M/S. REVA ELECTRIC CAR CO. P. LTD.versusM/S. GREEN MOBIL
- Citation
- 2011 INSC 822
- Decided
- 25 November 2011
- Disposal
- Disposed off
- Bench
- S S NIJJAR
Holding
An arbitration clause survives the termination of the contract and, when valid, obliges the parties to refer the dispute to arbitration, with the Chief Justice of India empowered to appoint a sole arbitrator.
Summary
The parties entered into a Memorandum of Understanding (MOU) on 25 September 2007 containing an arbitration clause. Although the MOU stipulated a trial period ending 31 December 2007, the petitioner unilaterally extended it until its termination on 25 September 2009, after which the respondent commenced legal proceedings in Brussels. The petitioner invoked the arbitration clause and sought appointment of a sole arbitrator under Sections 11(4) and 11(6) of the Arbitration and Conciliation Act, 1996. The respondent contended that the MOU had expired in 2007 and the arbitration clause could not cover the later disputes. The Court held that the MOU and its arbitration clause remained valid and survived termination under Section 16(1) of the Act, and that the Chief Justice of India is empowered to determine the existence of an arbitration agreement. Consequently, the Court appointed Justice R.V. Raveendran as sole arbitrator and disposed of the arbitration petition.
Issues considered
- Whether a valid arbitration agreement exists despite the termination or expiry of the underlying MOU
- Whether disputes arising after the termination of the MOU fall within the scope of the arbitration clause
- Whether the Chief Justice of India (or his designate) has jurisdiction to decide the existence of an arbitration agreement under Section 11
- Whether Section 16(1) of the Arbitration and Conciliation Act, 1996 renders the arbitration clause independent of the contract’s termination
- Whether appointment of a sole arbitrator under Sections 11(4) and 11(6) is appropriate in the present circumstances
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11(4), s. 11(5), s. 11(6), s. 11(9), s. 16(1)(a), s. 16(1)(b)
Subjects
Judgment
(2011) 13 (ADDL.) S.C.R. 359
M/S. REVA ELECTRIC CAR CO. P. LTD. A
v.
M/S. GREEN MOBIL
(Arbitration Petition No.18 of 2010)
NOVEMBER 25, 2011.
B
[SURINDER SINGH NIJJAR, J]
ARBITRATION AND CONCILIATION ACT, 1996:
s.11 (4), (5), (6) and 9 - Decision as to existence of a valid c
arbitration - HELD: It is for Chief Justice of India/his designate
to decide about the existence of a valid arbitration agreement
- In the instant case, the MOU contained an arbitration clause,
and there existed a valid arbitration agreement - The contract
existed till the date of its termination - Therefore, it cannot 0
be said that the disputes arising between the parties cannot
be referred to Arbitral Tribunal - The disputes have arisen in
relation to the termination of the MOU and the consequences
thereof - Such disputes would be clearly covered under the
arbitration clause - Clearly, therefore, the disputes raised bx E
the petitioner needs to be referred to arbitration - Under the
arbitration clause, a reference was to be made· that the
disputes were to be referred to a single arbitrator - Since the
parties have failed to appoint an arbitrator under the agreed
procedure, it is necessary to appoint an arbitrator- In exercise
of powers u/s 11 (4) and (6) of the Act, read with Paragraph 2 F
of the Scheme of 1996, arbitrator is appointed to adjudicate
the disputes that have arisen between the parties -
Appointment of the Arbitrators by the Chief Justice of India
Scheme, 1996 - Para 2.
G
s.16(1)(a) - Arbitration agreement - Scope of - HELD:
Section 16(1)(a) provides that an arbitration clause which
forms part of the contract shall be treated as an agreement
independent of the other terms of the contract - Even on the
359 H
360 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A termination of the contract, the arbitration agreement would
still survive - By virtue of s.16(1)(b), it continues to be
enforceable notwithstanding a declaration of the contract
being null and void - In view of the provisions contained in s.
16(1) of the Act, it cannot be said that with the termination of
B the MOU, the arbitration clause would also cease to exist.
The petitioner filed the instant application for
appointment of arbitrators stating that memos of
understanding (MOU) were entered· into between the
parties on 25.9.2007, 22.4.2008, 24.8.2008 and 1.4.2009 for
C supply of cars to the respondent to be sold in Belgium
· Region. However, as the respondent did not have the
necessary resources to build up the brand of the
petitioner, the latter through e-mail dated 25.9.2009
terminated the contract and asked the respondent to
D immediately cease the sales and marketing activities on
its behalf. The petitioner stated to have received a Writ
of Summons dated 14.1.2010 of legal proceedings
initiated by the respondent in the Commercial Court at
Brussels in Belgium claiming damages on ac:count of
E termination of fhe MOU dated 25.9.2007. The petitioner
thereafter issued' a notice dated 24.3.2010 to the
respondent invoking the arbitration clause of the MOU.
The respondent in its reply dated 7 .4.2010 denied
existence of any contractual relationship between the
· F parties on the date of termination of MOU on 25.9.2009.
The petitioner filed an arbitration application uls 9 of the
Arbitration and Conciliation Act 1996 before_the Court of
Principal· City Civil and Sessions Judge, Bangalore
praying for an order of injunction restraining the
G respondent from proceeding with the legal proceedings
in the Commercial Court at Brussels, Belgium. The
petitioner was granted a of temporary injunction.
Thereafter the petitioner filed the instant application.
The stand of the respondent was that the MOU dated
H 25.9.2007 expired on 31.12.2007, as it related to the "Test
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 361
and Trial period" which came to end on 31.12.2007 after A
which the parties decided to enter into a distribution
agreement which was sent by the petitioner to the
respondent on 15.11.2007 i.e. after 15 days prior to the
expiry of MOU. Therefore, the arbitration clause relied
ijpon by the petitioner did not cover any disputes/claims B
that relate to any period beyond 31.12.2007.
