NOBLE RESOURCES LTD.versusSTATE OF ORISSA AND ANR
- Citation
- 2006 INSC 607
- Decided
- 13 September 2006
- Bench
- S B SINHA
Holding
A writ petition is maintainable against a State corporation for alleged arbitrariness violating Article 14, but the court will not adjudicate detailed factual disputes or grant specific performance, leaving damages as the appropriate remedy.
Summary
Noble Resources Ltd. entered into a contract with the Orissa state-owned corporation OMC Ltd. to supply specified quantities of iron‑ore fines of grades A, B and C at agreed prices. OMC later refused to supply the remaining C‑grade quantity, citing a sharp rise in international prices and cancelled the tender, prompting the buyer to file a writ petition under Article 226 of the Constitution. The Orissa High Court dismissed the petition, holding that the dispute was purely contractual, and the matter should be decided in a civil suit. On appeal, the Supreme Court held that OMC, as a state instrumentality, is a "State" under Article 12 and its actions are subject to the equality clause of Article 14, making a writ petition maintainable where arbitrariness is alleged. However, the Court declined to entertain detailed factual disputes or order specific performance, noting that damages under the Specific Relief Act are an adequate remedy. It concluded that while the High Court’s approach was not entirely correct, its refusal to exercise discretionary jurisdiction could not be faulted. Consequently, the appeal was dismissed, leaving the parties to pursue ordinary civil remedies.
Issues considered
- The applicability of writ jurisdiction under Article 226 to contractual disputes involving a State corporation.
- Whether a breach of contract by a State instrumentality can be challenged on the ground of violation of Article 14 (equality).
- Whether rise in international market price justifies rescission of a supply contract.
- Whether specific performance of a contract can be ordered through a writ of mandamus.
- Whether the presence of disputed questions of fact bars the court from exercising judicial review.
Legislation cited
- Constitution of Indias. 12, s. 14, s. 226
- Indian Contract Act, 1872
- Specific Relief Act, 1963
Subjects
Judgment
NOBLE RESOURCES LTD. A
v.
STATEOFORISSA AND ANR.
SEPTEMBER 13. 2006
[S.B. SINHA AND DALVEER BHANDARI, JJ.] B
~ Constitution of India, 1950; Articles 12, 14 and 226:
Contract-Supply of iron ore fines of grading A, B and C within a
stipulated time period-Rise in price of C grade variety in international c
market-Non-supply of agreed quantity by the supplier ..md issuance offresh
/ tender-Challenge to--Dismissed by High Court holding that i~ involved
)
enforcement of a contract qua contract and thus not maintainable-On
appeal, Held: Supplier-Corporation is a State in terms of Article 12 of the.
Constitution-A writ petition would be maintainable against the State if it D
acted in violation ofequality clause in terms of Article 14 of the Constitution-
it could also be subjected to judicial review by the Courts to prevent
arbitrariness or favouritism on its part-However, it would not be appropriate
to decide serious disputed question of fact in exercise--of writ jurisdiction-
Though rise in international price of the commodities
., in question would not
by itself be a relevant consideration for the supplier to rescind the contract E
/
but it was not the sole ground to rescind the contract-flon-supply of the
co;11modities in question may constitute a breach of contract but having
,; regard to conduct of the parties it cannot be said that such decision was so
arbitrary as to attract the wrath ·of Article 14 of the. Constitutio~ontract
Act, 1872-Specijic Relief Act, 1963.
F
... 'Breach ofContract' and 'Threshold ofContract'-Distinction between-
Discussed.
'Judicial Review'-Scope of in contractual matter-Discussed.
The question which arose for consideration in this appeal was as to
G
-~ whether a writ petition is maintainable in contractual matter or not.
Appellant-buyer and Respondent No.2-supplier, a Corporation entered
into a contract in terms whereof the Corporation was to supply certain quantity
------
53' H
54 SUPREME COURT REPORTS [20061 SUPP. 6 S.C.R.
A each of Grade A, Grade Band Grade C iron ore fines at the agreed price.
Later, a fax was sent by the buyer to the Supplier followed by another fax,
stating that it had signed further sale contracts with some of its long term
buyers and was looking forward for completing the balance shipments. But
the respondent did not supply the requisite quantity of 'C' Grade iron ore ..
B fines in terms of the contract nor did it extend the validity of the tender beyond
the due date. In the meantime, the Supplier-Corporation invited another tender,
wherein the buyer also participated. Aggrieved, the appellant filed a writ
petition which was dismissed by the High Court. Hence the present appeal
Appellant-buyer contended that when a State-owned monopoly acts
C unfairly and unjustly, their action being violative of the equality clause
contained in Article 14 of the Constitution of India, a writ petition would be
maintainable; that a contract of supply should not be terminated on the premise
that the price of the commodity has gone up in the international market; that
arbitrarint.'SS and unreasonableness on the part of the supplier was self-evident
as he has taken two different stands before the High Court; that the High
D Court committed a manifest error insofar as it failed to take into consideration
that a monopoly concern should be directed to honour its contractual
obligations; and that remedies available in a suit per se cannot be a ground to
refuse relief under Article 226 of the Constitution of India.
