the appellant that the learned Arbitrator had awarded past,
           pendente lite and future interest in terms of Section 31(7) of
           the 1996 Act. However, in the garb of issuing a clarification,
           learned Arbitrator fundamentally altered the award resulting
           in heavy financial burden on the appellant.
     32.4. Therefore, learned Arbitrator had transgressed the scope of
           clarification sought for by the respondent, much beyond the
           scope of Section 33(1)(a) of the 1996 Act.
     32.5. Learned senior counsel in support of her above contention
           has placed reliance on the decision of this Court in Gyan
           Prakash Arya Vs. Titan Industries Ltd.,4 more particularly on
           paragraph 13 thereof.
     32.6. Ms. Divan vehemently argued that under the 1996 Act the
           arbitration proceedings came to be terminated upon making


4   (2023) 1 SCC 153
1596                                                        [2024] 11 S.C.R.

                           Supreme Court Reports


              of the award under Section 32 thereof. Any fresh award
              beyond the four corners of Section 33 of the said Act is barred
              and would be a nullity. It is a case of lack of subject-matter
              jurisdiction and, therefore, the clarification is non est in the
              eyes of law. In this connection, she has referred to a decision
              of this Court in Harshad Chiman Lal Modi Vs. DLF Universal
              Ltd.,5 more particularly to paragraphs 30 to 33 thereof. Any
              order passed by a tribunal lacking inherent jurisdiction would
              be coram non judice. Such an order would be a nullity and is
              non est. The same can be questioned at any stage i.e. at the
              stage of execution or even in a collateral proceeding.
     32.7. Proceeding further, learned senior counsel submits that this
           Court never had the opportunity in the earlier proceedings to
           examine the issue as to whether learned Arbitrator had acted
           without jurisdiction while issuing the clarification which resulted
           in modifying the original award. Therefore, the said issue may
           be examined and the civil appeal should be allowed.
     32.8. Finally, learned senior counsel referred to the decision of this
           Court in M/s. Hyder Consulting (UK) Ltd. (supra) and submits
           that in that case this Court had clarified the expression ‘the
           arbitral tribunal may include in the sum, for which the award is
           made’, occurring in Section 31(7)(a) of the 1996 Act, holding
           that the sum may include the principal amount and the interest
           accrued thereon and, therefore, grant of interest on interest
           or compound interest is permissible under Section 31(7)(b) of
           the said Act. She asserts that M/s. Hyder Consulting (UK) Ltd.
           (supra) is not an authority for the proposition that where the
           arbitrator had exercised his jurisdiction not to grant compound
           interest, even then such compound interest ought to be granted
           or is mandated to be granted. On the contrary, M/s. Hyder
           Consulting (UK) Ltd. (supra) recognises that such interest may
           be contained in the ‘sum’ or may not be contained in the said
           ‘sum’. According to her, it would be a complete absurdity if M/s.
           Hyder Consulting (UK) Ltd. (supra) is interpreted to mean that
           where interest on interest has not been granted or interest is
           not contained in the sum, it should be superimposed on an



5   (2005) 7 SCC 791
[2024] 11 S.C.R.                                                       1597

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


            existing award. Seen in the above backdrop, the direction of
            this Court to compute the interest amount, in accordance with
            the law laid down in M/s. Hyder Consulting (UK) Ltd. (supra),
            cannot be interpreted to mean that compound interest must
            be granted where it has not been granted in the first place.
     32.9. She, therefore, submits that the impugned order of the Division
           Bench of the High Court is required to be set aside and the
           entire controversy is required to be given a quietus.
33. Mr. C. Aryama Sundaram, learned senior counsel representing the
    respondent at the outset submits that the primary issue raised by
    the appellant in the present proceeding i.e. whether the Arbitrator
    had become functus officio and thus had no jurisdiction to issue the
    clarification dated 15.03.2005, was expressly raised by the appellant
    and decided in favour of the respondent by this Court on three earlier
    occasions. Firstly, the Division Bench of the High Court vide the order
    dated 03.01.2005 had permitted the respondent to approach the
    Arbitral Tribunal for seeking clarification. In the special leave petition
    filed by the appellant before this Court assailing the aforesaid order of
    the Division Bench, appellant had specifically challenged not only the
    power of the High Court to refer the matter to the learned Arbitrator
    for clarification but also the very jurisdiction of the learned Arbitrator
    to issue such clarification. The said SLP was dismissed by this Court
    vide the order dated 09.07.2007. Secondly, the clarification dated
    15.03.2005 of the learned Arbitrator was challenged by the appellant
    by filing objection in the pending execution proceeding. The challenge
    was made on the ground that the learned Arbitrator had become
    functus officio and thus had no authority to issue any clarification.
    Learned Single Judge had set aside the clarification of the learned
    Arbitrator by accepting the contention of the appellant which order
    was upheld by the Division Bench. Special leave petition filed by the
    respondent against the aforesaid order of the Division Bench was
    allowed by this Court vide the order dated 12.03.2015; judgments
    of the learned Single Judge as well as of the Division Bench of the
    High Court whereby the clarification issued by the learned Arbitrator
    was set aside were reversed by this Court vide the order dated
    12.03.2015. Thirdly, appellant had filed a miscellaneous application
    before this Court seeking clarification of the aforesaid order dated
    12.03.2015. In the said application, it was specifically pleaded that
    the order dated 12.03.2015 only considered the issue of interest:
1598                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


