Created byFuzzy Cloud

Supreme Court of India

MUNICIPAL COUNCIL THANESARversusVIRENDER KUMAR ETC.

Citation
2019 INSC 227
Decided
19 February 2019
Disposal
Case Partly allowed

Holding

Decree‑holders are entitled to statutory pre‑ and post‑award interest under Section 31(7) and the interest must be simple at 7% per annum, not compound.

Summary

The Municipal Council Thanesar auctioned shop premises to the respondents, but disputes arose over completion and possession. An arbitrator awarded the council to complete the work and to pay interest on advance rent and non‑refundable security at 7% per annum, without specifying the mode of calculation. The executing court applied yearly rests, the High Court altered it to quarterly rests (compound interest), and the respondents claimed both pre‑ and post‑award interest. The Supreme Court examined whether the decree‑holders were entitled to statutory benefits under Section 31(7)(a) and (b) of the Arbitration and Conciliation Act and whether the interest should be calculated with quarterly rests. Relying on Hyder Consulting, the Court held that the decree‑holders are entitled to statutory pre‑ and post‑award interest, but the award’s silence on compounding means interest must be simple at 7% per annum. Consequently, the appeals were partly allowed, directing simple interest calculation.

Issues considered

  • Whether decree‑holders are entitled to statutory benefits under Section 31(7)(a) and (b) of the Arbitration and Conciliation Act, 1996.
  • Whether the interest awarded at 7% per annum should be calculated with quarterly rests (compound interest) or as simple interest.

Legislation cited

Subjects

ArbitrationInterest calculationSimple interestCompound interestSection 31(7) Arbitration ActExecution of awardPre‑award interestPost‑award interestMunicipal councilAuctionPossession

Judgment

                         [2019] 5 S.C.R. 829                          829


              MUNICIPAL COUNCIL THANESAR                              A
                                v.
                   VIRENDER KUMAR ETC.
              (Civil Appeal Nos. 1751-1763 of 2019)
                      FEBRUARY 19, 2019                               B
                 [UDAY UMESH LALIT AND
        DR. DHANANJAYA Y CHANDRACHUD, JJ.]
       Arbitration and Conciliation Act, 1996: s.31(7)(a) and (b) –
Interest – Entitlement of Decree-holders to the statutory benefits    C
under ss.31(7)(a) and (b) – Held: Decree-holders-respondents are
entitled to post award interest in terms of s.31(7)(b) of the Act.
       Code of Civil Procedure, 1908: Execution of award – Interest
awarded in the arbitration award – In the award, it was not
specifically stated that the interest @ 7% p.a. was to be awarded     D
with quarterly rests – In fact, the award did not specify anything;
whether it was quarterly rests or yearly rests – It simply awarded
interest @ 7% p.a. – Executing Court put it with yearly rests which
the High Court in revisions preferred by the appellants modified to
quarterly rests – On appeal, held: Both the Executing Court and
the High Court completely erred and awarded compound interest in      E
favour of the respondents when the award had stipulated it to be
7% p.a. simplicitor – The award did not even remotely suggest that
such award of interest would be with a direction that interest be
capitalized on yearly or quarterly basis – It was pure and simple
award of interest @ 7% and could not be taken to be a direction to    F
award compound interest – Consequently, the pre-award interest
on the amounts in question shall be calculated @ 7% p.a. simple
interest – Arbitration and Conciliation Act, 1996 – s.31(7)(a)
and (b).
      Partly allowing the appeals, the Court                          G
     HELD: 1. The first issue that whether the decree-holders
were entitled to the statutory benefits under Section 31(7)(a)
and (b) of the Act was rightly answered in favour of the
decree-holders/respondents. The question is no longer res
                                                                      H
                               829
830            SUPREME COURT REPORTS                      [2019] 5 S.C.R.


