Created byFuzzy Cloud

Supreme Court of India

MP RURAL ROAD DEVELOPMENT AUTHORITY & ANR.versusM/S. L.G. CHAUDHARY ENGINEERS & CONT.

Citation
2012 INSC 49
Decided
24 January 2012
Disposal
Matter referred to larger bench

Holding

The Madhya Pradesh Arbitration Tribunal Act, 1983 is saved by Section 2(4) of the Arbitration and Conciliation Act, 1996 and continues to apply; the dispute must be arbitrated under the M.P. Act, and the Va Tech decision is per incuriam.

Summary

The M.P. Rural Road Development Authority entered into a works contract with L.G. Chaudhary Engineers for road construction. After alleged breaches, the Authority terminated the contract and encashed the contractor's bank guarantee, leading to a dispute. The contractor sought arbitration under the Arbitration and Conciliation Act, 1996, but the Authority argued that the Madhya Pradesh Arbitration Tribunal Act, 1983 (M.P. Act) required the dispute to be referred to the state tribunal. The Supreme Court examined whether the M.P. Act survives the later central legislation and whether a dispute arising from the termination of a works contract falls within the definition of "works contract" under the M.P. Act. The Court held that the M.P. Act is saved by Section 2(4) of the 1996 Act and continues to operate, and that the earlier Va Tech decision was per incuriam. Consequently, the appeal was allowed and the arbitration must proceed under the M.P. Act, not the 1996 Act.

Issues considered

  • Whether the provisions of the Madhya Pradesh Arbitration Tribunal Act, 1983 are displaced by the Arbitration and Conciliation Act, 1996.
  • Whether a dispute arising from the termination/cancellation of a works contract falls within the definition of "works contract" under the M.P. Act and must be referred to the state tribunal.
  • Whether the Supreme Court's decision in Va Tech Escher Wyss Flovel Ltd. v. MPSE Board is per incuriam and binding.
  • Whether there is a repugnancy between the two Acts under Article 254 of the Constitution.

Legislation cited

Subjects

ArbitrationStatutory arbitrationMadhya Pradesh Arbitration Tribunal ActArbitration and Conciliation Act 1996Per incuriamRepugnancy of statutesWorks contractTermination of contractConcurrent legislation

Judgment

                         [2012] 2 S.C.R. 162


A   MP RURAL ROAD DEVELOPMENT AUTHORITY & ANR.
                                  v.
          M/S. L.G. CHAUDHARY ENGINEERS & CONT.
                  (Civil Appeal No. 974 of 2012)

                        JANUARY 24, 2012
B
         [ASOK KUMAR GANGULY AND GYAN SUDHA
                      MISRA, JJ.]

       Arbitration: Whether the provision of Madhya Pradesh
C Arbitration Tribunal Act, 1983 which statutorily provides for the
  parties to the Works Contract to refer all disputes to the
  Arbitration Tribunal constituted u/s. 7 of the 1983 Act will
  continue to operate in view of the provisions of Arbitration and
  Conciliation Act, 1996 which is a Central Act, subsequently
D enacted - In view of difference of opinion, matter referred to
  larger bench - Madhya Pradesh Arbitration Tribunal Act, 1983
  - Arbitration and Conciliation Act, 1996.

       The appellant had entered into a 'Works Contract'
E with the respondent for construction and maintenance of
  Rural Road Package. Clause 24 of the Contract contained
  the 'Dispute Redress Mechanism'. The case of the
  appellant was .that in view of several breaches in Works
  Contract by the respondent, the appellant terminated the
  Works Contract and encashed the bank guarantee
F furnished by the respondent.

       ·On 29.8.2008, the respondent submitted a
  representation to the appellant against the encashment
  of bank guarantee. Prior to that on 5.8.2008, respondent
G filed a writ petition challenging the encashment of bank
  guarantee and the writ petition was disposed of with a
  direction that the bank guarantee may not be encashed
  till the disposal of the representation. Thereafter, on
  4.6.2009, the representation of the respondent was
H                                162
  M.P. RURAL ROAD DEV AUTHORITY v. L.G CHAUDHARY         163
                 ENGINEERS & CONT
  rejected. In the pending dispute, the respondent              A
  submitted additional claim on 24.2.2010 and requested
' the appellant to appoint an Arbitrator for adjudicating the
  dispute between the parties. On 24.4.2010, the appellant
  replied that Clause 25 of the Works Contract specifically
  provided for adjudication of disputes by the Arbitral         B
  Tribunal under the Madhya Pradesh Arbitration Tribunal
  Act, 1983 (M.P. Act). Then on 24.6.2010 respondent filed
  an application under Section 11 of the Arbitration and
  Conciliation Act, 1996 (A.C. Act 1996) for appointment of
  an Arbitrator before the High Court. On 8.9.2010, the High    c
  Court allowed the application of the respondent and
  appointed an arbitrator by placing reliance on a decision
  of the Supreme Court in *Va Tech Escher Wyass Flovel
  Ltd. Vs. MPSE Board.

      The question which arose for consideration in the         D
 instant appeal was whether the provision of the Madhya
 Pradesh Arbitration Tribunal Act, 1983 which statutorily
 provides for the parties to the Works Contract to refer all
 disputes to the Arbitration Tribunal constituted under
 Section 7 of the Act will continue to operate in view of the   E
 provisions of Arbitration and Conciliation Act, 1996 which
 is a Central Act, subsequently enacted.

     Referring the matter to larger bench, the Court

     HELD:                                                      F

      Per Ganguly, J: 1. Perusal of Section 7 of the Madhya
 Pradesh Arbitration Tribunal Act, 1983 (M.P. Act) showed
 that the nature of the dispute between the parties in the
 instant case was covered by the definition under Section       G
 2(d) read with Section 2(1 ). As such under Section 7 such
 a dispute has to be statutorily referred to Tribunal set up
 under the M.P. Act. Reading of Section 2(4) of A.C. Act
 1996 would show that Part-I of A.C. Act 1996, which is
 from Section 2 to Section 43, shall, except sub-section 1      H
    164     SUPREME COURT REPORTS            [2012] 2 S.C.R.


A of Sections 40, 41 and 43, apply to every arbitration under
  any other enactment for the time being in force where the
  arbitration was pursuant to an arbitration agreement
  except insofar as the provisions of this Part i.e. Part-I are
  inconsistent with the other enactment or with any other
B rule made thereunder. Similar provision relating to
  statutory arbitration was also there in Section 46 of
  Arbitration Act, 1940. The provisions of M.P. Act are
  inconsistent with the provisions of A.C. Act 1996. The
  M.P. Act is a special law providing for statutory arbitration
c in the State of Madhya Pradesh even in the absence of
  arbitration agreement. Under the provisions of A.C. Act
  1996, in the absence of an arbitration agreement,
  arbitration is not possible. There is also difference in the
  formation of arbitration tribunal as is clear from Section
0 2(1)(d) of A.C. Act 1996. Again under A.C. Act 1996,
  arbitral tribunal is defined under Section 2(1 )(d) as a sole
  arbitrator or a panel of arbitrators. But under M.P. Act,
  such a tribunal is created under Sections 3 and 4 of the
  Act. Under the M.P. Act, dispute has a special meaning
E as defined under ·section 2(1 )(d) of the Act whereas
  dispute has not been defined under the A.C. Act 1996.
  [Paras 9, 23, 24, 25) [176-F; 179-E-F-G; 180-B-D]

       2. The M.P. Act provides for the establishment of a
  tribunal to arbitrate in disputes to which the State
F Government or a public undertaking [wholly or
  substantially owned or controlled by the State
  Government], is a party, and for matters incidental thereto
  or connected therewith. The structure of the tribunal
  under the M.P. Act is also different from the structure of
G a tribunal under the A.C. Act 1996. It is clear from Section
  4 of the M.P. Act that the composition of tribunal and their
  qualification is statutorily provided. The term of office and
  salaries and allowances are also statutorily provided
  under Sections 5 and 6 of the M.P. Act. Section 8
H provides for the procedure to be followed by the tribunal
 M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY         165
                ENGINEERS & CONT.

