Created byFuzzy Cloud

Supreme Court of India

MAHANADI COALFIELDS LTD. & ORS.versusM/S. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.

Citation
2016 INSC 920
Decided
27 September 2016
Disposal
Case Partly allowed

Holding

The contractor was bound to complete the extra 30% work within the subsisting contract period and is liable for the penalty and compensation for the financial loss caused by its non‑performance.

Summary

Mahanadi Coalfields Ltd. awarded a contract to Dhansar Engineering for coal extraction, with a clause allowing the quantity to be varied by +/-30% during the contract. The company extended the contract period to July 2004 and, on 11 June 2004, ordered an additional 30% work. The contractor, citing financial loss, sought to close the contract and later withdrew, prompting the company to award the remaining work to a third party at a higher rate and impose a penalty. The High Court quashed the penalty, but the Supreme Court held that the contractor was bound to complete the extra work within the subsisting contract period and was liable for penalty and compensation for the loss incurred by the company. The Court allowed the contractor to make a representation on the penalty but otherwise upheld the company's claim. The appeal was partly allowed, setting aside the High Court's order.

Issues considered

  • The scope and applicability of clause 5 allowing +/-30% variation without a 45‑day notice at the contract's end
  • Whether the contractor was obligated to complete the extra 30% work within the original/extended contract period
  • Validity of the penalty imposed for non‑performance of the increased quantity
  • Whether the contractor should have resorted to the dispute‑settlement mechanism under clause 31 instead of a writ petition
  • Whether the company could recover the financial loss arising from paying a higher rate to a third party

Subjects

contractvariation clausepenaltybreach of contractextension of timefinancial losswork contractnotice period

Judgment

                         [2016] 7 S.C.R. 127


             MAHANADI COALFIELDS LTD. & ORS.                               A
                                   v.
      MIS. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.
                    (Civil Appeal No. 9732of2016)
                       SEPTEMBER 27, 2016
                                                                           B
         [T. S. THAKUR, CJI AND A. M. KHANWILKAR, J.]
       Contract - Work contract - For extraction and transfer of
Coal/Coal Measure Strata by deploying surface 111iners - As per
the terms and conditions of the tender docu111ent as well as the
agreement, the tender quantity could be reduced or increased by
30% on the sa111e ter111s and conditions - Ti111e for co111pletion of      c
contract work was extended at the request of the contractor - During
the subsistence of the contract period appellant-company passed
order for increase of 30% extra quantity - The contractor requested
the company for closure of contract and informed its intention to
withdraw fro111 operation after full contract period due to financial      D
hardship - The. company therefore gave lhe re111aining work to a
third party at higher rate - Co111pany i111posed penalty on the
contractor for non-execution of lhe remaining work - The penalty
was inclusive of the financial loss incurred by the company due to
allocation ofthat work at higher rate - Contractor filed writ petition -
Petition allowed by High Court - On appeal, held: Clause 5 of the          E
agreement empoil'ered lhe company to increase or reduce the quantify
of work by 30%, whilst the contract was subsisting - Therefore,
obligation of contractor to complete the extra work in ter111s of the
contract within the contract period or extended period was
imperative - Contractor co111mitted breach of contractual obligation       F
in not completing the balance work - The contractor is liable to
compensate for the financial loss suffered by the company in
assigning the remaining work at higher rate - However, liberty is
granted to the contractor to make representation to the co111pany
requesting to waive the penally in terms of the contract.
        Partly allowing the appeal, the Court                              G
        HELD: 1. Clause 5 of the Contract cannot be read in
 isolation. The other terms and conditions of the contract must be
 read as a whole. Clause 5 of the agreement dated 261h May 2003
 posits authority in the appellants to reduce or increase the
 tendered quantity by +/- 30%, whilst the contract is subsisting.          H
                                  127
128            SUPREME COURT REPORTS                       [2016) 7 S.C.R.


A     Indisputably, the original contract period was upto IS•h April, 2004.
      At the instance of the respondents, the same stood extended till
      ts•h July 2004. The extra 30% work was allotted to the
      respondents on 11 •h June 2004, before expiry of the extended
      contract period i.e. 151h July 2004. As the contract period was
      extended and that decision was allowed to attain finality, it
B
      inevitably obliged the respondents to fulfill all the contractual
      stipulations under the original agreement including to complete
      the assigned quantity of work - be it original quantity or extra
      quantity - before tS•h July 2004. The fact that they had to suffer
      financial loss due to low contract rate could not be cited as an
c     excuse to extricate from that contractual qbligation. [Para 18]
      J148-F-H; 149-AJ
            2. Failure to comply with the contractual obligation of
      executing the original quantity of work or the extra work, as the
      case may be, must visit the respondents with liability to
D     compensate the appellants in terms of other express clauses of
      the contract to the extent of unfinished work and in particular
      the financial loss suffered by the appellants for getting the same
      work executed through a third agency at a higher rate. The fact
      that the respondents executed 108.47% of work before lS'h July
      2004, could be no justification to relieve them of their obligation
E     to compensate the appellants with suitable amount for the
      unfinished contract work (out of 130%). [Para 19) (149-B-C]
            3. It is not correct to say that the extra quantity of work
      could not have been allotted to them, absent 45 clear days notice
      that too at the fag end of the contract period. It is one thing to say
F     that the contractor should be given suffieient time to complete
      the extra work commensurate with the extra quantity required
      to be executed by him. However, in law, it is not open to contend
      that even though the contract period is still subsisting, the
      principal (appellants) could not have exercised its option to
      increase the quantity of work to the extent permissible under
G
      that clause, to be executed by the contractor within the contract
      period. The principal (appellants) could be asked to exercise
      their option to extend the contract period beyond ts•h July, 2004,
      to enable the respondents to complete the unfinished extra work.
      If such request were to be made by the respondents, there would
H     have been corresponding obligation on the appellants to extend
 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                        129
        ENGINEERING CO. PVT. LTD. & ANR.

the contact period commensurate with the increased quantity of          A
work in terms of clause 5 of the agreement. The respondents,
instead, opted to walk out of the contract for the sole reason that
the contract rate agreed by them was very low and was causing
financial loss to them. That can be no just reason to not fulfill
their contractual obligation. [Para 20] (149-D-G]
                                                                         B
      4. Tile stipulation in clause 5 providing for 45 clear days
notice was not an impediment for the appellants to allot extra
quantity of work upto 30%, whilst the contract period was
subsisting.The said stipulation would come into play only if the
respondents were also called upon to increase the machine
capacity by upto 30% extra "daily" quantity. In the present case,        c
the appellants merely allotted extra 30% quantity without
requiring the respondents to increase the daily quantity. There
is markl'd difference between increasing the extra quantity during
the contract period and that of increasing the extra "daily"
quantity. [Para 21] [149-H; 150-A-B]                                     D
       5. The respondents are not right in contending that the
appellants-Company had no authority to grant extension of time
to complete the enhanced quantity. This is evidenct from the other
contractual terms such as Clause 11.0 - providing for variation in
the scheduled quantity, extent and rate; Clause 13 - time for
completion of contract and more particularly Clause 14.0 - for           E
extension of date of completion. Clause 14.0 (e) was available
and ought to have been invoked by the respondents in this
situation. [Para 22] [150-F-G]
       6. The respor.tlents committed breach of their contractual
obligation, in not completing the balance work out of 130% of            F
work (i.e. 130 - 108.47%). To that extent the respondents became
liable to compensate the appellants including by way of penalty
and in particular towards the financial loss caused to the appellants
due to assigning the unfinished work to a third agency (contractor)
at a higher rate. [Para 23] (151-B-C]
                                                                         G
      7. It is indisputable that financial loss was suffered by the
appellants on account of assigning the unfinished work to a third
agency (contractor) at a higher rate. The fact that no loss of
production was suffered by the appellants, cannot relieve the
respondents of that liability. It is a different matter that the
                                                                         H
130            SUPREME COURT REPORTS                      [2016] 7 S.C.R.



