M/S. ANGEL BABY PRODUCTS PVT. LTD.versusNEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY
- Citation
- 2010 INSC 743
- Decided
- 27 October 2010
- Disposal
- Dismissed
- Bench
- ALTAMAS KABIR
Holding
The Supreme Court dismissed the Special Leave Petition, upheld the imposition of penalty and interest, but directed that the two‑month extension period be excluded from the calculation of the payable amount.
Summary
The petitioners, Angel Baby Products Pvt. Ltd. and Hira Lal Gupta, failed to execute a lease deed for a commercial plot allotted by NOIDA within the 120‑day period, citing mis‑description of the plot and a municipal drain, and sought a waiver of the penalty. The Chief Executive Officer of NOIDA waived the penalty and granted an additional two‑month extension for completing the change of allottee’s name, but the Officer on Special Duty later imposed penalty and interest, interpreting the extension as only for constitutional change. The petitioners challenged the imposition of penalty and the officer’s interpretation before the High Court, which dismissed the writ petition and upheld the penalty. On appeal, the Supreme Court held that the petitioners’ conduct showed no intention to complete the lease formalities and that the officer’s order, though based on a misunderstanding, did not invalidate the penalty, directing that the two‑month extension period be excluded from the penalty calculation. Consequently, the Special Leave Petition was dismissed, leaving the penalty and interest payable.
Issues considered
- Whether the penalty for failure to execute the lease deed within the stipulated period is payable despite the CEO's waiver.
- Whether the two‑month extension granted for change of constitution also waives the penalty.
- Whether the Officer on Special Duty's interpretation of the CEO's order is legally valid.
- Whether the High Court's dismissal of the writ petition should be interfered with.
- How the penalty and interest should be calculated, particularly concerning the two‑month extension period.
Subjects
Judgment
[2010] 12 S.C.R. 1073
M/S. ANGEL BABY PRODUCTS PVT. LTD. A
v.
NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY
& ORS.
(Special Leave Petition (Civil) No. 10940 of 2008)
B
OCTOBER 27, 2010
[ALTAMAS KABIR AND A.K. PATNAIK, JJ.]
Lease deed - Execution of - Failure of allottee to
execute lease deed for commercial plot within the stipulated C
period on account of mis-description. of the plot and change
'
in the name of allottee - Imposition of penalty -
Representation for waiver - Extension of time to execute
lease deed - Failure to execute lease deed within the
extended time - Imposition of penalty and interest - Writ D
petition - Dismissed by High Court - On appeal, held: No
inclination on the part of allottee or petitioner company to
complete formalities for execution of lease deed pursuant to
the change in the name of al/ottee - Thus, on account of
subsequent conduct of petitioner company and allottee, order E
of High Court and decision of NO/DA relating to imposition
of penalty and interest not interfered with - Direction issued
to calculate penalty and interest as payable.
'HL' was allotted a commercial plot. He failed to
execute lease deed for the commercial plot within the F
stipulated period of 120 days on account of the mis-
description of the plot, existence of the municipal drain
on the portion of the plot, and in view of the change in
. the name of the allottee. The respondent-New Okhla
Industrial Development Authority imposed penalty for G·
failure to get the lease deed executed. On representation
by 'HL' and another, for waiver of penalty, the Chief
Executive Officer, NOIDA waived the penalty and granted
them further two months' time to complete the execution
1073 H
1074 SUPREME COURT REPORTS [2010] 12 S.C.R.
A of the lease deed. Before the expiry of two months, the
NOIDA authorities wrote a letter to the writ petitioners that
penalty would be charged with effect from 22nd
November, 2001. Again a representation for waiver of
penalty was made and the Board of NOIDA rejected the
B same, calling upon the writ petitions to pay the penalty.
The writ petitioners-'HL' and another, filed a writ petition
for quashing the notices issued by the respondent. The
High Court dismissed the writ petition and vacated the
interim order. Therefore, the petitioner filed the instant
c Special Leave Petition.