Disposing of the petition, the Court
Held: 1.1 In a petition u/s 11 (4),(5),(6) and (9) of the
Arbitration and Conciliation Act, 1996, it is for the Chief C
Justice of India/his designate to decide about the
existence of a valid arbitration agreement. [para 19] [376-
A-B]
A.P. Tourism Development Corporation Ltd. Vs. Pampa o
=
Hotels Ltd. 2010 (4) SCR 942 2010 (5) SCC 425; and Alva
Aluminium Limited, Bangkok Vs. Gabriel India Limited 2010
(13) SCR 803 = 2011 (1) SCC 167; Brigadier Man Mohan
Sharma, FRGS (Retd.) Vs. Lieutenant General Depinder
Singh 2008 (16) SCR 701 =2009 (2) SCC 600; National E
Insurance Company Limited Vs. Boghara Polyfab Private
Limited 2008 (13) SCR 638 = 2009(1) SCC 267; and SBP
& Co. Vs. Patel Engineering Ltd. & Anr. 2005 (4) Suppl.
=
SCR 688 2005 (BJ sec 618 - relied on
1.2 There is no dispute that the parties had entered F
into a legally valid and enforceable MOU dated 25.9.2007.
There is also no dispute that Clause 11 provides that the
disputes arising between the parties, at any time, in
relation to the MOU, shall be referred to arbitration. Clause
(2) of the MOU, undoubtedly, fixes the trial period upto G
31.12.2007. However, the clause also provides that the
petitioner may unilaterally decide to extend the MOU, if it
considers necessary. The correspondence between the
parties would show that the petitioner had proposed a
draft distribution agreement to the respondent for H
;
362 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
~ Adiscussion. Thereafter, a series of e-mails were
exchanged between the parties, but making it apparent
that no final consensus was reached. It would, therefore,
appear that the MOU was duly extended till it was
terminated as averred by the petitioner. [para 20) [376-C-
B E]
1.3 The petitioner has categorically pleaded that the
MOU was terminated on 25.9.2009 and has placed on
record the e-mail dated 25.9.2009 in which it is clearly
stated that MOU was entered into on 25.9.2007 for a test
C period of six months from the date of arrival of the trial
cars. It is further stated that.this period was extended on
an informal and voluntary basis by the petitioner for a
period extending to two years from the date of signing
of the MOU. During this two years period, a total of 15
D REVA cars have been sold and as the respondents did
not have in place the necessary resources to build the •
REVA brand and to launch the M1 v~hicles introduced by
REVA at the Frankfurt IAA, the respondent was asked to
immediately cease all sales and marketing activities on
E behalf of REVA brand. This termination of the agreement
has been acknowledged by the respondents in its e-mail
dated 7.10.2009. A perusal of this e-mail would also
demonstr~te that the disputes had clearly arisen between
the parties at that time. Clearly, therefore, the MOU has
F been extended till its termination on 25.9.2009. It is also
evident that the parties had failed to reach any fresh
agreement with regard to sale of REVA cars in Europe by
the respondents. The pleadings and the material on
record has clearly established that there was ai valid
G arbitration agreement incorporated in Clause 11 of the
MOU. [para 21] [376-F-H; 377-A-E]
2.1 The claims made by the respondents before the
Court at Brussels, clearly pertained to the contract under
the MOU dated 25.9.2007 which was terminated on
H 25.9.2009. It would be for the Arbitral Tribunal to decide
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 363
as to whether claims made are within the arbitration A
clause. The Arbitral Tribunal would also have to decide
the merits of the claim put forward by the respective
parties. [para 25 and 27] [379-D-F-G)
Bharat Petroleum Corporation Ltd. Vs. Great Eastern
Shipping Co. Ltd. 2007 (11 ) SCR 117 = (2008 (1) sec 503 B
- referred to.
2.2 The conclusion is inescapable that
notwithstanding the initial period under the MOU expiring
by 31.12.2007, the same was extended by the petitioner C
in exercise of its discretion under Clause (2) of the MOU.
The extended MOU was terminated only on 25.9.2009.
Therefore, it cannot be said that the disputes arising
between the parties cannot be referred to the Arbitral
Tribunal. The disputes have arisen in relation to the D
termination of the MOU and the consequences thereof.
Such disputes would be clearly covered under the
Arbitration clause which provides that in the event of any
dispute or difference arising at any time between the
parties in relation to the agreement shall be referred to a E
Sole Arbitrator. The clause is clearly not limited to the
disputes relating only to the initial period of the MOU till
31.12.2007. [para 30] [381-F-H; 382-A-B]
2.3 Irrespective of whether the MOU is now in
existence or not, the arbitration clause would survive. F
The disputes that have arisen between the parties clearly
pertain to the subject matter of the MOU. [para 31) [382-
B-C; 383-E]
Everest Holding Limited Vs. Shyam Kumar Shrivastava G
& Ors. 2008 (14) SCR 1221 =2008 (16) &CC 774 - relied
on·
2.4 Even assuming that MOU was not extended
beyond 31.12.2007, it would make little difference. Section
H
364 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A 16(1 )(a) of the Act provides that an arbitration clause
which forms part of the contract shall be treated as an
agreement independent of the other terms of the contract.
The plain meaning of the said clause would tend to show
that even on the termination of the agreement/contract,
B the arbitration agreement would still survive. To ensure
that there is no misunderstanding, s. 16(1 )(b) further
provides that even if the arbitral tribunal concludes that
the contract is null and void, it should not result, as a
matter of law, in an automatic invalidat,ion of the
c arbitration clause. By virtue of s.16(1)(b), it continues to
be enforceable notwithstanding a declaration of the
contract being null and void. In view of the provisions
contained in s. 16(1) of the Act, it cannot be said that with
the termination of the MOU on 31.12.2007, the arbitration
clause would also cease to exist. [para 33-34] [383-F-H;
0
385-A-D]
UNCITRAL Model Law - referred to.
2.5 In the instant case, the disputes that have arisen
E between the parties clearly relate to the subject matter of
the relationship between the parties which came into
existence through the MOU. Clearly, therefore, the
disputes raised by the petitioner need to be referred to
arbitration. Under the arbitration clause, a reference was
F to be made that the disputes were to be referred to a
single arbitrator. Since the parties have failed to appoint
an arbitrator under the agreed procedure, it is necessary
for this Court to appoint an arbitrator. In exercise of
powers u/s 11 (4) and (6) of the Act, read with Paragraph
G. 2 of the Appointment of Arbitrator by the Chief Justice of
India Scheme, 1996, the Sole Arbitrator is appointed to
adjudicate the disputes that have arisen between the
parties, on such terms and conditions as the Sole
Arbitrator deems fit and proper. [para 34-35] [385-D-H;
386-A] .
