NELATUR SAMPOORNAMMA W/O SRINIVASULUREDDYversusSPECIAL DEPUTY COLLECTOR, L.A., TELUGU GANGA PROJECT, PODALAKUR AT NELLORE, ANDHRA PRADESH
- Citation
- 2017 INSC 642
- Decided
- 19 July 2017
- Disposal
- Case Partly allowed
- Bench
- KURIAN JOSEPH
Holding
Compensation for fruit‑bearing trees must be calculated using the valuation and multiplier prescribed in the 1989 horticulture notification, resulting in a per‑tree award of Rs 2,000 in the facts of this case.
Summary
The appellant owned 0.15 acre of land with 45 three‑year‑old pomegranate trees that were acquired under a 1990 notification of the Land Acquisition Act, 1894. The award fixed the market value of each tree at Rs 65 and applied a multiplier of 2, later increased to 9 by the High Court, relying on a 1992 government order. The Supreme Court held that the valuation must be based on the 1989 horticulture department letter, which fixed the value at Rs 75 per tree, and that the correct multiplier was 9 as per the 1989 notification. However, the Court declined to follow a later 2016 decision awarding Rs 3,000 per tree, noting the temporal difference, and instead fixed compensation at Rs 2,000 per tree with statutory benefits. The appeal was partly allowed, modifying the High Court’s award.
Issues considered
- Whether the valuation of pomegranate trees for compensation should be based on the 1989 horticulture department notification or the 1992 government order.
- Which multiplier is applicable to fruit‑bearing trees under the relevant notification.
- Whether compensation awarded in a later case (2016) can be applied to the present 1992 acquisition.
Legislation cited
- Land Acquisition Act, 1894s. 18, s. 4(1), s. 54, s. 6
Subjects
Judgment
[2017] 6 S.C.R. 517
NELATUR SAMPOORNAMMA W/O SRINIVASULUREDDY A
v.
SPECIAL DEPUTY COLLECTOR, L.A., TELUGU GANGA
PROJECT, PODALAKUR AT NELLORE, ANDHRA PRADESH
&ANR.
B
(Civil Appeal No. 9287 of 2017)
JULY 19,2017
[KURIAN JOSEPH AND R. BANUMATHI, JJ.]
Land Acquisition Act, 1894 - s. 54 - Compensation for fruit C
bearing trees - Acquisition of appellant's land with pomegranate
tree orchard in 1990 - Reference Court applied the multiplier of '2'
and enhanced the market value of each pomegranate to Rs 651- -
High Court upheld the market rate, however enhanced the
multiplier to '9' - On appeal, held: As per Letter No. F(3) 2164189
dated 26.11.1989 of the Department, the revised value of D
pomegranate trees was fixed at Rs. 751- - On the date of acquisition
of the said land, the very same Notification was in effect and that
being so, both the Reference Court and High Court erred in fixing
the rate of the pomegranate trees at Rs. 651- relying on the
subsequent G.O.No.601 dated 19.06.1992 which was not in E
existence on the date of publication of the Notification - As per the
Notification dated 26.11.1989, the fruit bearing period being not
less than twelve years and the trees being three years old, the High
Court rightly applied the multiplier of '9' - Appellant sought
compensation of Rs.3,0001- per pomegranate tree relying on
judgment of this Court which cannot be made applicable to the F
instant case since the award of compensation in the said case was
of 08.03.1999, as opposed to award in the instant case which is of
14. 09.1992 - It is obvious that seven years back a fruit bearing
tree would have fetched lesser income than it would fetch now - On
facts, appellant awarded compensation of Rs.2,0001- per G
pomegranate tree along with all the statutory benefits.
