Created byFuzzy Cloud

Supreme Court of India

M/S VIJAY TRADING AND TRANSPORT COMPANYversusCENTRAL WAREHOUSING CORPORATION

Citation
2019 INSC 1215
Decided
7 November 2019
Disposal
Dismissed

Holding

The arbitral award upholding the termination, forfeiture of the security deposit and detention of equipment was valid and not liable to be set aside.

Summary

The appellant, Vijay Trading and Transport Co., entered into a two‑year handling and transportation contract with Central Warehousing Corporation. The contract was terminated by the corporation for the appellant’s failure to deliver an export‑loaded container to the port at Navi Mumbai, leading to forfeiture of the security deposit and detention of the appellant’s forklift and hand trolleys. An arbitrator upheld the termination, the forfeiture and rejected the appellant’s counterclaims, an award which the appellant challenged under Section 34 of the Arbitration and Conciliation Act, 1996. The Supreme Court examined whether the arbitrator’s findings were arbitrary, whether the forfeiture was beyond the contract terms, and whether any statutory ground existed to set aside the award. Finding that the appellant had indeed failed to transport the container, that the corporation’s actions were authorized by the contract clause and that the appellant had already received the award amount before filing the petition, the Court held there was no basis for interference. Consequently, the appeal was dismissed and the High Court’s judgment affirmed.

Issues considered

  • The validity of the arbitrator’s upholding of contract termination and forfeiture of the security deposit
  • Whether the detention and forfeiture of the forklift and hand trolleys was arbitrary or beyond the terms of the agreement
  • Whether the appellant’s counterclaims for refund of security deposit and damages for alleged detention of equipment should be allowed
  • Whether there were any grounds for setting aside the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996
  • Effect of the appellant’s receipt of the award amount before filing the Section 34 petition on the challenge

Legislation cited

Subjects

ArbitrationSection 34Contract terminationForfeiture of security depositDetention of equipmentExport‑import logisticsArbitral awardSupreme Court

Judgment

1162                      [2019]REPORTS
                SUPREME COURT    13 S.C.R. 1162            [2019] 13 S.C.R.


 A             M/S VIJAY TRADING AND TRANSPORT COMPANY
                                            v.
                    CENTRAL WAREHOUSING CORPORATION
                              (Civil Appeal No.655 of 2016)
 B                               NOVEMBER 07, 2019
                      [R. BANUMATHI, A.S. BOPANNA AND
                           HRISHIKESH ROY, JJ.]
              Arbitration and Conciliation Act, 1996: s.34 – Appellant
 C     contractor entered into an agreement with respondent corporation
       for carrying out work of Handling and Transportation at Inland
       Clearance Depot – Respondent corporation terminated the contract
       due to appellant’s non-performance of contractual obligations and
       forfeited the security deposit and also fork lift and hand trolleys –
       Arbitration award in favour of respondent corporation – Held:
 D     Failure to transport the container to the Port at Navi Mumbai
       resulted in missing of the export schedule – Taking into consideration
       the failure of the appellant to deliver the container at the Port at
       Navi Mumbai and the time taken in recovery of the container and
       the expenditure incurred by the respondent-Corporation in
 E     particular, furnishing of bank guarantee of Rs.10 lakhs, the
       detention of the equipments cannot be said to be arbitrary or beyond
       the terms of the agreement – Arbitrator and courts below recorded
       the concurrent findings that the appellant Contractor failed in
       carrying out the work as per the terms and conditions of the contract
 F     – Arbitrator rightly allowed the detention and forfeiture of the
       equipments of the contractor – Similarly, counter claim for the
       damages for the alleged detention and use of hand trolleys was
       rightly rejected – No reason warranting interference with the award
       passed by the Arbitrator – Contract – Termination of – Export-
       Import.
 G
             Dismissing the appeal, the Court
            HELD: 1. The Export loaded Container was handed over
       by the Manager, ICD, Varanasi to the appellant on 06.11.2001
       for delivery of the container at JNP, Navi Mumbai; but the
 H
                                       1162
            M/S VIJAY TRADING AND TRANSPORT COMPANY v.                    1163
                 CENTRAL WAREHOUSING CORPORATION


