M/S AROSAN ENTERPRISES LTD.versusUNION OF INDIA AND ANR.
- Citation
- 1999 INSC 418
- Decided
- 16 September 1999
- Disposal
- Appeal(s) allowed
- Bench
- B N KIRPAL
Holding
Time is not the essence where the contract provides for extension; the buyer’s withdrawal of cancellation is a waiver, and courts may not set aside an arbitral award absent statutory grounds, so the arbitral award is upheld.
Summary
Mis Arosan Enterprises Ltd entered into a contract with the Union of India/FCI for the supply of 58,000 metric tonnes of sugar, stipulating that shipment by 31 October 1989 was the essence of the contract but also allowing the buyer to extend the delivery period at a discount. The buyer cancelled the contract for non‑supply, later withdrew the cancellation without fixing a new delivery date, and remained silent to the seller’s repeated requests for an extension. The seller’s performance bank guarantee was forfeited and an arbitral award ordered its refund. The Delhi High Court set aside the award, holding that the buyer had implicitly accepted a new delivery date (14‑15 November 1989) and that the seller was in breach. The Supreme Court held that because the contract provided for extension, time was not the essence; the withdrawal of cancellation amounted to a waiver, the buyer’s silence forfeited his right to cancel, and no fresh date could be implied. Moreover, courts cannot interfere with an arbitral award absent the limited grounds in the Arbitration Act, 1940. Consequently, the appeal was allowed and the arbitral award restored.
Issues considered
- Whether time was the essence of the contract under Section 55 of the Indian Contract Act, 1872.
- Whether the buyer’s withdrawal of the cancellation constituted a waiver and whether a fresh delivery date could be implied.
- Whether the High Court had jurisdiction to set aside the arbitral award under the Arbitration Act, 1940.
- Whether the bank could dispute the seller’s performance under the Letter of Credit.
Legislation cited
- Arbitration Act, 1940s. 30, s. 33
- Indian Contract Act, 1872s. 55
Subjects
Judgment
MIS AROSAN ENTERPRISES LTD. A
v.
UNION OF INDIA AND ANR.
SEPTEMBER 16, l 999
[B.N. KIRPAL AND UMESH C. BANERJEE JJ.] B
Contract Act 1872-Section 55-Time as essence of the contract-
Contractor for supply of sugar within specified time-But contract also
provided for extension of time-Buyer not fulfilled some of ~is obligations-
Neither the port of discharge named nor the surveyor appointed-Further C
buyer cancelled the contract for non-supply within time and later withdrew
the cancellation order and again cancelled contract-Held, time is not the
essence of contract and mere fixation of time for delivery of goods will not
make it essence of contract-Jn such a case agreement shou.ld be read as
whole alongwith corresponding obligations of the parties in order to gather D
the true intention-Further, no presumption about extension of time or
presumed acceptance of a renewed date would arise-More so, withdrawing
of cancellation order of the contract by the buyer amounted to wavier of non-
performance by seller-Further, silence on the part of the buyer to the
repeated request of the seller for extension of time forfeited his right under
the contract and does not entitle the buyer to cancel the contract. E
Letter of Credit-Bank cannot raise a dispute as to whether the gooqs
have been supplied within time or not-It is rule ofprudence to have extended
delivery date on the letter of credit by way of amendment and the counter
guarantee should stipulate the delivery date-Buyer must state whether
amendment in the letter of credit was necessary or not. F
Arbitration Act, 1940-Section 30 and 33-Court's interference with
the arbitration award-Scope of-Default, time if essence ofcontract, quantum
of damages are issues offact-Held, courts have no authority to interdict an
award on factual issues-Further, in case of speaking award, unless there is G
total perversity court cannot set aside the award by reappraising the
evidence.
Respondents entered into a contract with the appellants for supply of
sugar within specified time. The shipment within the contracted delivery
period was to be the essence of contract. In case of delay the appellants were H
621
622 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A deemed to be in contractual default with a right to the respondents to cancel
the contract. Appellants furnished bank guarantee. TherJafter, the
respondents assigned the contract to the Food Corporation of India. Then, the
Corporation opened a letter of credit for full value of the contract; however,
its authentication was not effected within the delivery date. Even then, the
B respondents cancelled the contract for non supply of sugar within time.
Subsequently they withdrew the cancellation order but the letter of withdrawal
did not contain any new date of delivery. Appellants reminded the corporation
to fax the delivery date and take steps to effect the payment But the respondents
and corporation maintained total silence. Respondents cancelled the contract
on the ground of failure on the part of the appellants to fulfil its contractual
C obligations within the stipulated time. The performance bank guarantee of
the appellants was also forfeited. By the reason of forfeiture the matter was
referred to the arbitrator. The arbitrator published the award to the effect
that the appellants were entitled to refund of performance bank guarantee
amount This arbitral award was sustained by the Single Judge. In appeal,
the Division Bench held that the respondents had accepted the new date of
D delivery by which the appellants were bound to deliver and the failure of the
appellants to supply by the said date amounted to breach of contract and thus,
set aside the order of the Single Judge and also the arbitral award. Hence
this app~al.
Allowing the appeal, the Court
E
HELD: 1.1. Where time is essence of the contract there is no question
of any presumption or presumed extension or presumed acceptance of a •
renewed date. When there is no specific date available in the course of
conduct of the parties, then courts are not left with any conclusion but a
finding that the parties themselves by their conduct have given a go-by to the
F original term of contract as regards the time being essence of the contract
[632-E-G]
1.2. When the contract provides for extension of time, th_e same cannot
be termed to be essence of the contract and default in such a case does not
G make the contract voidable. It becomes voidable provided the matter in issue
can be brought within the ambit of the first para of Section 55 of the Contract
Act and it is only in that event the government would be entitled to claim
damages. (633-E] ·
Indian Contract and Specific Relief Acts by Pollock & Mui/a, referred
H to.
AROSAN ENTERPRISES LTD. v. U.0.1. 623
.. 1.3. Mere fixation of a period of delivery or time does not make time
as the essence of contract, but the agreement should be considered in its
entirety with the corresponding obligations of the parties so as to ascertain
the true intent of the parties. (643-G; 644-AI
A
1.4. The contract ought to be read with the time clause but subject to
certain other conditions. In the instant case, the goods were on the high seas B
and to be diverted to the ports of India, shortly, as such nomination of the
port, was an essential requirement, in order to make the seller liable for
breach of contract and entitlement of the buyer to claim damages. The port
of discharge had not been named nor was the surveyor appointed without
whose certificate - question of any payment would not arise, thus, it cannot C
be said that time was the essence of the contract.(643-C; 643-E; 644-A]
Benjamins 's Sales of Goods Act, (4th Edition), relied on.
1.5. When the contract itself provides reciprocal obligations and in the
event of non-fulfilment of some such obligations which have directed bearing D
on the contract, strict adherence of the time schedule or question of
continuing with the notion of the time being essence of the contract would
not arise. [642-G-H)
Halsbury 's Laws of England, (4th Edn.) Vol. 41, referred to.
E
1.6 The buyer cancelled the contract for non-supply within time and
later withdrew the letter of cancellation. This withdrawal of the cancellation
order of the contract by the buyer amounted to waiver of non-performance
by the seller. Thus, the presumption of the High Court to the effect that the
cancellation was on the representation of the seller is totally unwarranted. F
In the absence of any evidence fixation of future date of performance by the
appellate court is not justified and is untenable in law. Court cannot fix a date
on its own for performance of the contract. [634-H; 635-A-B)
1.7. There was a duty to speak on the part of the buyer to the repeated G
request of the seller for extension of time; failure to speak would forfeit all
the rights of the buyer in terms of the agreement. Further, failure to speak
would not jeopardise the seller's interest; neither would the same authorise
the buyer to cancel the contract. [637-F-G)
1.8. The bank cannot raise any dispute regarding the goods being H
624 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A actually supplied or not. It is the matter of prudence that to facilitate .
payment there should be an extended delivery date on the lettef of credit by
way of an amendment and the counter guarantee should stipulate the delivery
date. The requirement of a certificate that the original contract had been
fully complied with, it is necessary that the delivery for the purpose of the
B contract had to be extended since the original date by reason of efflux of time
had lapsed and the buyer must state"whether the amendment in the letter of
credit was necessary or not. [646-G-H; 647-A; D-E]
China Cotton Exporters v. Beharilal Ramcharan Cotton Mills ltd AIR
( 1961) SC 1295 and ITC Ltd., v. Debts Recovery Appellate Tribunal, [1998)
c 2 sec 70, distinguished.
UP. Coop. Federation Ltd. v. Singh Consultants and Engineers (P)
Ltd, [1998) 1 SCC 174, referred to.