Dismissing the Special Leave Petition, the Court
HELD: 1.1 The submissions questioning the order
passed by the Officer on Special Duty dated 11.04.02, and
D the various notices subsequently issued on the basis
thereof, demanding payment of penalty despite the order
of the Chief Executive Officer waiving imposition of such
penalty for the delay in execution of the lease deed,
cannot be accepted. [Para 12] [1081-F]
E
1.2 The materials on record indicate that there had
been correspondence exchanged between the parties
with regard to the land allotted and the area thereof on
account of the existence of the municipal drain either on
F the plot or in its vicinity. 'HL' also made a request for the
plot allotted in his name to be transferred in the name of
the petitioner company in which he and his son were
Directors. Since the same was likely to take some time
for completion of the formalities, a specific prayer was
made to waive the penalty due to delay in the execution
G of the lease deed. The CEO, NOIDA, extended the period
for completion of the formalities relating to the
constitutional change by a period of two months without
penalty from 24.03.02. Before the said period could
expire, the Officer on Special Duty, on a
H misunderstanding of the order passed by the CEO,
ANGEL BABY PRODUCTS PVT. LTD. v. NEW 1075
OKHLA INDUST. DEV. AUTH.
NOIDA, indicated by his order dated 11.04.02, that since A
the Chief Executive Officer had given two months' time
without penalty only for change of constitution, interest
on the outstanding instalments, penal interest .and
penalty, were liable to be recovered from the writ
petitioners. The Officer on Special Duty (G) passed an B
order on 26.04.02, directing that steps be taken in terms
of his earlier order dated 11.04.02, and indicating that two
months' time given to the writ petitioners was for
completion of formalities for change of the name of the
allottee. Up to the said stage, the case of the petitioner C
company for waiver of penalty can be accepted [Para 13]
[1081-G-H; 1082-A-D]
1.3 The subsequent correspondence which followed
between the parties and the failure of the petitioner
company and 'HL' to complete the execution of the lease D
deed even within the extended time of two months,
indicate that neither 'HL' nor the petitioner company had
any inclination to complete the formalities for execution
of the lease deed pursuant to the change in the name of
the allottee from 'HL' to the petitioner company. [Para 14] E
[1082-E-F]
1.4 From the letter dated 1.05.02, written by the
Deputy Manager (C), NOIDA, it is apparent that the
petitioner company and 'HL' were given a great degree
F
of latitude to complete the transaction. In fact, meetings
of the Committee had been convened on 23.10.02 and
26.11.02, in which 'HL' appeared and made submissions
for waiver of the penalty but on the basis of the record,
the Committee rejected the submissions of 'HL' and he
was subsequently informed of the decision of the G
Committee which was approved at a meeting of the
Authority convened on 15.02.03, under the Chairmanship
of the Additional Chief Executive Officer, NOIDA. Even if
initially a case might have been made out on behalf of the
H
1076 SUPREME COURT REPORTS [2010] 12 S.C.R.
A petitioner company that the execution of the lease deed
could not be completed on account of the mis-
description of the plot and in view of the prayer for
change in the name of the allottee, on account of the
subsequent conduct of the petitioner company and 'HL',
8 the order of the High Court or the decision of the NOIDA
relating to imposition of penalty and interest is not
interfered with. However, the interpretation given by the
Officer on Special Duty to the order passed by the CEO
on 24.03.02 is also not accepted and, it is directed that in
C calculating the penalty and interest as payable under the
agreement entered into between the parties, the said
period of two months from the date of the order dated
24.03.02, would be excluded. [Para 15) [1082-G-H; 1083-
A-E]
D CIVIL APPELLATE JURISDICTION : SLP (Civil) No.
10940 of 2008.
From the Judgment & Order dated 9.4.2008 of the High
Court of Judicature at Allahabad in Civil Misc. Writ Petition No.
E 16819 of 2003.
Manish K. Bishnoi for the Petitioner.
Jayant Bhushan, Manish Bishnoi, Amit Bhandari, Sanjeev
Panigrahi, Ravindra Kumar for the Respondents.
