M/S. DURGA RAM PRASADversusGOVT. OF ANDHRA PRADESH
- Citation
- 1994 INSC 539
- Decided
- 23 November 1994
- Disposal
- Dismissed
Holding
The contractor is not entitled to interest on the withheld amounts for the period prior to arbitration, and the arbitrator lacks jurisdiction to award such interest.
Summary
The appellant, a contractor, entered into a contract to construct a food‑grains godown for the Government of Andhra Pradesh. The engineer withheld part of the payment alleging that the work was not executed as per the contract. The dispute was referred to an arbitrator who awarded the contractor the withheld sum together with interest. The State challenged the award of interest, invoking clause 69 of the Model Development Scheme (MDSS) which contracts out interest on amounts due. The Supreme Court examined whether the contractor was entitled to interest from the dates of withholding and whether the arbitrator had jurisdiction to award such interest. It held that clause 69 bars interest on amounts that are to be determined on final settlement, and that the arbitrator cannot award interest for the period prior to reference. Consequently, the contractor is not entitled to interest and the High Court’s decision was affirmed. The appeals were dismissed without costs.
Issues considered
- Whether the contractor is entitled to interest on amounts wrongfully withheld by the engineer under clause 69 of the MDSS.
- Whether the arbitrator had jurisdiction to award interest for the period preceding the reference to arbitration.
Legislation cited
Subjects
Judgment
MIS DUGRA RAM PRASAD A
v.
GOVT. OF ANDHRA PRADESH
NOVEMBER23, 1994
[K. RAMASWAMY AND K. JA YACHANDRA REDDY, JJ.] B
Arbitration Act, 1940-Contract to execute work-Amount due to
contractor withheld-Claim of State that work not executed as per
contract-Arbitration-Entitlement of interest on amounts withheld by
State-Held: Party not entitled to interest.
, c
The appellant had entered into a contract to construct foodgrains
godown. In execution thereof, a dispute had arisen whether the
appellant had executed the work as per the contract and was entitled to
certain sums of money withheld by the engineer and also to the interest
payable thereon. The dispute had been referred to the Arbitrator, who D
in his Award awarded a sum of money with interest on the amounts
wrongfully withheld by the engineer. The State challenged the
entitlement of interest on the amounts withheld by the engineer. The
High Court negatived the claim for interest. These appeals by special
leave arise from the judgment of the High Court.
The appellant contended that when the appellant had executed the
E
work within the period, in terms of the contract, and the officials of the
respondent had wrongfully withheld the due payment, on the respective
dates, the appellant was entitled to the interest on the amounts
wrongfully withheld. It further contended that Clause 69 of the M.D.
S.S. was inapplicable to the facts of this case. F
The questions which arose for consideration were whether the
appellant was entitled to payment of interest from the respective dates
on which the amounts were withheld by the concerned engineer and
whether the dispute was arbitrable.
G
Dismissing the appeal, this Court
----
HELD: I.I. The claim of the State appears to be that the appellant
had not constructed the godown in accordance with the specifications
and that, therefore, they withheld the payment. Unless the dispute is
resolved and the amount is found due, the contractor is not entitled to H
2 SUPREME COURT REPORTS (1994] SUPP. 6 S.C.R
A the payment of it. The interest in terms of clause 69 of MDSS is
contracted out. When such be the position, then mere reference does
give jurisdiction to the arbitrator to award interest for the period prior
to the reference. [4G & H, 5 A]
A.P. S.R.T.C. v. P. Ramana Reddi, (1989) 1ALT195, Distinguished.
B
1.2. In this case the contractor is not entitled to payment of interest
in terms of clause 69 of MDSS for the period anterior to the reference
for arbitration until the final settlement of the amount due to the
contractor of his account is determined. In this case that dispute was
determined by the arbitrator in his award. Therefore, from the date of
C withholding till the date of award the appellant is not entitled to the
payment of interest. The arbitrator has no jurisdiction to arbitrate that
dispute. The High Court, therefore, rightly negatived the claim for
interest. [SE & F]
Executive Engineer (Irrigation) v. Abhaduta Jena, [1988] 1 SCC 418;
D State of Orissa v. Niranjan Swain, [1989) 4 SCC 269; Secretary, Irrigation
Department v. G.C. Ray, [1992)-1 SCC 508; Distinguished.
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 2262-63 of
1977.
E From the Judgment and Order dated 23.4.75 of the Andhra Pradesh
High Court in Memo of Cross-Objection in C.M.A. No. 191of1973.
B. Kanta Rao for the Appellant.
A.K. Ganguli, T. V.S.N. Chari and Nikhil Nayyar for the Respondent.
F The following Order of the Court was delivered:
. These appeals by special leave arise from the judgment of the Division
Bench of the Andhra Pradesh High Court in Memo of, Corss Objection in
C.M.A. No. 191/75 dated 23.4.75. The appellant had entered into a contract
on 16.3.65 to construct foodgrains godown at Karimnagar. In execution
G thereof, a dispute had arisen whether the appellant had executed the work as
per the contract and is intitled to certain sums of money withheld by the
engineer and also to the interest payable thereon at 12% etc. The dispute
has been referred to the Arbitrator, a retired Chief Engineer, who in his
Award dated 12.4.72 awarded a sum of Rs. 27, 776 with interest at 12% on
H the amounts wrongfully withheld by the Engineer. We are concerned in
D.R. PRASAD v. GOVT. OF A.P. r )3
these appeals only with the entitlement of interest on the amounts withheld A
by the engineer. The Division Bench concluded, while negativing the claim
for interest, thus:
"We are, however, inclined to agree with the first ground
. given by the Court below in negativing the claim for interest.
