Created byFuzzy Cloud

Supreme Court of India

M/S. DURO FELGUERA, S. A.versusM/S. GANGAVARAM PORT LIMITED

Citation
2017 INSC 1026
Decided
10 October 2017
Disposal
Disposed off

Holding

Each separate contract and the corporate guarantee constitute independent arbitration agreements, precluding a single arbitral tribunal and necessitating separate tribunals for each agreement.

Summary

The Supreme Court examined a dispute arising from five separate contracts and a corporate guarantee between the Spanish company Mis. Duro Felguera S.A. (and its Indian subsidiary) and Mis. Gangavaram Port Ltd. (GPL). Each contract contained its own arbitration clause, and the parties argued whether a single arbitral tribunal could resolve all disputes under a composite reference, invoking a Memorandum of Understanding (MoU) and the corporate guarantee. The Court held that, under the amended Section 11(6A) of the Arbitration and Conciliation Act, 1996, the court's role is limited to determining the existence of an arbitration agreement, and each separate agreement gives rise to a distinct arbitration agreement. Consequently, a single tribunal could not be constituted; two international commercial arbitration tribunals (for the foreign company) and four domestic tribunals (for the Indian subsidiary) are required. The Court also clarified that the MoU does not incorporate the arbitration clause of the original tender document, and the corporate guarantee’s arbitration clause remains independent. The petitions were disposed accordingly.

Issues considered

  • Whether a single arbitral tribunal can be constituted for all five split contracts and the corporate guarantee under international commercial arbitration.
  • Whether multiple arbitral tribunals are required for each separate contract and the corporate guarantee.
  • Whether the MoU incorporates the arbitration clause of the original tender document, creating a composite arbitration agreement.
  • Effect of the Arbitration and Conciliation (Amendment) Act, 2015, particularly Section 11(6A), on the court's jurisdiction to examine arbitration agreements.

Legislation cited

Subjects

ArbitrationMultiple arbitral tribunalsInternational commercial arbitrationSection 11(6A)Arbitration agreementMemorandum of UnderstandingCorporate guaranteeSplit contractsArbitration and Conciliation (Amendment) Act, 2015

Judgment

                        [2017] 10 S.C.R. 285


                  MIS. DURO FELGUERA, S. A.                              A
                                 v.
              MIS. GANGAVARAM PORT LIMITED
                (Arbitration Petition No. 30 of2016)
                        OCTOBER 10, 2017                                 B

        [KURIAN JOSEPH AND R. BANUMATHI, JJ.]
       Arbitration and Conciliation (Amendment) Act, 2015: ss. 11 (6)
and 11 (6A) - GPL awarded tender work to applicant-Foreign
company and FGJ-its lndian subsidiary - Later original contract
split into five different and separate packages with different job
                                                                         c
description - One contract with the applicant and four with FGl -
Each contract had separate arbitration clause - Dispute between
parties - Arbitration clause invoked - FGJ issued four arbitration
notices, applicant issued one arbitration notice whereas GPL issued
comprehensive arbitration notice consisting single arbitral tribunal     D
oi1 basis of MoU - Whether there has to be a single arbitral tribunal
for International Commercial Arbitration or Multiple Arbitral
Tribunals - Held: Since the dispute between the parties arose in
2016, the instant issue is governed by the amended provision of
s. 11 (6A) as per which the power of the court is con.fined only to
                                                                         E
examine the existence of the arbitration agreement - On facts, there
are five separate Letters of Award; five separate contracts awarded
to applicant and FGJ; separate suliject matters; separate and distinct
work; each containing separate arbitration clause signed by the
respective parties to the contract - Original Package split into five
different Packages, each having different works prima facie              F
 indicates the intention of the parties to split-up Original Package
 into jive different packages - Thus, when there are five separate
 contracts, one with foreign company and four with Indian subsidiary,
each having independei1t existence with separate arbitration clauses,
and Corporate Guarantee also contains an arbitration clause, there
cannot be a single arbitral tribunal for "International Commercial       G
Arbitration".
      Disposing of the matters, the Court
      HELD: Per Banumathi, J.:
      1.1 As per the amended provision of sub-section (6A) of H
                                 285
286           SUPREME COURT REPORTS                    [2017] 10 S.C.R.


A Section 11 of the Arbitration and Conciliation (Amendment) Act,
  2015(Act 3 of 2016), the power of the court is confined only to
  examine the existence of the arbitration agreement. It further
  clarifies that the decision of appointment of an arbitrator will be
  made by the Supreme Court or the High Court (instead of Chief
  Justice) and under Section 11(7), no appeal shall lie against such
B
  an appointment. The language in Section 11(6) of the Act "the
  Chief Justice or any person or institution designated by him" has
  been substituted by "Supreme Court or as the case may be the
  High Court or any person or institution designated b.v such Court".
  As per sub-section (6A) of Section 11, the power of the Court
c has now been restricted only to see whether there exists an
  arbitration agreement. The amended provision in sub-section (7)
  of Section ll provides that the order passed under Section 11(6)
  shall not be appealable and thus, finality is attached to the order
  passed under this Section. [Paras 13, 17] [299-H; 300-A-B; 301-
D D-EJ
            l.2 There is no dispute between the parties that the issue
      at hand is governed by the amended pro,ision of sub-section
      (6A) of Section 11. Even though Letters of .\ward are dated
      17.03.2012 and five separate contracts were enterl:'d into between
      the parties on 10.05.2012, the dispute arose between the parties
E     in 2016, GPL invoked the Bank Guarantee on 07.01.2016 and
      the applicant and its Indian Subsidiary-FGI issued notice of
      dissatisfaction on 04.02.2016 and 07.02.2016 respectively to GPL
      The applicant issued arbitration notice on 05.04.2016 for contract
      relating to Package No. 4 and FGI issued four arbitration notices
 F    dated 07.04.2016 for contracts relating to Packages No. 6 to 9.
      GPL also issued an arbitration notice on 13.04.2016. Since the
      dispute between the parties arose in 2016, the amended provision
      of sub-section (6A) of Section 11 would govern the issue, as per
      which the power of the Court is confined only to examine the
      existence of the arbitration agreement. ll'ara 191 [306-E-Gl
G
            l.3 Original Package No.4 Tender Document for GPL
      Expansion-2011 consisted of "Bulk Materiul Handling Systems
      including Engineering, Design, Procurement of Materials,
      Manufacturing, Supply erection, testing and commissioning of bulk
      material handling systems including all other associated works and
H     integration of the same with the existing coal handling systems
  MIS. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                       287
                      LIMITED

  (Package 4-"Works'J. By mutual consent and agreement of the             A
  parties, Original Package No.4 TD was split into five different
  Packages-New Package No. 4 (awarded to the applicant (Spanish
  Company)] and Packages No. 6, 7, 8 and 9 awarded to its Indian
  subsidiary-FGI. Letters of Award dated 17.03.2012 was awarded
  to the applicant and FGI for various Packages. Pursuant to Letters      B
  of Award, parties have entered into contract agreement on
  10.05.2012. There are five separate Letters of Award; five
  separate Contracts; separate subject matters; separate and
  distinct work; each containing separate arbitration clause signed
  by the respective parties to the contract. All the five contracts
  awarded to the applicant and FGI have independent arbitration           c
  clauses. The Original Package No. 4 TD split into five different
  Packages, each having different works prima facie indicates the
  intention of the parties to split-up original Package No. 4 TD into
. five different packages. [Paras 20-23] [307-A-C; 308-E-G; 310-
  A-B]
                                                                          D
        1.4 In the contract agreement, the parties have agreed
 that the documents mentioned in clause (2) of the agreement will
 have priority. Clauses as to the priority of the documents was
 incorporated in all other contract agreements-Package No. 4
 awarded to the applicant, Packages No. 6, 7, 8 and 9 awarded to
 Indian subsidiary FGI. In the sequence of documents of clause            E
 (2) of the contract agreement, the Tender Document is mentioned
 in the sequence only as (g) and all other documents or the other
 documents like Letters of Award, Special conditions of contract
 etc. have priority over the same. While so, the terms contained
 in Original Package No. 4 TD including the arbitration clause            F
 cannot have priority over the Special Conditions of contract of
 the split-up contracts. When the Original Package No. 4 TD has
 been split-up into five different Packages, GPL is not right in
 contending that inspite of split-up of the work, the Original
 Package No.4 TD collectively covered all the five Packages. After
 the Original Package No. 4. was split into five different contracts,     G
 the parties cannot go back to the. Original Package No.4 nor can
 they merge them into one·. It cannot be said that sub-clause 20.6
 of the Original Package No. 4 TD will still collectively cover all
 the five Packages to justify constitution of single Arbitral Tribunal.
 (Para 24] (310-B-C, F-H; 311-A]                                          H
288            SUPREME COURT REPORTS                    [2017] IO S.C.R.


A           1.5 The foreign company-applicant had executed a
      Corporate Guarantee dated 17.03.2012 guaranteeing the due
      performance of all the works awarded to the applicant and FGI.
      The Corporate Guarantee itself has its own separate and distinct
      arbitration clause. In the Corporate Guarantee, the applicant has
      undertaken to ensure performance of all the works both by the
B
      applicant and also the contracts pertaining to Packages No. 6 to
      9 awarded to FGI. The applicant has also undertaken that in the
      event of any delay in completion of the works as per the time
      stipulated for completion of the contracts, the applicant had
      undertaken to compensate for the delay, damages to GPL which
c     will be based on the overall contrart price collectively of all the
      contracts. [Paras 25, 261 (311-B, E-FI
         1.6 As per the terms of Corporate Guarantee, it shall cease
  on issuance of the performance certificate under all the contracts.
  Of course, the applicant has given the Corporate Guarantee for
D all the five contracts viz., New Package No.4, Packages No. 6 to
  9. Corporate Guarantee executed by the applicant dated
  17 .03.2012 also recognizes the split up of thl' original Package
  No. 4 Tender Document. As per the terms of the Corporate
  Guarantee, it is to be invoked only if breach is established in one
  of the five contracts. Since the Corporate Guarantee by itself has
E
  a separate arbitration clause, it cannot be contended that by virtue
  of the Corporate Guarantee executed by the applicant, there has
  to be a 'composite reference' of 'lnternatio11al Commercial
  Arbitration' which would cover all the five Packages. The
  Corporate Guarantee by the applicant cannot supersede the five
F split-up contracts and the special conditions of contract thereon.
  (Para 28] (312-G-H; 313-A-B]
            l. 7 The applicant and FGI have executed a tripartite
  Memorandum of Understanding (Mou) on 11.08.2012 which,
  according to GPL, covers all the five l'Ontracts namely New
G Package No. 4, Package No. 6, Package No. 7, Package No. 8
  and Package No. 9. In the said MoV both the applicant and FGI
  have agreed to carry out the works as per the priority of the
  documents listed therein which includes the Original Package
  No.4 Tender Document issued and final bid submitted by the
  applicant and FGI. [Para 29] [313-B-C]
H
  M/S. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                    289
                      LIMITED

      l.8 As per Section 7(5) of the Act, even though the contract A
between the parties does not contain a provision for arbitration,
an arbitration clause contained in an independent document will
be imported and engrafted in the contract between the parties,
by reference to such independent document in the contract, if
the reference is such as to make the arbitration clause in such B
document, a part of the contract. Section 7(5) requires a conscious
acceptance of the arbitration clause from another document, as a
part of their contract, before such arbitration clause could be read
as a part of the contract between the parties. The question
whether or not the arbitration clause contained in another
document, is incorporated in the contract, is always a question of C
construction of document in reference to intention of the parties.
The terms of a contract may have to be ascertained by reference
to more than one document. [Para 33] [315-D-.E]
         l.9 In the MoU, Original Package No.4 Tender Document
  is merely referred only to have more clarity on technical and D
  execution related matters and the parties agreed that the works
  shall be carried out as per the priority of the documents indicated
  thereon. Mere reference to Original Package No.4 Tender
  Document in the sequence of priority of documents (as serial
  No.4) indicates that the documents Original Package No. 4 TD
  containing arbitration clause was not intended to be incorporated E
· in its entirety but only to have Clarity in priority of the documents
  in execution of the work. Original Package No.4 TD occurs as
  Serial No.4 in sequence, after three other documents. There are
  a number of contract agreements between the parties - GPL,
  petitioner company and FGI. MoU dated 11.08.2012 itself does F
  not contain an arbitration clause. When reference is made to the
  priority of documents to have clarity in execution of the work,
  such general reference to Original Package N o.4 Tender
  Document will not be sufficient to hold that the arbitration clause
  20.6 in the Original Package No.4 TD is incorporated in the MoU.
  [Para 35) [317-G-H; 318-A, C-D)                                       G

       1.10 As per the amended provision of sub-section (6A) of
 Section 11, the power of the court is only to examine the existence
 of arbitration agreement. When there are five separate contracts
 each having independent existence with separate arbitration
                                                                       H
290            SUPREME COURT REPORTS                     [2017] lO S.C.R.


