MAKERS DEVELOPMENT SERVICES PVT. LTD.versusM. VISVESVARAYA INDUSTRIAL RESEARCH AND DEVELOPMENT CENTRE
- Citation
- 2011 INSC 796
- Decided
- 14 November 2011
- Disposal
- Dismissed
- Bench
- P SATHASIVAM
Holding
The Court held that only the limited interim relief restraining the defendant from creating third‑party rights (prayer g) was justified, while the mandatory injunctions sought in prayers a‑f could not be granted as the balance of convenience and prima facie case did not support them.
Summary
Makers Development Services Pvt. Ltd. entered into a 1980 agreement with M. Visvesvaraya Industrial Research and Development Centre for constructing a hotel complex and obtaining a 60‑year lease. After the construction stalled at 80 ft, the respondent served a notice to vacate the premises in July 2007. The appellant filed a suit for injunction and a notice of motion seeking specific performance and a permanent injunction (prayers a‑g). The single judge of the Bombay High Court granted only limited interim relief restraining the respondent from creating any third‑party rights over the land (prayer g) and dismissed the other prayers; the division bench affirmed this order. On appeal, the Supreme Court examined the three established principles for granting interim injunctions—prima facie case, balance of convenience, and irreparable loss—along with the parties' conduct, and concluded that the balance of convenience did not favor a mandatory injunction for construction. Consequently, the Court upheld the limited relief and dismissed both appeals, directing the parties to cooperate for speedy disposal of the main suit.
Issues considered
- Whether the appellant has made out a case for granting the entire injunction sought in prayers (a) to (g).
- Whether the single judge and the division bench erred in granting only the limited relief under prayer (g) and refusing the mandatory injunctions in prayers (a) to (f).
Legislation cited
- Code of Civil Procedure, 1908s. Order XXXIX, Rules 1 and 2
Subjects
Judgment
[2011] 13 (ADDL.) S.C.R. 109
MAKERS DEVELOPMENT SERVICES PVT. LTD. A
v.
M. ViSVESVARAYA INDUSTRIAL RESEARCH AND
DEVELOPMENT CENTRE
(Civil Appeal No. 9709 of 2011)
B
NOVEMBER 14, 2011.
[P. SATHASIVAM AND JASTI CHELAMESWAR, JJ.]
Code of Civil Procedure, 1908:
c
Or.39, rr. 1 and 2 - Temporary injunction - Grant of -
Basic principles to be considered - Explained.
0. 39 - rr. 1 and 2 - Prayer for temporary injunction -
Agreement between the parties stated to have been entered
into for construction of a hotel and for grant of its lease - After D
construction was raised upto 80' dispute between parties - Suit
for mandatory injunction - Temporary injunction restraining
the defendant from obstructing the construction etc. prayed -
Single Judge and Division Bench of High Court granting
limited interim order restraining the defendant from in any E
manner selling, transferring or creating third party interests in
the suit property - HELD: The single Judge was fully justified
in granting the limited relief - The Division Bench was also
fully justified in confirming the said limited order - As rightly
obseNed by the single Judge as well as Division Bench, if F
other reliefs were granted and the plaintiff was allowed to
proceed with the construction on the suit land, in the event of
dismissal of suit, the defendant cannot use the land in a
different manner with the structure without undertaking an
enormous exercise of demolishing the same. G
On 4.8.2007, the appellant in C.A. No. 9709 of 2011
filed a suit in the City Civil Court for injunction against the
respondent. The case of the plaintiff-appellant was that
109 H
110 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A on 10.11.1980 and agreement was entered into between
the parties for construction of a composite hotel complex
and for granting the plaintiff would be granted lease of
the Hotel (exclusive of the Convention and Exhibition
Centre) in favour of the plaintif-appellant for 60 years with
B an option of renewal of lease. Pursuant to the agreement,
the respondent put the appellant in possession of the suit
land on 16.07.1990. Since the appellant could not
complete the work due to disputes and differences, the
respondent, on 31.07.2007, affixed a notice on the
c premises notifying all concerned including the appellant
to move out of the property and instructed its security
persons not to permit the appellant to enter upon the said
property. By order dated 06.08.2007, the trial court held
that till the substantive suit was filed by the appellant, the
0 impugned notice dated 31.07.2007 would not be acted
upon by ~he defendants up to and inclusive of