H
REVA ELECTRIC CAR. CO. P. LTD. v. GREEN MOBIL 365
Case Law Reference: A
2007 (11) SCR 117 relied on para 15
2008 (14) SCR 1221 relied on para 15
2008 (16) SCR 701 relied on para 16
B
2008 (13) SCR 638 relied on para 16
2005 (4) Suppl. SCR 688 relied on para 16
2010 (4) SCR 942 relied on para 18
2010 (13) SCR 803 relied on para 18 c
2007 (11) SCR 117 referred to para 28
CIVIL ORIGINAL JURISDICTION : Arbitration Petition No.
18 of 2010.
D
Under Sections 11 (4) and 6 of the Arbitration and
Conciliation Act, 1996.
P.S. Narasimha, Vyapak Desai, P.V. Dinesh, Cherrie
Alexander for the Petitioner.
E
Tasneem Ahamadi, Sudhir Kumar Gupta, Manish Gupta
for the Respondent.
The Order of the Court was delivered by
ORDER F
SURINDER SINGH NIJJAR, J. 1. The petitioner has filed
the present application under Sections 11 (4) and (6) of the
Arbitration and Conciliation Act, 1996 read with paragraph 2
of the Appointment of the Arbitrators by the Chief Justice of
India Scheme, 1996. It is stated that the parties had entered G
into a legally valid and enforceable Memorandum of
Understanding ('MOU') dated 25th September, 2007,
providing, inter alia, for the respective obligation of both the
parties in connection with the marketing of the cars of the
petitioner. :rhough the term of the MOU was till December, H
366 SUPREME COURT REPORTS [2011] 13 (ADDL.) $.C.R.
A 2007, it was extended by the acts of the parties in terms of
Clause 2 of the MOU.
2. The petitioner makes a reference to various requests
made by the respondent for supply of cars in terms of MOU on
22nd April, 2008; 24th August, 2008; and 1st April, 2009. The
8 petitioner further claims that some time in September 2009,
disputes arose between the parties. Numerous e-mails were
exchanged between the parties, apart from the personal
discussions between their representatives, touching and
covering the disputes. It is the petitioner's claim that during the
C term of MOU, merely 15 cars of the petitioner had been sold
in the Belgium Region. The petitioner, therefore, claimed that
the respondent did not have in place the necessary resources
to build the brand of the petitioner. Consequently, through e-
mail dated 25th September, 2009 the petitioner requiested the
D respondent to immediately cease sales and marketing
activities on its behalf and take necessary steps of providing
after sales and service to existing car owners, till such time the
petitioner appointed its new distribut x. The petitioner claims
that the aforesaid e-mail duly constituted the termination of the
E contractual relationship between the parties as covered under
the MOU.
3. As a consequence of the aforesaid termination, the
parties have exchanged various e-mails raising claims and
F counter claims on 6th /7th /8th October, 2009.
4. The petitioner further claims to have received a Writ of
Summons dated 14th January, 2010 of legal proceedings
initiated by the respondent in Belgium before the First
Divisional Court, Room A of the Commercial Court in Brussels.
G According to the petitioner, the claims made by the respondent
before the Commercial Court, Brussels disclose that the
respondent instituted the legal proceedings inter alia claiming
damages from the petitioner on account of termination of the
MOU dated 25th September, 2007. On 15th March, 2010, the
H counsel for the respondent sent an e-mail.communi~tion that
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 367
[SURINDER SINGH NIJJAR, J.]
the respondent was willing to negotiate a global settlement with A
the petitioner and that the respondent through its counsel would
be available to discuss any such proposal. According to the
petitioner, the aforesaid communication also acknowledges the
fact that the rights and obligation of both the parties were
covered by the distributorship agreement, i.e. the MOU, which B
stood duly terminated.
5. The petitioner thereafter issued a notice dated 24th
March, 2010 through its counsel in terms of Clause 11 of the
MOU invoking a:rbitration under the MOU and .referring all C
disputes between the parties to arbit.ration. The petitioner in fact
nominated Mr. Justice Jayasimha Babu (Retired) as the Sole
Arbitrator, and failing confirmation by the respondent, as the
arbitrator of the petitioner on the three member Arbitral Tribunal
to be constituted in terms of Clause 11.
D
6. The respondent through its counsel sent a reply to the
notice dated 7th April, 2010 denying existence of any
contractual relationship between the parties on the date of
termination of MOU on 25th September, 2009.
E
7. The petitioner, therefore, filed Arbitration Application
No.576 of 2010 under Section 9 of the Arbitration and
Conciliation Act, 1996 before the Court of the Principal City
Civil & Sessions Judge at Bangalore praying for an order of
injunction restraining the respondent from proceeding with the
legal proceedings initiated before the First Divisional Court,
F
Room A of Commercial Court of Brussels, Belgium.
8. The petitioner had also moved l.A.No.1 in the aforesaid
suit dated 19th April, 2010 seeking an order of temporary
injunction which was granted by the Principal City Civil & G
Sessions Judge at Bangalore on 21st April, 2010. Thereafter
the petitioner has moved the present application for
appointment of the Arbitrator in terms of Clause 11 of the MOU
which reads as under:-
H
368 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A "11. Governing Law and Jurisdiction
i. This MOU shall be construed and enforced in·
accordance with the laws of India.
ii. In the event of any dispute or difference arising at any
B time between the parties hereto as to the construction,
meaning or effect of this Agreement or thing contained
herein or the rights, duties, liabilities and obligations of the
parties hereto in relation to this Agreement, the same shall
be referred to a single arbitrator, in case the parties can
c agree u"pon one (1) within a period of lhirty days upon
being called by a party to do so and failing such
agreement to three (3) arbitrators one (1) each to be
appointed by GREENMOBIL and RECC and the third to
be appointed by the two arbitrators so appointed. The
D award passed by such arbitrator(s) shall be final and
binding on both the parties.
