MAA BINDA EXPRESS CARRIER AND ANR.versusNORTHEAST FRONTIER RAILWAY AND ORS.
- Citation
- 2013 INSC 796
- Decided
- 29 November 2013
- Disposal
- Dismissed
- Bench
- T S THAKUR
Holding
A tender is merely an offer and the State may lawfully cancel it if the cancellation is not arbitrary, mala fide, or against public interest, so the appeal was dismissed.
Summary
Maa Binda Express Carrier submitted the highest bid for a three‑year lease of parcel‑van space on a railway train, but the Northeast Frontier Railway cancelled the tender citing technical and administrative deficiencies, including the absence of terms, conditions and a penalty clause. The carrier challenged the cancellation before the High Court, which initially set aside the cancellation, but the railway appealed and the Division Bench upheld the cancellation, holding that a tender is merely an offer and does not confer a vested right. On appeal, the Supreme Court examined whether the railway’s decision was arbitrary, mala fide, or violative of Article 14 and the scope of judicial review in government procurement. The Court reiterated that the State must act fairly and reasonably, but it may reject or cancel a tender provided the action is not arbitrary, unreasonable, or against public interest. Finding no mala fide intent and noting substantial financial loss that would have resulted from awarding the contract at the low bid, the Court dismissed the appeal, affirming the railway’s right to cancel the tender.
Issues considered
- Whether a tender submitted in response to a government notice creates a vested right to be awarded the contract.
- Whether the cancellation of the tender process by the railway was arbitrary, mala fide, or violative of Article 14 of the Constitution.
- What is the scope of judicial review in government tendering and contract award matters.
- Whether the deficiencies in the tender documents (absence of terms, conditions and penalty clause) justify cancellation of the tender.
Subjects
Judgment
[2013] 12 S.C.R. 529
MAA BINDA EXPRESS CARRIER AND ANR. A
v.
NORTHEAST FRONTIER RAILWAY AND ORS.
(Civil Appeal No. 10751 of 2013)
NOVEMBER 29, 2013
B
rr.s. THAKUR AND VIKRAMAJIT SEN, JJ.]
Government Contracts:
Tenders - Cancellation of tender process for deficiencies c
therein - Held: Submission of a tender in response to a notice
inviting such tenders is no more than making an offer which
the State or its agencies are under no obligation to accept -
Bidders- participating in the tender process cannot, therefore,
insist that their tenders should be accepted simply because 0
a given tender is the highest or lowest depending upon
whether the contract is for sale of public property or for
execution of works on behalf of Government - All that
participating bidders are entitled to is a fair, equal and non-
discriminatory treatment in the matter of evaluation of their E
tenders - To that extent the tenderer has an enforceable
right - In the instant case, there were serious deficiencies in
the entire tender process, which would have resulted in
substantial financial Joss to Railw9ys and 'it'was neitl:ler in
public interest nor necessitated by any legal compulsion ~
Therefore, the decision to cancel the tender process was in F
no way discriminatory or ma/a fide - It did not violate any
fundamental right of the appellant nor could the action of
respondent be termed unreasonable so as to warrant any
interference from the Court - Costs.
G
Tenders - ·Terms of - Judicial review of - Held: Power
exercised by the Government and its instrumentalities in
regard to allotment of contract is subject to judicial review at
the instance of an aggrieved party - Award of a contract is
529 H
530 SUPREME COURT REPORTS [2013) 12 S.C.R.
A essentially a commercial transaction which must be
determined on the basis of consideration that are relevant to
such commercial decision - This implies that terms subject
to which tenders are invited are not open to the judicial
scrutiny unless it is found that the same have been tailor
B made to benefit any particular tenderer or class of tender~rs
- Judicial review.
In response to a notice dated 12.7.2011 inviting
tenders for the grant of a three year lease of 23 tonnes
C of space in VPH (Parcel Van) on train No.15960/15959
Kamrup Express, the bid of the appellant for a sum of
Rs.1 ,46,872/- per trip for the proposed lease was found
to be the highest. However, the tender process was
discharged by the railway administration on account of
technical and administrative reasons. The communication
D dated 6.9.2011, in that regard sent to the appellant, was
assailed in a writ petition before the High Court. The
Single Judge allowed the writ petition with a direction that
so long as the appellant undertook to accept the penalty
clause as a part of the contract between the parties, the
E railway administration would consider its bid for
acceptance and resultant allotment of the contract.
