Created byFuzzy Cloud

Supreme Court of India

MANOHAR LAL SHARMAversusTHE PRINCIPLE SECRETARY & ORS.

Citation
2014 INSC 677
Decided
24 September 2014
Disposal
Disposed off

Holding

All coal block allocations, except the Moher and Moher Amroli Extension blocks to Sasan Power Ltd., the Tasra block to SAIL, and the Pakri Barwadih block to NTPC, are to be cancelled with a six‑month deferment, and the remaining allottees must pay an additional levy of Rs.295 per metric ton.

Summary

The Supreme Court was hearing the consequence proceedings arising from its earlier judgment that the allocation of coal blocks by the Screening Committee and the Government dispensation route was arbitrary and illegal. The Union of India submitted affidavits showing that 40 blocks were already producing coal and six were ready for extraction, and sought guidance on whether these allocations should be cancelled. The Court examined whether the allottees were entitled to a hearing, whether a committee should be set up to review each case, and whether an additional levy of Rs.295 per metric ton was justified. It held that the process of allotment could not be reopened and that all allotments, except for three blocks allotted to Sasan Power Ltd., one to SAIL and one to NTPC, must be cancelled, with a six‑month deferment to allow adjustment. The Court also ordered the remaining allottees to pay the additional levy and affirmed that CBI investigations into 12 of the blocks would continue.

Issues considered

  • The legality and arbitrariness of coal block allocations made by the Screening Committee and Government dispensation route.
  • What consequences should follow the declaration of illegality – whether all allocations should be cancelled or some preserved.
  • Whether the principles of natural justice require a hearing to each allottee before cancellation.
  • Whether a committee should be appointed to examine individual allotments.
  • The propriety and quantum of an additional levy of Rs.295 per metric ton of coal extracted.

Legislation cited

Subjects

coal block allocationillegal allotmentnatural justiceadditional levycancellation of allotmentsSupreme CourtArticle 32mining leaseCAGCBI investigation

Judgment

                          [2014] 12 S.C.R. 110


 A                     MANOHAR LAL SHARMA
                                  . v.
                THE PRINCIPLE SECRETARY & ORS.
               (Writ Petition (Criminal) No. 120 of 2012)
                        SEPTEMBER 24, 2014
 B
            [R.M. LODHA, CJI, MADAN B. LOKUR AND
                     KURIAN JOSEPH, JJ.]

         Coal - Allotment of coal blocks - Cancellation of -
 C Allotment of coal blocks made by Screening Committee of
     the Government of India and Government Dispensation route
     held arbitrary and illegal - Consequences of such
     cancellation - Affidavit by Union of India to the effect that coal
     is actually mined from 40 coal blocks listed in Annexure I to
  D the affidavit and 6 coal blocks listed in Annexure II are ready
     for extraction - Issue whether the allotment of these coal
     blocks to be cancelled or not - Held: Process of allotment
     cannot be reopened collaterally through the appointment of
     a committee, as it would virtually amount to nullifying the
  E judgment - All the parties likely to be adversely affected were
     given a hearing, .thus, principle of natural justice was applied
     - The first category of allotments are o,ther than those
     mentioned in Annexure 1 and Annexure 2 which are illegal
     and arbitrary, the allottees have not yet entered into any
· F ·mining lease and they have not yet commenced production,
     thus, all these allotments are quashed - Second category
     being the 46 coal blocks mentioned in Annexure 1 and
     Annexure 2, though have commenced production or are on
     the verge of commencing production - These allocations are
  G illegal and arbitrary, thus, are liable to be cancelled -
     However, the allotment of coal blocks Moher and Moher
     Amroli Extension allocated to Sasan Power Ltd. (UMPP),
     Tasia (allotted to Steel Authority of India Ltd. (SAIL), and Pakri
     Barwadih coal block (allotted to National Thermal Power

H                                   110
       MANOHAR LAL SHARMA v. PRINCIPLE                       111
                 SECRETARY
Corporation (NTPC), not liable to be cancelled - The                A
cancellation would take effect from 31st March, 2015- Period
of six months is being given since the Central Government
and GIL would need some time to adjust to the changed
situation and move forward as a/so adequate time is given
 to the coal block allottees to adjust and manage their affairs     B
- Allottees of the coal blocks other than those covered by the
judgment and the four coal blocks covered by this order to
pay an amount of Rs. 2951- per metric ton of coal extracted
 as an additional levy within the stipulated period - Coal
 extracted hereafter ti/131 st March, 2015 would also attract the   c
 additional levy of Rs. 2951- per metric ton - Scrutiny by CBI
 in respect of allotment of 12 coal blocks out of 46 would
 continue.

     Samaj Parivartana Samudaya v. State of Kamataka I.A.
No.201 & 219, 223 in I.A. No.204 and I.A. Nos. 224 in I.A. D
No.215 in WP(C) No. 562/2009;; Ashok Hurrah v. Rupa
Ashok Hurrah 2002 (2 ) SCR 1006 : (2002) 4 SCC 388;
National Textile Workers' Union v. P. R. Ramakrishna 1983
(1) SCR 922 : (1983) 1 SCC 228; Sheela Barse v. Union of
India 1988 ( 2) Suppl. SCR 643: (1988) 4 SCC 226; Onkar E
Lal Bajaj v. Union of India 2002 (5) Suppl. SCR 605 :(200~)
2 SCC 673; Chingleput Bottlers v. Majestic Bottling
Company 1984 (3) SCR 190 : AIR 1984 SC 1030 - referred
to.