17.09.2007. On 10.09.2007, the appellant moved a Notice
of Motion No. 3499 of 2007 in a Ssuit bearing No. 2618 of
2007 before the Single Judge of the High Court for a
E decree of specific performance, inter alia, praying for a
permanent injunction restraining the respondent from
dispossessing the appellant. By ad-interim order dated
14.09.2007, the assurance given in the City Civil Court
was directed to be observed and the respondent was
directed not to create any third party rights pending the
F Notice of Motion. During the pendency of the suit, by
letter dated 19.11.2007, the respondent terminated the
said Agreement. The single Judge, rejected prayers
mentioned in clauses (a) to (f) of the Notice of Motion and
granted limited interim relief in favour of the appellant with
G regard to prayer clause (g), namely, pending the hearing
and final disposal of the suit, the defendant-respondent
would not, in any manner, sell, transfer or create any third
party rights or interests in the suit property. The appeals
filed by the parties were dismissed by the Division Bench
H of the High Court.
MAKERS DEV SERVICES PVT. LTD. v. M. VISVESVARAYA 111
INDUS. RESEARCH AND DEV. CENTRE
In the instant appeals filed by the parties, the A
questions for consideration before the Court were: (i)
"whether the appellant/plaintiff has made out a case for
grant of injunction in its entirety, i.e. prayer clauses (a)
to (g)" and (ii) "whether learned the single Judge as well
as the Division Bench of the High Court committed an B
error in granting limited relief in respect of clause (g)".
Dismissing the appeals, the Court
HELD: 11.1 It is settled law that while passing an
interim order of injunction under 0. 39, rr. 1 and 2 of the c
Code of Civil Procedure, 1908, the court is required to
consider three basic principles, namely, (a) prima facie
case, (b) balance of convenience and inconvenience and
(c) irreparable loss and injury. In addition to these thr~e
basic principles, a court, while granting injunction must D
also take into consideration the conduct of the parties.
It is also established law that the court should not
interfere only because the property is a very valuable
one. Grant or refusal of injunction has serious
consequences depending upon the nature thereof; and E
in dealing with such matters the court must make all
endeavours to protect the interests of the parties. [Para
6] [116-D-F]
1.2 Inasmuch as the main suit is pendin3, it would
not be proper for this Court to delve into the matter and F
arrive at a categorical finding one way or the other. The
finding of the single Judge about the construction of the
building to the height of 80 ft. on the suit land by the
appellant cannot be ignored. However, whether the
defendant permitted the appellant to enter on the suit G
land and to carry on construction are all matters to be
decided in the main suit. [paras 10 & 11] [119-E-F]
1.3 What was claimed by the plaintiff was not a mere
prohibitory order but prayed for positive mandatory H
112 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A injunction which, as rightly observed by the Division
Bench, would permit the plaintiff to alter the status quo
on the suit land on the date of the suit. The single Judge
as well as the Division Bench on appreciation of entire
materials rendered the factual finding that the balance of
B convenience is not in favour of granting such mandatory
interim order as claimed in prayer clauses (a) t-0 (f). As
rightly observed by the single Judge as well as the
Division Bench, if other reliefs were granted and the
appellant was allowed to proceed with the construction
c on the suit land, in the event· of dismissal of the suit, the
defendant cannot use the land in a different manner with
the structure without undertaking an enormous exercise
of demolishing the same. It is relevant to point out that
though the appellant had stated that it had started
D construction in the year 1996, even after the information
by the defendant to the appellant in 2002 that the BEST
had given their 'no objection' for the demolition of
temporary receiving station and the appellant can
proceed with the demolition, however, the fact remains,
E the height of the construction was only 80 ft. which
shows that from the year 2001 to 2007, the appellant had
not carried on construction and there was no obstruction
from the side of the defendant. l,n view of all these factual
aspects and in the light of the stand of the defendant
F disputing the existence of the agreement, as rightly
observed by the single Judge as well as the Division
Bench, further permission for construction or ancillary
works cannot be granted during the pendency of the suit.