2.1. The issues relating to default, time being the essence of contract
D and quantum of damages are all issues of fact and arbitrators are within
their jurisdiction to decide the issue as they deem fit. The courts have no
right or authority to interdict an award on a factual issue. [652-G)
Olympus Superstructures Pvt. Ltd. v. Meena Vijay Khetan & Ors.,
[1999) 5 sec 651, relied on.
E
2.2. In the instant case, the Single Judge rightly held that the findings
of the arbitrators in regard to the extension of delivery period and failure
to fix fresh date has resulted in breach of the contract on the part of the
buyer and the same being purely based on appreciation of material on record,
it cannot be termed to he an error apparent on the face of the record entitling
F the court to interfere. [651-D-E)
M Chel/appan v. Secretary, Kera/a State Electricity Board & Anr.,
[1975) 1 sec 289, relied on.
Champsey Ehara & Co. v. Jivraj Ba/oo Co., AIR (1923) PC 66 and
G Union ofIndia v. Bungo Steel Furniture Pvt. Ltd., AIR (1967) SC 1032, cited.
2.3. Reappraisal of evidence by the court is not permissible and this
exercise of power by the court is unknown to a proceeding under Section 30
of the Arbitration Act. When there are no reasons in the award, question
of interference of the Court would not arise and when there are reasons, the
H interference would still not be available unless there exist total perversity
ARO SAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, J.] 625
in the award or the judgment is based on a wrong proposition of law, also A
when two views are possible on a question of law the court would not be
justified in interfering with the award. [649-B-C]
2.4. Error apparent on the face of record does not mean and imply
closer scrutiny of the merits of documents and materials on record. The
court cannot substitute its evaluation and come to the conclusion that the B
arbitrator had acted contrary to the bargain between the parties and if the
view of the arbitrator is a possible view, award or reasoning contained
therein cannot be examined. (649-D-E]
State of Rajasthan v. Puri Construction Co. Ltd, (1994) 6 SCC 485, C
relied on.
Sudarsan Trading Co. v. Govt. of Kera/a & Anr., [1989) 2 SCC 38,
referred to.
CIVIL APPELATE JURISDICTION: Civil Appeal Nos. 8010of1995. b
From the Judgment and Order dated 12.5.95 of the Delhi High Court in
F.A.O. (OS) No. 217of1994.
Mukul Rohtagi, G.L. Sanghi, R.N. Karanjawala, Ms. Seema Sapra, Ms.
Pooja Dua and Mrs. Manik Karanjawala for the Appellant.
E
S.K. Dholakia and Dr. A Francis Julian, for Mis. Arputham Aruna & Co.,
for the Respendent in F.C.I.
K.N. Rawal, Additional Solicitor General , P.P. Malhotra, Ms. Indira
Sawhney and B.V. Bairam Das for the Union of India.
F
The Judgment of the Court was delivered by
BANERJEE, J. These two Appeals by the grant of Special Leave and
arising out of the Judgment of the Delhi High Court focus two singularly
singular questions pertaining to (i) the time being the essence of the contract G
and (ii) authority of the High Court in the mafter of interference with an
Arbitral Award under the Repealed Act of 1940 (The Arbitration Act, 1940).
For effectual disposal of these two questions, noticed above, reference
to certain factual details in this judgment is inevitable and adverting thereto
it appears that on October 4, 1989 Union of India floated an invitation to H
626 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A tender for purchase of sugar to meet the urgent requirement of anticipated
scarcity in the Indian market during the Dussehra and Diwali festivals in
November, 1989 which however, and without much of a factual narration,
culminated in an Agreement dated 24th/25th October, 1989 with Mis. Arosan
Enterprises, being the Appellants herein, for the supply of 58000 metric
B tonnes of sugar. The Contract as above inter alia contained the following
terms:
"(a) That the claimant shall supply 58,000 M. T. of sugar (net weight
plus minus 5% at sellers option).
(b) That the claimant shall arrange shipment of entire quantity of the.
c contracted sugar so as to reach InE:i Ports not later than 31st
October, 1989; shipment within contracted delivery period
was to be the essence of the co tract.
/
In case of delay the seller was to be deemed to be in contractual default
with a right to the buyer to canpel the contract. The buyer could however
D extend the delivery period at a discount as may be mutually agreed between ·
the buyer and the seller.
(c) That price payable was to be U.S. Dollar 480 per metric tonne.
(d) That the seller had to establish an unconditional irrevocable
-
performance guarantee in favour of the buyer by any Indian
E Nationalised Bank at New Delhi for 10% of the total contract
value of the maximum guaranteed quantity to be shipped, within
7 days of the contract.
(e) That the payment was to be made to the seller by irrevocable
letter of credit (L/C) covering 100% value of the contract quantity.
F The L/C was to be established by the buyer within seven days
of the receipt of an acceptable performance Bank Guarantee.
(f) The Performance Bank Guarantee (PBG) was to be by any Indian
Nationalised Bank at New Delhi and was to be kept valid for a
minimum period of ninety days beyond the last date of contract
G shipment period."
The factual score further depicts that on 24th October, 1989, itself the
appellant did furnish a performance bank guarantee for $ 29,28,000 and upon
bank guarantee being furnished, the Government of India assigned the contract
to the Food Corporation oflndia (FCI) under clause 20 of the Agreement. FCI
H also in its tum opened a Letter of Credit for the full. value of the contract
AROSAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, J.] 627
though, however, as the records depict that while on 26th October, 1989, the A
Letter of Credit was opened by FCI but its authentication was not effected
within the delivery date i.e. 31st October, 1989.
Be it noted that in terms of the payment claus~, the payment was to be
made by the buyer by way of irrevocable letter of credit covering 100% of B
the contract quantity and Jetter of credit was to be established by the buyer
within seven days from the receipt of performance bank guarantee and it is
upon completion of the period of 7 days from the date of acceptance of the
performance guarantee, the letter of credit should have been authenticated
and that was to be effected by about 31st October, 1989. In the contextual
facts the authenticated bank guarantee was effected only on 2nd November, C
1989 i.e. after the expiry of the date of the delivery - It is on this score detailed
submissions have been made by both Mr. Rohtagi appearing in support of
the appeal and Mr. Dholakia appearing for FCI and Mr. K.N. Rawal, the
learned Addi. Solicitor General for the Union of India and it is in this perspective
certain further factual details would be of some assistance.
D
The telex messages from Food Corporation of India dated 3rd, 7th and
8th November, 1989 go to show that in fact there was the anxiety of the buyer
to obtain the goods and it is on these anxious inquiries, Mr. Rohtagi contended
that the time for delivery obviously stands extended and the essence of the E
contract been given a go-by.
The facts further depict that while the correspondence were had between
the parties as regards the delivery schedule, Government of India by a letter
dated 8th November transmitted an intimation which was despatched on 9th
November, 1989, canceling the contract at the risk and cost of the appellaut F
herein. Subsequently, however, on 11th November, 1989, the Government of
India unilaterally by its letter withdrew the Jetter of cancellation and on 15th
November, 1989 the appellant informed the FCI that by reason of the
cancellation, the cargo arranged already, has gone out of control and that a
new cargo was being arranged by reason wherefor FCI was asked to fix a new G
delivery date and consequently steps would be taken in regard thereto.
Needless to refer here, that the letter of withdrawal of cancellation, however,
did not contain any fixed date or new date of delivery. There was, however,
as the records depict, total silence from FCI, and consequently, the appellants
on 24th and 30th November, 1989 further reminded the cooperation to fix the
delivery date and take necessary steps to effect the payment under the law H
628 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A of trading. Significantly, both FCI and Government of India maintained a total
silence in regard thereto in spite thereof.
On the factual matrix it further appears that subsequently a meeting was
held between the claimants and the Union Minister for Food and Civil Supplies
wherein it was agreed that on the claimants paying a sum of Rs.5 lakhs
B towards the expenses incurred by the Government in opening the letter of
credit and claimants giving up any claim for damages, the performance bank
guarantee would be released - this aspect of the matter has however been •
very emphatically disputed by respondents and both the learned senior
Advocates appearing on behalf of the respondents contended that the Court
C would not be justified in assessing this aspect of the matter to be of any
relevance in the contextual facts. We shall refer to this aspect of the matter
later more fully in this judgment, but to complete the factual score, it appears
that on 25th January, 1990 the Government of India canceled the contract on
the ground that the seller had failed to fulfil its contractual obligations within
stipulated time which was mentioned to be on 31.l 0.89 and the performance
D bank guarantee of the claimants was also forfeited by FCI.
It is by reason of such a forfeiture, however, that the matter was
referred to arbitration in terms of the arbitration clause in the agreement
between the parties. There being however, no dispute, as regards the
E arbitration clause, we deem it convenient not to set out the same in
extenso and suffice it would be further to note th.at Sri Justice S.N.