appellant failed to transport the container to the destination port       A
and only with the intervention of the Court, the container was
located and recovered at Ghaziabad and received back at ICD,
Varanasi on 23.05.2003. But by then, the said container already
missed the export schedule. When the said Export loaded
Container was entrusted to the appellant, the appellant ought to          B
have transported the container to the port of destination with
due diligence. The respondent-Corporation was justified the
forfeiture of the security deposit on two counts:- firstly, in view
of the heavy claim raised by the Exporter for which they have
filed a claim of Rs.40 lakhs before the Consumer Forum and
secondly, on account of bank guarantee in the sum of Rs.10 lakhs          C
furnished by the respondent-Corporation for release of the
container. The Arbitrator and courts below recorded the
concurrent findings by holding the termination of the contract
legal and levy of forfeiture of the security amount and the levy of
fork lift is justified. [Para 11][1168-C-F]                               D
       2. The container handed over to the appellant was detained
by the third party who filed a Civil Suit against the appellant stating
that his dues had not been cleared by the appellant. The
respondent-Corporation had filed an application in the said suit
for release of the container which was rejected by the Civil Court,       E
Ghaziabad on 28.11.2002 and the respondent had to file a Civil
Revision Petition before the High Court in which a direction
was issued to the trial court to dispose of the application afresh.
It was thereafter, the trial court released the container on
furnishing a bank guarantee of Rs.10 lakhs by the respondent-
                                                                          F
Corporation. The trial court released the container only on
furnishing of bank guarantee of Rs.10 lakhs. It is stated that the
said civil suit is still pending in the Ghaziabad Court and is at the
stage of recording evidence. As held by the Arbitrator, the
appellant was given a contract to assist in smooth running of
international business of import and export and to have the time          G
management on top priority. Failure to transport the container
to the Port at Navi Mumbai resulted in missing of the export
schedule. Taking into consideration the failure of the appellant
to deliver the container at the Port at Navi Mumbai and the time
                                                                          H
1164              SUPREME COURT REPORTS                       [2019] 13 S.C.R.


 A     taken in recovery of the container and the expenditure incurred
       by the respondent-Corporation in particular, furnishing of bank
       guarantee of Rs. 10 lakhs, the detention of the equipments cannot
       be said to be arbitrary or beyond the terms of the agreement.
       [Paras 12, 13][1168-G-H; 1169-A, D-E]
 B            3. Even before filing of the objection petition under Section
       34 of the Act, the appellant received the full payment due and
       payable to him as per the arbitral award. According to the
       respondent-Corporation, the appellant has not disclosed the
       receipt of the money at the time of filing the petition under Section
 C     34 of the Act. The Arbitrator and the Courts below have recorded
       the concurrent findings that the appellant Contractor has failed
       in carrying out the work as per the terms and conditions of the
       contract and the Arbitrator has rightly allowed the detention and
       forfeiture of the equipments of the contractor and disallowed the
       counter claim No.4 of the appellant. Similarly, counter claim No.5
 D     which was for the damages for the alleged detention and use of
       hand trolleys was rejected and thus, the counter claim Nos.4 and
       5 were rightly disallowed by the Arbitrator. [Paras 14, 15][1169-
       F-H; 1170-A-B]
               CIVIL APPELLATE JURISDICTION: Civil Appeal No. 655 of
 E     2016.
             From the Judgment and Order dated 19.07.2010 of the High
       Court of Delhi at New Delhi in CM No. FAO (OS) 435/2010.
               Aniket Jain, Arvind Kumar Gupta, Abinash Kumar Mishra, Advs.
 F     for the Appellant.
               K.K. Tyagi, Iftekhar A., P. Narasimhan, Advs. for the Respondent.
               The Judgment of the Court was delivered by
               R. BANUMATHI, J.
 G            1. This appeal arises out of the impugned judgment dated
       19.07.2010 passed by the High Court of Delhi in FAO(OS) No.435 of
       2010 in and by which the High Court dismissed the appeal filed by the
       appellant thereby upholding the judgment of the learned Single Judge
       thereby affirming the dismissal of the objections filed under Section 34
 H     of the Arbitration and Conciliation Act, 1996 against the arbitral award
       dated 18.03.2005.
           M/S VIJAY TRADING AND TRANSPORT COMPANY v.                           1165
        CENTRAL WAREHOUSING CORPORATION [R. BANUMATHI, J.]


