Created byFuzzy Cloud

Supreme Court of India

NARMADA BACHAO ANDOLAN ETC. ETC.versusUNION OF INDIA AND ORS.

Citation
2000 INSC 489
Decided
18 October 2000
Disposal
Disposed off

Holding

The Court held that the dam construction shall proceed as per the Tribunal's award, the petitioners are barred by laches, and the 1987 environmental clearance is valid, with the Court retaining supervisory jurisdiction over relief, rehabilitation and environmental safeguards but not halting the project.

Summary

The Supreme Court examined a public‑interest writ petition challenging the construction of the Sardar Sarovar Dam on the Narmada River. The petitioners argued that the environmental clearance granted in 1987 was invalid, that the height of the dam should be reduced, and that the relief and rehabilitation measures for displaced persons violated fundamental rights. The Court held that the Tribunal's award fixing the dam height at 455 ft is final and binding, that the petitioners were guilty of laches for delaying their challenge, and that the environmental clearance, though based on incomplete studies, was not void. While the Court affirmed its power to monitor implementation of relief, rehabilitation and environmental safeguards, it refused to halt or alter the project. Consequently, the dam construction will continue as per the award, subject to the stipulated conditions and ongoing oversight by the Narmada Control Authority.

Issues considered

  • The petitioners' standing to challenge the Inter‑State Water Disputes Tribunal's award and the dam height after a long lapse (laches).
  • Whether the environmental clearance issued in 1987 was valid despite incomplete impact studies.
  • Whether the relief and rehabilitation package for displaced families complies with Article 21 and the ILO Convention.
  • Whether the height of the dam can be reduced from the Tribunal‑determined 455 ft.
  • The scope of judicial review over policy decisions and large infrastructure projects.
  • Whether a fresh independent environmental impact assessment is required before further construction.

Legislation cited

Subjects

public interest litigationenvironmental clearanceinter‑state water disputeNarmada damlachesrelief and rehabilitationtribal displacementjudicial reviewArticle 21precautionary principle

Judgment

A                 NARMADA BACHAO ANDOLAN ETC. ETC.
                                          v.
                          UNION OF INDIA AND ORS.

                                OCTOBER 18, 2000

B     [DR. A.S. ANAND, C.J., S.P. BHARUCHA AND B.N. KIRPAL, JJ.]


         Constitution of India-Articles 32 and 226-Public Interest litigation-
    Scope of-No directions can be issued which are against legal provisions.
c         Constitution of India-Articles 32 and 226-Judicial Review-Scope
    of-Courts cannot transgress into the field of policy decision-Government
    deciding to construct a dam-No violation of law or malafide--Held, Courts
    cannot sit in appeal over the policy decision of the Government.

D          Constitution of India-Articles 32 and 226-laches-Project for
    construction of dam approved 25 years ago-Huge investments made-
    Petitioner agitating against construction since 1986-Writ Petition filed in
    1994-Held, Petitioner cannot challenge the construction after such lapse
    of time.

E         Constitution of India-Article 32-Public Interest litigation-Petitioner
    challenging the construction of a dam on the ground that adequate steps
     were not taken for relief and rehabilitation of the oustees and that the
    adverse environmental effects were not taken into account-Award of Tribunal
    constituted under Inter States Water Disputes Act, 1956-Award laying down
F   the measures to, be taken for relief and rehabilitation of the oustees-Several
    authorities set up for monitoring the implementation of the Award as per the
    direction of the Tribunal-Authorities to see that measures to protect
    environment are also taken-Held, relief and rehabilitation and
    environmental concerns had been taken care of-Courts can only see if the
    Authorities are discharging their duties or not.
G
          Environment (Protection) Act, 1986-Section 3-Decision to construct
    a dam-Environmental clearance given on the basis of available studies and
    surveys which were not complete-Conditions imposed to complete
    environmental safeguards pari passu with the project work-Held, the
    environmental clearance cannot be said to be invalid-Constitution oflndia-
H
                                         94
                        NARMADA BACHAO ANDOLAN v. U.0.1.                             95
        Article 32.                                                                        A
              Environment (Protection) Act, 1986-Section 3-Polluting industries
__.__   and projects-Precautionary Principle and Polluter-pays principle-
        Applicability of-Held, would be applicable if the extent of damage likely to•
        be caused is not known-Burden of proof-Held, would be on the person
        who wants to change the status quo if the extent of damage likely to be            B
        caused is not known-Indian Evidence Act, 1872-Section 102.

              Inter State Water Disputes Act, 1956-Section 5(2) and 5(4)-Award
        of the Tribunal-Final and binding on parties-Third party cannot challenge
        the Award
                                                                                           c
              The Petitioner was agitating against the construction of the Sardar
        Sarovar Dam since 1986. In the present case the Petitioner had challenged
        the decision of the Govemment of India and the concerned State Governments
        to construct the dam in the Narmada river basin by way of the present Writ
        Petition filed in 1994.
                                                                                           D
              The idea of development of the Narmada river system was first mooted
        in 1946. The State of Gujarat granted administrative clearance Stage I of the
        project in 1961. The project was inaugurated on 5.4.1961 and preliminary
        work started. However, due to disagreement between the concerned States the
        project could not be implemented.
                                                                                           E
              The State of Gujarat filed a complaint under Section 3 of the Inter States
        Water Disputes Act, 1956 stating that water dispute had arisen between the
        State of Gujarat and the States of Madhya Pradesh and Maharashtra over the
        use, distribution and control of the waters of Narmada river. The Government
        of India constituted a Tribunal and referred the dispute to the Tribunal.          F
              While the dispute was still pending before the Tribunal, a forma.1
        agreement was entered into on 12.7.1974 between the Chief Ministers of the
        States of Madhya Pradesh, Maharashtra and Rajasthan and the Advisor to
        the Governor of Gujarat sorting out several issues which the Tribunal would
        otherwise have decided. However, dispute in respect of the height of the dam       G
        remained. The parties to the agreement agreed that the Tribunal would decide
        the said issue of height after considering the submission of the parties. If
        was also noted that the Narmada project should no longer be delayed in the
        best regional and national interests.

             The Tribunal declared its final award on 7.12.1979. The Tribunal              H
     96                      SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A examined the issues regarding allocation, height of the dam, hydrology and
    other related issues. The Tribunal decided that the height of the Sardar
    Sarovar Dam would be at Full Reservoir Level 455 feet. The Tribunal issued
    directions regarding submergence of land, acquisition of land and the             .i.....,

    rehal:»ilitation of displaced persons. The Tribunal directed that no
    submergence of any area should take place unless tht oustees are
B   rehabilitated. The Tribunal further directed constitution of Narmada Control
    Authority, an inter State administrative authority, for the purpose of securing
    compliance with and implementation of the decision and directions of the
    Tribunal. The Tribunal also directed constituting a Review Committee
    consisting of the Union Minister for Irrigations as its Chairperson and the
C   Chief Ministers of Madhya Pradesh, Gujarat, Maharashtra and Rajasthan as
    its members. The Review Committee could review the decisions of the
    Narmada Control Authority and the Sardar Sarovar Construction Advisory
    Committee.

          In order to carry out the directions of the Award. The Inter States Water
D   Disputes Act, 1956 was amended and Section 6-A was inserted. Thereafter,
    the Government of India framed a scheme and constituted Narmada Control
    Authority to give effect to the Award of the Tribunal. In 1987 the Narmada
    Control Authority created independent machinery of Environment Sub-group
    to ensure that the environmental safeguards were properly planned and
E   implemented.

          On 15.12.1980, the Central Water Commission referred the Sardar
    Sarovar Project to the Department of Science and Technology for
    environmental clearance. A meeting of the Environment Appraisal Committee
    of the Department of Environment was held on 12.4.1983 in which the project
F   was in principle approved.

           In January J 985, the Department of Environment and Forests of the
    Government of India issued "Guidelines of Environmental Impact Assessment
    of River Valley Projects". The Guidelines noted the undesirable consequences
G   of the river valley projects and the need to consider the environmental aspects
    along with other feasibility considerations. According to the Guidelines the
    cost of proposed remedial and mitigative measures, such as compensatory
    afforestation, to protect the environment had to be included in the cost of the
    project. The Guidelines stipulated that the Union of- India should give
    environmental clearance only after a) all the necessary data in respect of the
H   environmental impact of the project had been collected and assessed; (b) the
                      NARMADA BACHAO ANDOLAN v. U.0.1.                             97
      assessment showed that the Project could proceed; and (c) the environmental        A
      safeguard measures, and their cost, had been worked out.

            Thereafter, there were several meetings convened by various ministries
      for discussing issues relating to environment. In October, 1986 the Ministry
      of Water Resources forwarded a Note to the Ministry of Environment and
      Forests detailing the surveys/studies as well as work remaining to be done         B
      along with the time schedule therefor. The Note observed that delay was being
      caused due to inadequacy of the material for evaluation of the environmental
      impact of the project. It was opined in the said report that considering the
      importance and the urgency of the project and its benefits so far as power
      and irrigation facilities are concerned, it should be cleared from the             C,
      environmental angle, subject to conditions and stipulations.

            The Department of Environment and Forests made its own assessment
      and opined that formulation of catchment area programme, wildlife census by
      the Zoological Survey of India and survey by the Botanical Survey of India
      would take about three years. It finally decided that ifthe Government should      D
      decide to go ahead with the project it should be done with the provision of
      environment management authority with adequate power and teeth to ensure
      that environment management plan is implemented Pari passu with the
      engineering and other works.

            The matter relating to grant of environmental clearance was referred         E
      to the Prime Minister's Secretariat for clearance.

             On 19.12.1986 the Secretary, Ministry of Environment and Forests sent
      a Note to the Secretary to the Prime Minister on the environment aspects of
      the Narmada Sagar Project and Sardar Sarovar Project. In the Note, it was
      mentioned that due to inadequacy of the available data, it was not possible to     F
      assess the impact of the loss of habitat on the wildlife and the overall loss of
      biological diversity and genetic reserves. It was mentioned that the projects
      were at fairly advanced stages of preparedness. The Note recommended the
,;l   establishment of Narmada Management Authority with adequate powers and
      teeth to ensure that the Environmental Management Plan did not remain only         G
      on paper but was implemented pari passu with the engineering and other
      works.

            The Additional Secretary to the Prime Minister prepared a Note dated
      15.1.1987. The Note mentioned that the Department of Environment and
      Forests had recommended conditional approval of the project. The Prime             H
     98                       SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A Minister opined that it was perhaps good time to try for River Valley Authority.
          On 24.6.1987 the Ministry" of ,Environment and For_ests granted
    ·conditional approval to the projects. The conditions stipulated that

             (i)   The Narmada Control Authority would ensure that environmental
B                  safeguard measures are planned and implemented pari passu
                   with the progress of the work on the project.

            (ii) The surveys/studies assured would be carried out as per the
                 proposed schedule.

C           (iii) The Catchment Area treatment programme and the rehabilitation
                  plans would be so drawn as to be completed ahead of reservoir
                  filling.

            (rv)   The Department of Environment and Forests should be kept
                   informed of the progress on various works periodically.
D
         On 5.I0.1988 the Planning Commission approved investment in the
    project with the direction to comply with the conditions laid down in the
    environmental clearance of24.6.1987.

           Before this Court the Petitioner contended :-
E          HEIGHT OF THE DAM

         I. Having regard to the hydrology, the finding of the Tribunal is not
    correct and the height of the dam should be reduced from 455 feet. (This
    argument was also advanced by the State of Madhya Pradesh.)
F         DISPLACEMENT OF TRIBALS

           2. The forcible displacement of the tribal population from the project
    affected area was not in the national or public interest. It was in violation of
    Article 21 of the Constitution of India. It was also in violation of Article 12 of
G   the ILO Convention, to which India was a signatory, which stipulated that the
    tribal population should not be removed from their lands without their free
    consent except in accordance with national laws and regulations or reasons
    relating to national security or in the interest of national economic
    development. Article 12 further stated that when the removal of the tribal
    population was necessary as an exceptional measure, they should be provided
H   with land of quality at least equal to that of the land previously occupied by
                                NARMADA BACHAO ANDOLAN v. U.0.1.                             99
               them and they should be fully compensated for any resultant loss or injury.         A
               According to the Petitioner, .the Respondents had not shown that the
               displacement of the tribal population was required as an exceptional measure.

                     3. The projects were not in the best national interest and was not a
               solution to water problems. The projects would touch only the fringes of the
               drought prone areas of Kutch and Saurashtra.                                        B
-.                   RELIEF AND REHABILITATION

                     4. As a result of construction of the dam over 41000 families and 245
               villages would be affected. The authorities have considered only the families
               affected by submergence as project affected families. There is no scheme for        c
               rehabilitation of several other families that would be affected by the project.

                     5. The Narmada Control Authority has under estimated the total number
...            of affected families and the land required for these families' rehabilitation•
                                                                                                   D
                     6. The relief and rehabilitation p,,:1'..ages in the different States were
      --       different thereby restricting the choice of the oustees. This would lead to a
               situation where the oustees would be forced to shift to Gujarat, where the
               rehabilitation package was more favourable.

                    7. There were a large number of persons living in the submergence              E
               area who were not farmers and would lose their livelihood due to loss of the
               community and/or river. They were not being properly rehabilitated.

                     8. There was a need for an independent monitoring agency in respect of
               re-settlement & rehabilitation as the Re-settlement & Rehabilitation Sub-
               group merely endorses the assertions made by the Government.                        F

                     9. There was a clear requirement laid down by the Tribunal of village-
               wise communication rehabilitation in respect of the State of Gujarat. The
      ' ,.._   oustees were not offered a chance to re-settle in Gujarat as a community and
               thus the order of the Tribunal was violated.                                        G
                     10. There was no provision for grazing land and fuel wood for the project
               affected families.

                      J J. The rehabilitated people did not have adequate facility of irrigation
               at the place of their rehabilitation.                                               H
     100                     SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A          ENVIRONMENTAL CLEARANCE

            12. The environmental clearance given to the project in 1987 was without
      proper application of mind. The relevant surveys/studies were not available at
    · the time of granting of the environmental clearance.

B         13. As the deadline for completion of the studies was not met till 1990,
    the Ministry of Environment and Forests had declared that the environmental
    clearance given to the project had lapsed. The Ministry of Environment and



c
    Forests made a request to the Ministry of Water Resources for seeking
    extension of the clearance but ultimately no extension was sought and given.

           OTHER ENVIRONMENTAL ISSUES
                                                                                       ..
          14. As per the letter dated 24.6.1987 whereby environmental clearance
    was given to the project, the catchment area treatment programme was not to
    be done pari passu but was required to be completed before impoundment.
D   However, the impounding began in 1994 and the catchment area treatment
    programme had not been completed by then.

          15. That there was need for some independent agency to examine the
    various studies and action plans because if the studies and plans were not
    properly done or implemented, the 'area, which were supposed to benefit, would
E   end up being rendered unfit for cultivation.

          16. The compensatory afforestation was being carried outside the project
    impact area and on wastelands or lesser quality land, which would result in
    forest of a lesser quality.

F         17. The downstream impacts of the project would destroy fisheries and
    will result in salt-water ingress.

          18. The area of submergence would include several sites of
    archaeological importance and the.construction of the dam would mean loss
    of rich historical legacy.
G
         19. The impact of the project on the flora and fauna would be severe.
    The studies in respect of flora and fauna had been completed only recently
    and action plans were still awaited in many cases.

        20. The project would have serious impacts on health around the
H   submergence area and in the command area.
                     NARMADA BACHAO ANDOLAN v. U.0.1.                            101
          21. The Ministry of Environment and Forests has abdicated i.ts                A
     responsibility by accepting the studies and progress report of the
     Environmental Sub-group at the face value and without verification.

           Dismissing the Writ Petition by majority, the Court

           HELD : Per Kirpal, J. {for himself and Dr. A.S. Anand, C.J.)                 B

-          PUBLIC INTERFST LITIGATION

           I.I. Public Interest Litigation was an innovation essentially to safeguard
     and protect the human rights of those people who were unable to protect
     themselves. With the passage of time the Public Interest Litigation                C
     jurisdiction has been ballooning so as to encompass within its ambit subjects
     such as probity in public life, granting of largesse in the form of licences,

-    protecting environment and the like. But the balloon should not be inflated so
     much that it bursts. Public interest litigation should not be allowed to
     degenerate to becoming Publicity Interest Litigation or Private Interest
     Litigation. (218-C-DI                                                              D
            1.2. While exercising jurisdiction in Public Interest Litigation cases
     Court has not forsaken its duty and role as a Court of law dispensing justice
     in accordance with law. It is only where there has been a failure on the part
     of any authority in acting according to law or in non-action or acting in
     violation of the law that the Court has stepped in. No directions are issued       E
     which are in conflict with any legal provisions. Directions have, in appropriate
     cases, been given where the law is silent and inaction would result in violation



..
     of the Fundamental Rights or other legal provisions. (218-E-Fl

           JUDICIAL REVIEW
                                                                                        F
            2.1. While protecting the rights of the people from being violated in
     any manner utmost care has to be taken that the Court does not transgress
     its jurisdiction. There is in our Constitutional framework a fairly clear
     demarcation of powers. The Court has come down heavily whenever the
     executive has sought to impinge upon the Court's jurisdiction. At the same G
     time, in exercise of its enormous power the Court should not be called upon
     or undertake Governmental duties or functions. The Courts cannot run the
     Government nor the administration indulge in abuse or non-use of power and
     get away with it. The Courts must, therefore, act within their judicially
     permissible limitations to uphold the rule of law and harness their power in
     public interest. It is precisely for this reason that it has been consistently H
     102                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A held by this Court that in matters of policy the Court will not interfere. When
     there is a valid law requiring the Government to act in a particular manner
     the Court ought not to, without striking down the law, give any direction which
     is not in accordance with law. In other words, the Court itself is not above the
     law. 1218-F-H; 219-A-Bl

B         2.2. In respect of public projects and policies which are initiated by the
    Government, the Courts should not become an approval authority. Normally
    such decisions are taken by the Government after due care and consideration.
    In a democracy, welfare of the people at large, and not merely ofa small section
                                                                                             -
    of the society, has to be the concern of a responsible Government. If a
C   considered policy decision has been taken, which is not in conflict with any         J

    law or is not ma/a fide, it will not be in public interest to require the Court to
    go into and investigate those areas which are the functions of the executive.
    When two or more options or views are possible and after considering them
    the Government takes a policy decision it is then not the function of the Court
    to go into the matter afresh and, in away, sit in appeal over such a policy
D   decision. 1219-B-El

           2.3. The courts, in the exercise of their jurisdiction, will not transgress
     into the field of policy decision. Whether to have an infrastructural project
    or not and what is the type of project to be undertaken and how it has to be
    executed, are part of policy making process and the Courts are ill equipped
E   to adjudicate on a policy decision so undertaken. The Court, no doubt, has a
    duty to see that in the undertaking of a decision, no law is violated and people's
    fundamental rights are not transgressed upon except to the extent permissible
    under the Constitution.1217-G-H; 218-AI

           LACH ES
F
           3.1. Any challenge to a policy decision relating to an infrastructural
     project must be before the execution of the project is undertaken.Any delay
    in the execution of the project means over run in costs and the decision to
    undertake a project, if challenged after its execution has commenced, should
G   be thrown out at the very threshold on the ground of laches if the Petitioner
    had the knowledge of such a decision and could have approached the Court at
    that time. Just because a petition is termed as a Public Interest Litigation
    does not mean that ordinary principles applicable to litigation will not apply.
    Laches is one of them. 1218-A-B)

H          3.2. The Petitioner which had been agitating against the dam since 1986
                               NARMADA BACHAO ANDOLAN v. U.0.1.                              103
              is guilty of laches in not approaching the Court at an earlier point of time.         A
              The Narmada project, in principle, was cleared more than 25 years ago. After
              the environmental clearance was given the construction of the dam was
              undertaken and hundreds of crores have been invested before the Petitioner
              chose to file a Writ Petition in 1994 challenging the decision to construct
              the dam and the clearance as was given. 1136:H, E, Gf
                                                                                                    B
                    3.3. When such projects are undertaken and hundreds of crores of
    I         public money is spent, individual or organisations in the garb of Public Interest
iiiiiiilL
              Litigation cannot be permitted to challenge the public decision taken after a
              lapse of time. It is against the national interest and contrary to the established
_..,          principles of law that decisions to undertake developmental projects are              C
              permitted to be challenged after a number of years during which period public
              money has been spent in the execution of the project. 1137-A-Bf

                    HEIGHT OF THE DAM

                    4.1. The Tribunal had in no uncertain terms come to the conclusion              D
              that the height of the dam should be 455 ft. It had rejected the contention of
        '">   the State of Madhya Pradesh for fixing the height at a lower level. Any issue
              which has been decided by the Tribunal would, in law, be binding on the
        -     respective States. Once the Award is binding on the States, it will not be open
              to a third party like the Petitioner to challenge the correctness thereof.            E
                                                                          1138-B-C; 139-Df

                    The State of Karnataka v. State of Andhra Pradesh and Ors., 120001 9
              sec 572, relied on.
                    4.2. One of the indicators of the living standard of people is the per capita   F
        -     consumption of electricity. There is, however, perennial shortage of power in
              India, and therefore, it is necessary that the generation increases. In India
              there is more reliance now on thermal power projects. But these thermal
              power projects use fossil fuels, which are not only depleting fast but also
 ~            contribute towards environmental pollution. Global warming due to the                 G
              greenhouse effect has become a major cause of concern. On the other hand,
              the hydel power's contribution in the greenhouse effect is negligible and it
              can be termed ecology friendly. Not only this but the cost of generation of
              electricity in hydel projects is significantly less. The Award of the Tribunal
              has taken all these factors into consideration while determining the height
              of the dam at 455 ft. 1224-E-H; 225-AI                                                H
      104                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

 A           DISPLACEMENT OF TRIBALS

            5.1. The rehabilitation package contained in the Award of the Tribunal
     as improved further by the State of Gujarat and the other States primafacie
     shows that the land required to be allotted to the tribals is likdy to be equal,
     if not better, than what they had owned. It is apparent that the tribal population
 B   affected by the submergence would have to move but the rehabilitation package
     was such that the living condition would be much better than what it was before.
     Article 12 of the ILO Convention clearly suggested that when the removal of
     the tribal population is necessary as an exceptional measure, they shall be
     provided with land of quality at least equal to that of the land previously occupied
C    by them and they shall be fully compensated for any resultant loss or injury.
                                                      (143-H; 144-A; 143-D; 143-G-Hl
            5.2. The displacement of the tribals and other persons would not per se
     result in the violation of their fundamental or other rights. The effect is to see
     that on their rehabilitation at new locations they are better off than what they
     were. At the rehabilitation sites they will have more and better amenities than
D    which they enjoyed in their tribal hamlets. The gradual assimilation in the
     main stream of the society will lead to betterment and progress. (145-G-Hl
           5.3. The allegation that the Sardar Sarovar Project was not in the
     national or public interest is not correct. Dams play a vital role in providing
     irrigation for food security, domestic and industrial water supply, hydroelectric
E    power and keeping flood waters back. There would be a positive impact on
     preservation of ecology as a result from the project. The project by taking
     water to drought-prone and arid areas of Gujarat and Rajasthan would
     effectively arrest ecological degradation which was returning to make these
     areas inhabitable due to salinity ingress, advancement of desert, ground water
F    depletion, fluof'.ide and nitrite affected water and vanishing green cover. There
     will be improvement of fodder availability, which will reduce pressure on
     diversity and vegetation. The Sardar Sarovar Project by generating elean eco-
     friendly power will save the air pollution which would othern:ise take place by
                                                                                            -
     generation power of similar capacity. (144-A; 144-E; 145-D-F)

G         Gramophone Co. of India v. B.B. Pandey, [1984) 2 SCC 534; People's
     Union for Civil liberties v. Union of India, [199713 SCC 433 and Consumer
     Education and Research Centre v. Union of India, 11995) 3 SCC 42, cited.
            RELIEF AND REHABILITATION

            6.1. In governance of the State, decisions have to be taken where there
H are conflicting interest. If for one set of people there were only one solution,
                          NARMADA BACHAO ANDOLAN v. U.0.1.                            105
         namely, construction of a dam, the same would have an adverse effect on             A
         another set of people whose houses and agricultural land would be submerged
         in water. When a decision is taken by the Government after due consideration
         and full application of mind, the Court is not to sit in appeal over such
         decision. [220-C-DJ

               6.2. Displacement of people living on the proposed project sites and the      B
         areas to be submerged is an important issue. It is a fact that people are
         displaced by projects from their ancestral homes. Displacement of these people
         would undoubtedly disconnect them from their past, culture, custom and
         traditions, but then it becomes necessary to harvest a river for larger good.
_,,,,.   A natural river is not only meant for the people close by but it should be for      C
         the benefit of those who can make use of it, being away from it or near by. A
         properly drafted relief and rehabilitation plan would improve living standards
         of displaced persons after displacement. The relief and rehabilitation packages
         of the States, especially of Gujarat, are such that the living conditions of the
         oustees will be much better than what they had in their tribal hamlets.
                                                               [221-C-E; 221-H; 222-AI       D
   >           7.1. The Award of the Tribunal is binding on the States concerned. The
         said Award also envisages the relief and rehabilitation measures which are
         to be undertaken. If for any reason, any of the State Governments involved
         lag behind in providing adequate relief and rehabilitation then the proper          E
         course for a Court to take would be to direct the Award's implementation and
         not to stop the execution of the project. [222-H; 223-Al

               7.2. This Court, as a Federal Court of the country especially in a case
         of Inter-State river dispute where an Award had been made, has to ensure
         that the bindh1g Award is implemented. In this regard, the Court would have         F
         the jurisdiction to issue necessary directions to the State which, though
         bound, chooses not to carry out its obligations under the Award. Just as an
         ordinary litigant is bound by the decree, similarly a State is bound by the
         Award. Just as the execution of a decree can be ordered, similarly, the
         implementation of the Award can be directed. If there is a short fall in carrying
         out the re-settlement and rehabilitation measures, a time bound direction can       G
         and should be given in order to ensure the implementation.of the Award.
         Putting the project on hold is no solution. 1223-A-C)

              8. There is a basic difference in the impacts of the projects in the
         upstream submergence area and its impacts in the beneficiary zone of the
         command area. While people, who were oustees from the submergence zone,             H
     106                     .SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A    required re-settlement and rehabilitation, on the other hand, most of the people
     falling under the command area were in fact beneficiaries o£the projects and
     their remaining land would get relocated with the construction of the canal
     leading to greater agricultural output. (193-D-E)

           9. There appears to be no material on which it can be concluded that no
B proper surveys had been carried out for determining the number of project
     affected families who would be adversely affected by the construction of the
     dam. Each State has drawn detailed action plan and it is after requisite study
     had been made that the number of project affected families have been
     identified. (1931-G-H; 192-Al

C          10. It is incorrect to say that the difference in relief and rehabilitation
    packages, the package of Gujarat being the most liberal, amounts to
    restricting the choice of the oustees. Relief and rehabilitation packages in
    different States were different due to different geographical, local and
    economic conditions and availability of land in the States. The liberal packages
D   available to the Sardar Sarovar Project oustees in Gujarat are not available
    to the project affected people of other projects in Gujarat. Each State has its
    own package and the outsees have an option to select the one which was most
    attractive to them. There is no requirement that the liberalisation of the
    packages by States should be to the same extent. (192-B-D)

E          11.1. There is no basis for contending that some outside agency or
    National Human Rights Commission should see to the compliance of the
    Tribunal Award. There is an elaborate network of authorities which have to
    see to the execution and implementation of the project in terms of the Award.
    All aspects of the project are supervised and there is a Review Committee
    which can review any decision of the Narmada Control Authority and each of
F   the rehabilitating States have set up an independent Grievances Redressal
    Authority to take care that the relief and rehabilitation measures are properly
    implemented and the grievances, if any, of the oustees are redres~ed.
                                                                           (196-E-GJ

G         11.2. Dam has necessarily to be regarded as an infrastructural project.
    There are three stages with regard to the undertaking of an infrastructural
    project. One is conception or planning, second is decision to undertake the
    project and the third is the execution of the project. The conception and the
    decision to undertake a project are to be regarded as a policy decision. Once
    such a considered decision is taken, the proper execution of the same should
H   be taken expeditiously. It is for the Government to decide how to do its job.
                        NARMADA BACHAO ANDOLAN v. U.0.1.                            107
       When it has put a system in place for the execution of a project and such a         A
       system cannot be said to be arbitrary, then the only role which a Court may
       have to play is to see that the system works in the manner it was envisaged.
                                                                          (217-B-DJ

             12.1. The requirement in the Tribunal's Award was that the State of
       Gujarat should establish rehabilitation villages in Gujarat in the irrigation       B
       command of the Sardar Sarovar Project on the norms mentioned for
       rehabilitation of the families who were willing to migrate to Gujarat. This
       provision could not be interpreted to mean that the oustees' families should
       be resettled as a homogeneous group in a village exclusively set up for each
....   such group. The concept of community-wise re-settlement, therefore, cannot
       derive support from the above quoted stipulation. Subsequent to the Tribunal's
                                                                                           C
       Award, on the recommendation of the World Bank, the Government of Gujarat
       adopted the principle that resettlement of the oustees should be relocated as
       village units, village sections or families in accordance with the oustees'
       preference. The oustees' choice has actively guided the resettlement process.
                                                                           1193-F-HJ       D
             12.2. While re-settlement as a group in accordance with the outstees'
       preference was an important principle/objective, the other objectives were that
       the oustees should have improved or regained the standard of living that they
       were enjoying prior to their displacement and they should have been fully
       integrated in the community in which they were resettled. These objectives          E
       were easily achievable if they were resettled in the command area where the
       land was twice as productive as the affected land and where large chunks of
       land were readily available. This was what the Tribunal's Award stipulated
       and one objective could not be seen in isolation of the other objectives. [194-EJ

             12.3. The underlined principle in forming the relief and rehabilitation       F
       policy was not merely of providing land for project affected families but there
       was a conscious effort to improve the living conditions of the project affected
       families and to bring them into the mainstream. If one compares the living
       conditions of the project affected families in their submerging villages with
       the rehabilitation packages first provided by the Tribunal's Award and then         G
       liberalized by the States, it is obvious that the project affected families had
       gained substantially after their resettlement. 1194-H; 195-AJ

             13. Grazing land was not mandated or provided for in the Tribunal's
       Award but nevertheless, the grazing land ofsix villages was available for use
       of project affected families. It may be that the grazing land was inadequate        H
     108                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A but this problem will be faced by the entire State of Gujarat and not making
     such land available for them does not in any way violate any of provisions of
     the Award. (195-FJ

             14. Most of the resettlement of the project affected.families were
     provided irrigation facilities in the Sardar Sarovar Project command area or
B    in the command areas of other irrigation projects. In many of the out of
     command sites, irrigated lands were purchased. In cases where the irrigation
     facilities were not functioning, the Government of Gujarat had undertaken
     the work of digging tubewells in order to avoid any difficulty with regard to
     irrigation in respect of those oustees who did not have adequate irrigation
C    facilities. (195-G-Hl

           IS. More than adequate steps are being taken by the State of Gujarat
    not only to implement the Award of the Tribunal to the extent it grants relief
    to the oustees but the effort is to substantially improve thereon and, therefore,
    continued monitoring by this Court may not be necessary. The State of
D   Madhya Pradesh seems to be in no hurry in taking steps to effectively
    rehabilitate the project affected families in their home State. The State of
    Madhya-Pradesh is under an obligation to effectively resettle those oustees
    whose choice is not to go to Gujarat. (212-G; 214-C-Fl

           ENVIRONMENTAL CLEARANCE
E
           16.1. ft is not possible to accept the contention of the Petitioner that the
    environmental clearance of the project was given without application of mind.
    It is more than evident that the Government of India was deeply concerned
    with the environmental aspects of the Narmada Sagar and Sardar Sarovar
    Project. The Government was aware of the fact that number of studies and
F   data had to be collected relating to environment. Keeping this in mind, a
    conscious decision was taken to grant environmental clearance and in order
    to ensure that environmental management plans are implemented pari passu
    with engineering and other works. (160-G-H; 161-Al

G          16.2. At the time when the environmental clearance was granted by the
    Prime Minister whate\'·er studies were available were taken into consideration.
    It was known that the construction of the dam would result in submergence
    and the consequent effect which the reservoir will have on the ecology of the
    surrounding areas was also known. Various studies relating to environmental
    impact had been carried out. There are different facts of environment and if
H   in respect of a few of them adequate data was not available it does not mean
                     NARMADA BACHAO ANDOLAN v. U.0.1.                              109
    that the decision taken to grant environmental clearance was in any way               A
    vitiated. The clearance required further studies to be undertaken and this
    has been and is being done. Care for environment is an on going process and


-   the system in place would ensure that ameliorative steps are taken to counter
    the adverse effect, if any, on the environment with the construction oftlte dam.
                                                                          (177-D-Fl
                                                                                          B
          17. There could not have been any question of the environmental
    clearance granted to Sardar Sarovar Project being lapsed more particularly
    when the Environmental Sub-group had been consistently monitoring the
    progress of various environmental works and had been observing in its
    minutes of various meetings held from time to time, about its analysis of the         C
    works done by the respective States in the matter of the status of studies,
    surveys and environmental action plans. (164-C-D)

          OTHER ENVIRONMENTAL ISSUES

           18. Environmental and ecological consideration must, of course, be given       D
    due consideration but with proper channellisation of developmental activities
    ecology and environment can be enhanced. So far a number of such river valley
    projects have been undertaken in all parts of India. The Petitioner has not
    been able to point out a single instance where the construction of a Dam has,
    on the whole, had an adverse environmental impact. On the contrary the                E
    environment has improved. That being so there is not reason to suspect, with
    all the experience gained so far, that the position here will be any different
    and there will not be overall improvement and prosperity. (222-D; 222-FJ

           19.1. The 'precautionary principle' and the corresponding burden of
     proof on the person who wants to change the status quo will ordinarily apply         F
    in a case of polluting or other project or industry where the extent of damage
    likely to be inflicted is not known. When th.ere is a state of uncertainty due
    to lack of data or material about the extent of damage or pollution likely to be
    caused then, in order to maintain the ecology balance, the burden of proof
    that the said balance will be maintained must necessarily be on the industry          G
    or the unit which is likely to cause pollution. On the other hand where .the
    effect on ecology or environment of setting up of an industry is known, what
    has to be seen is that if the environment is likely to suffer, then what mitigative
    steps can be taken to offset the same. Merely because there will be a change
    is no reason to presume that there will be ecological disaster.
                                                                     (175-H; 176-A-BI     H
     110                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A         A.P. Pollution Control Boardv. Professor M. V. Mavadu, (199912 SCC
    718; Sierra Club et. v. Robert F. Froehlke, 350 bF. Supp. 1280 (1973);
    Tennessee Valley Authority v. Hiram G. Hill, 437 US 153, 57 L Ed 2d 117;
    Arlington Coalition on Transportation v. John A. Volpe, 458 F.2d 1323 (1972)
    and Environment Defence Fund, Inc. v. Corps of Engineers of United States
B   Army 325 F. Supp. 749 (1971), distinguished.

           Vellore Citizens' Welfare Forum v. Union of India, (199615 SCC 647,
     referred to.

