Created byFuzzy Cloud

Supreme Court of India

M/S BHAGHEERATHA ENGINEERING LTD.versusSTATE OF KERALA

Citation
2026 INSC 4
Decided
5 January 2026
Disposal
Appeal(s) allowed

Holding

The High Court erred; the arbitral tribunal had jurisdiction over all four disputes and the non‑issuance of a Section 21 notice is not fatal, so the arbitral award is upheld.

Summary

The appellant, Bhagheeratha Engineering Ltd., was awarded four road‑maintenance contracts under the Kerala State Transport Project and, after disputes over payments, referred the matters to an adjudicator under the contract’s General Conditions. The adjudicator decided in favour of the appellant on two disputes and against it on two others; the respondent (State of Kerala) then invoked the arbitration clause (Clause 25.3) claiming only dispute 1, while the appellant sought to arbitrate all four disputes. The High Court held that the arbitral tribunal was limited to dispute 1 and that the appellant’s failure to serve a Section 21 notice for disputes 2‑4 was fatal, setting aside the award. On appeal, the Supreme Court held that the respondent’s conduct precluded it from limiting the arbitration, that the arbitration clause was wide‑ranging, and that a Section 21 notice is merely procedural and not a jurisdictional prerequisite. Consequently, the Court restored the arbitral award in its entirety. The appeal was allowed.

Issues considered

  • Whether the arbitral tribunal was appointed only to adjudicate dispute 1 or could decide all four disputes under the contract’s arbitration clause.
  • Whether the appellant’s failure to issue a notice under Section 21 of the Arbitration and Conciliation Act, 1996, for disputes 2‑4 rendered its claim before the arbitrator fatal.
  • Whether the arbitral tribunal exceeded its jurisdiction by deciding matters beyond the dispute referred to it.
  • Whether the wording of Clause 25.3 of the contract makes the arbitration agreement comprehensive enough to cover all disputes arising out of the agreement.

Legislation cited

Headnote

Issue for Consideration Whether the High Court by the impugned order was justified in holding that the Arbitral Tribunal was appointed at the request of the State to adjudicate dispute No.1 only; was the non-issuance of a notice u/s.21, Arbitration and Conciliation Act, 1996 by the appellant its claim before the Arbitrator. Headnotes† Arbitration and Conciliation Act, 1996 – Four packages of Road Maintenance Contract were awarded to the appellant – Appellant quantified the amounts due and submitted the same for decision by the Executive Engineer – As per the

Subjects

Arbitral Tribunal did not exceed its jurisdiction in deciding the entire disputeEntire dispute could be raised before ArbitratorEntire disputeArbitration Clause widely wordedSection 21, Arbitration and Conciliation ActNotice under Section 21, Arbitration and Conciliation ActNo mandatory prerequisite for issuance of Section 21 notice prior to the commencement of ArbitrationParty at fault cannot take advantage of the sameRoad Maintenance ContractKerala State Transport Project (KSTP)Development of roads in KeralaCollaboration with World BankGeneral Conditions of Contract (GCC)Pending payments

Judgment

                   [2026] 1 S.C.R. 303 : 2026 INSC 4

                 M/s Bhagheeratha Engineering Ltd.
                                 v.
                          State of Kerala
                        (Civil Appeal No. 39 of 2026)
                               05 January 2026
           [J.B. Pardiwala and K.V. Vishwanathan,* JJ.]


                           Issue for Consideration
       Whether the High Court by the impugned order was justified in
       holding that the Arbitral Tribunal was appointed at the request of
       the State to adjudicate dispute No.1 only; was the non-issuance
       of a notice u/s.21, Arbitration and Conciliation Act, 1996 by the
       appellant fatal for it to pursue its claim before the Arbitrator.

                                  Headnotes†
       Arbitration and Conciliation Act, 1996 – Four packages of
       Road Maintenance Contract were awarded to the appellant –
       Appellant quantified the amounts due and submitted the same
       for decision by the Executive Engineer – As per the appellant,
       since the Executive Engineer/Superintending Engineer failed
       to take any decision, the appellant approached the Adjudicator
       under Clause 25.1 of the General Conditions of Contract, who
       ruled in favour of the appellant on dispute Nos.1 and 3 and
       against it on dispute Nos.2 and 4 – Respondent issued letter
       referring to arbitration Clause 25.3 expressing intention to
       refer only dispute No.1 to arbitration – Eventually, co-arbitrator
       nominated – By its award, the Arbitral tribunal answered all
       four disputes in favour of the appellant – Award challenged
       by the Respondent u/s.34 – Petition allowed by District Judge,
       award was set aside and the decision of the Adjudicator
       restored – Order upheld by High Court – Interference with:
       Held: High Court erred in setting aside the award on the basis
       that the appointment of the Tribunal was only to adjudicate dispute
       No.1 – On facts, conduct of the respondent precluded it from
       relying on the mandate of clause 24, 24.1 and 25 to contend
       that the appellant was foreclosed from raising the entire dispute


* Author
304                                                               [2026] 1 S.C.R.

                            Supreme Court Reports


       before the Arbitrator – The party at fault cannot be permitted to
       take advantage of the same – High Court also erred in holding that
       the non-issuance of notice u/s.21, A&C Act by the appellant with
       regard to dispute no.2 to 4 was fatal for it to pursue its claim before
       the arbitrator – There is no mandatory prerequisite for issuance
       of a s.21 notice prior to the commencement of Arbitration – Also,
       High Court erred in holding that the Arbitral Tribunal exceeded its
       jurisdiction in deciding the entire dispute – Arbitration Clause 25.3
       is widely worded and any dispute or difference arising between the
       parties relating to any matter arising out of or concerned with the
       agreement are to be settled in accordance with the A&C Act by the
       Arbitral Tribunal – Judgment of High Court set aside – Award of
       the arbitrator upheld in its entirety – Contract Act, 1872 – s.28(b).
       [Paras 14-16, 18, 22]

       Arbitration and Conciliation Act, 1996 – s. 21 – Object of – Was
       the non-issuance of a notice u/s.21 by the appellant fatal for
       it to pursue its claim before the Arbitrator:
       Held: No – The object of s.21 is only for the purpose of
       commencement of arbitral proceedings – s.21 is concerned only
       with determining the commencement of the dispute for the purpose
       of reckoning limitation – There is no mandatory prerequisite for
       issuance of a s.21 notice prior to the commencement of Arbitration
       – Issuance of a s.21 notice may come to the aid of parties and
       the arbitrator in determining the limitation for the claim – Failure
       to issue a s.21 notice would not be fatal to a party in Arbitration
       if the claim is otherwise valid and the disputes arbitrable – High
       Court erred in holding that the non-issuance of notice u/s.21 by
       the appellant with regard to dispute no.2 to 4 was fatal for it to
       pursue its claim before the arbitrator. [Paras 14, 16]

       Arbitration and Conciliation Act, 1996 – s.2(9), 23:
       Held: Once the Arbitral Tribunal is constituted claims, defence
       and, counter claims are filed – Party which normally files the claim
       first is, for convenience, referred to as the ‘claimant’ and the party
       which responds is called the ‘respondent’ – The said respondent
       is also along with the defence statement entitled to file its counter
       claim – Hence, to contend that the appellant cannot be referred
       to as a claimant because no notice u/s.21 has been issued is
       completely untenable. [Para 21]
[2026] 1 S.C.R.                                                                305

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


                               Case Law Cited
     State of Goa v. Praveen Enterprises [2011] 10 SCR 1026 : (2012)
     12 SCC 581; M.K. Shah Engineers & Contractors v. State of M.P.
     [1999] 1 SCR 419 : (1999) 2 SCC 594; ASF Buildtech Private
     Limited v. Shapoorji Pallonji & Company Private Limited (2025)
     9 SCC 76; Adavya Projects Private Limited v. Vishal Structurals
     Private Limited and Others [2025] 5 SCR 243 : (2025) 9 SCC 686;
     Indian Oil Corporation Ltd. v. Amritsar Gas Service and Others
     [1991] 1 SCC 533 : (1991) 1 SCC 533 – relied on.
     Steel Co. Ltd. v. Tiwari Road Lines [2007] 6 SCR 156 : (2007) 5
     SCC 703; MSK Projects India (JV) Limited v. State of Rajasthan and
     Another [2011] 9 SCR 402 : (2011) 10 SCC 573 – held inapplicable.