The Respondent-supplier submitted that the Appellant-buyer itself
E having shown its inability to lift iron ore fines in accordance with the schedule
&nd there being no complaint in respect of supplies made earlier, the writ
jurisdiction of the High Court under Article 226 of the Constitution of India
could not be invoked; that a writ petition involving disputed questions of fact
would not ordinarily lie and in that view of the mater the High Court rightly
F refused to exercise its extra ordmary jurisdiction; that when a decision is
taken for business purposes, the courts should not readily infer arbitrariness
on the part of the State; and that in any event, a writ petition for specific
perf.,rmance of contract would not lie when damages could be awarded for
breach of contract.
G Dismissing the appeal, the Court
HELD:t.1. Respondent No.2 is a 'State' within the meaning of Article
,.
12 of the Constitution of India. Its conduct in all fields including a contract
is expected to be fair and reasonable. It was not supposed to act arbitrarily,
capriciously or whimsically. 162-FI
H
NOBLE RESOURCES LTD. v. STA TE OFORISSA 55
1.2. It is trite that if an action on the part of the State is violative the A
equality clause contained in Article 14 of the Constitution of lnd!a, a writ
petition would be maintainable even in the contractual field. A distinction
must be made between a matter which is at the threshold of a contract and a
breach of contract; whereas in the former the court's scrutiny would be more
intrusive, in the latter the court may not ordinarily exercise its discretionary
jurisdiction of judicial review, unless it is found to be violative of Article 14 B
of the Constitution. While exercising contractual powers also, the Government
·bodies may be subjected to judicial review in order to prevent arbitrariness
or favouritism on its part. Indisputably, inherent limitations exist, but it would
not be correct to opine that under no circumstances a writ will lie only because
it involves a contractual matter. [62-G-H; 63-A) C
Radhakrishna Agarwal and Ors. v. State of Bihar and Ors., (1977) 3
sec 457, relied on.
1.3. It niay be true that where serious disputed questions of fact are
raised requiring appreciation of evidence, and, thus, for determination thereof, D
examination of witnesses would be necessary; it may not be convenient to decide
the dispute in a proceeding under Article 226 of the Constitution of India.
' - (64-C-D(
ABl International Ltd. & Anr. v. Export Credit Guarantee C01poration
ofIndia ltd & Ors., (200413 SCC 553; Mahabir Auio Stores & Ors. v. llidian E
Oil Corporation and Ors., (199013 SCC 75; State of Uttar Pradesh and Ors.
v. Vijay Bahadur Singh and Ors., [1982) 2 SCC 365; Mis. Dwarkadas Marfatia
& Sons v. Board of Trustees of the Port of Bombay, [1989) 3 SCC 293 and
Jamshed Hormusji Wadia v. Board of Trustees, Port ofMumbai and Anr., 120041
3 sec 214, referred to.
F
2.1. Contractual matters are not beyond the realm of judicial review.
.... Its application may, however, be limited. (66-A-BI
ABl International Ltd. & Anr. v. Export Credit Guarantee Corporation
of India Ltd. & Ors., 120041 3 SCC 553, relied on.
G
Bareilly Development Authority and Anr. v. Ajai Pal Singh and Ors.,
1198912 SCC 116; Indian Oil Corporation ltd. v. Amritsar Gas Service and
Ors., 1199111SCC533 and l.!.C. oflndiav; Escort ltd., [198611SCC264,
distinguished.
H
..
56 SUPREME COURT REPORTS (2006] SUPP. 6 S.C.R.
A 2.2. Although terms of the invitation to tender may not be open to judicial
scrutiny, but the courts can scrutinize the award of contract by the Government
or its agencies in exercise of their power of judicial review to prevent
arbitrariness or favouritism. However, the court may refuse to exercise its
jurisdiction, if it does not involve any public interest.
B Directorate of Education and Ors. v. Educomp Datama1ics ltd. and
Ors., 1200414 SCC 19, relied on.
2.3. Although the scope of judicial review or the development of law in
this field must be decided on its own facts, public interest may be one of the
factors to exercise power of judicial review. In a case where a public law
C element is involved, judicial review may be permissible. Another field where
judicial review is permissible would be when malafide or ulterior motive is
attributed.166-C-DI
Binny ltd. and Anr. v. V. Sadasivan and Ors., 1200516SCC657; G.B.
D Mahajan and Ors. v. Jalgaon Municipal Co11ncil and Ors .. (1991 ( 3 SCC 91;
State of UP and Anr., v. Johri Mal, (200414 SCC 714 and Asia Fo11ndation
and Construction ltd. v. Trafalgar House Construction India ltd. and Ors.,
119971 1 sec 738, relied on.