A     respondents were not put to notice before the final decision was
      taken by the appellants to recover the financial loss along with
      penalty. The respondents could have approached the appellants
      for reconsideration of their demand towards penalty, in terms of
      Clause 30.3 of the contract; and persuade the appellants to waive
      the penalty amount to be recovered from them. Even if this appeal
B
      succeeds, the respondents can be granted an opportunity to make
      a representation to the Appellants - company, who in turn can
      deal with the same in accordance with law. [Para 24] (151-F-H;
      152-A-C]
            Mau/a Bux v. Union ~f India (1969) 2 SCC 554 : 1970
c           (1) SCR 928; Gorkha Security Sen1ices " Government
            (NCT of Delhi) & Ors. (2014) 9 SCC 105; Kumari
            Shrilekha Vidyarthi & Ors v. State of U.P. (1991) 1 SCC
            212 : 1990 (1) Suppl. SCR 625 - referred to.
            8. However, that would not absolve the respondents from
D     the financial liability arising due to difference of rate of contract
      and the actual cost incurred by the appellants to complete the
      unfinished work out of 130% of the contract quantity, through a
      third agency at a higher rate. That can be recovered by the
      appellants from the respondents along with interest accrued
      thereon at such rate, as may be permissible in law, even if the
E     representation made by the respondents for recall or modification
      of the penalty amount is pending consideration. [Para 24] [152-
      D-E]
            Popcorn Enterainment vs. City Development
            Corporation, (2007) 9 SCC 593; Harbanslal Sahnia
F           & Anr. vs. Indian Oil Corporation Ltd. & Ors. (20fl3) 2
            SCC 107; Union of India & Ors. vs. Tantia Construction
            Pvt. Ltd. (2011) 5 SCC 697; M P. State Agro Industries
            Development Corpn. & Anr. vs. Jahan Khan (2007) 10
            SCC 88; Whirlpool Corporation vs. Registrar of Trade
            Marks, Mumbai (1998) 8 SCC 1 - referred to.
G                            Case Law Reference
      1970 (1) SCR 928               referred to            Para 24
      (2014) 9 sec 105               referred to            Para24
      1990 (1) Suppl. SCR 625        referred to            Para24
      2007 (3) SCR 17                referred to            Para 25
H     (2003) 2 sec 101               referred to            Para 25
 MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR                              131
           ENGINEERING CO. PVT. LTD.

2011 (5) SCR 397         referred to          Para 25                         A
2007 (9) SCR 715         referred to          Para 25
1998 (2) Suppl. SCR 359  referred to          Para 25
      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 9732
of2016.
      From the Judgment and Order dated 07.11.2012 of the High Court           B
of Orissa, Cuttack in W. P. (C) No. I 093 of 2006.
     Gourab Banerji, Sr. Adv., K. N. Madhusoodhanan KN., T. G.
Narayanan Nair, S. A. Haseeb, Sahil Tagotra, Advs. for the Appellants.
      Rakesh Dwivedi, Sr. Adv., Arunabh Chowdhury, Anupam Lal Das,
Vaibhav Tomar, Ms. Shruti Choudhry, Karma Dorjee, Anirudh Singh,
                                                                               c
Ms. Barna) i Chowdhury, Ad vs. for the Respondent.
      The Judgment of the Court was delivered by
      A. M. KHANWILKAR, J. I. Leave granted.
       2. This appeal challenges the judgment of the Division Bench of         D
the High Court of Orissa at Cuttack dated 71h November 2012 in Writ
Petition (Civil) No. I 093/2006.
       3. Briefly stated, on 2"d December 2002 the appellants issued notice
inviting tenders for the work of extraction and transfer of Coal/Coal
Measure Strata (CMS) by deploying "Surface Miners" on hiring basis             E
at various Open Cast Projects, inter-alia, at Lakhanpur.
The respondents were declared the lowest bidder having quoted
Rs.17/- per cubic meter for the stated.contract. A letter of intent was
issued in favour of the respondents on 4•h April,2003 which was accepted
by the respondents on 141h April, 2003. Work order was issued in favour        F
of the respondents on 23'd April, 2003 and a formal agreement was
executed between the parties on 26'h May 2003. The relevant clauses
of the agreement are clauses 2 to 5 which read as under:
      "2) Time shall be considered as one of the essence of the
      contract and the time for the completion e-f the contract shall         'G
      be counted from 16.04.2003 offrom the date of issue of L.O.L
      to which terms the contractor agreed at the time when his
      tender was accepted and the contract shall be completed by
      15. 04.2004 provided, sufficient face is provided by the
      management.
                                                                               H
132            SUPREME COURT REPORTS                        [2016] 7 S.C.R.


A           3) The ll'ork order has already been issued for a period of
            one year for a quantity of 49,50, 000 Cum. At the rate of
            Rs. 17. 00/Cum. for an amount of Rs. 8,41, 5 0. 000. 00.
            4) The contractor shall re-deploy the Swface Miner in other
            OCPs as per direction of the Company.
B           5) The tendered quantity may be reduced or increased by +/-
            30%. No claim shall lie on the company for such variation in
            guantitv whether increase or decrease. The tenderer must be
            in a position to increase the machine capacity upon 30% extra
            daily quantity within 45 days notice."
c                                                      (emphasis supplied)
            4. As the agreement refers to the terms and conditions of the
      tender document, we may usefully refer to the relevant clauses therein.
            "11.0 VARIATION IN SCHEDULED QUANTITY EXTENT AND
D           RATE
            The quantity given in the "Schedule of Quantity s provisional
            and is meant to indicate the extent of the ll'ork and to provide
            a uniform basis for tendering and any variation either by
            addition or omission shall not vitiate the contract.
E·          The tendered quantitv may be reduced or increased by 30%.
            No claim shall be on the company for such variation in
            quantity whether increase or decrease. Tenderer must be in a
            position to increase the machine capacily ll'ilhin 45 davs notice
            to achieve the extra increased quantity.
F           If the additional altered or substituted ll'ork includes any item
            of work for which no "rate is specified in the contract, "rate"
            for such item shall be determined by the Company
            Headquarters in the following manner:-
            The rate shall be derived from the rate for similar or near
G           similar item of work awarded in the Company, or
            The rate shall be derived from contractors rate claimed for
            such item of work supported by analysis of the rate claimed
            by the contractor. The rate to be determined by the Company
            Headquarters as may be considered reasonable taking into
H           account percentage of profit and overhead not exceeding ten
MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR                       133
 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

