Created byFuzzy Cloud

Supreme Court of India

MUNICIPAL CORPORATION, JABALPUR AND ORS.versusM/S. RAJESH CONSTRUCTIONS CO.

Citation
2007 INSC 418
Decided
13 April 2007
Disposal
Disposed off

Holding

The High Court was not justified in appointing a retired Chief Justice as arbitrator because it violated the contractual arbitration clause, which requires the contractor to furnish a security deposit before the corporation can constitute an Arbitration Board.

Summary

The Municipal Corporation of Jabalpur awarded a road‑construction contract to M/s Rajesh Constructions, which contained Clause 29 stipulating that any arbitration could only be initiated after the contractor furnished a security deposit and the corporation then constituted an Arbitration Board. A dispute arose and the contractor filed an application under Section 11(6)(c) of the Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator. The High Court appointed a retired Chief Justice of a High Court as sole arbitrator, ignoring the contractual requirement of a security deposit. The Supreme Court held that the High Court was not justified in doing so, as the appointment contravened the explicit procedure in Clause 29, and directed the corporation to first obtain the security deposit within six weeks and then constitute the Arbitration Board, which may take over the arbitration proceedings from the point already reached. The Court set aside the High Court’s order and disposed of the appeal.

Issues considered

  • Whether the High Court was justified in appointing a retired Chief Justice as arbitrator notwithstanding the contractual arbitration clause requiring a security deposit and a specific procedure.
  • Whether Section 11(6)(c) of the Arbitration and Conciliation Act, 1996 permits appointment of an arbitrator that overrides the parties' agreed arbitration procedure.
  • Whether the corporation’s obligation to constitute an Arbitration Board arises only after the contractor furnishes the security deposit as per Clause 29(d).

Legislation cited

Subjects

ArbitrationArbitration agreementSecurity depositSection 11Appointment of arbitratorContractual arbitration clauseHigh Court appointmentArbitration BoardContract law

Judgment

·-r
                 MUNICIPAL CORPORATION, JABALPUR AND ORS.                                 A
                                             v.
                          M/S. RAJESH CONSTRUCTIONS CO.

                                     APRIL 13, 2007

            [TA RUN CHATTERJEE AND P.K. BALASUBRAMANYAN, JJ.]                             B


·"'         Arbitration and Conciliation Act, 1996:

             s.11 (6)(c )-Arbitration Agreement stipulating that in case of dispute,
      Contractor would furnish the security deposit and thereafter Corporation            C
      would constitute the Arbitration Board-Dispute between the parties-
      Contractor filed application before High Court/or appointment ofarbitrator-
      High Court appointed retired Chief Justice of High Court as arbitrator-
      Justification of-Held, Not justified same being contrary to Arbitration
      agreement-As security deposit was not furnished by respondent, obligation           D
      of Corporation to constitute Arbitration Board could not arise-Respondent
      directed to furnish security within six weeks and then corporation would
;.    constitute arbitration board.

            The appellants floated a notice inviting tender for construction of a road.
      The job was awarded to the respondent. The tender contained various clauses;        E
      one amongst the same being Clause 29 which pertained to arbitration in case
      of any dispute. Dispute arose between the parties.

            The respondent filed an application under Section 11 (6)(c ) of the
      Arbitration and Conciliation Act, 1996 in the High Court seeking appointment
      of an arbitrator to adjudicate upon disputes. By an order dated 7th May, 2003,      F
      the High Court allowed the application directing the appellant-Corporation,
      to invoke the arbitration Clause 29.

            The Clause 29 of the contract stated that no reference for arbitration
      shall be maintainable unless the contractor furnishes the security deposit of       G
      a sum determined by the Corporation.

           Seeking enforcement of the order of the High Court dated 7th May, 2003,
      invoking Clause 29 for appointment of an arbitrator, the respondent filed
      another application. By the impugned order, retired Chief Justice of High
                                            137                                           H
    138                     SUPREME COURT REPORTS                    [2007] 5 S.C.R.