                                  List of Acts
     Arbitration and Conciliation Act, 1996; Contract Act, 1872; DIAC
     Arbitration Proceedings Rules, 2018.

                              List of Keywords
     Arbitral Tribunal did not exceed its jurisdiction in deciding the entire
     dispute; Entire dispute could be raised before Arbitrator; Entire
     dispute; Arbitration Clause widely worded; Section 21, Arbitration
     and Conciliation Act; Notice under Section 21, Arbitration and
     Conciliation Act; No mandatory prerequisite for issuance of Section
     21, Arbitration and Conciliation Act notice prior to the commencement
     of Arbitration; Party at fault cannot take advantage of the same;
     Road Maintenance Contract; Kerala State Transport Project (KSTP);
     Development of roads in Kerala; Collaboration with World Bank;
     General Conditions of Contract (GCC); Pending payments.

                             Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 39 of 2026
     From the Judgment and Order dated 07.01.2025 of the High Court
     of Kerala at Ernakulam in ARBA No. 56 of 2012

                          Appearances for Parties
     Advs. for the Appellant(s):
     Rajiv Shakdher, Sr. Adv., George Thomas, Dhiraj Abraham Philip,
     Sunny George, Febin Mathew Varghese, Ms. Lija Merin John,
     Ms. Soyarchon Khangrah.
306                                                           [2026] 1 S.C.R.

                           Supreme Court Reports


       Advs. for the Respondent(s):
       Naveen R Nath, Sr. Adv., Nishe Rajen Shonker, Mrs. Anu K Joy,
       Alim Anvar, Mrs. Devika A.l., Santhosh K, Ms. Disha Gupta, Aditya
       Nath, Sai Vaishnav.

                  Judgment / Order of the Supreme Court

                                  Judgment

       K.V. Viswanathan, J.

1.     Leave granted.
2.     The present appeal calls in question the correctness of the judgment
       dated 07.01.2025 passed by the Division Bench of the High Court of
       Kerala at Ernakulam in Arbitration Appeal No. 56/2012. By the said
       judgment, the Division Bench of the High Court upheld the order of
       the District Judge, Thiruvananthapuram, dated 22.06.2010 in O.P.
       (Arb.) No.238 of 2006, al beit, on different grounds. The District Judge
       had set aside the award of the Arbitrator as being beyond the scope
       of reference and against the terms and conditions of the contract
       and restored the decision of the Adjudicator. The Adjudicator had, by
       his order of 14.08.2004, decided four disputes and held in favour of
       the appellant insofar as dispute Nos. 1 and 3 were concerned and
       against the appellant in relation to dispute Nos. 2 and 4.
3.     The principal reason assigned by the High Court was that the Arbitral
       Tribunal was appointed at the request of the respondent-State to
       adjudicate on dispute no. (1) alone and the appellant never intended
       to raise any dispute regarding dispute nos. (2) to (4) by issuing a
       separate notice under Section 21 of the Arbitration and Conciliation
       Act, 1996 [for short “the A&C Act”]. The reasoning of the High Court
       is set out hereinbelow:-
            25. We must bear in our mind that the arbitral tribunal
            was appointed at the request of the State to adjudicate
            on dispute no. (1) alone. The appellant never intended
            to raise any dispute regarding point Nos. (2) to (4) by
            issuing a separate notice under Section 21 of the Act. The
            assumption that where one-party files an application and
            gets an arbitrator appointed, the other party can raise all
            such disputes under the contract before the arbitrator is
[2026] 1 S.C.R.                                                             307

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


           baseless, especially when the law governing the arbitration
           specifically provides that the arbitrator can decide only such
           dispute referred before him and not otherwise. To hold
           otherwise will certainly do violence to the statute. Hence,
           we find that the arbitral tribunal had clearly exceeded the
           jurisdiction in deciding the entire disputes. Perhaps the
           appellant was under a mistaken impression with regard to
           its right to have the entire disputes opened for arbitration.
           We must also note that the State was never put on notice
           regarding the intention of the appellant to go for arbitration.
           Even assuming that the contention of the appellant that the
           State had unequivocally agreed to arbitrate on the entire
           disputes, the tribunal ought to have framed an issue or
           given its finding on the jurisdiction as envisaged under
           Section 16. In the absence of any finding in this regard by
           the tribunal, we are afraid that the award in question clearly
           crossed the contours of the law and thus rendering itself to
           be inexecutable and falling within the mischief of Section
           34 of the Arbitration and Reconciliation [sic] Act, 1996.”
4.   It is the correctness of this decision, which the appellant has
     questioned before us in this appeal by way of special leave.
5.   The facts lie in a very narrow compass:-
     5.1 Four packages of Road Maintenance Contract were awarded
         to the appellant as part of the Kerala State Transport Project
         (KSTP) for development of roads in Kerala in collaboration with
         the World Bank. The work was awarded through competitive
         bidding.
     5.2 The four projects awarded to the appellant were the following:-
                “1. RMC 01” Thiruvananthapuram – Kottarakkara
                Road (5.70 to 25 KM)
                2. RMC 03: Thodupuzha – Kalur – Ounukal Road
                (0.00 to 20 KM)
                3. RMC 08: Kozikode – Mavoor Road (0.00 to 10.50
                KM)
                4. RMC 12: Quilandy – Thamarassery Road (0.00
                to 29.30 KM)”
308                                                           [2026] 1 S.C.R.