A     integra and stands answered in clear terms in Hyder Consulting
      case. [Paras 5.2, 7][833-F; 834-B-C]
            Hyder Consulting (UK) Ltd. v. Governor, State of Orissa
            through Chief Engineer (2015) 2 SCC 189 – relied on
            2. As regards the second issue, the Executing Court
B     correctly appreciated that the Award did not specifically state that
      the interest @ 7% per annum was to be awarded with quarterly
      rests. The Executing Court found that it was doubtful whether
      the award of interest was @ 7% with quarterly rests or yearly
      rests. The Executing Court put it with yearly rests which the
C     High Court in Revisions preferred by the appellants modified to
      quarterly rests. Both the Executing Court and the High Court
      completely erred and awarded compound interest in favour of
      the respondents when the award had stipulated it to be 7% per
      annum simplicitor. The Award did not even remotely suggest
      that such award of interest would be with a direction that interest
D     be capitalized on yearly or quarterly basis. It was pure and simple
      award of interest @ 7% and could not be taken to be a direction
      to award compound interest. Consequently, the pre-award
      interest on the amounts in question shall be calculated @ 7%
      per annum simple interest. The respondents shall be entitled to
E     the benefit under Section 31(7)(b) of the Act and post
      award interest shall also be @ 7% per annum simple interest.
      [Paras 8-12][834-C-D; 835-F-G; 835-A-B]
                            Case Law Reference
      (2015) 2 SCC 189               relied on              Para 6
F
            CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 1751-
      1763 of 2019.
           From the Judgment and Order dated 03.03.2017 of the High Court
      of Punjab and Haryana at Chandigarh in C.R. Nos. 6765 of 2015
      (O & M), C.R. No. 5198 of 2015 (O & M) to C.R. No. 5205 of 2015
G
      (O & M), C.R. No. 5510 of 2015 (O & M) to C.R. No. 5512 of 2015
      (O & M) and C.R. No. 4253 of 2015 (O & M).
                                     With
            Civil Appeal Nos. 1443-1444 of 2019.
H
 MUNICIPAL COUNCIL THANESAR v. VIRENDER KUMAR                                831
                     ETC.

      Ajay Majithia, Shekhar Kumar, Advs. for the Appellants.                A
      A. Tewari, Ms. Eliza Bar, Shree Pal Singh, Riju Mani Talukdar,
Anupam Raina, Saurav Trivedi, Sunando Raha, Raktim Gogoi, Kartikeya
Singh, Sarvwsa Chhajer, Anupam Lal Das, Chritarth Palli, Shubham
Bhalla, Advs. for the Respondents.
      The Judgment of the Court was delivered by                             B

      UDAY UMESH LALIT, J. 1.Leave granted.
      2. These appeals challenge the final judgment and order dated
03.03.2017 passed by the High Court of Punjab and Haryana at
Chandigarh in C.R.Nos. 6765 of 2015 (O&M), 5198 of 2015(O&M),                C
5199 of 2015(O&M), 5200 of 2015(O&M), 5201 of 2015(O&M), 5202
of 2015(O&M), 5203 of 2015(O&M), 5204 of 2015(O&M), 5205 of
2015(O&M), 5510 of 2015(O&M), 5511 of 2015(O&M), 5512 of
2015(O&M) and 4253 of 2015(O&M).
       3. Pursuant to public notice for auction of shops/showrooms, the      D
auction was conducted by the appellant on 18.10.2016 in which the
respondents participated and were declared successful bidders.
Thereafter, disputes arose between the parties whether the auctioned
premises were ready to be delivered on the relevant dates; whether the
construction was incomplete; and whether the civic amenities were made
available or not? The matters reached the High Court in various Writ         E
Petitions namely CWP Nos.13548 of 2008, 1015, 1016, 1017, 1018, 1020,
1062, 14793 and 19228 of 2009 and by a common order dated 14.07.2010
the disputes were referred to a sole Arbitrator. After considering the
matters, the Arbitrator passed a common Award on 14.10.2010. Para
21 of the Award was as under:-                                               F
      “21. In view of the above findings, award is passed in favour of
      the petitioners against the respondents with costs of Rs.10,000/-
      (Rupees Ten Thousand only) and Municipal Council, Thanesar, is
      directed to complete the work in all the respects of the Shopping
      Complex, situated in Kacha Gher, Thanesar, within one month; if
                                                                             G
      already completed, a notice be issued to the petitioners to take
      possession of the respective shops and also to execute the
      agreement within a week. Municipal Council, is further directed
      to give interest on the advance rent as well as non-refundable
      security, at the rate of interest offered by Nationalised Bank, i.e.
                                                                             H
832            SUPREME COURT REPORTS                            [2019] 5 S.C.R.