F
The Judgment of the Court was delivered by
ALTAMAS KABIR, J. 1. In this Special Leave Petition, the
Petitioner has challenged the decision of the Allahabad High
Court dismissing Writ Petition No.16819 of 2003, filed by one
G Hira Lal Gupta and another praying for quashing of the notices
dated 1.5.2002, 25.7.2002, 6.9.2002 and 22.3.2003 sent by
the authorities of The New Okhla Industrial Development
Authority, hereinafter referred to as 'NOIDA', imposing penalty
against the writ petitioners for failing to get the lease deed for
H commercial plot no.1/1-A, Sector 27, NOIDA, executed within
ANGEL BABY PRODUCTS PVT. LTD. v. NEW OKHLA1077
INDUST. DEV. AUTH. [ALTAMAS KABIR, J.]
the stipulated period of 120 days from the date of allotment of A
the plot. The said plot measuring 2970 sq. meters was initially
allotted to the Writ Petitioner No.1, Hira Lal Gupta, at the rate
of Rs.15,552/- per sq. meter. Later on, a revised allotment order
was issued to Shri Gupta reducing the area of the plot from
2970 sq. meters to 2590 sq. meters and the consideration for B
allotment of the plot was proportionately reduced. Subsequently,
disputes arose in regard to an irrigation drain which existed on
a portion of the said plot, although, the existence thereof was
not indicated in the brochure published by NOIDA. According
to the Writ Petitioners, since the said problem was not attended c
to, the lease deed could not be submitted for execution within
the prescribed period of 120 days which attracted imposition
of penalty.
2. On 24th March, 2002, the Petitioners made a
representation to the Chief Executive Officer, NOIDA, for waiver D
of penalty ori the ground that since the exact area and location
of the plot was different from that specified in the brochure, the
delay in execution of the lease deed could not be attributed to
the Writ Petitioners and, accordingly, penalty could not be
imposed against them. It appears that the Chief Executive E
Officer, NOIDA, waived the penalty imposed on the Writ
Petitioners and granted them further two months' time to
complete the execution of the lease deed. However, before the
expiry of the said period of two months, the NOIDA authorities
had written to the Wpt Petitioners on 1st May, 2002, indicating F
that penalty would be charged with effect from 22nd November,
2001. The Writ Petitioners responded to the said letter by
submitting a representation dated 15th May, 2002, praying for
waiving the penalty on account of the drain passing through plot
and also for providing any alternative plot in lieu of the plot G
already allotted.
3. The Writ Petitioners were informed on 22nd March,
2003, that the Board of NOIDA had rejected their proposal for
waiver of the penalty and that the same would have to be paid
H
1078 SUPREME COURT REPORTS (2010] 12 S.C.R.
A within 30 days, otherwise their allotment would be cancelled.
At the initial stage when the Writ Petition was filed, the High
Court had passed an interim order on 18th April, 2003, staying
the operation of imposition of penalty against the Writ
Petitioners. Ultimately, after considering the submissions made
s on behalf of the respective parties, the High Court took note of
Clause 25 of the Scheme indicating that the plots were to be
sold on "as is where is" basis, leading to the presumption that
the Writ Petitioners had knowledge of the existing irrigation
drain on the plot. The High Court also took note of the power
c reserved to the NOIDA authorities to vary the area of the plot,
which the allottee was bound to accept as final. The High Court
also took into consideration the submissions made on behalf
of the Board of NOIDA that in its 113th meeting held on 10th
February, 2003, the Petitioners' representation was finally
rejected but despite the same they did not deposit the penalty
0
and insisted upon the waiver of penalty and interest.
4. Having arrived at the conclusion that the Writ Petitioners
had knowledge of all the terms and conditions, status, location
and other details about the plot, which was advertised for
E allotment, the High Court felt that there was no merit in the Writ
Petition and dismissed the same. The interim order passed in
the matter was also vacated.
5. Mr. Jayant Bhushan, learned Senior Advocate, who
F appeared for the Petitioner Company, submitted that having
auctioned the plot in question without proper specifications and
contrary to the description in its brochure, it was not within the
competence of the NOIDA authorities to impose penalty on the
Petitioner Company for not completing the execution of the
G lease deed within the stipulated period of 120 days from the
date of allotment. In fact, in the aforesaid background, a
representation was made by Shri Hira Lal Gupta to the Chief
Executive Officer, NOIDA, indicating that he wanted to transfer
the plot in question to the Petitioner Company, wherein he and
his son are Directors. Since the said formalities were likely to
H
ANGEL BABY PRODUCTS PVT LTD. v. NEW OKHLA1079
INDUST. DEV. AUTH. [ALTAMAS KABIR, J.]
take some time, a prayer was made to the aforesaid Authority A
to extend the time for depositing the instalments and for making
the application in Form 37-1. In the same communication, a
further prayer was made to waive the penalty due to the delay
in execution of the lease deed. It is on that basis that Shri Hira
Lal Gupta was granted two months' time, without penalty, for B
completion of formalities.