     whether governed by S.L. Arora (supra) or by M/s. Hyder Consulting
     (UK) Ltd. (supra) and that other issues contained in the order of the
     learned Single Judge dated 19.02.2008 were not considered by this
     Court. After arguing the miscellaneous application at considerable
     length, appellant unconditionally withdrew the same when it was
     about to be dismissed. Mr. Sundaram submits that when an objection
     is raised but not pressed, it must be taken to have been impliedly
     overruled. Therefore, the party that had raised objection earlier would
     be precluded from raising the same again in view of the bar of res
     judicata. Thus, appellant is debarred from raising the same issue
     again and again (in this case for the fourth time).
     33.1. Learned senior counsel submits that the principle of constructive
           res judicata is applicable to execution proceeding as well and
           in this connection, relies upon a decision of this Court in
           Mohanlal Goenka Vs. Benoy Kishna Mukherjee.6
      33.2. He also submits that when the respondent had filed application
            before the learned Arbitrator for clarification on the question
            of interest upon permission being granted by the Division
            Bench of the High Court, appellant did not raise any objection
            before the learned Arbitrator as to its jurisdiction to issue
            such clarification or that the learned Arbitrator had become
            functus officio. Referring to the decision of this court in Gas
            Authority of India Limited Vs. Keti Construction (I) Limited,7 he
            submits that if objection as to jurisdiction is not raised before
            the Arbitral Tribunal, the same cannot be allowed to be raised
            later in subsequent proceedings.
     33.3. Proceeding further, Mr. Sundaram, learned senior counsel
           submits that after the learned Arbitrator had issued the
           clarification dated 15.03.2005, no petition was filed by the
           appellant under Section 34 of the 1996 Act. Therefore, appellant
           had consciously waived off its right to challenge the said
           clarification which has thus become final.
     33.4. Referring to the decision of this Court in M/s. Hyder Consulting
           (UK) Ltd. (supra), learned senior counsel submits that this



6   (1952) 2 SCC 648
7   (2007) 5 SCC 38
[2024] 11 S.C.R.                                                         1599

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


              Court in the aforesaid decision has held that the moment the
              arbitrator awards pendente lite interest under Section 31(7)
              (a) of the 1996 Act, the same automatically merges with the
              principal amount and becomes part of the ‘sum’ awarded. This
              means that there is no requirement of the arbitrator specifically
              mentioning in the award that the pendente lite interest would
              merge with the principal or that it would bear future interest;
              rather, in view of the language used in Section 31(7)(b) of the
              1996 Act, the pendente lite interest automatically merges with
              the principal so as to arrive at the ‘sum’ for the purpose of
              calculation of future interest. Clarification given by the learned
              Arbitrator is completely in consonance with the law laid down
              by this Court in M/s. Hyder Consulting (UK) Ltd. (supra). A bare
              reading of the original award dated 16.12.1997 conveys the
              same meaning. Therefore, it cannot be said that the learned
              Arbitrator had made any modification of the award or had
              passed a completely new award. It was purely and simply a
              clarification of what was awarded.
     33.5. Learned senior counsel for the respondent submits that this
           Court vide the order dated 12.03.2015 held that the interest
           component shall be calculated in accordance with the law
           laid down in M/s. Hyder Consulting (UK) Ltd. (supra). In the
           execution proceeding, respondent had lodged claim strictly in
           accordance with the law laid down in M/s. Hyder Consulting
           (UK) Ltd. (supra). This decision has been explained and
           reiterated by this Court in the case of Delhi Airport Metro
           Express Private Limited Vs. Delhi Metro Rail Corporation.8 This
           Court categorically held that in view of M/s. Hyder Consulting
           (UK) Ltd. (supra), the amount awarded under Section 31(7)
           (a) would include the principal amount plus the interest
           amount pendente lite. It was further held that the interest
           calculated as per Section 31(7)(b) of the 1996 Act would be
           on the sum arrived at under Section 31(7)(a) of the 1996
           Act. Learned senior counsel asserts that it would be wrong
           to say that learned Arbitrator had no jurisdiction to issue the
           clarification. A plain reading of Section 33(2) of the 1996 Act
           would show that the learned Arbitrator had the jurisdiction to
           issue the clarification. He submits that even learned Single


8   (2022) 9 SCC 286
1600                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


           Judge while setting aside the clarification acknowledged the
           fact that the learned Arbitrator had the jurisdiction to issue the
           clarification but the same had to be issued within 30 days.
           Once the Division Bench had given liberty to the respondent
           to seek clarification after 30 days even that issue i.e. seeking
           of clarification beyond 30 days would be of no consequence.
     33.6. Learned senior counsel submits that undue hardship and
           serious prejudice would be caused to the respondent if the
           concurrent findings of two courts which are based on order(s)
           of this Court are set aside. Contending that there is no merit
           in the civil appeal, respondent seeks dismissal of the same.
34. After the arguments were closed and judgment was reserved, we had
    permitted the parties to file brief summary of submissions actually
    canvassed before the Court. Pursuant to such permission, both the
    sides have filed brief summary of submissions.
35. Submissions made by learned counsel for the parties have received
    the due consideration of the Court. We have also considered the
    summary of submissions as well as the judgments cited at the bar.