           19.2. In the present case, what is being constructed is a large dam. The
    dam is neither a nuclear establishment nor a polluting industry. The
C   construction of a dam undoubtedly would result in the change of environment
    but it will not be correct to presume that the construction of a large dam like
    the Sardar Sarovar will result in ecological disaster. (176-C-DJ

           20. The environmental clearance of24.6.1987 required the work to be
D dont: pari passu with the construction of the dams 'and the filling of the
    reservoir. The Respondents had proceeded on the basis that the requirement
    in the letter of24.6.1987 that catchment area treatment programme and
    rehabilitation plans be drawn up and completed ahead of reservoir filling would
    imply that the work are to be done pari passu as far as catchment area
    treatment programme is concerned, with the filling of reservoir. The status
E   of compliance with respect to pari passu conditions shows that the overall
    works by and large were on schedule though, there was some ·slippage in
    Madhya Pradesh. (167-D-FJ

          21. There is no reason whatsoever as to why independent experts should
    be required to examine the quality, accuracy, recommendations and
F   implementation of the studies carried out The Narmada Control Authority
    and the Environmental Sub-group in particular have the advantage of having
    with them the studies which had been carried out and there is no reason to
    believe that they would not be able to" handle any problem, if and when, it arises
    or to doubt the correctness of studies made. (166-HI

G         22.1. Loss of forest because of any activity is undoubtedly harmful. But ·     ·,
    it cannot be ignored and it is important to note that these large dams also
    cause conversion of waste land into agricultural land and making the area
    greener. Large dams can also become instruments in improving the
    environment (222-A-BI
H          22.2. Wltile granting approval in 1987 to the submergence of forest
                    NARMADA BACHAO ANDOLAN v. U.0.1.                             11 r
    land and/or diversion thereof for the Sardar Sarovar Project, the Ministry of       A
    Environment and Forests had laid down a condition that for every hectare of


-   forest land submerged or diverted for construction of the project, there should
    be compensatory afforestation on one hectare of non-forest land plus
    reforestation on two hectare of degraded forest The State of Gujarat had fully
    complied with the condition by raising afforestation. If afforestation was taking
    place on wasteland or lesser quality land, it did not necessarily follow, as was
                                                                                        B

    contended by the Petitioners, that the forests would be of lesser quality or
    quantity. (168-C-DJ

          23. Until all the dams are constructed upstream and the entire flow of
    river is harnessed, which is not likely in the foreseeable future, there is no      C
    question of adverse downstream impact and the Petitioner's assertions in this
    regard are ill-conceived. In 1992 Sardar Sarovar Narmada Nigam Limited
    issued an approach paper on environmental impact assessment for the river
    reach downstream. The report clearly demonstrates that the construction of
    dam would result into more regulated and perennial flow into the river with
    an overall beneficial impact. (168-H; 170-A; 170-BI                                 D
          24. No centrally or state protected cultural sites were located in the
    submergence area of the project. The concerned State Governments carried
    out a complete survey of cultural and religious sites within the submergence
    zone to list all Archaeological sites which, though not protected under national    E
    law, were of sufficient value to merit relocation. (171-Al

          25. A condition of environmental clearance of 24.6.1987 as far as it
    related to flora and fauna was that the Narmada Control Authority would
    ensure in depth studies on flora and fauna needed for implementation of
    environmental safeguard measures. A number of studies were carried out              F
    which indicated that with the construction of the dam, water availability and
    soil moisture will increase and support varieties of plants and animals.
                                                                       (172-E-F(

          26. The area of public health was in no way being neglected. The
    principle features of the Gujarat Work Plan included establishment of a             G
    hospital near the dam site, strengthening of laboratory facility including
    establishment of mobile unit residual insecticidal spraying operations etc.
                                                                        (173-C(

          27. There is no reason to conclude that the Environmental Sub-group
    is not functioning effectively. The group which is headed by the Secretary,         H
      112                      SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.
"·
A Ministry of Environment and Forests is a high powered body whose work
      cannot be belittled merely on the basis of conjectures or surmises. 1174-F)

            DIRECTIONS

            I. Construction of the dam will continue as per the Award of the Tribunal.
                                                                    .         1225-G)
                                                                                         -
B
        2. As the Relief and Rehabilitation Sub-group has cleared the
  construction up to 90 meters, the same can be undertaken immediately.
                                                                                         ......
  Further raising of the height will be only pari passu with the implementation
  of the relief and rehabilitation and on the clearance by the Relief and
C Rehabilitation Sub-group. The Relief and Rehabilitation Sub-group will give
  clearance of further construction after consulting the three Grievances
  Redressal Authorities. 1226-B)

           3. The Environment Sub-group under the Secretary, Ministry of
     Environment & Forests, Government of India will consider and give, at each
D    stage of the construction of the dam, environment clearance before further
     construction beyond 90 meters can be undertaken. 1226-C)

           4. The permissfon to raise the dam height beyond 90 meters will be
     given by the Narmada Control Authority, from time to time, after it obtains
     the above-mentioned clearances from the Relief and Rehabilitation Sub-group
E    and the Environment Sub-group. (226-D)

           5. The States of Madhya Pradesh, Maharashtra and Gujarat are directed
     to implement the Award and give relief and rehabilitation to the oustees in
     terms of the packages offered by them and these States shall comply with any
     direction in this regard which is given either by the Narmada Control
F    Authority or the Review Committee or.the Grievances Redressal Authorities.
                                                                          (226-F)

           6. The Environment Sub-group will continue to monitor and ensure.that
     all steps are taken not only to project but to restore and improve the
     environment. [226-G)
G
           7. The Narmada Control Authority within four weeks shall draw up an
     Action Plan in relation to further construction and the relief and rehabilitation
     work to be undertaken. Such an Action Plan will fix a time frame so as to
     ensure relief and rehabilitation pari passu with the increase in the height of
     the dam. Each State shall abide by the terms of the action plan so prepared by
H    the Narmada Control Authority and in the event of any dispute or difficulty
                     NARMADA BACHAO ANDOLAN v. U.0.1.                            113

    arising, representation may be made to the Review Committee. However, each          A
    State shall be bound to comply with the directions of the Narmada Control


-
    Authority with regard to the acquisition of land for the purpose of relief and
    rehabilitation to the extent and within the period specified by the Narmada
    Control Authority. (226-H; 227-A-B)

          8. The Review Committee shall meet whenever required to do so in the          B
    event of there being any un-resolved dispute on an issue which is before the
    Narmada Control Authority. In any event the Review Committee shall meet at
    least once in three months so as to oversee the progress of construction of
    the dam and implementation of the relief and rehabilitation programmes. If
    for any reason serious differences in implementation of the Award arise and         C
    the same cannot be resolved in the Review Committee, the Committee may
    refer the same to the Prime Minister whose decision, in respect thereof, shall
    be final and binding on all concerned. [227-C-DI

          9. The Grievances Redressal Authorities will be at liberty, in case need
    arise, to issue appropriate directions to the respective States for. due            D
    implementation of the relief and rehabilitation programmes and in case of
    non implementation of its directions, the Grievances Redressal Authorities
    will be at liberty to approach the Review Committee for appropriate orders.
                                                                           (227-El

          10. Every endeavour shall be made to see that the project is completed        E
    as expeditiously as possible. [227-El

    Per Bharucha, J. (dissenting)

          1. When the Writ Petition was filed by the Petitioners, the process of
    relief and rehabilitation, such as it was, was going on. The Writ Petitioners       F
    were not guilty of any laches in that regard. When the public interest is so
    demonstrably involved, it would be against public interest to decline relief only
    on the ground that the Court was approached belatedly. (246-A-B]

           2. The catchment area treatment programme and the rehabilitation plans
    were required to be "so drawn as to be completed ahead of reservoir filling".       G
    What the clause as drawn required was that the catchment area treatment
    programme and the rehabilitation plans should be drawn in such a manner
    that the catchment area treatment and the rehabilitation works would be
    completed ahead ofimpoundment in the reservoir. This, plainly, was intended
    to offset, so far as was possible in the circumstances, the adverse effect of the
    impoundment of water in the reservoir upon the catchment and those who were         H
     114                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A required to be settled elsewhere. In fact, the impoundment began much before.
                                                                         (242-C-D)

           3.1. The environmental clearance was based on next to no data in regard
     to the environmental impact of the Project and was contrary to the terms of
     the then policy of the Union oflndia in regard to environmental clearances
                                                                                       --
B    and, therefore, no clearance at all. (241-CI

          3.2. Under its own policy, as indicated by the Guidelines of January, 1985
    issued by the Department of Environment and Forests, the Union of India was
    bound to give environmental clearance only after, (a) all the necessary data in
    respect of the environmental impact of the Project had been collected and
C   assessed; (b) the assessment showed that the Project could proceed; and (c)
    the environmental safeguard measures, and their cost, had been worked out.
                                                                             (242-H)

          3.3. The contemporaneous Notes prepared by the Ministry of Water
    Resources and the Ministry of Environment and Forests leave no manner of
D   doubt that the requisite data for assessment of the environment impact of the
    Project was not available when the environmental clearance thereof was
    granted. The Notes make clear that the studies, censuses, mapping of areas
    and field surveys for the collection of data for assessment of the environmental
    impact of the Project were likely to take a further 2 to 3 years. (241-A-CI
E        3.4. The conditions upon which the environmental clearance was given
    were that detailed surveys and studies would be carried out and the Narmada
    Control Authority would ensure that "environmental safeguard measures"
    were planned and implemented pari passu with the progress of work on the
    Project. What the environmental safeguards measures the Narmada Control
F   Authority was to ensure were, and what their cost would be, was not known
    when the environmental clearance was given. There was, therefore, no way in
    which this cost could be included in the cost of the Project, which was a
    requirement of the Guidelines of January, 1985 of the Department of
    Environment and Forests. [241-F-G)

G        3.5. The fact that the environmental clearance was given by the Prime
    Minister and not by the Ministry of Environment and Forests, as it would
    ordinarily have been done, makes no difference at all. (242-GI

           4. An adverse impact on the environment can have disastrous
    consequences for this generation and generations to come. This Court has
H   in its judgments on Article 2 I of the Constitution of India recognised this.
                   NARMADA BACHAO ANDOLAN v. U.0.1.                           115

    This Court cannot place its seal of approval on the project without first A
    ensuring that those best fitted tO do so have had the opportunity of gathering
    all necessary data on the environmentafimpact of the Project and of assessing
    it. They must then decide if environmental clearance to the project can be
    given, and, ifit can, what environmental safeguard measures have to be adopted,
    and their cost. (243-B)
                                                                                     B
          5. It should not be deemed that there is agreement to anything stated in
    the judgment of the majority for the reason that it has not been traversed in
    the present judgment. [246~C)

          DIRECTIONS
                                                                                     c
         1. The Environmental Impact Agency of the Ministry of Environment
    and Forests of the Union of India shall forthwith appoint a Committee of
    Experts in the fields mentioned in Schedule III of the Environmental Impact
    Assessment Notification, 1994. (246-D)


-         2. The Committee of Experts shall gather all necessary data on the
    environmental impact of the Project. They shall be free to commission or carry
    out such surveys and studies and the like as they deem necessary. They shall
                                                                                     D

    also consider such surveys and studies as have already been carried out.
                                                                           [246-E)
                                                                                     E
          3. Upon such data, the Committee of Experts shall assess the
    environmental impact of the Project and decide if environmental clearance to
    the Project can be given and, if it can what environmental safeguard measures
    must be adopted, and their cost. (246-F)

          4. In so doing, the Committee of Experts shall take into consideration     F
    the fact that the construction of the dam and other work on the Project has
    already commenced. (246-G)

          5. Until environmental clearance to the Project is accorded by the
    Committee of Experts as aforestated, further construction work on the dam
    shall cease. [246-HJ                                                             G
         6. The Grievance Redressal Authorities of the States of Gujarat, Madhya
    Pradesh and Maharashtra shall ensure that those ousted by reason of the
    Project are given relief and rehabilitation in due measure. (247-AJ

          7. When the project obtains environmental clearance each of the            H
    116                     .SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A Grievance Redressal Authorities of the States of Gujarat, Madhya Pradesh
    and Maharashtra shall, after inspection, certify, before work on the further
    construction of the dam can begin, that all those ousted by reason of the
    increase in the height of the dam by 5 meters from its present leYel have
    already been satisfactorily rehabilitated and also that suitable vacant land for
B   rehabilitating all those who will be ousted by the increase in the height of the
    dam by another 5 meters is already in the possession of the respective States.
                                                                         [247-8-C]

         8. This process shall be repeated for every successive proposed 5 mete'!"
    increase in the dam height. [247-D]
c         9. If for any reason the work on the Project, now or any time in the
    future, cannot proceed and the Project is not completed, all oustees who have
    been rehabilitated shall have the option to ~ontinue to reside wher~ they have
    been rehabilitated or to return to where they were ousted from, provided such
    place remains habitable, and they shall not be made at all liable in monetary
D   or other terms., on this account. (247-E]

          CIVIL ORIGINAL JURISDICTION : Writ Petition (C) No. 319 of I 994.

          (Under Article 32 of the Constitution of India)

                                           WITH
E
         W.P. (C) Nos. 345/1994 and 104/1997, SLP (C) No. 3608/1985, TC(C) No.
    3511995 and CA No. 6014/1994.

          Harish N. Salve, Solicitor General, Shanti Bhushan, M.G. Barot, Ashok
F   H. Desai, T.R. Andhyarujina, C.S. Vaidyanathan, Anoop G. Chaudhary, K.N.
    Shukla, Prashant Bushan, Sanjeev Kapoor, Narinder Verma, Ms. S. Divya,
    K.R.R. Pillai, E.C. Agrawala, Mahesh Agrawala, Rishi Agrawala, Pallav Sisodia,
    Tufail A. Khan, P. Parmeshwaran, S.N. Terdol. A.K. Srivastava, B.K. Prasad,
    Kamal Trivedi, Ms. H. Wahi, Pratesh Kapoor, Subrat Birla, T.M. Pitale, D.M.
    Nargolkar, S.K. Agnihotri, Ashok Kumar Singh, Sushi! Kr. Jain Addi. General
G   for State of Rajasthan, A. Misra, Ms. Anjali Doshi, Ms. Madhurima Tatia,
    Pallav Sisodia and A.P. Medh for the appearing parties.

          The Judgments of the Court were delivered by

          KIRPAL, J. Narmada is the fifth largest river in India and largest West
H flowing river of the Indian Peninsula. Its annual flow approximates to the
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                       117

combined flow of the rivers Sutlej, Beas and Ravi. Originating from the             A
Maikala ranges at Amarkantak in Madhya Pradesh, it flows Westwards over
a length of about 1312 km. before draining into the Gulf of Cam bay, 50 km.
West of Bharuch City. The first 1077 km. stretch is in Madhya Pradesh and
the next 35 km. stretch of the river forms the boundary between the States
of Madhya Pradesh and Maharasthra. Again, thoe next 39 km. forms the
boundary between Maharasthra and Gujarat and the last stretch of 161 km.            B
lies in Gujarat.

      The Basin area of this river is about l lac sq. km. The utilisation of this
river basin, however, is hardly about 4%. Most of the water of this peninsula
river goes into the sea. Inspite of the huge potential, there was hardly any
development of the Narmada water resources prior to independence.
                                                                                    c
       In 1946, the then Government of Central Provinces and Berar and the
then Government of Bombay requested the Central Waterways, Irrigation and
Navigation Commission (CWINC) to take up investigations on the Narmada
river system for basin-wise development of the river with flood control,            D
irrigation, power and extension of navigation as the objectives in view. The
study commenced in 1947 and most of the sites were inspected by engineers
and geologists who recommended detailed investigation for seven projects.
Thereafter in 1948, the Central Ministry of Works, Mines & Power appointed
an Ad~hoc Committee headed by Shri A.N. Khosla, Chairman, CWINC to
study the projects and to recommend the priorities. This Ad-hoc Committee           E
recommended as an initial step detailed investigations for the following projects
keeping in view the availability of men, materials and resources:

      l. Bargi Project

      2. Tawa Project near Hoshangabad
                                                                                    F
      3. Punasa Project and

      4. Broach Project

      Based on the recommendations of the aforesaid Ad-hoc Committee,
estimates for investigations of the Bargi, Tawa, Punasa (Narmadasagar) and          G
Broach Projects were sanctioned by the Government of India in March, 1949.

      The Central Water & Power Commission carried out a study of the
hydroelectric potential of the Narmada basin in the year 1955. After the
investigations were carried out by the Central Water & Power Commission,
the Navagam site was finally decided upon in consultation with the erstwhile        H
     118                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A   Government of Bombay for the construction of the dam. The Central Water
    & Power Commission forwarded its recommendations to the then Government
    of Bombay. At that time the implementation was contemplated in two stages.
    In Stage-I, "the Full Reservoir Level (hereinafter referred to as 'FRL') was
    restricted to 160 ft. with provision for wider foundations to enable raising of
B   the dam to FRL 300 ft. in Stage-II. A high level canal was envisaged in Stage-
    11. The erstwhile Bombay Government suggested two modifications, first the
    FRL of the dam be raised from 300 to 320 ft. in Stage-II and second the
    provision of a power house in the river bed and a power house at the head
    of the low level canal be also made. This project was then reviewed by a panel
    of Consultants appointed by the Ministry of Irrigation & Power who in a
C   report in 1960 suggested that the two stages of the Navagam dam as proposed
    should be combined into one and the dam be constructed to its final FRL 320
    ft. in one stage only. The Consultants also stated that there was scope for
    extending irrigation from the high level canal towards the Rann of Kutch.

          With the formation of the State of Gujarat on lst May, 1960, the Narmada
D   Project st~od transferred to that State. Accordingly, the Government of Gujarat
    gave an administrative approval to Stage-I of the Narmada Project in February,
    1961. The Project was then inaugurated by late Pandit Jawaharlal Nehru on
    5th April, 196 I. The preliminary works such as approach roads & bridges,
    colonies, staff buildings and remaining investigations for dam foundations
E   were soon taken up.

           The Gujarat Government undertook surveys for the high level canal in
     I 961. The submergence area survey of the reservoir enabled assessment of
     the storage capability of the Navagam reservoir, if its height should be raised
    beyond FRL 320 ft. The studies indicated that a reservoir with FRL + 460 ft.
F   would enable realisation of optimum benefits from the river by utilising the
    untapped flow below Punasa dam and would make it possible to extend
    irrigation to a further area of over 20 Iakh acres. Accordingly, explorations for
    locating a more suitable site in the narrower gorge ·portion were taken in hand
    and finally in November, 1963, site No. 3 was found to be most suitable on
    the basis of the recommendations of the Geological Survey of India and also
G   on the basis of exploration and investigations with regard to the foundation
    as well as construction materials available in the vicinity of the dam site.

          In November, 1963, the Union Minister of Irrigation- & Power held a
    meeting with the Chief Ministers of Gujarat and Madhya Pradesh at Bhopal.
H   As a result of the discussions and exchange of views, an agreement (Bhopal
                   NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                       119

          Agreement) was arrived at. The salient features of the said Agreement were:        A
                  (a) That the Navagam Dam should be built to FRL 425 by the
                  Government of Gujarat and its entire benefits were to be enjoyed by
'                 the State of Gujarat.
~·-

                  (b) Punasa dam (Madhya Pradesh) should be built to FRL 850. The
                                                                                             B
                  costs and power benefits of Punasa Power Project shall be shared in
                  the ratio I :2 between the Governments of Gujarat and Madhya Pradesh.
                  Out of the power available to Madhya Pradesh half of the quantum
                  was to be given to the State of Maharashtra for a period of 25 years
                  for which the State of Maharashtra was to provide a loan to the extent
                  of one-third the cost of Punasa Dam. The loan to be given _by the          c
                  State of Maharashtra was to be returned within a period of 25 years.

                 (c) Bargi Project was to be implemented by the State of Madhya
                 Pradesh, Bargi Dam was to be built to FRL 1365 in Stage I and FRL
                 1390 in Stage II and the Governments of Gujarat and Maharashtra
                 were to give a total loan assistance of Rs. I 0 crores for the same.        D
                 In pursuance of the Bhopal Agreement, the Government of Gujarat
          prepared a brief project report envisaging the Navagam Dam FRL 425 ft. and
          submitted the same to the Central Water and Power Commission under Gujarat
          Government's letter dated 14th February, 1964. Madhya Pradesh, however, did
          not ratify the Bhopal Agreement. In order to overcome the stalemate following      E
          the rejection of the Bhopal Agreement by Madhya Pradesh, a High Level
          Committee of eminent engineers headed by Dr. A.N. Khosla, the then Governor
          of Orissa, was constituted on 5th September, 1964 by the Government of
          India. The terms of reference of this Committee were decided by the Government
          of India in consultation with the States of Madhya Pradesh, Maharashtra and
                                                                                             F
          Gujarat. The same read as under:
    ...
    ~




                 (i) Drawing up of a Master Plan for the optimum and integrated
                 de\·elopment of the Narmada water resources.

                 (ii) The phasing of its implementation for maximum development of the
                 resources and other benefits.                                               G
                 (iii) The examination, in particular, ofNavagam and alternative projects,
                 if any, and determining the optimum reservoir level or levels.

                 (iv) Making recommendations of any other ancillary matters.

               The Khosla Committee submitted the unanimous report to the Government         H
     120                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A    of India in September, 1965 and recommended a Master Plan of the Narmada
     water development. In Chapter XI of the said Report, the Khosla Committee
     outlined its approach to the plan of Narmada development. An extract from
     this Chapter is reproduced below:

             "11.1 In their meeting from 14th to 18th December, 1964 at which the
B            State representatives were also present, the Committee laid down the
             following basic guidelines in drawing up the Master Plan for the
             optimum and integrated development of the Narmada water resources:-

              !. National interest should have over-riding priority. The plan should,
             therefore, provide for maximum benefits in respect of irrigation, power
C            generation, flood control, navigation etc. irrespective of State
             boundaries;

             2. Rights and interests of State concerned should be fully safeguarded
             subject to (I) above;

D            3. Requirements of irrigation should have priority over those of power;_

             Subject to the provision that suitable apportionment of water between
             irrigation and power may have to be considered, should it be found
             that with full development of irrigation, power production is unduly
             affected;

E            4. Irrigation should be extended to the maximum area within physical
             limits of command, irrespective of State boundaries, subject to
             availability of water; and in particular, to the arid areas along the
             international border with Pakistan both in Gujarat and Rajasthan to
             encourage sturdy peasants to settle in these border areas (later events
p            have confirmed ·the imperative need for this); and

            5. All available water should be utilised to the maximum extent possible
            for irrigation and power generation and, when no irrigation is possible,
            for power generation. The quantity going waste to the sea without
            doing irrigation or generating power should be kept to the un-avoidabie
            minimum."                                                                   <
G
           The Master Plan recommended by the Khosla Committee envisaged 12
    major projects to be taken up in Madhya Pradesh and one, viz., Navagam in
    Gujarat. As far as Navagam Dam was concerned, the Committee recommended
    as follows:-           ·

H          I. The terminal dam should be located at Navagam.
                        NARMADA BACHAO ANDOLAN v. U.O.I. [KIRPAL, J.]                       121
                    2. The optimum FRL of the Navagam worked out to RL 500 ft ..                   A
                   3. The FSL (Full Supply Level) of the Navagam canal at off-take should
              be RL 300 ft ..
      .--.,         4. The installed capacity at the river bed power station and canal power
              station should be 1000 mw and 240 mw respectively with one stand-by unit
              in each power station (in other words the total installed capacity at Navagam
                                                                                                   B
              would be 1400 mw).

                   The benefits of the Navagam Dam as assessed by the Khosla Committee
              were as follows:-

                      "(l) Irrigation of 15.80 lakh hectares (39.4 lakh acres) in Gujarat and      c
                      0.4 lakh hectares (l.00 lakh acres) in Rajasthan. In addition, the Narmada
                      waters when fed into the existing Mahi Canal sxstem would release
                      Mahi water to be diverted on higher contours enabling additional
                      irrigation of l.6 to 2.0 lakh hectares (4 to 5 lakh acres) approximately
                      in Gujarat and 3.04 lakh hectares (7.5 lakh acres) in Rajasthan.
                                                                                                   D
                      (2) Hydro-power generation of 95 l MW at 60% LF in the mean year
                      of development and 51 l MW on ultimate development of irrigation in
                      Gujarat, Madhya Pradesh, Maharashtra and Rajasthan."

                     The Khosla Committee stressed an important point in favour of high
              Navagam Dam, namely, additional storage. They emphasized that this additional        E
              storage will permit greater carryover capacity, increased power production
              and assured optimum irrigation and flood control and would minimise the
              wastage of water to the sea. The Khosla Committee also observed that
              instead of higher Navagam Dam as proposed, if Harinphal or Jalsindhi dams
              were raised to the same FRL as at Navagam, the submergence would continue
              to remain about the sarrie because the cultivated and inhabited areas lie
                                                                                                   F
              mostly above Harinphal while in the intervening 113 km (70 mile) gorge
              between Harinphal and Navagam, there was very little habitation or cultivated
              areas.

       -,,          The Khosla Committee report could not be implemented on account of
...           disagreement among the States. On 6th July, 1968 the State of Gujarat made
                                                                                                   G
              a complaint to the Government of India under Section 3 of the Inter-State
              Water Disputes Act, 1956 stating that a water dispute had arisen between the
              State of Gujarat and the Respondent States of Madhya Pradesh and
              Maharashtra over the use, distribution aild control of the waters of the Inter-
              State River Narmada. The substance of the allegation was that executive              H
     122                      SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A action had been taken by Maharashtra and Madhya Pradesh which had
    prejudicially affected the State of Gujarat and its inhabitants. The State of
    Gujarat objected to the proposal of the State of Madhya Pradesh to construct
    Maheshwar and Harinphal Dams over the river Nannada in its lower reach and

B
    also to the agreement reached between the States of Madhya Pradesh and
    Maharashtra to jointly construct the Jalsindhi Dam over Narmada in its course
                                                                                       L
                                                                                       '
    between the tWo States. The main reason for the objection was that if these
    projects were implemented, the same would prejudicially affect the rights and
    interests of Gujarat State by compelling it to restrict the height of the dam at
    Navag~ to FRL 210 ft. or less. Reducing the height of the dam would mean
    the permanent detriment of irrigation and power benefits that would be available
C   to the inhabitants of Gujarat and this would also make it impossible for Gujarat
    to re-claim the desert area in the Ranns of Kutch. According to the State of
    Gujarat, the principal matters in disputes were as under:
            (i)    The right of the State of Gujarat to control and use the waters
                   of the Narmada river on well-accepted principles applicable to
D                  the use of waters of inter-State rivers;
            (ii)   the right of the State of Gujarat to object to the arrangement
                   between the State of Madhya Pradesh and the State of
                   Maharashtra for the development of Jaisindhi dam;
            (iii) the right of the State of Gujarat to raise the Navagam dam to an
E                  optimum height commensurate with the efficient use ofNarmacia
                   waters including its control for providing requisite cushion for
                   flood control; and
            (iv) the consequential right of submergence of area in the States of
                 Madhya Pradesh and Maharashtra and areas in the Guja~t
F                State.

           Acting under Section 4 of the Inter-State Water Disputes Act, 1956, the
    Government of India constituted a Tribunal headed by Hon'ble Mr. Justice
    V. Ramaswamy, a retired Judge of this Court. On the same day, the Government
    made a reference of the water dispute to the Tribunal. The Reference being
G   in the following terms:

               "In exercise of the powers conferred by sub-section (I) of Section
           5 of the Inter-State Water Disputes Act, 1956 (33 of 1956), the Central
           Government hereby refers to the Narmada Water Disputes Tribunal for
           adjudication of the water dispute regarding the inter-State river,
H          Narmada, and the river-valley thereof, emerging from letter No. MIP-
          NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                        123
        5565/C- I 0527-K dated the 6th July, 1968, from the Government of . A
        Gujarat".

      On 16th October, 1969, the Government oflndia made another reference
of certain issues raised by the State of Rajasthan to the said Tribunal.

       The State of Madhya Pradesh filed a Demurrer before the Tribunal               B
stating that the constitution of the Tribunal and reference to it were ultra
vires of the Act. The Tribunal framed 24 issues which included the issues
relating to the Gujarat having a right to construct a high dam with FRL 530
feet and a canal with FSL 300 feet or thereabouts. Issues I (a), 1(b ), I (A), 2,3,
and 19 were tried as preliminary issues of law and by its decision dated 23rd
February, 1972, the said issues were decided against the respondents herein.          C
It was held that the Notification of the Central Government dated 16th October,
1969 referring the matters raised by the State of Rajasthan by its complaint
was ultra vires of the Act but constitution of the Tribunal and making a
reference of the water dispute regarding the Inter-State river Narmada was not
ultra vires of the Act and the Tribunal had jurisdiction to decide the dispute        D
referred to it at the instance of State of Gujarat. It further held that the
proposed construction of the Navagarrt project involving consequent
submergence of portions of the territories of Maharashtra and Madhya Pradesh
could form the subject matter of a "water dispute"· within the meaning of
Section 2(c) of the 1956 Act. It also held that it had the jurisdiction to give
appropriate direction to Madhya Pradesh and Maharashtra to take steps by              E
way of acquisition or otherwise for making submerged land available to
Gujarat in order to enable it to execute the Navagam Project and the Tribunal
had the jurisdiction to give consequ~nt directions to Gujarat and other party
States regarding payment of compensation to Maharashtra and Madhya
Pradesh, for giving them a share in the beneficial use of Navagam dam, and            F
for rehabilitation of displaced persons.

      Against the aforesaid judgment of the Tribunal on the preliminary
issues, the States of Madhya Pradesh and Rajasthan filed appeals by special
leave to this Court and obtained a stay of the proceedings before the Tribunal
to a limited extent. This Court directed that the proceedings before the              G
Tribunal should be stayed but discovery, inspection and other miscellaneous
proceedings before the Tribunal may go on. The State of Rajasthan was
directed to participate in these interlocutory proceedings.

      It appears that on 31.7.1972, the Chief Ministers of Madhya Pradesh,
Maharasthra, Gujarat and Rajasthan had entered into an agreement to                   H
     124                         SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A compromise the matters in dispute with the assistance of Prime Minister of
    India. This led to a formal agreement dated 12th July, 1974 being arrived_ at
    betwe_en the Chief Ministers of Madhya Pradesh, Maharashtra & Rajasthan
    and the Advisor to the Governor of Gujarat on a number of issues which the
    Tribunal otherwise would have had to go into. The main features of the
B   Agreement, as far as this case is concerned, were that the quantity of water
    in Narmada available for 75% of the year w_as to be assessed at 28 million acre
    feet and the Tribunal in determining the disputes referred to it was to proceed
    on _the basis of this assessment. The net available quantity of water for use
    in Madhya Pradesh and Gujarat was fo·be regarded as 27.25 million acre feet
    which was to be allocate~ .between the States. The height of the Navagam
C   Dam was to be fo:ed-by ·the Tribunhl after taking into consideration various
    contentions and submissions of the parties and if was agreed that the appeals
    filed in this Court by the States of Madhya Pradesh and Rajasthan would be
    withdrawn. It was also noted in this agreement that "development of Narmada
    should no longer be delayed in the best regional and nationat interests".
                             I

D         After the withdrawal of the appeals by the States of Madhya Pradesh
    and Rajasthan, the Tribunal proceeded to decide the remaining issues between
    the parties.

           On 16th August, 1978, the Tribunal declared it's Award under Section
     5(2) read with Section 5(4) of the Inter-State Water Disputes Act, 1956.
E    Thereafter, reference numbers 1,2,3,4 & 5of1978 were filed by the Union of
     India and the States of Gujarat, Madhya Pradesh, Maharashtra and Rajasthan
     respectively under Section 5(3) of the Inter-State Water Disputes Act, 1956.
     These references were heard by the Tribunal, which on 7th December, 1979,
    gave its final order. The' same was -published in the extraordinary Gazette by
     the Government of India on 12th December, 1979. In arriving at its final
F   decision, the issues regarding allocation, height of dam, hydrology and other
    related issues came to be s_ubjected to comprehensive and thorough
    examination by the Tribunal. Extensive studies were done by the Irrigation
    Commission and Drought Research Unit of India, Meteorological Department
    in matters of catchment area of Narmada Basin, major tributaries of Narmada
G   Basin, drainage area of Narmada Basin, climate, rainfall, variability ofrainfall,
    arid and semi-arid zones and scarcity area of Gujarat. The perusal of the report
    shows that the Tribunal also took into consideration various technical literature
    before giving its Award.
                                 AW ARD OF THE TRIBUNAL
H           The main parameters of the decision of the Tribunal were as under:
              NARMADA BACHAO ANDOLAN v. U.0.1. [KiRPAL, J.)                       125
            (A) DETERMINATION OF THE HEIGHT OF SARDAR SAROVAR                            A
            DAM

                The height of the Sardar Sarovar Darn was determined at FRL 455 ft ..
                The Tribt1:nal was ofthe view that the FRL +436 ft. was required for
                irrigation use alone. ·1n order to generate power throughout the year,
          . ·. it would be necessary to provide all the live storage above MDDL for      B
          ·· which an FRL · +453 ft. with MDDL +. 362 ft. ·would obtain gross
,,              capacity of 7.44 MAF. Therefore, the .Tribunal .was of the .y~ew that
              · FRL of the Sardar Sarovar Dam should be + 455 ft. providing gross
                storage of 7:70 MAf ..It directed the State qf Gujarat to took up and
          ... ·complete the constru~ti?.n of the _dam. . .                .
                     "'   ~,.:   .c   '   ""-.               f.
                                                                                         c
      ;
            (b) Geological and. SeismologiCal
                                 -
                                              aspects o(.the
                                                      .      dam site.

              The Tribunal accepted the recommend~tions of the Standing Cprnmittee
            · u~der Central Water &l?ower Commissi.on that there sh'ould.be seismic
              co-~ffi~ient of 0. i 0 g for the dam.
                                                                                         D
          ·. (c) RELIEF
                  -     '
                         AND.. REHABILITAION:
                                  ..      • r-



           The final Award contained dl~ecti.ons regarding submergence, land
     · ;'acquisition· and 'rehabilitation ofOispl~ced persons; The award d~fined
     ... ·the fu~arii~g of th.eland, oustee ~nd family: The Cujarat.Govemment
       · was: to pay to Madhya Pradesh and Maharasthra all C<?sts· including E
           compen's'ation, charges, expenses incurred by them for and in respect
          .of compuiso_ry acquisition of land. Further, the.Tribunai had provided-
           fOr rehabi!itation of oustees and civic amen"ities to be" provided to the
           oustees,· The award also provided. 'that if the State or' Gujarat was
         ·unable     to·.
                       re:~ettie' the ou;ste~s or thei ~ustees bei~g u.iiwilling to p
           occupy the area offered by the States, then .the oustees will be re- .
           settled by home .State and all expenses for this were to be borne by
           Gujarat. An important mandatory provision regarding rehabilitation
           was_ the one contained in Clause XI ~uh-clause IV(6)(ii) .which stated
           th~t no submergence of any area woufd take place unless the· oustees
           were renabilitated.        ·                 ·                            G
            (D) ALLOCATION OF THE NARMADA WATERS:

            The Tribunal determined th~ utilizable quantum of water of the Narmada
            at Sardar Sarovar Dam site on the basis -of 15% <l.ependability at 28
            MAF. It further ordered that out of the utilizable quantum of Narmada        H




                                                         '                                   '
     126                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A            water, the allocation between the States should be as under:
             Madhya Pradesh       : 18.25 MAF

             Gujarat              : 9.00 MAF

             Rajasthan            : 0.50 MAF
B            Maharasthra          : 0.25 MAF

            (E) PERIOD OF NON REVIEWABlLilY OF CERTAIN AWARD TERMS:

            The Award provided for the period of operation of certain clauses of
            the final order and decision of the Tribunal as being subject to review
c           only after a period of 45 years from the date of the publication of the
            decision of the Tribunal in the official gazette. What is important to
            note however is that the Tribunal's decision contained in clause II
            relating to determination of 75% dependable flow as 28 MAF was
            non-reviewable. The Tribunal decision of the determination of the
D           utilizable quantum of Narmada water at Sardar Sarovar Dam site on the
            basis of 75% dependability at 28 MAF is not a clause which is
                                                                                      •·
            included as a clause whose terms can be reviewed after a period of
            45 years.

          The Tribunal in its Award directed for the constitution of an inter-State
E   Administrative Authority i.e. Narmada Control Authority for the purpose of
    securing compliance with and implementation of the decision and directions
    of the Tribunal. The Tribunal also directed for constitution of a Review
    Committee consisting of the Union Minister for Irrigation (now substituted by
    Union Minister for Water Resources) as its Chairperson and the Chief Ministers
    of Madhya Pradesh, Maharashtra, Gujarat and Rajasthan as its members. The
F   Review Committee might review the decisions of the Narmada Control
    Authority and the Sardar Sarovar Construction Advisory Committee. The
    Sardar Saro var Construction Advisory Committee headed by the Secretary,
    Ministry of Water Resources as its Chairperson was directed to be constituted
    for ensuring efficient, economical and early execution of the project .
G         Narmada Control Authority is a high powered committee having the
    Secretary, Ministry of Water Resources, Government oflndia as its Chairperson,
    Secretaries in the Ministry of Power, Ministry of Environment and Forests,
    Ministry of Welfare, Chief Secretaries of the concerned four States as Members.
    In addition thereto, there are number of technical persons like Chief Engineers
H   as the members.
               NARMADA BACHAO ANDOLAN v. U.O.l. [KIRPAL, J.]                       127
            Narmada Control Authority was empowered to constitute one or more             A
     sub-committees and assign to them such of the functions and del~gate such
     of its powers as it thought fit. Accordingly, the Narmada Control Authority

--   constituted the following discipline based sub-groups:

             (i) Resettlement and Rehabilitation sub-group under the Chairmanship
             of Secretary, Ministry of Welfare;                                           B
             (ii) Rehabilitation Committee under Secretary, Minister of Welfare to
             supervise the rehabilitation process by undertaking visits to R&R
             sites and submergence villages.

             (iii) Environment Sub-group under the Chairmanship of Secretary,             C
             Ministry of Environment and Forests;

             (iv) Hydromet Sub-group under the Chairmanship of Member (Civil),
             Narmada Control Authority;

             (v) Power Sub-group under the Chairmanship of Member (Power)                 D
             Narmada Control Authority;

             (vi) Narmada main Canal Sub-committee under the chairmanship of
             Executive Member, Narmada Control Authority.

            The Award allocated the available water resources of the Narmada river        E
     between the four States. Based on this allocation, an overall plan for their
     utilisation and development had been made by the States. Madhya Pradesh
     was the major sharer of the water. As per the water resources development
     plan for the basin it envisaged in all 30 major dams, 135 medium dam projects
     and more than 3000 minor dams. The major terminal dam at Sardar Sarovar was
     in Gujarat, the remaining 29 being in Madhya Pradesh. Down the main course           F
     of the river, the four major dams were the Narmada Sagar (now renamed as
     Indira Sagar), Omkareshwar and Maheshwar all in Madhya Pradesh and Sardar
     Sarovar in Gujarat. Rajasthan was to construct a canal in its territory to utilize
     its share of 0.5 MAF.

             Relavant Details of the Sardar Sarovar Dam:                                  G
     As a result of the Award of the Tribunal, the Sardar Sarovar Dam and related
     constructions, broadly speaking, are to comprise of the following:

             (a) Main dam across the flow of the river with gates above the crest
             level to regulate the flow of water into the Narmada Main Canal.             H
     128                     SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A            (b) An underground River Bed Power through which a portion of the
             water is diverted to generate powe.r (1200 MW). This w~ter joins the
             main channel of the Narmada river downstream of the dam.

             (c) A saddle dam locate~ by the side of main reservoir thrqugh 'Yhich.      -
             water to the main canal.system flows.
B
             (d) A Canal Head Po~er House located at the toe of the .sad~le dain,
             through which -~he water .flowing to the ·maip can~I system .'is to be
             used to. geri~rate _power (250 MW). ·                  .      . ' '

             (e) The main canal'system-~nown a5 Narmada main canaf458 KM ..
C            long which is to carry away the ~ater ~eant for irrigation ~nd drinking .
             purposes to the canal systems of Gujarat and Rajasthan.

           Expected benefits from the project:

         The benefits expected to flow from the implementation of the Sardar
D   Sarovar Project had been estimated as follows:

          Irrigation: 17.92 lac hectare of land spread over 12 districts, 62 talukas
    and 3393 villages (75% of which is drought-prone areas) in Gujarat and 7~000
    hectares in the arid area~ of Barmer and Jallore districts. of Rajasthan. -

          Drinking Water facilities to 8215 viliages and 135 urban centers in
E   Gujarat both within and outside c'Ommand. These include 5825 .villages and ·.
    100 urban centers of Saurashtra and Kachchh which are _outside the command.
    In addition, 881 villages' affected due to high contents of fluoride will get
    potable water.

           Power Generation: 1450 Megawatt.
F
           Annual Employment Potential:

           7 lac man-years during construction

           6 lac man-years in post construction.
G         Protection against advancement of,little Rann of Kutch· and 'Raja8than ·.
    desert.                              ·· . '                     - .         ·

          Flood protection to riverine reac'1es measuring 30,000 hac, 210 villages
    including Bharuch city and 7.5 lac population.

H          Benefits to:
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                       129
      (a) Dhumkhal Sloth Bear Sanctuary.                                            A
      (b) Wild Ass Sanctuary in Little Rann of Kachchh
      (c) Black Buck Sanctuary at Velavadar.
      (d) Great Indian Bustard Sanctuary in Kachchh
      (e) Nat Sarovar Bird Sanctuary.
                                                                                    B
       Development of fisheries: Deepening of all village tanks of command
       which will increase their capacities, conserve water, will recharge ground
       water, save acquisition of costly lands for getting earth required for
       constructing canal banks and will reduce health hazard.

        Facilities of sophisticated communication system in the entire command.     C
      Increase in additional annual production on account of

                                                  (Rs. in crores)
     Agricultural production                         900                            D
      Domestic water supply                          100

      Power Generation                               440

      Total                                         1440

      POST A WARD CLEARANCES:                                                       E

      In order to meet the financial obligations, consultations had started in
1978 with the World Bank for obtaining a loan. The World Bank sent its
Reconnaissance Mission to visit the project site and carried out the necessary
inspection. In May, 1985, the Narmada Dam and Power Project and Narmada             F
Water Delivery and Drainage Project were sanctioned by the World Bank
under International Development Agency, credit No. 1552. Agreement in this
respect was signed with the Bank on I 0 .5 .1985 and credit was to be made
available from 6th January, 1986.

       With regard to the giving environmental clearance, a lot of discussion       G
took place at different levels between the Ministry of Water Resources and
the Ministry of Environment. Ultimately on 24th June, 1987 the Ministry of
Environment and Forests, Government of India accorded clearance subject to
certain conditions. The said Office Memorandum containing the environmental
clearance reads as follows:
                                                                                    H
    130                     SUPREME COURT REPORTS (2000) SUPP. 4 S.C.R.

A         "OFFICE MEMORANDUM

            Subject : Approval of Narmada Sagar Project, Madhya Pradesh and



B
            Sardar Sarovar Project, Gujarat from environmental angle.

           The Narmada Sagar Project, Madhya Pradesh and Sardar Sarovar
           Project Gujarat have referred to this Department for environmental
                                                                                      -
           clearance.

           2. On the basis of examination of details on these projects by the
           Environmental Appraisal Committee for River Valley Projects and
           discussions with the Central and State authorities the following details
C          were sought from the project authorities:

            I. Rehabilitation Master Plan
           2. Phased Catchment Area Treatment Scheme
           3. Compensatory Afforestation Plan
D          4. Command Area Development
           5. Survey of Flora and Fauna
           6. Carrying capacity of surrounding area.
          . 7. Seismicity and
E          8. Health Aspects
           3. Field surveys are yet to be completed. The first set of information
           has been made available and complete details have been assured to
           be furnished in 1989.

F          4. The NCA has been examined and its terms of reference have been
           amplified to ensure that environmental safeguard measures are planned
           and implemented in depth and in its pace of implementation pari passu
           with the progress of work on th.e projects.

           5. After taking into account all relevant facts the Narmada Sagar
G          Project, Madhya Pradesh and the Sardar Sarovar Project, Gujarat State
           are hereby accorded environmental clearance subject to the following
           conditions.

           (i)   The Narmada Control Authority (NCA) will ensure that
                 environmental safeguard measures are planned and implemented
H
         NARMADA BACHAO ANDOLAN v. U.O.I. [KIRPAL, J.]                     131
               pari passu with progress of work on project.                       A
        (ii)   The detailed surveys/studies assured will be carried out as per
               the schedule proposed and details made available to the
               Department for assessment.

