M/S. RAM BARAI SINGH & CO.versusSTATE OF BIHAR & ORS.
- Citation
- 2014 INSC 881
- Decided
- 17 December 2014
- Disposal
- Appeal(s) allowed
- Bench
- M Y EQBAL
Holding
A constitutional remedy by way of a writ petition is always available and an arbitration clause cannot ipso facto render the writ petition non‑maintainable.
Summary
M/s. Ram Bara Singh & Co. appealed against a Division Bench order that set aside a Patna High Court judgment allowing its writ petition under Art. 226. The respondents argued that an arbitration clause in the 1989 contract made the writ petition non‑maintainable, even though the contract had been completed and payments made years earlier. The Single Judge had allowed the writ petition, granting interest on delayed refund of a security deposit and remanding the labour‑escalation cost issue. The Division Bench reversed this, citing the arbitration clause as an alternative remedy. The Supreme Court held that a constitutional remedy via a writ petition is always available and an arbitration clause does not ipso facto render a writ petition non‑maintainable, especially when the parties did not raise the arbitration objection and the contract was no longer in existence. Consequently, the Supreme Court set aside the Division Bench order and restored the Single Judge’s judgment.
Issues considered
- Does the existence of an arbitration clause in a contract render a writ petition under Art. 226 non‑maintainable?
- Was the original contract still subsisting such that arbitration could be invoked, given that the work was completed and payments had been made?
Legislation cited
- Constitution of Indias. Article 226
Subjects
Judgment
A
(2014] 11 S.C.R. 286
M/S. RAM BARAi SINGH & CO.
•
v.
STATE OF BIHAR & ORS.
(Civil Appeal No. 11465 of 2014)
DECEMBE,R 17, 2014
B
[M.Y. EQBAL AND SHIVA KRITI SINGH, JJ.]
Constitution of India, 1951 - Art. 226 - Writ petition by
appellant - No objection taken by respondent as to
C entertainment of writ petition on the ground of availability of
alternative remedy - Writ petition rendered on merits by the
Single Judge of High Court - Letters Patent Appeal by
respondent - Division Bench allowed LPA, setting aside the
order of Single Judge on the ground that an alternative
o remedy by way of arbitration clause could have been resorted
to - On appeal, held: Constitutional remedy by way of writ
petition is always available to an aggrieved party and an
arbitration clause in an agreement between the part;es cannot
ipso facto render a writ petition "not maintainable" - On facts,
E there was no existing agreement because the work had been
completed and payment had already been made, and the final
judgment in the writ petition was rendered on merits - Thus,
order of the Division Bench is set aside and that of the Single
Judge is restored.
F Allowing the appeal, the Court
HELD: 1.1. A constitutional remedy by way of writ
petition is always available to an aggrieved party and an
arbitration clause in an agreement between the parties
G cannot ipso facto render a writ petition "not maintainable"
as wrongly held by the Division Bench. Availability of
alternative remedy is definitely a permissible gmund for
refusal by a writ court to exercise its jurisdiction in
appropriate cases. But once the respondents had not
H 286
• RAM BARAi SINGH & CO. v. STATE OF BIHAR
objected to entertainment of the writ petition on ground of
287
A
availability of alternative remedy, the final judgment
rendered on merits, cannot be faulted and set aside only
on noticing by the Division Bench that an alternative
remedy by way of arbitration clause could have been
resorted to. On facts, there was no existing agreement B
because the work had been completed and payment had
already been made long back. Thus, the order under
appeal is set aside and the judgment and order of the
Single Judge is restored. [Para 12, 13, 14) [291-0-G; 292-C]
State of U.P. & Ors. v. Bridge & Roof Company (India) C
Ltd. 1996 (4) Suppl. SCR 762: (1996) 6 sec 22; ABL.:
International Ltd. & Anr. v. Export Credit Guarantee
Corporation of India Ltd. & Ors. (2004) 3 SCC 553 - referrect
to.
D
Case Law Reference:
1996 (4) Suppl. SCR 762 referred to Para 10
(2004) a sec 553 referred to Para 10
CIVIL APPELLATE JURISDICTION : Civil Appeal No. E
11465 of 2014.