                      Case Law Reference:
                                                                    F

     2002 (2) SCR 1006             Referred to        Para 16
     1983 (1) SCR 922              Referred to        Para 18
     1988 (2) Suppl. SCR 643 Referred to              Para 20       G

     2002 (5) Suppl. SCR 605 Referred to              Para 21
     1984 (3) SCR 190              Referred to        Para 22

                                                                    H
    112       SUPREME COURT REPORTS                [2014] 12 S.C.R.


A        CRIMINAL ORIGINAL JURISDICTION : Writ Petition
    (Criminal) No. 120 of 2012.

          Under Article 32 of the Constitution of India.

                                  WITH
B
    W.P. (C) No. 463 and 515 of 2012

    W.P. (C) No. 283 of 2013

          Manohar Lal Sharma (Petitioner -in -person), Summan,
C   Prashant Bhushan, Pranav Sachdeva, Satyajit Desai, Akshaya
    M. Sudame, Anagha S. Desai, Jyoti Mendiratta for the
    petitioner.

         Mukul Rohatgi, AG., Ranjit Kumar, SG., Maninder Singh,
D   ASG., A. Saran, Anil B.' Divan, K.K. Venugopal, Ra11.ndra
    Srivastava, K.V. Viswanathan, Dr. Abhishek Manu Singhvi,
    Harish N. Salve, Dushyant Dave, Krishnan Venugopal, Paras
    Kuhad, Gopal Jain, Rakesh Dwivedi, Ajit Kumar Sinha, Vikas
    Singh, Dr. Rajeev Dhawan, T.R. Andhyarujina, Gopal Jian, Arijit
E   Prasad, Binu Tamta, Sushma Suri, D.S. Mahra, Amit Anand
    Tiwari, Sanchit Guru, Ashutosh Jha, Avinash Tripathi, Ramesh
    Babu M.R., Anip Sachthey, Mahi! Paul, Shagun Matta, Saakaar
    Sardana, Apoorv Kurup, Prashanto Sen, C.D. Singh, Rathi
    Rohit, V.C. Shukla, Sakshi Kakkar, Sanjeev K. Kapoor, Gauri
F   Rasgotra, Saman Ahsan, Prateek Kumar, Gaurav Juneja, Raja!
    Jariwal Raunak Dhilon, Sahil Narang, Karan Khanna, Shikhar
    Shrivstava (for Khaitan & Co.), Aditya Ganju (for Khaitan & Co.),
    Mahesh Agarwal, Rishi Agrawala, E.C. Agrawala, Neeha
    Nagpal, Parul Shukla, V. Shyam Mohan, Kuriakose Varghese,
G   Shrevas Mehrotra, Chaitali Dhinojia, D. Mahesh Babu, Nikhil
    Nayyar, Kirti Renu Mishra, Tapesh Kumar Singh, Mohd.
    Waquas, Aparna Bhat, Mamta Saxena, A.N. Singh, Tanima
    Kishore, Bhavanishankar V. Gadnis, Varun Pathak, Ravi
    Prakash, Raheel Kohli, Aditya Dewan, Ratan K. Singh, Suraj
H   Prakash, Shashi Bhushan, Akshay Malhotra, Tushar Roy, Rauf
        MANOHAR LAL SHARMA v. PRINCIPLE                      113
                 SECRETARY

  Rahim, Nandini Gore, Devina Sehgal, Trishala Kulkarni, Manik      A
  Karanjawala (For Karanjawala & Co.), Braj Kishore Mishra,
  Mishra Saurabh, Vanshaja Shukala, Ankit Kumar Lal, Kamini
  Jaiswal, S. Udaya Kumar Sagar, Hemantika Wahi, Jesal,
  Preeti Bhardwaj, Puja Singh, Anuradha Dutta, Fereshte D.
  Sethna, Vijayalakshmi Menon, Akriti, Tarinee Sudan, Varun         B
  Mishra, B.R. Menon, Pawan Upadhyaya, Sharmila Upadhyaya,
· E.R. Kumar, Shashank, Faisal Sherwani, Abhinay, Abhishek
  Deshmukh (For Parekh & Co.), Meenakshi Grover, Aishwarya
  Sinha, Kunal Verma, Aarohi Bhalla, Ashish Bermard, Sujata
  Kurdukar, Bharat Sangal, I. Abenla Aier, Pallavi Langar, Tushal   c
  Bakshi, Anitha Shenoy, Soumik Ghosal, Rana Mukherjee,
  Neha Sharma, D. Verma, B. Balaji, R. Rakesh Sharma, S.
  Anand, Shase, Lalit Bhasin, Nina Gupta, Sanjay Gupta, Mudit
  Sharma, Amit Sharma, Dipesh Sinha, Ashok Kr. Pariya,
  Anand Varma, Dhananjay Mishra, Ramendra Mohan Patnaik,            D
  L.K. Bhushan, Vaibhav Joshi (For Dua Associates) Dinesh
  Kumar Garg for the respondents.

      The Order of the Court was delivered

                           ORDER                                    E

      1. On 25th August, 2014 judgment was delivered in these .
 cases and it was held, inter alia, that the allotment of coal
 blocks made by the Screening Committee of the Government
 of India, as also the allotments made through the Government
                                                                F
 dispensation route are arbitrary and illegal. Since the
 conclusion arrived at would have potentially had far-reaching
 consequences, on which submissions were not made when the
 case was heard, the question of what should be the
 consequences of the declaration was left open for hearing.
                                                                    G
     2. The relevant paragraphs of the judgment dated 25th
 August, 2014 read as follows:-

      "155. The allocation of coal blocks through Government
                                                                    H
    114       SUPREME COURT REPORTS                  (2014) 12 S.C.R.