        (iii) The Catchment Area treatment programme and the Rehabilitation       B
              plans be so drawn as to be completed ahead of reservoir filling.
        (iv) The Department should be kept informed of progress on various
             works periodically.

      6. Approval under Forest (Conservation) Act, 1980 for diversion of          C
forest land will be obtained separately. No. work should be initiated on forest
area prior to this approval.

       7. Approval from environmental and forestry angles for any other
irrigation, power or development projects in the Narmada Basin should be
obtained separately.                                                              D
                                                                 Sd/-
                                                            (S. MUDGAL)
                                                           DIRECTOR (IA)"

       In November, 1987 for monitoring and implementation of various             E
environmental activities effectively, an independent machinery of Environment
Sub-Group was created by Narmada Control Authority. This Sub-Group was
appointed with a view to ensure. that the environmental safeguards were
properly planned and implemented. This Sub-Group is headed by the Secretary,
Ministry of Environment and Forests, Government of India, as its Chairperson
and various other independent experts in various fields relating to environment   F
as its members.

      After the clearance was given by the Ministry of Environment and
Forests, the Planning Commission, on 5th October, 1988, approved investment
for an estimated cost of Rs. 6406 crores with the direction to comply with the
conditions laid down in the environment clearance accorded on 24th June,          G
1987.

      According to the State of Gujarat and Union of India, the studies as
required to be done by the O.M. dated 24th June, 1987, whereby environmental
clearance was accorded, have been undertaken and the requisite work carried       H
     132                     SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A out. The construction of the dam had commenced in 1987.
            In November, 1990 one Dr. B.D. Sharma wrote a letter to this Court for
     setting up of National Commission for Scheduled Castes and Scheduled
     Tribes including proper rehabilitation of oustees of Sardar Sarovar Dam. This
     letter was entertained and treated as a writ petition under Article 32 of the
B    Constitution being Writ Petition No. 120 I of 1990.       ·

          On 20th September, 1991, this Court in the said Writ Petition bearing No.
     1201 of 1990 gave a direction to constitute the Committee headed by Secretary
     (Welfare) to monitor the rehabilitation aspects of Sardar Sarovar Project.

c         The Narmada Bachao Andolan, the petitioner herein, had been in the
    forefront of agitation against the construction of the Sardar Sarovar Dam.
    Apparently because of this, the Government of India, Ministry of Water
    Resources vide Office Memorandum dated 3rd August, l 993 constituted a
    Five Member Group to be headed by Dr. Jayant Patil, Member, Planning
D   Commission and Dr. Vasant Gowarikar, Mr. Ramaswamy R. Iyer, Mr. L.C. Jain
    and Dr. V.C. Kulandaiswamy as its members to continue discussions with the
    Nannada Bachao Andolan on issues relating to the Sardar Sarovar Project.
    Three months time was given to this Group to submit its report.

          During this time, the construction of the dam continued and on 22nd
E   February, 19.94 the Ministry of Water Resources conveyed its decision
    regarding closure of the construction sluices. This decision was given effect
    to and on 23rd February, 1994 closure often construction sluices was effected.

          In April, 1994 the petitioner filed the present writ petition inter atia
F

                                                                                      -
    praying that the Union of India and other respondents should be restrained
    from proceeding with the construction of the dam and they should be ordered
    to open the aforesaid sluices. It appears that the Gujarat High Court had
    passed an order staying the publication of the report of the Five Member
    Group established by the Ministry of Water Resources. On 15th November,
    1994, this Court called for the report of the Five Member Group and the
G   Government of India was also directed to give its response to the said report.

          By order dated 13th December, 1994, this Court directed that the report
    of the Five Member Group be made public and responses to the same were
    required to be filed by the States and the report was to be considered by the
    Narmada Control Authority. This Report was discussed by the Narmada
H   Control Authority on 2nd January, 1995 wherein disagreement was expressed
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                    133
by the State of Madhya Pradesh on the issues of height and hydrology.            A
Separate responses were filed ir. this Court to the said Five Member Group
Report by the Government of India and the Governments of Gujarat and
Madhya Pradesh.

    On 24th January, 1995, orders were issued by this Court to the Five
Member Group for submitting detailed further report on the issues of             B
      (a) Height
      (b) Hydrology
      (c) Resettlement and Rehabilitation and environmental matters.
                                                                                 c
Dr. Patil who had headed the Five Member Group expressed his unwillingness
to continue on the ground of ill-health and on 9th February, 1995, this Court
directed the remaining four members to submit their report on the aforesaid
issues.
       On 17th April, 1985 the Four Member Group submitted its report. The       D
said report was not unanimous, unlike the previous one, and the Members
were equally divided. With regard to hydrology, Professor V.C. Kulandaiswamy
and Dr. Vasant Gowariker were for adoption of 75% dependable flow of 27
MAF for the design purpose, on the basis of which the Tribunal's Award had
proceeded. On the other hand, Shri Ramaswamy R. Iyer and Shri L.C. Jain
were of the opinion that for planning purposes, it would be appropriate to opt   E
for the estimate of23 MAF. With regard to the question relating to the height
of the dam, the views of Dr. Gowariker were that the Tribunal had decided FRL
455 ft. after going into exhaustive details including social, financial and
technical aspects of the project and that it was not practicable at the stage
when an expenditure of Rs. 4000 crores had been incurred and an additional       F
contract amounting to Rs. 2000 crores entered into and the various parameters
and features of the project having been designed with respect to FRL 455 ft.
that there should be a reduction of the height of the dam. The other three
Members proceeded to answer this question by first observing as follows:

       "We must now draw conclusions from the foregoing analysis, but a          G
       preliminary point needs to be made. The SSP is now in an advanced
       stage of construction, with the central portion of the dam already
       raised to 80 m.; the canal constructed upto a length of 140 Kms. ; and
       most of the equipment for various components of the project ordered
       and some of it already wholly or partly manufactured. An expenditure
       of over Rs. 3800 crores is said to have been already incurred on the      H
     134                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A           project; significant social costs have also been incurred in terms of
            displacement and rehabilitation. The benefits for which these costs
            have been and are being incurred have not materialised yet. In that
            situation, any one with a concern for keeping project costs under
            check and for ensuring the early commencement of benefits would
            generally like to accelerate rather than retard the completion of the
                                                                                           -
B           project as planned. lf any suggestion for major changes in the features
            of the project at this juncture is to be entertained at all, there will have
            to be the most compelling reasons for doing so."

          lt then addressed itself to the question whether there were any compelling
    reasons. The answer, they felt, depended upon the view they took on the
C   displacement and rehabilitation problem. The two views which, it examined,
    were, firstly whether the problem of displacement and rehabilitation was
    manageable and, if it was, then there would be no case of reduction in the
    height. On the other hand, if relief and rehabilitation was beset with serious
    and persistent problems then they might be led to the conclusion that there
D   should be an examination of the possibility of reducing submergence and
    displacement to a more manageable size. These three Members then considered
    the question of the magnitude of the relief and rehabilitation problem. After
    taking into consideration the views of the States of Madhya Pradesh and
    Gujarat, the three Members observed as follows:

E           "We find that the Government of India's idea of phased construction
            outlined earlier offers a practical solution; it does not prevent the FRL
            from being raised to 455' in due course ifthe necessary conditions are
            satisfied; and it enables the Government of Madhya Pradesh to take
            stock of the position at 436' and call a halt if necessary. We would,
            however, reiterate the presumption expressed in paragraph 3.9.2. above
F           namely that no delinking of construction from R&R is intended and
           that by "phased construction" the Government of India do not mean
           merely tiered construction which facilitates controlled submergence in
           phases. We recommend phased construction in a literal sense, that is
           to say, that at each phase it must be ensured that the condition of
G          advance completion of R&R has been fulfilled before proceeding to
           the next phase (i.e. the installation of the next tier of the gates). This
           would apply even t~ the installation of the first tier. "Judicious
           operation of the gates" (while necessary) cannot be a substitute for
           the aforesaid condition."

H   The possibility of further construction when the FRL 436 ft. was reached or
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                        135
a stoppage at that stage was left open by the Members. With regard to the             A
environment it observed that this subject had been by and large covered in
the first FMG report.
RIVAL CONTENTIONS

       On behalf of the petitioners, the arguments of Sh. Shanti Bhushan,             B
learned senior counsel, were divided into four different heads, namely, general
issues, issues regarding environment, issues regarding relief and rehabilitation
and issues regarding review of Tribunal's Award. The petitioners have sought
to contend that it is necessary for some independent judicial authority to
review the entire project, examine the current best estimates of all costs
(social, environmental, financial), benefits and alternatives in order to determine   C
whether the project is required in its present form in the national interest or
whether it net;<;is .to be re-structured/modified. It is further the case of the
petitioners that -no work should proceed till environment impact assessment
has been fully done and its implications for the projects viability being
assessed in a transparent and participa~ory manner. This can best be done,            D
it is submitted, as a part of the comprehensive review of the project.

       While strongly championing the cause of environment and of the tribals
who are to be ousted as a result of the submergence, it was submitted that
the environmental clearance which was granted in 1987 was without any or
proper application of mind as complete studies in that behalf were not available      E
and till this is done the project should not be allowed to proceed further. With
regard to relief and rehabilitation a number of contentions were raised with
a view to persuade this Court that further submergence should not take place
and the height of the dam, if at all it is to be allowed to be constructed, should
be considerably reduced as it is not possible to have satisfactory relief and
rehabilitation of the oustees as per the Tribunal's Award as a result of which        F
their fundamental rights under Article 21 would be violated.

       While the State of Madhya Pradesh has partly supported the petitioners
inasmuch as it has also pleaded for reduction in the height of the dam so as
to reduce the extent of submergence and the consequent displacement, the              G
other States and the Union of India have refuted the contentions of the
petitioners and of the State of Madhya Pradesh. While accepting that initially
the relief and rehabilitation measures had lagged behind but now adequate
steps have been taken to ensure proper implementation of relief and
rehabilitation at least as per the Award. The respondents have, while refuting
other allegations, also questioned_ the bona jides of the petitioners in filing       H
     136                      SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R. ·

A this petition. It is contended that the cause of the tribals and environment is
     being taken up by the petitioners not with a view to benefit the tribals but
     the real reason for filing this petition is to see that a high dam is not erected
     per se. It was also submitted that at this late stage this Court should not
     adjudicate on the various issues raised specially those which have been
B    decided by the Tribunal's Award.

            We first propose to deal with some legal issues before considering the
     various submissions made by Sh. Shanti Bhushan regarding environment,
     relief and rehabilitation, alleged violation of rights of the tribals and the need
     for review of the project.
c          LACHES

           As far as the petitioner is concerned, it is an anti-dam organisation and
    is opposed to the construction of the high dam. It has been in existence since
    1986 but has chosen to challenge the clearance given in 1987 by filing a writ
D   petition in 1994. It has sought to contend that there was lack of study
    available regarding the environmental aspects and also because of the
    seismicity, the clearance should not have been granted. The rehabilitation
    packages are dissimilar and there has been no independent study or survey
    done before decision to undertake the project was taken and construction
E   started~


           The project, in principle, was cleared more than 25 years ago when the
     foundation stone was laid by late Pandit Jawahar Lal Nehru. Thereafter, there
     was an agreement of the four Chief Ministers in 1974, namely, the Chief
     Min!sters of Madhya Pradesh, Gujarat, Maharashtra and Rajasthan for the
F    project to be undertaken. Then dispute arose with regard to the height of the
     dam which was settled with the award of the Tribunal being given in 1978.
     For a number of yea~s, thereafter, final clearance was still not given. In the
    meantime some environmental studies were conducted. The final clearance
    was not given because of the environmental concern which is quite evident.
    Even though complete data with regard to the environment was not available,
G   the Government did in 1987 finally give environmental clearance. It is thereafter
    that the construction of the dam was undertaken and hundreds of crores have
    been invested before the petitioner chose to file a writ petition in 1994
    challenging the decision to construct the dam and the clearance as was given.
    In our opinion, the petitioner which had been agitating against the dam since
H   1986 is guilty of latches in not approaching the Court at an earlier point of
           NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      137
time.                                                                                A
      When such projects are undertake1_1 and hundreds of crores of public
money is spent, individual or organisations in the garb of PIL cannot be
permitted to challenge the policy decision taken after a lapse of time. It is
against the national interest and contrary to the established principles of law
that decisions to undertake developmental projects are permitted to be               B
challenged after a number of years during which period public money has
been spent in the execution of the project.

       The petitioner has been agitating against the construction of the dam
since 1986, before environmental clearance was given and construction started.
It has, over the years, chosen different paths to oppose the dam. At it's            C
instance a Five Member Group was co~stituted, but it's report could not
result in the stoppage of construction pari passu with relief and rehabilitation
measures. Having failed in it's attempt to stall the project the petitioner has
resorted to court proceeding:; by filing this writ petition long after the
environmental clearance was given and construction started. The pleas relating       D
to height of the dam and the extent of submergence, environment studies and
clearance, hydrology, seismicity and other issues, except implementation of
relief and rehabilitation, cannot be permitted to be raised at this belated stage.

       This Court has entertained this petition with a view to satisfy itself that
there is proper implementation of the relief and rehabilitation measurers at         E
least to the extent they have been ordered by the Tribunal's Award. In short
it was only the concern of this Court for the protection of the fundamental
rights of the oustees under Article 21 of the Constitution of India which led
to the entertaining of this petition. It is the Relief and Rehabilitation measures
that this Court is really concerned with and the petition in regard to the other
issues raised is highly belated. Though it is, therefore, not necessary to do        F
so, we however presently propose to deal with some of the other issues
raised.

A WARD-BINDING ON THE STATES

        It has been the effort on the part of the petitioners to persuade this       G
Court to decide that in view of the difficulties in effectively implementing the
Award with regard to relief and rehabilitation and because of the alleged
adverse impact the construction of the dam will have on the environment,
further construction of the dam should not be permitted. The petitioners
support the contention on behalf of the State of Madhya Pradesh to the effect        H
    138                      SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.
                                                                                           \.
A that the height of the dam should be reduced in order to decrease the number
    of oustees. In this case, the petitioners also submit that with regard to
    hydrology, the adoption of the figure 27 MAF is not correct and the correct
    figure is 23 MAF and in view thereof the height of the dam need not be 455
    feet.                                                                              ~


B          The Tribunal in this Award has decided a number of issues which have
    been summarised hereinabove. The question which arises is as to whether it
     is open to the petitioners to directly or indirectly challenge the correctness
    of the said decision. Briefly stated the Tribunal had in no uncertain terms
    come to the conclusion that the height of the dam should be 455 ft. It had
C    rejected the contention of the State of Madhya Pradesh for fixing the height
    at a lower level. At the same time in arriving at this figure, it had considered
    the relief and rehabilitation problems and had issued directions in respect
    thereof. Any issue which has been decided by the Tribunal would, in law, be
    binding on the respective states. That this is so has been recently decided
    by a Constitution Bench of this Court in The State of Karnataka v. State of
D   Andhra Pradesh and others, (2000) 3 Scale 505. That was a case relating to
    a water dispute regarding inter-State river Krishna between the three riparian     .--
    States and in respect of which the Tribunal constituted under the Inter-State
    Water Disputes Act, 1956 had given an Award. Dealing with the Article 262
    and the scheme of the Inter-State Water Disputes Act, this Court at page 572
E   observed as follows:

           "The inter-State Water Disputes Act having been framed by the
           Parliament under Article 262 of the Constitution in a complete Act by
           itself and the nature and character of a decision made thereunder has
           to be understood in the light of the provisions of the very Act itself.
F          A dispute or difference between two or more State Governments
           having arisen which is a water dispute ~nder Section 2(C) of the Act
           and complaint to that effect being made to the Union Government
           under Section 3 of the said Act the Central Government constitutes
           a Water Disputes Tribunal for the adjudication of the dispute in
           question, once it forms the opinion that the· dispute cannot be settled
G          by negotiations. The Tribunal thus constituted, is required to
           investigate the matters referred to it and then forward to the Central
           Government a report setting out the facts as found by him and giving
           its decision on it as provided under sub-Section (2) of Section 5 of
           the Act. On consideration of such decision of the Tribunal if the
H          Central Government or any State Government is of the opinion that
          NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                       139

        the decision in question requires explanation or that guidance is A
        needed upon any 'point not originally referred to the Tribunal then ·
        within three months from the date of the decision, reference can be
        made to the Tribunal for further consideration and the said Tribunal
        then forwards to the Central Government a further report giving such
        explanation or guidance as it deems fit. Thereby the original decision B
        of the Tribunal is modified to· the extent indicated in the further
        decision as provided under Section 5(3) of the Act. Under Section 6
        of ,the Act the Central Government is duty bound to publish the
        decision of the Tribunal in the ·official Gazette whereafter the said
        decision becomes final and binding on the parties to·the dispute and
        has to be given effect to, by them. The language of the provisions C
        of Section 6 is clear and unambiguous and unequivocally indicates
        th.at it is only the decision of the Tribunal which is required to be
        published in the Official Gazette and on such publication that decision
        becomes final and binding on the parties."

Once the Award is binding on the States, it will not be open to a third party        D
like. the petitioners to. challenge the correctness thereof. In terms of the
Award, the ~tate of Gujarat has a right to construct a dam upto the height
of 455 ft. and, at-the same time, the oustees have a right to demand relief and
re-settlement as directed in the Award. We, therefore, do not propose to deal
with any contention which, in fact, seems to challenge the correctness of an         E
Issue decided by the Tribunal.

GENERAL ISSUES RELATING TO DJS-PLACEMENT OF TRIBALS AND
ALLEGED VIOLATION OF THE RIGHTS UNDER ARTICLE 21 OF THE
CONSTITUTION:

The submission of Sh. Shanti Bhushan, l~arned senior counsel for the                 F
·petitioners was that the forcible displacement of tribals and other marginal
farmers from their land and other sources of livelihood for a project which was
not in the national or public interest was a violation of their fundamental
rights under Article 2.1 of the Constitution of India read with ILO Convention
 107 to which India· is a signatory. Elaborating this contention, it was submitted   G
that this Court had held in a large numBer of cases that international treaties
and covenants could be read into the domestic law of the country and could
be used by the courts to elucidate the interpretation of fundamental rights
guaranteed by the Constitution. Reliance in support of this contention was
placed on Gramaphone Co. of India Ltd. v. B.B. Pandey, [1984] 2 SCC 534,
PUCL v. Union ofIndia, [ 1997] 3 SCC 433 and CERC v. Union of India, [ 1995)         H
     140                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

 A 3 SCC 42. In this connection, our attention was drawn to the ILO Convention
    l 07 which stipulated that tribal populations shall not be removed from their
    lands without their free consent from their habitual territories except in
    accordance with national laws and regulations for reasons relating to national
    security or in the interest of national economic development. It was further
B stated that the said Convention provided that in such cases where removal
   of this population is necessary as an exceptional measure, they shall be
    provided wi.th lands of quality at least equal to that of lands previously
   occupied by them, suitabl~ to provide for their present needs and future
   development. Sh. Shanti Bhushan further contended that while Sardar Sarovar
   Project will displace and have an impact on thousands of tribal families it had
C not been proven that this displacement was required as an exceptional measure.
   He further submitted that given the seriously flawed assumptions of the
   project and the serious problems with the. rehabilitation and environmental
   mitigation, it could not be said that the project was in the best national
   interest, It was also submitted that the question arose whether the Sardar
   Sarovar project .could be said to be in the national and public interest in view
D of its current best estimates of cost, benefits and evaluation of alternatives
   and specially in view of the large displacement of tribals and other marginal
   farmers involved in the project. Elaborating this contention,' it "was contended
   that serious doubts had been raised about the benefits of the project - the
   very rationale which was sought to justify the huge displacement and the
E massive environmental impacts etc. It was contended on· behalf of the
  petitioners that a project which was sought to be' justified on the grounds of
  providing a permanent solution to water problems of the drought prone areas
  of Gujarat would touch only the fringes of these areas, namely, Saurashtra and
  Kutch and even this water, which was allocated on paper, would not really
  accrue due to host of reasons. It was contended that inspite of concentrating
F on small scale decentralized measures which. were undertaken on a large scale
  could address the water problem of these drought prone areas. Huge portions
  of the State resources were being diverted to the Sardar Sarovar Project and
  as a result the small projects were ignored and the water problem in these
  areas persists. It was submitted that the Sardar Sarovar Project. could be
G restructured to minimise the displacement. .
          Refuting the aforesaid arguments, it has been submitted on behalf of
    the Union of .India and the State of Gujarat that the petitioners have given
    a highly exaggerated picture of the submergence and other impacts of this
    project. It was also submitted that the petitioner's assertion that there was
H   large-scale, re-location and uprooting of tribals 'was not factually correct.
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.)                         141

According to the respondents, the project would affect only 245 villages in A
Gujarat, Maharashtra and Madhya Pradesh due to pondage and backwater
effect corresponding to I in I 00 year flood. The State-wise break up of
affected villages and the number of project affected families (PAFs) shows
that only four villages would be fully affected (three in Gujarat and one in
Madhya Pradesh) and 241 would be partially affected (16 in Gujarat, 33 in B
Maharasthra and 192 in Madhya Pradesh). The total project affected families
who would be affected were 40827. The extent of the submergence was
minimum in the State of Madhya Pradesh. The picture of this submergence
as per the Government of Madhya Pradesh Action Plan of I 993 is as follows:

       "Abadi will be fully submerged in 39 villages and partially in 116              C
       villages, agricultural land will be affected upto l 0% in 82 villages, l I
       to 25% in 32 villages, 26 to 50% in 30 villages, 51 to 75% in 14 villages,
       76 to 90% in 4 villages and I 00% in only 1 village. In 21 villages, only
       abadi will be affected and Government land only in 9 villages. Thus,
       in most of the villages, submergence is only partial."
                                                                                       D
      The submergence area of the SSP can be divided into two areas:
       (i) Fully tribal, hilly area covering the initial reach of about 105 villages
       with mainly subsistence economy. It includes 33 villages of
       Maharasthra, 19 of Gujarat and about 53 of Madhya Pradesh~ .
       (ii) Mixed population area in the plains ofNimad, with a well developed         E
       economy and connected to the mainstream. This area includes about
       140 villages in Madhya Pradesh.

These two areas have quite different topographic and habitation features
which result in totally different types of submergence impacts. The state of
the hilly area to be affected by its submergence and where most of the tribal          F
population exists is described by the Government of Madhya Pradesh Action
Plan, 1993 as follows:

       "The Narmada flows in hilly gorge from the origin to the Arabian Sea.
       The undulating hilly terrain in the lower submergence area of Sardar G
       Sarovar Project exhibit naked hills and depleted forests. Even small
       forest animals area very rarely seen because of lack of forest cover
       and water. The oft quoted symbiotic living with forests is a misnomer
       in this area because the depleted forests have nothing to offer but
       fuel wood. Soil is very poor mostly disintegrated, granite and irrigation
       is almost nil due to undulating and hilly land. Anybody visiting this H
     142                      SUPREME COURT REPORTS. [2000) SUPP. 4 S.C.R.

A            area finds the people desperately sowing even in the hills with steep
             gradient. Only one rain fed crop of mostly maize is sown and so there
             is no surplus economy.

             PAPs inhabiting these interior areas find generous rehabilitation and
             resettlement packages as a means to assimilate in the mainstream in
B            the valley."

           In 193 vi II ages of Madhya Pradesh to be affected by the project, a very
    high proportion of the houses would be affected whereas the land submergence
    was only 14. l %. The reason for this is that the river be4 is a deep gorge for
C about 116 km. upstream of the dam and as a result the reservoir will be long
    (214 km), narrow (average width of 1.77 km) and deep. The result of this is
    that as one goes further upstream, the houses on the river banks are largely
    affected "'.l'hile agricultural land which is at a distance from the river banks is
    spared. A majority of33014 families of Madhya Pradesh (which would include
    15018 major sons) would lose only their houses and not agricultural lands
D would be required to be resettled in Madhya Pradesh by constructing new
    houses in the new abadi. According to the Award, ag'ricultural land was to
  . be allotted-only ifthe project affected families lost 25% or more of agricultural
    land and on this basis as per the Government of Madhya Pradesh, only 830
    project affected families of Madhya Pradesh were required to be allotted
E agricultural land in Madhya Pradesh.
           According to'the Government of Gujarat the tribals constituted bulk of
     project affected families who would be affected by the dam in Gujarat and
     Maharasthra, namely, 97% and 100% respectively. Out of the oustees of
     project affected families of Madhya Pradesh, tribals constituted only 30%
F    while 70% were non-tribals. The total number of tribal project affected families
     were 17725 and out of these, 9546 are already re~settled .. It was further the
    case of the respondents that in Madhya Pradesh the agricultural land of the
    tribal villages was affected on an average to the extent of28% whereas in the
    upper reaches i.e. Nimad. where the agriculture was advanced, the extent of
G   submergence, on an average, was only 8.5%. The surveys conducted by
    HMS Gour University (Sagar), the Monitoring and Evaluation Agency set up
    by the Government of Madhya Pradesh, reveal that the major resistance to
    relocation was from the richer, non-tribal families ofNimad who feared shortage
    of agriculture labour if the landless labourers from the areas accepted re-
    settlement. In the Bi-Annual report, 1996 of HMS Gour University, Sagar, it
H   was observed as follows:
          NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                          143
        "The pre-settlement study of submerging villages has revealed many              A
        startling realities. Anti-dam protagonists presents a picture that tribals
        and backward people are the worst sufferers of this kind of
        development project. This statement is at least not true in case of the
        people of these five affected villages. Though, these villages comprise
        a significant population of tribals and people of weaker sections, but          B
        majority of them will not be a victim of displacement. Instead, they will
        gain from shifting. T~e present policy of compensation is most
        beneficial for the lot of weaker section. These people are living either
        as labourers or marginal farmers. The status of oustee will make them
        the owner of two hectares of land and a house. In fact, it is the land-
        owning class which is opposing the construction of dam by playing               C
        the card oftribals and weaker ~ections. The land-owners are presently
        enjoying the benefit of cheap labour in this part of the region.
        Availability of cheap labour is boon for agricultural activities. This
        makes them to get higher tetum with less inputs."

It is apparent that the tribal population affected by the submergence would             D
have to move but the rehabilitation package was such that the living condition
would be much better than what it was before there. Further more though 140
villages of Madhya Pradesh would be affected in the plains of Nimad, only
8.5% of the agricultural land of these villages shall come under submergence
due to SSP and as such the said project shall have only a marginal impact               E
on the agricultural productivity of the area.

      While accepting the legal proposition that International Treaties and
Covenants can be read into the domestic laws of the country the submission
of the respondents was that Article 12 of the ILO Convention No. 107
stipulates that "the populations concerned shall not be removed without their           F
free consent.from their habitual territories except in accordance. with national
laws and regulations relating to national security, or in the interest of national
economic development or of the health of the said populations".

      The said Article clearly suggested that when the removal of the tribal
~0pulation is necessary as an exceptional measure, they shall be provided               G
with land of quality atleast equal to that of the land previously occupied by
them and they shall be fully compensated for any resulting loss or injury. The
rehabilitation package contained in the Award of the Tribunal as improved
further by the State of Gujarat and the other States prima facie shows that
the land required to be allotted to the tribals is likely to be equai, if not better,   H
      144                      SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

 A than what they had owned.
            The allegat.ion that the said project was not in the national or public
      interest is not correct" seeing to the need of water for burgeoning population
     which is most critical and important. The population of India, which is now
     one billion, is expected to reach a figure between 1.5 billion and 1.8 billion in
 B   the year 2050, w~mld necessitate the need of2788 billion cubic meter of water
     annually in India to be above water stress zone and 1650 billion cubic metre
     to avoid being water scarce country. The i;tlain source of water in India is
     rainfall which occurs in about 4 months in a year and the temporal distribution
     of rainfall is so un~ven that the annual averages have very little significance
 C   for all practical purposes. According to the Union of India, one third of the
     country is always under threat of drought not necessarily due to deficient
     rainfall but many times due to its uneven occurrence. To feed the increasing
     population, more food grain is required and effort has to be made to provide
     safe drinking water, which, at present, is a distant reality for most of the
     population specially in the rural areas. Keeping in view the need to augment
 D   water supply, it is necessary that water storage capacities have to be increased
     adequately in order to ward off the difficulties in the event of monsoon failure
     as well as to meet the dC?mand during dry season. It is estimated that by the
     year 2050 the country needs to create storage of at least 600 billion cubic
     meter against the existing storage of 174 billion cubic meter.
 E          Dams play a vital role in providing irrigation for food security, domestic
     and industrial water supply, hydroelectric power and keeping flood waters
     back. On full. development, the Narmada has a potential of irrigating over 6
     million hectares of land and generating 3000 mw of power. The present stage
     of developm~nt is very low with only 3 to 4 Maf of waters being used by the
·F    party States for irrigation and drinking water. against 28 Maf availability of
     water at 75% dependability as fixed by NWDT and about I 00 MW power
     developed. 85% of the waters are estimated as flowing waste to sea. The
     project will· provide safe and c'lean drinking water to 8215 villages and 135
     towns in Gujarat and 131 villages in desert areas of Jalore district of Rajasthan,
G    though against these only 241 villages are getting submerged partially and
     only 4 villages fully due to the project.

         The cost and benefit of the project were examined by the World Bank
     m 1990 and the following passage speaks for itself:

H            "The argument in favour of the Sardar Sarovar Project is that the
             NARMADA BACHAO ANOOLAN v. U.0.1. [KIRPAL, .I:)                   145
            benefits are so large that they substantially outweigh the ·costs of the A
            immediate human and environmental disruption. Without the dam, the
            long term costs for people would be much greater and lack of an
            income source for future generations would put increasing pressure
            on the environment. If the waters of the Narmada river continue to
            flow to the sea unused there appears to be no alternative to escalatin~ B
            human deprivation, particularly in the dry ateas of Gujarat. The project
           ·has the potential to feed as many as 20 million people, provide domestic
            and industrial water for about 30 million, employ about 1 million, and
            provide valuable peak electric power in an area with high unmet power
            demand (farm pumps often get only a few hours power per day). In
            addition, recent research shows. substantial economic "multiplier" C
            effects (investment and employment triggered by development) from
            irrigation development. Set against the futures of about 70,000 project.
            affected people, even without the multiplier effect, the ratio of
            beneficiaries to affected persons is well over 100: !.. .. "

    There is merit in the contention of the respondents that there would be a D
    positive impact on preservation of ecology as a result from the project. The
    SSP would be making positive contribution for preserv~tion of environment
    in several ways. The project by taking water to drought-prone and arid parts
    ofqujarat and Rajasthan would effectively arrest ecological degradation which .
    was returning to make these areas inhabitable due to salinity ingress,
    advancement of desert, ground water depletion, fluoride and nitrite affected E
    water and vanishing green cover. The ecology of water scarcity areas is under
    stress and transfer of Narmada water to these areas will lead to sustainable
    agriculture and spread of green cover. There will also be improvement of
    fodder availability which will reduce pressure on biodiversity and vegetation.

•   The SSP by generating clean eco-friendly hydropower will save the air pollution F
    which would otherwise take place by thermal generation power of similar
    capacity.

          The displacement of the tribals and other persons would not per se
    result in the violation of their fundamental or other rights. The effect is to see
    that on their rehabilitation at new locations they are better off than what they G
    were. At the rehabilitation sites they will have ·more and better amenities than
    which they enjoyed in their tribal hamlets. The gradual assimilation in the ..
    main stream of the society will lead to betterment and progress.

    ENVIRONMENTAL ISSUES
         The four .issues raised under this head by Sh. Shanti Bhushan are as       H
     146                        SUPREME COURT REPORTS [2000] SU.PP. 4 S.C.R.

 A   unCler:

               I.    Whether the execution of a large project, having diverse and far
                     reaching environm.ental impact, without the proper study and
                     understanding of its environmental impact and without proper
                     planning of mitigative measures is a violation of fundamental
B                    rights of the affecteq people guaranteed under Article 21 of the
                     Constitution of India ?

               II.   Whether the diverse environmental impacts of•he Sardar Sarovar
                     Project ha.ve been properly stl}died and ·understood ?
                                                                                        ..
c              Ill. Whether any independent authority· has examined the
                    environmental costs and mitigative measures to. ~e undertaken
                    in order to decide whether the environmental costs are acceptable
                    and mitigative measures practical ? .
                                       '
               IV.   Whether the environmental conditions imposed .by the Ministry
D                    of Environment have been violated and if so, what is the.legal
                     effect of the violations ?

           It was submitted by Sh. Shanti Bhushan that a large project having·
     diverse and far reaching environmental impacts i!1 the concerned States wotild
     require a proper study and understanding of the environmental impacts. He
E contended that the study and planning with regard to environmental impacts
     must precede construction. According. to Sh. Shanti Bhoshan, when the
     envirpnmental clearance was given in 1987, proper study and analysis of the
  · environmental impacts and mitigative measures, which were required to be
    taken, were not available and, therefore, this clearance was not valid. The
    decision to construct the dam was stated to be. political one and was not a
F considered decision after taking into account the environmental impac!s of
    the project. The execution of SSP without a comprehensive assessment and
    evaluation ·of its environmental impacts and a decision regarding its
    acceptability was alleged to be a violation of the rights of the affected people
    under Article 21 of the Constitution of India. It was further submitted that no
G independent aµthority has examined vehemently the envirnnmental costs and
    mitigative measurers to be unpertaken in order to decide whether the
    environmental costs are acceptable and mitigative measures practical. With
    regard to tile enviro'!mental clearance given in June, 1987, the submission of·
 · Sh. Shanti Bhushan was that this was the conditional clearance and· the
   ·conditions imposed by the Ministry of Environment and Forests had been
H violated. The letter granting clearance, it was submitted, disclosed that even
              NARMADA·BACHAO A!NDOLAN v: U.0.1. [KIRPAL, J.]                      147

    the basic minimum studies and plans required for the environmental impact            A
    assessment had not been done. Further more it was contended that in the
    year 1990, as the deadline for completion of the studies was not met, the
    Ministry of Environment and Forests had declared that the clearance had
    lapsed. The Secretary of the said Ministry had requested the Ministry of
    Water Resources to seek extension of the clearance but ultimately no extension       B
    was sought or given and the studies and action plans continued to lag to the

-   extent that there was no comprehensive environmental impact-assessment of
    the project, proper mitigation plans were absent and the costs of the
    environmental measures were neither fully assessed nor included in the project
    costs. In support of his contentions, Sh. Shanti Bhushan relied upon. the
    report of a Commission called the Independent Review or the Morse                    C
    Commission. The said Commission had been set up by the World Bank and
    it submitted its report in June, 1992. In its report, the Commission had adversely
    commented on practically all· aspects of the project and in relation to
    environment, it was stated as under:

            "Important assumptions upon which the projects are based are now             D
            questionable or are known to be unfounded. Environmental and social
            trade-off have been made, and continue to be made, without a full
            understanding of the consequences. As· a result, benefits tend to be
            over-stated, while social and environmental costs are frequently
            understated. Assertions have been substituted for analysis.                  E
            We think that the Sardar Sarovar Projects as they stand are flawed,
            that resettlement and rehabilitation of all those displaced by the
            projects· is not' possible under the prevailing circumstances, and that
            the environmental impacts of the projects have n.ot been properly
            considered or a~equately addressed.                                          F
            The history of environmental aspects of Sardar Sarovar is a history
            of non-compliance. There is no comprehensive impact statement. The
•           nature and magnitude of environmental problems and solutions remain
            elusive."
                                                                                         G
          Sh. Shanti Bhushan submitted that it had become necessary for some
    independent judicial authority to review the entire project, examine the·current
    best estimates of all costs (social, environmental, financial), benefits and
    alternatives ·in order to determine whether the project is required in its·present
    form in the national interest, or whether it needs to be restructured/modified.      H
     148                     SUPREME COURT REPORTS (2000) SUPP. 4 S.C.R.

A          Sh. Shanti Bhushan further submitted that environmental impacts of the
     projects were going to be massive and full assessment of these impacts had
     not been done. According to him the latest available studies show that
     studies and action plans had not been completed and even now they were
     lagging behind pari passu. It was also contended that ntere listing of the
B    studies does not imply that everything is taken care of. Some of the studies
     were of poor quality and based on improper data and no independent body.
     had subjected these to critical evaluation.

     RE: ENVIRONMENTAL CLEARANCE:

          As considerable stress was laid by Sh. Shanti Bhushan challenging the
C   validity of the environmental clearance granted in 1987 inter alia on the
    ground that it was not preceded by adequate studies and .it was not a
    considered opinion and there was non-application of mind while clearing the
    project, we first propose to deal with the contention.

           The events after the Award and upto the environmental clearance granted
D   by the Government vide its letter dated 24th June, 1987 would clearly show
    that some studies, though incomplete, had been made with regard to different
    aspects of the environment. Learned counsel for the respondents stated that
    in fact on the examination of the situation, the claim made with regard to the
    satisfactory progress was not correct. In order to carry out the directions in
E   the Award about the setting up of an authority, the Inter-State Water Disputes
    Act, 1956 was amended and Section 6-A was inserted to set out how a
    statutory body could be constituted under the Act. On 10th September, 1980
    in exercise of the· powers conferred by Section 6-A of the Act the Central
    Government framed a scheme, constituted the Narmada Control Authority to
    give effect to the decision of the Award.
F
          In January, 1980, the Government of Gujarat submitted to the Central
     Water Commission a detailed project report in 14 volumes. This was an ·
    elaborate report and dealt wi.th various aspects like engineering details, canal
    systems, geology of area, coverage of command area etc. On 15th February,
    J980 the Central Water Commission referred SSP to the then Department of           '   •
G   Environment in Department of Science & Technology. At that point of time,
    environmental clearance was only an administrative requirement. An
    environmental checklist was forwarded to Government of Gujarat on 27th·
    February, 1980 which sought to elucidate information including following
    ecological aspects:
H          (i) Excessive sedimentation of the reservoir
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                     149
        (ii) Water logging                                                        A
        (iii) Increase in salinity of the ground water

        (iv) Ground water recharge
        (v) Health hazard-water borne diseases, industrial ponution etc.
        (vi) Submergence of important minerals                                    B
        (vii)Submergence of monuments
        (viii) Fish culture and aquatic life
        (ix) Plant life-forests
        (x) Life of migratory birds
                                                                                  c
        (xi) National Parle and Sanctuaries
        (xii) Seismicity due to filling of reservoir
The Government of Gujarat accordingly submitted information from September,
1980 till March, 1983. The information was also submitted on physio-social        D
and economic studies for Narmada Command Area covering cropping pattern,
health aspects, water requirement etc. A note of influence of Navagam dam
on fish yield including impact on downstream fisheries was also submitted.

      The techno-economic appraisal of the project was undertaken by the
Central Water Commission which examined water availability, command area          E
development, construction etc. The project was considered in the 22nd meeting
of the Technical Advisory Committee on Irrigation, Flood Control and Multi-
purpose projects held on 6.1.1983 and found it acceptable subject to
environmental clearance.