on receipt of reference and Section 9 provides for the          A
Constitution of Benches and Chairman's power of
distribution of business. Under Section 16(2) of the M.P.
Act, there is a time limit for giving the Award which is
absent in A.C. Act 1996. Section 17-A of the M.P. Act
confers inherent power on the Arbitral tribunal to make         B
orders as may be necessary for the ends of justice or to
prevent abuse of the process of the tribunal. Section 17-
8 also provides for power conferred on the tribunal for
correction of clerical or arithmetical mistakes. No such
power is given to an arbitral tribunal under A.C. Act 1996.     c
Section 19 of the M.P. Act gives High Court the suo motu
power of revision. The High Court has also been given
the power of revision to be exercised on an application
made by an aggrieved party within three months of the
award. While doing so, the High Court is to act like a          0
revisional court under SeCtion 115, CPC. It is clear from
the. said enumeration of the statutory provision that under
the M.P. Act the parties' autonomy in the choice of arbitral
tribunal is not there. In **State of Madhya Pradesh and
another vs. Anshuman Shukla, this Court while referring
                                                                E
to the M.P. Act and dealing with the nature of the arbitral
tribunal constituted under the said Act held that the said
Act is a special Act and provides for compulsory
arbitration. It provides for a reference and the tribunal has
been given the power of rejecting the reference at the
threshold. It also held that the M.P. Act provides for a        F
special limitation and fixes a time limit for passing an
award. It has also been hel.d that Section 14 of the M.P.
Act provides that the award can be challenged under
special circumstances and Section 17 provides for finality
of the award, notwithstanding anything to the contrary          G
contained in any other law relating to arbitration. All these
features of the Act were pointed by this Court in
**Anshuman Shukla to show that there is inconsistency
between the provisions of A.C. Act 1996 and those of the
M.P. Act. It is clear, therefore, that in view of the finding   H
    166     SUPREME COURT REPORTS            [2012] 2 S.C.R.


A of a co-ordinate Bench of this Court on the distinct
  feature of an arbitral tribunal under the said M.P. Act, the
  provisions of M.P. Act are saved under Section 2(4) of
  A.C. Act 1996. This Court while rendering the decision in
  *Va Tech did not either notice the previous decision of a
B co-ordinate Bench of this Court in **Anshuman Shukla
  or the provisions of Section 2(4) of A.C. Act 1996.
  Therefore, the decision of this Court in *Va Tech was
  rendered per incuriam. The decision in **Va Tech, having
  been rendered in per incuriam cannot be accepted as a
c precedent to decide the controversy in this case. [Paras
  26, 27, 28, 29, 30, 41] [180-E-G; 181-H; 182-A-H; 183-F-H;
  186-0]

    , **State of Madhya Pradesh and another vs. Anshuman
  Shukla (2008) 7 SCC 487: 2008 (8) SCR 349; The Bengal
D Immunity Company Limited vs. The State of Bihar and others
  1955 (2) SCR 603; State of UP. and another vs. Synthetics
  and Chemicals Ltd. and another (1991) 4 sec 139; Municipal
  Corporation of Delhi vs. Gurnam Kaur (1989) 1 SCC 101:
  1988 (2) Suppl. SCR 929 - relied on.
E
        *Va Tech Escher Wyass Flovel Ltd. Vs. MPSE Board &
    another 2011(13) sec 261 - per incurium

        Ravikant Bansal vs. M.P. Rural Road Development
    Authority and Anr. 2012 (3) SCC 513 - referred to.
F
        Young vs. Bristol Aeroplane Company, Limited 1944 (1)
    K.B. 718; Young vs. Bristol Aeroplane Company, Limited
    1946 Appeal Cases 163; Morelle Ld. vs. Wakeling & another
    (1955) 2 QB 379 - referred to.
G
     : 4. The provision for repeal under Section 85 of A.C.
  Act 1996 does not show that there is any express repeal
  of the M.P. Act. Apart from that the provision of Section
  2(4) of A.C. Act clearly militates against the said
H submissions. The argument of repugnancy is also not
 M.P. RURAL ROAD DEV AUTHORITY v. L.G CHAUDHARY         167
                ENGINEERS & CONT

tenable. In view of Entry 13 of the Concurrent List in the     A
Vllth Schedule of the Constitution, the State Government
is competent to enact laws in relation to arbitration. The
M.P. Act of 1983 was made when the previous Arbitration
Act of 1940 was in the field. That Act of 1940 was a Central
Law. Both the Acts operated in view of Section 46of1940        B
Act. The M.P. Act 1983 was reserved for the assent of the
President and admittedly received the same on
17.10.1983 which was published in the Madhya Pradesh
Gazette Extraordinary dated 12.10.1983. Therefore, the
requirement of Article 254(2) of the Constitution was          c
satisfied. Thus, M.P. Act of 1983 prevails in the State of
Madhya Pradesh. Thereafter, A.C. Act 1996 was enacted
by Parliament repealing the earlier laws of arbitration of
1940. It has also been noted that A.C. Act 1996 saves the
provisions of M.P. Act 1983 under sub-sections 2(4) and
                                                               0
2(5) thereof. Therefore, there cannot be any repugnancy.
In the instant case, the latter Act made by the Parliament
i.e. A.C. Act 1996 clearly showed an intention to the effect
that the State Law of Arbitration i.e. the M.P. Act should
operate in the State of Madhya Pradesh in respect of
certain specified types of arbitrations which are under the    E
M.P. Act 1983. This is clear from Sections 2(4) and 2(5) of
A.C. Act 1996. Therefore, there is no substance in the
argument of repugnancy and is accordingly rejected.
Therefore, appeal is allowed and the judgment of the
High Court which is based on the reasoning of *Va Tech         F
is set aside. In that view of the matter the arbitration
proceeding may proceed under M.P. Act of 1983 and not
under A.C. Act 1996. [Paras 43-48] [186-F-H 187-B-E; 188-
B-D]
                                                               G
    T. Barai vs. Henry Ah Hoe and another AIR 1983 SC 150
M. Karunanidhi vs. Union of India and another (1979) 3 SCC
431: 1979 (3) SCR 254 - relied on.

Per Gyan Sudha Misra, J: (Partly dissenting)
                                                               H
    168         SUPREME COURT REPORTS         [2012] 2 S.C.R.

A      1. Perusal of Section 7 of the Madhya Pradesh
  Arbitration Tribunal Act showed that the matter in the
  event of existence of a dispute between the parties in
  certain categories of cases where the State of Madhya
  Pradesh is a contracting party, the dispute shall be
B referred in writing to the tribunal irrespective of the fact
  whether the agreement contains an arbitration clause or
  not. From this provision, it is clearly apparent that
  reference of any dispute to the tribunal postulates an
  existence of a works contract and the definition of 'works
c contract' under Section 2(i) of the M.P. Arbitration Tribunal
  Act, 1983, it has clearly and unequivocally been specified
  as to what is a 'works contract' in relation to which the
  dispute is required to be referred in writing to the tribunal.
  Thus, on a perusal of the definition of 'works contract', it
D is manifestly clear that while the 'works contract' means
  an agreement pertaining to matters relating to the
  execution of any of the work enumerated in the definition
  of 'works contract', the same does not include the
  dispute pertaining to termination, cancellation or
  repudiation of works contract and the entire nature of
E transaction laid down therein relates to disputes which
  arise out of execution of the nature of work specified in
  the 'works contract'. However, the question whether the
  'works contract' has been legally repudiated and rightly
  cancelled or not is the question or dispute pertaining to
F termination of works contract has not been incorporated
  even remotely within the definition of 'works contract'. In
  view of this, the legal and logical consequence which can
  be reasonably drawn from the definition of 'works
  contract' would be, that if there is a dispute between the
G contracting parties for any reason relating to works
  contract which include execution of any work, relating to
  construction, repair or maintenance of any building or
  super-structure, dam, weir, canal, reservoir, tank, lake,
  road, well, bridge, culvert, factory, workshop, power
H house, transformers or such other works of the State




          ' I
 M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY         169
                ENGINEERS & CONT.