6. The said extension came to be considered by the
Officer on Special Duty (G), who interpreted the same to mean
that the Petitioner Company had been given two months' time
without penalty only for change of constitution, but that the C
interest on the outstanding instalments, penal interest and
penalty, whatever was outstanding, would have to be recovered,
as it was. On 1st May, 2002, the Deputy Manager (C), NOIDA,
wrote to Shri Hira Lal Gupta in regard to his request for effecting
the change relating to the transfer of the plot to the Petitioner D
Company. In his said letter, the said Authority requested Shri
Gupta to submit the documents indicated in the said letter in
order to effect the change of constitution in regard to the allottee
of the plot in question. In addition, Shri Gupta was informed that
on his failure to complete execution of the lease deed, a sum E
of Rs.62, 18,088.00 had become payable by way of late fee for
the period between 22nd November, 2001 to 30th April, 2002.
Furthermore, after the said period, penalty of Rs.38,863.05 per
day would also be payable. The Petitioner was requested to
deposit the penalty amount for completion of Form 37-1 for F
change of constitution and execution of the lease deed.
7. As indicated hereinabove, the imposition of penalty is
the bone of contention in this Special Leave Petition.
8. Mr. Bhushan reiterated the submissions made before G
the High Court that on 24th March, 2002, when two months'
time had been granted to the Petitioner Company by the Chief
Executive Officer, NOIDA, for completion of the formalities for
change of constitution, the Officer on Special Duty had acted
H
1080 SUPREME COURT REPORTS [2010] 12 S.C.R.
A illegally by passing an order on 11th April, 2002, which was
within three weeks from the date of the order of the Chief
Executive Officer, demanding payment of penal interest and
penalty. Mr. Bhushan contended that during the extended
period of two months, the Officer on Special Duty was not
B entitled to demand payment of penalty when, in fact, payment
of such penalty had been specifically waived by the Chief
Executive Officer.
9. On the other hand, learned counsel for the Respondent
Authority, supported the order of the Officer on Special Duty
C on the ground that the period for execution of the lease had
been extended by a period of two months by the Chief
Executive Officer in view of the prayer made by Shri Hira Lal
Gupta to transfer the allotment in the name of the Petitioner
Company, wherein both he and his son were Directors.
D Learned counsel reiterated the submissions made before the
High Court that the order of the Chief Executive Officer, NOIDA,
extending the time for completion of the execution of the lease
deed would have to be considered in that context only. He urged
that notwithstanding the time extended for completion of
E constitutional changes, the liability for payment of penalty did
not stop on account of the order of the Chief Executive Officer
which continued to remain operative after the expiry of 120 days
from the date of allotment and the Petitioner Company was,
therefore, liable to pay both the penalty charges as also the
F lease rent at the rate of Rs.38,863.05 per day. Mr. Ravindra
Kumar specifically referred to the subsequent order of the Chief
Executive Officer dated 22nd July, 2002, by which he directed
that the land (2590.86 sq. meters) shown in the brochure be
given to Shri Hira Lal Gupta and penalty be recovered as per
G rules. He urged that the effect of the earlier order passed by
the Chief Executive Officer on 24th March, 2002, stood
superseded by the subsequent order, whereby penalty was
directed to be recovered from the Writ Petitioners, according
to the rules.
H
ANGEL BABY PRODUCTS PVT. LTD. v. NEW OKHLA1081
INDUST. DEV. AUTH. [ALTAMAS KABIR, J.]
10. It was also reiterated that since the Petitioner A
Company had decided to invest a huge sum of money in the
allotted land, it is difficult to accept that the Petitioner Company
or its Directors would not have made enquiries as to the nature
of the land which was being allotted to them. In other words, it
has to be held that the Writ Petitioners were fully aware of the B
existence of the municipal drain on the land and absence of
knowledge thereof was nothing but a ploy on the part of the
Petitioner Company to avoid its responsibility regarding
payment of penalty for non-compliance of the conditions to
complete execution of the lease deed within 120 days from the c
date of allotment of the plot. Learned counsel submitted that
the position stood further compounded by the fact that under
Clause 25 of the general terms and conditions spelt out in the
brochure, it was clearly indicated that the allotment of the land
was subject to variations in the area of the plot and that the D
same would have to be accepted by the allottees on "as is
where is" basis.