     Analysis
36. Let us at the outset refer to and analyse the relevant provisions of
    the 1996 Act. Section 31 of the 1996 Act deals with the form and
    contents of arbitral award. Section 31 has eight sub-Sections. Sub-
    Section (7) is relevant to the debate. Sub-Section (7) as it stood at
    the relevant point of time reads as under:
          31. Form and contents of arbitral award –
              *            *          *            *          *
          (7)(a) Unless otherwise agreed by the parties, where and in
          so far as an arbitral award is for the payment of money, the
          arbitral tribunal may include in the sum for which the award
          is made interest, at such rate as it deems reasonable, on
          the whole or any part of the money, for the whole or any
          part of the period between the date on which the cause
          of action arose and the date on which the award is made.
          (b) A sum directed to be paid by an arbitral award shall,
          unless the award otherwise directs, carry interest at the
[2024] 11 S.C.R.                                                         1601

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


          rate of eighteen per centum per annum from the date of
          award to the date of payment.
     36.1. From a minute reading of sub-Section (7), it is seen that it has
           got two parts: the first part i.e. clause (a) deals with passing
           of award which would include interest up to the date on which
           the award is made. The second part i.e. clause (b) deals with
           grant of interest on the ‘sum’ awarded by the Arbitral Tribunal.
     36.2. Let us now discuss in detail the contours of the two clauses.
           As per clause (a), when an award is made by the arbitral
           tribunal for payment of money, the ‘sum’ which is awarded
           may include interest at such rate as the arbitral tribunal deems
           appropriate, on the whole or any part of the money and for
           the whole or any part of the period. The period for which the
           interest may be granted would be between the date on which
           the cause of action arose and the date on which the award
           is made. The expression which needs to be noticed in this
           part is the following: the arbitral tribunal may include in the
           sum for which the award is made interest at such rate as it
           deems reasonable.
     36.3. The word ‘may’ appearing in the above expression is quite
           significant. It implies that the arbitral tribunal has the discretion
           to grant interest at a reasonable rate. In other words, it may
           grant interest or it may not grant interest; but if it grants
           interest, it would be included in the ‘sum’ which is awarded
           by the arbitral tribunal.
     36.4. This brings us to the second part i.e. clause (b) which deals
           with post award interest. The ‘sum’ directed to be paid by the
           arbitral tribunal shall, unless the award otherwise directs, carry
           interest at the rate of 18 percent per annum from the date
           of the award to the date of payment. Thus, what clause (b)
           provides for is that the arbitral tribunal may award interest on
           the ‘sum’ adjudged under clause (a). But if no such interest is
           awarded, then there shall be interest at the rate of 18 percent
           on the ‘sum’ awarded by the arbitral tribunal from the date
           of the award to the date of payment. The two crucial words
           in this part are sum and shall. As seen from clause (a), the
           ‘sum’ awarded by the arbitral tribunal would include interest
1602                                                         [2024] 11 S.C.R.

                          Supreme Court Reports


            if it is granted by the arbitral tribunal. Therefore, the ‘sum’
            as awarded by the arbitral tribunal may or may not include
            interest. Whether the ‘sum’ so awarded includes or does not
            include interest, it would carry further interest at the rate of
            18 percent from the date of the award to the date of payment
            unless another rate of interest is granted by the arbitral tribunal.
            While granting of interest under clauses (a) and (b) by the
            arbitral tribunal is discretionary, the interest contemplated
            under clause (b) in the event of failure of the arbitral tribunal
            to award interest is mandatory. Therefore, the legislature has
            consciously used the word shall.
37. Thus from an analysis of Section 31(7)(a) of the 1996 Act, which
    provides for pre-award interest, it is seen that the provision begins
    with the expression unless otherwise agreed by the parties, thereby
    highlighting the legislative stance that parties possess the autonomy
    to determine pre-award interest on the payment of money awarded
    by the arbitral tribunal. However, no such discretion is available
    to the parties under Section 31(7)(b) of the 1996 Act though such
    discretion is available to the arbitral tribunal.
38. Natural corollary to the above analysis would be that the ‘sum’ so
    awarded by the arbitral tribunal which may include interest from the
    date when the cause of action arose to the date of the award, would
    carry further interest of 18 percent from the date of the award to the
    date of payment unless the arbitral award otherwise directs. Thus,
    the legislative intent is that the awarded sum whether inclusive of
    interest or not, in case included, then from the date of cause of action
    to the date of award, would carry further interest from the date of
    the award to the date of payment.
39. Generally, going by the provisions contained in Section 31(7) of
    the 1996 Act, it is evident that an arbitral tribunal has the power to
    grant (i) pre-award (ii) pendente lite (iii) post-award interest. Intention
    behind awarding pre-award interest is primarily to compensate the
    claimant for the pecuniary loss suffered from the time the cause of
    action arose till passing of the arbitral award. Further, this is also to
    ensure that the arbitral proceeding is concluded within a reasonable
    period to minimise the impact of the pre-award interest as well as
    interest pendente lite; thereby promoting efficiency in the arbitration
    process. Similarly, grant of post-award interest also serves a salutary
[2024] 11 S.C.R.                                                      1603

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     purpose. It primarily acts as a disincentive to the award debtor not
     to delay payment of the arbitral amount to the award holder.
40. In S.L. Arora (supra), a two-Judge Bench of this Court considered
    amongst others the question as to whether Section 31 (7) of the
    1996 Act authorises and enables arbitral tribunals to award interest
    on interest from the date of the award till payment. After referring
    to the old Arbitration Act, 1940 as well as to the provisions of the
    Interest Act, 1978, the Bench observed that unlike the old Act the
    1996 Act contains specific provision dealing with power of the arbitral
    tribunal to award interest. Analysing the aforesaid provision, the
    Bench further observed that Section 31 (7) makes no reference to
    payment of compound interest or payment of interest upon interest;
    nor does it require the interest which accrues till the date of the award
    to be treated as part of the principal from the date of the award for
    calculating the post-award interest. Examining the difference between
    clauses (a) and (b) of Section 31 (7) of the 1996 Act, the Bench
    observed that clause (a) relates to pre-award period interest whereas
    clause (b) relates to post-award period interest. The contract binds
    and prevails in regard to interest during the pre-award period. The
    contract has no application in regard to interest during the post-award
    period. Clause (a) gives discretion to the arbitral tribunal in regard to
    the rate, the period, the quantum (principal) when awarding interest.
    But such discretion is always subject to the contract between the
    parties. Clause (b) also gives discretion to the arbitral tribunal to
    award interest for the post-award period but that discretion is not
    subject to any contract; moreover, if that discretion is not exercised
    by the arbitral tribunal, then the statute steps in and mandates
    payment of interest at the specified rate of 18% per annum for the
    post-award period. While clause (a) gives the parties an option to
    contract out of interest, no such option is available in regard to the
    post-award period.
     40.1. Summing up, the Bench observed that in regard to pre-award
           period, interest has to be awarded as specified in the contract
           and in the absence of any contract, as per the discretion of the
           arbitral tribunal. On the other hand, in regard to the post-award
           period, interest is payable as per the discretion of the arbitral
           tribunal and in the absence of exercise of such discretion, at
           the mandatory statutory rate of 18% per annum. According
           to the Bench, the award of interest under sub-Section (7) of
1604                                                      [2024] 11 S.C.R.