Government or Public Undertaking including an                   A
agreement for the supply of goods or material and all
other matters relating to the execution of any of the said
works, the same would fall within the ambit of the
definition of 'works contract' and hence all disputes
pertaining or arising out of execution of the works             B
contract will have to be referred to the M.P. State
Arbitration Tribunal as envisaged under Section 7 of the
Act of 1983. Hence, in addition to the reasons assigned
in the judgment and order of Justice Ganguly, disputes
arising out of execution of works contract has to be            c
referred to the M.P. State Arbitration Tribunal and not
under the Arbitration and Conciliation Act, 1996. [Paras
4, 5] [189-A-C, G-H; 190-A-E]
     2. But in so far as the instant matter is concerned, the
facts disclosed that the appellant M.P. Rural Road              D
Development Authority cancelled the works contract
itself which was executed in favour of the respondent. In
that event, the works contract between the parties was
not in existence at all which would operate as a statutory
mandate for reference of the dispute to the M.P. State          E
Arbitration Tribunal. It is no doubt true that if the matter
were before an Arbitrator appointed under the Arbitration
and Conciliation Act, 1996 for adjudication of any dispute
including the question regarding the justification and
legality as to whether the cancellation of works contract       F
was legal or illegal, then the said Arbitrator in view of the
ratio of the judgment of the Supreme Court in Maharshi
Dayanand University & Anr. v. Anand Co-op L(C) Society
as also in view of the persuasive reasoning assigned in
the judgment and order reported in Heyman & Anr. Vs.            G
Darwins, Limited would have had the jurisdiction to
adjudicate the dispute regarding the justification and
legality of cancellation of works contract also. But the
same cannot be allowed to be raised under the M.P. Act
of 1983 since the definition of 'works contract'
                                                                H
   170      SUPREME COURT REPORTS              (2012] 2 S.C.R.


A unambiguously lays down in explicit terms as to what is
  the nature and scope of 'works contract' and further
  enumerates the specific nature of disputes arising out of
  the execution of works contract which would come within
  the definition of a 'works contract'. However, the same
B does not even vaguely include the issue or dispute
  arising out of cancellation and termination of contract
  due to which this question would not fall within the
  jurisdiction of M.P. State Arbitration Tribunal so as to be
  referred for adjudication arising out of its termination. Fall
c out certainly would be otherwise if the matter were to be
  -adjudicated by an Arbitrator appointed under the
  Arbitration and Conciliation Act, 1996 and that would be
  in view of the ratio of the decisions of the Supreme Court
  which held it permissible for the Arbitrator to adjudicate
D even the dispute arising out of cancellation or termination
  of an agreement or contract. This, however, cannot be
  allowed to broaden or expand the ambit and scope of the
  M.P. Act of 1983 where the State Legislature has passed
  a specific legislation in respect of certain specified types
E of arbitration determining as to what are the nature of
  disputes to be referred to the M.P. State Arbitration
  Tribunal and that specifically permits the reference of
  dispute arising out of execution of contract but clearly
   leaves out any dispute arising out of termination,
  cancellation or repudiation of 'works contract'. If the
F nature of dispute referred to the Arbitrator like the instant
   matter, related to a dispute pertaining to construction,
   repair, maintenance of any building super-structure, dam
   or for the reasons stated within the definition of 'works
   contract', the matter may be referred to the M.P. Tribunal
G in view of the fact that if there is a dispute in relation to
   execution of a works contract, then irrespective of the
   fact whether the agreement contains an arbitration clause
   or not, the dispute is required to be referred to the M.P.
   State Arbitration Tribunal for adjudication. But when the
H contract itself has been terminated, cancelled or
 M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY      171
                ENGINEERS & CONT.

repudiated as it has happened in the instant case, then A
the nature of dispute does not fall within the definition of
'works contract' for the sole reason that it does not
include any dispute pertaining to cancellation of a works
contract implying that when the works contract itself is
not in existence by virtue of its cancellation, the dispute B
cannot be referred to the M.P. State Arbitration Tribunal
but may have to be decided by an Arbitrator appointed
under the Arbitration and Conciliation Act, 1996. Hence,
the nature of the dispute which falls within the definition
of 'works contract' under Section 2(i) of the M.P. Act, 1983 c
and one of the contracting parties to the agreement is the
State of M.P., then irrespective of an arbitration agreement
the dispute will have to be referred to the Tribunal in
terms of Section 7 of the Act of 1983. But if the works
 contract itself has been repudiated and hence not in 0
existence at all by virtue of its cancellation/termination,
 then the dispute will have to be referred to an
 independent arbitrator to be appointed under the
 Arbitration and Conciliation Act, 1996 since the M.P. Act
 1983 envisages reference of a dispute to the State E
 Tribunal only in respect of certain specified types of
 arbitration enumerated under Section 2 (i) of the M.P. Act,
 1983. [Paras 6-9) [190-F-H; 191-A-H; 192-A-G]
     3. The impugned order of the High Court by which
the dispute relating to termination of works contract by F
the M.P. Rural Road Development Authority itself was
referred to an independent arbitrator appointed by the
High Court under the Arbitration and Conciliation Act,
1996 needs to be sustained and there is no need for a
de novo reference of the dispute to the M.P. State G
Arbitration Tribunal. In the alternative, the consequence
would have been otherwise and the matter could have
been referred to the State Arbitration Tribunal if the
dispute between the parties related to any dispute
emerging out of execution of works contract which could
fall within the definition of 'works contract' given out H
   172      SUPREME COURT REPORTS            [2012] 2 S.C.R.


A within the definition of 'works contract' under Section 2(i)
  of the M.P. Act of 1983. In order to avoid any ambiguity,
  in view of cancellation of the works contract itself which
  is the position in the instant case, the proceedings before
  the Arbitrator appointed by the High Court cannot be
B treated as non-est so as to refer the same once again to
  the tribunal for adjudication as the dispute does not
  emerge or pertain to execution of works contract but
  relates to non-existence of works contract by virtue of its
  cancellation. The question as to whether the dispute
c would be referred to the M.P. Tribunal in terms of Section
  7 of the M.P. Act of 1983 or to an independent arbitrator
  'under the Arbitration and Conciliation Act, 1996 will
  depend upon the factum whether the works contract is
  existing between the parties or not out of which the
0 dispute has arisen. In case, the works contract itself has
  been repudiated/cancelled, then, in view of its non-
  existence, Section 7 of the M.P. Act pertaining to
   reference of dispute to tribunal would not come into play
  at all by virtue of the fact that the dispute relating to
E execution of works contract alone can be referred to the
  tribunal in view of the specific nature of works contract
  enumerated within the definition of works contract under
  the Act of 1983. However, when the works contract itself
   becomes non-existent as a consequence of its
  cancellation, the matter will have to be referred to an
F independent arbitrator under the Arbitration and
   Conciliation Act, 1996 and not to M.P. State Arbitration
  Tribunal. Thus, while holding that the M.P. Act 1983
  should operate in the State of M.P. in respect of certain
   specified types of arbitration, the appointment of an
G independent arbitrator by the High Court under the
   Arbitration and Conciliation Act, 1996 needs to be
   sustained since the works contract itself is not in
   existence by virtue of its cancellation and hence this part
   of the dispute could not have been referred to the M.P.
H State Tribunal. [Paras 10-12] (192-H; 193-A-H; 194-A-C]
 M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY      173
                ENGINEERS & CONT.
    Maharshi Dayanand University & Anr. v. Anand Co-op      A
L(C) Society 2007 (5) SCC 295: 2007 (5) SCR 596 - relied
on.