3. I. Though it is rightly submitted by the appellant that rise in
E international price would not by itself be a relevant consideration to rescind
the contract, but then the same was not the sole ground for Respondent No.2
to refuse to supply iron ore fines to them. (70-EI
3.2. Ordinarily, a specific performance of contract would not be enforced
by issuing a writ of or in the nature of mandcmus, particularly when keeping
F in view the provisions of the Specific Relief Act, 1963 damages may be an
-
adequate remedy for breach of contract. (70-F-GI
3.3. The qu<!stions as to whether the respondent-Corporation had the
available stock of iron ore fines or the only ground to refuse supply thereof
was the rise in international prices, are matters which could not have been
G fully and effectively adjudicated in the writ proceedings. It was difficult for
the High Court to go into the other questions which have been raised before ,.
this Court by the Appellant. However, it is noticed that although a decision
had allegedly been taken by the Corporation not to supply iron ore fines prior
to the expiry of the contractual period, but the same had not been
H communicated. Its effect has to be determined keeping in view the fact as to
NOBLE RESOURCES LTD. v. STATEOFORISSA[S.B. SINHA.J.] 57
whether the Appellant suffered any loss thereby. The reasons for non-supply A
may constitute a breach of contract but having regard to the conduct of the
parties, it cannot be said that the same was so arbitrary so as to attract the
wrath of Article 14 of the Constitution of India. 170-G-H; 71-A-B-q
3.4. Although the approach of the High Court was not entirely correct,
its ultimate decision to refuse to exercise its discretionary jurisdiction cannot B
be faulted with. However, it is open to the appellant to take recourse to the
other remedy which is available in law.171-D-EI
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4108 of2006.
From the Judgment and Order dated 14.9.2004 of the High Court of C
Orissa at Cuttack in W.P. (C) No. 1463 of2004.
Ashok Desai, Amit Sibal, Udaya Kumar Sagar, A. Venayagan and Arif
Iqbal Chaudrfy (for Mis. Lawyers's Knit & Co.) for the Appellant.
Rajiv Dhawan, Suman Kukrety and Raj Kumar Mehta for the D
Respondents.
The Judgment of the Court was delivered by
S.B. SINHA, J. Leave granted.
E
Whether a writ petition is maintainable in contractual matter is the core
question involved in this appeal which arises out of a judgment and order
dated 14.09.2004 passed by a Division Bench of the Orissa High Court in Civil
Writ Petition No.1463 of 2004 whereby and whereunder the writ petition filed
by the Appellant herein was dismissed.
F
Admittedly, the parties entered into a contract in terms whereof the
Respondent No.2 herein was to supply 1,20,000 MT + I -10% each of Grade
A, Grade B and Grade C iron ore fines by September 2003. On or about
28.02.2003, the parties also agreed that the supply of full tender quantity
would be made in the sequence of C, B and A Grades iron ore fines at the G
prices offered by the Appellant. Indisputably, the Appellant disclosed the
names of the parties with which it had entered into agreements to supply iron
ore fines procured from the said Respondent. There is no dispute that
supply of C-Grade iron ore fines had been made by the Respondent No.2.
Indisputably, again supply of 64.236 MT of Grade-B iron ore flnes had also
been made. It is furthermore not in dispute that the Respondent No.2 offered H
58 SUPREME COURT REPORTS 120061 SUPP. 6 S.C.R.
A 25.000 MT of Grade-A iron ore fines to the Appellant herein which was not
accepted.
It appears that in regard to the supplies made from March, 2003 to
September. 2003 there had been no complaint on the part of the Appellant
about any breach of contract on the part of the Respondent No.2 On
B 05.09.2003, a fax was sent by the Appellant requesting the laycan in the
following terms :
''After the successful completion of mv Susan S, we now look
forward to receiving the laycan for the next shipment of Grade-B Iron
Ore Fines in the month of September.
c
We look forward to receiving your confirmation at the earliest
please, to enable us to nominate a suitable vessel."
Yet again by a fax dated 09.09.2003, its request was reiterated stating
that it had signed the sale contracts with some of its long term buyers and
D was looking forward for completing the balance shipments and honouring its
commitment to both Respondent No. 2 and its buyers. A request was made
by the Appellant seeking for personal intervention of the matter by the
Chairman and Managing Director of Respondent No.2.
E The Board Sub-Committee On Sales Policy of Respondent No.2, however,
by a resolution dated 22.09.2003 resolved :
"Out of the total quantity of A, B & C grade Iron Ore fines, two
C-grade and one B-grade material has been shipped by Mis Noble
Resources Ltd.. , Hong Kong and another B-grade material is due to be
•
loaded during the current month. It was informed that there is a stock
F of 60,000 MT A-grade material. I lakh MT B-grade material and 2.40
lakh MT C-grade material at Daitari. After receipt of information from
L.C. and confirmed by Company Secretary, it was decided that 60,000
MT, A-grade material is to be shipped to Mis Noble resources, Hong
Kong even after 30.08.03 and the party should be pursued not to
G insist for the balance quantity of A-grade as it is physically not
available with OMCV and hence cannot. supply the :nd shipment of
A-grade."
"Further as NINL has agreed that they will be lifting Iron Ore
Fines from October, 03 onwards, the requirement is to be reviewed and
H for the time being export sale of C-grade fines may be postponed.
NOBLERESOURCESLTD. v. S1:ATEOFORISSA[S.B. SINHA,J.] 59
Therefore, the tender auction taken by OMC Ltd. should be cancelled A
invited in .the News Paper and Website of OMC Ltd. for information
of all concerned. On the basis of the above decision the tender for
export sale of I.80,000 MT of C-grade Iron Ore fines was cancelled.''