A Court was appointed to act as an arbitrator to adjudicate upon the disputes
    between the parties. Appellant filed review application, which was rejected.       , __
    Hence the present appeal.

          Disposing of the appeal, the Court

B         HELD: 1. The High Court was not justified in appointing a retired Chief
    Justice of a High Court to act as a sole arbitrator as the same is contrary to
    Clause 29 of the contract. The High Court, by its earlier order dated 7th May,
    2003 directed the parties to invoke the arbitration clause and to appoint an
    arbitrator in compliance with Clause 29 of the contract entered into between       .r
    the parties. [Para 19] (145-G; 146-A]
c
         Datar Switchgears Ltd v. Tata Finance Ltd., [2000J 8 SCC 151 and Punj
    Llyods Ltd v. Petrone/ MHB Ltd., [2006J 2 SCC 638, held inapplicable.

          2.1. Clause 29 specifically stipulates that if any dispute arises between
    the parties, the party seeking invocation of the arbitration clause, shall first
D   approach the Chief Engineer and on his failure to arbitrate the dispute, the
    party aggrieved may file an appeal to MPL Com, failing which, the Corporation
    shall constitute an Arbitration Board to resolve the disputes in the manner
    indicated in Clause 29. However, before doing so, the party invoking                J..
    arbitration clause is required to furnish security of a sum to be determined
E   by the Corporation. [Para 20J (146-A, BJ

          2.2. Admittedly, the security has not been furnished by the respondent
    to the Corporation. Such being the position even today, the obligation of the
    Corporation to constitute an Arbitration Board to resolve disputes between
    the parties could not arise. (Para 21 J (146-C, DJ
F
          3.1. The Arbitrator appointed by the High Court has already commenced
                                                                                       ")'--
    the arbitration proceeding. The Corporation had submitted that they shall
    constitute an Arbitration Board as soon as the respondent furnishes security
    in terms of Clause 29(d) of the contract and if any direction is given to the
    Arbitration Board to proceed from the stage the Arbitrator had already
G   reached, that would not be objected. [Para 22J (146-E, FJ

          3.2. Such being the stand taken by the Corporation, the respondent is
    directed to furnish the security of a sum to be determined by the Corporation
                                                                                       ,..
    within six weeks from this date and in the event security determined by the
    Corporation is furnished within the time, the Corporation shall constitute an
H
                      MUNICIPAL CORPRN, JABALPUR "· RAJESHCONSTRUCTIONS CO. [TARUN CHATTERJEE, J.J
                                                                                                     139
    _...,,   Arbitration Board in compliance with Clause 29 of the contract. It is directed                A
             that the Arbitration Board shall proceed frQm the stage the Arbitrator
             appointed by the High Court had already reached. [Para 23) [146-G; 147-A)

                   4. That apart, it has to be kept in mind that it is always the duty of the
             court to construe the arbitration agreement in a manner so as to uphold the
             same. Therefore the High Court ought not to have appointed an arbitrator in                   B
             a manner, which was inconsistent with the arbitration agreement.
                                                                         [Para 24) (147-A-B)
      -~.

                   CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1945 of2007.

                   From the Judgment and Order dated 29.07.2004 & 08.04.2005 of the High                   c
             Court Madhya Pradesh at Jabalpur in M.C.C. Nos. 3295 of 2003 & 1579 of2004
             respectively.

                   Ranjan Mukherjee and S.C. Ghosh for the Appellants.

                   Amit Sharma and Anupam Lal Das for the Respondent.                                      D
                   The Judgment of the Court was delivered by
     :.
,                  TARUN CHATTERJEE, J. I. Delay Condoned.