   percent or on the basis of market rate. if any prevailing at the   A
   time when work was done.
   However, the Engineer-in-charge shall be at liberty to cancel
   the instruction by giving notice in writing and to arrange to
   carry out the work in such manner as he considers advisable
   under the circumstances. The contractor shall under no              B
   circumstances suspend the work in the plea of non-settlement
   of rates.
   The time ofco111pletion of the originally contracted work shall
   be extended/reduced by the Company in lhe proportion that
   the additional/reduced work (in value) hears to the original        c
   contracted work (in value). as 111ay be assessed and certified
   by the Engineer-in-charge.
   The company through its Engineer-in-charge or his
   representative, on behalf of the company, shall have power
   to 0111it any part of the work for any other reason and the         D
   contractor shall be bound to cany oul the work in accordance
   with the instruction given to Engineer-in-change. No clai111
   for extra chargeslda111ages shall be 111ade by the contractor
   on these grounds.
   /11 the event of any deviation being ordered which in the           E
   opinion of the contractor changes radically the original scope
   and nature of the contract, the contractor shall under no
   circu111stances smpend the work, either original or altered or
   substituted and the dispute/disagreement as to the nature of
   deviation or the rate to be paid therefore shall be resolved
   separately with the company.                                        F
    13. TIME FOR COMPLETION OF CONTRACT
    Time is the essence of the contract.
          The contractual period of work shall be as specified in
    NIT/LOI Agreement. The work shall be deemed to have
    commenced within 60 days of the issue of Letter of Intent at       G
    all the places and should be able to execute I 00% of the
    daily awarded quantity fro111 6/th day fro111 the date of issue
    of LOI.
         Agreement should be executed before the release of/",
    on Ale. bill.                                                      H
134       SUPREME COURT REPORTS                       (2016] 7 S.C.R.


A          For fai/z;re to reach the desired quantity from 61'" day of
      issue of LOI, contractor shall be liable for penalty @ 20% of
      amount for shortfall quantity i.e. (shortfall quantity x awarded
      rate x 20%).
           The contractor must be prepared to work continuously
B     for three shifts a day and all the working days in a yem:
           If the contractor, without valid reason, commits default in
      commencing the execution of the work within 60 days from
      the date of issue of LOI or fails to altain within specified date
      of issue of Letter of Intent, the required quantity to give the
C     ultimate output as per the schedule of quantity, the company
      shall without prejudice to any other right or remedy, be at
      liberty, by giving I 5 days notice in writing to the contractor,
      to forfeit the Earnest Money deposited by him and to terminate
      the contract.
D     .................... ..
      · 14.0 EXTENSION OF DATE OF COMPLETION
          On happening of any event causing delay as stated
      hereunder, the contractor shall apply for time extension to
      the CGMIGM of the Area.
E
      a) Abnormally bad weather
      b) Serous loss or damage by fire
      c) Civil Commotion, strike or lockout affecting execution of
      work
F     d) Non-availability of working force or site which is the
      responsibility of the company to supply.
      e) Any other cause which. at the sole discretion of the
      company. is beyond the control of the contractor.
G     The contractor may request the company in writing for
      extension of time within I 4 days of happening of such event
      ceasing delay stating the period for which extension is
      desired. the company may. considering the eligibility of the
      request. give a fair and reasonable exte11sion of time of
      completion of the work. Such extension shall be commu11icated
H
MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                         135
 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

   to the contractor, in writing, by the company through the            A
   Engineer-in-charge within 1 month of the date of receipt of
   such request.

   30.0 DEFAULT AND PENALTY
   30.1 LOSS OR DAMAGE                                                  B
   Any loss or anv expenditure for damages incurred by company
   will be recoverable from the contractor whether fitlly or partly
   if such expenditure for damages have been caused either
   directly or indirectly due to any negligence or failure on the
   part of the contractor.
                                                                        c
   30.2. SHORTFALL PENALTY IN MECHANICAL EXCAVATION
   AND LOADING
   The average daily quantity of the quarter shall be worked
   out by dividing the mutually agreed quarterly al/oiled quantity
   by the working days of the quarter, ending on 30'" June, 30'"         D
   September, 31" December & 31" March Average daily quantity
   of a quarter must conform to average daily quantity of the
   year contractual period.
   In the event of the Contractors failure to comply with the rate
   of rate of progress as per the agreed progress chart the              E
   contractor shall be liable to pay a penalty on the quantity by
   which the contractor has fallen short from the allotted
   quarterly quantity at the rate of 20% of the awarded rate.
   For failure of produce size coal as per NIT (-JOO 111111 size),
   the contactor shall also be liable for penalty at the rate of
                                                                         F
   20% of the awarded rate for such over size quantity.
   The shortfall penalty will be recovered concurrently from the
   running bill which will be adjusted annually suh}ect to that
   the total penalty is limited to 20% of (Annual Shortfall Quantity
   x Rate).
                                                                         G
   30.3 WA/VAL OF PENALTY
   The company may at its sole discretion waive the pqyment of
   penalty in full or in part in request received from the contractor
   depending the merit o[lhe case if the entire work is completed
   within the date as specified in the contract or within extended       H
136            SUPREME COURT REPORTS                          [2016] 7 S.C.R.


A           period approved without imposing penalty.
            31.0. SETTLEMENT OF DISPUTE
            Except where otherwise provided for in the contract, all
            questions and disputes relating to meaning of the scope,
            specification and instructions herein before mentioned and
B           as to any other question, claim right matter or thing
            whatsoever in any way arising out of or relating to the
            contract, instructions, orders or these conditions or otherwise
            concerning the works or the execution or failure to execute .
            the same whether arising during the progress of the work or
c           after the completion or abandonment thereof, shall be referred
            to the Chairman-Cum-Managing Director of the Company or
            any other person authorized by him.
            It is also a terms of the Contract if the contractor (s) do/does
            not make any demand for any claim(s) in writing 90 days of
D           receiving the intimation from the company that the bill is ready
            for payment or of the date of receiving payment whichever is
            earlier, the claim of the Contractor(s) will be deemed to have
            been waived and absolutely barred and the Company shall
            be released and discharged of all liabilities under the contract
            in respect of these claims. "
E
                                                         (emphasis supplied)
             5. The respondents commenced the work of surface miners at
      Lakhanpur and completed around 70% of the awarded quantity by the
      end ofFebruary 2004. Due to financial problems faced by the respondents
      vi de letter dated l 3m February 2004, they requested the appellants to
F     allow them to close the contract by invoking power to reduce the quantity
      by 30% of awarded quantity, under clause 11 of the general terms and
      conditions of the NIT; and to issue fresh tender for the remaining work.
      The appellants did not accede to the said request and informed the
      respondents vide letter dated l 6'h February 2004, stating that the
G     agreement is for performing the contract upto 100% of awarded value
      and provision of executing extra 30% quantity on the same terms and
      conditions. The respondents requested the appellants vide letter dated
      9'h May 2004 to extend the time frame for completion of the remaining
      contract 1:1pto l 5'h July 2004 as the contract period was only till I 5'h
      April, 2004. The said letter reads thus:
H
MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR                          137
 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

