M/S. INDUSTRIAL PROMOTION AND INVESTMENT CORPORATION OF ORISSA LIMITEDversusM/S. TUOBRO FURGUSON STEELS PRIVATE LIMITED & OTHERS
- Citation
- 2011 INSC 834
- Decided
- 5 December 2011
- Disposal
- Appeal(s) allowed
- Bench
- AFTAB ALAM
Holding
A contract of sale, once acted upon by payment of part consideration and transfer of possession, cannot be unilaterally rescinded, and the corporation is entitled to retain the part consideration and recover the balance with interest.
Summary
The Industrial Promotion and Investment Corporation of Orissa (the appellant) took over a foundry unit under Section 29 of the State Financial Corporation Act, 1951 and advertised it for sale on an "as is where is" basis. The respondents offered Rs.40 lakh, paid a down‑payment of Rs.8 lakh, and took possession of the unit, with the balance Rs.32 lakh to be paid in installments with interest as stipulated in the sale letter. The respondents failed to execute the required loan and sale documents and later sought a refund of the Rs.8 lakh, alleging missing machinery and other liabilities. The High Court ordered a refund with interest, but the Supreme Court held that a valid contract had been formed, the part consideration was earned, and the respondents remained liable for the balance and interest; consequently, the corporation was entitled to retain the Rs.8 lakh and recover the balance. The Court reversed the High Court order, dismissed the writ petition, and allowed the appeal.
Issues considered
- The existence and enforceability of the contract of sale despite the respondents' failure to execute subsequent documentation.
- Whether the part consideration of Rs.8 lakh paid by the respondents was refundable under the circumstances.
- The statutory right of the corporation to take possession of the unit under Section 29 of the State Financial Corporation Act, 1951 upon default.
- The applicability of forfeiture of earnest money versus part consideration in a completed sale.
Legislation cited
Subjects
Judgment
[2011] 13 (ADDL.) S.C.R. 445
M/S. INDUSTRIAL PROMOTION AND INVESTMENT A
CORPORATION OF ORISSA LIMITED
v.
M/S. TUOBRO FURGUSON STEELS PRIVATE LIMITED &
OTHERS
(Civil Appeal No.1850 of 2007) B
DECEMBER 5, 2011
[AFTAB ALAM AND RANJANA PRAKASH DESAI, JJ.]
State Financial Corporation Act, 1951: s.29 - Contract C
of sale -Corporation took over a Foundry Unit after its original
promoters defaulted in payment of its dues - Publication of
advertisement for sale of Unit - Sale of Unit to respondent
on down payment of Rs. 8 lacs - Balance amount of Rs.32
lacs was to be paid on installments - However, after taking D
possession of the Unit, respondent did not take steps to
complete the documentation as required in the sale letter -
Notice issued uls.29 to respondent and assets of the Unit
taken over by the Corporation - Writ petition by respondent
- High Court directed the Corporation to refund to the E
respondent Rs. 8 lacs along with interest - On appeal, held:
High Court did not even refer to the sale advertisement,
stipulations made in the sale Jetter and correspondences
between the parties and completely overlooked that the
parties, with their eyes widely open, had entered into the F
contract for sale of the Unit which was subject to the terms and
conditions clearly spelled out in the advertisement and in the
sale letter; that in furtherance of the contract, payment was
made and possession of the Unit changed hands - Both
sides had acted on the basis of the contract, changing their G
respective positions and assuming rights and obligations
against each other - The contract having been acted upon,
it could not be unilaterally abrogated on the sweet will of any
of the two sides - Jn terms of the contract, the respondents
445 H
446 SUPREME COURT REPORTS [2011) 13 (ADDL.) S.C.R.
A were obliged to pay the balance consideration amount of
Rs.32 lacs along with interest as provided in the sale letter -
In default of payment, it was the statutory right of the
Corporation to take possession of the Unit uls. 29 of the Act
- Corporation had not only the right to retain Rs. 8 lacs paid
B to it as part consideration but also to realise the balance
amount of consideration, in accordance with law - Order of
the High Court not sustainable.
The appellant-Corporation took over a Foundry Unit
C situated along with land, building, plant and machineries
under Section 29 of the State Financial Corporation Act,
1951, as its original promoters defaulted in payment of its
dues. The taken-over Unit was put to sale by publishing
advertisement in newspapers inviting offers for purchase
of the Unit. In the advertisement, it was stipulated that the
D sale would be on 'AS IS WHERE IS' basis. The intending
purchasers were allowed inspection of the Unit-on-sale.