A         dispensation route, however laudable the object may be,
          also is illegal since it is impermissible as per the scheme
          of the CMN Act. No State Government or public sector
          undertakings of the State Governments are eligible for
          mining coal for commercial use. Since allocation of coal
B         is permissible only to those categories under Section 3(3)
          and (4), the joint venture arrangement with ineligible firms
          is also impermissible. Equally, there is also no question
          of any consortium/leader/association in allocation. Only an
          undertaking satisfying the eligibility criteria referred to in
          Section 3(3) of the CMN Act, viz., which has a unit
c
          engaged in the production of iron and steel and generation
          of power, washing of coal obtained from mine or
          production of cement, is entitled to the allocation in addition
          to Central Government, a Central Government company or
          a Central Government corporation.
D
          156. In this context, it is worthwhile to note that the 1957
          Act has been amended introducing Section 11-A w.e.f.
          13.02.2012. As per the said amendment, the grant of
          reconnaissance permit or prospecting licence or mining
E         lease in respect of an area containing coal or lignite can
          be made only through selection through auction by
          competitive bidding even among the eligible entities under
          Section 3(3)(a)(iii), referred to above. However,
          Government companies, Government corporations or
F         companies or corporations, which have been awarded
          power projects on the basis of competitive bids for tariff
          (including Ultra Mega Power Projects) have been
          exempted of allocation in favour of them is not meant to
          be through the competitive bidding process.
G         157. As we have already found that the allocations made,
          both under the Screening Committee route and the
          Government dispensation route, are arbitrary and illegal,
          what should be the consequences, is the issue which

H
         MANOHAR LAL SHARMA v. PRINCIPLE                                  115
                  SECRETARY
      remains to be tackled. We are of the view that, to this                     A
      limited extent, the matter requires further hearing."

     3. Accordingly, we heard several learned counsels
appearing for a very large number of interveners, impleadment
applicants and State Governments. Substantive submissions
                                                              8
were made, amongst others, by the Coal Producers,
Association, the Independent Power Producers Association of
India and the Sponge Iron Manufacturers Association. These
associations had also been heard on an earlier occasion well
before judgment was delivered on 25th August, 2014.
                                                                                  c
      4. For the purposes of these "consequence proceedings",
the Union of India filed an affidavit dated 8th September, 2014.
It is stated in the affidavit that coal is actually being mined from
40 coal blocks listed in Annexure I to the affidavit. This list
includes two coal blocks allotted to an Ultra Mega Power                          D
Projects (Sasan Power Ltd. [UMPP] allotted the coal blocks
Moher and Moher Amroli Extension). Coal blocks allotted to
UMPPs have not been disturbed in the judgment. The list of the
40 coal blocks is attached to this order as Annexure 1.
                                                                                  E
     5. In addition to the above 40 coal blocks, it is stated in
the affidavit that 6 more coal blocks are ready for extraction of
coal in 2014-15 and this list is Annexure II to the affidavit. These
6 coal blocks have obtained the Mine Opening Permission from
the Coal Controller's Organization under Rule 9 of the Colliery
Control Rules 2004 1 (framed under the Mines and Minerals
                                                                                  F
(Development and Regulation) Act, 1957). This permission is


1.      9. Requirement of prior permission to open a coal mine, seam or
     section of a seam.--
                                                                                  G
              ' of a colliery shall open a coal mine, seam or a section of a
     (1) No owner
     seam without the prior permission in writing of the Central Government.
     (2) No owner of a colliery shall also commence mining operations in a
     colliery or seam or a section of a seam, in which the mining operation has
     been discontinued for a period exceeding one hundred and eighty days,
     without the prior permission in writing of the Central Government.           H
      116      SUPREME COURT REPORTS                [2014) 12 S.C.R.


   A granted subsequent to the execution of a mining lease. The list
,,   of these 6 coal blocks is attached to this order as Annexure 2.

           6. Therefore, the affidavit is quite clear that 40 coal blocks
      are already producing coal and 6 coal blocks are in a position
      to produce coal virtually with immediate effect. The question is .
  8
      whether the allotment of these coal blocks should be cancelled
      or not.

         7. It was submitted by the learned Attorney General that
    after the declaration of law and the conclusion that the allotment
  C of coal blocks was arbitrary and illegal, only two consequences
    flow from the judgment. The first is the natural consequence,
    that is, the allotment of the coal blocks (other than those
    mentioned in the judgment) should be cancelled and the Central
    Government is fully prepared to take things forward. The second
  D option is that 46 coal blocks (as above) be left undisturbed
    (subject to conditions) and the allotment of the remaining coal
    blocks should be cancelled.                                    •

         8. Expounding on the alternative consequence, it was
  E submitted that Coal India Limited (CIL) a public sector
    undertaking can take over and continue the extraction of coal
    from these 44 coal blocks without adversely affecting the rights
    of those employed therein. However, it was submitted that CIL
    would require some time to take over the coal blocks and
  F manage its affairs for continuing the mining process. Effectively
    therefore, it was submitted that even if the allotment of these
    44 coal blocks is cancelled, the Central Government can
    ensure that coal production will not stop.

