MUKUL SHARMAversusORION INDIA (P) LTD. THROUGH ITS MANAGING DIRECTOR
- Citation
- 2016 INSC 400
- Decided
- 10 May 2016
- Disposal
- Appeal(s) allowed
Holding
The defendant, having later accepted the plaintiff’s definition that excludes common areas, cannot resile from that mutually agreed position under Section 5 of the Indian Contract Act.
Summary
The appellant, Mukul Sharma, entered into a sale deed with Orion India for a specified built‑up area of a building. A dispute arose over whether the term "built‑up area" included common areas such as lifts, corridors and lobbies. Initially the plaintiff understood it to include common areas, but later raised a dispute and the defendant, through letters dated 9‑Mar‑1998 and 16‑Mar‑1998, accepted the plaintiff’s definition that excluded common areas. The trial court decreed specific performance in favour of the plaintiff, but the High Court set aside the decree, holding that the plaintiff could not resile from his earlier understanding under Section 5 of the Indian Contract Act. The Supreme Court held that it was the defendant who altered his position and subsequently agreed to the plaintiff’s definition, and therefore, under the spirit of Section 5, the defendant cannot now withdraw from that mutually agreed position. The appeal was allowed, the High Court judgment set aside, and the trial court directed to calculate the built‑up area according to the agreed definition.
Issues considered
- Whether the parties intended that "built‑up area" include common areas.
- Whether the plaintiff is entitled to specific performance of the sale deed.
- Whether the plaintiff is entitled to a monetary decree.
- Whether the defendant can resile from the later agreed definition of "built‑up area" under Section 5 of the Indian Contract Act, 1872.
- Whether extrinsic evidence may be used to interpret an undefined term in the contract.
Legislation cited
Subjects
Judgment
[2016] 2 S.C.R. 666
A MUKUL SHARMA
v.
ORION INDIA (P) LTD. THROUGH ITS MANAGING
DIRECTOR
B (Civil Appeal No. 4997 of2016)
MAY 10,2016
[KURIAN JOSEPH AND ROHINTON FALi NARIMAN, JJ.)
Specific performance: Suit for specific performance of
agreement - As per the agreement, certain proportion of built-up
c area was liable to be handed over to the plaintiff-appellant - Dispute
as to what is the built-up area - Appellant sent a letter stating that
built up area was understood to include the common area -
Defendant agreed to the definition of built up area as given by
plaintiff in order to resolve the matter - This was followed by another
D letter by defendant· wherein· they stated that all common area were
excluded as suggested by the plaintiff - Trial court decreed the suit
- However, High Court set aside the decision of the trial court - On
appeal, held: It was defendant who changed his stand and accepted
the position as raised by plaintiff - Thereafter and therefore, under
the spirit of s.5 of the Contract Act, defendant cannot resile from
E
the mutually agreed position.
Allowing the appeal, the Court
HELD: 1. It is not a case where the plaintiff resilea from the
agreement. It is a case where the defendant himself subsequently
F accepted the dispute raised by the plaintiff with regard to the
concept of 'built-up area'. In express terms, the respondent-
defendant has subsequently agreed that the built-up area will not
include the common area like lift well, corridor, lobby, duct, etc.
Admittedly, the expression "built up area" is not defined in the
sale deed. It is something to. be deciphered from the conduct of
G the parties. No doubt, the appellant plaintiff had, after five years
of the sale deed, as per letter understood the built up area as
including common area. But subsequently, he disputed the
position and it was the respondent-defendant who accepted and
agreed to the position that built up area does not include common
H area. It is not as if an attempt is made for interpreting the express
666
MUKUL SHARMA v. ORION INDIA (P) LTD. THROUGH ITS 667
MANAGING DIRECTOR
terms of an agreement, by subsequent condnct. It is a sitnation A
where there is a dispnte on a concept relating to an expression/
concept which is not explained in the agreement. The plaintiff
had initially understood the concept in a particular angle or manner.
.Bnt that does not prevent him from raising a dispute. And on
raising such a dispnte, nothing prevented the defendant from
B
insisting the plaintiff to stick to his original stand. On the contrary,
it is the defendant who changed his stand and accepted the position
as raised by the plaintiff. Thereafter and therefor, under the true
spirit of section 5 of the Contract Act, defendant cannot resile
from the mutually agreed position; [Para 9] (670-C-G]
Abdulla Ahmed vs. Animendra Kissen Mitter AIR 1950 c
SC 15:1950 SCR 30; Godhra Electricity Co. Ltd & Am:
vs. The State of Gujarat & Anr. AIR 1975 SC 32:1975
(2) SCR 42 - referred to.