However, the writ appeal filed by the Railways was
allowed and the writ petition of the appellant dismissed.
F Dismissing the appeal, the Court
HELD: 1. Submission of a tender in response to a
notice inviting such tenders is no more than makiilg an
offer which the State or its agencies are under no
obligation to accept. The bidders participating in the
G tender process cannot, therefore, insist that their tenders
should be accepted simply because a given tender is the
highest or lowest depending upon whether the contract
is for sale of public property or for execution of works on
behalf of the Government. All that participating bidders
H
MAA BINDA EXPRESS CARRIER v. NORTHEAST 531
FRONTIER RAILWAY
are entitled to is a fair, equal and non-discriminatory A
treatment in the matter of evaluation of their tenders.
[para 8] [537-A-C]
2.1. Power exercised by the Government and its
instrumentalities in regard to allotment of contract is 8
subject to judicial review at the instance of an aggrieved
'
party. In the matter of award of contr~_the Government
and its agencies have to act reasonably and fairly at all
points of tima. To that extent the tenderer has an
enforceable right in the court competent to examine C
wh~ther the aggrieved party has been treated unfairly or
discriminated against to the detriment of public interest.
In Michigan Rubber (India) Ltd., principles of law
applicable in this regard to the process for judicial review
have been identified. [para 8-10] [536-H, E-F; 538-A-B]
D
Raunaq International Ltd. v. I. V. R. Construction Ltd. and
Ors. 1998 (3) Suppl. SCR 421 = (1999) 1 SCC 492 Meerut
Development Authority v. Association of Management
=
Studies and Anr. etc. 2009 (6) SCR 663 (2009) 6 SCC 171
and Air India Ltd. v. Cochin International Airport Ltd. (2000) 1 E
SCR 505; Tata Cellular v. Union of India 1994 (2) Suppl.
SCR 122 = (1994) 6 SCC 651, and Jagdish Manda/ v. State
=
of Orissa and Ors. 2006 (10) Suppl. SCR 606 (2007) 14
SCC 517; Michigan Rubber (India) Ltd. v. State of Kamataka
=
and Ors. 2012 (8) SCR 128 (2012) 8 sec 216 - relied on. F
2.2. Award of a contract is essentially a commercial
transaction which must be determined on the basis of
considerations that are relevant to such commercial
decision. This implies that terms subject to which tenders
are invited are not open to the judicial scrutiny unless it G
is found that the same have been tailor made to benefit
any particular tenderer or class of tenderers. So also the
authority inviting tenders can enter into negotiations or
grant relaxation for bona fide and cogent reasons
H
532 SUPREME COURT REPORTS [2013] 12 S.C.R.
A provided such relaxation is permissible under the terms
governing the tender process. [para 8} [537-C-E]
2.3. In the instant case, it is not in dispute that tender
documents were not accompanied by the terms and
conditions applicable to the proposed contract. That
8
being so, award of a contract without specifying the
terms subject to which the same had to be worked was
bound to result in serious administrative and legal
complications. The absence of a penalty clause from the
tender documents was similarly a serious deficiency in
C the entire tender process. That apart, not only is the
reserve price higher than the amount offered by the
appellant but even the market survey has brought forth
rates higher than what was offered by the appellant.