All such arbitration proceedings shall be held in Bangalore
as per the Arbitration and Conciliation Act, 1996 as
amended from time to time."
E
9. In reply to the aforesaid petition, the respondent claimed
that the MOU dated 25th September, 2007 expired on 31st
December, 2007. The petition does not clearly set out the claim
or the period of the claim but the documents and implication
F of the contents of the present petition seem to indicate that the
claim of the petitioner is in respect of the commercial
distribution of the cars which commenced from 1st January,
2008 i.e. after the expiry of Memorandum of understanding. It
is also the plea of the respondent that the MOU relate to a test
G and trial period which came to an end on 31st December,
2007, after which the parties decided to enter into a distribution
agreement which was sent by the petitioner to the respondent
on 15th November, 2007, i.e., 15 days prior to the expiry of the
MOU. Therefore, the arbitration clause relied upon by the
H petitioner does not cover any disputes/claims that relate to any
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL369
[SURINDER SINGH NIJJAR, J.]
period beyond 31st December, 2007. It is further claimed that A
th·e petition is' only a counterblast to the proceedings filed by
the respondent before the Commercial Court at Brussels. This,
according to the respondent, is evident from the fact that the
respondent had instituted the proceedings in the Commercial
Court at Brussels on 14th January, 2010; the petitioner was B
intimated about the said proceedings vide e-mail dated 15th
March, 201 O; and the notice invoking the arbitration clause in
the MOU is dated 24th March, 2010. It is, therefore, clear that
the arbitration clause is invoked only to avoid proceedings
before the Commercial Court at Brussels. It is emphasised that c
the proceedings before the Commercial Court at Brussels
related to the period beyond the MOU when the parties had
commenced work of distributorship or dealership after the test
trial period under the MOU had come to an end.
10. I have heard the learned counsel for the parties. D
11. Mr. Narasimha, learned senior counsel appearing for
the petitioner submits that the averments made by the
respondent in reply to the petition make it abundantly clear that
the disputes pertained tq the MOU dated 25th September, E
2007. According to the learned counsel, there was no fresh
agreement entered into between the parties. Cars were being
supplied to the respondent in terms of Clause 2 of the MOU.
Making a reference to Clause 2, learned counsel submits that
the aforesaid clause makes it clear that the MOU was effective F
for a period of three to six months, from the date of arrival of
the cars in Belgium. This term was to be considered as the trial
period. On completion of the trial period but not later than 3rd
December, 2007, the parties were to mutually decide to
continue the marketing, sales, and service of the work hours G
by the respondent. They were also to enter into a fresh long term
agreement on mutually agreed terms and conditions. He
submits that till the date of the termination of the MOU, no fresh
agreement had been entered into between the parties. Relying
on the last sentence of the Clause 2, Mr. Narasimha submits
H
370 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A that it was the sole discretion of the petitioner to extend the
MOU in case the petitioner believed that the additional time is
required to complete the trial period. The aforesaid portion of
Clause 2 is as under :-
"RECC, at its sole discretion, may decide to extend the
B
MOU if RECC believes that additional time is requir~d to
complete the trial period."
12. He further submits that although the cars were being
supplied to the respondent but the petitioner was not satisfied
C with the prbgress made in the number of cars sold by the
respondent. Therefore, the respondent was constrained ·to
terminate the MOU, after a period of two years from the
commencement.
0 13. According to Mr. Narasimha, respondent has initiated
the proceedings in the Brussels Court only to pre-empt the
initiation of legal proceedings by the petitioner. He points out
that the pleadings in the Writ of Summons, clearly show: that
the respondent was only concerned with the effect of the
termination and not the period of the MOU. Respondent has
E admitted that the contractual relationship started in 2007. The
respondent has admitted that there is no other subsequent
agreement. In Paragraph 18 of the Writ of Summons, the
respondent admits that the contractual relationship was
subsisting till September, 2009. In Paragraph 30, it is admitted
F by the respondent that "the party summoned below terminated
the contract in an untimely and brutal manner on 25th
September, 2009".
14. He points out that the disputes have arisen in relation
G to the termination of the MOU and the consequences thereof.
Such disputes are clearly covered by the arbitration clause
which clearly provides for resolution of disputes through
arbitration. The clause provides that in the event of any dispute
or difference arising at any time between the parties in relation
H to the agreement shall be referred to a Sole Arbitrator. The
REVA ELECTRIC CAR CO. P LTD. v. GREEN MOBIL 371
[SURINDER SINGH NIJJAR, J.)
clause, according to the learned senior counsel, is not limited A
to the disputes relating only to the initial period of the MOU till
31st December 2007.
15. He submits irrespective of whether the MOU is now in
existence or not, the Arbitration clause would survive. He relies
8
on the decisions of this Court in- the cases of Bharat Petroleum
Corporation Ltd. Vs. Great Eastern Shipping Company Ltd. 1
and Everest Holding Limited Vs. Shyam Kumar Shrivastava
& Ors. 2 He further submits that this Court is required to refer
the disputes between the parties to the Sole Arbitrator, without C
any in-depth examination of the disputes. The Court is merely
to be satisfied that the disputes fall within the ambit of the
Arbitration Clause. In support of this submission, he relies on
the judgment of this Court in Brigadier Man Mohan Sharma,
FRGS (Retd.) Vs. Lieutenant General Depinder Singh. 3 He
also relies on the judgment in the case of National Insurance D
Company Limite_d Vs. Boghara Polyfab Private Limited4, in
support of the submission all disputes are such which need to
be decided by the Sole Arbitrator on merits, and can not be
decided by this Court in a petition under Section 11 (4) and 6
of the Arbitration and Conciliation Act, 1996. Learned counsel E
further submits that in accordance with the aforesaid clause the
petitioner had already nominated the Sole Arbitrator. The
respondent has, however, not accepted the aforesaid arbitrator.