                          Supreme Court Reports


       5.3 Under the General Conditions of Contract [for short “GCC”], the
           following mechanism was provided for adjudication of disputes:-
                 “24. Disputes
                 24.1 If the Contractor believes that a decision taken
                 by the Engineer was either outside the authority given
                 to the Engineer by the Contract or that the decision
                 was wrongly taken, the decision shall be referred to
                 the Adjudicator within 14 days of the notification of
                 the Engineer’s decision.
                 25. Procedure for Disputes
                 25.1 The Adjudicator shall give a decision in writing
                 within 28 days of receipt of a notification of a dispute.
                 25.2 The Adjudicator shall be paid daily at the
                 rate specified in the Contract Data together with
                 reimbursable expenses of the types specified in the
                 Contract Data and the cost shall be divided equally
                 between the Employer and the Contractor, whatever
                 decision is reached by the Adjudicator. Either party
                 may refer a decision of the Adjudicator to an Arbitrator
                 within 28 days of the Adjudicator’s written decision.
                 If neither party refers the dispute to arbitration within
                 the above 28 days, the Adjudicator’s decision will be
                 final and binding.
                 25.3 The arbitration shall be conducted in accordance
                 with the arbitration procedure stated in the Special
                 Conditions of Contract.”
                 Special Conditions of Contract
                 “4. ARBITRATION (GCC Clause 25.3)
                 The procedure for arbitration will be as follows:
                 25.3. (a) In case of Dispute or difference arising
                 between the Employer and a domestic contractor
                 relating to any matter arising out of or connected
                 with this agreement, such disputes or difference
                 shall be settled in accordance with the Arbitration
                 and Conciliation Act, 1996. The arbitral tribunal shall
[2026] 1 S.C.R.                                                         309

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


                consist of 3 Arbitrators one each to be appointed by
                the Employer and the contractor. The third Arbitrator
                shall be chosen by the two arbitrators so appointed
                by the Parties and shall act as presiding arbitrator.
                In case of failure of the two arbitrators appointed by
                the parties to reach upon a consensus within a period
                of 30 days from the appointment of the arbitrator
                appointed subsequently, the Presiding arbitrator
                shall be appointed by the Chairman of Executive
                Committee, Indian Roads Congress, New Delhi.”
     5.4 Clause 24.1 states that if the contractor believes that a decision
         taken by the Engineer was either outside the authority given to
         the Engineer by the contract or that the decision was wrongly
         taken, the decision shall be referred to the Adjudicator within
         14 days of the notification of the Engineer’s decision. Hence,
         it is clear that what is contemplated is that disputes may be
         referred to the Adjudicator, where the issue involves decisions
         beyond the authority of the Engineer, or where decision of the
         Engineer is erroneous.
     5.5 Further, under Clause 25.1, the Adjudicator was to give a
         decision within 28 days of the receipt of the notification of
         a dispute and under Clause 25.2, either party may refer the
         decision of the Adjudicator to an Arbitrator within 28 days of
         the Adjudicator’s written decision and if neither party refers
         the dispute to the arbitration within 28 days, the Adjudicator’s
         decision will be final and binding.
     5.6 In the present case, the appellant, by letters of 02.03.2004
         and 24.03.2004 quantified the amounts due and submitted
         the same for decision by the Executive Engineer. According
         to the appellant, since the Executive Engineer/Superintending
         Engineer failed to take any decision, the appellant, by a letter
         dated 15.04.2004, approached the Adjudicator under Clause
         25.1 of the GCC for decision on pending payments classifying
         the disputes as dispute Nos.1 to 4 under the following heads:-
                “The disputes before the Adjudicator were:
                1.   Value of work to be considered for calculating
                     the price adjustment for bitumen and POL.
310                                                            [2026] 1 S.C.R.

                           Supreme Court Reports


                  2.   Decision for releasing the escalation during the
                       extended periods.
                  3.   Price of bitumen to be considered for calculation
                       of price adjustment of the bitumen.
                  4.   Release of interest payable at 12% per annum
                       for the delay in releasing the eligible payments
                       beyond 42 hours from the date of submission
                       of the monthly statement of the value of work
                       done during the period as per Clause 42.2 and
                       43.1 of General Conditions of Contract.”
       5.7 The Adjudicator, by his decision of 14.08.2004, ruled in favour
           of the appellant on dispute Nos.1 and 3 and ruled against the
           appellant on dispute Nos. 2 and 4.
       5.8 Notwithstanding the decision of the Adjudicator and the
           submission of the final bill by the appellant, the respondent did
           not settle the bill on the ground that the finding of the Adjudicator
           qua dispute No.1 was unacceptable to the respondent.
       5.9 On 01.10.2004, the respondent addressed the following letter
           to the appellant.
                  “Sub: R MC-Contractors—RMC-01,03,08,12—
                         Adjudication-reg.
                  Ref: Award of Adjudicator dated 14.8.2004
                  Further to the letter cited under reference above, we
                  write to inform you that the award of the Adjudication
                  for Dispute No. 1 is not acceptable and we intent to
                  refer the matter for an arbitration. We have appointed
                  Mr. Subash Chandra Bose, as our arbitrator.
                  Therefore, you may propose your arbitrator as per
                  clause 25.3 of General Conditions of contract and
                  intimate for further action.”
       5.10 It will be seen that the reference was under Clause 25.3
            which is the arbitration clause. The letter was issued by the
            respondent and, according to the respondent, it was confined
            to dispute No.1, namely, “value of work to be considered for
            calculating the price adjustment for bitumen and POL.
[2026] 1 S.C.R.                                                          311

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


     5.11 In response to the letter dated 01.10.2004, the appellant sent
          a letter on 14.10.2004 to the respondent. The appellant stated
          that the adjudicator’s decision was issued on 14.08.2004 and
          the time limit for reference to arbitration was till 11.09.2004, (on
          the expiry of 28 days) and as such the letter dated 01.10.2004
          was beyond the stipulated time. The appellant stated that
          the decision of the adjudicator has become final and binding
          upon both the parties. The stand of the appellant was that,
          in view of the same, the Arbitral Tribunal has no jurisdiction
          to enter into the reference. The appellnt also stated that they
          have not received any payment and that compound interest
          would be charged.
     5.12 The respondent addressed a letter dated 30.10.2004 to the
          appellant in response to the appellant’s letter dated 14.10.2004.
          The respondent stated that by their letter dated 01.10.2004,
          they had conveyed their intention to refer dispute No.1 to the
          arbitrator. They further added that they disagreed with the
          “recommendations of the adjudicator”. It was further averred
          that under Clause 25.2 of the GCC the issue of delay in
          referring the matter to arbitration can also be referred and
          the appellant can take up the issue before the arbitrator. The
          crucial contents of the letter reads as follows:-
                “…… Moreover as per clause 24.1 of the agreement
                within 14 days you have to refer to the adjudicator
                any decision not acceptable to you. Whereas
                all the disputes referred are after the stipulated
                time for referring the decision of Engineer to
                Adjudicator. Hence your argument [sic] with
                regard to dates will cut at the root of petition
                considered by the adjudicator.
                Hence you are here by called upon to forward the
                name of the Co-arbitrator to constitute the tribunal.
                You are contractually bound to forward the name of
                the Co-arbitrator and question regarding dates and
                whether decision is binding on KSTP can be referred
                to the arbitrator.
                As stated earlier your claims before the adjudicator
                are delayed for several months and refused to
312                                                         [2026] 1 S.C.R.