                                                   ANNEXURE-P8           A
          DHANSAR ENGINEERING CO. PVT. LTD.,
                                                                  SITE
   P.O. Dhansar                 P. 0. Jorabaga
   Dhanbad - 828106 (Jharkhand) Via Be/pahar
                                Dist. :Jhars11guda(Orissa)               B
   Ph: 0326 - 30716117074.
   Fax: 0326 303294             Ph.: 066./5 -233222
                                  E-mail- decopl'ci dte. vsnl.net. in


   Ref No. DECO/NIT 27612004                  Date: 09. 05.2004          c
   To
   The chief General Manager
   Lakhanpur Area
   Mahanadi Coalfields Ltd.,                                              D
   (Throu~h proper channel)


   Sub: WORK OF EXTRACTION AND TRANSFER OF COAL/
   COAL MEASURE STRATA BY DEPLOYING SURFACE MINER
   ON HIRING AT LAKHANPUR OCP OF LAKHANPUR AREA
                                                                          E
   (NIT - 276) VIDE WORK ORDER NO. MCLICGM/LKPAI
   SO(M)/SUR. MINER/2003-041001 DATED 23.04.2003.


   Dear Sir,
       Management is fully aware that tender rate of Rs. 171-             F
   per Cum for the work is all ti111e low and wholly zmworkable.
   We are working at this rate at a colossal loss.
        We started the work almost at the approach of monsoon
   on 16. 04.2003 and we could not also speed up progress
   because of transportation restriction between 11.00 A.M &
   4. 00 P.M against heat wave alert and thereafter on-set of             G
   heavy rains consequenting upon bad, water-logged & slippery
   road followed by short supply of rakes. With all these
   operational hazards beyond our control, we could acco111plish
   34. 74 Lakhs Cum upto 31.03.2004.
                                                                          H
138            SUPREME COURT REPORTS                               [20 ! 6] 7 S.C.R.



A               As our financial loss was soaring day by day, we had
            requested for foreclosure of the work after we have completed
            70% of the work but this was not agreed to by GM(TC) vide
            his letter No. 1251 dated 26.03.2004.
                Therefore, being under contractual obligation we had, no
B           other alternative but to apply for extension of time upto
            15.07.2004 and would request you to kindly treat the contract
            as closed with the completion of the above mvarded quantity
            as we are ill-afford to bear further loss.

                 Thanking You,
c                                                        Yours faithft1lly,
                                                                      Sdl-
                                   For Dhansar Engineering Co. Pvt. Ltd."
             6. This request of the respondents was considered by the appellants
      in its 68 1h Meeting of the Board. Extension of three months time was
D     granted while reserving the right to impose penalty. The respondents
      were informed accordingly vide letter dated S1h June 2004. As a result of
      this decision, the contract period was extended until IS 1h July 2004 on
      the same terms and conditions agreed upon. As the contract period was
      subsisting till JSth July2004, the appellants issued an approval order dated
E     11th June 2004 to increase of 30% extra quantity i.e. 14.8 Lakh cubic
      meter at the existing rate of next tender rate or .whichever is lower,
      amounting to Rs. 252.42 Lakh. The respondents by letter dated J Jth
      June 2004, however, reiterated that the contract be treated as closed -
      as they were on the verge of completing the quantity specified in the
      contract by I S1h June 2004. The said letter reads thus:
F                                                   "ANNEXURE-P9
                         DHANSAR ENGINEERING CO. PVT. LTD.,
                                                             SITE

             P. 0. Dhansar                        P. 0. Jorabaga
             Dhanbad - 828106 (Jharkhand)        Via Belpahar
G            Ph: 0326 - 30716117074.             Dist.: Jharsuguda (Orissa)
             Fax: 0326 303294                    Ph.: 06645 -233222
                                                 E-mail - decopl0 dte. vsnl. net. in

             Ref No. DECO/NIT 27612004                    Dale: 11.06.2004

H
MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                                    139
 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

      To •                                                                         A
      The chief General Manager
      Lakhanpur Area
      Mahanadi Coalfields Ltd.,

      Sub: NIT NO. 276-EXTRACT/ON AND TRANSFER OF COAL/COAL
      MEASURE STRATA BY DEPLOYING SURFACE MINER ON HR/NG                           B
      BASIS AT LAKHANPUR OCP OF MCL

      Dear Sir,

           We would like to inform you that the order quantity of 49.50 lakh
      Cum is in the verge of completion, and is expected that this quantity         C
      will be fully completed by 15.06.2004.

           In this connection kindly refer to our letter No. DECO/NIT -2761
      2004 dated 09. 05.2004 under which we had requested your good-self
      to treat the contract as closed with the completion of the quantity of
      49.50 lakh Cum. In reiterating our request we would inform you that           D
      we may be forced to stop the machine as it is giving trouble and we are
      not able to repair the machine for dire scarcity ofjimd
            Thanking You,
                                                               Yours faithfully,
                                                                           Sd/-
                                      For Dhansar Engineering Co. Pvt. Ltd.         E

      Copy to:    I) The Director (Technical) MCL, Bur/a,
                  2) The General Manager, Lakhanpur Area. "


        7. The respondents by another letter dated 61h July 2004 seeking            F
closure of contract due to financial hardship, stated that they were
withdrawing their operations. The appellants, however, by letter dated
7•h July 2004 called upon the respondents to continue with the remaining
work assigned under the contract which was still subsisting; and also
noted that the respondents had by then completed only I 05% of the
contract work out of 130%. The said communication reads thus:                       G
                                                   "ANNEXURE -P12
        "UNDER JURISDICTION OF SAMBALPUR COURT ONLY"
                    MAHANADI COALFIELDS LIMITED
                (A SUBSDIARY OF COAL INDIA LIMITED)
                                                                                    H
140        SUPREME COURT REPORTS                           [2016) 7 S.C.R.


A     Corporate Office              Office o.fthe Chief General Manager

      M.C.l. Complex             LAKHANPVRAREA
      Jagriti Vihar              P. 0. bandhabahal - Via: Belpahar
      Bur/a - 768018             Dist.: Jharsuguda, Pin 768217
      Dist: Sambalpur (Orissa) phone: 33202, STD CODE: 06645
8
      Ref No. MCLICGMILKPAISO(M)/932                  Dale: 07.07.2004

      To

      Mis Dhansar Engineering Co. pvt. ltd.
C     Site Office: P. 0. Jorabaga, Via - Belpahar.
      Dist: Jharsuguda (Orissa)
      Pin: 768217.

      Ref {I) Work order No. MCLICGMLILKPAISOM{M)!Sur Miner/2003-
         041001 dated 23. 04.2003 for Exlraction am/Trans.fer ofCoal/Coal
D        measure strata by deploying 'Su~(ace Miners" on hiring basis at
         lakhanpur OCP (NIT-276).

