Created byFuzzy Cloud

Supreme Court of India

M/S SAGAR SUGARS & ALLIED PRODUCTS LTD.versusTHE TRANSMISSION CORPORATION OF A.P. LTD. & ORS.

Citation
2011 INSC 760
Decided
13 October 2011
Disposal
Disposed off

Holding

It is appropriate for the Andhra Pradesh Electricity Regulatory Commission to determine the price of power supplied by the appellant to the respondent during the disputed period and thereafter.

Summary

The appellant, Sagar Sugars & Allied Products Ltd., entered into a Power Purchase Agreement (PPA) with the Transmission Corporation of Andhra Pradesh Ltd. to sell electricity generated from bagasse. The sugar plant was not operational between 13 January 2003 and 21 January 2004, raising a dispute over whether the unutilised power should be priced at the same rate as non‑conventional energy projects as fixed by the Andhra Pradesh Electricity Regulatory Commission (APERC). The High Court had directed the parties to resolve the matter under the PPA, but the Supreme Court was asked to decide the appropriate tariff for the disputed period. The Court examined clause 2.2 of the PPA, which stipulated a base tariff of Rs.2.25 per unit with annual escalation and stated that post‑2004 pricing would be decided by APERC. It held that APERC, being the expert regulatory body, is best placed to determine the purchase price for the power supplied during the contested period and thereafter. Consequently, the appeals were dismissed and the matter was remitted to APERC to fix the tariff, with any balance payments to be made by the respondent.

Issues considered

  • Whether the price of unutilised power supplied by the appellant during the period when the sugar plant was not operational should be the same as the price for non‑conventional energy projects fixed by APERC.
  • Whether APERC has jurisdiction to determine the purchase price for such power under the PPA.
  • Interpretation of clause 2.2 of the PPA regarding tariff, escalation and post‑2004 price determination.

Legislation cited

Subjects

electricity tariffpower purchase agreementbagasse powernon‑conventional energyregulatory commissionprice determinationco‑generationAPERC

Judgment

                    [2011) 12 S.C.R. 1005


    M/S SAGAR SUGARS & ALLIED PRODUCTS LTD.                        A
                               v.
  THE TRANSMISSION CORPORATION OF A.P. LTD. &
                        ORS.
          (Civil Appeal No. 5159 of 2005)
                                                                   B
                     OCTOBER 13, 2011

      [R.V. RAVEENDRAN AND A.K. PATNAIK, JJ.]

      Electricity: Price and tariff of power- Fixation of- Power
 generated from bagasse, by-product of sugar industry run by       C·
 appellant - Supply of power to respondent no. 1 - Dispute
 between the appellant and respondent No. 1 was whether or
 not during the period 13.01.2003 to 21.01.2004, when the
 sugar plant of the appellant had not commenced production
of sugar, the unutilized power supplied by the appellant to        D
respondent No.1 would have the same price as the price of
power supplied by non-conventional energy projects in the
 State of Andhra Pradesh determined by the Andhra Pradesh
Electricity Regulatory Commission (APERC) - Held: It would
 be more appropriate for the APERC, which is a regulatory          E
 commission with expertise in determination of price and tariff
.of power, to decide what would be the price for supply of power
 by the appellant to the respondent no. 1 during the disputed
period and thereafter - Matter remitted to APERC - APERC
to consider all relevant materials and factors and finally         F
determine the price of power supplied during the disputed
period and t~ereafter.

    On 29.04.2000, the appellant entered into a
Memorandum of Understanding with Non-Conventional
Energy Development Corporation of Andhra Pradesh                   G
Limited (NEDCAP), a nodal agency for non-conventional
projects up to 20 MW, for setting up of a power plant in
which power was to be generated from bagasse, a by-
product of sugar factory. On 25.01.2002, the Andhra
                             1005                                  H
    1006   SUPREME COURT REPORTS            [2011] 12 S.C.R.