A           7% per annum, till physical/possession is handed over to the
            petitioners/allottees. Petitioners are further awarded damages
            by way of 12% interest on non-refundable security till delivery of
            possession as they have suffered mentally as well as loss of
            business due to delay in completion of work of the shops and
            handing over their possession. Requisite stamp papers be filed
B
            within week.”
            4. The appellants preferred objections under Section 34 of the
      Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the
      Act’) which were dismissed by the Additional District Judge on
      15.09.2012. The appellants, being aggrieved, preferred First Appeals
C     which were dismissed by the High Court of Punjab and Haryana on
      17.01.2014. The order of the High Court was also affirmed by this Court
      by dismissing Special Leave Petition (Civil) No.15550 of 2014 on
      04.08.2014. The directions issued in the Award thus became final.
            5. In Execution Proceedings taken out by the respondents, the
D     Executing Court in its order dated 23.03.2015 dealt with the matter as
      under:-
            “5. As per the award dated 14.10.2010 the arbitrator had directed
            the judgment debtor i.e. Municipal Council, Thanesar to give
            interest on the advance rent as well as non-refundable security, at
E           the rate of interest offered by nationalized bank i.e. 7% per annum
            till physical possession is handed over to the petitioners/allottees.
            Petitioners were further awarded damages by way of 12% interest
            on non-refundable security till delivery of possession. It is a settled
            legal position that an executing court cannot go beyond decree. A
F           plain reading of award dated 14.10.2010 shows that interest @
            7% per annum has been given to the decree holder on the advance
            rent as well as non-refundable security. “At the rate of interest
            offered by nationalized bank” mentioned in the award has to be
            read in continuation and cannot be isolated to give it a separate
            meaning. The award clearly stipulates that the rate of interest
G           being awarded by the arbitrator is at the rate which is offered by
            nationalized bank. The award is silent about the manner of
            calculation of interest. The award cannot be interpreted to mean
            that the manner of calculation of the interest has to be in accordance

H
     MUNICIPAL COUNCIL THANESAR v. VIRENDER KUMAR                                833
                ETC. [UDAY UMESH LALIT, J.]