                          Supreme Court Reports


                 nominate the name of co-arbitrator will be viewed
                 were serious and we hope you can understand
                 the implications of disobedience of request of
                 the employer. Moreover the employer is entitled
                 proceed further to set aside the recommendation of
                 adjudicator in accordance with agreement. Hence
                 you are required to forward the name of co-arbitrator
                 to our office and to Mr. Subash Chandra Bose to
                 proceed further. It is true that if the decision of
                 the Adjudicator is not acceptable to either party,
                 may refer within 28 days to the Arbitrator. But
                 there is no existing Arbitrator. This body has to
                 be constituted and then only refer the matter to
                 the Arbitrator. We have taken action to constitute
                 the Arbitration Panel.
                 Since this is a matter of dispute we are not in a
                 position to release the payment. Which shall be
                 subject to Arbitrations decision.”
                                               (Emphasis supplied)

       5.13 The respondent also stated that any refusal to nominate the
            co-arbitrator would be viewed seriously and hoped that the
            appellant will understand the implications of disobedience
            of request of the employer. It was also stated that since
            it is a matter of dispute, they were not in a position to
            release payment which shall be subject to the decision in
            arbitration.
       5.14 In response to the letter dated 30.10.2004 of the respondent,
            the appellant wrote to the respondent on 29.11.2004. After
            disagreeing with the interpretation of the respondent on Clause
            25.2, the appellant agreed to nominate the co-arbitrator. The
            letter further stated as follows:-
                 “We reiterate that the decision of the Adjudicator’s
                 decision dated 14.08.2004 is final and binding on
                 both the parties as per clause 25,2 of the GCC. Since
                 your grievance against the decision of adjudicator and
                 no notice to go for arbitration was given within the
[2026] 1 S.C.R.                                                         313

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


                stipulated period of GGC 25.2, the said decision is
                final and binding upon KSTP. Therefore, please take
                notice that we reserve the dispute that exists as on
                date for an adjudication by the Arbitral Tribunal is
                confined to the following.
                Whether the parties have agreed under the contract
                to accept the decision of the adjudicator as final
                and binding on both the parties if notice to refer the
                decision to arbitration is not given within 28 days of
                the decision of the adjudicator?
                If it is so agreed, whether the decision given by the
                adjudicator on 14.08.2004 is final and binding on both
                the parties as per clause 25.2 of the GCC?
                Since the amount payable as per the decision of
                the adjudicator is delayed, whether the contractor is
                entitled for monthly compound interest quarterly on
                the principle sum so adjudicated as demanded by
                the contractor vide letter dated 14-10-04? If so, what
                is the reasonable rate of interest payable?
                Without prejudice to the above, we would like
                record herein that if the Arbitral Tribunal ultimately
                decides that the adjudicator’s decision is not final
                and binding and can be reopened in arbitration,
                we would be raising the following issues for
                reference to the Arbitral Tribunal by way of counter
                claim.
                Whether the reason for delay in execution of work
                and the resultant extension of time of completion
                of the work is attributable to the contractor or to
                KSTP?
                If so, whether the contractor is entitled to
                escalation during the approved extended period
                of contract?
                Whether the liquidated damages imposed on the
                contractor during the extended period of contract
                is sustainable?
314                                                            [2026] 1 S.C.R.

                           Supreme Court Reports


                  Whether the contractor is eligible for interest
                  on all delayed payments beyond 42 days after
                  submission of the bill to the Engineer?
                  We have already submitted the final bill for all the
                  above projects and the payment is still pending
                  for payment. Payment for RMC 8 & 12 are due for
                  payment since 08-05-04 and 10.01.04 respectively.
                  We would request you to kindly release the
                  payment against the work done for which there is
                  no dispute for the item rates at an early date so
                  that accumulation of interest charges for the late
                  payment can be avoided.”
                                                  (Emphasis supplied)

       5.15 On 11.01.2005, the Arbitral Tribunal was constituted. Initially,
            the appellant did file the application to consider the Adjudicator’s
            decision as final and binding which the respondent opposed.
            However, the appellant did not press the application and agreed
            to file its claim before the Arbitrator. The respondent filed an
            application to treat the entire decision of the Adjudicator as
            null and void on the ground that it was contrary to Clause 24.1
            of the GCC. The respondent also objected to the appellant
            being allowed to file the claim petition with regard to all the
            issues which, according to the respondent, led to enlargement
            of the jurisdiction.
       5.16 Respondent in the statement filed on 09.03.2005 sought a
            declaration that the decision of the adjudicator be declared
            null and void and contended that the appellant’s reference to
            the adjudicator itself was out of time and that the acceptance
            of the dispute by the adjudicator was not as per Clause 24.1.
            The relevant para in the statement is as follows:-
                  “If the contractor had any protest or dispute in
                  calculating the ‘R’ value and price of Bitumen.
                  The contractor should have referred the matter
                  to the Adjudicator within 14 days of notification.
                  The notification is the date of payment as per
                  clause 24.1.
[2026] 1 S.C.R.                                                                    315

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


                The last date for referring the matter to the Adjudicator
                shall be as follows:

                    Contract         Date of           To be            Date of   Total
                                    payment          reported          report by delays
                                   (Decision)         to the          contractor
                                                    Adjudicator
                    RMC-01     -     6.9.03     -    20.09.03     -    15.4.04    209
                                                                                  days
                    RMC-03     -    15.3.03     -     29.3.03     -    15.4.04    383
                                                                                  days
                    RMC-08     -     8.7.03     -     22.7.03     -    15.4.04    267
                                                                                  days
                    RMC-12     -     5.6.03     -     19.6.03     -    15.4.04    299
                                                                                  days


                From the above it was noticed that the matter
                on dispute was referred to the Adjudicator was
                delayed. Hence the acceptance of dispute by
                the Adjudicator was not as per clause 24.1 and
                the Recommendation of the Adjudicator to be
                set aside.
                As explained in the para 7.2. Our main contention
                is that the contractor is the defaulter, who refers the
                decision of the employer in calculation of ‘R’ value
                and the Bitumen price for price escalation as a dispute
                after a huge delay as tabulated in para 7.2. The
                adjudicator not considered the delay made by the
                contractor in referring the dispute to the Adjudication.
                Since the contractors action for referring the
                disputes to the Adjudicator after expiring the time
                frame as per contract clause 24.1. The acceptance
                of dispute and award by the Adjudicators is
                considered to be null and void.”
                                                          (Emphasis supplied)

     5.17 By its ruling of 16.12.2005 under Section 16 of the A&C Act,
          the Arbitral Tribunal held that the claims of the appellant still
          remained unsettled. It further held that the arbitration clause
316                                                         [2026] 1 S.C.R.

                          Supreme Court Reports


             was comprehensive enough to include any matter arising
             out of or connected with the Agreement. It further held that
             the prayer of the respondent to declare the Adjudicator’s
             decision as null and void indicated their intention to reopen
             the four disputes originally brought for consideration before
             the Adjudicator. The Tribunal, however, disallowed the claims
             of the appellant insofar as they were beyond the claims raised
             before the Adjudicator. Pursuant to the decision under Section
             16, the appellant revised its claims and confined the claims
             to four issues permitted by the order of 16.12.2005. In view
             of this, we are not called upon to decide whether the Arbitral
             Tribunal was justified in confining the appellant to the four
             issues raised before the Adjudicator.
       5.18 By its award of 29.06.2006, the Arbitral Tribunal answered
            all four issues in favour of the appellant. In all, the appellant
            was awarded a total sum of Rs.1,99,90,777/- along with post
            award interest @ 18% p.a. Inter alia, the award of the arbitrator
            recorded that:-
             A)    several claims were first raised by the Appellant and they
                   still remained as unsettled claims;
             B)    Arbitration agreement is comprehensive enough to
                   cover any dispute arising out of or in connection with
                   the agreement;
             C)    The prayer of the respondent to declare the decision
                   of the adjudicator null and void virtually indicated their
                   intention to open the 4 disputes that are brought before
                   the Arbitral Tribunal;
             D)    Both parties have rejected the decision of the Adjudicator
                   which has now become infructuous.
       5.19 The respondent challenged the Award under Section 34 before
            the District Judge, Thiruvananthapuram in O.P.(Arbitration) No.
            238 of 2006. The respondent also challenged the decision
            under Section 16 dated 16.10.2005 in its Section 34 petition.
            By judgment dated 26.06.2010, the District Judge allowed
            respondent’s Section 34 petition and set aside the award
            and restored the decision of the Adjudicator on the following
            two grounds:-
[2026] 1 S.C.R.                                                        317