                   2. Leave granted.                                                                       E
                   3. This appeal is directed against the judgments and final orders dated
             29th July 2004 and 8th April, 2005 passed by a learned Judge of the High
             Court of Madhya Pradesh at Jabalpur in M.C.C. No. 3295 of2003 and M.C.C.
             No. 1579 of2004. By the order dated 29th July 2004, learned Judge of the High
             Court appointed Mr. Justice B.C. Verma, a retired Chief Justice of the Punjab                 F
             and Haryana High Court, as sole arbitrator to adjudicate upon disputes
             between the appellants and the respondent herein. The order dated 8th April,
             2005 passed in MCC No. 1579 of 2004 is under challenge as the application
             for review and/or recall of the order dated 29th July 2004 at the instance of
             the appellants was also rejected.
                                                                                                           G
                   4. Notice was issued on the application for condonation of delay and
     ·'<     also on the special leave petitions by this court on 12th September 2005. After
             exchange of affidavits an order was passed by this court on 5th January 2007
             in which one of us was a party. The said order of this court may be relevant
             for our decision which is as follows:-                                          H
    140                      SUPREME COURT REPORTS                     (2007] 5 S.C.R.

A               "Having regard to the facts of the case, we suggested to the
            parties that the Municipal Corporation may be directed by this Court
            to constitute a Board of Arbitrators under Clause 29 of the Agreement
            without any preconditions. Such an appointment should be made
            within three weeks from this Court's order and the Board of Arbitrators
            will take up the matter from the stage at which it has reached before
B           the Arbitrator appointed by the High court. The Board of Arbitrators
            shall thereafter conclude the proceedings within six months."

          5. However, this suggestion of this court made on 5th January 2007 was
    not accepted by the respondent and for that reason, we heard the appeal on
C merits.
          6. The appellants floated a notice inviting tender for construction of a
    road. Finally, half of the job was awarded to the respondent by entering into
    a contract on the same terms and conditions as contained in the tender. The
    tender contained various clauses; one amongst the same being Clause 29
O   which pertained to arbitration in case any dispute arose between the parties
    and reads thus:-

            "Except as otherwise provided in this contract all questions and
            disputes relating to the meaning of the specifications, drawing and
            instructions herein before mentioned and as to thing whatsoever, in
E           any way arising out or relating to the contract, designs, drawings,
            specifications, estimates concerning the works or the execution or
            failure to execute the same, whether arising during the progress of the
            work or after the completion or abandonment there 0f shall be referred
            to the City Engineer in writing for his decision, within a period of 30
            days of such occurrence. Thereupon the City Engineer shall give his
F           written instructions and/or decisions within a period of 60 days of
            such request. This period can be extended by mutual consent of the
            parties.

            Upon receipt of written instructions of decisions, the parties shall
            promptly proceed without delay to comply such instructions or
G           decisions. If the City Engineer fails to give his instructions or decisions
            in writing within a period of 60 days or mutually agreed time after
            being requested if the parties are aggrieved against the decision of
            the C. E., the parties may within 30 days prefer an appeal of the M.P.L.,
            Com. who shall afford an opportunity to the parties of being heard
H           and to offer evidence in support of his appeal. The M.P.L. Com will,
           MUNICIPAL CORPRN, JABALPUR "- RAJ ESH CONSTRUCTIONS CO. [T ARUN CHATTERJEE, J]   14!
         give his decision within 90 days. If any party is not satisfied with the A
--1
         decision of the M.P.L. Com, he can refer such disputes for arbitration
         by an Arbitration Board to be constituted i'y the Corporation which,
         shall consist of three members of whom one shall be chosen from
         among the officers belonging to be Urban Administration and
         Development Department not below the rank of B.E. one Retired
         Chief Engineer of any Technical Department and City Engineer B
         Nagar Nigam Jabalpur,

        The following are also the terms of this contract, namely, :

         a) No person other than the aforesaid Arbitration Board constituted
         by the Corporation (to handle cases of all Technical Departments)
         shall act as Arbitrator and it for any reason that is not possible the
                                                                                                  c
         matter shall not be referred to Arbitration at all.

         b) The Corporation may at any time effect any change in the personnel
         of the Board and the new members or members appointed to the
         Arbitration Board shall be entitled to proceed with the reference from D
         the stage it was left by his or their predecessors.
    I    c) The party invoking arbitration shall specify the dispute or disputes
~
         to be referred to arbitration under this clause together with the amount
         or amounts claimed in respect of each such dispute(s).