11. Mr. Ravindra Kumar submitted that no case had at all
been made out for interference with the orders passed by the
High Court dismissing the Writ Petition. E
12. For the reasons hereinafter following, we are unable
to accept Mr. Jayant Bhushan's submissions questioning the
order passed by the Officer on Special Duty dated 11th April,
2002, and the various notices subsequently issued on the basis F
thereof, demanding payment of penalty despite the order of the
Chief Executive Officer waiving imposition of such penalty for
the delay in execution of the lease deed.
13. The materials on record indicate that there had been
correspondence exchanged between the parties with regard to G
the land allotted and the area thereof on account of the
existence of the municipal drain either on the plot or in its
vicinity. Shri Hira Lal Gupta had also made a request for the
plot allotted in his name to be transferred in the name of the
Petitioner Company in which he and his son were Directors. H
1082 SUPREME COURT REPORTS [2010] 12 S.C.R.
A Since the same was likely to take some time for completion of
the formalities, a specific prayer was made to serve the penalty
due to delay in the execution of the lease deed. In such
background, the Chief Executive Officer, NOIDA, extended the
period for completion of the formalities relating to the
s constitutional change by a period of two months without penalty
from 24th March, 2002. Before the said period could expire,
the Officer on Special Duty, on a misunderstanding of the order
passed by the Chief Executive Officer, NOIDA, indicated by his
order dated 11th April, 2002, that since the Chief Executive
c Officer had given two months' time without penalty only for
change of constitution, interest on the outstanding instalments,
penal interest and penalty, were liable to be recovered from the
Writ Petitioners. To add to the confusion, a further order was
passed by the Officer on Special Duty (G) on 26th April, 2002,
D directing that steps be taken in terms of his earlier order dated
11th April, 2002, and indicating that two months' time given to
the Writ Petitioners was for completion of formalities for change
of the name of the allottee.
14. Up to this stage, the case of the Petitioner Company
E for waiver of penalty can be accepted, but the subsequent
correspondence which followed between the parties and the
failure of the Petitioner Company and Shri Hira Lal Gupta to
complete the execution of the lease deed even within the
extended time of two months, indicate that neither Shri Gupta
F nor the Petitioner Company had any inclination to complete the
formalities for execution of the lease deed pursuant to the
change in the name of the allottee from Shri Hira Lal Gupta to
the Petitioner Company.
G 15. From the materials on record and the subsequent
correspondence beginning with the letter dated 1st May, 2002,
written by the Deputy Manager (C), NOIDA, it is apparent that
the Petitioner Company and Shri Hira Lal Gupta were given a
great degree of latitude to complete the transaction. In fact,
H meetings of the Committee had been convened on 23rd
ANGEL BAB~ PRODUCTS PVT. LTD. v. NEW OKHLA 1083
INDUST. DEV. AUTH. [ALTAMAS KABIR, J.]
October, 2002 and 26th November, 2002, in which Shri Hira A
Lal Gupta appeared and made submissions for waiver of the
penalty but on the basis of the record, the Committee rejected
Shri Gupta's submissions and Shri Gupta was subsequently
informed of the decision of the Committee which was approved
at a meeting of the Authority convened on 15th February, 2003, B
under the Chairmanship of the Additional Chief Executive
Officer, NOIDA. Even if initially a case may have been made
out on behalf of the Petitioner Company that the execution of
the lease deed could not be completed on account of the mis-
description of the plot and in view of the prayer for change in c
the name of the allottee, on account of the subsequent conduct
of the Petltioner Company and Shri Gupta, we are not inclined
to interfere with the order of the High Court or the decision of
the NOIDA relating to imposition of penalty and interest.
However, we are also not inclined to accept the interpretation
0
given by the Officer on Special Duty to the order passed by the
Chief Executive Officer on 24th March, 2002, and, accordingly,
we direct that in calculating the penalty and interest as payable
under the agreement entered into between the parties, the said
period of two months from the date of the order dated 24th
March, 2002, shall be excluded. E
16. With the aforesaid modification of the order passed
by the Chief Executive Officer on 22nd July, ~002 and the
subsequent resolution of the NOIDA taken at the meeting
convened on 15th February, 2003, the Special Leave Petition F
stands dismissed.
17. There will, however, be no order as to costs.
N.J. SLP dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.