MAHANAGAR TELEPHONE NIGAM LTD.versusTATA COMMUNICATIONS LTD.
- Citation
- 2019 INSC 286
- Decided
- 27 February 2019
- Disposal
- Dismissed
- Bench
- R F NARIMAN
Holding
The dispute is governed by Section 74, and liquidated damages cannot exceed the contractual ceiling of 12%; the appeal is dismissed.
Summary
Mahanagar Telephone Nigam Ltd. (MTNL) entered into a purchase order with Tata Communications Ltd. for last‑mile connectivity, the contract stipulating that liquidated damages for delay could not exceed 12% of the contract value. Tata billed MTNL Rs 2,15,25,512 for services rendered, but MTNL unilaterally deducted a larger amount and imposed its own rental rates, leading Tata to file a petition before the Telecom Disputes Settlement and Appellate Tribunal (TDSAT) seeking recovery of Rs 1,10,57,268 plus interest. TDSAT held that only the contractual ceiling of 12% (approximately Rs 25.83 lakh) could be retained as liquidated damages and ordered MTNL to pay Tata Rs 84,74,087 with interest at 9%. On appeal, MTNL contended that a claim for quantum meruit under Section 70 of the Indian Contract Act was permissible despite the existence of a contract and that higher damages could be awarded. The Supreme Court ruled that the dispute falls under Section 74 (penalty/liquidated damages) rather than Section 70, reaffirming that the contractual limit of 12% is the final ceiling and that any excess must be refunded, thereby upholding the TDSAT order and dismissing the appeal.
Issues considered
- Whether a claim for quantum meruit under Section 70 of the Indian Contract Act is permissible when the parties are governed by an express contract.
- Whether liquidated damages can exceed the contractual maximum of 12% stipulated in the purchase order.
- Interpretation of the penalty clause under Section 74 of the Indian Contract Act in the present facts.
Legislation cited
- Indian Contract Act, 1872s. 70, s. 73, s. 74
- Telecom Regulatory Authority of India Act, 1997
Subjects
Judgment
[2019] 4 S.C.R. 885 885
MAHANAGAR TELEPHONE NIGAM LTD. A
v.
TATA COMMUNICATIONS LTD.
(Civil Appeal No.1766 of 2019)
FEBRUARY 27, 2019 B
[R. F. NARIMAN AND VINEET SARAN, JJ.]
Contract Act, 1872 – ss. 74 and 70 – Compensation for breach
of contract where penalty stipulated for – Claim in quantum meruit
u/s. 70 when parties governed by contract – Permissibility of –
C
Purchase Order wherein respondent was to provide last mile
connectivity at two places of the appellant and levy of liquidated
damages were to be limited to a maximum of 12% – Bills raised by
the respondent for the services rendered amounting to
Rs. 2,15,25,512/- – On account of limitation of 12%, the appellants
could not have levied and deducted an amount more than D
Rs. 25,83,181/-, however, the appellant proceeded to unilaterally
impose rentals at their own rate of dark fibre – Appellant adjusted
the amount from dues payable to the respondent by deduction from
the bill raised by the respondent – Respondent filed petition before
the tribunal against the appellant for recovery of Rs.1,10,57,268/-
E
plus interest thereon – Tribunal held that the principal amount to be
paid back to the respondent by the appellant would be
Rs.84,74,087/- with 9% interest thereon after deducting
Rs.25,83,181/- (12% liquidated damages) from Rs. 1,10,57,268/- –
On appeal, held: Instant case is covered by s. 74 – Tribunal rightly
held that a maximum of 12% can be levied as liquidated damages F
under the contract, which would amount to Rs. 25 lakh – Since this
clause governs the relations between the parties, contractually
speaking a higher figure, cannot be awarded as liquidated damages,
which is to be considered as final – Appellant can claim only this
sum – Thus, the order of the tribunal upheld – Telecom Regulatory
G
Authority of India Act, 1997.