Shankar, the former Chief Justice of the High Court of Orissa and Sri
K. C. Diwan, an Advocate were appointed as Arbitrators in terms
therewith and who in their turn made and published their award to the
effect that the claimants were entitled to the refund of the performance
F bank guarantee amount of $ 29,28,000. The claim of the claimant-
appellant herein, however, on account of interest was rejected. It is
this Arbitral award which was challenged before High Court and the
learned Single Judge found that FCI's letter dated 8th November, 1989
clearly depicted that they were still interested in taking delivery of the
goods and therefore the claimant was justified in asking for fixation
G of a fresh delivery date. The learned Single Judge further found that
the findings of the Arbitrators in regard to extention of the delivery
period and failure to fix the fresh date has resulted in breach of the
contract on the part of the Government and the same being purely
based on appreciation of materials on record, question of interference
-
H therewith would not arise since by no stretch it can be termed to be
AROSAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, J.] 629
an error apparent on the face of the record. The award, therefore, was A
sustained by the learned Single Judge. In an appeal therefrom however,
the fmding of the Single Judge was reversed and the Bench of the
Delhi High Court dealing with the Appeal in question recorded that
the buyer, being the Appellant herein, had in fact impliedly accepted
14/lSth November, 1989 as the new date of delivery by which the
seller was bound to deliver and the failure of the seller to supply by B
the said date constituted a breach of contract justifying the cancellation
and thus set aside the judgment and order of the learned Single Judge
as also the arbitral award. The Bench further ordered that the fmdings
of the Arbitrators to the effect that the buyer was obliged to fix fresh
dates of delivery was an error of law ori the fa~e of the record and C
as such there was a breach committed by the seller. It is against this
order of the Division Bench of the High Court that a Special Leave
Petition was filed before this Court and this Court by an order dated
4th September, 1995 granted special leave in pursuance whereof this
matter has come up for final disposal before this Bench.
D
Turning now on to th~issues as noticed above namely, whether
time was the essence of the contract or not, it would be convenient
to note the relevant extracts of the Arbitral award pertaining to the
issue in question. The Arbitrators, inter a/ia, found:
~'The ;.ithdrawal of the letter of cancellation (vide Ex.A.21) had E
the effect of reviving the original contract dated 24/25 October, 1989
with all its te~s except that sugar had to be delivered by 31 October,
1989. Stipulation in clause 3 of the contract that shipment with contract
delivery period is of the essence of the contract" also stood revived.
Letter of Credit had been established on the basis of the original F
contract which stipulated a fixed time for delivery but as no time for
delivery was fixed in the letter withdrawing the cancellation (Ex.A- 21 ),
the claimants naturally felt concerned and repeatedly requested the
respondent to do the needful.
G
Evidence adduced thus clearly shows that the Respondents sent
no reply whatever to the request of the claimants asking for
specification of the delivery time and for the needful being done in
regard to L/C in the changed circumstances after the withdrawal of the
letter of cancellation. On the contrary, all of a sudden they canceled H
630 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A the contract again by the letter dated 25.1.1990 Ex.A36. In our view,
this conduct of the respondents was unjustified and illegal in the
facts of this case.
Then again ft would be seen that the ground of cancellation taken
B in the letter of second cancellation Ex.A36 is the same as had been
taken earlier in letter Ex.A 17, namely failure t~ fulfil the contractual
obligation within the stipulated time of 31st October, 1989. The
respondents had already waived this ground. They were precluded
from canceling the contract on the same ground again after its revival.
·c The cancellation by Ex.A36 thus on a non-existent ground and illegal."
The Arbitrators further held that
"We further find that L/C opened by the respondents was with
D reference to the contract which stipulated a fixed time for delivery
(namely 31st October, 1989) but after revival of the contract the position
had changed materially. The original contract had been cancelled and
this cancellation .had been withdrawn and in the contract that stood
after withdrawal of the cancellation no time for delivery was stipulated.
It was incumbent on the respondents to apprise this position to the
E Bank and make suitable changes in the L/C. The claimants could
receive from the Bank, the amount secured by L/C for their benefit
only after satisfying the bank, that they had shipped the contracted
sugar in accord.ance with the terms of the contract. There is nothing
on the record to show that the respondents took any steps to inform
F the Bank of the changed position so that shipping documents
presented by the claimants after 31st October, 1989 could be examined
by the bank in the light of the new situation."
The argument is without merits. If the contract was revived on the
G understanding why was not this fact communicate.d to the claimants
in reply to their persistent queries about the date of delivery and why
was the L/C not suitably modified and the bank issuing the L/C
infomied accordingly. In fact, there is no foundation in the pleadings
for such a plan.
H
AROSAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, J.] 631
Admittedly in spite of these requests of the claimant for extension of A
delivery period no fresh delivery date was notified by the respondents.
Thus the extension of delivery period was never granted nor intimated
to the supplier/claimant."
B
The Arbitrators therefore came to a conclusion that there is a breach
of the contract committed by the respondents herein and consequently
forfeiture of the performance bank guarantee was illegal and not sustainable.
The learned Single Judge in the application for setting aside the award was
pleased to record:
c
"The cancellation of the contract on 25. l.1990 on the basis of non-
delivery of material by 31st October, 1989 was usually misconceived,
untenable and illegal because 31st October, 1989 had admittedly ceased
to be delivery date ....... .It appears that the argument that 14th November,
1989 or 15th November, 1~ were the fresh delivery dates is an after-
thought. If the respondents believed that these were the delivery D
dates, nothing prevented them from saying so at the relevant time.
The claimant repeatedly asked them to fix fresh delivery date.
Respondents could reply that these were the dates.
E
These show that the original delivery date of the contract hap become
part of the letter of credit. Unless the same was modified and the
modified date had been notified to the banks, the banks would be
paying under the credit at their own risk. No bank would be willing
to take such a risk. The result that follows is that the payment to the
supplier/claimant would have been in jeopardy unless the letter of F
credit was amended. The intention in the original contract was that
the supplier should get immediate payment through irrevocable letter
of credit. Without amendment of the letter of credit, the. said intention
of the contract could not be fulfilled. The supplier was justified in
ensuring that he would get the_ payment for the material supplied by- G
him before the supplies were made."
I
In the facts of the matter under consideration the leameti Single Judge
found that FCI by its letter dated 8th November, 1989 clearly depicted in no
uncertain terms that they were still interested in taking delivery of the goods
and which as a matter of fact according to the learned Single Judge changed H
632 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A the entire complexion of the matter. The other issue in which the learned
Single Judge delved into is in regard to the Court's authority of interference
vis-a-vis the award-this aspect of the matter would be dealt with later in this
judgment alongwith the second issue, as such we refrain ourselves from
making any comment thereon ~t this juncture.
B Turning attention on to the first issue, the Division Bench of the High
Court proceeded mainly on certain presumptions to wit:
(i) the telex message from the seller dated 8.11.89 was sent to the
buyer after receipt of the cancellation and thus const.ituted a
C representation against the cancellation . and it was pursuant to
this representation that the buyer had issued the letter dated
11th November, 1989 withdrawing the letter of cancellation.
(it) the presumption of the High iourt went also on to the effect
tbat the buyer had therefore impliedly fixed 14th/15th November,
D 1989 as the new date of delivery by which time, the seller was
bound to deliver and the failure of the seller to supply by the
said date constituted the breach of contract justifying the
cancellation in January, 1990.
E These presumptions of the High Court in our view are wholly
unwarranted in the contextual facts for the reasons detailed below but before
so doing it is to be noted that in the event the time is the essence of the
contract, question of their being any presumption or presumed extension or
presumed acceptance of a renewed date would not arise. The extension if
there be any, should and ought to be categorical in nature rather than being
F vague or in the anvil of presumptions. In the event the parties knowingly give
a go by to the stipulation as regards the time - the same may have two several
effects: (a) parties name a future specific date for delivery and (b) parties may
also agree to the abandonment of the contract - as regards· (a) above, there
must be a specific date within which delivery has to be effected and in the
G event there is no such specific date available in the course of conduct of the
parties, then and in that event, the Colirts are not left with any other conclusion
but a finding that the parties themselves by their conduct have given a go
by to the original tenn of the contract as regards the time being the essence
of the contract. Be it recorded that in the event the contract comes within the
ambit of Section 55, the remedy is also provided therein. For convenience
H sake Section 55 reads as below:
AROSAN ENTERPRISES LTD. v. U.O.I. [BANERJEE, J.] 633
"55. When a party to a contract promises to do a certain thing at or A
before a specified time, or certain things at or before specified times,
and fails to do any such thing at or before the specified time, the
contract, or so much of it as has not been performed, becomes voidable
at the option of the promiseP., if the intention of the parties was that
time should be of the essence of the contract.