      Sub: Contract of Swface Miner work at lakhnapur OCP (under NIT
          No. 276)

E     Dear Sir.

           Kindly re.fer to your letter No. DECO/NJT-27612004 dated 6.07.2004
           on the above subject.

           This is to bring to your notice that as per clause No.2 of the work
           order forming part of the agreemenl the tendered quantity can be
F
           increased by 30% and no claim shall lie on the company for such
           variation till date only 105% (approx.) of the awarded quantity
           has been executed by you. There is no communication fro111 MCL-
           HQ for ftnali:rntion of new contract for the above work till date.

           Jn such condition you are requested to continue your operation of
G
           surface 111iner at lakhanpur OCP till co111pletion of 30% extra
           quantity. Withdrawal of operations of Swface Miner at this stage
           will seriously affect dispatch of coal to our Pit head customer
           {OPGC) and other linkage customers earning a bad name to the
           company.
           Thanking You,
H
 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                                141
  ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

                                                            Yours faithfully,   A
                                                                        SD/-
                                                     GENERAL MANAGER
                                                      LAKHANPUR AREA

      Copy to:
      The Chairman-cum-Managing Directo1; MCL Buria                              B
      The Director (T), MCL, Bur/a
      The General Manager (TC), MCL HQ, Bur/a
      The Slaff Officer (Mining) LKPA"


       8. The respondents, however, renewed their request to the                 c
appcll.1;11' to allow them to close the contract vide letters dated Slh July
2004 amt 121" July 2004. The respondents finally wrote to the appellants
on 15 1" July 2004 which reads thus:
                                                       "ANNEXURE-Pl5

                    DHANSAR ENGINEERING CO. PVT. LTD.,                           D
                                                                        SITE

       P.O. Dhansar                                   P.O. Jorabaga
       Dhanbad- 828106 (Jharkhand)                    Via Belpahar
       Ph: 0326-307161/7074.                Dist.: Jharsuguda (Orissa)
       Fax: 0326 303294                     Ph.: 06645 -233222                   E
                                            E-mail-decopl@dte.vsnl.net.in

       Ref: No. DECO/NIT 276/2004
       Date: 15.07.2004

       To                                                                        F

       The General Manager,
       Lakhanpur Area, MCL,

       Sub: Closing Down of work of Surface Miner at lakhanpur OCP under
           NITNo.276                                                             G

       Dear Sir,

          A copy ofour letter No. DECO/NIT/2004 dated 12.07.2004 addressed
       to CMD MCL Burla with copies to D(T) and GM(TC), MCL HQ is
       enclosed herewith for your information.                                   H
142            SUPREME COURT REPORTS                              [2016] 7 S.C.R.


A                  As notified this is to inform you that we are stopping the work
            and withdrawing from operations at Lakhanpur OCP with effect from
            16.07.2004 (FN). It is not out of place to mention that we had been
            expressing out intention to abandon execution after completing I 00% of
            the work on account ofour un-economical plight out has been continuing
            wit the execution to cooperate with the management to arrange next
B           recourse, so as to ensure that the production schedule of Lakhanpur
            OCP does not suffer any set back.                ·
                   We could not however elicit any communication to our letters or
            any sympathetic decision from the·management. In the meanwhile the
            contract period also expired by 15.07 .2004.
                   In view of the above situation we have no other alternative but to
c           withdraw from operation after working the full period of the contract.
            You are therefore requested to kindly take up final measurement as on
            15.07.2004 and finalise the contract.
                   Thanking you and assuring you of our best cooperation to all
            time come.
D
                                                                    Yours faithfully,


                                                                              Sci/-
                                             For Dhansar Engineering Co. Pvt. Ltd.
E
            Copy to:
            I. The CMD, MCL, Burla Fax No. 0663 -2432066/2542366
            2. The D(T), MCL, Burla, Fax No. 0663-2542509
            3. TheGM (TC),MCL, Burla, Fax No. 0663-2542629."

F
             9. As the respondents had already informed the appellants of
      their intention to withdraw from operation after the full contract period,
      a fresh tender process was commenced by the appellants which
      culminated with a letterofintent in favourofthird party (Sainik Mining
      and Allied Services) but at a higher rate ofRs.31.50 per cubic meter.
G
              I 0. The bills submitted by the respondents for the work executed
      under the contract dated 26'h May 2003 were considered by the Board
      of the appellants in its 72"d meeting. The decision taken in the said meeting
      was communicated to the .respondents by letter dated 81h December
      2014 which reads thus:
H
MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR                                143
 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

   "ANNEXURE R/9                                                               A

   MAHANADI COALFIELDS LIMITED
   (A subsidiary of Coal India Limited)
   P.O. -Jagruti Vihar, Burla, Distt. Sambalpur-768020 (Orissa)
   Gram: SAMBCOAL,:           Fax: (0663)2542770
   Phone: PBX:- (0663) 2542461 to 2542469                                      B

   Ref.1\o. MCUSBP/GM(TC)/200411047               Dt. 08.12.2004

   To,
          General Manager,
          Lakhanpur Area                                                       c
   Dear Sir,
           Enclosed herewith please find a copy of Extract from the Draft
   Minutes of the 72"• meeting of the Board of Directors of MCL held on
   27 1h November, 2004 at Kolkata in respect of imposing penalty by way of
   forfeiture of Earnest Money Deposit of Rs. 20.00 lakhs to Mis. Dhansar      D
   Engineering (P) Ltd., for non-performance of 130% of the total contracted
   quantity under NIT - 276. The relevant extract is appended below:-
           " The Board deliberated on the subject in detail and in
   consideration of the facts and circumstances highlighted in the agenda
   note and in recognition of the clarification offered during deliberation,
   decided that penalty as proposed in the agenda note in terms of the          E
   pr_ovisions of the contract be imposed on Mis Dhansar Engineering pvt.
   Ltd. For non-performance of 130% of the total contracted quantity under
   NIT-276.
                Proposed in the Agenda Note
            Clause No. 16- (Forfeiture of Earnest Money)
                The contractor is liable for forfeiture Money Deposit under     F
   Clause No. l6(a) and l 6(d) which reads as under:-
   [ 6(2) withdraws his offer during the validity period of offer.
   I 6(a) fails to execute the order as per terms and conditions thereof.
   In the present case the EMD is Rs. 20.00 lakhs.
   Clause No. 30.2 (Shortfall penalty in Mechanical excavation and loading)
                130% of Contract Quantity-63,70,000.00 Cu.m.                   G
                Final quantity executed-53,49,437.55 Cu.m.
                Balance quantity to be executed- 10,20,562.45 Cu.m.
                Working rate                -Rs. 17.00 perCu.m.
                20% of working rate         Rs. 3.40 per Cu.m.
                Payable penalty for not executing
                Upto 130% quantity          Rs.34,69,91 l.OO
                                                                               H
144            SUPREME COURT REPORTS                            [2016] 7 S.C.R.