Dismissing the appeal, the Court
HELD: 1.1 Section 70 occurs in Chapter V of the Contract
Act, which chapter is headed, “of certain relations resembling
H
885
886 SUPREME COURT REPORTS [2019] 4 S.C.R.
A those created by contract”. There are five sections that are
contained in this Chapter. Each of them is posited on the fact that
there is, in fact, no contractual relationship between the parties
claiming under this Chapter. For example, under Section 68, if a
person incapable of entering into a contract is supplied
necessaries by another person, then the person who has furnished
B
such supplies becomes entitled to be reimbursed from the
property of the person so incapable of entering into the contract.
Section 69 also deals with a case where a person has no contractual
relationship with the other person mentioned therein, but who is
interested in the payment of money which the other person is
C bound by law to pay, and who, therefore, pays it on behalf of such
person. Such person is entitled to be reimbursed by the other
person. Under Section 71, again, the finder of goods spoken of is
a person who is fastened with the responsibility of a bailee as
there is no contractual relationship between the finder of goods
and the goods which belong to another person. Equally, under
D
Section 72, a person to whom money has been paid or anything
delivered by mistake or coercion must repay or return it, or else,
such person would be unjustly enriched. Here again, there is no
contractual relationship between the parties. It is in this setting
that Section 70 occurs. [Para 2] [890-F-H; 891-A-B]
E 1.2 The instant case is really covered by Section 74 of the
Contract Act, which occurs in Chapter VI, which is headed, “of
the consequences of breach of contract”. [Para 10] [895-B]
1.3 The impugned judgment of TDSAT rightly held that a
maximum of 12% can be levied as liquidated damages under the
F contract, which sum would amount to a sum of INR 25 lakh. Since
this clause governs the relations between the parties, obviously,
a higher figure, contractually speaking, cannot be awarded as
liquidated damages, which are to be considered as final and not
challengeable by the supplier. This being the case, the appellant
G can claim only this sum. Anything claimed above this sum would
have to be refunded to the respondent. The impugned judgment
of the TDSAT is upheld. [Paras 13, 14] [897-G-H; 898-A-B]
H
MAHANAGAR TELEPHONE NIGAM LTD. v. 887
TATA COMMUNICATIONS LTD.
Moselle Solomon v. Martin & Co. ILR (1935) 62 Cal A
612; Kanhayalal Bisandayal Bhiwapurkar (Dr.) v.
Indarchandji Hamirmalji Sisodia AIR 1947 Nag 84;
Alopi Parshad and Sons Ltd. v. Union of India
[1960] 2 SCR 793; Mulamchand v. State of M.P. [1968]
3 SCR 214; Orissa Industrial Infrastructure
B
Development Corpn. v. Mesco Kalinga Steel Ltd. (2017)
5 SCC 86; Kailash Nath Associates v. DDA (2015) 4
SCC 136 : [2015] 1 SCR 627 – referred to
Case Law Reference
(1935) 62 Cal 612 referred to Para 3 C
AIR 1947 Nag 84 referred to Para 4
[1960] 2 SCR 793 referred to Para 5
[1968] 3 SCR 214 referred to Para 6
(2017) 5 SCC 86 referred to Para 7 D
[2015] 1 SCR 627 referred to Para 11
CIVIL APPELLATE JURISDICTION: Civil Appeal No.1766 of
2019.
From the Judgment and Order dated 25.06.2018 of the Telecom E
Disputes Settlement and Appellate Tribunal, New Delhi in TP No.465 of
2012.
Sumit Chander, Shagufa Salim, Ms. Garima Prashad, Advs. for
the Appellant.
Ms. Dharitry Phookan, Adv. for the Respondent. F
The Judgment of the Court was delivered by
R. F. NARIMAN, J. 1. The present appeal arises out of a dispute
under the Telecom Regulatory Authority of India Act, 1997. The relief
sought through a petition before the Telecom Disputes Settlement and
G
Appellate Tribunal, New Delhi [“TDSAT”] by the respondent, Tata
Communication Ltd. against the appellant, Mahanagar Telephone Nigam
Ltd., is for a recovery of a sum of INR 1,10,57,268/- plus interest thereon.