      2. Brief facts which led to filing of this appeal are as under:-          A
       An agreement dated 30.08.2001 was entered into between the
respondent-Central Warehousing Corporation and the appellant for a
period of two years from 28.08.2001 to 27.08.2003 for carrying out the
work of Handling and Transportation at Inland Clearance Depot (ICD),
Varanasi. The respondent-Corporation terminated the contract on                 B
21.02.2002 under Clause X(A) and X(B) of the agreement due to
appellant’s poor performance as Handling and Transportation Contractor
and deterioration of the situation at the Inland Clearance Depot. The
security deposit furnished by the appellant upto the date of termination
was also forfeited.                                                             C
        3. Dispute arose between the parties which led to the appointment
of an arbitrator vide reference order dated 23.09.2002. The respondent-
Corporation claimed a sum of Rs.98,06,000/- with interest @ 18% thereon.
It was contended by the respondent-Corporation that the performance
of the appellant was not found satisfactory particularly, in regard to Export   D
loaded Container No.TRIU-4991702x40’, which was illegally detained
by the appellant and the appellant failed to transport the container to the
Port at Navi Mumbai. The said container was handed over to the appellant
on 06.11.2001 from the Inland Clearance Depot, Varanasi and did not
reach its destination, JNP, Navi Mumbai within the stipulated time period
i.e. upto 16.11.2001. When the exporter, M/s Bhola Nath Industries              E
pressed for early recovery of the container and also raised claims towards
compensation for loss of the container, the respondent-Corporation started
inquiries and issued several notices to the appellant for recovery of the
container and non-performance of contractual obligations. Only after
intervention of the Courts, the container was located and recovered at          F
Ghaziabad and received back at ICD, Varanasi on 23.05.2003. But by
then, the said container missed the export schedule. The exporter initially
declared that the cargo stuffed in the container was of no use to him; but
subsequently, reprocessed the same to make it usable.
       4. The appellant filed counter claims under various heads claiming       G
Rs.52,00,000/- with interest @ 18% thereon. It was submitted by the
appellant that the container in question was illegally detained by
M/s ODC Roadways to whom the container was entrusted for
transportation to Port, Navi Mumbai. According to the appellant, it had
taken all possible steps including approaching the High Court for speedy
                                                                                H
1166             SUPREME COURT REPORTS                          [2019] 13 S.C.R.


 A     recovery of the container and in spite of all the efforts taken by the
       appellant, respondent-Corporation terminated the contract illegally.
              5. Taking into consideration the claim and grounds for termination
       and also the reply filed by the appellant, the Arbitrator vide award dated
       18.03.2005 upheld the termination of the contract as valid and decided
 B     certain claims of the respondent in its favour. Certain counter claims of
       the appellant were also allowed by the learned Arbitrator. Other claims
       including counter claim No.3 (claim of Rs.4,30,284/- towards refund of
       security deposit) and counter claim No.4 (claim of Rs.15,75,484/-
       including interest of Rs.4,64,815/- towards illegal detention of the fork
 C     lift) were decided against the appellant. It was held by the Arbitrator
       that the termination of the contract is legal and justified and in view
       thereof, the respondent had the right to forfeit the security deposit. As to
       the claim of the appellant towards alleged detention of the fork lift and
       hand trolleys, the Arbitrator held that the detention of the equipments is
       right and justified. The Arbitrator held that it is seen from Clause 5(g) of
 D     the tender conditions of the contract that the respondent has the right to
       demand the balance due when sufficient sum is not available to cover
       the full amount recoverable from security deposit and other dues. In
       view of the heavy claim amount of M/s Bhola Nath Industries and
       Customs/Excise Department and others, the learned Arbitrator concluded
 E     that there is no illegality in the action on the part of the claimant in
       detaining the equipments like fork lift and hand trolleys as security.
              6. The appellant filed objections under Section 34 of the Arbitration
       and Conciliation Act contending that the order of termination whereby
       the security deposit was also forfeited does not record any reason for
 F     forfeiture of the security deposit. Similarly, no reason has been given by
       the Arbitrator for rejecting the counter claim No.3. In support of its
       counter claim No.4, the appellant averred that for successful executing
       of the contract, it had employed one fork lift and four hand trolleys at
       Inland Clearance Depot, Varanasi, which were owned by them and the
       same have been illegally detained by the respondent. On behalf of the
 G
       respondent-Corporation, it was contended that the forfeiture of the
       security deposit was justified on the following reasons – firstly in view
       of the heavy claim raised by M/s Bhola Nath Industries before the
       Consumer Forum, Lucknow and secondly, on account of bank guarantee
       to sum of rupees ten lakhs furnished by the respondent for release of the
 H
           M/S VIJAY TRADING AND TRANSPORT COMPANY v.                        1167
        CENTRAL WAREHOUSING CORPORATION [R. BANUMATHI, J.]