      At this point of time, the matter was handled by the Department of          F
Science and Technology which also had a Department dealing with
Environment. Environmental Appraisal Committee of the Department of
Environment, then headed by a Joint Secretary, had in its meeting held on
12.4.1983 approved the project, in principle, and required that further data be
collected. This Environmental Appraisal Committee dealt with the project on       G
two other occasions, namely, on 29.3.1985 when it deferred meeting to await
report of Dewan Committee on soil conservation and thereafter on 6.12.1985
when it deferred the meeting to await comments from the Forest Department.
As stated hereafter, subsequently the Secretary of newly constituted Ministry
of Environment and Forests took up further consideration of this project
along with other higher officials.                                                H
      150                     ':UPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A          After the project was approved, in principle, studies and collections of
    data were continuing. In May, 1983 the Namiada Planning Group, Government
    of Gujarat after completion of preliminary surveys submitted work plans for
  · various activities such as cropping pattern, health aspects, water requirements,
    distribution system, lay out and operation, develop~ent pla~ of the command,
B drainage and ground water development.
           In July, 1983, a study report on "Ecology and Environmental Impact of
      Sardar Sarovar Dam and its Environs" prepared by MS University was also
      submitted by Govemment_ofGujarat, covering the issues as mentioned below:
                                                                                       -
              *Climate
c             *Geology
              *Soil
              *Land use
             *Forest and Wildlife, Aquatic Vegetation
D            *Water Regime (Salinity, Tidal movements etc.)
             *Fisheries
             *Health
             *Seismicity

E           A review meeting was convened by the Secretary, Ministry of Water
      Resources in January, 1984 which was attended by a representative of the
      Department of Environm~nt. During this meeting, it was emphasized that the
      issues regarding catchment area treatment, impact on wildlife, health, water
      logging etc. should be studied in depth for assessment. The issue of charging
l'   -of cost of catchment area treatment to the project was also discussed. To sort
      out this matter, a meeting was subsequently convened by the Member,
      Planning Commission on 23rd May, 1984 in which the Ministry of Environment
      & Forests took a stand that there was a need for an integrated approach to
      basin development covering the catchment and command area. A project
     report, therefore, should be prepared to cover these aspects. Since the
G    catchment area for Narmada Sagar and Sardar' Sarovar was very vast, it was
     decided that an Inter-Departmental Committee should be set up by the Ministry
     of Agriculture under the Chairmanship of Dr. M.L. Dewan. This group could
     submit its report only in August, 1985 covering areas of catchment of Narmada
     and Sardar Sarovar and recommended that at least 25-30% of the area might
H    require treatment for these projects.
          NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.)                      151

       The consid.eration of the project in the Ministry, therefore, got deferred   A
for this report on catchment 'area treatment. During this time, Government of
Madhya Pradesh entrusted the studies on flora for Narmada Valley Project to
Botanical Survey of India and other ,related surveys were being carried out.
Even though there was a request on I 0th June, 1_985 from the Chief Minister
of Gujarat to the Mi,nister of State for Environment and Forests for delinking      B
of catchment area treatment works on clearance of the project, but this
request was not agreed.

        By this time the approval of SSP was being considered by the Secrl!tary,
 Ministry of Environment and Forests who invited other high officials in a
 review meeting which was held on 31st December, 1985 under his chairmanship.       C
 In this meeting, detailed presentations were made by the State officials of
 Gujarat, Madhya Pradesh and Maharasthra as well as the ex~erts who were
 involved in preparation of plans. The Secretary, Ministry of Environment and
 For~sts assessed and reviewed readiness on various environmental aspects
 like Catchment Area Treatment, Cpmpensatory Afforesation, Rehabilitation,
 Command area Development, Labour force and health issues, aquatic species,         D
 seismicity etc. and discussed the available reports in detail in the prese~ce
 of the officers of the Central/State Governments; Botanical Survey of India,
·senior officers of Forest Department, Planning Commission, Agriculture
 Department, Additional Inspector of Forests, Government of India, J?eputy
 Inspector General, Assistant. Inspector General of Forest, Government of
 India, senior officers of the Ministry of Environment and Forests, Secretary,      E
 Irrigation.
      As a follow up, the Government of Maharashtra submitted environmental
data regarding affected areas in Maharashtra. This included:

        *Impact assessment on wild life                                             F
        *Impact assessment on genetics, specifically identifying the plant
        types which are likely to be lost as a result of submergence.

        *Socio anthropological studies on tribals

        *The suitability of alternative land suggested for compensatory             G
        afforestation for growing.

        *Data regarding.alternate ·land in large blocks.

        *Arrangements made for exploitation of mineral resources going under
        submergence.                                                                H
     152                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A            *Alternative fuels to the labourers.

             *Micro-climatic changes.

             *Arrangements made for treatment of catchment area including swoil
             conservation afforestation.

B            *Steps taken for preserving archaeological and historical monuments.

             *Proper land use

             *Actions taken by Government of Maharashtra in pursuance of Dewan
             Committee Report.

C            *Arrangements for monitoring for environmental impact for the project.

             *Data related to rehabilitation of project affected persons.

         The Government of Gujarat also forwarded to the Government of India
    work plans on the following:
D          Forests and Wildlife
           Fish and Fisheries
           Health aspects

    The work plan on forests and wildlife incorporated actions to be taken on the
E   recommendations of the Inter-Departmental Committee headed by Dr. Dewan
    on soil conservation and afforestation works in the catchment area.

          In March, 1986, a meeting was convened by the Ministry of Water
    Resources in order to discuss the issues of fisheries, flora/fauna, health,
    archaeology with the officers of the Botanical Survey of India, Zoological
F   Survey of India, Archaeological Survey of India and the officers of the
    various departments of the State and Centre to gear up the preparation of the
    environmental work plans.

           The next meeting was held on 11th April, 1986. The Secretary, Ministry
G of Environmental and Forests, who chaired the meeting of senior officials,
    representatives of States and other agencies, sought additional information
    to be made available by 30th April, 1986 before assessment and management
    decision.

          In October, 1986, the Ministry of Water Resources prepared and
H   forwarded to the Ministry of Environment and Forests, a note on environmental
            NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                     153

aspects of the two projects and noted the urgency of the decision. It also           A
considered the importance of the project, should the project be taken at all,
environmental aspects of the project and ultimately rehabilitation, compensatory
afforestation, fauna and flora, catchment area treatment, public health aspect,
prevention of water logging. It then considered what remained to be done and
enumerated the same with time schedule as follows:
                                                                                     B
      I. Madhya Pradesh to complete the detailed survey of population likely
to be affected in all phases of N.S.P.                      ...... Three years

     2. Maharashtra to prepare a detailed rehabilitation plan for 33 villages
under phase I of SSP                                          .... Three years
                                                                                     c
      3. Madhya Pradesh to identify degraded forest lands twice the forest
area to be submerged for compensatory afforestation.       ..... Six months

         4. Survey of flora in Nannada valley assigned to Botanical Survey of
India.                                                          .... Two years

         5. Survey of Wildlife by Zoological Survey of India.       .... Two years   D
      6. Aerial photographs and satellite imagery to be analysed by All India·
Soil and Land Use Survey Organisation and National Remote Sensing Agency
and critically degraded areas in catchment.
         Field Surveys                                            ... Three years.   E
         Pilot studies to detennine measures for CAT In 25000 ha .
                                            ..... Three years after Aerial survey.
       In this note two options were considered - one to postpone the clearance
and. the otherwas to clear it with certain conditions with appropriate monitoring
authorities to ensure that the action is taken within the time bound programme.      F
It was concluded that in the light of the position set out, it was necessary
that the project should be cleared from the environmental angle, subject to
conditions and stipulations outlined.

      The Department of Environment and Forests made its own assessment              G
through a note of the Secretary, Ministry of Environment and Forests. It took
the view that following surveys/stu~ies as set out therein might take at least
2-3 years. It noted in this regard that:

          (i)   The estimate of Ministry of Water Resources on analysis of
                aerial photographs and satellite imageries as 2-3 years. ·
                                                                                     H
                                                                                                   ~-




     154                      SUPRE~E COURT REPORTS [2000] SUPP. 4 S.C.R.


A          . (ii)   Catchme_nt area treatment programme can be fonnulated by three
                    years thereafter;
             (iii) Wildlife census by Zoological Survey of India would take at
                   least three years;                                 '
             (iv) Survey by Botanical Survey of India would take three years.
B
    It further took the view that it was. essential that there should be a strong
    management authority. It finally concluded that if the Government should
    'decide to go ahead with the project it should be done with provision of
    environmental management authority with adequate powers and teeth to
                       I
    ensure that environment management plan is implemented pari passu with
C   engineering and other works. lt concluded that effective implementation of
    the engineering and environmental measures simultaneously will go long  a
    way and that such a project could be implemented by. harmonizing
    environmental conservation needs with 'the developmental effort.

D          The Ministry of Environment and Forests had not given environmental
     ciearance of N~rmada Sagar and Sardar Sarovar Dam despite all discussions
     which had taken place. The documents filed along with the affidavit of Shri
     P.K. Roy, Under Secretary, Prime Minister's Office dated 27th April, 2000
     indicate that there was difference of opinion with regard to the grant of
     environmental clearance between the Ministry of Water Resources and the
E    Ministry of Environment & Forests. This led to the matter being referred to
     the P.rime Minister's Secretariat fo.r clearance at ~he highest level. A note
     dated 20th November, 1986 prepared by the Ministry of Water Resources was
     forwarded to the Prime Minister Secretariat as well as to the Min'istry of
     Environment and Forests after dealing with the environmental aspects relating
F   to rehabilitation, catchment area treatment, command area development,
    compensatory· afforestation, flora and .fauna. This note i.ndicated that there
    were two options with regard to the clearance of the said project. One was
    to await for two to three years for.the completion of the operational plans and
    other detailed studies a·nd the second option was that the project should be
    given the n_ecessary clearance subject to the stipulation with regard to the      .. 4;.;..t

G   action to be taken in connection with vario.us · environm~ntal aspects and
    appropriate monitoring arrangements to ensure that the actions were tak~n in
    a time bound manner. The Ministry of Water Resources recomm~ded that it
    should be possible to give environmental clearance of the project and ensure
    that the conditions are properly. met through a process of clear assignment
H   of responsibility and frequent monitoring. The modus operandi for instituting
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      155
a monitoring system could be discussed at the meeting.                             A
      On 26th November, 1986, a meeting took place which was attended,
inter a/ia, by the S.ecretary, Ministry of Water Resources, Secretary, Ministry
of Environment & Forests, Additional Secretary, Prime MiRister Secretariat
and representatives of the Governments of Madhya Pradesh and Gujarat
regarding the environmental aspects of the Narmada Sagar and Sardar Sarovar        B
Project. The minutes of the meeting, inter alia, disclosed "it was decided that
the Government of Gujarat would identify lands for allocation to the project
affected persons of Madhya Pradesh within a specified period of time. The
meeting also envisaged the arrangement of a Monitoring and Enforcement
Authority to monitor the project and to ensure that the actions on the             C
environmental aspects proceed according to the schedule and pari passu
with the rest of the project". This Authority was not to be mainly a advisory
one but was to be given executive powers of enforcement including the power
to order stoppage of construction activity in the event of its being of the
opinion that there was lack of progress in action on the environmental front.
                                                                                   D
      On 19th December, 1986, the Secretary, Ministry of En_vironment and
Forests sent to the Secretary to the Prime Minister a combined note on the
environmental aspects of both the projects, namely, Narmada Sagar and Sardar
Sarovar Project. In this note, it was, inter a/ia, stated that there was absence
and inadequacy on some important environmental aspects even though the
Sardar Sarovar Project was in a fairly advance stage of preparedness. The          E
note also recommended the establishment of the Narmada Management
Authority with adequate powers and teeth to ensure that the Environmental
Management Plan did not remain only on paper but was implemented; and
implemented pari passu with engineering and other works. In the end, in the
note, it was stated as follows:                                                    F
       "If, despite the meagre availability of data and the state of readiness
       on NSP, the Government should decide to go ahead with the project
       it is submitted that it should do so only on the basis of providing a
       Management Authority as outlined above with the hope that the
       public opposition, not just by vested interests but by credible             G
       professional environmentalists, can be overcome. Effective
       implementation of the engineering and environmental measurers
       simultaneously would go a long way to prove ~hat even such a project
       can be implemented by harmonising environmental conservation needs
       with the development effort.
                                                                                   H
     156                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A          The choice is difficult but a choice has to be made."

     Along with this note was the statement showing the cost and the benefits
     of the Narmada Sagar and the Sardar Sarovar dam. The same reads as follows:

    "COSTS                        NARMADASAGAR                SARDAR SAROVAR
B
     l. Dam construction               Rs. 1400 crores         Rs. 4240 crores
                                       ( 1981 price level )    (1982·price level)

    2. Loss of forest                  Rs. 320 crores                                 -r-
c 3. Environmental
     loss of forests
                     cost of           Rs. 30923 crores         + - Rs. 8190 crores
                                                                                       ~


    4. Catchment area development Rs. 300 crores               Not available

    5. Command area development        Rs. 243.7 crores        Rs. 604.0 crores
D                                                              Rs. 300.0 crores
                                                               (conjunctive use)
    6. Loss of Mineral Reserves

    7. Diversion of 42 km Railway line

E   8. Population affected            129396 (1981 census)
                                      86572 (Excluding
                                      ropulation with land
                                      submerged for short
                                      period every year)

F   9. Land submerged                 91348 ha                  39134 ha

    Benefits
    10. Area irrigated                 123000 ha               1792000 ha
        Net culturable land           140960 ha                2120000 ha

G 11. Power Generations               223.5 MW(firm power) 300 MW
                                      I 000 MV (Installed  1450 (Installed
                                      capacity) 118.3 MW
                                      in 2023 A.O."
          After a series of meetings held between the Secretary to Prime Minister's
H   office as well as the Ministry of Water Resources, a detailed note dated 15th
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      157
January, 1987 was prepared by Mrs. Otima Bordia, Additional Secretary to the       A
Prime Minister. The notes opened by saying that Narmada Sagar and Sardar
Sarovar multipurpose projects have been pending approval of the Government
of India for a considerable amount of time. The States of Madhya Pradesh
and Gujarat have been particularly concerned and have been pressing for
their clearance. The main issues of environmental concern related to the
rehabilitation of the affected population, compensatory afforestation, treatment   B
of the catchment area, command area developmerit, pertaining particularly to
drainage, water logging and salinity. The said note mentioned that the
Department of Environment and Forests had sent a note with the approval
of the Minister for Environment and Forests and had recommended conditional
approval to the Narmada Sagar and Sardar Sarovar Projects subject to three         C
conditions:

        (i)    Review of design parameters to examine the feasibility of
               modifying the height of the dam;

        (ii)   Preparation in due time, detailed and satisfactory plans for        D
               rehabilitation, catchment area treatment, compensatory
               afforestation and command area development;
        (iii) Setting up of Narmada Management Authority with adequate
              powers and teeth to ensure that environmental management
              plans are implemented pari passu with engineering and other
               ~~                                                                  E
       It is further stated in the note that the Ministry of Water Resources and
the State Governments had no difficulty in accepting conditions (ii) and (iii).
With regard to review of design parameters and dam height, the Ministry of
Water Resources had examined the same after taking into consideration the          F
comments of the Central Water Commission and concluded that the reduction
of the FRL of the Narmada Sagar project would not be worthwhile. The
Secretary to the Prime Minister had discussed the matter with the Secretary,
Ministry of Water Resources and Secretary, Ministry of Environment and
Forests and it was agreed that the recommendation of the Minister of
Environment and Forests of giving clearance on the condition that items (ii)       G
and (iii) referred to hereinabove be accepted. The note also stated that in view
of the technical report, reduction in the dam height did not appear to be
feasible. This note of Mrs. Otima Bordia recommended that the Prime Minister's
approval was sought on giving conditional clearance. On this note, Mrs. Serla
Grewal, Secretary to the Prime Minister noted as follows:
                                                                                   H
     158                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A           "Proposal at para 17 may kindly be approved. This project has been
            pending clearance for the last 7 years and both the C.Ms. of Gujarat
            and Madhya Pradesh are keenly awaiting the clearance of the same.
            The agency, which is proposed to be set up to monitor the
            implementation of this project, will fully take care of the environmental
            degradation about which P.M. was concerned. The Ministry of
B           Environment and Forests have recommended clearance of this project
            subject' to conditions which will take care of P.M's apprehensions. I
            shall request Secretary, Water Res~urces, who will be Chairman of the
            Monitoring Agency, to see that no violation of any sort takes place
            and P.M's office will be kept informed of the progress of this project
c           every quarter. The matter is urgent as last week C.M. Gujarat had
            requested for green signal to be given to him before 20th January.

            P.M. may kindly appr?ve."

    The Prime Minister Shri Raj iv Gandhi, instead of giving the approval, made
D. the following note:
            "Perhaps this is a good time to try for a River Valley Authority.
            Discuss"

    It appears that the Ministry of Environment and Forests gave its clearance
E   to the setting up of Inter-Ministerial Committee and on 8th April, 1987,
    following note was prepared and forwarded to the Prime Minister.

           "This case has got unduly delayed. P.M. was anxious that speedy
           action should be taken. As such, since the Ministry of Environment
           have given its clearance subject to setting up of an Inter-Ministerial
           Committee as indicated at 'A' above, we may give the necessary
F          clearance. The three Chief Ministers may be requested to come bver
           early next week to give their clearance in principle for the setting up
           of a River Valley Authority so that simultaneous action can be initiated
           for giving practical shape to this concept. The clearance of the project,
           however, should b~ communicated within two weeks as I have been
G          informed by Shri Shiv Shanker and Shri Bhajan Lal that interested
           parties are likely to start an agitation and it is better if clearance is
           communicated before mischief is done by the interested parties."

         Along with another affidavit of Shri P.K Roy, Under Secretary, Prime
    Minister's Office dated 2nd May, 2000, some correspondence exchanged
H   between Legislature and the Prime Minister has also been placed on record
          NARMADA BACHAO ANDOLAN v. U.O.I. [KIRPAL, J.]                    159
relating to the granting of the environmental clearance by the Prime Minister.    A
On 31st March, 1987, Shri Shanker Sing Vaghela, the then Member of
Parliament, Rajya Sabha had written a letter to the Prime Minister in which it
was, inter a/ia, stated that the foundation stone for the Narmada Project had
been laid 25 years ago by the late Pandit Jawahar Lal Nehru and that after
the Tribunal's Award, Mrs. Indira Gandhi had cleared the project in 1978, but     B
still the environmental clearance had not so far been given. It was also stated
in his letter that the project was now being delayed on account of so-called
environmental problems. It was further stated in his letter that the Sardar
Sarovar Project, when completed, will solve more of the pressing problems of
environment than creating them. To this letter of Shri Vaghela, the Prime
Minister sent a reply dated 8th April, 1987 stating as follows:                   C
        "I have seen your letter of 31st March regarding the Narmada Project:
        All aspects have to be carefully considered before decisions are taken
        on a project of this size. This is being done.
            The environment and ecological factors cannot be dis-regarded.
        We cannot also dismiss the needs of our tribal people. Safeguards are     D
        required to ensure that rehabilitation plans are effective.
           All these aspects are being examined and a decision will be taken
        soon."
On 30th April, 1987, a press note was released by the Government of India,        E
in which it was stated that in a meeting presided over by the Prime Minister,
it was agreed by the Chief Ministers of Madhya Pradesh and Gujarat and
representatives of the Maharashtra Government that a high level River Valley
Authority would be set up for the control and development of the river basin.
This press note also stated that the Narmada Sagar and the Sardar Sarovar
Project on the river Narmada had been cleared. Soon, thereafter Shri Ahmad        F
Patel, Member of Parliament from Gujarat wrote a letter dated 14th April, 1987
to Shri Rajiv Gandhi expressing his gratitude for according clearance to the
Narmada multi-purpose project. This letter was replied to on 22nd April, 1987
by Shri Rajiv Gandhi who thanked Shri Patel for writing his letter dated 14th
April, 1987 regarding the Narmada project. On 20th April, 1987, Shri Shanker      G
Singh Vaghela wrote another letter to the Prime Minister. While thanking him
for clearing the project, it was stated that there was apprehension about the
environment and ecological factors and also about the needs of the tribal
people. The Prime Minister was requested "to clarify to the peopJe of Gujarat
whether or not these aspects have finally been cleared or not and all the
doubts on this front have been finally set at rest or not". On 4th May, 1987      H
     160                       SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

 A the Prime Minister replied to this letter in which it was stated as follows:
           "There should be no grounds for any misunderstanding in this regard.
     The Narmada Project has been cleared while at the same time ensuring that
     environmental safeguards will be enforced and effective measures taken for ·
     the rehabilitation of the tribals. You could ask the Ministry of Water Resources
B    or the State Government for details."
     Lastly, we need make reference to a letter dated 10th June, 1987 written by
     Smt. Chandraben Sureshbhai Shrimali, an M.L.A. of Gujarat and the reply of
     the Prime Minister thereto. In the said letter dated 10th June, 1987, Smt.
     Shrimali thanked the Prime Minister for clearing the Nannada project and it
C    was stated that the dry land of Gujarat and Saurashfra would be fertilised
     through Nannada Vojna. To this, reply dated 30th June, 1987 of the Prime
     Minister was as follows:

                 Thank you for your letter of 10th June. The visit to Surendranagar
             was useful and educative. We are all looking forward to the early
D            implementation of the Sardar Sarovar project. The question of
             environmental protection also needs serious attention. I wish you and
             the people of Surendranagar a good monsoon.

          From the documents and the letters referred to hereinabove, it is more
    than evident that the Government of India was deeply concerned with the
E · environmental aspects of the Nannada Sagar and Sardar Sarovar Project.
    Inasmuch as there was some difference of opinion between the Ministries of
    Water Resources and Environment & Forests with regard to the grant of
   environmental clearance, the matter was referred to the Prime Minister.
   Thereafter, series of discussions took place in the Prime Minister's Secretariat
   and the concern of the Prime Minister with regard to the environment and
F desire to safeguard the interest of the tribals resulted in some time being
   taken. The Prime Minister gave environmental clearance on 13th April, I 987
   and formal letter was iss1,1ed thereafter on 24th June, 1987.

           It is not possible, in view of the aforesaid state of affairs, for this Court
G to accept the contention of the petitioner that the environmental clearance of
    the project was given without application of mind. It is evident, and in fact
    this was the grievance made by Shri Vaghela, that the environmental clearance
    of the project was unduly delayed. The Government was aware of the fact that
    number of studies and data <had to be collected relating to environment.
    Keeping this in mind, a conscious decision was taken to grant environmental
H   clearance and in order to ensure that environmental management plans are
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.)                     161

implemented pari passu with engineering and other works, the Narmada              A
Management Authority was directed to be constituted. This is also reflected
from the letter dated 24th June, t 987 of Shri Mudgal giving formal clearance
to the project:

Re: OTHER ISSUES RELATING TO ENVIRONMENT
                                                                                  B
      Prior to the grant of the environmental clearance on 24th June, 1987,
sufficient studies were made with regard to different aspects of environment
on the basis of which conditional clearance was granted on 24th June, 1987,
one of the condition· of clearance being that the balance studies should be
completed within a stipulated time frame. According to the Government of
Gujarat, the conditions imposed in the environmental clearance granted on         C
June 24, 1987 were:

       (a)   The NCA would ensure that the environmental safeguard
             measures are planned and· implemented pari passu with the
             progress of work on the project.
                                                                                  D
        (b) The detailed survey/studies assur~d will be carried out as per
            the schedule proposed and details made available to the
            department for assessment.
       (c)   The catchment area treatment programme and rehabilitation plans
             be so drawn so as to be completed ahead of reservoir filling.
                                                                                  E
       (d) The department should be informed of progress on various
           works periodically.
      It was further submitted by the Government of Gujarat that none of
these conditions were linked to any concrete time frame.
       (a)   The first condition casts a responsibility on the NCA to ensure      F
             that the environmental aspects are always kept in view. The best
             way to attain the first and the fourth condition - was to create
             an environmental sub-group headed by the Secretary in the
             Ministry of Environment and Forest. ·
       (b)   The second condition - the conducting of surveys by its very         G
             nature - could not be made time bound. Tile surveys related to
             various activities to undo any damage or threat to the environment
             not only by the execution of the project but in the long term.
             Therefore, any delay in the conduct of surveys was not critical.
             Besides, a perusal of the latest status report on environment        H
        162                      SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A                     shows that a large number of surveys were carried out right from
                      1983 and also after 1987.
                (c)   The third condition has already stood fully complied with as
                      observed by Environment Sub-Group.                                 _.
                (d)   The fourth condition again involved keeping the department
B                     informed.

              It was submitted that the concept of "lapsing" is alien to such            ,..;.
        conditions. In other words, formal environmental and forest clearances granted
        by the Ministry of Environment and Forests, Government of India are not
C       lapsed and ar~ very much alive and subsisting.

           With regard to the lapsing of the clearance granted in 1987, it was
    contended by Mr. Harish Salve that a letter dated 25th May, 1992 was written
     by the Secretary, Ministry of Environment and Forests, Government of India
    to the Secretary, Ministry of Water Resources stating, inter a/ia, that the
D   conditions of clearance of the project were not yet met and, therefore, a formal
    request for extension of environmental clearance, as directed by Review
    Committee of Narmada Control Authority, may be made and failing which, a
    formal notification may be issued revoking the earlier clearance. It is, however,
    an admitted position that no formal notification has ever been issued revoking
    and/or cancelling the aforesaid two clearances at any point of time by the
E   Ministry of Environment and Forests, Government of India. The Secretary,
    Ministry of Environment and Forests has continued to hold and chair the
    meetings of Environment Sub-Group, Narmada Control Authority closely
    monitoring the execution of SSP for ensuring thaj, environmental safeguard
    measures are implemented pari passu with the progress of work. On 11th
    August, 1992, a letter was written by Narmada Control Authority to the
F   Secretary, Ministry of Environment and Forests sending action plan and
    status in respect of environmental safeguard measures taken and also stating
    amongst other details, the following:

              "A number of letters were exchanged between the MOWR and MOEF
              and a great deal of discussion took place both in the Environment
G             Sub-Group and NCA as to whether an application for extension of
              time as above is at all necessary. After a detailed discussion in the
              last NCA meeting on 25th July, 1992, it has been decided that NCA
              should clearly indicate the additional time required for the completion
              of the remaining studies like flora and fauna and some aspects of
H             fisheries and a revised action plan based· thereon be also sent
    \
        NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      163

       expeditiously."                                                            A
       xxxxx
       xxxxx
       "Keeping in view the fact and circumstances mentioned above, I
       request you to kindly agree to the schedule of the studies and the         B
       follow up actions as presented here. A brief account of the action
       plan together with bar charts are enclosed, presenting a pictorial
       view."

      On 15th December, 1992, a letter was written to the Secretary, Ministry
of Environment and Forests, more particularly stating as under, amongst other     C
things:

       "The Narmada Control Authority has already prepared an action plan
       and status on the environmental measures of Sardar Sarovar Project
       and submitted to the Ministry of Environment and Forests vide their
       letter No. NCA/EM/683 dated 11.8.1992 for concurrence. As may be           D
       seen from their report on action, so far there is no safeguard measures.
       During field season of every year this will be closely reviewed to
       attain pari passu objectives so that the submergence during monsoon
       is taken care of.
                                                                                  E
       The above actions are scheduled to be completed by June, 1993. No
       doubt, action in Maharashtra is lagging. The matter was taken up with
       the Chief Secretary of Maharashtra. A copy of his reply dated 7.11.1992
       is enclosed. You will observe that the reasons for the lag are largely
       due to the un-cooperative and agitational approach adopted by some
       people.                                                                    F
       Taking all these into account, you will appreciate that the action plans
       are adequate."

The Minister for Water Resources, Government of India wrote a letter on 27th
January, 1993 to the Minister of St~te for Environment and Forests stating G
that there had been no violation of environmental safeguard measurers. On
7th July, 1993, the Secretary, Ministry of Water Resources, Government of
India wrote a letter to the Secretary, Ministry of Environment and Forests,
Government of India, more particularly stating as under:

       "Progress of all the environmental works is summarised in the sheet        H
     164                         SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A                enclosed herewith. I share your concern for initial delay in some of
                 the studies but now it seems that the work has started in full swing.
                 However, there is a need to keep a close watch and I am advising the
                 NCA for the same."

   By letter dated 17th September, 1993, the Minister of State for Environment
B  and Forests, Government.of India wrote to the Minister for Water Resources,
   Government of India appreciating the efforts made by the concerned State
   Governments in making the environmental plans. The exchange of the aforesaid
   correspondence and the conduct of various meetings of the Environment
 · Sub-group from time to time under the Chairmanship of the Secretary, Ministry
C of Environment and Forests, disspells the doubt of the environment clearance
   having been lapsed. In· other words, there could not have been any question
   of the environmental clearance granted to SSP being lapsed more particularly
   when the Environment Sub-group had been consistently monitoring the
   progress of various environmental works and had been observing in its
   minutes of various meetings held from time to time, about its analysis of the
D works done by the respective States in the matter of the status of studies,
   surveys and environmental action plans in relation with:

           (i)     phased catchment area treatment;
           (ii) compensatory afforestation;

E          (iii) command area development;
           (iv) survey of flora, fauna etc.
           (v) archeological and anthropological survey;
           (vi) seismicity and rim stability of reservoir
           (vii) health aspects and
F
           (viii) fisheries development of SSP and NSP reservoirs.
          Sh. Shanti Bhushan in the course of his submissions referred to the
    report of the Morse Committee in support of his contentions that the project
    was flawed in more ways than one.
G          The Morse Committee was constituted, as already noted, by the World
    Bank. Its recommendations were forwarded to the World Bank. Apart from the
    Criticism of this report from other quarters, the World Bank itself, did not
    accept this report as is evident from its press release dated 22nd June, t 9n
    where it was, inter a/ia, stated as follows:

H            "The Morse Commission provided a draft of its report to the Bank for
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                       165
        management' comments several weeks prior to the final release of the        A
        document. About two weeks before this release, the commission
        provided a draft of its findings and recommendations. The final version
        of the report is the sole responsibility of its authors; the report was
        not cleared by the World Bank.

       On resettlement and rehabilitation (R&R), ~ank management agrees             B
       with the description of the R&R situation in each of the three states
       and with the report's conclusions about the sh~rtcomings in the
       preparation and appraisal of the project's R&R aspects. We also agree
       that work should have been done earlier on the issue of people
       affected by the canal in Gujarat. However, we do not share the view          C
       that resettlement would be virtually impossible even if Maharashtra
       and Madhya Pradesh adopted the liberal resettlement package provided
       for displaced people by the State of Gujarat. Given the experience so
       far, and the fact that most of the impact of submergence on people
       will not occur until 1997, there is still time to develop meaningful R&R
       packages and programs in consultation with the affected peopl~s.             D
       Efforts are being intensified to achieve this.

        On envi.ronment, bank management agrees with the independent review
        on the need for a more effective central management in the Narmada
        Basin on environment impact studies and mitigation programms.
        Management also agrees on the need to accelerate work on estuary            E
        studies and health matters in Gujarat. However, management does not
        share the review's conclusions about the environmental severity of
        the study delays. Command area issues are being addressed, including
        issues of water logging and salinity. On water availability (hydrology),
        Bank Management disagrees with the finding that there is insufficient       F
        impoundment of water upstream of the Sardar Sarovar Dam site to
        make the irrigation system work as designed."

The Government of India yide its letter dated 7th August, 1992 from the
Secretary, Ministry of Environment and Forests did not accept the report and
commented adversely on it                                                           G
       In view of the above, we do not propose, while considering the
petitioners' contentions, to place any reliance on the report of Morse Committee.

     It was submitted on behalf of the petitioners that the command area
development was an important aspect as the benefits of the project depended         H
     166                        SUPREME COURT REPORTS (2000) SUPP. 4 S.C.R.

A   on this and if proper studies and plans were not done and not implemented,
    the very areas that were supposed to benefit will end up being rendered unfit
    for cultivation and the water logging and salinisation could refer vast areas
    of the command unproductive. It was also submitted that still there was no
    integrated command area environmental impact assessment. After referring to
B   the status reports and studies regarding the command area development, it
    was submitted that there was need for some independent agency to examine
    the various stYdies, action plans and the experience and to see whether there
    was ground to believe that the proposed measures will work or not. It was
    contended that master plan for drainage and command area development was
    still not in place and even the full studies had not been done.
c
          While refuting the aforesaid contentions it was argued on behalf of
    learned counsel for the respondents that the SSP will provide irrigation water
    for a cultivable command area of 1.9 million hectares in Gujarat and 75,000
    hectares in Rajasthan. The introduction of fresh water to the drought-prone
    areas of Gujarat will create obvious benefits for the farming communities. In
D   order to safeguard these benefits, control and monitoring was suggested by
    the Secretary, Ministry of Environment and Forests and Chairman of the
    Environment Sub-group in the following areas from time to time:

           -   drainage, water logging and soil salinity;
E          -   water quality;
           -   forest loss;
           -   potential impact on flora and fauna;
           -   effects on public health;
F          - socio-economic impacts.
          Pursuant thereto fifty in-depth studies had been carried out by the State
    Governments of Gujarat and Rajasthan and some of the studies were still in
    progress. One of the ma:in objectives of carrying out these studies was to
    prevent excessive use of ground wa!er and water-logging.
G
          There is no reason whatsoever as to why independent experts should
    be required to examine tl)e quality, accuracy, recommendations and
    implementation of the studies carried out. The Narmada Control Authority
    and the Environmental Sub-group in particular have the advantage of having
    with them the studies which had been carried out and there is no reason to
H   believe that they wou,ld not be able to handle any problem, if and when, it
          NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      167

 arises or to doubt the correctness of the studies made.                            A
         It was submitted by Sh. Shanti Bhushan that the catchment area treatmem
  programme was not to be done pari passu but was required to be completed
  before the impoundment. This contention was based on the terms of the letter
  dated 24th June, I 987 wherein conditional environmental clearance was granted,
  inter alia, on the condition that "the catchment area treatment programme         B
  and rehabilitation plans be drawn so as to be completed ahead of reservoir
  filling". Admittedly, the impounding began in 1994 and the submission of Sh.
  Shanti Bhushan was that catchment area treatment programme had not been
  completed by them and, therefore, this very important condition had been
  grossly violated. Reference was also made to the Minutes of the Environmental     C
· Sub-group meetings to show that there had been slippage in catchment area
  treatment work.

        The clearance of June, 1987 required the work to be done pari passu
 with the construction of the dams and the filling of the reservoir. The area
 wherein the rainfall water is collected and drained into the river or reservoir D
 is called catchment area and the catchment area treatment was essentially
 aimed at checking of soil erosion and minimising the silting in the reservoir
 within the immediate vicinity of the reservoir in the catchment area. The
 respondents had proceeded on the basis that the requirement in the letter of
 June, 1987 that catchment area treatment programme and rehabilitation plans
 be drawn up and completed ahead of reservoir filling would imply that the E
 work was to be done pari passu, as far as catchment area treatment programme
 is concerned, with the filling of reservoir. Even though the filling of the
 reservoir started in 1994, the impoundment Award was much less than the
 catchment area treatment which had been affected. The status of compliance
 with respect to pari passu conditions indicated that in the year 1999, the F
 reservoir level was 88.0 meter, the impoundment area was 6881 hectares (19%)
 and the area where catchment treatment had been carried out was 128230
 hectares being 71.56% of the total work required to be done. The Minutes of
 the Environmental Sub-group as on 28th September, 1999 stated that catchment
 area treatment works were nearing completion in the states of Gujarat and
 Maharashtra. Though, there was some slippage in Madhya Pradesh, however, G
 overall works by and large were on schedule. This clearly showed that the
'monitoring of the catchment treatment plan was being done by the
 Environmental Sub-group quite effectively.

       With regard to compensatory afforestation it was contended by Sh.
 Shanti Bhushan that it was being carried out outside the project impact area.      H
     168                      SUPREME COURT REPORTS (2000) SUPP. 4 S.C.R.

A    Further, it was submitted that the practice of using waste land or lesser quality
     land for compensatory afforestation means that the forest will be of lesser
     quality. Both of these together defeated the spirit of the compensatory
     afforestation. It was contended that the whole compensatory afforestation
     programme was needed to be looked at by independent experts.

B          While granting approval in 1987 to the submergence of forest land and/
    or diversion thereof for the SSP, the Ministry of Environment and Forests had
     laid down a condition that for every hectare of forest land submerged or
    diverted for construction of the project, there should be compensatory
    afforestation on one hectare of non-forest land plus reforestation on two
C   hectare of degraded forest. According to the State of Gujarat, it had fully
    complied with the condition by raising afforestation in 4650 hectares of non-
    forest areas and 9300 hectares in degraded forest areas before 1995-96 against
    the impoundment area of 19%. The pari passu achievement of afforestation
    in Gujarat was stated to be 99.62%.

D         If afforestation was taking place on waste land or lesser quality land,
    it did not necessarily follow, as was contended by the petitioners, that the
    forests would be of lesser quality or quantity.

            It was also contended on behalf of the petitioners that downstream
     impacts of the project would include not only destruction· of downstream
E    fisheries, one of the most important ones in Gujarat on which thousands of
     people are dependent but will also result in salt water ingress. The project,
     it was contended, will have grave impacts on the Narmada Estuary and unless
     the possible impacts were properly studied and made public and mitigation
     plans demonstrated with the requisite budget, one could not accept the claim
F   that these matters were being looked into. The need to assess the problem
     was stated to be urgent as according to the petitioners rich fisheries
    downstream of the dam, including the famed Hilsa would be almost completely
    destroyed. The salinity ingress threatened the water suppl!' and irrigation use
    of over 210 villages and towns and Bharuch city. All these would not only
    have serious economic and other impacts but would also directly destroy the
G   livelihoods of at least I 0000 fisher families.

          Again all these contentions were based on the Morse Committee Report
    which the World Bank and the Union of India had already rejected. That apart,·
    according to the respondents, in 1992 Sardar SarovarNarmada Nigam Limited
    issued an approach paper on environmental impact assessment for the river
H   reach downstream. This provided technical understanding of the likely
          NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                   169

 hydrological changes and possible impact in relation thereto. It was further    A
 submitted by learned counsel for the respondents that the potential for
 environmental changes in the lower river and estuary had to be seen in the
 context of the long term development of the basin. The current stage was
 clearly beneficial. The three stages could be identified as follows:

 Stage I covers the period roughly from the completion of Sardar Sarovar Dam     B
 to the year 2015. Events occurring during this stage include (a) SSP Canal
 Command will have reached full development and requires diversion of some
 water, (b) the upstream demand will reach about 8 MAF and (c) the Narmada
 Sagar Dam will have been built and placed in operation.

  Stage 2 covers the period from 2015 and 2030 during which the demands          C
  upstream of SSP continue to grow and will reach about 12 MAF still below
·the volume of 18 MAF that Madhya Pradesh can take in a 75% year.

 Stage 3 covers the period upto and beyond full basin development.
 The report given by Mis. H.R. Wallingford in March, 1993 in respect of the      D
 down stream impacts of Sardar Sarovar Dam observes, inter a/ia, as under:

        "The overall conclusion of the team undertaking the assessment
        described in this report is that there are no down stream impacts
        whose magnitude and effect are such as to cause doubts to be cast
        over the wisdom of proceeding with the Sardar Sarovar Projects           E
        provided that appropriate monitoring and mitigation measurers are
        applied. Much of this work is already in progress under the auspices
        of the NPG, SSNNL and NCA. The recommendations in this report are
        intended to provide a synthesis of their work and suggestions as to
        whether it might be modified to enhance its usefulness."
                                                                                 F
        The said Mis. H.R. Wallingford in the findings of 1995 stated as
        under:

        "It is thought unlikely that any significant negative environmental
        impacts will occur over the next 30 years as a result of the project.
        Some possible adverse effects have been identified the main one          G
        being the effect of flood attenuation on Hi Isa migration. These needs
        to be monitored and more studies undertaken to better understand the
        conditions which trigger spawning. Beneficial impacts in this period
        include reduced flooding and more reliable dry season flows as well
        as an overall improvement of the health and well being of the people
        to the reliable domestic water supply, improved nutrition and enhanced   H
    170                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A           economic activity."

    The above report clearly demonstrates that the construction of dam would
    result into more regulated and perennial flow into the river with an overall
    beneficial impact. It is also evident that until all the dams are constructed
    upstream and the entire flow of river is harnessed, which is not likely in the
B   foreseeable future, there is no question of adverse impact including the
    fishing activity and the petitioner's assertions in this regard are ill-conceived.