A     clauses that is New Package No.4 (with foreign company) and
      Packages No. 6, 7, 8 and 9 [with Indian subsidiary (FGI)) based
      on MoU and C_orporate Guarantee, there cannot be a single
      arbitral tribunal for "lllternational Commercia/Arbitratio11". [Para
      361 [318-E-FJ
B           l.ll The Corporate Guarantee dated 17.03.2012 was
      executed by the foreign company undertaking to compensate for
      the delay, damages to the GPL. Since the Corporate Guarantee
      was by the foreign company which contains separate arbitration
      clause, there has to be a separate arbitral tribunal for resolving
C     the disputes arising out of the said Corporate Guarantee. [Para
      38J (319-B)
        1.12 New Package No. 4 TD- F.O.B. Supply of Bulk
  Material Handling Equipments USD 26,666,932 has been
  awarded to the foreign company-petitioner company. Since it is a
  foreign company, in so far as the contract awarded to the petitioner
D company i.e. New Package No.4 and the dispute arising out of
  the Corporate Guarantee executed by the foreign company is
  concerned, the arbitral tribunal has to be for the international
  commercial arbitration. [Para 39) [319-C)
            1.13 In the instant case, all five different Packages as well
E     as the Corporate Guarantee have separate arbitration clauses
      and they do not depend on the terms and conditions of the Original
      Package No.4 TD nor on the MoU, which is intended to have
      clarity in execution of the work.[Para 40] (319-G-H; 320-A)
            Chloro Contmls India Private ltd. v. Severn Trent Water
F           Purification Inc. and Ors. (2013) 1 SCC 641 : (20121
            13 SCR 402 - distinguished.
        1.14 The petitioner company being a foreign company, for
  each of the disputes arising under New Package No.4 and
  Corporate Guarantee, International Commercial Arbitration
G Tribunal are to be constituted. The petitioner has nominated
  Justice D.R. Deshmukh, Former Judge of Chhattisgarh High
  Court as their arbitrator. GPL has nominated Justice M. N. Rao,
  Former Chief Justice of Himachal Pradesh High Court. Alongwith
  the above two arbitrators Mr. Justice R.M. Lodha, Former Chief
H
 MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                       291
                     LIMITED

Justice of India is appointed as the Presiding Arbitrator of the         A
International Commercial Arbitral Tribunal. [Para 41] [320-.B-C]
      1.15 Package No.6 (Rs.208,66,53,657/-); Package No.7
(Rs.59,14,65,706/-); Package No.8 (Rs.9,94,38,635/-); and
Package No.9 (Rs.29,52,85, 558/-) have been awarded to the
Indian company-FGI. Since the issues arising between the parties         B
are inter-related, the same arbitral tribunal, Justice R.M. Lodha,
Former Chief Justice of India, Justice D.R. Deshmukh, Former
Judge of Chhattisgarh High Court and Justice M. N. Rao, Former
Chief Justice of Himachal Pradesh High Court, shall separately
constitute Domestic Arbitral Tribunals for resolving each of the
disputes pertaining to Packages No.6, 7, 8 and 9. [Para 42] [320-        C
D-E]
       Konkan Railway Corpn. Ltd. and Ors. v. Mehu/
       Construction Co. (2000) 7 SCC 201 : [2000] 2 Suppl.
       SCR 563; Konkan Railway Corpn. Ltd. & Am:. v. Rani
       Construction Pvt. Ltd. (2002) 2 SCC 388 : [2009) 10               D
       SCR 373; S.B.P & Co v. Patel Engineering Ltd and
       Anr. (2005) 8 SCC 618 : [2005) 4 Suppl. SCR 688;
       National Insurance Company Limited v. Boghara
       Pol;jab Private Limited (2009) 1 SCC 267 : [2008) 13
       SCR 638; Shree Ram Mills Ltd. v. Utility Premises (P)             E
       Ltd, (2007) 4 SCC 599 : [2007) 4 SCR 279; Arasmeta
       Captive Power Company Private Limited and Anr. v.
       Lafarge India Private Limited (2013) 15 SCC 414 :
       [2013] 17 SCR 496; MR. Engineers and Contractors
       Pvt. Ltd. v. Som Datt Builders Ltd. (2009) 7 SCC 696 :
       [2009) 10 SCR 373 - referred to.                                  F

Per Kurian, J. (Supplementing):
       1.1 The submission that the Memorandum of Understanding
(MoU) has subsumed all the separate agreements and therefore
and thereafter there can only be one agreement and, if so, only          G
one Arbitral Tribunal for all the disputes emanating from the five
different agreements and the Corporate Guarantee, is
misconceived. The whole purpose of the MoU is evident from
its text. It is clear that there is no novation by substitution of all
the five agreements nor is there a merger of all into one. The
                                                                         H
292            SUPREME COURT REPORTS                     [2017] 10 S.C.R.


A reference to Original Package No. 4 Tender Document is only
  for better clarity on technical and execution related matters. 7.
  The said finding is wholly in line with Section 7(5) of the 1996
  Act, which deals with incorporation by reference. The words "the
  reference is such as to make that arbitration clause part of the
  contract" are of relevance. Essentially, the parties must have
B
  the intention to incorporate the arbitration clause. The detailed
  analysis of Section 7(5) in M.R. Engineers case fortifies the
  conclusion that the MoU does not incorporate an arbitration
  clause. [Para 5, 6, 7]
            1.2 The submission that it is expedient that a single Arbitral
C     Tribunal is constituted, also cannot be appreciated. The parties
      are free to agree to anything for their convenience but once such
      terms are reduced to an agreement, they can resile from them
      only in accordance with law. [Para 9J
        1.3 The scope of the power under Section 11 (6) of the 1996
D Act was considerably wide in view of the decisions in SBP and
  Co. and Boghara Poly/ab cases. This position continued till the
  amendment brought about in 2015. After the amendment, all that
  the Courts need to see is whether an arbitration agreement exists
  - nothing more, nothing less. The legislative policy and purpose
E is essentially to minimize the Court's intervention at the stage of
  appointing the arbitrator and this intention as incorporated in
  s. 11 (6A) ought to be respected. [Para 13]
            1.4 Jn the instant case, there are six arbitrable agreements
      (five agreements for works and one Corporate Guarantee) and
 F    each agreement contains a provision for arbitration. Hence, there
      has to be an arbitral tribunal for the disputes pertaining to each
      agreement. While the arbitrators can be the same, there has to
      be six tribunals - two for international commercial arbitration
      involving the Spanish Company-petitioner and four for the
      domestic. [Para 14]
G
            M.R. Engineers and Contractors Pvt. Ltd v. Som Datt
            Builders Ltd. (2009) 7 SCC 696 : [2009) 10 SCR 373;
            S.B.P & Co v. Patel Engineering Ltd and Anr. (2005) 8
            SCC 618 : [20051 4 Suppl. SCR 688; Konkan Railway
            Corpn. Ltd. and Ors. v. Mehul Construction Co. (2000)
 H          7 SCC 201 : [2000) 2 Suppl. SCR 563; Konkan Railway
 MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT              293
                     LIMITED

     Corpn. Ltd. & Anr. v. Rani Construction Pvt. Ltd (2002)    A
     2 SCC 388 : [2009) 10 SCR 373; National Insurance
     Company Limited v. Boghara Polyfab Private Limited
     (2009) 1 SCC 267 : (2008) 13 SCR 638 - referred to.
                      Case Law Reference
In the .Judgment of Banumathi2 J :                              B

[2000) 2 Suppl. SCR 563           refer.red to       Para 14
[2009) 10 SCR 373                 referred to        Para 14
[2005] 4 Suppl. SCR 688           referred to        Para 15
[2008) 13 SCR 638                 referred to        Para 16
                                                                c
[2007) 4 SCR 279                  referred to        Para 16
(2013] 17 SCR 496                 referred to         Para 16
[2012] 13 SCR 402                 distinguished       Para 40
                                                                D
[2009) 10 SCR 373                 referred to         Para 34


In the Judgment of Kurian 2 J.:
[2009] 10 SCR373                  referred to         Para 7
                                                                E
[2005) 4 Suppl. SCR 688           referred to         Para 11
[2000] 2 Suppl. SCR 563           referred to         Para 11
[2009) 10 SCR 373                 referred to         Para 11
[2008] 13 SCR 638                 referred to         Para 12   F
      CIVIL ORIGINAL JURISDICTION : Arbitration Petition No.
30 of2016
                              WITH
     Arbitration Petition No. 31 of2016
                                                                G
     T. C. (C) No.25 of2017
     T. C. (C) No.26 of2017
     T. C. (C) No.27 of2017
     T. C. (C) No.28 of2017                                     H
294             SUPREME COURT REPORTS                           [2017] 10 S.C.R.


A           Mukul Rohatgi, Raju Ramachandran. Sunil Gupta, Dr. Abhishek
      Manu Singhvi, Sr. Advs., Ms. Anitha Shenoy, Ms. Rashmi Nandakumar,
      Ms. Srishti Agnihotri, Ms.Hamsini Shankar, lshwar Mohanty. Tarun
      Dua, Ms.Geetanjali Sethi, Faisal Sherwani,A. Paul, Ms.Sumati Sharma.
      Advs. for the appearing parties.
B           The Judgment of the Court was delivered by
         BANUMATHI, J. Arbitration Petition No.30 of 2016 has been
  filed by Mis Duro Felguera, S.A. under Section I l(6)(a) read with
  Sectiion I! ( l 2)(a) of the Arbitration and Conciliation Act, l 996 (for short,
  'the Act·) to appoint the nominee arbitrator on behalf of the respondent
c (second arbitrator) in terms of sub-clause 20.6 of the Special Conditions
  of the Contract with respect to the arbitration arising under the Contract
  dated l 0.05.2012. T.C. No.25 of 2017, T.C. No.26of2017, T.C. No.27
  of2017 and T.C. No.28 of 2017 have been filed by M/s. Felguera Gruas
  India Private Limited (hereinafter referred to as 'the FGI') for
  appointment of Domestic Arbitral Tribunal for resolving the dispute
D pertaining to the contract awarded to FGI. Arbitration Petition No.31 of
  2016 has been filed by M/s. Gangavaram Port Limited (hereinafter
  referred to as 'the GPL') to appoint an arbitrator under the Memorandum
  of Understanding (MoU) dated 11.08.2012 and to constitute a single
  Arbitral Tribunal by a composite reference for adjudication of all the
E disputes between the parties in connection with the "Works" covered
  under all the five Package Contracts and the Corporate Guarantee dated
  17.03.2012 executed by Duro Felguera.
             2. As the pa1ties and issues in both the arbitration petitions and the
      transfeJTed cases are one and the same, both arbitration petitions and
F     the transferred cases shall stand disposed of by this common order. For
      convenience, parties arc referred to as per their array in Arbitration
      Petition No.30of2016.
        3. BriefFacts: The Respondent-Gangavaram Port Limited (GPL)
  developed a green-field, ultra-modern, all-weather sea-port near
G Gangavaram Village in Visakhapatnam District in the State of Andhra
  Pradesh. This sea-port commenced operations in the year 2009. The
  Respondent intended to expand its facilities in the Pm1 with respect to
  Bulk Material Handling Systems. This included Engineering, Design,
  Procurement of Materials, Manufacturing, Supply, Erection, Testing and
  Commissioning of Bulk Material Handling Systems, as well as all other
H
  MIS. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                          295
               LIMITED [BANUMATHI, J.]