The question that arose between the parties is whether the appellant
H
888 SUPREME COURT REPORTS [2019] 4 S.C.R.
A was justified in adjusting this amount from the dues payable to the
respondent by deduction from the bills raised by the respondent. Since
the Purchase Order dated 01.10.2008 forms the basis for the claim, it is
important to set out clauses 4 and 8 of the said Purchase Order as
under:
B “4.SCOPE OF ORDER
xxx xxx xxx
iv. Termination of the bandwidth on STM-1 would be done at the
MTNL sites/locations in Delhi (Kidwai Bhawan and Nehru Place)
and Mumbai (Fountain Head & Prabha Devi) respectively as per
C the requirement with redundancy in last mile connectivity. For
this bandwidth termination purpose, optical/electrical converter,
cable and any other hardware/software etc. required, if any, would
be arranged by the bidder free of cost.”
xxx xxx xxx
D
“8. DELIVERY SCHEDULE
(i) The physical connectivity for bandwidth should be completed
within two months from the date of place of Purchase Order.”
The TDSAT, on considering this Purchase Order, held:
E “25. At this stage, it falls for consideration as to what relief the
petitioner is entitled to on the basis of strength of its own case.
For this purpose, it is useful to note at the outset that the petitioner
was required to provide the last mile connectivity as per paragraph
4(iv) of the P.O. within two months. It is also not in dispute that
F petitioner did not provide the required connectivity not only by
December 2008 but even by time when it chose to terminate the
contract on 11.01.2011. The defence pleaded and argued on behalf
of petitioner is that it was neither given access to the buildings/
premises of the respondents nor the permission for affecting the
last mile connectivity. This stand was sought to be justified by
G placing reliance on Emails written by the petitioner on 01.06.2010
which is more than a year after grant of permission by Delhi and
Mumbai units around March and April 2009. On going through
the communication dated 01.06.2010, it is evident that the plea
that respondents did not allow entry to the petitioner into their
H
MAHANAGAR TELEPHONE NIGAM LTD. v. 889
TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.]
premises in Mumbai has been raised quite belatedly and does not A
appear to be correct and convincing. Hence, we find petitioner’s
case to be weak and unacceptable in so far as it puts the blame
totally upon the respondent for its inability or failure to provide the
last mile connectivity. No doubt there was some delay by the
respondents at the initial stage but that alone cannot justify or
B
absolve petitioner’s total failure.
26.If we had reliable materials to find out the exact cost of providing
the last mile connectivity at each of the two premises in Mumbai
and Delhi, we would have reduced that much amount from the
claim of the petitioner and allowed the rest. That would have
served the interest of justice and prevented unjust enrichment of C
the petitioner. However, in absence of such reliable materials as
to actual costs which the petitioner has saved by non-compliance
with the requirements of paragraph 4(iv) of the P.O., we have
looked closely at the case of both the parties and we find that at
best the respondents could have invoked clause 16 and more D
particularly, clause 16.2 which provide for liquidated damages in
certain eventualities like failure to deliver the stores/services or to
install and commission the project in whole or in part. The admitted
default on the part of the petitioner can safely be treated as failure
or delay affecting the installation/commissioning of a part of the
project requiring last mile connectivity. In such a case, as per E
clause 16.2(b) of the Agreement (P.O.), liquidated damages can
be levied on the affected part of the project. As per clause 16.2(c),
the liquidated damages must be limited to a maximum of 12%. In
the present case the full amount billed and receivable by the
petitioner for services rendered is disclosed as Rs.2,15,25,512/-, F
hence, on account of limitation of 12%, the respondents could not
have levied and deducted an amount more than Rs.25,83,181/-.