In response to the advertisem1mt, the respondents
made an offer to purchase the Unit for a total
E consideration of Rs.40,00,0001- with down payment of
Rs.8,00,0001-. The offer made by the respondents was
accepted and the Corporation issued the sale letter. It
was stated in the sale letter that possession of the Unit
would be handed over to the respondents on payment
F of Rs.8,00,0001- and the balance amount of Rs.32,00,0001
- would be treated as fresh loan to respondent no.1 to be
repaid within a period of 6 years in quarterly instalments
after a moratorium of 18 months with interest at the rate
of 18 per cent per annum from the date of handing over
G the physical possession of the Unit. The sale formalities
were required to be completed within 30 days from the
date of issue of the letter. It was further stipulated in the
letter that the sale would lapse and the earnest money
forfeited if the documents were not executed within the
H prescribed time.
INDUS. PROM. AND INVES. CORPN. OF ORISSA LTD. v. 447
TUOBRO FURGUSON STEELS PVT. LTD.
In furtherance of the sale, respondents made A
payment of Rs.8,00,000/- to the appellant and following
·- the payment, possession of the Unit was made over to
respondents .. Before the delivery of possession, the
Director and other technical persons of the respondent
company verified/compared the assets with the inventory B
of assets item-wise and thereafter, took over possession
of the assets in presence of officers of the Corporation,
OSFC and 581 and the security personnel.
After taking possession of the Unit, the respondents
did not take any step to complete the documentation with C
IPICOL and OSFC as required in clause 7 of the sale
letter. The appellant then wrote number of letters asking
the respondents to execute the documents/loan
agreement with the Corporation and with the. OSFC. The
respondents, however, went on temporising in the matter. D
Instead of executing the necessary documents, the
respondents wrote to the appellant complaining about
the high rate of interest and requesting to lower it down.
The respondents also made the complaint that the
machineries were in very bad shape and were required E
to be replaced and unless the issue of the rate of interest
was resolved, it was not possible to start the operation
of the factory. The respondents also complained about
the difficulty in getting loans from the bank or other
financial institutions and asked the appellant whether it F
would give its consent to creation of pari passu or
second charge as security for the loan amount advanced
by the financial institutions. It also complained about the
electricity dues and sought the intervention of the
appellant to resolve the difficulties being faced by it. G
The appellant-Corporation once again wrote to
respondents asking them to pay the over due interest of
Rs.3,51,445/- as on March 31, 2000 and to execute the
necessary documents. The respondents did not make
H
448 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A any payment nor did they take any step to complete the
documentation. Instead, by letter dated July 20, 2001, they
asked the appellant to take back the Unit stating that from
July 31, 2001, they would withdraw the security personnel
engaged by them in the factory premises which was till
8 that date under their control. The appellant issued notice
under Section 29 of the State Financial Corporation Act,
1951 to respondents and took over the assets of the Unit.
The respondents filed a writ petition before the High Court
challenging the taking over of the assets by the appellant.
C The High Court allowed the writ petition and directed the
Corporation to refund to the respondents Rs.8,00,000/
along with interest at the prevailing bank rate that was
received by it as part of the sale consideration. The
instant appeal was filed challenging the order of the High
Court.
D
Allowing the appeal, the Court
HELD: 1. The case of the respondents, as noted by
the High Court was untenable on its face. Even according
E to the respondents it was only after having taken
possession of the Unit that they found that some vital
parts of the machineries were missing and there were
huge arrears of electricity dues and that the
recommendation for the industrial policy resolution was
not forthcoming. In those circumstances, the
F respondents realised that the Unit was not worth
Rs.40,00,000/·. The respondents went to the High Court
seeking refund of the part consideration money
Rs.8,00,000/- paid by them as if the antecedent acts of the
parties, namely, the issuance of the advertisement, the
G offer made by the respondents followed by negotiations
between the parties and the issuance of the sale letter by
the Corporation, the payment of Rs.8,00,000/· by the
respondents in pursuance of the sale letter followed by
their taking over the possession of the Unit meant
H
INDUS. PROM. AND INVES. CORPN. OF ORISSA LTD. v. 449
TUOBRO FURGUSON STEELS PVT. LTD.