  associated works and integration of the same with the existing coal A
 handling systems etc. For this purpose, on 08.08.2011, Gangavaram Port
  Limited invited a tender/bid. In response to the aforementioned tender
  dated 08.08.2011, the Spanish Company-Duro Felguera Plantas
  Industrials S.A. (since merged with the petitioner) along with its Indian
'subsidiary-Mis. Felguera Gruas India Private Limited (FGI) submitted a B
  Single Bid/Tender-Original Package No.4 Tender Document on
  15.11.2011. This included the Commercial Bid and the Technical Bid.
  After post-bid negotiations, the petitioner Duro Felguera and its subsidiary
  (FGI) were considered by GPL and Duro Felguera and FGI were selected
  as "the Contractors" for the work.
       4. After discussion between the parties, Original Package No. 4 c
 TD was divided into five different and separate Packages, namely, New
 Package No. 4-F.O.B. Supply of Bulk Material Handling Equipments
 (awarded to foreign company-Mis Duro Felguera), Package No. 6-
 design, manufacture, supply, installation, erection, testing, commissioning
 of Bulk Material Handling Equipments and all other activities related D
 therewith; Package No. 7-Civil Works and all other activities related
 therewith; Package No. 8-International Transportation of Bulk Material
 Handling Equipments and parts through sea including insurance and all
 related activities; Package No. 9-Installation, Testing and
 Commissioning of Ship Unloaders and all other activities related therewith
 (Packages No.6 to 9 awarded to Indian subsidiary-FGI). Separate E
 Letters of Award (dated 17.03.2012) for five different Packages were
 issued to Mis Duro Felguera, S.A. and the Indian Subsidiary-FGI forthe
 above said work respectively.
         5. Five different contracts were entered into on 10.05.2012 for
 five split-up Packages with different works viz. namely New Package         F
 No. 4 with foreign company-Mis Duro Felguera and Packages No. 6, 7,
 8 and 9 with FGI. Each of the Packages has special conditions of contract
 as weU as general conditions of contract. Each one of the Contract/
 Agreement for works under split-up Packages contains an arbitration
 clause namely sub-clause 20.6. Duro Felguera had also entered into a        G
 Corporate Guarantee dated 17.03.2012 guaranteeing due performance
 of all the works awarded to Duro Felguera and FGI. The said Corporate
 Guarantee had its own arbitration clause namely clause (8).
      6. Duro Felguera and FGihave executed a tripartite Memorandum
 of Understanding (MoU) with Mis Gangavaram Port Limited (GPL) on            H
296            SUPREME COURT REPORTS                         [2017] 10 S.C.R.



A     11.08.2012. In the said MoU. Duro Felguera and FGI have agreed to
      carry out the works as per the priority of documents listed therein. Case
      ofGPL is that the MoU dated 11.08.2012 being the latest covers all the
      five contracts namely New Package No. 4 awarded to M/s Duro
      Felguera and Packages No. 6 to 9 awarded to FGI. According to GPL,
      since MoU refers to original Package No. 4 Tender Document (TD)
B
      which contains arbitration clause, the Original Package No. 4 TD with
      its arbitration clause shall be deemed to have been incorporated in the
      MoU.
             7. Case of Mis. Gangavaram Port Limited is that the petitioner-
      M/s Duro Felguera, S.A. and its Indian Subsidiary-FGI failed to perform
c     their obligations, including their obligation to attend and rectify faulty
      works and complete the pending works etc. Further grievance ofGPL
      is that though the works were scheduled to be completed at the latest by
      16.03.2014, the petitioner-Mis Duro Fclgucra, S.A. and its Indian
      Subsidiary (FGI) caused inordinate delay in execution of the work and,
D     therefore, GPL was constrained to invoke the Bank Guarantee on
      07.01.2016 given by petitioner-Mis Duro Felguera. GPL had also issued
      Notices of Termination dated 31.01.2016 to the Foreign Company-Mis
      Duro Felguera and its Indian Subsidiary(FGI). Mis Duro Felguera, S.A.
      and its Indian Subsidiary (FGI) issued notice of dissatisfaction on
      04.02.2016 and 07.02.2016 to GPL. Subsequently Mis. Duro Felguera
E     issued an arbitration notice dated 05.04.2016 for New Package No. 4
      Contract and FGI issued four arbitration notices dated 07.04.2016 for
      Packages No. 6 to 9 Contracts. Both Mis. Duro Felguera and FG I have
      separately nominated Mr. Justice D.R. Deshmukh (Former Judge,
      Chhattisgarh High Court) as their nominee arbitrator for each of the five
F     contracts.
        8. GPL issued a comprehensive arbitration notice on l 3.04.2016
  appointing Mr. Justice M.N. Rao (Former Chief Justice, Himachal
  Pradesh High Court) as its nominee arbitrator under sub-clause 20.6 of
  the conditions of contract which form part of the "Original Package No.
G 4 Tender Document". Contention ofGPL is that "Original Package No.
  4 (TD) and the Corporate Guarantee by Mis. Duro Felguera" and the
  MoU dated 11.08.2012 cover all the five contracts, namely, New Package
  No. 4, Package No. 6, Package No. 7, Package No. 8 and Package No.
  9 as well as the Corporate Guarantee. Further case ofGPL is that five
  individual arbitration notices issued by Mis. Duro Felguera and FGI are
H
   MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                           297
                LIMITED [BANUMATHI, J.]

 untenable and since Duro Felguera-the foreign company has guaranteed          A
 the due performance of the works covered under all the five packages
 and there has to be only one single Arbitral Tribunal for resolving the
 disputes of"International Commercial Arbitration" arising between the
 parties.
        9. Mr. Mukul Rohtagi and Mr. RajuRamachandran, learned Senior          B
 Counsel for Mis Gangavaram Port Limited (GPL) submitted that the
 split up of the "Works" into five separate contracts was made only on
 the basis of the requests made by the Duro Felguera for convenience of
 the contractors. It was contended that all the works are inter-connected
 and inter-linked and if there arc separate arbitrations for each of the
 packages, and separate arbitration for New Package No. 4 and the              c
 Corporate Guaritntee take place, then in each arbitration, the respondent
 party will blame the lapse on the part of GPL in another Package and
 thereby attempt to escape liability. It was urged that the appointment of
 a single arbitral tribunal, under the MoU and the Corporate Guarantee
 will avoid conflicting awards between the pa1iics, huge wastage of time,      D
 resources and expenses; and would be consistent with law and public
 policy. The learned Senior Counsel further submitted that MoU was
 executed by Duro Felguera and FGI on 11.08.2012 and the contents of
 MoU including the priority of the documents referred therein prevail
 over the contents of the Letters of Award and the Contracts. It was,
 therefore, submitted that the arbitration clause covered under sub-clause     E
 20. 6 of the conditions of contract, which forms part of the "Original
 Package No. 4 Tender Document" which is incorporated in the MoU
 shall prevail over the arbitration clause covered under sub-clause 20.6
 of the contract for five packages. It was further submitted that having
 regard to the nature of disputes which extend over each of the Packages       F
 and collectively covered the Corporate Guarantee executed by Duro
 Fclguera under MoU, it would be just and proper to· make a 'composite
 reference' and have a single arbitral tribunal of "international
 commercial arbitration' for settling the dispute arising between the
 parties and the same would be consistent with the intention of the parties    G
 and public policy. It was urged that the contract for the "Works" has
 always been envisaged by the parties as one composite contract even
 though the contracts were split into various Packages and there cannot
 be multiple arbitral tribunals for adjudication of disputes between the
_parties as it would lead only to complications in settling the disputes and
 execution of the awards.                                                      H
298           SUPREME COURT REPORTS                        [2017] I0 S.C.R.


A        JO. Mr. Sunil Gupta learned Senior Counsel appearing for Duro
  Felguera-Spanish Company submitted that by conscious agreement of
  the parties, the Original Package No.4 Tender Document was superseded
  by five new Contracts with different works namely New Package No.
  4, Packages No.6, 7, 8 and 9, each of which have special co~ditions as
  well as general conditions of contract. It was further submitted that the
B
  Corporate Guarantee dated 17.03.2012 executed by Duro Felgucra
  g1,1aranteeing due performance of the works awarded to Duro Felguera
  and FGI has its own separate and distinct arbitration clause and the
  same has no connection with the arbitration clauses (sub-clause 20.6) of
  the five different contracts for New Package No. 4 and Packages No.
c 6, 7, 8 and 9. The learned Senior Counsel further submitted that the
  MoU dated 11.08.2012 which enlists priority of the documents to be
  considered is only to have clarity in carrying out the works and the MoU
  cannot override the terms of the contracts for five different packages
   including the arbitration clauses contained therein. It was submitted that
D the five new split-up Packages followed by five different Letters of
  Award and five difforent contracts were substantially different,
   independent and separate in their content and subject matter and there
   cannot be a 'composite reference' for efficacious settlement of disputes,
   it would be just and proper to have multiple arbitral tribunals and may be
   by the same arbitrators. The learned Senior Counsel submitted that so
E far as New Package l'-io.4 and the issues J'ertaining to the Corporate
   Guarantee executed on 17.03.2012 by Duro Felguera-the foreign
   Company, the arbitral tribunal has to be for International Commercial
   Arbitration.
            II. Reiterating the above submissions, Mr. Singhvi, the learned
 F   Senior Counsel appearing for Indian subsidiary-FGI contended that by
     conscious decision and agreement of the parties, Original Package No.
     4 (TD) was superseded and five new TDs with different works namely
     TD for New Package No. 4 and Packages No. 6, 7, 8 and 9 were
     brought into existence and there were separate Letters of Award and
     five separate contracts for each one of those split-up packages. It was
 G · submitted that each of the contracts contain special conditions as well
     as general conditions of contract apart from the arbitration clause, (sub-
     clause 20.6), which is relevant for governing the contractual and arbitral
     relations between the parties and in case of dispute arising between the
     parties under any of the respective contracts or the Corporate Guarantee,
 H the aggrieved party would have to invoke the respective arbitration clauses
             '
  MIS. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                            299
               LIMITED [BANUMATHI, J.]

in the respective contracts in question and cannot invoke the MoU dated        A
11.08.2012. It was further submitted that the Corporate Guarantee dated
17 .03 .2012 was executed by Duro Felguera under which it had
gtiaranteed the due performance of all the works awarded to Duro
Felguera and FGI and FGI is not a party under the said Corporate
Guarantee. It was further submitted that the MoU dated 11.08.2012
                                                                               B
came into existence long after the Contracts and it does not contain any
arbitration clause and MoU does not intend to alter the nature of the
rights, responsibilities and obligations of the pat1ies arising from the
respective contracts and, therefore, for settling the disputes arising under
the Packages No. 6, 7, 8 and 9 awarded to FGI, there have to be four
domestic arbitral tribunals and there cannot be a 'composite reference'        C
by invoking MoU.
       12. Considering the facts and circumstances and rival contentions
of the pat1ies, the following points arise for determination:
       (1)   Whether Gangavaram Port Limited (GPL) is right in
             contending that Memorandum of Understanding (MoU)                 D
             dated 11.08.2012 and Original Package No. 4 Tender
             Document and Corporate Guarantee dated I 7 .03.2012
             executed by Duro Felguera covers all the five split-up
             Packages awarded to Duro Felguera and FGI and whether
             there has to be a composite reference/single arbitral tribunal    E
             for "International ·Commercial Arbitration" covering all
             the five different Packages and also the Corporate
          -. Guarantee executed by Duro Fclguera?
       (2)       Whether there have to be 'mult1]J/e arbitral tribunals' for
                 each of the five different Packages of Work awarded to        F
                 the foreign company-Duro Felguera and Indian Subsidiary-
                 FGI (one International Commercial Arbitral Tribunal plus
                 four Domestic Arbitral Tribunals) and another one arbitral
                 tribunal for 'international commercial arbitration' under
                 Corporate Guarantee (17 .03.2012) executed by the foreign
                 company-Duro Felguera?                                        G

       13. The Arbitration and Conciliation (Amendment) Act, 2015
(w.e.f. 23.10.2015) has brought in substantial changes in the provisions
of the Arbitration and Conciliation Act, 1996. After the Amendment Act
3 of2016, as per the amended provision of sub-section (6A) of Section 11,
                                                                               H
300           SUPREME COURT REPORTS                          [2017] IO S.C.R.