II' •.
The said resolution was evidently taken in view of the increase of the
rates of iron ore fines in the international market, which has gone up B
manifold. Yet again the Board Committee On Sales Policy of the Respondent
No.2 decided as follows :
"(i) The validity of the tender will not be extended beyond 30.09.2003
and therefore no further quantity shall be supplie:I to Mis Noble
Resources Ltd. C
(ii) Fresh tender may be invited for B-Grade Iron Ore fines for one
shipment and one shipment of C-Grade. However, while doing
so it must be ensured that the quantity is available for export
after meeting the requirement ofNINL."
D
However, despite a reminder, no action had been taken and in the
meantime another invitation of tender was published. It is not in dispute that
the Appellant _also participated in the subsequent tender.
A writ petition was filed by the Appellant in the Orissa High Court. In
its first counter affidavit the Respondent No.2, inter alia, stated : E
"That the Board Sub-Committee on Sales Policy held on 8.5.2993
of OMC Ltd., decided to review the export of Iron Ore fines on the
basis of tender finalized in January-February, 2003. Basing on the
above direction the Board of Directors in their 339th meeting held on
26.08.03 took the foilowing decisions : F
"Regarding export of A-grade Iron ore fines, it was decided to
examine if there is a penal provision in the agreement/tender for
non-fulfillment of obligation on the part of OMC Ltd. It should
also examine whether any legal complicacy arises if the A variety
ore will be kept reserved for NINL. For the C-grade, Board G
approved for inviting fresh Tender"
Accordingly. tender was floated for a quantity of 1.80.000/- MT
+/- I0% of C'-grn<le Iron Ore fines in all editions of ECONOMIC TIMES
on 4.9.2003. Th~ 13oard Sub-Committee on sale held on 22.09.2003
observed as ro Ilo" s : H
60 SUPREME COURT REPORTS 12006] SUPP. 6 S.C.R.
A (i) ''Out of the total quantity of A B & C grade Iron Ore fines. two
C-grade and one B-grade material has been shipped by Mis
Noble Resources Ltd., Hong Kong and another B-grade materials
B
is due to be loaded during the current month. It was informed
that there is a stock of 60.000 MT A-grade materials, I lakh MT
B-grade material and 2.40 lakh MT C-grade material at Daitori.
.-
After receipt of information from L.C. and con finned by Company
Secretary. it was decided that 60.000 MT. A-grade material is to
be shipped to Mis Noble Resources. Hong Kong even after
30.08.2003 and the party should be perused not to insist for the
balance quantity of A-grade as it is physically not available with
c OMC and hence cannot supply the 2nd shipment of A-grade"
(ii) "Further as NINL has agreed that they will be lifting Iron Ore
fines from October 03 onwards, the requirement is to be reviewed
and for the time being export sale of C-grade fines may be
postponed. Therefore, the tender auction taken by OMC Ltd.,
D should be cancelled invited in the News Paper and Website of
OMC Ltd. for information of all concerned. On the basis of the
above decision the tender for export sale of 1,80,000 MT of C-
grade Iron Ore fines was cancelled.
11. That this matter was further referred to Board Committee on
E sales Policy held on 24.10.2003. The Committee decided as follows:
(i) The validity of the tender will not be extended beyond 30.09.2003
and therefore no further quantity shall be supplied to Mis Noble
Resources Ltd.
'
(ii) Fresh tender may be invited for B-grade Iron Ore fines for one
F shipment and one shipment ofC-grade. However, while doing so
it must be ensured that the quantity is available for export after
meeting the requirement ofNINL."
However, somehow a different stand was taken by the Respondent No.2
in its additional counter affidavit as it assigned the following reasons for its
G ability to supply iron ore fines, stating :
"(A) The primary crusher at Daitari which was an old plant got break
down during the contractual period and the spares were not
available in India for immediate repair. As a result production of
"A" & "B" grade iron ore got affected.
H
NOBLE RESOURCES LTD. v. ST ATEOF ORI SSA [S.B. SINHA. J.] 61
(B) The working permission issued by the Government of India, A
Ministry of Environment and Forest expired on 13.03.2003 and
the same was issued afresh by Government of India only on
9.4.2003, during which period there could not be any production.
(C) Production of"A" grade Ore was to be made by Selective Mining
which could not be possible due to restrictions imposed by the B
Director General Mines, Safety, Government of India.
(D) Railway Rakes were not available for transportation of Iron Ore
Fines from Daitari to Paradip, despite persuasion of OMC with
the Railway Authorities.
Further, during the said contractual period OMC has not sold iron C
ore of any grade to any party other than to Mis. Neelachal !spat
Nigam Ltd., which is wholly Government owned undertaking with
f which Government ofOrissa and OMC has a long term understanding
for supply of iron Ore to sustain the steel plant of NINL."·
By reason of the impugned judgment, a Division Bench of the Orissa
D
High Court dismissed the writ petition, inter alia, opining that it involved ..
enforcement of a contract qua contract and thus not maintainable.