A Pradesh Electricity Regulatory Commission (APERC) set
  up under the Andhra Pradesh Electricity Reforms Act,
  1998, permitted the appellant-company to supply the
  power generated in its plant to the respondent no.1,
  which had taken over the functions of the erstwhile
B Andhra Pradesh Electricity Board. On 10.07.2002, a Power
  Purchase Agreement (PPA) was entered into between the
  appellant and respondent no.1 which inter alia provided
  that the power to the extent of 9.99 MW would be supplied
  during the season and the power to the extent of 16.94
c MW would be supplied durinr the off season. On
  11.01.2003, respondent no.1 permitted the appellant to
  synchronize its plant with the power grid· and on
  13.01.2003, the appellant started supplying electricity
  energy to the power grid. On 01.03.2003, the appellant
  wrote to the APERC to direct respondent no.1 to
0
  purchase unutilized power of the appellant as sugar plant
  of the appellant could not be commissioned due to some
  difficulties and power generated in its power plant
  remained unutilized. On 17.03.2003, APERC directed
E respondent no.1 to amend the PPA to provide for surplus/
  additional quantity of power from the appellant. On
  17.03.2003, the Chief Engineer of respondent No.1 wrote
  to Superintending Engineer directing him to stop
  evacuation of power from the power plant of the appellant
  and to cut off the supply on the ground that the plant of
F the appellant could not be classified as co-generation till
  the sugar plant of the appellant was commissioned.

       In the instant appeals the dtspute betwee'n the
  appellant and respondent No.1 was whether or not during
G the period 13.01.2003 to 21.01.2004, when the sugar plant
  of the appellant had not commenced production of sugar,
  the unutilized power supplied by the appellant to
  respondent No.1 would have the same price as the price
  of power supplied by non-conventional energy projects
H
      SAGAR SUGARS & ALLIED PRODUCTS LTD. v.            1007
         TRANSMISSION CORPN., OF A.P. LTD.

in the State of Andhra Pradesh determined by the                A
APERC.

     Disposing of the appeals and remanding the matter
to the APERC, the Court

    HELD: It would be more appropriate for the APERC,           8
which is a regulatory commission with expertise in
determination of price and tariff of power, to decide what
would be the price for supply of power by the appellant
to the respondent no.1 during the disputed period
13.01.2003 to 21.01.2004 and thereafter. The APERC              C
would have to consider all relevant materials and factors
and finally determine the price of power supplied during
the period 13.01.2003 to 21.01.2004 and thereafter and in
accordance with the determination made by the APERC,
balance payments, if any, will .be made by the respondent       D
no.1 to the appellant. [Paras 9-1 O] [1012-D-G-H]

    Transmission Corporation of Andhra Pradesh Limited
and Anr. etc. etc. v. Sai Renewable Power Private Limited and
Others etc.etc.(2010) 6 Scale 541: (2010) 8 SCR 636- relied     E
on.
                    Case Law Reference:
      (2010) 8 SCR 636       · Relied on           Para 7
    CIVIL APPELLATE JURISDICTION : Civil Appeal No.             F
5159 of 2005.

    From the Judgment and Order dated 30.07.2004 of the
High Court of Judicature ofAndhra Pradesh at Hyderabad in
C.M.A. No. 3613 of 2004.                                        G
                           WITH

Civil Appeal No. 5157 of 2005.

                                                                H
    1008     SUPREME COURT REPORTS                 [2011] 12 $.C.R.


A      Dr. Rajeev Dhawan and R. Balasubramaniam, A.V.
    Rangam, Buddy A. Ranganadhan for the Appellant.

        Rakesh K. Sharma, S. Ramsubramanian and Sangita
    Chauhan for the Respondents.
B       The Judgment of the Court was delivered by

         A. K. PATNAIK, J. 1. These are the appeals against the
    common order dated 30.07.2004 passed by the Division Bench
    of the Andhra Pradesh High Court in Writ Appeal No. 191 of
c   2004 and C.M.A No. 3613 of 2003.

          2. The facts relevant for deciding these appeals very briefly
    are that on 29.04.2000 the appellant entered into a
    Memorandum of Understanding with Non-Conventional Energy
    Development Corporation of Andhra Pradesh Limited (for short
D . 'the NEDCAP'), a nodal agency for non-conventional projects
    up to 20 MW, for setting up of a power plant in which power
    was to be generated from bagasse, a by-product of sugar
    factory. On 25.01.2002, the Andhra Pradesh Electricity
    Regulatory Commission (for short 'the APERC') set up under
E the Andhra Pradesh Electricity Reforms Act, 1998, permitted
    the appellant-company to supply the power generated in its plant
    to the respondent no.1, which had taken over the functions of
    the erstwhile Andhra Pradesh El~ctricity Board. On 10.07.2002,
    a Power Purchase Agreement (for short 'the PPA') was
F entered into between the appellant and the respondent no.1
    which inter alia provided that the power to the extent of 9.99
    MW will be supplied during the season and power to the extent
    of 16.94 MW will be supplied during the off season. On
    11.01.2003, respondent no.1 permitted the appellant to
G synchronize its plant with the power grid and on 13.01.2003,
    the appellant started supplying electricity energy to the power
    grid. On 01.03.2003, the appellant wrote to the APERC to direct
    the respondent no.1 to purchase unutilized power of the.
    appellant as sugar .plant of the appellant could not be
H commissioned due to some difficulties and power generated
    SAGAR SUGARS & ALLIED PRODUCTS LTD. v.         '1009
 TRANSMISSION CORPN., OF AP. LTD. [AK. PATNAIK, J.]