The single Judge was fully justified in granting limited
relief in respect of prayer clause (g) and in declining the
G other reliefs in clauses (a) to (f). The Division Bench was
also fully justified in confirming the said limited order.
Both the parties are directed to cooperate with the court
for early conclusion of the hearing of Suit No. 2618 of
2007 pending before the single Judge of the High Court.
H [Para 12] (120-C-H; 121-A]
MAKE~S DEV. SERVICES PVT. LTD. v. M. VISVESVARAYA 113
INDUS. RESEARCH AND DEV. CENTRE
CIVIL APPELLATE JURISDICTION : Civil Appeal No. A
9709 of 2011.
From the Judgment & Order dated 28.06.2011 of the High
Court of Judicature at Bombay in Appeal No. 280 of 2008 in
Notice of Motion No. 3499 of 2007 in Suit No. 2618 of 2007. B
WITH
C.A. No. 9710 of 2011.
Shyam Divan, F. Pooniwala, Sandeep H. Junarkar, Pratap
Venugopal, Mumtaz Bandurwala, Surekha Raman, Namrata C
Sood, Anuj Sarma, K.J. John & Co. for the Appellant.
Mukul Rohtagi, Praveen Samdani, Ajay Khatla Walia,
Mahesh Agarwal, Radhika Gautam, Pratibha Mehta, E.C.
Agrawala for the Respondent.
D
P. SATHASIVAM, J. 1. Leave granted in both the Special
Leave Petitions. Both these appeals were heard together as
they arose out of the same set of facts and common questions
of law were involved.
E
2. SLP (C) No. 22276 of 2011 has been filed by the
Makers Development Services Pvt. Ltd. against the order
dated 28.06.2011 passed by the Division Bench of the Bombay
High Court in Appeal No. 280 of 2008 challenging the order
dated 25.04.2008 passed by the learned Single Judge in F
Notice of Motion No. 3499 of 2007 in Suit No. 2618 of 2007
declining the reliefs claimed in prayer clauses (a) to (f) pending
final disposal of the Suit and SLP (C) No. 25972 of 2011 has
been filed by M. Visvesvaraya lndusfrial Research and
Development Centre against the same order in Appeal No. 289 G
of 2008 in Notice of Motion No. 3499 of 2007 in Suit No. 2618
of 2007 granting relief in terms of prayer clause (g).
3. Brief facts:
a) Makers Development Services Pvt. Ltd.-the appellant H
114 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R
A herein (Original Plaintiff) is a Company registered under the
Companies Act, 1956 engaged in the business of
development, building, including the construction and
management of hotels and developments pertaining to other
hospitality services and management of properties. M.
3 Visvesvaraya Industrial Research and Development Centre-the
respondent herein {Original Defendant) is a Company
incorporated under the Companies Act, 1956 and is engaged,
inter alia, in promoting, establishing, conducting and
undertaking scientific research.
b) The Government of Maharashtra, by Resolutions dated
1'6.10.1970 and 18.11.1974, had granted lease of certain plots
of land to the defendant-Company at Backbay Reclamation,
Cuffe Parade, Mumbai, who was entitled and authorized to
enter into transactions with third parties in respect of the said
D land. A portion of that land admeasuring 13,326 sq. mts. which
forms a part of the larger land held by the defendant-Company
is the subject-matter of the present case.
c) An agreement dated 10.11.1980 was entered into
E between the parties for construction of a composite hotel
complex consisting of a Hotel Building, a Convention Centre
and an Exhibition Centre on the Suit Land (Tower No.2) and
the plaintiff would be granted lease of Hotel (exclusive of the
Convention and Exhibition Centre) for 60 years with an option
F of renewal of lease. This agreement came to be modified from
time to time.
d) Pursuant to the Agreement, the respondent put the
appellant in possession of the Suit Land on 16.07 .1990, which
continues to remain with the appellant till date.