nothing and did not create any rights or obligations in the A
parties. Strangely, the High Court did not even refer to the
sale advertisement, the stipulations made in the sale letter
and the correspondences between the parties. The High
Court completely overlooked that the parties, with their
eyes widely open, had entered into the contract for sale B
of the Unit which was subject to the terms and
conditions clearly spelled out in the advertisement and
in the sale letter; that in furtherance of the contract,
payment was made and possession of the Unit changed
hands. In other words, both sides had acted on the basis c
of the contract, changing their respective positions and
assuming rights and obligations against each other. The
contract having been acted upon, it could not be
unilaterally abrogated on the sweet will of any of the two
sides. In terms of the contract, the respondents were
0
obliged to pay the balance consideration amount of
Rs.32,00,000/- along with interest as provided in the sale
letter. In default of payment it was the statutory right of
the appellant-corporation to take possession of the Unit
under Section 29 of the Financial Corporation Act. In the E
aforesaid facts·and circumstances, there was no ground
for the High Court, to interfere in favour of the
respondents, much less to directfor refund of the part
consideration money paid by the respondents to the
appellant. [Paras 11-13] [456-A-H; 457 -A-B]
F
2. The question of forfeiture of the earnest money
would arise in case the parties had not acted upon in
furtherance of the sale letter but the matter in this case
went much beyond that stage. The parties agreed for the
sale of Unit for an amount of Rs.40,00,000/- out of which G
the respondents were required to make a down payment
of Rs.8,00,000/-, which they did. On payment of the part
consideration monet, the possession of the Unit was
made over to them. ~he respondents were, thus, under
the legal obligation to pay the balance consideration of H
450 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A Rs.32,00,000/- in instalments and along with interest, as
stipulated in the letter. The Corporation had, therefore,
not only the right to retain Rs.8,00,000/- paid to it as part
consideration but also to realise the balance amount of
consideration, in accordance with law. The order of the
B High Court is completely unsustainable. [Paras 14, 17]
[457-0-G; 458-E]
/sha Marbles vs. Bihar State Electricity Board & Anr.,
(1995) 2 sec 648 - relied on.
C Haryana Financial Corporation v. Rajesh Gupta (2010)1
SCC 655; V.K.Ashokan v. Assistant Excise Commissioner
(2009) 14 sec 85 - held inapplicable.
Case Law Reference:
D (1995) 2 sec 648 relied on Para 15
(2010)1 sec 655 held inapplicable Para 17
(2009) 14 sec 85 held inapplicable Para 17
E CIVIL APPELLATE JURISDICTION : Civil Appeal No.
1850 of 2007. •
From the Judgment and Order dated 29.06.2006 of the
High Court of Orissa at Cuttack in Writ Petition (Civil) No. 1556
of 2003.
F
Raj Kumar Mehta, Antaryami Upadhyay and Dal(id A. for
the Appellant.
Shrish Kumar Mishra and Ajay Kr. Singh for the
G Respondents.
The Judgment of the Court was delivered by
AFTAB ALAM, J. 1. This appeal, at the instance of Mis
Industrial Promotion and Investment Corporation of Orissa
H Limited ("Corporation" for the sake of brevity), is directed
INDUS. PROM. AND INVES. CORPN. OF ORISSA LTD. v. 451
TUOBRO FURGUSON STEELS PVT. LTD. [AFTAB ALAM, J.]
against the judgment and order dated June 29, 2006 passed A
by a Division Bench of the Orissa High Court. By the impugned
judgment, the High Court allowed the Writ Petition'(W.P.(Civil)
No.1556/2003) filed by respondent Nos.1 & 2 (M/s Tuobro
Furguson Steels Private Limited and its Director) and undoing
a contract of sale of an Industrial Unit entered into between the B
parties, directed the appellant to refund Rs.8,00,000/- (Rupees
Eight Lacs), that was paid by the respondents to the appellant
as part of the sale consideration, together with simple interest
at prevailing rates of interest of the State Bank of India on
deposits made by customers during the relevant period.
c
2. The facts relevant to appreciate the rival contentions of
the parties are brief and may be stated thus. A Foundry Unit
situated at Ganeswarpur Industrial Estate, Balasore, by the side
of NH-5, along with land, building, plant and machineries was
taken over by the Corporation under Section 29 of the State D
Financial Corporation Act, 1951, as its original promoters
namely, M/s Josna Casting Centre, defaulted in payment of its
dues. The taken-over Unit was put to sale vide advertisement
dated February 8, 1999 issued in Oriya and English
newspapers inviting offers for purchase of the Unit. A copy of E
the sale advertisement is at Annexure P1 which gives a
complete description of the Industrial Unit along with all the
relevant details. It is significant to note that in the advertisement
it was stipulated that the sale would be on 'AS IS WHERE IS'
basis. Further, the intending purchasers were allowed F
inspection of the Unit-on-sale from February 16 to 27, 1999.