                        Supreme Court Reports


           Section 31, like award of cost under sub-Section (8) of Section
           31 of the 1996 Act, are ancillary matters when the arbitral
           tribunal decides the substantive dispute(s) between the parties.
           Therefore, the expressions sum for which the award is made
           and a sum directed to be paid by an arbitral award contextually
           refers to the award on the substantive claims and not ancillary
           or consequential directions relating to interest and costs. The
           Bench explained that clause (b) of Section 31(7) is intended to
           ensure prompt payment by the award debtor once the award
           is made. The higher rate of interest is provided in clause (b)
           with the deliberate intent of discouraging award debtors from
           adopting dilatory tactics and to persuade them to comply with
           the award. Holding that in the absence of any provision for
           interest upon interest in the contract, arbitral tribunals do not
           have the power to award interest upon interest or compound
           interest either for the pre-award period or for the post-award
           period, the Bench concluded as under:
               34. Thus it is clear that Section 31(7) merely
               authorises the Arbitral Tribunal to award interest in
               accordance with the contract and in the absence of
               any prohibition in the contract and in the absence of
               specific provision relating to interest in the contract,
               to award simple interest at such rates as it deems
               fit from the date on which the cause of action arose
               till the date of payment. It also provides that if the
               award is silent about interest from the date of award
               till the date of payment, the person in whose favour
               the award is made will be entitled to interest at
               18% per annum on the principal amount awarded,
               from the date of award till the date of payment. The
               calculation that was made in the execution petition
               as originally filed was correct and the modification
               by the respondent increasing the amount due under
               the award was contrary to the award.
41. The correctness of the view taken in S.L. Arora (supra) was gone
    into by a three-Judge Bench of this Court in M/s. Hyder Consulting
    (UK) Ltd (supra). The majority opined that it was not possible to
    agree with the conclusion in S.L. Arora (supra) that Section 31(7)
    of the 1996 Act does not require that interest which accrues till the
[2024] 11 S.C.R.                                                         1605

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     date of the award be included in the sum from the date of the award
     for calculating the post-award interest. Justice Bobde in his majority
     opinion was of the view that the conclusion reached in S.L. Arora
     (supra) does not seem to be in consonance with the clear language
     of Section 31(7) of the 1996 Act. After extracting sub-Section (7) of
     Section 31 of the 1996 Act, the majority analysed clause (a) of sub-
     Section (7) in the following manner:
            4. Clause (a) of sub-section (7) provides that where an
            award is made for the payment of money, the Arbitral
            Tribunal may include interest in the sum for which the
            award is made. In plain terms, this provision confers a
            power upon the Arbitral Tribunal while making an award
            for payment of money, to include interest in the sum for
            which the award is made on either the whole or any part
            of the money and for the whole or any part of the period
            for the entire pre-award period between the date on
            which the cause of action arose and the date on which
            the award is made. To put it differently, sub-section (7)
            (a) contemplates that an award, inclusive of interest for
            the pre-award period on the entire amount directed to be
            paid or part thereof, may be passed. The “sum” awarded
            may be the principal amount and such interest as the
            Arbitral Tribunal deems fit. If no interest is awarded, the
            “sum” comprises only the principal. The significant words
            occurring in clause (a) of sub-section (7) of Section 31
            of the Act are “the sum for which the award is made”.
            On a plain reading, this expression refers to the total
            amount or sum for the payment for which the award
            is made. Parliament has not added a qualification like
            “principal” to the word “sum”, and therefore, the word
            “sum” here simply means “a particular amount of money”.
            In Section 31(7), this particular amount of money may
            include interest from the date of cause of action to the
            date of the award.
     41.1. Insofar clause (b) is concerned, the majority opined as under:
            7. ……..In other words, what clause (b) of sub-section (7)
            of Section 31 of the Act directs is that the “sum”, which
            is directed to be paid by the award, whether inclusive
1606                                                      [2024] 11 S.C.R.