Instead of adopting this lawful course, the respondents proceeded
to unilaterally impose rentals at their own rate of dark fibre. Such
action of the respondents amounts to adjudicating a claim in its
own favour without any authority for such unilateral act either G
under Section 70 of the Contract Act or under any of the provisions
of the Contract(P.O.).
xxx xxx xxx
H
890 SUPREME COURT REPORTS [2019] 4 S.C.R.
A 28.As a result of aforesaid discussion, the claim of the petitioner
is allowed but in part only. The principal amount which the
respondent must refund or pay back to the petitioner would be
Rs.1,10,57,268 – Rs.25,83,181= Rs.84,74,087/-. Petitioner has also
claimed an amount of Rs.66,33,414/- by way of interest from the
date the amounts became due and upto 15.07.2012. It has
B
calculated this amount by applying a rate of 18%. The calculations
are in Annexure P-14 which discloses the dates when the short
payments were made after deductions. We are not persuaded to
allow interest @ 18% in absence of any such stipulation in the
Agreement (P.O.). Hence, while allowing the principal amount of
C Rs.84,74,087/- in favour of the petitioner, we direct payment of
interest at the rate of 9% from the date the amounts became due
upto the date of this judgment/order.”
2. Having heard the learned counsel for both sides, one neat
question arises before this Court, which is, whether, when parties are
D governed by contract, a claim in quantum meruit under Section 70 of
the Indian Contract Act, 1872[“Contract Act”] would be permissible.
Section 70 of the Contract Act reads as under:
“70. Obligation of person enjoying benefit of non-gratuitous
act.—Where a person lawfully does anything for another person,
E or delivers anything to him, not intending to do so gratuitously, and
such other person enjoys the benefit thereof, the latter is bound to
make compensation to the former in respect of, or to restore, the
thing so done or delivered.”
This Section occurs in Chapter V of the Contract Act, which
F chapter is headed, “of certain relations resembling those created by
contract”. There are five sections that are contained in this Chapter.
Each of them is posited on the fact that there is, in fact, no contractual
relationship between the parties claiming under this Chapter. For example,
under Section 68, if a person incapable of entering into a contract is
supplied necessaries by another person, then the person who has furnished
G such supplies becomes entitled to be reimbursed from the property of
the person so incapable of entering into the contract. Section 69 also
deals with a case where a person has no contractual relationship with
the other person mentioned therein, but who is interested in the payment
of money which the other person is bound by law to pay, and who,
H
MAHANAGAR TELEPHONE NIGAM LTD. v. 891
TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.]
therefore, pays it on behalf of such person. Such person is entitled to be A
reimbursed by the other person. Under Section 71, again, the finder of
goods spoken of is a person who is fastened with the responsibility of a
bailee as there is no contractual relationship between the finder of goods
and the goods which belong to another person. Equally, under Section
72, a person to whom money has been paid or anything delivered by
B
mistake or coercion must repay or return it, or else, such person would
be unjustly enriched. Here again, there is no contractual relationship
between the parties. It is in this setting that Section 70 occurs.
3. An early judgment reported as Moselle Solomon v. Martin
& Co., ILR (1935) 62 Cal 612 resulted in a split verdict between the
two judges on the point of whether Section 70 of the Contract Act can C
apply when there is, in fact, a contract between the parties. Lort-Williams,
J. held:
“There remains to be decided the question whether the second
defendant is liable under section 70 of the Indian Contract Act
and to what extent. The remedy provided by this section is not D
dependent upon the law relating to the liabilities of principal and
agent. It is an independent remedy, which is based upon a different
cause of action, namely, upon whether a person has lawfully done
anything for another or has delivered anything to him not intending
to do so gratuitously, and such other person has enjoyed the benefit E
thereof. If so, he must either make compensation in respect of, or
restore the thing so done or delivered.”