         9. Learned Attorney General submitted that all the allottees
  G of coal blocks should be directed to pay an additional levy of
    Rs. 295/- per metric ton of coal extracted from the date of
    extraction as per the Report of the Comptroller and Auditor
    General (CAG) dealing with the financial loss caused to the
    exchequer by the illegal and arbitrary allotments. It was further
  H submitted that in the case of allottees supplying coal to the
       MANOHAR LAL SHARMA v. PRINCIPLE                        117
                SECRETARY
power sector, they should be mandated to enter into Power             A
Purchase Agreements (PPAs) with the State utility or
distribution company (as the case may be) so that the benefit
is passed on to the consumers.

     10. By way of abundant precaution, the learned Attorney          B
General pointed out that in respect of the allotment of 6 coal
blocks, a First Information Report has been lodged by the
Central Bureau of Investigation (CBI). Therefore, investigations
are in progress to ascertain whether any criminal offence has
been committed in respect of the allotment of 6 coal blocks. In
addition, it is pointed out that the CBI has on 3rd September,        C
2014 informed that a final decision with regard to any alleged
criminality or otherwise in the allotment of 6 other coal blocks
is pending consideration. In other words, the alleged criminality
in the allotment of 12 out of the 46 coal blocks identified by the
learned Attorney General is under scrutiny by the CBI.                D

     11. To put the suggestions of the learned Attorney General
in perspective, they are summarized below:

      ( 1)    All coal block allotments (except those mentioned       E
             in the judgment) may be cancelled.

      (2)    Alternatively,

      (a)    Extraction of coal from the 40 functional and 6
             "ready" coal blocks may be permitted and the             F
             remai~ing coal blocks be cancelled;

      (b)    The allottees of all 46 coal blocks be directed to pay
             an additional levy of Rs.295/- per metric ton of coal
             extracted from the date of extraction; and
                                                                      G
      (c)    The allottees of coal blocks for the power sector be
             also directed to enter into PPAs with the State
             utility or distribution company as the case may be.

     12. Learned Attorney General made two supplementary              H
    118      SUPREME COURT REPORTS                [2014) 12 S.C.R.


A   submissions, not directly connected with the suggestions made.
    It was submitted that though all the allotments made by the
    Screening Committee and through the Government
    dispensation route were held illegal and arbitrary, the allotment
    of lignite blocks was not the subject matter of discussion in the
s   judgment delivered on 25th August, 2014. This is correct and
    it is made clear that the judgment delivered on 25th August,
    2014 does not concern lignite blocks at all and their allotments
    are not covered by the said judgment.

C      13. Secondly, the figure of Rs. 295/- per metric ton of coal
  extracted as additional levy (based on the Report of the
  Comptroller and Auditor General) has been calculated on the
  basis of open cast mines and mixed mines, while underground
  mines were not taken into.calculation. Of the coal blocks sought
  to be "saved" from cancellation, it has not been pointed out by
D any learned counsel whether any one of the 46 coal blocks
  contains an underground mine or not. Therefore, there is no
  occasion to deal with a hypothetical case.

       14. In response to the submissions of the learned Attorney
E General, Mr. K.K. Venugopal, Senior Advocate, appearing on
  behalf of the Coal Producers Association submitted that
  cancellation of all the coal blocks would have very serious and
  far reaching consequences.

      15. The consequences of cancellation of the coal blocks
F were categorized by Mr. Venugopal under various heads and
  these are detailed below.

       (1) There would be a serious adverse impact on the
  economy of the country: It was submitted that Government
G companies are not in a position to supply the required quantity
  of coal; in fact, a large number of applications are pending with
  the Ministry of Coal for Jong term coal linkages; power stations
  have a supply of less than one week of coal and therefore there
  are possibilities of power outages; as many as 10 power plants
H of the National Thermal Power Corporation (NTPC) and the
       MANOHAR LAL SHARMA v. PRINCIPLE                        119
                SECRETARY
Damodar Valley Corporation (DVC) have been shut down                 A
because of shortage of. coal supply by Coal India ltd. (CIL);
there is an issue of poor quality of coal supplied by CIL; huge
investments up to about Rs. 2.87 lakh crores have been made
in 157 coal blocks as on December, 2012; investments in end-
use plants have been made to the extent of about Rs. 4 lakh          B
crores; the employment of almost 10 lakh people is at stake;
end-use plants have been designed keeping in mind the
specification of coal in the allocated coal block and cancellation
of the coal blocks would result in the end-use plant becoming
redundant; loans to the extent of about Rs. 2.5 lakh crores given    c
by banks and financial institutions would become non-
performing assets; the State Bank of India may suffer a loss of
up to Rs. 78,263 crores which is almost 7.9% of its net worth
for the financial year 2013; other Public Sector Banks such as
the Punjab National Bank and the Union Bank will receive a
                                                                     0
massive set back; Public Sector Corporations like Rural
Electricity Corporation and Power Finance Corporation have
an even higher exposure than banks; there will be global
ramifications of the de-allotments such as a negative impact
on investor confidence; acute distress in some industries; the       E
country's dependence on coal as a primary fuel source with up
to 60% for power generation may result in inflationary trends;
28,000 MW of power capac[ty will be affected due to de-
allocation; closure of coal mines would result in an estimated
loss of Rs. 4.4 lakh crores in terms of loss of royalty, cess,
direct and indirect taxes; coal imports (already very high) will     F
go up even more in FY 2016-17 to the extent of Rs.1.44 lakh
crores (without de-allocation); and on the other hand, the
production of coal would substantially increase in case all coal
blocks are made operational after the grant of necessary
permission.                                                          G

     (2) The cancellation of coal blocks would set back the
process (of extraction and effective utilization of coal) by about
7 to 8 years: It was submitted that the auction of coal blocks
would take at least 1-2 years and from past experience, it is        H
    120       SUPREME COURT REPORTS                 [2014] 12 S.C.R.