                       Supreme Court Reports


          or exclusive of interest, shall carry interest at the rate of
          eighteen per cent per annum for the post-award period,
          unless otherwise ordered.
    41.2. Thus, clause (a) of sub-Section (7) of Section 31 provides
          that the arbitral tribunal may include interest while making
          an award for payment of money in the sum for which the
          award is made and as per clause (b), the sum so directed to
          be made by the award shall carry interest at a certain rate
          for the post-award period. The purpose for enacting such a
          provision is to encourage early payment of the awarded sum
          and to discourage delay. Therefore, the ‘sum’ directed to be
          paid by the arbitral award under clause (b) of sub-Section (7)
          of Section 31 of the 1996 Act is inclusive of interest pendente
          lite. In M/s. Hyder Consulting (UK) Ltd (supra), the majority
          referred to Section 34 of the Civil Procedure Code, 1908 and
          after making a comparison of the said provision with Section
          31(7) of the 1996 Act observed that while enacting Section
          34 of the Civil Procedure Code, Parliament conferred power
          on a court to award interest on the principal sum adjudged
          and not merely on the ‘sum’ as provided in the 1996 Act.
          Observing that the departure from the language of Section
          34 of the Civil Procedure Code in Section 31(7) of the 1996
          Act is significant and shows the intention of the Parliament,
          it has been held as follows:
              12. It is settled law that where different language is
              used by Parliament, it is intended to have a different
              effect. In the Arbitration Act, the word “sum” has
              deliberately not been qualified by using the word
              “principal” before it. If it had been so used, there
              would have been no scope for the contention that the
              word “sum” may include “interest.” In Section 31(7)
              of the Act, Parliament has deliberately used the word
              “sum” to refer to the aggregate of the amounts that
              may be directed to be paid by the Arbitral Tribunal
              and not merely the “principal” sum without interest.
              13. Thus, it is apparent that vide clause (a) of sub-
              section (7) of Section 31 of the Act, Parliament
              intended that an award for payment of money
              may be inclusive of interest, and the “sum” of the
[2024] 11 S.C.R.                                                             1607

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


                   principal amount plus interest may be directed to
                   be paid by the Arbitral Tribunal for the pre-award
                   period. Thereupon, the Arbitral Tribunal may direct
                   interest to be paid on such “sum” for the post-award
                   period vide clause (b) of sub-section (7) of Section
                   31 of the Act, at which stage the amount would be
                   the sum arrived at after the merging of interest with
                   the principal; the two components having lost their
                   separate identities.
                   14. In fact this is a case where the language of
                   sub-section (7) clauses (a) and (b) is so plain and
                   unambiguous that no question of construction of a
                   statutory provision arises. The language itself provides
                   that in the sum for which an award is made, interest
                   may be included for the pre-award period and that
                   for the post-award period interest up to the rate of
                   eighteen per cent per annum may be awarded on
                   such sum directed to be paid by the arbitral award.
      41.3. The majority declared that S.L. Arora (supra) was wrongly
            decided in that it holds that a sum directed to be paid by
            an arbitral tribunal and the reference to the award on the
            substantive claim does not refer to interest pendente lite
            awarded on the sum directed to be paid upon award and
            that in the absence of any provision of interest upon interest
            in the contract, the arbitral tribunal does not have the power
            to award interest upon interest or compound interest either
            for the pre-award period or for the post-award period. It has
            been clarified that the ‘sum’ includes the principal as adjudged
            together with the interest granted.
42. A three-Judge Bench of this Court in UHL Power Company Limited
    Vs. State of Himachal Pradesh,9 declared that the judgment in S.L.
    Arora (supra) has since been overruled by a three-Judge Bench of this
    Court in M/s. Hyder Consulting (UK) Ltd. (supra). The majority view
    in M/s. Hyder Consulting (UK) Ltd. (supra) is that post-award interest
    can be granted by an arbitrator on the interest amount awarded.



9   (2022) 4 SCC 116
1608                                                           [2024] 11 S.C.R.

                            Supreme Court Reports


43. The question as to whether the sum awarded under clause (a) of
    sub-Section (7) of Section 31 of the 1996 Act will include interest
    pendente lite or not again came up for consideration before a two-
    Judge Bench of this Court in Delhi Airport Metro Express Private
    Limited Vs. Delhi Metro Rail Corporation.10 The Bench referred to
    the decision of this Court in M/s. Hyder Consulting (UK) Ltd (supra)
    and held as follows:
             15. It could thus be seen that the majority view of this
             Court in Hyder Consulting (UK) is that the sum awarded
             may include the principal amount and such interest as
             the Arbitral Tribunal deems fit. It is further held that, if no
             interest is awarded, the “sum” comprises only the principal
             amount. The majority judgment held that clause (a) of
             sub-section (7) of Section 31 of the 1996 Act refers to the
             total amount or sum for the payment for which the award
             is made. As such, the amount awarded under clause
             (a) of sub-section (7) of Section 31 of the 1996 Act would
             include the principal amount plus the interest amount
             pendente lite. It was held that the interest to be calculated
             as per clause (b) of sub-section (7) of Section 31 of the
             1996 Act would be on the total sum arrived as aforesaid
             under clause (a) of sub-section (7) of Section 31 of the
             1996 Act. S.A. Bobde, J. in his judgment, has referred to
             various authorities of this Court as well as Maxwell on the
             Interpretation of Statutes. He emphasised that the Court
             must give effect to the plain, clear and unambiguous
             words of the legislature and it is not for the courts to add
             or subtract the words, even though the construction may
             lead to strange or surprising, unreasonable or unjust or
             oppressive results.
      43.1. Since in that case interest was governed by Article 29.8 of
            the concession agreement between the parties, the Bench
            explained the power of the arbitral tribunal to award interest
            qua the agreement and held as follows:
                    17. It could thus be seen that the part which deals
                    with the power of the Arbitral Tribunal to award