          The area of submergence was stated to be rich in archaeological remains
    but it still remained to be studied. It was contended that there was danger
    ofrich historical legacy being lost and even a small increase in the dam height
C   would threaten to submerge many of the sites listed in the report of the
    Archaeological Survey of India. There were stated to be five monuments
    which would be affected at the dam height of 90 meter or above and no work
    was stated to have commenced to protect any of the five monuments.

          According to the State of Gujarat; the Ancient Monuments and
D   Archaeological Sites and Remains Act, 1958 charged the Central and/or State
    Department of Archaeology with responsibility for the protection of important
    cultural sites. Under the Act, sites were classified into three categories as
    follows:

E   Type I: Monuments of national importance which are protected by the Central
    Government;

    Type 2 : monuments of religious or cultural importance which are protected
    by the State Government; and

F   Type 3 : monuments which are neither Centrally nor State protected, but
    which are considered to be an important part of cultural heritage.

    Under the same law, authorities charged with the protection of the monuments
    are permitted to take suitable measures to ensure the preservation of any
    protected site under threat from decay, misuse or economic activity.
G
    In the case of Sardar Sarovar, where several sites may be submerged, the
    NOWT award stipulated that the entire cost of relocation and protection
    should be chargeable to Gujarat. Relocation work was to be supervised by
    the Depart~ent of Archaeology under the provisions of the Ancient
H   Monuments and Archaeological Sites and Remains Act, 1958.
               NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                        171
            The three State Governments carried out a complete survey of cultural          A
      and religious sites within the submergence zone. The principle of these
      surveys was to list all Archaeological sites, identify and name any site under
      State protection and further identify sites of religious or cultijral significance
      which, although not protected under national law, were of sufficient value to
      merit relocation. So far as the State of Gujarat is concerned the Department         B
      of Archaeology surveyed archeological sites in nineteen villages of
      submergence zone in Gujarat under the title of "Archaeological Survey of
      Nineteen Villages in Gujarat submerged by Sardar Sarovar Reservoir, 1989."

            In addition to baseline studies on archaeological aspects, work had
      been carried out on the anthropological heritage of Narmada Basin, including         C
      examination of evidence of ancient dwellings and cultural artifacts. The principal
      studies in this behalf are described below:

              Anthropological Survey oflndia: Narmada Salvage Plan: The Narmada
...           Salvage ·Plan contains detailed background data on
              palaeoanthropological, human ecological and other aspects of the             D
              Narmada Valley. By May, 1992, surface scanning of 17 sample villages
              coming under the submergence had been carried out and 424 specimens
              including ancient tools etc. had been collected.

              Anthropological Survey of India. Peoples of India: This project
              entailed a complete survey of 33 tribes of India including those of          E
              Narmada Basin. The study covered all aspects of tribal culture in India
              and was published in 61 volumes in 1992.

              Summary of current situation and progress, Government of Gujarat

            Survey of villages in               Complete for all items in the State
                                                                                           F
            submergence zone

            Identification of cultural sites    Complete for all items in the State

            Collection of data and              Complete
            documentation of sites
                                                                                           G
            Selection of appropriate sites       Complete

            Action Plan                           Complete

      It was further submitted on behalf of respondents that no centrally or State
      protected cultural sites were located in the submergen~e area of the project.        H
     172                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A In Gujarat, the Department of Archaeology concluded that the temples of
     Shoolpaneshwar and Hampheshwar were important monuments and should
     be moved to a higher level. Sites were selected for constructing new
     Shoolpaneshwar and Hampheshwar temples in consultation with temple
     trustees. Shoolpaneshwar had been relocated and reconstructured near Gora,
     about 15 Km downstream from the present location. Hampheshwar was also
B    constructed at higher ground in consultation with the temple trustees and
     pranpratistha was also planned on 22nd to 24th April, 2000 i.e. before the
     temple was submerged.

            In relation to flora and fauna studies, it was contended by the petitioners
C    that the studies had finished only recently and the action plans were awaited
     in many cases. In the meanwhile, extensive deforestation of the submergence
     zone had taken place, as also part of the area had been submerged, even as
     the studies have been on. It was also contended that the impact on some of
     these Wild Ass Sanctuary in Kutch would be very severe.

D         The guidelines of the Ministry of Environment and Forests required
    that while seeking environmental clearance for the hydropower projects, surveys
    should. be conducted so that the status of the flora and fauna present could
    be assessed. A condition of environmental clearance of 1987 as far as it
    related to flora and fauna was that the Narmada Control Authority would
    ensure in-depth studies on flora and fauna needed for implementation of
E   environmental safeguard measurers. It is the case of the respondents that
    number of studies were carried out and reports submitted. It was observed
    that the submergence area and catchment area on the right bank of the
    proposed reservoir exhibited a highly degraded ecosystem which was in
    contract to the left bank area where there was fairly go.od forest cover which
F   formed part of Shoolpaneshwar Wildlife Sanctuary. With regard to the study
    of fauna, the said report indicated that a well-balanced and viable eco-system
    existed in the Shoolpaneshwar Sanctuary. Moreover, with the construction of
    dam, water availability and soil moisture will increase and support varieties
    of plants and a~imals.

G          It was also contended on behalf of petitioners that the whole project
     will have sedous impacts on health, both around the submergence area and
    .in the command. The preventive aspects had not been given attention. There
     was no linkage between the studies and work.

          On behalf of State of Gujarat, it was contended that large number of
H   studies had been carried out on the health profile of villagers including
             NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                     173
    studies on water related diseases in SSP command area including the area          A
    downstream of the dam. The study of M.S. University in 1983 and other
    studies concluded that the most common diseases in the basin were Malaria,


-   Scabies, Dysentery and Diarrhoea. Of these only a threat to Malaria needed
    to be of concern. The study concluded that the incidence of hygiene related
    diseases other than Malaria could be reduced by better water availability. The
    Gujarat Work Plan covered villages within IO KMs radius of the reservoir
                                                                                      B
    including re-settled population and made provision for the monitoring,
    surveillance and control of Malaria. The principal features of the Gujarat Work
    Plan included establishment of a hospital at Kevadia near the dam site,
    strengthening of laboratory facility including establishment of mobile unit
    residual insecticidal spraying operations etc. This showed that the area of       C
    public health was in no way being neglected.

           The petitioner was also critical of the functioning of the Environmental
    Sub-group as it was contended that the claims of the studies and progress
    report were accepted at the face value and without verification. It was also
    contended that the Ministry of Environment and Forests had grossly abdicated      D
    its responsibility. This submission was based on the premise that clearance,
    which had been granted, had lapsed and the Ministry of Environment and
    Forests did not insist on the Ministry of Water Resources for its renewal and
    further more the Ministry of Environment and Forests had not taken any
    cognizance of the criticism about environmental aspects contained in the          E
    Morse Committee Report. Lastly the Five Member Group in its first report was
    critical in many respects and pointed out studies which had remained
    incomplete but no cognizance was taken by the Ministry of Environment and
    Forests. The repeated abdication, it was submitted, of the responsibility by
    the Ministry of Environment and Forests indicated that it was not taking the
    whole issue with the seriousness it deserved.                                     F
           On behalf of the State of Gujarat, it was contended that various alleged .
    dangers relating to environment as shown by the petitioners were mostly
    based on the recommendations of the Morse Committee Report and Five
    Member Group. While the report of Morse Committee does not require our
    attention, the same not having been accepted either by the World Bank or G
    the Government of India. Para 4.5.2 of the report ofFive Member Group which
    relates to creation of the Environment Sub-group commends it's establishment,
    it's observation about its powers is as follows:
           "4.5.2. It must be noted that the Environmental Sub-group is not a
           body which merely observes and reports, but watchdog body which            H
     174                     SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A            can recommend even the stoppage of work if it feels dissatisfied with
             the progress on the environment front. The recommendations of the
             Environmental Sub-Group will have to be considered by the NCA, and
             if there is any difference of opinion at that level, it will have to be
             referred to. the Review Committee, which has the Minister of Water
            and Environment and Forests as a member. It seems doubtful whether
B            any more effective mechanism could have been devised or made to
             work within the framework of our existing political and administrative
            structures, particularly in the context of a federal system. Secretary
            (Environment & Forests) has, in fact, been given a special position in
            the NCA inasmuch as he can insist on matters being referred to the
c           Review Committee and at the Review Committee the Minister of
            Environment and Forests forcefully plead the environmental cause; he
            can also make the environmental point of view heard at the highest
            level. If in spite of all these arrangements, the environmental point of
            view fails to be heard adequately, and if project construction tends to
            take an over-riding precedence, that is a reflection of the relative
D           political importance of these two points of view in our system. This
            can be remedied only in the long term through persuation and
            education, and not immediately through. institutional arrangements
            which run counter to the system." (Emphasis added)

E         Apart from the fact that we are not convinced that construction of the
    dam will result in there being an adverse ecological impact there is no reason
    to conclude that the Environmental Sub-group is not functioning effectively.
    The group which is headed by the Secretary, Ministry of Environment and
    Forests is a high powered body whose work cannot be belittled merely on
    the basis of conjectures or surmises.
F
          Sh. Shanti Bhushan, learned Senior Counsel while relying upon A.P.
    Pollution Control Board v. Professor M V. Mayadu, [1999] 2 SCC 718
    submitted that in cases pertaining to environment, the onus of proof is on
    the person who wants to change the status quo and, therefore, it is for the
    respondents to satisfy. the Court that there will be no environmental
G   degradation.

          In A.P. Pollution Control Board's case this Court was dealing with the
    case where an application was submitted by a company to the Pollution
    Control Board for permission to set up an industry for production of "BSS
    Castor Oil Derivatives". Though later on a letter of intent had been received
H   by the said company, the Pollution Control Board did not give its no-objection
             NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                        175
    certificate to the location of the industry at the site proposed by it. The          A
    Pollution Control Board, while rejecting the application for consent, inter alia,
    stated that the unit was a polluting industry which fell under the red category
    of polluting industry and it would not be desirable to locate such an industry
    in the catchment area of Himayat Sagar, a lake in Andhra Pradesh. The appeal
    filed by the company against the decision of the Pollution Board was accepted        B
    by the appellate authority. A writ petition was filed in the nature of public
    interest litigation and also by the Gram Pancliayat challenging the order of
    the appellate authority but the same was dismissed by the High Court. On
    the other hand, the writ petition filed by the company was allowed and the
    High Court directed the Pollution Board to grant consent subject to such
    conditions as may be imposed by it.                                                  C
          It is this decision which was the subject-matter of challenge in this
    Court. After referring to the different concepts in relation to environmental
    cases like the 'precautionary principle' and the 'polluter-pays principle', this
    Court relied upon the earlier decision of this Court in Ve/lore Citizens~
    Welfare Forum v. Union of India, [1996) 5 SCC 647 and observed that there            D
    was a new concept which places the burden of proof on the developer or
    industrialist who is proposing to alter the status quo and has become part
    of our environmental law. It was noticed that inadequacies of science had led
    to the precautionary principle and the said 'precautionary principle' in its tum
    had led to the special principle of burden of proof in environmental cases           E
I   where burden as to the ab~ence of injurious effect of the actions proposed
    is placed on those who want to change the status quo. At page 735, this
    Court, while relying upon a report of the International Law Commission,
    observed as follows:

                The precautionary principle suggests that where there is an              p
            identifiable risk of serious or irreversible harm, including, for example,
            extinction of species, widespread toxic pollution is major threats to
            essential ecological processes, it may be appropriate to place the
            burden of proof on the person or entity proposing the activity that
            is potentially harmful to the environment.
                                                                                         G
           It appears to us that the 'precautionary principle' and the corresponding
    burden of proof on the person who wants to change the status quo will
    ordinarily apply in a case of polluting or other project or industry where the
    extent of damage likely to be inflicted is not known. When there is a state
    of uncertainty due to lack of data or material about the extent of damage or
    pollution likely to be caused then, in order to maintain the ecology balance,        H
     176                    SUPREME COURT REPORTS                     [ 1998] I S.C.R.

A the burden of proof that the said balance will be maintained must necessarily
     be on the industry or the unit which is likely to cause pollution. On the other
     hand where the effect on ecology or _environment of setting up of an industry
     is known, what has to be seen is that if the environment is likely to suffer,
     then what mitigative steps can be taken to off set the same. Merely because
     there will be a change is no reason to presume that there will be ecological
B    disaster. It is when the effect of the project is known then the principle of
     sustainable development would come into play which will ensure that mitigative
     steps are and can be taken to preserve the ecological balance. Sustainable
     development means what type or extent of development can take place which
     can be sustained by nature/ecology with or without mitigation.
c         In the present case we are not concerned with the polluting industry
     which is being established. What is being constructed is a large dam. The
    dam is neither a nuclear establishment nor a polluting industry. The construction
    of a dam undoubtedly would result in the change of environment but it will
    not be correct to presume that the construction of a large dam like the Sardar
D   Sarovar will result in ecological disaster. India has an experience of over 40
    years in the construction of dams. The experience does not show that
    construction of a large dam is not cost effective or leads to ecological or
    environmental degradation. On the contrary there has been ecological
    upgradation with the construction of large dams. What is the impact on
E   environment with the construction of a dam is well-known in India and,
    therefore, the decision in A.P. Pollution Control Board's case (supra) will
    have no application in the present case.

           Reference was made by Sh. Shanti Bhushan to the decision of the
     United States District Court in the case of Sierra Club et. v. Robert F.
F    Froehlke, 350bF. Supp.1280 (1973). In that case work had begun on Wall\sville
     Project which, inter a/ia, consisted of a construction of a low dam. It was the
     case of the plaintiff that the construction of the project would destroy hundreds
    of thousands of trees and enormous grain, fish and other wild life will lose
    their habitat and perish. It was contended that the defendants were proceeding
    in violation of law by not complying with the requirements of National
G   Environmental Policy Act, 1969, [NEPA]. Plaintiff, inter a/ia, sought an
    injunction for restraining the undertaking of the project in violation of the said
    Act. The District Court held that notwithstanding the substantial amount of
    work had already been done in connection with the project but the failure to
    satisfy full disclosure requirement of NEPA injunction would be issued to halt
H   any further construction until requirements of NEPA had been complied with,
         NARMADA BACHAO ANDOLAN v. U.O.l. [KIRPAL, J.]                       177

that even though there was no Act like NEPA in India at the time when               A
environmental clearance was granted in 1987, nevertheless by virtue of
Stockholm Convention and Article 21 of the Constitution the principles of
Sierra Club decision should be applied.

       In India notification had been issued under Section 3 of the
Environmental Act regarding prior environmental clearance in the case of
                                                                                    B
undertaking of projects and setting up of industries including Inter-State
River Project. This notification has been made effective from 1994. There was,
at the time when the environmental clearance was granted in 1987, no obligation
to obtain any statutory clearance. The environmental clearance which was
granted in 1987 was essentially administrative in nature, having regard and         C
concern of the environment in the region. Change in environment does not
per se violate any right under Article 21 of the Constitution of India especially
when ameliorative steps are taken not only to preserve but to improve ecology
and environment and in case of displacement, prior relief and rehabilitation
measures take place pari passu with the construction of the dam.
                                                                                    D
      At the time when the environmental clearance was granted by the Prime
Minister whatever studies were available were taken into consideration. It was
known that the construction of the dam would result in submergence and the
consequent effect which the reservoir will have on the ecology of the
surrounding areas was also known. Various studies relating to environmental         E
impact, some of which have been referred to earlier in this judgment, had been
carried out. There are different facets of environment and if in respect of a
few of them adequate data was not available it does not mean that the
decision taken to grant environmental clearance was in any way vitiated. The
clearance required further studies to be undertaken and we are satisfied that
this has been and is being done. Care for environment is an on going process        F
and the system in place would ensure that ameliorative steps are taken to
counter the adverse effect, if any, on the environment with the construction
of the dam.

      Our attention was also drawn to the case of Tennessee Valley Authority        G
v. Hiram G. Hill, 437 US 153, 57 L Ed 2d 117, 98 S Ct (2279) where the
Tennessee Valley Authority had begun construction of the Tellico Dam and
reservoir project on a stretch of Little Tennessee River. While major portion
of the dam had been constructed the Endangered Species Act 1973 was
enacted wherein a small fish popularly known as the "Snail darter" was
declared an endangered species. Environmental groups brought an action in           H
      178                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

 A    the United States District Court for restraining impounding of the reservoir
      on the ground that such an action would violate the Endangered Species Act
      by causing the snail darter extinction. The District Court refused injunction
      but the same was granted by the United States Court of Appeal. On further
      appeal the US Supreme Court held that the Endangered Species Act prohibited
      the authority for further impounding the river. The said decision has no
 B    application in the present case because there is no such act like the Endangered
      Species Act in India or a declaration similar to the one which was issued by
      the Secretary of the Interior under that Act. What is, however, more important
      is that it has not been shown that any endangered species «existS\in the area
      of impoundment In Tennessee Valley Authority case it was an accepted
 C    position that the continu.ed existence of snail darter which was an endangered
      species would be comJ)1~~_ely jeopardised.

            Two other decisions were referred to by Sh. Shanti Bhushan - Arlington
      Coalition on Transportation v. John A. Volpe, [458 F.2d 1323 (1972)] and
      Environmental Defense Fund, Inc. v. Corps of Engineers of United States
 D    Army, [325 F.Supp. 749 ( 1971 )]. In both these decisions it was decided that the
     NEPA would be applicable even in case of a_ project which had commenced
      prior to the coming into force of the said Act but which had not been
     completed. In such cases there was a requirement to comply with the provisions
     of NEPA as already noticed earlier. The notification under Section 3 of the
.E   Environment Protection Act cannot be regarded as having any retrospective
     effect. The said not_ifi.cation _dated 27th January 1994, inter alia, provides as
     follows:
             "Now, therefore, in exercise of the powers conferred by sub-section
             (l) and clause (v) of sub-section (2) of Section 3 of the Environment
             (Protection) Act, 1986 (29of1986) read with clause (d) of sub-rule (3)
F            of rule 5 of the Environment (Protection) Rules, 1986, the Central.
             Government hereby directs that on and from the date of publication
             of this notification in the Official Gazette expansion or modernization
             of any activity (if pollution load is to exceed the existing one) or a new
             project listed in Schedule I to this notification, shall not be undertaken
G            in any part of India unless it has been accorded environmental clearance
             by the Central Government in accordance with the procedure hereinafter
             specified in this notification."
     This notification is clearly prospective and inter alia prohibits the undertaking
     of a new· project listed in Schedule I without prior environmental clearance of
H    the Central Government in accordance with the procedure now specified. In
              NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      179

      the present case clearance was given by the Central Government in 19~7 and        A
      at. that time no procedure was prescribed by any statute, rule or regulation.
    · The procedure now provided in 1994 for getting prior clearance cannot apply
      retrospectively to the project whose construction commenced nearly eight
      years prior thereto.

    RELIEF AND REHABILITATION                                                           B
           It is contended by the petitioner that as a result of construction of dam
    over 41,000 families will be affected in three States spread over 245 villages.
    The number of families have increased from 7000 families assessed by the
    Tribunal. It was further contended that the submergence area can be broadly
    divided into two areas, fully tribal area which covers the initial reach of about   C
    100 or so villages which are almost I 00 % tribal and hilly. These include all
    the 33 villages of Maharashtra, all 19 of Gujarat and many of the Madhya
    Pradesh. The second part of the submergence area is the mixed population
    area on the Nimad plains with a very well developed economy that is well
    connected to the mainstream. While the tribal areas are stated to be having
    a rich and diverse resource base and the self sufficient economy, the lack of       D
    so-called modem amenities like roads, hospitals and schools are far more a
    reflection of the neglect and disregard by the Government over tht'. last fifty
    years than on anything else. Of the 193 villages stated to be affected by
    Sardar Sarover submergence 140 lie in the Nimad plains. The population of
    these villages are a mixture of caste and tribal and these villages have all the    E
    facilities like schools, post offices, bus service etc.

           It was contended that whereas the project authorities talk only about
    the families affected by submergence, none .of the other families affected by
    the project are considered as PAFs nor has any rehabilitation package been
    designed for them. These non-recognised categories for whom no rehabilitation       F
    package is given are stated to be those persons living in submergence area
    who are not farmers but are engaged in other occupation like petty traders,
    village shop-keepers who are to be affected by submergence; colony affected

-   people whose lands were taken in 1960 to build the project colony, warehouses
    etc.; canal affected people who would be losing 25 per cent of their holdings
    because of the construction of the canals; drainage affected people whose
                                                                                        G

    lands will be acquired for drainage; I 0,000 fishing families living downstream
    whose livelihood will be affected; lands of the tribals whose catchment
    treatment area has been carried out; persons who are going to be affected by
    the expansion Shoolopaneshwar Sanctuary; persons going to be affected by
    Narmada Sagar Project and Garudeshwar Weir. It was contended that there             H
     180                       SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A    was an urgent need to assess comprehensively ,the totality of the impact and
     prepare category specific rehabilitation policies for all of them.

           It was also submitted that the total number of affected families in all the
     three States as per the Master Plan prepared by the Narmada Control Authority •
     is 40727. According to the petitioner, however, this figure is an under-estimate
B    and the estimate of the land required for these PAFs is also on a much lower
     side. The basis for making this submission is:

           (l) In each village there are many persons left out of the Government
     list of declared PAFs. These are joint holders [non recognised as landed
     oustees or PAFs] and the adult sons.
c
           (2) Incorrect surveys have been conducted and the affected persons
    have serious apprehensiorts about the validity of the surveys since at many
    places the level markings are suspect, in many cases the people '1affected at
    higher levels have been given notices for lower levels, many others at the
    same levels have been left out and so on. It is also alleged that there have
D   been short-comings in the policies and if they are corrected many more
    oustees will be entitled to PAFs status. Further more the cut off date for PAFs
    in Madhya Pradesh including adult soh is linked to the· date of issuance of
    notification. Since land acquisition process is still incomplete the number of
    adult sons entitled to land would increase with the issuance of fresh Section
E   4 Notification.

          From the aforesaid it was contended that the total impact in terms of
    number of oustees as well as land entitlement will be muc~ larger than what
    is considered in the Master Plan.

F          It is also submitted that there was major lacunae in the said policy like
     the three States having dissimilar policy for R&R. This difference in
    rehabilitation packages of different States, with the package of Gujarat bein£
    more favourable, is leading to a situation where the oustees are forced to shift
    to Gujarat. The other lacunae which are stated to have mafly serious prob.terns
                                                                                          .....   _
G   are alleged to be non provision for fuelwood and grazing land with fodder.
    No provision for rehabilitation of people involved in non-agricultural
    occupation. According to the petitioner the number of affected people even
    by submergence have been underestimated. The policy regime governing
    them has many serious lacunae. The increase in the numbers is due to lack
    of proper surveys and planning and the provision of just and due entitlements
H   to the PAFs. Since this process of providing just entitlements is still incomplete,
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      181

and the policies need a thorough review, the numbers and entitlements are          A
likely to go up further. Even the magnitude of the task of R&R cannot be
assessed properly till the above are considered and proper policies introduced.

       It is also contended that before embarking on the Sardar Sarovar Project
it was necessary that the Master Plan for rehabilitation of the families to be     B
affected is completed. According to the petitioner the Master Plan which was
submitted in the Court cannot be regarded as an acceptable Master Plan
inasmuch as it has no mention of people affected by Sardar Sarovar project
other than those affected by submergence and it has no estimate of resource
base of the oustees in their original village. Further the plan makes no
estimation of the forest land, grazing land and resources being used by the        C
oustees. The Master Plan persists with the discriminatory and differential
policies which are less than just to the oustees. There is also no planning for
community resettlement even though the Award of the llJarmada Tribunal
made detailed provision regarding rehabilitation of the oustees which required
that there should be village wise community rehabilitation.                        D
       In support of this contention reliance is placed on the following
stipulation for rehabilitation contained in the Award of the Narmada Tribunal
"That Gujarat shall establish rehabilitation villages in Gujarat in the
irrigation command of the SSP on the norms hereafter mentioned for
rehabilitation of the families who are willing to migrate to Gujarat." The         E
submission is that no specific rehabilitation village, as envisaged by the
Tribunal's Award, has been established in Gujarat. The issue of community
re-settlement is stated to be not merely an issue of community facility but is
a more fundamental issue. The issue is really one of preserving social fabric
and community relation of the oustees which, ;tis alleged, is being destroyed
due to dispersal of the community who are being resettled at different sites.      F
      Dealing with the situation of those oustees who have been resettled in
Gujarat it is submitted by the petitioner that there are large number of
grievances of the said outstees in 35 re-settlement sites. With the passage of
time the number of problems overall would become much more, is the                 G
contention. The petitioner finds fault with the quality of land which has been
given in Gujarat to the oustees contending that large number of oustees have
been given land outside the command area of irrigation and in some re-
settlement sites there is a serious water-logging problem. It also contends that
though some amenities have been provided but they are not adequate. It is
also the case of the petitioner that sufficient land for re-settlement of the      H
     182                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A    oustees from Madhya Pradesh is' not available in Gujarat despite the claim of
     the State of Gujarat to the contrary.

          With regard to Maharashtra it is contended by the petitioner that the
  ·official figure of the total number of PAFs affected in Maharashtra is not
   correct and the number is likely to be more than 3113 PAFs estimated by the
                                                                                      -
B State of Maharashtra. Further-more adequate land of desired quality has not
   been made available for resettlement till 90 mtr. and even thereafter. Reference
  ·is made to the affidavit of the State of Maharashtra in which it is stated that
   it proposes to ask for the release of 1500 hecta~es of forest land for re-
   settlement and the submission on behalf of the petitioner is that release of
C such land shall be in violation of Forest Conservation Act, 1980 and is not
   in public interest for forest cover will be further .depleted.

           With regard to the State of Madhya Pradesh it is submitted that as per
                      n
     the award the. PAFs have a right to choose whether to go to Gujarat or to
    stay in the home State. The ·State of Madhya Pradesh is stated to have
D planned the whole re-settlement based on the assumption that overwhelming
    proportion of oustees entitled to land will go to Gujarat yet even for the
    limited. number of oustee~ who are likely to stay in Madhya Pradesh the
    submission is that no land is available. The petitioner also disputes the
    averment of the State of Madhya Pradesh that the oustees have been given .
E a choice as to whether they would like to go to Gujarat or stay in the home
    State. According to the petitioner the majority of the oustees would prefer to
    stay in the home State that is Madhya Pradesh but sufficient land for their
  · resettlement in Madhya Pradesh is not available. According to the petitioner
    the State of Madhya Pradesh has stated that it does not have land for any
    PAFs above 830 and even for 830 PAFs the land is not available. It is also
F submitted that the Madhya Pradesh Government cannot wriggle out of its
    responsibility to provide land for the oustees by offering them cash
    compensation. The petitioner finds fault with the effort of the State of Madhya
    Pradesh to push the oustees to Gujarat whose rehabilitation scheme is more
   attractive and beneficial than that of Madhya Pradesh.
G
           The petitioner further contends that one of the fundamental principle
    laid down is that all the arrangements and resettlement of the oustees should
    be made one year in advance ofsubmersion. lil B.D. Sharma v. Union of
    India's case this Court has held that resettlement and rehabilitation has to be
    do.ne at least six months in advance of submersion, complete in all respects.
H   It is, therefore, contended that since offers to the Madhya Pradesh oustees
             NARMADA BACHAO ANDOLAN v. U.O.I. [KIRPAL, J.]                      183

    affected at 90 mtr. to be settled in Madhya Pradesh has not be~n made, there       A
    cannot be any question of fuf'ther construction till one year after the
    resettlement of these PAFs at 90 mtr.


-          The petitioner is also critical of the functioning of the R&R Sub-group
    and it is contended that the said Sub-group has not taken any cognizance
    of the various issues and problems enumerated by the petitioner. It is submitted   B
    that in assuring that the relief and rehabilitation arrangements are being done
    the said R&R Sub-group merely accepts the assertions of the Government
    rather than verifying the claims independently. There is also a complaint
    regarding the manner in which the R&R Committee takes decision on the spot
    when it makes frequent visits. It i.s contended that the decisions which are       C
    taken in an effort to solve the grievantes of the oustees is done in the most
    insensitive way. The R&R Sub-group, it is contended, is an official agency
    of the Government itself being a Sub-group of the NCA, which is pushing the
    project ahead and the question raised by the petitioner is as to how can the
    same body which is building a project and executing the R&R be also
    monitoring it.                                                                     D
           It is a case of the petitioners that there is a need for independent
    monitoring agency in the three States ~ho should be asked to monitor the
    R&R of the oustees and see to the compliance with the NOWT award. No
    construction should be permitted to be undertaken without clearance from
                                                                                       E.
    this authority. Lastly it is contended that large number of grievances are
    persisting even after twenty years and the pace of resettlement has been slow.
    The petitioner seems to have contended that_ the relief and rehabilitation can
    be manageable only if the height of the dam is significantly lessened which
    will red.uce submersion and displacement of people.
          In order to consider the challenge to the execution of the project with      F
    reference to Relief and Rehabilitation it is essential to see as to what is the
    extent and the nature of submergence.
          The Sardar Sarovar Reservoir level at 455 ft. would affect 193 villages
    in Madhya Pradesh, 33 villages in Maharashtra and 19 villages in Gujarat. The
    submergence villages are situated on the banks of river Narmada having             G
    gentle to steep slopes of the Satpura hills. A village is considered affected
    even when the water level touches the farm/hut at lowest level. It may be
    noted that only 4 villages (3 villages in Gujarat and I village in Madhya
    Pradesh) are getting submerged fully and the rest 241 villages are getting
    affected partially.                                                                H
     184                       SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A         The state-wise land coming under submergence (category-wise) is given
    below:
                                               STATES
                                                                     (In Hectares)

    SI. No Type of             Gujarat           Maharashtra      Madhya Total
B          land                                                   Pradesh

             Cultivated land 1877                1519             7883       11279

             Forest Land     41(i6               6488             2731       13385
             Other land
c            including river
             bed             1069                1592             10208      12869

             Total land        7112              9599             20822      37533

          The aforesaid table shows that as much as 12869 hectares of the
D
    affected land is other than agricultural and forest and includes the river bed
    area.

          When compared to other similar major projects, the Sardar Sarovar
    Project has the least ratio of submergence to the area benefited ( 1.97% only).
E   The ratio of some of the existing schemes is as much as 25% as can be seen
    from the table below:

    Sr.    Name of    State      Benefite d   Sub me     Irrigation Percentage
    No.    Project               Area (in ha) rgence     benefit    of area
                                              Area.      per ha     submerged
F                                             (in ha)    Suber-     to area
                                                         gence      irrigated

           Hirakud    Orissa          251150     73892   3.40        29.42

G          Shriram-   Andhra
           sagar      Pradesh         230679     44517   524         19.14

           Gandhisa- Madhya
           gar       Pradesh          503200     66186   7.60        13.15

H          Paithan    Mahara-         278000     35000   7.94        1529
                  NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, .I.]                      185
                          shtra                                                              A
              Tungbha- Kamataka 372000              37814      9.84         10.16
              dra
  ,,.         Pench       Maharashtra 94000         7750       12.13        824
                                                                                             B
              Nagarjun- Andhra         895000       28500      31.40       3.18
              sagar     Pradesh

              Bhakra      Himachal     676000       16800      4024        2.48
                          Pradesh
              Sardar      Gujarat     1903500       37533      50.71        1.97             c
              Sarovar


               Countering the assertion that the construction of the dam would result
        in large scale relocation and uprooting of tribals, the factual position seems
        to be that the tribals constitute bulk of PAFs in Gujarat and Maharasthra,           D
        namely, 97% and I 00% respectively. In the case of Madhya Pradesh, the
        tribals PAFs are only 30% while 70% are non-tribals.

               The tribals who are affected are in indigent circumstances and who
        have been deprived of modem fruits of development such as tap water,
        education, road, electricity, convenient medical facilities etc. The majority of     E
        the project affected families are involved in rain-fed agricultural activities for
        their own sustenance. There is partial employment in forestry sector. Since the
        area is hilly with difficult terrain, they are wholly dependent on vagaries of
        monsoon and normally only a single crop is raised by them. Out of the PAFs
        of Madhya Pradesh who have re-settled in Gujarat, more than 70% are tribal           F
        families. Majority of the total tribal PAFs are stated to have already been re-
        settled in Gujarat after having exercised their option. It is the contention of
        the State of Gujarat that the tribals in large number have responded positively
        to the re-settlement package offered by that state.

              In Madhya Pradesh, the agricultural lands of the tribal villages are           G
        affected on an average to the extent of 28% whereas in the upper reaches i.e.
        Nimad where the agriculture is advanced, the extent of submergence, on an
        average, is only 8.5%. The surveys conducted by HMS Gour University
..,     (Sagar) the Monitoring and Evaluation Agency, set up by Government of
        Madhya Pradesh, reveals that the major resistance to relocation is from the          H
     186                     SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A richer, non-tribal families ofNimad who fear shortage of agricultural labour if
     the landless labourers from the areas accept re-settlement.

           The displacement of the people due to major river valley projects has
    occurred in both developed and developing countries. In the past, there was
B   no definite policy for rehabilitation of displaced persons associated with the
    river valley projects in India. There were certain project specific programmes
    for implementation on temporary basis. For the land acquired, compensation
    under the provisions of Land Acquisition Act, 1~94 used to be given to the
    project affected families. This payment in cash did not result in satisfactory
    resettlement of the displaced families. Realising the difficulties of displaced
C   persons, the requirement of relief and rehabilitation of PAFs in the case of
    Sardar Sarovar Project was considered by the Narmada Water Disputes Tribunal
    and the decision and final order of the Tribunal given in 1979 contains
    detailed directions in regard to acquisition of land and properties, provision
    for land, house plots and civic amenities for the re-settlement and rehabilitation
    of the affected families. The re-settlement policy has thus emerged and
D   developed along with Sardar Sarovar Project.

           The Award provides that every displaced family, whose more than 25%
     of agricultural land holding is acquired, shall be entitled to and be allotted
     irrigable land of its choice to the extent of land acquired subject to ttie
E    prescribed ceiling of the State concerned with a minimum of two hectares
     land. Apart from this land based rehabilitation policy, the Award further
    provides that each project affected persons will be allotted a house plot free
    of cost and re-settlement and rehabilitation grant. The civic amenities required
    by the Award to be provided .at places of re-settlement include one primary
    school for every 100 families, one Panchayat Ghar, one dispensary, one seed
F   store, one children's park, one village pond and one religious place of worship
    for every 500 families, one drinking water well with trough and one tree
    platform for very 50 families; approach road linking each colony to main read;
    electrification; water supply, sanitary arrangement etc. The State Governments       >
    have liberalised the policies with regard to re-settlement and have offered
    packages more than what was provided for in the Award e.g the Governments
G   of Madhya Pradesh; Maharashtra and Gujarat have extended the R&R benefits
    through their liberalised policies even to the encroachers, landless/displaced
    persons, joint holders, Tapu land (Island) holders and major sons· (18 years
    old) of all categories of affected persons. The Government of Maharasthra
    has decided to allot one hectare of agricultural land free of cost even to
H   unmarried major <;laughters of all categories of PAFs.
               NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      187

           In the environmental clearance granted by the Ministry of Environment         A
     and Forests vide its letter dated 24th June, 1987, one of the conditions
     stipulated therein was for information from the project authorities on various


-    action plans including Rehabilitation Master Plan of 1989.

           It is the contention of the . petitioners that the failure to prepare a
     "Master Plan" constitutes non-compliance with the requirement of the
     Tribunal's Award as well as environmental clearance. The Tribunal's Award
                                                                                         B


-    does not use the expression 'Master Plan' but as per clause XI Sub-clause
     IV(2)(iii), what is required, is as under:

             "The three States by mutual consultation shall determine within two
             years of the decision of the Tribunal, the number and general location      C
             of rehabilitation villages required to be established by Gujarat in its
             own territory."

           It is with regard to this clause in the Award that, presumably, the
     aforesaid lettP-r of 24th June, 1987 granting environmental clearance required      D
     the preparation of the new Master Plan.

              In 1988 when the project was first cleared by the Planning Commission
      from investment ~ngle, it was estimated that 12180 families would be atfe:.•..u
       in three States. Based on these numbers, the State Governments independently
      prepared their action plans and announced their R&R policy based on                E
      Tribunal's Award. On the basis of the said action plans the Narmada Control
      Authority submitted Rehabilitation Master Plan to the Ministry of Environment
      and Forests along with its letter dated 3/4.5.1989. Out of the total population,
      which is affected 'by the submergence, large number are tribals and hence
      attention was paid by the State Governments to liberalise their policies for
       protecting the socio-economic and cultural milieu and to extend the R&R           F
      benefits even to other categories of persons who were not covered -by the
      Tribunal's Award. This led to the liberalisation of the R&R packages by the
      three States which packages have been referred to hereinabove. As a result
      of the liberalisation of the packages, the number of PAFs as estimated in 1992
      by the State Governments were 30144. Based on the material available, the          G
    . three State Governments prepared individual action plans in 1993 but those
      action plans were integrated by the Narmada Control Authority first in 1993
      and again in 1995 as an integrated Master Plan to present a holistic picture
      of the R&R programme. The Master Plan deals with socio-economic and
      cultural milieu of PAFs, the legal framework, R&R policy and procedures,
      implementation machinery, organisation for R&R, monitoring and evaluation,         H
     188                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A empowerment of women and youth, special care for vulnerable groups, financial
     plans for R&R etc. As per the 1990 Master Plan the total PAFs have increased
     to 40227 from 30144 due to addition of l 00 more genuine PAFs in Maharashtra.
     This Master Plan includes village-wise, category-wise PAFs and their preference
     in R&R to settle in home State or in Gujarat.

B         The reason for increase in number of PAFs has been explained in the
     Master Plan and the reasons given, inter a/ia, are:

             (a)   After CWC prepared backwater level data, the number of PAFs
                   in Madhya Pradesh (MP) increased by 12000 PAFs as their
                   houses are affected in a l in I 00 years flood.
c
             (b)   Government of Gujarat (GOG) included major sons of the dyke
                   villages as PAFs.

             (c)   Cut off date for major sons was extended by GOG and
                   Government of Maharashtra (GOM).
D                                                                                        ...
             (d)   PAFs affected in MP, have increased due to delay in publication
                   of Section 4 notification under the Land Acquisition Act.

             (e)   Persons socially or physically cut off due to impounding of
                   water in reservoir, are also considered as PAFs by all the three
E                  States.

             (f)   All the three States decided to consider encroachers as PAFs.

             (g)   Major unmarried daughters in Maharashtra are considered as a
                   separate family by Government of Maharashtra.

F            (h)   Some genuine PAFs were earlier left out (as many stayed in
                   remote areas or used to undertake seasonal migration to towns
                   and developed areas in search of casual work).

           As far as the State of Gujarat is concerned, its contention is that the
    task of R&R is not impossible as recognised by the FMG-l in its 1994 report
G   and according to the State, it is fully ready and prepared to re-settle in Gujarat
    all the PAFs upto FRL 455 ft.

         On 13th November, 1996, a meeting of the Review Committee of the
    Narmada Control Authority chaired by the Union Minister of Water Resources
H   was held. This meeting was attended by the Chief Ministers of all the States
              NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      189

     including Rajasthan and representatives of Ministry of Environment and            A
     Forests, Ministry of Social Justice and Empowerment, Government of India.
     In the meeting it was unanimously decided that the reviews of the

-    implementation of re-settlement and rehabilitation measures will be undertaken
     for every five meter height of the dam jointly. by the concerned R&R Sub-
     group and Environmental Sub-group so that work could progress pari passu          B
     with the implementation measurers. In its meeting held on 6th January, 1999,

-·   R&R Sub-Group of Narmada Control Authority observed that arrangements
     made by the States for R&R of the balance families pertaining to the dam
     height EL 90 meter were adequate and a meeting of the party States should
     be convened shortly to finalise the action plan. Pursuant thereto a special
     Inter-State Meeting was convened under the chairmanship of the Secretary          C
     to the Government of India, Ministry of So:ial Justice and Empowennent on
     21st January, 1999 at New Delhi and action plan for re-settl~ment and
     rehabilitation for balanced families of dam height EL 90 meter was finalised
     for implementation by the States. It is the case of the State of Gujarat that
     it had issued notices and made offers in January, 1998 to PAFs affected at
     RL 90 meter in connection with the selection of land and their re-settlement      D
     in Gujarat. According to it, even in respect of PAFs affected at RL 95 meter,
     notices were issued in January, 1999 and to the PAFs included in the
     subsequent list, notices were issued in September 1999. The process of land
     selection by PAFs who had opted to resettle in Gujarat at RL 95 meter was
     already started. According to the Union of India, the Master Plan was under       E
     implementation and the progress of R&R at various elevations of dam viz. EL
     90 meter, EL 95 meter, EL 110 meter and FRL 138.68 meter has been made.