At the same time, it had expressed its willingness to negotiate
the global settlement with the petitioner. F
16. On the other hand, Ms. Tasneem Ahamadi, has
submitted that the MOU having come to an end by efflux of time,
there was no question of any termination as claimed by the
petitioner. She further submits that the notice invoking G
arbitration was sent only as a counterblast to the summons
1. 2008 (1) sec 503.
2. 2008 (16) sec 774.
3. 2009 (2) sec 600.
4. 2009 (1) sec 267. H
372 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A receiyed by the petitioner from the Brussels Commercial Court.
Learned counsel further submitted that the disputes which form
the basis of the claim in the Brussels Commercial Court
pertained to a period subsequent to the period covered by the
MOU. The arbitration clause in the MOU relates only to disputes
B which relate to the test and trial period. Hence, an arbitrator can
not be appointed for settlement of disputes which occurs I relate
to a period after 31st December, 2007. The disputes raised
before the Commercial Court at Brussels are not covered by
the arbitration clause in the MOU. She had made a detailed
C reference to numerous e-mails exchanged between the parties
to submit that the parties had in fact entered into a long term
contract. This was only to be reduced to a formal document.
Since the disputes are not covered by the arbitration clause,
there can be no reference. In support of the aforesaid
submission, learned counsel relies on a judgment of this Court '
0
in the case of SBP & Co. Vs. Patel Engineering Ltd. & Anr. 5•
In view of the law laid down in the aforesaid judgment, according
to the learned counsel, the arbitration petition deserves to be
dismissed.
E 17. I have considered the submissions made by the
learned counsel for the parties. It appears that the submissions
made by Ms. Ahamadi that the question with regard to the
existence of a valid arbitration agreement would have to be
decided by this Court, is not without merit. This Court has on a
F number of occasions examined the scope and ambit of the
jurisdiction of the Chief Justice or his designate under Section
11 of the Arbitration and Conciliation Act, 1996. A reference
in this connect.ion can be made to the judgment of this Court in
SBP & Co. (supra) wherein a Constitution Bench of this Court
G has clearly held as under :
"39. It is necessary to define what exactly the Chief Justice,
approached with an application under Section 11 of the
Act, is to decide at that stage. Obviously, he has to decide
H 5. 2005 (8) sec 618.
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 373
[SURINDER SINGH NIJJAR, J.]
his own jurisdiction in the sense whether the party making A
the motion has approached the right High Court. He has
to decide whether there is an arbitration agreement, as
defined in the Act and whether the person who has made
the request before him, is a party to such an agreement. It
is necessary to indicate that he can also decide the B
question whether the claim was a dead one; or a long-
barred claim that was sought to be resurrected and
whether the parties have concluded the transaction by
recording satisfaction of their mutual rights and obligations
or by receiving the final payment without objection. It may c
not be possible at that stage, to decide whether a live claim
made, is one which comes within the purview of the
arbitration clause. It will be appropriate to leave that
question to be decided by the Arbitral Tribunal on taking
evidence, along with the merits of the claims involved in
0
the arbitration. The Chief Justice has to decide whether
the petitioner has satisfied the conditions for appointing
an arbitrator under Section 11 (6) of the Act. For the
purpose of taking a decision on these aspects, the Chief
Justice can either proceed on the basis of affidavits and E
the documents produced or take such evidence or get
such evidence recorded, as may be necessary. We think
that adoption of this procedure in the context of the Act
would best serve the purpose sought to be achieved by
the Act of expediting the process of arbitration, without too
many approaches to the court at various stages of the F
proceedings before the Arbitral Tribunal."
In the case of National Insurance Co. Ltd. (supra), this
Court again examined the question with regard to the scope
of the jurisdiction under Section 11 (6). In doing so, this Court G
explained the ratio of the Constitution Bench in SBP & Co.
(supra). In Para 21 of the Judgment, the power of the Arbitral
Tribunal in cases where the disputes are referred to arbitration
without the intervention of the court has been distinguished from
the power in matters where the intervention of the court is sought H
374 SUPREME COURT REPORTS [2011] 13 (AODL.) S.C.R.
A for appointment of an Arbitral Tribunal. In case where the matters
are sought to be referred to arbitration without the intervention
of the court it has been held that the Arbitral Tribunal can
decide the following questions l:lffecting its jurisdiction: (a)
whether there is an arbitration agreement; (b) whether the
B arbitration agreement is valid; (c) whether the contract in which
the arbitration clause is found is null and void, and if so, whether
the invalidity extends to the arbitration clause also.
18. In matters, where the intervention of the Chief Justice
C of India has been sought for appointment of a sole arbitrator
under Section 11(4), (5) and (6) of the Arbitration Act, 1996,
the Chief Justice or his designate will have to decide certain
preliminary issues. It would be apposite to notice here the
relevant observations made in Para 22, which are as follows :-
D "22. This Court identified and segregated the preliminary
issues that may arise for consideration in an application
under Section 11 of the Act into three categories, that is,
(1) issues which the Chief Justice or his designate is bound
to decide; (i1) issues which he can also decide, that is,
E issues which he may choose to decide; and (iii) issues
which should be left to the Arbitral Tribunal to decide.
22.1. The issues (first category) which the Chief Justice/
his designate will have to decide are:
F (a) Whether the party making the application has
approached the appropriate High Court.
(b) Whether there is an arbitration agreement and whether
the party who has applied under Section 11 of the Act, is
G a party to such an agreement.
22.2. The issues (second category) which the Chief
Justice/his designate may choose to decide (or leave
them to the decision of the Arbitral Tribunal) are:
H (a) Wtiether the claim is a dead (long-barred) claim
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 375
[SURINDER SINGH NIJJAR, J.]
or a live claim. A
(b) Whether the parties have concluded the
contract/transaction by recording satisfaction of their
mutual rights and obligation or by receiving the final
payment without objection.
B
22.3. The issues (third category) which the Chief Justice/
his designate should leave exclusively to the Arbitral
Tribunal are:
(1) Whether a claim made falls within the arbitration c
clause (as for example, a matter which is reserved
for final decision of a departmental authority and
excepted or excluded from arbitration).
(ii) Merits or any claim involved in the arbitration."
D
These observations were further reiterated by this Court
in the case of A.P. Tourism Development Corporation Ltd. Vs.