Mr. Ashok Desai, the learned Senior Counsel appearing on behalf of the
Appellant, would submit : E
(i) When a State-owned monopoly acts unfairly and unjustly, the action
being violative of the equality clause contained in Article 14 of the Constitution
of India; a writ petition would be maintainable;
(ii) A contract of supply should not be terminated on the premise that F
the price of the commodity has gone up in the international market which
cannot be said to be either reasonable or bona fide;
(iii) The Respondent No.2 having taken two different stands before the
High Court, arbitrariness and unreasonable on its part was self-evident;
G
(iv) The High Court committed a manifest error insofar as it failed to
take into consideration that a monopoly concern should be directed to honour
its contractual obligations in view of the decision of this Court in ABL
International Ltd. and Anr. v. Export Credit Guarantee Corporation of India
Ltd and Ors., [2004] 3 SCC 553;
H
62 SUPREME COURT REPORTS (2006] SUPP. 6 S.C.R.
A (v) Remedies available in a suit per se cannot be a ground to refuse
relief under Article 226 of the Constitution of India.
Dr. Rajeev Dhawan, the learned Senior Counsel appearing on behalf of
the Respondent, on the other hand. would submit that :
B (i) The Appellant itself having shown its inability to lift iron ore fines
in accordance with the schedule and there being no complaint in respect of
supplies made from March to September, the writ jurisdiction of the High
Court under Article 226 of the Constitution of India could not be invoked;
(ii) The writ petition having been filed only having regard to the
C escalating prices, the High Court rightly refused to exercise its discretionary
jurisdiction;
(iii) The main plea raised by the Appellant being applicability of the
doctrine of promissory estoppel which having no application in contractual
D matters, the writ petition was not maintainable;
(iv) A writ petition involving disputed questions of fact would not
ordinarily lie and in that view of the mater the High Court rightly refused to
exercise its extra ordinary jurisdiction;
E (v) When a decision is taken for b_usiness purposes, the courts should
not readily infer arbitrariness on the part c,f the State; and
(vi) In any event, a writ petition for specific performance of contract
would not lie when damages can be awarded for breach of contract.
The Respondent No.2 is a 'State' within the meaning of Article 12 of
F the Constitution of India. Its conduct in all fields including a contract is
expected to be fair and reasonable. It was not supposed to act arbitrarily,
capriciously or whimsically.
It is trite that if an action on the part of the. State is violative of the
G equality clause contained in Article 14 of the Constitution of India, a writ,
petition would be maintainable even in the contractual field. A distinction
indisputably must be made between a matter which is at the threshold of a
contract and a breach of contract; whereas in the former the court's scrutiny
would be more intrusive, in the latter the court may not ordinarily exercise its
discretionary jurisdiction of judicial review, unless it is found to be violative
H
NOBLE RESOURCES LTD. v. STAT~OFORISSA [S.B. SINHA,J.) 63
· of Article 14 of the Constitution. While exercising contractual powers also, A
the government bodies may be subjected to judicial review in order to prevent
arbitrariness or favouritism on its part. Indisputably, inherent limitations exist,
but it would not be correct to opine that under no circumstances a writ will
lie only because it involves a contractual matter.
' ...
This dicta of law was laid down by this Court as far back in 1977, B
wherein this Court in Radhakrishna Agarwal and Ors. v. State of Bihar and
Ors., [1977] 3 SCC 457 accepted the division of types of cases made by the
Patna High Court in which breaches of alleged obligation by the State or its
agents could be set up. It read as under :
"(i) Where a petitioner makes a grievance of breach of promise on
c
· the part of the State in cases where on assurance or promise made by
the State he ·has acted to his prejudice and predicament, but the
agreement is short of a contract within the meaning of Article 299 of
the Constitution;
D
(ii) Where the contract entered into between the person aggrieved
and the State is in exercise of a statutory power under certain Act or
Rules framed thereunder and the petitioner alleges a breach on the
part of the State; and
(iii) Where the contract entered into between the State and the E
person aggrieved is non-statutory and purely contractual and the
rights and liabilities of the parties are governed ~y the terms of the
contract, and the petitioner complains about breach of such contract
by the State." ·
It was further observed : F
"In the cases before us, allegations on which a violation of Article
14 could be based are neither properly made nor established. Before
any adjudication on the question whether Article 14 of the Constitution
could possibly be said to have been· violated, as between persons G
governed by siniilar contracts, they must be properly put in issue and
established. Even if the appellants could be said to have raised any
aspect of Article 14 of the Constitution and this Article could at all
be held to operate within the contractual field whenever the· State
enters into such contracts, which we gravely doubt, such questions
of fact do not appear to have been argued before the High Court. H
64 SUPREME COURT REPORTS [2006) SUPP. 6 S.C.R.
A And, in any event, they are of such a nature that they cannot be
satisfactorily decided without a detailed adduction of evidence, which
is only possible in ordinary civil suits, to establish that the State,
acting in its executive capacity through its officers. has discriminated
between parties identically situated. On the allegations and affidavit
B
evidence before us we cannot reach such a conclusion. Moreover, as •
we have already indicated earlier, the correct view is that it is the
contract and not the executive power, regulated by the Constitution.
which governs the relations of the parties on facts apparent in the
cases before us."
c It may, however, be true that where serious disputed questions of fact
are raised requiring appreciation of evidence, and, thus, for determination
thereof, examination of witnesses would be necessary; it may not be convenient
· to decide the dispute in a proceeding under Article 226 of the Constitution
of India.