           The measures which have been implemented for sustainable development
     with regard to preserving the socio-cultural environment of the displaced
                                                                                       F~
     persons in the States of Maharashtra, Gujarat and Madhya Pradesh are stated
     to be as follows:

            * Three choices to the people for the selection of relocation sites.
            * Integration of the displaced person with the neighbouring villages
            by organising medical check-up camps, animal husbandry camps,              G
            festivals, eye camps, rural development seminar for village workers
            etc.

             * Establishment of rehabilitation committees at different levels.
            * Respect of traditional beliefs, rituals and rights at the starting of H
     190                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A            house construction, the day and time of leaving the old house and
             village and the day and time of occupying the new house etc.
             * The sacred places at the native villages are being recreated along
             with their settlements at new sites.                                             ....
                                                                                              I

             * Installation of all the religious deities with the due consultation of
B            religious heads.
                                                                                          •
             * Promotion of cultural milieu viz. Social festivals, religious rights,
             rights of passage, presence of priests, shaman, kinsmen, clansmen etc.
                                                                                              -
             * Special consideration for the preservation of holistic nature of the
                         0
C            culture.

             * P_roper use of built-in-mechanism of cultural heritage of the displaced
             persons.

             * Launching of culturally appropriate development plan.
D            * Genuine representation of the traditional leader."
            The Tribunal had already made provision of various civic amenities
    which were further liberalised by the State Governments during implementation.
    The exist~ng development programmes were strengthened for ensuring
    sustainable development at the rehabilitation sites. These were Integrated
E   Rural Development Programme (IRDP) for agriculture, business and village
    industries; Integrated Child Development Scheme (ICDS) for nutrition, health
    and education; Jawahar Rojgar Yojna (JRY); aids for improved seeds, fertilizers,
    irrigation, animal husbandry; Training Rural Youth for self-employment
    (TRYSEM); Employment Guarantee Scheme (EGS), Social Assistance; Industrial
F   Training Institute (ITI); Tribal Development Programme (TOP), financial benefits
    to the backward classes, economically weaker sections, tribals and other
    backward classes (OBC), eye camps, subsidies to farmers (seed, tractorisation,
    fertilizers, diesel, etc.) agricultural prices support subsidy etc.

           Other benefits which were extended for improving the quality of life of
G the re-settled PAFs included fodder farm, mobile sale, shop of fodder, seeds
    cultivation training, initial help in land preparation for agricultural activities,
    better seeds and fertilizers, access to finance, special programme for women
    in the traditional skills enterpreneurship development, employment skill
    formation, different plantation programmes, special emphasis for pasture
    management, environment awareness and education programme, programmes
H   for bio-gas/smokeless chulhas, safe drinking water supply, electricity, lift
             NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                        191
    irrigation, fertilizers kit distribution, gypsum treatment of soil etc.              A
           The project authorities in these three States of Madhya Pradesh, Gujarat
    and Maharashtra represented that comprehensive health care was available
    in tribal areas where the displaced families had been re-settled. It was contended
    that extensive preventive health measures like mass immunization, anti-malaria       B
    programme, family welfare programmes, child development schemes etc. had
    been undertaken. What is important is that primary health centres were
    established at relocation sites for all necessary health facilities to the PAFs.

           The submission on behalf of Union of India was that there was a well-
    established mechanism of Government of India for coordination and monitoring C
    of Re-settlement & Rehabilitation (R&R) programmes in case of Sardar Sarovar
    Project. The R&R Sub-group and Rehabilitation Committee of Narmada Control
    Authority are responsible for applying its independent mind on R&R. The



-
    Sub-group convenes its meeting regularly to monitor and review the progress
    of R&R while Rehabilitation Committee visits the submergence area'i/relocation
    sites to see whether the rehabilitation is taking place physically and to hear D
    the individual problems of the PAPs. The R&R group, keeping in view the
    progress of relief and rehabilitation, has not permitted the height to be raised,
    until and unless it is satisfied that adequate satisfactory progress has been
    made with regard to R&R. Whereas at an earlier point of time in \ 994, the
    construction schedule had required the minimum block level to be raised to E
    85 meters, the R&R Sub-group had permitted the same to be raised to EL 69
    meter only during that period to match the R&R activity. It was in the meeting
    of R&R Sub-group on 6th January, 1999 after the R&R Sub-group had reviewed
    the progress and had satisfied itself that the land for re-settlement in Gujarat,
    Maharashtra and Madhya Pradesh, which were available, was more than
    required for the re-settlement of the balanced PAFs that it cleared the F
    construction upto the dam height EL 90 meters. The action plan for the same
    had been approved and is under implementation by the States concerned.

          The petitioners had contended that no proper surveys were carried out
    to determine the different categories of affected persons as the total number        G
    of affected persons had been shown at a much lower side and that many had
    been denied PAF status. From what is being stated hereinabove, it is clear
    that each State has drawn detailed action plan and it is after requisite study
    had been made that the number of PAFs have been identified. The number
    has substantially increased from what was estimated in the Tribunal's Award.
    The reason for the same, as already noticed, is the liberalisation of the R&R        H
     192                       SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A packages by the State Governments. Except for a bald assertion, there appears
     to be no material on which this Court can come to the conclusion that no
     proper surveys had been carried out for determining the number of PAFs who
     would be adversely affected by the construction of the dam.

           Re-settlement and rehabilitation packages in the three States were
B different due to different geographical, local and economic conditions and
    availability of land in the States. The liberal packages available to the Sardar
    Sarovar Project oustees in Gujarat are not even available to the project
    affected people of other projects in Gujarat. It is incorrect to say that the
    difference in R&R packages, the package of Gujarat being the most liberal,
C   amounts to restricting the choice of the oustees. Each State has its own
    package and the oustees have an option to select the one which was most
    attractive to them. A project affected family may, for instance, chose to leave
    its home State of Madhya Pradesh in order to avail the benefits of more
    generous package of the State of Gujarat while other PAFs similarly situated
    may opt to remain at home and take advantage of the less liberal package of
D   the State of Madhya Pradesh. There is no requirement that th~ liberalisation
    of the packages by three States shquld be to the same extent and at the same
    time, the States cannot be faulted if the package which is offered, though not
    identical with each other, is more liberal than the one envis·aged in the
    Tribunal's Award.
E
            Dealing with the contention of the petitioners that there were large
     number of persons who were living in the submergence area and were not
     farmers and would lose their livelihood due to loss of the community and/or
     loss of the river and were not being properly rehabilitated, Mr. Harish Salve,
     learned Senior Counsel contended that this averment was not true. According
F   to him, all the families in the 105 hilly tribal villages were agriculturists,
    cultivating either their own land or Government land and all of whom would
    be eligible for alternative agricultural land in Gujarat. Only a small number of
    non-agriculturists, mainly petty shopkeepers were found in these villages of
    tribal areas. In Gujarat there were 20 such non-agriculturists families out of
G   a total of 4600 affected families and all of these had been re-settled as per their
    choice so that they could restart their business. In Maharashtra out of 3213
    affected families, not a single family was stated to fall under this category.
    Amongst the affected families of Madhya Pradesh, the figure of such non-
    agriculturists family was also stated to be not more than couple of l 00. In our
    opinion it is neither possible nor necessary to decide regarding the number
H   of people likely to be so affected because all those who are entitled to be
                  NARMADA BACHAO ANDOLAN v. U.0 .1. [KIRPAL, J.]                      193
        rehabilitated as per the Award will be provided with benefits of the package         A
        offered and chosen.

              With regard to the colony affected people whose 1380 acres of land was
        acquired in six villages for the construction of a colony, most of th~ landholders
        had continued to stay in their original houses and about 381 p·ersons were           B
        stated to have been provided permanent employment in the project works. At
        the time, the land was acquired in I 962-63, compensation was paid and in
        addition thereto, the Government of Gujarat devised a special package in
        August, 1992 providing ex-gratia payment upto Rs. 36000.00 to the land losers
        for purchase of productive assets or land for those who had not received
        employment in the project.                                                           C

               Dealing with the contention of the petitioners that there will be 23500
        canal affected families and they should be treated at par to that of oustees

    -   in the submergence area, the respondents have broadly submitted that there
        is a basic difference in the impacts of the projects in the upstream submergence
        area and its impacts in the beneficiary zone of the command area. While              D
        people, who were oustees from the submergence zone, required re-settlement
        and rehabilitation, on the other hand, most of the people falling under the
        command area were in fact beneficiaries of the projects and their remaining
        land would now get relocated with the construction of the canal l_eading to
        greater agricultural output. We agree with this view and that is why, in the         E
        Award of the Tribunal, the State of Gujarat was not required to give to the
        canal affected people the same relief which was required to be given to the
        oustees of the submergence area.

               Dealing with the contention of the petitioners that the oustees were not
        offered a chance to re-settle in Gujarat as a community and that there was a         p
        clear requirement of village-wise communication rehabilitation which had not
        been complied with, the contention of the respondents was that no provision
        of Tribunal's Award had been shown which caused any such obligation on
        the Government of Gujarat. What the Award of the Trib1,mal required is re-
1       settlement of the PAFs in Gujarat at places where civic amenities like dispensary,
        schools, as already been referred to hereinabove, are available.                     G
               Subsequent to the Tribunal's Award, on the recommendation of the
        World Bank, the Government of Gujarat adopted the principle of re-settlement
        that the oustees shall be relocated as village units, village sections or families
        in accordance with the outstees preference. The oustees' choice has actively
        guided the re-settlement process. The requirement in the Tribunal's Award            H
     194                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A was that the Gujarat shall establish rehabilitation villages in Gujarat in the
     irrigation command of the Sardar Sarovar Project on the norms mentioned for
     rehabilitation of the families who were willing to migrate to Gujarat. This
     provision could not be interpreted to mean that the oustees families should
     be resettled as a homogeneous group in a village exclusively set up for each
    such group. The concept of community wise re-settlement, therefore, cannot
B   derive support from the above quoted stipulation. Besides, the norms referred
    to in the stipulation relate to provisions for civic amenities. They vary as
    regards each civic amenity vis-a-vis the number of oustees families. Thus, one
    panchayat ghar, one dispensary, one childrens' park, one s.eed store and one
    village pond is the norm for 500 families, one primary school (3 rooms) for 100
C   families and a drinking water well with trough and one platform for every 50
    families. The number of families to which the civic amenities were to be
    provided was thus not uniform and it was not possible to derive therefrom
    a standardised pattern for the establishment of a site which had nexus with
    the number of oustees' families of a particular community or group to be
    resettled. These were not indicators envisaging re-settlement of the oustees
D   families on the basis of tribes, sub-tribes, groups or sub-groups.

           While re-settlement as a group in accordance with the oustees preference
    was an important principle/objective, the other objectives were that the oustees
    should have improved or regained the standard of living that they were
E   enjoying prior to their displacement and they should have been fully integrated
    in the community in which they were re-settled. These objectives were easily
    achievable if they were re-settled in the command area where the land was
                                              •
    twice as productive as the affected land and where large chunks of land were
    readily available. This was what the Tribunal's Award stipulated and one
    objective could not be seen in isolation of the other objectives.
F
          The Master Plan, 1995 of Narmada Control Authority also pointed out
    that "~he Bhils, who are individualistic people building their houses away
    from one another, are getting socialised; they are learning to live together".
    Looking to the preferences of the affected people to live as a community, the
    Government of Gujarat had basically relied on the affected families' decision
G   as to where they would like to relocate, instead of forcing them to relocate
    as per a fixed plan.

          The underlined principle in forming the R&R policy was not merely of
    providing land for PAFs but there was a conscious effort to improve the living
H   conditions of the PAFs and to bring them into the mainstream. If one compares
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                       195

the living conditions of the PAFs in their submerging villages with the             A
rehabilitation packages first provided by the Tribunal's Award and then
 liberalised by the States, it is obvious that the PAFs had gained substantially
after their re-settlement. It is for this reason that in the Action Plan of 1993
of the Government of Madhya Pradesh it was stated before this Court that
"therefore, the re-settlement and rehabilitation of people whose habitat and        B
environment makes living difficult does not pose any problems and so the
rehabilitation and re-settlement does not pose a threat to environment". In the
affidavit of Dr. Asha Singh, Additional Director (Socio & CP), NVDA, as
produced by the Government of Madhya Pradesh in respect of visit to R&R
sites in Gujarat during 21st to 23rd February, 2000 for ascertaining the status
relating to grievances and problems of Madhya Pradesh PAFs resettled in             C
Gujarat, it was, inter alia, mentio'1ed that "the PAFs had informed that the
land allotted to them is of good quality and they take the crops of Cotton,
Jowar and Tuwar. They also stated that their status has improved from the
time they had come to Gujarat but they want that water should start flowing
in the canals as soon as possible and in that case they will be able to take
three crops in one year as their land is in the command area." Whereas the          D
conditions in the hamlets, where the tribals lived, were not good enough the
rehabilitation package ensured more basic facilities and civic amenities to the
re-settled oustees. Their children would have schools and children's park,
primary health centre would take care of their health and, of course, they
would have electricity which was not a common feature in the tribal villages.       E

      Dealing with the contention of the petitioners that there was no provision
for grazing land and fuel wood for the PAFs, it is rightly contended by the
State of Gujarat that grazing land was not mandated or provided for in the
Tribunal's Award but nevertheless, the grazing land of six villages was available
for use of PAFs. It may be that the grazing land was inadequate but this            F
problem will be faced by the entire State of Gujarat and not making such land
available for them does not in any way violate any of the provisions of the
Award.

       With regard to providing irrigation facilities, most of the re-settlement G
of the project affected families were provided irrigation facilities in the Sardar
Sarovar Project command area or in the command areas of other irrigation
projects. In many of the out of command sites, irrigated lands were purchased.
In cases where the irrigation facilities were not functioning, the Government
of Gujarat had undertaken the work of digging tubewells in order to avoid any
difficulty with regard to irrigation in respect of those oustees who did not H
     196                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R ..

A have adequate irrigation facilities. It was contended that because of the delay
     in the construction of the project, the cut off date of I st January~ 19'i!7 for
     extending R&R facilities to major sons were not provided. The Tribunal's
     Award had provided for land for major sons as on, 16.8.1978. The Government
     of Gujarat, however, extended this benefit and offered rehabilitation package
B    by fixing the cut off date of 1.1.1987 for granting benefits to major sons.
     According to the Tribunal's Award, the sons who had become major one year
     prior to the issuance of the Notification for land acquisition ·were entitled to
     be allotted land. The Land Acquisition Notification had been issued in 1981-
    82 and as per the Award, it was only those sons who had become major one
    year prior to. that date who would have become eligible for allotment of land.
C    But in order to benefit those major sons who had attained majority later, the
    Government of Gujarat made a relaxation so as to cover all those who became
    major upto 1.1.1987. The Government of Gujarat was under no obligation to
    do this and would have been quite within its right mer~ly to comply with the
    provisions of the Tribunal's Award. This being so, relaxation of cut off date
    so as to give extra benefit to those sons who attained age of majority at a
D   later date, cannot be faulted or criticised.

            Dealing with the contention of the petitioners that there is a need for
     a review of the project and that an independent agency should monitor the
     R&R of the oustees and that no construction should be permitted to be
E    undertaken without the clearance of such an authority, the respondents are
     right in submitting that there is no warrant for such a contention. The
     Tribunal's Award is final and binding on the States. The machinery of Narmada
     Control Authority has been envisaged and constituted under the Award
     itself. It is not possible to accept that Narmada Control Authority is not to
     be regarded as an independent authority. Of course some of the members are
F    Government officials but apart from the Union of India, the other States are
    also represented in this Authority. The project is being undertaken by the
    Government and it is for the Governmental authorities to execute the same.
    With the establishment of the R&R Sub-group and constitution of the
    Grievances Redressal Authorities by the States of Gujarat, Maharashtra and
G   Madhya Pradesh, there is a system in force which will ensure satisfactory re-
    settlement and rehabilitation of the oustees. There is no basis for contending
    that some outside agency or National Human Rights Commission should see
    to the compliance of the Tribunal Award.

                 MONITORING OF REHABILITATION PROGRAMME
H          The Ministry of Water Resources, Government of India is the Nodal
             NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                       197

    Ministry for the Sardar Sarovar Project and other Union Ministries involved A
    are the Ministries of Environment and Forests and Social Justice and
    Empowerment. As a consequence of the Tribunal's Award, Narmada Control
    Authority was created to co-ordinate and oversee the Q¥erall work of the
    project and to monitor the R&R activities including environmental safeguard
    measures. The Review Committee of the Narmada Control Authority consists
    of the Union Minister of Water Resources as its Chairman, the Union Ministry B
    of Environment and Forests and the Chief Ministers of Gujarat, Madhya
    Pradesh, Maharashtra and Rajasthan as Members. This Review Committee
    may suo moto or on the application of any party State or the Secretary,
    Ministry of Environment and Forests review any decision of the Narmada
    Control Authority. In the Narmada Control Authority, Re-settlement & C
    Rehabilitation (R&R) Sub-group has been created for closely monitoring the
    R&R progress. This Sub-group is headed by the Secretary, Government of
    India, Ministry of Social Justice & Empowerment and is represented by
    Members/Invitees of participating States, academic institutions having expertise
    in R&R, independent socio-anthropological experts and non-Governmental
    Organisations. The functions of this Sub-group are as follows:                   D
            I.   To monitor the progress of land acquisition in respect of
                 submergence land of Sardar Sarovar Project and Indira (Narmada)
                 Sagar Project (ISP).

           2.    To monitor the progress of implementation of the action plan of        E
                 rehabilitation of project affected families in the affected villages
                 of SSP and ISP in concerned states.

           3.    To review the R&R action plan from time to time in the light of
                 results of the implementation.

-          4.    To review the reports of the agencies entrusted by each of the
                 State in respect of monitoring and evaluation of the progress in
                                                                                        F

                 the matter of re-settlement and rehabilitation.

            5.   To monitor and review implementation of re-settlement and
                 rehabilitation programmes pari passu with the raising of the dam
                 height, keeping in view the clearance granted to ISP and SSP
                                                                                        G
                 from environmental angle by the Government of India and the
                 Ministry of Environment a~d Forests.

           6.    To coordinate states/agencies involved in the R&R programmes
                 of SSP and ISP.
                                                                                        H
        198                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

  A             7.    To undertake any or all activities in the matter of re-settlement
                      and rehabilitation pertaining to SSP and ISP.
                                  REHABILITATION COMMITIEE

              This Court vide order dated 9.8.1991 in B.D. Sharma v. Union of India
  B and others, [ 1992] Suppl. 3 sec 93 directed the formation of a Committee
       under the chairmanship of the Secretary, Ministry of Social Justice &
        Empowerment, Government of India to visit the submergence areas/re-
       settlement sites and furnish the rel?ort of development and progress made in
       the matter of rehabilitation. The Rehabilitation Committee headed by the
       Secretary, Government of India, Ministry of Social Justice and Empowerment
  C    and having representatives of the three State Governments as its members
       had been constituted. It is the case of the Union of India that this Committee
       visited regularly the various R&R sites and submergence villages in the three
       States and submitted reports to this Court from time to time. By order dated
       24th October, 1994, this Court in the aforesaid case of B.D.Sharma (supra)
       observed that all the directions issued by the Court from time to time have
  D    been complied with and nothing more be done in the petition and the petition
       was disposed off. Most of the recommendations/observations as made by
       this Committee are stated to have been complied fairly by the States concerned.

              In addition to the above, the officials of the Narmada Control Authority
.. E   are also stated to be monitoring the progress ofR&R regularly by making field
       visits. The individual complaints of the PAFs are attended and brought to the
       notice of the respective Governments.

                            GRIEVANCES REDRESSAL MECHANISM

 F            The appeal mechanism has been established in the policy statements by
       all the three State Governments for the redressal of grievances of the PAFs.
       According to this mechanism, if a displaced person is aggrieved by the
       decision of the Rehabilitation Officers in respect of any R&R process, he may
                                                                                             -
       appeal to the concerned agency/officers .

.G           Vide Resolution dated February 17, 1999, the Government of Gujarat set
       up a high-level authority called "Grievance Redressal Authority (GRA)" before
       whom the oustees already re-settled and to be re-settled in Gujarat could
       ventilate their grievances for redressal after their re-settlement till the process
       of re-settlement and re-habilitation is fully completed. The said Grievances
       Redressal Authority has Mr. Justice P.O. Desai, retired Chief Justice as its
 H     Chairman. This machinery had been established to:
                NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      199

               (A) create an Authority before whom oustees who have re-settled            A
                   in the State of Gujarat can ventilate their grievances relating to


...                the R&R measures taken by the State of Gujarat;

               (B) ensure that the oustees already settled and the oustees settled
                   hereinafter in the R&R sites created for re-settlement and
                   rehabilitation of the oustees from the States of Madhya Pradesh        B
                   and Maharashtra receive all the benefits and amenities in
                   accordance with the Award and the various Government
                   resolutions made from time to time;

               (C) ensure that Gujarat oustees re-settled in Gujarat have received
                   all the benefits and amenities due to them.                            c
             The Gujarat Rehabilitation Authority has installed a permanent in-house
       Grievances Redressal Cell (GRC) within Sardar Sarovar Punarvasavat Agency.
       The Grievances Redressal Cell deals with the grievances of the PAFs and the
       grievances redressal is undertaken by it in the following three ways.
                                                                                          D
               (i)    Grievances Redressal Cell deals grievances in the regular course
                      on the basis of applications i.e. by holding enquiries and
                      implementing decisions taken pursuant thereto.
               (ii)   Grievances redressal on the spot though mechanism of Tatkal
                      Fariyad Nivaran Samiti.,
                                                                                          E
               (iii) Grievances redressal under the mechanism of Single Window
                     Clearance System.

             Grievances Redressal Authority has surveyed sites in which PAFs have
       been re-settled and has submitted reports to this Court from time to time
       which disclose substantial compliance with the terms of the Award and the          F
       rehabilitation package.

              In its Fourth Report dated 15.11.1999, the Grievances Redressal Authority
       observed "pursuant to the grievances redressal measures taken by GRC,
  ,_
       whose approach is positive and grievance redressal oriented, a considerable        G
       number of grievances have been resolved by extensive land improvement
       work done on agricultural land at different sites within a period of six months
       i.e. April-September, 1999".

            The R&R Sub-group in its 20th field visit of the R&R sites in Gujarat
       on 12/J 3.1.2000 has noted as follows:                                             H
     200                      SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A           "The Committee after the visit and from interaction with the PAFs,
            concluded that there is vast improvement in the conditions of PAFs
            at these R&R sites as compared to the grievances reported for the
            same sites during previous visits by the Committee/NCA officers.
            Assessing the perception of PAFs the Committee observed that the
            majority of PAFs are happy and joining mainstream of country's
B           development".

          The Grievances Redressal Cell has dealt with and decided a total of
    over 6500 grievances.

C           At the instance of Grievances Redressal Authority, an Agricultural Cell
     is set up in Sardar Sarovar Punarvasavat Agency with effect from 1st July,
     1999. This was done with an objective of enhancing the productivity of
    agricultural land allotted to PAFs by adopting of suitable farm management
    practices and in assisting in resolving land related grievances. Similarly, w.e.f.
    1.5.1999, Medical Cells have been set up in Sardar Sarovar Punarvasavat
D   Agency for ensuring effective functioning of medical infrastructure and
    providing organised system of supervising and monitoring and also for
    conducting health survey-cum-medical check up activities. The Grievance
    Redressal Authority has become an effective monitoring and implementing
    agency with regard to relief and rehabilitation of the PAFs in Gujarat. Apart
E   from resolving independent grievances of PAFs and enforcing the compliance
    of the provisions of the Award through its exhaustive machinery and
    mechanism, it is also trying to guide in respect of various other issues not
    covered by the provisions of the Award such as

            (i) Vocational training of the oustees;
F           (ii) Review of Narmada oustees employment opportunity rules;

            (iii) Issue relating to Kevadia Colony;

            (iv) Issue relating to tapu land;

G           (v) Development of Kevadia as a tourist centre etc.

          In Maharashtra, a local. committee was constituted comprising of
    Additional Collector (SS), Divisional Forest Officer, Re-settlement Officer and
    two representatives of the oustees nominated by the local Panchayat Samities
    from among the elected members of the village panchayats in the project
H   affected villages/taluka. This Committee is required to examine the claims of
         NARMADA BACHAO ANDOLAN v. U.O.I. [KIRPAL, J.]                      201

the PAFs and give directions within a time frame and an appeal from its            A
decision lies to the Commissioner. In addition thereto, vide notification dated
 17th April, 2000 the Government of Maharasthra has set up a Grievances
Redressal Authority in lines established by the State of Gujarat and Mr.
Justice S.P. Kurdukar, retired Judge of this Court, has been appointed as its
Chairman. This Authority is expected to be analogous to the Grievances             B
Redressal Authority of Gujarat.

      In Madhya Pradesh, the grievances of the PAFs have first to be made
by a claim which will be verified by the patwari and then scrutinised by the
Tehsildar. PAFs may file an appeal against the decision ofR&R official before
the District Collector who is required to dispose off the same within a period     C
of three months. In the case of Madhya Pradesh also by Notification dated
30th March, 2000 the Government of Madhya Pradesh has constituted a
Grievances Redressal Authority similar to the one in Gujarat with Mr. Justice
Sohni, retired Chief Justice of Patna High Court as its Chairman.

       INDEPENDENT MONITORING & EVALUATION AGENCIES
                                                                                   D
       The Monitoring and Evaluation of the rehabilitation programme is also
being carried out by the independent socio-anthropological agencies appointed
by the State Governments of Maharashtra, Madhya Pradesh and Gujarat as
well as Narmada Control Authority. These agencies, which are professional
and academic institutes, conduct surveys and in-depth studies relating to          E
PAFs in the submergence and rehabilitation villages. The main object of the
monitoring is oriented towards enabling the management to assess the progress,
identify the difficulties, ascertaining problem areas, provide early warning and
thus call for corrections needed immediately.

      The Center for Social Studies, Surat is the monitoring agency for the        F
Government of Gujarat. This Institute has prepared 24 six monthly progress
reports in relation to the re-settlement of PAFs of submergence villages of
Gujarat. Similarly for the project affected families of Madhya Pradesh/
Maharashtra who have re-settled in Gujarat, the Government of Gujarat has
appointed the Gujarat Institute of Development Research, Ahmedabad as the          G
independent Monitoring and Evaluation Agency for monitoring R&R
programmes.

      In Madhya Pradesh the monitoring and evaluation had been carried out
by Dr. H.S. Gaur University, Sagar and the same has been dis-engaged now
and a new agency is being appointed. The findings of Dr. H.S. Guar University,     H
    202                       SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A   Sagar indicated that displaced families in Madhya Pradesh are, by and large,
    happy with the new re-settlement in Gujarat and one of the main reason
    behind their happiness was that the shifting from hamlets had changed their
    socio-economic status.

B          In Maharashtra the monitoring and evaluation was earlier being done
    by the Tata Institute of Social Sciences, Mumbai. This agency had reported
    that overall literacy rate among project affected persons above six years of
    age is about 97%, while illiteracy in submergence villages was rampant.
    Further more the report showed that in the submergence villages, the tribals
    mostly relied on traditional healers for their ailments. Now the current scenario
C   is that at R&R sites, health centres and sub-centres have been established.

          It is thus seen that there is in place an elaborate network of authorities
    which have to see to the execution and implementation of the project in terms
    of the Award. All aspects of the project are supervised and there is a Review
    Committee which can review any decision of the Narmada Control Authority
D   and each of the three rehabilitating States have set up an independent
    Grievances Redressal Authority to take care that the relief and rehabilitation
    measures are properly implemented and the grievances, if any, of the oustees
    are redressed.
                                                                                         .•
                                                                                             I

E         On 9th.May, 2000, this Court directed the State Governments of Gujarat,
    Madhya Pradesh and Maharashtra to file affidavits disclosing the latest
    status of re-settlement and rehabilitation work for the existing as well as
    prospective oustees likely to be affected by raising the height of the dam.
    Pursuant to the said direction affidavits on behalf of the three States have
    been filed and, in response thereto, the petitioners hav~ also filed an affidavit.
F
          On behalf of the State of Gujarat the affidavit of Sh. V.K. Babbar,
    Commissioner (Rehabilitation) and Chief Executive Officer, Sardar Sarovar
    Punavasvat Agency [SSPA] has been filed, according to which at FRL 138.68
    m. the status with regard to PAFs to be re-settled is stated to be as follows:

G         State           Total number of PAFs               Balance PAFs to be          ~


                          resettled/allotted agricultural    resettled in Gujarat        '
                          land in Gujarat

      Gujarat                 4575                                 25
H
                                   ..
           NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, .I.]                     203
   Maharashtra               710                               290                    A
   Madhya Pradesh           3280                            10450

   Total                    8565                            10765

      It is the case of State of Gujarat that 8565 PAFs have been accommodated        B
in 182 R&R sites fully equipped with the requisite civic amenities as provided
by the Tribunal's award. The agricultural land allotted to these PAFs is 16973
hectares.

      Dealing specifically with the status of PAFs at RL 90 mtr., 95 mtr. and
110 mtr. it is averred in the said affidavit that all the PAFs of Gujarat at RL       C
90 mtr. have been re-settled and the balance PAFs of Madhya Pradesh and
Maharashtra affected at RL 90 mtr. have already been offered R&R package
in Gujarat. The process of re-settlement is continuing and reliance is placed
on the observation of the GRA which has stated in its Fourth Report dated
15th November, 1999 that "There is substantial compliance of the Re-settlement        D
and Rehabilitation measures as mandated by the Final Report of NWDT,
including provision of civic amenities, and also of all the inter-linked provisions
of the Government of Gujarat and that, therefore, PAFs from the States of
Madhya Pradesh and Maharashtra affected upto the height of RL 90 mtr. can
be accommodated as per their choice at these selected 35 sites in Gujarat."
                                                                                      E
      With respect to the PAFs affected at RL 95 mtr. the affidavit states that
the PAFs of Gujarat have already been settled and while the affected PAFs
of Madhya Pradesh and Maharashtra have been offered R&R package in
Gujarat in January 1999, September 1999 and January 2000. The RL 95 mtr.
Action Plan for these PAFs has also been prepared by the Government of
Gujarat in consultation with the Governments of Madhya Pradesh and                    F
Maharashtra and has been sent to the NCA. The case of the State of Gujarat,
therefore, is that all the PAFs wanting to be re-settled in Gujarat have been
offered the package but consent of all the PAFs has not so far been received
but the Government of Gujarat has sufficient land readily available which can
be allotted to the said PAFs as soon as they come and select the same.                G
       With.r~gard to the status of PAFs at RL I IO mtr. all the PAFs of Gujarat
have been re-settled and 276}. PAFs [2642 of Madhya Pradesh and 119 of
Maharashtra] remain to be re-settled in Gajarat and R&R package will be
offered to them before November 2000. The land which is required to be
allotted to them is stated to be around 6074 hectares and the State of Gujarat        H
    204                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A   has in its possession 8146 hectares. The civic amenities in 40 new R&R sites
    ai;e scheduled to be completed by December 2000 and these sites would serve
    to accommodate not only PAFs between RL 95 mtr. and RL 110 mtr. but would
    also serve to accommodate PAFs from submergence villages which would be
    getting affected at levels above RL 110 mtr. The Action Plan giving the
B   village-wise details is said to have been sent to NCA in June 2000 for its
    approval.

           According to the said affidavit the balance number of PAFs remaining
    to be re-settled at Gujarat at FRL 138.68 mtr. is 10765. Taking into account that
    an additional area of 10% towards house plot and common civic amenities
    would be required in addition to the allotment of minimum 2 hectares of
C   agricultural land, the total land requirement per PAF would be approximately
    2.2 hectares. For planning purposes in respect of 10765 PAFs the land
    requirement would be about 23700 hectares. As against this requirement the
    status of land, as per the said affidavit, under different categories with the
    Government of Gujarat is stated to -be as under:
D
    Sr. No.                      PARTICULARS                       Land {Jn ha]

    1.        Land identified (offers received in respect of        15716 ha.
              private land and Government land) !5716 ha.

E   2.        Land available (private land for which price is      480 ha.

              approved by Expert Committee and offer/counter
              offer conveyed and acceptance of land holder
              obtained.          ,
              Land in possession of SSPA/GOG in 12 districts         8416 ha.
F
                                           Total                    24612 ha.

          It is averred that between March and 21st June 2000 the land in
    possession as well as the land identified has increased considerably.
G
           It has also been explained in the said affidavit that the Government of
    Gujarat has a well-established practice of procuring land for R&R at realistic
    market prices for willing sellers. Officers hold discussions with prospective
    sellers, verify the suitability of land and after the prices is settled the same
    is procured through legal process of Land Acquisition Act and consent
H   awards are passed so that the PAPs are assured of undisputed legal title free
              NARMADA BACHAO ANDOLAN v. U.O.I. [KIRPAL, J.]                       205
    from all encumbrances. This process of negotiated purchase has been                  A
    streamlined. At the instance of the GRA, a retired judge of the High Court
    is now appointed as Chairman of the Expert Committee with retired senior
    Government Secretaries as its members. This Expert Committee oversees the
-   exercise of purchase of suitable land at the market price. At the instance of
    the GRA, PAPs are being issued Sanads for the land allotted to them which            B
    will ensure provision of a proper legal document in their favour.

          Dealing with the term of the Award to the effect that Gujarat shall
    acquire and make available a year in advance of the submergence before each
    successive stage, land and house sites for rehabilitation of the oustees
    families from Madhya Pradesh and Maharashtra who are willing to migrate to           C
    Gujarat, the affidavit states that the Gujarat Government has already identified
    sufficient land for accommodating the balance PAFs remaining to be re-settled
    in Gujarat at FRL 138.68 mtr. In respect of PAFs upto RL 110 mtr. Gujarat has
    sufficient land available to meet the R&R requirements but for the PAFs
    above RL 110 mtr. suitable land has already been identified and the same             D
    would be acquired and made available one year in advance of the submergence
    before each successive stage. The affidavit gives reason as to why it is not
    advisable for the State, at this stage, to acquire the total requirement of land
    for FRL in one go. What is stated in the affidavit is as follows:

            (i)    Since at present GOG has sufficient land to meet R&R requirement      E
                   to accommodate PAFs upto RL 110 m, it would not be necessary
                   to acquire further land immediately, especially when the additional
                   land would be required only after the R&R Sub-group and
                   Environment Sub-grouµ give approval for RL 95 m. to RL 110 m.
                   after examining the preparedness at different stages. This would
                   ensure that public money is not unnecessarily blocked for a long      F
                   period.

            (ii)   By acquiring land much before it would be required, problems
                   of illegal trespass are likely to arise.

            (iii) The excess land would, by and large, remain fallow and no              G
                  agricultural production would take place.

            (iv) If the land remains fallow for long the overall productivity of the
                 land would be adversely affected.

            (v) . At the time of allotment, the State Government would again have        H
    206                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A                 to spend a sizeable amount to remove weeds, bushes, small trees
                  etc.

            (vi) The State Government would have to incur a sizeable amount to
                 prevent tampering with the boundary marks, prevent neighbourµtg
                 farmers removing the top soil or from diverting natural drains
B                passing through their fields towards the land purchased for
                 R&Retc.

          The affidavit also gives facts and figures showing that all requisite civic
    amenities have been developed and made available at the R&R sites. Some
C   of the salient features which are highlighted in this behalf ~re as under:

            *     A three-room primary school is provided in all MP/MH sites
                  irrespective of the number of families resettled.

            *    A dispensary with examination room, medical equipment,
                 medicines is provided in all MP/MH sites irrespective of the
D                number of resettled families.

            *    3439 PAFs (86%) out of the total MP/MH PAFs resettled in
                 Gujarat have availed of the Rs.45,000 financial assistance and
                 built pucca core houses.
E           *    Overhead tanks for drinking water are provided in large R&R
                 sites. ?

            *    At the instance of GRA, toilets are being provided in the houses
                 of PAFs with the help ofNGOs.

F         The total cost incurred so far by the Government of Gujarat in providing
    the land and civic amenities upto May 2000 is stated to be 194 crores. The
    Grievances Redressal Cell is stated to have redressed large number of
    grievances of the PAFs whether they were related to land, grant of civic
    amenities or others. The salient features of working of the Grievance Redressal
G   Cell is stated to be as follows:

            *    At present 2 senior IAS officers with supporting staff are working
                 exclusively for redressal of grievances.

            *    A reasoned reply is given to the applicants. The applicant is
H                also informed that if he is aggrieved with the decision he may
            NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.)                   207
               prefer an appeal to GRA within thirty days.                         A
        *      The Single Window Clearance System's main objective is to
               proactively resolve grievances and to avoid delays in inter-
               departmental co-ordination.

        *      Tatkal Fariyad Nivaran Samitis are held in the R&R sites to         B
               resolve grievance of the PAFs in an open forum.

        *      The PAFs are being involved at every stage of grievance
               redressal. The works have been carried out in most cases by the
               PAFs.

        *      The Agriculture Officers of the Agricultural Cell are actively      C
               helping, guiding the PAFs in their agricultural operations and
               upgradfog their skills.

      With a view to effectively rehabilitate and assimilate the PAPs Vasahat
Samitis have been constituted in 165 R&R sites, consisting of 5 PAPs, one          D
of whom is a female. This ensures the participation of the PAPs in the process
of development and these Samitis are vested with the responsibility to sort
out minor problems. With a view to ensure more effective participation in
Panchayat affairs and better integration of PAPs an Order under Section 98
of the Gujarat Panchayats Act, 1993 has been issued by the Government of
Gujarat providing that there shall be upto two invitees from amongst the PAPs      E
depending upon the number of PAPs at the sites in the village Panchayat
within whose jurisdiction the R&R are situated. Pursuant to this 196 PAPs
have been inducted as invitees to then Village Panchayats. The salient features
of the rehabilitation programme of the PAPs are as follows:

        *     PAFs are given productive assets in kind (7000/PAFs) to purchase     F
              bullocks, bullock carts, oil engines etc.

        *     PAFs are given subsistence allowance (Rs.4500/PAF) in cash to
              meet contingency needs in the initial period.

        *     Vocational training is provided to PAFs for improving their income   G
              levels, priority being given to those dependents who. are not
              entitled to be declared as PAFs on their own rights. Tool kits are
              supplied either free or with 50% subsidy.

        *     NGOs are actively involved in all the rehabilitation activities
              such as conducting training classes.                                 H
    208                     SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A           *    PAFs are being covered by the ongoing developmental schemes
                 of the Government (DRDA, Tribal Sub Plan etc.)

            *    An Extension (Agriculture) officers has been appointed for
                 approximately every 150 families to guide them in agriculture
                 operation and assist them in day to day problems (getting ration
B                cards, khedut khatavahis etc.)

            *    In recent years focus is on empowering the PAFs and making
                 them self dependent.

         Medical cell has been set up for providing services and treatment to
C   PAPs free of cost. The cell is headed by Deputy Director (Medical) and is
    having a nucleus of medical experts consisting of a physician, a pediatrician,
    a gynecologist, 21 MBBS doctors, pharmacists etc. The salient features of the
    medical help programme for the benefit of PAPs is stated to be as follows:

            *    The Medical Officers and paramedic staff are making house-to-
D                house visits to motivate the PAPs to come forward to avail of
                 the medical services.