Pampa Hotels Ltd. 8 • The aforesaid ratio of law has been
reiterated by this Court in Alva Aluminium Limited, Bangkok
Vs. Gabriel India Limited7. Upon consideration of the entire E
case law, it has been observed as follows :-
"18. It is in the light of above pronouncements, unnecessary
to delve any further on this issue. It is clear that once the
existence of the arbitration agreement itself is questioned
F
by any party to the proceeding initiated under Section 11
of the Act, the same will have to be decided by the Chief
Justice/designate as the case may be. That is because
existence of an arbitration agreement is a jurisdictional
fact which will have to be addressed while making an order
on a petition under Section 11 of the Act." G
19. In view of the aforesaid authoritative dicta, the
6. [2010 (5) sec 425.J.
1. 12011 (1) sec 161. H
376 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A submission of Ms. Ahamadi has to be accepted that in a
petition under Sections 11 (4)(5)(6) and (9) of the Arbitration Act,
1996, it is for the Chief Justice of India/his designate to decide
about the existence of a valid arbitration agreement. Now let
me examine the facts in the present case keeping in view the
s aforesaid well settled principles.
20. There is no dispute that the parties had entered into a
legally valid and enforceable MOU dated 25th September,
2007. There is also no dispute that Clause 11 provides that
C disputes arising between the parties, at any time, in relation to
the MOU, shall be referred to arbitration. Clause (2) of the MOU,
undoubtedly, fixes the trial period upto 31st December, 2007.
However, the clause also provides that the petitioner may
unilaterally decide to extend the MOU, if it considers necessary.
The correspondence between the parties would show that the
D petitioner had proposed a draft distribution agreement to the
respondent for discussion. Thereafter, a series of e-mails were
exchanged between the parties, but making it apparent that no
final consensus was reached. It would, therefore, appear that
the MOU was duly extended till it was terminated as averred
E by the petitioner.
21. The petitioner has categorically pleaded that the MOU
was terminated on 25th September, 2009. The petitioner has
placed on record the e-mail dated 25th September, 2009 in
F which it is clearly stated that MOU was entered into on 25th
September, 2007 for a test period of six months from the date
of arrival of the trial cars. It is further stated that this period was
extended on an informal and voluntary basis by the petitioner
for a period extending to two years from the date of signing of
G the MOU. During this two years period, a total of 15 REVA cars
have been sold. It is pointed out-that inspite of the best efforts
of the respondent and the efforts of the petitioner to support the
respondent, following a review of the European operations it
is believed that the respondents do not have in place the
resources to build the REVA brand, invest in the appropriate
H
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 377
[SURINDER SINGH NIJJAR, J.]
infrastructure, obtain necessary fiscal and/or subsidy and A
infrastructure support and are not adequately prepared to
launch the M1 vehicles introduced by REVA at the Frankfurt IAA.
Thereafter it requests the respondents to immediately cease
all sales and marking activities on behalf of REVA brand. This
termination of the agreement has been acknowledged by the B
respondents in its e-mail dated 7th October, 2009. A perusal
of this e-mail would also demonstrate that the disputes had
clearly arisen between the parties at that time. The e-mail
makes a grievance that the respondents had not been notified
of the termination of its dealership activities a few weeks ago C
when it had informed the petitioner of its negotiations with
potential Dutch partners. The respondents also repeated its
disappointment that the win-win soft-landing solution it proposed
on 25th September, 2009 was rejected by the petitioner. Rest
of the correspondence between the parties continues in the
same tenor.. Clearly, therefore, the MOU has been extended till D
its termination on 25th September, 2009. It is also evident that
the parties had failed to reach any fresh agreement with regard
to sale of REVA cars in Europe by the respondents. In my
opinion, the pleadings and the material on record has clearly
established that there was a valid arbitration agreement E
incorporated in Clause 11 of the MOU.
22. This takes me to the second submission of
Ms.Ahamadi that, in any event, the disputes cannot be referred
to arbitration as it pertained to a period subsequent to the term F
of the MOU. Mr.Narasimha has, however, pointed out that
according to the case pleaded by the respondents in the
Brussels Court which is evident from the writ of summons, all
the disputes pertained to the period prior to the termination of
the agreement by the petitioner. The writ of summons clearly G
mentions as follows :
"Whereas the first cars of the make REVA were marketed
in India from June 2001 onwards, then in the UK in 2003
and worldwide from 2007.
H
378 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A That the party summoned below had however promised
the arrival of more performing Lithium batteries that would
be installed in their vehicles from the middle of 2008, as
well as a new or more competitive and more attractive car
model by the end of 2008, the REVA 'NXR'.
B Whereas the contractual relationships between the
petitioner and the party summoned below started in 2007.
Whereas the distribution of the REVA cars by the
petitioner took place in two stage.
c That during an initial period the petitioner ran a pilot project
for the party summoned below to assess the marketing
possibilities of the REVA on the Belgian market.
That after a certain period of time the petitioner became
D an exclusive distributor of REVA cars for the BENULEX."
23. The writ of summons further mentions that the petitioner
had to run a pilot project of three to six months to test the
marketing possibilities of the REVA cars on the Belgium
E market. It is further pleaded that at the end of the test period
and at the latest on 31st December, 2007, the parties had to
decide jointly whether the petitioner would continue to provide
the promotion, sales and service of REVA Cars in Belgium
within the framework of a long-term distribution contract. The
F respondents further pleaded that :-
'Whereas, in spite of the absence of the signing of a written
contract between the parties, the petitioner de facto
became the exclusive distributor of REVA vehicles in the
BENELUX starting the month of January, 2008."
G
24. Thereafter the respondents gave details of the efforts
made by it for marketing of the REVA Cars from January, 2008
onwards. In paragraph 19 of the writ of summons, it is clearly
admitted as follows:-
H
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 379
[SURINDER SINGH NIJJAR, J.)
"Whereas on the 25th of September, 2009, as soon as the A
first REVA cars fitted with Lithium batteries and of the new
REVA NXR model arrive in Belgium the petitioner is going
to be ejected all of a sudden by the party summoned
below.