D On a conspectus of several decisions, a Division Bench of this Court
in ABE, International ltd. (supra) opined that such a writ petition would be
maintainable even if it involves some disputed questions of fact. It was
stated that no de.cision lays down an absolute rule that in all cases involving
disputes questions of facts, the party should be relegated to a civil court.
E
fo Mahabir Auto Stores & Ors. v. Indian Oil Corporation and Ors.,
[ 1990] 3 SCC 752, this Court observed :
" .. .It appears to us that rule of reason and rule against arbitrariness
and discrimination, rules of fair play and natural justice are part of the
F rule of law applicable in situation or action by State instrumentality
in dealing with citizens in a situation like the present one. Even
though the rights of the citizens are in the nature of contractual rights,
the manner, the method and motive of a decision of entering or not
entering into a contract, are subject to judicial review on the
touchstone of relevance and reasonableness, fair play. natural justice,
G
equality and non-discrimination in the type of the transactions and
nature of the dealing as in the present case."
In State of VIiar Pradesh and Ors. v. Vijay Bahadur Singh and Ors.,
[ 1982] 2 SCC 365, a Division Bench of this Court held that the Government
H cannot be denied to exercise its discretionary power provided the same is not
arbitrary.
NOBLE RESOURCES LTD. v. STATEOFOR!SSA [S.B. S!NHA,J.] 65
Interplay between writ jurisdiction and contractual disputes has given A
rise to a plethora of decisions by this Court. See for example Mis Dwarkadas
Ma1.fatia & Sons v. Board of Trustees of the Port of Bombay, [1989] 3 SCC
293 and Mahabir Allio Stores (supra).
In Jamshed Hormusji Wadia .v. Board of Trustees, Port of Mumbai and
Anr., [2004] 3 sec 214, this Court stated: B
'The position of law is settled that the State and its authorities
including instrumentalities of States have to be just, fair and reasonable
in all their activities including those in the field of contracts. Even
while playing the role of a landlord or a tenant, the State and its C
authorities remain so and cannot be heard or seen causing displeasure
or discomfort to Article 14 of the Constitution of India.
It is common knowledge that several rent control legislations exist
spread around the country, the emergence whereof was witnessed by
· the post-World War scarcity of accommodation. Often these legislations D
exempt from their applicability the properties owned by the Government,
semi-government or public bodies, Government-owned corporations,
trusts and other instrumentalities of State .. .""
Non statutory contracts have, however, been treated differently. [See
Bareilly Development Authority and Anr. v. Ajai Pal Singh and Ors., [1989) E
2 sec I I6J.
A distinction is also made between performance of a statutory duty
and/or dealing of a public matter by a State and its commercial activities. [See
Indian Oil Corporation Ltd. v. Amritsar Gas Service and Ors., [1991) I SCC
533 and L.l.C. of India v. Escort Ltd, [1986] I sec 264]. F
In ABL International Ltd (supra), this Court opined that on a given set
of facts, if a State acts in an arbitrary manner even in a matter of contract,
a writ petition would be maintainable. It was opined :
"It is clear from the above observations of this Court, once the G
State or an instrumentality of the State is a party of the contract, it
has an obligation in law to act fairly, justly and reasonably which is
the requirement of Article 14 of the Constitution of India. Therefore,
if by the impugned repudiation of the claim of the appellants the first
respondent as an instrumentality of the State has acted in
contravention of the abovesaid requirement of Article 14, then we H
66 SUPREME COURT REPORTS (2006] SUPP. 6 S.C.R.
A have no hesitation in holding that a writ court can issue suitable .
directions to set right the arbitrary actions of the first respondent ... "
Contractual matters are. thus, not beyond the realm of judicial review.
Its application may, however. be limited.
B Although terms of the invitation to tender may not be open to judicial
scrutiny, but the courts can scrutinize the award of contract by the Government
or its agencies in exercise of their power of judicial review to prevent
arbitrariness or favouritism. [See Directorate of Education and Ors. v.
Educomp Datamatics Ltd. and Ors., [2004] 4 SCC 19. However, the court
may refuse to exercise its jurisdiction, if it does not involve any public
c interest.
Although the scope of judicial review or the development of law in this
field has been noticed herein before particularly in the light of the decision of
this Court in ABL International ltd. (supra), each case, however, must be
D decided on its own facts. Public interest as noticed hereinbefore, may be one
of the factors to exercise power of judicial review. In a case where a public
law element is involved, judicial review may be permissibk. [See Binny Ltd.
and Anr v. V. Sadasivan and Ors., [2005] 6 SCC 657 and G.B. Mahajan and
Ors. v. Jalgaon Municipal Council and Ors., [1991] 3 SCC 91].