         d) Where the party invoking arbitration is the contractor no reference                   E
         for arbitration shall be maintainable, unless the contractor furnishes
         a security deposit of a sum determined according lo the table given
         below, and the sum so deposited shall on the determination of
         arbitration proceeding, be adjusted against the cost, if any awarded
         by the Board against the party and the balance remaining after such
                                                                                                  F
_/       adjustment or in the absence of the such cost being awarded the
 '·
         whole of the sum shall be refunded to him within one month from the
         date of the award.
         Amount of Claim                            Rate of Security Deposits
         For claim below Rs. I 00001-.              5% of amount claimed
                                                                                                  G
         For claim of Rs. !0000/-                   3% of amount claimed
         and above but                              subject to minimum of
         below Rs.1,00,0001-                        Rs. 5001-
         For claims of Rs.1,00,0001-                2% of the amount
         and above                                  claimed subject to
                                                    a minimum of Rs. 30001-                       H
    142                     SUPREME COURT REPORTS                    (2007) 5 S.C.R.

A          e) .... .
                                                                                        -..--
           /) .... .

           g) .... .
           h) .... ..
B                                                            "(Underlining is ours)

          7. Reference to sub-clauses (e) to (h) of the Arbitration Clause 29 would
    not be necessary in view of the fact that the said sub-clauses are not required
    to be considered for decision and accordingly are omitted.

c          8. In 2002, the respondent filed an application under Section l 1(6)(c) of
    the Arbitration and Conciliation Act 1996 (hereinafter called the" Act") in the
    High Court of Madhya Pradesh at Jabalpur seeking appointment of an arbitrator
    to adjudicate upol! disputes between it and the appellants, which came to be
    registered as M.C.C No. 285/2002. By an order dated 7th May 2003, a learned
D   Judge of the High Court allowed the application directing the appellant,
    Municipal Corporation, to invoke the arbitration clause and appoint an
    arbitrator in compliance with Clause 29 of the contract at the earliest to
    resolve the disputes between the parties. The learned Judge directed:                 .;._

            "In view of the aforesaid circumstances, the application filed by the
E           applicants under Section 11 (6){c) of the Act is hereby allowed. The
            respondents are directed to invoke the arbitration clause 29 and it
            is directed that as early as possible the arbitrator be appointed to
            resolve the dispute between the applicant and the respondent nos.
            I and 2."

F                                                             (Underlining is ours)

        9. A bare perusal of this direction made by the High Court, while
  allowing the application under Section I 1(6)(c) of the Act, would clearly
  indicate that the Corporation was directed to invoke the arbitration clause and
G appoint an Arbitration Board in compliance with Clause 29 of the contract.
  In that view of the matter, we examined Clause 29 of the contract and its sub
  clauses in detail from which the followings emerge:

            [!) No reference for arbitration shall be maintainable unless the
            contractor fi1rnishes the security deposit of a sum determined as per
H           the table given in sub-clause (d) of the contract by the Corporation.
                     MUNICIPAL CORPRN. JABALPUR •'. RAJESH CONSTRUCTIONS CO. (T ARUN CHATTERJEE, J.J   14J

     ··1           [II] Obligation of the Corporation would arise to constitute an                           A
                   Arbitration Board only after !he security deposit is detennined by the
                   Corporation and deposited by the contractor.

                   [III] The Corporation shall constitute a Board called 'Arbitration Board'
                   for arbitration which shall consist of three members of whom one shall
                   be chosen from among the officers belonging to the Urban                                  B
                   Administration and Development Department not below the rank of
                   B.E., one Retired ChiefEngineer of any Technical Department and City
                   Engineer, Nagar Nigam, Jabalpur; subject to compliance of (I) and (II)
                   as noted herein above.

                 10. At the risk of repetition, we may reiterate that the High Court while                   c
           allowing the application under Section 11(6)(c) of the Act directed appointment
           of the Arbitrator in tenns of Clause 29 of the contract, which contained the
           aforesaid provisions.