    Heyman & Anr. Vs. Darwins, Limited 1942 (1) All E.R.
337 - referred to.                                          B
                      Case Law Reference

Asok Kumar Ganguly:

  2011(13) sec 261           per incuriam   Paras13-15,
                                            19, 22, 30,
                                                            c
                                            41,48
  2012 (3) sec 513           referred to    Para 21
  2008 (8) SCR 349           relied on      Para 29,30
                                                            D
  1944 (1) K.B. 718          referred to    Para 32,34
  1946 Appeal Cases 163      referred to    Para 34,38
  1955 (2) SCR 603           referred to    Para 36
                                                            E
  (1955) 2 QB 379            referred to    Para 37
  (1991) 4 sec 139           relied on      Para 38
  1988 (2) Suppl. SCR 929 relied on         Para 39
  AIR 1983 SC 150            relied on      Para 46         F

  1979 (3) SCR 254           relied on      Para 46

  Gyan Sudha Misra:

  2007 (5) SCR 596           relied on      Para 7          G
  1942 (1) All E.R. 337      referred to    Para 7

    CIVIL APP ELLATE JURISDICTION : Civil Appeal No. 974
of 2012.
                                                            H
    174          SUPREME COURT REPORTS                  [2012] 2 S.C.R.


A       From the Judgment and Order dated 08.09.2010 of the
    High Court of M.P. at Indore in AC No. 14 of 2010.

             K.K. Venugopal, Mishra Saurabh, Puja Dhar, Ankur Talwar,
    B.S. Banthia, Vias Upadhyay, Dr. Vipin Gupta, Anand Dixit and
    Pratyush Tripathi for the appearing parties.
9
             The Judgment of the Court was delivered by

             GANGULY, J. 1. Leave granted,

C       2. The question which falls for consideration in this appeal
  is whether the provision of Madhya Pradesh Madhyasthan
  Adhikaran Adhiniyam, 1983 (hereinafter, 'M.P. Act') which
  statutorily provides for the parties to the Works Contract to refer
  all disputes to the Arbitration Tribunal constituted under Section
D 7 of the Act will continue to operate in view of the provisions of
  Arbitration and Conciliation Act, 1996 (hereinafter 'A.C. Act
  1996') which is a Central Act, subsequently enacted.

             3. The facts leading to the aforesaid controversy be noted
    first.
E
        4. The appellant-Madhya Praaesh Rural Road
    Development Authority and Anr., impugning the judgment of the
    High Court dated 8.9.2010 in this appeal, entered into a 'Works
    Contract' with the respondent for construction and maintenance
F   of Rural Road Package No.1958, District Jhabua.

        5. Clause 24 of the Contract contains the 'Dispute
    Redress Mechanism' and Clause 24.1 of the same provides
    as under:

G            "24.1 If any dispute or difference of any kind what-so-ever
             shall arise in connection with or arising out of this Contract
             or the execution of work of maintenance of the Works
             thereunder, whether before its commencement or during
             the progress of Works or after the termination,
H            abandonment or breach of the Contract, it shall, in the first
 M.P RURAL ROAD DEV. AUTHORITY v. LG CHAUDHARY                  175
    ENGINEERS & CONT. [ASOK KUMAR GANGULY, J.]

   · instance, be referred for settlement to competent authority,      A
     described along with their powers in the Contract Data,
     above the rank of the Engineer. The competent authority
     shall, within a period of forty five days after being requested
     in writing by the Contractor to do so, convey his decision
     to the Contractor. Such decision in respect of every matter       B
     so referred shall, subject to review as hereinafter provided,
     be final and binding upon the Contract. In case the Works
   . is already in progress, the Contractor shall proceed with
     the execution of the Works, including maintenance thereof,
     pending receipt of the decision of the competent authority        c
     as aforesaid, with all due diligence."

     6. Under the 'M.P. Act' "dispute" has statutorily been
defined under Section 2(d):

    "2(d) "dispute" means claim of ascertained money valued            D
    at Rupees 50,000 or more relating to any difference
    arising out of the execution or non-execution of a works
    contract or part thereof'

      7. "Works Contract" has also been defined under Section
                                                                       E
2(i) of the M.P. Act:

    "2(i) works contract" means an agreement in writing for the
    execution of any work relating to construction, repair or
    maintenance of any building or superstructure, dam, weir,
    canal, reservoir, tank, lake, road, well, bridge, culvert,         F
    factory, workshop, powerhouse, transformers or such other
    works of the State Government or Public Undertaking as
    the State Government may, by notification, specify in this
    behalf at any of its stages, entered into by the State
    Government or by an official of the State Government or            G
    Public Undertaking or its official for and on behalf of such
    Public Undertaking and includes an agreement for the
    supply of goods or material and all other matters relating
    to the execution of any of the said works"
                                                                       H
      176      SUPREME COURT REPORTS                  [2012] 2 S.C.R.


A         8. "Reference to Tribunal" is statutorily provided under
      Section 7 of the M.P. Act:

           "7. Reference to Tribunal - (1) either party to a works
           contract shall irrespective of the fact whether the
B          agreement contains an arbitration clause or not, refer in
         . writing the dispute to the Tribunal.

                  (2) Such reference shall be drawn up in such form
            as may be prescribed and shall be supported by an
            affidavit verifying the averments.
c
                 (3) The reference shall be accompanied by such fee
            as may be prescribed.

                  (4) Every reference shall be accompanied by such
            documents or other evidence and by such other fees for
D
            service or execution of processes as may be prescribed.

                   (5) On receipt of the reference under sub-section (1 ),
            if the Tribunal is satisfied that the reference is a fit case
            for adjudication, it may admit the reference but where the
E           Tribunal is not so satisfied it may summarily reject the
            reference after recording reasons therefor."

       9. From a perusal of Section 7, it is clear that the nature
  of the dispute between the parties in the instant case is
F covered by the definition under Section 2(d) read with Section
  2(1). As such under Section 7 such a dispute has to be
  statutorily referred to Tribunal set up under the M.P. Act.
      10. The case of the appellant is that in view of several
  breaches in Works Contract by the respondent, the appellant
G terminated the Works Contract and encashed the bank
  guarantee furnished by the respondent on 25.6.2008.
           11. The'reafter, on 29.8.2008, the respondent submitted a
      representation to the appellant against the encashment of bank
    H guarantee. Prior to that on 5.8.2008, respondent filed a Writ
  · M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY             177
       ENGINEERS & CONT. [ASOK KUMAR GANGULY, J.]

 Petition No. 4491/2008 challenging the encashment of bank             A
 guarantee and the writ petition was disposed of with a direction
 that the bank guarantee may not be encashed till the disposal
 of the representation. Thereafter, on 4.6.2009 the
 representation of the respondent was rejected after giving the
 appellant a personal hearing.                                         8

      12. In the pending dispute, the respondent submitted
 additional claim on 24.2.201 O and requested the appellant to
  appoint an Arbitrator for adjudicating the dispute between the
. parties. On 24.4.2010, the appellant replied that Clause 25 of       C
  the Works Contract specifically provides for adjudication of
  disputes by the Arbitral Tribunal under the M.P. Act.