A                   These penalties may be imposed individually or collectively
            depending on the decision taken by the Management. The imposition
            of penalty may be decided on the background that the contractor working
            at a very low rate has executed I 08.4 7% in spite of incurring heavy
            losses and withdrew only when the new contract was finished ensuring
            that there is no loss of production.
B
                                                                  Yours faithfully
                                                                     Sd/- lllegible
                                                            General Manager (TC)
            Encl : As above"

c
             11. The Board of the appellants in its 78 111 Meeting decided to
      impose penalty for non-execution of the balance contract work by the
      respondents and including the financial loss incurred by the appellants
      due to allocation of that work to third party at higher rate. Jn terms of
      that decision, an approval order for recovery of penalty was issued by
D     the appellants on J'd November 2005 which reads thus:
                                                                "ANNEXURE -19

            MAHANADI COALFIELDS LIMITED
            (A subsidiwy of Coal India limited)
            P. 0. - Jagriti Vihar
E           Bur/a - 768018
            Distt: Sambalpur-768020 (Orissa)
            Gram: SAMBCOAL,:           Fax: (0663) 2542770
            Phone: PBX:- 2542461to2542470

            Ref No. MCLISBPIGM(TC)/200511100               Date: 03.11.2005
F
                                     APPROVAL ORDER

            Sub: Imposition ofpenalty to Mis Dhansar Engineering Company Pvt.
            Ltd., under NIT-276 (DI; 01.12.2002) for the work of "Extraction and
            Transfer ofCoal/Coal Measure Strata by deploying "Surface Miners"
G           on hiring basis at lakhanpur OCP, Lakhanpur Area.

                   On recommendation of the commil/ee to examine the issue on
            imposition ofpenalty under NIT -276 dated 02.12.2002 to Mis Dhansar
            Engineering Company Pvt. ltd.. for the work of "Extraction and
            Transfer of Coal/Coal Measure Strata by deploying "Swface Miners"
H           on hiring basis at Lakhanpur OCP, lakhanpur Area, the same has
 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                                 145
  ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

      been pgreed by D(T) !D(F)ID(P)/CMDIMCl. The MCl Board in its               A
      78'• meeting held on 27. 10.2005 under item No. 78.C/20 has been
      pleased to approve the proposal of imposition of penalty in terms of
      provision of the contract to Mis. Dhansar Engineering Company Pvt.
      ltd. '73y non performance of 130% of total contacted under NIT-276
      (dt: 02. 12.2002) for an amount of Rs. 1,57,40,655.22 (Rupees One
      Crore Fifty-seven lakh Forty Thousand Six Hundred Fifty-five and           B
      paisa Twenty-two only) under the Clause - 30. 1 (loss or damage) of
      the agreement.
                                               Sd/- General Manager (TC)
      Distribution:
          1. GM lakhanpur Area
          2. CGM(F) MCl, HQ                                                      c
          3. TS to CMD, MCl
          4. TS to D(T), MCl
          5. Secy. To D(F), MCl
          6. Sanction Order file"

                                                                                 D
      12.Aggrieved, the respondents filed Writ Petition under Article
226 of the Constitution oflndia and prayed as follows:
                                       "PRAYER
      In the circumstances, it is therefore prayed that Your lordships be
      graciously pleased to issue a Rule NISI in the nature of certiorari
      calling upon the Opposite Parties, to show cause as why the impugned        E
      letter dated 08.12.2004 vide Annexure-22 issued by the General
      Manager (TC), Mahanadi Coal Fields limited, Opposite party No.2
      imposing penalty shall not be quashed and if the Opposite Parties fail
      to show cause or show insufficient cause make the said Rule absolute.
                                         AND
      Issue a Writ in the nature of mandamus directing the Opposite parties       F
      to pay a sum of Rs. 79,01,434.60 to the Petitioner No.I Company,
      which has been illegally withholding by the Opposite parties.
                                         AND
              Issue a Writ in the· nature of Mandamus directing the Opposite
      Parties to pay interest@ 18% per annum as the Opposite Parties have
      illegally withhold the outstanding dues of Rs. 79,01,434.60 of              G
      Petitioner No. I Company since 15. 07.2004.
                                         A/VD
              fssue such other Writ/Writs, Order/Orders, Direction/Directions
      as this Hon 'ble Court may deem it fit and proper.
              And/or this act ofKindness the Petitioner shall as_in duty bound
      ever pray. "                                                                H
146            . SUPREME COURT REPORTS                         [2016] 7 S.C.R .



A            l 3. The Writ Petition was opposed by the appellants by filing reply
      affidavit. The appellants raised preliminary objection about the
      maintainability of the Writ Petition. On merits, the appellants asserted
      that the demand raised against the respondents was in accord with the
      terms and conditions of the contract and ifthe respondents were aggrieved
      by the same they were free to resort to the procedure for settlement
B
      under clause 31 of the agreement. The Division Bench of the High Court,
      however, allowed the Writ Petition preferred by the respondents on the
      finding that it was not permissible for the appellants to allot extra work
      to the respondents at the fag end of the contract period in terms of
      clause 5 of the contract which envisaged giving 45 clear days notice for
c     variation of the quantity under the contract. That notice was given to the
      respondents only on J J<h June 2004 even though the extended contract
      period was to expire on J S<h July 2004. The Court held that, surprisingly
      after extending the contract period on S<h June 2004, within six days on
      11th June 2004 the appellants decided to enhance the contract quantity
      by 30%. That was not a bonafide act and was unacceptable. The Court
D
      also held that the appellants had not offered any explanation as to in
      what circumstances decision to impose penalty was taken by the Board
      of Directors. The Court further noted that the respondents had executed
      the contract upto I 08.4 7% at a very low rate, and incurred heavy losses
      in that regard. Further, a new contract for Lakhanpur OCP was already
E     awarded and there was no loss of production caused to the appellants.
      On these basis, the Division Bench allowed the Writ Petition in the
      following terms:
             "16. Accordingly, the letter dated 8.12.2004 of the General
            Manager (T.C) Mahanadi Coalfields Limited under Annexure-
F           22 proposing to levy shortfall penalty as well a~. its Approval
            Order dated 03.11.2005 under Annexure-A to the counter
            affidavit are hereby quashed. . The outstanding dues payable
            to the petitioner be released in its favour within the period of
            thirty days along with simple interest @ 8% per annum to be
            computed from the date of conclusion of contract, i.e. from
G           16. 7.2004. The bank guarantee furnished by the petitioners,
            pursuant to the direction of this Court dated 28. 7.2009 are
            hereby directed to be cancelled and consequently, directed
            that the same be returned to the petitioners forthwith.
                The writ petition is allowed with the aforesaid terms. No
H           Costs."
 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                                  147
  ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