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


            (i)     there was no provision in the contract for extending
                    the time for referring the issue beyond the period of 28
                    days; and
            (ii)    hence there cannot be any question of there being
                    any consensus between the parties for referring all the
                    disputes.
     5.20 In spite of so holding, the District Judge, for reasons best
          known to him, restored the recommendations of the Adjudicator.
          Aggrieved, the appellant filed an appeal under Section 37 of the
          A&C Act. The Division Bench, by the order impugned, clearly
          found that imposition of 28 days time-limit in Clause 25.2 was
          contrary to Section 28(b) of the Contract Act. However, on the
          ground that the appellant never sought reference of the dispute
          by issuing any notice under Section 21 of the A&C Act and
          only the respondent had issued such a notice on one issue,
          it found the award to be invalid. However, the order restoring
          the decision of the Adjudicator was not disturbed.
6.   We have heard Mr. Rajiv Shakdher, learned Senior Advocate, for
     the appellant and Mr. Naveen R. Nath, learned Senior Advocate for
     the respondent. We have gone through the records, including the
     written submissions filed by the respective parties.

     SUBMISSIONS OF THE APPELLANT: -
7.   The learned senior counsel for the appellant submits that the
     arbitration clause is exhaustive and covers any dispute or difference
     arising between the parties relating to any matter arising out of or
     connected with the agreement. According to the learned senior
     counsel, the agreement was not limited to the reference of disputes
     decided by the adjudicator. It is further contended by the learned
     senior counsel that the Division Bench has set aside the award on
     a ground not taken by the respondent before the Arbitral Tribunal
     or in Court. According to the learned senior counsel, such a course
     of action was beyond the scope of Section 37 appeal.
8.   Learned senior counsel further contends that there is a clear waiver
     under Section 4 of the A&C Act. Learned senior counsel for the
     appellant contends that notice is not envisaged at the stage of
     invocation under Clause 25.3 of the GCC and Clause 4 of the Special
     Conditions of Contract. Learned senior counsel contends that Section
318                                                            [2026] 1 S.C.R.

                           Supreme Court Reports


       21 of the A&C Act opens with the phrase “Unless otherwise agreed by
       the parties”, and contends that, in the present case, it was otherwise
       agreed in the contract that if a party wishes to settle the dispute, it
       may first notify claims to the other party and refer it for settlement
       with the engineer and, thereafter, refer it to the adjudicator. According
       to the learned senior counsel, the dispute has already been referred
       through two stages before referring it to arbitration.
9.     Learned senior counsel further contends that the purpose of Section
       21 was to primarily determine whether the claims are within limitation,
       and no award can be set aside for want of a Section 21 notice. In
       any event, learned senior counsel contends that the letter dated
       29.11.2004 issued by the appellant should be construed as the
       Section 21 notice. Assuming everything against the appellant, the
       learned senior counsel contends, that there is no requirement of
       issuance of notice under Section 21 by both parties. According to the
       learned senior counsel, if one party take steps to constitute an Arbitral
       Tribunal, the other party can raise all claims and counterclaims. Any
       other interpretation would result in multiple arbitration and conflicting
       awards. In conclusion, it was submitted that the Arbitral Tribunal is
       a final adjudicator regarding the arbitral procedure. So contending,
       it was prayed that the impugned order deserves to be set aside and
       the award of the arbitrator be upheld in entirety.

       SUBMISSIONS OF THE RESPONDENT: -
10. Learned senior counsel for the respondent contends that the dispute
    resolution mechanism comprises escalatory measures which would
    mean that the dispute needs to be first resolved by the engineer
    and, in case the decision was not acceptable, it was to be referred
    to the adjudicator within 14 days. According to the learned senior
    counsel, the adjudicator’s decision is required to be in writing within
    28 days of the receipt of the notification of dispute. Further what is
    referred to the arbitrator is the adjudicator’s decision and not the
    original dispute before the engineer.
11. Learned senior counsel submits that this is the agreed procedure for
    the appointment of the arbitrators as contemplated under Section
    11(2); that these escalatory measures have statutory significance
    since they are intended to narrow the dispute referable to the Arbitral
    Tribunal. In view of that, it is submitted that for a party to invoke
[2026] 1 S.C.R.                                                          319

           M/s Bhagheeratha Engineering Ltd. v. State of Kerala


     arbitration it must clearly and categorically be signified, by issuance
     of notice that it disputes the adjudicator’s decisions either in entirety
     or on specified issues.
12. Learned senior counsel submits that the procedure for appointment of
    an arbitrator must be strictly complied and even under Section 28(3) of
    the A&C Act, the Arbitral Tribunal is required to take into account the
    terms of the contract. Learned senior counsel submits that issuance
    of notice under Section 21 is a mandatory requirement and both the
    parties to an arbitration agreement have the right to be informed of
    the arbitral dispute before the constitution of the Arbitral Tribunal.
    According to the learned senior counsel, the appellant could never
    be the claimant and the expression claimant can only be attributed
    to that party who initiates the arbitration proceedings by issuance of
    notice under Section 21. Learned senior counsel disputes the fact
    that the letter dated 14.10.2004 or 29.11.2004 of the appellant could
    be treated as Section 21 notice. Learned senior counsel submits that
    the case of the respondent was covered by para 41(c) of the decision
    of this Court in State of Goa v. Praveen Enterprises1.

     QUESTIONS FOR CONSIDERATION: -
13. In the above background, the questions that arises for consideration
    are (a) whether the High Court by the impugned order was justified
    in holding that the Arbitral Tribunal was appointed at the request of
    the State to adjudicate dispute No. 1 only? (b) Was the non-issuance
    of a notice under Section 21 of the A&C Act by the appellant fatal
    for it to pursue its claim before the Arbitrator?

     ANALYSIS AND REASONING: -
14. In our opinion, the High Court totally erred in setting aside the
    award on the basis that the appointment of the Tribunal was only to
    adjudicate dispute No.1. The High Court also erred in holding that
    the non-issuance of notice under Section 21 of the A&C Act by the
    appellant with regard to dispute no. 2 to 4 was fatal for it to pursue
    its claim before the arbitrator. The High Court erred in holding that
    the Arbitral Tribunal exceeded its jurisdiction in deciding the entire
    dispute. We say so for the following reasons.



1   (2012) 12 SCC 581
320                                                           [2026] 1 S.C.R.