container. The respondent submitted that a claim of rupees forty lakhs       A
was lodged by M/s Bhola Nath Industries Ltd. Accordingly, it was decided
not only to withhold the payment due to the appellant, but also to forfeit
all the equipments in use.
       7. Considering the objections of the appellant and the claim of the
respondent-Corporation, the learned Single Judge of the High Court found     B
no infirmity in the reason recorded by the learned Arbitrator while
rejecting counter claim No.4. Counter claim No.3 was allowed to the
extent that in case the bank guarantee furnished by the respondent-
Corporation is discharged, the appellant would be entitled to refund the
security deposit in the sum of Rs.4,30,284/-. The appeal filed by the        C
appellant under Section 37 of the Arbitration and Conciliation Act was
dismissed vide the impugned judgment affirming the order of the learned
Single Judge.
       8. Before the Supreme Court, the appellant has only pressed
counter claim Nos.3 and 4. Mr. Aniket Jain, learned counsel for the          D
appellant has contended that the courts below erred in not appreciating
the fact that the appellant exercised due diligence and has taken efforts
for the recovery of illegally detained container including lodging of FIR
and initiating legal proceedings. It was submitted that the courts below
failed to appreciate that the conditions imposed regarding the refund of
security deposit is beyond the terms of the agreement between the parties    E
as well as the terms of reference made to the arbitrator and the order of
the learned Single Judge to replace the bank guarantee is untenable and
prayed for allowing of the appeal.
       9. Insofar as the forfeiture of security deposit is concerned,
Mr. K.K. Tyagi, learned counsel for the respondent-Corporation has           F
submitted that M/s Bhola Nath Industries, whose containers remained
missing for a long time on account of the conduct of the appellant had
lodged a claim against the respondent for a sum of rupees forty lakhs
and though the same has been dismissed for non-prosecution, the same
may be restored at any time at the instance of the complainant M/s           G
Bhola Nath Industries Ltd. It was therefore, contended that the forfeiture
of the security amount and fork lift cannot be said to be arbitrary or
unjustified and in accordance with the terms of the contract. Learned
counsel further submitted that the respondent Corporation had to furnish
a bank guarantee of rupees ten lakhs to get the container released in
                                                                             H
1168             SUPREME COURT REPORTS                           [2019] 13 S.C.R.


 A     view of the suit filed by the third party-M/s ODC against the appellant
       for retaining the container till their dues are paid by the appellant and the
       case is still pending and therefore, the learned Arbitrator has rightly upheld
       the act of the respondent-Corporation in forfeiting the security deposit.
             10. We have carefully considered the contentions of both the parties
 B     and perused the impugned judgment and the award passed by the learned
       Arbitrator and the order of the learned Single Judge and other materials
       on record.
              11. The Export loaded Container No.TRIU-4991702x40’ was
       handed over by the Manager, ICD, Varanasi to the appellant on 06.11.2001
 C     for delivery of the container at JNP, Navi Mumbai; but the appellant had
       failed to transport the container to the destination port and only with the
       intervention of the Court, the container was located and recovered at
       Ghaziabad and received back at ICD, Varanasi on 23.05.2003. But by
       then, the said container already missed the export schedule. When the
 D     Export loaded Container No.TRIU-4991702x40’ was entrusted to the
       appellant, the appellant ought to have transported the container to the
       port of destination with due diligence. The respondent- Corporation has
       justified the forfeiture of the security deposit on two counts:- firstly, in
       view of the heavy claim raised by M/s Bhola Nath Industries Ltd. for
       which they have filed a claim of rupees forty lakhs before the Consumer
 E     Forum, Lucknow and secondly, on account of bank guarantee in the
       sum of rupees ten lakhs furnished by the respondent-Corporation for
       release of the container. The learned Arbitrator and the Courts below
       have recorded the concurrent findings by holding the termination of the
       contract legal and levy of forfeiture of the security amount of Rs.4,30,284/
 F     - and the levy of fork lift is justified.
               12. The container handed over to the appellant was detained by
       the third party-M/s ODC Roadways represented by Sh. Prabhu Nath
       Sing, who filed a Civil Suit No.1127 of 2001 against the appellant stating
       that his dues had not been cleared by the appellant. The respondent-
 G     Corporation had filed an application in the said suit for release of the
       container which was rejected by the Civil Court, Ghaziabad on 28.11.2002
       and the respondent had to file a Civil Revision Petition No.180 of 2002
       before the High Court of Allahabad in which a direction was issued to
       the trial court to dispose of the application afresh. It was thereafter, the
       trial court released the container on furnishing a bank guarantee of rupees
 H
           M/S VIJAY TRADING AND TRANSPORT COMPANY v.                            1169
        CENTRAL WAREHOUSING CORPORATION [R. BANUMATHI, J.]