From the Judgment & Order dated 12.01.2011 of the High
Court of Judicature at Patna in LPA No. 762 of 2009.
F
Gaurav Agrawal for the Appellant.
Manish Kumar (for Gopal Singh) for the Respondents.
The Judgment of the Court was delivered by
G
SHIVA KIRT! SINGH, J. 1. Heard the parties. Leave
granted.
2. This appeal is directed against final judgment and order
• dated 12.01.2011 passed by the Division Bench of Patna High H
288 SUPREME COURT REPORTS [2014] 11 S.C.R.
A Court in L.P.A. No.762 of 2009 whereby the Letters Patent
Appeal preferred by the respondents herein was allowed and
•
order of the learned Single Judge dated 18.02.2009 in Writ
Petition bearing C.W.J.C. No.10173 of 2008 was set aside on
the sole ground that there was an arbitration clause in an
B agreement between the ·parties and since such alternative
remedy was not availed by the appellant, the writ petition itself
was not maintainable.
3. Learned counsel for the appellant has assailed the
aforesaid order of the Division Bench on facts as well as on
C law. On law, it was contended that the writ petition could not
have been held not maintainable, more so when no such
objection was taken by the other side. On facts, it was submitted
that the agreement noticed by the Division Bench no doubt
D contained an arbitration clause entitling either of the parties to
invoke arbitration by the concerned Superintending Engineer
in case of any dispute arising out of the agreement but the
Division Bench failed to notice that the agreement itself was
no longer in existence because the work was completed long
back and payments including payment on account of labour
E escalation costs amounting to Rs.9.53 lacs was paid in
February 1992. Thus, according to the appellant, the agreement
dated 06.02.1989 had worked itself out and it was much later
that a dispute arose when the respondent authorities withheld
the security amount of the appellant of Rs.30 lacs for a long
F period. On persistent demand, Rs.20 lacs out of the security
amount, was returned after 10 years in December 2002 and
that too without any interest. At that stage appellant came to
know that Engineer-in-Chief vide an order dated 09.06.2001
had ordered for making a recovery of Rs.9.53 lacs from the
G appellant which had been paid long back on account of labour
escalation cost.
4. The appellant preferred a writ petition bearing
C.W.J.C.No.3686 of 2005 to claim the interest on undue delay
H in refunding the security deposit and against the direction for
• RAM BARAi SINGH & CO. v. STATE OF BIHAR 289
[SHIVA KIRTI SINGH, J.]
recovery of labour escalation cost. The respondents did not A
raise plea of arbitration clause and that writ petition was
disposed of on 20.09.2006 allowing 12% interest on account
of delay in payment of security amount. The issue of labour
escalation cost was remanded back to the concerned
Engineer-in-Chief who was directed to pass a reasoned order B
after hearing the appellant or his representative, within a fixed
period. The appellant was granted liberty to seek his remedy
if he was aggrieved by the order that may be passed by the
Engineer-in-Chief.
5. The respondents preferred a Letters Patent Appeal
c
bearing No.877 of 2006 in which also they did not raise the
issue of alternative remedy by way of arbitration clause. The
LPA was disposed of on 11.12.2007 with the following
direction :
D
" ........ Since the matter is going on remand, the State has
to apply its mind afresh to the facts and circumstances of
the case and, therefore, the direction, as quoted above
would be juxtaposition to the order of remand. The question
of payment of interest by either side, however, will abide E
by the ultimate determination of the question by the State
of Bihar.
It goes without saying that the matter would be
examined and re-determined by the State expeditiously." F
6. The Engineer-in-Chief passed a fresh order on
21.05.2008 against the appellant over-ruling the various
grounds and objections raised by the appellant in his
representation relating to merits of the matter as well as
jurisdiction of the Engineer-in-Chief who, according to G
appellant, had no role in the issue which was to be finalized at
the stage of Executive Engineer and the Superintending
Engineer. The appellant challenged the order of Engineer-in-
Chief through writ petition bearing C.W.J.C. No.10173 of 2008
H
290 SUPREME COURT REPORTS [2014] 11 S.C.R.
A which was allowed by the learned Single Judge on 18.02.2009
•
by a reasoned order. There is no dispute that respondents filed
a counter affidavit but did not raise any objection of alternative
remedy by way of an arbitration clause in the agreement dated
06.02.1989.