G
e) Since the appellant could not complete the work and
due to disputes and differences, the respondent, on
31.07.2007, affixed a notice on the premises notifying all
concerned including the appellant to move out of the property
H
MAKERS DEV. SERVICES PVT. LTD. v. M. VISVESVARAYA 115
INDUS. RESEARCH AND DEV. CENTRE [P. SATHASIVAM, J.]
and instructed its security persons not to permit the appellant A
to enter upon the said property.
f) On 04.08.2007, the appellant filed a suit for injunction
before the City. Civil Court, Mumbai seeking interim and final
reliefs restraining the respondent from taking any illegal steps. B
By order dated 06.08.2007, the learned Judge held that till the
substantive suit is filed by the appellant, the impugned notice
dated 31.07.2007 will not be acted upon by the defendants upto
and inclusive of 17.09.2007.
g) On 10. 09. 2007, the appellant moved a Notice of C
Motion No. 3499 of 2007 in a Suit being No. 2618 of 2007
before the learned Single Judge of the Bombay High Court
for a decree of specific performance, inter alia, praying for a
permanent injunction restraining the respondent from
dispossessing the appellant. By ad-interim order dated D
14.09.2007, the assurance given in the City Civil Court was
directed to be observed and the respondent was directed not
to create any third party rights pending the Notice of Motion.
During the pendency of the suit, by letter dated 19.11.2007,
the respondent terminated the said Agreement. The learned E
single Judge, after referring the documents and affidavits on
record, rejected prayer clauses (a) to (f) of the Notice of Motion
and granted limited interim relief with regard to prayer clause
(g) in favour of the appellant.
h) Aggrieved by the order of the learned single Judge, the F
appellant preferred an appeal being Appeal No. 280 of 2008
before the Division Bench of the High Court. With regard to the
limited relief granted by the learned single Judge, the
respondent also filed an appeal being Appeal No. 289 of 2008
before the Division Bench of the High Court. G
i) The Division Bench, by a common judgment, upheld the
order of the learned single Judge and dismissed both the
appeals. Challenging the order of the Division Bench of the
H
116 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A High Court, the appellant and the respondent filed separate
special leave petitions before this Court.
4. Heard Mr. Shyam Divan, learned senior counsel for the
appellant and Mr. Mukul Rohatgi & Mr. Praveen Samdani,
B learned senior counsel for the respondent.
5. The points for consideration in these appeals are:-
a) Whether the appellant/plaintiff has made out a case
for grant of injunction in its entirety, i.e. prayer
c clauses (a) to (g)?
b) Whether learned single Judge as well as Division
Bench of the High Court committed an error in
granting limited relief in respect of clause (g)?
D 6. It is settled law that while passing an interim order of
injunction under Order XXXIX Rules 1 and 2 of the Code of Civil
Procedure, 1908, the Court is required to consider three basic
principles, namely, a) prima facie case, b) balance of
convenience and inconvenience and c) irreparable loss and
E injury. In addition to the above mentioned three basic principles,
a court, while granting injunction must also take into
consideration the conduct of the parties. It is also established
law that the Court should not interfere only because the property
is a very valuable one. Grant or refusal of injunction has serious
F consequences depending upon the nature thereof and in
dealing with such matters the court must make all endeavours
to protect the interest of the parties.
7. With the above principles, let us consider the claim of
both the parties.
G
8. The appellant/plaintiff, who filed Suit No. 2618 of 2007
on the file of original side of the High Court of Bombay prayed
for the following interim reliefs pending hearing and final
disposal of the said suit:
H
MAKERS DEV SERVICES PVT. LTD. v. M. VISVESVARAYA 117
INDUS. RESEARCH AND DEV. CENTRE [P. SATHASIVAM, J.]