B
If it was not the intention of the parties that time should be of the
essence of the contract, the contract does not become voidable by the
failure to do such thing at or before the specified time; but the
promisee is entitled to compensation from the promisor for any loss
occasioned to him by such failure.
c
If, in case of a contract voidable on account of the promisor's failure
to perform his promise at the time agreed, the promisee accepts
performance of such promise at any time other than that agreed, the
promisee cannot claim compensation for any loss occasioned by the
non-performance of the promise at the time agreed, unless, at the time D
of such acceptance, he gives notice to the promisor of his intention
to do so."
Incidentally the law is well settled on this score on which no further
dilation is required in this judgment to the effect that when the contract itself
provides for extension of time, the same cannot be termed to be the essence E
of the contract and default however, in such a case does not make the
contract voidable either. It becomes voidable provided the matter in issue can
be brought within the ambit of the first paragraph of Section 55 and it is only
in that event that the Government would be entitled to claim damages and not
otherwise.
F
In Pollock & Mulla's Indian Contract and Specific Relief Acts, three
several cases have been very lucidly discussed, where time can be termed to
be the essence of contract:
"I. Where the parties have expressly stipulated in their contract that
the time fixed for performance must be exactly complied with, G
2. Where the circumstances of the contract or the nature of the
subject matter indicate that the fixed date must be exactly complied
with and
3. Where time was not originally of the essence of the contract, but H
.....
634 SUPREME COURT REPORTS (1999) SUPP. 2 S.C.R.
A one party has been guilty of undue delay, the other party may give
notice requiring contract to be performed within reasonable time and
what is reasonable time is dependant on the nature of the transaction
and on proper reading of the contract in its entirety."
In the contextual facts, the Division Bench relied on the Telex messages
B of the seller, as noticed above, as a representation against cancellation but
the fact remains that there was in fact a definite indication of expression of
stand of the Government as regards the withdrawal of the letter of cancellation.
The issue arises as to the true effect of the withdrawal of the cancellation.
Incidentally on the factual score it appears that after withdrawai of the first
C letter of cancellation the Government again for the second time cancelled the
Agreement by a letter dated 25th January, 1990 to the following effect:
l. "Your attention is invited to the contract mentioned above for
supply of 58000 MTs of imported sugar, Clause 3 whereof stipulates
that the seller shall arrange shipment of the entire quantity so as to
D reach Indian ports, basis coast as per Clause 4(1) ibid not later than
31st October, 1989
2. As you have failed to fulfil the contractual obligation within
stipulated time and the time being the essence of the contract, the
contract is hereby cancelled at your risk and cost
E
3. The Performance Bank Guarantee tendered with reference to the
above contract .is also forfeited for the reasons mentioned above."
There is therefore, a cancellation of an agreement which once stood
cancelled and withdrawn: can it be termed to be an otherwise valid termination
F after recalling of the letter of cancellation in the month ofNovember, 1989. The
High Court has dealt with the entire correspondence in extenso between the (
.-
parties during this interegnum and as such we refrain ourselves from dealing
with the same in detail, suffice it to record that as a matter of fact from the
date of recalling of the cancellation letter, there were consistent reminders
G about the dispatch instruction, about the arrival of vessels and as to the port
of landing which were for the Respondents herein, to fix, .in term'S of the
Agreement but there was a total silence from the Respondent's end. Admittedly
and there cannot possibly be any doubt as regards the cancellation of
Agreement on the expiry of the time if the time is treated to be the essence
of the contract, but in the contextual fac;ts when as a matter of fact, there was
H a letter of cancellation in terms of the contract and assuming by reason of
AROSAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, .T.) 635
failure to supply as per the Agreement between the parties - but that cancellation A
stands withdrawn. There is, therefore, a waiver of the breach if there be any,
as regards non- performance of the contract and it is on this score that the
High Court has gone wrong on the issue of duty to speak and it is on this
score that the presumption of the High Court to the effect that the cancellation
was on the representation of the seller, is totally unwarranted. Fixation of a B
future date of performance in the absence of any evidence by the Appellate
Court, is not only unjustified but wholly untenable in law. Court cannot
possibly fix a date on its own for performance of the contract. It is thus
necessary to detail out herein below the observations of the Appellate Court
on this count. The Appellate Court in paragraph 29 of the judgment observed
~~~: c
"29. The delivery was to be effected by 31st October, 1989. On the
representation of the seller as contained in their messages dated 8th
and 9th November 1989 the cancellation was withdrawn. That is the
only conclusion possible. Any other conclusion will be wholly
erroneous. We therefore, cannot accept the submission that the D
withdrawal of cancellation was not on the representation of the seller.
On this view the respondents were bound in law to accept delivery
if effected by 14th/15th November, 1989. It is implicit that the buyers
had consented to take delivery by 14th/15th November, 1989. The
contention of learned counsel for the seller that the mention of 3 lst E
October, 1989 by the respondents in letter dated 25th January, 1990-
also shows that the respondents did not treat 14th/15th November,
1989 as the extended delivery date cannot be accepted. Since delivery
was not made at all, the mention of 31st October, 1989 in the letter of
cancellation (25th January, 1990) by itself would not show that the
buyer did not treat 14th/15th November, 1989 as delivery date. It thus F
cannot be said that the cancellation was on non-existent grounds. The
contract also stipulates that the buyer may extend the delivery period
at a discount as may be mutually agreed to between buyer and seller.
rn this state of affairs the further contention that the supply could not
be made by 14th/15th November, 1989 on account ofnon amendment G
of the delivery period in the contract and non amendment of Jetter of
credit cannot be accepted. This plea is clearly an after thought. Our
attention has not been drawn to any legal proposition which casts an
obligation, under these circumstances, on t~e buyer to fix a fresh date
of ~elivery. The effect of accepting the contention of the seller would
be that prior to 8th November, 1989, on the facts and circumstances H
636 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A of the present case, the breach was on the part of the seller but the
buyer having withdrawn the cancellation and not having specified the
fresh date of delivery, 31st October, 1989 having already passed, the
breach would be on the part of the buyer. The contention on the face
of it is fallicious. It has to be rejected."
B In paragraph 30 of the judgment the Bench observed:
"30. Apart from the urgent need for supply of sugar, otherwise too,
in commercial transaction of this nature, in law, ordinarily time is of
essence (See: Mis. China Cotton Exporters v. Beharilal Ramcharan
c Cotton Mills Ltd., AIR (1961) SC 1295. Further, in the present case,
the contract itself stipulates that the supply within the contracted
delivery period was to be the essence of the contract. In this view,
the delivery of sugar firstly before 31st October, 1989 and later by
J4th/15th November, 1989 was of essence and non supply within the
aforesaid periods by the seller would show that the seller is in breach
D of the contract. The buyer having withdrawn the cancellation of the
contract on seller's representation that the delivery will be made by
14th/15th November 1989 could not have refused to accept delivery
within the said period. It is also not possible for us to accept the
contention that the cancellation was not withdrawn on the
representation of the seller. On account of non-supply of sugar upto
E
8th November, 1989 and even failure to supply the shipping particulars
the contract was cancelled by the buyer. Thereupon the seller supplied
the shipping particulars and made a representation that the supply
would be made on or before 14th/15th November, 1989. Under these
circumstances the cancellation of the contract was withdrawn. The
F letter dated 11th November, 1989 withdrawing the cancellation states
that on reconsideration of the matter the cancellation is withdrawn. In
~ .
the letter dated 11th November, 1989 the absence of specific reference
to the representation of the seller that the delivery would be made by
14th/15th November, 1989. Under these circumstances, is of no
consequence. As already noticed above, the letter dated 11th
G November, 1989 was personally handed over to the representative of
the seller. On receipt of that letter the seller did not write to the buyer
to specify the fresh date of delivery or to ask for amendment of the
letter of credit. The next letter thereafter is dated 15th November, 1989. -·
The seller did not say in this letter that pursuant to what had been
H stated by it in message dated 8th November, 1989 the Ships had
AROSAN ENTERPRISES LTD. v. U.O.l. [BANERJEE, J.] 637
entered Indian waters and as such the buyer should incorpor~te fresh . A
date of delivery and amend the letter of credit so that shipping
documents could be furnished by seller to the buyer and that without
these amendments the bank may not pay the amount covered by the
letter of credit. On the other hand, the seller in the letter dated 15th
November, 1989 stated that the cargo had gone out of its control and B
fresh cargo would be arranged which will be arriving at Indian port
... within a few days. The seller asked for minimum 15 days time to
supply the cargo and requested for delivery period being extended
upto 30th November, 1989 with consequential amendments in the
letter of credit for acceptance of the documents. The buyer was not
obliged in law to extend the delivery period. The silence on the part C
of the buyer by not sending reply to the letter dated 15th November,
1989 and also not sending any reply to the subsequent_letters dated
20th November, 1989, 24th November, 1989, 4th December, 1989 and
20th December, 1989 only shows that the buyer was not willing to
extend delivery period after 15th November, 1989. The sugar was
required for the urgent need ofDussehra/Diwali festivals of November, D
1989 and the supply not having been made till 14th/15th November,
1989 the buyer was justified in not extending the delivery period.