A   unlikely that the auction would be successful due to lack of bids
    or proper participation; it would take. at least 5-6 years for
    making the auctioned coal blocks operational; in any event
    (based on the time lines given by the Ministry of Coal in the
    allocation letters) it would take 36-42 months to develop an
s   open cast mine and about 48-54 months to develop an
    underground mine; and the commissioning of end-use plants
    after obtaining various clearances would take a minimum of 3-
    4 years.

          (3) If the coal blocks are not cancelled, the allottees could
C continue their contribution towards corporate social
  responsibility and socio-economic development of the country:
  It was submitted on a positive note that the allottees have
  invested in basic infrastructure like road, rail links etc. since the
  coal blocks allotted to them were in areas where CIL was not
D interested in making an investment; the allottees have made
  huge investments in setting up other infrastructure such as
  schools, hospitals, facilities for clean and potable water,
  residential colonies, community centers, playground etc. and in
  creation of job opportunities; thousands of crores of rupees have
E already been paid by the coal block allottees by way of direct
  and indirect taxes 3nd in the form of royalty, cess etc.; and if
  the coal blocks are cancelled, the development activities
  initiated by the allottees would come to a standstill.

F       (4) Many of the allottees have problems peculiar to them
  which need to be examined along with ground realities: It was
  submitted that the delay in development of coal blocks is not
  attributable to the allottees who are actually·victims of the faults
  of the Screening Committee; delays are attributable to various
G reasons such as administrative delays on the part of the
  Ministry of Environment and Forest and Ministry of Coal, the
  consent by the Pollution Control Boards was not given on time,
  Court orders, Naxalite issues in some areas, State
  Governments directing that mining lease should not be
  executed, introduction of go/no go' areas or without statutory
H
         MANOHAR LAL SHARMA v. PRINCIPLE                                   121
                  SECRETARY
permission etc.; this Court has tacitly acknowledged                               A
administrative delays in grant of clearances in an order passed
on 1st September, 2014 in Samaj Parivartana Samudaya v.
State of Karnataka 2 ; the appropriate course of action to adopt
would be for this Court to appoint a Committee to examine the
peculiar facts of each individual allotment.                                       B

      (5) The additional levy of Rs. 295/- per metric ton of coal
extracted (described as a penalty) is unjustified: The figure of
loss of revenue to the exchequer to the extent of Rs. 295/- per
metric ton of coal extracted is borrowed from the Report of the                    C
CAG which Report is contested by the Government of India and
is pending consideration before a Parliamentary Committee on
Public Undertakings; the Report itself suggested that only a part
of the financial gain could have accrued to the national
exchequer; the Government of India has not applied its mind
while suggesting the figure of Rs. 295/- per metric ton and it                     D
has only considered the average price of coal as given by CIL
for the year 2010-11 (being Rs.1028/- per metric ton) and that
cannot be adopted for earlier financial years; the coal extracted
from the blocks allotted are of an inferior quality and the sale
price thereof is much lower than the average sale price of CIL;                    E
the CAG has not taken into consideration underground mines
while calculating the alleged financial loss; the cost of
production of coal for CIL is less since CIL has economically
viable mines as compared to the mines allocated to the private
sector which lack infrastructure and have several other                            F
problems; and penalty cannot be imposed with retrospective
effect since the coal extracted by the allottees has already been
utilized for production of power, steel, cement etc.

     16. Finally, Mr. Venugopal relied on Ashok Hurrah v.                          G
Rupa Ashok3 Hurrah 3 to contend that the allottees are entitled
to a hearing before the cancellation of their coal blocks in
2.     I.A. No.201 & 219, 223 in I.A. No.204 and I.A. Nos. 224 in I.A. No.215 in
     WP(C) No. 562/2009 .
3.      (2002) 4   sec 388.                                                        H
    122        SUPREME COURT REPORTS                 [2014) 12 S.C.R.


A   accordance with the well accepted principles of natural justice
    since the cancellation adversely affects their interests.
    Paragraph 51 of the Report was relied on and this reads as
    follows:

          "Nevertheless, we think that a petitioner is entitled to relief
B
          ex debito justitiae if he establishes ( 1) violation of the
          principles of natural justice in that he was not a party to
          the lis but the .judgment adversely affected his interests' or,
          if he was a party to the lis, he was not served with notice
          of the proceedings and the matter proceeded as if he had
c         notice, and (2) where in the proceedings a learned Judge
          failed to disclose his connection with the subject-matter or
          the parties giving scope for an apprehension of bias and
          the judgment adversely affects the petitioner."

D      17. Mr. Harish Salve, Senior Advocate, appearing for the
  Sponge Iron Manufacturers Association generally supported
  the submissions.made by Mr. Venugopal. He emphasized that
  the more appropriate course for this Court to adopt would be
  to appoint a Committee of three persons, including experts, to
E examine each individual allotment and consider the facts
  peculiar to each allottee and report to this Court whether the
  coal block allotment should be cancelled or not.