      13. Then on 24.6.201 O respondent filed an application
 under Section 11 of A.C. Act 1996 for appointment of an
 Arbitrator before the High Court. On 8.9.2010, High Court             D
 allowed the application of the respondent and appointed an
 Arbitrator by placing reliance on a decision of this Court in Va
 Tech Escher Wyass Flove/ Ltd. Vs. MPSE Board & another -
 Civil Appeal No. 3746 and 3747 of 2005.
                                                                       E
      14. In the case of Va Tech (supra), this Court after referring
 to both the M.P. Act and the A.C. Act 1996, held that the M.P.
 Act applies only where there is no arbitration clause and this
 Court further held that the M.P. Act stands impliedly repealed
 by the A.C. Act 1996 where there is an arbitration clause.
                                                                       F
      15. Facts in connection with the Va Teqh (supra) were that
 Va Tech was awarded a works contract by the M.P. State·
 Electricity Board and there was an arbitration clause in the
 agreement.
                                                                       G
      16. Va Tech filed an application under Section 9 of the A.C.
 Act 1996 which was rejected by the learned Additional District
 Judge and that order was also upheld by the High Court.

      17. Then Va Tech filed a special leave petition before this
 Court. This Court noting the provision of Section 7 of the M.P.       H
    178       SUPREME COURT REPORTS               [2012] 2 S.C.R.


A Act came to the aforesaid finding and ultimately held that the
  judgment of the High Court in Va Tech cannot be sustained and
  opined that application under Section 9 of A.C. Act 1996 is
  m·aintainable. The exact reasoning recorded by this Court in Va
  Tech is as follows:
B
       "In our opinion, the 1983 Act and the 1996 Act can be
       harmonised by holding that the 1983 Act only applies
       where there is no arbitration clause but it stands impliedly
       repealed by the 1996 Act where there is an arbitration
       clause. We hold accordingly.
c
          Hence, the impugned judgment cannot be sustained and
          we hold that the application under Section 9 of the 1996
          Act was maintainable."

D        18. Mr. K.K. Venugopal, learned senior counsel appearing
 · for the appellant submitted that the Division Bench of this Court,
   while coming to the aforesaid finding, has not noticed the
   relevant provision of the M.P. Act as well as the relevant
   provisions of A.C. Act 1996 and as such the same judgment
E was rendered 'per incuriam'.

         19. Learned senior counsel further submitted that another
    Division Bench of this Court in a case in which the Presiding
    Judge was common with the Bench which rendered the Va
    Tech (supra) ruling almost in a situation identical with Va Tech
F   issued notice and stayed the arbitration proceedings.

        20. In another case a Division Bench of this Court presided
    over by the same learned Judge who gave the Va Tech ruling
    passed the following order:
G         'This petition has been filed against the judgment and
          order dated 11th March, 2011 passed by the High Court
          of Madhya Pradesh at Gwalior Bench in Arbitration Case
          No.4 of 2010.

H               Learned counsel for the petitioner has relied on a
 M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY             179
    ENGINEERS & CONT [ASOK KUMAR GANGULY, J.]

    decision of this Court in Civil Appeal No. 3746 of 2005          A
    decided on 14th January, 2010.

           We are of the opinion that the aforesaid decision is
    distinguishable because in the present case the arbitration
    clause itself mentions that the arbitration will be by the
                                                                     8
    Madhya Pradesh Arbitration Tribunal. Hence, in this case
    arbitration has to be done by the Tribunal.

           The Special leave petition is dismissed."

     21. Relying on these two subsequent orders in the instant       c
case and in, Ravikant Bansal vs. M. P. Rural Road
Development Authority and Anr. - SLP(C) No.18867 of 2011,
Mr. Venugopal, the learned senior counsel submitted that
subsequent Division Bench presided over by the same learned
Judge who gave the Va Tech ruling has not followed the ratio
                                                                     0
in the case of Va Tech.
     22. lhe learned counsel said so to justify his contention
that the decision in Va Tech (supra) was rendered per
incuriam.
      23. If this Court looks at Section 2(4) of AC. Act 1996, it    E
will appear that Part-I of A.C. Act 1996, which is from Section
2 to Section 43, shall, except sub-section 1 of Sections 40, 41
and 43, apply to every arbitration under any other enactment
for the time being in force where the arbitration was pursuant
to an arbitration agreement except insofar as the provisions of      F
this Part i.e. Part-I are inconsistent with the other enactment or
with any other rule made thereunder.
     24. Similar provision relating to statutory arbitration was
also there in Section 46 of Arbitration Act, 1940. Section 46 is     G
set out below:
     "46. Application of Act to statutory arbitration - The
     provisions of this Act, except sub-section (1) of Sec. 6 and
     Secs. 7, 12, 36 and 37, shall apply to every arbitration
     under any other enactment for the time being in force, as       H
    180       SUPREME COURT REPORTS                 [2012] 2 S.C.R.


A         if the arbitration were pursuant to an arbitration agreement
          and as if that other enactment were an arbitration
          agreement, except in so far as this Act is inconsistent with
          that other enactment or with any rules made thereunder.

        25. If this Court compares the provisions of the M.P. Act
8
  with A.C. Act 1996 then the Court finds that the provisions of
  M.P. Act are inconsistent with the provisions of AC. Act 1996.
  The M.P. Act is a special law providing for statutory arbitration
  in the State of Madhya Pradesh even in the absence of
  arbitration agreement. Under the provisions of A.C. Act 1996
C in th~ absence of an arbitration agreement, arbitration is not
  possible. There is also difference in the formation of arbitration
  tribunal as is clear from Section 2(1)(d) of AC. Act 1996. Again
  under AC. Act 1996, arbitral tribunal is defined under Section
  2(1 )(d) as a sole arbitrator or a panel of arbitrators. But under
D M.P. Act such a tribunal is created under Sections 3 and 4 of
  the Act. And under the M.P. Act dispute has a special meaning
  as defined under Section 2(1)(d) of the Act whereas dispute
  has not been defined under the A.G. Act 1996.

E       26. It is clear from its long title that the M.P. Act provides
  for the establishment of a tribunal to arbitrate in disputes to
  which the State Government or a public undertaking [wholly or
  substantially owned or controlled by the State Government], is
  a party, and for matters incidental thereto or connected
F therewith. The structure of the tribunal under the M.P. Act is also
  different from the structure of a tribunal under the AC. Act 1996.
  It is clear from Section 4 of the M.P. Act that the composition
  of tribunal and their qualification is statutorily provided which
  is set out below:

G         "4. Chairman and Members of Tribunal and their
          qualifications.-(1) Subject to sub-section (2) and (3), the
          State Government may appoint a chairman and as many
          members to the Tribunal as it may consider necessary.

H         (1-a) The State Government may, in consultation with the
M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY             181
   ENGINEERS & CONT [ASOK KUMAR GANGULY, J.]

  Chairman, designate one of the Judicial Members as the            A
  Vice-Chairman who in the event of occurrenc.e of any
  vacancy in the office of the Chairman by reason of his
  death, resignation, leave or otherwise, shall during such
  vacancy, discharge the functions of the Chairman.
                                                                    B
        (2) No person shall be appointed as Chairman of the
  Tribunal, unless he is or has been a Judge of a High Court.

      (3) No person shall be qualified for appointment as
  a member of the Tribunal, unless-
                                                                    c
  {i) he is or has been a District Judge of not less than seven
  years standing: or

  {ii) he is or has been. a Revenue Commissioner or has
  held a post equivalent to the rank of Revenue
                                                                    0
  Cbmmissioner for a total period of not less than five years,
  or

  {iii)he is or has been:-

                {a) Chief Engineer in the service of the State      E
                Government in Public Works, Irrigation or
                Public Health Engineering Department; or

                {b) a Chief Engineer in the service of the
                Madhya Pradesh Electricity Board; or
                                                                    F
                {c) a Senior Deputy Accountant General of
                the Office of the Accountant General, Madhya
                Pradesh,

  for a period of not less than five years.
                                                                    G
        Provided that in the case of clause {iii), in exceptional
  circumstances, the State Government may, relax the
  prescribed minimum period of five years to three years."

  27. The term of office and salaries and allowances are            H
    182      SUPREME COURT REPORTS                 [2012] 2 S.C.R.