Turning now on to the issue of duty to speak, can it be said that silence
on the part of the buyer in not replying to the letters dated 15th November, E
1989, 20th November, 1989, 24th November, 1989, 4th December, 1989 and 20th
December, 1989 only shows that the buyer was not willing to extend the
delivery period after 15th November, 1989 - the answer cannot but be in the
negative, more so by reason of the fact that fixation of a second delivery date
by the Appellate Bench of the High Court as· noticed above cannot be termed
to be in accordance with the law. There was, in fact, a duty to speak and F
failure to speak would forfeit all the rights of the buyer in terms of the
Agreement. Failure to speak would not, as a matter of fact, jeopardise the
sellers interest neither the same would authorise the buyer to cancel the
contract when there has been repeated requests for acting in terms of the
agreement between the parties by the seller to that effect more so by reason O
of a definite anxiety expressed by the buyer as evidenced in the intimation
dated 8th November, 1989 and as found by the Arbitrator as also the Learned
Single Judge.
As noticed above, the entire judgment of the Appellate Bench proceeds
on the basis of certain presumptions, we are afraid however that reliance H
638 SUPREME COURT REPORTS (1999] SUPP. 2 S.C.R.
A thereon cannot but be tenned to be fallacious for inter alia the reasons
mentioned herein below:
''
(a) The first le.tter of cancellation of contract was received by the
seller on 9th November, 1989 after issuance of both the seller's
telex dated 8.11.89 and 9.11.89 to the buyer and therefore the
... B same could not amount to representations against the cancellation
as is being held by· the Appellate Court.
(b) The observation of the Appellate Bench pertaining to the ..;,;.
amendment of the delivery date in the letter of credit (i.e. upto
29th January, 1990) does seem to be erroneous in the contextual
c facts of the matter under consideration". The date of delivery was
specific in the letter of credit itself and in the event of non-
delivery within the period, there might be some complications
and as such request for extension of deli~ery date was made
though however, without any response from the buyer's end,
when, in fact, the conduct itself shows that the delivery date as
D mentioned in the letter of credit was not adhered to and the
parties were ad-idem on the score of extension.
(c) The letter of withdrawal of cancellation in any event does not
refer to any representation and nor does it fix any date of
delivery as has been so thought of by the High Court. The
E Appellate Court's presumption as to the fixation of the delivery
date being 14th/15th November, 1989 in the nonnal course of
event and had it been so, there would have been an express
intimation .from the buyer of such a specific extension.
(d) Diverse intimations as noticed above from the seller's end to the
F buyer, went unattended and not one letter was sent in reply
thereto recording therein that 14th/15th November, 1989 ought
to be the fresh date of delivery.
(e) When the contract was finally cancelled on 25th Januaiy, 1990,
the Respondents stand was that the delivery date breached by
G the claimant.was 31st October, 1989 and not 14th/15th November,
1989 as has now been fixed by the Appellate Bench of the High
Court.
(t) The Appellate Bench, in fact, has not been able to appreciate the
importance of the date of delivery in the letter of credit specially
H in an international commercial contract, since without the date
AROSAN ENTERPRISES LTD. v. U.O.l. [BANERJEE, J.] 639
-
of delivery being altered in the letter of credit itself and the bank A
being informed accordingly, question of release of any amount
to the seller by their bank would not arise.
(g) The Appellate Bench as a matter of fact has gravely erred in
having an implied delivery date when the parties in fact did not
stipulate at any point of time such a date. B
Let us now at this juncture consider this aspect of the matter in slightly
greater detail. The irrevocable letter of credit was issued by the Indian Overseas
Bank, Janpath favouring the Appellant herein for $ 27,840,000 drawn on
applicants for credit at site for 100% invoice value covering shipment of 58000
million tonnes net weight, plus/minus 5% to be packed in Polylined jute bags C
of 50 kgs net weight "accompanied by the following documents". The letter
of credit by itself records that the name of the Indian Port would be advised
by the Government by means of an amendment to the credit and it further
records that the credit is valid for negotiation upto three months from the date
of letter of credit subject to negotiation within 21 days from the date of report
of Independent/Joint Surveyor referred to in clause 5 of the documents. D
These documents include inter alia the following:
(a) Beneficiary certificate to the effect that all the terms and conditions
of the contract dated October, 24, 1989 and its annexures between
beneficiary and the applicants for the credit, have been fully
complied with - one original and two copies. E
(b) Certificates of inspection of quality, weight and packing in original
and 5 copies; at the ports of discharge signed and issued by the
applicants for the credit at the cost of the beneficiary, based on
minimum 5 random sampling and 5 check weightment certifying
(a) quality. · F
(c) Photocopy of the signed contract between beneficiary and
applicants for the credit
(d) Documents with discrepency should not be negotiated without
banks prior approval.
Incidentally, be it noted that the contract itself envisaged appointment G
of a Surveyor. Clause 9 of the Agreement provides:
"9. Inspection/survey at load port(s)
The quality, quantity and packing at the load port(s) shall be
supervised and certified by independent surveyors nominated by the H
640 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A Buyer at Sellers cost. The certificate of such nominated surveyors
based on· not less than 5 random sampling and 5 ch~ck' weightment
shall be final. The report of such surveyors shall, inter-alia, cover the
following."
"Load ports in Clause 9 above was subsequently amended to the port
B of discharge, the clause however, envisages the. appointment of an independent
Surveyor nominated by the buyer at the sellers cost and report of the surveyor
is of considerable importance since the contract itself provides the far of
activities of the Surveyors and the coverage under the Certificate and the
same are:
C (i) Cleanliness and fitness of the holds of vessel for receiving sugar
prfor to commencement of loading;
(ii) Quality and specifications;
(iii) Weight gross and net;
D (iv) Packing
(v) Total number of bags;
(vi) Arkings
(vii) Date of commencement and completion of leading
E (viii) Radioactivity-free certificate
(ix) Current crop of country of origin, mentioning crop years
(x) Load Rate
(xi) LOA/BEAM and
F (xii.) Arival Draft"
Whilst on the subject of documentary evidence and the presumption of
the Appellate Bench as regards the fixation of date of delivery, it would be
convenient to note the Shipment as also Price Clause in the Agreement. The
Shipment Clause reads as below:
G
"3. Shipment Period: Sellers shall arrange shipment quantity so as to
reach Indian Ports basis coast as per Clause 4(i) not later than 31st
October, 1989. Date of tendering notice of readiness of the vessel as
per clause 13(vii) here of shall be the date of delivery period. Shipment
within contract delivery period is of the essence of this contract. In
H case of any delay in reaching the shipments before the delivery period
AROSAN ENTERPRISES LTD. v. U.O.I. [BANERJEE, J.] 641
at Indian Port, it is clearly understood that except for the reasons of A
force majeure, the s,ller will be deemed to be in contractual default/
and the buyer will have the absolute right to cancel the contract at
the cost and risk and responsibility of the seller and claim for damages,
costs, losses, expenses to from the seller. The Buyer, may however,
extend the delivery period at a discount as may be mutually agreed B
to between the Buyer and the Seller. Any cargo(es), under-loading/
afloat on the date of this contract cannot be supplied."
The Price Clause reads as below:
"4. Price
c
I. In polylined jute bags, per metric tonne net weight, cost, insurance
and freight, free out, one safe Indian port at Buyer's option.
US 480.00 PMT
(US DOLLARS FOUR HUNDRED EIGHTY ONLY) PERM T. D
,. In case sugar is shipped in Polylined polypropylene bags, the above
price will be subject to a discount of US 2.00 per metric tonne net
weight of full cargo. The above price is based on discharge at one
safe Indian port at Buyer's option, on the west Coast if the vessel
carrying sugar is coming from the West of ·India, or on the East E
Coastal vessel carrying sugar is coming from the East of India for this
purpose. Tuticorin will be considered as a West Coast Indian port.
II. Opposite Coas! Discharge
The Buyer has the option to discharge the sugar at a port on the coast F
other than the basis coast as per Clause 4( I) above by paying additional
charges @ US$ 1.50 on the net weight of the full cargo.
III. Two Port Discharge
G
Buyer has the option to ·discharge the sugar at two ports on any one
coast for which the Buyer shall pay additional charges US $ 1.50 PMS
- on the net weight of full cargo. In case the second discharge port is
Calcutta or Haldia, the Buyer shall pay additional charges US $ 2.00
PMS on the net weight of full cargo instead of US $ l .50 PMS. For
discharge at two ports on the coast other than the basis coast as per H
----;
642 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A Clause No.4(1.) above, the additional charges for two port discharge
payable under this clause shall be over and above that payable under
Clause No.4(ii) above."