(at page 619)
On the other hand, Jack, J. held:
F
“As regards the appeal, it is clear that the second defendant cannot
be held liable under section 70 of the Contract Act, in as much as
this is a case of contract and, where there is an express contract,
section 70 has no application, as shown by the heading of Chapter
V of the Act, in which the section finds a place. It is headed “Of
Certain Relations Resembling Those Created by Contract”, G
evidently excluding relations actually created by contract, as in
this case. The Contract Act is, however, not exhaustive.”
(at page 623)
H
892 SUPREME COURT REPORTS [2019] 4 S.C.R.
A 4.In Kanhayalal Bisandayal Bhiwapurkar (Dr.) v.
Indarchandji Hamirmalji Sisodia, AIR 1947 Nag 84,a learned Single
Judge of the High Court was dealing with an application by an eye-
specialist of repute who wished to recover an amount of INR 188/- as
the price of professional work, i.e., getting a cataract removed in
accordance with an agreement with one Mt. Laxmibai and her son-in-
B
law, Mohan Lal, by which agreement, the said operation was to be
performed. An appeal to Sections 68 and 70 of the Contract Act was
turned down in the following terms:
“10. In the course of the argument, an appeal was made to the
principles underlying Ss. 68 and 70, Contract Act, for making the
C husband liable. Indeed S. 68, deals with the supply of necessaries
but that is in respect of a person incapable of entering into a
contract or “any one whom he is legally bound to support”, i.e.
the dependent of a person incompetent to contract. Indarchandji
was not incompetent to contract and this section is inapplicable to
D him. As to S. 70, it must be observed that this section cannot be
availed of by a person who relies on an express contract as the
plaintiff alleged to have entered into with Mt. Laxmibai in this
case. The husband never entered into the picture when the plaintiff
settled the terms with her. Nor is there anything to show how the
husband received any benefit. It is only actual benefit which will
E famish a ground of action. If the wife had been cured of her
ailment completely, perhaps that circumstance might be material;
but there is no evidence on the point.”
5. In Alopi Parshad and Sons Ltd. v. Union of India, (1960) 2
SCR 793, this Court dealt with an arbitration award which, inter alia,
F awarded certain amount on the basis of quantum meruit. In setting
aside the Award on the ground of error apparent on the face of the
record, this Court held:
“…… Ghee having been supplied by the Agents under the terms
of the contract, the right of the Agents was to receive remuneration
G under the terms of that contract. It is difficult to appreciate the
argument advanced by Mr. Chatterjee that the Agents were entitled
to claim remuneration at rates substantially different from the terms
stipulated, on the basis of quantum meruit. Compensation
quantum meruit is awarded for work done or services rendered,
H
MAHANAGAR TELEPHONE NIGAM LTD. v. 893
TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.]
when the price thereof is not fixed by a contract. For work done A
or services rendered pursuant to the terms of a contract,
compensation quantum meruit cannot be awarded where the
contract provides for the consideration payable in that behalf.
Quantum meruit is but reasonable compensation awarded on
implication of a contract to remunerate, and an express stipulation
B
governing the relations between the parties under a contract, cannot
be displaced by assuming that the stipulation is not
reasonable……”
(at page 809)
6. In Mulamchand v. State of M.P.,(1968) 3 SCR 214, this Court C
held that the provisions of Section 175(3) of the Government of India
Act are mandatory in character and based on public policy. Therefore,
the formalities that are stipulated when contracts are entered into on
behalf of the Government cannot be waived or dispensed with. In dealing
with a claim made under Section 70 of the Contract Act, this Court then
went on to hold: D
“…… In other words, if the conditions imposed by Section 70 of
the Indian Contract Act are satisfied then the provisions of that
section can be invoked by the aggrieved party to the void contract.