Allotment of any contract at the rate offered by the
D appellant would, therefore, result in a substantial financial
loss to the railways which is neither in the public interest
nor necessitated by any legal compulsion. Time lag in
such matters plays an important role as it indeed has in
the case at hand. [para 7] [535-G-H; 536-A-B, E-G]
E
2.4. Therefore, the decision to cancel the tender
process was in no way discriminatory or ma/a fide. On the
contrary, if a contract had been awarded despite the
deficiencies in the tender process serious questions
F touching the legality and propriety affecting the validity
of the tender process would have arisen. In as much as
the competent authority decided to cancel the tender
process, it did not violate any fundamental right of the
appellant nor could the action of the respondent be
termed unreasonable so as to warrant any interference
G from this Court. The Division Bench of the High Court
was, in that view, perfectly justified in setting aside the
order passed by the Single Judge and dismissing the
writ petition. [para 11] [539-E-G]
H
MAA BINDA EXPRESS CARRIER v. NORTHEAST 533
FRONTIER RAILWAY
Case Law Reference: A
1998 (3) Suppl. SCR 421 relied on para 6
2009 (6) SCR 663 relied on para 9
1994 (2) Suppl. SCR 122 relied on para 9 B
2006 (10) Suppl. SCR 606 relied on para 9
2012 (8) SCR 128 relied on para 9
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
10751 of 2013. c
From the Judgment and order dated 06.06.2012 of the
High Court of Guwahati, Assam in Writ Appeal No. 79 of 2012.
Dr. Abhishek Manu Singhvi, C. Mukund, Priyankar Saha,
0
Ekta Bhasin, Pankaj Sain, Amit Bhandari, Charul Sarin, Bijoy
Kumar Jainfor the appellants.
R.P. Bhatt, A.K. Srivastava, Vikas Malhotra, P. Agrawala,
Rajat Mathur, Shreekant N. Terdal for the respondents.
E
The Judgment of the Court was delivered by
T.S. THAKUR, J. 1. Leave granted.
2. This appeal arises out of a judgment and order dated
6th June, 2012 passed by a Division Bench of the Gauhati High F
Court whereby Writ Appeal (C) No.79 of 2012 has been
allowed; judgment and order dated 4th February, 2012 passed
by a Single Bench of that Court set aside and Writ Petition (C)
No.4668 of 2011 filed by the appellants dismissed.
G
3. In terms of a notice dated 12th July, 2011 Divisional
Commercial Manager, Tinsukia invited tenders for the grant of
a three year lease of 23 tonnes of space in VPH (Parcel Van)
on train No.15960/15959 Kamrup Express. Among those who
responded to the tender notice was the appellant herein who H
534 SUPREME COURT REPORTS [2013) 12 S.C.R.
A offered a sum of Rs.1.46,872/- per trip for the proposed lease.
The tender process was discharged by the railway
administration on account of technical and administrative
reasons no matter the appellant's offer was the highest. A
communication dated 6th September, 2011, addressed to the
B appellant was in that regard issued to the appellant who
assailed the same in W.P. (C) No.4668 of 2011 before the
High Court of Gauhati.
4. In their counter affidavit the railways defended the
C cancellation/discharge of the tender not only on the ground that
the appellant had acquired no vested right for allotment of the
contract in its favour merely because its bid was found to be
the highest, but also on the ground that the power to cancel/
withdraw the tender notice had been specifically reserved by
the railway administration in its favour. That apart, the
D cancellation of the tender process was sought to be justified
also on the ground that the railway administration had
discovered a serious deficiency in the same in as much as the
tender forms had been issued without enclosing therewith the
terms and conditions subject to which the contract could be
E allotted or awarded. It was also contended that an all important
penalty clause had not been incorporated in the tender
documents. These omissions and deficiencies were according
to the respondent sufficient for cancellation of the tender
process to be followed by a fresh process in due course.
F
5. A learned Single Judge of the High Court of Gauhati
before whom the matter was argued took the view that the
discharge of the tender process had caused prejudice to the
appellant by reason of his rates having become public. It was
G also held by the learned Single Judge that every public authority
was required to act fairly while granting contracts and that
reasons for cancellation of the tender process should have been
set out in the communication sent to the appellant instead of
being disclosed subsequently in the affidavit filed in opposition
H to the writ petition. The learned Single Judge accordingly
MAA BINDA EXPRESS CARRIER v. NORTHEAST 535
FRONTIER RAILWAY [T.S. THAKUR, J.)
allowed the writ petition with a direction that so long as the A
appellant undertook to accept the penalty clause as a part of
the contract between the parties the railway administration
would consider its bid for acceptance and resultant allotment
of the contract within 15 days of receipt of the undertaking.