A the power of the court is confined only to examine the existence of the
  arbitration agreement. It further clarifies that the decision of appointment
  of an arbitrator will be made by the Supreme Court or the High Court
  (instead of Chief Justice) and under Section 11 (7), no appeal shall lie
  against such an appointment.
B     Position prior to Amendment Act 3 of 2016
           14. Under Section 11 (6) of the Arbitration and Conciliation Act,
  1996, as it stood prior to Amendment Act 3 of 2016, on an application
  made by any of the parties, the Chief Justice of the High Court appoints
  an arbitrator for adjudication. Initially, the line of decisions ruled that the
c appointment of arbitrator is an administrative order passed by the Chief
  Justice. In Konkan Railway Corporation Limited and Others v. Mehul
  Construction Company, (2000) 7 SCC 20 l, it was held that the powers
  ofthe ChiefJustice under Section 11(6) of the Arbitration and Conciliation
  Act, 1996 are of administrative nature and that the Chief Justice or his
  designate does not act as a judicial authority while appointing an arbitrator.
D The same view was reiterated in the subsequent judgment of this Court
  in Konkan Railway Corporation Limited and Another v. Rani
  Construction Private Limited, (2002) 2 SCC 388.
          15. However, in the year 2005, a Constitution Bench of Seven
   Judges in SBP and Co. v. Patel Engineering Limited and Another,
 E (2005) 8 sec 618, made a departure from the previous judgments and
   held that the order passed by the Chief Justice is not administrative but
   judicial in nature and hence the same is subject to appeal under Article
    136 of the Constitution ofindia. The Court further held that in deciding
   the appointment of an arbitrator, the Chit:f Justice could first by way of
 F a preliminary decision decide the court's own jurisdiction of that matter
   to entertain the arbitration petition, the existence of a valid arbitration
   agreement, the subsistence of a "live claim i.e. the claim that is not
   barred by limitation".
         16. The judgment in SBP and Co. (supra) was further clarified
 G in National /11s11rance Company Limited v. Boghara Poly/ab Private
   Limited, (2009) l SCC 267, wherein this Court held that while appointing
   an arbitrator, the following could be considered:-
             "22. Where the intervention of the court is sought for
             appointment of an Arbitral Tribunal under Section 11, the
             duty of the Chief Justice or his designate is defined in
 H
  MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                             301
               LJMITED [BANUMATHI, J.]

        SBP & Co. (2005) 8 SCC 618. This Court identified and                   A
        segregated the preliminary issues that may arise for
        consideration in an application under Section 11 of the Act
        into three categories, that is, (i) issues which the Chief
        Justice or his designate is bound to decide; (ii) issues
        which he can also decide, that is, issued which he may                  B
        choose to decide; and (iii) issues which should be left to
        the Arbitral Tribunal to decide."
The judgments in Shree Ra111 Mills Ltd. v. Utility Premises (P) Ltd,
(2007) 4 SCC 599 and Aras111eta Captive Power Co111pany Private
Limited and Another v. Lafarge India Private Limited, (2013) 15
sec 414, are on the same line pertaining to the issues which have to be         c
dealt with by the Chief Justice or his designate.
Changes brought about by the Arbitration and Conciliation
(Amendment) Act, 2015 (Amendment Act 3 of 2016)
       17. The language in Section II (6) of the Act "the Chief.Justice         D
or any person or institution designated by him" has been substituted
by "Supreme Court or as the case may be the High Court or any
persoi1 or institution designated by such Court". Now, as per sub-
section (6A) of Section 11, the power of the Court has now been restricted
only to see whether there exists an arbitration agreement. The amended
provision in sub-section (7) ofScction 11 provides that the order passed        E
under Section I I (6) shall not be appealable and thus finality is attached
to the order passed under this Section. The amended Section 11 reads
as under:-
          "11. Appointment of arbitrators.- (I) A person of any
        nationality may be an arbitrator, unless otherwise agreed by the        F
        paiiies.
           (2) Subject to sub-section (6), the parties are free to agree on
        a procedure for appointing the arbitrator or arbitrators.
           (3) Failing any agreement referred to in sub-section (2), in an
                                                                                G
        arbitration with three arbitrators, each party shall appoint one
        arbitrator, and the two appointed arbitrators shall appoint the third
        arbitrator who shall act as the presiding arbitrator.
          (4) If the appointment procedure in sub-section (3) applies
        and-
                                                                                H
302    SUPREME COURT REPORTS                             (2017] 10 S.C.R.


A       (a) a party fails to appoint an arbitrator within thirty days from
            the receipt of a request to do so from the other party; or
        (b) the two appointed arbitrators fail to agree on the third
             arbitrator within thirty days from the date of their
             appointment,
B     the appointment shall be made, upon request of a party, by '[the
      Supreme Court or, as the case may be, the High Court or
      any person or institution designated by suclt Court].
         (5) Failing any agreement referred to in sub-section (2), in an
      arbitration with a sole arbitrator. if the parties fail to agree on the
 c    arbitrator within thirty days from receipt of a request by one
      party from the other party to so agree the appointment shall be
      made, upon request of a party, by *[tlte Supreme Court or, as
      the cme may be, the High Court or any person or institution
      designated by such Court}.
 D       (6) Where. under an appointment procedure agreed upon by
      the parties,-
        ( a) a party fails to act as required under the procedure; or
        (b) the parties, or the two appointed arbitrators, fail to reach
            an agreement expected of them under that procedure; or
 E
        (c) a person, including an institution, fails to perform any
            function entrusted to him or it under that procedure,
      a party may request *[the Supreme Court or, as tlte case may
      be, the High Court or any person or institution designated
 F    by such Court] to take the necessary measure, unless the
      agreement on the appointment procedme provides other means
      for securing the appointment.
        *[(6A) The Supreme court or, as the case may be, the
      High Court, while considering any application under sub-
 G    section (4) or sub-section (5) or sub-section (6), shall,
      notwithstanding any judgment, decree or order of any Court,
      confine to the examination of the existence of an arbitration
      agreement.]
        *[(6B) The designation of any person or institution by the
 H    Supreme Court or, as the case may be, the High Court, for
M/S. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                       303
             LIMITED [BANUMATHI, J.]

    the purposes of this section .~/tall not be regarded as a           A
    delegation of judicial power by the Supreme Court or tlte
    High Court.}
       (7) A decision on a matter entrusted by sub-section (4) or
    sub-section (5) or sub-section (6) to *[the Supreme Court or,
    as the case may be, tlte High Court or the person or i11Stitution   B
    desig11ated by such Court is final and no appeal including
    Letters Patent Appeal shall lie ag1dnst such decision].
       *[(8) The Supreme Court or, as the case may be, the High
    Court or the perso11 or i11stitution designated by such Court,
    before appointing an arbitrator, shall seek a disclosure in c
    writing from the prospective arbitrator i11 terms ofsub-sectio11 _
    (1) of sectio11 12, and have due regard to-                     -
      (a) any qualifications required of the arbitrator by the
          agreeme11t of the parties; a11d
      (b) the co11te11ts ofthe disclosure and other co11Siderations     D
          as are likely to secure the appointment of a11
          independe11t and impartial arbitrator.]
       (9) In the case of appointment of sole or thii:_d arbitrator in an
    international commercial arbitration, *[the Supreme Court or
    the person or institution designated by that Court} may appoint - E
    an arbitrator of a nationality other than the nationalities of the
    parties where the parties belong to different nationalities.
       *[(10) The Supreme Court or, as the case may be, the
    High Court, may make such scheme as the said Court may
    deem appropriate for dealing with matters entrusted by sub-         F
    section (4) or sub-section (5) or sub-section (6), to it.]
       ( 11) Where more than one request has been made under sub-
    section (4) or sub.section (5) or sub-section (6) to *[different
    High Courts or their designates, the High Court or its
    designate to whom the request has been first made} under            G
    the relevant sub-section shall alone be competent to decide on
    the request.
       *[(12)(a) Where the matters referred to in sub-sections
    (4), (5), (6), (7), (8) and sub-section (10) arise in an
    international commercial arbitration, the refere11ce to the         H
304            SUPREME COURT REPORTS                         [2017] JO S.C.R.



A            "Supreme Court or, as the case may be, the High Court" in
             those sub-sections shall be construed as a reference to the
             "Supreme Court",· and
                (b) where the matters referred to in sub-sections (4), (5),
             (6), (7), (8) a11d sub-section (10) arise in any other arbitration,
B            the reference to "the Supreme Court or, as the l'a.se may be,
             the Higlt Court" in those sub-sections shall be construed as
             a reference to the "High Court" within whose local limits
             the principal Civil Court referred to in clause (e) of sub-
             section(/) of section 2 is situate, a11d where the High Court
             itself is tlte Court referred to i11 tltat clause, to tltat Higlt
c            Court.]
                *{(13) An application made under tltis section for
             appoint111ent of an arbitrator or arbitrators sltal/ be disposed
             of by the Supreme Court or the High Court or lite person or
             institution designated by such Court, as the case may be, as
D            expeditiously as possible and an endeavour shall be made
             to dispose of the matter within a period of sixty days fro111
             the date of service of notice on the opposite party.
                (14) For the purpose of determination of the fees of the
             arbitral tribu11al and the ma1111er ofits payment to the arbitral
E            tribunal, the High Court may frame such rules as may be
             necessary, after taking into consideration the rates specified
             in the Fourth Schedule.
                Explanation.-For the removal of doubts, it is hereby
             clarified that this sub-section shall not apply to international
 F           commercial arbitration and in arbitrations (other than
             international commercial arbitration) in case where parties
             ltave agreed for determination of fees as per tlte rules of an
             arbitra/ institution.]"
      *Substituted by Act 3 of 2016 (w.e.f. 23.10.2015)
G
            18. The effect of the Arbitration and Conciliation (Amendment)
      Act, 2015 in Section 11 of the Act has been succinctly elucidated in the
      text book "Law Relating to Arbitration and Co11ciliatio11 by Dr. P. C.
      Markanda", which reads as under:-
             "The changes made by the Amending Act are as follows:
H
M/S. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                           305
             LIMITED [BANUMATHI, J.]

    1. The words 'Chief Justice or any person or institution designated     A
    by him' shall be substituted by the words 'the Supreme Court or,
    as the case may be, the High Court or any person or institution
    designated by such Court'. Thus, now it is not only the Chief
    Justice who can hear applications under Section 11, the power
    can be delegated to any judge as well.
                                                                            B
    2. As per sub-section (6-A), the power of the Court has now
    been restricted only to examination of the existence of an
    arbitration agreement. Earlier, the Chief Justice had been given
    the power to examine other aspects as well, i.e. limitation, whether
    the claims were referable for arbitration etc. in terms of the
    judgments of the Supreme Court in SBP and Co. v. Patel C
    Engineering Ltd., (2005) 8 SCC 618; and National Insurance·
    Co. Ltd. V. Boghara Poly/ab Pvt. Ltd., (2009) 1 SCC 267.
    Now all preliminary issues have been left for the arbitral tribunal
    to decide in terms of Section 16 of the Act.
    3. The Amending Act has categorically provided in sub-section D
    (6-B) that designation ofany person or institution by the Supreme
    Court or High Court would not be construed as delegation of
    judicial power. The order passed by a designated person or
    institution would continue to be regarded as a judicial order.
    4. It has been provided is sub-section (7) that the order passed        E
    under this section shall not appealable. This change means that
    finality is attached to the order passed under this section and it
    would not be subject to further examination by an appellate court.
    5. Sub-section (8) has been amended to bring it in conformity
    with amended section 12 with regard to ensuring independence            F
    and impartiality of the arbitrator. Before appointing any arbitrator,
    a disclosure in writing has to be obtained in terms of section
    12( l) of the Act. This is to ensure that the appointed arbitrator
    shall be independent and impaitial and also harmonizes the
    provisions of sections 11and12 of the Act.                              G.
    6. The Amending Act has introduced sub-section (13) which
    provides that the disposal of the application under this section
    has to be expeditious and endeavour shall be made to dispose of
    the application within a period of 60 days from the date of service
    of notice on the opposite party. This sub-section would ensure          H
306          SUPREME COURT REPORTS                           [2017] l 0 S.C.R.