It needs to be noted here that the Clause as regards any cargo being
under-loading/afloat on the date of the contract has been subsequently deleted.
B The contract term as regards the shipment period expressly provide thus that
c
the Shipment should reach Indian ports not later than 31st October, 1989 but
the issue is whether in the contextual facts time was the essence of the
contract and in the event the answer is in the affirmative, then and in that
event whether there was subsequent extension of time and what is the effect
therefor. Herein before in this judgment we did refer to the effect of subsequent
extension, but the issue as regards the factum of the time being the essence
-L
of the contract was left to be dealt with at the _later stage and as such, it would
be convenient to note the same at this juncture. Clause 3 of the Agreement
namely the Shipment period expressly records that Shipment within contract
delivery period was of the essence of the contract and it was clearly understood
D between the parties that except for reasons of force majeure the Seller would
be deemed to be in default and buyer would have the absolute right to cancel·
the contract at the cost, risk and responsibility of the seller. This particular
clause however itself provided that the buyer may however extend the delivery
period at a discount to be mutually agreed to between the buyer and the
E seller: the contract therefore, envisaged specifically an extension of the period
on a mutually agreed term. The Price Clause also is of some relevance in the
..
matter of appreciation of the Agreement between the parties vis-a-vis the
time. Clause 4 (ii) records that the buyer had the option to discharge the sugar
at a port on the coast, other than the basic coast by paying additional charge
and in terms of Clause 4(iii) the buyer had the option to discharge the sugar
F at two ports upon payment of additional charge. It is therefore, apparent that
different rates have been provided for different ports and specific naming of
the port is thus required before delivery is expected in the matter. On the wake
of this factual detail as appears from the record and by reason of non-
fulfilment of the buyers' obligations in terms of the agreement, can it be said
that the time was the essence of the contract? In our view the answer to this .....
G all important question is in the negative. The contract itself provides reciprocal
obligations and in the event of non-fulfilment of some such obligations and
which have a direct bearing onto them - strict adherence of the time schedule
or question of continuing with the notion of the time being the essence of
the contract would not arise. The obligations are mutual and the terms of the
H agreement are inter-dependent on each other.
-
AROSAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, J.] 643
Incidentally, paragraph 761 of Halsbury's Laws of England (4th Ed. A
Vol.41) seems to be very apposite in this context. The passage reads as below:
"761. Place of Delivery uncertain. Where the place of delivery is not
indicated by the contract , and is within the option of the seller or of
the buyer respectively, it is a condition precedent to the liability of
the buyer or of the seller respectively to accept or to deliver the B
goods that he should receive notice of the place of delivery."
If any credence is to be given to the above noted passage in Halsbury's
Laws of England being read with the terms of the contract, we do not find
any justification for the Appellate Bench of the High Court to come to a
conclusion that in fact time was the essence of the contract, since the C
condition precedent has not yet had taken place, neither the requirement of
appointment of Surveyor has been complied with: the contract ought to be
read with the time clause but subject however to certain other conditions. The
essential point is that the seller must be instructed in accordance with the
terms of the contract as to the way in which he can perform his duty in terms D
of the agreement and effect delivery upon the goods being put on board -
In the event the Port of Discharge is not named -can the goods be put on
board or can the seller be made responsible for his failure to put the goods
on board? The answer cannot but be in the negative. In the contextual facts,
the goods were on the high seas and to be diverted to the Ports of India,
shortly, as such nomination of the port, was an essential requirement, in order E
to make the seller liable for breach and entitlement of the buyer to claim
damages. In this context a passage from Benjamin's Sale of Goods Act (4th
Edition) seems to be rather appropriate: Paragraph 20-040 reads as below:
"The essential point is that the seller must be instructed, in accordance F
with any relevant terms of the contract, as to the way in which he can
perform his duty to put the goods on board. If no shipping instructions
are given, or if shipping instructions are not given within the time
allowed by the contract, the seller is not liable in damages for non-
delivery; and the buyer is liable in damages for non-acceptance."
Mere fixation of a period of delivery or a time in regard thereto does not
G
by itself make the time as the essence of the contract, but the agreement shall
have to be considered in its entirety and on proper appreciation of the intent
and purport of the clauses incorporated therein. The state of facts and the
relevant terms of the Agreement ought to be noticed in its proper perspective
so as to assess the intent of the parties. The Agreement must be read as a H
644 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A whole with corresponding obligations of the parties so as to ascertain the true
intent of the parties. In the instant case, the Port of Discharge has not been
named neither the Surveyor is appointed - without whose certificate, question
of any payment would not arise - can it still be said that time was the essence
of the contract, in our view the answer cannot but be a positive 'No'.
B Mr. Dholakia, the learned Senior Advocate as also Mr. Rawal, the
learned Additional Solicitor General, appearing for FCI and Union of India
respectively, strongly contended that the express words to the effect that the
delivery ought to be effected by 31st October, 1989 ought to be taken with
proper sanctity and the party be held responsible for not effecting delivery
C within the time stipulated in the Agreement and in this context strong reliance
was placed on the decision of this Court in the case of China Cotton
Exporters v. Bihari/al Ramcharan Cotton Mills Ltd, AIR (1961) SC .1295. We
are afraid however, that reliance on the decision of this Court in China Cotton
Case (supra) is totally misplaced. This Court in the above noted decision was
considering the true effect of the word "therefore'', which is totally absent
D here. For convenience sake however, paragraph 6 of the judgment is noted
herein below:
"6. We find thus that whatever may have been said earlier in the
printed portion of the contract the parties took care, after specifying
"October/November, 1950" as the date of shipment to make a definite
E
condition in the remarks column, on the important question whether
the shipment date was being guaranteed or not and if SO, to what
extent. The words are: "This contract is subject to import licence, and
therefore the shipment date is not guaranteed." Remembering, as we
must, that in commercial contracts, time is ordinarily of the essence
F of the contract and giving the word "therefore" its natural, grammatical
meaning, we must hold that what the parties intended was that to the
extent that delay in shipment stands in the way of keeping to the
shipment date October/November, 1950, this shipment date was not
guaranteed; but with this exception shipment October/November, 1950,
was guaranteed. It has been strenuously contended by the learned
G Attorney-General, that the parties were mentioning only one of the
many reasons which might cause delay in shipment and the conjunction
"therefore" was used only to show the connection between one of the
many reasons - by way of illustration and a general agreement that
the shipment date was not guaranteed. We do not consider this
H explanation of the use of "therefore" acceptable. If the parties intended
AROSAN ENTERPRISES LTD. v. U.O.I. [BANERJEE, J.] 645
that quite apart from delay in obtaining import licence, shipment date A.
was not guaranteed, the natural way of expressing such intention -an
intention contrary to the usual intention in commercial contracts of
treating time as the essence of the contract -would be to say: "This
contract is subject to import licence and the shipment date is not
guaranteed." There might be other ways of expressing the same
intention, but it is only reasonable to expect that anybody following B
the ordinary rules of grammar would not use "therefore" in such a
context except to mean that only to the extent that delay was due to
delay in obtaining import licence shipment time was not guaranteed.
The decision in China Cotton Exporter's (supra) cannot possibly thus C
lend any assistance in the contextual facts of the matter in issue. The facts
being, totally different and is thus clearly distinguishable. Further reliance
was placed by the Respondent in the decision of this Court in the case of
/. T.C. Ltd. v. Debt Recovery Appellate Tribunal and Others, [1998] 2 SCC 70
wherein this Court relying upon the decision in the case of U.P. Co- operative
Federation Ltd. v. Singh Consultants and Engineers (P) Ltd., [1988] 1 SCC D
174) observed in paragraph 17 of the report as below:
"17. lt is now well settled that the question whether goods were
supplied by the appellant or not is not for the Bank. This point has
already been decided by the decision of this Court in UP. Coop.
Federation case referred to above. In that case it was stated (at p.193) E
by Jagannatha Shetty, J. as follows: (SCC para 45)
"The bank must pay if the documents are in order and the terms
of credit are satisfied. The bank, however, was not allowed to
determine whether the seller had actually shipped the goods or F
whether the goods conformed to the requirements of the contract.
Any dispute between the buyer and the seller must be settled
between themselves. The courts, however, carved out an
exception to this rule of absolute independence. The courts held
that if there has been "fraud in the transaction" the bank could
·-· dishonour beneficiary's demand for payment. The courts have G
generally permitted dishonour only on the fraud of the beneficiary,
not the fraud of somebody else." (emphasis supplied)
-· It will be noticed from the italicised underlined portion in the above
passage that there will be no cause of action in favour of the bank
in cases where the seller has not shipped the goods or where the H
646 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A goods have not conformed to the requirements of the contract. The
Bank, in the present case before us, could not, by merely stating that
there was non-supply of goods by the appellant, use the words "fraud
or misrepresentation" for purposes of coming under the exception.