B
That during a telephone conversation on 25th September,
2009, confirmed in an email of the same date the party
summoned below suddenly announced its decision to
terminate the concession granted to the petitioner for the
Belelux, with immediate effect;
c
That the party summoned below asked the petitioner to
immediately stop the sale and promotion of the REVA cars
as well as the use of the REVA mark."
25. The claims made by the respondents clearly pertained o
to the contract which was terminated on 25th September, 2009.
In paragraph 30 of the writ of summons, it is pleaded as under
"That the parties summoned below terminated the contract
in any untimely and brutal manner on 25th September, E
2009."
26. On the aforesaid basis, the responde_nts claim
compensation and damages amounting to Euro 454,000.
F
27. The aforesaid averments and the material on record
would clearly demonstrate that the disputes that have arisen
between the parties clearly relate to the MOU dated 25th
September, 2007. It would be for the Arbitral Tribunal to decide
as to whether claims made are within the arbitration clause. The G
Arbitral Tribunal would also have to decide the merits of the
claim put forward by the respective parties. In view of the
material placed on record, it would not be possible to accept
the submissions of Ms. Ahamadi that the disputes were beyond
the purview of the arbitration clause.
H
380 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A 28. A similar matter was examined by this Court in the case
of Bharat Petroleum Corporation Ltd. Vs. Great Eastern
Shipping Co. Ltd. 8 In the aforesaid case, an agreement called •
time charter party was entered into between the appellant and
the respondent on 6th May, 1997 for letting on hire vessels for
B a period of two years from 22nd September, 1996 to 3oth June,
1997 and from 1st July, 1997 to 30th June, 1998. It appears
that certain disputes arose between the parties. Thereafter, on
the basis of the correspondence exchanged between the
parties with regard to the disputes, claims and counter claims
c were filed before the Arbltral Tribunal. Issues were duly framed
of which the following three issues may be of some relevance
in the present context viz.
"issue 1.-Whether the Hon'ble Arbitral Tribunal has no
jurisdiction to adjudicate upon the dispute between the
D claimant and the respondent for the period September
1998 to August 1999 irr respect of the vessel Jag Praja
for the reasons stated in Para 1 of the written statement?
issue 2.-Whether there is any common practice that if the
E vessel is not redelivered at the end of the period mentioned
in the time charter the vessel would be governed by the
charter party under which originally it was chartered?
• • • •
F issue 5.-Whether the time charter party dated 6-5-1997
came to an end by efflux of time on 30-8-1998? •
29. The Arbitral Tribunal by its order dated 12th May, 2003
came to the conclusion that the appellant having invoked the
G arbitration clause contained in the charter party agreement
dated 6th May, 1997, which was valid upto 31st December,
1998 and as the dispute between the parties related to the
period subsequent to 31st August, 1998, they had no
jurisdiction to decide the reference. The tribunal held that the
H 8. 12008) c1) sec so3J.
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 381
[SURINDER SINGH NIJJAR, J.]
charter party agreement dated 6th May, 1997 was superseded A
by .a fresh agreement. Therefore, original charter party dated
6th May, 1997 got extinguished. The respondents challenged
the said award before the High Court. Learned Single Judge
set aside the award and held that the Arbitral Tribunal has the
jurisdiction to adjudicate the disputes between the parties as B
the vessel continued to be hired by the appellant for the period
subsequent to 31st August, 1998 on the same terms and
conditions, as were contained in charter party agreement dated
6th May, 1997. It was held that the charter party dated 6th May,
1997 did not come tci an end by efflux of time and it was c
extended by the party on the same terms and conditions.
Correctness of this order was challenged in this Court. On
examination of the entire fact situation, it was held as follows :-
"19. It is, no doubt, true that the general rule is that an offer
is not accepted by mere silence on the part of the offeree, D
yet it does not mean that an acceptance always has to be
given in so many words. Under certain circumstances,
offeree's silence, coupled with his conduct, which takes the
form of a positive act,,.may constitute an acceptance-an
agreement sub silentio. Therefore, the terms of a contract E
between the parties can be proved not only by their words
but also by their conduct."
30. Examining the fact situation in the present case, I am
of the opinion that the conclusion is inescapable that F
notwithstanding the initial period under the MOU expiring by
31st December, 2007, the same was extended by the petitioner
in exercise of its discretion under Clause (2) of the MOU. The
extended MOU was terminated only on 25th September, 2009.
Therefore, it is not possible to accept the submission of Ms. G
Ahamadi that the disputes arising between the parties cannot
be referred to the Arbitral Tribunal. In my opinion, Mr.
Narasimha has rightly submitted that the disputes have arisen
in relation to the termination of the MOU and the consequences
thereof. Such disputes would be clearly covered under the
H
'
382 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A Arbitration clause which provides that in the event of any dispute
or difference arising at any time between the parties in relation
to the agreement shall be referred to a Sole Arbitrator. The
clause is clearly not limited to the disputes relating only to the
initial period of the MOU till 31st December, 2007.
B
31. I also find merit in the submission of Mr. Narasimha
that irrespective of whether the MOU is now in existence or not,
the arbitration clause would survive. The observations made by
this Court in the case of Everest Holding Ltd. (supra) would
clearly support the submission made by the learned senior
C counsel. In the aforesaid case, the parties had entered into a
Joint Venture Agreement·(tor short 'JVA') dated 25th
September, 2003 for the purpose of mining, processing and
export of Iron Ore. On 26th March, 2004, another JVA was
executed between the parties, particularly to iron out certain
D controversy in respect of JVA dated 25th September, 2003.
Article 14.3 of the said JVA contained an arbitration clause
providing that if the parties failed to resolve the matter through
mutual agreement, the dispute shall be reft::1Ted to an Arbitrator
appointed by mutual agreement of the two parties. The stand
E of the petitioner in the aforesaid case was that on 20th
September, 2004, it was shocked and surprised to receive
unwarranted notices for cancellation of JVA. The aforesaid
notice was replied on 6th October, 2004. Since the disputes
between the parties were not resolved, the petitioner invoked
F the arbitration clause. Respondent No. 1 in reply to the notice
refuted the claim of the petitioner and also refused to refer the
matter to arbitration on the ground that the JVA between the
petitioner and the respondent No.1 is not in existence as the
same had been terminated by respondent No.2. It was stated
G that in view of the aforesaid position, there could be no
invocation of Clause 14.3 of JVA.