E In State of UP and Ar.r. v. Johri Mal, [2004] 4 SCC 714, it was held:
"It is well settled that while exercising the power of judicial review
the court is more concerned with the decision-making process than
the merit of the decision itself. In doing so, it is often argued by the
defender of an impugned decision that the court is not competent to
F exercise its power when there are serious disputed questions of facts;
when the decision of the Tribunal or the decision of the fact-finding
body or the arbitrator is given finality .by t.he statute which governs
a given situatio.n or which, by nature of the activity the decision-
maker's opinion on facts is final. But while examining and scrutinising
the decision•making process it becomes ·inevitable to also appreciate
G the facts of a given case as otherwise the decision cannot be tested
under the grounds of illegality, irrationality or procedural impropriety.
How far the court of judicial review can reappreciate the findings of
facts depends on the ground of judicial review. For example, if a
decision is challenged as irrational, it would be well-nigh impossible
H to record a finding whether a decisior. is rational or irrational without
NOBLERESOURCESLTD. v. STATEOFORISSA[S.B. SINHA,.I.] 67
first evaluating the facts of the case and coming to a plausible A·
conclusion and then testing the decision of the authority on the
touchstone of the tests laid down by the court with special reference
to a given case. This position is well settled in the Indian administrative
law. Therefore, to a limited extent of scrutinising the decision-making
process, it is always open to the court to review the evaluation of B
facts by the decision-maker."
Another field where judicial review is permissible would be when ma/a
fide or ulterior motives is attributed. In Asia Foundation and Construction
Ltd. v. Trafalgar House Construction India Ltd. and Ors., [1997] I SCC 738,
this Court held :
c
" ... We are of the considered opinion that it was not within the
permissible limits of interference for a court of law, particularly when
there has been no allegation of malice or ulterior motive and particularly
when the court has nof found any ma/a fides or favouritism in the
grant of contract in favour of the appellant...." D
It was further held :
"Therefore, though the principle of judicial revi~w cannot be denied
so far as exercise of contractual powers of government bodies are
concerned, but it is intended to prevent arbitrariness or favouritism E
and it is exercised in the larger public interest or if it is brought to the
notice of the court that in the matter of award of a contract power has
been exercised for any collateral purpose. But on examining the facts
and circumstances of ihe present case· and on going through the
records we are of the considered opinion that none of the criteria has
been satisfied justifying Court's interference in the grant of contract F
in favour of the appellant...."
We, however, having regard to ABL International ltd. (supra), do not
accept Dr. Dhawan 's contention that only because there exists a disputed
question of fact or an alternative remedy is available, the same by itself would
be sufficient for the High Court to decline its jurisdiction. G
The case at hand may be considered having regard to the aforementioned
legal princ;ples in mind. The parties indisputably were bound by the terms
of the contract.
For determining the dispute; conduct of the Appellant was also relevant. H
68 SUPREME COURT REPORTS [2006] SUPP. 6 S.C.R.
A Indisputably, the Respondent No.2 in its letter dated 28.02.2003 offered
consignment of 25,000 MT of iron ore fines. It did not lift the same on the
ground that a small load would be unacceptable. On 13.05.2003, it lifted the
quantity of 46,280 MT of iron ore fines. although the said quantity would also
be small load. Although the consignment was to be on monthly basis. it had
been rescheduled.
B
In the writ petition it was averred :
"Referring to the present stock of 25,000 MT of A Grade iron ore
referred to in the letter of acceptance of Opposite Party No.2, the
Petitioner stated it was not viable to ship a parcel of 25,000/- MT of
c iron ore on its own and that it would need a minimum parcel of 60,000
MT. Given the tight vessel situation on the east coast and especially
in the Halia/Pradip area, the Petitioner stated that it would be advisable
for both the Opposite Party No.2 and the Petitioner to plan the first
ship in early April"
D The monthly schedule of shipment evidently was altered. We have
also noticed herein before that there had been no complaint on the part of the
Appe!;ant in regard to the supply of iron ore fines till August, 2003, by which
time 1,08, 181 MT of iron ore fines was supplied in two installments: In the
month of September 60,000 MT ofGrade-8 iron ore and 1,20,000 MT ofGrade-
E A iron was to be supplied. According to the Respondent No. 2, however,
such quantity was not possible in adherence of the schedule. We have
noticed hereinbefore that in its additional affidavit before the High Court, the
Respondent No.2 has not assigned any reason which can be said to be
contrary to its earlier stand. Some more reasons kave been assigned in regard
F to its inability to supply iron ore fines. It its Counter Affidavit, the Respondent
No.2 stated:
"That to sum up as per tender norms of the tender floated during
February, 2003, the price and quantity was valid till end of September
2003 as there was constraint in convergence of ore by rake from
Daitari to Pradip, the buyer was intimated by OMC Ltd., to conclude
G
the contract on shipment to shipment basis. OMC would have
concluded the contract for the entire tender quantity in one lot with
Mis Noble Resources Ltd. Hong Kong had there been no constraint
for convergence of cargo to Paradipif the balance quantity against the
tender norms would have been supplied to the petitioner company at
H the tendered prices of February, 2003 the Corporation would have
NOBLE RESOURCES LTD. v. STATEOFORISSA[S.B. SINHA.J.) 69
incurred huge loss as the price of iron ore in the International Market A
has increased manifold."