                  11. It may be kept on record that, on instruction, Mr. Ranjan Mukherjee,
           appearing on behalf of the Corporation, submitted that the Corporation was D
           ready and willing to constitute an Arbitration Board in compliance with
 }         Clause 29 of the contract without any reference being made to the Chief
           Engineer, or in case of failure of the Chief Engineer to take decision or give
           instruction in writing to file an appeal before MPL Com and that the Arbitration
           Board shall proceed from the stage at which the learned Arbitrator, appointed E
           by the High Court, had already reached.

                  12. Keeping in mind the aforesaid stand taken by the Corporation, we
           shall now consider whether the High Court was justified in appointing a
           retired Chief Justice of a High Court as the sole arbitrator to resolve the
---;       disputes raised by the parties.                                                                   F
                 13. Seeking enforcement of the order of the High Court dated 7th May
           2003, invoking Clause 29 for appointment of an arbitrator, the respondent filed
           another application being M.C.C.No. 3295/2003. By the impugned order, as
           noted herein earlier, Mr. B.C Venna, retired Chief Justice of Punjab and Haryana
           High Court was appointed by a learned Judge to act as an arbitrator to                            G
.l,.
           adjudicate upon the disputes between the parties.

                 14. Aggrieved by the aforesaid order of the learned Judge of the High
           Court, the appellants filed a review application before the High Court, which
           by the subsequent order dated 8th April, 2005 passed in M.C.C. No. 1579 of
                                                                                                             H
    144                      SUPREME COURT REPORTS                     (2007] 5 S.C.R.

A 2004, which is impugned in Special Leave Petition No.19333 of 2005, w~
    rejected. Feeling aggrieved by the aforesaid orders, this appeal has been filed--
    by the appellants.

         15. We have heard the learned counsel for the parties and gone through
    the material put on record in detail. At the outset, it is necessary for us to
B   examine Section l 1(6)(c) of the Act, which reads as under:

            "11. Appointment of arbitrators.-

            (I) ...

            (6)   Where, under an appointment procedure agreed upon by the
c                 parties, -
                  (a) A party fails to act as required under that procedure; or

                  (b) The parties, or the two appointed arbitrators, fail to reach an
                      agreement expected of them under that procedure; or
D
                  (c) A person, including an institution, fails to perform any
                      function entrusted to him or it under that procedure.

            A party may request the Chief Justice or any person or institution
            designated by him to take the necessary measure, unless the agreement
E           on the appointment procedure provides other means for securing the
            appointment." [Underlining is ours]

         16. Section l 1(6)(c) says that in case one of the parties to the arbitration
  agreement fails to perform any function entrusted to it, the other party shall
  have the right to approach the appropriate forum to take necessary measure
F in that regard. However, this provision also says that in a situation where the
  arbitration agreement provides for other measures for securing the appointment
  of an arbitrator, the same shall be followed.

         17.lt was contended by Mr. Ranjan Mukherjee, learned counsel appearing
  for the appellants, that it was not open to the High Court to appoint an
G arbitrator without complying with Clause 29 of the contract. According to him,
  as noted herein earlier, the High Court by its own order dated 7th May 2003
  directed appointment of an arbitrator in compliance with Clause 29 of the              .,;.
  contract which clearly provides a procedure for appointment of an arbitrator
  and also indicates who shall oe appointed arbitrator and how he shall be
H appointed. Mr. Mukherjee had brought to our notice that Clause 29 of the
                         MUNICIPAL CORPR.'I, JABALPUR v. RAJESH CONSTRUCTIONS CO. [TARUN CHATTERJEE, I.]   145