Case Law Reference
D
1950 SCR 30 referred to Para 10
1975 (2) SCR 42 referred to Para 10
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4997 of
2016.
From the Judgment and Order dated 01.09.2015 of the High Court, E
at Guwahati,.in RFA No. 38 of2006.
Shyam Divan, Sr. Adv., P. V. Yogeswaran for the Appellant.
Avijit Bhattacharjee, Ms. Upma Shrivastava for the Responden.t.
The following Order of the Court was delivered
ORDER F
I. Leave. granted.
2. The appellant filed Title Suit No.195 of 1998 before the Civil
Judge (Senior Division) No. I at Guwahati praying for specific
performance of the instrument dated 25.8.1992 between the appellant
G
and the respondent.
3. The dispute is only on a narrow compass. As per paragraph (1 L
of the aforesaid agreement, half of the built up area on the ground floor
of the proposed North Block of the complex as per the drawingNo.GBA/
891/03Adated 14.12.1990 and half of the built up area on the mei:zanine
H'
668 SUPREME COURT REPORTS [2016] 2 S.C.R.
A floor of the same building and complete built up area on the first floor in
the same building, were liable to be handed over to the appellant. On a
dispute as to what is the built up area, the appellant filed the civil suit.
The suit was decreed. Aggrieved by the same, the respondent-defendant
filed first appeal before the High Court. The following points for
determination were found to arise in the first appeal :
B
(i) Whether the parties had entered into agreement knowing that
'built up area' as mentioned in Ext. I agreement includes the
common area?
(ii) Whether the plaintiff is entitled to specific performance as
C claimed?
(iii) Whether plaintiff is entitled to a money decree as prayed for?
4. As per the impugned order, the High Court has taken the view
that the built up area includes the common area as understood by the
parties. Reliance is placed on Ex.'H' letter dated 15.9.1997 written by
D the appellant-plaintiff to the respondent-defendant. As per the said letter,
indisputably, the built up area has been understood to include the common
area.
5. However, the High Court has failed to appreciate Ex.3 letter
dated 9 .3 .1998 and Ex.4 letter dated 16.3 .1998 in the correct perspective.
E The relevant portion of annexure Ex.3 letter dated 9.3.1998 reads as
follows:
"(!)That the "built-up area" as in clause l(i), (ii) & (iii) of the
Agreement between yourself and the Company (Deed No.5581
dated 25/8/98) should be defined as "the area with in the four walls
F excluding the common area as lift well, lobby, corridor, etc.
(2) That our method of calculation and the area so calculated is
not acceptable to you.
Since we wish to resolve this long outstanding issue as early as
possible, we agree to your definition of"built-up area" and shall
G recalculate the area to be allotted to you and shall inform you
shortly."
6. This was followed by Ex.4 letterdated 16.3.1998 wherein it is
stated in the very opening paragraph of the said letter as follows:
"Further to our letter No.ORION/44-1198/028 dt.9/3/98, we furnish
H
MUKUL SHARMA v. ORION INDIA (P) LTD. THROUGH ITS 669
MANAGING DIRECTOR
below the built-up areas calculated for drg. Nos.GBA/891/03A, A
GBA/891/04A and GBA/891/05A using our accepted definition
of "built-up area''. Please note that all common area such as lift
well, corridor, lobby, duct, etc., have been excluded as suggested
QyyQy,."
(All emphasis supplied) B
7. It is unfortunate that the High Court has gone by the earlier
understanding of the plaintiff on the concept of built-up area and wholly
ignoring the understanding mutually entered into between the plaintiff
and the defendant on a later date. According to the High Court, since
the plaintiff had once accepted the position that built-up area included c
common areas, he is always bound by the same. If plaintiff had once
accepted the position in regard to the concept of 'built-up area' he cannot
resile subsequently in view of bar under section 5 of the Indian Contract
Act, 1872, once offer and acceptance is complete, it is held.
8. The relevant consideration by the High Court at para 26 of the D
impugned judgment reads as follows:
"If Ext.3 and Ext.4 are studied and compared it would appear
that prima facie, defendant undertook to accept the definition of
'built up area' given by the plaintiff and therafter deferred the
matter for recalculation of the entitlement on the light of such E
definition. But in the subsequent communication, the defendant
made recalculation as to entitlement of the plaintiff by applying
his own definition of the 'built up area' and thus included common
areas in the 'built up area'. This letter was written on 16.3 .1998.