          18. Learned counsel also emphasized the necessity of
F   granting a hearing to each allottee and referred to a passage
    from National Textile Workers' Union v. P. R.
    Ramakrishna" wherein the Constitution Bench emphasized
    the importance of natural justice in paragraph 16 of the Report.
    Particular emphasis was laid on the following passage:

G         " .... It will surely be a travesty of justice to deny natural
          justice on the ground that courts know better. There is a
          peculiar and surprising misconception of natural justice, in
          some quarters, that it is, exclusively, a principle of

H   4.    (1983) 1 sec 228.
          MANOHAR LAL SHARMA v. PRINCIPLE                          123
                    SECRETARY
        administrative law. It is not. It is first a universal principle   A
        and, therefore, a rule of administrative law. It is that part
        of the judicial procedure which is imported into the
        administrative process because of its universality. "It is of
        the essence of most systell)s of justice - certainly of the
        Anglo-Saxon System - that in litigation both sides of a            B
        dispute musts be heard before decision. 'Audi Alteram
        Partem' was the aphorism of St. Augustine which was
      . adopted by the courts at a time when Latin Maxims were
        fashionable". "Audi Alteram Partem is as much a principle
        of African, as it is of English legal procedure : a popular        c
        Yoruba saying is " 'wicked and iniquitous is he who
        decides a case upon the testimony of only one party to it"
        (T.O. Elias : The Nature of African Customary Law). Courts
                                                                               ·,
        even more than administrators must observe natural
        justice."                                                          D
      19. Mr. Salve also referred to a passage from
Administrative Law5 to contend that the principle of legal
relativity should be borne in mind by the Court so that "the law
can be made to operate justly and reasonably in cases where
doctrine of ultra vires, rigidly applied, would produce                    E
unacceptable results."

    . 20. Unfortunately, it is difficult to see relevance of the
passage cited by learned counsel since it deals with the nullity
and voidness of an Act or order which is ultra vires. The                  F
applicable principles are completely different and we are not
dealing with such a case. It would be more apposite to refer to
a passage from Sheela Barse v. Union of lndia 6 cited by Dr.
A.M. Singhvi, Senior Advocate (appearing for the Independent
Power Producers Association of India) wherein this Court                   G
observed the future is important (and that is what we are
looking at). This Court said:


·s.      Administrative Law by Sir William Wade, 9th Edn.
6.       (1988) 4 sec 226.                                                 H
      124       SUPREME COURT REPORTS                [2014] 12 S.C.R.


 A          "Again, the relief to be granted looks to the future and is,
            generally, corrective rather than compensatory which,
            sometimes, it also is. The pattern of relief need not
            necessarily be derived logically from the rights asserted
            or found. More importantly, the court is not merely a
  B         passive, disinterested umpire or onlooker, but has a more
            dynamic and positive role with the responsibility for the
            organization of the proceedings, moulding of the relief and
            - this is important - also supervising the implementation
            thereof. The court is entitled to, and often does, seek the
. c         assistance of expert panels, Commissioners, Advisory
            Committee, amici etc. This wi:de range of the
            responsibilities necessarily implies correspondingly higher
            measure of control over the parties, the subject matter and
            the procedure. Indeed as the relief is positive and implies
            affirmative action the decisions are not "one-shot"
 D
            determinations but have ongoing implications. Remedy is
            both imposed, negotiated or quasi-negotiated."

           21. Dr. A.M. Singhvi also submitted a note which
      essentially and substantially reiterates some of the submissions
 E    made by Mr. Venugopal. It is not, therefore, necessary to repeat
      those submissions. He also referred to Onkar Lal Bajaj v.
      Union of lndia7 to submit that in the case of apparently tainted
      allotment of dealerships for petroleum products, this Court felt
      the necessity of appointing a Committee and therefore we
  F   should also appoint a Committee of retired judges to examine
      each individual case of coal block allotment.

         22. Dr. Rajeev Dhavan, Senior Advocate appearing for
    one of the interveners referred to Chingleput Bottlers v.
    Majestic Bottling Company" to emphasize the necessity of
  G applying the principles of natural justice before cancelling the
    allotments made in favour of the allottees.

      7.   (2003) 2 sec 673 .
  H   8.    AIR 1984 SC 1030.
        MANOHAR LAL SHARMA v. PRINCIPLE                        125
                  SECRETARY
     23. Other learned counsels more or less repeated ar:i,d           A
reiterated the submissions made, with slight variations and
emphasis depending upon the facts of the case of their
respective clients, including State Governments.

      24. In response to the submissions made by various               8
learned counsels, it was submitted by the learned Attorney
General that all the aspects mentioned above including the
economic implications or fall-out of the cancellation of coal block
allotments and the possible adverse impact that it may have
on other socio-economic factors have been taken into
consideration and it is only thereafter that the affidavit has been    C
filed by the Union of India, which has been explained by him in
his opening address. In other words, the Union of India is fully
prepared to face the consequences of the cancellation of all
coal blocks, if need be, and is desirous of moving forward.
                                                                       D
     25. The learned Attorney General vehemently opposed the
setting up of any committee as proposed by learned counsels.
He categorically and emphatically stated that the Central
Government has no difficulty in taking matters forward
consequent upon the cancellation of the coal blocks.                   E
      26. Learned counsels for the ·a11ottees have essentially
 raised two contentions. Firstly, the principles of natural justice
-require that they must be heard before their coal block
 allotments are cancelled. Secondly, we should appoint a
 committee to consider each individual case to determine
                                                                       F
 whether the coal block allotments should be cancelled or not.

      27. As far as the second contention is concerned, this is
strongly opposed by the learned Attorney General and we think
he is right in doing so. The judgment did not deal with any            G
individual case. It dealt only with the process of allotment of coal
blocks and found it to be illegal and arbitrary. The process of
_allotment cannot be reopened collaterally through the
appointment of a committee. This would virtually amount to
nullifying the judgment. The process is a continuous thread that       H
    126      SUPREME COURT REPORTS                [2014] 12 S.C.R.