"(a) That pending the hearing and final disposal of the Suit, A
the Defendant be ordered and directed to do, sign,
execute, deliver and register all such acts, deeds, matters
writings, documents, authorities papers, plans, sanctions
and things as may be necessary to enable the Plaintiff to
continue construction on the Suit Land in terms of the Suit B
Contract;
(b) That pending the hearing and final disposal of the Suit,
the Defendant by itself, its servants and agents or any
person or persons claiming by, from, through or under them C
be restrained by an order and injunction of this Court from
dispossessing the Plaintiff or removing the authorized
representatives, employees, staff, workers and labourers
of the Plaintiff and their respective family member or their
belongings and articles or the construction materials,
equipment and other belongings of the Plaintiff from the D
Suit Land;
(c) That pending the hearing and final disposal of the Suit,
it be ordered and decreed that the Defendant to allow the
Plaintiff to continue construction on the Suit Land and E
unhindered access to the Suit Land and allow ingress to
and egress from the Suit Land, by the Plaintiff, its
representatives, employees and contract labour as also for
all construction materials and equipment without in any
manner, directly or indirectly, obstructing or hindering the F
Plaintiff.
(d) That pending the hearing and final disposal of the Suit,
the Defendant by itself, its servants and agents or any
person or persons claiming by, from, though or under them
be restrained by an order and injunction of this Court from G
in any manner restraining, preventing impending or
obstructing implementation of the Suit Contract or
construction on the Suit Land or access to and ingress to
and egress from the Suit Land, of the Plaintiff or its
authorized representatives, employees. workers, labourers H
118 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A and their respective family members or preventing,
impeding or obstructing construction material or equipment
of the Plaintiff from being brought on to the Suit land or in
any manner, directly or indirectly, by any act of omission
or commission, withholding or causing to be withheld
B essential utilities such as power and water supply to the
Suit Land for construction by the Plaintiff;
(e) That pending the hearing and final disposal of the Suit,
the Defendant by itself, its servants and agents or any
person or persons claiming by, from, through or under them
c be restrained by an order and injunction of this Court from
in any manner, whether directly or indirectly, revoking or
acting on any purported revocation of the Letter of Authority
granted by the Defendant to the Plaintiff or in any manner,
whether directly or indirectly, hindering, impeding or
D obstructing construction on the Suit Land in terms of the
Suit Land in terms of the Suit Contract;
(f) That pending the hearing and final disposal of the Suit,
the Defendant by itself, its servants and agents or any
E person or persons claiming by, from, through or under them
be restrained by an order and injunction of this Court from
in any manner committing unlawful trespass or from in any
manner intimidating the Plaintiff, its employees, workers,
labourers and other agencies appointed by the Plaintiff;
F (g) That pending the hearing and final disposal of the Suit,
the Defendant by itself, its servants and agents or any
person or persons claiming by, from, through or under them
be restrained by an order and injunction of this Court from,
in any manner, selling transferring, dealing with, disposing
G of, alienating encumbering or creating any third party rights
or interest in, or entering into any agreement or
arrangement with any one else in respect of the Suit Land
or any part thereof;"
H 9. Among the above prayers for interim reliefs, the learned
MAKERS DEV. SERVICES PVT. LTD. v. M. VISVESVARAYA 119
INDUS. RESEARCH AND DEV. CENTRE [P. SATHASIVAM, J.]
single Judge granted relief only in respect of prayer clause (g) A
that too with a condition, namely, except the words "dealing
with". The learned single Judge on satisfying himself and after
thorough scrutiny of the materials placed rejected the relief
insofar as prayer clauses (a) to (f), which resulted in filing of
above two appeals by the appellant and the defendant. It is the B
claim of the appellant/plaintiff that on the basis of the contract
between the parties, the learned single Judge and the Division
Bench should have granted an order permitting the appellant
to carry on further construction especially when construction of
about 80 ft. had already been raised by the appellant on the c
suit land. On the other hand, it is the case of the defendant that
there is no existing agreement between the parties and the only
point is that the parties have agreed to enter into an agreement
and, therefore, the learned single Judge as well as the Division
bench were not justified even in granting interim order in terms D
of prayer (g).