ten lakhs by the respondent-Corporation. The trial court released the            A
container only on furnishing of bank guarantee of rupees ten lakhs. It is
stated that the said civil suit is still pending in the Ghaziabad Court and is
at the stage of recording evidence.
        13. Insofar as the allegation of detention of fork lift and hand
trolleys, the respondent-Corporation has stated that after finalisation of       B
the arbitration case between the respondent-Corporation and the appellant,
all the dues as per the order of the Arbitrator has been paid to the
contractor; but the appellant did not approach the respondent-Corporation
for lifting their equipments and as such the same were lying at ICD,
Bhadohi occupying valuable space. According to the respondent-                   C
Corporation, for the space occupied by the equipments, the total rent for
the period up to 31.05.2007 works out to Rs.41,746/- and Rs.89,049/-
for fork lift and hand trolleys respectively. Be that as it may, according
to the respondent-Corporation, the detention of the equipments were
made as per the terms of the agreement at Clause 5(g) and the same
was accepted by the arbitrator. As held by the learned Arbitrator, the           D
appellant was given a contract to assist in smooth running of international
business of import and export and to have the time management on top
priority. Failure to transport the container to the Port at Navi Mumbai
resulted in missing of the export schedule. Taking into consideration the
failure of the appellant to deliver the container at the Port at Navi Mumbai     E
and the time taken in recovery of the container and the expenditure
incurred by the respondent-Corporation in particular, furnishing of bank
guarantee of rupees ten lakhs, the detention of the equipments cannot
be said to be arbitrary or beyond the terms of the agreement.
       14. It is pertinent to note that the appellant has received an amount     F
of Rs.11,06,598/- as the amount allowed by the Arbitrator vide award
dated 18.03.2005 by DD No.079915 dated 03.09.2005. Thus, even before
filing of the objection petition under Section 34 of the Act, the appellant
has received the full payment due and payable to him as per the arbitral
award dated 18.03.2005. According to the respondent-Corporation, the
                                                                                 G
appellant has not disclosed the receipt of the money at the time of filing
the petition under Section 34 of the Act.
       15. The learned Arbitrator and the Courts below have recorded
the concurrent findings that the appellant Contractor has failed in carrying
out the work as per the terms and conditions of the contract and the
                                                                                 H
1170              SUPREME COURT REPORTS                       [2019] 13 S.C.R.


 A     learned Arbitrator has rightly allowed the detention and forfeiture of the
       equipments of the contractor and disallowed the counter claim No.4 of
       the appellant. Similarly, the counter claim No.5 which was for the damages
       for the alleged detention and use of hand trolleys has been rejected and
       thus, the counter claim Nos.4 and 5 have been rightly disallowed by the
 B     learned Arbitrator. We do not find any reason warranting interference
       with the award passed by the Arbitrator and the impugned judgment and
       this appeal is liable to be dismissed.
             16. In the result, the impugned judgment dated 19.07.2010 passed
       by the High Court in FAO(OS) No.435 of 2010 is affirmed and this
 C     appeal is dismissed. No costs.


       Devika Gujral                                              Appeal dismissed.



 D




 E




 F




 G




 H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.