                           Supreme Court Reports


       CONDUCT OF THE RESPONDENT: -
15. Firstly, the sequence of events clearly demonstrates that the present
    was a case where conduct of the respondent clearly precluded it
    from relying on the mandate of clause 24, 24.1 and 25 to contend
    that the appellant was foreclosed from raising the entire dispute
    before the Arbitrator. This is because: -
       a)   Clause 24.1 stipulated a time limit of 14 days to refer the
            decision of the Engineer to the adjudicator. While the appellant
            contends that the Engineer never decided on any issue after
            the appellant quantified the amounts and submitted the same
            on 02.03.2024 and 24.03.2024, the respondent has a different
            story to tell. According to the respondent, the payment dates
            of 06.09.2023, 15.03.2003, 08.07.2003 and 05.06.2003 for
            the four different contracts respectively, itself were the dates
            of the decision of the Engineer and the appellant delayed the
            reference to the adjudicator by 209 days, 383 days, 267 days
            and 299 days respectively. Even the adjudicator proceeded on
            the basis that the date of payments was the date of decision
            of the Engineer. Before the adjudicator no objection was taken
            by the respondent about the reference to the adjudicator itself
            being barred by time and beyond the scope of clause 24.1.
            The adjudicator went ahead and decided dispute Nos.1 and 3
            in favour of the appellant and dispute Nos.2 and 4 in favour of
            the respondent. The Adjudicator gave his decision on 14 August
            2004. Under Clause 25.1, the adjudicator was approached on
            15.04.2004 and going by clause 25.1 the adjudicator ought to
            have given his decision within 28 days from 15.04.2004, that is
            on or before 13.05.2004. This is the second instance of parties
            including adjudicator not following the drill of clause 25.1, in its
            true letter and spirit.
       b)   Under Clause 25.2, either party can refer the decision of the
            adjudicator to the Arbitrator within 28 days of the adjudicator’s
            written decision and if neither party refers the dispute to the
            adjudicator within 28 days, the adjudicator’s decision will be
            final and binding. In this case, it was on 01.10.2004 i.e. after
            the expiry of 56 days that the respondent issued the letter which
            they claimed was the reference of the decision in dispute No.1
            of the adjudicator. The High Court in the impugned order has
[2026] 1 S.C.R.                                                           321

           M/s Bhagheeratha Engineering Ltd. v. State of Kerala


            in any event found that the 28 days time limit offends Section
            28(b) of the Contract Act. Further, when the appellant wrote back
            objecting to the breach of time limit of 28 days, the respondent
            wrote back saying that the issue of delay in referring can itself
            be referred to the Arbitrator and that they disagreed with the
            recommendation of the adjudicator. This itself indicates that
            notwithstanding clause 25.2 specifying that on the expiry of
            28 days the decision of the adjudicator was final and binding,
            the respondent never treated the decision of the adjudicator
            as final and binding.
     c)     Further, the appellant had not received any payments under
            any of the heads and the respondent asserted that since the
            matter is in dispute, they were not in a position to release the
            payment which, according to them, is subject to the decision
            of the Arbitrator.
     d)     The appellant also wrote to the respondent stating that they
            disagreed with the interpretation of the respondent of clause
            24.2 and that they will be raising all issues before the Arbitrator
            to which there was no response from the respondent.
     e)     To make the matters worse for the respondent before the Arbitral
            Tribunal they filed an application to treat the entire decision of
            the adjudicator as null and void on the ground that clause 24.1
            had been violated.
     f)     The Arbitral Tribunal adjudicating on the Section 16 objection
            of the respondent under Section 16 of A&C rightly held that
            the claims of the appellant remained unsettled and further that
            the arbitration clause was comprehensive enough to include
            any matter arising out of or connected with the agreement.
            The Tribunal further held that the prayer of the respondent to
            declare the adjudicator’s decision as null and void indicated
            their intention to reopen the four disputes originally brought
            for consideration.
     This Court in M.K. Shah Engineers & Contractors vs. State of
     M.P.2, a case similar to the present where the employer was trying



2   (1999) 2 SCC 594
322                                                            [2026] 1 S.C.R.

                           Supreme Court Reports


       to take advantage of its own wrong, rejected the contention of the
       employer and held as follows: -
            “14. In Halsbury’s Laws of England (4th Edn.) Vol. 2, vide
            paras 652, 654, at pp. 363, 365, the law is so stated. The
            arbitration agreements may contain a clause which requires
            a certain act to be completed within a specified period and
            which provides that if that act is not done, either the claim
            or the ability to commence an arbitration will be barred.
            Such clauses are sometimes known as “Atlantic Shipping”
            clauses. The consequences of the expiry of a contractual
            limitation period before the completion of the specific act
            may however be avoided in three circumstances:
            (i) if the court exercises its discretion statutorily conferred
            on it, to extend the period to avoid undue hardship;
            (ii) if the arbitration clause confers a discretion on the
            arbitrator to extend the period and he exercises it;
            (iii) if the conduct of either party precludes his relying on
            the time-bar against the claimant.
            17. No one can be permitted to take advantage of one's
            own wrong. The respondent-State of M.P. cannot and
            could not have been heard to plead denial of the two
            appellants' right to seek reference to arbitration for non-
            compliance with the earlier part of clause 3.3.29. In the
            case of M/s Chabaldas & Sons, the clause was complied
            with. Alternatively, even if it was not complied with in the
            case of M/s Chabaldas & Sons, but certainly in the case
            of M/s M.K. Shaw, the fault for non-compliance lies with
            the respondent-State of M.P. through its officials. The plea
            of bar, if any, created by the earlier part of clause 3.3.29
            cannot be permitted to be set up by a party which itself has
            been responsible for frustrating the operation thereof. It will
            be a travesty of justice if the appellants for the fault of the
            respondents are denied the right to have recourse to the
            remedy of arbitration. A closer scrutiny of clause 3.3.29
            clearly suggests that the parties intended to enter into
            an arbitration agreement for deciding all the questions
            and disputes arising between them through arbitration
            and thereby excluding the jurisdiction of ordinary civil
[2026] 1 S.C.R.                                                       323

           M/s Bhagheeratha Engineering Ltd. v. State of Kerala


            courts. Such reference to arbitration is required to be
            preceded by a decision of the Superintending Engineer
            and a challenge to such decision within 28 days by the
            party feeling aggrieved therewith. The steps preceding
            the coming into operation of the arbitration clause
            though essential are capable of being waived and if
            one party has by its own conduct or the conduct of its
            officials, disabled such preceding steps being taken, it
            will be deemed that the procedural prerequisites were
            waived. The party at fault cannot be permitted to set up
            the bar of non-performance of prerequisite obligation
            so as to exclude the applicability and operation of the
            arbitration clause.”
                                              (Emphasis supplied)

     We draw considerable support from the ratio of M.K. Shah (supra) on
     the aspect of conduct of the respondent and the holding therein, that
     the party at fault cannot be permitted to take advantage of the same.
     Further, like in M.K. Shah (supra) the Arbitration clause here also is
     of wide amplitude. In view of the above, we reject the contention of
     the respondent that the procedure for appointment of an arbitrator
     has not been complied with in this case and, as such, the award has
     to be set aside. We find absolutely no merit in the same.

     OBJECT OF SECTION 21 OF A&C ACT: -
16. Secondly, the object of Section 21 of A&C Act, is only for the purpose
    of commencement of arbitral proceedings is also well settled.
    Section 21 is concerned only with determining the commencement
    of the dispute for the purpose of reckoning limitation. There is no
    mandatory prerequisite for issuance of a Section 21 notice prior to
    the commencement of Arbitration. Issuance of a Section 21 notice
    may come to the aid of parties and the arbitrator in determining the
    limitation for the claim. Failure to issue a Section 21 notice would
    not be fatal to a party in Arbitration if the claim is otherwise valid
    and the disputes arbitrable. In ASF Buildtech Private Limited vs.
    Shapoorji Pallonji & Company Private Limited3, one of us, J.B.
    Pardiwala J., felicitously put the principle thus: -


3   (2025) 9 SCC 76
324                                                    [2026] 1 S.C.R.