10   (2022) 9 SCC 286
[2024] 11 S.C.R.                                                               1609

       North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


                    interest, would operate if it is not otherwise agreed
                    by the parties. If there is an agreement between the
                    parties to the contrary, the Arbitral Tribunal would
                    lose its discretion to award interest and will have to
                    be guided by the agreement between the parties.
                    The provision is clear that the Arbitral Tribunal is
                    not bound to award interest. It has a discretion to
                    award the interest or not to award. It further has a
                    discretion to award interest at such rate as it deems
                    reasonable. It further has a discretion to award interest
                    on the whole or any part of the money. It is also not
                    necessary for the Arbitral Tribunal to award interest
                    for the entire period between the date on which the
                    cause of action arose and the date on which the
                    award is made. It can grant interest for the entire
                    period or any part thereof or no interest at all.
44. Again in the case of Morgan Securities & Credits (P) Ltd. Vs.
    Videocon Industries Ltd.,11 the issue before this Court was whether
    the expression unless the award otherwise directs appearing in
    Section 31(7)(b) of the 1996 Act only provides the arbitrator the
    discretion to determine the rate of interest or both the rate of interest
    and the ‘sum’ which must be paid. After an exhaustive examination,
    this Court summarized the findings as under:
             28.1. The judgment of the two-Judge Bench in S.L.
             Arora was referred to a three-Judge Bench in Hyder
             Consulting on the question of whether post-award interest
             could be granted on the aggregate of the principal and
             the pre-award interest arrived at under Section 31(7)(a)
             of the Act.
             28.2. Bobde, J.›s opinion in Hyder Consulting held that the
             arbitrator may grant post-award interest on the aggregate
             of the principal and the pre-award interest. The opinion did
             not discuss the issue of whether the arbitrator could use
             their discretion to award post-award interest on a part of
             the “sum” awarded under Section 31(7)(a).



11   (2023) 1 SCC 602
1610                                                           [2024] 11 S.C.R.

                          Supreme Court Reports


          28.3. The phrase “unless the award otherwise directs” in
          Section 31(7)(b) only qualifies the rate of interest.
          28.4. According to Section 31(7)(b), if the arbitrator does
          not grant post-award interest, the award holder is entitled
          to post-award interest at eighteen per cent.
          28.5. Section 31(7)(b) does not fetter or restrict the
          discretion that the arbitrator holds in granting post-award
          interest. The arbitrator has the discretion to award post-
          award interest on a part of the sum.
          28.6. The arbitrator must exercise the discretionary power
          to grant post-award interest reasonably and in good faith,
          taking into account all relevant circumstances.
         28.7     *          *         *         *        *
45. Let us now turn to Section 33 of the 1996 Act which provides for
    correction and interpretation of award; additional award. Section 33
    reads as under:
          33. Correction and interpretation of award; additional
          award.—(1) Within thirty days from the receipt of the
          arbitral award, unless another period of time has been
          agreed upon by the parties—
          (a) a party, with notice to the other party, may request
          the arbitral tribunal to correct any computation errors, any
          clerical or typographical errors or any other errors of a
          similar nature occurring in the award;
          (b) if so agreed by the parties, a party, with notice to
          the other party, may request the arbitral tribunal to give
          an interpretation of a specific point or part of the award.
          (2) If the arbitral tribunal considers the request made under
          sub-section (1) to be justified, it shall make the correction
          or give the interpretation within thirty days from the receipt
          of the request and the interpretation shall form part of the
          arbitral award.
          (3) The arbitral tribunal may correct any error of the type
          referred to in clause (a) of sub-section (1), on its own
          initiative, within thirty days from the date of the arbitral award.
[2024] 11 S.C.R.                                                            1611

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


          (4) Unless otherwise agreed by the parties, a party with
          notice to the other party, may request, within thirty days
          from the receipt of the arbitral award, the arbitral tribunal to
          make an additional arbitral award as to claims presented in
          the arbitral proceedings but omitted from the arbitral award.
          (5) If the arbitral tribunal considers the request made under
          sub-section (4) to be justified, it shall make the additional
          arbitral award within sixty days from the receipt of such
          request.
          (6) The arbitral tribunal may extend, if necessary, the period
          of time within which it shall make a correction, give an
          interpretation or make an additional arbitral award under
          sub-section (2) or sub-section (5).
          (7) Section 31 shall apply to a correction or interpretation
          of the arbitral award or to an additional arbitral award
          made under this section.
     45.1. As per sub-Section (1), within 30 days from the date of receipt
           of the arbitral award, a party with notice to the other party, may
           request the arbitral tribunal to correct any computation errors,
           any clerical or typographical errors or any other errors of a
           similar nature occurring in the award. Further, if the parties
           agree, a party with notice to the other party, may request the
           arbitral tribunal to give an interpretation of a specific point or
           part of the award. The period of 30 days contemplated under
           sub-Section (1) may stand extended to another period of time
           if agreed upon by the parties. Therefore, ordinarily the time
           limit for correction of errors or for interpretation of a specific
           point or part of the award is 30 days from the date of receipt
           of the arbitral award. However, the limitation of 30 days can
           be waived for another period of time, if agreed upon by the
           parties. Question for consideration is what would be the
           contours of the expression unless another period of time has
           been agreed upon by the parties, as appearing in sub-Section
           (1) of Section 33.
     45.2. Sub-Section (7) of Section 33 clarifies that correction or
           interpretation of arbitral award or passing of additional arbitral
           award would attract Section 31 of the 1996 Act as discussed
1612                                                      [2024] 11 S.C.R.