            *    In all dispensaries, a full time multipurpose health worker (female)
                 is available.

E           *    Multi-specialization diagnostic/treatment camps are organised
                 fortnightly, where advance investigations are diagnostic facilities
                 like ECG, X-ray ultrasound are available.

           *     Patients requiring further services are brought to Government
                 hospitals or any other speciality hospital and necessary treatment
                 given free of cost.
F
           *    GOG has placed an order for a mobile medical hospital equipped
                with diagnostic and treatment equipments.

           *    A comprehensive health survey and medical check up covering
                29423 PAPs has been completed. A special record system of
G               family health folder and health profile of each PAP is prepared.

           *    Nutrition supplements are given to children (upto 6 years),
                expectant and lactating mothers through the Integrated Child
                Development Scheme (ICDS).

           *    Special food supplement in the form of ~'Hyderabad Mix" is
H               given to malnourished children and vulnerable target groups.
                NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                      209

               *    School going children are covered under the Mid-Day Meal              A
                    Scheme.

               *    Under TB Control, all chest symptomatic persons are screened
                    by special examinations like sputum microscopy, X-ray, blood
                    tests and persons found positive for TB are given domiciliary
                    treatment under direct observation of doctors or paramedics. In       B

....           *
                    77 cases, treatment is completed and patients are cured .

                    Under preventive health care, health education material is
                    distributed and Health and Cleanliness Shibirs are organized.

               *    A special survey covering physically handicapped and mentally
                                                                                          c
                    retarded persons has been organized and social welfare benefits
                    given.

               *    Other National Health Programmes (maternal child health,


 -
                    immunization, school health check up, family welfare etc.) are
                    regularly conducted.
                                                                                          D
             An Agricultural Cell has been set up in the SSP~ which assists the
       Grievances Redressal Machinery in resolving the problem relating to the
       agricultural land. Th~ salient features of this cell are as follows:

               *    The Agriculture Cell is involved in pu~chasing land, supervision
                    of land improvement works and processing land related                 E
                    grievances of the PAFs.

               *    Agriculture training classes are organized for PAFs in the training
                    institutes of the State Government.

               *    Assistance is given for availing crop-loan credit from banks and      F
                    extension education is imparted in matters of marketing, cropping
                    pattern, use of improved seeds, insecticides and latest equipments.

               *    Afforestation was carried out in 33 R&R sites during 1999-2000
                    by planting 3500 saplings which are protected by bamboo tree-
                    guards. Plantation is done along the roadside, common plots,          G
                    school premises etc. In the remaining sites plantation work is
                    undertaken by NGOs.

             At the instance of GRA an educational cell has been set up in the SSPA.
       The main function of which is to improve the quality of education imparted
       and to improve the school enrolment. The salient features of this cell are as      H
    210                           SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A    under:

                  *    School enrolment which was 4110 in 1998-99, increased to 4670
                       in 1999-2000. Out of the 4670 students enrolled, 2126 were girls
                       (46.3%).

B                 *    The number of schools is 170 and the number of teachers in 384.
                       In the last academic year, 66 schools were upgraded by increasing
                       the number of classes.

              *        SSPA is regularly sending the teachers for in-service training. So
                       far 120 teachers have been imparted training.

c             *        Every year during the period of June to August, a special drive
                       is taken to increase the school enrolment.

              *        In the current year 150 adult education classes have been started
                       in the R&R sites with the help of NGOs.

D             *       An advisory committee has been created to make
                      recommendations on how to improve the education being
                                                                                            -
                      imparted. Members include faculty of MS University, officers of
                      Education Department, Principal of Teacher Training Centre.

           It is further averred in this affidavit that at the instance of GRA a large
E   number of measures have been taken to improve the 0rganisational structure
    of SSPA so as to effectively meet the challenge of R&R and make the R&R
    staff accountable. The salient features of this are stated to be as follows:

              *       A strategic policy decision has been taken to create three separate
                      divisions in SSP A for Rehabilitation, Re-settlement and Planning.
F                     Each division is in charge of a senior level officer of the rank of
                      Additional/Joint Commissioner.

              *       Staff strength in SSPA has been considerably augmented
                      especially at the field lev~I.

G             *       To review the structural and functional aspects of SSPA services
                      of a management consultancy agency (M/s TCS) has been
                      engaged and draft report has been received and is being examined.

              *       A demographic survey is to be conducted to comprehensively
                      document information regarding the PAPs with spec"ial reference
H                     to their family composition, marriage, births; deaths, life
            NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                     211
               expectancy, literacy, customs, culture, social integration etc.       A
        *      Staff is being trai~1ed to sensitize them especially with regard to
               rehabilitation and second-generation issues. Senior level officers
               have been sent for R&R training at Administrative Staff College
               of lndia, Hyderabad.
                                                                                     B
       From the aforesaid affidavit it is more than clear that the GRA, of which
Mr. Justice P.D. Desai, is the Chairman, has seen to the establishment of
different cells and have taken innovative steps with a view to making R&R
effective and meaningful. The steps which are being taken and the assistance
given is much more than what is required under the Tribunal's Award. There
now seems to be a commitment on the part of the Government of Gujarat to C
see that there is no laxity in the R&R of the PAPs. lt appears that the State
of Gujarat has realised that without effective R&R facilities no further
construction of the dam would be permitted by the NCA and under the
guidance and directions of the GRA meaningful steps are being undertaken
in this behalf. lo this connection we may take note of the fact that along with D
the said affidavit Sh. V.K. Babbar, again under the directions of the GRA, has
given an undertaking to this Court, which reads as follows:-

        I.    As per this undertaking, inter alia, in respect of scattered pieces
              or parcels of lands in possession of the SSPA for R&R which
              do not add upto a contiguous block of 7 hectares by themselves         E
              or in conjunction with other lands steps will be taken to purchase
              or acquire contiguous lands so that the said small pieces of land
              become a part of continuous block of 6 hectares or more. This
              exercise will be undertaken and completed on or before 3 lst
              December, 2000. ln case it is not possible to have a contiguous        F
              block of minimum of 6 hectares further directions will be sought
              from GRA or such piece or parcel of land will be put to use for
              other public purposes relating to R&R but which may not have
              been provided for in the NWDT award.

       2.     Henceforth, the land which is acquired or purchased for R&R            G
              purposes shall be contiguous to each other so as to constitute
              a compact block of 6 hectares.
                                                                                         ·,
       3.     Henceforth land to be purchased for R&R will be within a radius
              of 3 kms. from an existing or proposed new site and if there is
              a departure from this policy prior approval of the GRA will be         H
     212                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A                 obtained.

             4.   Demarcation of boundary of 5211 hectares of land whose survey
                  has been undertaken by the GRA and carving out individual
                  plots of 2 hectares for allotment to PAFs will be undertaken and
                  completed on or before 31st December, 2000.
B            5.   The other undertakings relate to soil testing and/or ensuring
                  that suitable land is made available to the PAFs after the quality
                  of land is cleared by the agriculture experts of the Gujarat
                  Agriculture University. With regard to the lands in possession
                  of the SSPA which are low lying and vulnerable to water logging
c                 during monsoon, an un.dertaking has been given that the land
                  has been deleted from the inventory of lands available for R&R
                  unless such lands are examined by the Agricultural Cell ofSSPA
                  and it is certified that the access to these lands is clear and
                  unimpeded and that they are suitable for R&R. Compliance report
                  in this regard is to be submitted to the GRA on or before 31st
D                 December, 2000.

           In addition to the aforesaid undertaking of Sh. V.K. Babbar, undertakings
    of the Collectors ofKhedr, Vadodara, Ahmedabad, Narmada, Panchmahal and
     Bharuch °Districts have also been filed. Apart from reiterating what is contained
E   in the undertaking of Sh. V.K. Babbar, in these undertakings of the Collectors,
    it is stated that necessary mutation entries regarding entering the name of
    SSPA/SSNNL in the village records ofright in respect of the land in possession
    for R&R or PAFs likely to be re-settled in Gujarat have been made but the
    certification of these entries will be completed and the matter reported to the
    GRA before 31st August, 2000. If this is not done the land is to be deleted
F   from the inventory of land available for R&R. Necessary mutation entries in
    the village records or rights regarding removal of encumbrances of original
    landholders shall also be completed by that date.

           From what is noticed hereinabove, this Court is satis.fied that more than
    adequate steps are being taken by the State of Gujarat not only to implement
G   the A ward of the Tribunal to the extent it grants relief to the oustees but the
    effort is to substantially improve thereon and, therefore, continued monitoring
    by this Court may not be necessary.

          On behalf of the State of Madhya Pradesh, in response to this Court's
H   order dated 9th May, 2000, an affidavit of Sh. H.N. Tiwari, Director (TW),
          NARMADA BACHAO ANDOLAN v. U.O.I. [KIRPAL, J.]                       213

  Narmada Valley Development Authority has been filed. It is stated therein that     A
  with a view to arrange re-settlement of the PAFs to be affected at different
  levels detailed instructions to the Field Officers of the submergence area were
  issued by Sh. Tiwari vide letter dated 20th May, 2000 in respect of all the
. aspects of resettlement of the PAFs. This is related to identification of land,
  processing of land acquisition cases and passing of the Award, taking of
  PAFs to Gujarat for selection of land, allotment of land to the PAFs who
                                                                                     B
  decide to remain in Madhya Pradesh and development of sites. There are 92
  sites for re-settlement of the PAFs which are required to be established and
  out of these 18 are stated to be fully developed, development in 23 sites is
  in progress, 18 sites are such where location has been determined and land
  identified but development work has not started and 33 sites are such where        C
  location of land for the development is to be decided by the task force
  constituted for this purpose.

       Dealing specifically with the states of PAFs to be affected at different
 levels this affidavit, inter alia, states that with regard to PAFs to be affected
 at EL 85 mtr. those of whom who have opted to go to Gujarat land.has been           D
 offered to them by the Government of Gujarat, those PAFs who have changed
 their mind and now want to remain in Madhya Pradesh land is being shown
 to them in Madhya Pradesh.

        It has not been categorically stated whether the PAFs who are so             E
 affected have been properly resettled or not. On the contrary, it is stated that
 no Awards in land acquisition cases have been passed in respect of six
 villages and it is only after the Awards are passed that house plots will be
 allotted and compensation paid. The provision for financial assistance for
 purchase of productive assets will be released when the PAFs shift and start
 construction of the houses. The reason for not making the payment in advance        F
 rightly is that if the grants are paid to the oustees before they shift they may
 possibly squander the grant and the State Government may be required to
 pay again to establish them on some self employment venture. For the re-
 settlement of PAFs in Madhya Pradesh out of ten relocation sites mentioned
 in the affidavit only five have been fully developed. It is also stated that 163    G
 PAFs are resisting from shifting to Gujarat under the influence of anti dam
 activists, though they have been given notices containing offer of the land
 and house plots by the Government of Gujarat. In addition thereto 323 PAFs
 who were earlier resisting have now been persuaded and arrangements for
 selection of land for them in Gujarat has been initiated.
                                                                                     H
     214                       SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

 A          With regard to the R&R status of PAFs to be affected at EL 95 mtr. it
     is, inter alia, stated that those losing 25 per cent of their holdings are entitled
     to be allotted cultivable land and notices were given to them to identify the
     land which can be allotted. In the said notice it was stated that the development
     process will be undertaken with regard to the said land only after it is selected
 B   by the PAFs. There is also a mention in the affidavit filed in the name of
     Narmada Bachao Andolan, the petitioner herein, not allowing the State
     Government to conduct survey for demarcation of the submergence area and
     identification of the PAFs to be affected at EL 132.86 mtrs. [436 ft.]. Six out
     of twenty five relocation sites required to be developed have been fully
     developed.
 c
          Affidavit on behalf of the State of Madhya Pradesh draws a picture of
    rehabilitation which is quite different from that of Gujarat. T~ere seems to be
    no hurry in taking steps to effectively rehabilitate the Madhya Pradesh PAFs
    in their home State. It is indeed surprising that even awards in respect of six
    villages out of 33 villages likely to be affected at 90 mtr. dam height have not
D been passed. The impression which one gets after reading the affidavit on
    behalf of the State of Madhya Pradesh clearly is that the main effort of the
    said State is to try and convince the PAFs that they should go to Gujarat
   whose rehabilitation package and effort is far superior to that of the State of
    Madhya Pradesh. It is, therefore, not surprising that vast majority of the PAFs
E of Madhya Pradesh have opted to be re-settled in Gujarat but that does not
   by itself absolve the State of Madhya Pradesh of its responsibility to take·
   prompt steps so as to comply at least with the provisions of the Tribunal's
   Award relating to relief and rehabilitation. The State of Madhya Pradesh has
   been contending that the height of the dam should be lowered to 436 ft. so
   that lesser number of people are dislocated but we find that even with regard
F to the rehabilitation of the oustees at 436 ft. the R&R programme of the State            ....
   is no where implemented. The State is under an obligation to effectively
   resettle those oustees whose choice is not to go to Gujarat. Appropriate
  directions may, therefore, have to be given to ensure that the speed in
  implementing the R&R picks up. Even the interim report of Mr. Justice Soni,              .....
G the GRA for the State of Madhya Pradesh, indicates lack of commitment on
  the States part in looking to the welfare of its own people who are going to
  be under the threat of ouster and who have to be rehabilitated. Perhaps the
  lack of urgency could be because of lack of resources, but then the
  rehabilitation even in the Madhya Pradesh is to be at the expense of Gujarat.
  A more likely reason could be that, apart from electricity, the main benefit of
H the construction of the dam is to be of Gujarat and to a lesser extent to
            NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                  215

Maharashtra and Rajasthan. In a federal set up like India whenever any such A
Inter-State project is approved and work undertaken the States involved have
a responsibility to co-operate with each other. There is a method of settling
the differences which may arise amongst there like, for example, in the case
of Inter-State water dispute the reference of the same to a Tribunal. The
Award of the Tribunal being binding the States concerned are duty bound B
to comply with the terms thereof.

      On behalf of the State of Maharashtra affidavit in response to this
Court's order dated 9th May, 2000, the position regarding the availability of
land for distribution to the PAFs was stated to be as follows:

      (i)    Total land made available by the Forest                             c
             Department                                     4191.86 Hectares

      (ii) Land which could not be allotted at present
            to PAF

             (a) Gaothan land [used residential purposes      209.60 hectares    D
             (b) Land occupied by river/ nallah/hills         795.62 hectares
             (c) Land under encroachment by third parties     434.13 hectares

      ·Therefore, the net land available At present
       for allotment was 4191.86 (-) 1439.35                 2752.51 hectares    E
      Total area of land allotted To 1600 PAFs              2434.01 hectares

      Remaining cultivable land Available with
      the State 2752 - 2434.01                                318.50 hectares
                                                                                 F
 It is further stated in this affidavit that out of 795.62 hectares of forest land
which was reported to be uncultivable the State has undertaken a survey for
ascertaining whether any of these lands can be made available for cultivation
and distribution by resorting to measures like funding, terracing and levelling.
It is estimated that 30 to 40 hectares of land would become available. In
addition thereto the affidavit states that the Government of Maharashtra has G
decided to purchase private land in nearby villages for re-settlement of PAFs
and further that GRA has been established and Justice S.P. Kurdukar, a retired
judge of this Court has been appointed as its Chainnan. It is categorically
stated in this affidavit that the State Government would be in a position to
make these land available to all the concerned project affected families.          H
     216                      SUPREME COURT. REPORTS [2000] SUPP. 4 S.C.R.

A    CONCLUSION

           Water is one element without which life cannot sustain. Therefore, it is
     to be regarded as one of the primary duties of the Government to ensure
     availability of water to the people.

B           There are only three sources of water. They are rainfall, ground ~ater
     or from river. A river itself gets water either by the melting of the snow or
     from the rainfall while the ground water is again dependent on the rainfall or
     from the river. In most parts of India, rainfall takes place during a period of
     about 3 to 4 months known as the Monsoon Season. Even at the time when
C    the monsoon is regarded as normal, the amount of rainfall varies from region
     to region. For example, North-Eastern States of India receive much more
     rainfall than some of other States like Punjab, Haryana or Rajasthan. Dams are
     constructed not only to provide water whenever required but they also help
     in flood control by storing extra water. Excess of rainfall causes floods while
     deficiency thereof results in drought. Studies show that 75% of the monsoon
D    water drains into the sea after flooding a large land area due to absence of
    the storage capacity. According to a study conducted by the Central Water
    Commission in 1998, surface water resources were estimated at 1869 cu km
    and rechargeable groundwater resources at 432 cu km. It is believed that only
    690 cu km of surface water resources (out of 1869 cu km) can be utilised by
    storage. At present the storage capacity of all dams in India is 174 cu km.
E   which is incidentally less than the capacity ofKariba Dam in Zambia/Zimbabwe
    (180.6 cu km) and only 12 cu km more than Aswan High Dam of Egypt.

           While the reservoir of a dam stores water and is usually situated at a
     place where it can receive a lot of rainfall, the canals take water from this
p    reservoir to distant places where water is a scare commodity. It was, of course,
     contended on behalf of the petitioner that if the practice of water harvesting
     is resorted to and some check dams are constructed, there would really be
     no need for a high dam like Sardar Sarovar. The answer to this given by the
    respondent is that water harvesting serves a useful purpose but it cannot
    ensure adequate supply to meet all the requirements of the people. Water
G   harvesting means to collect, preserve and use the rain water. The problem of
    the area in question is that there is deficient rainfall and small scale water
    harvesting projects may not be adequate. During the non rainy days, one of
    the essential ingredients of water harvesting is the storing of water. It will not
    be wrong to say that the biggest dams tb the smallest percolating tanks meant
H   to tap the rain water are nothing but water harvesting structures to function
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                         217
by receiving water from the common rainfall.                                           A
      Dam serves a number of purposes. It stores water, generates electricity
and releases water throughout the year and at times of scarcity. Its storage
capacity is meant to control floods and the canal system which emanates
therefrom is meant to convey and provide water for drinking, agriculture and
industry. In addition thereto, it can also be a source of generating hydro-            B
power. Dam has, therefore, necessarily to be regarded as an infrastructural
project.

      There are three stages with regard to the undertaking of an infrastructural
project. One is conception or planning, second is decision to undertake the
project and the third is the execution of the project. The conception and the          C
decision to undertake a project is to be regarded as a policy decision. While
there is always a need for such projects not being unduly delayed, it is at
the same time expected that as thorough a study as is possible will be
undertaken before a decision is taken to start a project. Once such a considered
decision is taken, the proper execution of the same should be taken                    D
expeditiously. It is for the "Government to decide how to do its job. When it
has put a system in place for the execution of a project and such a system
cannot be said to be arbitrary, then the only role which a Court may have to
play is to see that the system works in the manner it was envisaged.

      A project may be executed departmentally or by an outside agency. The            E
choice has to be of the Government. When it undertakes the execution itself,
with or without the help of another organisation, it will be expected to
undertake the exercise according to some procedure or principles. The NCA
was constituted to give effect to the Award, various sub-groups have been
established under the NCA and to look after the grievances of the resettled
oustees and each State has set up a Grievance Redressal Machinery. Over                F
and above the NCA is the Review Committee. There is no reason now to
assume that these authorities will not function properly. In our opinion the
Court should have no role to play.

      rt is now well-settled that the courts, in the exercise of their jurisdiction,   G
will not transgress into the field of policy decision. Whether to have an
infrastructural project or not and what is the type of project to be undertaken
and how it has to be executed, are part of policy making process and the
Courts are ill equipped to adjudicate on a policy decision so undertaken. The
Court, no doubt, has a duty to see that in the undertaking of a decision, no
law is violated and people's fundamental rights are not transgressed upon              H
         218                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A except to the extent permissible under the Constitution. Even then any
         challenge to such a policy decision must be before the execution of the
         project is undertaken. Any delay in the execution of the project means over
         run in costs and the decision to undertake a project, if challenged after it's
         execution has commenced, should be thrown out at the very threshold on the
B        ground of latches if the petitioner had the knowledge of such a decision and
         could have approached the Court at that time. Just because a petition is
         termed as a PIL does not mean that ordinary principles applicable to litigation
         will not apply. Latches is one of them.

              Public Interest Litigation [PIL] was an innovation essentially to safeguard
C       and protect the human rights of those people who were unable to protect
        themselves. With the passage of time the PIL jurisdiction has been ballooning
        so as to encompass within its ambit subjects such as probity in public life,
        granting of largess in the form of licences, protecting environment and the
        like. But the balloon should not be inflated so much that it bursts. Public
        Interest Litigation should not be allowed to degenerate to becoming Publicity
D       Interest Litigation or Private Inquisitiveness Litigation.

    o          While exercising jurisdiction in PIL cases Court has not forsaken its
        duty and role as a Court of law dispensing justice in accordance with law. It
         is only where there has been a failure on the part of any authority in acting
E       according to law or in non-action or acting in violation of the law that the
        Court has stepped in. No directions are issued which are in conflict with any
        legal provisions. Directions have, in appropriate cases, been given where the
        law is silent and inaction would result in violation of the Fundamental Rights
        or other Legal provisions.

F              While protecti11g the rights of the people from being violated in any
        manner utmost care has to be taken that the C:mrt does not transgress its
        jurisdiction. There is in our Constitutional frame-work a fairly clear demarcation
        of powers. The Court has come down heavily whenever the executive has
        sought to impinge upon the Court's jurisdiction.
                                                                                             ....•   .



G             At the same time, in exercise of its enormous power the Court should
        not be called upon or undertake governmental duties or functions. The Courts
        cannot run the Government nor the administration indulge in abuse or non-
        use of power and get away with it. The essence of judicial review is a
        constitutional fundamental. The role of the higher judiciary under the
H       constitution casts on it a great obligation as the sentinel to defend the values
              NARMADA BACHAO ANDOLAN v. U.0.l. [KIRPAL, J.]                        219

    of the constitution and rights of Indians. The courts must, therefore, act            A
    within their judicially permissible limitations to uphold the rule of law and
    harness their power in public interest. It is precisely for this reason that it has
    been consistently held by this Court that in matters of policy the Court will
    not interfere. When there is a valid law requiring the Government to act in
    a particular manner the Court ought not to, without striking down the law,            B
    give any direction which is not in accordance with law. In other words the
    Court itself is not above the law.

-          In respect of public projects and policies which are initiated by the
    Government the Courts should not become an approval authority. Normally
    such decisions are taken by the Government after due care and consideration.          C
    In a democracy welfare of the people at large, and not merely of a small
    section of the society, has to be the concern of a responsible Government.
    If a considered policy decision has been taken, which is not in conflict with
    any law or is not mala fide, it will not be in Public Interest to require the Court
    to go into and investigate those areas which are.the function of the executive.
    For any project which is approved after du~ ~eliberation the Court should             D
    refrain from being asked to review the decision just because a petitioner in
    filing a PIL alleges that such a decision should not have been taken because
    an opposite view against the undertaking of the project, which view may have
    been considered by the Government, is possible. When two or more options
    or views are possible and after considering them the Government takes a               E
    policy decision it is then not the function of the Court to go into the matter
    afresh and, in a way, sit in appeal over such a policy decision.

          What the petitioner wants the Court to do in this case is precisely that.
    The facts enumerated hereinabove clearly indicate that the Central Government
    had taken a decision to construct the Dam as that was the only solution               F
    available to it for providing water to water scare areas. It was known at that
    time that people will be displaced and will have to be rehabilitated. There is
    no material to enable this Court to come to the conclusion that the decision
    was ma/a fide. A hard decision need not necessarily be a bad decision.
                                                                                          G
           Furthermore environment concern has not only to be of the area which
    is going to be submerged and its surrounding area. The impact on environment
    should be seen in relation to the project as a whole. While an area of land
    wit.I submerge but the construction of the Dam will result in multifold
    improvement in the environment of the areas where the canal waters will
    reach. Apart from bringing drinking water within easy reach the supply of             H
     220                      SUPREM_E COURT REPORTS [2000) SUPP. 4 S.C.R.

A water to Rajasthan will also help in checking the advancement of the Thar
     Desert. Human habitation will increase there which, in tum, will help in
     protecting the so far porous border with Pakistan.

           While considering Gujarat's demand for water, the Government had
     reports that with the construction of a high dam on the river Narmada, water
B    could not only be taken to the scarcity areas of Northern Gujarat, Saurashtra
     and parts of Kutch but some water could also be supplied to Rajasthan.

          Conflicting rights had to be considered. If for one set of people namely
    those of Gujarat, there was only one solution, namely, construction of a dam,
    the same would have an adverse effect on another set of people whose
C   houses and agricultural land would be submerged in water. It is because of
    this conflicting interest that considerable time was taken before the project
    was finally cleared in 1987. Perhaps the need for giving the green signal was
    that while for the people of Gujarat, there was no other solution but to provide
    them with water from Narmada, the hardships of oustees from Madhya Pradesh
D   could be mitigated by providing them with alternative lands, sites and
    compensation. In governance of the State, such decisions have to be taken
    where there are conflicting interests. When a decision is taken by the
    Government after due consideration and full application of mind, the Court is
    not to sit in appeal over such decision.

E          Since long the people of India have been deriving the benefits of the
     river valley projects. At the time of independence, food-grain was being
     imported into India but with the passage of time and the construction of more
    dams, the position has been reversed. The large-scale river valley projects per
    se all over the country have made India more than self-sufficient in food.
     Famines which used to occur have now become a thing of the past. Considering
F   the benefits which have been reaped by the people all over India with the
    construction of the dams, the Government cannot be faulted with deciding to
    construct the high dam on the river Narmada with a view to provide water
    not only to the scarcity areas of Gujarat but also to the small areas of the State
    of Rajasthan where the shortage of water has been there since the time
G   immemorial.

          In the case of projects of national importance where Union of India and/
    or more than one State(s) are involved and the project would benefit a large
    section of the society and there is evidence to show that the said project had
    been contemplated and considered over a period of time at the highest level
H   of the States and the Union of India and more so when the project is
              NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                        221
     evaluated and approval granted by the Planning Commission, then there                 A
     should be no occasion for any Court carrying out any review of the same or
     directing its review by any outside or "independent" agency or body. In a


-
     democratic set up, it is for the elected Government to decide what project
,.
     should be undertaken for the benefit of the people. Once such a decision had
     been taken that unless and until it can be proved or shown that there is a
     blatant illegality in the undertaking of the project or in its execution, the Court   B
     ought not to interfere with the execution of the project.

            Displacement of people living on the proposed project sites and the
     areas to be submerged is an important issue. Most of the hydrology projects
     are located in remote and in-accessible areas, where local population is, like C
      in the present case, either illiterate or having marginal means of employment
     and the per capita income of the families is low. It is a fact that people are
     displaced by projects from their ancestral homes. Displacement of these
     people would undoubtedly disconnect them from their past, culture, custom
     and traditions, but then it becomes necessary to harvest a river for larger
     good. A natural river is not only meant for the people close by but it should D
     be for the benefit of those who ca~ make use of it, being away from it or near
      by. Realising the fact that displacement of these people would disconnect
     them from their past, culture, custom and traditions, the moment any village
     is earmarked for take over for dam or any other developmental activity, the
     project implementing authorities have to implement R&R programmes. The E
     R&R plans are required to be specially drafted and implemented to mitigate
     problems whatsoever relating to all, whether rich or poor, land owner or
     encroacher, farmer or tenant, employee or employer, tribal or non-tribal. A
     properly drafted R&R plan would improve living standards of displaced
     persons after displacement. For example residents of villages around Bhakra
     Nangal Dam, Nagarjun Sagar Dam, Tehri, Bhillai Steel Plant, Bokaro and Bala F
     Iron and Steel Plant and numerous other developmental sites are better off
     than people living in villages in whose vicinity no development project came
     in. It is not fair that tribals and the people in un-developed villages should
     continue in the same condition without ever enjoying the fruits of science and
     technology for better health and have a higher quality of life style. Should G
     they not be encouraged to seek greener pastures elsewhere, if they can have
     access to it, either through their own efforts due to information exchange or
     due to outside compulsions. It is with this object in view that the R&R plans
     which are developed are meant to ensure that those who move must be better
     off in the new locations at Government cost. In the present case, the R&R
     packages of the States, specially of Gujarat, are such that the living conditions H
     222                     SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

A of the oustees will be much better than what they had in their tribal hamlets.
          Loss of forest because of any activity is undoubtedly harmful. Without
    going into the question as to whether the loss of forest due to river valley
    project because of submergence is negligible, compared to de-forestation due
    to other reasons like cutting of trees for fuel, it is true that large dams cause
B   submergence leading to loss of forest areas. But it cannot be ignored and it
    is important to note that these large dams also cause conversion of waste
    land into agricultural land and making the area greener. Large dams can also
    become instruments in improving the environment, as has been the case in
    the Western Rajasthan, which transformed into a green area because of Indira
C   Gandhi Canal, which draws water from Bhakhra Nangal Dam. This project not
    only allows the farmers to grow crops in deserts but also checks the spread
    of Thar desert in adjoining areas of Punjab and Haryana.

           Environmental and ecological consideration must, of course, be given
    due consideration but with proper channellisation of developmental activities
D   ecology and environment can be enhanced. For example, Periyar Dam Reservoir
    has become an elephant sanctuary with thick green forests all round while at
    the same time wiped out famines that used to haunt the district of Madurai
    in Tamil Nadu before its construction. Similarly Krishnarajasagar Dam which
    has turned the Mandya district which was once covered with shrub forests
    with wild beasts into a prosperous one with green paddy and sugarcane fields
E   all round.

          So far a number of such river valley projects have been undertaken in
    all parts of India. The petitioner has not been able to point out a single
    instance where the construction of a Dam has, on the whole, had an adverse
    environmental impact. On the contrary the environment has improved. That
F   being so there is no reason to suspect, with all the experience gained so far,
    that the position here will be any different and there will not be overall
    improvement and prosperity. It should not be forgotten that poverty is regarded
    as one of the causes of degradation of environment. With improved irrigation
    system the people wit.I prosper. The construction of Bhakra Dam is a shining
G   example for all to see how the backward area of erstwhile undivided Punjab
    has now become the granary of India with improved environment than what
    was there before the completion of the Bhakra Nangal project.

         The A ward of the Tribunal is binding on the Stat~s concerned. The said
    Award also envisages the relief and rehabilitation measures which are to be
H   undertaken. If for any reason, any of the State Governments involved lag
         NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, J.]                     223
behind in providing adequate relief and rehabilitation then the proper course,     A
for a Court to take, would be to direct the Award's implementation and not
to stop the execution of the project. This Court, as a Federal Court of the
country specially in a case of inter-State river dispute where an Award had
been made, has to ensure that the binding Award is implemented. In this
regard, the Court would have the jurisdiction to issue necessary directions        B
to the State which, though bound, chooses not to carry out its obligations
under the Award. Just as an ordinary litigant is bound by the decree, similarly
a State is bound by the Award. Just as the execution of a decree can be
ordered, similarly, the implementation of the Award can be directed. If there
is a short fall in carrying out the R&R measures, a time bound direction can
and should be given in order to ensure the irnplernentati.on of the Award.         C
Putting the project on hold is no solution. It only encourages recalcitrant
State to flout and not implement the award with impunity. This certainly
cannot be pennitted. Nor is it desirable in the national interest that where
fundamental right to life of the people who continue to suffer d~e to shortage
of water to such an extent that even the drinking water becomes scarce, non-
cooperation of a State results in the stagnation of the project.                   D

      The clamour for the early completion of the project and for the water
to flow in "the canal is not by Gujarat but is also raised by Rajasthan.

      As per Clause 3 of the final decision of the Tribunal published in the       E
Gazette notification of India dated 12th December, 1979, the State of Rajasthan
has been allocated 0.5 MAF of Narmada water in national interest from Sardar
Sarovar Darn. This was allocated to the State of Rajasthan to utilise the same
for irrigation and drinking purposes in the arid and drought-prone areas of
Jalore and Barmer districts of Rajasthan situated on the international border
with Pakistan, which have no other available source of water.                      F
      Water is the basic need for the survival of human beings and is part
of right of life and human rights as enshrined in Article 21 of the Constitution
of India and can be served only by providing source of water where there
is none. The Resolution of the U.N.O. in 1977 to which India is a signatory,       G
during the United Nations Water Conference resolved unanimously inter alia
as under:

     "All people, whatever their stage of development and their social and
economic conditions, have the right to have access to drinking water in , ,
quantum and of a quality equal to their basic needs."                      H
     224                      SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A           Water is being made available by the State of Rajasthan through tankers
     to the civilians of these areas once in four days during summer season in
     quantity, which is just sufficient for their survival. The districts of Barmer and
     Jalore are part of 'Thar Desert' and on account of scarcity of water the desert
     area is increasing every year. It is a matter of great concern that even after
B    half a century of freedom, water is not available to all citizens even for their
     basic drinking necessity violating the human right resolution of U.N.O. and
     Article 21 of the Constitution of India. Water in the rivers of India has great
     potentiality to change the miserable condition of the arid, drought-prone and
     border areas of India.                                                     ~·


C          The availability of drinking water will benefit about 1.91 lac of people
     residing in 124 villages in arid and drought-prone border areas of Jalore and
     Barmer districts of Rajasthan who have no other source of water and are
     suffering grave hardship.

           As already seen, the State of Madhya Pradesh is keen for the reduction
D of the dam's height to 436 ft. Apart from Gujarat and Rajasthan the State of
    Maharashtra also is not agreeable to this. The only benefit from the project
    which Maharashtra get is it's share of hydel power from the project. The
    lowering of the height from 455 ft. to 436 ft. will take away this benefit eve11
    though 9399 hectares of it's land will be submerged. With the reduction of
E   height to 436 ft. not only will there be loss of power generation but it would
    also render the generation of power seasonal and not throughout the year.

           One of the indicators of the living standard of people is the per capita
    consumption of electricity. There is, however, perennial shortage of power in
    India and, therefore, it is necessary that the generation increases. The world
F   over, countries having rich water and river syste!lJS have effectively exploited
    these for hydel power generation. In India, the share of hydel power in the
    total power generated was as high as 50% in the year 1962-63 but the share
    of hydel power started declining rapidly after I 980. There is more reliance now
    on thermal power projects. But these thermal power projects use fossil fuels,
    which are not only depleting fast but also contribute towards environmental
G   pollution. Global warming due to the greenhouse effect has become a major
    cause of concern. One of the various factors responsible for this is the
    burning of fossil fuel in thermal power plants. There is, therefore, international
    concern for reduction of greenhouse gases which is shared by the World
    Bank resulting in the restriction of sanction of funds for thermal power
H   projects. On the other hand, the hydel power's contribution in the greenhouse
           NARMADA BACHAO ANDOLAN v. U.0.1. [KIRPAL, .I.]                       225
. ·effect is negligible and it can be termed ecology friendly. Not only this but        A
   the cost of generation of electricity in hydel projects is significantly less. The
   Award of the Tribunal has taken all these factors into consideration while
   determining the height of the dam at 455 ft: Giving the option of generating
   eco-friendly electricity and substituting it by thennal power may not, therefore,
   be the best option. Perhaps the setting up of a thermal plant may not displace       B
  as many families as a hydel project may but at the same time the pollution
  caused by the thermal plant and the adverse affect on the neighbourhood
  could be far greater than the inconvenience caused in shifting and rehabilitating
  the oustees of a reservoir.

       There is and has been in the recent past protests and agitations not             C
 only against hydel projects but also against the setting up of nuclear or
 thermal power plants. In each case reasons are put forth against the execution
 of the prop~sed project either as being dangerous (in case of nuclear) or
 causing pollution and ecological degradation (in the case of thermal) or
 rendering people homeless and posses adverse environment impacts as has
 been argued in the present case. But then electricity has to be generated and          D
 one or more of these options exercised. What option to exercise, in our
 Constitutional framework, is for the Government to decide keeping various
 factors in mind. In the present case, a considered decision has been taken and
 an Award made whereby a high dam having an FRL of 455 ft. with capability
 of developing hydel power to be constructed. In the facts and circumstances            E
 enumerated hereinabove, even if this Court could go into the question, the
 decision so taken cannot be faulted.

 DIRECTIONS

       While issuing directions and disposing of this case, two conditions              F
 have to be kept in mind, (i) the completion of project at the earliest and (ii)
 ensuring compliance with conditions on which clearance of the project was
 given including completion of relief and rehabilitation work and taking of
 ameliorative and compensatory measures for environmental protection in
 compliance with the scheme framed by the Government thereby protecting the
 rights under Article 21 of the Constitution. Keeping these principles in view,         G
 we issue the following directions.

          (1)   Construction of the dam will continue as per the Award of the
                Tribunal.

          (2)   As the Relief and Rehabilitation Sub-group has cleared the              H
    226                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A                 construction up to 90 meters, the same can be undertaken
                  immediately. Further raising of the height will be only pari passu
                  with the implementation of the relief and rehabilitation and on
                  the clearance by the Relief and Rehabilitation Sub-group. The
                  Relief and Rehabilitation Sub-Group will give clearance of further
                  construction after consulting the three Grievances Redressal
B                 Authorities.

           (3)   The Environment Sub-group under the Secretary, Ministry of
                 Environment & Forests, Government of India will consider and
                 give, at each stage of the construction of the dam, environment
c                clearance before further construction beyond· 90 meters can be
                 undertaken.

           (4)   The permission to raise the dam height beyond 90 meters wiH be
                 given by the Narmada Control Authority, from time to time, after
                 it obtains the above-mentioned clearances from the Relief and
D                Rehabilitation Sub-group and the Environment Sub-group.

          (5)    The reports of the Grievances Redressal Authorities, and of
                 Madhya Pradesh in particular, shows that there is a considerable
                 slackness in the work of identification of land, acquisition of
E                suitable land and the consequent steps necessary to be taken
                 to rehabilitate the project oustees. We direct the States of Madhya
                 Pradesh, Maharashtra and Gujarat to implement the Award and
                 give relief and rehabilitation to the oustees in terms of the
                 packages offered by them and these States shall comply with
                 any direction in this regard which is given either by the NCA
F                or the Review Committee or the Grievances Redressal Authorities.
          (6)    Even though there has been substantial compliance with the
                 conditions imposed under the environment clearance the NCA
                 and the Environment Sub-group will continue to monitor and
                 ensure that all steps are taken not only to protect but to restore
G                and improve the environment.
          (7)    The NCA will within four weeks from today draw up an Action
                 Plan in relation to further construction and the relief and
                 rehabilitation work to be undertaken. Such an Action Plan will
                 fix a time frame so as to ensure relief and rehabilitation pari
H                passu with the increase in the height of the dam. Each State shall
      NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA, J.]                       227
              abide by the terms of the action plan so prepared by the NCA         A
              and in the event of any dispute or difficulty arising,
              representation may be made to the Review Committee. However,
              each State shall be bound to comply with the directions of the
              NCA with regard to the acquisition of land for the purpose of
              relief and rehabilitation to the. extent and within the period       B
              specified by the NCA.
        (8)   The Review Committee shall meet whenever required to do so
              in the event of there being any un-resolved dispute on an issue
              which is before the NCA. In any event the Review Committee
              shall meet at least once in three months so as to oversee the
              progress of construction of the dam and implementation of the        c
              R&R programmes.
                  If for any reason serious differences in implementation of the
              Award arise and the same cannot be resolved in the Review
              Committee, the Committee may refer the same to the Prime Minister
              whose decision, in respect thereof, shall be final and binding on    D
              all concerned.
        (9)   The Grievances Redressal Authorities will be at liberty, in case
              the need arises, to issue appropriate directions to the respective
              States for due implementation of the R&R programmes and in
              case of non-implementation of its directions, the GRAs will be       E
              at liberty to approach the Review Committee for appropriate
              orders.
        (10) Every endeavour shall be made to see that the project is
             completed as expeditiously as possible.
                                                                                   F
        This and connected petitions are disposed off in the aforesaid terms.

     BHARUCHA, J. I have read the judgment proposed to be delivered by
my learned brother, the Hon'ble Mr. Justice B.N. Kirpal. Respectfully, I regret
my inability to agree therewith.
                                                                                   G
     I do not set out the facts here: they are detailed in Brother Kirpal's
judgment.