A           speedy disposal of applications under this section and all
            contentious issues have been left to be decided by the arbitral
            tribunal.
            7. For determining the fee structure of the arbitral tribunal, it has
            been recommended that the High Courts may frame the
B           necessary rules and for that purpose, a model fee structure has
            been provided in the Fourth Schedule of the Amending Act.
            However, this sub-section would not be applicable for the fee
            structure in case of international commercial arbitrations and
            domestic arbitrations where the parties have agreed for
            determination of fee as per rules of an arbitral institution. This
c           sub-section has been inserted to ensure a reasonable fee structure
            since the cost of arbitration has increased manifold due to high
            charges being levied on the parties by the arbitral tribunal and
            other incidental expenses.
            [Reference: Law Relating to Arbitration and Conciliation
D           by Dr. P.C. Markanda; Lexis Nexis, Ninth Edition, Page
            460)
         19. There is no dispute between the parties that the issue at hand
  is governed by the amended provision of sub-section (6A) of Section 11.
  Even though Letters of Award are dated 17.03.2012 and five separate
E contracts were entered into between the parties on 10.05.2012, the
  dispute arose between the parties in 2016 as pointed out earlier,
  Gangavaram Port Limited invoked the Bank Guarantee on 07.01.2016
  and Mis. Dura Felguera and its Indian Subsidiary-FGI issued notice of
  dissatisfaction on 04.02.2016 and 07.02.2016 respectively to Gangavaram
F Port Limited. Mis. Dura Felguera issued arbitration notice on 05.04.2016
  for contract relating to Package No. 4 and FGI issued four arbitration
  notices dated 07.04.2016 for contracts relating to Packages No. 6 to 9.
  Gangavaram Port Limited also issued an arbitration notice on 13.04.2016.
  Since the dispute between the parties arose in 2016, the amended
  provision of sub-section (6A) of Section 11 shall govern the issue, as per
G which the power of the Court is confined only to examine the existence
  of the arbitration agreement.
      Whether there has to be a Single Arbitral Tribunal for
      'International Commercial Arbitration' or 'Multiple Arhitral
      Tribunals'?
H
 M/S. DURO FELGUERA, S. A. v. MIS. GANGAVA'RAM PORT                          307
              LIMITED [BANUMATHI, J.]

      20. Original Package No.4 Tender Document for Gangavaram A
Port Limited Expansion-2011 consisted of "Bulk Material Handling
Systems including Engineering, Design, Procurement of Materials,
Manufacturing, Supply erection, testing and coriunissioning of bulk
material handling systems including all other 0:5sociated works and
integration of the same with the existing coal handling systems B
(Package 4- "Works''). By mutual consent and agreement of the parties,
Original Package No.4 TD was split into five different Packages-New
Package No. 4 [awarded to Duro Felguera (Spanish Company)] and
Packages No. 6, 7, ~and 9 awarded to its Indian subsidiary-FGI. Letters
of Award dated 17.03.2012 was awarded to Duro Felguera and FGI for
various Packages. Pursuant to Letters of Award, parties have entered C
into contract agreement on 10.05.2012. These split-up contracts have
Volume I-Conditions of Contract; Volume II-Employer's Requirement,.
Scope ofWork, Specifications and Drawings; and Volume Ill-Schedule
of Prices. Five different Packages, the Letters of Award and the contract
awarded to Duro Fclguera and FGI and the Scope of Work and the
                                                                          D
value thereof, read as under:
    Package &      L.0.A.      Date of Contract &        Value/Price
      Parties        (2)       the Scope of Work              (4)
        (ll                             13)
    No.4         17.o3.2012    10.5.12                USO 26,666,932
    GPL-DF                     f.O.B.     SUPPLY
    (Spain)                    Of             BULK                           E
                               MATERIAL
                               HANDLING
                               EQUIPMENTS
    No.6         17.03.2012    10.5.12                Rs.208 ,66 ,53 ,65 7
    GPL-FGI                    Design,
    (India)                    manufacture,
                               supply,
                               installation,                                 F
                               erection,     testing,
                               commissioning of
                               Bulk         Material
                               Handling
                               Equipments and all
                               other       activities
                               related therewith                             G
    No.7         17 .03.2012   10.5 .12               Rs.59,14,65,706
    GPL-FGI                    Civil works and all
    (India)                    other       activities
                               related therewith
    No.8         17.03.2012    10.5.12                Rs.9,94,38,635
    GPL-FGI                    International
    (India)                    Transportation of
                               Bulk Material                                 H
308             SUPREME COURT REPORTS                           [2017] IO S.C.R.


A
                                        Handling
                                        Equipments and
                                        Parts through sea
                                        including
                                        insurance and all
                                        related activities
B             No.9         17.03.2012    10.5.12             Rs.29,52,85,558
              GPL-FGI                   Installations,
              (India)                   testing,             Some works
                                        commission of        deleted & price
                                        ship Unloaders       reduced to
                                        and other            Rs. 12,63,03,095
c                                       activities.
                                        25.7.14
                                        Variation of
                                        Contract
                  THECORPORATEGUARANTEECONTRACf
              GPL-DF       17.03.2012        ..... ....      Arbitration
D             (Spain)      Corporate                         Oanse-Cl.8
                           Guarantee

             21. On behalf of GPL, it was repeatedly urged that the works are
      intrinsically connected, inseparable, integrated, interlinked and that they
      are one composite contract and that they were split up only on the request
      and representations given by Duro Felguera and FGI. As discussed
E
      earlier, as per amended provision Section 11 (6A), the power of the
      Supreme Court or the High Court is only to examine the existence of an
      arbitration agreement. From the record, all that we could sec arc five
      separate Letters of Award; five separate Contracts; separate subject
      matters; separate and distinct work; each containing separate arbitration
F     clause signed by the respective parties to the contract.
            22. All the above five contracts awarded to Duro Fclguera and
      FGI have independent arbitration clauses. Mr. Sunil Gupta and Mr.
      A.M. Singh vi, learned Senior Counsel have taken us through the contract
      agreements in New Package No. 4 awarded to Mis Duro Felgucra and
G     Package No.6 (for sample) awarded to FGI and submitted that all the
      five different contracts have independent arbitration clauses (in sub-
      clause 20.6). In the contract New Package No.4 there is a header
      "Supp~v of Bulk Material Handling Equipments and Parts on FOB
      Basis". Likewise, contract agreement for Package No.6 contains the
      header "Design, manufacture, supply, installation, erection, testing
H
 MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                            309
              LIMITED [BANUMATHI, J.)

commissioning of Bulk Material Handling Equipments and all other              A
activities related therewJth ". Various clauses in the Original TD
Package No.4 were suitably modified and incorporated in the split-up
contract agreements. Sub-clause 20.6 dealing with arbitration in the
original Package No.4 TD has been reproduced in New Package No.4
and other Packages No. 6 to 9. The contract for New Package No. 4             B
which was entered into between Mis. Duro Fclgucra and GPL, also
contains an arbitration clause, which reads as under:
       "Sub-Clause 20.6 - Arbitration
       Any dispute in respect of which amicable settlement has not
       been reached within the period stated in Sub-Clause 20.5, shall        c
       be finally and conclusively settled by Arbitration under the
       Arbitration and Conciliation Act, 1996 by appointing two arbitrators
       one by each party and a presiding arbitrator to be appointed by
       the said arbitrators. Any such arbitration proceeding shall be
       within the exclusive jurisdiction of court of law at Hyderabad,
       India. The place of Arbitration shall be Hyderabad and the             D
       Language of Arbitration shall be English. The Contractor shall
       continue to attend to discharge all his obligations under the
       Contract during pendency of the Arbitration proceedings."
      23. Likewise, the four different contract Packages No. 6, 7, 8
and 9 which were awarded to FGI for different works also contain an           E
arbitration clause. Sub-clause 20.6 of Package No.6-Design,
manufacture, supply, installation, erection testing, commissioning
of Bulk Material Handling Equipments etc., reads as under:-
       "Sub-Clause 20.6 - Arbitration
                                                                              F
       Any dispute in respect of which amicable settlement has not
       been reached within the period stated in Sub-Clause 20.5, shall
       be finally and conclusively settled by Arbitration under the
       Arbitration and Conciliation Act, 1996 by appointing two mbitrators
       one by each party and a presiding arbitrator to be appointed by
       the said arbitrators. Any such arbitration proceeding shall be         G
       within the exclusive jurisdiction of court of law at Hyderabad,
       India. The place of Arbitration shall be Hyderabad and the
       Language of Arbitration shall be English. The Contractor shall
       continue to attend to discharge all his obligations under the
       Contract during pendency of the Arbitration proceedings."
                                                                              H
310           SUPREME COURT REPORTS                         [2017] IO S.C.R.


A Like Package No. 6. Contract/Agreement pertaining to other packages
   awarded to FGI, namely, Packages No.7, 8 and 9 also contain similar
  arbitration clause in sub-clause 20.6. The Original Package No. 4 TD
  split into five different Packages, each having different works prima
  facie indicates the intention of the parties to split-up original Package
  No. 4 TD into five different packages, as was discussed above.
8
         24. In the contract agreement, the parties have agreed that the
  documents mentioned in clause (2) of the agreement will have priority.
  Clause (2) of the agreement in New Package No. 4 awarded to Duro
   Felguera, reads as under:-
C           "2.The following documents shall form and be read and construed
            as part of this Agreement and shall have the priority one over
            the other in the following sequence:
              (a) this Agreement;
             (b) the Letter of Award;
D
              (c) Special Conditions of Contract (Conditions of Particular
                  Applications)
             (d) General Conditions of Contract;
              (e) the Employer's Requirements, Scope ofWork, Specifications
E                 and Drawings;
              (t) the Schedule of Prices;
              (g) the Tender to the extent annexed herewith."
  Similar clauses as to the priority of the documents was incorporated in
F all other contract agreements-Packages No. 6, 7, 8 and 9 awarded to
  Indian subsidiary FGI. In the sequence of documents of clause (2) of
  the contract agreement quoted above, the Tender Document is mentioned
  in the sequence only as (g) and all other documents or the other documents
  like Letters of Award, Special conditions of contract etc. have priority
  over the same. While so, the terms contained in Original Package No.
G 4 TD including the arbitration clause cannot have priority over the Special
  Conditions of contract of the split-up contracts. When the Original
  Package No. 4 TD has been split-up into five different Packages, GPL
  is not right in contending that inspite of split-up of the work, the Original
  Package No.4 TD collectively covered all the five Packages. After the
H Original Package No. 4 was split into five different contracts, the parties
  MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                            311
               LIMITED [BANUMATHI, J.]

cannot go back to the Original Package No.4 nor can they merge them            A
into one. We do not find merit in the submissions ofGPL that sub-clause
20.6 of the Original Package No. 4 TD will still collectively cover all the
five Packages to justify constitution of single Arbitral Tribunal.
       25. The foreign company-Duro Felguera had executed a Corporate
Guarantee dated 17.03.2012 guaranteeing the due performance of all             B
the works awarded to Duro Fclguera andFGI. The Corporate Guarantee
itself has its own separate and distinct arbitration clause. The arbitration
clause of the Corporate Guarantee i.e. clause (8) reads as under:
         "8. This Corporate Guarantee shall be governed by the
         Indian Laws. In case of any disputes, the Parties shall c
         endeavor to settle the same amicably. In case of failure to
         settle the disputes amicably, the same shall be finally
         settled under the Arbitration and Conciliation Act 1996 of
         India by appointing two Arbitrators, one by each party and
         a Presiding Arbitrator to be appointed by the said
         Arbitrators. The award of the Arbitrators shall be final D
         and binding on the Corpoi:ate Company and the Employer.
         Any such Arbitration proceeding shall be at Hyderabad
         and within the Jurisdiction of the Court of Law at
         Hyderabad, Andhra Pradesh, India.The Arbitration shall
         be conducted in English language."                          E
        26. In the Corporate Guarantee, Duro Felguera has undertaken
  to ensure performance of all the works both by Duro Felguera and also
  the contracts pertaining to Packages No. 6 to 9 awarded to FGI. Duro
. Felguera has also undertaken that in the event of any delay in completion
  of the works as per the time stipulated for completion of the contracts,     F
  Duro Felguera had undertaken to compensate for the delay, damages to
  GPL which will be based on the overall contract price collectively of all
  the contracts. The relevant clauses read as under:-
         "1. The Corporate Company hereby guarantees and
         covenants with the employer that FGI will perform all its             G
         obligations and duties as per package 6 to package 9,
         failing which the corpora_te company shall take over from
         FGI, as may be demanded by the employer under this
         Guarantee, and shall perform or cause to be performed at
         its own cost and risk and all the responsibilities, obligations
                                                                               H
312           SUPREME COURT REPORTS                          [2017] 10 S.C.R.