Partly allowing the appeal, the Court
HELD: 1.1 As per Letter No. F(3) 2164/89 dated
26.11.1989 of the Department of Horticulture, the revised value
H
517
518 SUPREME COURT REPORTS [2017] 6 S.C.R.
A of fruit bearing trees viz. pomegranate was fixed at Rs.75/-. On
the date of Section 4(1) Notification i.e. 30.03.1990, it is evident
that the very same Notification was in effect and that being so,
the Reference Court as well as the High Court committed an
error in fixing the rate of the pomegranate trees at Rs.65/-
B relying on the subsequent G.O.No.601 dated 19.06.1992 which
was not in existence on record on the date of publication of Section
4(1) Notification. Insofar as the multiplier applied is concerned,
as per the Notification of the year 1989, the fruit bearing period
being not less than twelve years and the trees being three years
old, the High Court rightly applied the multiplier of "9". [Para
C 13] [522-B-D]
1.2 Planting, raising and making commercial use of fruit
bearing trees is a painstaking affair and cost of the same is
consistently on rise as the years are passing by which is to be
kept in view. Award of compensation in relation to fruit bearing
0 trees. depends on facts and circumstances of each case. The
appellant has sought compensation of Rs.3000/- per
pomegranate tree relying on judgment of this Court dated
29.11.2016 in Civil Appeal Nos.11404-11405 of 2016. However,
the compensation of Rs. 3,000/- per pomegranate tree, as has
been awarded in the said case, cannot be made applicable to the
E instant case, considering the fact that award of compensation in
the said case dated 08.03.1999, as opposed to award in the instant
case which is dated 14.09.1992. A period of about seven years is
a considerable period to be taken note of while computing cost
of planting and raising fruit bearing trees. It is obvious that seven
F years back a fruit bearing tree would have fetched lesser income
than it would fetch now. Accordingly,, in the facts and circumstances
of the instant case, appellants are awarded compensation of
Rs.2,000/- per pomegranate tree alongwith the statutory
benefits like solatium and interest on the same. [Paras 14, 15]
[522-E-F; 523-B-D]
G Kera/a State Electricity Board v. Livisha and Ors. (2007)
6 SCC 792:(2007) 7 SCR 356 - referred to.
Case Law Reference
[2007] 7 SCR 356 referred to Para 14
H
NELATUR SAMPOORNAMMA v. SPECIAL D.C., TELUGU 519
GANGA PROJECT, AP. & ANR.
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 9287 A
of 2017.
From the impugned final Judgment and Order dated 12-03-2014
passed by the High Court of Andhra Pradesh at Hyderabad in LAAS
No.989/2007
WITH B
Special Leave Petti ion (Civil) No.30562of2016.
Thomas P. Joseph, Sr. Adv. V. Sridhar Reddy, Abhijit Sengupta,
Advs.for the Appellant.
Guntur Prabhakar, Ms.Prerna Singh, Advs. for the Respondents. C
The Judgment of the Court was delivered by
R. BANUMATHI, J. 1. Leave granted.
2. This appeal by way of special leave under Section 54 of the
Land Acquisition Act, 1894 has been preferred by the claimant assailing D
the judgment and order dated 12.03.2014 in LA.AS. No.989/2007 passed
by the High Court of Judicature of Andhra Pradesh at Hyderabad by
which the High Court concurred with the order of the Reference Court
estimating the income from each pomegranate tree at Rs.65/- and in-
creasing the multiplier of"9" instead of"2" alongwith statutory benefits,
thereby awarding the total compensation ofRs.26,325/-(45x65x9) for E
45 pomegranate trees.
3. The Executive Engineer, Telugu Ganga Project, Division No. I,
Nell ore sent a requisition for acquisition oflands ofDachur Village for
foreshore submersion ofKandelara ReservoirunderTelugu Ganga Project
to an extent of Acs.56.53. Out of this, upto Acs.30.85 is patta land and F
the remaining is Government land. Out of Acs.30.85, award was al-
ready passed for an extent of Acs.30.70 in the office of Executive Engi-
neer under Award proceedings A.15/91-92 dated 05.03.1992. In re-
spect of the remaining 0.15 cents award could not be passed since the
land was covered by pomegranate fruit bearing trees for which valua- G
tion was not given by the Assistant Director of Horticulture for want of
guidelines from the Government.
4. The appellant herein is the owner of the land admeasuring
0.15 acre alongwith 45 pomegranate trees in Sy. No.592/2, Reach No.57
H
520 SUPREME COURT REPORTS [2017] 6 S.C.R.
A of Dachur Village of Kaluvoya Nanda! of SPSR Nellore District of
Andhra Pradesh. On 30.03.1990, a Notification was issued under Sec-
tion 4( I) of the Land Acquisition Act for acquisition of the said land.