       14.Aggrieved, the appellants have filed the present appeal. This           A
Court passed an interim order on I 21h April, 2013, directirig to maintain
status quo as it existed on that date until further orders.
       15. According to the appellants the High Court has committed
manifest error in entertaining the Writ Petition. Firstly, in respect of a
purely contractual matter and moreso when efficacious remedy under                B
clause 31 of the contract was available to the respondents for redressal
of their grievance. Secondly, on merits the High Court has misconstrued
and misapplied the contractual terms and in particular clause 5 ofthe
contract. However, ifthe terms and conditions of the contract are read
as a whole, it leaves no manner of doubt that the appellants had the
discretion to extend the original contract period; and having done so at          c
the request of the respondents, the respondents were bound by the terms
of the contract till 15 1h July 2004. Further, before that date at any point of
time, :: was open to the appellants to reduce or increase the contract
quantity upto 30%. The sole plea of the respondents for their inability to
perform the contract was founded on financial difficulty and sufferance           D
offurther loss due to low contract rate. That can be no consideration for
walking out of the contract. Moreso, after the extra quantity was allocated
the respondents could have asked for further time for completing the
extra work, if they were not in a position to complete the same within
the contract period. That request could have been considered by the
appellants appropriately. The respondents did not do so. Instead, they             E
insisted to withdraw from operation merely because the rate of contract
was not affordable to them. Resultantly, the appellants had to allot the
extra quantity of unfinished work by the respondents, to third party at a
higher rate. The fact that the appellants did not suffer any loss of
production, it does not follow that no financial loss was suffered by the          F
appellants due to higher rate paid for the unfinished extra work. The
appellants were, therefore, justified in recovering the difference of rate
in respect of unfinished extra work and penalty therefor. That was a
legitimate demand under the terms and conditions of the contract between
the parties.
                                                                                   G
       16. The respondents, on the other hand, contend that it was unfair
on the part of the appellants not to allow the respondents to close the
contract as per the original contract and within the extended contract
period i.e. upto I 51h July 2004. Further, the respondents cannot be made
liable for the unfinished extra quantity of work as that was allotted only
                                                                                   H
148             SUPREME COURT REPORTS                              [2016] 7 S.C.R.



A     on 11th June 2004, leaving very Iittle time for the respondents to complete
      the same for which the appellants should blame themseh . . ,. According
      to the respondents, the High Court was right in concluding that clause 5
      of the agreement did not permit the appella1its to allot an extra quantity
      of work to the extent of 30% at the fag end of the extended contract
      period, absent 45 clear days notice mandated therein. Further, the High
B
      Court has passed an equitable order also keeping in mind that the
      respondents had already executed 108.4 7% of the contract work by
      suffering heavy losses, which fact is substantiated from the execution
      of new contract at the rate of Rs.31.50 per cubic meter as against the
      rate of Rs.17 /- per cubic meter payable to the respondents. It is also
c     contended thatthe demand for penalty amount is unilateral and without
      any just cause. The same is illegal. Hence, contends the learned counsel,
      the appeal be dismissed.
             17. Having heard the learned counsel for the parties at some length,
      we find force in the plea of the appellants. The challenge in the Writ
D     Petition filed by the respondents was limited to the letter dated 8th
      December 2004, issued by the General Manager of the appellants. The
      respondents had not challenged the extension Of contract period till 15th
      July 2004 vide letter dated 5th June 2004, the decision of the appellants
      to allot an extra quantity of30% work and much less the decision of the
      Board to impose penalty taken on 27th October, 2005 and communicated
E     to the respondents vide Approval Order dated 3rd November 2005. The
      High Court, however, has not only set aside the letter dated 8th December
      2004 but also the Approval Order dated 3rd November 2005.
             18. For doing so, the High Court has taken support from clause 5
      of the Contract. That clause cannot be read in isolation. The other terms
F     and conditions of the contract must be read as a whole. Clause 5 of the
      agreement dated 26th May 2003 posits authority in the appellants to reduce
      or increase the t.endered quantity by +/- 30%, whilst the contract is
      subsisting. Indisputably, the original contract period was upto J 5th April,
      2004. At the instance of these respondents, the same stood extended till
G     J5th July 2004. The extra 30% work was allotted to the respondents on
      11th June 2004, before expiry of the extended contract period i.e. 15th
      July 2004. As the contract period was extended and that decision was
      allowed to attain finality, it inevitably obliged the respondents to fulfill all
      the contractual stipulations under the original agreement including to
      complete the assigned quantity of work- be it original quantity or extra
H
 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                                  149
  ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

quantity- before l 5'h July 2004. The fact that they had to suffer financial      A
loss due to low contract rate could not be cited as an excuse to extricate
from that contractual obligation.
        19. Failure to comply with the contractual obligation of executing
the original quantity of work or the extra work, as the case may be, must
visit the respondents with liability to compensate the appellants in terms        B
of other express clauses of the contract to the extent of unfinished work
and in particular the financial loss suffered by the appellants for getting
the same work executed through a third agency at a higher rate. The
fact that the respondents executed I08.4 7% of work before l 5'h July
2004, could be no justification to relieve them of their obligation to
compensate the appellants with suitable amount for the unfinished contract        c
work (out of 130%).
       20. Presumably to get over this position, the respondents relying
on clause 5 of the agreement would contend that the extra quantity of
work could not be allotted to them, absent 45 clear days notice that too
at the fag end of the contract period. This argument, in our opinion, is a         D
complete misreading of the said clause. It is one thing to say that the
contractor should be given sufficient time to complete the extra work
commensurate with the extra quantity required to•be executed by him.
However, in law, it is not open to contend that even though the contract
period is still subsisting, the principal (appellants) could not have exercised    E
its option to increase the quantity of work to the extent permissible under
that clause, to be executed by the contractor within the contract period.
The principal (appellants) could be asked to exercise their option to extend
the contract period beyond J5•h July, 2004, to enable the respondents to
complete the unfinished extra work. If such request were to be made by
the respondents, there would have been corresponding obligation oi~ the            F
appellants to extend the contact period commensurate with the increased
quantity of work in terms of clause 5 of the agreement. The respondents,
instead, opted to walk out of the contract for the sole reason that the
contract rate agreed by them was very low and was causing financial
loss to them. That can be no just reason to not fulfill their contractual          G
obligation.
       21. Relying on the third sentence (last sentence) in clause 5, it
was contended that the employer could not have increased the tendered
quantity in absence of 45 clear days notice. We agree with the appellants
that the said stipulation would come into play only if the respondents
                                                                                   H
150             SUPREME COURT REPORTS                            [2016) 7 S.C.R.