A           and duties of FGI under package 6 to Package 9 so far as
            and to the extent FGI was liable to perform it, without any
            additional time and cost implication to the employer,
            subject to the employer continuing to meet its own
            obligations under package 6 to package 9 with respect to
            payments, approvals for drawings and other related
B
            matters to the corporate company as if the corporate
            company were the principal contractor in place of FGI.
            2. In the event of any delay in completion of the works as
            per the time for completion of the contracts for the reasons
            attributable to FGI and/or the corporate company, such
c           that these delays in turn results in causing overall delay
            in completion of all or any one of the contracts, then the
            corporate company hereby undertakes to compensate for
            the delay damages to the employer, which shall be based
            on the overall contract price collectively of all the contracts
D           and any other contract that may be entered into by and
            between the employer and the corporate company or
            FGI .......... "
         27. Content10n of GPL is that as per the Corporate Guarantee,
  the Spanish Company has inter alia undertaken to compensate GPL for
E delay  damages, based on the overall contract price collectively of all the
  Contracts awarded to both Duro Fclguera and FGI, arising on account
  of delay in completion of the works in any one or all of the five Contracts.
  It is contended that the Spanish Company is obligated to take over and
  perform the works at its own costs, risk and responsibilities, as if it is the
  Principal Contractor including for the works awarded to the Indian
F Subsidiary and therefore as per terms of Corporate Guarantee executed
  by Duro Fclguera, there has to be a single arbitral tribunal for all the
  Packages.
        28. As per the terms of Corporate Guarantee, it shall cease on
  issuance of the performance certificate under all the contracts. Of course,
G Duro Felguera has given the Corporate Guarantee for all the five
  contracts viz., New Package No.4, Packages No. 6 to 9. Corporate
  Guarantee executed by Duro Felguera dated 17.03.2012 also recognizes
  the split up of the original Package No. 4 Tender Document. As per the
  terms of the Corporate Guarantee, it is to be invoked only if breach is
H established in one of the five contracts. Since the Corporate Guarantee
 MIS. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                            313
              LIMITED [BANUMATHI, J.]

by itself has a separate arbitration clause, it cannot be contended that by   A
virtue of the Corporate Guarantee executed by Duro Felguera, there
has to be a 'composite reference' of 'International Commercial
Arbitration' which would cover all the five Packages. The Corporate
Guarantee hy Duro Felguera cannot supersede the five split-up contracts
and the special conditions of contract thereon.
                                                                              B
       29. Duro Felguera and FGI have executed a tripartite
Memorandum ofUnderstanding (MoU) on 11.08.2012 which, according
to GPL, covers all the five contracts namely New Package No. 4,
Package No. 6, Package No. 7, Package No. 8 and Package No. 9. In
the said MoU both Duro Felguera and FGI have agreed to carry out the
works as per the priority of the documents listed therein which includes      c
the Original Package No.4 Tender Document issued and final bid
submitted by Duro Felguera and FGI. The relevant portion of
Memorandum of Understanding reads as under:-
        "This Memorandum of Understanding (MoU) has been
        executed at Hyderabad on 11 •h August 2012 by and                     D
        between:
        Mis Gangavaram Port Limited.....
           And
        Mis Duro Felguera Plantas lndusfries, S.A ....... .,                  E
        Mis Felguera Gruas India Private Limited ........
       (Both DFPI and FGI shall jointly be referred to as the
       Contractors. The Employer and the contractors shall
       collectively be referred tQ as the Parties. All the captive
                                                                              F
       terms used if any herein shall have the same meaning
       ascribed to it in the Contract.)
       Whereas the parties have entered into different package
       contracts for execution of Bulk Material Handling System
       under "Original Package 4 Tender Document" covering ·
       ship unloaders, stackers, reclaimers, in-motion wagon G
       loading system, conveyors, transfer towers, electrical and
       control works, civil works, etc1 and in order to have more
       clarity on technical and execution related matters, the
       parties hereby agree that the works shall be carried out
       as per the following priority of documents.                H
314           SUPREME COURT REPORTS                       [2017] lOS.C.R.


A             1. Annexure I to the Letter of Award issued for Package
                 4 Contract.
              2. Annexure III to the Letter of Award issued for
                 Package 4, 6, 7, 8, and 9 contracts.
              3. Clarifications/Addendum No.I to 4 (in the descending
B                order) issued by the Employer to the Original Package
                 4 Tender Document.
              4. The Original Package 4 Tender Document issued by
                 the Employer.

c             5. Final Technical Bid submitted by the Contractors in
                 response to the Original Package 4 Tender
                 Document.
      The parties undertake to keep this MoU as strictly confidential."
         30. Contention of GPL is that Memorandum of Understanding
 D (dated 11.08.2012) collectively covers all the five Packages and MoU
   shall prevail over the arbitration clauses contained in fi vc different
   Packages. In this regard, reliance was placed upon sub-section (5) of
   Section 7 of the Act to contend that since reference is made to Original
   Package No.4 TD in MoU, arbitration clause 20.6 must be deemed to
   have become part ofMoU. In support of their contention, learned Senior
 E
   Counsel Mr. Mukul Rohatgi and Mr. Raju Ramchandran appearing for
   GPL, placed reliance upon Chloro Controls India Private Ltd. v. Severn
   Trent Water Purification Inc. and Others (2013) 1 SCC 641.
          31. Per contra, the learned Senior Counsel for Duro Felguera and
   FGI submitted that merely because MoU refers to Original Package
 F
   No.4 Tender Document, such mere reference cannot lead to an inference
   of arbitration clause being incorpo,rated as it only depends upon the
   intention of the Pa11ies. It was further submitted that the Memorandum
   of Understanding (MoU) is merely a supplementary document which
   was meant to lay down the priority of documents only to clarify the
 G priority in execution of the work under different Packages. It was further
   submitted that MoU was neither intended to alter the nature of the rights,
   responsibilities and obligafions of the parties involved in the respective
   contracts nor does it override the terms of the main contract including
   the arbitration clauses in the five different packages.
 H
 MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                             315
              LIMITED [BANUMATHI, J.]

       32. In light of the above contentions, the point falling for            A
consideration is by virtue of sub-section (5) of Section 7, whether the
MoU is to be taken as the basis for arbitration, justifying the constitution
of single arbitral tribunal because a reference is made to Original Package
No.4 TD in Memorandum of Understanding (MoU).
      33. Section 7 (5) of the Arbitration and Conciliation (Amendment)        B
Act, 2015 reads as under:-
         "7. Arbitration agreeme11t.-(l) .....
        (5) The reference in a contract to a document containing an
        arbitration clause constitutes an arbitration agreement if the
        contract is in writing and the reference is such as to make that       C
        arbitration clause part of the contract."
As per Section 7(5) of the Act, even though the contract between the
parties does not contain a provision for arbitration, an arbitration clause
contained in an independent document will be imported and engrafted in
the contract between the parties, by reference to such independent D
document in the contract, if the reference is such as to make the
arbitration clause in such document, a part of the contract. Section
7(5) requires a conscious acceptance of the arbitration clause from
another document, as a part of their contract, before such arbitration
clause could be read as a part of the contract between the parties. The E
question whether or not the arbitration clause contained in another'
document, is incorporated in the contract, is always a question of
construction of document in reference to intention of the pmiies. The
terms of a contract may have to be ascertained by reference to more
than one document.
                                                                               F
      34. In M.R. Engineers tind Contractors Private Limited v. Som
Datt Builders Limited (2009) 7 SCC 696, the Supreme Court held that
even though the contract between the parties does not contain a provision
for arbitration, an arbitration clause contained in an independent document
will be incorporated into the contract between the parties, by reference,
if the reference is such as to make the arbitration clause in such document,   G
a part of the contract. In M. R. Engineers and Contractors Private
Limited (supra), this Court held as under:-
        13 ........ Having regard to Section 7(5) of the Act, even though
        the contract between the parties docs not contain a provision for
                                                                               H
316    SUPREME COURT REPORTS                          [2017] JO S.C.R.


A     arbitration, an arbitration clause contained in an independent
      document will be imported and engrafted in the contract between
      the pa11ies, by reference to such independent document in the
      contract, if the reference is such as to make the arbitration
      clause in such document, a part of the contract.
B
      22. A general reference to another contract will riot be sufficient
      to incorporate the arbitration clause from the referred contract
      into the contract under consideration. There should be a special
      reference indicating a mutual intention to incorporate the
c     arbitration clause from another document into the contract. The
      exception to the requirement of special reference is where the
      referred document is not another contract, but a standard form
      of terms and conditions of trade associations or regulatory
      institutions which publish or circulate such standard terms and
      conditions for the benefit of the members or others who want to
D     adopt the same.


      24. The scope and intent of Section 7( 5) of the Act may therefore
      be summarised thus:
 E         (i) An arbitration clause in another document, would get
        incorporated into a contract by reference, if the following
        conditions arc fulfilled:
           (1) the contract should contain a clear reference to the
           documents containing arbitration clause,
 F
           (2) the reference to the other document should clearly
           indicate an intention to incorporate the arbitration clause
           into the contract,
           (3) the arbitration clause should be appropriate, that is
           capable of application in respect of disputes under the
 G         contract and s~ould not be repugnant to any term of the
           contract.
          (ii) When the parties enter into a contract, making a general
        reference to another contract, such general reference would
        not have the effect of incorporating the arbitration clause from
 H
 M/S. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                              317
              LIMITED [BANUMATHI, J.]

         the referred document into the contract between the parties.           A
         The arbitration clause from another contract can be
         incorporated into the contract (where such reference is made),
         only by a specific reference to arbitration clause.
             (iii) Where a contract between the parties provides that the
          execution or performance of that contract ,shall be in terms of       B
          another contract (which contains the terms and conditions
          relating to performance and a provision for settlement of
          disputes by arbitration), then, the terms of the referred contract
          in regard to execution/performance alone will apply, and not
          the arbitration agreement in the referred contract, unless there
          is special reference to the arbitration clause also.
                                                                                c
            (iv) Where the contract provides that the standard form of
          terms and conditions of an independent trade or professional
          institution (as for example the standard terms and conditions
          ofa trade association or architects association) will bind them
          or apply to the contract, such standard form of terms and             D
          conditions including any provision for arbitration in such standard
          terms and conditions, shall be deemed to be incorporated by
          reference. Sometimes the contract may also say that the parties
          are familiar with those terms and conditions or that the parties
          have read and understood the said terms and conditions.               E
             ( v) Where the contract between the paiiie's stipulates that
          the conditions of contract of one of the parties to the contract
          shall form a part of their contract (as for example the general
          conditions of contract of the Government where the
          Government is a party), the arbitration clause forming part of        F
          such general conditions of contract will apply to the contract
          between the parties."
        35. Considering the MoU, in light of the above ratio, as pointed
out earlier, in the MoU, Original Package No.4 Tender Document is
merely referred only to have more clarity on technical and execution            G
related matters and the parties agreed that the works shall be carried
out as. per the priority of the documents indicated thereon. Mere reference
to Original Package No.4 Tender Document in the sequence of priority
of documents (as serial No.4) indicates that the documents Original
Package No. 4 TD containing arbitration clause was not intended to be
                                                                                H
318                SUPREME COURT REPORTS                        [2017) IO S.C.R.