          with the norms of a nationalized bank. Interpreting the award as       A
          calculation of interest of 7% per annum on advance rent and non-
          refundable security with quarterly rests would mean that compound
          interest has to be calculated. The same does not appear to be the
          intention of the learned arbitrator as it is not specifically stated
          that interest at the rate of 7% per annum was awarded with
                                                                                 B
          quarterly rests.
          6.        Even as per the Reserve Bank of India guidelines liberty
          has been given to the nationalized banks to pay interest on domestic
          savings deposit accounts either at quarterly intervals or by giving
          longer rests. Admittedly different nationalized banks have their
          own rate of interest and are free to determine the manner of           C
          calculation by giving shorter or longer period of rests. In the
          absence of any specific direction given by the learned arbitrator
          in the award dated 14.10.2010, no further interpretation in the
          award is feasible and the rate of interest has to be read as 7% per
          annum which has to be calculated with yearly rests. As per award       D
          dated 14.10.2010, the interest has to be calculated only till the
          delivery of possession. The possession of the respective shops
          has already been handed over to the decree holders.”
      5. The appellants being aggrieved, filed aforementioned Civil
Revisions in the High Court which were disposed of on 03.03.2017.                E
The questions that arose for consideration were formulated by the High
Court as:
          “Twin questions that fall for consideration of this Court are; (i)
          whether the decree-holders are entitled to the statutory benefits
          under Section 31(7)(a) and (b) of the Act; and (ii) whether the        F
          decree-holders-petitioners are also entitled to calculate the amount
          of interest on advance rent and nonrefundable security, at the
          rate of interest offered by nationalized bank, i.e. 7% per annum,
          with quarterly rests.”
      Relying on the majority view in Hyder Consulting (UK) Ltd. vs.             G
Governor, State of Orissa through Chief Engineer1, the High Court
answered the first issue in favour of the respondents and concluded that
they were entitled to post award interest in terms of Section 31(7)(b) of
the Act. As regards second issue, it was held that the respondents were
1
    (2015) 2 SCC 189                                                             H
834             SUPREME COURT REPORTS                           [2019] 5 S.C.R.


A     also entitled to interest @ 7% per annum with quarterly rests. The view
      so taken by the High Court is presently under challenge.
            6. We have heard Mr. Ajay Majithia, learned counsel for the
      appellants and Mr. A. Tewari, Mr. Anupam Raina, Mr. Raktim Gogoi
      and Mr. Chritarth Palli, learned advocates for the respondents.
B            7. The first issue was rightly answered in favour of the
      respondents. The question is no longer res integra and stands answered
      in clear terms in Para 10 of the Judgment of Bobde, J. and paras 27-28
      of the Judgment of Sapre, J. in Hyder Consulting (supra). The view
      taken by the High Court on this issue is absolutely correct.
C             8. As regards the second issue, the Executing Court correctly
      appreciated that the Award did not specifically state that the interest @
      7% per annum was to be awarded with quarterly rests. In fact, the
      Award did not specify anything; whether it be quarterly rests or yearly
      rests. It simply awarded interest @ 7% per annum. Since the Award
D     was completely silent on that aspect, at the stage of execution, no addition
      or alteration could be made in the operative directions issued in the Award.
      The Award had seen the challenges at three levels and at none of those
      stages, there was any modification in the operative directions of the
      Award.

E            9. The Executing Court found that it was doubtful whether the
      award of interest was @ 7% with quarterly rests or yearly rests. In
      fact, the situation was more fundamental, whether there was award of
      any compound interest at all. The Executing Court put it with yearly
      rests which the High Court in Revisions preferred by the appellants
      modified to quarterly rests. In our view, both the Executing Court and
F     the High Court completely erred and awarded compound interest in favour
      of the respondents when the award had stipulated it to be 7% per annum
      simplicitor. The Award did not even remotely suggest that such award
      of interest would be with a direction that interest be capitalized on yearly
      or quarterly basis. It was pure and simple award of interest @ 7% and
G     could not be taken to be a direction to award compound interest.
             10. We, therefore, accept the submission made by the learned
      counsel for the appellants as regards second issue and direct that the
      direction issued in the para 21 of the Award shall be construed as simple
      interest @ 7% per annum.
H
  MUNICIPAL COUNCIL THANESAR v. VIRENDER KUMAR                                   835
             ETC. [UDAY UMESH LALIT, J.]

       11. Consequently, the pre-award interest on the amounts in question       A
shall be calculated @ 7% per annum simple interest. The respondents
shall be entitled to the benefit under Section 31(7)(b) of the Act and post
award interest shall also be @ 7% per annum – simple interest.
     12. With the aforesaid modification the appeals are partly allowed.
No order as to costs.                                                            B

Devika Gujral                                          Appeals partly allowed.




                                                                                 C




                                                                                 D




                                                                                 E




                                                                                 F




                                                                                 G




                                                                                 H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.