The dispute as to non-supply of goods was a matter between the
seller and buyer and did not, as stated in the above decision, provide
B any cause of action for the Bank against the seller."
Reliance was also placed to the Law of Bankers' Commercial Credits
by Gutteridge and Megrah wherein the authors stated that:
"Banks issuing irrevocable credits subject to the Uniform Customs are
c not concerned with the sales contract or the goods; if it were otherwise
credit business would be impossible. In law the credit contract stands
by itself and is not to be interpreted to the point of amendment or
augmentation by reference to the contract of sale or to any external
document."
D The authors further laid emphasis on the General Provision (C) of the
Uniform Customs which states that:
"(c) Credits, by their nature, are separate transactions from the sales
or other contracts on which they may be based and banks are in no
way concerned with or bound by such contracts."
E
Further emphasis was also laid by authors on Article 8(a) which provides
that:
"(a) In documentary credit operations all parties concerned deal in
documents and not in goods."
F
Relying on the above, it was cqntended that the plea as raised by the
Appellant that the amendment to the letter of credit is a requirement in order
to obtain payment cannot but be termed to a myth and as such should not
be relied upon - while it is true that the documents by themselves make and
G create a separate agreement with the Bank, and the Bank cannot possibly
raise any dispute in regard thereto as to whether the goods are actually been
supplied or not, but two factors ought to be kept in mind apart from what we
have stated herein before in this judgment. The first being, to facilitate
payment it is better to have the extended delivery date on the letter of credit
itself by way of an amendment, so as to a\oid any future complication. This
H is not a rule of law or a requirement of law but a matter of prudence. The
ARO SAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, J.] 647
second aspect is the counter guarantee of the Nova Scotia Bank. The counter A
guarantee also stipulates the delivery date and in the event of some queries
raised in regard thereto, the party in whose favour such a letter of credit
stands, would be put to unnecessary and frivolous litigation for no fault of
the beneficiary. As noticed above it is not a requirement of law but a matter
of prudence. No exception can possibly be taken to the views expressed by B
this Court in ITC's case or the statement in the Law of Bankers' Commercial
Credits. Be it further noted that substance of both citations noticed above is
the enforceability of the letter of credit by way of a separate transaction, in
any event, that would mean and imply litigation in the event of there being
any issue raised as regards the delivery period. Parties ought not to be
allowed to be plunged into litigation, as such both the citations do not have C
any relevance apropos the submission made by the Appellants herein. Apart
therefrom and in any event in the matter of compliance of the tenns and
conditions of letter of credit, reference of a delivery date is a requirement
since the original contract stood incorporated in the letter of credit itself and
the delivery date being shown therein as 31st October, 1989. The requirement
of a certificate that original contract has been fully complied with, makes it D
necessary that the delivery for the purpose of the contract had to be extended
since the original date by reason of efflux of time has lapsed. The learned
Single Judge of the High Court looked at the matter from another point Of
view as well and he observed:
E
"Looking at it from another angle, if amendment in the letter of credit
was not necessary, the respondents should say so in reply to the
various letters of the claimants in this connection ... ."
Whether the Respondents should have said it or not as observed by
the learned Single Judge, but the fact remains that there was total silence and F
nothing prevented them from stating that such an endorsement either is or
is not required but as noticed above, the Respondents herein has maintained
delightful silence on that score.
In the premises it would thus be safe to conclude that by reason of the G
non-fulfillment of the three conditions as noted above, que·stion of time being
the essence of the contract would not arise and as such delivery was to be
expected within a reasonable time but before the expiry of the reasonable time,
diverse letters were sent asking for details but the buyer maintained total
silence when there was a duty to speak as noted above. The Appellate
Court's finding that the contract stood extended upto 14th/15th October, 1989 H_
648 SUPREME COURT REPORTS (1999] SUPP. 2 S.C.R.
A does not have any factual support and as such totally .unwarranted and thus
cannot be sustained. For the self - same reason the finding of the Appellate
Court as regards the issue of law, warranting intervention of the High Court
. vis-a-vis the award, cannot also be sustained. This is apart from the fact that
it is a factual issue upon proper reading of the material documents on record.
In any event upon coming to a conclusion that facts detail out in the judgment
B (under Appeal) unmistakably record that a new date of delivery is available
on record - Question of the same being an issue of law does not arise in the
facts of the matter under consideration. The letter of the Government oflndia
dated 11.11.89 stated that the matter has since been reconsidered and the
letter of cancellation stands withdrawn though however, without prejudice !O
C rights and contentions of the Government but there was as a matter of fact,
reconsideration of the entire issue and it is only on that basis that the letter
of cancellation was withdrawn. The facts depict that on 15th November, 1989,
an intimation was sent by the Appellants to FCI stating that due to the
cancellation, the cargo already arranged for, has gone out of control and a
new cargo was being arranged. In the same letter the Appellant further asked
D for fixation of a new date of dellvery and to make consequential amendment
for acceptance of documents under the letter of credit by the Bank but no
reply is sent. Letters of reminders have been sent again on 20th November,
1989, 24th November, 1989 but without any response whatsoever and
subsequently the cancellation came in January, 1990 as noticed above,
E forfeiting the performance Bank Ouarantee by FCI. In that view of the matter,
question of the time being the essence would not arise in the contextual facts.
More so by reason of the fact that the cargo was a cargo afloat on the High
seas .
Turning attention on to the other focal point, namely the interference
F of the court, be it noted that Section 30 of the Arbitration Act, 1940 providing
for setting aside an award of an arbitrator is rather restrictive in its operation
and the statute is also categorical on that score. The use of the expression
'shall' in the main body of the Section makes it mandatory to the effect that
the award of an arbitration shall not be set aside excepting for the grounds
G as mentioned therein to wit: (i) arbitrator or umpire has misconducted himself;
(ii) ·award has been made after the supersession of the arbitration or the
proceedings becoming invalid; and (iii) award has been improperly procured
or otherwise invalid.
The above noted three specific provisions under Section 30 thus can
H only be taken recourse to in the matter of setting aside of an award. The
AROSAN ENTERPRISES LTD. v. U.0.1. [BANERJEE, J.] 649
legislature obviously had in its mind that the Arbitrator being the judge A .
chosen by the parties, the decision of the Arbitrator as such ought to be final
between the parties.
Be it noted that by reason of a long catena of cases, it is now a well
settled principle of law that reappraisal of evidence by the court is not
permissible and as a matter offact exercise of power by the Court to reappraise B
the evidence is unknown to a proceeding under Section 30 of the Arbitration
Act. In the event of there being no reasons in the award, question of
interference of the court would not arise at all. In the event, however, there
are reasons, the interference would still be not available within the jurisdiction
of the Court unless of course, there exist a total perversity in the award or C
the judgment is based on a wrong proposition of law: In the event however
two views are possible on a question of law as well, the Court would not be
justified in interfering with the award.
The common phraseology 'error apparent on the face of the record'
does not itself, however, mean and imply closer scrutiny of the merits of D
documents and materials on record: The court as a matter of fact, cannot
substitute its evaluation and come to the conclusion that the arbitrator had
acted contrary to the bargain between the parties. If the view of the arbitrator
is a possible view the award or the reasoning contained therein cannot be
examined. In this context, reference may be made to one of the recent decision E
of this Court in the case of State of Rajasthan v. Puri Construction Co. Ltd.,
[1994] 6 SCC 485 wherein this court relying upon the decision of Sudarsan
Trading Co. 's case Sudarsan Trading Co. v. Government of Kera/a and Anr.,
[ 1989] 2 SCC 3 8, observed in paragraph 31 of the Report as below:
"A court of competent jurisdiction has both right and duty to F
decide the lis presented before it for adjudication according to the
best understanding of law and facts involved in the lis by the judge
presiding over the court. Such decision even if erroneous either in
factual determination or application of law correctly, is a valid one and
binding inter partes. It does not, therefore, stand to reason that the G
arbitrator's award will be per se invalid and inoperative for the simple
reason that the arbitrator has failed to appreciate the facts and has
committed error in appreciating correct legal principle in basing the
award. An erroneous decision of a court of law is open to judicial
review by way of appeal or revision in accordance with the provisions
of law. Similarly, an award rendered by an arbitrator is open to challenge H
650 SUPREME COURT REPORTS (1999] SUPP. 2 S.C.R.
- A within the parameters of several provisions of the Arbitration Act.