        ~-;     contract clearly stipulated that no person other than the Arbitration Board A
                constituted by the Corporation would act as arbitrator provided that the party
                invoking arbitration clause furnishes a security deposit of a sum determined
                according to the table given in the contract itself. After such determination
                and on deposit of the said sum by the party invoking arbitration clause, it
                would become the duty and obligation of the Corporation to constitute an
                Arbitration Board as provided in Clause 29 of the contract. Accordingly, Mr. B
                Mukherjee contended that since the High Court by its earlier order dated 7th
,..            of May, 2003, having directed the parties to invoke arbitration clause in
        --\
               compliance with Clause 29 of the contract, it was not open to the High Court
               to appoint a retired Chief Justice of a High Court as an Arbitrator before the
               respondent had furnished security and before detennination of the amount of                       c
               security by the Corporation, as provided in Clause 29 (d) of the contract,
               which clearly says, as noted herein earlier, that no reference for arbitration
               shall be maintainable unless the contractor furnishes the security deposit of
               a sum determined by the Corporation. Mr. Mukherjee, therefore, contended
               that the High Court was not justified in appointing a retired Chief Justice of
               a High Court to act as an Arbitrator over looking Clause 29(d) of the contract D
               and also without considering the fact that obligation of the Corporation to
           •   appoint an arbitrator to resolve a dispute between the parties would only arise
       ~
               when the contractor had furnished security which was to be determined by
               the Corporation.
                                                                                                                 E
                      18. This submission of Mr. Mukherjee was seriously contested by Mr.
               Amit Sharma, learned counsel appearing for the respondent. According to
               him, no interference can be made with the impugned order since the High
               Court was fully justified in appointing an arbitrator in the manner it had done.
               In this connection reliance was placed on the case of Datar Switchgears Ltd.
               v. Tata Finance Ltd, [2000] 8 SCC 151. Reliance was also placed by Mr. F
               Sharma on the case of Punj Llyods Ltd v. Petronet MHB Ltd., [2006] 2 SCC
               638. Relying on the aforesaid two decisions, Mr. Sharma invited us to re-
               consider the submission of Mr. Mukherjee and to dismiss the present appeal.

                      19. Having heard the learned counsel for the parties and after considering
               the rival submissions made on their behalf and examining Clause 29 of the G
               contract in detail, we are of the view that the High Court was not justified
      .....'   in appointing a retired Chief Justice of a High Court to act as sole arbitrator
               as the same is contrary to Clause 29 of the contract. As noted earlier, the High
               Court, by its earlier order dated 7th May 2003 directed the parties to invoke
               the arbitration clause and to appoint an arbitrator in compliance with Clause H
    146                      SUPREME COURT REPORTS                    [2007] 5 S.C.R.

A 29 of the contract entered into between the parties.                                   .....
           20. Clause 29 specifically stipulates, as indicated herein earlier, that if
    any dispute arises between the parties, the party seeking invocation of the
    arbitration clause, shall first approach the Chief Engineer and on his failure
    to arbitrate the dispute, the party aggrieved may file an appeal to MPL Com,
B   failing which, the Corporation shall constitute an Arbitration Board to resolve
    the disputes in the manner indicated in Clause 29. However, before doing so,
    the party invoking arbitration clause is required to furnish security of a sum
                                                                                         >-
    to be determined by the Corporation.

       21. In this case, admittedly, the security has not been furnished by the
c respondent to the Corporation. We, in fact, asked Mr. Sharma, appearing on
    behalf of the respondent to ascertain on the date of the hearing of the appeal,
    whether the security deposit was made or not. On instruction, Mr. Sharma
    informed us that such security has not yet been deposited. Such being the
    position even today, we hold that the obligation of the Corporation to constitute
D   an Arbitration Board to resolve disputes between the parties could not arise
    because of failure of the respondent to furnish security as envisaged in
    Clause 29(d) of the contract. Therefore, we are of the opinion, that on account
    of non-furnishing of security by the respondent, the question of constituting
    an Arbitration Board by the Corporation could not arise at all. Accordingly,           "'
    we hold that the High Court was not justified in appointing a retired Chief
E   Justice of a High Court as Arbitrator by the impugned order.