The first condition is that a person should lawfully do something
for another person or deliver something to him; the second condition E
is that doing the said thing or delivering the said thing he must not
intend to act gratuitously; and the third condition is that the other
person for whom something is done or to whom something is
delivered must enjoy the benefit thereof. If these conditions are
satisfied, Section 70 imposes upon the latter person the liability to F
make compensation to the former in respect of, or to restore, the
thing so done or delivered. The important point to notice is that in
a case falling under Section 70 the person doing something for
another or delivering something to another cannot sue for the
specific performance of the contract, nor ask for damages for the
breach of the contract, for the simple reason that there is no G
contract between him and the other person for whom he does
something or to whom he delivers something. So where a claim
for compensation is made by one person against another under
Section 70, it is not on the basis of any subsisting contract between
H
894 SUPREME COURT REPORTS [2019] 4 S.C.R.
A the parties but on a different kind of obligation. The juristic basis
of the obligation in such a case is not founded upon any contract
or tort but upon a third category of law, namely, quasi-contract or
restitution……”
(at pp. 221-222)
B 7. This judgment has been recently referred to and followed in
Orissa Industrial Infrastructure Development Corpn. v. Mesco
Kalinga Steel Ltd., (2017) 5 SCC 86 at paragraph 21.
8. Indeed, the aforesaid position in law is made clearer by Section
73 of the Contract Act. Section 73 reads as follows:
C
“73. Compensation for loss or damage caused by breach of
contract.— When a contract has been broken, the party who
suffers by such breach is entitled to receive, from the party who
has broken the contract, compensation for any loss or damage
caused to him thereby, which naturally arose in the usual course
D of things from such breach, or which the parties knew, when they
made the contract, to be likely to result from the breach of it.
Such compensation is not to be given for any remote and
indirect loss or damage sustained by reason of the breach.
Compensation for failure to discharge obligation
E
resembling those created by contract.—When an obligation
resembling those created by contract has been incurred and has
not been discharged, any person injured by the failure to discharge
it is entitled to receive the same compensation from the party in
default, as if such person had contracted to discharge it and had
F broken his contract.
Explanation.—In estimating the loss or damage arising
from a breach of contract, the means which existed of remedying
the inconvenience caused by the non-performance of the contract
must be taken into account.”
G 9. This Section makes it clear that damages arising out of a breach
of contract is treated separately from damages resulting from obligations
resembling those created by contract. When a contract has been broken,
damages are recoverable under paragraph 1 of Section 73.When,
H
MAHANAGAR TELEPHONE NIGAM LTD. v. 895
TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.]
however, a claim for damages arises from obligations resembling those A
created by contract, this would be covered by paragraph 3 of Section
73.
10. Indeed, the present case is really covered by Section 74 of the
Contract Act, which occurs in Chapter VI, which is headed, “of the
consequences of breach of contract”. Section 74 states: B
“74. Compensation for breach of contract where penalty
stipulated for.— When a contract has been broken, if a sum is
named in the contract as the amount to be paid in case of such
breach, or if the contract contains any other stipulation by way of
penalty, the party complaining of the breach is entitled, whether C
or not actual damage or loss is proved to have been caused thereby,
to receive from the party who has broken the contract reasonable
compensation not exceeding the amount so named or, as the case
may be, the penalty stipulated for.
Explanation.—A stipulation for increased interest from the D
date of default may be a stipulation by way of penalty.
Exception.—When any person enters into any bail-bond,
recognizance or other instrument of the same nature, or, under
the provisions of any law, or under the orders of the Central
Government or of any State Government, gives any bond for the E
performance of any public duty or act in which the public are
interested, he shall be liable, upon breach of any condition of any
such instrument, to pay the whole sum mentioned therein.
Explanation.—A person who enters into a contract with
Government does not necessarily thereby undertake any public F
duty, or promise to do an act in which the public are interested.”
11. In Kailash Nath Associates v. DDA, (2015) 4 SCC 136,
after considering the case law on Section 74, this Court held:
“43. On a conspectus of the above authorities, the law on
compensation for breach of contract under Section 74 can be G
stated to be as follows:
43.1. Where a sum is named in a contract as a liquidated amount
payable by way of damages, the party complaining of a breach
H
896 SUPREME COURT REPORTS [2019] 4 S.C.R.
A can receive as reasonable compensation such liquidated amount
only if it is a genuine pre-estimate of damages fixed by both parties
and found to be such by the court. In other cases, where a sum is
named in a contract as a liquidated amount payable by way of
damages, only reasonable compensation can be awarded not
exceeding the amount so stated. Similarly, in cases where the
B
amount fixed is in the nature of penalty, only reasonable
compensation can be awarded not exceeding the penalty so stated.