                     Supreme Court Reports


       163. The marginal note appended to Section 21 of the
       1996 Act makes it abundantly clear that the notice to be
       issued thereunder is for the purpose of “commencement
       of arbitration proceedings”. The substantive provision
       further makes it clear that the date on which a request/
       notice of invocation for referring a dispute is received
       by the respondent, would the date on which the arbitral
       proceedings in respect of a particular dispute commences.
       The words “particular dispute” assume significance in the
       interpretation of this provision and its underlying object.
       It indicates that the provision is concerned only with
       determining when arbitration is deemed to have
       commenced for the specific dispute mentioned in the
       notice. The language in which the said provision is
       couched is neither prohibitive or exhaustive insofar
       as reference of any other disputes which although not
       specified in the notice of invocation yet, nonetheless
       falls within the scope of the arbitration agreement.
       The term “particular dispute”, does not mean all
       disputes, nor does it confine the jurisdiction of the
       Arbitral Tribunal which is said to be one emanating
       from the “arbitration agreement” to only those disputes
       mentioned in the notice of invocation, as it would
       tantamount to reading a restriction into the jurisdiction
       of the Arbitral Tribunal to the bounds of the notice of
       invocation instead of the arbitration agreement. Thus,
       there is no inhibition under Section 21 of the 1996 Act
       for raising any other dispute or claim which is covered
       under the arbitration agreement in the absence of
       any such notice. Section 21 is procedural rather than
       jurisdictional it does not serve to create or validate the
       arbitration agreement itself, nor is it a precondition for
       the existence of the Tribunal’s jurisdiction, but merely
       operates as a statutory mechanism to ascertain the
       date of initiation for reckoning limitation.
       165. Section 23 sub-section (1) places an obligation upon
       the claimant to state the facts supporting his “claim”, the
       points at issue and the relief or remedy sought by way of
[2026] 1 S.C.R.                                                            325

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


           its statement of claim, before the Arbitral Tribunal. Notably,
           the legislature, in the first part of the said sub-section,
           has deliberately and consciously used the term “claim”
           as opposed to “particular dispute” employed in Section 21
           of the 1996 Act. Although, it could be said that the term
           “particular dispute” under Section 21 connotes a larger
           umbrella within which the term “claim” under Section 23
           would be subsumed, thereby suggesting that there is no
           scope to deviate from what was sought to be referred
           by the notice of invocation, we do not think so. We say
           so because, the requirement for providing the points at
           issue and the relief or remedy sought that exists in sub-
           section (1) of Section 23 of the 1996 Act is patently absent
           in Section 21 of the 1996 Act, which clearly shows that the
           scope and object of these two provisions are at variance
           to each other. Further, this sub-section does not stipulate
           either explicitly or implicitly, that such “claim” must be the
           same or in tandem with the “particular dispute” in respect
           of which the notice of invocation was issued under Section
           21 of the 1996 Act. This distinction in terminology is neither
           incidental nor redundant; rather, it reflects a conscious
           legislative design to demarcate the procedural objective
           of Section 21 from the substantive function sought or the
           framing of issues served by Section 23. Unlike Section 23,
           Section 21 does not require any articulation of the relief
           its sole purpose is to indicate when arbitration is deemed
           to have commenced, for the limited purpose of computing
           the limitation period.
           169. Any restriction on the nature or content of claims,
           counterclaims, or set-offs in arbitration must be
           sourced solely from the express language of Section
           23 and not from Section 21. Section(s) 21 and 23 of
           the 1996 Act although overlap in some aspects with
           each other in terms of the claims that would ordinarily
           be referred to the Tribunal more often than not tend to
           coincide, yet they are by no means tethered together
           in such a manner that neither of them can survive
           without one another. The latter serves only a procedural
           function and does not condition or limit the Tribunal’s
326                                                         [2026] 1 S.C.R.

                          Supreme Court Reports


            jurisdiction to adjudicate claims that may not have
            been specifically invoked at the threshold stage. To
            read such a limitation into the statutory scheme would
            run contrary to both the text and the object of the Act.”
                                                (Emphasis supplied)

       More recently in Adavya Projects Private Limited v. Vishal
       Structurals Private Limited and others4, this Court reiterating
       the purpose and significance of a notice under Section 21 had the
       following to observe: -
            “24. At this point, it is important to note this Court’s
            decision in State of Goa v. Praveen Enterprises [State
            of Goa v. Praveen Enterprises, (2012) 12 SCC 581]
            wherein it was held that the claims and disputes raised
            in the notice under Section 21 do not restrict and limit
            the claims that can be raised before the Arbitral Tribunal.
            The consequence of not raising a claim in the notice
            is only that the limitation period for such claim that is
            raised before the Arbitral Tribunal for the first time will
            be calculated differently vis-à-vis claims raised in the
            notice. However, non-inclusion of certain disputes in
            the Section 21 notice does not preclude a claimant from
            raising them during the arbitration, as long as they are
            covered under the arbitration agreement. Further, merely
            because a respondent did not issue a notice raising
            counterclaims, he is not precluded from raising the
            same before the Arbitral Tribunal, as long as such
            counterclaims fall within the scope of the arbitration
            agreement.”
                                                [Emphasis supplied]

17. At this stage, it is appropriate to refer to the following passage from
    the decision of this Court in Indian Oil Corporation Ltd. v. Amritsar
    Gas Service and Others5 which reinforces our holding:-



4   (2025) 9 SCC 686
5   (1991) 1 SCC 533
[2026] 1 S.C.R.                                                            327

           M/s Bhagheeratha Engineering Ltd. v. State of Kerala


            “15. The appellant’s grievance regarding non-consideration
            of its counter-claim for the reason given in the award does
            appear to have some merit. In view of the fact that reference
            to arbitrator was made by this Court in an appeal arising
            out of refusal to stay the suit under Section 34 of the
            Arbitration Act and the reference was made of all disputes
            between the parties in the suit, the occasion to make a
            counter-claim in the written statement could arise only
            after the order of reference. The pleadings of the parties
            were filed before the arbitrator, and the reference covered
            all disputes between the parties in the suit. Accordingly,
            the counter-claim could not be made at any earlier stage.
            Refusal to consider the counter-claim for the only reason
            given in the award does, therefore, disclose an error of law
            apparent on the face of the award. However, in the present
            case, the counter-claim not being pressed at this stage
            by learned counsel for the appellant, it is unnecessary to
            examine this matter any further.”

     ARBITRATION CLAUSE – WIDELY WORDED: -
18. Thirdly, Clause 25.3 is widely worded and any dispute or difference
    arising between the parties relating to any matter arising out of or
    concerned with the agreement are to be settled in accordance with
    the A&C Act by the Arbitral Tribunal. As held in State of Goa vs.
    Praveen Enterprises6 if an arbitration agreement provides that all
    disputes between the parties relating to the contract shall be referred
    to arbitration, the reference contemplated is the act of parties to the
    arbitration agreement. In Praveen Enterprises (supra) it has been
    further held as follows:-
            “19. There can be claims by a claimant even without
            a notice seeking reference. Let us take an example
            where a notice is issued by a claimant raising disputes
            regarding Claims A and B and seeking reference
            thereof to arbitration. On appointment of the arbitrator,
            the claimant files a claim statement in regard to the said
            Claims A and B. Subsequently if the claimant amends


6   (2012) 12 SCC 581
328                                                    [2026] 1 S.C.R.