3. In response to the advertisement the respondents made
an offer (revised by letters dated April 12, 1999 and August 5,
1999) to purchase the Unit for a total consideration of G
Rs.40,00,000/- (Rupees Forty Lacs) with down payment of
Rs.8,00,000/- (Rupees Eight Lacs). The offer made by the
respondents was considered by the Advisory and Disposal
Committee of the Corporation, and in acceptance of the offer,
the Corporation issued the sale Jetter dated September 10,
H
4?2 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
.A 1999. A copy of the sale letter is at Annexure P2. In the sale
letter it was stated that possession of the Unit would be handed
over to the respondents on payment of Rs.8,00,000/- (Rupees
Eight Lacs) and the balance amount of Rs.32,00,000/- (Rupees
Thirty Two Lacs) would be treated as fresh loan to respondent
B no.1 to be repaid within a period of 6 years in quarterly
instalments after a moratorium of 18 months with interest at the
rate of 18 per cent per annum from the date of handing over
the physical possession of the Unit. The sale formalities were
required to be completed within 30 days from the date of issue
C of the letter. It was further stipulated in the letter that the sale
would lapse and the earnest money forfeited if the documents
were not' executed within the prescribed time. In clause 2 of the
letter it was once again repeated that the sale was on "AS IS
WHERE IS" basis and no further claim in that respect would
be entertained by the Corporation. In clause 5 it was stated that
D the sale of fixed assets was free from liabilities other than the
deferred payment of loan of Rs.32,00,000/- (Rupees Thirty Two
Lacs) with interest as stated in the earlier paragraph of the
letter. Clause 8 made it clear that the sale did not pre-suppose
sanction of any additional loan in favour of the purchaser for
E operation of the Unit. In clause 9 of the letter it was stated that
though the Corporation would recommend to all concerned to
assist and help the buyer of the Unit (the respondents) but
would not be in any manner responsible if any of the benefits
were not granted to the Unit or if there was delay in grant of
F any of the benefits. It was expressly made clear that the denial
of any benefits to the Unit by any financial organisation or any
other body or delay in grant of any concession or benefit shall
not be a ground for non-payment of the Corporation's dues.
G 4. In furtherance of the sale, respondents made payment
of Rs.8,00,000/- (Rupees Eight Lacs) to the appellant and
following the payment, possession of the Unit was made over
to respondents on September 15, 1999. Before the delivery of
possession, the Director and other technical persons of the
H respondent company verified/compared the assets with the
INDUS. PROM. AND INVES. CORPN. OF ORISSA LTD. v. 453
TUOBRO FURGUSON STEELS Pvr. LTD. [AFTABALAM, J.]
inventory of assets item-wise and thereafter, took over A
possession of the assets on September 15, 1999 in presence
of officers of the Corporation, OSFC and SBI and the security
personnel. The handing over of possession of the Unit was
witnessed by a 'Memo of Delivery of Possession of Assets'
executed both on behalf of the appellant and the respondent B
company. A copy of "the Memo of Delivery of Possession of
Assets" is annexed as Annexure P-3 to the appeal memo.
5. After taking possession of the Unit, the respondents did
not take any step to complete the documentation with IPICOL C
and Orissa State Financial Corporation as required in clause
7 of the sale letter. The appellant then wrote a number of letters
(on October 12, 1999, January4, 2000 and February28, 2000)
asking the respondents to execute the documents/loan
agreement with the Corporation and with the Orissa State
Financial Corporation. The respondents, however, went on D
temporising in the matter. Instead of executing the necessary
documents, the respondents wrote to the appellant complaining
about the high rate of interest and requesting to lower it down.
The respondents also made the complaint that the machineries
were in very bad shape and required to be replaced and unless E
the issue of the rate of interest was resolved, it would not be
possible to start the operation of the factory. The respondents
also complained about the difficulty in getting loans from the
bank or other financial institutions and asked the appellant
whether it would give its consent to creation of pari passu or F
second charge as security for the loan amount advanced by the
financial institutions. It also complained about the electricity
dues and sought the intervention of the appellant to resolve the
difficulties being faced by it.
G
6. On March 24, 2000, the appellant - Corporation once
again wrote to respondents asking them to pay the over due
interest of Rs.3,51,445/- as on March 31, 2000 and to execute
the necessary documents.