Since the arbitrator is a judge by choice of the parties and more often
-"'-
than not a person with little or no legal background, the. adjudication
of disputes by an arbitration by way of an award can be challenged ;,..
only within the limited scope of several provisions of the Arbitration ',
B
Act and the legislature in its wisdom has limited the scope and ambit
of challenge to an award in the Arbitration Act. Over the decades,
judicial decisions have indicated the parameters of such challenge
consistent with the provisions of the Arbitration Act. By and large
~
I-
'
..
.
-
the Courts have disfavoured interference with arbitration award on
account of error of law and fact on the score of misappreciation and
c misreading of the materials on record and have shown definite
inclination to preserve the award as far as possible. As reference to r
arbitration of disputes in commercial and other transactions involving I
substantial amount has increased in recent times, the Courts were
impelled to have fresh look on the ambit of challenge to an award by
the arbitrator so that the award does not get undesirable immunity. In
D ,----
recent times, error in law and fact in basing an award has not been
given the wide immunity as enjoyed earlier, by expanding the import J
and implication of "legal misconduct" of an arbitrator so that award
by the arbitrator does not perpetrate gross miscarriage of justice and
the same is nqt reduced to mockery of a fair decision of the lis \
between the parties to arbitration. Precisely for the aforesaid reasons, \
E ~
the erroneous application of law constituting. the very basis of the
award and improper and incorrect findings of fact, which without
closer and intrinsic scrutiny, are ·demonstrable on the face of the
materials on record, have been held, very rightly, as legal misconduct
rendering the award as invalid. It is necessary, however, to put a note
F of caution that in the anxiety to render justice to the party to arbitration,
the court should not reappraise the evidences intrinsically with a
close scrutiny for finding out that the conclusion drawn from some
facts, by the arbitrator is, according to the understanding of the court,
erroneous. Such exercise of power which can be exercised by· an
appellate Court with power to reverse the finding of fact, is alien to
G
the scope and ambit of challenge of an award under the Arbitration
Act. Where the error of finding of facts having a bearing on the award
is patent and is easily demonstrable without the necessity of carefully
weighing the various possible viewpoints, the interference with award "\
based on erroneous finding of fact is permissible. Similarly, if an award
H is based by applying a principle of law which is patently erroneous,
AROSAN ENTERPRISES LTD. v. U.0.1. (BANERJEE, J.] 651
and but for such erroneous application of legal principle, the award A
could not have been made, such award is liable to be set aside by
holding that there has been a legal misconduct on the part of the
arbitrator. In ultimate analysis it is a question of delicate balancing
between the permissible limit of error of law and fact and patently
erroneous finding easily demonstrable from the materials on record B
and application of principle of law forming the basis of the award
which is patently erroneous. It may be indicated here that however
objectively the problem may be viewed, the subjective element inherent
in the judge deciding the problem, is bound to creep in and influence
the decision. By long training in the art of dispassionate analysis,
such subjective element is, however, reduced to minimum. Keeping C
the aforesaid principle in mind, the challenge to the validity of the
impugned award is to be considered with reference to judicial decisions
on the subject."
It is on the basis of this well settled proposition that the learned Single
Judge came to a conclusion that the findings of the Arbitrators in regard to D
the extension of delivery period and failure to fix the fresh date has resulted
in breach of the contract on the part of the Government and the same being
purely based on appreciation of material on record by no stretch it can be
termed to be an error apparent on the face of the record entitling the court
to interfere. The Arbitrators have, in fact, come to a conclusion on a closer E
scrutiny of the evidence in the matter and re-appraisal of evidence by the
Court is unknown to a proceeding under Section 30 of the Arbitration Act.
Re-appreciation of evidence is not permissible and as such we are not inclined
to appraise the evidence ourselves sa'!"e a11d except what is noticed herein
before pertaining to the issue as the time being the essence of the contract.
In this context, reference may be made to a decision of this Court in the case F
of M Chellappan v. Secretary, Kera/a State Electricity Board and Anr.,
[197 5] l SCC 289. Mathew, J. speaking for the Three Judge Bench in paragraph
12 and 13 observed as below:
"12. The High Court did not make any pronouncement upon this
question in view of the fact that it remitted the whole case to the G
arbitrators for passing a fresh award by its order. We do not think that
there is any substance in the contention of the Board. In the award,
the umpire has referred to the claims under this head and the arguments
of the Board for disallowing the claim and then awarded the amount
without expressly adverting to or deciding the question of limitation. H
652 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
A From the findings of the umpire under this head it is not seen that
these claims were barred by limitation. No mistake of law appears on
the face of the award. The umpire as sole arbitrator was not bound
to give a reasoned award and if in passing the award he makes a
mistake of law or of fact, that i~ no ground for challenging the validity
of the award. It is only when a proposition of law is stated in the
B award and which is the basis of the award, and that is erroneous, can
the award be set aside or remitted on the ground of error of law
apparent on the face of the record:
Where an arbitrator makes a mistake either in law or in fact in
determining the matters referred, but such mistake does not appear on
c the face of the award, the award is good notwithstanding the mistake,
and will not be remitted or set aside.
The general rule is that, as the parties choose their own arbitrator to
be the judge in the disputes between them, they cannot, when the
D award is good on its face, object to his decision, either upon the law
or the facts., (see Russell on Arbitration, 17th ed., p.322).
13. An error of Jaw on the face of the award means that you can find
in the award or a document actually incorporated thereto, as for
instance, a note appended by the arbitrator stating the reasons
E for his judgment, some legal proposition which is the basis of
the award and :which you can then say is erroneous (see Lord
Dunedin in Champsey Ehara & Co. v. Jivraj Baloo Co.). In
Union of India v. Bungo Steel Furniture Pvt. Ltd., this Court
adopted the proposition laid down by the Privy Council and
applied it. The Court has no jurisdiction to investigate into the
F merits of the case and to examine the documentary and oral
evidence on the record for the purpose of finding out, whether
or not the arbitrator has committed an error of law."
In any event, the issues raised in the matter on merits relate to default,
G time being the essence, quantum of damages - these are all issues of fact,
and the Arbitrators are within their jurisdiction to decide the issue as they
deem it fit - the Courts have no right or authority to interdict an award on
a factual issue and it is on this score the Appellate Court has gone totally
wrong and thus exercised jurisdiction which it did not have. The exercise of
jurisdiction is thus wholly unwarranted anti the High Court has thus exceeded
H its jurisdiction warranting interference by this Court. As regards issues of fact
AROSAN ENTERPRISES LTD. v. U.O.I. [BANERJEE, J.] 653
as noticed above and the observations made herein above obtains support A
from a judgment of this Court in the case of Olympus Superstructures Pvt.
ltd v. Meena Vijay Khetan & Ors., [1999] 5 SCC 651. Before we conclude one
significant feature ought to be noticed. Admittedly, a meeting was held
between the claimants and the Minister of Food and Civil Supply and according
to the claimant, it was agreed that on the claimants paying a sum of Rs.5 lakhs B
towards expenses incurred by the Government in opening the Letter of Credit
, and on the claimants giving up any claim for damages, the Performance Bank
Guarantee would be released. While some discrepancy arise pertaining to the
meeting in regard to the above subject but the subsequent evidence disclosed
as ·appears from the record of the Arbitrators that the Appellants herein
purchased a Bank Draft for Rs.5 lakhs from the State Bank of India and took C
it to the office of Government of India on 27th November, 1989 but it was not
accepted. The Arbitrators as appears summoned relevant file of the Government
which was produced and the reasoned award contain the following:
"During the cross examination of Shri S.K. Swamy the note made in
this file by the Minister referred to by S. Santokh Singh was vertabim D
repeated in the question but to the witness Shri Swamy on 8th May,
199 l. How the claimants got the verbatim text of this note, if the file
was privileged, is not clear, but what we found was that the note of
the Minister on the file was exactly in the same words as the question
put to Mr. Swamy in .his cross examination dated 8.5.91. All facts E
stated by S. Santokh Singh are mentioned in this note. This part of
the statement of S. Santokh Singh is thus sufficiently corroborated by
this note and S. Santokh Singh has also produced the draft for
Rupees five lakh mentioned by him in his statement."
This aspect of the matter has also been totally overlooked by the
1
F
Appellate Bench of the High Court. Needless to record that two Arb itrators
Hon'ble Mr. Justice S.N. Shankar, a retired Chief Justice of the Orissa High
Court and Shri K.C. Diwan, Senior Advocate upon appraisal of evidence and
have considered the matter in its entirety and in proper perspective. As such,
the question of interference with the Arbitral Award does not and cannot
arise. In that view of the matter, these Appeals succeed. The order of the G
Appellate Bench of the High Court stand set aside and the order of the
learned Single Judge of the Delhi High Court stands restored. Each party
however to bear its own cost.
N.J. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.