A also statutorily provided under Sections 5 and 6 of the M:P. Act.
  Section 8 provides for the procedure to be followed by the
  tribunal on receipt of reference and Section 9 provides for the
  Constitution of Benches and Chairman's power of distribution
  of business. Under Section 16(2) of the M.P. Act there is a time
B limit for giving the Award which is absent in A.C. Act 1996.
  Section 17-A of the M.P. Act confers inherent power on the
  Arbitral tribunal to make orders as may be necessary for the
  ends of justice or to prevent abuse of the process of the tribunal.
  Section 17-B also provides for power conferred on the tribunal
c for correction of clerical or arithmetical mistakes. No such
  power is given to an arbitral tribunal under A.C. Act 1996.
  Section 19 of the M.P. Act gives High Court the suo motu
  power of revision: The High Court has also been given the
  power of revision to be exercised on an application made by
  an aggrieved party within three months of the award, While
0
  doing so, the High Court is to act like a revisional court under
  Section 115 of the CPC.

    ' 28. It is clear from the aforesaid enumeration of the
  statutory provision that under the M.P. Act the parties' autonomy
E in the choice of arbitral tribunal is not there.

         29. In State of Madhya Pradesh and another vs.
    Anshuman Shukla - (2008) 7 SCC 487, this Court while
    referring to the M.P. Act and dealing with the nature of the
F arbitral tribunal constituted under the said Act held that the said
  . Act is a special Act and provides for compulsory arbitration. It
    provides for a reference and the tribunal has been given the
    power of rejecting the reference at the threshold. It also held
    that the M.P. Act provides for a special limitation and fixes a
G time limit for passing an award. It has also been held that
    Section 14 of the M.P. Act provides that the award can be
    challenged under special circumstances and Section 17
    provides for finality of the award, notwithstanding anything to
    the contrary contained in any other law relating to arbitration.
    All these features of the Act were pointed by this Court in
H
 M.P. RURAL ROAD DEV. AUTHORITY v. LG CHAUDHARY                  183
    ENGINEERS & CONT. [ASOK KUMAR GANGULY, J.]

Anshuman Shukla (supra) to show that there is inconsistency              A
between the provisions of A.C. Act 1996 and those of the M.P.
Act. In para 28 of the judgment, this Court while referring to the
provisions of M.P. Act held:

     "The provisions of the Act referred to hereinbefore clearly         B
     postulate that the State of Madhya Pradesh has created
     a separate forum for the purpose of determination of
     disputes arising inter alia out of the works contract. The
     Tribunal is not one which can pe said to be a domestic
     tribunal. The Members of the Tribunal are not nominated
     by the parties. The disputants do not have any control over         C
     their appointment. The Tribunal may reject a reference at
     the threshold. It has the power to summon records. It has
     the power to record evidence. Its functions are not limited
     to one Bench. The Chairman of the Tribunal can refer the
     disputes to another Bench. Its decision is final. It can award      D
     costs. It can award interests. The finality of the decision is
     fortified by a legal fiction created by making an award a
     decree of a civil court. It is executable as a decree of a
     civil court. The award of the Arbitral Tribunal is not subject
     to the provisions of the Arbitration Act, 1940 and the              E
     Arbitration and Conciliation Act, 1996. The provisions of
     the said Acts have no application."

                                (para 28, page 497 of the report)

     30. It is clear, therefore, that in view of the aforesaid finding   F
of a co-ordinate Bench of this Court on the distinct feature of
an arbitral tribunal under the said M.P. Act the provisions of
M.P. Act are saved under Section 2(4) of A.C. Act 1996. This
Court while rendering the decision in Va Tech (supra) has not
either noticed the previous decision of~ co-ordinate Bench of            G
this Court in Anshuman Shukla (supra) or the provisions of
Section 2(4) of A.C. Act 1996. Therefore, we are constrained
to hold that the decision of this Court in Va Tech (supra) was
rendered per incuriam.
                                                                         H
    184        SUPREME COURT REPORTS                   [2012] 2 S.C.R.

A       31. This was the only point argued before us by the learned
    counsel for the appellant.

      32. The principle of per incuriam has been very succinctly
  formulated by the Court of Appeal in Young vs. Bristol
B Aeroplane Company, Limited reported in 1944 (1) K.B. 718.

         33. Lord Greene, Master of Rolls formulated the principles
    on the basis of which a decision can be said to have been
    rendered 'per incuriam'. The principles are:

c         "Where the court has construed a statute or a rule having
          the force of a statute its decision stands on the same
          footing as any other decision on a question of law, but
          where the court is satisfied that an earlier decision was
          given in ignorance of the terms of a statute or a rule having
D         the force of a statute the position is very different. It cannot,
          in our opinion, be right to say that in such a case the court
          is entitled to disregard the statutory provision and is bound
          to follow a decision of its own given when that provision
          was not present to its mind. Cases of this description are
          examples of decisions given per incuriam."
E
                                                             (Page 729)

      34. The decision in Young (supra) was subsequently
  approved by the House of Lords in Young vs. Bristol Aeroplane
F Company, Limited reported in 1946 Appeal Cases 163 at page
  169 of the report.

       35. Lord Viscount Simon in the House of Lords expressed
  His Lordship's agreement with the views expressed by the Lord
  Greene, the Master of Rolls in the Court of Appeal on the
G principle of per incuriam (see the speech of Lord Viscount
  Simon at page 169 of the report).

     36. Those principles have been followed by the
  Constitution Bench of this Court in The Bengal Immunity
H Company Limite.d vs. The State of Bihar and others reported
 M.P. RURAL ROAD DEV. AUTHORITY v. L.G. CHAUDHARY             185
    ENGINEERS & CONT [ASOK KUMAR GANGULY, J.]
in 1955 (2) SCR 603 [See the discussion in pages 622 and              A
623 of the report].

     37. The same principle has been reiterated by Lord
Evershed, Master of Rolls, in Morelle Ld. vs. Wakeling &
another [(1955) 2 QB 379 at page 406]. The principle has been         B
stated as followed:

     " ... As a general rule the only cases in which decisions
     should be held to have been given per incuriam are those
     of decisions given in ignorance or forgetfulness of some
     inconsistent statutory provision or of some authority binding    C
     on the court concerned; so that in such cases some part
     of the decision or some step in the reasoning on which it
     is based is found, on that account, to be demonstrably
     wrong ....... "
                                                                      D
                                                      (page 406)

     38. In the case of State of U.P. and another vs. Synthetics
and Chemicals Ltd. and another reported in (1991) 4 sec
139, this Court held the doctrine of 'per incuriam' in practice
means 'per ignoratium' and noted that English Courts have             E
developed this principle in relaxation of the rule of stare decisis
and referred to the decision in the case of Bristol Aeroplane
Co. Ltd. (supra). The learned Judges also made it clear that
the same principle has been approved and adopted by this
Court while interpreting Article 141 of the Constitution (see para    F
41).

     39. In the case of Municipal Corporation of Delhi vs.
Gurnam Kaur reported in (1989) 1 SCC 101, a three-Judge
Bench of this Court explained this principle of.per incuriam very     G
elaborately in paragraph 11 at page 110 of the report and in
explaining the principle of per incuriam the learned Judges
held:

     " ...... A decision should be treated as given per incuriam
                                                                      H
    186        SUPREME COURT REPORTS                  (2012] 2 S.C.R.


A         when it is given in ignorance of the terms of a statute or of
          a rule having the force of a statute ....... "

         40. In paragraph 12 the learned Judges observed as
    follows:
B         " ...... One of the chief reasons for the doctrine of precedent
          is that a matter that has once been fully argued and
          decided should not be allowed to be reopened. The weight
          accorded to dicta varies with the type of dictum. Mere
          casual expressions carry no weight at all. Not every
c         passing expression of a judge, however eminent, can be
          treated as an ex cathedra statement, having the weight of
          authority."