7. The respondents did not make any payment nor did they H
454 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R.
A take any step to complete the documentation. Instead, by letter
dated July 20, 2001, they asked the appellant to take back the
Unit stating that from July 31, 2001, they would withdraw the
security personnel engaged by them in the factory premises
which was till that date under their control. On October 12, 2001,
B respondents informed the appellant that a theft had taken place
in the factory premises which was at that time under their
possession. On April 29, 2002, respondents once again wrote
to the appellant that they would withdraw the security personnel
if the assets were not taken over by the appellant within 15 days.
c Faced with the recalcitrant attitude of respondents, the
appellant issued notice under Section 29 of the State Financial
Corporation Act, 1951 to respondents and took over the assets
of the Unit.
8. On February 17, 2003, the respondents went to the High
D Court challenging the taking over of the assets by the appellant.
9. On June 17, 2004, the appellant decided to sell the Unit
along with its assets to Sun Agro Foods & Exports for a
consideration of Rs.17,00,000/- (Rupees Seventeen Lacs) but
E could not hand over possession to the new buyer in view of the
interim order passed by the High Court in the Writ Petition filed
by the respondents. Finally, by the impugned order dated June
29, 2006, the High Court allowed the Writ Petition filed by the
respondents and directed the Corporation to refund to the
F respondents Rs.8,00,000/ (Rupees Eight Lacs) along with
interest at the prevailing bank rate that was received by it as
part of the sale consideration.
10. The order of the High Court is brief and does not even
advert to all the relevant facts as stated above.
G
11. It took note of the case of the respondents-writ
petitioners in the following manner:-
"According to the petitioner, after taking possession
of the said Unit, it found that because of missing of some
H
INDUS. PROM. AND INVES. CORPN. OF ORISSA LTD. v. 455
TUOBRO FURGUSON STEELS Pvt LTD. [AFTABALAM, J.]
vital parts of the machines and machineries, huge arrear A
electric dues and lack of grant of recommendation for l.P.R.
the Unit does not worth Rs.40,00,000/- (Forty Lakhs) and,
therefore, petitioner made correspondences with opposite
party No.1 seeking reliefs on those accounts besides
requesting to reduce the rate of interest on the differential B
amount to be paid in instalments and that when opposite
party No.1 turned a deaf ear to all such approaches and
representations, petitioner opted to withdraw from the
Industrial Unit and surrender the same in favour of
opposite party No.1. With such assertion, petitioner has c
filed the present writ petition with the prayer to issue a writ
of mandamus directing opposite party No.1 to give the
rehabilitation package (as mentioned in the prayer portion
of the writ petition) or alternative to direct opposite party
No.1 to return the amount of Rs.8,00,000/- (eight lakhs) D
which was paid by it in September, 1999 with interest at
the prevailing Bank rate."
The High Court then noted the stand of the Corporation that it
was not possible to give the rehabilitation package, as
requested by the respondents because they had failed to E
adhere to the terms of the sale letter. Having noted the stand
of the Corporation, the High Court disposed of the Writ Petition
and passed the operative order in the following terms:-
"Regard being had to the aforesaid facts and F
submission, we find that when opposite party no.1 is not
intending to give rehabilitation assistance package as
prayed for by the petitioner, therefore, it is appropriate that
opposite party No.1 should refund the amount of
Rs.8,00,000/- (eight lakhs) together with simple interest at G
prevailing rates of interest of the State Bank of India on
deposits made by customers during the relevant period.
The amount be worked out accordingly and be paid to the
petitioner within a period of four months, failing which the
entire sum shall carry compound interest therefrom."
H
456 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R
A We are unable to appreciate the order of the High Court and
we see no basis on which such an order could have been
passed. The case of the respondents, as noted by the High
Court was untenable on its face. Even according to the
respondents it was only after having taken possession of the
B Unit that they found that some vital parts of the machineries
were missing and there were huge arrears of electricity dues
and that the recommendation for the industrial policy resolution
was not forthcoming. In those circumstances, the respondents
realised that the Unit was not worth Rs.40,00,000/- (Rupees
c Forty Lacs).