A     were also called upon to increase the machine capacity by upto 30%
      extra "daily" quantity. In the present case, the appellants merely allotted
      extra 30% quantity without requiring the respondents to increase the
      daily quantity. There is marked difference between increasing the extra
      quantity during the contract period and that of increasing the extra "daily"
      quantity. In the case of latter, the contractor would be required to step
B
      up the machine capacity for which giving of 45 clear days notice to him
      is necessary. Suffice it to observe that the stipulation in the third sentence
      of clause 5 providing for 45 clear days notice was not an impediment for
      the appellants to allot extra quantity of work upto 30%, whi 1st the contract
      period was subsisting.
c             22. The respondents had then relied on the notings of the Project
      Officer dated 26'h January 2005 to contend that assigning of extra work
      to the respondents at the fag end of the contract period was doubted
      even by the said officer. The observations of the Project Officer cannot
      be the basis to construe the scope of Clause 5 of the contract. Besides,
D     it was only an inter-depa11mental communication which was duly
      considered at different level in the office of the appellants, but finally it
      is the decision of the Board of Directors of the appellants that must
      prevail. As a matter of fact, Clause 5 of the agreement empowers the
      appellants to increase or reduce the quantity of work upto permissible
      limit whilst the contract was subsisting. That power having been
E     exercised, the obligation of the contractor to complete the extra.work in
      terms of the subject contract within the contract period or extended
      contract period was imperative. The respondents are not right in
      contending that the appellants-Company had no authority to grant
      extension of time to complete the enhanced quantity. This contention
F     deserves to be stated to be rejected, keeping in mind the other contractual
      terms such as Clause 11.0 - providing for variation in the scheduled
      quantity, extent and rate; Clause 13 - time for completion of contract
      and more particularly Clause 14.0- for extension of date of completion.
      Clause 14.0 (e) was available and ought to have been invoked by the
      respondents in this situation. It postulates that for any other cause not
G     specifically provided in sub-clauses (a) to (d) of the same Clause, at the
      so.le discretion of the appellants, the date ofcompletion could be extended,
      ifit was found to be necessary because of situation beyond the control
      of the contractor. That clause could be invoked for the situation in which
      the respondents were placed due to extra work allocated to them at the
H     fag end of the coritract (extended) period.
 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                                  151
  ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

        23. ln our opinion, clause 5 did not prohibitthe principal (appellants)   A
to allot upto extra 30% quantity of work, for want of 45 clear days of
subsisting contract period. Whereas, that option could be exercised by
the appellants at any time until the contract period was subsisting, which
in this case was until J5•h July 2004. In the present case, such notice
regarding increase of work upto 30% permissible under clause 5 of the
                                                                                   B
agreement, was given on 11 •h June 2004. On this finding, it must follow
that the respondents committed breach of their contractual obligation, in
not completing the balance work out of 130% of work (i.e. 130 -
 I 08.4 7%). To that extent the respondents became liable to compensate
the appellants including by way of penalty and in particular towards the
financial loss caused to the appellants due to assigning the unfinished            c
work to a third agency (contractor) at a higher rate. The amount
demanded by the appellants includes the difference of contractual rate
 and the actual loss suffered by the appellants for completing the unfinished
 work through a third agency (contractor) at a higher rate, as is noticed
 from the communication dated 8'11 December 2004 sent to the
                                                                                   D
 respondents.
        24. The respondents, would then contend that, the appellants
without giving any opportunity to the respondents unilaterally imposed
penalty and despite the noting of the General Managerthat there was no
loss of production to the appellants. Similarly, a doubt was expressed by
                                                                                   E
the Project Officer regarding giving extra work to the respondents at
the fag end of the contract period. The respondents have relied on the
decision of this Court in Mau/a Bux vs. U11io11 of lntlia 1, in which it
has been held that "where a sum is named in the contract in the nature
of a penalty, where loss in terms of money can be determined. th1.: party
claiming compensation must prove the loss suffered by it." It is, however,         F
indisputable that financial loss was suffered by the appellants on account
ofassigning the unfinished work to a third agency (contractor) at a higher
rate. In that, the contract rate for the same work to be done by the
respondents would have been at Rs. 17/- per cubic meter, which the
appellants were required to get it executed at the rate of Rs. 31.50 per
cubic meter through a third agency. The fact that no loss of production            G
was suffered by the appellants cannot relieve the respondents of that
 liability. It is a different matter that the respondents were not put to
 notice before the final decision was taken by the appellants to recover
 the financial loss along with penalty. The respondents could have
1
    (1969) 2 sec 554                                                               H
152             SUPREME COURT REPORTS                          [2016] 7 S.C.R.



A     approached the appellants for reconsideration of their demand towards
      penalty, in terms of Clause 30.3 of the contract; and persuade the
      appellants to waive the penalty amount to be recovered from them. The
      respondents, however, chose to straightway approach the High Court
      by way of Writ Petition. Notably, the High Court has not set aside the
      penalty amount as such, butthe entire demand being impermissible. Since
B
      we have reversed the findings and conclusion of the High Court and
      even if this appeal succeeds, the respondents can be granted an
      opportunity to make a representation to the Appel Iants - company, who
      in turn can deal with the same in accordance with law. If the appellants
      accept the claim of the respondents about the unjustness of penalty or
c     quantum thereof, they would be free to withdraw or modify their claim
      for recovery of penalty amount, if so advised. In the event, the appellants
      reject the representation, they will be free to recover the amount as
      demanded towards penalty along with interest accrued thereon, as may
      be permissible in law. However, that would not absolve the respondents
      from the financial liability arising due to difference of rate of contract
D
      and the actual cost incurred by the appellants to complete the unfinished
      work out of 130% of the contract quantity, through a third agency at a
      higher rate. That can be recovered by the appellants from the respondents
      along with interest accrued thereon at such rate, as may be permissible
      in law, even ifthe representation made by the respondents for recall or
E     modification ofthe penalty amount is pending consideration. Considering
      the above, it is not necessary for us to burden this judgment with the
      contention of the respondents that the penalty imposed without any notice
      or hearing to the respondents is vitiated; as also the decisions relied in
      support of that contention in the case of Gorklta Security Services vs.
      Govemment (NCT ofDel/ii) & Ors. 1 and Kunwri Slirileklia Vidyartlli
F     & Ors vs. State of U.P. 3
             25. Similarly, it is not necessary for us to burden this judgment
      with the decisions relied on by the respondents, to contend that existence
      of alternative remedy is no bar to entertain a Writ Petition under Article
      226 of the Constitution of India, as held in the cases of Popcorn
G     Enterainment vs. City Development Corporation 4, Harbanslal
      Sallnia & Anr. vs. Indian Oil Corporation Ltd. & Ors.-', Union of
      2
        (2014) 9 sec 105
      3
       (1991) I SCC212
      ' (2007) 9 sec 593
H     ' (2003) 2 sec 101
 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR                                153
  ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.]

India & Ors. vs. Tantia Construction Pvt. Ltd.•, M.P. State Agro                A
Industries Developmen_t Corpn. & Anr. Vs. Jalwn Kllan 7 and
Whirlpool Corporation vs. Registrar of Trade Marks, M umbai8• For,
we have already examined the merits of the controversy and more so
granted liberty to the respondents to make representation to the appellants
on the question ofjustness of the demand towards penalty or the quantum
                                                                                B
thereof. It will be open to the respondents to pursue remedy in that
behalf, as may be permissible in law. We are not expressing any opinion
one way or the other on the issue of penalty amount. All questions in
that behalf are left open.
       26. Accordingly, we partly allow this appeal. The judgment of the
Division Bench dated 7'h November 2012 is set aside. The reliefs claimed        c
by the respondents in the Writ Petition are disposed of in the above
terms.
       27. The appeal is partly allowed in the above terms with no order
as to costs.
                                                                                D
Kalpana K. Tripathy                                    Appeal partly allowed.




' (2011)5sec 697
         osec 88
' (2007) 1
         sec 1
• (1998) 8


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "contract"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.