                     Supreme Court Reports


       the claim statement by adding Claim C [which is
       permitted under Section 23(3) of the Act] the additional
       Claim C would not be preceded by a notice seeking
       arbitration. The date of amendment by which Claim
       C was introduced, will become the relevant date for
       determining the limitation in regard to the said Claim
       C, whereas the date on which the notice seeking
       arbitration was served on the other party, will be the
       relevant date for deciding the limitation in regard to
       Claims A and B. Be that as it may.
       26. Section 23 of the Act makes it clear that when the
       arbitrator is appointed, the claimant is required to
       file the statement and the respondent has to file his
       defence statement before the arbitrator. The claimant
       is not bound to restrict his statement of claim to the
       claims already raised by him by notice, “unless the
       parties have otherwise agreed as to the required
       elements” of such claim statement. It is also made
       clear that “unless otherwise agreed by the parties” the
       claimant can also subsequently amend or supplement
       the claims in the claim statement. That is, unless the
       arbitration agreement requires the arbitrator to decide
       only the specifically referred disputes, the claimant
       can while filing the statement of claim or thereafter,
       amend or add to the claims already made.
       27. Similarly, Section 23 read with Section 2(9)
       makes it clear that a respondent is entitled to raise
       a counterclaim “unless the parties have otherwise
       agreed” and also add to or amend the counterclaim,
       “unless otherwise agreed”. In short, unless the
       arbitration agreement requires the arbitrator to
       decide only the specifically referred disputes, the
       respondent can file counterclaims and amend or add
       to the same, except where the arbitration agreement
       restricts the arbitration to only those disputes which
       are specifically referred to arbitration, both the claimant
       and the respondent are entitled to make any claims
       or counterclaims and further entitled to add to or
       amend such claims and counterclaims provided they
[2026] 1 S.C.R.                                                          329

         M/s Bhagheeratha Engineering Ltd. v. State of Kerala


           are arbitrable and within limitation.
           41. The position emerging from the above discussion
           may be summed up as follows:
           (a) Section 11 of the Act requires the Chief Justice
           or his designate to either appoint the arbitrator(s)
           or take necessary measures in accordance with the
           appointment procedure contained in the arbitration
           agreement. The Chief Justice or the designate is not
           required to draw up the list of disputes and refer them
           to arbitration. The appointment of the Arbitral Tribunal
           is an implied reference in terms of the arbitration
           agreement.
           (b) Where the arbitration agreement provides for
           referring all disputes between the parties (whether
           without any exceptions or subject to exceptions),
           the arbitrator will have jurisdiction to entertain any
           counterclaim, even though it was not raised at a stage
           earlier to the stage of pleadings before the arbitrator.
           (c) Where however the arbitration agreement requires
           specific disputes to be referred to arbitration and
           provides that the arbitrator will have the jurisdiction
           to decide only the disputes so referred, the arbitrator’s
           jurisdiction is controlled by the specific reference and
           he cannot travel beyond the reference, nor entertain
           any additional claims or counterclaims which are not
           part of the disputes specifically referred to arbitration.”
     It will be seen that when the Arbitral Tribunal is constituted, the
     claimant is required to file the statement and the respondent to file his
     defence statement with counter claim, if any, before the arbitrator. The
     claimant is not bound to restrict his statement of claim to the claims
     raised by him in the notice issued, if any, before. The claimant can
     also amend or supplement the claims in the claim statement unless
     the arbitration agreement requires the arbitrator to decide only the
     specifically referred disputes. Equally, counter claims can also be
     filed and amended. In the present case, we have already held that
     the rigors of clause 24, 24.1 and 25 have not been followed by the
     parties and by their conduct the entire dispute have been thrown
     at large before the Arbitral Tribunal. Hence, the contention of the
330                                                            [2026] 1 S.C.R.

                           Supreme Court Reports


       respondent that the case of the parties is governed by para 41(c)
       of Praveen Enterprises (supra) is rejected.

       RELEVANT STATUTORY PROVISIONS: -
19. Section 2(9) of the A&C Act reads as under:-
            “2(9) Where this Part, other than clause (a) of section 25
            or clause (a) of sub-section (2) of section 32, refers to a
            claim, it shall also apply to a counter-claim, and where
            it refers to a defence, it shall also apply to a defence to
            that counter-claim.”
20. Section 23 of the A&C Act as is relevant is also setout hereinbelow:-
            “23. Statement of claim and defence.—(1) Within the
            period of time agreed upon by the parties or determined
            by the arbitral tribunal, the claimant shall state the facts
            supporting his claim, the points at issue and the relief or
            remedy sought, and the respondent shall state his defence
            in respect of these particulars, unless the parties have
            otherwise agreed as to the required elements of those
            statements.
            (2) The parties may submit with their statements all
            documents they consider to be relevant or may add a
            reference to the documents or other evidence they will
            submit.
            (2A) The respondent, in support of his case, may also
            submit a counter-claim or plead a set-off, which shall be
            adjudicated upon by the arbitral tribunal, if such counter-
            claim or set-off falls within the scope of the arbitration
            agreement.
            (3) Unless otherwise agreed by the parties, either party
            may amend or supplement his claim or defence during
            the course of the arbitral proceedings, unless the arbitral
            tribunal considers it inappropriate to allow the amendment
            or supplement having regard to the delay in making it.”
       It will be noticed that once the Arbitral Tribunal is constituted claims,
       defence and, counter claims are filed. Party which normally files the
       claim first is, for convenience, referred to as the ‘claimant’ and the
[2026] 1 S.C.R.                                                              331

            M/s Bhagheeratha Engineering Ltd. v. State of Kerala


     party which responds is called the ‘respondent’. The said respondent
     is also along with the defence statement entitled to file its counter
     claim. Hence, to contend that the appellant cannot be referred to
     as a claimant because no notice under Section 21 has been issued
     is completely untenable. To illustrate the point, the rules from the
     DIAC rules are set out: -
             “DIAC Arbitration Proceedings Rules, 2018
             2.1(g) “Claimant”, notwithstanding any nomenclature given
             to the parties in any Court in any proceeding between
             them, means the party which files the Statement of Claim
             first in point of time. The other party(ies) shall be referred
             to as “Respondent(s)”. The party filing Counter-Claim(s)
             shall be referred as “Counter-Claimant”.
21. The judgment cited by the respondent namely Iron & Steel Co. Ltd. v.
    Tiwari Road Lines7, and MSK Projects India (JV) Limited vs. State
    of Rajasthan and Another8, have no application to the facts of the
    case, as not only is there no breach of procedure in the appointment
    of Arbitral Tribunal, the Arbitral Tribunal has also not travelled beyond
    the scope of the reference. No other argument touching upon the
    merits of the award have been canvassed before us.
22. For the reasons stated above, we set aside the judgment of the
    High Court of Kerala at Ernakulam dated 07.01.2025 in Arbitration
    Appeal No. 56/2012. The consequence will be that the award of the
    arbitrator dated 29.06.2006 is upheld in its entirety. The appeal is
    allowed. No order as to costs.

     Result of the case: Appeal allowed.




     †
         Headnotes prepared by: Divya Pandey




7   (2007) 5 SCC 703
8   (2011) 10 SCC 573


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitral Tribunal did not exceed its jurisdiction in deciding the entire dispute"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.