But prior to that it is the plaintiff who had accepted the concept of
'built up area' as given by the defendant in his letter dated 15.9.1997 F
and made his own calculation about the entitlement of 'built up
area'. According to the version of the plaintiff in the said letter
dated 15.9.1997 (Ext.H), he was allotted possession of 8726.43
sq.ft of 'built up area' in total in three floors, namely, first floor,
mezz.anine floor and the third floor. Out of this total 'built up area' G
of8726.43 sq.ft., plaintiff himself admitted in the said letter that
there was 558.19 sq.ft. common area in the first floor, 544.74
sq.ft common area in the mezzanine floor and 540 sq.ft in the
third floor. Thus, out of 8726.43 sq.ft 'built up area' handed over
to the plaintiff, there was 558.19 sq.ft+ 554. 74 sq.ft+ 540 sq. ft=
1652.93 sq.ft common areas and balance 7083.50 sq.ft under H
670 SUPREME COURT REPORTS (2016) 2 S.C.R.
A exclusive possession of the plaintiff. The plaintiff after showing
this calculation claimed thereafter that he was still entitled to
3445.57 sq.ft in the top floor i.e. eighth floor. The sum of8726.43
sq.ft+ 3445.57 sq.ft is 12172 sq.ft and so there is logic behind this
calculation shown by the plaintiff. Once this calculation is accepted,
it is clear that prior to issuance ofletter 9.3.1998, the plaintiffhad
B
accepted the proposition that built up area would include common
areas. If plaintiff had accepted the proposition of the defendant in
regard to concept of'built up area' he cannot resile subsequently
in view of bar under section 5 of the Indian Contract Act, 1872."
9. It is not a case where the plaintiffresiled from the agreement. It
c is a case where the defendant himself subsequently accepted the dispute
raised by the plaintiff with regard to the concept of 'built-up area'. In
express tenns, the respondent-defendant has subsequently agreed that
the built-up area will not include the common area like lift well, corridor,
lobby, duct, etc. Admittedly, the expression "built up area" is not defined
D in the sale deed. It is something to be deciphered from the conduct of
the parties. No doubt, the appellant plaintiff had, after five years of the
sale deed, as per letter Ex.'H' dated 15.9.1997 understood the built up
area as including common area. But subsequently, he disputed the position
and it was the respondent-defendant who accepted and agreed to the
position that built up area does not include common area. It is not as ifan
E attempt is made for interpreting the express terms of an agreement, by
subsequent conduct. It is a situation where there is a dispute on a concept
relating to an expression/concept which is not explained in the agreement.
The plaintiff had initially understood the concept in a particular angle or
manner. But that does not prevent him from raising a dispute. And on
F raising such a dispute, nothing prevented the defendant from insisting
the plaintiffto stick to his original stand. On the contrary, it is the defendant
who changed his stand as per Ex.3 and Ex.4 and accepted the position
as raised by the plaintiff. Thereafter and therefor, under the true spirit of
section 5 of the Contract Act, defendant cannot resile from the mutually
agreed position.
G
I 0. In Abdulla Ahmed vs. Animendra Kissen Miller - AIR 1950
SC 15, this Court has dealt with a similar situation and it has been held
that"
"Extrinsic evidence to detennine the effect of an instrument is
H pennissible where there remains a doubt as to its true meaning.
MUKUL SHARMA v. ORION INDIA (P) LTD. THROUGH ITS 671
MANAGING DIRECTOR
Evidence of the acts done under it is a guide to the intention of the A
parties in such a case and particular]y when acts are done shortly
after the date of the instrument."
This was followed in The Godhra Electricity Co. Ltd & Anr. vs.
The State of Gujarat & Anr. - AIR 1975 SC 32 :
"In these circumstances, we do not think we will be justified in B
not following the decision of this Court in Abdulla Ahmed vs.
Animendra Kissen Mitter - 1950 SCR 30 at p.46 = (AIR 1950
SC 15 at p.21 ), where this Court said that extrinsic evidence to
determine the effect of an instrument is permissible where there
remains a doubt as to its true meaning and that evidence of the c
acts done under it is a guide to the intention ·of the parties,
particularly, when acts are done shortly after the date of the,
instrument."
11. We, accordingly, allow this appeal, set aside the impugned
judgment of the High Court with regard to the finding on the 'built-up D
area' and restore that of the trial court.
12. We find that the High Court has remanded the matter to the
trial court forthe purpose of calculation of the built up area to be handed
over to the plaintiff-appellant. We direct the trial court to make the
calculation in terms of this judgment and accordingly, dispose of the suit E
expeditiously.
No costs.
Devika Gujral Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.