B
6. Aggrieved by the judgment and order abovementioned,
the railway administration preferred Writ Appeal (C) No.79 of
2012 before the Division Bench of the High Court of Gauhati.
Relying upon the decision of this Court in Raunaq International
Ltd. v. I. V.R. Construction Ltd. and Ors. (1999) 1 SCC 492 the
Division Bench held that the appellant acquired no right to claim C
the award of the contract merely by reason of its bid being the
highest. It further held that the scope of judicial review being
limited in tender matters, the Court had to restrain itself from
interfering with the process so long as the decision of the
competent authority was not against public interest, irrational, D
ma/a fide or illegal. It was also held that merely because the
order discharging tender process was silent as to the reasons
for the decision the same did not prevent the Court from looking
into the records to find out the basis on which the cancellation
was ordered. So also the argument that exposure of rates E
offered by the appellant would result in prejudice to the
appellant was rejected as a ground to justify interference with
the decision of the railway administration which was otherwise
held to.be legal and bona fide. The present appeal assails the
said decision as seen earlier. F
7. We have heard learned counsel for the parties at some
length. The material facts are not in dispute. It is not in dispute
that tender documents were not accompanied by the terms and
conditions applicable to the proposed contract. That being so, G
award of a contract without specifying the terms subject to which
the same had to be worked was bound to result in serious
administrative and legal complications. It is also not in dispute
that no tender Box Opening Committee had been nominated
with the approval of the Controlling Officer nor was any H
536 SUPREME COURT REPORTS [2013] 12 S.C.R.
A verification of tender documents conducted by the Division
concerned for their genuineness. The absence of a penalty
clause from the tender documents was similarly a serious
deficiency in the entire tender process. Cancellation of the
tender process could not, in that view, be said to be ma/a fide
B to call for interference by the High Court. The respondents have,
in their written submissions filed before us, referred to Circular
No.12 of 2006 by which guidelines for leasing out existing
space in trains for the purposes of operating parcel services
have been issued. These guidelines, inter alia, stipulate that a •
c tender Committee shall be put together which requirement was
also not complied with while issuing the tender notice in the I
instant case. That apart, the Ministry of Railways has, by Circular I
No.13 dated 31st May, 2012, revised the rate structure for
0
booking of parcel and luggage services. The revised rate for
Kamrup Express is Rs.4756/- per ton. The reserve price
calculated on that basis comes to Rs.1 84, 100/-. The offer made
by the appellant was much below that amount. Besides, a
l
market survey conducted in terms of an interim order passed
by the High Court had revealed that the contract could fetch
Rs.2,25,000/- per trip which was substantially higher thar
E Rs.1,46,872/- quoted by the appellant Suffice it to say that not
only is the reserve price applicable as on date higher than the
amount offered by the appellant but even the market survey has
brought forth rates higher than what was offered by the
appellant. Allotment of any contract at the rate offered by the
F appellant would, therefore, result in a substantial financial loss
to the railways which is neither in the public interest nor
necessitated by any legal compulsion. Time lag in such matters
plays an important role as it indeed has in the case at hand.
G
8. The scope of judicial review in matters relating to award
of contract by the State and its instrumentalities is settled by a
long line of decisions of this Court. While these decisions
clearly recognize that power exercised by the Government and
H its instrumentalities in regard to allotment of contract is subject
MAA BINDA EXPRESS CARRIER v. NORTHEAST 537
FRONTIER RAILWAY [T.S. THAKUR, J.]
to judicial review at the instance of an aggrieved party, A
submission of a tender in response to a notice inviting such
tenders is no more than making an offer which the State or its
agencies are under no obligation to accept. The bidders
participating in the tender process cannot, therefore, insist that
their tenders should be accepted simply because a given B
tender is the highest or lowest depending upon whether the
contract is for sale of public property or for execution of works
on behalf of the Government. All that participating bidders are
entitled to is a fair, equal and non-discriminatory treatment in
the matter of evaluation of their tenders. It is also fairly well- c
settled that award of a contract is essentially a commercial
transaction which must be determined on the basis of
consideration that are relevant to such commercial decision.