in its power plant remained unutilized and on 17.03.2003,             A
APERC directed the respondent no.1 to amend the PPA to
provide for surplus/ additional quantity of power from the
appellant. On 17.03.2003, the Chief Engineer of respondent
No.1 wrote to Superintending Engineer directing him to stop
evacuation of power from the power plant of the appellant and         B
to cut off the supply on the ground that the plant of the appellant
cannot be classified as co-generation till the sugar plant of the
appellant was commissioned.

      3. The appellant then filed Writ Petition No. 7395 of 2003      C
in the Andhra Pradesh High Court challenging the letter dated
17.032003 of the Chief Engineer of the respondent ~o.1 and
the learned Single Judge passed the orders on 02.05.2003
directing issue of notice to the respondents and directing the
respondents, as an interim measure, to purchase power from
the appellant and to pay to the appellant Rs.2.00 per 11nit. The      D
respondent No.1 then filed a review petition before the APERC
for reconsideration of its earlier directions to amend the PPA
issued on 17 .03.2003 and on 01.10.2003 the APERC allowed
the- review petition and cancelled its directions issued on
17.03.2003. The appellant then challenged the order dated             E
01.10.2003 of the APE RC before the Division Bench of the
High Court in C.M.A. No. 3613 of 2003 and the Division Bench
of the High Court granted interim stay of the order dated
01.10.2003 of the APERC.
                                                                      F
     4. On 15.12.2003, the learned Single Judge of the High
Court allowed Writ Petition No, 7395 of 2003 of the appellant
and quashed the letter dated 17.03.2003 of the Chief Engineer
of the respondent No.1 · and directed the respondent No.1 to
evacuate the power as agreed under the PPA and as directed            G
by the APERC by order dated 17.03.2002. Against the said
order dated 15.12.2003 of the learned Single Judge, the
respondent filed Writ Appeal No. 371 of 2004 and on
12.02.2004 the Division Bench passed an interim order that
no further payment need to be made by respondent no.1 to the          H
    1010     SUPREME COURT REPORTS                 [2011] 12 S.C.R.


A appellant. Thereafter, on 22.04.2004 the Division Bench
    modified its earlier interim order dated 12.02.2004 and directed
    the respondent to pay the appellant at the rate of Rs.2.69 per
    unit instead of Rs.2.00 per unit and the said order was to
  . continue till further orders in the Writ Petition.
B
         5. Finally on 30.07.2004, the Division Bench of the High
    Court passed the impugned order in Writ Appeal No. 191 of
    2004 as well as in C.M.A. No. 3613 of 2003 setting aside the
    order dated 15.12.2003 of the learned Single Judge in Writ
    Appeal No. 7395 of 2003 and directed the parties to approach
C the appropriate forum chosen by the parties under the PPA for
    resolving the dispute. By the impugned order the Division Bench
    also held that the appellant will be entitled to tariff as fixed by
    the Division Bench of the High Court in Writ Appeal No. 371
    of 2004.
D
         6. Dr. Rajeev Dhavan, learned senior counsel for the
    appellant, submitted that the sugar plant has, in the meanwhile,
    commenced the production on 21.01.2004 and the only dispute
    which has to be decided by this Court is VJith regard to the price
E of the power supplied by the appellant to the respondent during
    the period from 13.01.2003 to 21.01.2004.