12. The respondents went to the High Court seeking
refund of the part consideration money Rs.8,00,000/- (Rupees
Eight Lacs) paid by them as if the antecedent acts of the
parties, namely, the issuance of the advertisement, the offer
D made by the respondents followed by negotiations between the
parties and the issuance of the sale letter by the Corporation,
the payment of Rs.8,00,000/- (Rupees Eight Lakhs) by the
respondents in pursuance of the sale letter followed by their
taking over the possession of the Unit meant nothing and did
E not create any rights or obligations in the parties. Strangely, the
High Court did not even refer to the sale advertisement, the
stipulations made in the sale letter and the correspondences
between the parties. The High Court completely overlooked that
the parties, with their eyes widely open, had entered into the
F contract for sale of the Unit which was subject to the terms and
conditions clearly spelled out in the advertisement and in the
sale letter; that in furtherance of the contract, payment was
made and possession of the Unit changed hands. In other
words, both sides had acted on the basis of the contract,
G changing their respective positions and assuming rights and
obligations against each other. The contract having been acted
upon, it could not be unilaterally abrogated on the sweet will of
any of the two sides. In terms of the contract the respondents
were obliged to pay the balance consideration amount of
H Rs.32,00,000/- (Rupees Thirty Two Lacs) along with interest as
INDUS. PROM. AND INVES. CORPN. OF ORISSA LTD. v. 457
TUOBRO FURGUSON STEELS PVT. LTD. [AFTAB ALAM, J.]
provided in the sale letter. In default of payment it was the A
statutory right of the appellant-corporation to take possession
of the Unit under Section 29 of the Financial Corporation Act.
13. In the aforesaid facts and circumstances, there was no
ground for the High Court, to interfere in favour of the 8
respondents, much less to direct for refund of the part
consideration money paid by the respondents to the appellant.
14. Before concluding, however, we must take note of the
submissions made by Mr. Shrish Kumar Misra, learned counsel
for the respondents, who tried to defend the order of the High C
Court. Mr. Misra submitted that the Corporation had no right to
forfeit the amount of Rs.8,00,000/- (Rupees Eight Lacs) paid
by the respondents as part consideration for the sale of the Unit
and at best they could forfeit the earnest money of Rs.50,000/
- (Rupees Fifty Thousand) paid by the respondents while D
making the offer to purchase the Unit. There is no substance
at all in the submission. The question of forfeiture of the earnest
money would have arisen in case the parties had not acted
upon in furtherance of the sale letter but the matter in this case
went much beyond that stage. The parties agreed for the sale E
of Unit for an amount of Rs.40,00,000/- (Rupees Forty Lacs)
out of which the respondents were required to make a down
payment of Rs.8,00,000/- (Rupees Eight Lacs), which they did.
On payment of the part consideration money, the possession
of the Unit was made over to them. The respondents were, thus, F
under the legal obligation to pay the balance consideration of
Rs.32,00,000/- (Rupees Thirty Two Lacs) in instalments and
along with interest, as stipulated in the letter. The Corporation
had, therefore, not only the right to retain Rs.8,00,000/- (Rupees
Eight Lacs) paid to it as part consideration but also to realise G
the balance amount of consideration, in accordance with law.
15. Mr. Misra next submitted that according to clause 5 of
the sale letter the fixed assets of the Unit were free from
liabilities other than the deferred payment of loan of
H
458 SUPREME COURT REPORTS (2011] 13 (ADDL.) S.C.R.
A Rs.32,00,000/- (Rupees Thirty Two Lacs) but in reality there
were many dues, including dues of electricity, against the Unit.
We find no substance in this submission either. According to
us, there was no misrepresentation of facts in clause 5 or in
any other clauses of the sale letter. As to the electricity dues, it
B may be noted that the decision of this Court in Jsha Marbles
vs. Bihar State Electricity Board & Anr.,(1995) 2 SCC 648 had
already come by the time the respondents took over the Unit
and it was for them to take benefit of the decision of this Court.
16. Mr.Misra also tried to seek support from two decisions
C of this Court (1) in Haryana Financial Corporation Vs. Rajesh
Gupta (2010) 1 SCC 655, paragraphs 20 and 22 and (2) in
V.K.Ashokan vs. Assistant Excise Commissioner (2009) 14
SCC 85, paragraph 69. These two decisions have no
application to the facts of the case and do not even slightly
D advance the case of the respondents.
17. On hearing counsel for the parties and on going
through the materials on record, we find, for the reasons stated
above, that the order of the High Court is completely
E unsustainable. We, accordingly, set aside the impugned order
and dismiss the writ petition filed by the respondents.
18. In the result, the appeal is allowed with costs, quantified
at Rs.10,0001- (Rupees Ten Thousand).
F D.G. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.