This implies that terms subject to which tenders are invited are
not open to the judicial scrutiny unless it is found that the same
0
have been tailor made to benefit any particular tenderer or
class of tenderers. So also the authority inviting tenders can
enter into negotiations or grant relaxation for bona fide and
cogent reasons provided such relaxation is permissible under
the terms governing the tender process.
E
9. Suffice it to say that in the matter of award of contracts
the Government and its agencies have to act reasonably and
fairly at all points of time. To that extent the tenderer has an
enforceable right in the Court who is competent to examine
whether the aggrieved party has been treated unfairly or F
discriminated against to the detriment of public interest. (See:
Meerut Development Authority v. Association of Management
Studies and Anr. etc. (2009) 6 SCC 171 and Air India Ltd. v.
Cochin lntemational Airport Ltd. (2000) 1 SCR 505).
G
10. The scope of judicial review in contractual matters was
further examined by this Court in Tata Cellular v. Union of India
(1994) 6 SCC 651, Raunaq International Ltd.'s case (supra)
and in Jagdish Manda/ v. State of Orissa and Ors. (2007) 14
sec 517 besides several other decisions to which we need H
538 SUPREME COURT REPORTS [2013] 12 S.C.R.
A not refer. In Michigan Rubber (India) Ltd. v. State of Karnataka
and Ors. (2012) 8 SCC 216 the legal position on the subject
was summed up after a comprehensive review and principles
of law applicable to the process for judicial review identified in
the following words:
B
"19. From the above decisions, the following principles
emerge:
(a) the basic requirement of Article 14 is fairness in action
by the State, and non-arbitrariness in essence and
c substance is the heartbeat of fair play. These actions are
amenable to the judicial review only to the extent that the
State must act validly for a discernible reason and not
whimsically for any ulterior purpose. If the State acts
within the bounds of reasonableness, it would be
D legitimate to take into consideration the national priorities;
(b) fixation of a value of the tender is entirely within the
purview of the executive and courts hardly have any role
to play in this process except for striking down such action
of the executive as is proved to be arbitrarv or:
E
unreasonable. If the Government acts in conformity with
certain healthy standards and norms such as awarding
of contracts by inviting tenders, m those circumstances,
the interference by Courts is very limited;
F (c) In the matter of formulating conditions of a tender
document and awarding a contract, greater latitude is
required to be conceded to the State authorities unless
the action of tendering authority is found to be malicious
and a misuse of its statutory powers, interference by
G Courts is not warranted;
(d) Certain preconditions or qualifications for tenders
have to be laid down to ensure that the contractor has the
capacity and the resources to successfully execute the
work; and
H
MAA BINDA EXPRESS CARRIER v. NORTHEAST 539
FRONTIER RAILWAY [T.S. THAKUR, J.]
(e) If the State or its instrumentalities act reasonably. A
fairly and in public interest in awarding contract. here
again, interference by Court is verv restrictive since no
person can claim fundamental right to carrv on business
with the Government.
20. Therefore, a Court before interfering in tender or B
contractual matters, in exercise of power of judicial review,
should pose to itself the following questions:
(i) Whether the process adopted or decision made by the
authority is ma/a fide or intended to favour someone; or C
whether the process adopted or decision made is so
arbitrarv and irrational that the court can say: "the decision
is such that no responsible authority acting reasonably
and in accordance with relevant law could have reached";
and (ii) Whether the public interest is affected. If the
0
answers to the above questions are in negative. then
there should be no interference under Article 226."
(emphasis supplied)
1 i. As pointed out in the earlier part of this order the
decision to cancel the tender process was in no way E
discriminatory or ma/a fide. On the contrary, if a contract had
been awarded despite the deficiencies in the tender process
serious questions touchin'g the legality and propriety affecting
the validity of the tender process would have arisen. In as much
as the competent authority decided to cancel the tender F
process, it did not violate any fundamental right of the appellant
nor could the action of the respondent be termed unreasonable
so as to warrant any interference from this Court. The Division
Bench of the High Court was, in that view, perfectly justified in
setting aside the order passed by the Single Judge and G
dismissing the writ petition.
12. In the result this appeal fails and is hereby dismissed
with costs assessed at Rs.25,000/-
R.P. Appeal dismissed. H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.