      I take the view that the Sardar Sarovar Project does not require to be
re-examined, having regard to its cost effectiveness or otherwise, and that the
seismicity aspect of the Project has been sufficiently examined and no further     H
     228                     SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

 A consideration thereof is· called for. I do not accept the submission on behalf
     of the petitioner that those ousted by reason of the canals emanating from
     the reservoir in the Project must have the same relief and rehabilitation
                                                                                     .!
     benefits as those ousted on account of the reservoir itself; this is for the
     reason that the two fall in different classes.

 B         Having said this, I tum to the aspect of the environmental clearance of
     the Project. The Planning Commission accorded provisional sanction to the
     Project subject t.o the environment clearance thereof being obtained. At the
     relevant time, the responsibility for giving environmental clearance lay with
     the Department of Environment in the Ministry of Environment and Forests
C of the Union Government. The Department had in January, 1985 issued
     Guidelines for Environmental Impact Assessment of River Valley Projects. The
     Preface thereof stated that environmental appraisal was an important
     responsibility assigned to the Department. It involved the evaluation of the
    environmental implications of, and the incorporation of necessary safeguards
    in, activities having a bearing on environmental quality. While river valley
D projects were a basic necessity to a country whose economy was largely
    based on agriculture, over the years the realisation had dawned that river
    valley projects had their due quota of positive and adverse impacts which had
    to be carefully assessed and balanced for achieving sustained benefits.
    Therefore, it had been decided in the late 70s that all river valley projects
    should be subjected to a rigorous assessment of their environmental impact
E so that necessary mitigative measures could be duly incorporated therein at
    the inception stage. The Guidelines set out the procedure to be adopted for
    carrying out environmental impact assessments. In the Chapter headed
    Relevance of Environmental Aspects for River Valley Development Projects,
    the Guidelines stated, "Concern for environmental pollution is rather a recent
F phenomenon which has been triggered mainly by the backlash effect of
   accelerated industrial growth in the developed countries. The two major
   criteria - the project should maximise economic returns and it should be
   technically feasible - are no longer considered adequate to decide the
   desirability or even the viability of the project. It is now widely recognised
   that the development effort may frequently produce not. only sought for
G 'benefits, but other - often unanticipated - undesirable consequences as well
   which may nullify the socio-economic benefits for which the project is
   designed." After reference to the strong feelings that were often expressed
   in favour of measures that would provide the provision of adequate food and
   shelter to the millions, the Guidelines stated, "Such strong feelings are easy
H to understand in the context of the prevailing economic stagnation. It does
          NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA. J.]                       229
    not, however, follow that the arguments advanced are valid. The basic flaw A
    in these arguments is that they presume incompatibility between environmental


-   conservation and the development effort." Apart from some selected cases
    where the uniqueness of the natural resources, like wildlife, flora and genetic
    pool, which demanded exclusive earmarking of a given region for their specific
    use, the majority of cases did not call for a choice between development
    projects and preservation of the natural environmental; but in all cases there B
    was great need to consider the environmental aspects along with other
    feasibility considerations. It was imperative to analyse whether the_ adoption
    of environmental measures was going to result in any short or long term
    social or economic benefits. A careful study of the direct costs involved,
    which would be caused by the absence of environmental mitigative measures C
    on river valley projects, was an eye opener. These included effects on health,
    plant genetic resources, aquatic resources, water-logging and salinity of
    irrigated soils, deforestation and soil conservation. During the planning and
    feasibility assessment stages, several factors had to be taken into account,
    including short and long term impact on population and human settlements
    in the inundated and watershed areas, impact of flora and fauna (wildlife) in D
    the vicinity, impact on wildlife, including birds, impact on national parks and
    sanctuaries, on sites and monuments of historical, cultural and religious
    significance and on forests, agriculture, fisheries and recreation and tourism.
    Requisite date for impact assessment was not readily available, this being
    relatively a new discipline, and it had to be generated through such field E
    surveys as :

           - "Pre-impoundment census of flora & fauna, particularly the rare &
               endangered species, in submergence areas;

           -   Census of animal population and available grazing areas;
                                                                                       F
           -   Land-use pattern in the area with details of extent & type of forest;

           -   Pre-impoundment survey of fish habitat and nutrients levels;
           -   Groundwater level, its quality, and existing water use pattern;

           -   Mineral resources, including injurious minerals, in the impounciment.   G
           -   Living conditions of affected tribals/aboriginals etc.

    The cost of proposed remedial and mitigative measures to protect the
    environment had to be included in the project cost. Mitigative measures
    included, among other things, compensatory afforestation. Only when the
    incorporation of environmental aspects in the project planning was made a          H
     230                      SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

 A part and parcel of all river valley projects would there be hope to protect and
     preserve "our national environment and fulfill the objective of rapid economic
     development on the sustained basis while safeguarding the natural resources
     including the air, water, land, flora and fauna for the benefit of present and
     future generations." The necessary data that was required to be collected. for
B    impact assessment was set out in the Guidelines. A chart of the impact
     assessment procedure was also contained in the Guidelines.

           It appears that, though it ought rightly to have been taken by the
     Ministry of Environment and Forests, the decision whether or not to accord
     environmental clearance to the Project was left to the Prime Minister.
c         A note was prepared by the Ministry of Water Resources in or about
    October, 1986 on the environmental aspects of the Sardar Sarovar and the
    Narmada Sagar Multi Purpose Projects. It stated that a decision on the
    clearance of these projects from the environmental angle and under the Forest
   Conservation-Act, 1980 had become a matter ofurgency. Delays had occurred
D which had necessitated a recasting of the schedule. The Ministry of
   Environment and Forests had been doing its best to expedite the process of
   examination and clea_rance "but have been finding the material submitted
    inadequate and unsatisfactory. ......... ". While the State Governments had done
   their best to meet the requirements, "some of the information and action will
E necessarily take time and will have to proceed pari passu with the
   implementation of the project, which in any case will take a decade or more
   to complete." The Note stated that the Ministry of Water Resources shared
  the concerns and anxieties of the Ministry of Environment and Forests, as
   also the sense of urgency of the Governments of Gujarat and Madhya Pradesh,
  who felt that it was urgently of the Governments of Gujarat and Madhya
F Pradesh, who felt that it was urgently necessary to take a decision in regard
  to the clearance. Under the sub-heading, "Should the projects be taken up
  at all?'', the Note stated that the abandonment of the projects would mean
  the abandonment of the generation of 2450 MW of power and of the
  possibilities of economic development which that quantum of power would
  bring, as also increased agricultural production resulting from the creation of
G an irrigation potential of 2.041 million hectares. No effective alternatives to the
  two projects were available. Reference to the adverse environmental impact
  of the project carried the implicit assumption that if the projects were not
  sanctioned the status-quo would remain and there would be no deterioration
  of the environment. Such an assumption was not warranted. Despite the
H submergence of land and displacement of people and livestock, there was no
               NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA, J.)                     231
         case for the abandonment of the projects. What needed to be done was to A
         take appropriate and adequate counter measures to off-set the environmental
         impact of the projects. The Note then gave a broad picture of the likely
         environmental impact of the two projects. In respect of the flora and fauna,
'        it said, "Quantified data not yet available." In respect of the possibitity of soil
    "
         erosion from the catchment leading to excessive siltation of the reservoirs, it
         said, "Extent of critically degraded area needing treatment to be identified". B
         Specifically in respect of the Sardar Sarovar Project, the Note said that for the
         area to be submerged in Maharashtra, the Maharashtra Government had
         proposed compensatory afforestation over an area of 6490 hectares and the
         Madhya Pradesh was preparing an action plan to reforest about 5500 hectares
         of the denuded forest in the impact area. In respect of fauna, the Note said C
        that the Narmada Sagar Project authorities had commissioned a wildlife census
         of the areas by the Zoological Survey of India and were negotiating terms
         with the Indian Institute of Wildlife Management, Dehradun, for carrying out
         detailed wildlife studies for re-location purposes. They proposed to undertake
         all necessary steps to minimise the adverse impact of the Project on wildlife.
         Gujarat and Maharashtra were also taking similar action with the help of D
         specialised agencies. In respect of the Projects' flora, the Note said that the
         first preliminary survey in the area by the Botanical Survey of India was
         started in December, 1985 and it was estimated that the survey would take two
         to three years to be completed. In respect of catchment area treatment, the
         Note said that field surveys were likely to be started shortly. The Project E
         authorities had identified three representative pilot project areas. The biological
         and engineering measures to be adopted in the treatment of the balance of
         the catchment area would be designed on the basis of the experience to be
         gained from these pilot projects. Under the sub-heading, "What still remains
         to be done", the Note stated, "While some .plans have been made, studies


-        undertaken and action initiated, it will be clear from the preceding F
        paragraphs that much still remains to be done. Indeed, it is the view of the
         Ministry of Environment, Forests and Wildlife that what has been done so
        far whether by way of action or by way of studies does not amount to much,
        and that many matters are as yet in the early and preliminary stages." What
        was then set out was an enumeration of what remained to be done. The survey G
        offlora, to assess if there were any rare or threatened plant species, had been
        assigned to the Botanical Survey of India, which was expected to be completed
        in a period of two years. The wildlife survey undertaken by the Zoological
        Survey of India was also likely to take two take two years. The Indian
        Institute of Wildlife Management, Dehradun was to consider and assess the
        impact on wildlife of the destruction of their habitant, and to prepare a project H
     232                       SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

A report for their re-location. After all these reports became available, a master
     plan had to be prepared. Field surveys for the identification of the critically
     eroding areas was necessary and would take three years. The results from
     pilot studies would be available only after three years. Then, under the sub-
     heading, "Options in regard to the Clearance of the Projt:'.cts", the Note stated:

B          "There are two options :

               (i) As a number of studies, censuses, field surveys, mapping of
                   areas, etc., are likely to take between 2 and 3 years, one possibility
                   is that all these should be completed; detailed operational plans
                   for catchment treatment compensatory afforestation,
c                  rehabilitation and resettlement of affected population; and
                   remedial or re-location measures for planned species, wildlife,
                   etc., formulated; the responsibility for their implementation clearly
                   identified; and then the projects should be given a clearance
                   from the environmental and forest angles. This will mean a
D                  postponement of the clearance of projects by about 3 years.

             (ii)   The other option is that the projects should be given the
                    necessary clearance now, with clear conditions and stipulations
                    in regard to the actions to be taken on the various environmental
                    aspects and appropriate monitoring arrangement to ensure that
E                   the actions are taken in a time-bound manner. ·

                    13.2. The arguments against a postponement of clearance by
                    three years are very strong."

           The postponement of the decision at this stage seemed, to the writers
F of Note, scarcely conceivable. A postponement would lead to substantial
     increases in project costs and the benefits expected from the projects would
    be delayed. Also the work that had already been doQe would be rendered
    infructuous. The deferment of clearance by three years would put the
    organisational set-up that had been built up into a state of uncertainty retard
G   the momentum that had been gathered, and sap the organisational morale and
    motivation. The Note added, "Finally, the numerous studies, surveys, data
    collection exercises, plans for remedial measures, etc., where have been
    enumerated earlier would involve time, money and organisation commitment.
    With the project decision postponed for three years, and with no assurance
    that at the end of that period,. the decision will be positive, it is difficult
H   believe that all these studies, surveys and plans relating to the environmental
            NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA, J.]                        233
     aspect will be pursued with energy and enthusiasm, and the necessary                  A .
     resources devoted to them. In other words, the postponement of the decision
     in the interest of collecting the information relating to the environmental
     aspects and completing the formulation of the necessary operational plans
     may in fact prove to be a self defeating exercise. On the other hand, if the
     project decisions are taken now, subject to firm conditions and stipulations          B
     regarding the environmental aspects, there is greater likelihood of these
     conditions being met... ........A possible argument against the immediate clearance
     of the projects could be that once the projects are cleared, the management
     would concentrate on the engineering and construction aspects and would
     not pay adequate attention to the environmental and human aspects. There
     seems to be no need for such apprehensions. It should be entirely possible            C
     to give a conditional clearance and ensure that the conditions are properly
     met through a process of clear assignment of responsibility and frequent
     monitoring ............ Moreover, even assuming that the postponement of a decision
     by three years will improve the availability of detailed information and the
     state of preparedness on environmental matters, there can be no greater
     assurance at that stage than there is now regarding the whole-hearted and             D
     effective implementation of the remedial and ameliorative measures. We would
     still have to depend on proper monitoring ...... ". In conclusion, the Note urged
     that clearance for the environmental angle and under the Forest Conservation
     Act, 1980 be given immediately, subject to conditions and stipulations relating
     to the various environmental and related aspects outlined in the Note. (Emphasis      E
     supplied)

            Another Note was prepared by the Ministry of Water Resources and
     forwarded to the Additional Secretary to the Prime Minister on 20th November
      1986. Insofar as catchment area treatment was conc·emed, it concluded that


..   it was certain that the catchment area treatment programme could not be
     realistically formulated and assessed for atleast another three years. Therefore,
     it was premature to comment on the efficacy or otherwise of the catchment
     area treatment programme which was still to be formulated. The action
                                                                                           F



     programme for Command area development was yet to be made available. The
     lining of the canal network and the digging of tubewells in the Command               G
     could not be considered to be adequate. A lot of field work and planning was
     needed to be done to arrive at a workable and effective Command area
     development programme. As to compensatory afforestation, the land for the
     same was yet to be identified and procured before it could be evaluated for
     the purpose. In regard to the loss of flora and fauna, the following studies
     were considered absolutely essential to determine the adequacy or otherwise           H




..
     234                       SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A of the left ov,,et' habitat to sustain wildlife:
     "A wildlife census of the area" (ZSI will take atleast 2-3 years to complete the
     survey):

             (0     Preparation of a Master Plan showing all protected areas, National
B                   Parks, Wjldlife Reserves, Reserve and Protected Forests, etc. on
                    which should be superimposed the area to be taken up for
                    various reservoirs, roads, canals, S\'lttlement colonies, etc.
             (ii)   Study of the carrying capacity of the surrounding areas where
                    the wildlife from the submergence area will disperse."
c         In the circumstances, it was not considered possible to assess the
    impact of the loss of habitat on the wildlife and the overall loss of biological
    diversity. The absence and inadequacy of data on the following environmental
    aspects persisted :

D            "(i) Rehabilitation;
             (ii)   Catchment Area Treatment;
             (iii) Command Area Development;

             (iv) Compensatory Afforestation; and
E            (v)    Flora and Fauna."

            Considering the magnitude of rehabilitation, involving a large percentage
     of tribals, loss of extensive forest area rich in biological diversity, enormous
     environmental cost of the project and considering the fact that the basic data
     on vital aspects was still not available "there could be but one conclusion,
F    that theproject(s) are not ready for approval. " "There were two options in
     regard to the clearance. As a number of studies, censuses, field surveys,
    mapping of areas etc. was likely to take between two and three years, one               1




    possibility was that all these should be completed; detailed operational plans
    for catchment treatment, compensatory afforestation, rehabilitation and re-
G   settlement of affected population and remedial or re-location measures for                  .....:
    plant species, wildlife, etc. formulated; the responsibility for their implementation
    clearly identified; and then the projects should be given a clearance from the
    environmental and forest angles. This would mean a postponement of the
    clearance of projects by about three years." The other option was that the
    project should be given the necessary clearance with conditions and
H   stipulations in regard to the actions to be taken on the various environmental
             NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA, J.]                   235

       aspects with appropriate monetary arrangements. The Note recommended the      A
       latter option. (Emphasis supplied)

              On 19th December, 1986 the Ministry of Environment and Forests sent
       to the Secretary to the Prime Minister a Note on the environment aspects of
       the Narmada Sagar and the Sardar Sarovar Projects. The Note stated that it
       covered the major environmental issues which included the rehabilitation of B
       the affected population, catchment area treatment, Command area development,
....   compensatory afforestation and the loss of flora and fauna. It explained the
       then status of each of these aspects in terms of availability of data and plans
       and the readiness to execute them. It said that other components of the
       environmental aspect like the higher incidence of water borne diseases and C
       loss of mineral reserves were important but were not dealt with in detail in
       the note. It stated that the respect of catchment area treatment, the requirement
       was of demarcation of critically degraded area on the basis of aerial
       photographs, satellite imagery and ground checks; creation of a chain of
       nurseries of suitable species for biological treatment of the catchment area;
       and preparation of phased action programme for biological and engineering D
       treatment of the degraded catchment area. Considering that catchment area
        treatment on an intensive scale was imperative, both to reduce silt load and
        to maintain ecological balance, and keeping in view the fact that the
       interpretation of the aerial photographs and satellite imagery would take at
        least one year for completion, to be followed by ground truth checks; the E
       detailed land and soil surveys would take three years to be completed; the
       geo-morphological studies to suggest the engineering and biological treatment
        for the eroded areas were still to be taken up and the chain of nurseries
        needed to provide the necessary saplings in adequate quantity along with
       manpower and other infrastructure requirements were still to be mobilised, it
       was "reasonable to conclude that the catchment area treatment programme F
       can be realistically formulated only after three years when these data become
       available". Command area development was to achieve the prevention of
       water-logging and salinity, the optimisation of water utilisation and the
        maintenance of water quality. A detailed survey of the Command area was
        required on priority to prepare a package of the nature and quantity of G
       development and drainage and on farm works to fully uti'.ise the irrigation
       potential. An action programme was yet to be detailed. The Ministry of Water
        Resources was preparing an Evaluation Report covering the extent of likely
       water-logging and salinity problems and the effectiveness of measures
       proposed or likely to be proposed to combat these problems "as per the
       action programme to be formulated". In so far as compensatory afforestation H
    236                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A was concerned, the Project authorities had not been able to identify non-
    forest land for compensatory afforestation and had proposed to undertake
    afforestation on double the extent for degraded forest and, which proposal
    was fairly detailed and seemed satisfactory. In the matter of the loss of flora
    and fauna the Note stated "that the forest area, specially affected by the           ...._
B   Narmada Sagar Project, represents area harbouring rich heritage of genetic
    resources as well as wildlife. The. preliminary study carried out by the
    Environmental Planning and Coordination Organisation, Bhopal as well as the
    observations made by the World Bank clearly underlined the need for preparing
    a master plan showing not just the present status but also the likely scenarios
    after ~he project was implemented. The prime concern was to ascertain the
C   loss of biological diversity and whether the wildlife would be able to sustain
    itself after the destruction of its habitat. The following studies were considered
    absolutely essential both to determine the loss of flora and the adequacy or
    otherwise of the left over habitat to sustain the wildlife :

                  A wildlife census of the area (ZSI will take at least 2-3 years to
D                 complete the survey);

                  Preparation of a Master Plan showing all protected areas i.e.
                  National Parks, Wildlife Reserves, Reserve and Protected Forests,
                  etc. on which should be superimposed the areas cannot be taken
                  up for various reservoirs, roads, canals, settlement colonies,
E                 etc.;

                  Study of the carrying capacity of the surrounding areas where          ':
                  the wildlife from the submergence area will disperse.

    These studies are considered specially important in the case ofNSP. The work
    initiated by BSI and ZSI at the request of the Project Authorities will be
F
    completed only by 1989. The other studies have not yet been initiated. Under
    the circumstances, it is not possible to assess the impact of the loss of habitat
    on the wildlife and the overall loss of biological diversity and genetic
    reserves.

G         Even if one were to assume that the forests to be destroyed do not
    contain genetic resources, which in any case cannot be valued, the simple
    loss of these forests would have an environmental cost estimated at several
    thousand crore! of Rupees as per norms developed by FRL. The environmental
    cost is thus colossal".

H           The Note concluded :
       NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA, J.)                       237
        "(l) Taking note of the fact that the project formulation has been in       A
              progress for more than three decades and the active interaction
              of the Project authorities with the Department of Environment
              has been going on for almost three years, the absence and
              inadequacy of data on some important environmental aspects
              still persists.
                                                                                    B
        (2)   In an objective sense the NSP is not ready for clearance from
              environmental angle. Even though SSP is in a fairly advanced
              stage of preparedness, it is neither desirable nor recommended
              that the SSP should be given approval in isolation on technical
              and other grounds.                                                    c
        (3)   The state of readiness in the case of NSP is such that it gives
              just an outline of the Intention Plan. The fact that this Intention
              Plan will be converted to an Action Plan and there be effectively
              implemented has to be taken on trust. In case of Sardar Sarovar
              Project (SSP), readiness to execute is reasonably good except on      D
              the issue of rehabilitation of oustees specially from M.P. and
              Maharashtra.

        (4)   Holding up of the projects even for the next few months is not
              likely to improve the level of preparedness on most of the
              environmental aspects, specially in the case of NSP. In the           E
              meanwhile, further studies will not perhaps pick. up speed and
              thus at no time will the requisite information be fully available.

        (5)   A large amount of money has already ·been invested on SPP
              which is critically linked - on technical and operational aspects
              - to NSP. However, it may not be too late even now to modify          F
              some of the parameters of NSP and SSP to minimise
              environmental damage while at the same time ensuring option
              of utilisation of water resources.


                                                                                    G
The Choice is difficult but a choice has to be maqe." (Emphasis supplied)

       A Note was pr~pared on 15th January, 1987 in the Prime Minister's
Office. It noted that the main issues on environmental concerns were the
rehabilitation of the affected population, compensatory afforestation, treatment
of the catchment area and Command area develop!llent, pertaining, particularly;     H
    238                      SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A to drainage, water logging arid salinity. The Department of Environment and
    Forests·had raised the point that the rehabilitation plan was not ready, land
    had not been surveyed, areas of land use capability and water availability had
    not been identified and the land being suggested for rehabilitation, prima
    facie, appeared to be infertile. Detailed meetings with the State Governments
B   revealed that they were seriously undertaking surveys, land identification and
    preparation of a rehabilitation plan, of which the first phase was more or less
    ready. The catchment area treatment preparation would take time. A
    compensatory afforestation programme could be chalked out without difficulty.
    The issue was whether detailed plans should be made fully ready before
    giving environmental clearance or whether there could be a conditional
C   clearance so that the Project could start. The Secretary to the Prime Minister
    had discussed the matter with the Secretary, Water Resources and the Secretary,
    Environment and Forests and it had been agreed that clearance might be
    given on the following conditions :

         "Preparation in due time of detailed- and satisfactory plans for
D   rehabilitation, catchment area treatment, compensatory afforestation and
    Command Area Development.

          Setting up of Narmada_ Management Authority with adequate powers
    and teeth ·to ensure that environmental management plans are implemented
E   pari passu .with engineering and other works".

          Below the aforesaid Note, the Secretary to the Prime Minister sought
    his approval to conditional clearance of the Project from the environmental
    angle. The Project, she said, had been pending clearance for seven years and
F   the Chief Ministers of Gujarat and Madhya Pradesh were keenly awaiting it.
    The Chief Minister of Gujarat had requested a "green signal" before 20th
    January, 1987.

          On 19th January, 1987 the Prime Minister made a handwritten
    endorsement on the aforesaid Note, "Perhaps this is a good time to try for
G   a River Valley Authority. Discuss". But it appears that a River Valley Authority
    was not found feasible and the sanction to the Project from the environment
    of angle was issued by the Ministr.y of Environment and Forests on 24th
    June, 1987.

                  The environmental sanction to the Project reads thus :
H
    NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA, J.]                      239
                             "Office Memorandum                                 A
    Subject :    Approval of Narmada Sagar Project, Madhya Pradesh and

-    I.
                 Sarovar Project, Gujarat from environmental angle.

          The Narmada Sagar Project, Madhya Pradesh and Sardar Sarovar
          Project, Gujarat have been referred to this Department for            B
          environmental clearance.

    2.    On the basis of examination of details of these projects by the
          Environmental Appraisal Committee for River Valley Projects and
          discussions with the Central and State authorities, the following
          details were sought from the project authorities:                     C
          (i) Rehabilitation Master Plan.

          (ii) Phased Catchment Area Treatment Scheme.

          (iii) Compensatory Afforestation Plan.
                                                                                D
          (iv) Command Area Development

          (v) Survey of Flora and Fauna.

          (vi) Carrying Capacity of surrounding area.

          (vii) Seismicity; and
                                                                                E

          (viii) Health Aspects.

    3.    Field Surveys are yet to be completed. The first set of information
          has been made available and complete details have been assured        F
          to be furnished by 1989.

    4.    The NCA has been expanded and its terms of reference have
          been amplified to ensure that environmental safeguard measures
          are planned and implemented in depth and in its pace of
          implementation pari passu with the progress of work on the            G
          project.

    5.    After taking into account all relevant facts of Narmada Sagar
          Project, Madhya Pradesh and the Sardar Sarovar Project, Gujarat
          are hereby accorded environmental clearance subject to the
          following conditions:
                                                                                H
     240                         SUPREME COURT REPORTS [2000) SUPP. 4 S.C.R.

 A                (0 The Narmada Control Authority (NCA) will ensure that
                      environmental safeguard measures are planned and implemented
                      pari passu with progress of work on projects.

                  (ii) The detailed surveys/studies assured will be carried out as per     -
                       the schedule proposed and details made available to the
 B                     Department for assessment.

                  (iii) The Catchment Area Treatment programme and the Rehabilitation
                        plans be so drawn as to be completed ahead of reservoir filling.   --
                  (iv) The Department should be kept informed of progress on various
 C                     works periodically.

             6.      Approval under Forest (Conservation) Act, 1980 for diversion of
                     forest land will be obtained separately. No work should be
                     initiated on forest area prior to this approval.

D            7.      Approval from environmental and forestry angles for any other
                     irrigation, power or development projects in the Narmada Basin
                     should be obtained separately."

         Even in 1987, when the environmental clearance to the Project was
   given, it had been found necessary by the Union of India to rigorously assess
E the environmental impact of river valley projects. This was to determine
   whether the uniqueness of the natural resources, like wildlife, flora and the
   genetic pool in the region, demanded its exclusive earmarking for that purpose,
   in which event the river valley project would not be accorded clearance. Even
  otherwise, it was imperative to consider the Project's environmental aspects,
p such as its effect on health, plant genetic resources, aquatic resources, water-
  logging and salinity of irrigated soils, deforestation and soil conservation. Its
  short and long term impact on population, on flora and fauna, on wildlife, on
  national parks and sanctuaries, on historical, cultural and religious monuments,
  on forests, agriculture, fisheries and recreation and tourism had to be taken
  in account. Field surveys were necessary for generating the requisite data for
G the impact assessment. The cost of the proposed remedial and mitigated
  measures had to be included in the project cost. The necessary data that was
  required to be collected for the purposes of the assessment of a project's
  environmental impact was set out in Guidelines for the purpose issued by the
  Ministry of Environment and Forests of the Union Government (which have
H been referred to above).
        NARMADA BACHAO ANDOLAN v. U.O.I. [BHARUCHA, J.)                      241
       The contemporaneous Notes prepared by the Ministry of Water                  A
Resources and the Ministry of Environment and Forests, also referred to
above, leave no manner of doubt that the requisite data for assessment of the
environmental impact of the Project was not available when the environmental
clearance thereof was granted. In the words of one of the Notes, "While some
plans have been made, studies undertaken and action initiated, it will be clear     B
from the preceding paragraphs that muc'h still remains to be done. Indeed it
is the view of the Ministry of Environment, Forests and Wildlife that what has
been done so far whether by way of action or by ~ay of studies does not
amount to much and that many matters are yet in the early and preliminary
stages". The Notes make clear that the studies, censuses, mapping of areas
and field surveys for the collection of data for assessment of the environmental    C
impact of the Project were likely to take a further 2 to 3 ye~. An environmental
clearance based on next to no data in regard to the environmental impact of
the Project was contrary to the terms of the then policy of the Union of India
in regard to environmental clearances and, therefore, no clearance at all.

       The environmental clearance of 24th June, 1987 stated that details had       D
 been sought from the Project authorities in respect of the rehabilitation master
 plan, phased catchment area treatment· scheme, compensatory afforestation
 plan, Command area development, survey of flora and fauna, carrying capacity
 of surrounding area, seismicity and health aspects; field surveys had yet to
 be completed and complete details had been assured by 1989. Clearly, therefore,    E
 the necessary particulars in regard to the environmental impact of the Project,
 as required by the Guidelines, were not available when the environmental
 clearance was given, and it, therefore, could not have been given.

         The conditions upon which the environmental clearance was given were
  that detailed surveys and studies would be carried out and the Narmada            F
  Control Authority, whose terms of reference had been amplified, would ensure
· that "environmental safeguard measures" were planned and implemented pari
  passu with the progress of work on the Project. No further assessment of the
  environmental impact of the Project was contemplated by the environmental
  clearance, nor, indeed, was it ever carried out.
                                                                                    G
       What the environmental safeguards measures the Narmada Control
 Authority was to ensure were, and what their cost would be, was not known
 when the environmental clearance was given. There was, therefore, no way
 in which this cost could be included in the cost of the Project, whic~ was a
 requirement of the Guidelines.·
                                                                                    H
        242                      SUPREME COURT REPORTS (2000] SUPP. 4 S.C.R.

._ A         While the environmental safeguard measures were to be planned and
      implemented pari passu with the progress of the work on the Project, the
      catchment area treatment programme and the rehabilitation plans were required
      to be "so drawn as to be completed ahead of reservoir filling". This condition
      clearly required that before any water was impounded in the reservoir the
      catchment area treatment programme was not only to be drawn but also to
 B be completed; so also the rehabilitation plans. If, as the Project authorities
      interpreted this clause, only the drawing of the catchment area treatment
     programme and the rehabilitation plans were to be completed ahead of reservoir
     filling, the clause would have read: "The catchment area treatment programme
     and the rehabilitation plans shall be drawn ahead of reservoir filling". What
 C the clause as drawn required was that the catchment area treatment programme
     and the rehabilitation plans should be drawn in such a manner that the
     catchment area treatment and the rehabilitation works would be completed
     ahead of impoundment in the reservoir. This, plainly, was intended to off set,
     so far as was possible in the circumstances, the adverse effect of the
  .. impoundment of water in the reservoir upon the catchment and those who
 D were required to be settled elsewhere. In fact, the impoundment began much
     before.

             Learned counsel for the Union of India submitted that most of the
       necessary surveys and studies had been carried out in regard to the
 E     environmental impact of the Project before the environmental clearance was
       given, and the invited our attention to what had been done. The short answer
       to the submission on behalf of the Union of India is that the two concerned
       Ministries of the Union of India thought otherwise at the relevant time. To
       quote the Note of one Ministry again, "While some plans have been made,
       studies undertaken and action initiated, it would be clear from the preceding
 F     paragraph that much still remains to be done. Indeed it is the view of the
       Ministry of Environment, Forests and Wildlife that what has been done so
       far whether by way of action or by way of studies does not amount to much
       and that many matters are yet in the early and preliminary stages".

 G           The fact that the environmental clearance was given by the Prime
       Minister and not by the Ministry of Environment and Forests, as it would
       ordinarily have beeri done, makes no difference at all. Under its own policy,
       as indicated by the Guidelines, the Union of India was bound to give
       environmental clearance only after (a) all the necessary data in respect of the
       environmental impact of the Project had been collected and assessed; (b) the
H      assessment showed that the Project could proceed; and (c) the environmental
       NARMADA BACHAO ANDOLAN v. U.0.1. [BHARUCHA, J.]                     243

safeguard measures, and their cost, had been worked out.                          A

        An adverse impact on the environment can have disastrous
consequences for this generation and generations to come. This Court has
in its judgments on Article 21 of the Constitution recognised this. This Court
cannot place its seal of approval on so vast an undertaking as the Project B
without first ensuring that those best fitted to do so have had the opportunity
of gathering all necessary data on the environmental impact of the Project and
of assessing it. They must then decide if environmental clearance to the
Project can be given, and, if it can, what environmental safeguard measures
have to be adopted, and their cost. While surveys and studies on the
environmental aspects of the Project have been carried out subsequent to the C
environmental clearance, they are not, due to what are euphemistically called
"slippages", complete. Those who now examine whether environmental
clearance to the Project should be given must be free to commission or carry
out such surveys and studies and the like as they deem necessary. They must
also, of course, consider such surveys and studies as have already been D
carried out. Given that the construction of the dam and other work on the
Project has already commenced, this factor must play a part in their deciding.
whether or not environmental clearance should be accorded. Until environmental
clearance to the Project is accorded by them, further construction work on the
dam shall cease.
                                                                                  E
       The Union of India has issued a notification on 27th January, 1994
called the "Environmental Impact Assessment Notification 1994" (and amended
it on 4th May, 1994). Its terms are not applicable to the present proceedings,
but its provisions are helpful in so far as they prescribe who is to assess the
environmental impact assessment reports and environment management plans
that are submitted by applicants for new projects including hydro-electric
                                                                                  F
projects. The notification says, "The reports submitted with the application
shall be evaluated and assessed by the Impact Assessment Agency, and if
deemed necessary it may consult a Committee of Experts, having a composition
as specified in Schedule-III of this Notification. The Impact Assessment
Agency (IAA) would be the Union Ministry of Environment and Forests. The          G
Committee of Experts mentioned above shall be constituted by the IAA or
such other body under the Central Government authorised by the !AA in this
regard .................. ".

      Schedule III of the notification reads thus :
                                                                                  H
      244                                SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

 A                           "COMPOSITION OF THE EXPERT COMMITTEES FOR
                               ENVIRONMENTAL IMPACT ASSESSMENT

            I.         The Committees will consist of experts in the following disciplines:

                      (i) Eco-System Management
B
                      (ii) Air/Water Pollution Control

                      (iii) Water Resource Management

                      (iv) Flora/Fauna Conservation and Management

c                     (v)       Land Use Planning

                      (vi)      Social Sciences/Rehabilitation

                      (vii)     Project Appraisal

                      (viii) Ecology
D
                      (ix)      Environmental Health

                      (x)       Subject Are Specialists

             (XI) Representatives of NGOs/Persons concerned with Environmental
E            Issues.

                 2.          The Chairman will be an outstanding and experienced ecologist
                             or environmentalist or technical professional with wide managerial
                             experience.
             3.              The representative of IAA will act as Member - Secretary.
F
             4.              Chairman and members will serve in their individual capacities,
                             except those specifically nominated as representatives.
             5.              The membership of a Committee shall not exceed 15".

G The Environmental Impact Agency of the Union Ministry of Environment and
     Forests shall now appoint a committee of experts composed of experts in the
     fields mentioned in Schedule III of the notification. and that committee of
     experts shall assess the environmental impact of the Project as stated above.

          When the writ petition was heard at the admission stage, this Court was
H    most concerned about the distressing state of the relief to and rehabilitation
       NARMADA BACHAO ANDOLAN v. U.O.I. [BHARUCHA, J.]                       245

of those ousted on account of the Project. The proper implementation of relief      A
and rehabilitation measures was the aim of the Court at that time; but it was
not contemplated that the other issues in the writ petition would not to be
considered at the stage of its final hearing.

      The many interim orders that this Court made in the years in which this
writ petition was pending show how very little had been done in regard to           B
the relief and rehabilitation of those ousted. It is by reason of the interim
orders, and, in fairness, the co-operation and assistance of learned counsel
who appeared for the States, that much that was wrong has now been
redressed. The States have also been persuaded to set up Grievance Redressal
Authorities and it will be the responsibility of these Authorities to ensure that   C
those ousted by reason of the Project are given relief and rehabilitation in due
measure.

       The States are lagging behind in the matter of the identification -and
acquisition of land upon which the oustees are to be resettled. Having regard
to the experience of the past, only the Grievance Redressal Authorities can         D
be trusted by this Court to ensure that the States are in possession of vacant
lands suitable for the rehabilitation of the oustees. During the time that it
takes to assess the environmental impact of the Project, the States must take
steps to obtain, by acquisition or otherwise, vacant possession of suitable
lands upon which the oustees can be rehabilitated. When the Project obtains         E
environmental clearance, assuming that it does, each of the Grievance Redressal
Authorities of the States of Gujarat, Madhya Pradesh and Maharashtra must
certify, after inspection, before work on the further construction of the dam
can begin, that all those ousted by reason of the increase in the height of
the dam by 5 meters from its present level have already been satisfactorily
rehabilitated and also that suitable vacant land for rehabilitating all those who   F
will be ~msted by the increase in the height of the dam by another 5 meters
is already in the possession of the respective States; and this process must
be repeated for every successive proposed 5 meter increase in the dam height.

      Only by ensuring that relief and rehabilitation is so supervised by the       G
Grievance Redressal Authorities can this Court be assured that the oustees
will get their due.

      It is necessary to provide for the contingency that, for one or other
reason, the work on the Project, now or at any time in the future, does not
proceed and the Project is not completed. Should that happen, all oustees           H
    246                        SUPREME COURT REPORTS [2000] SUPP. 4 S.C.R.

A   who have been rehabilitated must have option to continue to reside where
    they were ousted from, provided such place remains habitable, and they must
    not be made at all liable in monetary or other terms on this account.

           When the writ p1tition was filed the process of relief and rehabilitation,
    such as it was, was going on. The writ petitioners were not guilty of any
B   !aches in that regard. In the writ petition they raised other issues, one among
    them being related to the environmental clearance of the Project. Given what
    has been held in respect of the environmental clearance, when the public
    interest is so demonstrably involved, it would be against public interest to
    decline relief only on the ground that the Court was approached belatedly.
c
         I should not be deemed to have agreed to anything stated in Brother
    Kirpal's judgment for the reason that I have not traversed it in the course of
    what I have stated.

            In the premises,
D
            (I)   The Environmental Impact Agency of the Ministry of Environment
                  and Forests of the Union of India shall forthwith appoint a
                  Committee of Experts in the fields mentioned in Schedule III of
                  the notification dated 27th January, 1994, called the
                  Environmental Impact Assessment Notification 1994.
E
            (2)   The Committee of Experts shall gather all necessary data on the
                  environmental impact of the Project. They shall be free to
                  commission or carry out such surveys and studies and the like
                  as they deem necessary. They shall also consider such surveys
                  and studies as have already been carried out.
F
           (3)    Upon such data, the Committee of Experts shall assess the
                  environmental impact of the Project and decide if environmental
                  clearance to the Project can be given and, if it can, what
                  environmental safeguard measures must be adopted, and their
                  cost.
G
           (4)    In so doing, the Committee of Experts shall take into consideration
                  the fact that the construction of the dam and other work on the
                  Project has already commenced.

           (5)    Until environmental clearance to the Project is accorded by the
H                 Committee of Experts as aforestated, further construction work
         NARMADA BACHAO ANDOLAN v. U.O.l. [BHARUCHA, J.]                      247
               on the dam shall cease.                                               A
         (6)   The Grievance Redressal Authorities of the States of Gujarat,
               Madhya Pradesh and Maharashtra shall ensure that those ousted
               by reason of the Project are given relief and rehabilitation in due
               measures.
               When the Project obtains environmental clearance, assuming
                                                                                     B
         (7)
               that it does, each of the Grievance Redressal Authorities of the
               States of Gujarat, Madhya Pradesh and Maharashtra shall, after
               inspection, certify, before work on the further construction of
               the dam can begin, that all those ousted by reason of the
               increase in the height of the dam by 5 meters from its present . C
               level have already been satisfactorily rehabilitated and also that
               suitable vacant land for rehabilitating all those who will be
               ousted by the increase in· the height of the dam by another 5
               meters is already in the possession of the respective States.
         (8)   This process shall be repeated for every successive proposed          D
               5 meter increase in the dam height.
         (~)   If for any reason the work on the Project, now or at any time in
               the future, cannot proceed and the Project is not completed, all
               oustees who have been rehabilitated shall have the option to
               continue to reside where they have been rehabilitated or to           E
               return to where they were ousted from, provided such place
               remains habitable, and they shall not be made at all liable in
               monetary or other terms on this account.

      The writ petition is allowed in the aforesaid terms. The connected
matters are disposed of in the same terms.                                           F
     No order as to costs.

B.K.M.                                 Petitions, Appeal and T.C. disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "public interest litigation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.