10. Inasmuch as the main suit is pending, it would not be
proper for this Court to delve into the matter and arrive at a
categorical finding one way or other. Accordingly, we have to
find out whether there is prima facie case and 'balance of E
convenience' in terms of principles mentioned above.
11. The finding of the learned single Judge about the
construction of the building to the height of 80 ft. on the suit land
by the appellant cannot be ignored. However, whether the F
defendant permitted the appellant to enter on the suit land and
to carry on construction are all matters to be decided in the
main suit. The limited relief granted in clause (g) by the learned
single Judge is quite understandable, otherwise, it could be
possible for the defendant to deal with the suit land with third G
parties or encumber it before the final disposal of the suit.
However, as rightly observed by the learned single Judge as
well as Division Bench, if other reliefs which we have already
extracted above are granted, in the event of dismissal of a suit,
undoubtedly, it would create enormous difficulties for the H
120 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A defendant using the plot or land freely and without any difficulty.
In other words, if the appellant was allowed to proceed with the
construction on the suit land, in the event of dismissal of suit,
the defendant cannot use the land in a different manner with
the structure without undertaking an enormous exercise of
B demolishing the same. Further, what was claimed by the plaintiff
was not a mere prohibitory order but prayed for positive
mandatory injunction which, as rightly observed by the Division
Bench, would permit the plaintiff to alter the status quo on the
suit land on the date of the suit.
c 12. The learned single Judge as well as Division Bench
on appreciation of entire materials rendered the factual finding
that the balance of convenience is not in favour of granting such
mandatory interim order as claimed in prayer clauses (a) to (f).
D It is relevant to point out that though the appellant had stated
that it had started construction in the year 1996, even after the
information by the defendant to the appellant in 2002 that the
BEST had given their 'no objection' for the demolition of
temporary receiving station and the appellant can proceed with
the demolition, however, the fact remains, the height of the
E construction was only 80 ft. which shows that from the year 2001
to 2007, the appellant had not carried on construction and there
was no obstruction from the side of the defendant. In view of
all these factual aspects and in the light of the stand of the
defendant disputing the existence of the agreement, as rightly
F observed by the learned single Judge as well as Division
Bench, further permission for construction or ancillary works
cannot be granted during the pendency of the suit. We are
satisfied that the learned single Judge was fully justified in
granting limited relief in respect of prayer clause (g) and
G declined the other reliefs in clauses (a) to (f). The Division
Bench was also fully justified in confirming the said limited order.
Though learned senior counsel for the respondent has prayed
for certain directions such as execution of a mortgage deed
etc., for the same reasons mentioned above, we are not inclined
H
MAKERS DEV SERVICES Pvr LTD. v. M. VISVESVARAYA 121
INDUS. RESEARCH AND DEV. CENTRE [P. SATHASIVAM, J.]
to grant such relief as claimed. As observed earlier, at this A
stage, it is not desirable to go into all the details and render a
specific finding which would undoubtedly affect the claim of both
the parties in the main suit. On the other hand, we are in entire
agreement with the prima facie conclusion arrived at by the
learned single Judge and the Division Bench. B
13. Inasmuch as, as early as on 25.04.2008, the learned
single Judge directed hearing of the suit be expedited, taking
note of various other aspects/impediments highlighted by both
the parties including construction of a protection/security wall c
on the sea side, we request the learned single Judge of the
High Court to dispose of the suit being No. 2618 of 2007 as
early as possible preferably within a period of nine months from
the date of the receipt of the copy of this judgment. We also .
direct both the parties to cooperate with the court for early
0
conclusion of the hearing as directed above.
14. In the light of the above discussion and reasonings, we
find no merit in both the appeals, consequently; they are
·dismissed with no order as to costs.
E
R.P. Appeals dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.