        41. Following the aforesaid principles, this Court is
0   constrained to hold that the decision in Va Tech (supra), having
    been rendered in per incuriam, cannot be accepted as a
    precedent to decide the controversy in this case.

        42. In reply the learned counsel for the respondent only
  submitted that the M.P. Act is repugnant to A.C. Act 1996 since
E the same is a later Act made by Parliament. The learned
  counsel referred to the provisions of Article 254 of the
  Constitution. The learned counsel also urged that in view of the
  provision of Section 85 of A.C. Act 1996, the M.P. Act stands
  impliedly repealed.
F
       43. The said argument cannot be accepted. The provision
  for repeal under Section 85 of A.C. Act 1996 does not show
  that there is any express repeal of the M.P. Act. Apart from that
  the provision of Section 2(4) of A.C. Act clearly militates against
G the aforesaid submissions.

        44. The argument of repugnancy is also not tenable. Entry
    13 of the Concurrent List in the Vllth Schedule of the
    Constitution runs as follows:

H         "13. Civil procedure, including all matters included in the
 M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY                   18 7
    ENGINEERS & CONT. [ASOK KUMAR GANGULY, J]
    Code of Civil Procedure at the commencement of this                    A
    Constitution, limitation and arbitration."

     45. In view of the aforesaid Entry, the State Government
is competent to enact laws in relation to arbitration. The M.P.
Act of 1983 was made when the previous Arbitration Act of                  B
1940 was in the field. That Act of 1940 was a Central Law. Both
the Acts operated in view of Section 46 of 1940 Act.

     46. The M.P. Act 1983 was reserved for the assent of the
President and admittedly received the same on 17.10.1983
which was published in the Madhya Pradesh Gazette                          C
Extraordinary dated 12.10.1983. Therefore, the requirement of
Article 254(2) of the Constitution was satisfied. Thus, M.P. Act
of 1983 prevails in the State of Madhya Pradesh. Thereafter,
A.C. Act 1996 was enacted by Parliament repealing the earlier
laws of arbitration of 1940. It has also been noted that A.C. Act          D
1996 saves the provisions of M.P. Act 1983 under sub-sections
2(4) and 2(5) thereof. Therefore, there cannot be any
repugnaAcy. (See the judgment of this Court in T. Barai vs.
Henry Ah Hoe and another reported in AIR 1983 SC 150). In
this connection the observations made by the Constitution                  E
Bench of this Court in the case of M. Karunanidhi vs. Union
of India and another reported in (1979) 3 sec 431 are very
pertinent and the following observations are excerpted:

    " ...... ltis, therefore, clear that in view of this clear intention   F
    of the legislature there can be no room for any argument
    that the State Act was in any way repugnant to the Central
    Acts. We have already pointed out from the decisions of
    the Federal Court and this Court that one of the important
    tests to find out as to whether or not there is repugnancy
    is to ascertain the intention of the legislature regarding the         G
    fact that the dominant legislature allowed the subordinate
    legislature to operate in the same field pari passu the
    State Act."

                                               (para 37, page 450)         H
    188       SUPREME COURT REPORTS                 [2012) 2 S.C.R.


A      47. It is clear from the aforesaid observation that in instant
  case the latter Act made by the Parliament i.e. A.C. Act 1996
  clearly showed an intention to the effect that the State Law of ·
  Arbitration i.e. the M.P. Act should operate in the State of
  Madhya Pradesh in respect of certain specified types of
B arbitrations which are under the M.P. Act 1983. This is clear
  from Sections 2(4) and 2(5) of A.C. Act 1996. Therefore, th.ere
  is no substance in the argument of repugnancy and is
  accordingly rejected.

       48. Therefore, appeal is allowed and the judgment of the
C High Court which is based on the reasoning of Va Tech (supra)
  is set aside. This Court holds the decision in Va Tech (supra)
  has been rendered in per incuriam. In that view of the matter
  the arbitration proceeding may proceed under M.P. Act of 1983
  and not under A.C. Act 1996.
D
          49. There will be no order as to costs.

          GYAN SUDHA MISRA, J. 1. Leave granted.

       2. While concurring and endorsing the reasonings
E assigned in the judgement of learned Justice Ganguly, I propose
  to add and thus partly dissent on certain aspects involved in
  the instant appeal which would have a bearing on the relief
  granted to the respondent by the High Court which appointed
  an arbitrator under the Arbitration and Conciliation Act, 1996
F for adjudication of the dispute in regard to cancellation of the
  works contract between the contesting parties therein.

       3. In this context, Section 7 of the Madhya Pradesh
  Madhyasthan Adhikaran Adhiniyam, 1983 (hereinafter referred
G to as the 'M.P. Arbitration Tribunal Act, 1983') needs to be
  reiterated which itself lays down as follows:

          "Reference to Tribunal" - (1) either party to a works contract
          s~all irrespective of the fact whether the agreement
          contains an arbitration clause or not, refer in writing the
H         dispute to the Tribunal."
 M.P RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY                189
     ENGINEERS & CONT. [GYAN SUDHA MISRA, J.]

      4. On perusal of the aforesaid provision enumerated under       A
Section 7, it is explicitly clear that the matter in the event of
existence of a dispute between the parties in certain
categories of cases where the State of Madhya Pradesh is a
contracting party, the dispute shall be referred in writing to the
tribunal irrespective of the fact whether the agreement contains      B
an arbitration clause or not. From this provision it is clearly
apparent that reference of any dispute to the tribunal postulates
an existence of a works contract and the definition of 'works
contract' under Section 2 (i) of the M.P. Arbitration Tribunal Act,
1983, it has clearly .and unequivocally been specified as to what     c
is a 'works contract' in relation to which the dispute is required
to be referred in writing to the tribunal. We may therefore
meticulously recollect the definition of 'works contract' which
lays down as follows:-

     "works contract" means an agreement in writing for the           D
     execution of any work relating to construction, repair or
     maintenance of any building or superstructure, dam, weir,
     canal, reservoir, tank, lake, road, well, bridge, culvert,
     factory workshop, powerhouse, transformers or such other
     works of the State Government or Public Undertaking as           E
     the State Government may, by notification, specify in this
     behalf at any of its stages, entered into by the State
     Government or by an official of the State Government or
     Public Undertaking or its official for and on behalf of such
     Public Undertaking and includes an agreement for the             F
     supply of goods or material and all other matters relating
     to the execution of any of the said works."

      5. Thus on a perusal of the definition of 'works contract',
it is manifestly clear that while the 'works contract' means an
                                                                      G
agreement pertaining to matters relating to the execution of any
of the work enumerated in the definition of 'works contract', the
same does not include the dispute pertaining to termination,
cancellation or repudiation of works contract and the entire
nature of transaction laid down therein relates to disputes
which arise out of execution of the nature of work specified in       H
    190       SUPREME COURT REPORTS                   [2012] 2 S.C.R.


A   the 'works contract'. However, the question whether the 'works
    contract' has been legally repudiated and rightly cancelled or
    not is the question or dispute pertaining to termin<!'tion of works
    contract has not been incorporated even remotely within the
    definition of 'works contract'. In view of this, the legal and logical
B   consequence which can be reasonably drawn from the
    definition of 'works contract' would be, that if there is a dispute
    between the contracting parties for any reason relating to works
    contract which include execution of any work, relating to
    construction, repair or maintenance of any building or super-
C   structure, dam, weir, canal, reservoir, tank, lake, road, well,
    bridge, culvert, factory, workshop, power house, transformers
    or such other works of the State Government or Public
    Undertaking including an agreement for the supply of goods or
    material and all other matters relating to the execution of any
D   of the said works, the same would fall within the ambit of the
    definition of 'works contract' and hence all disputes pertaining
    or arising out of execution of the works contract will have to be
    referred to the M.P. State Arbitration Tribunal as envisaged
    under Section 7 of the Act of 1983. Hence, in addition to the
E   reasons assigned in the judgment and order of learned Brother
    Justice Ganguly, disputes arising out of execution of works
    contract has to be referred to the M.P. State Arbitration Tribunal
    and not under the Arbitration and Conciliation Act, 1996.