We may herein notice a statement on tenders floated and accepted in
respect of the iron ore fines after 30.09.2003, which is as under :
.
"DATE OF QUALITY OF HIGHEST PRICE SEE PRICE
B
TENDER IRON ORE PRICE QUOTED IN
OPENING FINES BY TENDER
QUANTITY NOBLE AT P.50
USD/D
MT
Price in
Quoted
by USD/DMT c
12.11.03 B-Grade-60.000 M/s Burwill 47.10 31.75 14.96
MT+- 10% Hong Kong
C, Grade- M/s Bunvill 45.10 29.25 13.86
60,000 Hong Kong
MT+-10°/o
D
03.02.04 C-Grade- Sudamin 63.30 59.80 13.86
1.20.000 Metal.
MT+- 10% London
20.03.04 C-Grade- VISA 75.06 62.68 13.86
1.20.000 Com trade,
MT+- 10% AG. E
Switzerland
22.06.04 C-Grade- Noble 25.70 25.70 13.86
1,20,,000 Resources,
MT+- 10% Hong Kong
07.09.04 C-Grade-60,000 .IMR 46.35 44.68 13.86
MT+- 10% Resources, F
Hong Kong
22.11.04 C-Grade- Noble 40.18 . 40.18 13.86
L20.000 Resources.
MT +- 10~~ Hong Kong
24.01.05 C-Grade-60.000 Noble 53.08 53.08 13.86 G
MT +- 10% Resources, .
Hong Kong
15.03.05 C-Grade-60.000 !MR 58.10 54.00 13.86
MT+- 10% Metallurgical
Resources AG
Switzerland H
70 SUPREME COt.;RT REPORTS [2006] SUPP. 6 S.C.R.
A The Appellant evidently participated in subsequent tenders. It became
successful in some of them. It did not raise any protest. It took part in the
said process without any demur.
We have noticed hereinbefore that the price of iron ore fines in the
international market varied from time to time. After September. 2003, a tender
B was issued. The. Appellant took part in the said tender. Its tender was
accepted in relation to Grade-C iron ore fines. Its offers on 22.06.2004, 22.11.2004
and 24.01.2005 had also been accepted.
The table quoted hereinbefore also points out that the Appellant had
C also understood the implication of phenomenal rise in price in the international
market.
We may at this juncture furthermore notice that the contractual terms
came to an end in September, 2003. It participated in the bids of prices much
higher than the contractual prices during the period 12.11.2003 and 03.02.2004.
D The stand of the Respondents that only having regard to the f1.~t that there
had been increase in the prices, the Appellant filed a writ petition only in
February, 2004, cannot be said to be wholly misconceived.
The submission of Mr. Desai that rise in international price would not
by itself be a relevant consideration to rescind the contract may be correct,
E but then the same was not the sole ground for the Respondent No.2 to refuse
to supply iron ore fines to the Appellants.
Moreover, certain serious disputed questions of fact have arisen for
......
determination. Such disputed questions of facts ordinarily could not have
been entertained by the High Court in exercise of its power of judicial review.
F
Ordinarily, a specific performance of contract would not be enforced by
issuing a writ of or in the nature of mundamus, particularly when keeping
in view the provisions of the Specific Relief Act, 1963 damages may be an
adequate remedy for breach of contract.
G The questions as to whether OMC had the available stock of iron ore
fines or the only ground to refuse supply thereof was the rise in international
prices, are matters which could not have been fully and effectively adjudicated
in the writ proceedings. It was difficult for the High Court to go into the other
questions which have been raised before u5 by the Appellant. namely. the
H effect of the purported decision of OMC to offer to the Appellant 60.000 MT
NOBLE RESOURCES LTD. v. STATEOFORISSA [S.R SINHA, J.) 71
of' A' Grade iron ore tines .provided the Appellant gave up all other contractual A
rights which stating the bad faith on the part of OMC. We may, however,
notice that although a decision had allegedly been taken by OMC not to
supply iron ore tines prior to the expiry of the contractual period, but the
same had not been communicated. Its effect has to be determined keeping in
view the fact as to whether the Appellant suffered any loss thereby. The B
reasons for non-supply, we may reiterate, may constitute a breach of contract
but having regard to the conduct of the parties, it cannot be said that the
same was so arbitrary so as to attract the wrath of Article 14 of the Constitution
of India. Before us also what has been emphasized is the purported breaches
of contract by the Respondent. A contention has .also been raised by Mr.
Desai that keeping in view the facts and circumstances of this case, this Court C
should mould the relief. We dci nol intend to do so and leave the parties
to raise all contentions before an appropriate forum.
For the reasons aforementioned, we are of the opinion that although the
approach of the High Court was not entirely correct, its ultimate decision to D
refuse to exercise its discretionary jurisdiction cannot be faulted with.
The appeal is, therefore, dismissed. We, however, leave it open to the
Appellant to take recourse to the other remedy which is available in law. In
the facts and circumstances of the case, there shall be no order as to costs.
E
S.K.S. Appeal dismissed.
)
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.