A   runs through all the allotments. Since it was fatally flawed, the
    beneficiaries of the flawed process must suffer the
    consequences thereof and the appointment of a committee
    would really amount to permitting a body to examine the
    correctness of the judgment. This is clearly impermissible.
B
       28. It is true that this Court has taken the assistance of one
  committee or the other in several cases but that was where an
  inquiry was required to be conducted and this Court was
  obviously not in a position to conduct any such inquiry. This had
  happened, for example, in Onkar Lal Bajaj. No such occasion
C or situation has arisen in the present case to necessitate the
  appointment of a committee. Therefore, the question of
  appointing a committee simply does not arise.

       29. The first contention relates to the applicability of the
D principles of natural justice. As far as this is concerned, it has
  specifically been recorded in the judgment (in paragraph 11)
  to the following effect:

         "Three Associations, viz., Coal Producers Association,
         Sponge Iron Manufacturers Association and Independent
E
         Power Producers Association of l~dia have made
         applications for their intervention stating that these
         associations represented large number of allottees who
         have been allocated subject coal blocks. Accordingly, Mr.
         K.K. Venugopal, learned senior counsel was heard for
F        Coal Producers Association and Mr. Harish N. Salve,
         learned senior counsel was heard on behalf of the Sponge
         Iron Manufacturers Association and Independent Power
         Producers Association of India. They C'ommenced their
       · arguments on 09.01.2014, which continued on 15.01.2014
G        and concluded on 16.01.2014."

       30. Therefore, it is incorrect to say that these associations
  which represented the bulk (if not all) the allottees or
  beneficiaries of coal blocks were not heard.. They presented
H their point of view, like any other party to a /is and it was only
       MANOHAR LAL SHARMA v. PRINCIPLE                         127
                SECRETARY
then that judgment was delivered.                                      A

     31. Similarly, several States were also heard as recorded
in paragraph 10 of the judgment. In this regard, it was said:

     "The"arguments re-commenced on 05.12.2013. On that
     day, arguments of the States of Jharkhand, Chhatt\sgarh           8
     and Odisha were concluded and matters were fixed for
     08.01.2014. On 08.01.2014, the arguments on behalf of
     the States of Maharashtra, Andhra Pradesh, Madhya
     Pradesh and West Bengal were concluded and the
     matters were fixed for 09.01.2014. On that day, arguments         C
   · of learned Attorney General were concluded."

     32. In effect, therefore, all parties likely to be adversely
affected were given a hearing. The principles of natural justice,
though universal, must be realistically and pragmatically_             o
applied.

      33. In Sheela Barse it was observed, and we endorse that
view, that the relief to be granted in a case always looks to the
future. It is generally corrective and in some cases it is
compensatory. The present case takes within its fold all three         E
elements mentioned in Sheela Barse. Our judgment highlighted
the illegality and arbitrariness in the allotment of coal blocks and
these "consequence proceedings" are intended to correct the
wrong done by the Union of India; these proceedings look to
the future in that by highlighting the wrong, it is expected that      F
the Government will not deal with the natural resources that
belong to the country as if they belong to a few individuals who
can fritter them away at their sweet will; these proceedings may
also compensate the exchequer for the loss caused to it, in the
manner suggested by the learned Attorney General, and which            G
We now propose to consider.                                       -

     _34. There are two categories of coal block allotments: the
first category being allotments other than those mentioned in
Annexure. 1 and Annexure 2; the second category being the 46           H
    128     SUPREME COURT REPORTS                (2014] 12 S.C.R.


A   coal blocks mentioned in Annexure 1 and Annexure 2 that could
    possibly be "saved" from cancellation on certain terms and
    conditions, as submitted by the learned Attorney General.

        35. As far as the first category of coal block allotments is
  concerned, they must be cancelled (except those mentioned in
8
  the judgment). There is no reason to "save" them from
  cancellation. The allocations are illegal and arbitrary; the
  allottees have not yet entered into any mining lease and they
  have not yet commenced production. Whether they are 95%
  ready or 92% ready or 90% ready for production (as argued
C by some learned counsel) is wholly irrelevant. Their allocation
  was illegal and arbitrary, as already held, and therefore we
  quash all these allotments.

       36. Learned Attorney General identified 46 coal blocks that
D could be "saved" from the guillotine, since all of them have
  commenced production or are on the verge of commencing
  production. As these allocations are also illegal and arbitrary ·
  they are also liable to be cancelled. However, the allotment of
  three coal blocks in Annexure 1 is not disturbed and they are
E Moher and Moher Amroli Extension allocated to Sasan Power
  Ltd. (UMPP) and Tasra (allotted to Steel Authority of India Ltd.
  (SAIL), a Central Government public sector undertaking not
  having any joint ventu"re).

        As far the 6 coal blocks mentioned in Annexure 2 are
F concerned, the allocatees have not yet commenced production.
  They do not stand on a different or· better footing as far the
  consequences are concerned. These allotments are also liable
  to be cancelled. The allocation of the Pakri Barwadih coal block
  (allotted to National Thermal Power Corporation (NTPC), being
G a Central Government public sector undertaking not having any
  joint venture) is not liable to be cancelled.

       37. Except the above two allocations made to the UMPP
  and the two allocations made to the Central Government public
H sector undertaking. not having any joint venture mentioned
         MANOHAR LAL SHARMA v. PRINCIPLE                       129
                  SECRETARY
  above, all other allocations mentioned in Annexure 1 and             A
, Annexure 2 are cancelled.