       6. But in so far as the instant matter is concerned, the facts
F disclose that the appellant M.P. Rural Road Development
  Authority cancelled the works contract itself which was executed
  in favour of the respondent. In that event. the works contract
  between the parties was not in existence at all which would
  operate as a statutory mandate for reference of the dispute to
G the M.P. State Arbitration Tribunal.

       7. It is no doubt true that if the matter were before an
  Arbitrator appointed under the Arbitration and Conciliation Act,
  1996 for adjudication of any dispute including the question
H regarding the justification and legality as to whether the
 M.P RURAL ROAD DEV AUTHORITY v. L.G CHAUDHARY                191
     ENGINEERS & CONT [GYAN SUDHA MISRA, J)

cancellation of works contract was legal or illegal, then the said   A
Arbitrator in view of the ratio of the judgment of the Supreme
Court in Maharshi Dayanand University & Anr. Vs. Anand Co-
op L(C) Society, 2007 (5) sec 295, as also in view of the
persuasive reasoning assigned in the judgment and order
reported in Heyman & Anr. Vs. Darwins, Limited, 1942 (1) All         B
E.R. 337 would have had the jurisdiction to adjudicate the
dispute regarding the justification and legality of cancellation
of works contract also. But the same cannot be allowed to be
raised under the M.P. Act of 1983 since the definition of 'works
contract' unambiguously lays down in explicit terms as to what       c
is the nature and scope of 'works contract' and further
enumerates the· specific nature of disputes arising out of the
execution of works contract which would come within the
definition of a 'works contract'.

     8. However, the same does not even vaguely include the          D
issue or dispute arising out of cancellation and termination of
contract due to which this question, in my considered opinion,
would not fall within the jurisdiction of M.P. State Arbitration
Tribunal so as to be referred for adjudication arising out of its
termination. As already stated, fall out certainly would be          E
otherwise if the matter were to be adjudicated by an Arbitrator
appointed under the Arbitration and Conciliation Act, 1996 and
that would be in view of the ratio of the decisions of the
Supreme Court referred to hereinbefore which has held it
permissible for the Arbitrator to adjudicate even the dispute        F
arising out of cancellation or termination of an agreement or
contract. This however, cannot be allowed to broaden or expand
the ambit and scope of the M.P. Act of 1983 where the State
Legislature has passed a specific legislation in respect of
certain specified types of arbitration determining as to what are    G
the 'nature of disputes to be referred to the M.P. State
Arbitration Tribunal and that specifically permits the reference
of dispute arising out of execution of contract but clearly leaves
out any dispute arising out of termination, cancellation or
repudiation of 'works contract'. In order to clarify the point       H
    192       SUPREME COURT REPORTS                 (2012) 2 S.C.R.


A further, what needs to be emphasized is that if the nature of
  dispute referred to the Arbitrator like the instant matter, related
  to a dispute pertaining to construction, repair, maintenance of
  any building super-structure, dam or for the reasons stated
  within the definition of 'works contract', the matter may be
B referred to the M.P. Tribunal in view of the fact that if there is a
  dispute in relation to execution of a works contract, then
  irrespective of the fact whether the agreement contains an
  arbitration clause or not, the dispute is required to be referred
  to the M.P. State Arbitration Tribunal for adjudication. But when
C the contract itself has been terminated, cancelled or repudiated
  as it has happened in the instant case, then the nature of dispute
  does not fall within the definition of 'works contract' for the sole
  reason that it does not include any dispute pertaining to
  cancellation of a works contract implying that when the works
  contract itself is not in existence by virtue of ifs cancellation, the
0
  dispute cannot be referred to the M.P. State Arbitration Tribunal
  but may have to be decided by an Arbitrator appointed under
  the Arbitration and Conciliation Act, 1996.

       9. Hence, the nature of the dispute which falls within the
E definition of 'works contract' under Section 2(i) of the M.P. Act,
  1983 and one of the contracting parties to the agreement is
  the State of M.P., then irrespective of an arbitration agreement
  the dispute will have to be referred to the Tribunal in terms of
  Section 7 of the Act of 1983. But if the works contract itself has
F been repudiated and hence not in existence at all by virtue of
  its cancellation/termination, then in my considered view, the
  dispute will have to be referred to an independent arbitrator to
  be appointed under the Arbitration and Conciliation Act, 1996
  since the M.P. Act 1983 envisages reference of a dispute to
G the State Tribunal only in respect of certain specified types of
  arbitration enumerated under Section 2 (i) of the M.P. Act,
  1983.                                                   r



         10. As a consequence and fall out of the aforesaid
    discussion, the impugned order of the High Court by which the
H
  M.P. RURAL ROAD DEV. AUTHORITY v. L.G CHAUDHARY               193
       ENGINEERS & CONT. [GYAN SUDHA MISRA, J.]
  dispute relating to termination of works contract by the M.P.         A
  Rural Road Development Authority itself was referred to an
  independent arbitrator appointed by the High Court under the
  Arbitration and Conciliation Act, 1996 needs to be sustained
  and there is no need for a de nova reference of the dispute to
  the M.P. State Arbitration Tribunal. In the alternative, the          B
· consequence would have been otherwise and the matter could
  have been referred to the State Arbitration Tribunal if the dispute
  between the parties related to any dispute emerging out of
  execution of works contract which could fall within the definition
  of 'works contract' given out within the definition of 'works         c
  contract' under Section 2(i) of the M.P. Act of 1983. In order to
  avoid any ambiguity, it is reiterated that in view of cancellation
  of the works contract itself which is the position in the instant
  case, the proceedings before the Arbitrator appointed by the
  High Court cannot be treated as non-est so as to refer the same       0
  once again to the tribunal for adjudication as the dispute does
  not emerge or pertain to execution of works contract but relates
  to non-existence of works contract by virtue of its cancellation.

     11. Thus the sum and substance of what I wish to
emphasize is that the question as to whether the dispute would          E
be referred to the M.P. Tribunal in terms of Section 7 of the M.P.
Act of 1983 or to an independent arbitrator under the Arbitration
and Conciliation Act, 1996 will depend upon the factum whether
the works contract is existing between the parties or not out of
which the dispute has arisen. In case, the works contract itself        F
has been repudiated/cancelled, then, in view of its non-
existence, Section 7 of the M.P. Act pertaining to reference of
dispute to tribunal would not come into play at all by virtue of
the fact that the dispute relating to execution of works contract
alone can be referred to the tribunal in view of the specific           G
nature of works contract enumerated within the definition of
works contract under the Act of 1983. However, when the works
contract itself becomes non-existent as a consequence of its
cancellation, the matter will have to be referred to an
independent arbitrator under the Arbitration and Conciliation           H
    194      SUPREME COURT REPORTS                 [2012] 2 S.C.R.


A Act, 1996 and not to M.P. State Arbitration Tribunal.

       12. Thus, while holding that the M.P. Act 1983 should
  operate in the State of M.P. in respect of certain specified types
  of arbitration, the appointment of an independent arbitrator by
B the High Court under the Arbitration and Conciliation Act, 1996
  needs to be sustained since the works contract itself is not in
  existence by virtue of its cancellation and hence this part of the
  dispute could not have been referred to the M.P. State Tribunal.

      13. Consequently, the instant appeal stands partly allowed.
C There will be no order as to costs.

                               ORDER

       In view of some divergence of views expressed in the two
  judgments delivered today by us, the matter may be placed
D before Hon'ble the Chief Justice of India for constituting a larger
  Bench to resolve the divergence.

   D.G.                            Matter referred to larger Bench.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.