After declaration under Section 6 and after conducting enquiry, award
was passed in Award No.1/92-93 dated 14.09 .1992.
B 5. On 14.09.1992, Award No.1/92-93 was passed after fixing
the market value for the rain-fed dry lands at Rs.7,500/- per acre which
works out to Rs. I, 125/- for the land of 0.15 cents and of the pomegran-
ate trees which were three years old at Rs.42.17 P. per tree which
totally works out to Rs.1898/- as recommended by the Assistant Direc-
tor of Horticulture and Engineering Department. The compensation
c was accordingly paid. The claimant appellant received the compensa-
tion under protest and made application under Section 18 of the Land
Acquisition Act to refer the matter to the Civil Court for enhancement
of compensation.
6. On reference, O.P.No.64 of 1994 was heard by the Senior
D Civil Judge, Gudur, Nell ore District. In the Reference Court, the case of
the claimant appellant was that while passing the Award, the Land Ac-
quisition Officer assessed the market value of each pomegranate tree at
Rs.31/- to Rs.52/- per year which is a very low rate and paid for two
years only and that the Land Acquisition Officer assessed the market
E value of the trees without resorting to the capitalisation method of valu-
ation. The claimants also submitted therein that each pomegranate tree
earned a gross yield of Rs.325/- per annum and expense of each tree
was Rs.25/- from gross income per year. The claimant contended that
nearly JOO fruits from each tree and each frnit was valued at Rs.325/-
on the date of notification and the net value estimated was Rs.3,600/-
F for each pomegranate tree adopting multiplier of' 12 '.
7. In the Reference Court, claimants examined C.Ws 1 and 2.
R.W.1 was examined on behalfofthe Referring Officer. Exhibits A 1 to
AS and Ex.BI were marked. Vide judgment and order dated 27 .09.2004,
the Senior Civil Judge, Gudur, Nellore District applied the multiplier of
G '2' based on GO.Ms. No.601 dated 19.06.1992 and enhanced the mar-
ket value of each pomegranate tree to Rs.65/- and also awarded sola-
tium and other statutory benefits.
8. Being dissatisfied with the order of the Reference Court, the
claimant approached the High Court by way of an appeal being
H
NELATUR SAMPOORNAMMA v. SPECIAL D.C., TELUGU 521
GANGA PROJECT, AP. & ANR. [R. BANUMATHI, J.]
L.A.A.S.No.989 of 2007. The High Court based on the evidence on A
record arrived at a conclusion that the pomegranate trees existing on the
land at the time of acquisition were three years old and as per G.O. Ms.
No.601 dated 19.06.1992 marked as Ex.A2, fruit bearing period being
12 years, the relevant multiplier adopted should have been "9" and not
"2''.
B
9. Aggrieved by the order of the High Court, the appellant is
before us by way of special leave to appeal.
10. Learned counsel for the appellant submitted that when the
land with orchard of the appellant was acquired and possession was
taken by the Government pursuant to a Notification under Section 4( I) C
of the Land Acquisition Act published on 30.03.1990, as per letter No.
F(3) 2164/89 dated 26.11.1989 of the Director of Horticulture,
Government of Andhra Pradesh at Hyderabad, the revised net valuation
of pomegranate trees was at Rs.300/- per tree per annum and adopting
12 years as fruit bearing period, the High Court ought to have awarded D
higher compensation. Learned counsel for the appellant has relied upon
the decision of this Court in Civil Appeal Nos. 11404-405 of2016 dated
29.11.2016 whereby this Court has awarded compensation ofRs.3,000/
- per pomegranate tree in connection with lands acquired for Somashila
Project submergence. The learned counsel for the appellant prayed
that the same amount of compensation of Rs.3,000/- per pomegranate E
be awarded to the appellant. Learned counsel for the appellant further
submitted that the reduction of market value by I 0% on the purported
ground that there are no optimum irrigation facilities is unsustainable as
the Award itself records that there exists a well in .Survey No.505/6
which is the land belonging to junior maternal uncle of the appellant and F
that the acquired land was being irrigated from the said well as per the
understanding that existed between them.