A     incorporated in its entirety but only to have clarity in priority of the
      documents in execution of the work. Be it noted that Original Package
      No.4 TD occurs as Serial No.4 in sequence, after three other documents
      VIZ .. .,

                  "(i) Annexure I to the Letter of Award issued j(Jr Package
B                 No. 4 Contract: and (ii) Annexure fl! lo the Letter of Award
                  issued for Packages No. 4, 6, 7, 8 and Y contracts; and
                  (iii) Clarifications!Addendwns No. 1 to 4 (in the descending
                  order) issued hy the Employer to the Original Package No.
                  4 Tender Document. "
c There are a number of contract agreements between the parties - GPL,
  Duro Felguera and FGI. It is pertinent to note that MoU dated 11.08.2012
  itself does not contain an arbitration clause. When reference is made to
  the priority of documents to have clarity in execution of the work, such
  general reference to Original Package No.4 Tender Document will not
  be sufficient to hold that the arbitration clause 20.6 in the Original Package
D No.4 TD is incorporated in the MoU.
               36. The submission of GPL is that since referene..: to Original
      Package No.4 TD is made in MoU, the arbitration dause is incorporated
      in th..: MoU and ther..: has to be a 'composite reference· for settling the
      disputes under different contracts by constitution of single arbitral tribunal
 E    for dealing with the international commercial arbitration. As discussed
      earlier, as per the amended provision of sub-section (6A) of Section 11,
      the power of the court is only to examine the existence of arbitration
      agreement. When there are five separate contracts each having
      independent existence with separate arbitration clauses that is New
 F    Package No.4 (with foreign company Duro Felguera) and Packages
      No. 6, 7, 8 and 9 [with Indian subsidiary (FGI)] based on MoU and
      Corporate Guarantee, there cannot be a single arbitral tribuna I for
      ''international Commercial Arbitration".
             37. It was submitted that if the reque~t (1f GPL is accepted and all
 G    Packages arc considered under the sam.: rdcr..:ncc, they shall be treated
      as international commercial arbitrations, then FGI may lose the opportunity
      of challenging the award under Section 34(2A) of th..: Act. In response
      to the above submission, GPL offered to concede and submitted that
      Section 34 (2A) of the Act may be invoked by Indian subsidiary-FG!,
      though Section 34(2A) is not applicable to international commercial
 H
  MIS. DURO FELGUERA, S. A. v. M/S.•GANGAVARAM PORT                               319
                      LIMITED [BANUMATHI, J.]

arbitration. Such a concession is against the provisions and specific             A
mandate of legislature and cannot be accepted.
       38. The Corporate Guarantee dated 17.03.2012 was executed by
the foreign company-Duro Felguera undertaking to compensate for the
delay, damages to the GPL. Since the Corporate Guarantee was by the
foreign company-Duro Felguera which contains separate arbitration                 B
clause, there has to be a separate arbitral tribunal for resolving the disputes
arising out of the said Corporate Guarantee.
      39. New Package No. 4 TD- F.O.B. Supply of Bulk Material
Handling Equipments USD 26,666,932 has been awarded to the foreign
company-Duro Felguera. Since Duro Felguera is a foreign company, in               c
so far as the contract awarded to Duro Felguera i.e. New Package
No.4 and the dispute arising out of the Corporate Guarantee executed
by the foreign company-Duro Felguera is concerned, the arbitral tribunal
has to be for the international commercial arbitration.
       40. The learned Senior Counsel for GPL relied upon Chloro D
Controls India Private Ltd. (supra), to contend that where various
agreements constitute a composite transaction, court can refer disputes
to arbitration if all ancillary agreements are relatable to principal
agreement and performance of one agreement is so intrinsically interlinked
with other agreements. Even though Chloro Controls has considered
the doctrine of "composite reference", "composite performance" etc., E
ratio of Chloro Co11trols may not be applicable to the case in hand. In
Cltloro Controls, the arbitration clause in the principal agreement i.e.
clause ·(30) required that any dispute or difference arising under or in
connection with the principal (mother) agreement, which could not be
settled by friendly negotiation and agreement between the parties, would F
be finally settled by arbitration conducted in accordance with Rules of
ICC. The words thereon "under and in connection with" in the principal
agreement was very wide to make it more comprehensive. In that
background, the performance of all other agreements by respective
parties including third parties/non-signatories had to fall in line with the
principal agreement. In such factual background, it was held that all G
 agreements pertaining to the entire disputes are to be settled by a
''.composite reference". The case in band stands entirely on different·
 footing. As discussed earlier, all five different Packages as well as the
 Corporate Guarantee have separate arbitration clauses and they do not
 depend on the terms and conditions of the Original Package No.4 TD H
320             SUPREME COURT REPORTS                         [20 l 7J JO S.C.R.



A     nor on the MoU, which is intended to have clarity in execution of the
      work.
            41. Duro Felguera being a foreign company, for each of the
      disputes arising under New Package No.4 and Corporate Guarantee,
      International Commercial Arbitration Tribunai arc to be constituted. Mi
B     s. Duro Felguera has nominated Mr. Justice D.R. Deshmukh (Former
      Judge of Chhattisgarh High Court) as their arbitrator. Gangavaram
      Port Limited (GPL) has nominah:d Mr. Justice M.N. Rao (Former
      Chief Justice of Himachal Pradesh High Court). Alongwith the above
      two arbitrators Mr. Justice R.M. Lodha, Former ChiefJustice oflndia is
      appointed as the Presiding Arbitrator of the International Commercial
c     Arbitral Tribunal.
         42. Package No.6 (Rs.208,66.53.657/-); Package No.7
   (Rs.59,14,65,706/-); Package No.8 (Rs.9.94.38.6351-); and Package No.9
   (Rs.29,52,85, 5581-) have been awarded to the Indian company-FOi.
   Since the issues arising between the parties are inter-related. the same
D arbitral tribunal, Justice R.M. Lodha, Former Chief Justice oflndia,
   Justice D.R. Deshmukh, Former Judge of Chhattisgarh High
  ·Court and Justice M. N. Rao, Former Chit:f Justice of Himachal
   Pradesh High Court, shall separately constitl<IL Domestic Arbitral
   Tribunals for resolving each of the disputes pertaining to Packages No.6,
E 7, 8 and 9.
             43. Arbitration Petition No. 30 of 2016 filed by Duro Felguera
      shall stand allowed and Arbitration Petition No.31 of2016 filed by GPL
      shall stand disposed of in the same line. Transfer Case No. 25/2017,
      Transfer Case No. 26/2017, Transfer Case No. 2712017 and Transfer
F     Case No. 28/2017 filed by FGI shall also stand disposed of in the above
      lines. Parties shall bear their respective costs.

            KURIAN, J.: I. While agreeing with the conclusions in the
      illuminating judgment of my esteemed sister Banumathi, J., I feel that a
      few more lines would add greater lustre to thl.' j •c1dgment.
G
            2. What is the effect of the change introduced by the Arbitration
      and Conciliation (Amendment) Act, 2015 (hereinafter reforred to as .. the
      2015 Amendment") with particular reference to Section 11(6) and the
      newly added Section I 1(6A) of the Arbitration and Conciliation Act.
      1996 (hereinafter referred to as .. the 1996 Act") is the crucial question
H     arising for consideration in this case.
 M/S. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                           321
               LIMITED [KURIAN, J.]

      3. Section 11(6A) added by the 2015 Amendment, reads as                A
follows:
       "11 (6A) The Supreme Court or, as the case may be, the High
       Court, while considering any application under sub-section (4)
       or sub-section ( 5) or sub-section ( 6), shall, notwithstanding any
       judgment, decree or order of any Court, confine to the                B
       examination of the existence of an arbitration agreement."
                                                    (Emphasis Supplied)
       From a reading of Section l 1(6A), the intention of the legislature
is crystal clear i.e. the Court should and need only look into one aspect-
the existence of an arbitration agreement. What are the factors for          C
deciding as to whether there is an arbitration agreement is the next
question. The resolution to that is simple - it needs to be seen if the
agreement contains a clause which provides for arbitration pertaining to
the disputes which have arisen between the parties to the agreement.
       4. On the facts of the instant case, there is no dispute that there D
are five distinct contracts pertaining to five different works. No doubt c
that all the works put together are for the expansion of facilities at
Gangavaram Port. However, the pa1iies took a conscious decision to
split the works which led to five separate contracts and consequently an
arbitration Clause in each split contract was retained. The sixth one, E
namely the Corporate Guarantee also contains an arbitration clause.
      5. The main thrust of the arguments of Mr. Mukul Rohatgi, learned
Senior Counsel, is that the Memorandum of Understanding (hereinafter
referred to as "MoU") has subsumed all the separate agreements and
therefore and thereafter there can only be one agreement and, if so,
                                                                             F
only one Arbitral Tribunal for all the disputes emanating from the five
different agreements and the Corporate Guarantee. This submission in
our view is misconceived. The whole purpose of the MoU is evident
from its text, the relevant portion of which has been extracted below:-
        "Whereas the parties have entered into different package             G
        contracts for execution of Bulk Material Handling System under
        "Original Package 4 Tender Document" covering ship unloaders,
        stackers, reclaimers, in-motion wagon loading system, conveyors,
        transfer towers, electrical and control works, civil works, etc.
        and in order to have more clarity on technical and execution
                                                                             H
322             SUPREME COURT REPORTS                           [2017] IO S.C.R.


A             related matters, the parties hereby agree that the works shall be
              carried out as per the following priority of documents:
              1. Annexure I to the Letter of Award issued for Package 4
              Contract.
              2. Annexure Ill to the Letter of Award issued for Package 4, 6,
B             7, 8 and 9 contracts.
              3. Clarifications/ Addendum No. 1 to 4 (in the descending order)
              issued by the Employer to the Original Package 4 Tender
              Document.
C             4. The Original Package 4 Tender Document issued by the
              employer.
              5. Financial Technical Bid submitted by the contractors in
              response to the Original Package 4 Tender Document."
                                                             (Emphasis supplied)
D
            6. It is clear that there is no novation by substitution of all the five
      agreements nor is there a merger of all into one. The reference to Original
      Package No. 4 Tender Document is only for better clarity on technical
      and execution related matters.
            7. The above finding is wholly in line with Section 7(5) of the 1996
E
      Act. Section 7 which deals with arbitration agreement reads as follows:-
              "7. Arbitration agreement.-( I) In this Part, "arbitration
              agreement" means an agreement by the parties to submit to
              arbitration all or certain disputes which have arisen or which
              may arise between them in respeti of a defined legal relationship,
F             whether contractual or not.
              (2) An arbitration agreement may be in the form of an arbit1:ation
              clause in a contract or in the form of a separate agreement.
              (3) An arbitration agreement shall be in writing.
G             (4) An arbitration agreement is in writing if it is contained in -
              (a) a document signed by the parties;
              (b) an exchange of letters, telex, telegrams or other means of
              telecommunication including communication through electronic
              means which provide a record of the agreement; or
H
    M/S. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                           323
                  LIMITED [KURIAN, J.]