        22. It is not disputed before us that the learned Arbitrator appointed by
  the High Court has already commenced the arbitration proceeding. Mr.
  Mukherjee, appearing on behalf of the Corporation, on instruction, had
  submitted before us that they shall constitute an Arbitration Board as soon
F as the respondent furnishes security in terms of Clause 29( d) of the contract
                                                                                           ,___

  and if any direction is given to the Arbitration Board to proceed from the
  stage the learned Arbitrator had already reached, that would not be objected
  to. That is to say, Mr. Mukherjee contended that the Arbitration Board may
  be directed to take over the arbitration proceedings from the stage the learned
G Arbitrator had already reached.
        23. Such being the stand taken by the Corporation, we direct the                  ,...
  respondent to furnish the security of a sum to be determined by the Corporation
  within six weeks from this date and in the event security determined by the
  Corporation is furnished within the time mentioned herein earlier, the Corporation
H shall constitute an Arbitration Board in compliance with Clause 29 of the
                  MUNICIPAL CORPRN, JABALPUR v. RAJESH CONSTRUCTIONS CO. (T ARUN CHATTERJEE. !.)   147

~·1
        contract. It is directed that the Arbitration Board shall proceed from the stage                 A
        the learned Arbitrator appointed by the High Court had already reached.

              24. That apart, it has to be kept in mind that it is always the duty of
        the court to construe the arbitration agreement in a manner so as to uphold
        the same. Therefore we must hold that the High Court ought not to have
        appointed an arbitrator in a manner, which was inconsistent with the arbitration                 B
        agreement.

_..._          25. Before parting with this judgment, we will be failing in our duty if
        we do not consider and deal with the decisions cited by Mr. Sharma appearing
        on behalf of the respondent. First decision relied on by him was Datar
        Switchgears Ltd. case (supra). It is difficult to understand how the said                        c
        decision would be of assistance to Mr. Shanna. In this decision, this Court
        was dealing with a case falling under Section 11(6) of the Act where no time
        limit is prescribed, whereas time limit of 30 days is prescribed under Section
        11(4) and (5) of the Act. In that context, it was held by this court that if one
        party makes a demand for appointment of an arbitrator to the opposite party                      D
        and the latter does not make an appointment within 30 days of demand, the
   I
        right of appointment of arbitrator does not get automatically forfeited after
 ~      expiry of 30 days. This Court held that under Section 11(6), if the opposite
        party has not made an appointment within 30 days of demand, the right to
        make appointment is not forfeited but still continues. However, the right of
        the opposite party ceases when an application under Section 11 seeking                           E
        appointment of an arbitrator is filed. This is not the factual situation in the
        present case, nor are we concerned with this aspect in the present case.

              26. So far as the case of Punj Llyods Ltd (supra) is concerned, it is true
        that this decision of this Court was rendered by a bench of three Judges
                                                                                                         F
        which affinned the decision in the case of Datar Switchgears Ltd. (supra).
        Since we are not concerned in the facts and circumstances of the present case
        with the question decided by this Court· in the aforesaid two decisions, we
        are unable to rely on those decisions.

              27. For the reasons aforesaid, the order dated 29th July 2004 which has                    G
        given rise to Civil Appeal arising out of Special Leave Petition No.19332 of
        2005 is set aside and we direct the Corporation to constitute an Arbitration
 '4:-
        Board in tenns of Clause 29 within a period of three months from this date,
        provided the respondent furnishes security in tenns of the table provided in
        Clause 29(d) of the contract, as detennined by the Corporation within a period
        of six weeks from this date. We, however, make it clear that in view of the                      H
    148                    SUPREME COURT REPORTS                   [2007] 5 S.C.R.

A stand taken by the Corporation, as noted herein earlier, the Arbitration Board
    shall commence their proceedings from the stage the arbitrator appointed by
    the High Court had already reached.

          28. Since we have set aside the order dated 29th July 2004, Civil Appeal
    arising out of Special Leave petition No. 19333 of2005 filed against the order
B   dated 8th April, 2005 has become infructuous.

         29. The Appeal is disposed of in the manner indicated above. There will
    be no order as to costs.

    D.G.                                                     Appeal disposed of.
c




                                                                                      ~-




                                                                                     "'-·


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.