In both cases, the liquidated amount or penalty is the upper limit
beyond which the court cannot grant reasonable compensation.
43.2. Reasonable compensation will be fixed on well-known
C principles that are applicable to the law of contract, which are to
be found inter alia in Section 73 of the Contract Act.
43.3. Since Section 74 awards reasonable compensation for
damage or loss caused by a breach of contract, damage or loss
caused is a sine qua non for the applicability of the section.
D
43.4. The section applies whether a person is a plaintiff or a
defendant in a suit.
43.5. The sum spoken of may already be paid or be payable in
future.
E 43.6. The expression “whether or not actual damage or loss is
proved to have been caused thereby” means that where it is
possible to prove actual damage or loss, such proof is not dispensed
with. It is only in cases where damage or loss is difficult or
impossible to prove that the liquidated amount named in the
F contract, if a genuine pre-estimate of damage or loss, can be
awarded.”
12. In the present case, clauses 16.2 to 16.4 are relevant, and are
set out as under:
“16.2 (a)FOR DELIVERY OF STORES:
G Should the supplier fail to deliver the store/services or any
consignment thereof within the period prescribed for delivery,
the purchaser shall be entitled to recover 0.5% of the value of
the delayed supply for each week of delay or part thereof for
H
MAHANAGAR TELEPHONE NIGAM LTD. v. 897
TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.]
a period up to 10 (TEN) weeks and thereafter at the rate of A
0.7% of the value of the delayed supply for each week of
delay or part thereof for another TEN weeks of delay. In the
case of package supply where the delayed portion of the supply
materially hampers installation and commissioning of the
systems, L/D charges shall be levied as above on the total
B
value of the concerned package of the Purchase Order.
However, when supply is made within 21 days of QA clearance
in the extended delivery period, the consignee may accept the
stores and in such cases the LD shall be levied upto the date
of QA clearance.
16.2 (b)FOR INSTALLATION & COMMISSIONING C
Should the supplier fail to install and commission the project
within the stipulated time the purchaser shall be entitled to
recover 0.5% of the value of the purchase order for each week
of delay or part thereof for a period upto 10 (TEN) weeks and
thereafter @ 0.7% of the value of purchase order for each D
week of delay or part thereof for another 10 (TEN) weeks of
delay. In cases, where the delay affects installation/
commissioning of part of the project and part of the equipment
is already in commercial use, then in such cases, LD shall be
levied on the affected part of the project. E
16.2 (c).The Liquidated Damages, as per Clause 16.2(a) and
16.2(b) above shall be limited to a maximum of 12%, even in case
the DP extension is given beyond 20 weeks.
16.3. Provisions contained in Clause 16.2(a) shall not be applicable
for durations (periods) which attract L.D. against clause 16.2(b) F
above.
16.4. Quantum of liquidated damages assessed and levied by the
purchaser shall be final and not challengeable by the supplier.”
13. As has been correctly held by the impugned judgment, a
G
maximum of 12% can be levied as liquidated damages under the contract,
which sum would amount to a sum of INR 25 lakh. Since this clause
governs the relations between the parties, obviously, a higher figure,
contractually speaking, cannot be awarded as liquidated damages, which
H
898 SUPREME COURT REPORTS [2019] 4 S.C.R.
A are to be considered as final and not challengeable by the supplier. This
being the case, the appellant can claim only this sum. Anything claimed
above this sum would have to be refunded to the respondent.
14. In this view of the matter, we uphold the impugned judgment
of the TDSAT and dismiss the present appeal.
B
Nidhi Jain Appeal dismissed.
C
D
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.