                         Supreme Court Reports


            supra. Therefore, the language of sub-Section (1) of Section
            33 makes it abundantly clear that the period of 30 days as
            provided in Section 33(1) is not an inflexible period. If the
            parties agree, the said period can be extended.
     45.3. There is no dispute to the proposition of law laid down in
           Harshad Chiman Lal Modi (supra), relied upon by the appellant,
           that where a court has no jurisdiction over the subject matter
           of the suit by reason of any limitation imposed by the statute,
           charter or commission, it cannot take up the cause or matter;
           an order passed by the court having no such jurisdiction is
           a nullity. Question is whether such a proposition would have
           any application to the facts and circumstances of the present
           case. As we have seen, there was no embargo on the Arbitral
           Tribunal to exercise jurisdiction over the subject matter. The
           only limitation was that the correction and/or interpretation of
           the award should be done within 30 days from the date of
           receipt of the arbitral award unless another period of time has
           been agreed upon by the parties. Therefore, the expression
           unless another period of time has been agreed upon by the
           parties assumes critical significance.
46. Reverting back to the facts of the present case, learned Arbitrator
    passed the award on 16.12.1997. After adjusting the claims and
    counter claims, learned Arbitrator granted principal amount of
    Rs. 1,70,70,720.80 (corrected to Rs. 1,70,40,720.80 as per the
    corrigendum dated 18.12.1997). On the question of interest, learned
    Arbitrator awarded simple interest @ 18% per annum on the award
    amount from 01.04.1990 i.e. the date of cause of action to the date
    of actual payment except on claim No. 23(b).
47. In the execution proceeding before the learned Single Judge, an order
    was passed on 26.08.2004. Learned Single Judge framed an issue
    for consideration as to whether post-award interest under Section
    31(7) of the 1996 Act would be calculated on the principal amount
    adjudged or on the principal amount plus interest on the principal
    amount which has accrued from the date of cause of action to the
    date of passing of the award as under the 1996 Act, award is to be
    enforced as a decree of the court. According to the learned Single
    Judge, it was an important issue affecting a large volume of litigation.
[2024] 11 S.C.R.                                                       1613

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     Therefore, to avoid proliferation of litigation and unnecessary appeals,
     learned Single Judge was of the view that the aforesaid question
     should be decided by a Division Bench.
48. From a perusal of the Division Bench order dated 03.01.2005, it is
    seen that respondent had contended that there was no clarity as
    to whether the interest awarded by the Arbitral Tribunal was under
    Section 31(7)(a) of the 1996 Act or not. Respondent then made a
    submission that he may be permitted to approach the Arbitral Tribunal
    for a clarification on this issue. In view of such submission, Division
    Bench granted permission to the respondent to approach the Arbitral
    Tribunal for clarification. While granting such permission, Division
    Bench did not answer the above question clarifying that it had not
    expressed any opinion about payment of interest either under Section
    31(7)(a) or under Section 31(7)(b) of the 1996 Act.
49. In terms of the permission granted, respondent filed an application
    before the learned Arbitrator seeking clarification of the interest
    awarded by the learned Arbitrator qua Section 31(7) of the 1996 Act.
    In its response to the application of the respondent filed before the
    learned Arbitrator, appellant contended that the learned Arbitrator had
    awarded simple interest @ 18% per annum on the awarded amount
    from 01.04.1990 to the date of actual payment except on claim No.
    23(b). Referring to the interest portion of the award, it stated that
    interest was required to be paid on Rs. 1,70,70,720.80 minus Rs.
    5,61,208.00 [for claim No. 23(b)] equal to Rs. 1,65,09,512.80, which
    is the principal amount. Therefore, it was contended that interest
    was to be paid on the amount of Rs. 1,65,09,512.80 till the date
    of payment. According to the appellant, respondent was entitled to
    interest on Rs. 1,65,09,512.80 from 01.04.1990 to 22.04.2002 @
    18% per annum. This comes to Rs. 3,56,60,547.64. Appellant had
    paid Rs. 1,65,09,512.80 on 22.04.2002 and another amount of Rs.
    2,11,29,475.20 was paid towards interest also on 22.04.2002. It
    was submitted that learned Arbitrator had awarded interest for the
    past period, pendente lite and also future interest. Thus, learned
    Arbitrator had exercised his jurisdiction under Section 31(7)(a) as
    well as under Section 31(7)(b) of the 1996 Act. Therefore, there was
    no need for clarification.
50. What is therefore discernible from the above is that appellant had
    participated in the clarificatory proceeding before the learned Arbitrator
1614                                                      [2024] 11 S.C.R.

                         Supreme Court Reports


     taking the stand that no clarification as sought for was required on
     merit.
51. Learned Arbitrator issued the clarification on 15.03.2005. It was
    clarified that the amount awarded alongwith interest for the pre-
    reference and pendente lite periods become the decretal amount.
    As per Section 31(7)(b), this amount would carry further interest @
    18% per annum. Thus, learned Arbitrator clarified that post-award
    interest shall be payable on the awarded sum i.e. the amount of claim
    awarded (principal amount) plus interest for the pre-reference period
    and pendente lite upto the date of the award at the rate mentioned
    thereunder.
52. Appellant did not challenge the clarification dated 15.03.2005 under
    Section 34 of the 1996 Act; instead appellant questioned the same in
    the execution proceeding before the learned Single Judge. Learned
    Single Judge in his order dated 19.02.2008 held that learned Arbitrator
    had become functus officio and thus had no authority to entertain
    the application for clarification. Learned Arbitrator, in his award, had
    granted simple interest @ 18% per annum on the awarded amount i.e.
    the principal amount from 01.04.1990 to the date of actual payment
    which takes care of the interest part. The decree holder (respondent
    herein) neither challenged the award nor sought clarification within
    30 days. It is also not a case where the award debtor (appellant
    herein) had agreed for extension of time limit. Holding that learned
    Arbitrator had no authority to make any change in the award, learned
    Single Judge set aside the clarification.
53. When the respondent approached the Division Bench assailing the
    above decision of the learned Single Judge, the Division Bench
    held vide the order dated 23.02.2012 that in view of the judgment
    in S.L. Arora (supra), compound interest under the 1996 Act cannot
    be granted. Accordingly, challenge to the decision of the learned
    Single Judge was rejected.
54. When the matter came up before this Court in Civil Appeal No. 2841
    of 2015 at the instance of the revenue, this Court observed that the
    decision in S.L. Arora (supra) has been overruled in M/s. Hyder
    Consulting (UK) Ltd. (supra) declaring that the interest component
    payable to the respondent shall be computed in accordance with
    the law laid down in M/s. Hyder Consulting (UK) Ltd. (supra). Both
    the orders of the learned Single Judge and the Division Bench were
[2024] 11 S.C.R.                                                         1615