          (c) an exchange of statements of claim and defence in which           A
          the existence of the agreement is alleged by one party and not
          denied by the other.
          (filhe reference in a contract to a document containing an
          arbitration clause constitutes an arbitration agreement if the
          contract is in writing and the reference is such as to make that      B
          arbitration clause part of the contract."
                                                      (Emphasis Supplied)
      Section 7(5) deals with incorporation by reference. The words
"the reference is such as to make that arbitration clause part of the
contract" are of relevance. Essentially, the parties must have the intention    c
to incorporate the arbitration clause. In M.R. Engineers and
Contractors Pvt. Ltd. v. Som Datt Builders Ltd. 1, Raveendran, J.
has dealt with this particular requirement in a comprehensive manner.
To quote:
          "14. The wording of Section 7(5) of the Act makes it clear that       D
          a mere reference to a document would not have the effect of
          making an arbitration clause from that document, a part of the
          contract. The reference to the document in the contract should
          be such that shows the intention to incorporate the arbitration
          clause contained in the document, into the contract. If the           E
          legislative intent was to import an arbitration clause from another
          document. merely on reference to such document in the contract,
          sub-section (5) would not contain the significant later part which
          reads: "and the reference is such as to make that arbitration
          clause part of the contract", but would have stopped with the
          first part which reads:                                               F
            "7. (5) The reference in a contract to a document containing
            an arbitration clause constitutes an arbitration agreement if
            the contract is in writing .... "
                   xxx                xxx            xxx                        G
          19. Sub-section (5) of Section 7 merely reiterates these well-
          scttled principles of construction of contracts. It makes it clear
          that where there is a reference to a document in a contract, and
          the reference shows that the document was not intended to be
1
    (2009) 7 sec 696                                                            H
324    SUPREME COURT REPORTS                         (2017] I0 S.C.R.


A     incorporated in entirety, then the reference will not make the
      arbitration clause in the document, a part of the contract, unless
      there is a special reference to the arbitration clause so as to
      make it applicable.
                xxx            xxx                xxx
B     22. A general reference to another contract will not be sufficient
      to incomorate the arbitration clause from the referred contract
      into the contract under consideration. There should be a special
      reference indicating a mutual intention to incorporate the
      arbitration clause from another document into the contract. The
      exception to the requirement of special reference is where the
c     referred document is not another contract. but a standard form
      of terms and conditions of trade associations or regulatory
      institutions which publish or circulate such standard terms and
      conditions for the benefit of the members or others who want to
      adopt the same.
D                                               xxx
              xxx            xxx
      24. The scope and intent of Section 7(5) of the Act may therefore
      be summarised thus:
      (i) An arbitration clause in another document, would get
 E    incorporated into a contract by reference, if the following
      conditions arc fulfilled:
        (1) the contract should contain a clear reference to the
        documents containing arbitration clause,
        (2) the reference to the other document should clearly indicate
 F      an intention to incorporate the arbitration clause into the
        contract,
        (3) the arbitration clause should be appropriate, that is capable
        of application in respect of disputes under the contract and
        should not be repugnant to any term of the contract.
 G    (ii) When the parties enter into a contract, making a general
      reference to another contract, such general reference would not
      have the effect of incorporating the arbitration clause from the
      referred document into the contract between the parties. The
      arbitration clause from another contract can be incomorated into
 H
MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                               325
               LIMITED [KURIAN, J.]

       the contract (where such reference is made), only by a specific          A
       reference to arbitration clause.
        (iii) Where a contract between the parties provides that
       the execution or performance of that contract shall be in
       terms of another contract (which contains the terms and
       conditions relating to performance and a provision for                   B
       settlement of disputes by arbitration), then, the terms of
       the referred contract in regard to execution/performance
       alone will apply, and not the arbitration agreement in the
       referred contract, unless there is special reference to the
       arbitration clause also.
                                                                                c
       (iv) Where the contract provides that the standard form of terms
       and conditions of an independent trade or professional institution
       (as for example the standard terms and conditions of a trade
       association or architects association) will bind them or apply to
       the contract, such standard form of terms and conditions including
       any provision for arbitration in such standard terms and conditions, D
       shall be deemed to be incorporated by reference. Sometimes
       the contract may also say that the parties are familiar with those
       terms and conditions or that the parties have read and understood
       the said terms and conditions.
         (v) Where the contract between the parties stipulates that the E
       conditions of contract of one of the parties to the contract shall
        form a part of their contract (as for example the general conditions
        of contract of the Government where the Government is a party),
        the arbitration clause forming part of such general conditions of
        contract will apply to the contract between the parties."            F
                                                      (Emphasis supplied)
      8. The detailed analysis of Section 7(5) in M.R. Engineers
(supra) further fortifies our conclusion that the MoU does not incorporate .
an arbitration clause.
                                                                                 G
        9. Learned Senior Counsel also contended that for convenience,
it is expedient that a single Arbitral Tribunal is constituted. We are afraid
that this contention also cannot be appreciated. The parties arc free to
agree to anything for their convenience but once suc'li tcnns arc reduced
to an agreement, they can rcsilc from them only in accordance with law.
                                                                                 H
326               SUPREME COURT REPORTS                          [20 I 7] IO S.C.R.


A             10. Having said that, this being one of the first cases on Section
       11(6A) of the 1996 Act before this Court, I feel it appropriate to briefly
       outline the scope and extent of the power of the High Court and the
       Supreme Court under Sections 11(6) and l 1(6A).
        11. This Court in S.B.P & Co v. Patel Engineering Ltd and
B Another 2 overruled Konkan Railway Corpn. Ltd. and others v.
  Mehul Construction Co. 3 and Konkan Railway Corpn. Ltd. &
  another. v. Rani Construction Pvt. Ltd. 4 to hold that the power to
  appoint an arbitrator under Section I 1 is a judicial power and not a mere
  administrative function. The conclusion in tne decision as summarized
  by Balasubramanyan, J. speaking for the majority reads as follows:
c
               "47. We, therefore, sum up our conclusions as follows:
               (i) The power exercised by the Chief Justice of the High Court
               or the Chief Justice oflndia under Section 11 (6) of the Act is not
               an administrative power. It is a judicial power.
D              (ii) The power under Section 11(6) of the Act, in its entirety,
               could be delegated, by the Chief Justice of the High Court only
               to another Judge of that Court and by the Chief Justice of India
               to another Judge of the Supreme Court.
               (iii) In case of designation of a Judge of the High Court or of the
E              Supreme Court, the power that is exercised by the designated
               Judge would be that of the Chief Justice as conferred by the
               statute.
               (iv) The ChiefJustice or the designated Judge will have the right
               to decide the preliminmy aspects as indicated in the earlier part
               of this judgment. These will be his own jurisdiction to entertain
F
               the request. the existence of a valid arbitration agreement, the
               existence or otherwise of a Ii ve claim, the existence of the
               condition for the exercise of his power and on the qualifications
               of the arbitrator or arbitrators. The ChiefJustice or the designated
               Judge would be entitled to seek the opinion of an institution in the
G              matter ofnominating an arbitrator qualified in terms of Section
               I 1(8) of the Act if the need arises but the order appointing the
               arbitrator could only be that of the ChiefJustice or the designated
               Judge.
      '(2005J s sec 618
      ' (2000J 1 sec 201
H     ·1 (2002) 2 sec 388
M/S. DURO FELGUERA, S. A. v. M/S. GANGAVARAM PORT                            327
              LIMITED [KURIAN, J.]

    (v) Designation of a District Judge as the authority under Section       A
    11 (6) of the Act by the Chief Justice of the High Court is not
    warranted on the scheme of the Act.
    (vi) Once the matter reaches the Arbitral Tribunal or the sole
    arbitrator, the High Court would not interfere with the orders
    passed by the arbitrator or the Arbitral Tribunal during the course      B
    of the arbitration proceedings and the parties could approach the
    Court only in terms of Section 37 of the Act or in terms of Section
    34 of the Act.
    (vii) Since an order passed by the Chief Justice 9f the High
    Court or by the designated Judge of that Court is a judicial order,      c
    an appeal will lie against that order only under Article 136 of the
    Constitution to the Supreme Court.
    (viii) There can be no appeal against an order of the Chief Justice
    of India or a Judge of the Supreme Court designated by him
    while entertaining an application under Section 11 (6) of the Act.       D
    (ix) In a case where anArbitral Tribunal has been constituted by
    the parties without having recourse to Section 11(6) of the Act,
    the Arbitral Tribunal will have the jurisdiction to decide all matters
    as contemplated by Section 16 of the Act.
    (x) Since all were guided by the decision of this Court in Konkan        E
    Rly. Corpn. Ltd. v. Rani Construction (P) Ltd. and orders under
    Section 11 (6) of the Act have been made based on the position
    adopted in that decision, we clarify that appointments of
    arbitrators oi· Arbitral Tribunals thus far made, are to be treated
    as valid, all objections being left to be decided under Section 16
                                                                             F
    of the Act. As and from this date, the position as adopted in this
    judgment will govern even pending applications under Section
    11(6) of the Act.
    (xi) Where District Judges had been designated by the Chief
    Justice of the High Court under Section 11(6) of the Act, the
                                                                             G
    appointment orders thus far made by them will be treated as
    valid;, but applications ifany pending before them as on this date
    will stand transferred, to be dealt with by the ChiefJustice of the
    High Court concerned or a Judge of that Court designated by
    the Chief Justice.
                                                                             H
328             SUPREME COURT REPORTS                          [2017] IOS.C.R.


A             (xii) The decision in Konkan Rly. Corpn. Ltd. v. Rani
              Construction (P) Ltd is overruled."
                                                           (Emphasis Supplied)
          12. This position was further clarified in National Insurance
      Company Limited v. Boghara Polyfab Private Limited5 To quote:
B
              "22. Where the intervention of the court is sought for appointment
              ofanArbitral Tribunal under Section 11, the duty of the Chief
              Justice or his designate is defined in SBP & Co. This Cou11
              identified and segregated the preliminary issues that may arise
              for consideration in an application under Section 11 of the Act
c             into three categories, that is, (i) issues which the Chief Justice or
              his designate is bound to decide; (ii) issues which he can also
              decide, that is, issues which he may choose to decide; and (iii)
              issues which should be left to the Arbitral Tribunal to decide.
              22.1. The issues (first category) which the Chief Justice/his
D             designate will have to decide are:
                (a) Whether the party making the application has approached
                the appropriate High Court.
                (h) Whether there is an arbitration agreement and whether
                the party who has applied under Section l l of the Act, is a
E
                party to such an agreement.
              22.2. The issues (second categmy) which the Chief Justice/his
              designate may choose to decide (or leave them to the decision
              of the Arbitral Tribunal) are:
F               (a) Whether the claim is a dead (long-barred) claim or a live
                claim.
                (b) Whether the parties have concluded the contract/transaction
                by recording satisfaction of their mutual rights and obligation
                or by receiving the final payment without objection.
G             22.3. The issues (third category) which the Chief Justice/his
              designate should leave exclusively to the Arbitral Tribunal are:
                (i) Whether a claim made falls within the arbitration clause (as
                for example, a matter which is reserved for final decision of a
H     '(2009J 1 sec 261
  MIS. DURO FELGUERA, S. A. v. MIS. GANGAVARAM PORT                               329
               - LIMITED [KURIAN, J.]

             departmental authority and excepted or excluded from                 A
             arbitration).
             (ii) Merits or any claim involved in the arbitration."
       13. The scope of the power under Section 11 (6) of the 1996 Act
was considerably wide in view of the decisions in SBP and Co. (supra)
and Boghara Polyfab (supra). This position continued till the amendment B
brought about in 201 S. After the amendment, all that the Courts need to
see is whether a~ arbitration agreement exists - nothing more, nothing
less. The legislative policy and purpose is essentially to minimize the
Court's intervention at the stage of appointing the arbitrator and this
intention as incorporated in Section 11 (6A) ought to be respected.      c
       14. In the case at hand, there are six arbitrable agreements (five
agreements for works and one Corporate Guarantee) and each agreement
contains a provision for arbitration. Hence, there has to be an Arbitral
Tribunal for the disputes pertaining to each agreemenL While the
arbitrators can be the same, there has to be six Tribunals - two for D
international commercial arbitration involving the Spanish Company-
M/s Duro Felguera, S.A. and four for the domestic.


Nidhi Jain                                                 Matters disposed ot:


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.