B
7. The learned Single Judge allowed the writ petition
preferred by the appellant by setting aside the order of the
Engineer-in-Chief dated 21.05.2008. The Court found that the
Engineer-in-Chief had raised demand of interest in the yea_r
C 2008 along with refund of labour escalatior. cost only to offset
the State's liability to pay interest on refund of secllrity deposit
after a delay of about 10 years. Thus the action of the
respondents was held to be for ulterior reasons and objection
to labour escalation cost after a long gap from its actual
payment was held to be arbitrary and unreasonable.
0
8. The aforesaid order of the learned Single Judge dated
18.02.2009 was set aside by the Division Bench by the order
under appeal on the ground already noticed earlier.
E 9. We find ourselves in agreement with case of the
appellant that the Division Bench failed to notice the relevant
facts including the history of earlier litigation. It also failed to
notice that the agreement itself had worked out long back and
in the earlier round of litigation as well as in the present round -
F the respondents never raised any objection on the basis of
arbitration clause.
10. The Division Bench noticed the judgment of this Court
in the case of State of U.P. & Ors. v. Bridge & Roof
G Company (India) Ltd. (1996) 6 sec 22 as well as in the case
of ABL International Ltd. & Anr. v. Export Credit Guarantee
Corporation of India Ltd. & Ors. (2004) 3 SCC 553 for
coming to the conclusion that where the contract itself provides
an effective alternative remedy by way of reference to
H arbitration, it is good ground for declining to exercise
• RAM BARAi SINGH & CO. v. STATE OF BIHAR
[SHIVA KIRTI SINGH, J.]
291
extraordinary jurisdiction under Article 226 of the Constitution A
of India and that the Court will not permit recourse to other
remedy without invoking the remedy by way of arbitration,
"unless, of course, both the parties to the dispute agree on
another mode of dispute resolution."
B
11. In our considered view, the aforesaid two decisions
did not warrant setting aside of the judgment of learned Single
Judge without going into merits and dismissing the writ petition
at appellate stage on ground of alternative remedy when no
such objection was taken by the respondents either before the C
writ court or even in the Memorandum of Letters Patent Appeal.
12. In our view, a constitutional remedy by way of writ
petition is always available to an aggrieved party and an
arbitration clause in an agreement between the parties cannot
ipso facto render a writ petition "not maintainable" as wrongly D
held by the Division Bench. Availability of alternative remedy
is definitely a permissible ground for refusal by a writ court to
exercise its jurisdiction in appropriate cases. But once the
respondents had not objected to entertainment of the writ
petition on ground of availability of alternative remedy, the final E
judgment rendered on merits cannot be faulted and set aside
only on noticing by the Division Bench that an alternative remedy
by way of arbitration clause could have been resorted to.
13. In our view, learned counsel for the appellant has made F
out a case for setting aside the order under appeal both on the
facts noticed above which show that there was no existing
agreement because the work had been completed and
payment had already been made long back and also on the
question of law raised in this appeal that a constitutional G
remedy through a writ petition cannot be held to be not available
and not maintainable on account of an alternative remedy. It is
for the writ court to consider whether in an appropriate case,
writ petitioner should be relegated to avail alternative remedy
or not. But once writ petition is heard at length and decided H
I
A
292 SUPREME COURT REPORTS (2014] 11 S.C.R.
against one or the other party on merits, such a decision/order
cannot be held to be bad in law only on the ground that writ
•
petition was not maintainable due to availability of alternative
remedy.
8 14. Having considered the matter on merits as reflected
by the order of the learned Single Judge, we find sufficient merit
in this appeal and hence it is allowed. The order under appeal
is set aside and the judgment and order of the learned Single
Judge is restored along with a cost of Rs.25,000/- (Rupees
C twenty five thousand) to be paid by the respondents to the
appellant within two months.
Nidhi Jain Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.