        7. Mr. Dhavan submitted that by the order dated
  22.04.2004 of the Division Bench in Writ Appeal No. 371 of
F 2004, the respondent No.1 was to be paid at the revised rate
  of Rs.2.69 per unit and on 08.02.2006, this Court has by an
  interim order, directed that the appellant would be entitled to
  receive payment at the rate of Rs.3.11 per unit as an interim
  measure for the period from 13.01.2003 to 20.01.2004 and
  also at the same rate of Rs.3.11 per unit for the period
G 21.01.2004 onwards, as has been paid to other co-generating
  plants, excluding the money already paid. He submitted that in
  Transmission Corporation of Andhra Pradesh Limited and
  Another etc. etc. v. Sai Renewable Power Private Limited and
  Others etc.etc. [(2010) 6 SCALE 541= (2010) 8 SCR 636 =
H JT 2010 (7) SC 1] this Court has issued some directions
    SAGAR SUGARS & ALLIED PRODUCTS LTD. v.            1011
 TRANSMISSION CORPN., OF A.P. LTD. [A.K. PATNAIK, J.]

relating to price payable for power supplied by non-conventional A
power projects. He referred to Para 4 of the judgment of this
Court in the aforesaid case to show that the APERC had
approved the rate of Rs.2.25 per unit with 5% escalation per
annum from 1994-1995, being the base year, for supply of
power generated by the non-conventional power projects and B
this was also the price fixed in clause 2.2 of the P.P.A for supply
of electricity by the appellant to the respondent no.1. He
submitted that the benefit of the aforesaid judgment of this Court
delivered on 08.07.2010 should therefore be granted to the
appellant and directions be issued to respondent no.1 c
accordingly.

     8. Learned counsel for respondent no.1, on the other hand,
submitted that the judgment of this Court delivered on
08.07.2010 in Iransmission Corporation of Andhra Pradesh
Limited and Another etc. etc. v. Sai Renewable Power Private      D
Limited and Others etc.etc. (supra) was on tariff and purchase
price of power produced by co-generation non-conventional
energy plants and the plant of the appellant was not a co-
generation plant during the period from January, 2003 to
January, 2004, as there was no production of sugar in the plant   E
during the aforesaid period and therefore the judgment of this
Court in Transmission Corporation of Andhra Pradesh
Limited and Another etc. etc. v. Sai Renewable Power Private
Limited and Others etc.etc. (supra) has no relevance to the
price of power supplied by the appellant to the respondent No.1   F
during January, 2003 to January, 2004.

    9. We have considered the submissions of the learned
counsel for the parties and we find that clause 2.2 of P.P.A.
between the appellant and respondent no.1 reads as follows:       G

    "2.2. The company shall be paid the tariff for the energy
    delivered at the interconnection point for sale to
    APTRANSCO at Rs.2.25 paise per unit with escalation at
    5% per annum with 1994-95 as base year and to be
    revised on 1st April of every year up to the year 2003-       H
    1012     SUPREME COUR'r REPORTS                (2011] 12 S.C(.R.


A       2004. Beyond the year 2003=2004, the purchase price by
        APTRANSCO will be decided by Andhra Pradesh
         Electricity Regulatory Commission. There will be further
        .review of purchase price on completion of ten years from
         the date of commissioning of the project, when the
B        purchase price will-be reworked on the basis of Return on
         Equity, O& M expenses and the Variable Cost.

      The dispute between the appellant and respondent No.1 before
      us is whether or not during the period 13.01.2003 to
      21.01.2004, when the sugar plant of the appellant had not
C corrunenced production of sugar, the unutilized power supplied
      by the appellant to the respondent No.1 will have the same price
      as the price of power supplied by rron-cQnVentional energy
      projects in the State of Andhra Pradesh determined by the
      APERC. It will be more appropriate for the APERC, which is a
D regulatory commission with expertise in determination of price
      and tariff of power, to decide what would be the price for supply
    . of power by )he appellant to the respondent no.1 during the
      disputed period 13.01.2003 to 21.01.2004 and thereafter. By
      the judgment dated 08.07.2010 of this Court in Tr:ansmission
E - Corporation of Andhra Pradesh Limited and Another etcr.. etc.
      v. Sai Renewable Power Private Umited and Others etc.etc.           - ·
      (supra), this Court has also remanded the matters to APERC
      to decide the 'purchase price' for proeurement of the electricity
      generated by non-conventional energy developers in the facts
r:: of the circumstances of the case.

          10. We, therefore, dispose of these appeals by directing
    that the APERC will consider all relevant materials and factors
    and finally determine the price of power supplied during the
G   period 13.01.2003 to 21.01.2004 and thereafter and in
    accordance with the determination made by the APERC,
    balance payments, if any, will be made by the respondent no.1
    to the appellant. The appeals are disposed of accordingly.
    There shall be no order as to costs.

H D.G.                                         Appeals disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "electricity tariff"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.