32. Considering the aforesaid fact situation, this Court
observed that under Clause 14.2, the parties had agreed that
they would use all reasonable efforts to resolve ~he disputes,
H
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 383
[SURINDER SINGH NIJJAR, J.]
controversy or claim arising out of or relating to these A
agreements. Since the parties have failed to resolve their
differences, the same had to be referred to Arbitration under
Clause 14.3. It was held that there is a valid Arbitration
Agreement between the parties as contained in the JVA, which
the parties are required to adhere to and are bound by the B
same. In other words, if there is any dispute between the parties
to the agreement arising out of or in relation to the subject
matter of the said JVA, all such disputes and differences have
to be adjudicated upon and decided through the process of
Arbitration by appointing a mutually agreed Arbitrator. This c
Court observed as follows:-
"Though the JVA may have been terminated and cancelled
as stated. but it was a valid JVA containing a valid
arbitration agreement for settlement of disputes arising out
of or in relation to the subject-matter of the JVA. The D
argument of the respondent that the disputes cannot be
referred to the arbitration as the agreement is not in
existence as of today is therefore devoid of merit."
In my opinion, the aforesaid observations are squarely E
applicable to the facts in the present case. The disputes that
have arisen between the parties clearly pertain to the subject
matter of the MOU.
33. Even if, I accept the submission of Ms.Ahamadi that F
MOU was not extended beyond 31st of December, 2007, it
would make little difference. Section 16(1 )(a) of the Arbitration
and Conciliation Act, 1996 provides that an arbitration clause
which forms part of the contract shall be treated as an
agreement independent of the other terms of the contract. The
plain meaning of the aforesaid clause would tend to show that ·G
even on the termination of the agreement/contract, the
arbitration agreement would still survive. It also seems to be
the view taken by this Court in Everest Holdings Ltd. (supra).
Accepting the submission of Ms.Ahamadi that the arbitration
H
384 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A clause came to an end as the MOU came to an end by efflux
of time on 31st December, 2007 would lead to a very uncertain
state· of affairs, destroying the very efficacy of Section 16(1).
The aforesaid section provides as under :
"16. Competence of arbitral tribunal to rule on its
B
jurisdiction -(1) The arbitral tribunal may rule on its own
jurisdiction, including ruling on any objections with respect
to the existence or validity of the arbitration agreement, and
for that purpose -
c (a) an arbitration clause which forms part of a contract
shall be treated as an agreement independent of
the other terms of the contract; and
(b) a decision by the arbitral tribunal that the contract
D is null and void shall not entail ipso jure the invalidity
of the arbitration clause."
. 34. The aforesaid provision has been enacted by the
legislature keeping in mind the provisions contained in Article
16 of the UNCITRAL Model Law. The aforesaid Article reads
E as under:-
"Article 16 - Competence of arbitral tribunal to rule on its
jurisdiction -
(1) The arbitral tribunal may rule on its own jurisdiction,
F
including any objections with respect to the existence or
validity of the arbitration agreement. For that purpose, an
arbitraiion clause which forms part of a contract shall be
treated as an agreement independent of the other terms
of the contract. A decision by the arbitral tribunal that the
G contract is null and void shall not entail ipso Jure the
invalidity of the arbitration clause.
(2) ............................................................ ..
H (3) .............................................................. :
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL 385
[SURINDER SINGH NIJJAR, J.]
Under Section 16(1 ), the legislature makes it clear that A
while considering any objection with respect to the existence
or validity of the arbitration agreement, the arbitration clause
which formed part of the contract, has to be treated as an
agreement independent of the other terms of the contract. To
ensure that there is no misunderstanding, Section 16(1)(b) B
further provides that even if the arbitral tribunal concludes that
the contract is null and void, it should not result, as a matter of
law, in an automatic invalidation of the arbitration clause.
Section 16(1)(a) presumes the existence of a valid arbitration
clause and mandates the same to be treated· as an agreement c
independent of the other terms of the contract. By virtue of
Section 16(1)(b), it continues to be enforceable notwithstanding
a declaration of the contract being null and void. In view of the
provisions contained in Section 16(1) of the Arbitration and
Conciliation Act, 1996, it would not be possible to accept the 0
submission of Ms.Ahmadi that with the termination of the MOU
on 31st December, 2007, the arbitration clause would also
cease to exist. As noticed earlier, the disputes that have arisen
between the parties clearly relate to the subject matter of the
relationship between the parties which came into existence
through the MOU. Clearly, therefore, the disputes raised by the E
petitioner needs to be referred to arbitration. Under the
arbitration clause, a reference was to be made that the disputes
were to be referred to a single arbitrator. Since the parties have
failed to appoint an arbitrator under the agreed procedure, it
is necessary for this Court to appoint the Arbitrator. F
35. In exercise of my powers under Section 11 (4) and (6)
of the Arbitration and Conciliation Act, 1996 read with
Paragraph 2 of the Appointment of Arbitrator by the Chief
Justice of India Scheme, 1996, I hereby appoint Hon.Mr.Justice G
R.V. Raveendran, R/o 8/2, Krishna Road, Basavangudi,
Bangalore, Former Judge of the Supreme Court of India, as
the Sole Arbitrator to adjudicate the disputes that have arisen
between the parties, on such terms and conditions as the
H
386 SUPREME C.OURT REPORTS (2011] 13 (ADDL) S.C.R.
A learned Sole Arbitrator deems fit and proper. Undoubtedly, the
learned Sole Arbitrator shall decide all the disputes arising
between the parties without being influenced by any prima facie
opinion expressed in this order, with regard to the respective
claims of the parties.
B
36. The registry is directed to communicate this order to
the Sole Arbitrator to enable him to enter upon the reference
and decide the matter as expeditiously as possible.
37. The Arbitration Petition is accordingly disposed of.
c
R.P. Arbitration Petition disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.