Under clause 69 of M.D.S.S. which has to be treated as part B
of the contract, it is provided "nor shall the contractor be
entitled to interest upon any guarantee fund or payments in
arrears, nor upon any balance which may, on the final
settlement of his accounts, be found to be due to him." Even
if it is assumed that the recoveries from the bills were
I wrongfully made, such sums would be sums which would be C
found due to the contractors on the final settlement of
accounts."
We are not concerned with the correctness of the views expressed on
other issues as the State did not file appeals. Shri Kanta Rao, the learned D
counsel for the appellant contended that when the appellant had executed
the work within the period, in terms of the contract, and the officials of the
respondent had wrongfully withheld the due payment, on the respective ·
dates, the appellant is entitled to the interest on the amounts wrongfully
withheld. He further contends that clause 69 of the M.D.S.S. is inapplicable
to the facts of this situation. In support thereof, he places reliance on the E
judgment ofa learned single Judge of that Court reportedA.P.S.R.T.C. v. P.
Ramana Reddi, (1989) 1ALT195.
The question, therefore, is whether the appellant is entitled to payment
of interest from the respective dates on which the amounts were withheld
by the concerned engineer and the dispute is arbitrable? F
Clause 69 ofM.D.S.S. reads thus:
"69. Interest on money due to the contractor:-
(a) No omission by the Executive Engineer or the Sub- G
Divisional officer to pay the amount due upon certificates
shall vitiate or make void the contract, nor shall be contractor
be entitled to interest upon any gaurantee found or payments
in arrear, nor upon any balance which may, on the final
setlement of his accounts, be found to be due to him."
H
4 SUPREME COURT REPORTS [1994] SUPP. 6 S.C.R
A A reading of this clause gives an indication that interest on money due
to the contractor was negatived in the following circumstances:
(1) the omission by the Executive Engineer or Sub-Divisional officer to
pay the amount due upon certificates shall not vitiate or make the contract
void:
B
(2) the contractor shall not be entitled to interest upon:
(a) any guarantee found;
(b) payments in arrears; and
c (c) upon any balance which may on final settlement of his account to
be found to be due to him. The question is whether the contractor is entitled
to the payment of interest on the amounts wrongfully withheld from the
respective dates. Clause (c) of the second part of clause 69 of the MDSS
would indicate that there should be a final settlement of the account and
upon its settlement, if it is found to be due and payable to the contractor, on
D such amount also the contractor is not entitled to the payment of interest as
contracted under clause 69 of the MDSS. When such is the position,
whether the contractor is entitled to payment of interest on mere makeing a
claim and reference made to the arbitrator and whether the arbitrator gets
jurisdiction to award interest on the amount due from the respective dates
on which the payments were withheld by the concerned engineer?
E
It is true that the learned single Judge of the A.P. High Court appears to
have considered the question and the construction of clause 69 was put up
is in favour of the contractor as contended for. It is not a correct approach.
The construction put up on clause 69 of MDSS is not correct. However, on
F the facts in that case there does not appear to be any dispute as to the
amount due. Therefore, the learned Judge had proceeded that since the
contract provides for withholding the payment for a suspended period of six
months, if the amount is withheld beyond that period, the contractor would
be entitled to the payment of interest. That is not the factual scenario in this
case. The very dispute is whether the appellant is entitled to the payment of
G the amount pursuant to the contract. The claim of the State appears to be
that the appellant had not constructed the godown in accordance with the
'
specifications and that, therefore, they withheld the payment. Unless the
dispute is resolved and the amount is found due, the contractor is not
entitled to the payment of it. Thereon interest in terms of clause 69 of the
MDSS is contracted out. When such be the position, then mere refere~ce
H
D.R. PRASAD v. GOVT. OF A.P. 5
does give jurisdiction to the arbitrator to award interest to the period prior A
to the reference.
This Court in Executive Engineer (Irrigation) v. Abhaduta Jena,
[ 1988] 1 sec 418, in para 20 held that:
"In the remarnrng cases which arose before the B
commencement of the Interest Act, 1978, the respondents are
not entitled to claim interest either before the commencement
of the proceedings ..... They are nor entitled to claim interest
for the period prior to the commencement of the arbitration
I proceedings for the reason that the Interest Act, 1839 does
not apply to their cases and there is no agreement to pay C
interest or any usage of trade having the force of law or any
other provision of law under which the claimants were
entitled to recover interest."
This ratio was followed by another Bench of this Court in State of
Orissa v. Niranjan Swain, [1989] 4 SCC 269. In Secretary, Irrigation D
Department v. G.C. Roy, [1992] 1 SCC 508, the Constitution Bench was
concerned with the case whether the contractor is entitled to interest
pendente lite. The controversy, therefore, centres round the question
whether the contractor is entitled to the interest pendente lite. The ratio
therein, therefore, has no relevance for the purpose of this case. The ratio in
Jena's case on the above quoted ratio is still good law. Accordingly, we are E
of the view that the contractor is not entitled to payment of interest in terms
of clause 69 of MDSS for the period anterior to the reference for arbitration
until the frnal settlement of the amount due to the contractor of his account
is determined. In this case that dispute was determined by the arbitrator in
his award. Therefore, from the date of withholding till the date of award the
appellant is not entitled to the payment of interest. The arbitrator has no F
jurisdiction to arbitrate that dispute. The Division Bench, therefore, rightly
negatived the claim for interest.
The appeals are accordingly dismissed, but in the circumstances, G
without costs.
A.G. Appeals dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.