      North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


     set aside, further clarifying that it would be open to the respondent
     to seek execution as per the law pronounced by this Court in M/s.
     Hyder Consulting (UK) Ltd. (supra).
55. Thereafter, the executing court i.e. learned Single Judge passed
    the order dated 19.04.2017. Learned Single Judge, firstly, held
    that it was no longer open to examine the question as to whether
    the respondent had any right to approach the learned Arbitrator
    to seek clarification or whether the learned Arbitrator had become
    functus officio since the Division Bench had expressly permitted the
    respondent to seek clarification from the learned Arbitrator which
    decision was not interfered with by this Court. Thereafter, the decision
    of the Single Bench setting aside the clarification of the learned
    Arbitrator which was affirmed by the Division Bench were set aside
    by this Court in the civil appeal of the respondent with liberty to the
    respondent to seek execution as per the law laid down in M/s. Hyder
    Consulting (UK) Ltd. Secondly, learned Single Judge clarified that
    the respondent would be entitled to post-award interest not only on
    the claims as awarded but also on the pre-award interest as well
    as on the interest pendente lite. The quantum of pre-award interest
    and the interest pendente lite would be calculated and included in
    the amount awarded i.e. the ‘sum’ and the post-award interest would
    run on the said ‘sum’ i.e. principal amount plus interest (pre-award
    interest plus interest pendente lite).
56. When the appellant assailed this order before the Division Bench,
    vide the impugned order dated 01.07.2019, the Division Bench held
    as follows:
          17. We, thus, reject the contentions of the learned counsel
          for the appellant for the reason that in the order dated
          12.03.2015, the Supreme Court has directed that the
          High Court would decide the issue of interest component
          payable to the respondent in accordance with law laid
          down in M/s Hyder Consulting (UK) Ltd. (supra) and not in
          accordance with law laid down in S.L. Arora (supra). The
          other reason for rejecting the contentions of the appellant
          is that the grounds, which are sought to be urged before
          us, are not available to the appellant at this stage in these
          proceedings, which are execution proceedings. The matter
          had attained finality upto the Apex Court and we cannot
          interfere on the merits of the case at this stage.
1616                                                       [2024] 11 S.C.R.

                         Supreme Court Reports


          18. However, in view of the submissions of the parties with
          respect to the quantity, with the consent of the parties, we
          set aside the operative part of the order dated 19.04.2017
          pertaining only to the calculations and permit both the
          parties to make submissions restricted to the quantum of
          the amount payable to the respondent.
57. Thus, as can be seen, the impugned order is a consent order. Division
    Bench of the High Court after taking the consent of the parties had
    remitted the matter back to the High Court only as to the calculations
    permitting both the parties to make submissions before the learned
    Single Judge on the quantum payable to the respondent. If that be the
    position, it is not open to the appellant to assail the aforesaid order.
58. The issue raised by the appellant in the present proceeding i.e.
    learned Arbitrator had become functus officio and therefore had
    no jurisdiction to issue the clarification, was also raised in the
    miscellaneous application filed by the appellant before this Court
    seeking clarification of the order dated 12.03.2015. While dismissing
    the miscellaneous application, no leave was granted by this Court
    to agitate the aforesaid issue in any other proceeding. Therefore,
    viewed from this perspective also, it is not open to the appellant to
    raise the aforesaid issue again in the present proceeding.

     Conclusion
59. In view of what we have discussed above, the interpretation given by
    us to Section 33(1) of the 1996 Act and on a cumulative assessment
    of the attendant facts and circumstances of the case, we are of
    the view that the clarification sought for and issued by the learned
    Arbitrator would be covered by the expression unless another period
    of time has been agreed upon by the parties appearing in Section
    33 (1) of the 1996 Act. This is a case where court had permitted the
    respondent to seek clarification from the learned Arbitrator beyond
    the initial period of 30 days whereafter the appellant fully participated
    in the clarificatory proceeding. Therefore, the present case would be
    covered by the above expression. In the circumstances, contention of
    the appellant that the learned Arbitrator had become functus officio
    and therefore lacked jurisdiction to issue the clarification cannot be
    accepted and is thus rejected.
[2024] 11 S.C.R.                                                       1617

         North Delhi Municipal Corporation v. M/s. S.A. Builders Ltd.


60. That apart, it is not the case of the appellant that the interest portion
    is covered by the contract agreement between the parties. In the
    absence thereof, Section 31(7)(a) as well as Section 31(7)(b) of
    the 1996 Act would have their full effect. The sum awarded would
    mean the principal amount plus the interest awarded from the date
    of cause of action upto the date of the award. Thereafter, as per
    Section 31(7)(b) of the 1996 Act, the sum (principal plus interest)
    would carry interest @ 18% from the date of the award to the date
    of payment. This would be consistent with the law laid down by this
    Court in M/s. Hyder Consulting (UK) Ltd (supra).
61. We thus see no error or infirmity in the impugned order passed
    by the Division Bench of the High Court. Consequently, we are of
    the view that the appeal lacks merit and is, accordingly, dismissed.
    However, there shall be no order as to costs.

     Result of the case: Appeal dismissed.


     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Section 33 of the Arbitration and Conciliation Act, 1996"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.