11. Per contra, supporting the judgment of the High Court,
learned counsel for the respondent submitted that as per the evidence
on record all the 45 pomegranate trees existing on the land are three G
years old and the fruit bearing period is twelve years and thus the relevant
multiplier "9" was rightly applied for the purpose of determination of the
compensation for the pomegranate trees. Insofar as the judgment in
Civil Appeal Nos.11404-11405 of2016 is concerned, it is submitted that
the said order relates to Somashila Project submergence of which the
H
522 SUPREME COURT REPORTS [2017] 6 S.C.R.
·A award was of the year 1999 and the same cannot be applied to the
present case.
12. Heard the learned counsel for the parties at some length.
Pemsed the impugned judgment and considered the documents and other
materials placed on record.
B
13. As stated by the learned counsel for the appellant as per
Letter No. F(3) 2164/89 dated 26.11.1989 of the Department of
Horticulture, the revised value of fmit bearing trees viz. pomegranate
was fixed at Rs.75/-. On the date of Section 4(1) Notification i.e.
30.03.1990, it is evident that the very same Notification was in effect
c and that being so, the Reference Court as well as the High Court
committed an error in fixing the rate of the pomegranate trees at Rs.65/
- relying on the subsequr.nt G.O.No.601 dated 19.06.1992 which was
not in existence on record on the date of publication of Section 4( 1)
Notification. Neither the Reference Court ought to have fixed the value
of tree at Rs.65/- nor the High Court should have affirmed it. Insofar as
D the multiplier applied is concerned, after having given our thoughtful
consideration, we are of the view that as per the Notification of the year
1989, the fmit bearing period being not less than twelve years and the
trees being three years old, the High Court has rightly applied the multiplier
of"9".
E 14. Planting, raising and making commercial use of fruit bearing
trees is a painstaking affair and cost of the same is consistently on rise
as the years are passing by which is to be kept in view. Award of
compensation in relation to fruit bearing trees depends on facts and
circumstances of each case. It has been held in Kera/a State Electricity
F Board v. Livisha and Ors. (2007) 6 SCC 792, in the following terms:
"11. So far as the compensation in relation to fruit bearing trees
are concerned the same would also depend upon the facts and
circumstances of each case. We may, incidentally, refer to a recent
decision of this Court in Land Acquisition Officer v. Kamandana
Ramakrishna Rao AIR 2007 SC 1142 wherein claim on yield basis
has been held to be relevant for determining the amount of
compensation payable under the Land Acquisition Act, same
principle has been reiterated in Kapur Singh Mistry v. Financial
Commission and Revenue Secretary to Govt. of Punjab and Ors.
State ofHaryana v. Gurcharan Singh and Anr. [ 1995] I SCR 408,
H
NELATUR SAMPOORNAMMA v. SPECIAL D.C., TELUGU 523
GANGA PROJECT, AP. & ANR. [R. BANUMATHI, J.]
and Airports Authority oflndia v. Satyagopal Roy [2002] 2 SCR A
505."
15. The appellant has sought compensation of Rs.3000/- per
pomegranate tree relying on judgment of this Court dated 29.11.2016 in
Civil Appeal Nos.11404-11405 of 2016. In the facts and circumstances
of the said case, considering the cost of planting and efforts involved in B
growing trees in general and in particular raising the pomegranate tree
over the efflux of time, this Court deemed it appropriate to award Rs.
3000/- as compensation for each of the pomegranate tree. However,
the compensation of Rs. 3000/- per pomegranate tree, as has been
awarded in the abovementioned case, cannot be made applicable to the
present case, considering the fact that award of compensation by Land C
Acquisition Officer in the said case dated 08.03.1999, as opposed to
award in the present case which is dated 14.09.1992. A period of about
seven years is a considerable period to be taken note of while computing
cost of planting and raising fruit bearing trees. It is obvious that seven
years back a fruit bearing tree would have fetched lesser income than it D
would fetch now. Accordingly, in the facts and circumstances of the
present case, we deem it appropriate to award Rs.2,000/- per
pomegranate tree as compensation to the appellant. To this extent the
order of the High Court stands modified.
16. The appellants are awarded compensation ofRs.2,000/- per E
pomegranate tree. The appellant shall also be entitled to all statutory
benefits like solatium and interest on the same. The appeal is partly
allowed in the above terms.
Nidhi Jain Appeal partly allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.