      38. It was submitted by the learned Attorney General that
 on the cancellation of the coal block allotments, CIL would
 require some breathing time to manage its affairs. The Central 8
 Government is keen to move ahead but some time would be.
 required to manage the emerging situation. Similarly, breathing
 tfme is also required to be given to the allottees to manage their
 affairs on the cancellation of the coal blocks.

      39. In view of the submissions made, although we have            C
 quashed the allotment of 42 out of these 46 coal blocks, we
 make it clear that the cancellation will take effect only after six
 months from today, which is with effect from 31st March, 2015.
 This period of six months is being given since the learned
 Attorney General submitted that the Central Government and            D
 CIL would need some time to adjust to the changed situation
 and move forward. This period will also give adequate time to
 the coal block allottees to adjust and manage their affairs. That
 the CIL is inefficient and incapable of accepting the challenge,
 as submitted by learned counsel, is not an issue at all. The          E
 Central Government is confident, as submitted by the learned
 Attorney General, that the CIL can fill the void and take things
 forward.

      40. In addition to the request for deferment of cancellation,
                                                                       F
 we also accept the submission of the learned Attorney General
 that the allottees of the coal blocks other than those covered
 by the judgment and the four coal blocks covered by this order
 must pay an amount of Rs. 295/- per metric ton of coal extracted
 as an additional levy. This compensatory amount is based on
 the assessment made by the CAG. It may well be that the cost          G
 of extraction of coal from an underground mine has not been
 taken into consideration by the CAG, but in matters of this
 nature it is difficult to arrive at any mathematically acceptable
 figure quantifying the loss sustained. The estimated loss of Rs.
 295/- per metric ton of coal is, therefore, accepted for the          H
    130         SUPREME COURT REPORTS             (2014] 12 S.C.R.


A purposes of these cases. The compensatory paymerit,on this
  basis should be made within a period of three months and in
  any case on or before 31st December, 2014. The coal
  extracted hereafter till 31st March, 2015 will also attract the
  additional levy of Rs. 295/- per metric ton.
B
        41. lt is made clear that the scrutiny by the CBI in respect
  of the allotment of 12 coal blocks out of 46 identified by the
  learned Attorney General (and for that matter against any other
  allottee) will continue and .be taken to its logical conclusion.
C Needless to say, the observations and findings in this order
  shall have no bearing on the pending investigations.

   Nidhi Jain                 Order passed in consequence proceedings.
        MANOHAR LAL SHARMA v. PRINCIPLE                   131
                  SECRETARY
                                              Annexure 1         A

Details of 40 coal blocks which have come into
oroduction

 SI.     Name of Coal Block      Name of Allocatee
 No.                             Company                         8

 1.      Gare Palma IV/4         Jayaswal Neco Ltd.

 2.     '· Chotia                Prakash Industries Ltd.
                                          .


 3.      Namchik Namphuk         Arunachal Pradesh               c
                                 Mining Corp.

 4-5.    GarePalma IV/2&3        JSPL

 6.      Belgaon                 Sunflag Iron &Steel Ltd
                                                                 D
 7-12. Baranj I-IV, Kiloni and   Karnataka Power Corp
       Manoradeep                Ltd.

 13.     Kathautia               Usha Martin Ltd.
                                                                 E
 14.     Parbatpur               Electrosteel Castings
                                 Ltd.

 15.     Gare Palma IV/7         RAPL
                                 (Now Sarda Energy
                                 Ltd.)                           F

 16.     Barjore                 WBPDCL

 17.     Tara (East)             WBSEB

 18.     Tara (West)             WBPDCL                          G
 19.     Gare Palma IV/1         Jindal Power Ltd.

 20.     Sarshatali              CESC

 21      T~l<>hira-1             Hjnrl~I"" lnrlu<:trie<: I +rl   H
    132     SUPREME COURT REPORTS           [2014] 12 S.C.R.


A    22-23. Gotitoria (East & West)   BLA Industries

     24.
      .
            Gare Palma IV/5           Monnet lspat Ltd.

     25.    Pachwara Central          Punjab State Electricity
                                      Board
B
     26.    Tasra                     Steel Authority of India
                                      Ltd.

     27.    Barjora North             DVC
c    28.    Marki Mangli-1            B.S. lspat

     29-30. Marki Mangli-111
            Marki Mangli-11

D    31.    Trans Damodar             WBMTCDL

     32-33. Moher & Moher Amlori      Sasan Power Ltd.
            Extension

     34.    Ard hag ram               Sova lspat Ltd. & Jai
E                                     Balaji Industries Ltd.

     35-36. Parsa (east) & Kanta      RRVUN Ltd.
            Bas an

     37-38. Gangaramchak &            WBPDCL
F           Gangaramchak Bhadulia

     39.    Amelia North              MPSMDC Ltd.

     40.    Pachwara North            WBPDCL
G




H
        MANOHAR LAL SHARMA v. PRINCIPLE               133
                 SECRETARY
                                               Annexure 2   A

Details of Coal Blocks which are likely come into
production during 2014-15

  SI.      Company Name            Name of Coal Block
  No.                                                       B
  of
  block

  1.       GVK Power (Govindwal Tokisud North
           Sahib)                                           c
   2.      DVC                     Khagra Joydev

   3.      Prism Cement            Sial Ghogri

   4.      Jaiprakash Associates   Mandia North             D
           Ltd.

   5.      MPSMCL                  Bicharpur

   6.      NTPC                    Pakri Barwadih
                                                            E


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "coal block allocation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.